1 MPO Staff Report MPO Technical Advisory Committee: March 13, 2013 MPO Executive Board: March 20, 2013 RECOMMENDED ACTION: Matter of MnDOT Kennedy Bridge Study and NDDOT Sorlie Bridge Phase I Report Matter of the MnDOT Kennedy Bridge Study and NDDOT Sorlie Bridge Report. Background: The MPO has programmed $25M to complete rehab work in FY2016 on the Kennedy Bridge. As part of the decision process, MnDOT is going to complete a study on alternatives of rehab and possibly alternatives on replacement. A preliminary meeting was held between the consultants and local representatives. Attached is powerpoint and fact sheet distributed. NDDOT has selected Kadrmas, Lee and Jackson (KLJ) to complete the RFP s identified Phase I portion of the document for the scheduled improvement in 2018 on the Sorlie Bridge. Phase I meetings have been held and KLJ is drafting a scope of work to complete an Environmental Impact Statement (EIS). Findings and Analysis: None Support Materials: Kennedy Bridge preliminary meeting powerpoint Kennedy Bridge Fact Sheet
2
3 Meeting Agenda Introductions ti Kennedy Bridge background and study overview Need for action and context Alternatives to be evaluated Future meeting plans and community involvement 2
4 Bridge Description & Background Kennedy Bridge built 1963; now 50 years old 1,261 feet long; 2 steel truss main spans and 11 steel beam approach spans Eastbound and westbound directions each have two 12 ft. wide lanes and a 4 ft. shoulder More than 20,000 vehicles per day cross on US Highway 2 (main east-west highway) Spans the Red River and floodway immediate area includes recreational and historic features (note: we will soon discuss needs/context) 3
5 Bridge Planning Study Overview Primary Study Components: Bridge rehabilitation alternatives at es Bridge replacement alternatives Public and agency input Environmental resources and community values project context Shdl Schedule Goals and Process: Planning study = months (findings by about the end of 2013) Identify objectives and follow-up actions for 2014 and beyond 4
6 Need for Action Pi Primary Need required element for any alternative: ti Continue to provide a structurally sound crossing of the Red River at this location Secondary Needs desirable; to be incorporated into reasonable alternatives: Provide a reliable crossing for the traffic demands Evaluate pedestrian/bicycle access and connectivity it at this location Other needs to be identified Other Considerations: Regulatory requirements, including historic resources Structural t redundancy d River hydraulics and geotechnical conditions 5
7 Need & Context Bridge Foundations Soils along the Red River are known to slump (move slowly), generally from the river banks toward the middle of the river The Kennedy Bridge was designed to accommodate soil movement; the bridge s bearings have periodically been adjusted There is a need to address: Feasibility and limitations for further adjustments Other short- and long-term actions for Pier 6 (ND side of the river) River flow/flood effects on foundations (scour) Bearing on Pier 6 Pier 6 Evidence of scour 6
8 Need & Context Red River Floods Next red river crossings: Sorlie Bridge (1 mile south) - Oslo Bridge (20 miles north) Bridge closure order during flooding (Kennedy is last locally): Source: GF/EGF Bridge Closure Management Study (May 9, 2007) 7
9 Context Historic/Cultural & Recreational Kennedy Bridge is eligible for listing on the National Register of Historic Places Riverside Historic District (north of bridge, in ND) Historic St. Michael s Hospital (south of bridge, in ND) Red River Greenway trails, parklands, campground, floodway 8
10 Discussion Need for action Context and community objectives Other 9
11 Alternatives ti to be Evaluated Existing bridge maintenance, rehabilitation, and improvements Short-term (focus on primary need, to maintain crossing) Longer-term, including potential to add pedestrian and bicycle improvements (primary and secondary needs) Replacement bridge alternatives Bridge types Roadway alignments and cross section Pedestrian & bicycle accommodations 10
12 Project Timeline e Proposed SAC Meetings: March 6, May 22, July 17, September 4, and November 20 11
13 Discussion and Next Steps 12
14 Kennedy Bridge Planning Study Fact Sheet (February 2013) Kennedy Bridge Planning Study East Grand Forks, MN Grand Forks, ND Study Contact Information: MnDOT Project Manager: Derrick Dasenbrock, , MnDOT District 2 Bridge Engineer: Roger Hille, , roger.hille@state.mn.us CH2M HILL (Consultant) Project Manager: Dale Thomas, , dale.thomas@ch2m.com CH2M HILL Public Involvement Lead: Doug Abere, , douglas.abere@ch2m.com This MnDOT study will evaluate a range of issues related to maintenance and rehabilitation of the US Highway 2 Kennedy Bridge, as well as potential replacement alternatives. The 2013 Study will refine the options examined to determine the most promising alternatives. More detailed engineering and decision making steps will follow in 2014 and beyond. Primary Study Components: Bridge Rehabilitation A range of rehabilitation issues will be examined including technical aspects of the steel truss, foundations, hydraulic considerations, and geotechnical conditions. Bridge Replacement A variety of bridge replacement concepts will be identified and discussed, including an alignment adjacent to the existing bridge. This