ADAPTIVE NETWORK PROTECTION IN MICROGRIDS
|
|
|
- Clifton Pitts
- 10 years ago
- Views:
Transcription
1 ADAPTIVE NETWORK PROTECTION IN MICROGRIDS Alexandre Oudalov a, Antonio Fidigatti b a ABB Switzerland Ltd., Corporate Research, Segelhof 1, CH-5405 Dättwil, Switzerland Phone , Fax [email protected] b ABB SACE S.p.A, Via Baioni 35, 24123, Bergamo, Italy Phone [email protected] Keywords: Microgrids; adaptive protection; distributed energy resources; islanded operation; relay settings; directional interlock ABSTRACT Microgrids comprise low voltage distribution systems with distributed energy resources (DER) and controllable loads which can operate connected to the medium voltage grid or islanded in a controlled coordinated way. This concept aims to move from connect and forget philosophy towards an integration of DER. Microgrids are expected to provide environmental and economic benefits for endcustomers, utilities and society. However, their implementation poses great technical challenges, such as a protection of microgrid. Local generation in a combination with a possible islanded operation can pose protection sensitivity and selectivity problems in case of fault depending on the relay settings. This paper presents a novel adaptive microgrid protection system using digital relaying and advanced communication. The protection system is based on a centralized architecture where relay protection settings are modified centrally with regard to a microgrid operating condition.
2 1 INTRODUCTION Power systems currently undergo considerable change in operating requirements mainly as a result of deregulation and due to an increasing amount of distributed energy resources (DER). In many cases DER include different technologies that allow generation in small scale (micro-sources) and some of them take advantage of renewable energy resources (RES) such as solar, wind or hydro energy. Having micro-sources close to the load has the advantage of reducing transmission losses as well as preventing network congestions. Moreover, the chance of having a power supply interruption of end-customers connected to a low voltage (LV) distribution grid is diminished since adjacent micro-sources, controllable loads and energy storage systems can operate in the islanded mode in case of severe system disturbances on the transmission system level (in fact a power delivery can be fully independent of the state of the main grid). This is known today as a microgrid [1, 2] and is depicted in Figure 1 where the microgrid is connected to the main medium voltage (MV) grid when the circuit breaker 1 (CB1) is closed (the circuit breakers CB3.2 and 6.2 are normally open). Microgrids may potentially offer various advantages to end-consumers, utilities and society, such as: Improved energy efficiency Minimized overall energy consumption Reduced greenhouse gases and pollutant emissions Improved service quality and reliability Cost efficient electricity infrastructure replacement In light of these, the microgrid concept has stimulated many researchers and attracted the attention of governmental organizations in Europe, USA and Japan [3-5]. Nevertheless, there are various technical issues associated with the integration and operation of microgrids. One of the major challenges is a protection system for microgrid which must respond to both main grid and microgrid faults. In the first case the protection system should isolate the microgrid from the main grid as rapidly as necessary to protect the microgrid loads. In the second case the protection system should isolate the smallest part of the microgrid when clears the fault [6]. A segmentation of microgrid, i.e. a creation of multiple islands or sub-microgrids must be supported by micro-source and load controllers. Under these circumstances, problems related to selectivity (false, unnecessary tripping) and sensitivity (undetected faults or delayed tripping) of protection system may arise. Issues related to a protection of microgrids and distribution grids with a large penetration of DER have been addressed in recent publications [7-10]. Basically, there are two main issues, first is related to a number of installed micro-sources in the microgrid and second is related to an availability of a sufficient level of shortcircuit current in the islanded operating mode of microgrid since this level may drop down substantially after a disconnection from the stiff medium voltage grid.
3 Figure 1: Typical microgrid layout. In [11], authors have made short-circuit current calculations for a radial feeder with DER and observed that short-circuit currents, which are used in over-current (OC) protection relays, depend on the connection point of and the feed-in power of DER. Because of these directions and amplitudes of short circuit currents will vary. In fact, operating conditions of microgrid are constantly changing because of the intermittent micro-sources (wind and solar) and periodic load variation. Also a network topology can be regularly changed aimed at loss minimization or achievement of other economic or operational targets. In addition controllable islands of different size and content can be formed as a result of faults in the main grid or inside a microgrid. In such circumstances a loss of relay coordination may happen and generic OC protection with a single setting group may become inadequate, i.e. it will not guarantee a selective operation for all possible faults. Therefore, it is essential to ensure that settings chosen for OC protection relays take into account a grid topology and changes in location, type and amount of generation. Otherwise, unwanted operation or failure to operate when required may occur. In order to cope with bi-directional power flows and low short-circuit current levels in microgrids dominated by micro-sources with power electronic interfaces a new protection philosophy is required, where setting parameters of relays must be checked/updated periodically to ensure that they are still appropriate. This paper presents a novel adaptive microgrid protection concept using advanced communication system, real-time measurements and data from off-line short circuit analysis. This concept is based on an adaptation of protection relay settings with regard to a microgrid state (topology, generation and load). Further, on the hardware realization (basic components, communication, etc.) of this concept and numerically simulated test results are presented. The outlay of this paper is as follows, Section 2 gives an overview of major protection issues in microgrids. Section 3 illustrates a novel adaptive protection concept for microgrids, followed by a discussion of the simulated results in Section 4. Section 5 provides conclusions.
4 2 PROTECTION ISSUES IN MICROGRIDS A protection of low voltage distribution grid where feeders are radial with loads tapped-off along feeder sections is usually designed assuming an unidirectional power flow and is based on OC relays with time-current discriminating capabilities. OC protection detects the fault from a high value of the fault current flowing downwards. In modern digital relays, a tripping short-circuit current can be set for a wide range, e.g *CB rated current. If a measured current is above the tripping setting, the relay operates to trip the CB on the line with a short delay defined by a coordination study and compatible with a locking strategy used (no locking, fixed hierarchical locking, directional hierarchical locking). Figure 2: Different fault scenarios in microgrid. During the last decade, the classical set up in distribution grids has slowly been changing due to the installation of DERs such as photovoltaic (PV) panels, wind and micro-gas turbines, fuel cells, batteries, etc. Most of the micro-sources and energy storage devices are not suitable for supplying power directly to the grid and have to be interfaced to the grid with power electronics (PE) interfaces. A use of PE interfaces leads to a number of challenges in microgrid protection, especially in the islanded mode. Figure 2 represents the same microgrid as shown in Figure 1 with two feeders connected to the LV bus and to the MV bus via a distribution transformer. Each feeder has three switchboards (SWB). Each SWB has star or delta configuration and connects the local DER and load to the feeder. We analyzed two external (F1, F2) and two internal (F3, F4) microgrid faults. All LV CBs (from CB1 to CB6.5) may have different ratings but are equipped with OC protection and used for segmenting the microgrid. In general, protection issues in the microgrid can be divided in to two groups with regard to the microgrid operating state, see Table 1. It also point out the importance of the 3S (sensitivity, selectivity and speed) requirements for different cases, which provides a basis for the design criteria for the microgrid protection system.
