Electricity to your property
|
|
- Lynette Hudson
- 8 years ago
- Views:
Transcription
1 Vattenfall Distribution AB Electricity to your property How an electrical connection is made and what you need to consider
2 How electricity reaches your property 8 simple steps! 1. Please leave plenty of time! Bear in mind that the process will take at least five to eight weeks. In rural areas, often involving long distances, this may take longer. Up-to-date prices can be found at where you can also order a quote. 2. Contact a certified electrician to assist you with the work. The electrician will send a preliminary application to us, describing the work to be carried out and including a map showing the property as well as a site plan. 3. We will send you a quote for the connection fee, in response to either your request or the electrician s preliminary application. The quote sets out what you and Vattenfall each need to do. 4. You order the connection by signing the order form enclosed with the quote and returning this to us. 5. Each connection requires a different amount of work. We may need to reinforce the electricity network, order a new substation or request permission from landowners and authorities. We will confirm the order once we know what is required for your specific connection. You will then be notified of when we plan to have completed the work up to your site and provided with the information you need to choose an electricity supplier. 6. Once we have received your order and the electrician s preliminary application, we will notify your electrician that work can begin. 7. In addition to wiring the house, the electrician will install a meter box and ensure that the correct cable protection conduit is purchased and laid underground. Once the electrician has completed this work, a notification of completion will be sent to us. 8. You will receive information about your subscription once we have connected the service cable to your meter box. The electrician is responsible for connecting the electricity to your unit. We will backfill outside your site and you are responsible for backfilling on your site. 5
3 There is a lot to think about when constructing a new build! If you require electricity at your property, it is Vattenfall Eldistribution s task to connect your property to the electricity network, if it is located within our network area. Electrical work carried out at your site or at your unit must be performed by a certified electrician. This electrician will act as your agent and assist you during the process. Most of your contact with us will be through your electrician. A good, reliable electricity supply We own the electricity network in your area and maintain it to ensure consistent high quality. When connecting a new unit, we calculate how the electricity network will be affected. We may need to reinforce the network in order to maintain its quality. There is usually a substation that can support the new unit. In some cases we will need to construct a new one, however kv Electricity s journey from power plants to your wall socket The coloured area shows the part involved in connection work. Main substation kv Before the electricity reaches your wall sockets from the power station it has to be stepped down several times to reach the appropriate voltage kv Regional station Substation (1) Substations often look like small prefabricated houses and are found in every residential area. These receive power from the nearest distribution station, where the voltage is stepped down. The substation further reduces the voltage so it can be supplied to a junction box V Junction box (2) and electricity meter box (3) In the junction box, often a small grey box located near the property, electricity is distributed to the property s separate electricity meter boxes or electrical rooms. Distribution station kv 1 Service cable (4) The service cable runs from the junction box to the customer s meter box or electrical room. In this diagram, the meter box is located on the outside wall of the house. 2
4 How long does an electrical connection take? This depends on for instance the area in which the connection will take place and the time of year. In urban areas, it typically takes five to eight weeks from receipt of a written request from you, the customer, and a preliminary application from your electrician. You should anticipate a longer period in rural areas. We may need to construct a new substation, for example, if the distance from the existing station is too great. The process may take longer if we need permission from landowners and authorities. Once we have received your order, we will inform you of the date we plan to complete our part of the work. Please leave plenty of time! How much does an electrical connection cost? The connection fee is based on the distance as the crow flies from our nearest substation to your property, as well as the size of your main fuse. Up-to-date prices can be found on our website. The exact price for your specific connection will be provided in the quote. KABELSKÅP Zone model The fee is an average price and is the same for each zone, regardless of where in Sweden the connection takes place. The price is based on the Energy Markets Inspectorate s own model. The connection fee consists of two elements: a fee for access to the electricity network and a fee for the service cable. NÄT- STATION ZON 1 ZON 2 ZON 3 ZON 4 Access to electricity network We ensure that the electricity network in your area can support your electricity consumption. We will either already have constructed a substation, which is common in urban areas, or we will need to construct a new one. We will run electrical cables up to the junction box where we will make space for your connection. Service cable We will excavate and lay electrical cables from the junction box to your site boundary. We will then lay our service cable on your site and install an electricity meter in your meter box. How do I place my order? Your chosen electrician will send us a preliminary application and we will send you a quote. You order work from us by signing the order form included with the quote. Once we have received your order, we will send you a confirmation including the delivery date and our contact person. The confirmation will also include the information you need to choose an electricity supplier. Meanwhile, we will start our work by running electrical cables up to your site boundary and the electrician can then prepare to carry out work. Up-to-date prices can be found on the website. Tip! Watch our information films at 3
5 Work on your site You are responsible for work carried out on your site. Ensuring that the correct cable protection conduit is purchased and laid underground is an important part of this bear in mind that laying a cable protection conduit is a requirement. We will run our service cable to your meter box through the cable protection conduit. If there are already electrical cables at the site, you can contact our Customer Services department to find out where these are located. If you would like to have cables removed, you will need to bear the cost of doing this. It is best to coordinate excavation for cables with excavation for the water and sewage pipes. Contact therefore the cable owners for the telephone, broadband and cable TV connections in good time. You can check whether your electrician is certified at Who does what The electrician will wire the house and install a meter box. Once the work is complete, a notification of completion will be sent to us. The electrician is also responsible for connecting the electricity. You will receive information about your subscription once we have connected the service cable to the meter box. We will backfill outside your site and you are responsible for backfilling on your