Parking Infrastructure Development. in Santariskes Medical Campus (SMC), VILNIUS, LITHUANIA

Size: px
Start display at page:

Download "Parking Infrastructure Development. in Santariskes Medical Campus (SMC), VILNIUS, LITHUANIA"

Transcription

1 Parking Infrastructure Development in Santariskes Medical Campus (SMC), VILNIUS, LITHUANIA

2 Santariskes Medical Campus (SMC) main medical campus in lithuania 64 ha 6 public / 2 private medical institutions employees HOSPITAL BEDS PATIENTS & 1 M visitors ANNUALY HEALTH CARE / HOSPITAL PUBLIC RESEARCH INSTITUTION OTHER 2

3 The current situation in SMC's Parking infrastructure Fails to ensure full accessibility for health services Insufficient, incoherent and inefficient Non-compliant with regulatory requirements Overloaded and not safe for users Encourages illegal parking 3

4 EXISTING PARKING SPACE AND FEES PARKING SPACES IN PARKING LOTS 42 % 12 % 11 % 24 % Employees with permits VISItORS VISITORS Employees with permits paid 40 LTL/montH FREE Tolled 2LTL/HOUR FREE 240 ON STREET 11 % ON STREET tolled 2 LTL/hour Most of this car parking space has to be removed due to regulatory requirements or for SMC development reasons. SMC is designated as a yellow parking toll zone by Vilnius city municipality (2Lt/h). This is the only tolled parking area outside Vilnius city centre (1Lt/h to 6Lt/h). There are 40 parking spaces in 2 private parking lots which are not included in the project. 4

5 Future of the SMC Expected development of THE SMC Today In 1 to 5 years In 5 to 25 years medical institutions Number of employees Number of patients & visitors annualy M M M Estimated DEMAND FOR parking SPACES

6 Project goals Implementing an efficient, integrated system for SMC parking management Designing and building new parking infrastructure Implementing an electronic parking management system Reconstructing existing parking lots Improvement of the parking service quality Operation and maintenance of all parking infrastructure for 25 years 6

7 Project HighlighTs Project goal Project owner Development of new parking infrastructure in SMC Ministry of Health of Lithuania Partnership Type Concession Contract Type Design, Build, Finance, Operate, Transfer Project Duration 25 years Investment estimated 16.7 M EUR (VAT excl.) NUMBER OF PARKING spaces CONSTRUCTED Obligatory: min 937 new spaces reconstruction of the existing spaces Optional: up to new spaces Number of Parking spaces Operated from 937 to new spaces up to existing spaces 7

8 SMC Parking infrastructure DEVELOPMENT SCHEME maximum NEW PARKING SPACES 937 MIN to replace removed or reallocated parking space for employees and visitors MIN to replace removed existing parking space plus additional spaces if needed TODAY 1st DEVELOPMENT STAGE (Short Run) 2ND DEVELOPMENT STAGE (Long Run) Existing PARKING SPACES in parking lots 240 on street for employees for visitors max on demand: at least 446 spaces to be removed to allow SMC developement at least 30 allocated to disabled or special purpose vehicle parking or dropoff zones 866 max in 1-2 years: at least 537 in parking lots and 240 on street to be removed at least 160 allocated to disabled or special purpose vehicle parking or dropoff zones 8

9 PARKING SPACE AND DEVELOPMENT SCHEME EXISTING PARKING SPACE AND AVAILABLE LAND PLOTS SUGGESTED FOR CONSTRUCTION PARKING SPACE TO BE REMOVED OR REALLOCATED DURING 1 ST DEVELOPMENT STAGE (Short Run) PARKING SPACE TO BE REMOVED OR REALLOCATED DURING 2 ND DEVELOPMENT STAGE (Long Run) BUILDINGS 9

10 investor's responsibilities and pricing model Investor's responsibilities Develop the business plan Raise financing Create new infrastructure Set pricing and receive income PRICING MODEL Investor submits the pricing model during the tender procedures Different pricing models should be developed for employees and visitors The priority is low prices for SMC employees, and then for visitors 10

11 Project TIMELINE Feasibility study Selection of the project consultants Market consultation Contract award Q Q Q Q Q Q Q Q Q Project aproved by Ministry of Finance PPP commission Government Tender documentation preparation Public procurement procedures Start of the project implementation 11

12 PREQualification CRITERIA CRITERIA Economic and Financial THE CANDIDATE SHALL MEET Average turnover of construction and installation works (3 yrs) Average turnover of non-residential real estate management services (3 yrs) Critical liquidity ratio Ability to raise the project funding Minimum value 4.65M EUR 0.29M EUR 0,5 4.65M EUR Technical and Professional License to carry out design and construct buildings At least 1 construction contract of a similar size (5 yrs) At least 1 construction contract implemented for new parking facilities (5 yrs) 3 yrs of experience in parking management experience in multistorey parking management experience in large-scale parking management experience in paid parking management Competent experts: project manager, building construction managers, parking service specialist, traffic management specialist Specialised or sufficient 4.65M EUR 500 spaces spaces 1 multistorey parking 500 spaces in 1 lot 1 paid parking lot 12

13 Most Economically Advantageous Tender PRICE 60 % 20% Monthly permit price for employees 40% Hourly price for visitors 40% Income sharing threshold Income is shared by giving 75% of income over the threshold to the authority QUALITY 40 % 30% 20% Newly built spaces Reconstructed existing spaces 40% 10% Technical aspects Traffic management solutions Functionality Parking payment system Environment solutions Project implementation schedule 13

