The Stockholm bypass. Stuttgart, 17 th of February 2014
|
|
- Dana Phillips
- 7 years ago
- Views:
Transcription
1 The Stockholm bypass Stuttgart, 17 th of February 2014 Johan Brantmark, Project Director Lars Malthe, Head of Procurement Louise Melander, Head of Communication
2
3 A city on water
4 with a vulnerable traffic system
5 A growing metropolitan region 2 million today 2.4 million by 2030 The County of Stockholm is growing by approximately 100 persons a day
6 Regional development plan The Stockholm bypass will: form an outer ring road together with Norrortsleden and Crossconnection Södertörn link north and south and many of the regional urban cores create a single market for jobs, homes and services
7 Why we need The Stockholm bypass To make life easier in a growing region Fuse together north and south single market for homes, jobs and services Develop more regional cores Reduce the vulnerability of Stockholm s transport system New opportunities for public transport on and outside the bypass Environmental benefits thanks to less congestion, more space for public transport and a better urban environment
8
9 The Stockholm bypass Length: Tunnel: Travel time: No. of lanes: Interchanges: Traffic 2035: Cost: just over 21 km just over 18 km approximately 15 minutes three in each direction six 140,000 vehicles/day SEK 27.6 billion EUR 3.1 billion (2009 prices)
10 Just over 18 out of 21 km in tunnels Current E18 C Current C E4 Graphics: Tomas Öhrling 2010 Stockholm bypass cross-section with slopes up to junctions at Lovö and Vinsta. Note that the drawing is not to scale
11 Main tunnel 2 parallel main tunnels 3 lanes in each direction Emergency exits every 100 m 17+1 km in length Normal section approx.135 m² Ramp tunnels approx. 20 km
12 A safe journey The security concept is being elaborated in collaboration with other authorities Safe design Parallel tunnels without oncoming traffic Round the clock CCTV Frequent emergency exits Permanent fire fighting system Detectors
13
14 Environment and climate 80% of the road runs in a tunnel to minimise impact on the environment and residential areas Guideline values for noise and air quality in and outside the tunnel must be achieved Energy-efficient solutions will be applied ADFASDFASDFASDFASDF
15 The Royal Domain of Drottningholm
16 In the next two years we need to procure Tunnels and Civil works to a total value of 2 billion euro. Johan Brantmark
17 Contracting tenders preliminary plan Six contracts for the main tunnel Six interchanges comprises five major contracts E&M Contracts Preparatory work ADFASDFASDFASDFASDF
18 Interchanges From south to north: Kungens kurva Lovö Vinsta Hjulsta Akalla Häggvik
19 Kungens Kurva in brief 3 Interchanges
20 Kungens kurva today
21 Interchange Kungens kurva
22 ADFASDFASDFASDFASDF
23 ADFASDFASDFASDFASDF
24
25 Kungens kurva, Contracts FSE 101 Roads and Bridges Vårby Backe FSE 105 Concrete Tunnel Kungens Kurva FSE 117 Pedestrian and Bicycle Bridge Kungens Kurva FSE 215 Concrete Tunnels Skärholmen Primary amounts Excavated rock m 3 Excavated soil m 3 Concrete m 3 Soil reinforcement m 2 Excavated rock m 3 Excavated soil m 3 Concrete m 3 Soil reinforcement m 2 Concrete tunnel incl. trough m Rock tunnel 20 m Eight metres wide 150 metres long Construction time about 1.5 years Excavated rock m 3 Excavated soil m 3 Concrete m 3 Soil reinforcement m
26 Lovö, Vinsta, Hjulsta in brief 3 Interchanges
27 Hjulsta today
28 Interchange Hjulsta
29 Hjulsta, Contracts FSE501 - Hjulsta södra Interchange FSE502 - Hjulsta norra Interchange Primary amounts, total No. metres (3+3 lanes) new/reconstructed road: approx. 1.8 km Of this total no. metres of road: - in concrete tunnel: approx. 550 m - concrete trench: approx. 150 m - on bridges: approx. 700 m No. metres new/reconstructed road for ramps and local road with 1 to 2 lanes: approx. 2.5 km Of which total no. metres of road: - on bridges: approx. 550 m No. metres of lime cement columns: approx m of columns No. metres new/reconstructed pedestrian/cycle path: approx. 500 m Plus various re-laying of water pipes and cables Piling and Sheet piling
30 Akalla-Häggvik in brief 2 Interchanges
31 Akalla today
32 Interchange Akalla
33 Häggvik today
34 Interchange Häggvik
35 Akalla & Häggvik, Contracts FS 61 Akalla interchange FS 62 Häggvik interchange Primary amounts, total Major construction elements: 2.5 km new motorway 6 concrete bridges, totalling 500 m in length, the longest bridge 230 m 3 concrete tunnels, total length 550 m 1 concrete trench of 300 m Supporting walls, total length m Flat slabs m
36 Rock tunnels in brief
37 Construction = Temporary jetties Length main tunnels: 2x18 km Length ramp tunnels: approx. 14 km 3 temporary jetties Total rock: 19 million tonnes Boring method: Drill & blast 6 main contracts Work at several sites simultaneously Minimise disruption Access tunnels Temporary jetty