site. Area of responsibility Responsible Excavation on site Cable protection conduit and a pull wire in conduit Backfilling following excavation on site Material property owner Work property owner property owner property owner Service cable in cable protection conduit Vattenfall Eldistribution Vattenfall Eldistribution Connection of service cable to meter box Vattenfall Eldistribution Meter panel and meter box property owner property owner Meter, data collection system Vattenfall Eldistribution Vattenfall Eldistribution Choose the correct main fuse Once the subscription has started, you will pay a subscription fee and a variable electricity transfer fee to Vattenfall Eldistribution. The subscription fee is based on the size of the main fuse and also includes authority charges. The larger the main fuse and the higher the amps, the more electricity you can use at once. If your main fuse is too low, it will blow and need to be replaced frequently. Read more about the function of the main fuse and how to find out the size of your fuse at Electricity meter Main fuse Spacer When the main fuse is unscrewed you will see the spacer at the bottom of the fuse box. Consult an electrician to choose the correct size of main fuse. 4
6 The service cable and outer wall meter box are installed as follows. The outer wall box should be installed vertically on a solid surface free from vibration. It may not, for instance, be mounted on the lock side of the front door or on the same horizontal frame member EL the waste bin holder is screwed into. The inner diameter of the conduit should be at least twice the outer diameter of the cable. The outer diameter should be at least 50 mm. TELE min 0,9 m max 2,2 m Your electrician supplies an outer wall box, which can be mounted on the outer wall or flush with the outer wall. The electricity meter is supplied and installed by the network company. Backfilled ground Your electrician will supply an outer wall meter box. This can be mounted on the outer wall or flush with the outer wall. The electricity meter will be supplied and installed by Vattenfall Eldistribution. Bend radius min 0,5 m min 0,35 m 1,0 m Cable pull pit between building shell and site boundary to facilitate cable pulling. The conduit is sealed at both ends after the pipe is laid, to prevent water, sand or other materials from entering. It is important to use the correct cable protection conduit. Installation of the service cable with conduit recessed in foundation wall or outside foundations and outer wall meter box mounted flush with wall. Cable requirements for simultaneous laying of electricity and telecommunications service connections in site ground. Tele Cable TV etc orange cable conduit Service cable min 0,35 m yellow cable conduit The cable protection conduit for the service pipe must: be smooth on the inside and yellow on the outside have an outer diameter of at least 50 mm for a normal house and larger if necessary Laid from the site boundary to within a metre of the house where there should be a cable pull pit have a filling height of minimum of 0.35 metres and maximum 1 metre contain a pullwire be sealed, so that filling material or water cannot enter 0,05 m 5
7 Glossary C Cable protection conduit Protects the service cable on the customer s site and is laid underground. Cable pull pit An open pit in which the conduit is accessible and cables can be pulled through. Connection point The ownership boundary between Vattenfall s electricity network and the customer s unit. D Data collection system Gathers the meter readings for the customer s electricity consumption. Electricity bills are based on these figures. E Electricity meters Placed in the meter box and record how much electricity is consumed. The information is gathered by a data collection system. Electricity supplier The company from which the customer purchases electricity. J Junction box Where the network operator connects the service cables to the various meter boxes and electrical rooms at the property. M Main fuse The fuse on the incoming service cable in the customer s meter box. The main fuse determines the subscription fee. Meter box Located on the customer s site, usually on the outside of the building. This box contains the electricity meter. The property owner owns and maintains the meter box. N Network operator Owns and maintains the electrical cabling up to the customer s connection point and is responsible for meters and metering of electricity consumption. Notification of completion The electrician informs Vattenfall that the customer s unit is ready to be connected. Preliminary application The electrician orders a new or modified connection to Vattenfall s electricity network. Property designation The legal name given to the property by the land survey authority. This is important for us, so we know where your connection will take place. S Service cable The Vattenfall cable through which the customer s electrical unit is connected to the network, at the connection point. Service cable fuse The fuse at the start of the service cable, in Vattenfall s junction box, pylon or transformer station. Site plan Drawn up in conjunction with the building permit and shows the placement of buildings as well as the property designation. Subscription A subscription provides access to the electricity network and the customer pays a fixed connection fee to the network operator. Substation Transforms voltage from high voltage to low voltage. U P Unit ID A code for the electrical unit, used by all network operators to keep track of which electrical unit belongs to which customer. The last nine figures are unique to the unit. Further information can be found on our website Further information on electrical connections can be found at for private customers or for business customers. Once the connection is complete, you can log in at to order SMS notifications during power failures, view invoices and consumption or find out more about smart payment and our customer promises. We explain each element of the invoice on our website. If you would like help with reducing your energy costs, you can meet our energy experts at for private customers or for business customers. 6
8 Please contact us The quote includes contact details for your representative, who you can contact with any questions relating to electrical connection work. Customer Services Private Customers Tel. +46 (0) Business Customers Tel. +46 (0)
9 My checklist To do! Date Order quote, attach site plan Contact a certified electrician Sign and return order Vattenfall sends confirmation Choose electricity supplier Electrician sends a preliminary application Coordinated excavation (water and sewage, telephone, TV, broadband) Electrician sends notification of completion Connection scheduled Vattenfall connects unit Pay connection fee Contact details for a Vattenfall Eldistribution representative for my connection Name Telephone number Vattenfall Eldistribution AB 6
10 Vattenfall Eldistribution AB RU 2560, SE Stockholm Customer Services for Private Customers Tel +46 (0) (weekdays 9 am 5 pm) kundservice@vattenfall.com Customer Services for Business Customers Tel +46 (0) (weekdays 8 am 4.30 pm) foretagskundservice@vattenfall.com
Utilities and existing services
Construction Services Building standards for mechanical and electrical installations Utilities and existing services October 2012 Directorate: Environment Construction Services - Building standards for
More informationElectric Service Guide for Commercial Construction
Electric Service Guide for Commercial Construction Contents Contacting KCP&L... 2 Voltages... 2 Temporary Service... 2 Customer-Provided Temporary Service... 2 KCP&L-Provided Temporary Service.... 2 Current
More informationFor business. Wiring your business for broadband. What happens when copper is required?