5 2.1 Grid connected external fault (F1, F2) In case of fault F1 a main grid (MV) protection clears the fault. If sensitive loads are presented in microgrid, the microgrid could be isolated by CB1 as fast as in 70 ms (depending on a voltage drop in the microgrid). Also the microgrid must also be isolated from the main grid by CB1 in case of no protection units tripping in medium voltage. Table 1: Major classes of microgrid protection problems Operating mode Grid connected (CB1 is closed) Islanded (CB1 is open) External faults (main grid) MV feeder, busbar (F1) Fault is normally managed by MV system. Microgrid isolation by CB1 in case of no MV protection tripping. Possible fault sensitivity problems for CB1* Distribution transformer (F2) Fault is normally managed by MV system (CB0). CB1 is opened by follow-me function of CB0. In case if communication fails then possible fault sensitivity problem for CB1*. Fault location Internal faults (microgrid) LV feeder (F3) Disconnect a smallest portion of microgrid (CB1.2 and CB2.1). CB1.2 is opened by fault current from the grid (high level). Low level of a reversed fault current from feeder s end may cause sensitivity problems for CB2.1*. In this case a follow-me function of CB1.2 can to open CB2.1. In case if communication fails then possible fault sensitivity problems for CB2.1*. Disconnect the smallest portion of microgrid (CB1.2 and CB2.1). Low level of fault currents from both directions may cause sensitivity problems for CB1.2 and CB2.1*. LV consumer (F4) Faulty load is isolated by CB2.4 or fuse. In case of no tripping the SWB is isolated by CB2.5 and local DER is cut-off. No sensitivity or selectivity problems. Faulty load is isolated by CB2.4 or fuse. In case of no tripping the SWB is isolated by CB2.5 and local DER is cut-off. Sensitivity or selectivity problems not likely. *) low fault current contribution from the Microgrid in case of DER with PE interfaces. A detection of F1 with a generic OC relay can be problematic in the case when most of micro-sources in the microgrid are connected by means of PE interfaces having built-in fault current limitation, i.e. there is no significant rise in current passing through CB1. Typically they are capable of supplying *I DERrated to a fault, unless the converters are specifically designed to provide high fault currents. These numbers are much lower than a short-circuit current supplied by the main grid. A directional OC relay acting on CB1 is a feasible solution only if the current is used for the fault detection. In order to increase relay sensitivity a setting for a reverse current is defined as a sum of fault current contributions from all connected DERs (1). This value will vary in case of a large number of different types of DERs. Thus, the setting has to be continuously monitored and adapted when microgrid generation undergoes considerable changes (related to the number and type of connected DERs). Alternatively, voltage drop (magnitude and duration) or/and system frequency (instantaneous value and rate of change) can be used as another indicators for a tripping of CB1 [12]. Some distribution network operators (DNO)
6 may require microgrid to stay connected and supply reactive power to the fault for up to several seconds. In case of fault F2 a distribution transformer OC protection clears the fault by opening CB0. CB1 is opened simultaneously by follow-me function (hardware lock) of CB0. In case of hardware lock failure a possible fault sensitivity problem can arise as in the case of fault F1. Typical solutions are similar to the F1 case, such as directional adaptive OC protection, under-voltage and under-frequency protection. 2.2 Grid connected fault in the microgrid (F3) In case of fault F3 a microgrid protection should disconnect the smallest possible portion of the LV feeder by CB1.2 and CB2.1. CB1.2 is opened due to a high level of short-circuit current supplied by the main MV grid. If CB1.2 fails to trip, the fault F3 must be cleared by CB1.1 which is a backup protection for CB1.2. However, the sensitivity of OC protection relay in CB1.1 can be potentially disturbed in the case when synchronous DERs (e.g. diesel generator) are installed and switchedon in SWB1 (i.e. between CB1.1 and the fault F3). In this case the fault current passing the CB1.1 with a DER will be smaller than in case without a DER. This effect is known as protection blinding (the larger the synchronous DER the greater is the effect) and may result in a delayed CB1.1 tripping because of the fault current transition from a definite-time part to an inverse-time part of relay tripping characteristic. The delayed fault tripping will lead to an unnecessary disconnection of local synchronous DERs (usually low power diesel generators have very low inertia and can lose synchronism if fault clearing too slow). However, this issue can be solved by a proper coordination of the microgrid and the DER protection systems. Another option is adapting protection settings with regard to the current operating conditions (DER status). If, as likely, CB1.2 operates faster than CB2.1 it will island a part of the microgrid which will be connected to the fault F3. If it is possible to balance a generation and load in the islanded segment of the microgrid it is expedient to isolate that group of micro-sources and loads from the fault F3 by opening CB2.1 and possibly closing CB However, a reversed and low level short circuit current in case of DERs with PE interfaces will cause a sensitivity problem for CB2.1 similar to one described in Section 2.1 in case of the fault F1. Possible solutions include directional adaptive OC protection and a follow-me function of CB1.2 which opens CB2.1 (in case of communication failure possible sensitivity problems for CB2.1). 2.3 Grid connected fault in the end-consumer site (F4) In case of fault F4 a high short-circuit current is supplied to the fault from the main grid together with a contribution from DER and will lead to a tripping of CB2.4. Frequently, there is a fuse instead of CB which is rated in such a way that a shortest possible fault isolation time is guaranteed. In case of no tripping the SWB2 is isolated by CB2.5 and local DER is cut-off. No sensitivity or selectivity problems are foreseen in this scenario.
7 2.4 Islanded mode fault in the microgrid (F3) The microgrid operates in the islanded mode when it is intentionally disconnected from the main MV grid by CB1 (full microgrid) or any CB along the LV feeder (a segment of the microgrid). This operating mode is characterized by an absence of a high level of short-circuit current supplied by the main grid. Generic OC relays would be required to be replaced by directional OC relays because fault currents flow from both directions to the fault F3. If CB1.2 and CB2.1 use setting groups chosen for the grid connected mode they will have a selectivity problem to detect the fault F3 and trip within acceptable time frame in case of DER with PE interfaces; the fault current could shift from a definite-time part to an inverse-time part of the relay tripping characteristic. The question arises: why one needs to care about a fault if there is no fault current? The answer to this question is (a) for safety reasons (b) to avoid damage to equipment caused by permanent faults which may propagate. There are two possible ways to address the problem of absence of a high level short-circuit current: Install a source of high short-circuit current (e.g. a flywheel or a supercapacitor) to trip CBs/blow fuses with settings/ratings for the grid connected mode. However, a short-circuit handling capability of PE interfaces can be increased by increasing the respective overloading rating which leads to extra investment cost. In case such source of high short-circuit current is installed, it would be typically connected to the LV bus bar. Install an adaptive microgrid protection using on-line data on microgrid topology and status of available micro-sources/loads. 2.5 Islanded mode fault in the end-consumer site (F4) In case of fault F4, a low short-circuit current is supplied to the fault from the local DERs. There is no grid contribution. However, CB2.4 settings selected for the main grid connected mode are just slightly higher than rated load current. It assures that the end-customer site will be disconnected even if only DERs with PE interfaces are available in the microgrid. In case of no tripping the SWB2 must be isolated by CB2.5 using directional OC relay. Similar to the grid connected mode there are no sensitivity or selectivity problems are foreseen in the islanded mode for the fault in the end-consumer site. 2.6 Conclusive remarks Finally it was seen that the main microgrid protection problem is related to a large difference between fault currents in main grid connected and islanded modes. A microgrid protection system must have a high sensitivity to faults and selectively isolate/sectionalize microgrid especially in the case of DERs with PE interfaces (low fault current levels). In fact a decision on either sectionalize microgrid or shut it down in case of fault will depend on needs of microgrid customers and whether a cost involved (protection and communication) could be justified for benefits gained by a sectionalizing (e.g. reduced end-consumer interruption time). According to
8 system reliability index figures, approximately faults (overhead lines) and <5 (underground cables) per 100 km occur annually in typical European LV networks [13]. It implies that, taking into account the on the connections faults, less than 2 faults per 5 years (overhead lines) and 1 fault per 20 years (underground cables) will take place inside a typical microgrid spanning over 1 km. However, more faults happen in MV grid and microgrid has to be isolated from these faults too. 3 ADAPTIVE PROTECTION FOR MICROGRID This section illustrates an adaptive protection system that can potentially solve problems identified in the previous section by anticipating an impact of microsources (DERs) and microgrid configuration on the relay performance and accordingly change the relay settings to ensure that the whole microgrid is protected at all times. Adaptive protection is as "an online activity that modifies the preferred protective response to a change in system conditions or requirements in a timely manner by means of externally generated signals or control action" [14]. Technical requirements and suggestions for a practical implementation of an adaptive microgrid protection system are as following: Use of numerical directional OC relays because fuses or electromechanical and standard solid state relays are (especially for selectivity holding) inapplicable - they do not provide the flexibility for changing the settings of tripping characteristics and they have no current direction sensitivity feature. Numerical directional OC relays must dispose of possibility for using different tripping characteristics (several settings groups) that can be parameterized locally or remotely automatically or manually. Use of new/existing communication infrastructure (e.g. twisted pair, power line) and standard communication protocols (Modbus, IEC61850) such that individual relays can communicate and exchange information with a central computer or between different individual relays fast 1 and reliably to guarantee a required application performance. An adaptive protection system which will satisfy these requirements will be characterized by a relatively high investment cost in comparison to a conventional protection system based on fuses. In light of this it is interesting to carry out a separate 1 The communication time lag and the maximum time lag are not critical values for this application, because the communication infrastructure is used to collect information about the microgrid configuration and to change accordingly relay settings only. The interlock, if required, is done by means of physical point-to-point connection. On master-slave protocol like Modbus the changes of the configuration have to be identified with a maximum delay of 1-10 seconds dependent on the dimension of the network, and the protection reconfiguration has to be completed in times of the same order as previous ones, providing that basic backup protection functions are present during the transitory phase. On pear-to-pear protocol like IEC61850 the changes on the network configuration are triggering the protection reconfiguration. The accepted delays are equivalent with the previous ones.
