1 Subject: Prepared by: Capital Works Programme 2015/16 Tairāwhiti Roads Alexios Kavallaris (Capital Manager - Tairāwhiti Roads) Meeting Date: 22 October 2015 Report to INFRASTRUCTURE SERVICES Committee for noting SUMMARY The purpose of this report is to inform the Committee of three resilience projects (1-3) and three heavy productive motor vehicle bridge strengthening projects (4-6): 1) Anaura Bay Road (Nuhiti) rock revetment 2) Southern Seawall Repair, Beach Road, Tokomaru Bay 3) Mata Road Realignment R.P ) Horoeka and Te Pahi bridges deck strengthening 5) Gaddum s bridge strengthening 6) Mata (Huiarua) bridge deck replacement A Powerpoint presentation of the projects will be provided at the meeting. RECOMMENDATIONS That the Committee 1. receives the report. Alexios Kavallaris Capital Manager Tairāwhiti Roads Barry Vryenhoek Operations Group Manager Keywords: Tairāwhiti Roads, land transport, capital projects A Page 1 of 6

2 1. BACKGROUND Six capital projects have been approved for funding in the financial year. are: These 1.1 Anaura Bay Road (Nuhiti) Rock Revetment The works are to partially construct two rock revetments with buttress fill behind whilst beginning earthworks for a future road realignment of approximately 220m length of the Anaura Bay Road. This was a high priority as it was a commitment to the residents and landowners affected by consistent road closures. The seaward slope is being undermined by erosion from the action of the sea, which has resulted in the regression of the slope and a reduced road formation width. The damage is a result of a combination of factors including tides, current and wave action from the ocean as well as the mobilisation of the slip upslope of the road. The future road realignment is intended to cut the road further inland into more stable material and take weight off the top of the slope. The revetments to be constructed on the seaward side of the buttress fill are intended to reinforce the toe of the slope. This is expected to protect the toe from further erosion and help stabilise the existing slips. The future placement of topsoil, grass seeding and planting of the slopes below the new road will provide additional stability. Works include clearing the site of vegetation, stripping of topsoil, excavation of loose slip material at the toe and on the face of the seaward slope, some excavation for the construction of the new road with the excavated material being placed as buttress fill on the beach against the seaward slope and the partial construction of the rock revetments. The works are for Stage 1 of the four stage construction sequence. This stage is for the construction of approximately one quarter of the rock revetments and a portion of the earthworks relating to cutting in the road realignment along with buttress fill behind the rock revetments. Fill for the buttress is to be gained from the road cutting. Estimated Total Cost for Stage 1: $250,000 Preliminary design drawings completed Community consultation in progress Resource consent in progress Archaeological report in progress Mangatuna quarry consenting yet to begin Detailed design and contract documentation currently in progress Will proceed to construction open tendering by February 2015 Anticipated construction period for Stage 1 is 3-4 months A Page 2 of 6

3 Current status Community consultation in progress Resource consent in progress 1.2 Mata Road Realignment R.P This section of road has been slumping/subsiding for many years. Additional to this there is a large volume of heavy traffic and poor road width and visibility. There have been many requests from the public, local councillors, landowners and road users to improve this section of road. Currently the road can be restricted to one way only. Road users are unable to see oncoming traffic and the use of radio to communicate is the only way to negotiate this section of road safely. Not everyone has a radio. Option 1 - Carry out road alignment which would benefit the visibility of the road. Option 2 - Stay with the existing road alignment and widen the roadway, carry out sight benching and remove vegetation to improve sight visibility. With both options there will still be ongoing issues with the stability of this site. A neighbouring landowner has agreed to Council gaining access and utilising his land to enable improvement works. Estimated Total Cost: $250,000 Investigation phase in order to produce an options report and agree on the engineer s preferred option. Apply for resource consent with Council and progress consultation with stakeholder for the option that needs land acquisition. Preliminary and detailed design. Contract documentation and tender process. Progressing with investigation to produce options report due by 21 November Southern Seawall Repair, Beach Road, Tokomaru Bay The concrete seawall alongside Beach Road, Tokomaru Bay, has been damaged. There is a large hole in the wall that is causing backfill to be lost from behind the wall. This has been covered by a steel plate as a temporary measure but a more permanent solution is required. The scope of the permanent work is to remove the temporary plate and repair the concrete wall. This includes: Dewatering and protecting the repair area from the ocean. Removing the temporary plate and fixings. Excavating the material from in front of the wall down to bedrock. Removing all loose material from the damaged area and preparing the exposed concrete and reinforcement. Drilling and epoxying MateenBar reinforcing into the walls and base of the damaged area. A Page 3 of 6

4 Inserting and grouting seepage pipes. Placing concrete repair material. Placing rock rip-rap against the toe of the new repair. The scope of the permanent work is to repair this erosion. This includes: Dewatering and protecting the repair area from the ocean. Excavating the material from in front of the wall down to bedrock. Removing all loose material from the area and preparing the exposed concrete and reinforcement. Cutting the bedrock foundation to the correct profile. Drilling and epoxying MateenBar reinforcing into the existing concrete. Placing the concrete repair material. Backfilling behind the existing seawall. Placing rock rip-rap against the toe of the new repair. Estimated Total Cost: $300,000 Project will be staged as $150,000 is only available this financial year. Investigation of both buttress and seawall repair done. Detailed design and contract documentation completed by December Construction period from February to April Resources consent to be finalised once final design completed. 1.4 Horoeka and Te Pahi Bridges Deck Strengthening To carry out an assessment of two bridges on Waimata Road: Horoeka Bridge at RP 9.85 and Te Pahi Bridge at RP Both bridges previously assessed in 2006 giving >100% Class 1 (>44t gross weight). Reassessment of these bridges was considered necessary as new evaluation methods have since been introduced and also to determine their capacities to accommodate High Productivity Motor Vehicles loading. Estimated logging activities forecasting in tonnes is shown below: Accumulated volume Waimata Hokoroa 2016/ / / / / / /24 Tonnes 85, , , , , , ,000 1,327,496 Estimated Total Cost: $120,000 for both bridges A Page 4 of 6