evaluation will consider several bridge types and layouts to determine those considered most promising for a possible replacement. Public and Agency Input Stakeholders who may be impacted by changes in the condition or operation of the bridge, as well as many public agencies, will be included in the planning process. The various stakeholders, including the general public, will be invited to participate in meetings to identify key issues and provide feedback. Environmental Resources and Community Values The study area will be reviewed for environmental resources and constraints, including the area s historic and recreational features and values. Related issues will include avoiding/minimizing any adverse effects and the potential to include pedestrian and bicycle accommodations at the crossing. (02/19/13 Study Kickoff)
15 Kennedy Bridge Planning Study Study Advisory Committee (SAC) Meeting Dates and Planned Topics (Draft: ) 2013 SAC Dates * SAC Meeting Themes/Content March 6 Introduce study scope & objectives Present and discuss Purpose & Need and bridge context Discuss proposed meeting schedule and community involvement May 22 Continue discussion of bridge context Discuss/refine needs; develop goals, objectives, and evaluation criteria Present and discuss rehab/replacement bridge traffic implications Discuss and preview public information meeting (proposed for June) Present status of technical studies (hydraulic, geotechnical & environmental/historic memos) July 17 Review and refine goals, objectives, and evaluation criteria Present overview of rehab options Discuss bridge replacement options Present status of technical studies (hydraulic, geotechnical & environmental/historic memos) September 4 Continue discussion of bridge replacement options Discuss and preview public information meeting in October Present status of technical studies (hydraulic, geotechnical & environmental/historic memos) November 20 Present highlights of the draft final report Discuss next steps * Proposed dates, subject to change. MnDOT S.P. No (03/06/13 Study Kickoff SAC)
Alternatives Evaluation Overview
Alternatives Evaluation Overview 124 Alternatives were analyzed against the evaluation criteria Criteria and criteria weighting were set by the Community Task Force Ratings were quantitative and qualitative
More information3.1 Historical Considerations
3. Recommended Scope of Bridge improvements 3.1 Historical Considerations In the fall of 2000, an outside consultant, Fraser Design, suggested that the existing 4 th St. Bridge is potentially eligible
More informationInformational Workshop Public Meeting Kanawha Falls Bridge Project
Informational Workshop Public Meeting Kanawha Falls Project WV Department of Transportation Division of Highways in Cooperation with the Federal Highway Administration State Project S310-13-0.02 00 Federal
More informationBridge Rehabilitation Alternatives
Kennedy Bridge Planning Study Technical Memorandum: Bridge Rehabilitation Alternatives MnDOT S.P. No. 6018-02 Prepared for: Minnesota Department of Transportation DRAFT April 28, 2014 Prepared by: Report
More informationPublic Information & Public Scoping Meeting
Public Information & Public Scoping Meeting William F. Cribari Memorial Bridge Route 136 over the Saugatuck River Review of Rehabilitation Study Report Public Scoping for the gathering and analysis of
More informationREHABILITATION PACKAGE 1-a
1-a WINONA BRIDGE (BRIDGE 5900) REHABILITATION PACKAGE 1-a Rehab option 1-a is a rehabilitation package whereby all spans of the existing structure would be rehabilitated to the degree feasible and strengthened
More informationOpen House Public Meeting for the Thurmond Bridge Rehabilitation Project State Project: State Project S310-25/2-0.10 Federal Project: BR-0252(001)D
Open House Public Meeting for the State Project: State Project S310-25/2-0.10 Federal Project: BR-0252(001)D May 7, 2015 Old Glen Jean Bank Glean Jean, WV 4:00-7:00 PM www.transportation.wv.gov PROJECT
More informationRed Wing Bridge Project. PAC #5/TAC #8 Meeting July 18, 2013
Red Wing Bridge Project PAC #5/TAC #8 Meeting July 18, 2013 Alternatives Analysis Agenda Overview of Past Progress Progress Since April PAC Bridge 9103 Rehabilitation Study Bridge 9040 Rehab vs. Replacement
More informationAlternatives to the Circ Project Prioritization Methodology Prepared for Circ Task Force July 28, 2011
Alternatives to the Circ Project Prioritization Methodology Prepared for Circ Task Force July 28, 2011 CCRPC staff has developed a draft methodology described below and detailed in the attached pages for
More informationSR 89/Fanny Bridge Community Revitalization Project. Draft Environmental Impact Report/ Environmental Impact Statement/ Environmental Assessment
SR 89/Fanny Bridge Community Revitalization Project Draft Environmental Impact Report/ Environmental Impact Statement/ Environmental Assessment 2015 Meeting Purpose Provide a summary description of alternatives
More information3 Tappan Zee Bridge Rehabilitation Options
3 Tappan Zee Bridge Rehabilitation Options 3.1 Introduction This chapter describes possible options that rehabilitate and enhance the existing Tappan Zee Bridge. Four Rehabilitation Options have been developed:
More information2015 ODOT Bridge Design Conference May 12, 2014. DeJong Rd Bridge High- Seismic Zone Case Study: Bridge Rehab vs. Replacement.
