US 51 Ohio River Bridge Engineering and Environmental Study
|
|
|
- Roland Green
- 9 years ago
- Views:
Transcription
1 US 51 Ohio River Bridge Engineering and Environmental Study ITEM NOS & Prepared by: Michael Baker Jr., Inc Ormsby Station Rd Louisville, KY August 16, 2013
2 Table of Contents Contents EXECUTIVE SUMMARY OHIO RIVER BRIDGE CONCEPTS ALIGNMENT ALTERNATIVE 1 SUPERSTRUCTURE REPLACEMENT USING THE EXISTING PIERS ALIGNMENT ALTERNATIVES 2, 2A AND 2B NEW ALIGNMENT ALIGNMENT ALTERNATIVES 3 AND 3A NEW ALIGNMENT ALIGNMENT ALTERNATIVES 4 AND 5 NEW ALIGNMENT ALTERNATIVES FOR FURTHER CONSIDERATION August 16, 2013
3 EXECUTIVE SUMMARY The purpose of this white paper is to inform the reader about the structural Rehabilitation and Replacement alternatives for the existing bridge. Appropriate actions can then be developed for an approved environmental document to either repair or replace the existing bridge. Bridge concepts considered for this phase of the project are Tied Arches, Box Girders, Cable Stay, and Through Truss bridges. This document should be considered in the context of the environmental study and is not intended to be a standalone evaluation of the concepts. Alternative 1 Superstructure replacement Preliminary analysis indicates that re use of the existing piers may be feasible, however additional study is necessary. Extensive rehabilitation of the piers would be required to meet the requirements for seismic and vessel collision events. Preserves the existing navigation span arrangement at 800ft and 650ft and would reduce the amount of new construction associated with the longer alternatives presented. Through Truss and Arch Bridges are both feasible for this alternative. Alternative 2, 2A, 2B Located just upstream of the existing bridge between RM and USCG requires a 900ft horizontal clearance and vertical clearance of at least feet Cable Stay, Truss and Arch Bridges are all suitable bridge types. Existing US 51 Bridge would be demolished and removed. Alternative 3, 3A Located just upstream of the existing Illinois Central RR bridge between RM and USCG requires a 1,200ft horizontal clearance and vertical clearance of at least feet Cable Stay is the recommended bridge type for this location. Existing US 51 Bridge would be demolished and removed. Alternative 4 and 5 Located upriver of the existing Illinois Central RR bridge at RM and respectively USCG requires a 1,000ft horizontal clearance and vertical clearance of at least feet Cable Stay, Truss and Arch Bridges are all suitable bridge types. Existing US 51 Bridge would be demolished and removed. Approach Spans The approach structures would likely be steel multi-girder for spans of 150 to 400 ft. or concrete beam for spans of 100 to 150 ft. on new piers utilizing continuous units and efficient span arrangements as much as possible. Portions of approach span bridge located over the Ohio River would likely be long span welded plate girders to minimize the number of piers in the waterway. For the cost estimates of the new bridge alignments 2, 2A, 2B, 3, 3A, 4 and 5, square foot costs from similar cable stayed bridge projects were used as the basis of the estimate. The cable stay bridge is thought to be a very representative economic structure in the span ranges required for this project. Because of the unique site conditions and proximity to the New Madrid Fault, it is recommended that additional engineering analysis be performed to determine the most suitable bridge type for this site. 3 August 16, 2013
4 US 51 Ohio River Bridge Engineering and Environmental Study Figure 1 Level 2 Alternatives 4 August 16, 2013
5 1. OHIO RIVER BRIDGE CONCEPTS For the current Alignment Alternatives 1, 2, 2A, 2B, 3, 3A, 4 and 5, through truss, through arch, cable stayed and concrete box girder bridge types have been evaluated, to rehabilitate or replace the structurally deficient and functionally obsolete US-51 Bridge over the Ohio River at Cairo, Illinois. Reasonable assumptions and comparisons of bridge types from previous Ohio River Bridge projects were used in the decision making process. See Figure 1 for alignments of the alternatives being considered. Cost estimates have been prepared for the alignments based on historical square foot costs of similar bridges. While this method is very useful, it does have limitations with respect to drawing conclusions from sites that may be different than the one under consideration. The square foot cost estimates of the various structure types investigated were modified to take into account the depth of scour and depth of deep foundations. This is due to the site geotechnical conditions and the requirement of a site specific seismic analysis with either a 2,500 or 1,000 year return interval due to the proximity of the New Madrid Fault, along with the structure being a critical and essential bridge over the Ohio River. These assumptions and concerns will require further investigations as this project moves forward. For the cost estimates of the new bridge alignments 2, 2A, 2B, 3, 3A, 4 and 5, square foot costs from similar cable stay bridge projects were used as the basis of the estimate. The cable stay bridge is thought to be a very representative economic structure in the span ranges required for this project. Because of the unique site conditions and proximity to the New Madrid Fault, it is recommended that additional engineering analysis be performed to determine the most suitable bridge type for this site. 2. ALIGNMENT ALTERNATIVE 1 SUPERSTRUCTURE REPLACEMENT USING THE EXISTING PIERS With this alternative, the existing River Bridge piers would be widened and strengthened for current AASHTO seismic and barge impact requirements and reused. This would allow for a wider superstructure to be placed on top and a strengthened shaft and foundation to resist governing seismic forces mentioned above. A preliminary pier strengthening concept is shown in Figure 2. The existing pier shafts require a reinforced concrete encasement approximately 2 feet thick to be constructed around the existing river pier shafts and a steel pipe pile supported reinforced-concrete footing approximately 16 feet thick around each foundation. US Coast Guard approval is required for reducing the center channel by approximately 4 feet for the pier shaft encasement from 630 feet to about 626 feet and reducing the Illinois channel by 4 feet from 780 feet to about 776 feet. To minimize the reduction to the channel, foundation modifications would be located below water at the top of the caisson. The preliminary top of footing would provide 12ft of draft for navigation approximately 85% of the time. During low water events the draft would not be maintained and during extreme low water the footing may become exposed. Acceptable draft requirements have not been established by the US Coast Guard at this current phase of the project. The US Coast Guard also has the following vertical clearance requirement for all alternatives for superstructure low steel and they must provide a vertical clearance of at least feet above zero on the Cairo gage. 55 ft. above the 2% flood, low steel Elev. = (Elev ORD + 55 ft. = Elev ft. ORD) 69 ft. above June flow, low steel Elev. = (Elev ORD + 69 ft. = Elev ft. ORD) 5 August 16, 2013