5 Investigation assessment done. Benefit cost ratio, detailed design and construction drawings done. Construction estimate and contract documentation due by 16 October Open market tender by mid-november Construction estimate and contract documentation. 1.5 Gaddum s Bridge Strengthening Gaddum s Bridge is at 6678 Matawai Road and carries a single lane carriageway over the Motu River. The structure is a single span castellated steel bridge with timber deck founded on concrete abutments. The bridge is to be upgraded to allow tanker access. This involves strengthening the main girders primarily but also increasing support capacity to the central beam of the bridge. The timber deck will also be replaced with a new timber deck. Timber was deemed more appropriate than concrete as it will be lightweight and therefore will not put too much additional load onto the existing abutments. Scope of works includes: Access Traffic Management Demolition Steelwork Timberwork Barrier installation Corrosion protection Estimated Total Cost: $200,000 Investigation assessment done. Preliminary and detailed design done. Construction estimate and contract documentation done. Open market tender in progress, closing date for submission 23 October 2015 Open market tendering. 1.6 Mata (Huiarua) Bridge Deck Replacement The site of work is at the Mata (Huiarua) Bridge on Mata Road (Upper). This site is located 116km north of Gisborne, 35km west of Tokomaru Bay. Once the bridge is complete, Mata Road will be fully enabled for HPMV capability. A Page 5 of 6

6 This project involves replacing the existing deck on Mata (Huiarua) Bridge on all four spans in order to increase the carriageway width and improve the live load capacity to full HPMV. The work involves: Remove existing deck and guardrails. Shear stud installation. Precast concrete deck with in-situ infills. Joint installation. New galvanised steel protection barriers. Minor earthworks. Seismic steelwork retrofit. Paint beam top flange and seismic steelwork. Traffic management. Liaison with service authorities and local landowners. Estimated Total Cost: $500,000 Project was tendered in December Contract awarded on February Contract postponed allowing for Ernslaw One to reprogramme their operations due to potential bridge closure. Contract recommences on 26 October 2015 and estimated completion either before Xmas break or one week after Xmas holidays. Suspension period until 26 October A Page 6 of 6

BRIDGES ARE relatively expensive but often are

BRIDGES ARE relatively expensive but often are Chapter 10 Bridges Chapter 10 Bridges Bridg Bridges -- usually the best, but most expensive drainage crossing structure. Protect bridges against scour. BRIDGES ARE relatively expensive but often are the

More information

A slope being cleared up prepared for the installation of the rock bolts. The provision of access to a working slope poses certain difficulties in

A slope being cleared up prepared for the installation of the rock bolts. The provision of access to a working slope poses certain difficulties in A slope being cleared up prepared for the installation of the rock bolts. The provision of access to a working slope poses certain difficulties in most cases. A preliminary treated slope with the surface

More information

2015 ODOT Bridge Design Conference May 12, 2014. DeJong Rd Bridge High- Seismic Zone Case Study: Bridge Rehab vs. Replacement.

2015 ODOT Bridge Design Conference May 12, 2014. DeJong Rd Bridge High- Seismic Zone Case Study: Bridge Rehab vs. Replacement. 2015 ODOT Bridge Design Conference May 12, 2014 DeJong Rd Bridge High- Seismic Zone Case Study: Bridge Rehab vs. Replacement Mary Ann Triska 2015 HDR, all rights reserved. Presentation Outline Project

More information

Emergency repair of Bridge B421

Emergency repair of Bridge B421 Emergency repair of Bridge B421 over the Olifants River after fl ood damage INTRODUCTION AND BACKGROUND Bridge B421 is located on the R555 at km 5.03 on Section 01E between Witbank (now known as emalahleni)

More information

Unit Price Averages Reports

Unit Price Averages Reports Unit Price Averages Reports 12/7/2015 UNIT PRICE AVERAGES REPORT Disclaimer The information provided in the following Unit Price Averages Report is only for the use of Alberta Infrastructure & Transportation

More information

by Marc Herring, Project Engineer

by Marc Herring, Project Engineer by Marc Herring, Project Engineer 2 Background Maintenance Improvements Strategic Importance Structural Concerns Design - Deck Strengthening Construction - Deck Strengthening Customer Focus Value for Money

More information

Bruce Highway (Cooroy to Curra) Section A (Cooroy southern interchange to Sankeys Road)

Bruce Highway (Cooroy to Curra) Section A (Cooroy southern interchange to Sankeys Road) Bruce Highway (Cooroy to Curra) Section A (Cooroy southern interchange to Sankeys Road) Industry Briefing - 13 February 2013 Bruce Highway Upgrade (Cooroy to Curra) The Bruce Highway Upgrade (Cooroy to

More information

Transport and Main Roads Specifications MRS03 Drainage, Retaining Structures and Protective Treatments

Transport and Main Roads Specifications MRS03 Drainage, Retaining Structures and Protective Treatments Specification (Measurement) Transport and Main Roads Specifications MRS03 Drainage, Retaining Structures and Protective Treatments October 2016 Copyright http://creativecommons.org/licenses/by/3.0/au/

More information

The unit costs are based on the trend line of the 3 low bids for the average quantity.

The unit costs are based on the trend line of the 3 low bids for the average quantity. Page 1 of 8 COST ESTIMATE GENERAL INSTRUCTIONS The unit costs are based on the trend line of the 3 low bids for the average quantity. Apply the Unit Costs to ordinary structures. Unit Costs should generally

More information

Safe & Sound Bridge Terminology

Safe & Sound Bridge Terminology Safe & Sound Bridge Terminology Abutment A retaining wall supporting the ends of a bridge, and, in general, retaining or supporting the approach embankment. Approach The part of the bridge that carries

More information

Bridge Manual - Part I - May CHAPTER 6 SHOP DRAWINGS, CONSTRUCTION PROCEDURES, AND OTHER SUBMISSIONS

Bridge Manual - Part I - May CHAPTER 6 SHOP DRAWINGS, CONSTRUCTION PROCEDURES, AND OTHER SUBMISSIONS Bridge Manual - Part I - May 005 6-1 CHAPTER 6 SHOP DRAWINGS, CONSTRUCTION PROCEDURES, AND OTHER SUBMISSIONS 6.1 APPROVAL PROCESS 6.1.1 General The official MassHighway procedure for submission of and

More information

2006-2008 MHD BRIDGE SECTION WEIGHTED AVERAGE UNIT PRICES GUIDELINES FOR THE USE OF THE WEIGHTED AVERAGE UNIT PRICE TABULATION SHEETS

