1 VILLAGE : DEVGAON TEHSIL : RITHI DISTRICT : KATNI MINERAL : SAND STONE KHASRA NO : 7 PART AREA : 2.00 HECTARE PRPOSED PRODUCTION: 800 M 3 /YEAR STATE : MADHYA PRADESH LEASE PERIOD : 10 YEAR SUBMITTED UNDER RULES 42 (E) & PMCP UNDER 42 (J-2) OF MMR, 1996 FOR GRANT OF QUARRY LEASE LESSEE: SHRI RAHMAN KHAN BALIMA SMT JAMILA B W/O LATE SHRI SIKANDAR KHAN,RESI. VILLAGE DEVGAON, TEHSIL. RITHI DISTT. KATNI (M.P) PREPARED BY: Address:- Arya Geo-Tech Services Amit Mishra (Geologist) Regd. No. RQP/DGMMP/66/2013,Valid upto 29/07/2018 Kabara Colony, Nagpur Road Distt.-Chhindwara (M.P.),

2 1. ENVIROMENT MANAGEMENT PLAN (A) A NOTE THE STATUS OF THE BASE LINE INFORMATION WITH REGARD TO THE FOLLOWING- 1.0 Introduction The environment management plan has been prepared for subject opencast semi mechanized mining operation for Sand stone with capacity of 800 m 3 per year. The EMP includes formulation, implementation and monitoring of environmental protection measures during operation of the project. The EMP list out all these measures for the mining activities. The EMP is prepared keeping in view of all possible strategies oriented towards impact minimization. The main objectives of EMP are given below: To establish the present environmental scenario considering the other activities in the study area. To anticipate the impacts of existing and proposed mining operations on the environment. To prepare a detailed action plan for implementation of mitigative measures. To suggest preventive and mitigative measures to minimise adverse impacts and to maximize beneficial impacts. To suggest a post operational monitoring programmes of mitigative measures to ensure the quality of environment To suggest the formation of a core group responsible for implementation of protective measures and regular monitoring of such implementation To prepare a capital cost estimate and annual recurring cost for Environmental Management Plan. Through environment plan is under execution for existing operation; however it is required to provide further strength for effectiveness. Mitigation measures at the source level and an overall management plan are elicited so as to conserve the environment. It is observed that quarry area is recorded as degreased sand stone. There is no quarries are adjacent to the subject area and no another quarries are located in the 500 meter radius. Water body in SW direction canal Implementation of EMP is should consider the above stated tenure. The environmental attributes, which are likely to be affected, are land use, topography, water resources, soil, air quality, socio-economic status, ecology and public health. Environmental Management System The management as a part of its environment policy declared its responsibility and commitment to protect the environment and to ensure the public safety.

3 To realise the implementation of its environmental policy, project management should give proper structure to environmental management system. Air Environment The potential sources of air pollution arising from the existing is observed from excavation of mineral, waste dumps, haul roads and transportation of mineral in the vicinity. Air pollution caused by mining and associated activities can be classified into the following categories: Gaseous pollutants (Nitrogen Oxides, Sulphur Dioxide and Carbon Monoxides); and Particulate Matter. Forever mitigative measures suggested for air pollution control are based on the baseline ambient air quality monitoring data. It is desirable that air quality should be monitored on a regular basis to check it vis-à-vis the standards prescribed by CPCB and in cases of non-compliance, appropriate mitigative measures has also been adopted. Dust control measures Dust is the major pollutant generated from the mining operations. Dust is also generated during handling and transportation of the material. The environmental control measures, which has been taken up are existing as well as proposed to control the fugitive dust released during the sand stone production are given below: a) Haulage road & Dumps: During the mining of Sand stone boulder for following measures has been taken to mitigate the effect of Sand stone mining operation over ambient air environment: Frequent Water spraying has already been carried out on the haulage roads, services road & dump area and same practice will continue in future also. Considering the location of village dumping has been done in North West and south direction. Over burden dumps will not be left active for longer period and will be used for reclamation purposes. Over burden dumps has been temporary stabilized with legumes and grasses to prevent the erosion of soil and to arrest the dust emission during windy days. Water has already been sprayed over the muck pile and dumps to reduced the dust generation; Dust mask has been provided to all workers. Regular maintenance of vehicles and machines has been carried out in order to control emissions; Cutting tools for Sand stone have been used with the spray of water to reduce the dust emission.

4 During the drilling of Sand stone block, water has been sprayed, so reduced the dust emission. Emission Sources and Control Options Operation or source Mining Operations Loading Hauling (emissions from roads) Control options Water wetting Water wetting, Soil stabilization, Traffic control. All above measures is expected to be continue in future Controlling of CO levels The concentration of CO in ambient air was less than 1 ppm at This can be controlled by proper maintenance and servicing of vehicles. Controlling of NO2 levels The source of NO2 would be due to vehicular emissions. This can be controlled by proper maintenance and servicing of vehicles. Occupational health & safety measure wrt air environment All the above precautions has been adopted to prevent dust generation at site and to be dispersed in the outside environment. However, for the safety of workers at site, dust masks have also been provided. Dust masks is help to prevent preventing inhalation of PM thereby reducing the risk of lung diseases and other respiratory disorders. Regular health monitoring (ones in a year) of workers has also been carried out. Noise Environment The main source of noise in mining activity vehicle movement ambient noise levels are well within the stipulated limits of CPCB. Blasting and drilling has been not required for mining activity as per mining plan. In order to further control the noise levels in the work zone following measures are adopted: Mitigation Measures to Reduce Ambient Noise Levels The following control measures are being adopted to keep the ambient noise levels well below the limits: A thick tree belt shall be being provided in phased manner around the periphery of the mine to screen the noise; Trees shall be planted on both sides of roads used for transport of men and material; Proper maintenance has been done of noise generating machinery including the transport vehicles; and Silencers have been provided to modulate the noise generated by machines. Installation of noise generating machinery, strictly in compliance with the recommendations of the manufacturers. This would ensure an

5 installation free from vibration and exhaust leaks which are also major contributors to increased noise levels Provision of insulating caps and aids at the exit of noise source on the machinery. Use of damping materials such as thin rubber sheet for wrapping the worn places of compressors, generators etc. Shock absorbing techniques to reduce impact Apart from above, the formation of internal dump and green belt development will also muffle the noise to a great extent. Regular maintenance of machines and vehicles have been carried out regularly. All moving parts of machine have been properly lubricated; Non-moving parts of machine have been properly fastened Acoustic treatment for rotating equipments Measures to Protect Workers from High Noise Levels The following measures have been taken to protect the workers from exposure to higher noise levels: i. The workforce working at the mining face, where high noise level is expected, has been provided with protective device for occupational safety. ii. Compulsory use of personnel protective equipment (PPE) such as ear plugs for the workers Water Environment There is no water course in the lease area. Water body for sw direction. The water table in the quarry area varies from 20 to 30 m whereas mining will be done up to avg m above surface level thus ground water table will not touch during conceptual period. Surface water source will not be affected in the quarry area due to small scale, opencast mining. Rainwater may get accumulated in the working pit. The pumped out water will be used to fill the village pond, which is used by villagers. The quality of discharged water must be ensured after settling tank before draining at pond. Water requirement of the project is estimated is 2.00 kl per day, which will be met from existing bore well, pit water and through tanker. Following measures has been taken to avoid accumulation of water: 1. Pump has already been installed to lift accumulated rain water from working pit. 2. Garland drain have been proposed to nearest nalla the waste dumps which help to restrict/retain the loose particles. Depth & length of garland drain is observed 0.50m and 1000 m respectively.