14 INDICATIVE SCHEDULE OF THE Selection process Concession competition notice PQQ PQQ Assessment 2 months 1 month Preliminary Solution Preparation 2-3 months Contract award Preliminary Solution Assessment BINDING Solution Preparation BINDING solution Assessment Negotiation Final Arrangements and Financial Close 1 month 1-2 months 1 month 1 month 3-4 months 14

15 PARTNERSHIP SCHEME USER S OF THE INFRASTRUCTURE Makes payments for the contract management PROJECT OWNER Ministry of Health Assigns parking infrastructure BIDDER INVESTOR CONCESSION CONTRACT RECEIVES INCOME PROJECT IMPLEMENTATION SPECIAL PURPOSE VEHICLE Ltd. CONCESSIONAIRE PROVIDES SERVICES PROJECT FUNDING PRIVATE INVESTORS/ SHAREHOLDERS COMMERCIAL BANKS IFIs MaNAGES CONTRACT INVESTMENT FUNDS Assigns contract management rights AND Makes payments for the contract management PROJECT ADMINISTRATOR 15

16 Expectations Infrastructure for users Functional and comfortable to use, and providing easy access, parking management systems, quick parking solutions and drop-off zones for patients. Low parking prices Low parking prices for employees and visitors is a priority. Free parking is required for the disabled, for ambulances and other special purpose vehicles, and for short-stay use (15 minutes or less). Lower operating cost Environmentally friendly technology and operational efficiency. Tomorrow's solutions Proposition of innovative solutions where possible. Investment vs. total cost of ownership Possibility for bigger capital investment if operating and maintenance costs can be reduced. The city s identity vs. design Optimal technical solution incorporated in Vilnius City's architectural and visual identity. Effective partnership Establishment of relationships, communication routes and systems, active support and enhancement of these throughout the life of the project so that a sustainable partnership of trust and respect is maintained. 16

17 CONTACTS JUSTINAS IVAŠKA Project ManageR justinas.ivaska@santa.lt Irmantas Butkauskas INVeSTORS RELATIONS irmantas.butkauskas@investlithuania.com Additional information on procurement:

Financing PPPs: Project Finance June 2006

Financing PPPs: Project Finance June 2006 Financing PPPs: Project Finance June 2006 Index Section I. Section II. Section III. Project Finance Spanish Market Advantages Risk Matrix P. 2 Section I Project Finance Project Finance Definition Definition:

More information

Preliminary Draft JOB DESCRIPTIONS AND QUALIFICATIONS OF KEY PERSONNEL. XXXXX PPP Unit

Preliminary Draft JOB DESCRIPTIONS AND QUALIFICATIONS OF KEY PERSONNEL. XXXXX PPP Unit Preliminary Draft JOB DESCRIPTIONS AND QUALIFICATIONS OF KEY PERSONNEL XXXXX PPP Unit Chief Executive Officer Job Description: The CEO is tasked with the establishment of a PPP Unit for the Government

More information

Law of Mongolia on Concessions

Law of Mongolia on Concessions Economic Policy Reform and Competitiveness Project April 2005 Ulaanbaatar, Mongolia This publication was produced for review by the United States Agency for International Development The views expressed

More information

Invitation for Expression of Interest

Invitation for Expression of Interest Invitation for Expression of Interest Consulting Services for the Transaction Advisory Services for involvement of operator being able to manage based on a lease contract in areas serviced by Yerevan Water

More information

Department of the Environment and Local Government. Project Management. Public Private Partnership Guidance Note 7. 14 April 2000

Department of the Environment and Local Government. Project Management. Public Private Partnership Guidance Note 7. 14 April 2000 Project Management Project Management Public Private Partnership Guidance Note 7 14 April 2000 Guidance Note 7 14 April 2000 Project Management Contents Section Page I INTRODUCTION...1 SCOPE AND PURPOSE

More information

FLOW CHART OF PROCESSES FOR OBTAINING PERMITS IN SISAK MOSLAVINA COUNTY

FLOW CHART OF PROCESSES FOR OBTAINING PERMITS IN SISAK MOSLAVINA COUNTY FLOW CHART OF PROCESSES FOR OBTAINING PERMITS IN SISAK MOSLAVINA COUNTY SI-MO-RA d.o.o. S. i A. Radića 8b, Sisak simora@simora.hr www.simora.hr Sisak projekti d.o.o. Rimska 26, Sisak www.sisak-projekti.hr

More information

Developing by Public Private Partnership (PPP): Meeting infrastructure needs successfully.

Developing by Public Private Partnership (PPP): Meeting infrastructure needs successfully. Developing by Public Private Partnership (PPP): Meeting infrastructure needs successfully. Vicky D. Kefala Head, Investments & Development Projects Consolidated Contractors Company (CCC) MBA Finance, BA

More information

B U I L D I N G P A R T N E R S H I P S F O R E N E R G Y S E C U R I T Y www.inogate.org

B U I L D I N G P A R T N E R S H I P S F O R E N E R G Y S E C U R I T Y www.inogate.org "INOGATE Technical Secretariat & Integrated Programme in support of the Baku Initiative and the Eastern Partnership energy objectives" Project B U I L D I N G P A R T N E R S H I P S F O R E N E R G Y

More information

arrangements typified by joint working between the public and private sectors covering all types of collaboration across the private-public sector

arrangements typified by joint working between the public and private sectors covering all types of collaboration across the private-public sector 20//204 PUBLIC PARTNERSHIP PRIVATE on Institutional Arrangement and Policy Implications Case Studies from the Republic of Korea November 8, 204 Seung-Jin Baek Economic Development Division UN ECLAC What

