1 The Rehabilitation Alternative Huey P. Long Bridge Case Study Bruce E. Peterson, P.E. Project Manager Modjeski and Masters, Inc. March 22, 2010
2 Replacement vs. Rehabilitation Project Background Introduction 4 Construction Contracts Main Bridge Substructure Main Bridge Superstructure Truss Widening Railroad Modifications Approaches and Main Bridge Deck Widening EXISTING BREAK Project Status Project Timeline Construction Photographs PROPOSED WIDENING
3 Replacement vs. Rehabilitation Bridge construction represents a large capital investment. Through time, all bridges receive routine maintenance. However, eventually they must be replaced or rehabilitated. Beyond the obvious difference in cost, there are other significant differences between these two approaches. How is the decision made? What influences the choice between these two alternatives?
4 Replacement vs. Rehabilitation Louisiana Dept. of Transportation and Development (LADOTD) Methodology for Selecting and Programming Bridges for Replacement and Rehabilitation Priority for the selection of bridges for replacement or rehabilitation with Federal bridge replacement funds based on three (3) parameters: 1. Structural adequacy 2. Functional adequacy and serviceability 3. Essential for public use
5 Replacement vs. Rehabilitation The three parameters are based on the following information: 1. Structural deficiency 2. Posted bridges (weight limits below statutory limits) 3. Traffic count (ADT) 4. Class of highway 5. Available detour routes 6. Bridge geometry (particularly bridges < 20 ft. wide) 7. Bridge inspection reports 8. Local district recommendations for replacement (submitted annually)
6 Replacement vs. Rehabilitation Federal Highway Administration (FHWA) formula for prioritizing bridges Overall rating called a sufficiency rating Sufficiency rating assigns a numeric value ranging from 0 to 100 to a given bridge with the following percentage points applied to each parameter ITEM WEIGHT Structural Adequacy 55 % Functional Adequacy and Serviceability 30 % Essential For Public Use 15 %
7 Replacement vs. Rehabilitation Requirement for replacement: Sufficiency Rating < 50 Classification as structurally deficient or functionally obsolete Requirement for rehabilitation: Sufficiency Rating < 80
8 Replacement vs. Rehabilitation As previously noted there are three elements to the Sufficiency Rating 1. Structural Adequacy 2. Functional Adequacy and Serviceability 3. Essential for Public Use Let s examine each in detail.
9 Replacement vs. Rehabilitation Structural Adequacy Most important factor in evaluation process as a bridge failure could be catastrophic Determined from: List of posted bridges (bridges with load restrictions) Bridge inspection reports Local district recommendations
10 Replacement vs. Rehabilitation Functional Adequacy and Serviceability Bridge geometry a key element Clear roadway width most important factor Narrow bridges, if structurally adequate, can be widened rather than replaced Determined from: Bridge inspection reports Local district recommendations
11 Replacement vs. Rehabilitation Functional Adequacy and Serviceability (con d) Serviceability is related to factors such as Stream scour Maintenance for movable bridges Deck deterioration Other important factors include frequency and severity of marine, railroad, and automotive traffic accidents
12 Replacement vs. Rehabilitation Essential For Public Use Determined by the: Traffic count (ADT) Class of highway Available detour routes Structural and functional adequacy of the bridge is evaluated with the traffic count in order to minimize exposure to unsafe conditions Example: two bridges with the same degree of inadequacy, the one with the higher traffic volume would receive the higher priority
13 Replacement vs. Rehabilitation Essential For Public Use (con d) Bridges located on a truck or school bus route or crosses a major river or stream receive extra attention Non-redundant routes (no available detours) receive a higher priority than bridges on redundant routes
14 Replacement vs. Rehabilitation How Select? Numerous rational methods available Recommended procedure for State of Louisiana 1. Compile 3 lists Bridges with lowest sufficiency rating Bridges with the highest priority based on local district recommendations Bridges that are most severely posted for load restrictions 2. Generally, if a bridge makes all three lists, it will have a high priority for replacement
15 Replacement vs. Rehabilitation Sufficiency Rating Posted Bridges List STRUCTURAL ADEQUACY Bridge Inspection Report District Recommendations Sufficiency Rating Bridge Geometry, Accidents, etc. FUNCTIONAL ADEQUACY AND SERVICEABILITY Bridge Inspection Report District Recommendations Sufficiency Rating Highway Class and Traffic Count (ADT) ESSENTIALLITY TO THE PUBLIC Available Detour Routes District Recommendations Traffic Type FINAL ORDER OF PRIORITY Source: LADOTD Bridge Design Manual
16 Replacement vs. Rehabilitation Other Considerations - Replacement Pros: 1. New structure would meet all current standards Loads Geometry Highway standards 2. New Construction Do not have to connect new components with existing ones. Reduced potential for surprises during construction 3. Estimating construction cost potentially more accurate Cons: 1. Potential for greater environmental impacts 2. Potential for greater costs 3. Potential need for more right-of-way 4. Can require time for public to agree on a location and other impacts related to a new structure 5. Can take more time from start of planning to final completion and delivery to public 6. Removal of an historic structure
17 Replacement vs. Rehabilitation Other Considerations - Rehabilitation Pros: 1. Have the potential to reuse existing elements, thus saving time and money 2. Potentially less environmental impacts 3. Potentially less right-of-way requirements 4. Can fix some legacy issues that do not meet current standards or are less than desirable Cons: 1. Increased potential for problems and unknown discoveries with the existing structure 2. Greater demands on determination of existing conditions, details, geometry, etc. in order to produce accurate plans 3. Ability to meet all current standards may be difficult 4. Accurate estimation of construction costs can be difficult 5. Modification of an historic structure
18 Replacement vs. Rehabilitation Other Considerations (con d) Environmental Historic structure? Impacts? Remaining life of structure Structural condition (corrosion) and capacity Remaining fatigue life
19 Replacement vs. Rehabilitation Other Considerations (con d) Owner s Concerns and Issues 1. Time required to perform the work 2. Funding Available local funding? Federal funds available? 3. Public Wants the work completed yesterday Does not want to be inconvenienced during the work Low cost (no increased direct costs; e.g.. taxes, tolls, etc.) While doing this work, why not fix these other problems and/or address other needs... it s only a little more $$ (scope creep)
20 Replacement vs. Rehabilitation Where does the Huey P. Long Bridge fit within this criteria? Structurally Adequacy? - GOOD Excellent condition; adequate strength Reduced fatigue life of stringers and floorbeam brackets Functionally Adequacy and Serviceability? - POOR 18 feet wide roadways Barriers not current standards Essential For Public Use? - ESSENTIAL Few Mississippi River crossings in metro region; essential for highway traffic Only rail crossing of Miss. River south of Baton Rouge
21 Location New Orleans Metro Area French Quarter Huey P. Long Bridge
22 Before the Bridge
23 Before the Bridge
24 Construction of The Existing Bridge
25 Construction of The Existing Bridge
26 Construction of The Existing Bridge
27 Construction of The Existing Bridge
28 Construction of The Existing Bridge
29 Construction of The Existing Bridge
30 Background Huey P. Long Bridge Completed in December 1935, the bridge is one of the longest railroad bridges in the world.
31 Background Huey P. Long Bridge Combined railroad highway bridge 2 tracks 4 lanes 9 ft. width
32 Background Huey P. Long Bridge Very heavily built Carries largest modern RR load without distress Many years of service life remaining
33 Project Background By widening the existing structure rather than constructing a new river crossing: Reduce environmental impact, property takings. Reduce project cost. Reuse existing right-ofway and traffic corridors. Final report published April 1988.