2015 ODOT Bridge Design Conference May 12, 2014 DeJong Rd Bridge High- Seismic Zone Case Study: Bridge Rehab vs. Replacement Mary Ann Triska 2015 HDR, all rights reserved. Presentation Outline Project
More informationCITY OF TRAIL MEMORANDUM
0 C CITY OF TRAIL MEMORANDUM DATE: TO: FROM: SUBJECT: March 24, 2011 FILE NO. 5400-02 DAVID PEREHJJDOFF, CHIEF ADM1NTSTRATIVE OFFICER WARREN PROULX, ENGINEERING TECHMCIAN OLD TRAIL BRIDGE With the interest
More informationImproving Access in Florida International University Biscayne Bay Campus Executive Summary
EXECUTIVE SUMMARY Improving Access in Florida International University Biscayne Bay Campus Executive Summary Prepared for: Miami-Dade County Metropolitan Planning Organization (Miami-Dade MPO) Prepared
More informationRehabilitation of the Red Bank Road Bridge over Hoover Reservoir. Presented By: Doug Stachler, P.E.
Rehabilitation of the Red Bank Road Bridge over Hoover Reservoir Presented By: Doug Stachler, P.E. Project Organization Owner Delaware County Engineers Office Design Consultant CH2M HILL Contractor Double
More informationIH-635 MANAGED LANES PROJECT, SEG. 3.2
IH-635 MANAGED LANES PROJECT, SEG. 3.2 Location: Dallas, Texas Owner: Texas Department of Transportation Client: Ferrovial Agroman Construction Cost: $1 Billion Construction Completion Date: December,
More informationHarlem River Bridges Access Plan
Harlem River Bridges Access Plan Workshop Round 2 September 10, 2015 Harlem River Bridges Access Plan: Overview Agenda Presentation: Background + overview of concepts for review (15 20 min) Participation:
More informationDepartment of Public Works P.O Box 4186, San Rafael, CA 94913-4186 415/473-7877 Fax: 415/473-3724
Department of Public Works P.O Box 4186, San Rafael, CA 94913-4186 415/473-7877 Fax: 415/473-3724 San Antonio Road Bridge Replacement September 9, 2015 Community Meeting Summary The County of Marin in
More informationARC Bike/Ped Plan Equity Discussion. Presented to ARC Bike/Ped Plan Equity Advisory Group July 29 th, 2015
ARC Bike/Ped Plan Equity Discussion Presented to ARC Bike/Ped Plan Equity Advisory Group July 29 th, 2015 The Bicycle 1973 ARC A Plan & Program for Its Use as a Mode of Transportation & Recreation The
More informationBackground and Goals for the Project
City of Asheville, NC REQUEST FOR PROPOSALS Wilma Dykeman Riverway Environmental Analysis, Project Development, and Preliminary Design Submittal Address: Dan Baechtold, AICP City of Asheville Engineering
More informationUS 51 Ohio River Bridge Engineering and Environmental Study
US 51 Ohio River Bridge Engineering and Environmental Study ITEM NOS. 1-100.00 & 1-1140.00 Prepared by: Michael Baker Jr., Inc. 9750 Ormsby Station Rd Louisville, KY 40223 August 16, 2013 Table of Contents
More informationPedestrian & Bicycle Plan
RAMSEY COMMUNITIES COUNTYWIDE Pedestrian & Bicycle Plan PRIMER: LEGAL FRAMEWORK PRIMER: LEGAL FRAMEWORK Walking and Biking for All e 2 CHAPTER 2: Walking and Biking for All This page intentionally left
More informationPresentation to Community Task Force July 9, 2007
Alternative Evaluation Results Presentation to Community Task Force July 9, 2007 Outline of Presentation Overview of alternative evaluation Alternative evaluation methodology Process and assumptions General
More informationTH 23 Access Management Study Richmond to Paynesville
TH 23 Access Management Study Richmond to Paynesville Prepared For: Minnesota Department of Transportation District 8 Prepared By: Short Elliott Hendrickson Inc. July 2015 Table of Contents I. Introduction...