2006-2008 MHD BRIDGE SECTION WEIGHTED AVERAGE UNIT PRICES GUIDELINES FOR THE USE OF THE WEIGHTED AVERAGE UNIT PRICE TABULATION SHEETS 2006-2008 MHD BRIDGE SECTION WEIGHTED AVERAGE UNIT PRICES GUIDELINES FOR THE USE OF THE WEIGHTED AVERAGE UNIT PRICE TABULATION SHEETS GENERAL 10/16/2008 The listed average unit prices are based on the

More information

Hard engineering reduces the energy of breaking waves by building big structures between the sea and the land, or by building breakwaters that force

Hard engineering reduces the energy of breaking waves by building big structures between the sea and the land, or by building breakwaters that force Hard engineering reduces the energy of breaking waves by building big structures between the sea and the land, or by building breakwaters that force the waves to break before they reach the beach. Sea

More information

SEDIMENT/STORMWATER MANAGEMENT BASIN CONSTRUCTION CHECKLIST

SEDIMENT/STORMWATER MANAGEMENT BASIN CONSTRUCTION CHECKLIST SEDIMENT/STORMWATER MANAGEMENT BASIN CONSTRUCTION CHECKLIST For permanent structures per Delaware SCS Pond Code 378 and Delaware Sediment and Stormwater Regulations KEY PROJECT INFORMATION Item meets standard

More information

CITY OF TRAIL MEMORANDUM

CITY OF TRAIL MEMORANDUM 0 C CITY OF TRAIL MEMORANDUM DATE: TO: FROM: SUBJECT: March 24, 2011 FILE NO. 5400-02 DAVID PEREHJJDOFF, CHIEF ADM1NTSTRATIVE OFFICER WARREN PROULX, ENGINEERING TECHMCIAN OLD TRAIL BRIDGE With the interest

More information

IH-635 MANAGED LANES PROJECT, SEG. 3.2

IH-635 MANAGED LANES PROJECT, SEG. 3.2 IH-635 MANAGED LANES PROJECT, SEG. 3.2 Location: Dallas, Texas Owner: Texas Department of Transportation Client: Ferrovial Agroman Construction Cost: $1 Billion Construction Completion Date: December,

More information

Seismic Innovations & Enhancements

Seismic Innovations & Enhancements West Approach West Span Yerba Buena Island Transition SAS Skyway Oakland Touchdown F A C T S H E E T Seismic Innovations & Enhancements The seismic retrofit of the entire Bay Bridge includes numerous cutting-edge

More information

5 ALTERNATIVE SOLUTIONS AND EVALUATION

5 ALTERNATIVE SOLUTIONS AND EVALUATION Page 23 5 ALTERNATIVE SOLUTIONS AND EVALUATION The process used for the assessment and evaluation of the alternatives follows the procedures of the Municipal Class EA, as described below: Identify a reasonable

More information

Structural Design of Dam Sluice Gate Walkway Slabs: Retrofit and Replacement Options

Structural Design of Dam Sluice Gate Walkway Slabs: Retrofit and Replacement Options Structural Design of Dam Sluice Gate Walkway Slabs: Retrofit and Replacement Options Introduction Local utility identified reinforced concrete maintenance walkways at each of their dam s seven sluice gates

More information

Exmouth Floating Jetties

Exmouth Floating Jetties Exmouth Floating Jetties June 2010 Various householders $55,000 per jetty, plus $7,000 for top mass footing This project involved the supply and installation of an initial five floating jetties to private

More information

On Line Widening of the N7 Naas Road Integrating Design and Construction Scheme Description and Background Tender Design Priorities Integrated Program

On Line Widening of the N7 Naas Road Integrating Design and Construction Scheme Description and Background Tender Design Priorities Integrated Program On Line Widening of the N7 Naas Road Integrating Design and Construction Presentation By Jim Thorpe BSc, Dipl Eng, CEng, MIEI, MICE Project Manager Roughan & O Donovan Faber Maunsell Alliance Contractor

More information

Informational Workshop Public Meeting Kanawha Falls Bridge Project

Informational Workshop Public Meeting Kanawha Falls Bridge Project Informational Workshop Public Meeting Kanawha Falls Project WV Department of Transportation Division of Highways in Cooperation with the Federal Highway Administration State Project S310-13-0.02 00 Federal

More information

SECTION 206 EXCAVATION FOR STRUCTURES

SECTION 206 EXCAVATION FOR STRUCTURES SECTION 206 EXCAVATION FOR STRUCTURES 206.1 Description. This work shall consist of the necessary excavation for the foundations of all structures, removal and disposal of all excavated material, backfilling

More information

EAST AYRSHIRE COUNCIL. CABINET 24 April 2013 2013-14 BRIDGE AND CULVERT STRENGTHENING PROGRAMME

EAST AYRSHIRE COUNCIL. CABINET 24 April 2013 2013-14 BRIDGE AND CULVERT STRENGTHENING PROGRAMME EAST AYRSHIRE COUNCIL CABINET 24 April 2013 2013-14 BRIDGE AND CULVERT STRENGTHENING PROGRAMME Report by the Depute Chief Executive/Executive Director of Neighbourhood Services PURPOSE OF REPORT 1 The

More information

BRIDGE RESTORATION AND LANDSLIDE CORRECTION USING STRUCTURAL PIER AND GRADE BEAM

BRIDGE RESTORATION AND LANDSLIDE CORRECTION USING STRUCTURAL PIER AND GRADE BEAM BRIDGE RESTORATION AND LANDSLIDE CORRECTION USING STRUCTURAL PIER AND GRADE BEAM Swaminathan Srinivasan, P.E., M.ASCE H.C. Nutting/Terracon David Tomley, P.E., M.ASCE KZF Design Delivering Success for

More information

GUIDELINES FOR GEOTECHNICAL INVESTIGATION OF BRIDGE STRUCTURES. Materials Engineering Report No. 2009-8M (Supersedes Report No.