38 3 temporary jetties Approximately 50 percent of the rock mass will be transported between the access tunnels in Sätra, Malmviken and the north of Lovö by sea to temporary reception points
39
40
41 Rock tunnels, Contracts Description Primary amounts, rock FSE 209 Main tunnel, Skärholmen m 3 FSE 210 FSE 302 FSE 308 Access tunnels and temporary harbour, Skärholmen Access tunnels, temporary harbour and main tunnel, Norra Lovö Access tunnels, temporary harbour and main tunnel, Södra Lovö m m m 3 FSE 403 Main tunnel, Johannelund m 3 FSE 410 Access tunnels and main tunnel, Lunda m 3 FSE 607 Access tunnel, Akalla m 3 FSE 613 Main tunnel, Akalla m
42 Sale of rock masses The Swedish Transport Administration intends to sell the rock masses from the main tunnels as follows: The total sales volume amounts to approximately 19 million tonnes of rock masses. The Swedish Transport Administration owns the rock masses that are excavated from the rock tunnel contracts. (however, for early contracts concerning work tunnels, the contractor owns the rock masses) The Swedish Transport Administration can as an option also own the rock masses that are excavated from above-ground contracts. The Swedish Transport Administration signs contracts concerning the sale with one or more buyers of the rock masses with a reception in the region responsible for the necessary permits, reception and storage of the rock masses. The contractors for rock tunnels transport and deliver the rock masses to the Swedish Transport Administration's assigned buyers
43 Installations of Mechanical and Electrical Systems Upcoming procurement: Spring of 2014 FSE815 Communication systems during construction The contract include Radio systems in the main tunnel Access Control Systems Evacuation Alarm Control and Monitoring System Size of contract: 5-10 million euro
44 Challenges Safety during construction Traffic Management during construction Quality controll during construction Minimize effects on climate Sensitive culture landscape and environment Ground water management 3D Modelling - BIM Keeping time and costs
45 GOVERNMENT S PERMISSIBILITY ASSESSMENT EIA, 2009 (Gained legal force 2011) The Stockholm bypass 2014 and onwards LAND AQUISITION PLAN MUNICIPALITIES DETAILED DEVELOPMENT PLANS OTHER ASSESSMENTS (Natura 2000) (Nature and culture reserves) ENVIRONMENTAL RULINGS PROJECT PLANNING CONSTRUCTION DOCUMENTS CONSTRUCTION Time EIA = Environmental Impact Assessment
46 Procurement of contracts in
47 Time schedule for procurements The first tender request Prequalification Requests for main contracts Procurements of infrastructure operations Procurement of installation contracts Time
48 Procurement forms The Stockholm bypass project procure in accordance with the Swedish Public Procurement Act (LOU). The majority of our contract procurements are above the threshold value. This means that all procurements are published in the EU database Tenders Electronic Daily (TED). Selective procurement - prequalification will be selected when many bidders can be expected, or for reasons of time pressure
49 Our tender request documents As a starting point, all technical qualifications and contract documents are drawn up in Swedish. If a need is demonstrated, individual documents as well as complete acts can be translated into English. We follow the industry's common standard agreements for contracts such as AB 04 and ABT
50 Contract forms Somewhat simplified, the contract forms can be summarised as follows. Rock tunnels and work tunnels are procured as build only contracts, based on BQ. Bridges and concrete tunnels for junctions are procured as design-build contracts. Roads and reconstructions of existing installations are procured as build only contracts based on BQ. Installations in tunnels are procured as design-build contract, based on system and functional requirements
51 Language Prequalification: Swedish or English Contract and as built: Swedish During construction: Swedish or English ADFASDFASDFASDFASDF
52 Question time
Member Nation Report 2010 from Denmark.
Member Nation Report 2010 from Denmark. The has during the year 2010 arranged 6 member meetings including two technical site visits. The first technical site visit covered the 5.3 km long Leipzig City
More informationThe Follo Line Project
The Follo Line Project Longest. UrbAN. Complex. Faster. 2015/1 Norwegian National Rail Administration the follo line project 1 2 the follo line project The project The Follo Line Project is currently the
More informationJan Schönbeck, Head of Strategic Contracts and Procurement. Seminar in Berlin 13 June 2012
Jan Schönbeck, Head of Strategic Contracts and Procurement Seminar in Berlin 13 June 2012 The task of the Swedish Transport Administration is responsible for the long-term planning of the transport system
More informationTesting of installations in road tunnels.