More information

Investment incentives in Bulgaria

Investment incentives in Bulgaria Investment incentives in Bulgaria Types of incentives under the current Bulgarian legislation Tax incentives Incentives under the Investment Promotion Act (IPA) Employment incentives (training and job

More information

How To Improve The Economic And Social Prospects Of The Euro Zone

How To Improve The Economic And Social Prospects Of The Euro Zone Twelve levers for the development of the Single Market Developments on public procurement Ms Kristin SCHREIBER Deputy Head of cabinet of Commissioner Barnier NB: The information contained in this presentation

More information

PROJECT PREPARATORY TECHNICAL ASSISTANCE

PROJECT PREPARATORY TECHNICAL ASSISTANCE A. Justification PROJECT PREPARATORY TECHNICAL ASSISTANCE 1. The Government of Azerbaijan, the Ministry of Transport and Baku Metro Company requested ADB to help improving its urban transport system and

More information

Developing a Public-Private Partnership Framework: Policies and PPP Units

Developing a Public-Private Partnership Framework: Policies and PPP Units Note 4 May 2012 Developing a Public-Private Partnership Framework: Policies and PPP Units This note is the fourth in a series of notes on developing a comprehensive policy, legal, and institution framework

More information

PRAGUE AIRPORT KLADNO RAILWAY LINK

PRAGUE AIRPORT KLADNO RAILWAY LINK PRAGUE AIRPORT KLADNO RAILWAY LINK Investor: SŽDC s.o. (Railway Infrastructure Administration) Project manager: METROPROJEKT Praha a.s. (some parts in consortium with SUDOP Praha a.s.) PRAGUE AIRPORT KLADNO

More information

UNECE PPP Healthcare Standard

UNECE PPP Healthcare Standard INTERNATIONAL SPECIALIST CENTRE OF EXCELLENCE ON PPPs IN HEALTH MANILA, PHILIPPINES UNECE PPP Healthcare Standard Questions on lessons learned in the development of Public-Private Partnership ( PPP ) programmes

More information

Tender specifications. Framework contract for Redundant Internet access. Open call for tender EEA/OSE/09/006

Tender specifications. Framework contract for Redundant Internet access. Open call for tender EEA/OSE/09/006 Annex I Tender specifications Framework contract for Redundant Internet access Open call for tender EEA/OSE/09/006 1. Purpose The purpose of this call is to award a framework contract for a period of six

More information

HOW TO HIRE AN ARCHITECT

HOW TO HIRE AN ARCHITECT HOW TO HIRE AN ARCHITECT Welcome. We prepared this guide after seeing so many people struggle with understanding the design and construction process. This process can seem like a complex and frightening

More information

Public Sector Comparator for Highway PPP Projects. Henry Kerali Lead Transport Specialist

Public Sector Comparator for Highway PPP Projects. Henry Kerali Lead Transport Specialist Public Sector Comparator for Highway PPP Projects Henry Kerali Lead Transport Specialist Presentation Outline Purpose and Definition of PSC Basis for comparison between Public v. Private Valuing risk Characteristics

More information

HOW TO HIRE AN ARCHITECT. office. Level 3, 272 Parnell Rd Auckland. web. www.myarchitects.co.nz email.home@myarchitects.co.nz phone.

HOW TO HIRE AN ARCHITECT. office. Level 3, 272 Parnell Rd Auckland. web. www.myarchitects.co.nz email.home@myarchitects.co.nz phone. HOW TO HIRE AN ARCHITECT introduction Nothing is more exciting than starting a building project, and nothing will affect the success of your project more than hiring the right architect. An architect not

More information

NETLIPSE NETWORK MEETING 27-28.5.2013 Seppo Mäkinen Finnish Transport Agency 27.5.2013

NETLIPSE NETWORK MEETING 27-28.5.2013 Seppo Mäkinen Finnish Transport Agency 27.5.2013 NETLIPSE NETWORK MEETING 27-28.5.2013 Seppo Mäkinen Finnish Transport Agency 27.5.2013 Mainroad 4 Järvenpää Lahti PPP Project 1997 2012 FINLAND 27.5.2013 27.5.2013 Seppo Mäkinen Mainroad 4 Järvenpää -

More information

Energy Efficiency in Public Administration (Eco.AP): Advantages of the ESCO model

Energy Efficiency in Public Administration (Eco.AP): Advantages of the ESCO model Energy Efficiency in Public Administration (Eco.AP): Advantages of the ESCO model Napoli 10 th of April 2015 23 de Março de 2012 Description Eco.AP Program Eco.AP Program Objectives: Promote the efficient

More information

REPORT FEHMARNBELT FIXED LINK. Financial Analysis - February 2003. Main Results. March 2003. Prepared by Sund & Bælt / Femer Bælt

REPORT FEHMARNBELT FIXED LINK. Financial Analysis - February 2003. Main Results. March 2003. Prepared by Sund & Bælt / Femer Bælt REPORT FEHMARNBELT FIXED LINK Financial Analysis - February 23 Main Results Prepared by Sund & Bælt / Femer Bælt March 23 A division of Sund & Bælt Holding A/S Vester Søgade 1 DK-161 Copenhagen V Tel.

