ESB Networks Response. ERGEG Consultation. Voltage Quality Regulation in Europe
|
|
|
- Juliana Lindsey
- 10 years ago
- Views:
Transcription
1 NETWORKS ESB Networks Response to ERGEG Consultation on Voltage Quality Regulation in Europe Date: 22 February 2007 Distribution System Operator ESB Networks Page 1 of 12
2 Contents 1.0 INTRODUCTION ESB DISTRIBUTION SYSTEM Number of customers and location Description of Distribution Networks Voltage regulation in the ESB Distribution System RESPONSES TO RECOMMENDATIONS TO CENELEC FOR REVISING EN Improve definitions and measurement rules Limits for Voltage Variations Extend the Scope of EN to high and extra high voltage systems Avoid ambiguous indicative values for Voltage events Consider Duties and rights of all parties involved Introduce limits for voltage events SPECIFIC QUESTIONS ON THE RECOMMENDATIONS TO CENELEC FOR REVISING EN What is the appropriate responsibility sharing curve between equipment and grid What is the most appropriate way of protecting equipment against damage or failure due to short duration over-voltages Are there benefits further than customer protection important enough to justify reducing the range of voltage variations from Un ±10% to a narrower band How to consider random year by year variations in setting limits especially for voltage dips and other events correlated to weather How can power quality contracts be defined in order to focus improvements in voltage quality levels according to customer preferences GENERAL OBSERVATIONS ON THE REVISION OF EN50160 AND REGULATION OF POWER QUALITY...12 Page 2 of 12
3 1.0 Introduction ESB Networks recognises the vital importance of voltage quality to electricity customers. Ultimately the correct function of the customer s equipment depends on the characteristic of the voltage and the design of equipment. Standards such as EN are key in co-ordination of electricity system design and equipment design such that correct function is achieved and damage to equipment is avoided. ESB Networks welcomes the participation of the European Regulators in the standards development process. The consultation paper Towards Voltage Quality Regulation in Europe points to a number of aspects of EN which need to be addressed and represents an agenda for the review which is currently being undertaken by CENELEC. ESB Networks welcomes the opportunity to contribute to the process. ESB faces particular challenges in relation to voltage quality. For a significant proportion of customers voltage quality does not conform to EN at the moment. Significant investment is being made to reinforce the networks so that voltage quality will conform to this norm. ESB is concerned that the limits on voltage variations in particular would be tightened. To conform to a tighter standard would require substantial extra investment. Ultimately such investment would need to be funded by customers and it is not clear that this is in the best interests of customers. 2.0 ESB Distribution System ESB is the sole distribution network operator in the Republic of Ireland. Data on the number of customers and customer detail are provided below. 2.1 Number of customers and location The population of the Republic of Ireland is approximately 4 million. The geographic area is 70,000 sq km. Overall the population density is one of the lowest in Europe. An important characteristic for electricity distribution is that approximately 40% of the population live in the country side, outside of cites, towns and villages. Figure I below shows the population density Page 3 of 12
4 Figure 1. Population density of the Republic of Ireland Most of the land mass has a population density of between 10 and 100 per square km with a substantial proportion less than 50 people per square km. In terms of electricity customers, the total number of customers at end of 2005 was 1.96 Million and total GWh distributed in 2005 was 21,311 GWh 2.2 Description of Distribution Networks The distribution system in the Republic of Ireland which ESB Networks owns and operates contains 110kV, 38kV, 20kV, 10kV and LV networks, The configuration of the Distribution System is illustrated schematically in Figure 2 below. Medium Voltage is either 10kV or 20kV Page 4 of 12
5 110 kv 38 kv 110kV/MV Substation Medium Voltage Medium Voltage Network MV/LV Substation Low Voltage Network Figure 2. Representation of the Distribution System in Republic of Ireland Key Statistics about the size of the ESB are given in Table 2 below: Subtransmision Medium & Low voltage 110kV S/Stns MV Network 110/38kV 83 Overhead - 3 Phase 24, /MV 21 Overhead - 1 Phase 53, /38kV Tranformer capacity (MVA) 6,040 Cables 6, /MV Tranformer capacity (MVA) 1,190 MV/LV S/stns 38kV Network Pole mounted - 3 phase 16,124 Overhead 5,633 Pole mounted - 1 phase 186,524 Cables 559 Ground mounted 15,781 38kV S/Stns LV Network No. of Stations 430 Overhead 52,371 Tranformer capacity (MVA) 4,900 Underground 10,864 Table 2 ESB Distribution System at end 2005 The main feature of the ESB Distribution system is the huge extent of overhead line per customer. The reason is the high proportion of customers located in rural areas and the fact that these customers live in separate dwellings in the countryside rather than in villages and towns. Long lengths of line are needed to reach these customers. To serve this rural customer base, ESB has adopted a system which is unusual in Europe. 38/MV substations feed radial 3-phase MV Overhead lines. Branch Lines consisting of two phase conductors are connected to the 3-phase line. These branch lines are referred to as single phase lines although they actually consist of two phase conductors. Near to houses, single phase transformers are connected to the single phase spur lines. These single transformers feed between 1 and 10 houses within a distance of approx 300m from the transformer. This design explains why there is so much single phase MV network and so many single phase transformers. Page 5 of 12
6 2.3 Voltage regulation in the ESB Distribution System. The distribution system in the Republic of Ireland has been designed to deliver an LV Voltage of under normal operating conditions. This is equivalent to 230V +6%, -10% ESB also plans for an outage of a single item of plant at MV and higher voltages. The outage could be caused by a fault or could be to facilitate maintenance. This is referred to as an N-1 contingency. For networks supplying rural areas, the voltage is generally lower under such contingencies. For N-1 contingencies, the design target is 244V 195V. Scenario Target LV Voltage Range Volts % of Un (230 V) Normal Operation %, -10% N 1 Contingency %, -15% Voltage at the MV busbars in 38/MV substations is maintained within a 2% bandwidth when the 38KV system is in normal configuration. The MV system is planned so that in normal configuration volt drop is limited to 5%. 3% voltage drop is allowed on the MV / LV transformer and 7% on the LV network. These allowed voltage drops total to 17%. However, assuming that the peak loads on the MV and LV network, will not coincide often, then the resultant voltage should comply with the requirements of EN MV Bus MV Network Xfmr LV Customer 10,440/20, /237V 2% 5% Normal 10% Standby 3% 5% 2% Voltage Regulation 10.7/ kV -1% 0% Load 100% Load 6% 244V 5% 4% 230V -1% MV N-1 Contingency -4% -10% 207V Figure 2 MV / LV Voltage Control in Distribution System -15% 196V Page 6 of 12