6 Figure 2 - ALT 1 Pier Strengthening Concept 6 August 16, 2013
7 Figure 3 Existing Bridge Layout Through Truss Bridge Type A conventional variable depth Warren truss with verticals and a parallel chord Warren truss without verticals were considered for the river structure, spanning from Piers A through F (shown in Figure 3). The approach structures would either be steel multi-girder for spans of 150 to 400 ft. or concrete beam for spans of 100 to 150 ft. on new piers utilizing continuous units and efficient span arrangements as much as possible. The proposed approach span replacement costs, excluding demolition, are in the range of $185 to $235 per square foot depending on site specific factors such as seismic requirements, substructure geometry and foundation types. Shorter spans with limited beam depths or through type structures are necessary over the railroads to meet vertical clearance requirements. The locations of the existing approach span piers would not result in efficient continuous beam span arrangements and would require costly rehabilitation for the wider superstructure for reuse and therefore are recommended to be replaced. The variable depth Warren truss has a great deal of visual clutter due to the combination of verticals and diagonals necessary for the efficient design of the truss, whereas the parallel chord truss is open, visually clean and has favorable aesthetics. Therefore, a parallel chord truss bridge would be appropriate for Alternative 1. There would be some variation in the depth of the parallel chords from about 80 ft. to about 65 ft. between the 800 ft. span and 650 ft. spans respectively for cost efficiency. The following components make up the superstructure geometry of the through truss bridge type: cast in place conventionally reinforced concrete deck slab and parapets longitudinal stringers directly supporting the slab floorbeams at each truss panel point that transfer the load of the stringers and deck slab to each panel point two main truss systems consisting of top and bottom chords and diagonals lateral bracing in each plane of the top and bottom chord portal frames (end sway frames). intermediate sway frames The construction costs for both truss alternatives are comparable for this level of evaluation. Both 50 ksi and 70 ksi steel would be used to decrease member size and therefore lessen the effects of dead load on the existing piers A through F. Erection of the main spans and side spans would most likely occur in a balanced cantilever from each main pier simultaneously. Either tie-downs, falsework bents or a combination of the two systems would be necessary to ensure stability of the partially constructed truss. Falsework bents and tie-downs would be placed in a manner that does not restrict navigational use of the Ohio River (primary) channel. Accelerated construction techniques have been used to construct trusses, including floating and lifting 7 August 16, 2013
8 completed portions of the bridge into place. Lateral sliding is another technique that can possibly also be utilized. Long Span through trusses are some of the most difficult bridge structures to maintain and inspect. High performance painting systems are usually required due to the direct exposure of much of the bridge to splash zones from vehicular traffic. In addition, the three-dimensional junction of truss chords, diagonals, lateral bracing and portal bracing are areas difficult to access and maintain. Fixed ladders and inspection walkways would be provided for ease of inspection for some of the deck and truss members. The use of mobile inspection equipment, such as snoopers with lane closures for inspection of areas not accessible by ladders and inspection walkways, is somewhat problematic due to interference created by main truss diagonals. Through Arch Bridge Type Conventional through tied arches with vertical suspender cables and more modern networked and basket-handle tied arches with skewed suspender cables were considered for the River Structure spanning the three spans supported by Piers B through E thus limiting the length of the more expensive river structure. Continuous steel multi-girder or concrete beam approach spans on new piers with efficient span arrangements should be utilized as much as possible to result in a very cost efficient alternative. Piers B through E would be rehabilitated as discussed above and Piers A and F, and all other approach span piers are assumed to be replaced with new piers. In general, the arch solution is a clean and open form and has minimal impact of the view shed. The networked tied arch has the same openness and visual clarity of the conventional arch but is more efficient and requires less structural steel that lessen the effects of dead load on the existing piers B through E, the networked tied arch would be appropriate for this location for Alternative 1. The arch height would be about 160 ft. for the 800 ft. span and about 130 ft. for the 650 ft. spans. The following components make up the superstructure geometry of tied arch alternative: cast in place conventionally reinforced concrete deck slab and parapets longitudinal stringers directly supporting the slab floorbeams to transfer the load of the stringers and deck slab to each tie girder. two main arch systems consisting of the arch rib, hanger cables and tie girder lateral bracing between the upper arch ribs and lower lateral bracing at the floor system Arch rib members and tie girder members can either be box or H shaped. Arch tie girders are considered fracture critical and are required to meet AASHTO material toughness and fracture critical fabrication requirements along with having internal redundancy by bolting rather than welding tie girder webs and flanges together. The tied arch would also have to de designed for cable loss. The construction cost for both arch alternatives are comparable for this level of evaluation. A networked tied arch would require less steel but would have increased fabrication costs due to the skewed suspender cables and connections. 50 ksi steel would be considered for the floor system and 70 ksi steel would be considered for the arch rib and tie girder system for increased toughness and to decrease member sizes, therefore lessening the effects of dead load on the existing piers B through E. An erection advantage of the tied arch is that in recent years, arches have been assembled off site, floated in and then lifted into place. The conventional erection method would require falsework at each pier so that the first portion of the arch, tie beam and floorsystem can be supported during construction. Once the first portion is erected, towers and tie-back cables can support the remainder of arch construction from the existing piers. Falsework would be placed in a manner that does not restrict navigational use of the Ohio River (primary) channel. In terms of maintenance and serviceability, arches are similar to trusses. Arches have only a small portion of the arch rib in the splash zone limiting the overall exposure of the steel portion of the bridge to a highly corrosive environment. Tie girders are subjected to direct tension with bending, and are 8 August 16, 2013