9 cost-benefit analysis in case of microgrid. Cost will correspond to investment and operating costs over a system lifetime and benefit will correspond to a reduced outage time and opportunity loss. It is not a subject of this study where the focus is on a technical realization of an adaptive protection system for microgrids. An example of centralized adaptive protection system is shown in Figure 3. Figure 3: Centralized adaptive protection system for microgrid. There is a microgrid central controller (MCC) and communication system in addition to elements shown in Figure 1. Communication electronics make each CB with an integrated directional OC electronic trip unit (relay) capable of exchanging information with MCC. For example, in Figure 3 CBs are connected to the serial communication bus RS485 and use standard industrial communication protocol Modbus. By polling individual relays the MCC can read data (electrical values, status) from CBs and if necessary modify a subset of the relay settings (tripping characteristics) on the fly without any resetting protection needs. Each individual relay takes a tripping decision locally (independently of MCC) and performs in accordance to Figure 4. Figure 4: Local protection function inside circuit breaker.
10 In case an abnormal situation is detected a tripping condition is checked (a measured current in a specific direction is compared with the actual relay setting). If the tripping condition is reached a CB is open. The main goal of the adaptive protection system shown in Figure 3 is to maintain settings of each relay with regard to a current state of the microgrid. It is effectuated by a special module in MCC which is responsible for a periodic check and update of relay settings. It consists of two main components: Pre-calculated information during off-line fault analysis of a given microgrid On-line operating block 3.1 Off-line analysis A set of meaningful microgrid configurations as well as feeding-in states of DERs (on/off) is created for off-line fault analysis and is called an event table. Each record in the event table has a number of elements equal to a number of monitored CBs in the microgrid (some elements may have higher priority than others, e.g. the central CB which connects LV and MV grids) and is binary encoded, i.e. element=1 if a corresponding CB is closed and 0 if it is open (Figure 5). Next, fault currents passing through all monitored CBs are estimated by simulating shortcircuits (3-phase, 2-phase, phase-to-ground, etc.) in different locations of the protected microgrid at a time in accordance with IEC During repetitive shortcircuit calculations a topology or a status of a single DER is modified between iterations. As different fault locations for different microgrid states are processed the results (the magnitude and direction of fault current seen by each relay) are saved in a specific data structure. Figure 5: Structure of event table. Based on these results suitable settings for each directional OC relay and for each particular system state are calculated in such a way that guarantees a selective operation of microgrid protection. These settings are grouped into an action table which has the same dimension as the event table. In addition to a regulation of protection settings other actions such as activation of protection function can be done, e.g. a directional interlock can be activated in the islanding situation. The event and action tables are part of the configuration level of the microgrid protection and control system shown in Figure 6, where: External Field Level represents energy market prices, weather forecast, heuristic strategy directives and other utility information
11 Management Level includes historic measurements and distribution management system (DMS) Configuration Level consists of a computer or PLC situated centrally (substation) or locally (switchboard) which is able to detect a system state change and send a required action to hardware level Hardware Level transmits a required action from the configuration level to on-field devices by means of a communication network. In the case of a large microgrid, this function can be divided between several local controllers which communicate only selected information to the central unit. Protection Level may include CB status, release settings, interlocking configuration, etc. Together with Real-time Measurements Level they are sitting inside on-field devices. 3.2 On-line operation During the on-line operation the MCC monitors the microgrid state by polling individual directional OC relays. This process runs periodically or is triggered by an event (tripping of CB, protection alarm, etc.) and uses communication system shown in Figure 3. The microgrid state information received by the MCC is used to construct a status record which has a similar dimension as a single record in the event table. Figure 6: Microgrid protection and control architecture. The status record is used to identify a corresponding entry in the event table. Finally, the algorithm retrieves the pre-calculated relay settings from the corresponding record in the action table and uploads the settings to on-field devices via the
12 communication system. Figure 7 illustrates phases of the adaptive protection algorithm. Figure 7: 3.3 Directional interlock Phases of on-line adaptive protection algorithm with available look-up tables (the event and action tables). Fault detection and selective isolation are very challenging tasks in microgrids dominated by DERs with PE interfaces (Table 1). This subsection presents a solution based on extension of the microgrids adaptive protection system with a directional interlock. A non-directional interlock is a well known technique used in radial distribution feeders without DERs [15]. The interlock starts from the end of the feeder towards the supply side and connects an output port of the trip unit to an input port of the trip unit immediately to the supply side by means of a simple screened-twisted-pair cable. In the case of fault, the CB immediately to the supply side sends a locking signal to the hierarchically higher CB and, before intervening, checks that a similar locking signal has not been reached by the CB on the load side. This guarantees a selective operation of relays even where it is not possible to use a current discrimination. However, in a presence of DERs along the feeder the non-directional interlock will not work correctly because the fault can be supplied from both sides and all CBs between the fault and the most remote DER at the end of the feeder will be unnecessarily tripped which makes difficult to detect the fault location An evolution of this pre-cabled system could be an adaptive directional interlock in order to avoid a non-selective operation of relays in the microgrid. The interlock direction is changed by reassignment output and input ports of corresponding relays. The interlock direction is changed on-fly (in less than 50 ms) depending on a direction of the fault current with regard to a direction of the interlock (towards supply side, i.e. main MV grid) before the fault (Figure 8). The reassignment of ports is based on the following rules: if The fault current direction is opposite to the present interlock direction then Keep present port assignment and if Relay sends locking signal to the present interlock direction The fault current direction is similar to the present interlock direction then switch output/input ports, i.e. interlock direction And relay sends locking signal to the new interlock direction (opposite to the present interlock direction)
13 Figure 8: Adaptive directional interlock. Adaptive directional interlock sends the blocking signals in correct directions, i.e. relays on both sides of faulty element will trip and selectively isolate the fault. 4 SIMULATION RESULTS This section shows an illustrative example of an adaptive protection system combined with a directional interlock and the results are discussed. We used the same microgrid setup as shown in Figure 3. Parameters of the test microgrid are given in Appendix. The microgrid consists of several DERs including synchronous machines and units with PE interfaces. We explored two scenarios with regard to a microgrid configuration and status of DERs: Microgrid without DERs in the grid connected mode Microgrid with DERs (synchronous machines) in the grid connected and islanded modes 4.1 Microgrid with DERs switched off in the grid mode The first scenario is shown in Figure 9. This microgrid topology was used as a base case and the first entry in the event table.
14 Figure 9: Scenario A1: microgrid with DERs switched off is connected to a medium voltage distribution grid. We assume that each electronic trip circuit breaker has a similar shape of an overcurrent protection trip curve (Figure 10). The trip curve consists of an inverse time part L (protection against overloads), a constant time delay part S (protection against short circuit with short time delay trip) and an instantaneous part I (instantaneous protection against short circuit). In order to provide a selective operation of circuit breakers we used different time delays t s in the range between I kmin (expected minimum short circuit current) and I kmax (expected maximum short circuit current). The values of I kmin /I kmax are obtained from the results of off-line numerical simulations of 3-phase, 2-phase, single phase faults in accordance to IEC The CB1 closest to the source has highest t s and the most distant CB3.2 and CB6.2 have the lowest t s (Figure 11). The instantaneous tripping part I is removed from all curves for a simplification purposes. The microgrid topology and suitable OC protection settings for all CBs (calculated during the off-line fault analysis [17]) in the base case are shown in Table 2 based on Figure 9 and Figure 11. DER and load protection settings do not set here but the information on DER and load status (on/off) is required for a correct operation of the microgrid adaptive protection. Figure 10: Typical time-current curve for a low voltage electronic trip circuit breaker [15].