Testing of installations in road tunnels. Agenda The Norra Länken-project Presentation of the magnitude of the tests FAT-site with different systems and objects Testing workflow of the Norra Länken-project
More informationC9 - BIM implementation on Stockholm Bypass Project Using PowerCivil. Trafikplats Akalla och Häggvik, ÅF-URS.
C9 - BIM implementation on Stockholm Bypass Project Using PowerCivil. Trafikplats Akalla och Häggvik, ÅF-URS. Track: Civil Presenter: Mateusz Nettmann AGENDA 1. Introduction: A. URS Company B. People involved
More informationProgram: 13.00 13.40 Presentation of the Project, Norra länken (Mr Björn Terstad)
Welcome! Program: 13.00 13.40 Presentation of the Project, Norra länken (Mr Björn Terstad) 13.40 14.25 Tunnelvisit (Mr Björn Terstad, Mr Michael Lundborg, Mr Kenneth Delehag) 1 2010-06-22 Norra länken
More informationCALL IN PROGRAMS, CATEGORIES, AND TERMS *
CALL IN PROGRAMS, CATEGORIES, AND TERMS * AUDIT DEPARTMENT 1. Internal Audit Services 2014 2018 AVIATION DEPARTMENT 2014 2018 1. Aeronautical, Environmental & Technical Services 2. Airport Capacity Planning
More informationNewsletter: Construction Information, No. 1 28 June 2010
1 ( 6 ) Newsletter: Construction Information, No. 1 28 June 2010 Premiere for the newsletter about construction and disruption In connection with the start of the construction of the New Karolinska Solna
More informationNETLIPSE NETWORK MEETING 27-28.5.2013 Seppo Mäkinen Finnish Transport Agency 27.5.2013
NETLIPSE NETWORK MEETING 27-28.5.2013 Seppo Mäkinen Finnish Transport Agency 27.5.2013 Mainroad 4 Järvenpää Lahti PPP Project 1997 2012 FINLAND 27.5.2013 27.5.2013 Seppo Mäkinen Mainroad 4 Järvenpää -
More information(25) CONCEPT STUDY OSLO HUB A MEGA PROJECT 07.06.2016. Nina Tveiten Norwegian National Rail Administration
(25) CONCEPT STUDY OSLO HUB A MEGA PROJECT 07.06.2016 Nina Tveiten Norwegian National Rail Administration The study has been conducted on behalf of: The Ministry of Transport and Communications The Municipality
More informationE6 Trondheim-Stjørdal, the Trondheim section.
Tendering processes E6 Trondheim-Stjørdal, the Trondheim section. ENGLISH october 2008 www.vegvesen.no/e6ost Contents 1 INTRODUCTION 1.1 Prequalification 1.2 National transportation plan 1.3 Resolutions
More informationThe Gotthard Base Tunnel
The Gotthard Base Tunnel The tunnel On 11 December 2016, the Gotthard Base Tunnel will come into scheduled operation. At 57 kilometres in length, it is the longest rail tunnel in the world. It has virtually
More informationTHE PROVISIONAL CENTRAL PRODUCT CLASSIFICATION
THE PROVISIONAL CENTRAL PRODUCT CLASSIFICATION GROUP 867 ARCHITECTURAL, ENGINEERING AND OTHER TECHNICAL SERVICES Excerpt from CPCprov-en-Publication.doc - United Nation Statistic Division Group Class Subclass
More informationHow will the construction of the City Line affect you? English
English How will the construction of the City Line affect you? How the City Line will affect people living, working or using public transport in Stockholm. The City Line will be noticed! The City Line
More informationAlphington sewer replacement
Alphington sewer replacement Frequently asked questions We understand you might have some questions for us so here are a few to provide you with more information. You are also welcome to call us on 1800
More informationPreparing for the Fornebu Metro Line. Ingeborg Krigsvoll, Sporveien Oslo AS June 7, 2016
Preparing for the Fornebu Metro Line Ingeborg Krigsvoll, Sporveien Oslo AS June 7, 2016 Sporveien Norway s largest supplier of public transportation Unibuss AS Buss Revenue: 1 468 million Employees. 1
More informationMobility Management during Road Construction in Sweden The case of the Stockholm Bypass E4
Mobility Management during Road Construction in Sweden The case of the Stockholm Bypass E4 For a growing region Background National Guidelines Feasibility study Measures 2 2013-06-04 3 2013-06-04 Why the
More informationTraffic Management During Construction
Traffic Management During Construction The construction of Dublin Port Tunnel couldn t begin until a traffic management plan had been developed and agreed to facilitate construction of the Tunnel and to
More informationChapter 22. Lump Sum Project Guidelines
Chapter 22 Lump Sum Project Guidelines 22.1 General...22-1 22.2 Project Selection...22-3 22.3 Plans Preparation...22-5 22.4 Preliminary Estimate...22-7 22.5 Specifications...22-9 22.6 Contracts Administration...22-11
More informationSustainable transport in Stockholm. Gustaf Landahl City of Stockholm
Sustainable transport in Stockholm Gustaf Landahl City of Stockholm The Capital of Scandinavia Outline Is Stockholms transport sustainable? Stockholm grows fast Carrots and sticks Conclusions Urban Mobility
More informationTransport planning in the Stockholm Region
Stockholm County Council Office of Regional Planning and Urban Transportation Hans Hede Transport planning in the Stockholm Region METREX/Moscow International workshop June 2006 A region with great potential
