1 June 16, 2015 DESIGN DEVELOPMENT PRESENTATION HIGH SCHOOL, JUNIOR HIGH SCHOOL & INTERMEDIATE SCHOOL ADDITIONS & RENOVATIONS KAUFMAN INDEPENDENT SCHOOL DISTRICT

2 Acknowledgments 2 Kaufman HS & Norman JHS Narratives 3 Site Plans 6 Kaufman HS Floor Plans 9 Kaufman HS Space Program 16 Renderings 17 HIGH SCHOOL, JUNIOR HIGH & INTERMEDIATE SCHOOL ADDITIONS & RENOVATIONS KAUFMAN INDEPENDENT SCHOOL DISTRICT Kaufman HS Construction and Demolition Sequences 22 Norman JHS Floor Plan 24 Elevation Rendering 25 Nash Intermediate School Narrative 27 Nash Intermediate School Floor Plan 28 Schedule 29 TABLE OF CONTENTS High School, Junior High School & Intermediate School Additions & Renovations, Kaufman Independent School District 1

3 Kaufman ISD Dr. Lori Blaylock Superintendent Byron Gregg President John Zaby Vice President Britt Murrey Secretary Chip Langston Trustee Linda Mott Trustee Christine Borders Trustee Kathy Castles Trustee Kaufman ISD Design Team Dr. Lori Blaylock Superintendent Kell Clopton Assistant Superintendent of Schools Joe Nicks Assistant Superintendent of Academics Project Design Team Tom Lueck, AIA Principal, Huckabee Heather Barksdale, AIA Associate Principal, Huckabee Casey Casstevens Lead Designer, Huckabee Jason Stevenson Project Leader, Huckabee Tami O Neal Interior Designer, Huckabee Construction Manager Balfour Beatty Dallas, TX HIGH SCHOOL, JUNIOR HIGH & INTERMEDIATE SCHOOL ADDITIONS & RENOVATIONS KAUFMAN INDEPENDENT SCHOOL DISTRICT Brian Carter Angela Corder Dr. Dan Crawford Director of Finance Director of Technology Principal, Kaufman High School Civil Engineering Teague, Nall & Perkins Dallas, TX MEP Engineering Romine, Romine, & Burgess Fort Worth, TX Faculty & Staff Dr. Tim Allen Kaufman High School Assistant Principal, Kaufman High School Structural Engineering JQ Dallas, TX Jeremy Melton Faculty & Staff Principal, O.P. Norman Junior High School O.P. Norman Junior High School Technology/Security Huckabee Fort Worth, TX Faculty & Staff Gary Campbell High School ACKNOWLEDGMENTS High School, Junior High School & Intermediate School Additions & Renovations, Kaufman Independent School District 2

4 Kaufman High School Introduction Kaufman High School is one of several schools planned to be renovated and expanded as part of the November 2014 Bond as a way to: Address an aging campus Provide new instructional space for current capacity issues as well as future growth Increase safety and security The current High School is composed of multiple detached buildings and classrooms that open to the exterior, creating safety and security issues. Not only has it exceeded its functional student capacity, the support spaces such as an auditorium and the gymnasiums are either not sufficient or not present at all. The proposed facility will address the issues above by demolishing a majority of the existing campus, and replacing it with new construction that is energy efficient, accommodates the new and future student capacity, and adds an auditorium, new competition gym, and new career and technical programs space. The new facility will also have additional security features which increase the safety of the students and faculty. HIGH SCHOOL, JUNIOR HIGH & INTERMEDIATE SCHOOL ADDITIONS & RENOVATIONS KAUFMAN INDEPENDENT SCHOOL DISTRICT Site Design The existing site does not provide a separate drive for parents and buses, creating confusion and safety hazards during peak traffic times. The proposed plan will provide separate drives for each transportation type, as well as separate staff, visitor, and student parking. A large parking lot on the North side of the site will accommodate all student parking, and is perfectly situated for special events held in the auditorium, competition gym, and cafetorium. It is also adjacent to the relocated and reoriented softball field, providing convenient and accessible parking for that facility as well. Access drives and loading areas will be provided for larger scale deliveries and vehicles, located at the Auditorium, Fine Arts wing, and Ag Shop. A new drive will separate the new High School facility from the Junior High, creating separation and better access around the building. Aging Facilities and Student Capacity Over the years, Kaufman High School has gained several buildings on campus, all connected by outdoor covered walkways. The existing core instructional spaces are not sufficient for today s instructional methods or programs, nor the student capacity that exists today. As growth in Kaufman ISD is expected to continue, additional instructional space is desired. New programs focused on career and technical education require specialized classrooms and labs, which are not present in the existing facility. The proposed design incorporates several of the newer spaces on the campus, namely the gymnasium, cafetorium, and science wing, replacing and supplementing the older spaces with new construction. The existing science and math wing will be updated, adjacent to additional classroom and laboratory space of new construction. New administration, library, core instructional space, and career and technical spaces will create a connection between the existing science wing and the existing Cafetorium. The new library will provide a centrally located area for students to utilize in several different ways, using traditional resources as well as the newest technology. A multi-level space is allocated for the library, which allows for several different zones within the same space for CONTINUED NARRATIVE High School, Junior High School & Intermediate School Additions & Renovations, Kaufman Independent School District 3