6 3. Garland drains have been proposed made along the slop of hill along the village side. Length & depth of garland drain is observed approx 1000 m and 2.5m 4. It must be ensured that silt content in the mines discharged is minimum. 5. It must be ensured that quality of drinking water for the worker is hygienic. Land Environment and solid waste management The original topography of the part of area will further be affected due to the operation. Land use details as per mining plan after and before mining operation. Biological Environment Since there are no notified endangered species in the area, which will be effected due to the mining activities, therefore the biological environment will not have significant impact due to proposed activity. The impact on the biological environment due to amount of dust generation is minimised by welldeveloped green belt in and around mining lease area. The green belt development not only functions as foreground and background landscape features resulting in harmonizing and amalgamating the physical structures of the mines with surrounding environment, but also acts as pollution sink as indicated above. Thus, implementation of afforestation program is of paramount importance. In addition to augmenting present vegetation, it will also check soil erosion, make the ecosystem more complex and functionally, stable and make the climate more conducive. The plantation matrix should be adopted for the green belt development includes pits of 0.3m x 0.3m x 0.3 m size with the spacing of 2.0 m x 2.0m. Selection Criteria of plant species for Green Development Plant The selection of plant species for the development depends on various factors such as climate, elevation and soil. Area falls under the tropical region and thus the local species should be selected. Following criteria may be taken for selection of species. The species should be fast growing. The species should form a dense canopy. As far as possible, the species should be indigenous and locally available Soil improving plants (Nitrogen fixing, rapidly decomposable leaf litter). Plant Species for Mine Area and its Boundary Acacia nilotica Leuceana leucocephala Albizzia species Morus indica/alba Acacia auriculiformis Prosopis species Azadirachta indicata Syzygium cuminii

7 Annona squamosa Tamarindus indica Bauhinia variegata Terminelia arjuna Butea monosperma Zizyphus species Cassia festula Carissa species Dalbergia sisoo Feronia species Erythrina indica Phylanthus species Ficus bengalensis Madhuca species Ficus religiosa Magnifera species Grewia species Leuceana leucocephala Plantation Schedule A stage-wise comprehensive afforestation program is prepared and shall be implemented. The locations of the proposed greenbelt along with area of the green cover are given in the conceptual plan. Afforestation plan ENVIRONMENT IMPACT & MANAGEMENT: Ecology: Stage Wise Cumulative Plantation REQUIREMENTS OF PLANTS FOR AFFORESTATION/RECLAMATION Year Unworked Plantation area bench of pit Village side Total area green belt Area Trees Area Trees Area Trees Area Trees Area Trees Present Nil Nil 1 st to 5th th to conceptual period Total Occupational, Health and Safety To avoid any adverse affects on the health of workers due to dust & noise, sufficient measures have been provided in the mining project. These may include: Provision of rest shelters for mine workers with amenities like drinking water, fans, toilets etc. Provision of personal protection devices to the workers; Dust suppression of haul road; and First-aid facilities in the mining area. The management will carry out periodical health check up with view to ascertaining the effective implementation of policy. All first aid facilities has already been provided in the quarry office All the medicines prescribed by doctors has been provided to the employees at free of cost by the management. The working personnel has already been given the following appropriate personnel protective equipments. Industrial safety helmets.

8 Ear plugs. Industrial safety shoes. Safety helmets Safety spectacles Gas tight rubber goggles Petromax lamp/torches Axes/hand saw Gloves (PVC, asbestos, special rubber make)- Rubber glove Blanket Rubber sole shoes and gum boots Safety shoes with toe protection Shoes with non-skid soles Safety belt with life line (leather, hard rubber or neoprene) Socio economic Measures Socio-economic was been conducted in 5 villages of the study area out of villages. The selected villages under its CSR plan identifies the needs of the surrounding villages and has developed a social management plan to benefit the surrounding areas. Thus the surrounding villages have been benefited from the mining activity. Local employed generated approximate 20 numbers as per the qualification and skill unskilled. Has already carried out number of welfare activities in the area like: Proposed CSR activate Samuhik Kanya Vivah Deeping of local pond Free Medical Camp (Eye & Dental check-up) Contribute to Local Area Development Fund Free drinking water supply facility to nearby village by Tanker Details of budgetary arrangement for environment management. Cost of EMP S. No. Head 1 Air pollution monitoring 2 Water pollution monitoring Approximate Capital cost (Rs. In lacs/annum) Basis 0.30 Cost has been include water spray arrangement 0.30 Include cost of septic tank, garland Approximate Basis recurring cost per annum (Rs. in lacs/annum) 0.20 Expected cost includes regular monitoring by approved third party 0.20 Expected cost includes regular monitoring by approved third

9 S. No. Head 3 Noise pollution monitoring 4 Solid and hazardous waste management 5 Environmental Monitoring and management 6 Plantation at Site Approximate Capital cost (Rs. In lacs/annum) Basis Approximate recurring cost per annum (Rs. in lacs/annum) Basis drain, party Expected cost includes regular monitoring by approved third party 0.00 Capital cost 0.00 include cost of providing garland drain, settling tank & dump management Recurring cost would incur on hiring of consultants for environmental management and payment of various statutory fees to Regulatory agencies 0.40 Plantation in and around site. TOTAL Maintenance of plantation Signature AMIT KUMAR MISHRA REGN. NO. RQP/DGMMP/66/2013 Valid up to

Arya Geo-Tech Services Amit Mishra (Geologist) Regd. No. RQP/DGMMP/66/2013,Valid upto 29/07/2018 Kabara Colony, Nagpur Road Distt.-Chhindwara (M.P.