More information

BMT Tax Depreciation Estimate

BMT Tax Depreciation Estimate Estimate House & Land Packages TOWNSVILLE, QLD 4810 181 Mulgrave Road PO Box 1720 t 07 4031 5699 f 07 4031 5799 e info@bmtqs.com.au w www.bmtqs.com.au Australia Wide Service ABN 44 115 282 392 18 March,

More information

''The construction of the Public Urban Centre in Sikorskiego St. and Legionów Ave. in Łomża

''The construction of the Public Urban Centre in Sikorskiego St. and Legionów Ave. in Łomża ''The construction of the Public Urban Centre 12 10 8 Kolumna 1 Kolumna 2 Kolumna 3 6 4 2 0 Wiersz 1 Wiersz 2 Wiersz 3 Wiersz 4 The location of Łomża The city is located in the north-east of Poland in

More information

Estevan Student and Market Rental Housing Project. Assessment Report

Estevan Student and Market Rental Housing Project. Assessment Report Estevan Student and Market Rental Housing Project Assessment Report This Estevan Student and Market Rental Housing Project Assessment has been prepared by Preferred Choice (DJ Leier Enterprises Ltd.) with

More information

Version Author Revisions Made Date 1.6 David Sharkey Executive Board 27 March 2012 2.0 Robin Hunt

Version Author Revisions Made Date 1.6 David Sharkey Executive Board 27 March 2012 2.0 Robin Hunt Purchasing Policy Originator name: Section / Dept: Implementation date: Date of next review: Related policies: Policy history: Robin Hunt Procurement 1 December 2013 Finance Regulations, Purchase Card

More information

Certificate in Construction Project Management

Certificate in Construction Project Management Certificate in Construction Project Management Duration: 6 Months Distance Learning Programme Language: English RICS Member: 895.00 + VAT Non RICS Member 995.00 + VAT Course Summary As a result of the

More information

Implementation of qualified electronic signatures in the process of creating project and technical documentation. Austria. January 28 th 2016

Implementation of qualified electronic signatures in the process of creating project and technical documentation. Austria. January 28 th 2016 Implementation of qualified electronic signatures in the process of creating project and technical documentation The experiences of member countries of the ECEC Austria Dr. Herbert Döller January 28 th

More information

PPP Practioner s Notes

PPP Practioner s Notes PPP Practioner s Notes Capacity Challenges in PPP Program and Contract Management Mariana Abrantes de Sousa PPP DAYS 2012 UNECE Geneva Key issues in PPP program and contract management Functions of the

More information

Ministry of Information and Communication Technology EXPRESSION OF INTEREST

Ministry of Information and Communication Technology EXPRESSION OF INTEREST EXPRESSION OF INTEREST Consultancy Services for SubmarineFibre Optic Connectivity in Rodrigues (Authorised under Section 24(2) of the Public Procurement Act 2006) Reference No. : MICT/Q3/2012/EOI 1.0 Introduction

More information

Pre-Planning Application Advice

Pre-Planning Application Advice Pre-Planning Application Advice Development Management 1 Why seek pre-application advice? It can be very helpful to seek our advice about your planning proposals before submitting your actual application.

More information

Vivek Aggarwal Managing Director, MP Road Dev. Corporation Bhopal (M.P.), INDIA

Vivek Aggarwal Managing Director, MP Road Dev. Corporation Bhopal (M.P.), INDIA Vivek Aggarwal Managing Director, MP Road Dev. Corporation Bhopal (M.P.), INDIA Madhya Pradesh Road Development Corporation MP Road Development Corporation Ltd. incorporated in July 2004. Chief Minister

More information

RECOMMENDATIONS ON BUSINESS PLAN PREPARATION

RECOMMENDATIONS ON BUSINESS PLAN PREPARATION RECOMMENDATIONS ON BUSINESS PLAN PREPARATION 1. General provisions Business plan must contain: name of the investment project, as well description of its essence and feasibility; substantiation of the

More information

Release: 1. CPCCBS6010 Conduct and report on building surveying audits of residential buildings up to three storeys

Release: 1. CPCCBS6010 Conduct and report on building surveying audits of residential buildings up to three storeys Release: 1 CPCCBS6010 Conduct and report on building surveying audits of residential buildings up to three storeys CPCCBS6010 Conduct and report on building surveying audits of residential buildings up

More information

FOR USE WITH PPP PROJECTS 1 SAMPLE GUIDELINES FOR PRE-QUALIFICATION AND COMPETITIVE BIDDING PROCESS 2

FOR USE WITH PPP PROJECTS 1 SAMPLE GUIDELINES FOR PRE-QUALIFICATION AND COMPETITIVE BIDDING PROCESS 2 FOR USE WITH PPP PROJECTS 1 SAMPLE GUIDELINES FOR PRE-QUALIFICATION AND COMPETITIVE BIDDING PROCESS 2 1. PRE-QUALIFICATION 1.1 The requirements for pre-qualifications will be reasonable and efficient and

More information

Law No. 67 for the year 2010

Law No. 67 for the year 2010 Disclaimer This English translation of the Law No. 67 for the year 2010 has been reviewed by Zulficar & Partners Law Firm and Trowers & Hamlins in association with Nour Law Office. Neither The Ministry

More information

SAMPLE TERMS OF REFERENCE FOR ELECTRICITY SECTOR PRIVATIZATION TRANSACTION ADVISORY SERVICES

SAMPLE TERMS OF REFERENCE FOR ELECTRICITY SECTOR PRIVATIZATION TRANSACTION ADVISORY SERVICES SAMPLE TERMS OF REFERENCE FOR ELECTRICITY SECTOR PRIVATIZATION TRANSACTION ADVISORY SERVICES Table of Contents 1st. INTRODUCTION... 3 2nd. ELECTRICITY SECTOR BACKGROUND. 4 3rd. SCOPE OF WORK. 6 PHASE :

More information

Public Sector Procurement RIBA Position Paper 8 April 2011

Public Sector Procurement RIBA Position Paper 8 April 2011 Public Sector Procurement RIBA Position Paper 8 April 2011 Background: This position paper on access to public sector procurement and public tendering processes for architects services has been endorsed