For business Wiring your business for broadband Your cabling requirements are dependent on the size and complexity of your business. Smaller businesses should follow the wiring recommendations for residential
More informationElectric Service Conversion Overhead-to-Underground. Minnesota
Electric Service Conversion Overhead-to-Underground Xcel Energy Electric Connections Minnesota Process Please fill out these forms and complete this checklist to begin your application process: 1) Overhead-to-Underground
More informationMedical Lighting. XL4 Patient Light
Medical Lighting XL4 Patient Light The XL4 is the new ergonomically designed, energy efficient patient light from EDL Lighting Limited. Its purpose is to cover a spectrum of applications within the Healthcare
More informationElectric Service Guide for Residential Construction
Electric Service Guide for Residential Construction Table of Contents Contacting KCP&L... 2 Existing Home Remodeling or Additions... 2 Changing your electric service... 2 What you need to know before you
More informationGas Meter Clearances and Service Installation Requirements
March 2015 Gas Meter Clearances and Service Installation Requirements Builder/Owner/Developer Requirements Call PSE s Customer Construction Services 1-888-321-7779 or visit PSE.com/CustomerConstruction
More informationElectric Service Guide for Residential Construction
Electric Service Guide for Residential Construction TABLE OF CONTENTS Contacting KCP&L... 2 Existing Home Remodeling or Additions... 2 Building a New Home... 3 KCP&L Services at a Glance... 4 Current Transformers...
More informationHDA -----------------------------------------------------------
----------------------------------------------------------- Lightstrips ---------------------------------------------------------------------- Ceiling system for heating and cooling LIGHTSTRIPS LIGHTSTRIPS
More informationElectrical Practices for Construction Work
1. Purpose Electrical Practices for Construction Work The purpose of this Code is to provide practical guidance and set minimum safety requirements for electrical practices on all construction sites in
More informationBUILDERS AND CONTRACTORS GUIDE FOR ELECTRIC SERVICE
BUILDERS AND CONTRACTORS GUIDE FOR ELECTRIC SERVICE Toll Free Telephone Numbers Residential Services 800.454.3853 Commercial Services 800.653.5307 Utility Locating Company N.C. 800.632.4949 S.C. 888.721.7877
More informationGas Meter Clearances and Service Installation Requirements
March 2016 Gas Meter Clearances and Service Installation Requirements Builder/Owner/Developer Requirements Call PSE's Customer Construction Services 1 888 321 7779 or visit PSE.com/CustomerConstruction
More informationREQUIREMENTS AND SPECIFICATIONS FOR HIGH VOLTAGE CUSTOMER BUILT FACILITIES PEPCO ENGINEERING
REQUIREMENTS AND SPECIFICATIONS FOR HIGH VOLTAGE CUSTOMER BUILT FACILITIES PEPCO ENGINEERING Revised October, 2013 TABLE OF CONTENTS 1.0 INTRODUCTION... 3 2.0 REQUIRED DRAWINGS... 3 2.1 Site Plan... 3
More information4. REQUEST FOR ELECTRIC SERVICE. 4.1 General Service Information
4. REQUEST FOR ELECTRIC SERVICE To establish an electric service, temporary or permanent, contact UI s Customer Care Center by calling: 1-800-722-5584 (7:00 a.m. 7:00 p.m., Monday Friday and 7:00 AM to
More informationMandatory Part 1.4 BUILD OVER OR NEAR SEWERS, STORMWATER DRAINS AND WATER MAINS
Mandatory Part 1.4 BUILD OVER OR NEAR SEWERS, STORMWATER DRAINS AND WATER MAINS Table of Contents Purpose... 2 Commencement... 2 Application... 2 Referral Agency... 2 Compliance with the QDC... 2 Associated
More informationMOBILE HOME SERVICE REQUIREMENTS GAS
ELECTRIC AND GAS 1.0 INDEX 1.0 INDEX 2.0 PURPOSE 3.0 GENERAL 4.0 REFERENCE MATERIAL 5.0 TYPICAL UNDERGROUND UTILITY LAYOUT 6.0 METER PAD DETAILS 7.0 GENERAL INSTALLATION PROCEDURES 8.0 PEDESTAL SPECIFICATIONS
More informationApplying For New or Revised Electric Service
Applying For New or Revised Electric Service Dear Customer: ComEd is happy to assist you in initiating new or revised electric service to your location. Please complete, sign and return the attached service
More informationMarch 2006 DIVISION 3 - CW 2140-R3 TABLE OF CONTENTS