7 For an N-1 contingency on the MV system, an additional 5% voltage drop is allowed. With a base line of +6%, this means a delivered voltage of -15%. If the N 1 contingency exists for a number of days, as it could if maintenance is being done or for a major fault, then voltage could be lower than -10% for more than 95% of the time. As the current EN only requires the voltage to be within standard while the network is in normal configuration, this does constitute a non compliance New houses continue to be built in the country side all the time and the number of house being supplied by the rural networks is continually increasing. Furthermore the average annual consumption is increasing. Customers are installing some apparatus with high demand e.g. electric showers. As a result, there is a substantial number (probably about 10,000 customers) whose voltage does not conform to standard with the network in normal operation. A much greater number of customers could receive a voltage lower than -15% for some N 1 contingencies especially at times of high load. To improve this position ESB is currently in the process of converting the longer and heavily loaded rural overhead 10kV networks to 20kV operation. Also small single phase transformers (5kVA) are being changed to larger sizes (15 kva minimum). When individual customers complain of poor voltage, a recorder is installed to check for compliance with EN If it is determined that the voltage does not conform to EN 50160, then feeding LV network is reinforced. At the moment, between 1,600 and 1,900 non-conformances are being registered every year. ESB spends between 4 and 6M each year reinforcing LV networks in response to these complaints. 3.0 Responses to Recommendations to CENELEC for revising EN In this sections, ESB Networks comments on ERGEGs recommendations to CENELEC outlined in section 4 of the ERGEG consultation document 3.1 Improve definitions and measurement rules ESB agrees that efforts should be made to improve definitions of some voltage quality parameters in EN and that international consensus on definitions is highly desirable. 3.2 Limits for Voltage Variations As described in paragraph 2.3 above, ESB has designed its system to maintain LV voltage above -10% of Un (207V) in normal conditions and -15% in N- 1 contingencies. Meeting this objective is challenging because of continually increasing load on the networks. Substantial expenditure is being incurred to improve the networks to meet these criteria. ESB Networks view Page 7 of 12
8 is that the -10% lower limit for normal network configurations should be retained. As regards the application of the 95% of the time, ESB believe that some allowance must be made for the occasional coincidence of loads when measuring against the lower limit for voltage variations. Networks are designed based on statistical concepts presuming some diversity between customers load which is found to be acceptable in practice. We do not believe that a requirement for voltage to be above -10% for 100% of the time is in the best interests of customers. In ESB s case it would require more onerous design criteria which would lead to greater expenditure on new connections and on reinforcing the network. In practice most equipment functions reasonably well at voltages between Un -10% (207V) and Un -15% (195V). ESB Network s view is that customers would prefer to endure the very occasional reduction in performance of equipment rather than fund the extra investment that would be required to deliver voltage above -10% 100% of the time. This point also applies to the N-1 contingency situations. In ESBs case, if it were required to ensure voltage is no lower than Un -10% for N-1 conditions, substantial investment would be required. We believe it would be necessary to reconductor 75% of the 3phase overhead MV lines system and 50% of the 38kV overhead lines. The cost would be in the region of 700 M. This is approximately 1,000 per customer located in rural areas. As the N -1 contingency arises only occasionally, ESB s view is that customers would prefer to accept the temporary reduction in equipment performance rather than fund this investment. In relation to the averaging interval, ESB accept that in principle it may be appropriate to have an additional upper limit based on a shorter averaging interval than 10 min. in this case the limit should be higher than +10%. The rationale is that voltage regulation equipment is normally set such that there is a delay before responding to voltage going outside target range. This is to avoid excessive number of tap change operations and consequential higher maintenance costs and reduced lifetimes. In the event of sudden changes on the transmission or sub-transmission system due to switching or tripping of load due to fault, a number of transformer tap changes may be required to bring the voltage back within target range. For example, the transmission grid code in Ireland allows an instantaneous voltage change in some circumstances of ±10%. The settings on voltage regulating relays are such that it would take 1 minute for the first tap change to occur and 1.5 minutes approximately to recover from such and event. So if customers voltage was at +6% before the event, it would be at +16% for 1 minute before the tap change operations would restore the voltage to target range. In deciding on what voltage limit should be associated with a shorter time interval, CENELEC should take account of what equipment can tolerate. We believe that in practice equipment can withstand higher voltages than UN +10 for short periods. This needs to be discussed with equipment manufacturers. Page 8 of 12