GUIDELINES FOR GEOTECHNICAL INVESTIGATION OF BRIDGE STRUCTURES. Materials Engineering Report No. 2009-8M (Supersedes Report No. GUIDELINES FOR GEOTECHNICAL INVESTIGATION OF BRIDGE STRUCTURES Materials Engineering Report No. 2009-8M (Supersedes Report No. 21) F CHOWDHURY GEOMECHANICS AND STRUCTURAL MATERIALS ENGINEER S REHMAN GEOTECHNICAL

More information

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE TECHNICAL SPECIFICATION PART 8000 - PRECAST CONCRETE TABLE OF CONTENTS Item Number Page 8100 PRECAST CONCRETE CONSTRUCTION - GENERAL 8-3 8101 General

More information

Index. protection. excavated drop inlet protection (Temporary) 6.50.1 6.51.1. Block and gravel inlet Protection (Temporary) 6.52.1

Index. protection. excavated drop inlet protection (Temporary) 6.50.1 6.51.1. Block and gravel inlet Protection (Temporary) 6.52.1 6 Index inlet protection excavated drop inlet protection (Temporary) 6.50.1 HARDWARE CLOTH AND GRAVEL INLET PROTECTION Block and gravel inlet Protection (Temporary) sod drop inlet protection ROCK DOUGHNUT

More information

SAFETY GUIDELINES FOR EXCAVATIONS (Based on 1926, Subpart P)

SAFETY GUIDELINES FOR EXCAVATIONS (Based on 1926, Subpart P) SAFETY GUIDELINES FOR EXCAVATIONS (Based on 1926, Subpart P) All contractors that perform excavation work must have a competent person who is responsible for ensuring safety associated with all excavation

More information

Brighton i360 - Beach Landing June Technical Q&A

Brighton i360 - Beach Landing June Technical Q&A Brighton i360 - Beach Landing June 2015 - Technical Q&A Conceived and designed by Marks Barfield Architects, creators of the London Eye, the 162 metres high Brighton i360 has an observation pod rising

More information

Winona Bridge Work Package #5 Bridge No (Existing Bridge) Rehabilitation and Reconstruction Installment #3 The $30 million Cost Growth

Winona Bridge Work Package #5 Bridge No (Existing Bridge) Rehabilitation and Reconstruction Installment #3 The $30 million Cost Growth Winona Bridge Work Package #5 Bridge No. 5900 (Existing Bridge) Rehabilitation and Reconstruction Installment #3 The $30 million Cost Growth March 9, 2016 The history of the Winona Bridge project spans

More information

Single Family Residential Erosion and Sediment Control Standards

Single Family Residential Erosion and Sediment Control Standards July 2011 Planning and Development Services Single Family Residential Erosion and Sediment Control Standards This booklet contains standard plans and procedures appropriate for typical residential building

More information

SECTION 02100 SITE PREPARATION

SECTION 02100 SITE PREPARATION SECTION 02100 SITE PREPARATION PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and General Provisions of Contract, including General Conditions and Supplementary Conditions and Division 1 through Division

More information

The words GENERAL NOTES are part of the FSHT cell. The general notes cell, GNNTE, shall be snapped to the top of the G.

The words GENERAL NOTES are part of the FSHT cell. The general notes cell, GNNTE, shall be snapped to the top of the G. ( OF BRIDGE PLANS) General: The following are suggested wordings for notes that are regularly needed on the title sheet of bridge plans. Where these notes are fully applicable, there may be no need to

More information

Portway Extensions Concept Development Study APPENDIX F PRELIMINARY CONSTRUCTION COST ESTIMATES

Portway Extensions Concept Development Study APPENDIX F PRELIMINARY CONSTRUCTION COST ESTIMATES Portway Extensions Concept Development Study Final Report APPENDIX F PRELIMINARY CONSTRUCTION COST ESTIMATES Portway Extensions Concept Development Study Final Report In advance of an economic impact analysis

More information

Stormwater/Wetland Pond Construction Inspection Checklist

Stormwater/Wetland Pond Construction Inspection Checklist : Construction Inspection ChecklistsTools Stormwater/Wetland Pond Construction Inspection Checklist Project: Location: Site Status: Date: Time: Inspector: SATISFACTORY/ UNSATISFACTORY COMMENTS Pre-Construction/Materials

More information

EXCAVATIONS AND TRENCHING. Environmental Health and Safety Office

EXCAVATIONS AND TRENCHING. Environmental Health and Safety Office EXCAVATIONS AND TRENCHING Environmental Health and Safety Office July 2014 Table of Contents I. General Requirements:... 1 II. Protective Systems... 4 Appendix A... 7 EHS 07/2014 EXCAVATIONS AND TRENCHING

More information

REHABILITATION PACKAGE 1-a

REHABILITATION PACKAGE 1-a 1-a WINONA BRIDGE (BRIDGE 5900) REHABILITATION PACKAGE 1-a Rehab option 1-a is a rehabilitation package whereby all spans of the existing structure would be rehabilitated to the degree feasible and strengthened

More information

Aberdeen Western Peripheral Route/ Balmedie-Tipperty

Aberdeen Western Peripheral Route/ Balmedie-Tipperty Aberdeen Western Peripheral Route/ Balmedie-Tipperty Aberdeen and Grampian Chamber of Commerce Transport Group Town House Council Chamber, Aberdeen 26 November 2015 Speakers Scott Shaw, Project Manager

More information

King Post Wall Information

King Post Wall Information King Post Wall Information DAWSON-WAM specialise in the installation of piled retaining wall systems including steel sheet piling, concrete piled walls and king post walls. This document is our guide to

More information

PRELIMINARY COST ESTIMATE FOR SINGLE SPAN OVERFILLED PRECAST CONCRETE ARCH BRIDGE STRUCTURES

PRELIMINARY COST ESTIMATE FOR SINGLE SPAN OVERFILLED PRECAST CONCRETE ARCH BRIDGE STRUCTURES PRELIMINARY COST ESTIMATE FOR SINGLE SPAN OVERFILLED PRECAST CONCRETE ARCH BRIDGE STRUCTURES TRINITY COUNTY BRIDGES CALIFORNIA FOREST HIGHWAY 148: SHANTY CREEK CROSSING AND HIGHWAY 149: VAN HORN GULCH

More information

Materials. Estimating Steel. Players. Materials. Shop Drawings. Detailing Process. Standard shapes. Fabricated members, Built-up sections

Materials. Estimating Steel. Players. Materials. Shop Drawings. Detailing Process. Standard shapes. Fabricated members, Built-up sections Materials Standard shapes W sections, C channels, Structural T, Angles, Pipes, Tubes, Rods and Plates Fabricated members, Built-up sections Adding plates to beam flanges, Stiffeners to beam webs Built

More information

Source: Port Mann Bridge Plans Unveiled Today, CBC News, February 4, 2009.

