1 ENVIRONMENT MANAGEMENT PLAN 1.0 Introduction This report discusses the management plan for mitigation/abatement of adverse environmental impacts and enhancement of beneficial impacts due to mining. The EMP has been designed within the framework of various legislative and regulatory requirements on environmental and socio-economic aspects. Sri G. M. Nagaraju proposes to conduct open cast method mining for Quartz in an area of 4.8 ha in Survey No. 1, Mustikovela Village, C. K. Palli Mandal, Ananthapuramu District, Andhra Pradesh. Industries and Commerce (M-II) Department, Government of Andhra Pradesh vide G. O. Ms. No. 114 dated has accorded permission to surrender ha and to retain 4.8 ha. The Mining plan has been approved by the Deputy Director of Mines and Geology, vide Letter No. 49/MMS/ATP/2016 dated The proposed production of Quartz is tons/annum. Capital cost proposed for the mining will be approximately Rs. 55 Lakhs. Sri G. M. Nagaraju is conscious of its environmental responsibility towards the society in minimizing the pollution load due to this project and accordingly decided to carry out the Environment Management Plan. The objective of preparing environment management plan is to delineate effective measures to control and to mitigate the environmental pollution. This report presents the environment management plan, detailing the environmentally sound technology and the measures needed to contain and mitigate the anticipated environmental impacts due to the project. 1.1 Uses of Quartz Quartz containing 99% plus Silica is used in glass industry. This is also used in electrical industry for making semi conductors. There is demand for quartz in indigenous industry and also for export 1.2 Mining Technology The mine workings were proposed to be carried out by manual open cast method with the help of Jack hammer drilling & blasting. 1.3 Mine Location The mine lease area falls in the Survey of India topo sheet no. 57 F/12 with the co-ordinates 1-1

2 of Latitude 'N and Longitude 'E with a elevation of 541 m. The nearest village is Guvvalagondipalli located at a distance of 0.7 km from the ML area in SE direction. Tirumani to Guvvalagondipalli village road passing at a distance of 0.6 km in SE direction. Mushtikovila- Nyamaddala road passing at 3.9 km from the lease area in SE direction. Nearest railway station is Makkajipalli at a distance of 13.7 km from the lease area in SE direction. Nearest town is Dharmavaram at a distance of 28 Km from the ML area in NE direction. Ramagiri West RF is at a distance of 4.3 km in NW direction. Gutturu west RF is at a distance of 5.2 km in SE direction. Andhra Pradesh- Karnataka state boundary is passing at a distance of 1.1 km in NW direction. There are no national parks, wildlife sanctuaries and critically polluted areas are observed in 10km radius of the mine lease area. Mine lease location map is presented in figure 1.1. Details of the mine lease area are presented in table 1.1. The lease area is bounded by following Geo coordinates Latitude Longitude '35.00"N 77 30'41.70"E '34.30"N 77 30'36.00"E '42.00"N 77 30'33.00"E '44.40"N 77 30'38.70"E Table 1.1 Details of the Mine Lease area State & District Mandal Village Sy. No. Area in ha Ownership Andhra Pradesh & Ananthapur 1.4 Land use pattern of the lease area C. K. Palli Mustikovela Government Land The quarry lease area is part of uneven, elongated roughed hilly rocky terrain. Table 1.2 Land use pattern in lease area S. No Purpose Extent (ha) 1 Area under quarrying Waste dump area Road Infrastructure(Office, rest shelter) Green belt Vacant Total

3 G. M. Nagaraju Environment Management Plan Figure 1.1 Mine lease Location Map of Sri G. M. Nagaraju 1-3

4 Figure 1.2 Mine lease boundary map of Sri G. M. Nagaraju 1-4

5 2.0 Physiography The Mine lease area is a part of uneven, elongated roughed hilly rocky terrain. The minimum RL is 97 RL on Southeastern side and maximum of 151 RL at Central reef. The area is having 4 pits with varying depth of 1.5 to 5 m. Over all water flow is from east to west in direction, from higher elevation to lower elevation. The area is of rock basin underneath the soil, therefore the vegetation is very less. The thickness of soil cover varies from 0.5 m to 1 m in the lower part of the area, where as at higher elevation it is very less. The slant place at Northeastern side is covered by Red & Black sandy soils. 2.1 Regional Geology The regional Geology of area incorporates Archaean Dharwars Ramagiri Schist belt with intrusives of acidic veins. The quartz intrusives into schist belt is predominant in the area. Generally the region is having Schist, Quartzite, Feldspar and Quartz terrain with gold intercalations. The general strike of rock structures is almost North 30 West- South 30 east in direction. The area is having gold bearing quartz in schist, hence in surrounding area number of abandoned gold mines are there. The main ground geological succession of the area is as follows. Recent and sub-recent Upper Archaeons Middle Archaeons Lower Archaeons : Alluvium, Gravels & Soil cover : Dharwars, Ramagiri Shist belt with intrusive, : Schist, Metamorphic rocks : Igneous rock formation Local Geology of the area The local Geology of the area is found to be as follows, with reference to Geological mapping done in the area. Soil cover 0.5 m to 1.0 m thickness (on lower levels) Quartz Thickness Varies from 1.5 to 18m (exposed at pit bottom to the surface) Granitic Schist More than 18 m thickness, not measured. The intrusive body of quartz available in the area is isolated and having limited extent of mineralisation. The strike direction of the deposit is in N 30 W-S 30 E dipping vertically. The major joints are parallel to the quartz mineralisation in direction. The quartz is having concoidal fracture. The physical quality of the quartz is white and semi glassy in nature. The country rock Schist is also having joint planes parallel to the general strike of the quartz. 1-5

6 Cross Section/ Category G. M. Nagaraju Environment Management Plan 3.0 Details of Exploration 3.1 Exploration Proposed afresh During this scheme period from to it is proposed to dig 6 trail trenches along the contact zone of Quartz vein in grid wise manner by following the UNFC guidelines. Since the date of commencement of mining upto march 2014, the lessee has produced about 5175 tons of quartz. 4.0 Method of Estimation of Reserves This mine is operating one. The mineral is geologically proved and measured and economically feasible for mining and hence it is considered as proved reserves and classified as 111 of UNFC Code under G-1 category up to 120 m level from the surface. The lowest of Quartz exposure at surface is at 112 RL at Southern side; hence the level between 120 m RL and 112m RL is considered as probable reserves and classified as 121 of UNFC Code under G- 2 category. G1 & G2 category minerals are feasible for mining, therefore it is considered as mineable reserves. Cross Section length (m) Cross Section height (m) Table 1.3 Mineable reserves of Quartz Cross Cross x2.5 Bulk section section Volume density Area influence (m 3 ) (Geological (m 2 ) (m) Reserves) T 90% Recoverable reserves (T) Waste (T) Waste (m 3 ) AA /G BB / G CC / G DD / G G1 Total AA / G BB / G CC / G DD / G G2 Total Mineable Reserves G3 category Possible Geological resources: Reserves blocked in buffer zone & Ultimate pit limit Volume x2.5 Bulk density 90% Recoverable Waste Waste Category (m 3 ) (Geological Reserves) T reserves (T) (T) (m 3 ) G3 Total

7 4.1 Mineable Reserves & Anticipated Life of the Mine Total Proved and Probable Reserves area considered as mineable reserves. Mineable Reserves = T ROM Proposed average annual production = T Life of Mine = Mineable Reserves / Proposed average annual production = / =11 years 5.0 Mining Method The lessee is undertaking open cast manual mining method by conducting blasting for disintegration of hard strata in this mine. Then by digging with the help of crow-bars or pick axe the lumps will be produced. Big lumps will be broken into small pieces or lumps of 3" to 24" size will be segregated & loaded into trucks manually and dispatched for consumer point. Drilling will be done whenever hard strata come across the working. Occasionally Loader or JCB will be used for heaping and loading in case labour not attend the duties. During production, about 10 % waste will be generated. The Quartz in this area is white and need less dressing. 5.1 Year wise development and production The Quartz is exposed to surface and in the pits developed at major part of the area. In this scheme period it is proposed to produce quartz from top of the mound depleting in successive years by slicing the height. Therefore, the development such as cutting of side burden on either side of quartz will be done in last three years. Year : In it is proposed to produce 6900 T of Quartz by cutting a bench of 1.5 m height by utilizing 1840 m 2 area. Anticipating 90 % recovery, 6210 T of salable Quartz will be produced. During production, 690 T of waste will be generated. At the end of the year, the bottom level will of the bench will reach 145 m RL. Year : In it is proposed to produce T of Quartz by cutting multiple benches of 1.5 m height each totaling to 3 m by utilizing m 2 area. Anticipating 90 % recovery, T of salable Quartz will be produced. During production, 6540 T of waste will be generated. At the end of the year, the bottom level will of the bench will reach 139 m RL. 1-7