More information

Gebze Izmir Motorway & Izmit Bay Crossing Project

Gebze Izmir Motorway & Izmit Bay Crossing Project Gebze Izmir Motorway & Izmit Bay Crossing Project F.Mehmet Coşan CFO Haluk BÜYÜKBAŞ Secretary General, TCA Gebze Orhangazi Izmir Project is the landmark transaction for the infrastructure sector in Turkey

More information

Information about Changes of JSC Citadele banka Services Pricelist from January 1, 2015

Information about Changes of JSC Citadele banka Services Pricelist from January 1, 2015 Information about Changes of JSC Citadele banka Services Pricelist from January 1, 2015 Dear customers, Hereby we inform about the following fee changes effective from January 1, 2015, applicable for customers,

More information

Buying and selling an unincorporated business

Buying and selling an unincorporated business Introduction This section covers the main tax issues that arise when buying or selling a business owned by a sole trader, a partnership or a company. The tax consequences differ, depending on whether the

More information

Minerals production in Hungary 1990-2006 (Mtons) - source: Hungarian Office for Mining and Geology

Minerals production in Hungary 1990-2006 (Mtons) - source: Hungarian Office for Mining and Geology MINING In the last twenty years the mining industry experienced dramatic changes. In the fossil fuel and metallic ores sector the big state-owned mining companies collapsed and/or transformed into private

More information

Asset Management Policy for Major PFI Projects

Asset Management Policy for Major PFI Projects Asset Management Policy for Major PFI Projects Agenda Asset Management Drivers Typical AM positioning in Motorway PFI Asset management Strategy Works Planning and Scheduling Innovation & Risk Mitigation

More information

CLIENT S GUIDE 1. WHERE TO START 1. 2. WHAT TO CONSIDER 3. ANSWER THE WHYS 4. NEEDS & OPTIONS REVIEW HOW TO HIRE AN ARCHITECT

CLIENT S GUIDE 1. WHERE TO START 1. 2. WHAT TO CONSIDER 3. ANSWER THE WHYS 4. NEEDS & OPTIONS REVIEW HOW TO HIRE AN ARCHITECT CLIENT S GUIDE 1. WHERE TO START 1. 2. WHAT TO CONSIDER 3. ANSWER THE WHYS 4. NEEDS & OPTIONS REVIEW 2. HOW TO HIRE AN ARCHITECT Welcome. We prepared this guide after seeing so many people struggle with

More information

REQUEST FOR PROPOSAL WAYFINDING AND SIGNAGE CONSULTANT

REQUEST FOR PROPOSAL WAYFINDING AND SIGNAGE CONSULTANT REQUEST FOR PROPOSAL WAYFINDING AND SIGNAGE CONSULTANT Objective 1) The Wayfinding and Signage (W&S) Consultant shall develop a wayfinding and signage solution for the interior of Terminal One (only the

More information

Concessions and PPPs. Brief 18. Public Procurement. August 2011

Concessions and PPPs. Brief 18. Public Procurement. August 2011 Brief 18 August 2011 Public Procurement Concessions and PPPs C O N T E N T S What are concessions? Different use of the term concession under national laws Does the Directive apply to concessions? What

More information

Financing and capital structure

Financing and capital structure Financing and capital structure Hannu Linnoinen Executive Vice President, CFO 1 3 Dec. 2013 Capital Markets Day Project type s effect on return, risk and financing Project margin % ~ 20% ~ 15% ~ 10% Construction

More information

Comparative Study of Frameworks to protect the Long Term Interests of Pension Funds Investing in Public-Private Partnerships

Comparative Study of Frameworks to protect the Long Term Interests of Pension Funds Investing in Public-Private Partnerships EMAIL contact@fosterinfrastructure.com WEB www.fosterinfrastructure.com Comparative Study of Frameworks to protect the Long Term Interests of Pension Funds Investing in Public-Private Partnerships Pty

More information

The following services are being offered and can be sub-categorised as follows:

The following services are being offered and can be sub-categorised as follows: INTRODUCTION Midlink Financial Services was established in 2002 by Anita Kotze with a view to providing services in the rapidly growing and changing financial and property markets. The business caters

More information

Railway Crossing Information System

Railway Crossing Information System Railway Crossing Information System ITS Canada Presentation June 2, 2014 Ian Steele, P.Eng Agenda Click to edit Master title style RBRC Program Project Background Concept of Operations Design Process Design

More information

International Real Estate Conference 99

International Real Estate Conference 99 International Real Estate Conference 99 Co-sponsors: Pacific Rim Real Estate Society (PRRES) Asian Real Estate Society (AsRES) Kuala Lumpur, 26-30 January 1999 PROPERTY MANAGEMENT FEES. ARE MANAGERS UNDERSELLING

More information

COWI s Role in the Copenhagen Metro Project

COWI s Role in the Copenhagen Metro Project COWI s Role in the Copenhagen Metro Project On the occasion of the award by the Copenhagen Cultural Foundation for COWI A/S part in the implementation of Phase 1 of the Copenhagen Metro 2 COWI s Role in

More information

Facilitating Renewable Energy Finance Presenting your Project to Financial Institutions

Facilitating Renewable Energy Finance Presenting your Project to Financial Institutions Facilitating Renewable Energy Finance Presenting your Project to Financial Institutions Deltcho Vitchev Renaissance Finance International Financing Renewable Energy One of the main issues - lack of bankable

More information

Public-Private Partnerships

Public-Private Partnerships Public-Private Partnerships Closing Critical Issues Washington, Background In limited recourse finance, the primary source of debt service is the cash flow generated by the Project will evaluate all factors