5 collaboration or individual study. The administration is located at the main entry, which incorporates a controlled access vestibule. Located off of the main corridor, the new career and technical education wing provides spaces specially designed for the programs that will available for study. The Audio/Visual studio is a special space, which will allow for student broadcasts and video production in a professional setting. Art classrooms are located in this wing as well, which allows for students to be involved in traditional art instruction as well as graphic arts, which will have its own computer lab spaces. The traditional art classrooms boast an abundance of natural light and their own covered courtyard area, for outdoor activities. All classrooms in this wing have windows to the corridor, which allow students to view the innovative approach these programs exhibit. Not only does this allow for student work to be displayed, it assists in generating interest in the programs themselves. As students walk from this area down the main corridor, they enter the new two-story classroom wings. The configuration of these two wings allows for all classrooms to receive natural light, and wider spaces along the corridors create natural congregation points for students, which keeps the flow of traffic unobstructed. The main corridor terminates at a large lobby space, located in front of the new Auditorium. The new performance venue with 750 seats will be constructed adjacent to the existing Cafetorium. It will include a fly loft as well as current sound and lighting capabilities, to allow for UIL performance events as well as a variety of musical and theater performances. The new fine arts wing including band hall will be located adjacent to the auditorium. Also accessed from the main lobby are the Cafetorium and Athletics area. The existing Cafetorium and stage will remain, allowing student dining to continue, as well as providing a venue for dinner theater or luncheon events. Alongside the existing competition gymnasium, a new competition gymnasium will be constructed with enough seats to house the entire student body. Raised, fixed seating will create a dramatic environment for athletic competition, and the two practice courts will allow more reasonable practice times to be available for students. A new Ag shop will be constructed at the back of the new gymnasium, which allows for direct access with trailers and large vehicles as these programs require. This access also connects to the drive that currently leads to the Ag barn. HIGH SCHOOL, JUNIOR HIGH & INTERMEDIATE SCHOOL ADDITIONS & RENOVATIONS KAUFMAN INDEPENDENT SCHOOL DISTRICT Safety and Security Currently, with the buildings connected without a secure pathway, exterior doors are required to be open for the majority of the day to provide student access. Also, the main entry to the school relies on a visitor to choose to check in at the main office prior to their intended destination. In order to address these issues, the design addresses security through a controlled access vestibule at the main entry, surveillance cameras throughout the facility, an enclosed connection to the buildings on campus, and access control on all exterior doors. High School, Junior High School & Intermediate School Additions & Renovations, Kaufman Independent School District 4