Arya Geo-Tech Services Amit Mishra (Geologist) Regd. No. RQP/DGMMP/66/2013,Valid upto 29/07/2018 Kabara Colony, Nagpur Road Distt.-Chhindwara (M.P. VILLAGE : SALIYA BINEKA TEHSIL : BANDA DISTRICT : SAGAR MINERAL : CRUSHER STONE KHASRA NO : 270 AREA : 2.00 HECTARE PRPOSED PRODUCTION : 18000 M 3 /Year STATE : MADHYA PRADESH LEASE PERIOD : 10 YEAR SUBMITTED

More information

ENVIRONMENT MANAGEMENT PLAN

ENVIRONMENT MANAGEMENT PLAN ENVIRONMENT MANAGEMENT PLAN FOR VILLAGE TEHSIL DISTRICT AREA MINERAL : Makrohar : Mada : Singrauli (M.P.) : 1.00 hect : Metal Stone KHASRA No : 176,178 PRODUCTION CAP : 15375 Cu.mt/year Metal Stone APPLICANT

More information

ENVIRONMENT MANAGEMENT PLAN

ENVIRONMENT MANAGEMENT PLAN ENVIRONMENT MANAGEMENT PLAN OF M/s Baghel Infrastructure Pvt. Ltd. AT Khasra No 1203/1 Vill- Makrohar, Tehsil-Mada, District-Singrauli (M.P.) Production Capacity: 8158Cu.mt/year Metal Stone Area 1.00 Hectare

More information

ENVIRONMENT MANAGEMENT PLAN

ENVIRONMENT MANAGEMENT PLAN ENVIRONMENT MANAGEMENT PLAN OF Shri Kuldeep Choudhary AT Khasra No.Part of 112 Vill.-Golpura, Tehsil-Gandhwani, District-Dhar (M.P.) Production Capacity: 4543 Cu.mt/year Basalt Stone&4543 Cu.mt/year Murram

More information

ENVIRONMENT MANAGEMENT PLAN

ENVIRONMENT MANAGEMENT PLAN ENVIRONMENT MANAGEMENT PLAN LIMESTONE 1. INTRODUCTION: The proposed Bagdhara Limestone area, near Village- Bagdhara, Taluka- Jamjodhpur and District-Jamnagar, Gujarat has been granted to Dipakkumar Anantray

More information

ENVIRONMENTAL MANAGEMENT PLAN :-

ENVIRONMENTAL MANAGEMENT PLAN :- ENVIRONMENTAL MANAGEMENT PLAN :- The Environment Management Plan (EMP) is required to ensure sustainable development in the area of the proposed project. Hence it needs to be all encompassive plan for

More information

ENVIRONMENT MANAGEMENT PLAN

ENVIRONMENT MANAGEMENT PLAN ENVIRONMENT MANAGEMENT PLAN Page 33 ENVIRONMENT MANAGEMENT PLAN BLACK TRAP 1.0. INTRODUCTION: The proposed M/s. Black Trap Mine of Govindbhai Karshanbhai Ram area at near Vill.Chuldi, Tal.Malia-Hatina,

More information

ENVIRONMENT MANAGEMENT PLAN

ENVIRONMENT MANAGEMENT PLAN ENVIRONMENT MANAGEMENT PLAN FOR VILLAGE TEHSIL DISTRICT AREA MINERAL : Kothi : Pawai : Panna (M.P.) : 1.370 Hectare : Flagstone KHASRA No : 31 PRODUCTION CAP : Max 875 Cu.mt/year Flagstone APPLICANT Shri

More information

ENVIRONMENT MANAGEMENT PLAN

ENVIRONMENT MANAGEMENT PLAN ENVIRONMENT MANAGEMENT PLAN ENVIrONMENT MaNaGEMENT plan 1. INTRODUCTION: Shri Ratilal Ravji Solanki have a Blacktrap mining lease project for an area of 1.00.00 Ha located on Survey no. 984 paiki, Village:

More information

Environment Management Plan

Environment Management Plan Environment Management Plan FOR Quarry Lease of Crusher Stone Area 1.437Hectare, Kh. No. 40/8 KA AT Village: BHAWANDA, Tehsil: SEONI MALWA Distt HOSHANGABAD (M. P.) Proponent M/S JYORI CONSTRUCTION COMPANY

More information

Environment Management Plan

Environment Management Plan Environment Management Plan FOR Mining of Agariya Crusher stone Quarry Area-4.00,Hectare Kh No-141/3/1,141/4,141/5 At Village- Agariya, Tehsil: Gouharganj Distt. Raisen SHRI. ASHOK SHARMA S/O SHRI GANGAPRASAD

More information

Environment Management Plan

Environment Management Plan Environment Management Plan FOR Mining of Crusher Stone Area 2.000 Hectare, Khasra No. 42/2 Village AT THANWARI Tehsil District State SEONI SEONI MADHYA PRADESH Proponent SHRI LAKHAN LAL S/O SHRI CHETAN

More information

PROPOSED TERMS OF REFERENCE

PROPOSED TERMS OF REFERENCE PROPOSED TERMS OF REFERENCE ABOUT THE PROJECT: Rampura Marble Mine (ML No.- 420/91) is proposed by M/s Continental Minerals Pvt. Ltd. The Mine Lease area consists of 3.0 ha, which is located at Khasra

More information

ENVIRONMENT MANAGEMENT PLAN

ENVIRONMENT MANAGEMENT PLAN ENVIRONMENT MANAGEMENT PLAN 1 [Type the company name] ENVIRONMENT MANAGEMENT PLAN LIMESTONE (BUILDING) 1.0. INTRODUCTION: The proposed M/s. Building Lime Stone Mine of Shree Jitubhai Parbatbhai Chudashma

More information

Environment Management Plan

Environment Management Plan Environment Management Plan FOR Mining of Sildhara Flage Stone Quarry Area-.1.50,Hectare Kh No-87 At Village- Sildhara, Tehsil Panna, Distt.Panna MR.BRIJMOHAN SINGH S/O SHRI JAI RAM SINGH RESI-VILLAGE

More information

Proposed Terms of Reference for EIA studies

Proposed Terms of Reference for EIA studies 1 Proposed Terms of Reference for EIA studies Base line data collection will be collected for the Post-Monsoon season 2016 (September to November 2016) in study area and 10 kms radius from project site.

More information

EnVirOnMEnT ManaGEMEnT PLan. FOr. M/S. LiME STOnE MinE OF. Dhirajlal Panchanbhai Vachhani. area. PrOPOSEd PrOdUCTiOn:-36000 TPa

EnVirOnMEnT ManaGEMEnT PLan. FOr. M/S. LiME STOnE MinE OF. Dhirajlal Panchanbhai Vachhani. area. PrOPOSEd PrOdUCTiOn:-36000 TPa EnVirOnMEnT ManaGEMEnT PLan FOr M/S. LiME STOnE MinE OF dhirajlal PanChhanBhai VaChhani area (SUrVEY no.49 PaiKi, ViLL.Unadari, TaL.Una, dis.junagadh) PrOPOSEd PrOdUCTiOn:-36000 TPa PrOJECT COST: - 15

More information

Project Details- Minor Minerals (Other Than Sand)

Project Details- Minor Minerals (Other Than Sand) Project - Minor Minerals (Other Than Sand) Sr. ABOUT THE PROPOSAL 1. Name of Lease Holder M/s. KARMANBHAI JODHABHAI RABARI (Partner) 2. Location address Mr. Karmanbhai Jodhabhai Rabari Survey No- 194 Paikee,