More information

PUBLIC-PRIVATE PARTNERSHIP IN INFRASTRUCTURE

PUBLIC-PRIVATE PARTNERSHIP IN INFRASTRUCTURE A GUIDEBOOK ON PUBLIC-PRIVATE PARTNERSHIP IN INFRASTRUCTURE ECONOMIC AND SOCIAL COMMISSION FOR ASIA AND THE PACIFIC This Guidebook was developed by Mr. Abdul Quium of the Transport Division of ESCAP. Its

More information

PREQUALIFICATION DOCUMENT FOR PROVISION OF WEBSITE HOSTING AND MAINTENANCE SERVICES - TENDER NO KENAS NO/19/2013/2015

PREQUALIFICATION DOCUMENT FOR PROVISION OF WEBSITE HOSTING AND MAINTENANCE SERVICES - TENDER NO KENAS NO/19/2013/2015 PREQUALIFICATION DOCUMENT FOR PROVISION OF WEBSITE HOSTING AND MAINTENANCE SERVICES - TENDER NO KENAS NO/19/2013/201 KENYA ACCREDITATION SERVICE P.O BOX 47400-00100 NAIROBI KENYA Tel: 0787 39 679 or 072

More information

The Inkosi Albert Luthuli Hospital. Cairo, May 25 26, 2008

The Inkosi Albert Luthuli Hospital. Cairo, May 25 26, 2008 The South Africa PPP Program The Inkosi Albert Luthuli Hospital Transaction Cairo, May 25 26, 2008 1 USAID Support (1999-2005) to: Establish the PPP Unit (2000) Develop the policy/regulatory y framework

More information

Procurement Journey Notes - GB - Version 8. Procurement Journey - SOC Mitigation

Procurement Journey Notes - GB - Version 8. Procurement Journey - SOC Mitigation Procurement Journey - SOC Mitigation The following notes should be considered when developing/ implementing all procurement strategies. It considers the strategy subject and determines whether enhanced

More information

LAW OF MONGOLIA ON CONCESSIONS CHAPTER ONE. GENERAL PROVISIONS

LAW OF MONGOLIA ON CONCESSIONS CHAPTER ONE. GENERAL PROVISIONS LAW OF MONGOLIA 28 January 2010 State Palace, Ulaanbaatar city Article 1. Purpose of the law ON CONCESSIONS CHAPTER ONE. GENERAL PROVISIONS 1.1. The purpose of this law is to regulate matters related to

More information

Introduction Building project management

Introduction Building project management Introduction Building project management Construction management 2. (BMEEPEKT601-BMEEPEKK601) 10-02-2011 Introduction Lecturers: Adrienn Lepel PhD István Vidovszky PhD Guest lecturers Requirements Two

More information

PUBLIC PROCUREMENT SYSTEM AND REFORM IN AFGHANISTAN Anwar M. Raufi

PUBLIC PROCUREMENT SYSTEM AND REFORM IN AFGHANISTAN Anwar M. Raufi Anwar M. Raufi 1729 OUTLINE OF THE CONTENTS OF THE TOPIC TO BE PRESENTED 1- Procurement system of Afghanistan before ten years, i.e. before 2001. Afghanistan had a series of provisions regulating procurement

More information

Norwegian road tolling: scope, limits and perspectives for the future

Norwegian road tolling: scope, limits and perspectives for the future Norwegian road tolling: scope, limits and perspectives for the future Morten Welde Norwegian Public Roads Administration ITS UK, Annual RUC forum, London, November 12, 2008 1 Presentation outline 1. Scope

More information

ASSAM POWER GENERATION CORPORATION LIMITED

ASSAM POWER GENERATION CORPORATION LIMITED ASSAM POWER GENERATION CORPORATION LIMITED Notice Inviting Expression of Interest for Consultancy in connection of Assam Power Sector Investment Program financed by ADB NIT No. NIT/PMU/05 of 2014-15 Director

More information

Rechtsanwälte, Lawyers, Abogados, Advocaten

Rechtsanwälte, Lawyers, Abogados, Advocaten Diana Zuuring Ricardo Soriano nr 20, 3C 29601 Marbella, Malaga, Spain Tel: (34) 952906185 Fax: (34) 952816813 www.zuuring.com e-mail: diana@zuuring.com Rechtsanwälte, Lawyers, Abogados, Advocaten Introducing

More information

Welcome to the City of Houston

Welcome to the City of Houston Welcome to the City of Houston City of Houston Statistics City Departments 26 Departments Total Population 21,000+ Employees City of Houston s Largest Departments Houston Police Department - 7,247 Houston

More information

PUBLIC PROCUREMENT CONTRACTS

PUBLIC PROCUREMENT CONTRACTS PUBLIC PROCUREMENT CONTRACTS Public authorities conclude contracts to ensure the supply of works and delivery of services. These contracts, concluded in exchange for remuneration with one or more operators,

More information

Business Area Distribution

Business Area Distribution Business Area Distribution David Ringmar Director Network Strategy and Development Vattenfall Capital Markets Day, Solna, 27 May 2015 Facts and figures Business Area Distribution Vattenfall s total lenght

More information

List of fees charged by the Bucharest Stock Exchange. A. Fees and commissions applicable to Participants

List of fees charged by the Bucharest Stock Exchange. A. Fees and commissions applicable to Participants A. Fees and commissions applicable to Participants 1. Admission and maintenance fees for a Participant on the trading system (in RON, VAT included) 1.1 One-off fees 1.1.1 Fee for the admission of a Participant