8 Year : In the production of quartz will be continued by cutting multiple benches of 3 to 1.5 m height by cutting slices from top to bottom. It is proposed to produce T of Quartz by utilizing 6435 m 2 & 7280 m 2 respectively. Anticipating 90 % recovery, T of salable Quartz will be produced. During production, 7556 T of waste will be generated. At the end of the year, the bottom level will of the bench will reach m RL. Year : In year it is proposed to produce T of Quartz by cutting multiple benches of 1.5 & 3 m height by utilizing 8000 m 2 & 8610 m 2 area. Anticipating 90 % recovery, T of salable Quartz will be produced. During production, 9458 T of waste will be generated. At the end of the year, the bottom level will of the bench will reach 130 m RL. The year wise production quantities are given below. Table 1.4 Year Wise Production for Quartz Year Volume x2.5 BD 90 % Recovery 10 % Waste X 1.3 SF (m 3 ) ROM (T) Production (T) Waste (T) (m 3 ) (Swell waste) m Total Average Conceptual Mining For any mine conceptual mining plan amounts to, fore-seeing in totality and planning for mining and related activities throughout its life span, till such time all the usable ore minerals arc exhausted to the economical limits and lease area is reclaimed to the extent possible. Apart from physico-chemical and mineralogical parameters which form primary basis for compilation of conceptual mine plan, several other factors such as grade of sub grade ores, marketability and the norms laid down by the Government agencies from time to time play important roles. With ever increasing and changing needs of humanity, coupled with technological advancements, sub grade ores of the date become marketable ores in future. Therefore, preparation of ideal conceptual mine plan for any mine is difficult and such plan period prepared, remains acceptable only under given circumstances, it cannot be overlooked that, any such plan undergoes amendments and revisions in the course of 1-8

9 progressive stages of exploration and exploitation. It is always borne in mind to bring back near natural shape to the area and its economic value is elevated. It is further ensured that, there is positive contribution to the environment and socio-economic development of the region. 6.0 Drilling & Blasting For fragmentation of Quartz, the blasting is conducted in this area. The blast hole of 1.5m will be drilled with an inclination of 5 to 10 with the help of 34 mm dia. drill rod, Jack Hammer and Air Compressor as usual practice in most of the quartz mine. Depth of Hole 1.5 m x spacing 1.2 m x burden of 1.0 m x 2.5 MT density = 4.5 MT of Quartz produced per hole. 7.0 Extent of Mechanization The Quartz is hard in structure, therefore it is proposed to undertake blasting by deploying air-compressor and drilling jack-hammer, with drilling rods. Except this, no machineries are required. Hired trucks will do the transportation of Quartz to distant destination. The following machinery is proposed to be deployed. Table 1.5 List of Machinery S. No. Description No. of Units 1 Jack Hammers 1 2 Air Compressor 1 3 Trucks 1 Minor Tools: Chisels, Crow bars, pick of axes spades. Except drilling tools no other machinery will be used in mine. 8.0 Employment Potential The following personnel have been deployed for undertaking mining operations in the subject area to work 300 days. Table 1.6 Employment potential S. No. Designation No. 1 Mines Manager/Mate/Blaster 1 2 Mining Engineer 1 3 Workers 48 Total

10 9.0 Use of Mineral Quartz: Quartz containing 99% plus Silica is used in glass industry. This is also used in electrical industry for making semi conductors. There is demand for quartz in indigenous industry and also for export Water requirement Water requirement of 12.9 KLD is mainly for drinking purpose, domestic purpose, green belt maintaining and for sprinkling on Mine haulage roads the water shall be drawn from nearby village. The domestic waste water shall be sent to septic tank followed by soak pit. The water requirement is presented in table 1.7. Table 1.7 Water Requirement S. No Water Usage Quantity KLD 1 Wet drilling operation (On production 100 Ltr/1 m 3 ) Water sprinkling on haul 1Ltr/Sq.Mt (2240 m 2 )+1/4 th for waste dump Ltr/Head (50 No s) Green 0.3 KL for 0.15 ha 2 times a day 0.6 Total Environment Management Plan Environmental protection is an issue that no organisation can neglect and hope to survive. The by products of civilization are being dumped upon the environment to a degree that the environment finds difficult to assimilate. The key to the success of the integrated approach to pollution prevention and control is the management and operation of the organisation. Effective committed management delivers a successful operation. As total commitment to the environment, not just for compliance with legal or regulatory compliance will be the essence of environment management. Many companies have recognized the benefits of implementing an effective environmental management system. Environmental management plan can be effectively implemented to mitigate the pollution levels by observing the following: a. Pollution will be prevented or reduced at the source b. Pollution that can not be prevented will be recycled in an environmentally safe manner. 1-10

11 c. Pollution that can not be prevented or recycled will be treated in environmentally safe manner and d. Disposal and other releases into the environment will be used only as a last resort and will be conducted in an environmentally safe manner. The proposed project is Quartz mine. The mine owners are aware of the adverse impacts due to the mining activity and propose to initiate a number of measures for the environment protection within the mine area and in the surrounding areas. The company has a stated environmental policy of ensuring regulatory compliance with respect to the statutory laws and regulations and those periodically issued by the Ministry of Environment, GOI, New Delhi, CPCB, New Delhi and A.P Pollution Control Board, Hyderabad Sources of Pollution and Control Measures The sources of pollution from the proposed activity are mainly from Mining, Drilling, Blasting and transportation of mineral Controlling Dust Level The air in this area is pollution free as there are no pollutant factories. The commencement of mining in this area will create air pollution due to emission of dust during mining, blasting and transportation. That will be suppressed by putting cloth at drilling spot, sprinkling water on mine lay out road etc. The suggested control measures are: Water spraying to be adopted at faces/sites before and after blasting, faces/sites while loading; and use of sharp drill bits for drilling holes and drills with water flushing systems (wet drilling) to reduce dust generation. Water sprinkling will be provided at appropriate places for preventing dust pollution during handling & stockpiling of mineral and regular water spraying on haulage roads during transportation of mineral and waste by water sprinklers Noise Generation The major source of noise pollution is due to drilling of drill holes, machinery and Blasting. Protective equipment to reduce the noise levels like ear muffs and other protective devices will be provided to the staff working near noise generating sources. The greenbelt development will also help in the reduction of noise levels outside the mine. Noise barriers in the form of trees are provided to attenuate the noise levels. Training would be imparted to mine personnel to generate awareness about the damaging effects of noise. Proper 1-11

12 maintenance of the equipment will also reduce the noise. The noise produced due to machinery operation and vehicles are negligible Occupational Safety and Health Health and safety aspects of the mine will be taken care off as per the World Bank (WB) guidelines on open pit mining. The guidelines provide the detailed information on the aspects that are required to be taken into account for maintaining proper health and safety issues. The workers continuously exposed to dust will be provided with some protective devices like dust mask to prevent respiratory disorders. The workers continuously exposed to a high noise will be provided with ear muffs/ earplugs. Green belt in and around the mining area will be developed to attenuate noise and dust impact. The blasting carried out in the mine area will be carefully planned and executed under the supervision of a responsible officer, to avoid any accidents. Drinking water supply for the employees will be provided by the project authority. The standard of the drinking water will be per WHO guidelines. Periodical training programme to inform the employees about their task, associated risk, and safe working practices will be undertaken. Training will also include information on accident prevention, proper control and maintenance of equipment and safe material handling practices. Proper fencing will be provided around the mine pits and waste dump areas to prevent the accidents and cattle felt. A regular monitoring of the Occupational Health and Safety will reduce the chances of accidents in the mine. Records of job related accidents and illness should be maintained. These informations will be reviewed and evaluated to improve the effectiveness of Environmental Health and Safety programme Occupational Safety and Health to Control Dust Inhalation Very little dust is expected to be generated during mining and dose not effect the environment. However while drilling, wet drilling will be practiced. It is a small scale mining activity and not much vehicular movement is expected. Water sprinkling arrangement will be provided to reduce the dust emissions and green belt will be developed around the pits to reduce dust generation and noise generation. Trucks are covered with tarpaulin during transportation and overloading of trucks will be avoided to prevent dust generation. PUC certified tractors will be used for transportation of mineral and waste within the lease area. Greenbelt will be developed with tall trees around the waste dump area to prevent dust 1-12

13 emission. All the above precautions would be adopted to prevent dust generation at site and to be dispersed in the outside environment. However, for the safety of workers at site, engaged at the strategic locations/dust generation points like drills, loading & unloading points dust masks would be provided. Dust masks would prevent inhalation of RSPM thereby reducing the risk of lung diseases and other respiratory disorders. Regular health monitoring of workers will be carried out Occupational Safety and Health to Control Exposure to Noise Blasting will be done using safety fuse using slurry explosive to reduce vibrations, and the amount of explosive used will also be less at a time. There will not be heavy earth moving machinery which may create some noise pollution. Thus the vibration and noise will be well controlled within permissible limits. Trucks are kept in switch-off mode while loading and the speed of the trucks are restricted to limited speed of 15-20kmph to prevent the noise generation and safety purposes. To protect the workers from exposure to high levels of noise, following measures would be adopted; by provision of protective devices like ear muffs/ear plugs to workers who cannot be isolated from the source of high intensity noise, reducing the exposure time of workers to the higher noise levels by shift management Control of Ground Vibrations & Fly Rocks Boulder In this area the applicant proposes to deploy blasting with less quantity of explosives. There is going to be hardly any impact on surroundings, as there are less blasting and intended to use low power explosives in this mine. It is a small scale mine and only limited No. of holes are blasted. Ground vibrations due to blasting and its impact on various mine structures, should be studied in details when the mine becomes operational, especially the charge per delay factor. General measures to reduce ground vibration & fly rocks resulting from blasting are given below: Peak particle velocity or ground vibrations for safety of nearby structures and residential buildings should be well within 1 mm/sec; To contain fly rocks, stemming column should not be less than the burden of the hole, and the blasting area should be muffled; Blasting should be carried out in the daytime, as during the night time the sound intensity 1-13