More information

Environmental Management Plan

Environmental Management Plan Environmental Management Plan FOR BOULDER, GRAVEL AND SAND MINOR MINERAL Mine lease area: 13.20 Ha Village Mandlai Tehsil Raipur Rani, District- Panchkula and State - Haryana Category of Project: B2 Lease

More information

Project Details- Minor Minerals (Other Than Sand)

Project Details- Minor Minerals (Other Than Sand) Project - Minor Minerals (Other Than Sand) Sr. ABOUT THE PROPOSAL 1. Name of Lease Holder M/s. ABDUL MUNAF MOHAMMEDMIYA MALEK Mr.Abdul Munaf Mohammedmiya malek (Proprietor) 2. Location address OPP Block

More information

Environmental Management Plan

Environmental Management Plan Environmental Management Plan ENVIRONMENTAL MANAGEMENT PLAN An Environmental Management Plan is prepared for construction phase, post construction phase (commissioning & operation) and for post project

More information

CHANDAM7AIL,P SAND DEPOSIT

CHANDAM7AIL,P SAND DEPOSIT 1 RVER SAND QUARRY 11 ENVRONMENT MANEGMENT PLAN OF CHANDAM7AL,P SAND DEPOST VLLAGE- GHAWDAWAL, TEHSHL- LAltEAR DSTRCT- BMTUD, STATE- MADHYA PRADESH (MASRL4 NO- 1, 10, 15, AREA- 5.975 Hectare APPLCANT Sub

More information

Final Environmental Impact Assessment of Smt. Singam Bhavani Laterite Mining ADDITIONAL STUDIES

Final Environmental Impact Assessment of Smt. Singam Bhavani Laterite Mining ADDITIONAL STUDIES ADDITIONAL STUDIES 7.0 DISASTER MANAGEMENT PLAN It is presumed that the proposed mining process would be designed and engineered with all possible safety measures and standard code of practices. In spite

More information

Project Details-Minor Minerals (Other Than Sand)

Project Details-Minor Minerals (Other Than Sand) Project Details-Minor Minerals (Other Than Sand) Sr. No. Details Particulars ABOUT THE PROPOSAL 1. Name Of lease Holder M/s. Kirtikumar Samji Sengani 23 0'27.43"N 69 24'10.21"E 2. Location address Survey

More information

ENVIRONMENTAL MANAGEMENT PLAN

ENVIRONMENTAL MANAGEMENT PLAN ENVIRONMENTAL MANAGEMENT PLAN CONTENTS OF ENVIRONMENTAL MANAGEMENT PLAN Chapter Title Page No. 1. INTRODUCTION 1-4 2. PROJECT PROPONENT 1 2.1 Project Location and Accessibility 1 2.2 Infrastructure and

More information

ENVIRONMENT MANAGEMENT PLAN

ENVIRONMENT MANAGEMENT PLAN 6. REHABILITATION AND RESETTLEMENT (R & R) PLAN Since the project is private land, there is no reserves forest or protected forest land within the applied area. There is no human settlements within the

More information

2. PRE-FEASIBILITY REPORT

2. PRE-FEASIBILITY REPORT 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The proposed project is Building stone quarry having lease area of 1.214 ha and falls under Category- A as per EIA Notification 2006 and its amendments of

More information

S/o Vishnudas Chakraborty, residence at R/o Narsinghgarh, District Rajgarh (M.P.).

S/o Vishnudas Chakraborty, residence at R/o Narsinghgarh, District Rajgarh (M.P.). RISK ASSESSMENT The Crusher stone deposit lease area is located at Village Badodiya Jagir, Tehsil - Narsinghgarh, District - Rajgarh (M.P.). 02.00 Ha quarry lease area with production of 3306 cubic meter/year

More information

ENVIRONMENT MANAGEMENT PLAN

ENVIRONMENT MANAGEMENT PLAN 1.0 INTRODUCTION ENVIRONMENT MANAGEMENT PLAN The Environment Management Plan has been developed with a view to bring down the levels of impacts during proposed mining activities In each of the areas of

More information

2. PRE-FEASIBILITY REPORT

2. PRE-FEASIBILITY REPORT 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The proposed project is Building stone quarry having lease area of 0.809 ha and falls under Category- A as per EIA Notification 2006 and its amendments of

More information

Fauna- No particular type of fauna finds except snakes, hynus & Jackals, wild cat, wildhen etc. are found in and around the area.

Fauna- No particular type of fauna finds except snakes, hynus & Jackals, wild cat, wildhen etc. are found in and around the area. Environmental Management Plan Baseline information Topography:- The general slope of the area is towards east and gently sloping from 25 0 to 30 0 except southern part which is sloping towards south The

More information

ENVIRONMENTAL MANAGEMENT PLAN. Nilaya Hills/ Heights Promoted by M/s RBS Developers (Group Housing & Commercial Building Project)

ENVIRONMENTAL MANAGEMENT PLAN. Nilaya Hills/ Heights Promoted by M/s RBS Developers (Group Housing & Commercial Building Project) ENVIRONMENTAL MANAGEMENT PLAN Of Nilaya Hills/ Heights Promoted by M/s RBS Developers (Group Housing & Commercial Building Project) at Khasra Nos. 1353Min,1354Min,1355, 1356, 1358, 1357, 1587 Ka, 1587Kha,

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT PRE FEASIBILITY REPORT for PROPOSED PROJECT FOR SOIL MINING of M/s. BHAVINKUMAR VINODBHAI LAD SURVEY NO. 98, MOJE ANCHELI, TAL. BARDOLI, DIST. SURAT, GUJARAT 1 CONTENTS Sr. Description Page No. No. 1.

More information

How To Conduct An Environmental Impact Assessment

How To Conduct An Environmental Impact Assessment Proposed Terms of Reference for EIA studies 1. Introduction The proposed expansion of Bulk Drugs & Intermediates manufacturing unit by M/s. Sri Krishna Pharmaceuticals Limited (Unit V). is located at Plot

More information

ENVIRONMENTAL MANAGEMENT PLAN

ENVIRONMENTAL MANAGEMENT PLAN ENVIRONMENTAL MANAGEMENT PLAN Of M/s. SRINIVASA GRANITES 5.010 HA COLOUR GRANITE MINING SY. NO. 539/B & 546/P UPPAMAGULUR (V), BALLIKURAVA (M) PRAKASAM (DT), ANDHRA PRADESH Submitted by SV ENVIRO LABS

More information

ENVIRONMENTAL MANAGEMENT PLAN

ENVIRONMENTAL MANAGEMENT PLAN Of MINING OF BLACK GRANITE 1.0 HA SURVEY NO: 38/11 OF CHINNAGANDLAPALLI VILLAGE, SANTHIPURAM MANDAL, CHITTOOR DISTRICT, ANDHRA PRADESH. By M/s. EVERSHINE GRANITILES LAKSHMIPURAM, KUPPAM, CHITTOOR, ANDHRA