6 O.P. Norman Junior High School Introduction O.P. Norman Junior High School is one of several schools planned to be renovated as part of the November 2014 Bond as a way to: Address an aging campus Provide appropriate instructional space for current capacity issues as well as future growth Increase safety and security The Junior High School is currently attached to Kaufman High School, without a proper separation of campuses. As part of the Kaufman High School project, this connection will be severed, allowing for both campuses to operate independently, and students to remain in their appropriate buildings. Portions of the existing High School, currently located in what will be part of the Junior High building, will be repurposed to house the Gary Campbell High School students. These students will have a separate entry and support spaces from the Junior High. The new Junior High will receive a portion of this vacated space as well, to address capacity issues. Renovation and repurposing of several interior spaces will address operational challenges and state standard deviations. Also, additional security features will be incorporated which increase the safety of the students and faculty, and exterior improvements are planned to elevate the aesthetic of the building. HIGH SCHOOL, JUNIOR HIGH & INTERMEDIATE SCHOOL ADDITIONS & RENOVATIONS KAUFMAN INDEPENDENT SCHOOL DISTRICT Aging Facilities and Student Capacity The renovations at the Junior High School campus are focused on repurposed space. As the student capacity has grown, there is a need for an additional science lab and associated prep area. This will be achieved by combining two traditional classrooms, and outfitting the lab with the proper furniture and equipment for today s instruction. The remaining labs will be retrofitted to meet current state standards. In addition, several classrooms from the vacated high school space will be allocated for the Junior High, adding to the available instructional space. Exterior improvements are slated for this campus as well. Once the connection to the High School is removed, there will be inevitable façade work that is required to address the newly exposed wall. In addition to the required modifications, aesthetic improvements are also desired to update the front façade, and allow the new construction of the High School to relate to the existing Junior High in a more cohesive manner. Safety and Security Currently, the administration area is not located at the main entry point of the campus. Repurposing of existing space will allow for the administration area to be relocated, and a controlled vestibule to be incorporated at the main entry. Surveillance cameras will be added to the facility, as well as access control on all exterior doors. The exterior of the building will not only receive some much-needed attention, but also additional exterior lighting to improve safety. High School, Junior High School & Intermediate School Additions & Renovations, Kaufman Independent School District 5

7 Existing Junior High School to Stay Existing High School to Stay Existing Buildings to be Demolished Existing Maintenance/Transportation/Technology EXISTING KAUFMAN HIGH SCHOOL & JUNIOR HIGH CAMPUS High School, Junior High School & Intermediate School Additions & Renovations, Kaufman Independent School District 6

8 KISD ENTRANCE STAFF/VISITOR PARKING (122) EXISTING BUILDING S. HOUS TON ST. EXISTING BUILDING EXISTING BUILDING FUTURE EXPANSION VISITOR PARKING (42) BAND PRACTICE AREA STUDENT/ FACULTY PARKING (376) RELOCATED SOFTBALL FIELD AG YARD HS FIELD HOUSE NORMAN JUNIOR HIGH RENOVATION ADDITIONAL PARKING (32) COLOR LEGEND Existing Building Additions N JUNIOR HIGH Parking/Pavement Walkways PROPOSED KAUFMAN HIGH SCHOOL & JUNIOR HIGH SITE PLAN High School, Junior High School & Intermediate School Additions & Renovations, Kaufman Independent School District 7

9 COLOR LEGEND Existing Building Additions Parking/Pavement Walkways EXISTING BUILDING FF P-O RO SD VISITOR PARKING (42) STAFF/VISITOR PARKING FF O (122) ROP R PA T EN D STUDENT/ EVENT ENTRY EXISTING BUILDING STUDENT/ EVENT ENTRY EXISTING BUILDING MAIN ENTRY BU S. HOUS TON ST. Phase One BAND PRACTICE AREA RELOCATED SOFTBALL FIELD STUDENT/ FACULTY PARKING (376) FUTURE EXPANSION AG YARD HS FIELD HOUSE N PROPOSED KAUFMAN HIGH SCHOOL & JUNIOR HIGH SITE PLAN High School, Junior High School & Intermediate School Additions & Renovations, Kaufman Independent School District 8

10 FOR SECURITY REASONS, THE FLOOR PLANS HAVE BEEN REMOVED. PLEASE CONTACT THE DISTRICT FOR COPIES KAUFMAN HIGH SCHOOL - FLOOR PLAN High School, Junior High School & Intermediate School Additions & Renovations, Kaufman Independent School District 9