9 considered fatigue sensitive elements. Recent tied arch bridges incorporate a fully redundant tie system in order to provide an alternate load path in the event of a tie component failure. For arches composed of box ribs and tie girders, inspection access is provided inside the arch rib and tie girders for inspection with a series of access holes and fixed ladders where required. Mobile inspection equipment, such as snoopers with lane closures, is used for inspections of all other areas. An inspection walkway can also be provided under the floor system. Cable Stayed Bridge Type A Cable Stayed Alternative was considered for the River Structure, spanning Piers A through F. The four towers would be approximately 180ft. high and constructed on existing Piers B through E. Piers A and F would support the end spans of the balanced cable stayed unit and all other approach span piers would be replaced with new piers to support the steel multi-girder or concrete beam approach spans similar to the Through Truss Alternative. Due to the inherent flexibility of cable stayed bridges, a wide range of aesthetic possibilities exist and are primarily dependent upon stay cable geometry and pylon shape. H-shaped pylons with two vertical planes of cables and A-shaped pylons with two inclined planes of cables were considered because of the narrow bridge superstructure width. It is also assumed the cables will be configured in a semi fan cable configuration. Steel and concrete edge girder alternatives were considered to provide the required vertical clearance for navigation. The success of this bridge form in the 600 ft. to 2000 ft. range is primarily due to its inherent ease of constructability. Cable stayed bridges are customarily erected by the balanced cantilever method of erection after the tower and initial deck segment at the tower are constructed. Cable stayed bridges offer substantial improvements for maintenance and serviceability over truss and arch alternatives. Painting is required only for steel edge girder alternatives and can be eliminated if weathering steel is utilized. Since all structural steel is below the deck and out of the vehicle splash zone, properly applied high performance painting systems should have an excellent service life. Vibration induced by wind and rain-wind combinations has been a serviceability issue over the past 30 years, but recent code developments, coupled with a better understanding of the mechanisms responsible for stay cable vibrations, have virtually eliminated this problem. Due to the difficulties and cost associated with deck replacement of cable stayed bridges because the deck is an integral element resisting compression forces imparted by stay cables, high performance overlays such as epoxy are typically required to extend the deck service life. Cable stayed bridges require design for future deck replacement and are designed for cable loss similar to tied arches. Cable stayed bridges are among the easiest bridges to inspect when complete access to all elements, except cables, can be provided by fixed ladders and inspection walkways. The use of mobile inspection equipment can be a little problematic due to interference created by the stay cables. Both the steel and concrete edge girder cable stayed bridges are considered the most economical cable stayed alternatives for the site. However, the extremely high cost of strengthening or essentially replacing the existing piers to accept the tower loads eliminates this bridge type from further consideration for Alignment Alternative1 Superstructure Replacement using the existing piers. Concrete Box Girder Bridge Type Both Cast-in-Place Concrete Box Girders and Segmental Concrete Box girders would require a superstructure depth of approximately 30 feet at the river piers and 10 feet at mid-span and therefore would have an adverse effect on the proposed profile grade due to providing the required vertical clearance for navigation. This bridge type was therefore eliminated from consideration for Alignment Alternative 1. 9 August 16, 2013
10 3. ALIGNMENT ALTERNATIVES 2, 2A AND 2B NEW ALIGNMENT These alignments are located just upstream of the existing bridge. All three of these alternatives between Ohio River Mile Points and would serve the same function and result in similar impacts. After construction of this alternate, the existing US-51 Bridge at Ohio River Mile Point would be demolished and removed. We have reviewed the clear span of the existing bridges on the Ohio River in Kentucky, including the proposed cable stayed bridges at Louisville and the new bridge at Cape Girardeau on the Mississippi River, and have recommended a 900 ft. horizontal clearance envelope perpendicular to the sailing line at this location. Additional navigation clearance is available in the 200 ft. side spans. The US Coast Guard requirements for this alternative are as follows: 900 ft. main channel horizontal clearance adjacent to the sailing line ft minimum vertical clearance required in channel Bridge Types Considered The required clearance of 900 ft. for the main span of the bridge can be accommodated by the tied arch, through truss, or cable stayed bridge. Steel Plate Girder approach spans would be utilized over the remaining section of the river to reduce the number of piers constructed in the river. Arch Bridge Single 925 ft. tied arch span Approx. 180 ft. high Cable Stayed Bridge Span Arrangement of Approx. tower height above deck, 200 ft. Steel Plate Girder approaches over rest of the river Through Truss Span Arrangement Approx. 70 ft. depth Concrete Box Girder Not recommended due to main span length and required depth of structure. 4. ALIGNMENT ALTERNATIVES 3 AND 3A NEW ALIGNMENT Alternatives 3 and 3A share the same river crossing and Illinois approach location but different Kentucky approach locations. These alignments are located just upstream of the existing Illinois Central Railroad bridge between Ohio River Mile Mark and After construction of this alternate, the existing US-51 Bridge at Ohio River Mile Point would be demolished and removed. A clear span of slightly more than 1,200 feet would be required at this location to line up proposed piers with the existing railroad bridge piers. The span layout would line up the right descending pier of the proposed bridge with the right descending pier of the railroad bridge on the Illinois Bank. The US Coast Guard requirements for this alternative are as follows: 1200 ft. main channel horizontal clearance lined up with the existing railroad bridge piers 105.3ft minimum vertical clearance required in channel 10 August 16, 2013