More information

STANDARD TEMPLATE FOR EVALUATION OF ALL PROJECTS / ACTIVITIES. 2 Name of the organization/owner. M/s.N.R.Global Granite

STANDARD TEMPLATE FOR EVALUATION OF ALL PROJECTS / ACTIVITIES. 2 Name of the organization/owner. M/s.N.R.Global Granite STANDARD TEMPLATE FOR EVALUATION OF ALL PROJECTS / ACTIVITIES S.No Information required Information to be furnished by the proponents 1 Name of the project or activity Black Granite Mines 2 Name of the

More information

PROJECT DETAILS. Smt. Rajeshwari M.Viraktamath of Lokapur, Mudhol Taluk, Bagalkot Dist has a

PROJECT DETAILS. Smt. Rajeshwari M.Viraktamath of Lokapur, Mudhol Taluk, Bagalkot Dist has a 1 CHAPTER-01 1. Introduction PROJECT DETAILS Smt. Rajeshwari M.Viraktamath of Lokapur, Mudhol Taluk, Bagalkot Dist has a mining lease M.L.No 2425, over an area of 2.78 Ha, in the Sy.Nos. 76/2, Patta Land

More information

TERMS OF REFERENCE FOR SCOPING OF EIA STUDY

TERMS OF REFERENCE FOR SCOPING OF EIA STUDY TERMS OF REFERENCE FOR SCOPING OF EIA STUDY Ours project is a proposed large scale unit and categorized as 5(h)-B as per the EIA notification 2006 of MoEFCC, New Delhi and subsequent amendments. Looking

More information

The Terms of reference (ToR) for conducting Rapid EIA study for the proposed project is described below:

The Terms of reference (ToR) for conducting Rapid EIA study for the proposed project is described below: Proposed Terms of Reference for EIA Study Objective: In order to identify the environmental impacts due to construction and operation of the proposed project and associated facilities, a study will be

More information

PROJECT PROPONENT : B.ASHOK KUMAR, S/O. B.SHESHANNA SHETTY, YESHAWANTHA NAGAR, SANDUR -583119, BELLARY KARNATAKA.

PROJECT PROPONENT : B.ASHOK KUMAR, S/O. B.SHESHANNA SHETTY, YESHAWANTHA NAGAR, SANDUR -583119, BELLARY KARNATAKA. BUILDING STONE QUARRY NOTIFICATION. No. DMG/DDH/QLS/NTN-17/2014-15/1659, EXTENT : 14.55 ACRES, SITUATED IN SY. No. 240 OF KALINGERI VILLAGE, SANDUR TALUK, BELLARY DISTRICT, KARNATAKA. PROJECT PROPONENT

More information

Pre-Feasibility Report For Building Stone Quarry Of M/s G T B Enterprises At Sy No: 23, Thammanayakanahally Village, Anekal Taluk, Bengaluru District, Karnataka (Extent- 4-00 Acre) Pre-Feasibility Report

More information

ENVIRONMENTAL MANAGEMENT PLAN

ENVIRONMENTAL MANAGEMENT PLAN ENVIRONMENTAL MANAGEMENT PLAN Of M/s. MARAM VENKA REDDY GRANITES 2.077 HA COLOUR GRANITE MINING SY. NO. 103/P (USH-VEERLAKONDA) KONIDENA (V), BALLIKURAVA (M) PRAKASAM (DT), ANDHRA PRADESH Submitted by

More information

Building Stone Quarry

Building Stone Quarry ENVIRONMENTAL MANAGEMENT PLAN For Building Stone Quarry Of Sri. Shivappa Puttappa Basapur In part of Sy No. 28/A, Bingapur village, Hangal Taluk Haveri District, Karnataka (Extent- 1-00 Acres) 1 CHAPTER-01

More information

PRE-FEASIBILITY CUM EMP REPORT FOR SAND EXTRACTION PROJECT (FROM RIVER PURNA PAT) FOR. KESHAVBHAI RATANJIBHAI PATEL 150 MT/day

PRE-FEASIBILITY CUM EMP REPORT FOR SAND EXTRACTION PROJECT (FROM RIVER PURNA PAT) FOR. KESHAVBHAI RATANJIBHAI PATEL 150 MT/day A PRE-FEASIBILITY CUM EMP REPORT FOR SAND EXTRACTION PROJECT (FROM RIVER PURNA PAT) FOR KESHAVBHAI RATANJIBHAI PATEL 150 MT/day VILL.:VIRPOR, TAL.: VALOD, DIST.: TAPI INDEX LIST OF CONTENTS CHAPTER DESCRIPTION

More information

PRE-FEASIBILITY REPORT

PRE-FEASIBILITY REPORT PRE-FEASIBILITY REPORT OF MASONRY STONE (CHEJA PATTHAR) MINING PROJECT (ML Area: 1.0 ha, M.L. No. 65/2011, Production Capacity-1, 11,780 TPA) Near Village: Gangora, Tehsil: Pahari, District: Bharatapur

More information

PRE-FEASIBILITY CUM DETAIL PROJECT REPORT FOR SAND EXTRACTION PROJECT: 300 MT/DAY (FROM RIVER TAPI PAT)

PRE-FEASIBILITY CUM DETAIL PROJECT REPORT FOR SAND EXTRACTION PROJECT: 300 MT/DAY (FROM RIVER TAPI PAT) A PRE-FEASIBILITY CUM DETAIL PROJECT REPORT FOR SAND EXTRACTION PROJECT: 300 MT/DAY (FROM RIVER TAPI PAT) OF PADMABEN JAYANTIBHAI OAD RESI. AT: VILL: GHALA, TAL: KAMREJ, DIST: SURAT INDEX LIST OF CONTENTS

More information

PROPOSED TERMS OF REFERENCE

PROPOSED TERMS OF REFERENCE Annexure-IV PROPOSED TERMS OF REFERENCE 1.0 Proposed Scope of Work for EIA Study The components of the EIA study include: Detailed description of all elements of the project activities (existing and proposed

More information

RISK ASSESSMENT. STONE QUARRY (2.40 Ha)

RISK ASSESSMENT. STONE QUARRY (2.40 Ha) RISK ASSESSMENT FOR STONE QUARRY (2.40 Ha) Gat no. 85, A/p Karanjvihire, Tahsil Khed, District Pune, Maharashtra OF M/s Shankar Ramchandra Earthmovers Pvt. Ltd. Risk Assessment for Stone Quarry Mining

More information

Environment Impact Assessment study:

Environment Impact Assessment study: (A) Environment Impact Assessment study: 1. Pollution Potential: Air Emission: Dust Emission during Mining, Transportation & Crushing of the Stones which will be controlled by water sprinkling and development

More information

ENVIRONMENTAL MANAGEMENT PLAN

ENVIRONMENTAL MANAGEMENT PLAN ENVIRONMENTAL MANAGEMENT PLAN Of M/s. D.BHARATHI 11.76 Acres Silica Sand Mine, Sy.No. 44/3,50/4,50/5&50/6 ADDEPALLI (V), CHILLAKUR (M), SPSR NELLORE DISTRICT ANDHRA PRADESH Prepared by SV ENVIRO LABS &