15 Figure 11: Trip curves for circuit breakers in the upper feeder (identical for CBs in the lower feeder) in the base case and a tripping sequence in Scenario A1 (Figure 9). Table 2: Scenario A1: Status of Circuit Breakers 1=close, 0=open and Overcurrent Protection Settings t s in Seconds. Black Box and Bold Numbers Show CBs that See the Fault Upper feeder Lower feeder DER + load DER + load CB1 CB2 CB1.1 CB1.2 CB2.1 CB2.2 CB3.1 CB CB3 CB4.1 CB4.2 CB5.1 CB5.2 CB6.1 CB CB1.3 CB1.4 CB1.5 CB2.3 CB2.4 CB2.5 CB3.3 CB3.4 CB CB4.3 CB4.4 CB4.5 CB5.3 CB5.4 CB5.5 CB6.3 CB6.4 CB In case of fault in the cable between SWB1 and SWB2 (Figure 9) all CBs between the fault and the LV busbar see the fault supplied by the main MV grid (black box and bold numbers in Table 2), but only CB1.2 will trip after t s =300 ms (Figure 11) and CB2.1 will be opened by the follow-me function of CB1.2 in order to avoid connecting the fault to the healthy feeder by closing CB3.2 and CB6.2. Other CBs that see the fault are delayed (in absence of a logic discrimination auxiliary connection). However, this method is limited by a number of discriminating time steps (t s is recommended to be less than 800 ms) and is only suitable for feeders with a small number of switchboards.
16 Figure 12: Scenario A2: microgrid with all DERs switched off is connected to the medium voltage distribution grid. Assume SWB2 and SWB3 are re-supplied via SWB6 (CB3.2 and CB6.2 are closed) after the fault between SWB1 and SWB2 is selectively eliminated (CB1.2 and CB2.1 are open). A selectivity problem may appear if using base case protection settings from Table 2. For example, if the second fault will appear between SWB2 and SWB3 (Figure 12) it will be eliminated by CB3.2 and CB6.2 (t s =100ms) instead of CB3.1 (t s =200 ms) and the load in SWB3 will be unnecessarily tripped. Figure 13: Base case trip curves and a tripping sequence in Scenario A2 with non-directional OC protection (Figure 12). Selectivity can be improved by: Applying directional OC relays Modification of protection settings of non-directional OC relays In the first case we would need to install a new hardware. Each relay will have two t s settings, one for each direction (clockwise and counter-clockwise) as shown in Table 3. In this case a selective protection operation is guaranteed (Figure 14) and SWB3 will remain connected after the fault is eliminated.
17 Table 3: Scenario A2: CB Status and Directional OC Protection Settings t S Upper feeder Lower feeder DER + load DER + load CB1 CB2 CB1.1 CB1.2 CB2.1 CB2.2 CB3.1 CB CB3 CB4.1 CB4.2 CB5.1 CB5.2 CB6.1 CB CB1.3 CB1.4 CB1.5 CB2.3 CB2.4 CB2.5 CB3.3 CB3.4 CB CB4.3 CB4.4 CB4.5 CB5.3 CB5.4 CB5.5 CB6.3 CB6.4 CB Figure 14: Base case trip curves and a tripping sequence in Scenario A2 with directional OC protection (Figure 12). In the second case we modify S part of the base case trip curves by adjusting t s settings (Figure 15). A second record in the event and action tables is created during the off-line fault analysis. In particular we can observe lower t s for CB2.2 and CB3.1 and higher t s for CB3.2 and CB6.2 in comparison to the values shown in Table 2. The second solution with t s modification is characterized by more narrow range of time delays. The maximum t s =0.6 s versus 0.8 s in case of directional OC protection. Table 4: Scenario A2: CB Status and Modified OC Protection Settings t S Upper feeder Lower feeder CB1 CB2 CB1.1 CB1.2 CB2.1 CB2.2 CB3.1 CB CB3 CB4.1 CB4.2 CB5.1 CB5.2 CB6.1 CB DER + load CB1.3 CB1.4 CB1.5 CB2.3 CB2.4 CB2.5 CB3.3 CB3.4 CB3.5
18 DER + load CB4.3 CB4.4 CB4.5 CB5.3 CB5.4 CB5.5 CB6.3 CB6.4 CB Figure 15: Modified base case trip curves (t s settings) and a tripping sequence in Scenario A2 with non-directional OC protection (Figure 12). 4.2 Microgrid with DERs switched on in the grid and islanded modes Assume there is a considerable change in the microgrid configuration and status of DER units: the cable between SWB4 and SWB5 is disconnected for a maintenance work and SWB5 and SWB6 are supplied via SWB3 (CB3.2 and CB6.2 are closed) as illustrated in Figure 16. Figure 16: Scenario B1: microgrid with synchronous DERs switched on is connected to the medium voltage distribution grid. Two identical synchronous diesel generators (parameters are given in Appendix) are connected in SWB1 and SWB6. In addition we assume that all non-directional OC protection relays use t s settings from the base case shown in Table 2. In case of fault between SWB1 and SWB2 (Figure 16) there is no problem to detect and selectively isolate the fault from the main grid side by CB1.2, also because the fault current seen by CB1.2 becomes higher I kmax = 15 ka vs ka in the
19 base case due to a contribution from the synchronous DER in SWB1. The fault current supplied by the second DER in SWB6 and seen by CB2.1 is 2 ka. It can only activate the L part of the relay s trip curve with the expected tripping time delay of 40 s. Therefore, CB2.1 is opened by the follow-me function of CB1.2 and isolates the fault from the LV feeder side in t s =300 ms (if using directional OC protection then t s =600 ms, see Table 3). Figure 17: Base case trip curves and a tripping sequence in Scenario B1 with directional OC protection (Figure 16). The main concern is t s 300 ms set for the OC relay in CB1.2 which may affect a stability of the synchronous DER with a small inertia in SWB1. A preferred solution is based on the adaptive directional interlock (Section 3.3). The time delay t s is set at 100 ms for all OC relays in the microgrid. Then blocking signals are sent in correct directions which prevents an unnecessarily disconnection of DERs and healthy parts of the microgrid. Next we assume that after an isolation of the first fault the island which includes SWB2, 3, 5 and 6 is formed as shown in Figure 18. The synchronous DER in SWB6 is switched to a frequency control mode and additionally each load in the island is dropped from 100A to 50A. Assume there is a second fault inside the islanded microgrid between SWB2 and SWB3 and all non-directional OC relays use t s settings from the base case shown in Table 2. Ideally, the fault should be cleared by CB2.2 and CB3.1. CB2.2 can not trip since there is no fault current source in SWB2, but it can be opened by the follow-me function of CB3.1. The t s of CB3.1 is set at 200 ms for a minimum fault current level of 4*In CB = 3.2 ka. In case of using directional OC protection (Table 3) t s = 300 ms for CB3.1.
20 Figure 18: Scenario B2: islanded microgrid with the synchronous DER. However, the maximum fault current supplied by the synchronous DER in SWB6 and seen by CB3.1 I kmax =2.4 ka. This will activate the L part of the relay s trip curve with the expected tripping time delay of 25 s. During this time DER in SWB6 will be disconnected by its out-of-step protection. In order to guarantee fast fault isolation in the islanded mode where the main grid does not contribute to the fault, the trip curve must be pushed to the left dynamically depending on the microgrid topology and a number of connected DERs (1). DERs that have to be taken into consideration are the subset of units that contribute to the short circuit current on the defined direction. I n = k min kder * I (1) rder 1 where I rder is a rated output current of a particular DER and k is a fault current contribution coefficient (2). I I kder k = (2) where I kder is a fault current supplied by a particular DER. This coefficient is set at 1.1 for DERs with power electronics interfaces and at 5 for synchronous DER units. The modified trip curves for scenario B2 are illustrated in Figure 19. Protection settings for all CBs in the island are calculated during the off-line fault analysis and shown in Table 5 as recorded in the event and action tables. Another protection alternative is based on the adaptive directional interlock (Section 3.3). The tripping time is set at 100 ms for all CBs inside the island and the minimum short circuit current has to be dynamically modified (reduced). rder
21 Figure 19: Base case and modified trip curves and a tripping sequence in Scenario B2 (Figure 18). Table 5: Scenario B2: Modified OC Protection Settings I KMIN and t S Upper feeder Lower feeder DER + load DER + load CB1 CB2 CB1.1 CB1.2 CB2.1 CB2.2 CB3.1 CB I kmin 3.2 3, t s CB3 CB4.1 CB4.2 CB5.1 CB5.2 CB6.1 CB I kmin t s CB1.3 CB1.4 CB1.5 CB2.3 CB2.4 CB2.5 CB3.3 CB3.4 CB CB4.3 CB4.4 CB4.5 CB5.3 CB5.4 CB5.5 CB6.3 CB6.4 CB CONCLUSIONS In this paper, the effect of DERs and topological changes on sensitivity and selectivity of microgrid protection (loss of relay coordination) is investigated. A novel adaptive microgrid protection system using digital relaying and advanced communication infrastructure is proposed. The adaptive protection system is based on a centralized architecture with precalculated information where protection settings are updated periodically by the microgrid central controller with regard to a microgrid operating state. Settings for non-directional or directional over-current relays are pre-calculated during off-line fault analysis of a given microgrid. Fault detection and selective isolation are very challenging tasks in microgrids dominated by DER with power electronics interfaces. The proposed solution is based on extension of the microgrids adaptive protection system with a directional interlock.