More informationSewalls Falls Road Bridge. Cultural Resource Meeting April 4, 2013
Sewalls Falls Road Bridge Cultural Resource Meeting April 4, 2013 Meeting Purpose Review of the project process to date Project replacement vs. rehabilitation Review of recent public process Review of
More informationMontana Department Transportation
Montana Department Transportation Work Zone Safety and Mobility Transportation Management Plan Development Process 2015 Background Montana Department of Transportation s WZSM policy and guidance is predicated
More informationWelcome! Purpose of Tonight s Meeting. Informational Open House to discuss two City projects: Goal is to LISTEN TO YOU
Purpose of Tonight s Meeting Informational Open House to discuss two City projects: Fairchild Street Subway Phase I Engineering: Immediate need to replace subway Bowman Avenue Feasibility Study Future
More informationSAFETEA-LU TECHNICAL CORRECTIONS BILL SUMMARY
SAFETEA-LU TECHNICAL CORRECTIONS BILL SUMMARY Draft 7/2/08 The SAFETEA-LU Technical Corrections Bill (HR 1195) was enacted on June 6, 2008 (P.L. 110-244). The Bill can be found at: http://frwebgate.access.gpo.gov/cgi-bin/getdoc.cgi?dbname=110_cong_bills&docid=f:h1195enr.txt.pdf
More informationExecutive Summary. Transportation Needs CHAPTER. Existing Conditions
CHAPTER 1 Executive Summary The City of Forest Grove Transportation System Plan (TSP) was updated to keep it consistent with recent growth trends in the city and other transportation planning efforts in
More informationKOSCIUSZKO BRIDGE PROJECT BRIDGE PRIMER
KOSCIUSZKO BRIDGE PROJECT BRIDGE PRIMER The New York State Department of Transportation (NYSDOT) is preparing an Environmental Impact Statement (EIS) to evaluate alternatives for the rehabilitation or
More informationVeterans Memorial Bridge (Orange Avenue) PD&E Study
Veterans Memorial Bridge (Orange Avenue) PD&E Study From City Island Parkway to South Peninsula Drive FDOT FPID# 242172-128-01 Volusia County Project# P-5351-1 Project Limits End Project City Island Veterans
More informationChapter 5. Transportation. Decatur County Comprehensive Plan. Introduction. Goals and Objectives. Goal. Objectives. Goal.
Chapter 5 Transportation Chapter 5: Transportation Introduction The transportation system forms the backbone of a community. I-74 connects Decatur County with the large metropolitan areas of Cincinnati
More informationRoss River Suspension Bridge Ross River, Yukon. Life Cycle Cost Analysis
DNA project managers planners architects engineers David Nairne + Associates Ltd Suite 250 171 W Esplanade North Vancouver British Columbia Canada V7M 3J9 T 604 984 3503 F 604 984 0627 E dna@ davidnairne.com
More information5 ALTERNATIVE SOLUTIONS AND EVALUATION
Page 23 5 ALTERNATIVE SOLUTIONS AND EVALUATION The process used for the assessment and evaluation of the alternatives follows the procedures of the Municipal Class EA, as described below: Identify a reasonable
More informationAlterna ves Development & Evalua on
Spring 2015 Newsletter Issue III WHERE ARE WE IN THE PROCESS? Since the NLSD Phase I Study kickoff in 2013, numerous meetings have been held with the public, the existing conditions and transportation
More informationREQUEST FOR PROPOSALS FROM PREQUALIFIED CONSULTING FIRMS FOR SPECIFIC PROJECT J BIKEWAY FEASIBILITY STUDY IN NORTHWEST COOK AND KANE COUNTIES
REQUEST FOR PROPOSALS FROM PREQUALIFIED CONSULTING FIRMS FOR SPECIFIC PROJECT J BIKEWAY FEASIBILITY STUDY IN NORTHWEST COOK AND KANE COUNTIES On Wednesday, May 7, 2014, CMAP held a non-mandatory pre-bid
More informationNorthern Nevada Water Planning Commission
12-07-11: NNWPC Agenda Item 6 Northern Nevada Water Planning Commission DATE: November 29, 2011 STAFF REPORT TO: FROM: SUBJECT: Chairman and Members, Northern Nevada Water Planning Commission Jim Smitherman,
More informationSafe & Sound Bridge Terminology
Safe & Sound Bridge Terminology Abutment A retaining wall supporting the ends of a bridge, and, in general, retaining or supporting the approach embankment. Approach The part of the bridge that carries
More informationContext Sensitive Design for Urban Transportation in West Philadelphia