More information

TERMS OF REFERENCE FOR THE RAPID EIA STUDY FOR SHIVKAR LIGNITE BLOCK, DIST. BARMER, RAJASTHAN

TERMS OF REFERENCE FOR THE RAPID EIA STUDY FOR SHIVKAR LIGNITE BLOCK, DIST. BARMER, RAJASTHAN 1. GENERAL TERMS OF REFERENCE FOR THE RAPID EIA STUDY FOR SHIVKAR LIGNITE BLOCK, DIST. BARMER, RAJASTHAN The main objective of the EIA study is to assess the positive and negative impacts likely to accrue

More information

PRE- FEASIBILITY REPORT

PRE- FEASIBILITY REPORT PRE- FEASIBILITY REPORT Applicant: M/s Regaliya Minerals Pvt. Ltd. Page 0 1.0 EXECUTIVE SUMMARY This mining project falls under Category A (presence of interstate boundary between Haryana and Rajasthan

More information

Proposed Terms of Reference for EIA studies

Proposed Terms of Reference for EIA studies Proposed Terms of Reference for EIA studies 1(a): STANDARD TERMS OF REFERENCE FOR CONDUCTING ENVIRONMENT IMPACT ASSESSMENT STUDY FOR NON-COAL MINING PROJECTS AND INFORMATION TO BE INCLUDED IN EIA/EMP REPORT

More information

2x800 MW Thermal Power Project Near Village Paraspani, Tehsil Pathargama, Godda- District By Adani Power (Jharkhand) Limited

2x800 MW Thermal Power Project Near Village Paraspani, Tehsil Pathargama, Godda- District By Adani Power (Jharkhand) Limited (IV) Proposed Terms of Reference for EIA Studies Project Category Project Proponent Location Paraspani Thermal Power Plant (2x800 MW) Coal based Thermal Power Project A [1(d) Thermal Power Plant 500 MW]

More information

Birmingham City University / Students Union Aspects and Impacts Register. Waste. Impacts description

Birmingham City University / Students Union Aspects and Impacts Register. Waste. Impacts description Birmingham City University / Students Union and Impacts Register Waste Production of non - hazardous waste Production of hazardous waste Storage of non - hazardous waste Potential for waste to be disposed

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT PRE FEASIBILITY REPORT. 23 TABLE OF CONTENT Sr. No. Content Page No. 1.0 Executive Summary 25 2.0 Introduction of Project and Background Information 26 3.0 Project Description 28 4.0 Site Analysis 33 5.0

More information

For Building Stone Quarry

For Building Stone Quarry ENVIRONMENTAL MANAGEMENT PLAN For Building Stone Quarry Of M/s Valchand K Shaha At Sy No: 105/4A Yamagarni Village, Chikkodi Taluk, Belgaum District, Karnataka (Extent- 1-00 Acres) 1 CHAPTER-01 Project

More information

Project Details-Minor Minerals ( Rajula Building Stone)

Project Details-Minor Minerals ( Rajula Building Stone) Project Details-Minor Minerals ( Rajula Building Stone) Sr.No. Details Particulars PROPOSAL 1. Name of Lease Holder Dineshbhai Laljibhai Sarvaiya 2. Location address At Village : Rajula, Ta : Rajula, Dist

More information

Sustainable Resource Management Ltd

Sustainable Resource Management Ltd 6.0 Predicted nvironmental Impacts 6. Stages and Impacts Considered An nvironmental Impact Analysis has been carried out whereby all the possible environmental, socio economic and health & safety aspects

More information

SAFETY DATA SHEET EVO-STIK PLUMBERS MAIT

SAFETY DATA SHEET EVO-STIK PLUMBERS MAIT Revision Date November 2012 Revision 9 1 / 5 SAFETY DATA SHEET According to Regulation (EC) No 1907/2006 SECTION 1: IDENTIFICATION OF THE SUBSTANCE/MIXTURE AND OF THE COMPANY/UNDERTAKING 1.1. Product identifier

More information

ENVIRONMENT MANAGEMENT PLAN

ENVIRONMENT MANAGEMENT PLAN ENVIRONMENT MANAGEMENT PLAN 1.0 Introduction This report discusses the management plan for mitigation/abatement of adverse environmental impacts and enhancement of beneficial impacts due to mining. The

More information

TERMS OF REFERENCE. BEFORE CONSTRUCTION: Sl No TOR RESPONSE 1. Legalities of the land: Is the land The Project is clear from all angles.

TERMS OF REFERENCE. BEFORE CONSTRUCTION: Sl No TOR RESPONSE 1. Legalities of the land: Is the land The Project is clear from all angles. TERMS OF REFERENCE Name of the Project: M/s Suadela Constructions Pvt. Ltd. Address: Sy.No. 321/2B(P),321/2C(P),322/1,323/1(P),323/1(P),323/3,323/4,323/5(P), 323/6,323/7,325/1(P),325/2,327,328/1,328/2(P),328/3,328/4,330,331,332/2

More information

ABANDONMENT COST, FINANCIAL ASSURANCE AND PRESENTATION OF THE DOCUMENT. Abandonment cost :

ABANDONMENT COST, FINANCIAL ASSURANCE AND PRESENTATION OF THE DOCUMENT. Abandonment cost : ABANDONMENT COST, FINANCIAL ASSURANCE AND PRESENTATION OF THE DOCUMENT. Abandonment cost : Determining the cost associated with closure and accruing these costs during the life of the mining operation

More information

ENVIRONMENT MANAGEMENT PLAN

ENVIRONMENT MANAGEMENT PLAN ENVIRONMENT MANAGEMENT PLAN 1.0 Introduction This report discusses the management plan for mitigation/abatement of adverse environmental impacts and enhancement of beneficial impacts due to mining. The

More information

RISK ASSESSMENT REPORT

RISK ASSESSMENT REPORT RISK ASSESSMENT REPORT Submitted by: Rakesh Kumar, Partner M/s Maluka Bricks Industry Village Maluka, Sub-Tehsil Bhagta Bhaika, Tehsil & District Bathinda. (Punjab) (M): 0-98141-22141 1 ACTIVITY 2 1. Construction,

More information

RISK ASSESSMENT REPORT

RISK ASSESSMENT REPORT RISK ASSESSMENT REPORT Submitted by: M/s D.D. Bricks Co. Prop. : Harbhagwan Village: Mohan Ke Uttar Tehsil: Guru Harsahai District: Ferozepur, Punjab (M): 0-99993-38601 Construction, operation or decommissioning

More information

Environment Management Plan. Residential & Commercial project

Environment Management Plan. Residential & Commercial project For Residential & Commercial project at S. No. 44 (P), 45 (P) & 46 (p), Village Balewadi, Tehsil Haveli, District Pune Contents Introduction... 3 1.1 During construction phase... 3 1.2 During operation

More information

1.1 INTRODUCTION. The Lessee is proposes to produce about 7315 Cum/year of Colour Granite. The total cost of the project is Rs.