34 Project Background EXISTING PROPOSED WIDENING
35 Project Background Study of new bridge in corridor; 5 alternates considered. High cost and large amount of ROW; project dropped. LADOTD authorized M&M to perform conceptual widening study. 3 widening alternates considered Geotechnical investigation of soil capacity under caissons Present Preliminary Design Main Bridge; Fatigue Evaluation. Line and Grade Study Approaches. Environmental Processing Agency Consensus Completion of final design plans; main bridge widening, railroad modifications, and approaches, Construction main bridge substructure widening, railroad modifications, and main bridge superstructure widening.
36 Huey P. Long Widening Project START PROJECT WEST BANK RR MOD EAST BANK APPR. END PROJECT WEST BANK APPR. EAST BANK RR MOD MAIN BRIDGE PIER, TRUSS, AND DECK WIDENING
37 Main Bridge Pier Widening START PROJECT WEST BANK RR MOD EAST BANK APPR. END PROJECT WEST BANK APPR. EAST BANK RR MOD MAIN BRIDGE PIER, TRUSS, AND DECK WIDENING
38 Main Bridge Pier Widening EXISTING Pier A Piers I & II Pier III Pier IV PROPOSED WIDENING
39 Widened Pier Steel Frame Caisson Upper Encase Lower Encase
40 Widened Pier - Details The upper portion of the pier widening is composed of a steel frame. The steel frame significantly reduces the loads on the pier by eliminating concrete and permits the center bearing to be jacked, relieving load from the exterior bearings. This is beneficial by reducing load on the end faces of the existing concrete distribution block on top of the existing caisson.
41 Widened Pier - Details The steel frame will also permit more accurate setting and adjustment of the final bearing elevations after the lower encasement is poured. Inspection access will be provided for the steel metalwork in the upper portion of the pier widening.
42 Widened Pier - Details Constructability of Pier Frame Must be constructed around existing pier No construction access from above due to existing superstructure Staged construction Key splice locations.
43 Widened Pier - Details The lower portion of the encasement serves several functions The nose areas are columns to support the widening truss support bearings. The remainder confines the existing pier concrete and granite masonry blocks which currently has minimal reinforcing.
44 Widened Pier - Details
45 Widened Pier - Details
46 Strength of the Existing Concrete One of the major questions for widening the substructure was the strength of the existing concrete. Existing concrete was specified for 2000 psi. Based on construction records, actual strength much higher Using methods to estimate moderate amount of additional concrete strengthening with aging, 4000 psi could be used with confidence for the strength of the existing concrete.
47 Strength of the Existing Concrete PIER AND CAISSON CONCRETE STRENGTHS LOCATION USED Piers 3,800 4,500 8,800 4,000 Caisson 3,300 3,870 7,565 3, = ACI Committee 209, Prediction of Creep, Shrinkage, and Temperature Effects in Concrete Structures (ACI 209R-92) = Properties of Concrete by A. M. Neville
48 Existing Pier Conditions Underwater Acoustic Inspection performed April 2006 by C. H. Fenstermaker & Associates. Piers I, II, III, & IV examined and found to be in good condition. The equipment provided detailed information of the existing conditions. Examination though the use of a diver would be more costly, must be performed in extreme low to no visibility, and is dangerous.
49 Existing Pier Conditions Pier I North Face
50 Existing Pier Conditions Pier II West Nose
51 Main Bridge Truss Widening START PROJECT WEST BANK RR MOD EAST BANK APPR. END PROJECT WEST BANK APPR. EAST BANK RR MOD MAIN BRIDGE PIER, TRUSS, AND DECK WIDENING
52 Main Bridge Truss Widening Cantilever Truss Span Simple Through Truss Span EXISTING PROPOSED WIDENING
53 Cross Sections Existing Bridge
54 Widened Main Bridge Features 2 new trusses added, parallel to existing trusses. Roadways widened from 18 ft. to 43 ft. Currently: 2 9 ft. lanes No offset Proposed: 3 11 ft. lanes 8 ft. shoulder 2 ft. offset
55 Normal terminology for truss bridges would be U.S. & D.S. trusses. Widened HPL Bridge is a multiple truss plane structure U.S. Widening Truss U.S. Existing Truss D.S. Existing Truss D.S. Widening Truss Nomenclature
56 2D versus 3D Analysis and Design Traditional Truss Analysis (2D) Vertical loads, e.g. D & L, supported by main (vertical) trusses Transverse loads, e.g. W, supported by top and bottom lateral trusses, sway frames, and portals
57 2D versus 3D Analysis and Design 3 Dimensional Analysis Used Widened bridge is multiple truss plane system 3D analysis reflects the reality of the structure and its behavior Load sharing will occur and it is beneficial Members not normally supporting live load will have live loads Need to know the amount of live load in non-traditional live load supporting members.
58 2D versus 3D Analysis and Design 3D SAP Computer Model
59 Floorbeam and Hangers Superposition needed to solve final forces in the existing and widened hangers Moment and sequence of construction affect forces
60 Construction and Erection Method and Sequence of Construction provided in Contract Plans Contractor proposed option also available in contract plans Contractor proposed his own method
61 Maintenance of Traffic Through Construction Marine Traffic Maintained same vertical and horizontal clearances Rail Traffic Maintained Vehicular Traffic Maintained by use of staged construction
62 Main Bridge Maintenance of Traffic WORK PERFORMED IN TRUSS WIDENING CONTRACT
63 Main Bridge Maintenance of Traffic - Stage 1 WORK PERFORMED IN TRUSS WIDENING CONTRACT
64 Main Bridge Maintenance of Traffic - Stage 2 WORK PERFORMED IN TRUSS WIDENING CONTRACT PREVIOUS STAGE
65 Main Bridge Maintenance of Traffic - Stage 3 WORK PERFORMED IN TRUSS WIDENING CONTRACT PREVIOUS STAGE
66 Main Bridge Maintenance of Traffic - Stage 4 WORK PERFORMED IN APPROACH AND DECK WIDENING CONTRACT PREVIOUS STAGE
67 Main Bridge Maintenance of Traffic - Stage 4-5 SWITCH TRAFFIC
68 Main Bridge Maintenance of Traffic - Stage 5 WORK PERFORMED IN APPROACH AND DECK WIDENING CONTRACT PREVIOUS STAGE
69 Main Bridge Maintenance of Traffic - Stage 6 WORK PERFORMED IN APPROACH AND DECK WIDENING CONTRACT PREVIOUS STAGE
70 Main Bridge Maintenance of Traffic - Stage 7 WORK PERFORMED IN APPROACH AND DECK WIDENING CONTRACT PREVIOUS STAGE
71 Top laterals, bottom laterals, sway frames, and portal frames must hinge to permit movement Erect rigid part over roadways open to traffic; hinge remaining part. Deflection Issues
72 Railroad Modifications - Westbank START PROJECT WEST BANK RR MOD EAST BANK APPR. END PROJECT WEST BANK APPR. EAST BANK RR MOD MAIN BRIDGE PIER, TRUSS, AND DECK WIDENING
73 Railroad Modifications - Westbank Project Site Railroad LA 18 Hwy. 90 EXISTING
74 Huey P. Long Widening Project Westbank Railroad Modifications LA18 Existing Site Conditions US HWY 90 To Huey P. Long Bridge