11 Bridge Types Considered The required clearance of 1200 ft, for the main span of the bridge can be accommodated by the tied arch, or cable stayed bridge. Steel Plate Girder approach spans would be utilized over the remaining section of the river to reduce the number of piers constructed in the river. Arch Bridge Three Single 1,225 ft., 500 ft., 500 ft. tied arch spans Approx. 240 ft. high Steel Plate Girder approaches over rest of the river Cable Stayed Bridge Span Arrangement of Approx. tower height above deck, 300 ft. Steel Plate Girder approaches over rest of the river Through Truss Not recommended due to main span length Concrete Box Girder Not recommended due to main span length and required depth of structure. 5. ALIGNMENT ALTERNATIVES 4 AND 5 NEW ALIGNMENT These alignments are located further upstream of the existing Illinois Central Railroad bridge between Ohio River Mile Marks and and have similar main river span arrangements. After construction of this alternate, the existing US-51 Bridge at Ohio River Mile Point would be demolished and removed. The US Coast Guard navigational requirements for these two alternatives are as follows: 1,000 ft. main channel horizontal clearance adjacent to the sailing line ft minimum vertical clearance required in channel Bridge Types Considered The required clearance of 1,000 ft, for the main span of the bridge can be accommodated by the tied arch, through truss, or cable stayed bridge. Steel Plate Girder approach spans would be utilized over the remaining section of the river to reduce the number of piers constructed in the river. Arch Bridge Single 1,025 ft. tied arch span Steel Plate Girder approaches over rest of the river Cable Stayed Bridge Span Arrangement of Approx. tower height above deck, 200 ft. Steel Plate Girder approaches over rest of the river Through Truss Possible, but at the upper limit for truss spans Concrete Box Girder Not recommended due to main span length and required depth of structure. 11 August 16, 2013
12 6. ALTERNATIVES FOR FURTHER CONSIDERATION The Truss, Arch and Cable Stayed Bridge Types proposed as described for Alignment Alternatives1, Combined 2, 3A, and 4 are the most favorable alternatives for initial construction costs, constructability, maintenance, serviceability inspectability and therefore recommended for further consideration in the next phase of this project. The alternatives are further summarized as follows: Alternative 1 Superstructure replacement Preliminary analysis indicates that re-use of the existing piers may be feasible, however additional study is necessary. Extensive rehabilitation of the piers would be required to meet the requirements for seismic and vessel collision events. Through Truss and Arch Bridges are both feasible for the 800 ft. and 650 ft. spans required for this alternative. Alternative 2, 2A, 2B Cable Stay, Truss and Arch Bridges are all suitable bridge types for the 900 ft. horizontal clearance and vertical clearance of at least feet. Alternative 3, 3A Cable Stay is the recommended bridge type for this location for the 1,200 ft. horizontal clearance and vertical clearance of at least feet. Alternative 4 and 5 Cable Stay, Truss and Arch Bridges are all suitable bridge types for the 1,000 ft. horizontal clearance and vertical clearance of at least feet. 12 August 16, 2013
Safe & Sound Bridge Terminology
Safe & Sound Bridge Terminology Abutment A retaining wall supporting the ends of a bridge, and, in general, retaining or supporting the approach embankment. Approach The part of the bridge that carries
Design of Steel Structures Prof. S.R.Satish Kumar and Prof. A.R.Santha Kumar. Fig. 7.21 some of the trusses that are used in steel bridges
7.7 Truss bridges Fig. 7.21 some of the trusses that are used in steel bridges Truss Girders, lattice girders or open web girders are efficient and economical structural systems, since the members experience
REHABILITATION PACKAGE 1-a
1-a WINONA BRIDGE (BRIDGE 5900) REHABILITATION PACKAGE 1-a Rehab option 1-a is a rehabilitation package whereby all spans of the existing structure would be rehabilitated to the degree feasible and strengthened
The Rehabilitation Alternative Huey P. Long Bridge Case Study. Bruce E. Peterson, P.E. Project Manager Modjeski and Masters, Inc.
The Rehabilitation Alternative Huey P. Long Bridge Case Study Bruce E. Peterson, P.E. Project Manager Modjeski and Masters, Inc. March 22, 2010 Replacement vs. Rehabilitation Project Background Introduction
Design of Bridges. Introduction. 3 rd to 4 th July 2012. Lecture for SPIN Training at the University of Dar es Salaam
Design of Bridges Introduction 3 rd to 4 th July 2012 1 FUNCTION OF A BRIDGE To connect two communities which are separated by streams, river, valley, or gorge, etc. 2 EVOLUTION OF BRIDGES 1. Log Bridge
Analysis of the Response Under Live Loads of Two New Cable Stayed Bridges Built in Mexico
Analysis of the Response Under Live Loads of Two New Cable Stayed Bridges Built in Mexico Roberto Gómez, Raul Sánchez-García, J.A. Escobar and Luis M. Arenas-García Abstract In this paper we study the
3.1 Historical Considerations
3. Recommended Scope of Bridge improvements 3.1 Historical Considerations In the fall of 2000, an outside consultant, Fraser Design, suggested that the existing 4 th St. Bridge is potentially eligible
APPENDIX H DESIGN CRITERIA FOR NCHRP 12-79 PROJECT NEW BRIDGE DESIGNS
APPENDIX H DESIGN CRITERIA FOR NCHRP 12-79 PROJECT NEW BRIDGE DESIGNS This appendix summarizes the criteria applied for the design of new hypothetical bridges considered in NCHRP 12-79 s Task 7 parametric
National Council of Examiners for Engineering and Surveying. Principles and Practice of Engineering Structural Examination
Structural Effective Beginning with the April 2011 The structural engineering exam is a breadth and exam examination offered in two components on successive days. The 8-hour Vertical Forces (Gravity/Other)
Bridge Type Selection
Bridge Type Selection The major consideration for bridge type selection for bridges on the State Aid system is initial cost. Future maintenance costs, construction time, and location are considered when
CONCEPTUAL REHABILITATION ALTERNATIVE
Appendix D While federal law requires preservation/rehabilitation of historic bridges be considered, there is no standard procedure to determine when rehabilitation is appropriate and when replacement
Challenging Skew: Higgins Road Steel I-Girder Bridge over I-90 OTEC 2015 - October 27, 2015 Session 26
2014 HDR Architecture, 2014 2014 HDR, HDR, Inc., all all rights reserved. Challenging Skew: Higgins Road Steel I-Girder Bridge over I-90 OTEC 2015 - October 27, 2015 Session 26 Brandon Chavel, PhD, P.E.,
Chapter 3 Pre-Installation, Foundations and Piers
Chapter 3 Pre-Installation, Foundations and Piers 3-1 Pre-Installation Establishes the minimum requirements for the siting, design, materials, access, and installation of manufactured dwellings, accessory
2015 ODOT Bridge Design Conference May 12, 2014. DeJong Rd Bridge High- Seismic Zone Case Study: Bridge Rehab vs. Replacement.