Source: Port Mann Bridge Plans Unveiled Today, CBC News, February 4, 2009. Total project cost $2.5 billion (Canadian) Financed by tolls about $3 each direction. Total project length 37 km (McGill St in Vancouver to 216 th in Langley) The new Port Mann bridge 10 lanes (existing

More information

THE OBJECTIVES OF ROUTINE ROAD CUTS AND FILLS

THE OBJECTIVES OF ROUTINE ROAD CUTS AND FILLS Chapter 11 Slope Stabiliza bilization and Stability of Cuts and Fills THE OBJECTIVES OF ROUTINE ROAD CUTS AND FILLS are 1) to create space for the road template and driving surface; 2) to balance material

More information

FINAL SECTION OF COASTAL PROTECTION RIVER DODDER PART 8 PROPOSALS London Bridge and New Bridge

FINAL SECTION OF COASTAL PROTECTION RIVER DODDER PART 8 PROPOSALS London Bridge and New Bridge FINAL SECTION OF COASTAL PROTECTION RIVER DODDER PART 8 PROPOSALS London Bridge and New Bridge Planning and Development Acts 2000-2006 Planning and Development Regulations 2001-2006, Part 8 March 2012

More information

Ohio Department of Transportation Division of Production Management Office of Geotechnical Engineering. Geotechnical Bulletin

Ohio Department of Transportation Division of Production Management Office of Geotechnical Engineering. Geotechnical Bulletin Ohio Department of Transportation Division of Production Management Office of Geotechnical Engineering Geotechnical Bulletin GB 2 SPECIAL BENCHING AND SIDEHILL EMBANKMENT FILLS Geotechnical Bulletin GB2

More information

DESCRIPTION OF WORK:

DESCRIPTION OF WORK: DEPARTMENT OF PUBLIC WORKS COUNTY OF HENRICO P.O. BOX 27032 RICHMOND, VIRGINIA 23273 PERMIT NO. One (1) copy of application and four (4) copies of plans are hereby made to the Director of Public Works

More information

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND TELECOMMUNICATION CABLES IN THE VICINITY OF TRANSPORTATION FACILITIES

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND TELECOMMUNICATION CABLES IN THE VICINITY OF TRANSPORTATION FACILITIES APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND TELECOMMUNICATION CABLES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE JURISDICTION OF ALBERTA TRANSPORTATION 1.0 Application Procedures 2.0

More information

Chaudière Crossing Bridge Rehabilitation

Chaudière Crossing Bridge Rehabilitation Chaudière Crossing Bridge Rehabilitation Douglas K. Lowry P. Eng., Armtec Infrastructure Incorporated David Delicate, P.Eng. Public Works and Government Services Canada (Retired) Prepared for presentation

More information

HUNDORP BRIDGE. Bridge deck rehabilitation using cross-laminated timber. Authors: Structural engineers Rune B Abrahamsen and Trond E Nyløkken

HUNDORP BRIDGE. Bridge deck rehabilitation using cross-laminated timber. Authors: Structural engineers Rune B Abrahamsen and Trond E Nyløkken HUNDORP BRIDGE Bridge deck rehabilitation using cross-laminated timber Authors: Structural engineers Rune B Abrahamsen and Trond E Nyløkken Location 70 km north of Lillehammer 250 km north of Oslo. The

More information

Short Span Bridge Design Alternatives

Short Span Bridge Design Alternatives Conference Short Span Bridge Design Alternatives By: Jack Elston, P.E., Steve Megginson, P.E., S.E. AGENDA Introduction Bridge Planning Alternatives Design Comparisons Summary 2 Introduction Pragmatic

More information

Triton Knoll Offshore Wind Farm Limited Electrical System. Outline Traffic Management Plan

Triton Knoll Offshore Wind Farm Limited Electrical System. Outline Traffic Management Plan Triton Knoll Offshore Wind Farm Limited Electrical System Outline Traffic Management Plan October 2014 RWE Innogy UK Triton Knoll TMP Copyright 2014 RWE Innogy UK Ltd All pre-existing rights reserved.

More information

SPECIFICATIONS FOR ERECTION OF STRUCTURAL STEEL

SPECIFICATIONS FOR ERECTION OF STRUCTURAL STEEL SPECIFICATIONS FOR ERECTION OF STRUCTURAL STEEL 1.0 DESCRIPTION The Work shall consist of:.1 Unloading and erecting structural steel components (e.g. girders, diaphragms, jacking beams, stiffeners, girder

More information

Geological Survey of Ireland Landslides Workshop 21 April 2009

Geological Survey of Ireland Landslides Workshop 21 April 2009 Investigation & Repair of a Small Landslide on the Torr Head Coast Road, North Antrim Mark Cassidy, Byrne Looby Partners (formerly Doran Consulting Geological Survey of Ireland Landslides Workshop 21 April

More information

MINNESOTA DEPARTMENT OF TRANSPORTATION ESTIMATED PRODUCTION RATES FOR COMPUTING CONTRACT TIME

MINNESOTA DEPARTMENT OF TRANSPORTATION ESTIMATED PRODUCTION RATES FOR COMPUTING CONTRACT TIME SET-UP AND MOBILIZATION MOBILIZATION LS 1-3 Days CONTRACTOR SURVEY LS 1-3 Days REMOVALS CONCRETE PAVEMENT SQ YD 1000-4000 BITUMINOUS SURFACE SQ YD 8000-12000 CLEAR AND GRUBBING ACRE/DAY 2-4 CLEAR AND GRUBBING

More information

Introducing the Grid-Strip TM Soil Reinforcement System. Precast Panel Walls Wire Walls Two-Stage Precast Walls

Introducing the Grid-Strip TM Soil Reinforcement System. Precast Panel Walls Wire Walls Two-Stage Precast Walls Precast Panel Walls Wire Walls Two-Stage Precast Walls ail.ca Introducing the Grid-Strip TM Soil Reinforcement System Simplifies installations Saves time and money Save time. Save money. Specify a fast,