75 Huey P. Long Widening Project Westbank Railroad Modifications Replacement Support LA18 Future Roadway US HWY 90 To Huey P. Long Bridge Final Site Conditions
76 Huey P. Long Widening Project Westbank Railroad Modifications
77 Huey P. Long Widening Project Westbank Railroad Modifications
78 Huey P. Long Widening Project Westbank Railroad Modifications
79 Westbank Sequence of Construction 1. Construct foundations for new cross girders 2. Install falsework to lift existing girder spans 3. Begin 24 hour rail traffic closure 4. Lift existing girder spans off steel tower 5. Remove upper portion steel tower 6. Erect cross girders 7. Lower existing girder spans onto new cross girders 8. Restore rail traffic 9. Remove remaining portion of steel tower 24 HOUR RAIL CLOSURE
80 Railroad Modifications - Eastbank START PROJECT WESTBANK RR MOD EASTBANK APPR. END PROJECT WESTBANK APPR. EASTBANK RR MOD MAIN BRIDGE PIER, TRUSS, AND DECK WIDENING
81 Railroad Modifications - Eastbank Clearview Pkwy. EXISTING Project Site Jefferson Hwy
82 Huey P. Long Widening Project Eastbank Railroad Modifications Vacant Gas Station Clearview Pkwy. Power Poles & Power Line To Huey P. Long Bridge Jefferson Hwy. Existing Site Conditions QWEST Line Existing Superstructure and Towers to be Replaced
83 Huey P. Long Widening Project Eastbank Railroad Modifications New Bents Clearview Pkwy. Vacant Gas Station Future Elevated Roadway Future Roadway Final Site Conditions QWEST Line Jefferson Hwy. To Huey P. Long Bridge
84 Huey P. Long Widening Project Eastbank Railroad Modifications
85 Eastbank Sequence of Construction 1. Construct new concrete straddle bents 2. Prepare steel tower and other falsework 3. Begin 24 hour rail traffic closure 4. Remove girders under one of the tracks 5. Erect new girders for one track 6. Re-establish track 7. Restore rail traffic 8. Repeat girder replacement for other track (Steps 3 7 above) 9. Remove steel tower 24 HOUR RAIL CLOSURE
86 Approaches & Deck Widening START PROJECT WEST BANK RR MOD EAST BANK APPR. END PROJECT WEST BANK APPR. EAST BANK RR MOD MAIN BRIDGE PIER, TRUSS, AND DECK WIDENING
87 Approaches & Deck Widening Start Project Bridge City Ave. Interchange WEST BANK APPROACH Conflict w/ Existing Rdwy
88 Approaches & Deck Widening Cantilever Truss Span Simple Through Truss Span EXISTING PROPOSED WIDENING
89 Approaches & Deck Widening Jefferson Hwy Interchange End Project NOPBRR Spur Conflict w/ Existing Rdwy EAST BANK APPROACH
90 Approaches & Deck Widening
91 Approaches & Deck Widening EB APPR. EB APPR.
92 Approaches & Deck Widening Created using Google SketchUp
93 Approaches & Deck Widening W.P. CAP TRUMPET TRUMPET PC COLUMN FOUNDATION
94 Approaches & Deck Widening TOTAL SUBSTRUCTURE UNITS X 6 COLUMN BENTS 8 x 14 8 x 12 6 x 12 4 x 6
95 Approaches & Deck Widening Column Type 4: 8 x 14 Column Type 3: 8 x 12 Column Type 2: 6 x 12 Column Type 1: 4 x 6
96 Approaches & Deck Widening Trumpet for 8 x 14 Columns Trumpets for 6 & 8 x 12 columns Trumpet for 4 x 6 columns 8 x 14 6 x 12 8 x 12 4 x 6
97 Approaches & Deck Widening Adjust Footing Depth As Necessary Typical Bent Full Height Trumpet Sub- Trumpet Size 1 Sub- Trumpet Size 2
98 Main Bridge Deck Widening WORK PERFORMED IN APPROACH CONTRACT
99 Approaches & Deck Widening West Bank Approach - West Bank Bound East Bank Approach - East Bank Bound
100 Approaches & Deck Widening WB APPR. Location of West Bank Steel Girder Spans West Bank Approach East Bank Bound
101 Approaches & Deck Widening Location of East Bank Steel Girder Spans EB APPR. East Bank Approach West Bank Bound
102 Approaches & Deck Widening
103 Approaches & Deck Widening SWITCH TRAFFIC
104 Project Timeline Project Schedule Main Bridge Substructure Railroad Modifications Superstructure Fabrication & Erection Approaches & Main Bridge Re-decking Work Completed Railroad Modifications Main Bridge Pier Widening Work Under Construction Main Bridge Truss Widening West Bank Approach, Main Bridge Deck Widening, East Bank Approach
105 Project Status Completed Main Bridge Pier Widening Letting Date: December 14, 2005 Notice To Proceed Date: April 10, 2006 Construction Bid: $ 98,826,907 Contractor: Massman Construction Co.
106 Main Bridge Pier Widening EXISTING Pier A Piers I & II Pier III Pier IV PROPOSED WIDENING
107 Main Bridge Pier Widening
108 Main Bridge Pier Widening
109 Main Bridge Pier Widening
110 Main Bridge Pier Widening
111 Main Bridge Pier Widening Distribution Block
112 Main Bridge Pier Widening
113 Main Bridge Pier Widening
114 Main Bridge Pier Widening
115 Main Bridge Pier Widening
116 Main Bridge Pier Widening
117 Main Bridge Pier Widening
118 Main Bridge Pier Widening
119 Main Bridge Pier Widening
120 Main Bridge Pier Widening
121 Main Bridge Pier Widening
122 Main Bridge Pier Widening
123 Main Bridge Pier Widening
124 Main Bridge Pier Widening
125 Main Bridge Pier Widening G&G Steel New Orleans
126 Main Bridge Pier Widening
127 Main Bridge Pier Widening
128 Main Bridge Pier Widening
129 Main Bridge Pier Widening
130 Main Bridge Pier Widening
131 Main Bridge Pier Widening
132 Main Bridge Pier Widening
133 Main Bridge Pier Widening
134 Main Bridge Pier Widening
135 Main Bridge Pier Widening
136 Main Bridge Pier Widening
137 Main Bridge Pier Widening
138 Main Bridge Pier Widening
139 Main Bridge Pier Widening
140 Main Bridge Pier Widening
141 Main Bridge Pier Widening
142 Project Status - Completed Railroad Modifications Letting Date: May 10, 2006 Notice To Proceed Date: August 28, 2006 Construction Bid: $ 13,782,713 Contractor: Boh Bros. Construction Co.
143 Railroad Modifications - Westbank Project Site Railroad LA 18 Hwy. 90 EXISTING
144 Railroad Modifications - Westbank
145 Railroad Modifications - Westbank
146 Railroad Modifications - Westbank
147 Railroad Modifications - Westbank G&G Steel New Orleans
148 Railroad Modifications - Westbank
149 Railroad Modifications - Westbank
150 Railroad Modifications - Westbank
151 Railroad Modifications - Westbank
152 Railroad Modifications - Westbank
153 Railroad Modifications - Westbank
154 Railroad Modifications - Westbank
155 Railroad Modifications - Eastbank Clearview Pkwy. EXISTING Project Site Jefferson Hwy
156 Railroad Modifications - Eastbank
157 Railroad Modifications - Eastbank
158 Huey P. Long Widening Project Eastbank Railroad Modifications
159 Railroad Modifications - Eastbank
160 Railroad Modifications - Eastbank
161 Railroad Modifications - Eastbank
162 Railroad Modifications - Eastbank
163 Railroad Modifications - Eastbank
164 Railroad Modifications - Eastbank
165 Railroad Modifications - Eastbank
166 Railroad Modifications - Eastbank
167 Railroad Modifications - Eastbank
168 Project Status Under Construction Main Bridge Truss Widening Letting Date: March 28, 2007 Notice to Proceed Date: November 5, 2007 Construction Bid: $ 452,605,568 Contractor: Massman Construction Co., Traylor Brothers Inc., and IHI, Inc.