2015 ODOT Bridge Design Conference May 12, 2014 DeJong Rd Bridge High- Seismic Zone Case Study: Bridge Rehab vs. Replacement Mary Ann Triska 2015 HDR, all rights reserved. Presentation Outline Project
3 Tappan Zee Bridge Rehabilitation Options
3 Tappan Zee Bridge Rehabilitation Options 3.1 Introduction This chapter describes possible options that rehabilitate and enhance the existing Tappan Zee Bridge. Four Rehabilitation Options have been developed:
Residential Deck Safety, Construction, and Repair
Juneau Permit Center, 4 th Floor Marine View Center, (907)586-0770 This handout is designed to help you build your deck to comply with the 2006 International Residential Building code as modified by the
FEBRUARY 2014 LRFD BRIDGE DESIGN 4-1
FEBRUARY 2014 LRFD BRIDGE DESIGN 4-1 4. STRUCTURAL ANALYSIS AND EVALUATION The analysis of bridges and structures is a mixture of science and engineering judgment. In most cases, use simple models with
IH-635 MANAGED LANES PROJECT, SEG. 3.2
IH-635 MANAGED LANES PROJECT, SEG. 3.2 Location: Dallas, Texas Owner: Texas Department of Transportation Client: Ferrovial Agroman Construction Cost: $1 Billion Construction Completion Date: December,
6 RETROFITTING POST & PIER HOUSES
Retrofitting Post & Pier Houses 71 6 RETROFITTING POST & PIER HOUSES by James E. Russell, P.E. 72 Retrofitting Post & Pier Houses Retrofitting Post & Pier Houses 73 RETROFITTING POST AND PIER HOUSES This
Informational Workshop Public Meeting Kanawha Falls Bridge Project
Informational Workshop Public Meeting Kanawha Falls Project WV Department of Transportation Division of Highways in Cooperation with the Federal Highway Administration State Project S310-13-0.02 00 Federal
Engineers at Liftech designed the structure of the first container crane and have designed and reviewed thousands of container cranes since.
Engineers at Liftech designed the structure of the first container crane and have designed and reviewed thousands of container cranes since. Liftech is the structural review engineer of record for most
Truss. are both simple and A Matsuo Example continuous trusses. The
Girder Bridge A girder bridge is perhaps the most common and most basic bridge. A log across a creek is an example of a girder bridge in its simplest form. In modern steel girder bridges, the two most
CITY OF TRAIL MEMORANDUM
0 C CITY OF TRAIL MEMORANDUM DATE: TO: FROM: SUBJECT: March 24, 2011 FILE NO. 5400-02 DAVID PEREHJJDOFF, CHIEF ADM1NTSTRATIVE OFFICER WARREN PROULX, ENGINEERING TECHMCIAN OLD TRAIL BRIDGE With the interest
Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation
Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation Jeff R. Hill, P.E. Hayward Baker Inc. 111 W. Port Plaza Drive Suite 600 St. Louis, MO 63146 314-542-3040 [email protected]
4.3.5 - Breakaway Walls
4.3.5 - Breakaway Walls Elevation of a structure on a properly designed foundation reduces the potential for water damage from flooding. When the space below the lowest elevated floor is maintained free
Quality Control and Quality Assurance Guide
Quality Control and Quality Assurance Guide Bridge Division, Design Section October 2013 Table of Contents Chapter 1 About this Guide... 3 Chapter 2 Goals and Objectives... 5 Chapter 3 Participants...
Analysis of the Interstate 10 Twin Bridge s Collapse During Hurricane Katrina
Analysis of the Interstate 0 Twin Bridge s Collapse During Hurricane Katrina By Genda Chen, Emitt C. Witt III, David Hoffman, Ronaldo Luna, and Adam Sevi The Interstate 0 Twin Span Bridge over Lake Pontchartrain
TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE
TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE TECHNICAL SPECIFICATION PART 8000 - PRECAST CONCRETE TABLE OF CONTENTS Item Number Page 8100 PRECAST CONCRETE CONSTRUCTION - GENERAL 8-3 8101 General
The Analysis of Open Web Steel Joists in Existing Buildings
PDHonline Course S117 (1 PDH) The Analysis of Open Web Steel Joists in Existing Buildings Instructor: D. Matthew Stuart, P.E., S.E., F.ASCE, F.SEI, SECB, MgtEng 2013 PDH Online PDH Center 5272 Meadow Estates
Cable-Stayed Bridge Uses New Post-Tensioning System
Stretching over the Ohio River Cable-Stayed Bridge Uses New Post-Tensioning System By William B. Caroland, PE, and Jorge M. Suarez, PE Located approximately 2.8 miles downstream from the suspension bridge
4B-2. 2. The stiffness of the floor and roof diaphragms. 3. The relative flexural and shear stiffness of the shear walls and of connections.
Shear Walls Buildings that use shear walls as the lateral force-resisting system can be designed to provide a safe, serviceable, and economical solution for wind and earthquake resistance. Shear walls
SEISMIC UPGRADE OF OAK STREET BRIDGE WITH GFRP
13 th World Conference on Earthquake Engineering Vancouver, B.C., Canada August 1-6, 2004 Paper No. 3279 SEISMIC UPGRADE OF OAK STREET BRIDGE WITH GFRP Yuming DING 1, Bruce HAMERSLEY 2 SUMMARY Vancouver
Value Engineering vs. Alternate Designs in Bridge Bidding
Value Engineering vs. Alternate Designs in Bridge Bidding Compares the advantages and disadvantages of alternate designs and value engineering in bidding of bridges as experienced in the State of Florida.