Context Sensitive Design for Urban Transportation in West Philadelphia Transportation Research Board 85 th Annual Meeting 24 January 2006 Jeffrey M. Casello University of Waterloo Robert Wright City of
More informationMaine-New Hampshire Connections Study. Public Informational Meeting September 24, 2009
Maine-New Hampshire Connections Study Public Informational Meeting September 24, 2009 1 Meeting Overview Welcome Update on Stimulus Application/BICA 10 minutes Study Schedule Update - 5 minutes Traffic
More informationBlacklands Corridor Feasibility Study. Public Meeting November 7, 2013 McClendon Elementary School Nevada, TX
Blacklands Corridor Feasibility Study Public Meeting November 7, 2013 McClendon Elementary School Nevada, TX Overview Welcome and Project Overview Michael Morris Recent Progress Analyzing Existing and
More informationLouisville Region: Travel Management Coordination Center
Louisville Region: Travel Management Coordination Center Mobility Services for All Americans ITS Phase 1 Grant Project Team Leads: TARC & KIPDA Region IV Conference May 2008 Evolution of Coordination Travel
More informationSt. Cloud Area Planning Organization TECHNICAL ADVISORY COMMITTEE MINUTES
St. Cloud Area Planning Organization TECHNICAL ADVISORY COMMITTEE MINUTES A regular meeting of the St. Cloud Area Planning Organization s (APO) Technical Advisory Committee (TAC) was held on Wednesday,
More informationRPA 14/ATURA Surface Transportation Program (STP) APPLICATION FOR FUNDS
RPA 14/ATURA Surface Transportation Program (STP) APPLICATION FOR FUNDS Please provide the following information when applying to RPA 14/ATURA for Surface Transportation Program (STP) funding for projects
More informationAppendix A Alternative Contracting General Engineering Consultant RFP. Appendix A
Appendix A 1 1.0 Requirements and Minimum Qualifications This section outlines requirements and minimum qualifications for the GEC. It is anticipated that the GEC will be used to support and supplement
More informationAction on Amendment Five to the FFYs 2015-18 TIP Page 1 of 8 Boston Region MPO Staff - 9/3/2015
Project ID Project Description Funding District Funds Funds Information Indicates a change in project cost Indicates removed from TIP (cost not reflected in total) Indicates a project moved in from another
More informationREPORTS & PRESENTATIONS AGENDA ITEM #III-3 CORTEZ BRIDGE PROJECT DEVELOPMENT AND ENVIRONMENT (PD&E) STUDY
NOTES REPORTS & PRESENTATIONS AGENDA ITEM #III-3 CORTEZ BRIDGE PROJECT DEVELOPMENT AND ENVIRONMENT (PD&E) STUDY Presenter: Summary: Tony Sherrad, FDOT Project Manager The Cortez Bridge in Manatee County,
More informationCAPPELEN MEMORIAL BRIDGE REHABILITATION
CAPPELEN MEMORIAL BRIDGE REHABILITATION Owner: Hennepin County Engineering: HNTB with Olson-Nesvold Engineering (ONE) and others Section 106 Historical Committee: Hennepin County, MnDOT Cultural Resources
More informationRiver Flood Assessment for northeast SC and southeast NC Saturday, October 17, 2015 1120 AM EDT
River Flood Assessment for northeast SC and southeast NC Saturday, October 17, 2015 1120 AM EDT National Weather Service Wilmington NC http://weather.gov/ilm Prepared By: Rick Neuherz Richard.Neuherz@noaa.gov
More informationEscape the Limblessage
Click Click to edit to Master edit Master text styles text styles Riverside County - Orange County Second level Third level Fourth level Fifth level 1 1 MIS Corridor Demand 2 2 County Line Crossings %
More informationCONCEPTUAL REHABILITATION ALTERNATIVE
Appendix D While federal law requires preservation/rehabilitation of historic bridges be considered, there is no standard procedure to determine when rehabilitation is appropriate and when replacement
More informationNashville District Workload for Nashville SAME Professional Development Workshop
Nashville District Workload for Nashville SAME Professional Development Workshop Thomas Cayce, PE Chief, Programs and Project Delivery Branch Nashville District 17 August 2011 US Army Corps of Engineers
More informationNepean River Bridge. The NSW Government is building a new pedestrian and cyclist bridge over the Nepean River to connect Penrith and Emu Plains.