9 3.3 Extend the Scope of EN to high and extra high voltage systems The necessity for European wide voltage quality standards at higher voltages where very few customers are connected is not clear. Voltage disturbances at HV will be reflected down at MV and LV. So, if voltage standards are set for MV and LV, this will require a network operator to ensure an adequate voltage quality at HV. As there are different voltages in place in different countries, it may prove difficult to set limits that will have European wide application. In the case of voltage variations, the requirement for the HV system is determined by the tapping range of the transformers being supplied. This is probably different in different countries. In that case, there is no benefit in having European standards specifying limits for voltage variations at high voltage. In countries where there are different system operators for distribution and sub-transmission systems, voltage quality standards for HV could have a role. It could prove more practical for a national regulator to set appropriate standards for its country rather than extending the scope of EN Avoid ambiguous indicative values for Voltage events ESB Networks agree that the first step is to agree a classification system for dips and swells. When that is agreed a monitoring programme can be started which could establish a base line level of voltage events in a given location over a number of years. The characteristics of the networks are different in different countries and even in different parts of the same country. Consequently the profile of voltage events will vary with location. Ultimately it may prove difficult to set binding limits for voltage events that would apply across all of Europe. 3.5 Consider Duties and rights of all parties involved ESB Networks agree that it is important to achieve a cost effective coordination between system related standards and equipment standards. ESB Networks agree with the statement that it is useful to stipulate the minimum short circuit power being provided by a network operator. Minimum short circuit levels can be specified for a particular customer class based on the normal profile of equipment used by that customer class. If individual customers install unusual equipment which causes voltage quality disturbances, then the customer can be held responsible and be requested to bear the cost of the solution. 3.6 Introduce limits for voltage events ESB Networks agree that limits for voltage events must take account of different network structures in the various countries and even within countries. i.e. overhead/underground, neutral grounding and short circuit power. Page 9 of 12
10 It may prove difficult to set limits for European wide application. An alternative approach would be to harmonise classification of voltage events and for national regulators to set targets for each of its regulated network operators. Which ever approach is adopted, it will be important to allow sufficient time to gather historical data to establish the present status. 4.0 Specific Questions on the recommendations to CENELEC for revising EN In this section, ESB Networks address some of the specific questions raised by ERGEG in section 7 of the consultation document. 4.1 What is the appropriate responsibility sharing curve between equipment and grid ESB Network does not have sufficient expertise on equipment to answer this question comprehensively. It will require dialogue and exchange of information in the CENELEC working group. However ESB is concerned that significant weight is being given to the ITIC curve. ESB believe that the ITIC curve was first developed in the 1970s when electronic equipment was powered via bridge rectified power supplies. We understand that most equipment nowadays has switched mode type power supplies. It is believed that switched mode power supplies can work on a much wider range of voltage. 4.2 What is the most appropriate way of protecting equipment against damage or failure due to short duration over-voltages. A new limit should be set for short duration over voltages. This limit should be higher than UN + 10% to allow for the operation of voltage regulating equipment in the power distribution network. It needs to take account of the resilience of equipment in general use today. 4.3 Are there benefits further than customer protection important enough to justify reducing the range of voltage variations from Un ±10% to a narrower band. There would be some savings in losses in adopting a tighter standard. However in most situations, the savings in losses would not offset the substantial extra capital expenditure required. The impact of tightening the limits would be to impose additional net burden on customers. It would be inappropriate to try and enforce loss reduction by tightening the voltage standards. Other mechanisms are available to regulators to ensure that losses are taken into account when designing the networks. Page 10 of 12
11 4.4 How to consider random year by year variations in setting limits especially for voltage dips and other events correlated to weather This is one of the difficulties in including binding limits for events which like supply interruptions are not entirely under the network operators control. The best approach is probably to allow national regulators to monitor performance against specified targets with rules that allow adjustments for periods of exceptional weather. For simplicity, the smaller definitions of exceptional events should be used for interruptions and for voltage events. 4.5 How can power quality contracts be defined in order to focus improvements in voltage quality levels according to customer preferences If definitions in EN are improved and monitoring programmes started with results published, customers with special power quality needs will be able to assess whether the voltage quality available at their site meets there need. If a customer requires a higher quality supply than is generally available, they should be allowed to enter a contract with the network operator. The best approach may be to avoid stipulating the exact form of such contracts but rather to allow regulators to adjudicate in the event of dispute Page 11 of 12
12 5.0 GENERAL OBSERVATIONS ON THE REVISION OF EN50160 AND REGULATION OF POWER QUALITY To conclude, we would like to make some general comments about the topic. When contemplating any tightening of EN it is important to consider the costs to Network operators of achieving the new standard. The costs of resolving the co-ordination problem by making the equipment more robust must also be considered and the most economic solution adopted. If it is ultimately decided to amend EN 50160, it is important that regulators take account of any extra costs on network operators. Networks operators could be faced with higher maintenance costs and additional capital expenditure if there is a tightening of the permitted voltage range and pressure to reduce perturbations of the supply. Finally, ESB Networks recognise the increasing importance of quality of supply to its customers and the need to improve co-ordination of equipment and network design in order to meet modern customer expectations. We hope that we can make some contribution to the fulfilment of this objective and in particular we hope that our comments on the ERGEG paper will prove to be useful. Page 12 of 12
SUMMARY - RELATIONSHIP BETWEEN QUALITY OF SERVICE DEMANDED AND TARIFF
SUMMARY - RELATIONSHIP BETWEEN QUALITY OF SERVICE DEMANDED AND TARIFF PA Consulting Services SA Authors: C. Guidi / J. Espain - / J. García Argentina Restructuring of Electric Sectors in Latin America
Networks. ESB Networks Ltd Basis of Charges for Connection to the Distribution System. Commercial and Customer Asset Management ESB Networks Ltd.