June 2007 CHAPTER 7 - CULVERTS 7.0 CHAPTER 7 - CULVERTS 7.1 GENERAL
7.0 7.1 GENERAL For the purpose of this manual, culverts are defined as structures that are completely surrounded by soil and located below the surface of the roadway parallel to the general direction
Overhang Bracket Loading. Deck Issues: Design Perspective
Deck Issues: Design Perspective Overhang Bracket Loading Deck overhangs and screed rails are generally supported on cantilever brackets during the deck pour These brackets produce an overturning couple
Index 20010 Series Prestressed Florida-I Beams (Rev. 07/12)
Index 20010 Series Prestressed Florida-I Beams (Rev. 07/12) Design Criteria AASHTO LRFD Bridge Design Specifications, 6th Edition; Structures Detailing Manual (SDM); Structures Design Guidelines (SDG)
Evaluation of Appropriate Maintenance, Repair and Rehabilitation Methods for Iowa Bridges
T. J. Wipf, F. S. Fanous, F. W. Klaiber, A. S. Eapen Evaluation of Appropriate Maintenance, Repair and Rehabilitation Methods for Iowa Bridges April 2003 Sponsored by the Iowa Department of Transportation
SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS
July 14, 2015 1.0 GENERAL BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS This work shall consist of furnishing all materials, equipment, labor, and incidentals necessary for conducting bi-directional
KOSCIUSZKO BRIDGE PROJECT BRIDGE PRIMER
KOSCIUSZKO BRIDGE PROJECT BRIDGE PRIMER The New York State Department of Transportation (NYSDOT) is preparing an Environmental Impact Statement (EIS) to evaluate alternatives for the rehabilitation or
COLUMN-FREE OFFICE SPACE RISES IN CHICAGO S LOOP
COLUMN-FREE OFFICE SPACE RISES IN CHICAGO S LOOP 30 x45 bay provides maximum tenant flexibility and increases leasing marketability By David E. Eckmann AIA, S.E. P.E. SURGING DEMANDS FOR RENTABLE OFFICE
Materials. Estimating Steel. Players. Materials. Shop Drawings. Detailing Process. Standard shapes. Fabricated members, Built-up sections
Materials Standard shapes W sections, C channels, Structural T, Angles, Pipes, Tubes, Rods and Plates Fabricated members, Built-up sections Adding plates to beam flanges, Stiffeners to beam webs Built
Draft Table of Contents. Building Code Requirements for Structural Concrete and Commentary ACI 318-14
Draft Table of Contents Building Code Requirements for Structural Concrete and Commentary ACI 318-14 BUILDING CODE REQUIREMENTS FOR STRUCTURAL CONCRETE (ACI 318 14) Chapter 1 General 1.1 Scope of ACI 318
METHOD OF STATEMENT FOR STATIC LOADING TEST
Compression Test, METHOD OF STATEMENT FOR STATIC LOADING TEST Tension Test and Lateral Test According to the American Standards ASTM D1143 07, ASTM D3689 07, ASTM D3966 07 and Euro Codes EC7 Table of Contents
Optimum proportions for the design of suspension bridge
Journal of Civil Engineering (IEB), 34 (1) (26) 1-14 Optimum proportions for the design of suspension bridge Tanvir Manzur and Alamgir Habib Department of Civil Engineering Bangladesh University of Engineering
Steel joists and joist girders are
THE STEEL CONFERENCE Hints on Using Joists Efficiently By Tim Holtermann, S.E., P.E.; Drew Potts, P.E.; Bob Sellers, P.E.; and Walt Worthley, P.E. Proper coordination between structural engineers and joist
MEMORANDUM. 1509 West Swann Avenue, Suite 225 Tampa, Florida 33606 Phone (813) 258-8818 Fax (813) 258-8525
1509 West Swann Avenue, Suite 225 Tampa, Florida 33606 Phone (813) 258-8818 Fax (813) 258-8525 To: From: Date: Subject: Mr. Thomas Gibson, City of St. Petersburg Jeffrey D. Malyszek, PE and Deborah C.
Brandangersundet Bridge A slender and light network arch
Brandangersundet Bridge A slender and light network arch Rolf Magne Larssen Dr. ing./ Ph.D. Dr. ing A. Aas-Jakobsen AS Oslo, Norway [email protected] Rolf Magne Larssen, born 1958, received his Ph.D. in structural
Prestressed Concrete I-Beam and TxGirder Haunch Design Guide
Prestressed Concrete I-Beam and TxGirder Haunch Design Guide Components of the Haunch Camber: Camber is the upward deflection in the beam after release of the prestressing strands due to the eccentricity
REPAIR AND STRENGTHENING OF HISTORICAL CONCRETE BRIDGE OVER VENTA RIVER IN LATVIA
1 REPAIR AND STRENGTHENING OF HISTORICAL CONCRETE BRIDGE OVER VENTA RIVER IN LATVIA Verners Straupe, M.sc.eng., Rudolfs Gruberts, dipl. eng. JS Celuprojekts, Murjanu St. 7a, Riga, LV 1024, Latvia e-mail:
TECHNICAL USER MANUAL for STANDARD HALF THROUGH UNDERBRIDGES Z TYPE
NR/CIV/TUM/1200 Rev D May 2010 TECHNICAL USER MANUAL for STANDARD HALF THROUGH UNDERBRIDGES Z TYPE Standard Detail and Design Drawings Page 1 of 38 NR/CIV/TUM/1200 Rev D May 2010 Summary This technical
INTRODUCTION TO BEAMS
CHAPTER Structural Steel Design LRFD Method INTRODUCTION TO BEAMS Third Edition A. J. Clark School of Engineering Department of Civil and Environmental Engineering Part II Structural Steel Design and Analysis
EAST LYME HIGH SCHOOL
Overview: 1971 N 1966 GYM 1966 CLASSROOM WING 1966 AUD. 1971 GYM 1998 1998 POOL EAST LYME HIGH SCHOOL Original 1966 Building: The original East Lyme High School was constructed in 1966 and was composed
Structural Failures Cost Lives and Time
Structural Failures Cost Lives and Time Recent failures of storage bins, silos and other structures highlight the need to increase awareness of hazards associated with these structures. Since 2010, one