169 Main Bridge Truss Widening Cantilever Truss Span Simple Through Truss Span EXISTING PROPOSED WIDENING
170 Main Bridge Truss Widening Industrial Steel Construction Gary, IN New Orleans
171 Main Bridge Truss Widening Truss Monitoring STATIC MONITORING SYSTEM 433 Members (777 Vibrating Wire Strain Gages) 5 Piers (10 Vibrating Wire Tilt Meters) Wind Speed/Direction DYNAMIC (LIVE LOAD) MONITORING SYSTEM 31 Members (50 Electrical Resistance Strain Gages)
172 Main Bridge Truss Widening Work Platform
173 Main Bridge Truss Widening Work Platform
174 Main Bridge Truss Widening Floorbeam Modifications Template Fit Up Check
175 Main Bridge Truss Widening Floorbeam Modifications Installation of Wedge Fill
176 Main Bridge Truss Widening Floorbeam Modifications Installation of Wedge Fill
177 Main Bridge Truss Widening Work on Existing Structure Bottom Chord
178 Main Bridge Truss Widening Work on Existing Structure Top Chord
179 Main Bridge Truss Widening Widening Truss Bottom Laterals
180 Main Bridge Truss Widening Remove Existing Sidewalk Install Temporary Steel Barrier
181 Main Bridge Truss Widening Main Bridge Erection - Methods A B A B B A = Stick Build B = Span by Span
182 Main Bridge Truss Widening Main Bridge Erection
183 Main Bridge Truss Widening Main Bridge Erection
184 Main Bridge Truss Widening Main Bridge Erection
185 Main Bridge Truss Widening Main Bridge Erection
186 Main Bridge Truss Widening Main Bridge Erection
187 Main Bridge Truss Widening Main Bridge Erection
188 Main Bridge Truss Widening Main Bridge Erection
189 Main Bridge Truss Widening Main Bridge Erection
190 Main Bridge Truss Widening Main Bridge Erection December 2009
191 Main Bridge Truss Widening Main Bridge Erection December 2009
192 Main Bridge Truss Widening Contractor s Erection Scheme Span by Span Erection East Anchor Arm Suspended Span Through Truss Span
193 Project Status Under Construction West Bank Approach, Main Bridge Deck Widening, East Bank Approach Letting Date: March 19, 2008 Notice to Proceed Date: May 5, 2008 Construction Bid: $ 433,950,000 Contractor: Kiewit Massman Traylor Constructors
194 Approaches & Deck Widening START PROJECT WEST BANK RR MOD EAST BANK APPR. END PROJECT WEST BANK APPR. EAST BANK RR MOD MAIN BRIDGE PIER, TRUSS, AND DECK WIDENING
195 Approaches & Deck Widening Box Culverts
196 Approaches & Deck Widening At Grade Roadways West Bank
197 Approaches & Deck Widening Foundations - Westbank
198 Approaches & Deck Widening Foundations - Westbank
199 Approaches & Deck Widening Substructure - Westbank
200 Approaches & Deck Widening Substructure - Westbank
201 Approaches & Deck Widening Superstructure - Westbank
202 Approaches & Deck Widening Superstructure - Westbank
203 Approaches & Deck Widening Superstructure - Westbank
204 Approaches & Deck Widening Superstructure - Westbank
205 Approaches & Deck Widening Superstructure - Westbank
206 Approaches & Deck Widening Superstructure - Westbank
207 Approaches & Deck Widening Superstructure - Westbank
208 Approaches & Deck Widening Substructure Pier IVA Created using Google SketchUp
209 Approaches & Deck Widening Substructure Pier IVA
210 The Rehabilitation Alternative Huey P. Long Bridge Case Study
211 Q & A 1. Priority for the selection of bridges for replacement or rehabilitation with Federal bridge replacement funds based on three parameters. Name them.? 2. Of the three parameters above, which is given the highest weight?? 3. What Sufficiency Rating is required for replacement?? 4. Bridge geometry is a key element of Functional Adequacy and Serviceability. What is the most important factor within bridge geometry?? 5. For the case study project, name one key design challenge?? 6. For the case study project, how was approach bent formwork simplified??
212 Q & A 1. Priority for the selection of bridges for replacement or rehabilitation with Federal bridge replacement funds based on three parameters. Name them. Structural adequacy, functional adequacy and serviceability, and essential for public use. 2. Of the three parameters above, which is given the highest weight? Structural adequacy 3. What Sufficiency Rating is required for replacement? < Bridge geometry is a key element of Functional Adequacy and Serviceability. What is the most important factor within bridge geometry? Clear roadway width 5. For the case study project, name one key design challenge? Maintenance of traffic, deflection between existing and widened structures, not imposing deflection induced loads into the existing bridge. 6. For the case study project, how was approach bent formwork simplified? 2/3 s of the forms were the same, and the rest required only simple formwork changes
US 51 Ohio River Bridge Engineering and Environmental Study
US 51 Ohio River Bridge Engineering and Environmental Study ITEM NOS. 1-100.00 & 1-1140.00 Prepared by: Michael Baker Jr., Inc. 9750 Ormsby Station Rd Louisville, KY 40223 August 16, 2013 Table of Contents
More informationSafe & Sound Bridge Terminology
Safe & Sound Bridge Terminology Abutment A retaining wall supporting the ends of a bridge, and, in general, retaining or supporting the approach embankment. Approach The part of the bridge that carries
More information3.1 Historical Considerations
3. Recommended Scope of Bridge improvements 3.1 Historical Considerations In the fall of 2000, an outside consultant, Fraser Design, suggested that the existing 4 th St. Bridge is potentially eligible
More informationREHABILITATION PACKAGE 1-a
1-a WINONA BRIDGE (BRIDGE 5900) REHABILITATION PACKAGE 1-a Rehab option 1-a is a rehabilitation package whereby all spans of the existing structure would be rehabilitated to the degree feasible and strengthened
More informationSewalls Falls Road Bridge. Cultural Resource Meeting April 4, 2013
Sewalls Falls Road Bridge Cultural Resource Meeting April 4, 2013 Meeting Purpose Review of the project process to date Project replacement vs. rehabilitation Review of recent public process Review of
More informationInformational Workshop Public Meeting Kanawha Falls Bridge Project
Informational Workshop Public Meeting Kanawha Falls Project WV Department of Transportation Division of Highways in Cooperation with the Federal Highway Administration State Project S310-13-0.02 00 Federal
More information3 Tappan Zee Bridge Rehabilitation Options
3 Tappan Zee Bridge Rehabilitation Options 3.1 Introduction This chapter describes possible options that rehabilitate and enhance the existing Tappan Zee Bridge. Four Rehabilitation Options have been developed:
More information2015 ODOT Bridge Design Conference May 12, 2014. DeJong Rd Bridge High- Seismic Zone Case Study: Bridge Rehab vs. Replacement.