Networks ESB Networks Ltd Basis of Charges for Connection to the Distribution System Revision Date: 14/01/20010 Revision No.: 1 Document No: DOC-10129-AXQ Issued by: ESB Networks Ltd Approved by : CER
Power products and systems. Intelligent solutions for power distribution Zone concept
Power products and systems Intelligent solutions for power distribution Zone concept Securing continuous power supply ABB is one of the world's leading power and automation technology companies whose products,
Chapter 1. Network Structures
Chapter 1 Network Structures Definition Standard IEC 60038 defines voltage ratings as follows: Low voltage (): for a phase-to-phase voltage of between 100 V and 1,000 V, the standard ratings are: 400 V
Phase Attribute Identification using GPS Technology
Phase Attribute Identification using GPS Technology Date 11 June 2009 John Sinclair Power Quality Manager Slide 1 Topics of Discussion Remote Phase Identification How it works Principals of operation Benefits
For a phase-to-phase voltage between 100 V and 1000 V. The standard ratings are: 400 V - 690 V - 1000 V (at 50 Hz)
24 1. NETWORK CONFIGURATIONS definition Standard IEC 38 defines voltage ratings as follows: - Low voltage () For a phase-to-phase voltage between 100 V and 1000 V. The standard ratings are: 400 V - 690
Nuclear Power Plant Electrical Power Supply System Requirements
1 Nuclear Power Plant Electrical Power Supply System Requirements Željko Jurković, Krško NPP, [email protected] Abstract Various regulations and standards require from electrical power system of the
IESO Supply Deliverability Guidelines
PUBLIC IMO_GDL_0021 IESO Supply Deliverability Guidelines Issue 3.0 This document is to be used to evaluate long-term system adequacy and connection assessments Public Disclaimer The posting of documents
VOLTAGE CONTROL IN DISTRIBUTION SYSTEMS AS A LIMITATION OF THE HOSTING CAPACITY FOR DISTRIBUTED ENERGY RESOURCES
VOLTAGE CONTROL IN DISTRIBUTION SYSTEMS AS A LIMITATION OF THE HOSTING CAPACITY FOR DISTRIBUTED ENERGY RESOURCES C. Schwaegerl*, M.H.J. Bollen, K. Karoui #, A. Yagmur + *Siemens AG, # Tractebel STRI AB
EVALUATION OF ALTERNATIVE BACKUP PROTECTION SCHEMES ON A 66KV DISTRIBUTION NETWORK
EVALUATION OF ALTERNATIVE BACKUP PROTECTION SCHEMES ON A 66KV DISTRIBUTION NETWORK F. Malone*, P.D. Doyle *ESB International, Ireland [email protected] ESB International, Ireland [email protected]
How the National Grid System Operates. Chris Gorman Lead Account Executive Syracuse
How the National Grid System Operates Chris Gorman Lead Account Executive Syracuse 2 Parts of the Electric System Parts of the Electric System 1. Generating Station: Produces Electricity. 2. Transmission
Earthing Guidance Notes
Central Networks Earthing Manual Section E2 Earthing Guidance Notes Version: 2 Date of Issue: September 2007 Author: Nigel Johnson Job Title: Earthing Specialist Approver: John Simpson Job Title: Head
16 West Coast Regional Plan
16 West Coast Regional Plan 16.1 Regional overview 16.2 West Coast transmission system 16.3 West Coast demand 16.4 West Coast generation 16.5 West Coast significant maintenance work 16.6 Future West Coast
BC Hydro. Electric Distribution System Cost of Service Study
BC Hydro Electric Distribution System Reimer Consulting Group Inc. Arnie Reimer May 7, 2010 Table of Contents 1. Executive Summary... 3 2. BC Hydro Electric Distribution System... 4 2.1. General Description...
Executive summary 2. 1 Introduction 4
Flexible Networks for a Low Carbon Future Future Network Monitoring Strategy September 2015 Contents Executive summary 2 Glossary 3 1 Introduction 4 2 Fundamental principles of monitoring 5 2.1 LCT monitoring
F.C. Chan General Manager, CLP Engineering Ltd., Hong Kong SAR, China
ELECTRIC POWER DISTRIBUTION SYSTEMS F.C. Chan General Manager, CLP Engineering Ltd., Hong Kong SAR, China Keywords: Distribution system planning, Load characteristics, Subtransmission Lines, Distribution
FRCC Standards Handbook. FRCC Automatic Underfrequency Load Shedding Program. Revision Date: July 2003
F R C C FRCC Standards Handbook FRCC Automatic Underfrequency Load Shedding Program Revision Date: July 2003 FRCC Underfrequency Load Shedding Program Modification and Approval Process Requests to modify
STATEMENT OF CHARGING METHODOLOGY FOR USE OF ELECTRICITY NORTH WEST LIMITED S ELECTRICITY DISTRIBUTION NETWORK
STATEMENT OF CHARGING METHODOLOGY FOR USE OF ELECTRICITY NORTH WEST LIMITED S ELECTRICITY DISTRIBUTION NETWORK This statement is effective from 1 April 2010 This statement is approved by the Gas and Electricity
COMPLIANCE REVIEW OF 2006/07 ASSET MANAGEMENT PLAN. Top Energy Limited
PB ASSOCIATES COMPLIANCE REVIEW OF 2006/07 ASSET MANAGEMENT PLAN Prepared for PB Associates Quality System: Document Identifier : 153162 Top Energy Final Report Revision : 2 Report Status : Final Date
Size template. Grid Connection Masterclass Energex John Lansley Senior Network Solutions Engineer
Size template Grid Connection Masterclass Energex John Lansley Senior Network Solutions Engineer The average system size has doubled since 2010 Key Network Issues Reverse power on up to 12 off 11 kv feeders
Network Consulting for Power Grid Optimization
Network Consulting for Power Grid Optimization Project experience in India Network Consulting Competences Page 1 Our worldwide representation Manchester The Hague Denver Schenectady San Diego Houston Mexico