STRUCTURAL CONCEPT FOR LIGHT GAUGE STEEL FRAME SYSTEM
Chapter 9 STRUCTURAL CONCEPT FOR LIGHT GAUGE STEEL FRAME SYSTEM 9.1 BACKGROUND Steel is widely used in the construction of multi-storey buildings. However, steel construction is seldom used and is traditionally
Page & Turnbull imagining change in historic environments through design, research, and technology
DCI+SDE STRUCTURAL EVALUATIONS OFFICE BUILDING, TOOL SHED & WATER TANK, AND BLACKSMITH & MACHINE SHOP BUILDINGS SAN FRANCISCO, CALIFORNIA [14290] PRIMARY PROJECT CONTACT: H. Ruth Todd, FAIA, AICP, LEED
After reading this lesson you will be able to: 12.3 IMPORTANCE OF ROOF 12.4 TYPES OF ROOF IN A HOUSE
86 :: Certificate in Construction Supervision (CIVIL) 12 ROOF 12.1 INTRODUCTION The structure provided to cover the house surface (floor) is known as roof. For different situation and requirement, it is
Historic Bridges of Frederick County. Frederick County, Maryland Division of Public Works Department of Highways and Transportation (301) 600-1687
Historic Bridges of Frederick County Frederick County, Maryland Division of Public Works Department of Highways and Transportation (301) 600-1687 Frederick County s Bridges We have 212 bridges over 20
PRELIMINARY SEISMIC CONSIDERATIONS FOR PULASKI SKYWAY REHABILITATION PROJECT. Xiaohua H. Cheng 1
PRELIMINARY SEISMIC CONSIDERATIONS FOR PULASKI SKYWAY REHABILITATION PROJECT Abstract Xiaohua H. Cheng 1 The 3.5 mile (5.63 km) long Pulaski Skyway is located in northern New Jersey, serving as a major
Report on. Wind Resistance of Signs supported by. Glass Fiber Reinforced Concrete (GFRC) Pillars
Report on Wind Resistance of Signs supported by Glass Fiber Reinforced Concrete (GFRC) Pillars Prepared for US Sign and Fabrication Corporation January, 2006 SUMMARY This study found the attachment of
Rehabilitation of Locks on the Kentucky River
Rehabilitation of Locks on the Kentucky River Joshua M. Repp, PE Bergmann Associates Presentation Overview River System History Evolution of Lock and Dams Structures Existing Condition of Structures Lock
Public Information & Public Scoping Meeting
Public Information & Public Scoping Meeting William F. Cribari Memorial Bridge Route 136 over the Saugatuck River Review of Rehabilitation Study Report Public Scoping for the gathering and analysis of
Detailing of Reinforcment in Concrete Structures
Chapter 8 Detailing of Reinforcment in Concrete Structures 8.1 Scope Provisions of Sec. 8.1 and 8.2 of Chapter 8 shall apply for detailing of reinforcement in reinforced concrete members, in general. For
BRIDGES ARE relatively expensive but often are
Chapter 10 Bridges Chapter 10 Bridges Bridg Bridges -- usually the best, but most expensive drainage crossing structure. Protect bridges against scour. BRIDGES ARE relatively expensive but often are the
Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations
Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations Nathan A. Ingraffea, P.E., S.E. Associate, KPFF Consulting Engineers, Portland, Oregon, USA Abstract The use of steel sheet
INCREASE OF DURABILITY AND LIFETIME OF EXISTING BRIDGES. PIARC TC 4.4 EXPERIENCE.
INCREASE OF DURABILITY AND LIFETIME OF EXISTING BRIDGES. PIARC TC 4.4 EXPERIENCE. M.Sc. Gediminas Viršilas Head of Bridge Division, Lithuanian Road Administration Working group 2 of PIARC Technical Committee
1,045 m length of the Deh Cho Bridge
Innovative Design Features: Lightweight truss: The principles of lightweight design led to a saving of 25% in the use of structural steel. State of the art deck system: Designed as a four-way slab, it
Handling, Erection and Bracing of Wood Trusses
Handling, Erection and Bracing of Wood Trusses Follow these guidelines for safe installation of Wood Trusses. These guidelines should not be considered to be the only method for erecting and bracing of
Risk - Based Inspection Frequencies
Risk - Based Inspection Frequencies Glenn A. Washer, PhD University of Missouri Columbia, MO April 23, 2013 Northwest Bridge Inspector s Conference 1 NCHRP 12-82 Developing Reliability Based Bridge Inspection
1997 Uniform Administrative Code Amendment for Earthen Material and Straw Bale Structures Tucson/Pima County, Arizona
for Earthen Material and Straw Bale Structures SECTION 70 - GENERAL "APPENDIX CHAPTER 7 - EARTHEN MATERIAL STRUCTURES 70. Purpose. The purpose of this chapter is to establish minimum standards of safety
FINAL FAILURE INVESTIGATION WESTCHESTER NORTH LAGOON BRIDGE. Anchorage, Alaska
FINAL FAILURE INVESTIGATION WESTCHESTER NORTH LAGOON BRIDGE Anchorage, Alaska August 2014 Prepared for: Municipality of Anchorage Project Management and Engineering P.O. Box 196650 Anchorage, Alaska 99519-6650
INDIANA DEPARTMENT OF TRANSPORTATION BRIDGE INSPECTION PROGRAM CODING GUIDE
INDIANA DEPARTMENT OF TRANSPORTATION BRIDGE INSPECTION PROGRAM CODING GUIDE BRAGI Bridge Reporting for Appraisal & Greater Inventory Volume III: Other INDOT Items November 2011 Item Number Item Name BRAGI
5 ALTERNATIVE SOLUTIONS AND EVALUATION
Page 23 5 ALTERNATIVE SOLUTIONS AND EVALUATION The process used for the assessment and evaluation of the alternatives follows the procedures of the Municipal Class EA, as described below: Identify a reasonable
FORM DESIGN. easy to work with, and generally available.