14 becomes higher; Blasting should not be carried out when strong winds are blowing towards the inhabited areas; Each blast should be carefully planned, checked, and executed under the supervision of a responsible officer. Blasting data/observations should be recorded; and As per the mining plan, in order to ensure slope stabilization, controlled production blasting shall be adopted to avoid tension cracks and back breaks. Such cracks may get filled with water, which reduces the stability of excavated slopes and the angle of slopes Peak Particle Velocity The vibrations are measured as per the assessment criteria given under Bureau of Indian Standard, IS: (Reaffirmed 2003) - Criteria for Safety and Design of Structures Subject to Underground Blasts. Per the assessment criteria, the value of ground particle velocity may be computed from the following expression: V = K1 [Q 2/3 /R] 1.25 Where V = Ground particle velocity in mm/sec K1 = Constant which may be normally taken as 880 for soil, weathered or soft rock and 1400 for hard rock. Q = Charge per delay (kg), and R = Distance (m) from blast point Based on the above equation, the ground particle velocities at different distances (3 m, 3.2 m, 5 m, 10 m, 50 m, 70 m, 100 m, 150 m and 200 m, 500 m) are calculated considering K1 as 880 for soft rocks and 1400 for hard rocks. As per the Standard, for safety of structures from threshold damage, the ground particle velocity should not exceed the following: Soil, Weathered or Soft rock 70 mm/sec Hard Rock 100 mm/sec The results are presented in the Table 1.7 below for the maximum charge 1-14

15 Table 1.7 Ground Particle Velocity (V) Charge Peak Particle Velocity (V) mm/second S. Constant Per Delay Distance from the Blasting (R in meters) No (K1) (Q in Kg) It is clear that with Q = 0.2 kg charge per day shall result in ground particle velocity is 70 mm/sec in soft rock within a distance of 1.14 m while in the hard rock the ground particle velocity is 100 mm/sec shall be within 1.16 m. There shall not be any structure with in 2m of the quarry area, and it may be, concluded that the ground vibrations generated by blasting during the mining operations will not likely to effect the structures proposed in the vicinity of > 2 m from the point of blast. Concrete structures like office, store etc should not be proposed within the core mine area. These structures otherwise will be affected by the ground vibrations Water Quality Management Since there is no chemical discharge either from the mine or from the processing mine, there will not be water pollution. The proposed mine workings will not touch the ground water aquifer as the working will be done on top of hill. The maximum depth of the mining will be 18 m from top of hill. Hence there will not be water pollution. There will be no change in quality of water Water Resources There are no wells or springs in the area. Hence there will not be adverse effect on ground water due to mining. The daily water requirement for the mine operations would be approximately 12.9 KLD. Water sprinkling on mine haulage roads etc shall consume 2.5 KLD. Wet drilling operations consume about 7.5 KLD. For green belt development water consumption is about 0.6 KLD. Domestic purpose is about 2.3 KLD. The water is to be sourced from nearby village through tankers. The generation of wastewater from domestic sources is expected to be approximately 1.7 KLD, which will be sent to septic tank followed by soak pit Water Management Following measures will be adopted to mitigate the impact on the water resources: The blasting activities will have to take care on the sinkholes, cracks and fissures in the site activities. 1-15

16 During excavation and drilling activities effort must be taken to avoid face collapse at these cracks and fissures. To prevent surface water contamination by oil/grease, leak proof containers shall be used for storage and transportation of oil/grease. The floors of oil/grease handling area will be kept effectively impervious. To prevent degradation and maintain the water quality during rainy season, adequate control measures should be adopted to check the mine run-off into the natural streams. Following control measures are proposed to be adopted: 14.3 Catchment Area Treatment Plan A catchment area treatment plan has been developed keeping in mind the results of the hydrology/ hydrogeology study as well as the climate data. As there are no perennial water sources running on or through the site, the mine water discharge is limited to the monsoon season only. To keep water from entering the mine during this period, a garland drain will be developed along the mine s top bench, which will bend to guide the water to the nearest natural surface drain. In terms of water quality, good mining practices are planned, additionally the natural state of surrounding areas, should ensure that rain water run-off from the mine does not contain any toxic elements. As the site has no overburden or excess clay, potential discharge of sediments is quite limited and any residual clay or limestone particles which are washed down will be captured by a sump located at the lowest bench. The sump will be cleaned regularly and discharge water monitored consistently. If required, based on monitoring, an additional catch pit can be located at the main garland drain. The sump proposed in the bottom bench will be designed based on the peak discharge and will be expanded over a period of time to accommodate the increasing quantum of water discharge. Presently, the capacity of the sump is designed to hold the entire quantum of peak discharge water for more than 10 minutes i.e KL/hr. The garland drain shall be provided surrounding the mine area. Check dam and salutation pond need to be constructed of appropriate size to arrest silt and sediment flows from soil and mineral dumps. The water so collected should be utilised for watering the mine area, roads, green belt development etc. The drain should be regularly desalted and maintained. The garland drain (size, gradient and length) and sump capacity 1-16

17 should be designed keeping 50% safety margin over and above the peak sudden rainfall and maximum discharge in the area adjoining the mine site. Sump capacity should also provide adequate retention period to provide proper settling of silt material. The surface water around the mine, and infrastructure will be regularly tested and appropriate control measures adopted in case of any pollutant is detected above the prescribed limits Waste Management and Dump area During these four years about T ( m 3 ) of waste will be produced. This waste will be dumped over an area of 0.3 ha in eastern side of the lease area Land Management Land degradation is one of the major adverse impacts of opencast mining in the form of excavated voids and also in the form of waste dumps. Land reclamation plan must, therefore, be implemented simultaneously with the mining activities Land Reclamation It is a small scale of manual open cast mining. However, due to open quarry some land surface may be disturbed. There is no proposal for reclamation of the pit in this plan period Soil Conservation Measures Top soil is not expected in this mine. To prevent soil erosion and wash-off of dump-fines from freshly excavated benches and dumps following measures shall be adopted: Garland drains will be provided around the mine wherever required to arrest any soil from the mine area being carried away by the rain water; Toe drains with suitable baffles will be provided all along the toe of the soil dumps to arrest any soil from the dump slopes being carried away by the rain water; Loose material slopes will be covered by mineation by making contour trenches at 2 m interval to check soil erosion both due to wind and rain; Retaining walls (concrete or local stone) will be provided, around the stockpile or wherever required, to support the benches or any loose material as well as to arrest sliding of loose debris House Keeping Proper house keeping and cleanliness will be maintained in the infrastructure facilities. Wet mopping will be adopted to conserve water. Sign boards will be provided in the work areas and the road and building highlighting the safety and occupational aspects. 1-17

18 16.0 Transport Systems Tirumani to Guvvalagondipalli village road passing at a distance of 0.6 km in SE direction. Mushtikovila- Nyamaddala road passing at 3.9 km from the lease area in SE direction. Nearest railway station is Makkajipalli at a distance of 13.7 km from the lease area in SE direction. Number of truck trips will be 11 per day. When the material is sold to the parties, are it is expected to lift the minerals by their own vehicles or hired ones from the mine. Sufficient parking facilities will be provided for vehicles loading and unloading of material. Safety signs will be displayed inside and outside the mine to avoid road accidents Environmental Greening Program Environmental greening program is an important component of the Environment Management Plan and is an imperative requirement for any major industrial activity, as per the guidelines issued by the Ministry of Environment and forests, Govt. of India. Conceptualization, design and implementation of the proposed activity, taking into account the specific requirement of the proposed mining activity and the site conditions are presented. During this plan period about 125 Eucalyptus saplings will be planted per year over an area of 375 m 2 (50 L x 7.5 W) in southeastern side of lease area. A thorny fencing shall provide to guard the trees from the cows and goats, necessary manpower shall be arranged for vigilance. The environmental greening program as designed comprises the location and development of a shelterbelt and Afforestation in about 0.15 Hectares. The shelterbelt will contain species, which act as windbreakers so that the environment within the mine is contained; the planting of different species in rows is envisaged in general in the greenbelt Socio-economic Environment The project provides an opportunity for the local people to get employment directly or indirectly and helps in the upliftment of the socioeconomic status of the area. The proposed project would generate an employment of 50. The management will involve in social activities of stakeholders/surrounding community by planning the betterment of neighboring social conditions through awareness and welfare programs to ensure an improved relation, useful in the long run. Many of the beneficiaries of such programs will include own employees as well. The goodwill of the local populace can never be ignored. It is proposed to 1-18

19 supply drinking water and medical facilities to the villagers. The channels employed may vary either through direct contact or by means of local organizations. Another important facet of social environment identified by the project proponents is a green appearance; hence the management will develop a green belt towards aesthetic beautification as the same is necessary to be considered as a responsible, social neighbour Disaster Planning The complete mining operation will be carried out under direction of qualified mines manager and superior mining personnel, following the directions of Directorate General of Mines Safety (DGMS) and officers of Indian Bureau of Mines. Code of practice of different operations will be formulated to maintain of high standard of safety. Work persons have been given vocational training and further the standing will be continued to new entrants. Moreover mining staff would be sent to refresher courses from time to time to keep them abreast of the regulations. However following natural/ industrial hazards may occur during normal operation Slope failure at the mine faces; Accident due to explosives; Accident due to heavy equipment/machinery; Sabotage in case of magazine; and Accidents due to fly rocks and boulders. In order to take care of above hazards/disasters, the following control shall be adopted: All safety precautions and provisions of Metalliferous Mine regulation 1961 are strictly followed during all mining operations; Checking and regular maintenance of garland drains and earthen bunds to avoid any inflow of surface water into mining area; Entry of unauthorized persons shall be prohibited; Fire fighting and first aid provisions in the mines office and mining Area; Provision of all the safety appliances such as safety boots, helmets, goggles etc. would be made available to the employees and regular check to ensure the use; Training and refresher courses for all the employees working in the hazardous premises; Working of mine as per approved plan, related amendments and other regulatory provisions; 1-19