More information

Public Sector ICT Procurement

Public Sector ICT Procurement Learn how to successfully handle procurements of ICT solutions in your public institution European Seminar 4 th - 5 th March 2013, Berlin Brochure 1 EUROPEAN SEMINAR Do not lock your institution into a

More information

Telecommunications Regulation. NORWAY Advokatfirmaet Thommessen AS

Telecommunications Regulation. NORWAY Advokatfirmaet Thommessen AS Telecommunications Regulation NORWAY Advokatfirmaet Thommessen AS CONTACT INFORMATION Haakon Opperud Advokatfirmaet Thommessen AS Haakon VII gate 10 0116 Oslo +47 23 11 11 11 hop@thommessen.no 1. What

More information

Mongolia: Fifth Health Sector Development Project

Mongolia: Fifth Health Sector Development Project Fifth Health Sector Development Project (RRP MON 45009) Subsector Analysis (Summary): Medical Waste Management Project Number: 45009 Loan Number: XXXX November 2012 Mongolia: Fifth Health Sector Development

More information

Community Academies Trust Leasing Policy

Community Academies Trust Leasing Policy Community Academies Trust Leasing Policy Page 1 of 6 1. Introduction Community Academies Trust (CAT) is committed to ensuring that its systems of financial governance conform to the requirements of both

More information

Purchasing Real Estate in México by CARLOS SOLÓRZANo

Purchasing Real Estate in México by CARLOS SOLÓRZANo Article Number: 1009-01 CARLOS SOLÓRZANO SOLORZANO CORPORATION Purchasing Real Estate in México by CARLOS SOLÓRZANo Buying real estate in Mexico is secure and the process could be seamless if done properly.

More information

City of Vantaa New Plans and Projects

City of Vantaa New Plans and Projects City of Vantaa New Plans and Projects Smart Mobility for Better Cities Conference 12 May, 2011 Gilbert Koskela Project Engineer Marja-Vantaa project City of Vantaa has been a forerunner in Finland in studying

More information

Designing Health and Safety into Procurement and Contract Management

Designing Health and Safety into Procurement and Contract Management Designing Health and Safety into Procurement and Contract Management Environmental Services Association Scottish Environmental Services Association Welsh Environmental Services Association Environmental

More information

Preliminary Value for Money Analysis

Preliminary Value for Money Analysis Preliminary Value for Money Analysis Comparison of Project Delivery Methods and Financing Options C-470 ExpressLanes November 2014 Outline Executive Summary Comparison of Delivery Options Base Case Plan

More information

PPP Seminar : Health Royal Liverpool Hospital Case study

PPP Seminar : Health Royal Liverpool Hospital Case study PPP Seminar : Health Royal Liverpool Hospital Case study Gavin Quantock Deloitte Corporate Finance 23 July 2014 Case study Royal Liverpool hospital PPP and Health Background Deloitte involvement Structure

More information

MIV Market for Investment Vehicles

MIV Market for Investment Vehicles give the right direction to your investment Vehicle MIV Market for Investment Vehicles Overview MIV (Market for Investment Vehicles) is the regulated market of Borsa Italiana created with the scope to

More information

Client Consultancy. Description of services December 2003. The Danish Council of Practising Architects (PAR)

Client Consultancy. Description of services December 2003. The Danish Council of Practising Architects (PAR) Description of services December 2003 Client Consultancy The Danish Council of Practising Architects (PAR) The Association of Consulting Engineers in Denmark (FRI) PAR and FRI Description of services for

More information

BMT Tax Depreciation Estimate

BMT Tax Depreciation Estimate Estimate Lot 412 Furlong Drive, Laurimar DOREEN, VIC 3754 Level 50, 120 Collins Street GPO Box 4260 t 03 9654 2233 f 03 9654 2244 e info@bmtqs.com.au w www.bmtqs.com.au Australia Wide Service ABN 44 115

More information

Introduction to Public-Private Partnerships (P3s)

Introduction to Public-Private Partnerships (P3s) Introduction to Public-Private Partnerships (P3s) Today s Instructor Patrick DeCorla-Souza P3 Program Manager Office of Innovative Program Delivery Program Development Team Course Outline Slide 2 Lesson

More information

Annex A: Pre-Qualification Questionnaire Core Questions

Annex A: Pre-Qualification Questionnaire Core Questions Annex A: Pre-Qualification Questionnaire Core Questions This Pre-Qualification Questionnaire ( PQQ ) has been issued by the Authority in connection with a competitive procurement conducted under the Public

More information

consultants chartered accountants registered auditors

consultants chartered accountants registered auditors consultants chartered accountants registered auditors What is VAT? VAT is a tax on the sale of goods and services. It is paid by the end consumer. For example, when you go into a shop and buy a television

More information

Bicycle and Public Transport Dream Team or Rivals? The Berlin Experience

Bicycle and Public Transport Dream Team or Rivals? The Berlin Experience Bicycle and Public Transport Dream Team or Rivals? The Berlin Experience Conference Integrated Urban Mobility Dresden, 12./13. March 2009 Burkhard Horn Senate Department for Urban Development, Berlin Overview

More information

Wind farm project development in Poland experience report from a market participant

Wind farm project development in Poland experience report from a market participant Wind farm project development in Poland experience report from a market participant Conference Marktpotential der Offshore- Windenergie in Polen für deutsche Unternehmen Table of Contents 1. CRE who we

More information

1/ 11 TED19_TFL 24/03/2016- ID:2016-000048 Standard form 2 - EN Rapid Charge Point Concession Framework