2015 ODOT Bridge Design Conference May 12, 2014 DeJong Rd Bridge High- Seismic Zone Case Study: Bridge Rehab vs. Replacement Mary Ann Triska 2015 HDR, all rights reserved. Presentation Outline Project
More informationOpen House Public Meeting for the Thurmond Bridge Rehabilitation Project State Project: State Project S310-25/2-0.10 Federal Project: BR-0252(001)D
Open House Public Meeting for the State Project: State Project S310-25/2-0.10 Federal Project: BR-0252(001)D May 7, 2015 Old Glen Jean Bank Glean Jean, WV 4:00-7:00 PM www.transportation.wv.gov PROJECT
More informationNational Council of Examiners for Engineering and Surveying. Principles and Practice of Engineering Structural Examination
Structural Effective Beginning with the April 2011 The structural engineering exam is a breadth and exam examination offered in two components on successive days. The 8-hour Vertical Forces (Gravity/Other)
More informationCONCEPTUAL REHABILITATION ALTERNATIVE
Appendix D While federal law requires preservation/rehabilitation of historic bridges be considered, there is no standard procedure to determine when rehabilitation is appropriate and when replacement
More informationChallenging Skew: Higgins Road Steel I-Girder Bridge over I-90 OTEC 2015 - October 27, 2015 Session 26
2014 HDR Architecture, 2014 2014 HDR, HDR, Inc., all all rights reserved. Challenging Skew: Higgins Road Steel I-Girder Bridge over I-90 OTEC 2015 - October 27, 2015 Session 26 Brandon Chavel, PhD, P.E.,
More informationMicropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation
Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation Jeff R. Hill, P.E. Hayward Baker Inc. 111 W. Port Plaza Drive Suite 600 St. Louis, MO 63146 314-542-3040 JRHill@HaywardBaker.com
More informationFEBRUARY 2014 LRFD BRIDGE DESIGN 4-1
FEBRUARY 2014 LRFD BRIDGE DESIGN 4-1 4. STRUCTURAL ANALYSIS AND EVALUATION The analysis of bridges and structures is a mixture of science and engineering judgment. In most cases, use simple models with
More informationRed Wing Bridge Project. PAC #5/TAC #8 Meeting July 18, 2013
Red Wing Bridge Project PAC #5/TAC #8 Meeting July 18, 2013 Alternatives Analysis Agenda Overview of Past Progress Progress Since April PAC Bridge 9103 Rehabilitation Study Bridge 9040 Rehab vs. Replacement
More informationDesign of Bridges. Introduction. 3 rd to 4 th July 2012. Lecture for SPIN Training at the University of Dar es Salaam
Design of Bridges Introduction 3 rd to 4 th July 2012 1 FUNCTION OF A BRIDGE To connect two communities which are separated by streams, river, valley, or gorge, etc. 2 EVOLUTION OF BRIDGES 1. Log Bridge
More informationMethodology to Identify Preservation Priority Bridges
Methodology to Identify Preservation Priority Bridges Louisiana Historic Bridge Inventory Task 8 Prepared for Louisiana Department of Transportation and Development Prepared by www.meadhunt.com November
More informationPublic Information & Public Scoping Meeting
Public Information & Public Scoping Meeting William F. Cribari Memorial Bridge Route 136 over the Saugatuck River Review of Rehabilitation Study Report Public Scoping for the gathering and analysis of
More informationResidential Deck Safety, Construction, and Repair
Juneau Permit Center, 4 th Floor Marine View Center, (907)586-0770 This handout is designed to help you build your deck to comply with the 2006 International Residential Building code as modified by the
More informationEvaluation of Appropriate Maintenance, Repair and Rehabilitation Methods for Iowa Bridges
T. J. Wipf, F. S. Fanous, F. W. Klaiber, A. S. Eapen Evaluation of Appropriate Maintenance, Repair and Rehabilitation Methods for Iowa Bridges April 2003 Sponsored by the Iowa Department of Transportation
More informationIH-635 MANAGED LANES PROJECT, SEG. 3.2
IH-635 MANAGED LANES PROJECT, SEG. 3.2 Location: Dallas, Texas Owner: Texas Department of Transportation Client: Ferrovial Agroman Construction Cost: $1 Billion Construction Completion Date: December,
More information4B-2. 2. The stiffness of the floor and roof diaphragms. 3. The relative flexural and shear stiffness of the shear walls and of connections.
Shear Walls Buildings that use shear walls as the lateral force-resisting system can be designed to provide a safe, serviceable, and economical solution for wind and earthquake resistance. Shear walls
More informationAnalysis of the Response Under Live Loads of Two New Cable Stayed Bridges Built in Mexico
Analysis of the Response Under Live Loads of Two New Cable Stayed Bridges Built in Mexico Roberto Gómez, Raul Sánchez-García, J.A. Escobar and Luis M. Arenas-García Abstract In this paper we study the
More informationINDIANA DEPARTMENT OF TRANSPORTATION BRIDGE INSPECTION PROGRAM CODING GUIDE
INDIANA DEPARTMENT OF TRANSPORTATION BRIDGE INSPECTION PROGRAM CODING GUIDE BRAGI Bridge Reporting for Appraisal & Greater Inventory Volume III: Other INDOT Items November 2011 Item Number Item Name BRAGI
More information~iffiui ~ Bridge Condition Survey. Inspection Date: 21 May 2003 District: San Angelo County: Tom Green Highway:
Texas Depadment of Transpo,tation Bridge Condition Survey Inspection Date: 21 May 2003 District: San Angelo County: Tom Green Highway: Irving Street Facility Name: Lone Wolf Bridge Structure Number: B00315-031
More informationDesign of Steel Structures Prof. S.R.Satish Kumar and Prof. A.R.Santha Kumar. Fig. 7.21 some of the trusses that are used in steel bridges
7.7 Truss bridges Fig. 7.21 some of the trusses that are used in steel bridges Truss Girders, lattice girders or open web girders are efficient and economical structural systems, since the members experience
More informationField Damage Inspection and Static Load Test Analysis of Jiamusi Highway Prestressed Concrete Bridge in China
Advanced Materials Research Vols. 163-167 (2011) pp 1147-1156 Online available since 2010/Dec/06 at www.scientific.net (2011) Trans Tech Publications, Switzerland doi:10.4028/www.scientific.net/amr.163-167.1147
More informationRehabilitation of the Red Bank Road Bridge over Hoover Reservoir. Presented By: Doug Stachler, P.E.