20 Cleaning of mine faces shall be done regularly; Handling of explosives, charging and blasting shall be carried out by competent persons only; Provision of magazine at safe place with fencing and necessary security arrangement; Suppression of dust on the haulage roads by providing water sprinkling Environment Management Cell A Cell for Environmental Management within the mine at the project level, will take the overall responsibility for co-ordination of the actions required for environmental management and mitigation, and for monitoring the progress of the proposed management plans and actions to be taken for the project. The Cell will be under the overall supervision of the Mine Manager, and responsible for monitoring of the implementation of the various actions which are to be executed by the agencies specified in the EMP. The Cell will be headed by Mine Manager and the other members of the cell that will include a Horticulturist and 1 no. of supervisor. The EMC will prepare a formal report on environmental management and mitigation for the Environmental Engineer at the Mine, at six-monthly intervals. Reports on any urgent or significant issues may be prepared at shorter intervals. Apart from responsibilities listed above, the EMC will have the responsibility of the following: Collection of water and air samples within and outside the work zone; Analyzing the water and air samples; Implementation of the control and protective measures; Land reclamation and vegetation; Co-ordination of the environment related activities; Collection of the statistics of health of workers; Green belt development; Awareness and implementing safety programmes; and Monitor the progress of implementation of EMP Post Project Monitoring The survey of air pollution comprises of the following monitoring aspects; a. Ambient air quality survey b. Noise Level Monitoring 1-20

21 c. Water quality monitoring Ambient air quality and noise level Monitoring will be carried out at minimum three stations, one station within mine site and two stations nearby residential areas outside the mine. Parameters like suspended particulate matter, sulphur dioxide, oxides of nitrogen carbon monoxide and lead will be monitored. The frequency of monitoring is preferably once in three months on 24 hour basis. The samples will be collected in accordance with the procedures given by CPCB. Existing ambient air quality in the mine lease area is as follows Other Management Aspects Records will be maintained for the analysis of ambient air quality and noise levels. These records are not only required for the perusal of the Pollution Control Board authorities. The management will maintain the records as per the hazardous waste regulations and EPA regulations and apply for the annual consents for air and water, and renewal of authorization for the storage of hazardous waste as per the Hazardous Waste (Handling & Management) Rules, The records of hazardous waste manifest will be maintained. The format of the same is enclosed in appendix. The mine shall obtain the consent for operation (CFO) as required under section 25/26 of the Water act, 1974 and under section 21/22 of Air Act, 1981, before trial production and commissioning from the State Pollution Control Board. The CFO will be renewed each year by the management. The mine will submit environmental statement every year before September 30. The management ensures that it will comply with all the directions and regulations issued by the Ministry of Environment and Forests, New Delhi, State and Centre Pollution Control Boards. The Consent for Establishment, Consent for Operation will be displayed in a conspicuous location for the information of the inspecting authorities of different departments Cost proposed for Environmental Protection Measures The cost estimate of environment management is presented in table

22 Sl no G. M. Nagaraju Environment Management Plan Description Table 1.9 Environment Management - Cost Estimate Item Capital cost (Rs.) Recurring cost (Rs.) Remarks Nose masks93no's Once a week. Replaceable, and cost can increase with time Cloth for drillers 4 no's 1.0m each Issued quarterly Gunny bags for covering the As and when needed, surface of jackhammer holes Lump sum. 1 Air pollution Road 1 Ltr/2240 Water tanker one Sq. m. and waste dump tankers per day for 300 settling (1/4 of wetting) days Ltrs tank Plantation on road side - 3m interval and buffer zone - 3m interval plus maintenance Re-plant the non-surviving plants, watering and protection from animals Sub Total Construction of garland drains Once only for the lease period/life of mine De-silting operations Yearly and manual operations 2 Water pollution filling sand Cost of construction of Construction of retaining wall wall around the dip side of for waste dump in slope side the dump. Once in year, cost incurred Construction of check dams is to buy sand bags and Sub Total Maintenance of machinery suitably - Rs per Included in main cost 3 Noise pollution months PPE's like Ear muffs - Rs. 15 each Once in six months Sub Total Occupational Safety and Health Providing First aid kits - 2 No's and fire extinguishers - 2 No's Providing Personal protective equipments to all employees (hand Rs. 30, safety Rs and Rs. 100) Training and awareness programs on risk factors during emergencies by the experts Once in year, replace by conducting periodical checkup Safety shoe twice in a year, helmets once in three years and hand gloves thrice in a year Once in six months and create sign boards about the risk and safety precautions regularly Periodical medical checkup Once in a year and supply 1-22

23 and supply of medicines - Rs. 600 per head Sub Total Ambient air quality studies - Once in six months locations Water quality studies - Once a Environmental year - 2 Locations monitoring Noise studies - Once in six months - 2 Locations Vibration studies - Once in year - 1 locations Sub Total Grand Total of medicines for every three months Will be done through MoEF&CC/NABL recognised laboratories 1-23

Final Environmental Impact Assessment of Smt. Singam Bhavani Laterite Mining ADDITIONAL STUDIES

Final Environmental Impact Assessment of Smt. Singam Bhavani Laterite Mining ADDITIONAL STUDIES ADDITIONAL STUDIES 7.0 DISASTER MANAGEMENT PLAN It is presumed that the proposed mining process would be designed and engineered with all possible safety measures and standard code of practices. In spite

More information

ENVIRONMENT MANAGEMENT PLAN

ENVIRONMENT MANAGEMENT PLAN ENVIRONMENT MANAGEMENT PLAN 1.0 Introduction This report discusses the management plan for mitigation/abatement of adverse environmental impacts and enhancement of beneficial impacts due to mining. The

More information

Project Details- Minor Minerals (Other Than Sand)

Project Details- Minor Minerals (Other Than Sand) Project - Minor Minerals (Other Than Sand) Sr. ABOUT THE PROPOSAL 1. Name of Lease Holder M/s. KARMANBHAI JODHABHAI RABARI (Partner) 2. Location address Mr. Karmanbhai Jodhabhai Rabari Survey No- 194 Paikee,

More information

ENVIRONMENT MANAGEMENT PLAN

ENVIRONMENT MANAGEMENT PLAN ENVIRONMENT MANAGEMENT PLAN OF M/s Baghel Infrastructure Pvt. Ltd. AT Khasra No 1203/1 Vill- Makrohar, Tehsil-Mada, District-Singrauli (M.P.) Production Capacity: 8158Cu.mt/year Metal Stone Area 1.00 Hectare

More information

ENVIRONMENT MANAGEMENT PLAN

ENVIRONMENT MANAGEMENT PLAN ENVIRONMENT MANAGEMENT PLAN FOR VILLAGE TEHSIL DISTRICT AREA MINERAL : Makrohar : Mada : Singrauli (M.P.) : 1.00 hect : Metal Stone KHASRA No : 176,178 PRODUCTION CAP : 15375 Cu.mt/year Metal Stone APPLICANT

More information

Project Details- Minor Minerals (Other Than Sand)

Project Details- Minor Minerals (Other Than Sand) Project - Minor Minerals (Other Than Sand) Sr. ABOUT THE PROPOSAL 1. Name of Lease Holder M/s. ABDUL MUNAF MOHAMMEDMIYA MALEK Mr.Abdul Munaf Mohammedmiya malek (Proprietor) 2. Location address OPP Block

More information

2. PRE-FEASIBILITY REPORT

2. PRE-FEASIBILITY REPORT 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The proposed project is Building stone quarry having lease area of 1.214 ha and falls under Category- A as per EIA Notification 2006 and its amendments of

More information

2. PRE-FEASIBILITY REPORT

2. PRE-FEASIBILITY REPORT 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The proposed project is Building stone quarry having lease area of 0.809 ha and falls under Category- A as per EIA Notification 2006 and its amendments of

More information

Project Details-Minor Minerals (Other Than Sand)

Project Details-Minor Minerals (Other Than Sand) Project Details-Minor Minerals (Other Than Sand) Sr. No. Details Particulars ABOUT THE PROPOSAL 1. Name Of lease Holder M/s. Kirtikumar Samji Sengani 23 0'27.43"N 69 24'10.21"E 2. Location address Survey

More information

ENVIRONMENT MANAGEMENT PLAN

ENVIRONMENT MANAGEMENT PLAN ENVIRONMENT MANAGEMENT PLAN OF Shri Kuldeep Choudhary AT Khasra No.Part of 112 Vill.-Golpura, Tehsil-Gandhwani, District-Dhar (M.P.) Production Capacity: 4543 Cu.mt/year Basalt Stone&4543 Cu.mt/year Murram

More information

ENVIRONMENTAL MANAGEMENT PLAN

ENVIRONMENTAL MANAGEMENT PLAN ENVIRONMENTAL MANAGEMENT PLAN Of M/s. D.BHARATHI 11.76 Acres Silica Sand Mine, Sy.No. 44/3,50/4,50/5&50/6 ADDEPALLI (V), CHILLAKUR (M), SPSR NELLORE DISTRICT ANDHRA PRADESH Prepared by SV ENVIRO LABS &

More information

ENVIRONMENT MANAGEMENT PLAN

ENVIRONMENT MANAGEMENT PLAN ENVIRONMENT MANAGEMENT PLAN FOR VILLAGE TEHSIL DISTRICT AREA MINERAL : Kothi : Pawai : Panna (M.P.) : 1.370 Hectare : Flagstone KHASRA No : 31 PRODUCTION CAP : Max 875 Cu.mt/year Flagstone APPLICANT Shri

More information

PROPOSED TERMS OF REFERENCE

PROPOSED TERMS OF REFERENCE PROPOSED TERMS OF REFERENCE ABOUT THE PROJECT: Rampura Marble Mine (ML No.- 420/91) is proposed by M/s Continental Minerals Pvt. Ltd. The Mine Lease area consists of 3.0 ha, which is located at Khasra

More information

S/o Vishnudas Chakraborty, residence at R/o Narsinghgarh, District Rajgarh (M.P.).