More informationFIBER-OPTIC CABLE PLAN CHECK
Engineering Division 201 North Broadway, Escondido, CA 92025 (760) 839-4651, FAX (760) 839-4597 FIBER-OPTIC CABLE PLAN CHECK To: Date: Project: Project No. Address: Check No. Attn: Via: The attached plans
More informationCathkin Relief Road Planning Statement
Cathkin Relief Road Planning Statement The Proposal This statement sets out the background to the Cathkin Relief Road project currently being progressed by South Lanarkshire Council. The project will provide
More informationAPPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE
APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE JURISDICTION OF ALBERTA TRANSPORTATION 1.0 Application Procedures 2.0
More informationI-25/ARAPAHOE INTERCHANGE RECONSTRUCTION PROJECT
MANDATORY PRE-BID SIGN IN CDOT Carrie DeJiacomo, Program Engineer John Hall, Resident Engineer Telecia McCline, Project Manager Tammy Maurer, Assistant Project Manager David Evans/Hartwig Design Consultant
More informationAmendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation by Tunnelling
Engineering and Construction Services Division Standard Specifications for Sewers and Watermains TS 415 April 2013 Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation
More informationBruce Highway (Cooroy to Curra) Section A (Cooroy southern interchange to Sankeys Road)
Bruce Highway (Cooroy to Curra) Section A (Cooroy southern interchange to Sankeys Road) Industry Briefing - 13 February 2013 Bruce Highway Upgrade (Cooroy to Curra) The Bruce Highway Upgrade (Cooroy to
More informationIH-635 MANAGED LANES PROJECT, SEG. 3.2
IH-635 MANAGED LANES PROJECT, SEG. 3.2 Location: Dallas, Texas Owner: Texas Department of Transportation Client: Ferrovial Agroman Construction Cost: $1 Billion Construction Completion Date: December,
More informationElevated Roads for Sri Lanka
Elevated Roads for Sri Lanka M.T.R. Jayasinghe (Senior Professor, Structural Engineering, University of Moratuwa) Senior Professor M.T.R. Jayasinghe is a Professor of Structural Engineering, University
More informationCoastal Highway Route E39 Project
Coastal Highway Route E39 Project Teknologidagene 22th September 2015 Trondheim Kjartan J Hove/ Jørn Arve Hasselø/ Harald I. Johnsen Norwegian Public Roads Administration Coastal Highway Route E39 E39
More informationCivil. 2. City of Seattle Supplement to the Specification for Road, Bridge and Municipal Construction, most current addition.
Design Guide Basis of Design This section applies to the design and installation of earthwork and backfill. Design Criteria No stockpiling of excavation materials is allowed unless the Geotechnical Engineer
More informationSöderströmtunnel: immersion in downtown Stockholm, Sweden
Söderströmtunnel: immersion in downtown Stockholm, Sweden J. Glückert Dipl.-Ing, Züblin Ground Engineering, Stuttgart, Germany N.H.J. Vink MSe, M. Reijm BSc, P.T. van Westendorp BSc Strukton Immersion
More informationBUSINESS DEVELOPMENT INITIATIVE SMALL BUSINESS PROGRAM GUIDANCE FOR RESERVING CONTRACTS
Construction/Maintenance Contracts and Design/Build Low Bid Contracts 1. Districts are responsible for reviewing their work program and identifying contracts that are good candidates for the Business Development
More informationMELBOURNE METRO RAIL NEWSLETTER
Commercial Rd MELBOURNE METRO RAIL NEWSLETTER SHAPING MELBOURNE S RAIL FUTURE Welcome to the first edition of Melbourne Metro Rail News. This newsletter will keep you up-to-date on progress of the Melbourne
More informationPROFESSIONAL SERVICE FIRM QUESTIONNAIRE
PROFESSIONAL SERVICE FIRM QUESTIONNAIRE PERFORMANCE OF EXPERT PROFESSIONAL ARCHITECTURAL, ENGINEERING AND RELATED SERVICES FOR THE PORT AUTHORITY OF NEW YORK AND NEW JERSEY Thank you for your interest
More informationCITY OF VINCENT CONSTRUCTION MANAGEMENT PLAN GUIDELINES
CITY OF VINCENT CONSTRUCTION MANAGEMENT PLAN GUIDELINES INTRODUCTION What is a Construction Management Plan? The City of Vincent requires careful management of construction involving excavation and retention
More informationLarge infrastructure projects in Sweden. Lotta Brändström Executive Director, Major Projects
Large infrastructure projects in Sweden Lotta Brändström Executive Director, Major Projects Why was the Swedish Transport Administration created? An overall approach to all modes of transport A clearer
More informationAPPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND TELECOMMUNICATION CABLES IN THE VICINITY OF TRANSPORTATION FACILITIES
APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND TELECOMMUNICATION CABLES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE JURISDICTION OF ALBERTA TRANSPORTATION 1.0 Application Procedures 2.0
More informationTriton Knoll Offshore Wind Farm Limited Electrical System. Outline Traffic Management Plan
Triton Knoll Offshore Wind Farm Limited Electrical System Outline Traffic Management Plan October 2014 RWE Innogy UK Triton Knoll TMP Copyright 2014 RWE Innogy UK Ltd All pre-existing rights reserved.