22 Several scenarios have been set up to illustrate the effects of adaptation of relay settings. The results of these simulations have been reported and analyzed. 6 REFERENCES [1] Lasseter, R. Microgrids, in Proc. IEEE PES Winter Meeting, New York, [2] Hatziargyriou, N. Asano, A. Iravani, R. Marnay, C. Microgrids, IEEE Power Energy Mag., [3] Kroposki, B. Lasseter, R. Ise, T. Morozumi, S. Papathanassiou, S. Hatziargyriou, N. Making Microgrids Work, IEEE Power Energy Mag., [4] EU Microgrids [online]. Available: [5] European Technology Smart Grid Platform. Smart-grids: Vision and Strategy for European Electricity Networks of the Future [online]. Available: [6] Feero, W. Dawson, D. Stevens, J. Protection Issues of the Microgrid Concept, [online]. Available: [7] Driesen, J. Vermeyen, P. Belmans, R. Protection issues in microgrids with multiple distributed generation units, in Proc. of the 4th Power Conversion Conference, Nagoya, [8] Nukkhajoei, H. Lasseter, R. Microgrid Protection, in Proc. IEEE PES General Meeting, [9] Al-Nasseri, H. Redfern, M. O'Gorman, R. Protecting microgrid systems containing solid-state converter generation, in Proc. Int. Conf. on Future Power Systems, [10] Vilathgamuwa, D. M. Loh, P.C. Li, Y. Protection of Microgrids During Utility Voltage Sags, IEEE Trans. on Industrial Electronics, [11] Girgis, A. and Brahma, S. Effect of Distributed Generation on Protective Device Coordination in Distribution System, in Proc. Large Engineering Systems Conf., [12] Tumilty, R. M. Elders, I. M. Burt, G. M. McDonald, J.R. Coordinated Protection, Control and Automation Schemes for Microgrids, in Int. Journal of Distributed Energy Resources, [13] Questionnaire about distribution networks. Summary of results [online]. Available: [14] Rockefeller, G. et al., Adaptive Transmission Relaying Concepts for Improved Performance, IEEE Trans. on Power Delivery, 1988.
23 [15] Yong, S. Michalak, T. Optimizing system coordination and over-current protection with zone selective interlocking, in Proc. Textile, Fiber and Film Industry Conference, [16] ABB SACE S.p.A, Working with the Trip Characteristic Curves of ABB SACE Low Voltage Circuit Breakers, White paper, Available [online]: [17] ABB SACE S.p.A, DOC simulation tool, version 1.0, ACKNOWLEDGEMENTS The authors would like to acknowledge the support of European Commission in co-funding this work through the MORE MICROGRIDS Consortium (contract: SES ) and all their partners for their invaluable inputs. 8 APPENDIX Parameters of utility grid Value Rated voltage, V 6000 Short circuit power, MVA 500 Parameters of distribution transformer Value Rated voltage primary/secondary, V 6000/400 Rated power, kva 630 Vcc, % 4 LV distribution system TN-S Parameters of cables Value Type EPR/XLPE Cross-section phase, mm 2 3x185 Cross-section neutral, mm 2 95 Nominal current, A 750 Resistance at 20 0 C phase/neutral, mohm 8.34/16.24 Inductance at 20 0 C phase/neutral, mohm 6.17/6.25 Length, meters 150 Parameters of feeder circuit breakers Value Rated voltage, V 400 Rated current, A 800 Parameters of loads Value Rated voltage, V 400 Rated current, A 100 Rated power factor, cosϕ 0.9
24 Parameters of synchronous DERs Value Rated voltage, V 400 Rated apparent power, kva 160 Rated power factor, cosϕ 0.8 Direct-axis sub-transient reactance Xd, % 9.6 Quadrature-axis sub-transient reactance Xq, % 10.2 Direct-axis transient reactance Xd, % 21 Direct-axis synchronous reactance Xd, % 260 Negative sequence reactance X2, % 9.8 Zero sequence reactance X0, % 2.1 Direct-axis sub-transient short circuit time constant Td, ms 11 Direct-axis transient short circuit time constant Td, ms 85
PacifiCorp Original Sheet No. 476 FERC Electric Tariff, Substitute 6 th Rev Volume No. 11 APPENDIX 2 TO SGIP
PacifiCorp Original Sheet No. 476 APPENDIX 2 TO SGIP SMALL GENERATOR INTERCONNECTION REQUEST (Application Form) Transmission Provider: Designated Contact Person: Address: Telephone Number: An Interconnection
Electrical Network Management System
Electrical Network Management System Optimisation of the electrical network Measure to understand Understand to control Control to optimise Cost of power and fluids Power quality Power availability 2 Improvement
Advanced Protection of Distribution Networks with Distributed Generators
Date:- 8 10 March 2011 Venue: University of Manchester EES-UETP Course title Advanced Protection of Distribution Networks with Distributed Generators Peter Crossley Director of the Joule Centre School
Isolated-Parallel UPS Configuration
Isolated-Parallel UPS Configuration 1 Inhalt 1 Introduction... 4 2 IP systems configuration... 6 3 Projects... 17 4 Conclusions... 17 2 Abstract The isolated-parallel UPS configuration has become well
TURBOtech srl. SED-635 Digital Excitation System. Industrial Electronics Sector FEATURES
SED-635 Digital Excitation System SED-635 is a complete excitation system capable of adapting to control synchronous generators of any size. The integration of the TOUCH SCREEN operator interface and a
Medium voltage products UniSec for Smart Grid Air-insulated medium-voltage secondary distribution switchgear
Medium voltage products UniSec for Smart Grid Air-insulated medium-voltage secondary distribution switchgear Index 3 Overview 4 Standard Levels 6 Monitoring & Control 7 Measurements 8 Protection & Logic
Technical Challenges of Smart- and Microgrids
1 Renewable Efficient Energy II Conference Vaasa, Finland 21-22 March 2012 Technical Challenges of Smart- and Microgrids Sampo Voima and Kimmo Kauhaniemi University of Vaasa, Finland [email protected]
SCADA Systems Automate Electrical Distribution
SCADA Systems Automate Electrical Distribution PC-based supervisory control and data acquisition systems increase uptime, cut costs and improve utilization. A White Paper from InduSoft Fabio Terezinho
GE Protection and Control Business Department. Page 1 Date 5/11/99
GE Protection and Control Business Department Page 1 GE Protection and Control Business Department Proven Overcurrent Protection with Power Management Communication The The Advantages of Microprocessor
Eaton s E-Series protective relay family
E-Series protective relays Feeder distribution relays Motor relays Transformer relays Generator relays Eaton s E-Series protective relay family Microprocessor-based design Eaton s E-Series relay family
Transmission Protection Overview
Transmission Protection Overview 2012 Hands-On Relay School Brian Smyth Schweitzer Engineering Laboratories Pullman, WA Transmission Line Protection Objective General knowledge and familiarity with transmission
Effective: September 10, 2006 Vermont Attachment 1 to Rule 5.500 Public Service Board Page 1 of 6
Public Service Board Page 1 of 6 STANDARD APPLICATION FOR INTERCONNECTION OF GENERATION RESOURCES IN PARALLEL TO THE ELECTRIC SYSTEM OF: (Interconnecting Utility) Preamble and Instructions: An owner of
Application-oriented testing of line differential protection end to end in the field using the corresponding RelaySimTest template
Application Note Application-oriented testing of line differential protection end to end in the field using the corresponding RelaySimTest template Author Jens Baumeister [email protected] Date
Connection of micro-generation to the electricity distribution network
Connection of micro-generation to the electricity distribution network Network recommendation YA9:09 Sivu 1(20) CONTENTS INTRODUCTION...3 1. MARKINGS AND DEFINITIONS...3 2. DEFINITION OF MICRO-GENERATION
Physical Address: City: State: Zip Code:
Application for Small Generator Facility Interconnection Tier 2, Tier 3 or Tier 4 Interconnection (For Small Generator Facilities with Electric Nameplate Capacities of 10 MW and less) Applicant Contact
Secure your electrical network. PACiS The Safety Solution for Healthcare Institutions
Secure your electrical network The Safety Solution for Healthcare Institutions Fast Secure : the solution for fault isolation and electrical network restoration in less than 500 ms 03 A Real Time System
LS1024B / LS2024B/ LS3024B. Solar Charge Controller USER MANUAL