BL20A0501 Electricity distribution technology. Introduction Jarmo Partanen
BL20A0501 Electricity distribution technology Introduction Jarmo Partanen Introduction to ED Prof. Jarmo Partanen, D.Sc Jukka Lassila Topics of lectures Introduction to Electricity Distribution, 27.10
ES281 COMPANY-SPECIFIC APPENDICES TO ENA ENGINEERING RECOMMENDATION G81 PART 1
ES281 COMPANY-SPECIFIC APPENDICES TO ENA ENGINEERING RECOMMENDATION G81 PART 1 Design and Planning Specification for New Low Voltage Installations for Housing Developments 1. SCOPE This appendix to ENA
Agenda do Mini-Curso. Sérgio Yoshio Fujii. Ethan Boardman. [email protected]. [email protected]
Agenda do Mini-Curso Sérgio Yoshio Fujii [email protected] Ethan Boardman [email protected] Agenda do Mini-Curso Sistemas de Distribuição (DMS) Characteristics of Distribution Network
Transformers Energy efficient transformer solutions European Minimum Energy Performance Standard (MEPS)
Transformers Energy efficient transformer solutions European Minimum Energy Performance Standard (MEPS) 2 European MEPS for transformers The EU MEPS (European Minimum Energy Performance Standard) Transformers
environment briefing02
PRODUCED BY THE SAFETY, HEALTH & ENVIRONMENT GROUP OF THE ENERGY NETWORKS ASSOCIATION - JULY 2006 environment briefing02 transporting electricity Overhead Lines or Underground Cables? Introduction The
Ladies and Gentlemen,
Ladies and Gentlemen, I would like to begin my speech by thanking deeply the Maniatakeion Foundation and especially the Chairman, Mr. Dimitris Maniatakis for his invitation and to congratulate him for
A Network Reference Model for Distribution Regulation and Planning: the Spanish Case
A Network Reference Model for Distribution Regulation and Planning: the Spanish Case Jesús Pascual Peco González Instituto de Investigación Tecnológica (IIT) Universidad Pontificia Comillas, Madrid http://www.iit.upco.es
Medium voltage products UniSec for Smart Grid Air-insulated medium-voltage secondary distribution switchgear
Medium voltage products UniSec for Smart Grid Air-insulated medium-voltage secondary distribution switchgear Index 3 Overview 4 Standard Levels 6 Monitoring & Control 7 Measurements 8 Protection & Logic
Requirements for Offshore Grid Connections. in the. Grid of TenneT TSO GmbH
Requirements for Offshore Grid Connections in the Grid of TenneT TSO GmbH Bernecker Straße 70, 95448 Bayreuth Updated: 21 December 2012 1/10 Requirements for Offshore Grid Connections in the Grid of TenneT
SOUTHERN MARYLAND ELECTRIC COOPERATIVE, INC. HUGHESVILLE, MD
SOUTHERN MARYLAND ELECTRIC COOPERATIVE, INC. HUGHESVILLE, MD HOLLAND CLIFF HEWITT ROAD 230 KV TRANSMISSION LINE PROJECT ELECTRIC ALTERNATIVE EVALUATION STUDY BLACK & VEATCH CORPORATION B&V Project 146026(G)
Comparison of GIS and AIS systems for urban supply networks
Comparison of GIS and AIS systems for urban supply networks Studies carried out by ABB show that for urban supply networks the combination of HV gas-insulated switchgear (GIS) and HV cable has important
Guideline for Energy Efficient Electrical systems for building. Presentation by TERI
Guideline for Energy Efficient Electrical systems for building Presentation by TERI Objective of study The study highlights how BBMP can implement energy efficiency measures in building in co-ordination
Voltage regulation in distribution systems - Tap changer and Wind Power
CODEN:LUTEDX/(TEIE-5270)/1-59/(2010) Industrial Electrical Engineering and Automation Voltage regulation in distribution systems - Tap changer and Wind Power David Sáez Romero D of Industrial Electrical
NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission Limited, Scottish Hydro Electric Transmission Limited
NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission Limited, Scottish Hydro Electric Transmission Limited TABLE OF CONTENTS 1.0 Purpose and Scope...2 1.1 Methodology Purpose...2
NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission PLC, Scottish Hydro Electric Transmission Limited
NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission PLC, Scottish Hydro Electric Transmission Limited TABLE OF CONTENTS 1.0 Purpose and Scope...2 1.1 Methodology Purpose...2 2.0
Daily Daily Network Network Network Energy Rates Step Rates Capacity. Price Rates Rates
Excludes GST Effective from 1 July 2010 Tariff Class Daily Daily Network Network Network Energy Rates Step Rates Capacity Capacity Price Rates Rates No. Network Price DLF Access Non-ToU Time of Use (ToU)
NORTHERN IRELAND ELECTRICITY Ltd STATEMENT OF CHARGES FOR USE OF. THE NORTHERN IRELAND ELECTRICITY Ltd ELECTRICITY DISTRIBUTION SYSTEM
NORTHERN IRELAND ELECTRICITY Ltd STATEMENT OF CHARGES FOR USE OF THE NORTHERN IRELAND ELECTRICITY Ltd ELECTRICITY DISTRIBUTION SYSTEM BY AUTHORISED PERSONS Effective from 1 October 2011 to 30 September
Network Price List (excludes GST)
Network Price List (excludes GST) Effective from 1 July 2007 Monthly Monthly Monthly Network Network Network Energy Rates Step Rates Demand Capacity Capacity Price Network Price DLF Access Rates Rates
Technical Trial of Broadband IP/Internet over ESB Power Networks. Engineers Ireland. October 2006
Technical Trial of Broadband IP/Internet over ESB Power Networks Engineers Ireland October 2006 Outline of Presentation 1. Introduction to Broadband Power Line Carrier 2. Trial start up 1. Objectives 2.