More informationSector Design Concepts
Section C Sector Design Concepts C7 Sector 7 Great North Road Underpass 6 6 6 C7. Existing situation Sector 7 refers to the cut and cover section of the project linking the northern end of the deep tunnels
More informationBUSINESS DEVELOPMENT INITIATIVE SMALL BUSINESS PROGRAM GUIDANCE FOR RESERVING CONTRACTS
Construction/Maintenance Contracts and Design/Build Low Bid Contracts 1. Districts are responsible for reviewing their work program and identifying contracts that are good candidates for the Business Development
More informationProject Rijksweg 15, Maasvlakte-Vaanplein
Project Rijksweg 15, Maasvlakte-Vaanplein challenges of a DBFM-contract Adrie Franken, Contractmanager A15 MaVa Rijkswaterstaat Topics Project scope Procurement strategy characteristics of the DBFM-contract
More informationAppendix A Alternative Contracting General Engineering Consultant RFP. Appendix A
Appendix A 1 1.0 Requirements and Minimum Qualifications This section outlines requirements and minimum qualifications for the GEC. It is anticipated that the GEC will be used to support and supplement
More informationWho Thinks of Budapest as a Cycling City? Velo City 2013, Vienna - Who Thinks of Budapest as a Cycling City?
Who Thinks of Budapest as a Cycling City? Who Thinks of Budapest as a Cycling City? László Sándor KERÉNYI BKK Centre for Budapest Transport Department for Transport Strategy 2 Budapest Splendid architecture
More informationPrecautions (Annexes 1 + 2) < Deployment of the resources of the Heritage Protection Service > < Specialists >
FEDERAL OFFICE FOR CIVIL PROTECTION June 1999 PROTECTION FOR HISTORIC ITEMS AT TIMES OF DISASTER Hazard Analysis Precautions (Annexes 1 + 2) Emergency action (Annex 3) Restoration / Reconstruction Identify
More informationPLANNING CAREFUL NORTH VANCOUVER PIPE BURST REQUIRES
WATER & SEWER REHAB TECHNOLOGIES NORTH VANCOUVER PIPE BURST REQUIRES CAREFUL PLANNING Close proximity to storage silos, poor ground conditions and clogged storm sewer pipe puts trenchless contractor to
More informationGranger Bay Boulevard and Green Point Roundabout
Granger Bay Boulevard and Green Point Roundabout INTRODUCTION Aurecon was appointed for the design and construction supervision of the Granger Bay Boulevard and Green Point roundabout that provides access
More informationFigure 5.6a Construction worksites and corridor access Note: Indicative only, subject to detailed design.
A 0 NORTH 200 metres George Lane worksite North Strathfield Station worksite Strath eld Triangle A B Existing rail corridor Proposed underpass approach New/extended bridge Worksites Existing track Proposed
More informationLEGISLATIVE COUNCIL PANEL ON PLANNING, LANDS AND WORKS
For discussion on 2 April 2001 LC Paper No. CB(1)907/00-01(03) LEGISLATIVE COUNCIL PANEL ON PLANNING, LANDS AND WORKS PWP Item No. 277CL Tseung Kwan O development, phase II, Remaining engineering works
More informationTunnelling & Underground. Specialists
Tunnelling & Underground Specialists Mined Tunnels Excavation at Ayer Rajah Avenue, Singapore Introduction Amberg & TTI Engineering Pte Ltd (AETTI) was established in Singapore in 2002 by Amberg Engineering
More informationTransportation Management Plan Template
DATE: TO: FROM: SUBJECT: Date Name Position Transportation Service Center Name Position Transportation Service Center Transportation Management Plan Job Number(s) Control Section(s) Route Details County
More informationWork Type Definition and Submittal Requirements
Work Type: Highway Materials Testing Geotechnical Laboratory Testing, Geotechnical Laboratory Testing, Standard Penetration (SPT) & Rock Coring, Cone Penetration Test, Solid Stem Auger Drilling, and Materials
More informationReport to INFRASTRUCTURE SERVICES Committee for noting
15-377 Subject: Prepared by: Capital Works Programme 2015/16 Tairāwhiti Roads Alexios Kavallaris (Capital Manager - Tairāwhiti Roads) Meeting Date: 22 October 2015 Report to INFRASTRUCTURE SERVICES Committee
More informationSÖDERLEDSTUNNEL STOCKHOLM FIRE PROTECTION OF THE WESTERN TUBE A CASE STUDY
SÖDERLEDSTUNNEL STOCKHOLM FIRE PROTECTION OF THE WESTERN TUBE A CASE STUDY AGENDA INTRODUCTION / PROJECT OVERVIEW DESIGN / FIRE PROTECTION PROJECT DETAILS ABOUT TBT INTRODUCTION UNDERPASSING ISLAND SÖDERMALM
More informationEngineering Policy 146. Severe Weather Management Plans
Engineering Policy 146 Severe Weather Management Plans January 2014 Contents Engineering Policy... 1 1 Policy statement... 1 2 Applicability... 1 3 Context... 1 4 Objectives and benefits... 1 5 Consultation...