March 2006 CW 2140 - SEWER AND MANHOLE CLEANING TABLE OF CONTENTS 1. DESCRIPTION... 1 1.1 General... 1 1.2 Definitions... 1 1.3 Referenced Standard Constructions... 1 3. CONSTRUCTION METHODS... 1 3.1 High
More informationELECTRIC METERING COMMERCIAL & INDUSTRIAL
ELECTRIC METERING COMMERCIAL & 1.0 INDEX 1.0 INDEX 2.0 SCOPE 3.0 GENERAL REQUIREMENTS 4.0 METER LOCATIONS 5.0 UNDERGROUND TERMINATIONS 6.0 METERING TRANSFORMER ENCLOSURES 7.0 SINGLE CUSTOMER METER INSTALLATIONS
More informationINSTALLATION & USER INSTRUCTIONS
INSTALLATION & USER INSTRUCTIONS LED ELECTRIC FIRE Focal Point Fires plc. Christchurch, Dorset BH23 2BT Tel: 0202 499330 Fax: 0202 499326 www.focalpointfires.co.uk e : sales@focalpointfires.co.uk MODELS
More informationStep 1: Application Instructions
Step 1: Application Instructions CONTENTS Introduction Customer and Electrician Instructions Completing Section 1 or Section 2 Definitions INTRODUCTION Every effort has been made to provide clear instruction
More informationFiberstars Lighted Laminar Flow Fountain Installation Manual
Fiberstars Lighted Laminar Flow Fountain Installation Manual 79-15037-00 REV Xx http://www.fiberstars.com Page 1 of 8 SAVE THESE DIRECTIONS! These directions are provided to ensure the proper installation
More informationIT&T Infrastructure Standards
Technology Services IT&T Infrastructure Standards Version 1.5 17 th April 2015 Page 1 Table of contents 1 CHANGE HISTORY... 3 1.1 DOCUMENT HISTORY... 3 1.2 REVIEWERS... 3 1.3 APPROVALS... 3 2 INTRODUCTION...
More informationInstallation information. METTLER TOLEDO MultiRange Floor scales / Pit scales
Installation information METTLER TOLEDO MultiRange Floor scales / Pit scales KC300/KCS300 KC600/KCS600 KD600/KD1500 KE1500/KE3000 KES1500/KES3000 KG3000/KG6000 KN1500 Floor scales / Pit scales Contents
More informationStandard terms and conditions
Standard terms and conditions INTRODUCTION For the provision of a water service (Water Supply, Wastewater and Drainage) Under Section 73(2)(a) of the Water Services Act 2012, landowners may be entitled
More informationMETER REQUIREMENTS GENERAL REQUIREMENTS SECTION D
12 - ELECTRIC SERVICE HANDBOOK SECTION D METER REQUIREMENTS This chapter gives you information on Central Lincoln s metering requirements. It's divided into three sections: General requirements This section
More informationElectrical for Detached Garages: Updated Feb 19, 2016 for 2015 CE Code in force Jan. 1, 2016. Underground branch circuit feeding a detached garage:
Electrical for Detached Garages: Updated Feb 19, 2016 for 2015 CE Code in force Jan. 1, 2016 * Garage construction requires permits (electrical, building) * Permits must be applied for at the time. * Dial
More informationSeparation of common services (above and below ground) INDUSTRY BULLETIN. Background. Separation distances. Proximity of services below ground
Government of Western Australia Department of Commerce Separation of common services (above and below ground) The purpose of this industry bulletin is to remind building practitioners of their responsibilities
More information50AI01oe 02/15. Labko GRP cesspools. Instructions for installation, operation and maintenance
02/15 Labko GRP cesspools Instructions for installation, operation and maintenance Reliable solutions Wastewater treatment systems Contents 1 LABKO CESSPOOLS... 3 1.1 GENERAL... 3 1.2 IMPORTANT TO KNOW
More informationSPECIFICATIONS FOR THE INSTALLATION OF FIRE ALARM SYSTEMS, SPRINKLER SYSTEMS, AND MASTER BOXES IN THE POQUONNOCK BRIDGE FIRE DISTRICT
SPECIFICATIONS FOR THE INSTALLATION OF FIRE ALARM SYSTEMS, SPRINKLER SYSTEMS, AND MASTER BOXES IN THE POQUONNOCK BRIDGE FIRE DISTRICT The purpose of these specifications is to insure that there are minimum
More informationInstallation Instructions For Slider Casement Air Conditioners
Installation Instructions For Slider Casement Air Conditioners NOTE: These instructions describe installation in a typical wood framed window with a wood SLIDE-BY sash, or installation in a metal CASEMENT
More informationPLEASE NOTE. For more information concerning the history of these regulations, please see the Table of Regulations.