1.1 INTRODUCTION. The Lessee is proposes to produce about 7315 Cum/year of Colour Granite. The total cost of the project is Rs. 1. INTRODUCTION 1.1 INTRODUCTION M/s.M.S.P GRANITES have granted quarry lease for Colour Granite over an extent of 16.56 Hectare in Sy. No. 01 of Kori Village, Parvathipuram Mandal, Vizianagaram District,

More information

Environment Impact Assessment of Thermal Power Plant for Sustainable Development

Environment Impact Assessment of Thermal Power Plant for Sustainable Development International Journal of Environmental Engineering and Management. ISSN 2231-1319, Volume 4, Number 6 (2013), pp. 567-572 Research India Publications http://www.ripublication.com/ ijeem.htm Environment

More information

TERMS OF REFERENCE FOR THE RAPID EIA STUDY

TERMS OF REFERENCE FOR THE RAPID EIA STUDY TERMS OF REFERENCE FOR THE RAPID EIA STUDY 1 SUMMARY OF EIA METHODOLOGY STEP I : SCOPING OF THE ASSESSMENT Own with prevailing regulatory setting and criteria Identification of Environmental Assessment

More information

APPENDIX 4. Risk Tables

APPENDIX 4. Risk Tables APPENDIX 4 Tables Preliminary Qualitative Criteria The qualitative risk assessment criteria have been developed to identify key risks to the environment, society, heritage and business reputation. The

More information

Pre- FEASIBILITY REPORT

Pre- FEASIBILITY REPORT Pre- FEASIBILITY REPORT In Respect Of JHILIMINDA SAND BED OVER 20.30 ACRES OR 8.215 HA IN VILLAGE JHILIMINDA, ATTABIRA TAHASIL OF BARGARH DISTRICT, ODISHA (For the Financial Year-2015-16 to 2019-20) Prepared

More information

G. M. Nagaraju Environment Management Plan

G. M. Nagaraju Environment Management Plan ENVIRONMENT MANAGEMENT PLAN 1.0 Introduction This report discusses the management plan for mitigation/abatement of adverse environmental impacts and enhancement of beneficial impacts due to mining. The

More information

Environmental Management Plan

Environmental Management Plan Environmental Management Plan ENVIRONMENTAL MANAGEMENT PLAN 1.0 Introduction: Background: The Quarry lease, for Black Granite over an extent of 1.482 ha. in Sy Nos. 10 & 23, Sankavaram Village, Kanigiri

More information

PRE- FEASIBILITY STUDY REPORT. M/s. SAI MINERALS

PRE- FEASIBILITY STUDY REPORT. M/s. SAI MINERALS PRE- FEASIBILITY STUDY REPORT FOR M/s. SAI MINERALS BLACK TRAP MINING (AREA 04-00-00 HECTARE) OF APPLICANT (Mr. AMARJITSINH R. VARACHHIYA) (PARTNER) AT SURVEY NO: 13, AT: ASHNAVI, TAL: JHAGADIA, DIST:

More information

PRE-FEASIBILITY REPORT FOR SHAHABAD STONE QUARRYING. In 1-30 Acres of Patta Land Survey Number: 48/2 Kallur Road Village

PRE-FEASIBILITY REPORT FOR SHAHABAD STONE QUARRYING. In 1-30 Acres of Patta Land Survey Number: 48/2 Kallur Road Village PRE-FEASIBILITY REPORT FOR SHAHABAD STONE QUARRYING In 1-30 Acres of Patta Land Survey Number: 48/2 Kallur Road Village Chincholi Taluk Kalaburagi District, Karnataka By Sri. Jagannath S/o Sri. Shiva Reddy

More information

Ratdi Limestone (Building) Mine Location Near Village- Ratdi, Taluka & district Porbandar, (Gujarat) Latitude. 9.0m RL.

Ratdi Limestone (Building) Mine Location Near Village- Ratdi, Taluka & district Porbandar, (Gujarat) Latitude. 9.0m RL. PRE-FEASIBILITY REPORT 1. EXECUTIVE SUMMARY: Particulars Details Project Name Ratdi Limestone (Building) Mine Location Near Village- Ratdi, Taluka & district Porbandar, (Gujarat) Latitude 21 0 73 73.4

More information

COMPLIANCE STATUS OF CONDITIONS IMPOSED IN ENVIRONMENTAL CLEARANCE FOR 8.5 MTPA BAUXITE MINING VIDE LETTER NO J-11015/650/2007-IA.II(M),DTD.19.02.

COMPLIANCE STATUS OF CONDITIONS IMPOSED IN ENVIRONMENTAL CLEARANCE FOR 8.5 MTPA BAUXITE MINING VIDE LETTER NO J-11015/650/2007-IA.II(M),DTD.19.02. COMPLIANCE STATUS OF CONDITIONS IMPOSED IN ENVIRONMENTAL CLEARANCE FOR 8.5 MTPA BAUXITE MINING VIDE LETTER NO J-11015/650/2007-IA.II(M),DTD.19.02.09 PROJECT NAME: UTKAL ALUMINA INTERNATIOAL LIMITED. PERIOD

More information

SAFETY DATA SHEET BOSTIK AQUAGRIP 536

SAFETY DATA SHEET BOSTIK AQUAGRIP 536 Revision Date November 2014 1 / 6 SAFETY DATA SHEET BOSTIK AQUAGRIP 536 According to Regulation (EC) No 1907/2006 SECTION 1: IDENTIFICATION OF THE SUBSTANCE/MIXTURE AND OF THE COMPANY/UNDERTAKING 1.1.

More information

Physical flow accounts: principles and general concepts

Physical flow accounts: principles and general concepts Physical flow accounts: principles and general concepts Julian Chow United Nations Statistics Division 1 st Sub-Regional Course on SEEA 23-27 September 2013 Malaysia SEEA Conceptual Framework Outside territory

More information

Pre- FEASIBILITY REPORT

Pre- FEASIBILITY REPORT Pre- FEASIBILITY REPORT In Respect Of SRIPURA SAND BED-BOVER 35.25 ACRES OR 14.265 HA IN VILLAGE SRIPURA, JHARSUGUDA TAHASIL OF JHARSUGUDA DISTRICT, ODISHA (For the Financial Year-2015-16 to 2019-20) Prepared

More information

LIQUID WASTE TREATMENT FACILITY MENDIS ROAD, HUDSON CREEK DRAFT GUIDELINES FOR A PUBLIC ENVIRONMENTAL REPORT

LIQUID WASTE TREATMENT FACILITY MENDIS ROAD, HUDSON CREEK DRAFT GUIDELINES FOR A PUBLIC ENVIRONMENTAL REPORT LIQUID WASTE TREATMENT FACILITY MENDIS ROAD, HUDSON CREEK DRAFT GUIDELINES FOR A PUBLIC ENVIRONMENTAL REPORT Introduction The purpose of this Public Environmental Report (PER) is to provide the Government