S/o Vishnudas Chakraborty, residence at R/o Narsinghgarh, District Rajgarh (M.P.). RISK ASSESSMENT The Crusher stone deposit lease area is located at Village Badodiya Jagir, Tehsil - Narsinghgarh, District - Rajgarh (M.P.). 02.00 Ha quarry lease area with production of 3306 cubic meter/year

More information

ENVIRONMENTAL MANAGEMENT PLAN :-

ENVIRONMENTAL MANAGEMENT PLAN :- ENVIRONMENTAL MANAGEMENT PLAN :- The Environment Management Plan (EMP) is required to ensure sustainable development in the area of the proposed project. Hence it needs to be all encompassive plan for

More information

ENVIRONMENTAL MANAGEMENT PLAN

ENVIRONMENTAL MANAGEMENT PLAN ENVIRONMENTAL MANAGEMENT PLAN CONTENTS OF ENVIRONMENTAL MANAGEMENT PLAN Chapter Title Page No. 1. INTRODUCTION 1-4 2. PROJECT PROPONENT 1 2.1 Project Location and Accessibility 1 2.2 Infrastructure and

More information

ENVIRONMENT MANAGEMENT PLAN

ENVIRONMENT MANAGEMENT PLAN ENVIRONMENT MANAGEMENT PLAN 1.0 Introduction This report discusses the management plan for mitigation/abatement of adverse environmental impacts and enhancement of beneficial impacts due to mining. The

More information

ENVIRONMENTAL MANAGEMENT PLAN

ENVIRONMENTAL MANAGEMENT PLAN Of MINING OF BLACK GRANITE 1.0 HA SURVEY NO: 38/11 OF CHINNAGANDLAPALLI VILLAGE, SANTHIPURAM MANDAL, CHITTOOR DISTRICT, ANDHRA PRADESH. By M/s. EVERSHINE GRANITILES LAKSHMIPURAM, KUPPAM, CHITTOOR, ANDHRA

More information

ENVIRONMENTAL MANAGEMENT PLAN

ENVIRONMENTAL MANAGEMENT PLAN ENVIRONMENTAL MANAGEMENT PLAN Of M/s. SRINIVASA GRANITES 5.010 HA COLOUR GRANITE MINING SY. NO. 539/B & 546/P UPPAMAGULUR (V), BALLIKURAVA (M) PRAKASAM (DT), ANDHRA PRADESH Submitted by SV ENVIRO LABS

More information

Proposed Terms of Reference for EIA studies

Proposed Terms of Reference for EIA studies 1 Proposed Terms of Reference for EIA studies Base line data collection will be collected for the Post-Monsoon season 2016 (September to November 2016) in study area and 10 kms radius from project site.

More information

ENVIRONMENT MANAGEMENT PLAN

ENVIRONMENT MANAGEMENT PLAN 1.0 INTRODUCTION ENVIRONMENT MANAGEMENT PLAN The Environment Management Plan has been developed with a view to bring down the levels of impacts during proposed mining activities In each of the areas of

More information

Pre- FEASIBILITY REPORT

Pre- FEASIBILITY REPORT Pre- FEASIBILITY REPORT In Respect Of JHILIMINDA SAND BED OVER 20.30 ACRES OR 8.215 HA IN VILLAGE JHILIMINDA, ATTABIRA TAHASIL OF BARGARH DISTRICT, ODISHA (For the Financial Year-2015-16 to 2019-20) Prepared

More information

PRE- FEASIBILITY REPORT

PRE- FEASIBILITY REPORT PRE- FEASIBILITY REPORT Applicant: M/s Regaliya Minerals Pvt. Ltd. Page 0 1.0 EXECUTIVE SUMMARY This mining project falls under Category A (presence of interstate boundary between Haryana and Rajasthan

More information

Pre- FEASIBILITY REPORT

Pre- FEASIBILITY REPORT Pre- FEASIBILITY REPORT In Respect Of SRIPURA SAND BED-BOVER 35.25 ACRES OR 14.265 HA IN VILLAGE SRIPURA, JHARSUGUDA TAHASIL OF JHARSUGUDA DISTRICT, ODISHA (For the Financial Year-2015-16 to 2019-20) Prepared

More information

CHANDAM7AIL,P SAND DEPOSIT

CHANDAM7AIL,P SAND DEPOSIT 1 RVER SAND QUARRY 11 ENVRONMENT MANEGMENT PLAN OF CHANDAM7AL,P SAND DEPOST VLLAGE- GHAWDAWAL, TEHSHL- LAltEAR DSTRCT- BMTUD, STATE- MADHYA PRADESH (MASRL4 NO- 1, 10, 15, AREA- 5.975 Hectare APPLCANT Sub

More information

ENVIRONMENTAL MANAGEMENT PLAN

ENVIRONMENTAL MANAGEMENT PLAN ENVIRONMENTAL MANAGEMENT PLAN Of M/s. MARAM VENKA REDDY GRANITES 2.077 HA COLOUR GRANITE MINING SY. NO. 103/P (USH-VEERLAKONDA) KONIDENA (V), BALLIKURAVA (M) PRAKASAM (DT), ANDHRA PRADESH Submitted by

More information

ENVIRONMENT MANAGEMENT PLAN

ENVIRONMENT MANAGEMENT PLAN ENVIRONMENT MANAGEMENT PLAN 1.0 Introduction This report discusses the management plan for mitigation/abatement of adverse environmental impacts and enhancement of beneficial impacts due to mining. The

More information

ENVIRONMENT MANAGEMENT PLAN

ENVIRONMENT MANAGEMENT PLAN ENVIRONMENT MANAGEMENT PLAN Page 33 ENVIRONMENT MANAGEMENT PLAN BLACK TRAP 1.0. INTRODUCTION: The proposed M/s. Black Trap Mine of Govindbhai Karshanbhai Ram area at near Vill.Chuldi, Tal.Malia-Hatina,

More information

Environmental Management Plan

Environmental Management Plan Environmental Management Plan ENVIRONMENTAL MANAGEMENT PLAN An Environmental Management Plan is prepared for construction phase, post construction phase (commissioning & operation) and for post project

More information

ENVIRONMENT MANAGEMENT PLAN

ENVIRONMENT MANAGEMENT PLAN ENVIRONMENT MANAGEMENT PLAN ENVIrONMENT MaNaGEMENT plan 1. INTRODUCTION: Shri Ratilal Ravji Solanki have a Blacktrap mining lease project for an area of 1.00.00 Ha located on Survey no. 984 paiki, Village:

More information

Environment Management Plan

Environment Management Plan Environment Management Plan FOR Quarry Lease of Crusher Stone Area 1.437Hectare, Kh. No. 40/8 KA AT Village: BHAWANDA, Tehsil: SEONI MALWA Distt HOSHANGABAD (M. P.) Proponent M/S JYORI CONSTRUCTION COMPANY

More information

TERMS OF REFERENCE. BEFORE CONSTRUCTION: Sl No TOR RESPONSE 1. Legalities of the land: Is the land The Project is clear from all angles.

TERMS OF REFERENCE. BEFORE CONSTRUCTION: Sl No TOR RESPONSE 1. Legalities of the land: Is the land The Project is clear from all angles. TERMS OF REFERENCE Name of the Project: M/s Suadela Constructions Pvt. Ltd. Address: Sy.No. 321/2B(P),321/2C(P),322/1,323/1(P),323/1(P),323/3,323/4,323/5(P), 323/6,323/7,325/1(P),325/2,327,328/1,328/2(P),328/3,328/4,330,331,332/2

More information

Environment Management Plan

Environment Management Plan Environment Management Plan FOR Mining of Agariya Crusher stone Quarry Area-4.00,Hectare Kh No-141/3/1,141/4,141/5 At Village- Agariya, Tehsil: Gouharganj Distt. Raisen SHRI. ASHOK SHARMA S/O SHRI GANGAPRASAD

More information

Form -1 Mining Plan & Pre-feasibility Report

Form -1 Mining Plan & Pre-feasibility Report Form -1 Mining Plan & Pre-feasibility Report FOR QUARRYING OF GREY GRANITE (EXTENT 1.8.0Ha)-B2 PROJECT S.F.Nos 35/2D, 35/3, 35/2E (P)& 3/1A1 (P) Village Chendarapalli Taluk Krishnagiri District Krishnagiri