Nepean River Bridge May 2016 The NSW Government is building a new pedestrian and cyclist bridge over the Nepean River to connect Penrith and Emu Plains. The new bridge will provide a safe crossing for
More informationREGIONAL NON-MOTORIZED TRANSPORTATION NETWORK
Chapter 10 Bicycle and Pedestrian SAFETEA-LU legislation requires that non-motorized users be considered in the LRTP. The legislation allows for bicycle and pedestrian safety to be incorporated into the
More informationabcde Buckinghamshire County Council Report to: Development Control Committee AGENDA ITEM 8 Date 9 April 2002
abcde Report to: Buckinghamshire County Council Development Control Committee AGENDA ITEM 8 Date 9 April 2002 Title Author Electoral Divisions Affected Recommendation Resources Appraisal Proposed Demolition
More informationMEMORANDUM COMMUNITY AND ECONOMIC DEVELOPMENT DEPARTMENT
#19 MEMORANDUM COMMUNITY AND ECONOMIC DEVELOPMENT DEPARTMENT TO: SUBJECT: John C. Phillips, City Manager Downtown Riverfront Park Preliminary Design (Armory Park) REVISED Scope of Services Schreiber Anderson
More informationEffect on structures. Uniform settlement - no concerns. Angular distortion - causes damage due to tensile strain
Effect on structures Uniform settlement - no concerns Angular distortion - causes damage due to tensile strain 1/500 - safe limit for no cracking of buildings 1/150 - potential structural damage 36 37
More informationExhibit A Scope of Work
Exhibit A Scope of Work The agreement for S.P. 3116-142 (T.H. 169-Cross Range Expressway) includes final design plans for a 1.55 mile length of a 2 lane to 4 lane expansion project located 0.66 miles SW
More informationTask 1 Project Management and Project Organization Work Plan
City of Palmdale Active Transportation Program Plan Scope of Work At their January 22, 2015 meeting, the California Transportation Commission (CTC) allocated funding for the above-referenced project as
More informationIN THE CITY COUNCIL OF THE CITY OF LIVERMORE, CALIFORNIA A RESOLUTION TO APPROVE A COMPLETE STREETS POLICY
IN THE CITY COUNCIL OF THE CITY OF LIVERMORE, CALIFORNIA A RESOLUTION TO APPROVE A COMPLETE STREETS POLICY The term " Complete Streets" describes a comprehensive, integrated transportation network with
More information14-97. 14-97.002 Definitions. For the purposes of this rule chapter the following definitions shall apply unless the context clearly shows otherwise:
14-97 14-97.001 Purpose. This rule chapter sets forth an access control classification system and access management standards to implement the State Highway System Access Management Act of 1988. The implementation
More information5.14 Floodplains and Drainage/Hydrology
I-70 East Final EIS 5.14 Floodplains and Drainage/Hydrology 5.14 Floodplains and Drainage/Hydrology This section discusses floodplain and drainage/hydrology resources and explains why they are important
More informationDESIGN ASSISTANCE APPLICATION
DESIGN ASSISTANCE APPLICATION for FY 2016 NEW RIVER MULTI USE PATH: PINNACLE PEAK ROAD TO HAPPY VALLEY ROAD CITY OF PEORIA APPLICATIONS ARE DUE VIA ONLINE SUBMITTAL BY 10:00 AM ON MONDAY, JUNE 29, 2015
More informationThe purpose of this meeting is to inform the public of the updates to the project, and to get input before the finalization of the project.
The purpose of this meeting is inform the public of the updates the project, and get input before the finalization of the project. The following panels describe the purpose and hisry of the project, along
More informationProject R-4467 PROJECT DESCRIPTION PROJECT SCHEDULE PURPOSE OF THIS MEETING WHAT WILL BE DONE WITH THE COMMENTS? FOR MORE INFORMATION:
Workshop #3 Aug ust 2012 PROJECT DESCRIPTION The North Carolina Department of Transportation (NCDOT) proposes to maintain a direct highway connection between Hertford and Winfall along or close to US 17
More informationPUBLIC INFORMATIONAL MEETING THURSDAY APRIL 30, 2015
PUBLIC INFORMATIONAL MEETING THURSDAY APRIL 30, 2015 AT ACTON TOWN HALL FAULKNER ROOM 472 MAIN STREET ACTON, MASSACHUSETTS 7:00 PM FOR THE PROPOSED ASSABET RIVER RAIL TRAIL (ARRT) IN THE TOWNS OF ACTON
More informationEarth Retaining Structures
Earth Retaining Structures and Asset Management Earth Retaining Structures and Asset Management A Critical Component Tool in Maintaining Public Safety Earth Retaining Structures (ERS) are often an overlooked
More informationCITY OF ROANOKE AND TOWN OF VINTON, VIRGINIA. RSTP Funds Joint Application FOR
CITY OF ROANOKE AND TOWN OF VINTON, VIRGINIA RSTP Funds Joint Application FOR Tinker Creek Pedestrian Bridge: Tinker Creek and Glade Creek Greenways Connection Date: September 15, 2014 RSTP Project Profile
More informationJurisdictional Scan of Traffic Management during Incidents on Bridges
Jurisdictional Scan of Traffic Management during Incidents on Bridges Discussion Paper Engineering Branch BC Ministry of Transportation and Infrastructure September 2008 1.0 Purpose Unplanned closures
More informationLOUISIANA DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT CONSTRUCTION PLANS QUALITY CONTROL / QUALITY ASSURANCE MANUAL
LOUISIANA DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT CONSTRUCTION PLANS QUALITY CONTROL / QUALITY ASSURANCE MANUAL August 2008 TABLE OF CONTENTS Section 1 - Introduction... 3 1.1 Defining Plan Quality...