PLEASE NOTE This document, prepared by the Legislative Counsel Office, is an office consolidation of this regulation, current to August 1, 2013. It is intended for information and reference purposes only.
More informationAPPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE
APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE JURISDICTION OF ALBERTA TRANSPORTATION 1.0 Application Procedures 2.0
More informationSaferand easierinstallation
EN 85-07 Saferand easierinstallation IföSigninstallationsystem andifösignbuilt-incistern www.ifosanitar.com/sign Aneffectivesolution withmanyadvantages. Ifö Sign installation system makes life a little
More informationReference Guide for Obtaining Permits and Utility Services For New Construction
Reference Guide for Obtaining Permits and Utility Services For New Construction (Revised 04-2012) Table of Contents City Offices Telephone Numbers...1 Application for Utilities...2 Building Permits New
More informationSHALLOW UTILITIES JOINT PROVISIONING GUIDELINES SCOPE
AN INFORMATION GUIDE SCOPE PROJECT MANAGER Joint Provisioning Guidelines for Shallow Utility Services in Residential Areas where the Electric, Gas, Telephone & Cable TV facilities are Buried in the same
More informationCOLOR VIDEO DOOR PHONE CDV-71BE/D
COLOR VIDEO DOOR PHONE CDV-71BE/D 513-11, Sangdaewon-dong, Jungwon-gu, Seongnam-si, Gyeonggi-do, Korea Int l Business Dept. : Tel.; +82-31-7393-540~550 Fax.; +82-31-745-2133 Web site : www.commax.com Printed
More informationApplication for electricity connections Business premises. Electricity. Send your completed application form with supporting documentation to:
Electricity Thank you for considering for your electricity connections. We have put together these notes to help you fill out your and to ensure we receive all the correct information for your application
More informationAT&T Specifications Trenching Conduit Boxes and M anholes Aerial Entrance Masts Service Cabinets Bonding and Grounding
AT&T Specifications Trenching Conduit Boxes and M anholes Aerial Entrance Masts Service Cabinets Bonding and Grounding A Guide for California Developers of Com m ercial Property This guide consists of
More informationINSTALLATION GUIDELINES for SOLAR PHOTOVOLTAIC SYSTEMS 1
City of Cotati Building Division 201 W. Sierra Ave. Cotati, CA 94931 707 665-3637 Fax 792-4604 INSTALLATION GUIDELINES for SOLAR PHOTOVOLTAIC SYSTEMS 1 Any PV system on a new structures should be included
More informationDetector transparent with Color Inserts. FAA 500 TR P Trim Ring transparent with Color Inserts. FCA 500 / FCA 500 E Detector Bases
Detector Color Detector transparent with Color Inserts FAA 500 TR W Trim Ring FAA 500 TR P Trim Ring transparent with Color Inserts FAA 500 BB Ceiling Mount Back Box FCA 500 / FCA 500 E Detector Bases
More informationNew Electric Connection Application Packet Commercial and Industrial. City of Plummer P.O. Box B, Plummer, ID 83851 (208) 686-1641
New Electric Connection Application Packet Commercial and Industrial General Information: Maps: City of Plummer P.O. Box B, Plummer, ID 83851 (208) 686-1641 Please type or print plainly in ink. Applications
More informationBryant Woods Condominium Association. Antenna and Satellite Dish Installation Rules
Antenna and Satellite Dish Installation Rules Dear Residents: Enclosed please find the Antenna Rules that have been adopted by the Board. If you have any questions, comments or concerns relating to the
More informationARE YOU WIRING FOR A SMART HOME? Guidelines for homeowners on the wiring requirements for telecommunications and other wired services.
ARE YOU WIRING FOR A SMART HOME? Guidelines for homeowners on the wiring requirements for telecommunications and other wired services. INTRODUCTION Installing the right wiring when building or renovating
More informationACS-30-EU-EMDR-10-MOD
Multi-application heat tracing Control and Monitoring in commercial and residential buildings Roof & Gutter de-icing sensor module Technical Information Approvals Module IP rating Ambient operating temperature
More informationVehicle Restraint Installation Manual
Vehicle Restraint Installation Manual SHR-5000 9 Carriage SHR-5000 12 Carriage MADE IN U.S.A. This Manual Covers Restraints Built After Serial Numbers: 4487000001 and up PRINTED IN U.S.A. RITE-HITE PRINT
More informationSUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS
July 14, 2015 1.0 GENERAL BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS This work shall consist of furnishing all materials, equipment, labor, and incidentals necessary for conducting bi-directional
More information3 IN 1 BATHROOM HEATER
3 IN 1 BATHROOM HEATER MODEL NO.: A515 - SH MINI FUNCTION: HEATER, EXHAUST FAN AND LIGHT Dear customers, Thank you for selecting the AUPU 3 in 1 Bathroom Heater. Please read all instructions before commencing
More informationUndergrounding high voltage electricity transmission. The technical issues
Undergrounding high voltage electricity transmission The technical issues This is an interactive PDF document with clickable links from the contents to all sections and back and also to URL and email links.
More informationSolar Panel Installations
Solar Panel Installations Page 1 of 6 SINGLE-FAMILY RESIDENTIAL CHECKLIST City of Hayward Development Services Department Revised: 7-09-15 PERMIT REQUIREMENTS Permits are required for all solar panel installations.