More information

ENVIRONMENT MANAGEMENT PLAN

ENVIRONMENT MANAGEMENT PLAN ENVIRONMENT MANAGEMENT PLAN 1 [Type the company name] ENVIRONMENT MANAGEMENT PLAN LIMESTONE (BUILDING) 1.0. INTRODUCTION: The proposed M/s. Building Lime Stone Mine of Shree Jitubhai Parbatbhai Chudashma

More information

Environment Management Plan

Environment Management Plan Environment Management Plan FOR Mining of Crusher Stone Area 2.000 Hectare, Khasra No. 42/2 Village AT THANWARI Tehsil District State SEONI SEONI MADHYA PRADESH Proponent SHRI LAKHAN LAL S/O SHRI CHETAN

More information

Environment Management Plan

Environment Management Plan Environment Management Plan FOR Mining of Sildhara Flage Stone Quarry Area-.1.50,Hectare Kh No-87 At Village- Sildhara, Tehsil Panna, Distt.Panna MR.BRIJMOHAN SINGH S/O SHRI JAI RAM SINGH RESI-VILLAGE

More information

Environmental Management Plan

Environmental Management Plan Environmental Management Plan FOR BOULDER, GRAVEL AND SAND MINOR MINERAL Mine lease area: 13.20 Ha Village Mandlai Tehsil Raipur Rani, District- Panchkula and State - Haryana Category of Project: B2 Lease

More information

How To Conduct An Environmental Impact Assessment

How To Conduct An Environmental Impact Assessment Proposed Terms of Reference for EIA studies 1. Introduction The proposed expansion of Bulk Drugs & Intermediates manufacturing unit by M/s. Sri Krishna Pharmaceuticals Limited (Unit V). is located at Plot

More information

ENVIRONMENT MANAGEMENT PLAN

ENVIRONMENT MANAGEMENT PLAN ENVIRONMENT MANAGEMENT PLAN LIMESTONE 1. INTRODUCTION: The proposed Bagdhara Limestone area, near Village- Bagdhara, Taluka- Jamjodhpur and District-Jamnagar, Gujarat has been granted to Dipakkumar Anantray

More information

TERMS OF REFERENCE FOR THE RAPID EIA STUDY FOR SHIVKAR LIGNITE BLOCK, DIST. BARMER, RAJASTHAN

TERMS OF REFERENCE FOR THE RAPID EIA STUDY FOR SHIVKAR LIGNITE BLOCK, DIST. BARMER, RAJASTHAN 1. GENERAL TERMS OF REFERENCE FOR THE RAPID EIA STUDY FOR SHIVKAR LIGNITE BLOCK, DIST. BARMER, RAJASTHAN The main objective of the EIA study is to assess the positive and negative impacts likely to accrue

More information

EnVirOnMEnT ManaGEMEnT PLan. FOr. M/S. LiME STOnE MinE OF. Dhirajlal Panchanbhai Vachhani. area. PrOPOSEd PrOdUCTiOn:-36000 TPa

EnVirOnMEnT ManaGEMEnT PLan. FOr. M/S. LiME STOnE MinE OF. Dhirajlal Panchanbhai Vachhani. area. PrOPOSEd PrOdUCTiOn:-36000 TPa EnVirOnMEnT ManaGEMEnT PLan FOr M/S. LiME STOnE MinE OF dhirajlal PanChhanBhai VaChhani area (SUrVEY no.49 PaiKi, ViLL.Unadari, TaL.Una, dis.junagadh) PrOPOSEd PrOdUCTiOn:-36000 TPa PrOJECT COST: - 15

More information

TERMS OF REFERENCE FOR SCOPING OF EIA STUDY

TERMS OF REFERENCE FOR SCOPING OF EIA STUDY TERMS OF REFERENCE FOR SCOPING OF EIA STUDY Ours project is a proposed large scale unit and categorized as 5(h)-B as per the EIA notification 2006 of MoEFCC, New Delhi and subsequent amendments. Looking

More information

RISK ASSESSMENT. STONE QUARRY (2.40 Ha)

RISK ASSESSMENT. STONE QUARRY (2.40 Ha) RISK ASSESSMENT FOR STONE QUARRY (2.40 Ha) Gat no. 85, A/p Karanjvihire, Tahsil Khed, District Pune, Maharashtra OF M/s Shankar Ramchandra Earthmovers Pvt. Ltd. Risk Assessment for Stone Quarry Mining

More information

Form -1 Mining Plan & Pre-feasibility Report

Form -1 Mining Plan & Pre-feasibility Report Form -1 Mining Plan & Pre-feasibility Report TO OBTAIN ENVIRONMENTAL CLEARANCE FOR QUARRYING OF BLACK GRANITE (DOLERITE) (EXTENT 2.81.0Ha)-B2 PROJECT IN S.F.Nos 9,80,258/2B,258/6A & 258/6B Village Naduvanapalli

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT PRE FEASIBILITY REPORT for PROPOSED PROJECT FOR SOIL MINING of M/s. BHAVINKUMAR VINODBHAI LAD SURVEY NO. 98, MOJE ANCHELI, TAL. BARDOLI, DIST. SURAT, GUJARAT 1 CONTENTS Sr. Description Page No. No. 1.

More information

PRE - FEASIBILITY REPORT

PRE - FEASIBILITY REPORT PRE - FEASIBILITY REPORT FOR OBTAINING PRIOR ENVIRONMENT CLEARANCE TO Building Stone MINING ACTIVITY FOR CATEGORY B3 UNDER THE EIA NOTIFICATION 3006 AMENDED ON 31/05/3013 TO 1.97.58 SHREE SHAH ENGINEERING

More information

Pre- FEASIBILITY REPORT

Pre- FEASIBILITY REPORT Pre- FEASIBILITY REPORT In Respect Of KAIPADAR NEW BUILDING STONE QUARRY (KHA) OVER 7.50 ACRES OR 3.00 HA IN VILLAGE KAIPADAR, KHURDA TAHASIL OF (For the Financial Year-2015-16 to 2019-20) Prepared on

More information

Pre- FEASIBILITY REPORT

Pre- FEASIBILITY REPORT Pre- FEASIBILITY REPORT In Respect Of SARANKOTE STONE QUARRY OVER 2.40 ACRES OR 0.971 HA IN VILLAGE SARANKOTE, BARKOTE TAHASIL OF DEOGARH DISTRICT, ODISHA (For the Financial Year-2015-16 to 2019-20) Prepared

More information

Fauna- No particular type of fauna finds except snakes, hynus & Jackals, wild cat, wildhen etc. are found in and around the area.

Fauna- No particular type of fauna finds except snakes, hynus & Jackals, wild cat, wildhen etc. are found in and around the area. Environmental Management Plan Baseline information Topography:- The general slope of the area is towards east and gently sloping from 25 0 to 30 0 except southern part which is sloping towards south The

More information

PRE-FEASIBILITY REPORT

PRE-FEASIBILITY REPORT PRE-FEASIBILITY REPORT OF MASONRY STONE (CHEJA PATTHAR) MINING PROJECT (ML Area: 1.0 ha, M.L. No. 65/2011, Production Capacity-1, 11,780 TPA) Near Village: Gangora, Tehsil: Pahari, District: Bharatapur

More information

ENVIRONMENT MANAGEMENT PLAN

ENVIRONMENT MANAGEMENT PLAN 6. REHABILITATION AND RESETTLEMENT (R & R) PLAN Since the project is private land, there is no reserves forest or protected forest land within the applied area. There is no human settlements within the

More information

PROPOSED TERMS OF REFERENCE

PROPOSED TERMS OF REFERENCE Annexure-IV PROPOSED TERMS OF REFERENCE 1.0 Proposed Scope of Work for EIA Study The components of the EIA study include: Detailed description of all elements of the project activities (existing and proposed

More information

Environmental Management Plan

Environmental Management Plan Environmental Management Plan ENVIRONMENTAL MANAGEMENT PLAN 1.0 Introduction: Background: The Quarry lease, for Black Granite over an extent of 1.482 ha. in Sy Nos. 10 & 23, Sankavaram Village, Kanigiri

More information

Pre- FEASIBILITY REPORT

Pre- FEASIBILITY REPORT Pre- FEASIBILITY REPORT In Respect Of KAIPADAR NEW BUILDING STONE QUARRY (GA) OVER 2.50 ACRES OR 1.00 HA IN VILLAGE KAIPADAR, KHURDA TAHASIL OF KHURDA DISTRICT, ODISHA (For the Financial Year-2015-16 to

More information

Pre- FEASIBILITY REPORT

Pre- FEASIBILITY REPORT Pre- FEASIBILITY REPORT In Respect Of (For the Financial Year-2015-16 to 2019-20) Prepared on Behalf of SRI ANTARYAMI BISWAL Chhend, Rourkela, Dist-Sundargarh, Odisha PREPARED BY The Techno Chamber, Plot

More information

Environment Impact Assessment study:

Environment Impact Assessment study: (A) Environment Impact Assessment study: 1. Pollution Potential: Air Emission: Dust Emission during Mining, Transportation & Crushing of the Stones which will be controlled by water sprinkling and development

More information

PRE FEASIBILITY REPORT & ENVIRONMENT MANAGEMENT PLAN

PRE FEASIBILITY REPORT & ENVIRONMENT MANAGEMENT PLAN PRE FEASIBILITY REPORT & ENVIRONMENT MANAGEMENT PLAN Of COLOUR GRANITE MINE 1.000 HA SURVEY NO: 186/1 OF KUPPIGANIPALLI VILLAGE, GUDUPALLI MANDAL, CHITTOOR DISTRICT, ANDHRA PRADESH. Proposed By M/s. SREE