EPSOLAR LS1024B / LS2024B/ LS3024B Solar Charge Controller USER MANUAL Thank you very much for selecting our product! This manual offers important information and suggestions with respect to installation,
Modeling of PV Based Distributed Generator Systems with Diverse Load Patterns
Modeling of PV Based Distributed Generator Systems with Diverse Load Patterns Mehmet H. Cintuglu, [email protected], Armando Altamirano, [email protected] Osama A. Mohammed, [email protected] Energy Systems
Relion. Power system protection and automation reference Fast substation busbar protection with IEC 61850 and GOOSE
Relion Power system protection and automation reference Fast substation busbar protection with IEC 61850 and GOOSE Fast substation busbar protection with IEC 61850 and GOOSE Falu Elnät AB applies new power
Totally Integrated Power SIESTORAGE. The modular energy storage system for a reliable power supply. www.siemens.com/siestorage
Totally Integrated Power SIESTORAGE The modular energy storage system for a reliable power supply www.siemens.com/siestorage Totally Integrated Power (TIP) We bring power to the point. Our products, systems,
FIT TIER 2 Application
FIT TIER 2 Application Application Information The below information Auto-Fills from your registration information: Building Permit Application Date: Project Completion Date: Name: Address: City: State:
Electrical Shore Connections / Cold Ironing
STANDARD FOR CERTIFICATION No. 2.25 Electrical Shore Connections / Cold Ironing JULY 2014 The electronic pdf version of this document found through http://www.dnv.com is the officially binding version
Test & Data Management Software
Test & Data Management Software TDMS protective relays energy meters transducers power quality CT-VT-PT transformers ground grid circuit breakers batteries surge arresters The Integrated Testing Solution
Part 1 System Modeling & Studies for Existing Systems
Part 1 System Modeling & Studies for Existing Systems Operation Technology, Inc. Copyright 2009 Result of rapid release of energy due to an arcing fault between two conductors. Bus voltages > 208V Temperatures
A MODERN DISTRIBUTION MANAGEMENT SYSTEM FOR REGIONAL ELECTRICITY COMPANIES
A MODERN DISTRIBUTION MANAGEMENT SYSTEM FOR REGIONAL ELECTRICITY COMPANIES A Roberts, T Berry, W D Wilson Schneider Electric Ltd, UK SYNOPSIS This paper describes the features of a modern Distribution
ADMS(Advanced Distribution Management System ) in Smart Grid
ADMS(Advanced Distribution Management System ) in Smart Grid 柯 佾 寬 博 士 Yi-Kuan Ke, Ph.D. 2014/03/28 Smart Grid Solution Smart Grid Solution Overview Smart Grid Solutions Smart Network Operation - Distribution
Earth Fault Detection Basics in Theory
Earth Fault Detection Basics in Theory Author: Dipl.-Ing. Ingo Kühnen Woodward Power Solutions Krefelder Weg 47 47906 Kempen, Germany Kempen, 16.04.2010 Earth_Fault_Detection_20100416.doc page 1 1. Star
How To Choose A Transformer
Consider open loop MV network as an example source 1 source 2 NC NC NC or NO main MV switchboard A B Detail design of substation NC NC NC NO NC NC switchboard 1 switchboard 2 switchboard 3 MV MV MV LV
TDMS Test & Data Management Software
Test & Data Management Software TDMS protective relays energy meters transducers power quality CT-VT-PT transformers ground grid circuit breakers batteries surge arresters The Integrated Testing Solution
Context: significant penetration of DG = increased risks for system security
Distributed Generation: towards an effective contribution to power system security IEEE Tampa GM 2007: Panel on Impact of Dispersed Generation on Power System structure & security Bruno Meyer Outline Context:
General Validation Test Program for Wind Power Plants Connected to the Hydro-Québec Transmission System
General Validation Test Program for Wind Power Plants Connected to the Hydro-Québec Transmission System Direction Planification des actifs et expertise de transport February 2011 TABLE OF CONTENTS 1. CONDUCTING
Future grid infrastructure Field tests of LVDC distribution
Future grid infrastructure Field tests of LVDC distribution LUT LVDC Research Group: Andrey Lana, Pasi Nuutinen, Antti Pinomaa, Tero Kaipia, Pasi Peltoniemi, Aleksi Mattsson, Jarmo Partanen Introduction
Power network telecommunication
www.siemens.com Power network telecommunication Teleprotection Answers for infrastructure and cities. Binary I/O The best protection against high-voltage grid failures When it comes to managing power networks,
Coordinated and Optimized Control of Distributed Generation Integration
Coordinated and Optimized Control of Distributed Generation Integration Hui Yu & Wenpeng Luan China Electric Power Research Institute July, 2015 1 Background and introduction 2 Coordinated control of distributed
IEC 61850 in ZX Gas-insulated medium voltage switchgear
IEC 61850 in ZX Gas-insulated medium voltage switchgear IEC 61850 in ZX Just as the supply of electrical power is becoming more and more important in a networked world, demands for the integration of electrical
Features. Display. Measurements. Intelligent. Accuracy. Models. Installation DEIF A/S. Multi-instrument 4921210109D
7000/7000C/7020 Multi-instrument 4921210109D Features Measurements All 3-phase AC measurements True RMS Replaces analogue meters Demand on each phase current Accuracy U, I and F class 0.5 Other values
Nuclear Power Plant Electrical Power Supply System Requirements
1 Nuclear Power Plant Electrical Power Supply System Requirements Željko Jurković, Krško NPP, [email protected] Abstract Various regulations and standards require from electrical power system of the
Nu-Lec Training Modules
PTCC Controller Nu-Lec Training Modules Product Training Operator Training PTCC The Basics An overview of the construction and physical features of the Pole Top Control Cubicle PTCC Operation and Features
VOLTAGE CONTROL IN DISTRIBUTION SYSTEMS AS A LIMITATION OF THE HOSTING CAPACITY FOR DISTRIBUTED ENERGY RESOURCES
VOLTAGE CONTROL IN DISTRIBUTION SYSTEMS AS A LIMITATION OF THE HOSTING CAPACITY FOR DISTRIBUTED ENERGY RESOURCES C. Schwaegerl*, M.H.J. Bollen, K. Karoui #, A. Yagmur + *Siemens AG, # Tractebel STRI AB
Medium voltage products. Technical guide Smart grids
Medium voltage products Technical guide Smart grids Contents 2 1. Introduction 8 2 The different components and functions of a smart grid 8 2.1 Integration of distributed renewable energy sources 9 2.2
Solar Power Plant Design and Interconnection
Solar Power Plant Design and Interconnection Wind & Solar Super Session July 27, 2011 E.H. Camm, S.E. Williams S&C Electric Company Outline Introduction Utility-scale PV power plant Grounding Reactive
Preparing for Distributed Energy Resources
Preparing for Distributed Energy Resources Executive summary Many utilities are turning to Smart Grid solutions such as distributed energy resources (DERs) small-scale renewable energy sources and energy
Control of Distributed Generation Units in Stand-Alone Industrial Networks
2 nd International Conference on Electrical Systems Design & Technologies, Hammamet Tunisia, Nov. 8-10, 2008 Control of Distributed Generation Units in Stand-Alone Industrial Networks Ali Asghar Ghadimi
What Matters for Successful Integration of Distributed Generation
What Matters for Successful Integration of Distributed Generation Thomas Ackermann Energynautics GmbH, Germany [email protected] Expert User of DIgSILENT PowerFactory for Power Systems Studies
The Application of Circuit Breakers to Reduce Downtime in Datacentres
The Application of Circuit Breakers to Reduce Downtime in Datacentres Tim Campbell BEng MIET. Marketing Manager, Terasaki Electric (Europe) Ltd. Abstract Circuit breakers fulfil several functions in the
Agenda do Mini-Curso. Sérgio Yoshio Fujii. Ethan Boardman. [email protected]. [email protected]
Agenda do Mini-Curso Sérgio Yoshio Fujii [email protected] Ethan Boardman [email protected] Agenda do Mini-Curso Sistemas de Distribuição (DMS) Characteristics of Distribution Network
Distribution Operations with High-penetration of Beyond the Meter Intermittent Renewables. Bob Yinger Southern California Edison April 15, 2014