More informationL_All_Vocatinal_Ed_Construction. Sector: Construction. Sr. No Specialisation Page No 1 Construction and Building Technology 02.
L_All_Vocatinal_Ed_Construction Sector: Construction Sr. No Specialisation Page No 1 Construction and Building Technology 02 1 P a g e 2 P a g e VOCATIONAL EDUCATIONAL QUALIFICATION FRAMEWORK (Sector -
More informationBuilding Industry Guide to Fibre Broadband
Building Industry Guide to Fibre Broadband Information for residential developers, architects, builders and electricians about ultra-fast broadband. Delivering new possibilities Enable s fibre broadband
More informationA guide to connecting to fibre optic networks for homeowners, architects, builders and developers.
A guide to connecting to fibre optic networks for homeowners, architects, builders and developers. Chorus is New Zealand s largest telecommunications utility company. We maintain and build the local access
More informationNELSON HEAT TRACING SYSTEMS
DESCRIPTION The HASK-P Hazardous Area Seal Kit provides the cable termination and explosion proof seal parts needed to make the power end electrical connections associated with Nelson Heat Tracing Systems
More information0095.05 June 30. 2011 July 18, 2014 1 of 7
Standard Number: Superseding: Effective Date: Page: 0095.05 June 30. 2011 July 18, 2014 1 of 7 Pole Attachments, Automated Meter Reading and Cellular Phone Antennas 1. Scope 2. Application This standard
More informationNTUA GUIDELINES FOR DESIGNING AN ELECTRICAL POWER DISTRIBUTION SYSTEM FOR NEW DEVELOPMENTS
NTUA GUIDELINES FOR DESIGNING AN ELECTRICAL POWER DISTRIBUTION SYSTEM FOR NEW DEVELOPMENTS These guidelines are intended to familiarize Developers regarding some issues that are important to get electric
More informationOPERATING INSTRUCTIONS
24 HOUR IMMERSION HEATER TIME CONTROLLER Cat. No TS900B OPERATING INSTRUCTIONS TS900B 24 Hour Immersion Heater Time Controller 24 hour programme ring Self-cancelling and Override switch Setting pins Time
More informationBeacon Hill Sewer District Standard Specifications
Beacon Hill Sewer District Standard Specifications Residential Gravity Side Sewer Including Design Criteria and Standard Construction Drawings Residential Gravity Side Sewer Design Criteria 1. Provisions
More informationCable usage designation. Number of ducts required Number of spare ducts to be provided < 3 4-10 > 11
EXTERNAL SERVICE DUCTS AND CABLE TROUGHING SECTION 190 Service ducts routes generally DUCTS 1 Except where shown otherwise on the Contract Drawings, the number, type and size of ducts shall be determined
More informationTechnical Information
Technical Information This section of the catalogue provides technical information that will help specify, install and maintain Surelock McGill devices and components. The topics are listed below: Blast
More information39HQ Airovision Air Handling Units
39HQ Airovision Air Handling Units Mounting instructions CONTENTS 1 - TRANSPORT AND LIFTING INSTRUCTIONS... 3 1.1 - General... 3 1.2 - Transport and storage... 3 1.3 - Roof edge protection during transport
More informationBUILDING OVER OR NEAR WATER & SEWER MAINS POLICY
MURRAY SHIRE COUNCIL BUILDING OVER OR NEAR WATER & SEWER MAINS POLICY ADOPTED: 1 May 2012 1 BUILDING OVER OR NEAR WATER AND SEWER MAINS POLICY CONTENTS 1. Objective... 2 2. Requirements for Building Near
More informationInterface between Eircom Network and Additional Telephone Equipment
Interface between Eircom Network and Additional Telephone Equipment External Terminating Unit The ETU (small cabinet, 230mm x 150mm x 150mm) is fitted by the customer on an exterior wall, at a point approx
More informationIRRIGATION PUMPING Table of Contents - Section 900
IRRIGATION PUMPING Table of Contents - Section 900 PARAGRAPH 900.1 GENERAL 1 900.2 METERING REQUIREMENTS 1 900.3 CUSTOMER S CONTROL EQUIPMENT 2 900.4 SERVICE CONDUCTOR REQUIREMENTS 2 900.5 RECOMMENDATIONS
More informationEARTHING AND BONDING AT SECONDARY SUBSTATIONS
DISTRIBUTION CONSTRUCTION MANUAL SECTION 4 - SUBSTATIONS ISSUE B SEPT 1996 4.4.4 EARTHING AND BONDING AT SECONDARY SUBSTATIONS 1 SCOPE This section of the Distribution Construction Manual lays down the
More informationInnovative DOOR STATION Solutions
Innovative DOOR STATION Solutions When a visitor arrives at your front door or gate we ring... Your mobile when you are out Your normal telephones in your home Your PABX system in your office Communicating
More informationEZ-Steer Assisted Steering System
EZ-Steer Assisted Steering System Installation Instructions Platform Kit P/N 53059-54 Case IH CVX 1135 CVX 1145 CVX 1155 CVX 1170 CVX 1190 CVX 1195 CVX 135 CVX 145 CVX 155 CVX 175 CVX 195 New Holland TVT
More informationPREASSEMBLED ELEMENTS FOR LIFTING AND SLIDING DOORS
SYSTEM COMPONENTS PREASSEMBLED ELEMENTS FOR FIFTING AND SLIDING DOORS s r ood gn i d i l s dna gn i t f i f r o f s t neme l e de l bme s s ae r P PREASSEMBLED ELEMENTS FOR LIFTING AND SLIDING DOORS These
More informationAMS 120. EFT Guest Card Terminal & Refund unit
AMS 120 EFT Guest Card Terminal & Refund unit ACCOUNT MANAGEMENT STATIONS Wall mounted kiosk offering Visitor card purchase and refund Card deposit EFT purchase, refund and loading Full statement facilities
More informationInstallation Guide. DEVIreg 530. Electronic Thermostat. www.devi.com
Installation Guide DEVIreg 530 Electronic Thermostat www.devi.com The English language is used for the original instructions. Other languages are a translation of the original instructions. (Directive
More informationWhitepaper. Modular Substation Cable Termination Design. Author: Allan Bozek P.Eng, MBA, EngWorks Inc, Calgary, Canada
Whitepaper Modular Substation Cable Termination Design Author: Allan Bozek P.Eng, MBA, EngWorks Inc, Calgary, Canada Abstract The methods for cable penetrations into modular industrial substations are
More informationNetworks. ESB Networks Ltd Basis of Charges for Connection to the Distribution System. Commercial and Customer Asset Management ESB Networks Ltd.