More informationHow to Design and Build a Fence/G traverse Bridge or Graffiti Project
Outline Project Location Project Description Project History Site Constraints Geotechnical Investigation & Soil Profile Foundation Design Process Photos Project Location Project Limits: The Grand River
More informationMID-HUDSON SOUTH TRANSPORTATION COORDINATING COMMITTEE APRIL 6, 2011. TIP Public Review Meeting
MID-HUDSON SOUTH TRANSPORTATION COORDINATING COMMITTEE APRIL 6, 2011 TIP Public Review Meeting Meeting Agenda New York Metropolitan Transportation Council Major Products Transportation Improvement Program
More informationREQUEST FOR PROPOSAL. Consulting Services for a Thomas Street Corridor Master Plan
REQUEST FOR PROPOSAL Consulting Services for a Thomas Street Corridor Master Plan INTRODUCTION The city of Wausau is seeking a qualified planning, development, design, and engineering consultant to develop
More informationDesign of Bridges. Introduction. 3 rd to 4 th July 2012. Lecture for SPIN Training at the University of Dar es Salaam
Design of Bridges Introduction 3 rd to 4 th July 2012 1 FUNCTION OF A BRIDGE To connect two communities which are separated by streams, river, valley, or gorge, etc. 2 EVOLUTION OF BRIDGES 1. Log Bridge
More informationAging sewer pipes buried in the Bow River bed, from the foot of Muskrat Street to Glen Avenue must be replaced A raised crossing pipes crossing over
ewer utility crossing pedestrian bridge Aging sewer pipes buried in the Bow River bed, from the foot of Muskrat Street to Glen Avenue must be replaced A raised crossing pipes crossing over the river at
More informationProject Manager & Key Staff Standards for Technical Proposals Projects using Level A and/or Level B prequalification disciplines
Projects using Level A and/or Level B prequalification disciplines Project Manager PROJECT MANAGER Key Staff/ ROADWAY DESIGN (TP Section 5) (TP Section 6) BACHELORS DEGREE 4 TO 8 YEARS (TP Sections 6 &
More informationRoadway Congestion 139,600 135,300 134,700 NA 4,300 4,900. Table 7-2 Transportation Criteria - Roadway Congestion (2035)
7 Transportation Criteria 7.1 Introduction A goal of this project is to improve mobility in the corridor. To that end, all the major Project alternatives identified at this point in the study include significant
More informationThe Rehabilitation Alternative Huey P. Long Bridge Case Study. Bruce E. Peterson, P.E. Project Manager Modjeski and Masters, Inc.
The Rehabilitation Alternative Huey P. Long Bridge Case Study Bruce E. Peterson, P.E. Project Manager Modjeski and Masters, Inc. March 22, 2010 Replacement vs. Rehabilitation Project Background Introduction
More informationMicropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation
Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation Jeff R. Hill, P.E. Hayward Baker Inc. 111 W. Port Plaza Drive Suite 600 St. Louis, MO 63146 314-542-3040 JRHill@HaywardBaker.com
More informationLane Shutdowns and Mobile Operations
PERFORMANCE ACTIVITY 408 TREE REMOVAL WORK DESCRIPTION 1 WORK DESCRIPTION 2 Fallen Tree Standing Tree 408 TREE REMOVAL ACTIVITY DESCRIPTION Cut and remove tree as necessary. WORK DESCRIPTION 1 Fallen Tree
More informationBoston University Bridge Rehabilitation Project. June 30, 2009 6:30-8 p.m. Boston University Photonics Center
Boston University Bridge Rehabilitation Project June 30, 2009 6:30-8 p.m. Boston University Photonics Center Commonwealth of Massachusetts Governor Deval L. Patrick Lieutenant Governor Timothy Murray Energy
More informationSR-18 Corridor Improvements in Wood County
Public Meeting Information Package SR- Corridor Improvements in Wood County Thursday, May 19, 2011 10:00 a.m. to 1:00 p.m. Meeting Location: Hancock-Wood Electric Cooperative Building 1399 Business Park
More informationWindmill Hill Bulkhead Improvements Project. Community Meeting 2 April 13, 2015
Windmill Hill Bulkhead Improvements Project Community Meeting 2 April 13, 2015 Tonight s Meeting Agenda A. Introductions and overview B. Community Meeting 1 summary C. Recap of current conditions D. Improvement
More informationFederal Guidelines for STP-U Funding
MPC 5.f Attachment 1 STP-U Eligibility Guidelines Page 1 of 5 Federal Guidelines for STP-U Funding SURFACE TRANSPORTATION PROGRAM (STP) ELIGIBLE EXPENDITURES PERIOD AVAILABLE: FY + 3 Years FUND: Highway
More informationKENTUCKY TRANSPORTATION CABINET. Department of Rural and Municipal Aid. Office of Local Programs