1 Distribution Operations with High-penetration of Beyond the Meter Intermittent Renewables Bob Yinger Southern California Edison April 15, 2014 Southern California Edison SCE provides power to: Nearly
ZONE SELECTIVE INTERLOCKING (ZSI) APPLICATION AND TESTING GUIDE SIEMENS WL UL489 AND UL1066 AIR CIRCUIT BREAKERS
Definition: Zone Selective Interlocking (ZSI) - A method which allows two or more ground fault breakers to communicate with each other so that a short circuit or ground fault will be cleared by the breaker
Technical Information POWER PLANT CONTROLLER
Technical Information POWER PLANT CONTROLLER Content The Power Plant Controller offers intelligent and flexible solutions for the control of all PV power plants in the megawatt range. It is suitable for
New Supervisory Control and Data Acquisition (SCADA) Based Fault Isolation System for Low Voltage Distribution Systems
International Conference on Computer and Communication Engineering (ICCCE 2010), 11-13 May 2010, Kuala Lumpur, Malaysia New Supervisory Control and Data Acquisition (SCADA) Based Fault Isolation System
Wide Area Monitoring Current Continental Europe TSOs Applications Overview
Wide Area Monitoring Current Continental Europe TSOs Applications Overview Version 5 System Protection & Dynamics Working Group 20th September 2015 1. Content 1. Content... 2 2. Introduction... 3 3. Main
Permissible ambient temperature Operation Storage, transport
The Sitras PRO combined DC protective unit and controller is used in the power supply for DC railways in mass transit and main-line systems up 3,000 V DC. It protects DC switch gear and contact line systems
ESB Networks Response. ERGEG Consultation. Voltage Quality Regulation in Europe
NETWORKS ESB Networks Response to ERGEG Consultation on Voltage Quality Regulation in Europe Date: 22 February 2007 Distribution System Operator ESB Networks Page 1 of 12 Contents 1.0 INTRODUCTION...3
Circuit Breakers and Switchgear. Thomas Greer Director of Engineering TLG Services
Circuit Breakers and Switchgear Thomas Greer Director of Engineering TLG Services Presentation Outline Switchgear Definition Overcurrent Protection Devices Circuit Breaker Trip Curves and Coordination
COMPARISON OF THE FACTS EQUIPMENT OPERATION IN TRANSMISSION AND DISTRIBUTION SYSTEMS
COMPARISON OF THE FACTS EQUIPMENT OPERATION IN TRANSMISSION AND DISTRIBUTION SYSTEMS Afshin LASHKAR ARA Azad University of Dezfoul - Iran [email protected] Seyed Ali NABAVI NIAKI University of Mazandaran
Franco Vecchiato, SAM LPBS Regional Manager New SACE Emax 2 From Circuit-breaker to Power Manager
Franco Vecchiato, SAM LPBS Regional Manager New SACE Emax 2 From Circuit-breaker to Power Manager SACE Emax 2 From Circuit-Breaker to Power Manager Our customers need more efficient solutions, to Increase
CERTS Microgrid Research and Lessons Learned
CERTS Microgrid Research and Lessons Learned Advanced Grid Technologies Workshop Microgrid Controls and Management Systems July 9, 2015 Bob Lasseter University of Wisconsin Madison Power System of the
APPLICATION NOTE. Increasing PV Hosting Capacity on LV Secondary Circuits with the Gridco System empower TM Solution
APPLICATION NOTE Increasing PV Hosting Capacity on LV Secondary Circuits with the Gridco System empower TM Solution INCREASING PV HOSTING WITH EMPOWER TM SOLUTION Executive Summary Distributed solar photovoltaic
TA Kahraman Yumak ELK412 - Distribution of Electrical Energy Lab. Notes v1.0 2013 Spring web.itu.edu.tr/yumakk. Distance Protection
Distance Protection Announcement: You are not supposed to prepare a pre-report. But there will be an oral examination, so you are strongly advised to study this note regarding to the pre-study questions
OPTIMIZING POWER SYSTEM PROTECTION FOR MODERN DATA CENTERS
OPTIMIZING POWER SYSTEM PROTECTION FOR MODERN DATA CENTERS Data center power systems are constructed with a premium on reliability at a significant cost. The return on this investment is realized if it
Power products and systems. Intelligent solutions for power distribution Zone concept
Power products and systems Intelligent solutions for power distribution Zone concept Securing continuous power supply ABB is one of the world's leading power and automation technology companies whose products,
PROGRAM CRITERIA FOR ELECTRICAL ENGINEERING TECHNOLOGY
PROGRAM CRITERIA FOR ELECTRICAL ENGINEERING TECHNOLOGY Scope These program criteria apply to programs having titles involving Electrical Engineering Technology including: electrical engineering, electrical
Computer Network. Interconnected collection of autonomous computers that are able to exchange information
Introduction Computer Network. Interconnected collection of autonomous computers that are able to exchange information No master/slave relationship between the computers in the network Data Communications.
Industrial Ethernet How to Keep Your Network Up and Running A Beginner s Guide to Redundancy Standards
Redundancy = Protection from Network Failure. Redundancy Standards WP-31-REV0-4708-1/5 Industrial Ethernet How to Keep Your Network Up and Running A Beginner s Guide to Redundancy Standards For a very
White Paper - July 2012. ATS021-ATS022 Automatic transfer switching
White Paper - July 202 02-022 Automatic transfer switching 02-022 Automatic transfer switching Index. Introduction...2 2. Description of... Switching logics...6 Transformer for the main and generator
Power Generator Switching for Power Engineers Inc. with. Distrix Software Defined Infrastructure. A Distrix Networks Case Study.
Power Generator Switching for Power Engineers Inc. with Distrix Software Defined Infrastructure A Distrix Networks Case Study November, 2015 2015 Distrix Networks Ltd. All Right Reserved 1 The project
TRACTION NETWORK MONITORING AND PROTECTION SYSTEM SMTN-3 CITY ELECTRIC TRANSPORT RAILWAYS METRO INDUSTRY
TRACTION NETWORK MONITORING AND PROTECTION SYSTEM SMTN-3 CITY ELECTRIC TRANSPORT RAILWAYS METRO INDUSTRY 2 TRACTION NETWORK MONITORING AND PROTECTION SYSTEM Traction network monitoring and protection system,
Integration of Distributed Generation in the Power System. IEEE Press Series on Power Engineering
Brochure More information from http://www.researchandmarkets.com/reports/2171489/ Integration of Distributed Generation in the Power System. IEEE Press Series on Power Engineering Description: A forward
SmartGrids SRA 2035. Summary of Priorities for SmartGrids Research Topics
SmartGrids SRA 2035 Summary of Priorities for SmartGrids Research Topics Version 19 June 2013 Setting Priorities related to SRA 2035 research areas and topics The following section reports on the conclusions
For a phase-to-phase voltage between 100 V and 1000 V. The standard ratings are: 400 V - 690 V - 1000 V (at 50 Hz)
24 1. NETWORK CONFIGURATIONS definition Standard IEC 38 defines voltage ratings as follows: - Low voltage () For a phase-to-phase voltage between 100 V and 1000 V. The standard ratings are: 400 V - 690
Feeder protection. for overhead lines and cables in isolated neutral or compensated networks. Specification
Feeder protection for overhead lines and cables in isolated neutral or compensated networks Specification Feeder protection for overhead lines and cables in isolated neutral or compensated networks Version
Executive summary 2. 1 Introduction 4
Flexible Networks for a Low Carbon Future Future Network Monitoring Strategy September 2015 Contents Executive summary 2 Glossary 3 1 Introduction 4 2 Fundamental principles of monitoring 5 2.1 LCT monitoring
Cahier technique no. 196
Collection Technique... Cahier technique no. 196 Integration of local power generation in industrial sites and commercial buildings T. Hazel "Cahiers Techniques" is a collection of documents intended for
Local Back-up Protection for an Electric Power System
MULTILIN GER-3178 GE Power Management Local Back-up Protection for an Electric Power System LOCAL BACK UP PROTECTION FOR AN ELECTRIC POWER SYSTEM J. BERDY TABLE OF CONTENTS Transmission Line Back-Up Protection...............................................