More information

ALABAMA DEPARTMENT OF TRANSPORTATION DATE : 11/22/13 PAGE : VENDOR RANKING

ALABAMA DEPARTMENT OF TRANSPORTATION DATE : 11/22/13 PAGE : VENDOR RANKING PAGE : 998-1 VENDOR RANKING CONTRACT TIME : 390 Working Days (available days) CONTRACT DESCRIPTION : BIRMINGHAM PROJECT(S) : APD-1602(551) for constructing the Grade, Drain, Partial Base & Pave, Bridge

More information

DESIGN GUIDELINES FOR EARTH RETENTION

DESIGN GUIDELINES FOR EARTH RETENTION DESIGN GUIDELINES FOR EARTH RETENTION Strata Systems, Inc. 380 Dahlonega Rd., Suite 200 Cumming, GA 30040 USA www.geogrid.com TABLE OF CONTENTS MECHANICS OF RETAINING WALLS... 3 THE STRATAWEB SOLUTION...4

More information

Geotechnical Building Works (GBW) Submission Requirements

Geotechnical Building Works (GBW) Submission Requirements Building Control (Amendment) Act 2012 and Regulations 2012: Geotechnical Building Works (GBW) Submission Requirements Building Engineering Group Building and Construction Authority May 2015 Content : 1.

More information

Alberta Transportation Bridge Inspection & Maintenance System (Web 2005) 00747-1 Bridge. Bridge Inspection. Assistant Name Assistant Class

Alberta Transportation Bridge Inspection & Maintenance System (Web 2005) 00747-1 Bridge. Bridge Inspection. Assistant Name Assistant Class Bridge File Number Year Built/Year Supstr 00747-1 Bridge 1964/1964 Bridge or Town Name SUNNYSLOPE Located Over Located On 582:04 C1 33.896 Water Body Cl./Year Navigabil. Cl./Year Legal Land Location KNEEHILLS

More information

NOTES TO SPECIFICATIONS FOR NORMAL AND HIGH QUALITY QUALITY ASSURANCE LEVEL CONTRACTS

NOTES TO SPECIFICATIONS FOR NORMAL AND HIGH QUALITY QUALITY ASSURANCE LEVEL CONTRACTS NOTES TO SPECIFICATIONS FOR NORMAL AND HIGH QUALITY ASSURANCE LEVEL CONTRACTS These notes are for the guidance of Transit New Zealand's staff and consultants, and must not be included in the contract documents.

More information

SECTION 15076 CEMENT-MORTAR LINED AND COATED STEEL PIPE

SECTION 15076 CEMENT-MORTAR LINED AND COATED STEEL PIPE SECTION 15076 CEMENT-MORTAR LINED AND COATED (CML&C) STEEL PIPE PART 1 GENERAL 1.01 DESCRIPTION This section designates the requirements for steel pipe fabrication, test in shop, installation of steel

More information

Technical Report 4. Construction Methodology Report

Technical Report 4. Construction Methodology Report Technical Report 4 Construction Methodology Report 29 March 2012 Revision History Revision Nº Prepared By Description Date A Andrew Goldie (Fletcher) 17/2/12 Document Acceptance Action Name Signed Date

More information

Pipeline bridge crossing for mining trucks A geotechnical engineering design.

Pipeline bridge crossing for mining trucks A geotechnical engineering design. Pipeline bridge crossing for mining trucks A geotechnical engineering design. Bernard Shen Pells Sullivan Meynink, Sydney, Australia ABSTRACT The Donaldson open pit coal mine is located in Blackhill, New

More information

June 2007 CHAPTER 7 - CULVERTS 7.0 CHAPTER 7 - CULVERTS 7.1 GENERAL

June 2007 CHAPTER 7 - CULVERTS 7.0 CHAPTER 7 - CULVERTS 7.1 GENERAL 7.0 7.1 GENERAL For the purpose of this manual, culverts are defined as structures that are completely surrounded by soil and located below the surface of the roadway parallel to the general direction

More information

Photo 2. View showing flour mill, machine shed, veranda and saw mill + storage shed.

Photo 2. View showing flour mill, machine shed, veranda and saw mill + storage shed. May 7,2015 KSANDER & ASSOCIATES CONSULTING PROFESSIONAL ENGINEERS 130 HUINTER STREET, UNIT 103, PETERBOROUGH, ONTARIO K9H2K8 TELEPHONE (705) 743-9221 FAX 743-0904 Ontario Region Conservation Authority

More information

UNDERWATER BRIDGE INSPECTION REPORT HENNEPIN COUNTY, CITY OF MINNEAPOLIS

UNDERWATER BRIDGE INSPECTION REPORT HENNEPIN COUNTY, CITY OF MINNEAPOLIS UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 27611 PLYMOUTH AVENUE OVER THE MISSISSIPPI RIVER HENNEPIN COUNTY, CITY OF MINNEAPOLIS OCTOBER 28, 2012 PREPARED FOR THE MINNESOTA DEPARTMENT OF TRANSPORTATION

More information

Civil. 2. City of Seattle Supplement to the Specification for Road, Bridge and Municipal Construction, most current addition.

Civil. 2. City of Seattle Supplement to the Specification for Road, Bridge and Municipal Construction, most current addition. Design Guide Basis of Design This section applies to the design and installation of earthwork and backfill. Design Criteria No stockpiling of excavation materials is allowed unless the Geotechnical Engineer

More information

Taseko Mine Potential Costs to Public Road System from Truck Transport of Mine Concentrate

Taseko Mine Potential Costs to Public Road System from Truck Transport of Mine Concentrate Taseko Mine Potential Costs to Public Road System from Truck Transport of Mine Concentrate Introduction and Purpose of Road Review EIS did not include costs or impacts of year-round transport of mine concentrate

More information

Bridge Component Concrete Standard

Bridge Component Concrete Standard Bridge Component Concrete Standard Ministry of Forests, Lands and Natural Resource Operations All concrete bridge component products supplied for the Ministry of Forests, Lands and Natural Resource Operations

More information

Evaluating the Condition of Seawalls/Bulkheads

Evaluating the Condition of Seawalls/Bulkheads Volume 2 Evaluating the Condition of Seawalls/Bulkheads By: Coastal Systems International, Inc. Typical bulkhead under construction Seawalls and bulkheads (walls) provide shoreline stabilization for many

More information

The purpose of this meeting is to inform the public of the updates to the project, and to get input before the finalization of the project.