1/ 11 TED19_TFL 24/03/2016- ID:2016-000048 Standard form 2 - EN Rapid Charge Point Concession Framework 1/ 11 TED19_TFL 24/03/2016- ID:2016-000048 Standard form 2 - EN CONTRACT NOTICE - ABOVE THRESHOLD SECTION I: CONTRACTING AUTHORITY I.1) NAME, ADDRESSES AND CONTACT POINT(S) Official name: Transport for

More information

BULLETIN OF LOAN INTEREST RATES

BULLETIN OF LOAN INTEREST RATES Banka ProCredit sh.a, Rr. Dritan Hoxha Tirane, Shqipëri BULLETIN OF LOAN INTEREST RATES Last modification: 02 December 2015 EUR/USD ALL Private loan Overdraft Consumer loan (max. term 60 months) Loan Loan

More information

How To Manage Two Web Portals In South Africa

How To Manage Two Web Portals In South Africa TERMS OF REFERENCE FOR WEBSITE MAINTENANCE AND SUPPORT FOR THE LED.CO.ZA AND LGICT.ORG.ZA WEB PORTALS HOSTED BY SALGA BACKGROUND The South African LED Network and LGICT Network are projects hosted by the

More information

Investors day. Investors Day. Marketing and economics Vice President Benoit CARON. January 8 th, 2004. January 8th, 2004 Page 29

Investors day. Investors Day. Marketing and economics Vice President Benoit CARON. January 8 th, 2004. January 8th, 2004 Page 29 Investors Day Marketing and economics Vice President Benoit CARON January 8 th, 2004-29 - January 8th, 2004 Page 29 Products: Renault Trucks in the future - 30 - January 8th, 2004 Page 30 Renault Trucks

More information

DIRECTORATE OF AUDIT, RISK AND ASSURANCE Internal Audit Service to the GLA INTERIM REVIEW OF ROYAL ALBERT DOCK PROCUREMENT

DIRECTORATE OF AUDIT, RISK AND ASSURANCE Internal Audit Service to the GLA INTERIM REVIEW OF ROYAL ALBERT DOCK PROCUREMENT DIRECTORATE OF AUDIT, RISK AND ASSURANCE Internal Audit Service to the GLA INTERIM REVIEW OF ROYAL ALBERT DOCK PROCUREMENT DISTRIBUTION LIST Audit Team David Esling, Head of Audit and Assurance Phil Drysdale,

More information

Guide to Subdivision and Land Development

Guide to Subdivision and Land Development Guide to Subdivision and Land Development Fraser Thomas Ltd...... is a consulting company located in Manukau City which has provided Surveying, Engineering, Planning and Resource Management services in

More information

Business Succession Planning With ESOPs

Business Succession Planning With ESOPs acumen insight Business Succession Planning With ESOPs Presented by Alan Taylor, CPA Partner ideas attention reach expertise depth agility talent Disclaimer Information contained herein is of a general

More information

PPP POLICY AND REGULATION IN INDONESIA

PPP POLICY AND REGULATION IN INDONESIA MINISTRY OF NATIONAL DEVELOPMENT PLANNING / NATIONAL DEVELOPMENT PLANNING AGENCY (BAPPENAS) PPP POLICY AND REGULATION IN INDONESIA Dr. Ir. BASTARY PANDJI INDRA, MSP DIRECTOR FOR PPP DEVELOPMENT 8 FEBRUARI

More information

The South African Council for the Project and Construction Management Professions. Guideline Scope of Services and Tariff of Fees

The South African Council for the Project and Construction Management Professions. Guideline Scope of Services and Tariff of Fees The South African Council for the Project and Construction Management Professions Guideline Scope of Services and Tariff of Fees For Persons Registered in terms of the Project and Construction Management

More information

Financing Tools for Public-Private Partnerships in Illinois

Financing Tools for Public-Private Partnerships in Illinois Financing Tools for Public-Private Partnerships in Illinois June 24, 2011 CHICAGO 111 West Monroe Street Chicago, IL 60603-4080 (312) 845-3000 NEW YORK 330 Madison Avenue New York, NY 10017-5010 (212)

More information

GIMPA EXECUTIVE CONFERENCE CENTRE

GIMPA EXECUTIVE CONFERENCE CENTRE LOCAL GHANA INSTITUTE OF MANAGEMENT & PUBLIC ADMINISTRATION (GIMPA) In Collaboration With The WORLD BANK AND ILO TURIN CENTRE Announces a GOODS & EQUIPMENT PROCUREMENT MANAGEMENT COURSE DATE: 5 TH 23 RD

More information

Presentation for investors

Presentation for investors ethics teamwork responsibility ambition Presentation for investors Financial results 1H 2011 Agenda I. Important events of the period Successes of 1H 11 Challenges for the future 3 3 11 II. Financial results

More information

INDIVIDUAL CONSULTANCY

INDIVIDUAL CONSULTANCY INDIVIDUAL CONSULTANCY ARCHITECTURAL CONSULTANT SERVICE TO DEVELOP A CONCEPT DESIGN AND UPDATE THE BUILDING SPECIFICATIONS FOR THE ONE UN HOUSE IN RWANDA TERMS OF REFERENCE 1. Background and Project Description

More information

Position Description

Position Description To apply for this position, please provide an up to date resume, covering letter, and statement addressing the Key Selection Criteria in section 6 of this Position Description. Your application will not

More information

The National Council of the Slovak Republic has adopted the following Act: Article I. 1 Scope of the act

The National Council of the Slovak Republic has adopted the following Act: Article I. 1 Scope of the act Slovak Investment and Trade Development Agency Address: Trnavská cesta 100, 821 01 Bratislava, Slovak Republic Tel.: +421 2 58 260 100, Fax: +421 2 58 260 109, E-mail: invest@sario.sk, www.sario.sk Act

More information