Rehabilitation of the Red Bank Road Bridge over Hoover Reservoir Presented By: Doug Stachler, P.E. Project Organization Owner Delaware County Engineers Office Design Consultant CH2M HILL Contractor Double
More informationCITY OF TRAIL MEMORANDUM
0 C CITY OF TRAIL MEMORANDUM DATE: TO: FROM: SUBJECT: March 24, 2011 FILE NO. 5400-02 DAVID PEREHJJDOFF, CHIEF ADM1NTSTRATIVE OFFICER WARREN PROULX, ENGINEERING TECHMCIAN OLD TRAIL BRIDGE With the interest
More informationChapter 3 Pre-Installation, Foundations and Piers
Chapter 3 Pre-Installation, Foundations and Piers 3-1 Pre-Installation Establishes the minimum requirements for the siting, design, materials, access, and installation of manufactured dwellings, accessory
More information1,045 m length of the Deh Cho Bridge
Innovative Design Features: Lightweight truss: The principles of lightweight design led to a saving of 25% in the use of structural steel. State of the art deck system: Designed as a four-way slab, it
More informationOptimum proportions for the design of suspension bridge
Journal of Civil Engineering (IEB), 34 (1) (26) 1-14 Optimum proportions for the design of suspension bridge Tanvir Manzur and Alamgir Habib Department of Civil Engineering Bangladesh University of Engineering
More informationDraft Table of Contents. Building Code Requirements for Structural Concrete and Commentary ACI 318-14
Draft Table of Contents Building Code Requirements for Structural Concrete and Commentary ACI 318-14 BUILDING CODE REQUIREMENTS FOR STRUCTURAL CONCRETE (ACI 318 14) Chapter 1 General 1.1 Scope of ACI 318
More informationStay Cable Replacement of the Luling Bridge
Stay Cable Replacement of the Luling Bridge Armin Mehrabi, Bridge Engineering Solutions, PC 2009 Louisiana Transportation Engineering Conference February 8-11, 2009, Baton Rouge, LA Lower Anchorage Upper
More informationQuality Control and Quality Assurance Guide
Quality Control and Quality Assurance Guide Bridge Division, Design Section October 2013 Table of Contents Chapter 1 About this Guide... 3 Chapter 2 Goals and Objectives... 5 Chapter 3 Participants...
More informationSTRUCTURAL ASSESSMENT. Full Metal Jacket Building 0 Prince Street, Alexandria, VA
STRUCTURAL ASSESSMENT FOR Full Metal Jacket Building 0 Prince Street, Prepared by: ALPHA CORPORATION (Alpha) 1850 S. Loudoun Street, Suite 200 Winchester, VA 22601 540-723-0704 September 22, 2010 J. Michael
More informationPaving Capitalization Work Categories and Treatments
Statement of ODOT Infrastructure Capitalization Policy Government Accounting Standards Board (GASB) 34 requires public agencies to capitalize infrastructure assets on their financial statements for periods
More informationAlternatives Presentation Meeting Middlebury WCRS(23)
Alternatives Presentation Meeting Middlebury WCRS(23) Main Street (VT 30/TH 2 Bridge 102) and Merchants Row (TH 8 Bridge 2) over Vermont Railway June 4, 2013 Twilight Hall Auditorium, Middlebury College
More informationNumerical Analysis of the Moving Formwork Bracket Stress during Construction of a Curved Continuous Box Girder Bridge with Variable Width
Modern Applied Science; Vol. 9, No. 6; 2015 ISSN 1913-1844 E-ISSN 1913-1852 Published by Canadian Center of Science and Education Numerical Analysis of the Moving Formwork Bracket Stress during Construction
More informationOverhang Bracket Loading. Deck Issues: Design Perspective
Deck Issues: Design Perspective Overhang Bracket Loading Deck overhangs and screed rails are generally supported on cantilever brackets during the deck pour These brackets produce an overturning couple
More informationProject Information. New Hope - Lambertville Toll Bridge - Pavement Rehabilitation & Approach Bridges Repairs -
Project Information Existing Conditions Cracked and settled pavement. Structural failure within the asphalt pavement section. Anticipated Project Elements Reconstruction of all asphalt pavement on US Route
More informationCHAPTER 4 EXISTING TRANSPORTATION MANAGEMENT
CHAPTER 4 EXISTING TRANSPORTATION MANAGEMENT TRANSPORTATION MANAGEMENT SYSTEMS Prior to 1991, the Missouri Department of Transportation (MoDOT) had begun development of several independent management systems.
More informationScreening Transportation Assets for Vulnerability
Screening Transportation Assets for Vulnerability Impacts of Climate Change and Variability on Transportation Systems & Infrastructure (Gulf Coast Study, Phase 2) FHWA Office of Planning Environment and
More informationINCREASE OF DURABILITY AND LIFETIME OF EXISTING BRIDGES. PIARC TC 4.4 EXPERIENCE.
INCREASE OF DURABILITY AND LIFETIME OF EXISTING BRIDGES. PIARC TC 4.4 EXPERIENCE. M.Sc. Gediminas Viršilas Head of Bridge Division, Lithuanian Road Administration Working group 2 of PIARC Technical Committee
More informationGUIDELINES FOR UTILITY INSTALLATIONS Part 1 - Wire Lines and Communications Cables
Engineering Department SEPTEMBER, 2007 GUIDELINES FOR UTILITY INSTALLATIONS Part 1 - Wire Lines and Communications Cables General Requirements This section applies to all public and private utilities,
More informationCHAPTER 4 FIELD INSPECTION, DATA COLLECTING, REPORT WRITING AND REPORT REVIEW
Bridge Inspection Handbook 4-1 CHAPTER 4 FIELD INSPECTION, DATA COLLECTING, REPORT WRITING AND REPORT REVIEW 4.1 INTRODUCTION In this chapter, MassDOT policies and procedures for performing bridge inspections
More informationREPORTS & PRESENTATIONS AGENDA ITEM #III-3 CORTEZ BRIDGE PROJECT DEVELOPMENT AND ENVIRONMENT (PD&E) STUDY
NOTES REPORTS & PRESENTATIONS AGENDA ITEM #III-3 CORTEZ BRIDGE PROJECT DEVELOPMENT AND ENVIRONMENT (PD&E) STUDY Presenter: Summary: Tony Sherrad, FDOT Project Manager The Cortez Bridge in Manatee County,
More informationSUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS
July 14, 2015 1.0 GENERAL BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS This work shall consist of furnishing all materials, equipment, labor, and incidentals necessary for conducting bi-directional
More informationSource: Port Mann Bridge Plans Unveiled Today, CBC News, February 4, 2009.