The purpose of this meeting is to inform the public of the updates to the project, and to get input before the finalization of the project. The purpose of this meeting is inform the public of the updates the project, and get input before the finalization of the project. The following panels describe the purpose and hisry of the project, along

More information

INCREASE OF DURABILITY AND LIFETIME OF EXISTING BRIDGES. PIARC TC 4.4 EXPERIENCE.

INCREASE OF DURABILITY AND LIFETIME OF EXISTING BRIDGES. PIARC TC 4.4 EXPERIENCE. INCREASE OF DURABILITY AND LIFETIME OF EXISTING BRIDGES. PIARC TC 4.4 EXPERIENCE. M.Sc. Gediminas Viršilas Head of Bridge Division, Lithuanian Road Administration Working group 2 of PIARC Technical Committee

More information

FUTURE SLAB. PENETRATIONS and. DEMOLITION of POST-TENSIONED FLOORS

FUTURE SLAB. PENETRATIONS and. DEMOLITION of POST-TENSIONED FLOORS FUTURE SLAB PENETRATIONS and DEMOLITION of POST-TENSIONED FLOORS 1.0 INTRODUCTION Post-tensioned floor slabs in Australia and South East Asia are now universally regarded as the most cost effective form

More information

US 51 Ohio River Bridge Engineering and Environmental Study

US 51 Ohio River Bridge Engineering and Environmental Study US 51 Ohio River Bridge Engineering and Environmental Study ITEM NOS. 1-100.00 & 1-1140.00 Prepared by: Michael Baker Jr., Inc. 9750 Ormsby Station Rd Louisville, KY 40223 August 16, 2013 Table of Contents

More information

REHABILITATION OF THE FIGUEIRA DA FOZ BRIDGE

REHABILITATION OF THE FIGUEIRA DA FOZ BRIDGE REHABILITATION OF THE FIGUEIRA DA FOZ BRIDGE A.Rito Proponte, Lda, Lisbon, Portugal J. Appleton A2P Consult, Lda, Lisbon, Portugal ABSTRACT: The Figueira da Foz Bridge includes a 405 m long cable stayed

More information

CHALLENGES AND INNOVATIVE SOLUTIONS FOR BRIDGE FOUNDATION REPAIRS

CHALLENGES AND INNOVATIVE SOLUTIONS FOR BRIDGE FOUNDATION REPAIRS CHALLENGES AND INNOVATIVE SOLUTIONS FOR BRIDGE FOUNDATION REPAIRS Drew Monnier 1, P.Eng. (Presenting) Kimberly Yathon 2, B.Sc. CE (Presenting) Ruth Eden 1, M.Sc., P.Eng. Randy Fingas 1, P.Eng. Emile Shehata

More information

twenty six concrete construction: foundation design ELEMENTS OF ARCHITECTURAL STRUCTURES: FORM, BEHAVIOR, AND DESIGN DR. ANNE NICHOLS SPRING 2014

twenty six concrete construction: foundation design ELEMENTS OF ARCHITECTURAL STRUCTURES: FORM, BEHAVIOR, AND DESIGN DR. ANNE NICHOLS SPRING 2014 ELEMENTS OF ARCHITECTURAL STRUCTURES: FORM, BEHAVIOR, AND DESIGN DR. ANNE NICHOLS SPRING 2014 lecture twenty six concrete construction: www.tamu.edu foundation design Foundations 1 Foundation the engineered

More information

Structural Inspection Foundations

Structural Inspection Foundations Structural Inspection Foundations 0211 Footings Concrete pad and continuous footings The concrete footings consist of continuous strip footings at the building perimeter of the following sizes: 16 wide

More information

Twin Cities LRT Structures. Jim Alexander Director, Design and Engineering Southwest LRT Project Metropolitan Council/Metro Transit

Twin Cities LRT Structures. Jim Alexander Director, Design and Engineering Southwest LRT Project Metropolitan Council/Metro Transit Twin Cities LRT Structures Jim Alexander Director, Design and Engineering Southwest LRT Project Metropolitan Council/Metro Transit 1 Today s Topics METRO Green Line: Washington Avenue Bridge Retrofit Southwest

More information

14 Geotechnical Hazards

14 Geotechnical Hazards Volume 2: Assessment of Environmental Effects 296 14 Geotechnical Hazards Overview This Chapter provides an assessment of the underlying geotechnical conditions to identify: any potential liquefaction

More information

CHAPTER III SITE EXPLORATION

CHAPTER III SITE EXPLORATION CHAPTER III SITE EXPLORATION Investigational Programs. Field investigations can be divided into two major phases: a surface examination and a subsurface exploration. 1 Surface Examination a. Literature

More information

Pedestrian Plaza Bridge by Jim Aitken, ARCADIS U.S. Inc.; Mike Clements, Georgia DOT; and Tim Schmitz, formerly with ARCADIS U.S. Inc.

Pedestrian Plaza Bridge by Jim Aitken, ARCADIS U.S. Inc.; Mike Clements, Georgia DOT; and Tim Schmitz, formerly with ARCADIS U.S. Inc. Fifth Street Pedestrian Plaza Bridge by Jim Aitken, ARCADIS U.S. Inc.; Mike Clements, Georgia DOT; and Tim Schmitz, formerly with ARCADIS U.S. Inc. The newly constructed Fifth Street Bridge over I-75/I-85

More information

twenty seven concrete construction: foundation design ARCHITECTURAL STRUCTURES: FORM, BEHAVIOR, AND DESIGN HÜDAVERDİ TOZAN SPRING 2013 lecture

twenty seven concrete construction: foundation design ARCHITECTURAL STRUCTURES: FORM, BEHAVIOR, AND DESIGN HÜDAVERDİ TOZAN SPRING 2013 lecture ARCHITECTURAL STRUCTURES: FORM, BEHAVIOR, AND DESIGN HÜDAVERDİ TOZAN SPRING 2013 lecture twenty seven concrete construction: Bright Football Complex www.tamu.edu foundation design Foundations 1 Foundation