Forms play a major role in concrete construction. They give the plastic concrete its shape and hold it until it hardens. Forms protect the concrete, assist in curing it, and support any reinforcing rods
INSTALLATION. General. Important Note. Design. Transport
General The roof trusses you are about to install have been manufactured to precise engineering standards. To ensure that the trusses perform as designed, it is essential that they be handled, erected
Virginia Approach Spans
Virginia Concrete Conference 2009 Woodrow Virginia Approach Spans David Tackoor, HNTB Formerly of URS Corp for Potomac Crossing Consultants Woodrow 1 Second Severn Crossing 2 Medway Crossing (Channel Tunnel
Foundations 65 5 FOUNDATIONS. by Richard Chylinski, FAIA and Timothy P. McCormick, P.E. Seismic Retrofit Training
Foundations 65 5 FOUNDATIONS by Richard Chylinski, FAIA and Timothy P. McCormick, P.E. 66 Foundations Foundations 67 FOUNDATIONS Let's assume that the retrofit has been done correctly from the roofline
Red Wing Bridge Project. PAC #5/TAC #8 Meeting July 18, 2013
Red Wing Bridge Project PAC #5/TAC #8 Meeting July 18, 2013 Alternatives Analysis Agenda Overview of Past Progress Progress Since April PAC Bridge 9103 Rehabilitation Study Bridge 9040 Rehab vs. Replacement
STRUCTURAL ASSESSMENT. Full Metal Jacket Building 0 Prince Street, Alexandria, VA
STRUCTURAL ASSESSMENT FOR Full Metal Jacket Building 0 Prince Street, Prepared by: ALPHA CORPORATION (Alpha) 1850 S. Loudoun Street, Suite 200 Winchester, VA 22601 540-723-0704 September 22, 2010 J. Michael
Formwork for Concrete
UNIVERSITY OF WASHINGTON DEPARTMENT OF CONSTRUCTION MANAGEMENT CM 420 TEMPORARY STRUCTURES Winter Quarter 2007 Professor Kamran M. Nemati Formwork for Concrete Horizontal Formwork Design and Formwork Design
Ross River Suspension Bridge Ross River, Yukon. Life Cycle Cost Analysis
DNA project managers planners architects engineers David Nairne + Associates Ltd Suite 250 171 W Esplanade North Vancouver British Columbia Canada V7M 3J9 T 604 984 3503 F 604 984 0627 E dna@ davidnairne.com
Elevating Your House. Introduction CHAPTER 5
CHAPTER 5 Elevating Your House Introduction One of the most common retrofitting methods is elevating a house to a required or desired Flood Protection Elevation (FPE). When a house is properly elevated,
Hunter College school of Social Work Thesis Proposal
Fall 2009 Hunter College school of Social Work Thesis Proposal To analyze how energy efficiency can be implemented using facade and green roof redesign. It ties structural engineering concepts with existing
Design and Construction of Cantilevered Reinforced Concrete Structures
Buildings Department Practice Note for Authorized Persons, Registered Structural Engineers and Registered Geotechnical Engineers APP-68 Design and Construction of Cantilevered Reinforced Concrete Structures
A transverse strip of the deck is assumed to support the truck axle loads. Shear and fatigue of the reinforcement need not be investigated.
Design Step 4 Design Step 4.1 DECK SLAB DESIGN In addition to designing the deck for dead and live loads at the strength limit state, the AASHTO-LRFD specifications require checking the deck for vehicular
BRIDGE DESIGN MANUAL
BRIDGE DESIGN MANUAL 2003 Edition (U.S. Customary Units) State of Connecticut Department of Transportation Revisions: 7/04, 11/04, 1/05, 3/05, 1/09, 3/09, 2/11 PREFACE The Connecticut Department of Transportation
Joist. Reinforcement. Draft 12/7/02
Joist Reinforcement Draft 12/7/02 1 JOIST REINFORCING The purpose of this CSD Design Aid is to provide procedures and suggested details for the reinforcement of open web steel joists. There are three basic
Basic Principles & Common Practices
DETAILING STAIRS: Basic Principles & Common Practices Figure 1: Stair Terminology By Andrew J. Bellerby This article is designed to provide an introduction to detailing stairs. It explains the basic principles
Peer Review Scope of Work
1.0 PROJECT OVERVIEW The St. Croix River Crossing Project has been developed in response to traffic congestion, operation deficiencies, safety concerns, and structural deficiencies of the Stillwater Lift
Bracing Webs in Trusses that have Dissimilar Configurations
Bracing Webs in Trusses that have Dissimilar Configurations Released April 25, 2006 Issue: Truss Design Drawings (TDD) that are prepared in accordance with ANSI/TPI 1, National Design Standard for Metal
REINFORCED CONCRETE. Reinforced Concrete Design. A Fundamental Approach - Fifth Edition. Walls are generally used to provide lateral support for:
HANDOUT REINFORCED CONCRETE Reinforced Concrete Design A Fundamental Approach - Fifth Edition RETAINING WALLS Fifth Edition A. J. Clark School of Engineering Department of Civil and Environmental Engineering
LEGACY REPORT ER-5110. www.icc-es.org. ICC Evaluation Service, Inc. Reissued November 1, 2003. Legacy report on the 1997 Uniform Building Code
LEGACY REPORT Reissued November 1, 2003 ICC Evaluation Service, Inc. www.icc-es.org Business/Regional Office # 5360 Workman Mill Road, Whittier, California 90601 # (562) 699-0543 Regional Office # 900
How To Build A Luxury Apartment Complex In London
Post Tensioning Awards 2009 Project Summary Type of structure Location Architects Structural Engineer Residential with leisure suites including Swimming pool, Cinema, Virtual Golf, Wine Cellars, and Parking
EFFECTS ON NUMBER OF CABLES FOR MODAL ANALYSIS OF CABLE-STAYED BRIDGES
EFFECTS ON NUMBER OF CABLES FOR MODAL ANALYSIS OF CABLE-STAYED BRIDGES Yang-Cheng Wang Associate Professor & Chairman Department of Civil Engineering Chinese Military Academy Feng-Shan 83000,Taiwan Republic
HURRICANE MITIGATION RETROFITS FOR EXISTING SITE-BUILT SINGLE FAMILY RESIDENTIAL STRUCTURES
HURRICANE MITIGATION RETROFITS FOR EXISTING SITE-BUILT SINGLE FAMILY RESIDENTIAL STRUCTURES 101 Retrofits Required. Pursuant to Section 553.844 553.884, Florida Statutes, strengthening of existing site-built,
A 38-story design-build steel structure features a staggered-truss frame
ALADDIN HOTEL A 38-story design-build steel structure features a staggered-truss frame Robert J. McNamara is president of McNamara/Salvia, Inc., in Boston. Among his more notable projects during his more
Certification: Building Plans Examiner. Exam ID: B3
Certification: Building Plans Examiner Exam ID: B3 Scope: A Building Plans Examiner will be responsible for reviewing submitted plans to determine if they meet the requirements of the various Building