Networks ESB Networks Ltd Basis of Charges for Connection to the Distribution System Revision Date: 14/01/20010 Revision No.: 1 Document No: DOC-10129-AXQ Issued by: ESB Networks Ltd Approved by : CER
More information2013 Wireless Video Intercom INSTALLATION GUIDE
2013 Wireless Video Intercom INSTALLATION GUIDE INDEX System configuration and wiring VL-SWD501 System Component.. 4 VL-SWD501EX wiring schematic diagram VL-SWD501EX wiring type and length... 5.... 6 Door
More information2014 NEC Guide Lines for Home Owner Doing Electrical Work on their Property
2014 NEC Guide Lines for Home Owner Doing Electrical Work on their Property A brief summary of the most used code references for residential wiring State of Idaho Division of Building Safety Electrical
More informationINFRASTRUCTURE, FLOOD PROTECTION AND REMEDIATION. Infrastructure Flood Protection Remediation Policies
INFRASTRUCTURE, FLOOD PROTECTION AND REMEDIATION Infrastructure Flood Protection Remediation Policies DRAFT POOLBEG PLANNING SCHEME 196 FIGURE 9.1: UTILITIES WAYLEAVES Electricity Cables 8m Wayleave for
More informationBathroom Cabinet. Installation & User Guide. Illuminated Mirrors. www.illuminated-mirrors.uk.com
Illuminated Mirrors The UK s Largest LED Mirror Supplier to Trade and Retail Installation & User Guide Bathroom Cabinet www.illuminated-mirrors.uk.com Bathroom Cabinet Installation & User Guide Thank you
More informationElectrical Wiring Technical Bulletin
Electrical Wiring Technical Bulletin Overview In general, SIP construction is easier and more cost effective when things are planned and thought out before the panels are manufactured. This process will
More informationGuide to working on Public Sewers
Guide to working on Public Sewers affected by Building Works Introduction Severn Trent Water Ltd requires the work to be done in order to protect the public sewer and minimise the risk of us having to
More informationSecurity. Alarm central unit. Ref.-No. KNX Alarm central unit EAM 4000
Security Alarm Central Unit 3 4 Technical KNX Alarm central unit EAM 4000 ETS-product family: Alarm system Product type: Alarm central unit The alarm central unit is a modern alarm system using the KNX
More informationUser Manual. Video Doorphone CDV-1020AQ
User Manual Video Doorphone CDV-1020AQ 513-11, Sangdaewon-dong, Jungwon-gu, Seongnam-si, Gyeonggi-do, Korea Int l Business Dept. Tel. : +82-31-7393-540~550 Fax. : +82-31-745-2133 Web site : www.commax.com
More information6mm Two Door Offset Quadrant
Installation Guide 6mm Two Door Offset Quadrant 226MBJ 0914RN Offset Quadrant 226MBJ.indd 1 07/08/2015 14:03 Cu w Before you Start Please read this Installation Guide fully. Although these instructions
More informationRack Installation Instructions
Rack Installation Instructions Guidelines This publication provides information about how to install your server into a standard rack cabinet using the rail kit shipped with your server. If you no longer
More informationNEW ZEALAND ELECTRICAL CODE OF PRACTICE. for ELECTRICAL SAFE DISTANCES
NZECP 34:2001 ISSN 0114-0663 NEW ZEALAND ELECTRICAL CODE OF PRACTICE for ELECTRICAL SAFE DISTANCES NZECP 34:2001 NEW ZEALAND ELECTRICAL CODE OF PRACTICE for ELECTRICAL SAFE DISTANCES Issued by: Manager,
More informationFIRE ALARM SYSTEM. A. Shop drawings shall be submitted as follows: 1. Manufacturer's published literature. for aspproval.