More informationITEM 8(a) MANAGEMENT COMMITTTE 2 JUNE 2015
ITEM 8(a) MANAGEMENT COMMITTTE 2 JUNE 2015 APPENDIX Report from Harbour Management Board -1April 2015 Weymouth Harbour Walls Remediation Work Harbour Management Board 1 April 2015 Weymouth Harbour Walls
More informationLETBANE PÅ RING 3. Information about the public procurement process
Information about the public procurement process Document ID: L3-X-LB-PRE-0001 Version: 2.0 Issue date: 2015-11-10 Issued by: Ring 3 Letbane I/S Approved by: AGF Anne-Grethe Foss Checked by: PAMA Patrik
More informationUnit Price Averages Reports
Unit Price Averages Reports 12/7/2015 UNIT PRICE AVERAGES REPORT Disclaimer The information provided in the following Unit Price Averages Report is only for the use of Alberta Infrastructure & Transportation
More informationElectricity to your property
Vattenfall Distribution AB Electricity to your property How an electrical connection is made and what you need to consider How electricity reaches your property 8 simple steps! 1. Please leave plenty of
More informationPROJECT COST ESTIMATES & FEASIBILITIES
PROJECT COST ESTIMATES & FEASIBILITIES Project Cost and budget management Project success elements Scope meet the scope defined for the project Budget It is within established budget Programme It is designed
More informationBusiness Unit. Tunnelling & Civil Engineering. Infrastructure solutions from a single source.
Business Unit Tunnelling & Civil Engineering Infrastructure solutions from a single source. 6 14 20 4 Innovative solutions on a sound basis 6 Tunnelling Setting new standards Transportation tunnels Power
More informationDescription of Selected Services under the UN CPC system in which the EC made Market Access Commitments in the EPA
Description of Selected Services under the UN CPC system in which the EC made Market Access Commitments in the EPA 7471 Travel agency and tour operator services Services rendered for passenger travel by
More informationDESCRIPTION OF WORK:
DEPARTMENT OF PUBLIC WORKS COUNTY OF HENRICO P.O. BOX 27032 RICHMOND, VIRGINIA 23273 PERMIT NO. One (1) copy of application and four (4) copies of plans are hereby made to the Director of Public Works
More informationWhy build the Silvertown Tunnel?
Why build the Silvertown Tunnel? Over the last 30 years east London has changed with the redevelopment of former industrial areas into major commercial and residential districts. The development of Canary
More informationSECTION IX SLIP LINING PIPELINES
AN SECTION IX SLIP LINING PIPELINES February, 2008 TABLE OF CONTENTS SECTION IX - SLIP LINING PIPELINES 9.01.00 GENERAL...2 9.01.01 SCOPE... 2 9.02.00 MATERIAL...2 9.03.00 CONSTRUCTION...2 9.03.01 REQUIREMENTS...