Underground vs. Overhead Transmission and Distribution
electric power engineering Underground vs. Overhead Transmission and Distribution Your Power System Specialists June 9, 2009 1 NATIONAL TRENDS Municipalities have passed laws requiring new distribution
Hyperlinks are Inactive
Prepared by: NIB/EOB PLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES 05503 Department: Electric T&D Section: T&D Engineering and Technical Support Approved by: G.O. Duru (GOD)
SHE Transmission. 2015_10_30 Transmission Losses Strategy Rev 2.0 October 2015
SHE Transmission 2015_10_30 Transmission Losses Strategy Rev 2.0 October 2015 Summary This paper presents SHE Transmission s views and approach on the impact of transmission losses on the transmission
Market Growth and New Regulations Demand Network Modernization
CASE ESB NETWORKS: POLE TOP COMMUNICATION INCREASES EFFICIENCY IN IRELAND Viola s solution for remotely operating pole-top reclosers and switches increases reliability, cuts operating costs and helps to
The electrical energy produced at the gen
300 300 Principles of Power System CHAPTER CHAPTER 12 Distribution Systems General 12.1 Distribution System 12.2 Classification of Distribution Systems 12.3 A.C. Distribution 12.4 D.C. Distribution 12.5
Cost Benefit Methodology for Optimal Design of Offshore Transmission Systems
Centre for Sustainable Electricity and Distributed Generation Cost Benefit Methodology for Optimal Design of Offshore Transmission Systems Predrag Djapic and Goran Strbac July 2008 FUNDED BY BERR URN 08/1144
Hendrix Spacer Cable
Hendrix Spacer Cable What is Spacer Cable? Covered Conductor Withstands temporary branch contact Eliminates temporary faults Protects wildlife Less clearance issues Compact Configuration Multiple Circuits
Power transformers. Special transformers Railway
Power transformers Special transformers Railway A leader in railway systems Our compact and low-weight transformers fully comply with the customer s specifications. The products are developed together
The Narragansett Electric Company d/b/a National Grid, Filing to Amend Terms and Conditions for Distribution Service Docket No.
Jennifer Brooks Hutchinson Senior Counsel September 3, 2010 VIA HAND DELIVERY & ELECTRONIC MAIL Luly E. Massaro, Commission Clerk Rhode Island Public Utilities Commission 89 Jefferson Boulevard Warwick,
POWER NETWORKS. 2014-15 Electricity Network Tariffs and Charges and Future Price Trends
POWER NETWORKS 2014-15 Electricity Network Tariffs and Charges and Future Price Trends August 2014 Power and Water Corporation Table of Contents 1 Business Characteristics... 3 2 2014 Network Price Determination...
FIXED CHARGE: This is a cost that goes towards making the service available, including
ELECTRICITY BILL COMPONENTS FIXED CHARGE: This is a cost that goes towards making the service available, including installation and maintenance of poles, power lines and equipment, and 24-hour customer
RCP2 Portfolio Overview Document
RCP2 Portfolio Overview Document Portfolio: Expenditure Class: Base Capex Expenditure Category: Grid Replacement & Refurbishment As at date: 15 November 2013 Expenditure Forecast Real 2012/13 NZ$ (m) 2015-2016
Title 20 PUBLIC SERVICE COMMISSION. Subtitle 50 SERVICE SUPPLIED BY ELECTRIC COMPANIES. Chapter 02 Engineering
Title 20 PUBLIC SERVICE COMMISSION Subtitle 50 SERVICE SUPPLIED BY ELECTRIC COMPANIES Chapter 02 Engineering Authority: Public Utility Companies Article, 2-121, 5-101 and 5-303, Annotated Code of Maryland.