Total project cost $2.5 billion (Canadian) Financed by tolls about $3 each direction. Total project length 37 km (McGill St in Vancouver to 216 th in Langley) The new Port Mann bridge 10 lanes (existing
More informationUncovered Decks & Porches
Uncovered Decks & Porches Building Guides for Homeowners Why Do I need a Permit? D I D Y O U K N O W? As owner-builder you are the responsible party of record on such a permit. If your work is being performed
More informationHow To Write An Analysis System For Bridge Test
Study of Analysis System for Bridge Test Chen Ke, Lu Jian-Ming, Research Institute of Highway, 100088, Beijing, China (chenkezi@163.com, lujianming@263.net) Summary Analysis System for Bridge Test (Chinese
More informationCIRCULAR LETTER 2007-20 Page 2 of 5 November 30, 2007
CIRCULAR LETTER 2007-20 PPC DECK BEAM NEW SHAPE IMPLEMENTATION, STANDARD BRIDGE PLAN RETIREMENT, AND PPC DECK BEAM INSPECTION COUNTY ENGINEERS/SUPERINTENDENTS OF HIGHWAYS MUNICIPAL ENGINEERS/DIRECTORS
More informationRoss River Suspension Bridge Ross River, Yukon. Life Cycle Cost Analysis
DNA project managers planners architects engineers David Nairne + Associates Ltd Suite 250 171 W Esplanade North Vancouver British Columbia Canada V7M 3J9 T 604 984 3503 F 604 984 0627 E dna@ davidnairne.com
More informationHEAVY MOVABLE STRUCTURES, INC. 12 TH BIENNIAL SYMPOSIUM NW 17 TH AVENUE BRIDGE REHABILITATION OVER THE MIAMI RIVER MIAMI-DADE COUNTY
HEAVY MOVABLE STRUCTURES, INC. 12 TH BIENNIAL SYMPOSIUM November 3-6, 2008 NW 17 TH AVENUE BRIDGE REHABILITATION OVER THE MIAMI RIVER MIAMI-DADE COUNTY John Low, P.Eng. Hardesty & Hanover, LLP CARIBE ROYALE
More informationVirginia Approach Spans
Virginia Concrete Conference 2009 Woodrow Virginia Approach Spans David Tackoor, HNTB Formerly of URS Corp for Potomac Crossing Consultants Woodrow 1 Second Severn Crossing 2 Medway Crossing (Channel Tunnel
More informationSTRUCTURAL FORENSIC INVESTIGATION REPORT
STRUCTURAL FORENSIC INVESTIGATION REPORT Partial Failure of Ramp AC Dunn Memorial Bridge Interchange BIN 109299A City of Albany, Albany County, New York July 27, 2005 Prepared by: NYSDOT October 20, 2005
More informationREPAIR AND STRENGTHENING OF HISTORICAL CONCRETE BRIDGE OVER VENTA RIVER IN LATVIA
1 REPAIR AND STRENGTHENING OF HISTORICAL CONCRETE BRIDGE OVER VENTA RIVER IN LATVIA Verners Straupe, M.sc.eng., Rudolfs Gruberts, dipl. eng. JS Celuprojekts, Murjanu St. 7a, Riga, LV 1024, Latvia e-mail:
More informationComparison of Bridge Rehabilitation versus Bridge Replacement Concepts
Technical Memorandum Comparison of Bridge Rehabilitation versus Bridge Replacement Concepts Introduction The comparison of rehabilitation versus replacement of the Sellwood Bridge is being conducted in
More informationEAST LYME HIGH SCHOOL
Overview: 1971 N 1966 GYM 1966 CLASSROOM WING 1966 AUD. 1971 GYM 1998 1998 POOL EAST LYME HIGH SCHOOL Original 1966 Building: The original East Lyme High School was constructed in 1966 and was composed
More informationHow To Check For Scour At A Bridge
Case Studies Bridge Scour Inspection and Repair Edward P. Foltyn, P.E. Senior Hydraulic Engineer ODOT Bridge Unit 2013 PNW Bridge Inspectors Conference April 2013 REFERENCES Stream Stability at Highway
More informationSEISMIC UPGRADE OF OAK STREET BRIDGE WITH GFRP
13 th World Conference on Earthquake Engineering Vancouver, B.C., Canada August 1-6, 2004 Paper No. 3279 SEISMIC UPGRADE OF OAK STREET BRIDGE WITH GFRP Yuming DING 1, Bruce HAMERSLEY 2 SUMMARY Vancouver
More informationChapter 5 RISK MANAGEMENT ANALYSIS CHAPTER 5 RISK MANAGEMENT ANALYSIS PAGE 49
Chapter 5 RISK MANAGEMENT ANALYSIS CHAPTER 5 RISK MANAGEMENT ANALYSIS PAGE 49 This page intentionally left blank. PAGE 50 MINNESOTA GO MNDOT TRANSPORTATION ASSET MANAGEMENT PLAN RISK MANAGEMENT ANALYSIS
More informationStructural Condition and Replacement Memorandum
Structural Condition and Replacement Memorandum Prepared by: D. Morales, MSA Design & Consulting Checked by: C. Subrizi, MSA Design & Consulting Reviewed by: Roupen Donikian, PB Submitted by: Gary Kennerley,
More informationBridge Rehabilitation Alternatives
Kennedy Bridge Planning Study Technical Memorandum: Bridge Rehabilitation Alternatives MnDOT S.P. No. 6018-02 Prepared for: Minnesota Department of Transportation DRAFT April 28, 2014 Prepared by: Report
More informationPENNDOT 3D MODELING FOR STRUCTURES WORKSHOP. Presented by: Steven Pletcher and Chris Daniels, P.E. October 21, 2014
PENNDOT 3D MODELING FOR STRUCTURES WORKSHOP Presented by: Steven Pletcher and Chris Daniels, P.E. October 21, 2014 Agenda Introduction G.A. & F.C. Wagman History Process used to prepare 3D models Estimating
More informationLOAD TESTING OF SOME NEW BRIDGES IN LATVIA
LOAD TESTING OF SOME NEW BRIDGES IN LATVIA Edmunds Akimovs, Civ.Eng., Bridge Engineer, Consulting Company Inzenierbuve, Address: Azenes st. 20, Riga, LV1048, Latvia. E-mail: eakimovs@inzenierbuve.lv Ainars
More informationHistoric Bridge Alternatives Analysis Layout
Section 4(f) of the USDOT Act of 1966 (Title 49, USC, Section 303) requires special considerations be made regarding the use of any publicly owned park, recreation area, wildlife/waterfowl refuge or historic
More informationCable-Stayed Bridge Uses New Post-Tensioning System
Stretching over the Ohio River Cable-Stayed Bridge Uses New Post-Tensioning System By William B. Caroland, PE, and Jorge M. Suarez, PE Located approximately 2.8 miles downstream from the suspension bridge
More informationChaudière Crossing Bridge Rehabilitation
Chaudière Crossing Bridge Rehabilitation Douglas K. Lowry P. Eng., Armtec Infrastructure Incorporated David Delicate, P.Eng. Public Works and Government Services Canada (Retired) Prepared for presentation
More informationKOSCIUSZKO BRIDGE PROJECT BRIDGE PRIMER
KOSCIUSZKO BRIDGE PROJECT BRIDGE PRIMER The New York State Department of Transportation (NYSDOT) is preparing an Environmental Impact Statement (EIS) to evaluate alternatives for the rehabilitation or
More informationSession 5D: Benefits of Live Load Testing and Finite Element Modeling in Rating Bridges
Session 5D: Benefits of Live Load Testing and Finite Element Modeling in Rating Bridges Douglas R. Heath P.E., Structural Engineer Corey Richard P.E., Project Manager AECOM Overview Bridge Testing/Rating
More informationBridge Type Selection
Bridge Type Selection The major consideration for bridge type selection for bridges on the State Aid system is initial cost. Future maintenance costs, construction time, and location are considered when
More informationCAPPELEN MEMORIAL BRIDGE REHABILITATION
CAPPELEN MEMORIAL BRIDGE REHABILITATION Owner: Hennepin County Engineering: HNTB with Olson-Nesvold Engineering (ONE) and others Section 106 Historical Committee: Hennepin County, MnDOT Cultural Resources
More informationElevating Your House. Introduction CHAPTER 5
CHAPTER 5 Elevating Your House Introduction One of the most common retrofitting methods is elevating a house to a required or desired Flood Protection Elevation (FPE). When a house is properly elevated,
More informationRole of Underwater Substructure Inspections in Bridge Management
Role of Underwater Substructure Inspections in Bridge Management R. RICHARD AVENT MOHAMED ALAWADY DAVID J. MUKAI Louisiana State University INTRODUCTION In the past, the condition of underwater substructures
More informationPRELIMINARY SEISMIC CONSIDERATIONS FOR PULASKI SKYWAY REHABILITATION PROJECT. Xiaohua H. Cheng 1
PRELIMINARY SEISMIC CONSIDERATIONS FOR PULASKI SKYWAY REHABILITATION PROJECT Abstract Xiaohua H. Cheng 1 The 3.5 mile (5.63 km) long Pulaski Skyway is located in northern New Jersey, serving as a major
More informationCHAPTER FOUR: EXISTING TRANSPORTATION MANAGEMENT
CHAPTER FOUR: EXISTING TRANSPORTATION MANAGEMENT 4.1 Transportation Management Systems Prior to 1991, the Missouri Department of Transportation (MoDOT) had begun development of several independent management
More information5 ALTERNATIVE SOLUTIONS AND EVALUATION
Page 23 5 ALTERNATIVE SOLUTIONS AND EVALUATION The process used for the assessment and evaluation of the alternatives follows the procedures of the Municipal Class EA, as described below: Identify a reasonable
More informationAsset Maintenance Bridge Emergency Response
FDOT Districts 1 & 7 Structures and Facilities Office Asset Maintenance Bridge Emergency Response Bridge No. 100300 Gandy Boulevard (US 92) over Tampa Bay, FL Jose Pepe Garcia, P.E., Florida DOT David
More informationTruss. are both simple and A Matsuo Example continuous trusses. The
Girder Bridge A girder bridge is perhaps the most common and most basic bridge. A log across a creek is an example of a girder bridge in its simplest form. In modern steel girder bridges, the two most
More informationAnalysis of the Interstate 10 Twin Bridge s Collapse During Hurricane Katrina
Analysis of the Interstate 0 Twin Bridge s Collapse During Hurricane Katrina By Genda Chen, Emitt C. Witt III, David Hoffman, Ronaldo Luna, and Adam Sevi The Interstate 0 Twin Span Bridge over Lake Pontchartrain
More informationI-676 (Vine Expressway) Bridge Reconstruction Project 22 nd - 18 th Streets Philadelphia, PA. PSPE Presentation, December 3, 2015
I-676 (Vine Expressway) Bridge Reconstruction Project 22 nd - 18 th Streets Philadelphia, PA PSPE Presentation, December 3, 2015 Location Map N PROJECT LOCATION 22 nd 18 th Streets PHILADELPHIA, PA General
More informationMEMORANDUM. 1509 West Swann Avenue, Suite 225 Tampa, Florida 33606 Phone (813) 258-8818 Fax (813) 258-8525
1509 West Swann Avenue, Suite 225 Tampa, Florida 33606 Phone (813) 258-8818 Fax (813) 258-8525 To: From: Date: Subject: Mr. Thomas Gibson, City of St. Petersburg Jeffrey D. Malyszek, PE and Deborah C.