..OR How To Protect your 3-Phase Equipment Investment with 3-Phase Monitors from Time Mark...
..OR How To Protect your 3-Phase Equipment Investment with 3-Phase Monitors from Time Mark... TIME MARK CORPORATION 11440 EAST PINE STREET TULSA, OK 74116 USA tel 918 438-1220 fax 918 437-7584 www.time-mark.com
ISIO 200. Binary Input/Output (I/O) Terminal with IEC 61850 Interface
ISIO 200 Binary Input/Output (I/O) Terminal with IEC 61850 Interface Compact and Easy ISIO 200 Put your Binary I/Os where you need them ISIO 200 is a simple and versatile binary I/O terminal with IEC 61850
Design and Implementation of SCADA System Based Power Distribution for Primary Substation ( Monitoring System)
Design and Implementation of SCADA System Based Power Distribution for Primary Substation ( Monitoring System) Aye Min Zaw 1, Hla Myo Tun 2 Department of Electronic Engineering, Mandalay Technological
IEC 61850: Communication Networks and Systems in Substations
IEC 61850: Communication Networks and Systems in Substations Sistemi e strumenti per l'automazione, A. Flammini, AA2011-2012 Background I: Power Grid Sistemi e strumenti per l'automazione A. Flammini,
Energy Systems Integration
Energy Systems Integration Dr. Martha Symko-Davies Director of Partnerships, ESI March 2015 NREL is a national laboratory of the U.S. Department of Energy, Office of Energy Efficiency and Renewable Energy,
Telemetry system for cathodic protection equipment of underground metal pipelines
RECOMMENDATION PCRA 009 June 2010 Rev. 0 Committee for Cathodic Protection and Associated Coatings Telemetry system for cathodic protection equipment of underground metal pipelines DISCLAIMER: The present
Application of Four-Pole Circuit Breakers within Data Centers
Application of Four-Pole Circuit Breakers within Data Centers December 2013/AT324 by Frank Waterer, Fellow Engineer, Schneider Electric Engineering Services Make the most of your energy SM Revision #1
Advanced Distribution Grid Management for Smart Cities
Smart Grid Solutions Advanced Distribution Grid Management for Smart Cities Kevin Corcoran, Director Product Line Management IEEE SmartGridComm 2015 Miami, FL Bridging Smart Cities & Smart Grids Common
Inverter / Charger Installation General Operations and AC and DC Connections
Inverter / Charger Installation General Operations and AC and DC Connections The Inverter is just one piece. Sometimes, a tendency is to mount the inverter and batteries, and make it work It is better
Engineering innovation
Eaton's Electrical Engineering Services & Systems Solutions Focus Seamless Solutions for Reliable, Efficient and Safe Power Systems Engineering innovation Progressive solutions for today s power systems
New SACE Emax 2 for UL 1066 From Circuit Breaker to Power Manager
New SACE Emax 2 for UL 1066 From Circuit Breaker to Power Manager 2 1SDC200039B0201 New SACE Emax 2 for UL 1066 Circuit breakers switch power SACE Emax 2 manages it. SACE Emax 2 is the new benchmark of
ANCILLARY SERVICES SUPPLIED TO THE GRID: THE CASE OF THISVI CCGT POWER PLANT (GREECE)
Claudio Cavandoli, Alessandro Crippa EDISON S.p.A., Engineering Department ANCILLARY SERVICES SUPPLIED TO THE GRID: THE CASE OF THISVI CCGT POWER PLANT (GREECE) 1 ANCILLARY SERVICES SUPPLIED TO THE GRID:
Il Progetto INTEGRIS. Risultati e nuove prospettive per lo sviluppo delle Smart Grid October 2nd 2013 Brescia
Il Progetto INTEGRIS. Risultati e nuove prospettive per lo sviluppo delle Smart Grid October 2nd 2013 Brescia From INTEGRIS a solution architecture for energy smart grids Jean Wild - Schneider Electric
Industrial IT for Substation Automation & Protection
Industrial IT for Substation Automation & Protection Exploit the potential of ABB substation automation Improve your performance In view of the increasingly competitive arena where power providers are
Technical Requirements for Renewable Energy Systems Connected to the Low Voltage (LV) Network via Inverters
Technical Requirements for Renewable Energy Systems Connected to the Low Voltage (LV) Network via Inverters Specification Number: HPC-9FJ-12-0001-2012 CONTENTS 1 Introduction... 6 1.1 Context... 6 1.2
Disturbance Recoder SPCR 8C27. Product Guide
Issued: April 1999 Status: Updated Version: C/26.04.2006 Data subject to change without notice Features Versatile digital disturbance recorder module for recording various phenomena in the electric power
Product Description Full Voltage Starting Electric Fire Pump Controllers FTA1000
Product Description Full Voltage Starting Electric Fire Pump Controllers FTA1000 Description Firetrol FTA1000 Full Voltage Fire Pump Controllers are intended for use with electric motor driven fi re pumps
Federal Wage System Job Grading Standards for Electric Power Controlling, 5407. Table of Contents
Federal Wage System Job Grading Standards for Electric Power Controlling, 5407 Table of Contents WORK COVERED... 2 WORK NOT COVERED...2 TITLES... 2 GRADE LEVELS... 2 SPECIAL ADDITIONAL RESPONSIBILITIES...
F.C. Chan General Manager, CLP Engineering Ltd., Hong Kong SAR, China
ELECTRIC POWER DISTRIBUTION SYSTEMS F.C. Chan General Manager, CLP Engineering Ltd., Hong Kong SAR, China Keywords: Distribution system planning, Load characteristics, Subtransmission Lines, Distribution
ABB central inverters PVS800 100 to 1000 kw
Solar inverters ABB central inverters PVS800 100 to 1000 kw ABB central inverters raise reliability, efficiency and ease of installation to new levels. The inverters are aimed at system integrators and
On the Road to. Duke takes the road less traveled and arrives at a new level of distribution automation.
On the Road to Intelligent CONTINUOUS REMOTE MONITORING INTEGRATED VOLT/VAR CONTROL Duke takes the road less traveled and arrives at a new level of distribution automation. LAYING A SOLID FOUNDATION In
Increased power protection with parallel UPS configurations
Increased power protection with parallel UPS configurations Making the selection between Centralized Bypass and Distributed Bypass systems Janne Paananen Application Engineer, Large Systems Group Eaton
Application/Connection Examples
This Quick Start Guide is designed to familiarize the user with the connection and configuration of the DTS-305 DIN rail mounted single / 3 phase power & energy meter with RS-485 or TCP communications.
What will MV switchgear look like in the future? by Jean-Marc Biasse
What will MV switchgear look like in the future? by Jean-Marc Biasse Table of contents Introduction... 2 Brief history of the technologies used in medium voltage switchgear and control gear... 4 Evolution
Chapter 1. Network Structures
Chapter 1 Network Structures Definition Standard IEC 60038 defines voltage ratings as follows: Low voltage (): for a phase-to-phase voltage of between 100 V and 1,000 V, the standard ratings are: 400 V