KENTUCKY TRANSPORTATION CABINET Department of Rural and Municipal Aid Office of Local Programs Office of Local Programs Transportation Enhancements Safe Routes to School Congestion Mitigation and Air Quality
More informationBicycle and Pedestrian Subcommittee (BPS) Recommendation FY 2015 Transportation Alternatives Program (TAP) Allocation
Bicycle and Pedestrian Subcommittee (BPS) Recommendation FY 2015 Transportation Alternatives Program (TAP) Allocation The Montgomery Metropolitan Planning Organization (MPO) receives a direct annual allocation
More informationPeer Review Scope of Work
1.0 PROJECT OVERVIEW The St. Croix River Crossing Project has been developed in response to traffic congestion, operation deficiencies, safety concerns, and structural deficiencies of the Stillwater Lift
More informationBRUCE TOWNSHIP 32 MILE ROAD VILLAGE OF ROMEO 30 MILE ROAD CENTRAL SANITARY SEWER DISTRICT CAMPGROUND ROAD 28 MILE ROAD MOUND ROAD VAN DYKE AVENUE
26 MILE ROAD M-53 M-53 OWNER ENGINEER N TRUNKLINE SEWER AND SECTIONS 27, 34, 35, & 36 OF THE CENTRAL SANITARY SEWER DISTRICT T-4-S R-12-E,, SRF NO. 5623-01 BRUCE TOWNSHIP 32 MILE ROAD VILLAGE OF ROMEO
More informationSection 6 Traffic Analysis
Section 6 Traffic Analysis Traffic Operations of the Preferred Network Alternative After the Preferred Network was identified and confirmed by local policy makers and area residents, detailed traffic analysis
More informationSCOPE OF WORK for High Speed Rail and Intercity Passenger Rail Program Federal Grant Application Development
Draft 06162009 SCOPE OF WORK for High Speed Rail and Intercity Passenger Rail Program Federal Grant Application Development The Minnesota Department of Transportation (Mn/DOT) requires the services of
More informationComprehensive Mobility Project Development Process Capital Metro ¼-Cent Fund Analysis
Comprehensive Mobility Project Development Process Capital Metro ¼-Cent Fund Analysis Transportation & Mobility projects that meet the following criteria: enhances regional mobility; supports public transit;
More informationFederal Highway Administration 1200 New Jersey Avenue, SE Washington, DC 20590 202-366-4000
1 of 8 12/27/2013 8:21 AM U.S. Department of Transportation Federal Highway Administration 1200 New Jersey Avenue, SE Washington, DC 20590 202-366-4000 MAP-21 - Moving Ahead for Progress in the 21st Century
More informationArapaho & Roosevelt National Forests 2013 Flood: Long-term Recovery in a Changed Landscape
Arapaho & Roosevelt National Forests 2013 Flood: Long-term Recovery in a Changed Landscape Spring 2014 The flood of September 2013 changed the landscape of the Boulder and Canyon Lakes Ranger Districts.
More informationMarion County Public Works
Marion County Public Works Federally Funded Transportation Program Title VI Annual Accomplishment Report Fiscal Year 2014/15 Marion County Public Works Department Introduction The Marion County Department
More informationSoapstone Connector Feasibility Study
Technical Report Soapstone Connector Feasibility Study Prepared by ATCS, plc., 2553 Dulles View Drive, Herndon, VA 20171, (703) 430-7500 www.atcsplc.com In association with: Michael Baker Corporation,
More informationDIRECTIONS TO THE UNIVERSITY OF GEORGIA (print version)
DIRECTIONS TO THE UNIVERSITY OF GEORGIA (print version) Athens, Georgia - home to the University of Georgia - is located 60 miles northeast of Atlanta. TRAVELIING NORTH: US 129/441, Macon TRAVELING NORTH
More informationDesign Guidelines for School Site and Adjacent Lands Planning
Design Guidelines for School Site and Adjacent Lands ning Halton Technical Stakeholders Sub-Committee May 2011 ------------------------------------------------------- Acknowledgments Halton District School
More informationDowntown Tampa Transportation Vision
Downtown Tampa Transportation Vision Executive Summary August 1, 2006 Hillsborough County Metropolitan Planning Organization County Center, 18 th Floor Tampa, Florida 33602 813-272-5940 www.hillsboroughmpo.org
More informationCapacity Deficiency Project Application Jackson MPO Surface Transportation Program
Capacity Deficiency Project Application Jackson MPO Surface Transportation Program The following information must be completed for all Capacity Deficiency proposed Jackson MPO STP projects. MPO staff will
More informationBelmont Street Bridge Rehabilitation Project
Belmont Street Bridge Rehabilitation Project Christian Gospel Church Worcester 43 Belmont Street Worcester MA February 20, 2015 7:00PM Agenda Introductions Project site and overview Project history Construction
More information