More informationSan Francisco Oakland Bay Bridge East Span Seismic Safety Project
San Francisco Oakland Bay Bridge East Span Seismic Safety Project Presented To: Society of American Military Engineers May 16, 2013 Brian Maroney, P.E. Dr. Engr. Karen Wang, P.E. Pier E9 Following the
More information6 RETROFITTING POST & PIER HOUSES
Retrofitting Post & Pier Houses 71 6 RETROFITTING POST & PIER HOUSES by James E. Russell, P.E. 72 Retrofitting Post & Pier Houses Retrofitting Post & Pier Houses 73 RETROFITTING POST AND PIER HOUSES This
More informationCHAPTER 9 LONG TERM MONITORING AT THE ROUTE 351 BRIDGE
CHAPTER 9 LONG TERM MONITORING AT THE ROUTE 351 BRIDGE 9.1 INTRODUCTION An important reason that composite piles have not gained wide acceptance in the civil engineering practice is the lack of a long
More informationValue Engineering vs. Alternate Designs in Bridge Bidding
Value Engineering vs. Alternate Designs in Bridge Bidding Compares the advantages and disadvantages of alternate designs and value engineering in bidding of bridges as experienced in the State of Florida.
More informationPeer Review Scope of Work
1.0 PROJECT OVERVIEW The St. Croix River Crossing Project has been developed in response to traffic congestion, operation deficiencies, safety concerns, and structural deficiencies of the Stillwater Lift
More informationStone Arch Bridges of Washington County, MD
Stone Arch Bridges of Washington County, MD Presentation for the County Engineers Association of Maryland (CEAM) 2009 Spring Conference May 14, 2009 Scott Hobbs, P.E. Capital Projects Engineering John
More informationHistoric Bridges of Frederick County. Frederick County, Maryland Division of Public Works Department of Highways and Transportation (301) 600-1687
Historic Bridges of Frederick County Frederick County, Maryland Division of Public Works Department of Highways and Transportation (301) 600-1687 Frederick County s Bridges We have 212 bridges over 20
More informationINTRODUCTION TO BEAMS
CHAPTER Structural Steel Design LRFD Method INTRODUCTION TO BEAMS Third Edition A. J. Clark School of Engineering Department of Civil and Environmental Engineering Part II Structural Steel Design and Analysis
More informationREPAIR AND RETROFIT OF BRIDGES DAMAGED BY THE 2010 CHILE MAULE EARTHQUAKE
Proceedings of the International Symposium on Engineering Lessons Learned from the 2011 Great East Japan Earthquake, March 1-4, 2012, Tokyo, Japan REPAIR AND RETROFIT OF BRIDGES DAMAGED BY THE 2010 CHILE
More informationColorado Off-System Bridge Program Description and Guidelines for Selecting Bridges for Rehabilitation or Replacement Funding
C Colorado Off-System Bridge Program Description and Guidelines for Selecting Bridges for Rehabilitation or Replacement Funding These guidelines are intended to provide assistance in selecting OFF-SYSTEM
More informationSurface Transportation Program (STP) Projects
Toledo Metropolitan Area Council of Governments American Reinvestment and Recovery Act (Economic Stimulus Program) Application Packet for: Surface Transportation Program (STP) Projects APPLICATIONS DUE
More informationPage & Turnbull imagining change in historic environments through design, research, and technology
DCI+SDE STRUCTURAL EVALUATIONS OFFICE BUILDING, TOOL SHED & WATER TANK, AND BLACKSMITH & MACHINE SHOP BUILDINGS SAN FRANCISCO, CALIFORNIA [14290] PRIMARY PROJECT CONTACT: H. Ruth Todd, FAIA, AICP, LEED
More informationReal-Time Performance Monitoring of the Tacony-Palmyra Bridge
Real-Time Performance Monitoring of the Tacony-Palmyra Bridge Yarnold, Moon, Aktan, Glisic IABMAS 2012 TACONY PALMYRA LIVE INFRASTRUCTURE FIELD LABORATORY: TACONY PALMYRA LIVE INFRASTRUCTURE FIELD LABORATORY:
More informationAlberta Guidelines for Upgrading Bridgerails and Approach Guardrail Transitions
Alberta Guidelines for Upgrading Bridgerails and Approach Guardrail Transitions Raymond Yu Alberta Transportation Bob Ramsay UMA Engineering Ltd Clive Clarke Alberta Transportation Bill Kenny Alberta Transportation
More informationRisk - Based Inspection Frequencies
Risk - Based Inspection Frequencies Glenn A. Washer, PhD University of Missouri Columbia, MO April 23, 2013 Northwest Bridge Inspector s Conference 1 NCHRP 12-82 Developing Reliability Based Bridge Inspection
More informationTABLE OF CONTENTS. Section / Article Page
TABLE OF CONTENTS Section / Article Page 1. INTRODUCTION 1.1 Purpose................ 6 1.2 Definitions................ 6 1.3 Guidelines and References............ 7 2. AGREEMENTS 2.1 Applicant and Contractor
More informationUSE OF MICROPILES IN TEXAS BRIDGES. by John G. Delphia, P.E. TxDOT Bridge Division Geotechnical Branch
USE OF MICROPILES IN TEXAS BRIDGES by John G. Delphia, P.E. TxDOT Bridge Division Geotechnical Branch DEFINITION OF A MICROPILE A micropile is a small diameter (typically less than 12 in.), drilled and
More information