More information

ABANDONMENT COST, FINANCIAL ASSURANCE AND PRESENTATION OF THE DOCUMENT. Abandonment cost :

ABANDONMENT COST, FINANCIAL ASSURANCE AND PRESENTATION OF THE DOCUMENT. Abandonment cost : ABANDONMENT COST, FINANCIAL ASSURANCE AND PRESENTATION OF THE DOCUMENT. Abandonment cost : Determining the cost associated with closure and accruing these costs during the life of the mining operation

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT PRE FEASIBILITY REPORT FOR M/S. AMRUT STONE QUARRY (AREA 2.57 HECTARE) OF APPILCANT MR. RAJNIKANT BHAGWANJIBHAI KATHIRIYA (Partner) AT BLOCK NO: 98,VILL: ZAB, TAL: MANDVI, DIST: SURAT 394163 GUJARAT. 1

More information

FORM -1 MINING PLAN & PRE-FEASIBILITY REPORT. FOR QUARRYING OF ROUGH STONE (Extent: 3.00.0Ha)-B2 Project

FORM -1 MINING PLAN & PRE-FEASIBILITY REPORT. FOR QUARRYING OF ROUGH STONE (Extent: 3.00.0Ha)-B2 Project FORM -1 MINING PLAN & PRE-FEASIBILITY REPORT FOR QUARRYING OF ROUGH STONE (Extent 3.00.0Ha)-B2 Project!!"# $%&'( )!*+ $*, % -!#( # )(!&.* /012 3345 36 7898 ;?DGGMN

More information

1.1 INTRODUCTION. The Lessee is proposes to produce about 7315 Cum/year of Colour Granite. The total cost of the project is Rs.

1.1 INTRODUCTION. The Lessee is proposes to produce about 7315 Cum/year of Colour Granite. The total cost of the project is Rs. 1. INTRODUCTION 1.1 INTRODUCTION M/s.M.S.P GRANITES have granted quarry lease for Colour Granite over an extent of 16.56 Hectare in Sy. No. 01 of Kori Village, Parvathipuram Mandal, Vizianagaram District,

More information

Project Name: Nangal (M.L. No. 134/03) Masonary Stone Mine PRE- FEASIBILITY REPORT

Project Name: Nangal (M.L. No. 134/03) Masonary Stone Mine PRE- FEASIBILITY REPORT PRE- FEASIBILITY REPORT 1.0 EXECUTIVE SUMMARY 1.1 Executive Summary The proposed mining project falls under Category A Project or activity 1(a) as per EIA Notifications 2006 and amended thereof due to

More information

Proposed Terms of Reference for EIA studies

Proposed Terms of Reference for EIA studies Proposed Terms of Reference for EIA studies 1(a): STANDARD TERMS OF REFERENCE FOR CONDUCTING ENVIRONMENT IMPACT ASSESSMENT STUDY FOR NON-COAL MINING PROJECTS AND INFORMATION TO BE INCLUDED IN EIA/EMP REPORT

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT PRE FEASIBILITY REPORT ON NAFRI STONE QUARRY NO.2 (IN MAYURBHANJ DISTRICT OF ODISHA) Lease Area: 4.97 acres or 2.01 Ha. of Sri Shyamsundar Bhattar & Others Baripada EXECUTIVE SUMMARY CHAPTER 1 Nafri Stone

More information

2x800 MW Thermal Power Project Near Village Paraspani, Tehsil Pathargama, Godda- District By Adani Power (Jharkhand) Limited

2x800 MW Thermal Power Project Near Village Paraspani, Tehsil Pathargama, Godda- District By Adani Power (Jharkhand) Limited (IV) Proposed Terms of Reference for EIA Studies Project Category Project Proponent Location Paraspani Thermal Power Plant (2x800 MW) Coal based Thermal Power Project A [1(d) Thermal Power Plant 500 MW]

More information

COMPLIANCE STATUS OF CONDITIONS IMPOSED IN ENVIRONMENTAL CLEARANCE FOR 8.5 MTPA BAUXITE MINING VIDE LETTER NO J-11015/650/2007-IA.II(M),DTD.19.02.

COMPLIANCE STATUS OF CONDITIONS IMPOSED IN ENVIRONMENTAL CLEARANCE FOR 8.5 MTPA BAUXITE MINING VIDE LETTER NO J-11015/650/2007-IA.II(M),DTD.19.02. COMPLIANCE STATUS OF CONDITIONS IMPOSED IN ENVIRONMENTAL CLEARANCE FOR 8.5 MTPA BAUXITE MINING VIDE LETTER NO J-11015/650/2007-IA.II(M),DTD.19.02.09 PROJECT NAME: UTKAL ALUMINA INTERNATIOAL LIMITED. PERIOD

More information

For Building Stone Quarry

For Building Stone Quarry ENVIRONMENTAL MANAGEMENT PLAN For Building Stone Quarry Of M/s Valchand K Shaha At Sy No: 105/4A Yamagarni Village, Chikkodi Taluk, Belgaum District, Karnataka (Extent- 1-00 Acres) 1 CHAPTER-01 Project

More information

M/s. Karshanbhai Bhagvanbhai Rabari

M/s. Karshanbhai Bhagvanbhai Rabari PRE FEASIBILITY REPORT FOR M/s. Karshanbhai Bhagvanbhai Rabari Black TRAP MINING (AREA 1.00 HECTARE) OF APPLICANT Mr. Karshanbhai Bhagvanbhai Rabari (Proprietor) AT Survey No. 194 Paikee, Vill: Thoriyali,

More information

Pre-Feasibility Report For Building Stone Quarry Of M/s G T B Enterprises At Sy No: 23, Thammanayakanahally Village, Anekal Taluk, Bengaluru District, Karnataka (Extent- 4-00 Acre) Pre-Feasibility Report

More information

Building Stone Quarry

Building Stone Quarry ENVIRONMENTAL MANAGEMENT PLAN For Building Stone Quarry Of Sri. Shivappa Puttappa Basapur In part of Sy No. 28/A, Bingapur village, Hangal Taluk Haveri District, Karnataka (Extent- 1-00 Acres) 1 CHAPTER-01

More information

1. INTRODUCTION. The lessee proposes to produce only about 10,188 TPA of Barytes. The total cost of the project is Rs. 20 lakhs only.

1. INTRODUCTION. The lessee proposes to produce only about 10,188 TPA of Barytes. The total cost of the project is Rs. 20 lakhs only. 1. INTRODUCTION 1.1 INTRODUCTION M/S SOUTHERN MINING COMPANY was granted a Barytes mine Lease area over an extent of 4.048 hectares in Sy. No: 944,945 & 946 of Kalva Village, Orvakal Mandal, Kurnool District

More information

Project Details-Minor Minerals ( Rajula Building Stone)

Project Details-Minor Minerals ( Rajula Building Stone) Project Details-Minor Minerals ( Rajula Building Stone) Sr.No. Details Particulars PROPOSAL 1. Name of Lease Holder Dineshbhai Laljibhai Sarvaiya 2. Location address At Village : Rajula, Ta : Rajula, Dist

More information

PROPOSAL FOR HOUSTON COUNTY BAN ON SILICA SAND MINING / PROCESSING ACTIVITY. Introduction and Assumptions

PROPOSAL FOR HOUSTON COUNTY BAN ON SILICA SAND MINING / PROCESSING ACTIVITY. Introduction and Assumptions PROPOSAL FOR HOUSTON COUNTY BAN ON SILICA SAND MINING / PROCESSING ACTIVITY Introduction and Assumptions 1. The existing section 27 Mineral Extraction of the Zoning Ordinance would remain and continue

More information

PROJECT DETAILS. Smt. Rajeshwari M.Viraktamath of Lokapur, Mudhol Taluk, Bagalkot Dist has a

PROJECT DETAILS. Smt. Rajeshwari M.Viraktamath of Lokapur, Mudhol Taluk, Bagalkot Dist has a 1 CHAPTER-01 1. Introduction PROJECT DETAILS Smt. Rajeshwari M.Viraktamath of Lokapur, Mudhol Taluk, Bagalkot Dist has a mining lease M.L.No 2425, over an area of 2.78 Ha, in the Sy.Nos. 76/2, Patta Land

More information

Storm Water Management Requirements for Construction Projects Less than One Acre

Storm Water Management Requirements for Construction Projects Less than One Acre Storm Water Management Requirements for Construction Projects Less than One Acre Purpose: UC Irvine s Phase II Small MS4 Storm Water Permit requires construction projects less than one acre in size to

More information

ENVIRONMENTAL MANAGEMENT PLAN. Nilaya Hills/ Heights Promoted by M/s RBS Developers (Group Housing & Commercial Building Project)

ENVIRONMENTAL MANAGEMENT PLAN. Nilaya Hills/ Heights Promoted by M/s RBS Developers (Group Housing & Commercial Building Project) ENVIRONMENTAL MANAGEMENT PLAN Of Nilaya Hills/ Heights Promoted by M/s RBS Developers (Group Housing & Commercial Building Project) at Khasra Nos. 1353Min,1354Min,1355, 1356, 1358, 1357, 1587 Ka, 1587Kha,

More information

The Terms of reference (ToR) for conducting Rapid EIA study for the proposed project is described below:

The Terms of reference (ToR) for conducting Rapid EIA study for the proposed project is described below: Proposed Terms of Reference for EIA Study Objective: In order to identify the environmental impacts due to construction and operation of the proposed project and associated facilities, a study will be