More information

HIGH LEVEL SEISMIC UPGRADE COST ESTIMATE FOR CENTRE BLOCK, PARLIAMENT HILL

HIGH LEVEL SEISMIC UPGRADE COST ESTIMATE FOR CENTRE BLOCK, PARLIAMENT HILL HIGH LEVEL SEISMIC UPGRADE COST ESTIMATE FOR CENTRE BLOCK, PARLIAMENT HILL Prepared for: Public Works and Government Services Canada Parliamentary Precinct Branch Prepared by: Halsall Associates 210 Gladstone

More information

Post Tensioning Awards 2009

Post Tensioning Awards 2009 Post Tensioning Awards 2009 Project Summary Type of structure Location Architects Structural Engineer Residential with leisure suites including Swimming pool, Cinema, Virtual Golf, Wine Cellars, and Parking

More information

AASHTO Bridge Preservation T-9 Subcommittee

AASHTO Bridge Preservation T-9 Subcommittee AASHTO Bridge Preservation T-9 Subcommittee VDOT s Use of Corrosion Resistant Metallic Reinforcing Bars in Bridge Construction April 21, 2015 Kendal R. Walus, PE State Structure and Bridge Engineer 2 3

More information

Virginia Approach Spans

Virginia Approach Spans Virginia Concrete Conference 2009 Woodrow Virginia Approach Spans David Tackoor, HNTB Formerly of URS Corp for Potomac Crossing Consultants Woodrow 1 Second Severn Crossing 2 Medway Crossing (Channel Tunnel

More information

COMMONWEALTH OF PENNSYLVANIA DEPARTMENT OF TRANSPORTATION BUREAU OF PROJECT DELIVERY

COMMONWEALTH OF PENNSYLVANIA DEPARTMENT OF TRANSPORTATION BUREAU OF PROJECT DELIVERY GENERAL : CONTRACT DRAWING : 1. DESIGN SPECIFICATIONS: THE FOLLOWING ARE TO BE PLACED ON THE CONTRACT DRAWINGS WHEN REQUIRED: AND DESIGNED IN ACCORDANCE WITH THE AASHTO SPECIFICATIONS FOR HIGHWAY BRIDGES,

More information

7.4 Loads and Load combinations

7.4 Loads and Load combinations 7.4 Loads and Load combinations 7.4.1 Loads on bridges The following are the various loads to be considered for the purpose of computing stresses, wherever they are applicable. Dead load Live load Impact

More information

INDOT Bridge Asset Engineers

INDOT Bridge Asset Engineers Common Bridge Maintenance Issues Pete White, P.E. Greenfield District Bridge Asset Engineer, INDOT February 16, 2016 INDOT Bridge Asset Engineers LaPorte (Northwest) - Steve Benczik, P.E. (Outgoing) Mark

More information

twenty six concrete construction: foundation design Foundation Structural vs. Foundation Design Structural vs. Foundation Design

twenty six concrete construction: foundation design Foundation Structural vs. Foundation Design Structural vs. Foundation Design ELEMENTS OF ARCHITECTURAL STRUCTURES: FORM, BEHAVIOR, AND DESIGN DR. ANNE NICHOLS SRING 2014 lecture twenty six Foundation the engineered interface between the earth and the structure it supports that

More information

twenty six concrete construction: foundation design Foundation Structural vs. Foundation Design Structural vs. Foundation Design

twenty six concrete construction: foundation design Foundation Structural vs. Foundation Design Structural vs. Foundation Design ELEMENTS OF ARCHITECTURAL STRUCTURES: FORM, BEHAVIOR, AND DESIGN DR. ANNE NICHOLS SRING 2013 lecture twenty six Foundation the engineered interface between the earth and the structure it supports that

More information

SEISMIC UPGRADE OF OAK STREET BRIDGE WITH GFRP

SEISMIC UPGRADE OF OAK STREET BRIDGE WITH GFRP 13 th World Conference on Earthquake Engineering Vancouver, B.C., Canada August 1-6, 2004 Paper No. 3279 SEISMIC UPGRADE OF OAK STREET BRIDGE WITH GFRP Yuming DING 1, Bruce HAMERSLEY 2 SUMMARY Vancouver

More information

Portable Bridges. Stream crossings on forest roads frequently. For Forest Road Stream Crossings. Stream Crossing Structures.

Portable Bridges. Stream crossings on forest roads frequently. For Forest Road Stream Crossings. Stream Crossing Structures. ANR-1074 Portable Bridges For Forest Road Stream Crossings Stream crossings on forest roads frequently create problems for loggers and many landowners. Stream crossings are costly to build and time-consuming

More information

Session 3: Guardrail Design and Sitespecific. Considerations

Session 3: Guardrail Design and Sitespecific. Considerations FHWA Roadway Departure Technology Transfer Roadside Safety Systems Installer Training : Guardrail Design and Sitespecific Installation Considerations 3-1 Course Topics Session 2 Testing Requirements and

More information

Florida Department of Transportation 605 Suwannee Street Tallahassee, FL 32399-0450

Florida Department of Transportation 605 Suwannee Street Tallahassee, FL 32399-0450 RICK SCOTT GOVERNOR Florida Department of Transportation 605 Suwannee Street Tallahassee, FL 32399-0450 JIM BOXOLD SECRETARY Tips for Professional Services Prequalification Resume Submission In an effort

More information

Preparing the Erosion and Sedimentation Control Plan

Preparing the Erosion and Sedimentation Control Plan 4 Preparing the Erosion and Sedimentation Control Plan Preparing the Erosion and Sedimentation Control Plan 4 Preparing the Erosion and Sedimentation Control Plan GENERAL CONSIDERATIONS Before preparing

More information

A CASE STUDY ON THE USE OF FLEXIBLE EARTH RETAINING STRUCTURE IN UNSTABLE SLOPES

A CASE STUDY ON THE USE OF FLEXIBLE EARTH RETAINING STRUCTURE IN UNSTABLE SLOPES A CASE STUDY ON THE USE OF FLEXIBLE EARTH RETAINING STRUCTURE IN UNSTABLE SLOPES H. Turan DURGUNOGLU Ahmet SAHIN Onder AKCAKAL Zetas Zemin Teknolojisi A.S., TOKI-Housing Development Zetas Zemin Teknolojisi

More information