Connection of micro-generation to the electricity distribution network
Connection of micro-generation to the electricity distribution network Network recommendation YA9:09 Sivu 1(20) CONTENTS INTRODUCTION...3 1. MARKINGS AND DEFINITIONS...3 2. DEFINITION OF MICRO-GENERATION
Estimation of electrical losses in Network Rail Electrification Systems
Estimation of electrical losses in Network Rail Electrification Systems Page 1 of 16 Contents 1. BACKGROUND...3 2. PURPOSE...3 3. SCOPE...3 4. DEFINITIONS & ABBREVIATIONS...4 5. NETWORK RAIL INFRASTRUCTURE
Fundamentals of Power
Fundamentals of Power Fundamentals of Power 2008 American Power Conversion Corporation. All rights reserved. All trademarks provided are the property of their respective owners. Learning Objectives At
SURVEY OF HARMONIC DISTORTION IN LV AND MV NETWORKS: RESULTS AND CORRECTIVE STRATEGIES
SURVEY OF HARMONIC DISTORTION IN LV AND MV NETWORKS: RESULTS AND CORRECTIVE STRATEGIES E Bompard*, E Carpaneto*, R Napoli*, P Ribaldone**, C Vercellino** * Dipartimento di Ingegneria Elettrica Industriale,
Low Voltage Asset Management (LVAM) The key to reliable and safe electricity
Low Voltage Asset Management (LVAM) The key to reliable and safe electricity Archie Jaykaran Distribution Division Eskom SA Contents Change drivers Scope, Approach, Project status LV Planning and Design
GPS Interfacing of Banediya Feeder (M.P) Using MI Power Software
GPS Interfacing of Banediya Feeder (M.P) Using MI Power Software Swati Paliwal 1, V.K Tayal 2, H.P Singh 3 Assistant professor, Department of Electrical & Electronics Engineering, Northern India Engineering
Medium Voltage (MV) & High Voltage (HV) Training Module 6. Date of the presentation
Medium Voltage (MV) & High Voltage (HV) Training Module 6 Date of the presentation Electrical System Basics MV vs. HV - Definitions Differences between USA and the rest of the world IEC define a high voltage
ECE 586b Course Project Report. Auto-Reclosing
ECE 586b Course Project Report Auto-Reclosing Srichand Injeti May 5, 2008 Department Of Electrical and computer Engineering University Of Western Ontario, London Ontario Table of contents 1. Introduction...1
South African Distribution Code
South African Distribution Code Glossary and Definitions Version 6.0 July 2014 This document is approved by the National Energy Regulator of South Africa (NERSA) Issued by: RSA Grid Code Secretariat Contact:
Trade of Electrician. Three-phase Distribution Boards And Socket Circuits
Trade of Electrician Standards Based Apprenticeship Three-phase Distribution Boards And Socket Circuits Phase 2 Module No. 2.3 Unit No. 2.3.2 COURSE NOTES Created by Charlie Walsh - Athlone TC Revision
Calculation of Voltage Sag Indices for Distribution Networks
Calculation of Voltage Sag Indices for Distribution Networks Juan A. Martinez-Velasco, Member, IEEE, Jacinto Martin-Arnedo, Nonmember Abstract This paper is presenting the main results of a work aimed
TRANSMISSION SERVICE RATE SCHEDULE Effective from 1 April 2015
TRANSMISSION SERVICE RATE SCHEDULE Effective from 1 April 2015 A SERVICE CONNECTION CHARGES Note : All charges in this Schedule are exclusive of GST. 1 Service Connection This includes cables, associated
ELECTRICAL ENGINEERING DESIGN CRITERIA APPENDIX F
ELECTRICAL ENGINEERING DESIGN CRITERIA APPENDIX F TABLE OF CONTENTS Appendix F - Electrical Engineering Design Criteria F.1 Introduction...F-1 F.2 Codes and Standards...F-1 F.3 Switchyard and Transformers...F-1
PB POWER ISLAND OF IRELAND CAVAN-TYRONE AND MEATH-CAVAN 400KV PROJECTS PRELIMINARY BRIEFING NOTE OVERHEAD AND UNDERGROUND ENERGY TRANSMISSION OPTIONS
ISLAND OF IRELAND CAVAN-TYRONE AND MEATH-CAVAN 400KV PROJECTS PRELIMINARY BRIEFING NOTE OVERHEAD AND UNDERGROUND ENERGY TRANSMISSION OPTIONS FEBRUARY 2008 PB POWER PB Power Page i EXECUTIVE SUMMARY General
EDB Information Disclosure Requirements Information Templates for Schedules 11a 13
EDB Information Disclosure Requirements Information Templates for Schedules 11a 13 Disclosure Date 31 March 2015 Start Date (first day) 1 April 2015 Templates for Schedules 11a 13 (Asset Management Plan)
Principles of Distribution charging:
Principles of Distribution charging: Electricity networks Introduction A three-stage approach involves the following steps: 1. The analysis and quantification of costs. The cost concept that is relevant
ENGINEERING COMPETENCIES ENTRY LEVEL ENGINEER. Occupation Specific Technical Requirements
ENGINEERING COMPETENCIES ENTRY LEVEL ENGINEER Responsible for performing entry level engineering analysis, design, plan, review and inspection for small to medium projects and/or designated segments of
Treasure Valley Electrical Plan
Treasure Valley Electrical Plan Community Advisory Committee January 25, 2006 Agenda 10 a.m. Welcome 10:10 a.m. Follow up DSM discussion 10:30 a.m. TVEP CAC process update 10:40 a.m. Transmission Presentation
Primary and Secondary Electrical Distribution Systems
Primary and Secondary Electrical Distribution Systems Critical Facilities Round Table 12th Quarterly Membership Meeting June 2, 2006 David D. Roybal. P.E. Eaton Electrical Cutler-Hammer Products Utility
SECTION 2 TECHNICAL DESCRIPTION OF BPL SYSTEMS
SECTION 2 TECHNICAL DESCRIPTION OF SYSTEMS 2.1 INTRODUCTION Access equipment consists of injectors (also known as concentrators), repeaters, and extractors. injectors are tied to the backbone via fiber
EFFICIENT ELECTRICAL ENERGY TRANSMISSION AND DISTRIBUTION INTERNATIONAL ELECTROTECHNICAL COMMISSION