More information

Pollution Incident Response Plan

Pollution Incident Response Plan Pollution Incident Response Plan Introduction Schmidt Quarries is committed to ensuring all aspects of our quarrying activities comply with the environmental legislative requirements in NSW. This Pollution

More information

ENVIROMENT MANAGEMENT PLAN FOR DEVGAON SAND STONE DEPOSIT AREA 2.00 HECTARE TEHSIL RITHI DISTT- KATNI (M.P)

ENVIROMENT MANAGEMENT PLAN FOR DEVGAON SAND STONE DEPOSIT AREA 2.00 HECTARE TEHSIL RITHI DISTT- KATNI (M.P) VILLAGE : DEVGAON TEHSIL : RITHI DISTRICT : KATNI MINERAL : SAND STONE KHASRA NO : 7 PART AREA : 2.00 HECTARE PRPOSED PRODUCTION: 800 M 3 /YEAR STATE : MADHYA PRADESH LEASE PERIOD : 10 YEAR SUBMITTED UNDER

More information

STANDARD TEMPLATE FOR EVALUATION OF ALL PROJECTS / ACTIVITIES. 2 Name of the organization/owner. M/s.N.R.Global Granite

STANDARD TEMPLATE FOR EVALUATION OF ALL PROJECTS / ACTIVITIES. 2 Name of the organization/owner. M/s.N.R.Global Granite STANDARD TEMPLATE FOR EVALUATION OF ALL PROJECTS / ACTIVITIES S.No Information required Information to be furnished by the proponents 1 Name of the project or activity Black Granite Mines 2 Name of the

More information

Policy and Regulations Faridabad (India)

Policy and Regulations Faridabad (India) Policy and Regulations Faridabad (2009) Policy and Regulations Faridabad (India) 1.1 Policies No specific regulations have been framed for addressing the management of plastic waste, and it is thus governed

More information

Outlet stabilization structure

Outlet stabilization structure Overview of Sedimentation and Erosion Control Practices Practice no. 6.41 Outlet stabilization structure Erosion at the outlet of channels, culverts, and other structures is common, and can cause structural

More information

WILLOCHRA BASIN GROUNDWATER STATUS REPORT 2009-10

WILLOCHRA BASIN GROUNDWATER STATUS REPORT 2009-10 WILLOCHRA BASIN GROUNDWATER STATUS REPORT 2009-10 SUMMARY 2009-10 The Willochra Basin is situated in the southern Flinders Ranges in the Mid-North of South Australia, approximately 50 km east of Port Augusta

More information

PRE- FEASIBILITY STUDY REPORT. M/s. SAI MINERALS

PRE- FEASIBILITY STUDY REPORT. M/s. SAI MINERALS PRE- FEASIBILITY STUDY REPORT FOR M/s. SAI MINERALS BLACK TRAP MINING (AREA 04-00-00 HECTARE) OF APPLICANT (Mr. AMARJITSINH R. VARACHHIYA) (PARTNER) AT SURVEY NO: 13, AT: ASHNAVI, TAL: JHAGADIA, DIST:

More information

Definition of Tower from the Bradley County Zoning Resolution

Definition of Tower from the Bradley County Zoning Resolution Definition of Tower from the Bradley County Zoning Resolution 43. TOWER. Any outdoor structure designed and constructed to support one (1) or more transmitting or receiving devices for telephone, radio

More information

There is no water, surface tension cracks, nor other environmental conditions present that reduce the stability of the excavation.

There is no water, surface tension cracks, nor other environmental conditions present that reduce the stability of the excavation. Part 1926 Subpart P Introduction The Occupational Safety and Health Administration (OSHA) issued its first Excavation and Trenching Standard in 1971 to protect workers from excavation hazards. Since then,

More information

Environmental Management Plan

Environmental Management Plan Environmental Management Plan ENVIRONMENTAL MANAGEMENT PLAN 1. INTRODUCTION: 1.1 Background: The mining lease, for colour granite over an extent of 1.0 ha. in Sy No.333 of Arikara Village, Alur Mandal,

More information

Arya Geo-Tech Services Amit Mishra (Geologist) Regd. No. RQP/DGMMP/66/2013,Valid upto 29/07/2018 Kabara Colony, Nagpur Road Distt.-Chhindwara (M.P.

Arya Geo-Tech Services Amit Mishra (Geologist) Regd. No. RQP/DGMMP/66/2013,Valid upto 29/07/2018 Kabara Colony, Nagpur Road Distt.-Chhindwara (M.P. VILLAGE : SALIYA BINEKA TEHSIL : BANDA DISTRICT : SAGAR MINERAL : CRUSHER STONE KHASRA NO : 270 AREA : 2.00 HECTARE PRPOSED PRODUCTION : 18000 M 3 /Year STATE : MADHYA PRADESH LEASE PERIOD : 10 YEAR SUBMITTED

More information

Birmingham City University / Students Union Aspects and Impacts Register. Waste. Impacts description

Birmingham City University / Students Union Aspects and Impacts Register. Waste. Impacts description Birmingham City University / Students Union and Impacts Register Waste Production of non - hazardous waste Production of hazardous waste Storage of non - hazardous waste Potential for waste to be disposed

More information

Emergency Spillways (Sediment basins)

Emergency Spillways (Sediment basins) Emergency Spillways (Sediment basins) DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short-Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1] [1]

More information

PROPOSED BASALT QUARRY

PROPOSED BASALT QUARRY RISK ASSESSMENT FOR PROPOSED BASALT QUARRY OF SHRI RAKESH VIKAS POWAR Page 1 1. Introduction A main principle of risk assessment is that it should take place before any changes are made. Risks should be

More information

City of Shelbyville Site Inspection Checklist

City of Shelbyville Site Inspection Checklist City of Shelbyville Site Inspection Checklist General Information Project Name: KYR10 Permit Number: Date: Project Location: Contractor: Conractor Representative: Inspector's Name: Title: Signature : Weather

More information

PRE-FEASIBILITY CUM EMP REPORT FOR SAND EXTRACTION PROJECT (FROM RIVER PURNA PAT) FOR. KESHAVBHAI RATANJIBHAI PATEL 150 MT/day

PRE-FEASIBILITY CUM EMP REPORT FOR SAND EXTRACTION PROJECT (FROM RIVER PURNA PAT) FOR. KESHAVBHAI RATANJIBHAI PATEL 150 MT/day A PRE-FEASIBILITY CUM EMP REPORT FOR SAND EXTRACTION PROJECT (FROM RIVER PURNA PAT) FOR KESHAVBHAI RATANJIBHAI PATEL 150 MT/day VILL.:VIRPOR, TAL.: VALOD, DIST.: TAPI INDEX LIST OF CONTENTS CHAPTER DESCRIPTION

More information

PRE-FEASIBILITY CUM DETAIL PROJECT REPORT FOR SAND EXTRACTION PROJECT: 300 MT/DAY (FROM RIVER TAPI PAT)

PRE-FEASIBILITY CUM DETAIL PROJECT REPORT FOR SAND EXTRACTION PROJECT: 300 MT/DAY (FROM RIVER TAPI PAT) A PRE-FEASIBILITY CUM DETAIL PROJECT REPORT FOR SAND EXTRACTION PROJECT: 300 MT/DAY (FROM RIVER TAPI PAT) OF PADMABEN JAYANTIBHAI OAD RESI. AT: VILL: GHALA, TAL: KAMREJ, DIST: SURAT INDEX LIST OF CONTENTS

More information

BRITISH GEOLOGICAL SURVEY

BRITISH GEOLOGICAL SURVEY BRITISH GEOLOGICAL SURVEY RISK ASSESSMENT FOR WORKING IN QUARRIES Definitions from Health & Safety Executive anything that can cause harm. the chance that someone will be harmed by the hazard. Health and

More information

Environmental Site Inspection Checklist

Environmental Site Inspection Checklist Note : This form is designed for general use and may not be exhaustive. Modifications and additions may be necessary to suit individual projects and to address specific environmental issues and associated

More information

PRE- FEASIBILITY STUDY REPORT

PRE- FEASIBILITY STUDY REPORT PRE- FEASIBILITY STUDY REPORT FOR RAJNIKANT GORDHANBHAI CHANIYARA PROPOSED BLACK TRAP MINING (AREA 03-00-53 HECTARE) OF APPLICANT (Mr.Rajnikant Gordhanbhai chaniyara) (PAWOR OF ATTORNEY) AT BLOCK NO: 66

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT PRE FEASIBILITY REPORT. 23 TABLE OF CONTENT Sr. No. Content Page No. 1.0 Executive Summary 25 2.0 Introduction of Project and Background Information 26 3.0 Project Description 28 4.0 Site Analysis 33 5.0

More information

LIQUID WASTE TREATMENT FACILITY MENDIS ROAD, HUDSON CREEK DRAFT GUIDELINES FOR A PUBLIC ENVIRONMENTAL REPORT

LIQUID WASTE TREATMENT FACILITY MENDIS ROAD, HUDSON CREEK DRAFT GUIDELINES FOR A PUBLIC ENVIRONMENTAL REPORT LIQUID WASTE TREATMENT FACILITY MENDIS ROAD, HUDSON CREEK DRAFT GUIDELINES FOR A PUBLIC ENVIRONMENTAL REPORT Introduction The purpose of this Public Environmental Report (PER) is to provide the Government

More information