More informationIncident Handling in Complex Motorway Tunnels, Stockholm
Incident Handling in Complex Motorway Tunnels, Stockholm The Presentation Workshop in Hannover, October 23, 2003 Background Contribution from the Regional Project VIKING Incident & Emergency in context
More informationCompany Profile. www.totospa.it
www.totospa.it Table of contents 1 Toto Group Structure 2 Toto S.p.a. Costruzioni Generali: Overview 3 Business Interests 4 5 6 7 8 Toto s Strength: Know How Toto s Technological Assets The Construction
More informationSECTION 31 20 00 EARTH MOVING
SECTION 31 20 00 PART 1 - GENERAL 1.01 DESCRIPTION A. This Section describes the requirements for excavating, filling, and grading for earthwork at Parking Structure, new exit stair and as required to
More informationHIGHWAY DESIGN REPORT. Appendix 4. Proposed Design Principles for City Passings
HIGHWAY DESIGN REPORT Appendix 4 Proposed Design Principles for City Passings June 2000 Contents Page 1 Introduction 2 1.1 Purpose 2 1.2 Definition of city passing 2 1.3 Safety Problems 2 1.4 Planning
More informationSafe & Sound Bridge Terminology
Safe & Sound Bridge Terminology Abutment A retaining wall supporting the ends of a bridge, and, in general, retaining or supporting the approach embankment. Approach The part of the bridge that carries
More informationCopenhagen, Denmark - Trends in Public Perception
CYKELN TAR ÖVER GATAN NØRREBROGADE IN COPENHAGEN FROM TRAFFICSTREET TO CYCLE/BUSSTREET AGENDA Nørrebrogade before Green Wave V.1 The political vision Planning process Nørrebrogade today? FACTS Length:
More informationBIM in Infrastructure - Consultant s perspective. BIM Event - BPCC. November 6 th, 2014. Mateusz Nettmann
BIM in Infrastructure - Consultant s perspective BIM Event - BPCC November 6 th, 2014 Mateusz Nettmann 1 Agenda Project Introduction Impact on Design Process Challenges Benefits COMPANY CONFIDENTIAL: Use
More informationGeotechnical Building Works (GBW) Submission Requirements
Building Control (Amendment) Act 2012 and Regulations 2012: Geotechnical Building Works (GBW) Submission Requirements Building Engineering Group Building and Construction Authority May 2015 Content : 1.
More informationRoadway Cost Per Centerline Mile Revised June 2014
Rural Arterial From LRE MOT * Mobilization * Subtotal Total PE Design (15%) CEI (15%) Total Project ** New (2-Lane Roadway) with 5' Paved Shoulders $3,351,896 $335,190 $368,709 $4,055,794 $1,013,949 $5,069,743
More informationDesign and Build of Passenger Terminal Building North Extension At Macau International Airport (RFQ-198) Section 6 Bill of Quantities
At Macau International Airport (RFQ-198) Section 6 Bill of Quantities Bill Nr. 1 Preliminaries Bill Nr. 1 PRELIMINARIES NOTES : (1) The work shall be done during day time and night time according to CAM/ADA
More informationAbandoned Underground Utility Line Congestion A CONTRACTOR S PERSPECTIVE
Abandoned Underground Utility Line Congestion A CONTRACTOR S PERSPECTIVE PRESENTER: ROBERT BOB MEADS, PRESIDENT R&M Consultants & Project Management, LLC Virginia Beach, VA Purpose of Presentation To share
More informationSeparating lanes our way Steel guard rail
a Separating lanes our way Steel guard rail Factfile Birstaverken Birstaverken AB was founded in 1961 and is a manufacturing company with its own plant for hot-dip galvanising. We develop, design, manufacture
More informationCOWI s Role in the Copenhagen Metro Project
COWI s Role in the Copenhagen Metro Project On the occasion of the award by the Copenhagen Cultural Foundation for COWI A/S part in the implementation of Phase 1 of the Copenhagen Metro 2 COWI s Role in
More informationNew Karolinska Solna University Hospital. Information Meeting PPP procurement Stockholm Arlanda 3 October 2008
New Karolinska Solna University Hospital Information Meeting PPP procurement Stockholm Arlanda 3 October 2008 Information Meeting PPP procurement Speakers 1. Catharina Elmsäter-Svärd, Stockholm County
More informationBefore applying for a Road Opening Licence, please read and understand the following information.
Sept 2012 Before applying for a Road Opening Licence, please read and understand the following information. What is a Road Opening Licence? A Road Opening Licence (ROL) is a licence that allows the holder
More informationThree minutes about the City Line the commuter train tunnel that will make life easier and greener
Three minutes about the City Line the commuter train tunnel that will make life easier and greener English 1. GOOD FOR YOU Saving you time Delays and overcrowding on rail services are caused by the fact
More informationMilan M5 metro extension the construction of Lotto station
Milan M5 metro extension the construction of Lotto station Giuseppe LUNARDI, Rocksoil S.p.A., Italy giuseppe.lunardi@rocksoil.com Luca MANCINELLI, Rocksoil S.p.A., Italy, luca.mancinelli@rocksoil.com Massimiliano
More informationM8 M73 M74 Motorway Improvements Project
M8 M73 M74 Motorway Improvements Project October 2013 Introduction This major transport infrastructure project will complete and upgrade the M8 and key sections of the M73 and M74 to finalise the motorway
More informationMassDOT s Work Zone Transportation Management Procedures. By: Neil Boudreau, MassDOT and Michael Sutton, P.E., VHB
MassDOT s Work Zone Transportation Management Procedures By: Neil Boudreau, MassDOT and Michael Sutton, P.E., VHB What is the Work Zone Safety and Mobility Rule? 23 CFR 630 Subpart J, effective October
More informationUndergrounding high voltage electricity transmission. The technical issues
Undergrounding high voltage electricity transmission The technical issues This is an interactive PDF document with clickable links from the contents to all sections and back and also to URL and email links.