Polk School District Specifications for the New Fire Alarm in the Existing Building Eastside Elementary School FIRE ALARM SYSTEM 1.01 SUBMITTALS A. Shop drawings shall be submitted as follows: 1. Manufacturer's
More informationElectrical Safety Products
Electrical Safety Products Trelleborg Electrical Safety Products A safe working environment is important in all industries, but in the electrical generation and supply industry, it is paramount. Trelleborg
More informationCHAPTER VIII LINE PLANT SYSTEM COMMUNICATION THROUGH RE CABLE
CHAPTER VIII LINE PLANT SYSTEM COMMUNICATION THROUGH RE CABLE 8.1 SYSTEM 8.1.1 Armoured, screened underground cables are used for control communication in electrified areas to limit induction effect. 8.2
More informationAVOIDANCE OF ELECTRICAL HAZARDS WHEN WORKING NEAR OVERHEAD ELECTRIC LINES
overhead 23/11/04 2:28 PM Page 1 AVOIDANCE OF ELECTRICAL HAZARDS WHEN WORKING NEAR OVERHEAD ELECTRIC LINES ESB Code 9803203 overhead 23/11/04 2:28 PM Page 2 overhead 23/11/04 2:28 PM Page 3 Page 1 of 20
More informationHow To Read A Pipe From A Sensor
Liquid Level Sensor Installation on pipes. Sensing by means electrostatic capacity and is not influenced by the color of the pipe or liquid. Available in 8 to mm dia. and to mm dia. models to enable sensing
More informationNEW RANGE OF CABINETS DRIVIATM. Innovation at your service. THE GLOBAL SPECIALIST in electrical and digital building infrastructures
NEW RANGE OF CABINETS DRIVIATM Innovation at your service THE GLOBAL SPECIALIST in electrical and digital building infrastructures Drivia true innovation The new electrical panel for the residential and
More informationDepending on which elastic support you have you can secure the V2 power unit to the following seat bracket tubes: EXTERNAL DIAMETER 27.
ASSEMBLY 1 - EPS V2 POWER UNIT (SOLUTION 5) 1.1 - POSITIONING INSIDE THE SEAT TUBE WITH ELASTIC SUPPORT IN THE SEAT BRACKET TUBE Depending on which elastic support you have you can secure the V2 power
More informationEXTeRUS. EXTeRUS - With patented design, able to join technology. and quality of materials with a charming shape. Unique
EXTeR US G L A S S - With patented design, able to join technology and quality of materials with a charming shape. Unique thanks to its outstanding loading capability with 150 kg maximum weight and height
More informationPlease check with your local inspection authority for any additional requirements before installation.
Specifications for Residential Overhead Electric Service Installation This brochure addresses most typical residential overhead service installations. Variances for the following specifications must be
More informationCity of Fort Smith Building Permit Process Frequently Asked Questions
Question: W ho must obtain a building permit? City of Fort Smith Building Permit Process Frequently Asked Questions Answer: This answer is the same for residential or commercial building. Any owner or
More informationLEAKING SUPPLY PIPE? YOUR GUIDE TO WATER SUPPLY LEAKS. You were out when we visited today.
LEAKING SUPPLY PIPE? YOUR GUIDE TO WATER SUPPLY LEAKS You were out when we visited today. Check the back of this leaflet to find out why we called and what happens next. NW FSM3-1/15 INTRODUCTION Helping
More information50 TO 60 INSTALLATION INSTRUCTIONS v1.0
50 TO 60 INSTALLATION INSTRUCTIONS v1.0 PLEASE READ Thank you for purchasing The TV Shield. Please read the following, before starting the installation process. UYou will need to unscrew the ten (10) black
More informationALARM SYSTEM INSTALLATION GUIDE
ALARM SYSTEM INSTALLATION GUIDE Congratulations on the purchase of your Egardia alarm system. Egardia's website www.egardia.com Customer services Please visit www.egardia.com if you would like further
More informationStep by step guide to installing your own Ku Band satellite dish
Step by step guide to installing your own Ku Band satellite dish If you don't feel comfortable installing your own system, your local TV Aerial or Handyman can easily follow these helpful guidelines for
More informationBUILT-IN DISHWASHER INSTALLATION INSTRUCTIONS
BUILT-IN DISHWASHER INSTALLATION INSTRUCTIONS PLEASE READ COMPLETE INSTRUCTIONS BEFORE YOU BEGIN LEAVE INSTALLATION INSTRUCTIONS AND USER'S GUIDE WITH OWNER ALL ELECTRIC WIRING AND PLUMBING MUST BE DONE
More informationUnderground Commercial Electric Service
Underground Commercial Electric Service SCANA Corporation 2013 Revised: June 2013 Table of Contents SECTION PAGE I. Specification and Requirements 2 A. General B. Definition of Terms C. Company and Developer
More informationAUDIO VIDEO INTERCOM SYSTEMS SECURITY & SAFETY AT YOUR FINGER TIPS AUDIO VIDEO INTERCOM SYSTEMS
AUDIO VIDEO INTERCOM SYSTEMS SECURITY & SAFETY AT YOUR FINGER TIPS AUDIO VIDEO INTERCOM SYSTEMS 1 DORANI VIDEO INTERCOM - 2 WIRE SERIES 7 TFT MONITOR TECHNICAL SPECIFICATIONS 7 Colour TFT screen 480 x
More information