More information

Project Details-Minor Minerals (Sand Stone)

Project Details-Minor Minerals (Sand Stone) Project Details-Minor Minerals (Sand Stone) Sr. Details Particulars No. PROPOSAL 1. Name of Lease Holder MANSUKHBHAI CHIKANBHAI KALADIYA 2. Location Address Sand Stone mining at Survey no:- 503 Paiki,

More information

[SIMPLIFIED MINING SCHEME] Index

[SIMPLIFIED MINING SCHEME] Index Index S.No DESCRIPTION PAGE NO. 01 General information about lessee 05 02 Details of mining lease 06-08 03 No.of existing mining pits, their dimensions and 08-12 locations, plan & section of the pits,

More information

PRE-FEASIBILITY REPORT

PRE-FEASIBILITY REPORT PRE-FEASIBILITY REPORT FOR QUARRYING ROUGH STONE Over an Extent of 0.34.8 Hectares in S.F. No. 22/5A (Patta Land) in Kachchirayanpatti Village, Melur Taluk, Madurai District & Tamil Nadu State 1. EXECUTIVE

More information

Introduction to Waste Treatment Technologies. Contents. Household waste

Introduction to Waste Treatment Technologies. Contents. Household waste Contents Introduction to waste treatment technologies 3 Section 1: The treatment of recyclable waste 4 Bulking facilities 5 Materials Reclamation Facility (MRF) 6 Reuse and recycling centres 8 Composting

More information

Environmental guidelines for preparation of an Environment Management Plan

Environmental guidelines for preparation of an Environment Management Plan Environmental guidelines for preparation of an Environment Management Plan Environment Protection Authority MAY 2013 Australian Capital Territory, Canberra 2013 This work is copyright. Apart from any use

More information

V. ENVIRONMENTAL IMPACT ANALYSIS E. Hazardous Materials

V. ENVIRONMENTAL IMPACT ANALYSIS E. Hazardous Materials E. HAZARDOUS MATERIALS An Environmental Site Assessment Phase I Update was performed on the subject properties by California Environmental Inc. in March 2000 1. This report is included in Appendix E of

More information

PRE-FEASIBILITY REPORT FOR FULLERS EARTH QUARRYING

PRE-FEASIBILITY REPORT FOR FULLERS EARTH QUARRYING PRE-FEASIBILITY REPORT FOR FULLERS EARTH QUARRYING In 2-00 Acres of Patta Land Survey Number: 68/1 Kudhalli Village Chincholi Taluk Kalaburgi District, Karnataka By Srishail G Sajjan S/o Sri Gutteppa Sajjan

More information

Sl No Specific conditions : Status

Sl No Specific conditions : Status Conditions of MoEF, Govt. of India, New Delhi vide MoEF vide letter No. J-11015/345/2007-IA.II(M) dated 10 th Dec. 2008 issued with Environmental Clearance with reference to Mahagiri Mines (Chromite) of

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT PRE FEASIBILITY REPORT ON NAFRI STONE QUARRY NO.2 (IN MAYURBHANJ DISTRICT OF ODISHA) Lease Area: 4.97 acres or 2.01 Ha. of Sri Shyamsundar Bhattar & Others Baripada EXECUTIVE SUMMARY CHAPTER 1 Nafri Stone

More information

Environmental Guidelines for Preparation of an Environmental Management Plan

Environmental Guidelines for Preparation of an Environmental Management Plan 2013 Environmental Guidelines for Preparation of an Environmental Management Plan Environmental Management Division Environmental Protection Agency 3/13/2013 ENVIRONMENTAL GUIDELINES FOR PREPARATION OF

More information

Executable EMP for Residential & Commercial Project by Ms. Abisky Ritkriti Keshavnagar LLP

Executable EMP for Residential & Commercial Project by Ms. Abisky Ritkriti Keshavnagar LLP Executable EMP for Residential & Commercial Project by Ms. Abisky Ritkriti Keshavnagar LLP Project Location: S.No. 8/3/2, 8/3/3, Mundhwa, Tal- Haveli, Dist- Pune. Project Details: 1 Plot Area 14200 sqm

More information

Climate Change and Sri Lanka. Ajith Silva Director/ Policy and Planning Ministry of Environment and Natural Resources Sri Lanka

Climate Change and Sri Lanka. Ajith Silva Director/ Policy and Planning Ministry of Environment and Natural Resources Sri Lanka Climate Change and Sri Lanka Ajith Silva Director/ Policy and Planning Ministry of Environment and Natural Resources Sri Lanka Asia Total Area: 65610 Km Land Area : 62705 Km Inland water : 2905 Km 2 Coastal

More information

PRE FEASIBILITY REPORT & ENVIRONMENT MANAGEMENT PLAN

PRE FEASIBILITY REPORT & ENVIRONMENT MANAGEMENT PLAN PRE FEASIBILITY REPORT & ENVIRONMENT MANAGEMENT PLAN Of COLOUR GRANITE MINE 1.000 HA SURVEY NO: 186/1 OF KUPPIGANIPALLI VILLAGE, GUDUPALLI MANDAL, CHITTOOR DISTRICT, ANDHRA PRADESH. Proposed By M/s. SREE

More information

Pre-feasibility Report

Pre-feasibility Report 1.0 INTRODUCTION EXECUTIVE SUMMARY Balanga Sand Bed over an area of 12.50Ac./5.06Ha. of, Sri Nilamani Behera is located in village Uthaninuagaon, under Tahasil- Badasahi in Mayurbhanj district of Odisha.

More information

sustainability report

sustainability report sustainability report Sustainable development In the midst of turbulent macro-economic conditions adversely impacting the coal sector, we maintain our focus on building a business that has a viable, long-term

More information

APPLICATION (FORM-1, PRE-FEASIBILITY REPORT)

APPLICATION (FORM-1, PRE-FEASIBILITY REPORT) APPLICATION (FORM-1, PRE-FEASIBILITY REPORT) Environmental Clearance For Minor Mineral Mine Rampuri Stone Mine Mining Lease Area: 4.85Ha, Proposed Production: 50,107 TPA Quartzite AT Village- Rampuri,

More information

1.1 INTRODUCTION. The Lessee is proposes to produce about 200 Cum/year of Black Granite. The total cost of the project is Rs.

1.1 INTRODUCTION. The Lessee is proposes to produce about 200 Cum/year of Black Granite. The total cost of the project is Rs. 1. INTRODUCTION 1.1 INTRODUCTION M/s.SOHAN ART & GRANITE INDUSTRY have granted quarry lease for Black Granite over an extent of 1.00 Hectare in Sy. No. 101 of Kappali Village, Ramasamudram Mandal, Chittoor

More information