More informationAll Electronic Tolling System (AETS) Implementation Project
All Electronic Tolling System (AETS) Implementation Project I-90 (Western Turnpike / Boston Extension) & Harbor Crossings Stephen M. Collins MassDOT Director of Statewide Tolling Presented by: Donald Bell
More informationGEORGE J. CAMBOURAKIS, P.E., C. ENG. PRESIDENT & CHIEF STRUCTURAL ENGINEER
GEORGE J. CAMBOURAKIS, P.E., C. ENG. PRESIDENT & CHIEF STRUCTURAL ENGINEER Professional Experience: Pride and Passion in the Art of Structural Engineering since 1979. Professional Registration: Professional
More informationCONSTRUCTION SEQUENCE & PROGRAMME
CONSTRUCTION SEQUENCE & PROGRAMME 2 CONTENTS 1.0 Introduction 7 2.0 Key activities 8 2.1 Airport related activities 2.2 Construction of new roads and accesses 2.3 Earthworks zone a 2.4 Earthworks zone
More informationGovernment of Himachal Pradesh Transport Department Shimla
Government of Himachal Pradesh Transport Department Shimla Pre-Qualification of Consultants / Architects for the Construction of I&C Building and Infrastructure for Baddi at Himachal Pradesh On behalf
More informationThe Construction of a New Roskilde Fjord Link. Information Meeting October 30th 2014 13.00-16.00 Park Inn Hotel, Copenhagen S
The Construction of a New Roskilde Fjord Link Information Meeting October 30th 2014 13.00-16.00 Park Inn Hotel, Copenhagen S Agenda Welcome Jens Jørgen Holmboe, Construction & Maintenance Director Background
More informationEntreprenørdagen 14. mars 2011
Entreprenørdagen 14. mars 2011 Program 1130 1200 Velkommen og litt å bite i Dagsorden 1200 Info om Fellesprosjektet v/ PL Taale Stensbye 1230 Entreprisene v/ Byggelederne 1330 Kontrakter/anleggsbetingelser
More informationParking Infrastructure Development. in Santariskes Medical Campus (SMC), VILNIUS, LITHUANIA
Parking Infrastructure Development in Santariskes Medical Campus (SMC), VILNIUS, LITHUANIA Santariskes Medical Campus (SMC) main medical campus in lithuania 64 ha 6 public / 2 private medical institutions
More informationCity of Colleyville Community Development Department. Site/Landscape Plan Application Packet
City of Colleyville Community Development Department Site/Landscape Plan Application Packet Development Application Fees City of Colleyville 100 Main Street Colleyville TX 76034 817.503.1050 Zoning Zoning
More informationDulles Corridor Metrorail Project
Dulles Corridor Metrorail Project MONTHLY COST AND SCHEDULE UPDATE FOR PHASE 2 AS OF JULY 31, 2015 SEPTEMBER 2015 Phase 2 Cost Summary July Expenditures $ 19.2 Million Total Expenditures $ 508.7 Million
More informationPREFERRED REQUIREMENTS: WATER SUPPLIES AND ACCESS FOR SUBDIVISIONS IN RURAL ZONES
PREFERRED REQUIREMENTS: WATER SUPPLIES AND ACCESS FOR SUBDIVISIONS IN RURAL ZONES NOVEMBER 2006 1 TABLE OF CONTENTS Glossary of Terms 3 Introduction 4 Where Do These Guidelines Apply? 6 Statutory Requirements
More informationIFE Level 4 Certificate in Fire Science and Fire Safety (HL)
IFE Level 4 Certificate in Fire Science and Fire Safety (HL) Unit 2: Fire Safety Unit Reference Number: D/505/5932 Introduction This unit focuses on the prevention and detection of fire in premises and
More informationHelsinki on a growth track
BUI LDI NG HEL SIN KI Helsinki on a growth track With its rising population and the construction of large new residential and commercial areas, Finland s capital Helsinki will grow faster than ever in
More informationPurpose of the Local Liaison Committee
Agenda 1. Welcome, introductions and purpose of the Local Liaison Committee 2. Introduction to the scheme 3. Progress update 4. Elect a chair for future meetings 5. Agree agenda and terms of reference
More informationMaliakos Kleidi Project Construction & Challenges faced. Presentation to ELAC 2014
Maliakos Kleidi Project Construction & Challenges faced Presentation to ELAC 2014 Dimosthenis Papakrivopoulos, Civil Engineer, Deputy Project Director of MKCJV 09.05.2014 Index Introduction The Project
More informationLIGHT RAIL ON RING 3 NOVEMBER 19 TH 2014. Supplier Workshop. Islevbro station (Rødov
LIGHT RAIL ON RING 3 NOVEMBER 19 TH 2014 Supplier Workshop Islevbro station (Rødov 1 Agenda In the Auditorium: 1. Welcome and programme; purpose of the day 2. Ring 3 in Brief 3. Vision of Light Rail on
More information