EFFICIENT ELECTRICAL ENERGY TRANSMISSION AND DISTRIBUTION INTERNATIONAL ELECTROTECHNICAL COMMISSION EFFICIENT ELECTRICAL ENERGY TRANSMISSION AND DISTRIBUTION 1 EFFICIENT ELECTRICAL ENERGY TRANSMISSION
25 Distribution System Automation
Chap25 exe 21/06/02 8:30 Page 442 Distribution System Automation Introduction 25.1 Factors influencing the application of automation to distribution networks 25.2 Primary distribution system automation
4160: THE GREEN 480 MEDIUM VOLTAGE ELECTRICAL SYSTEMS
4160: THE GREEN 480 MEDIUM VOLTAGE ELECTRICAL SYSTEMS for DATA CENTERS Michael Mosman, PE Chief Technical Officer CCG Facilities Integration Incorporated FACILITIES INTEGRATION INCORPORATED MEDIUM VOLTAGE
Pilot Framework Guidelines on Electricity Grid Connection Ref: E10-ENM-18-04 7 December 2010
Pilot Framework Guidelines on Electricity Grid Connection Ref: E10-ENM-18-04 7 December 2010 European Regulators Group for Electricity and Gas Contact: Council of European Energy Regulators ASBL 28 rue
A least-cost electrification proposal for Kisiizi, Uganda Sten Bergman Sr. Energy Specialist, The World Bank
A least-cost electrification proposal for Kisiizi, Uganda Sten Bergman Sr. Energy Specialist, The World Bank 1. Introduction Kisiizi Hospital is a Church of Uganda "Private not-for-profit health care provider
ASSET MANAGEMENT LCNI 2014 Wednesday 22 nd October. Jennifer Woodruff Innovation & Low Carbon Networks Engineer
ASSET MANAGEMENT LCNI 2014 Wednesday 22 nd October Jennifer Woodruff Innovation & Low Carbon Networks Engineer Asset Management Efficient asset management ensures that risk is effectively managed and returns
Step Voltage Regulators
Step Voltage Regulators Don Wareham Field Application Engineer Today s Agenda Introduction Voltage Regulator theory Voltage Regulator application considerations Installation and proper bypassing Wrap-up/questions
Electricity Service Standards
CODE OF PRACTICE Electricity Service Standards Revised August 2015 Contents 1. Preface... 1 Format... 1 2. Application and Objectives... 2 3. Service Standards... 3 3.1 General... 3 3.2 Particular... 3
Brochure. Electric generators to power the world
Brochure Electric generators to power the world We provide motors and generators, services and expertise to save energy and improve customers processes over the total life cycle of our products, and beyond.
AMSC s Superconductor Cable Technologies for Electric Utilities
International Workshop 2014 AMSC s Superconductor Cable Technologies for Electric Utilities Michael Ross, P.E. Managing Director of Superconductor Power Systems AMSC Corporate Facts Headquartered in MA,
OPERATIONS CAPITAL. The Operations Capital program for the test years is divided into two categories:
Filed: September 0, 00 EB-00-0 Tab Schedule Page of OPERATIONS CAPITAL.0 INTRODUCTION Operations Capital funds enhancements and replacements to the facilities required to operate the Hydro One Transmission
CUSTOMER REQUIREMENTS AT POWER SUBSTATIONS
CUSTOMER REQUIREMENTS AT POWER SUBSTATIONS Customer Handout Date Aug 2, 2010 Version 1.0 File Name Customer Requirements At Power Substations Document Id Outside Plant Engineering 1 Table Of Contents 1.0
APPLICATION NOTE USING A MODEL 3060-MS SERIES AS A REGENERATIVE AC SOURCE FOR PV INVERTER TEST APPLICATIONS. Abstract.
USING A MODEL 3060-MS SERIES AS A REGENERATIVE AC SOURCE FOR PV INVERTER TEST APPLICATIONS Abstract This application note describes the necessary procedure to use a standard Pacific Power Source Model
Transfer Equipment Controls
Control Types Manual Transfer Switches Nonautomatic Transfer Switches Automatic Transfer Switches The type of control system for the transfer switch will vary depending on the type of switching equipment
7. Reactive energy compensation
593 7. Reactive energy compensation 594 7. REACTIVE ENERGY COMPENSATION Reactive energy compensation is an important element for reducing the electricity bill and improving the quality of the electrical
Fundamentals of Modern Electrical Substations Part 1: Mission of Electrical Substations and their Main Components
Fundamentals of Modern Electrical Substations Part 1: Mission of Electrical Substations and their Main Components Course No: E02-010 Credit: 2 PDH Boris Shvartsberg, Ph.D., P.E., P.M.P. Continuing Education
MV, HV AND EHV SWITCHGEAR TESTING & COMMISSIONING
Training Title MV, HV AND EHV SWITCHGEAR TESTING & COMMISSIONING Training Duration 5 days Training Date MV, HV and EHV Switchgear Testing & Commissioning 5 20 24 Apr $3,750 Dubai, UAE In any of the 5 star
ELECTRICAL INSULATION TESTING OF HV EQUIPMENT UP TO 33kV
1. SCOPE This document details PowerSystems requirements for electrical testing of HV Equipment up to and including 33kV. 2. ISSUE RECORD This is a Reference document. The current version of Controlled
Trends in Power Quality
Trends in Power Quality Herwig Renner Graz University of Technology Institute for Electrical Power Systems Contents Results from long term harmonic and flicker measurement in Austria Discussion flicker
ESB Networks Ltd Statement of Charges
ESB Networks Ltd Statement of Charges Revision Date: 9/2014 Revision No.: 11 Document No: DOC-101209-AXR Issued by: ESB NETWORKS LTD Approved by : CER Effective Date: 01/10/2014 Commercial and Renewable
GLOSSARY. Glossary of Terms for Capacity Based Demand Response PUBLIC. Issue 3.0 GOT-1
PUBLIC GOT-1 GLOSSARY Glossary of Terms for Capacity Based Demand Response Issue 3.0 This document provides a glossary of terms with definitions used in the Capacity Based Demand Response program. Public