11 PROGRAM OF SPACES NO. OF ROOMS NET AREA PROPOSED KAUFMAN HIGH SCHOOL Dressing Rooms CULINARY ARTS 3068 TEACHER SUPPORT 6,432 CORE SUBJECT CLASSROOMS 39,600 English Classrooms Social Studies Collaboration/Workroom/RR Science Labs (New) Science Labs (Existing) Math (New) Math (Existing) Collaboration/Workroom/RR Foreign Language Classrooms Multi-Purpose Computer Labs Collaboration/Workroom/RR FINE ARTS 10,585 Band Hall 1 1 2,800 Band Hall Practice Rooms Instrument Storage Uniform Storage Music Library Band Director Office Office Band Ensemble Percussion Room Percussion Storage Instrument Repair Drum Major Restrooms 2 52 Delivery Access Music Library Choir Rehearsal (Renovated) Choir Storage (Renovated) Choir Office (Renovated) Choir Practice (Renovated) 4 65 Make-up Backstage Costume Storage Prop Storage Assembly/Receiving/Storage Black Box Rehearsal Rm 1 1,748 Theater Arts/Fine Arts Office OTHER ELECTIVES 1,242 Journalism 1 1,242 SPECIAL SERVICES 3,318 Life Skills - Moderate Classroom LIfe Skills - Severe Classroom Life Skills - PAES Lab Life Skills - Efficiency Life Skills - Kitchen/Laundry/RR Content Mastery SpEd Office 590 CAREER & TECHNOLOGY BUSINESS EDUCATION 11,969 Business Labs (BIM) Health Science Classrooms Health Science Lab 1 1,266 Health Science Lab Storage Health Science Storage TV Studio Computer Lab - Animation/Graphic A/V Control Rm A/V Storage Editing Room 1 75 Render Room Engineering/Robotics Lab Engineering Storage Engineering Dirty Lab Culinary Classroom Culinary Arts Lab Pantry Storage ATHLETICS 18,340 Competition Gym w/ 2 Practice Courts 1 8,490 Seating w/ Locker Rooms Below (incl. Boys BB, Girls 11-12, Storage & Laundry) 1 9,850 ANCILLARY SPACES LEARNING RESOURCE CTR 8,123 Media Center Library (2nd Floor) Media Cafe Office Study Rooms 3 90 Workroom ADMINISTRATION 6,895 Principal Office Principal Secretary Main Reception Admin Conference Admin Work/Mail Rm Admin RR PEIMS Office Admin File Storage Admin Storage 1 95 Assist Princ. Offices AP Waiting/Sec Clinic Book Rm ARDs Conf Rm Teacher Workrooms/ Collaboration/RR (included in Core Spaces) Multi-User Restrooms (New) Multi-User Restrooms (Existing) MISCELLANEOUS 2,437 General Storage MEP/IDF/Common Main Electrical Rm Mechanical Rms 4 64 Main Distribution Rm IDF Rms 4 64 General Storage OVERALL Existing Math/Science Building 24,250 Existing Cafeteria Building 33,820 Existing Practice Gym/Lkr Rm Bldg 39,800 Overall SF (Existing) 97,870 Overall SF (New) 175,114 Gross Building SF 272,984 VISUAL ARTS 3074 Art Lab 2 1,208 Art Storage Dark Room Kiln Room THEATER ARTS 16,142 Auditorium, seating for ,993 Aud. Lobby (Incl. in Circulation) 0 0 AGRICULTURE EDUCATION 6,534 Ag Classrooms Ag Science Classroom Ag Mechanical Shop 1 3,810 Ag Mechanical Storage Ag Mechanical Tool Storage Ag Office Ag Mezzanine Security Office ISS Room Attendance Office COUNSELOR S SUITE 1,569 Counselor s Office Counselor Reception/Waiting Test Material Storage Go Center Aud. Public Restrooms Stage 1 3,700 SPACE PROGRAM High School, Junior High School & Intermediate School Additions & Renovations, Kaufman Independent School District 10

12 RENDERING - MAIN ENTRANCE High School, Junior High School & Intermediate School Additions & Renovations, Kaufman Independent School District 11

13 RENDERING - STUDENT ENTRANCE PLAZA High School, Junior High School & Intermediate School Additions & Renovations, Kaufman Independent School District 12

14 RENDERING - SOUTHEAST VIEW FROM STADIUM High School, Junior High School & Intermediate School Additions & Renovations, Kaufman Independent School District 13

15 RENDERING - MEDIA CENTER CAFE High School, Junior High School & Intermediate School Additions & Renovations, Kaufman Independent School District 14

16 RENDERING - MAIN ENTRANCE CORRIDOR High School, Junior High School & Intermediate School Additions & Renovations, Kaufman Independent School District 15

17 CONSTRUCTION SEQUENCE High School, Junior High School & Intermediate School Additions & Renovations, Kaufman Independent School District 16

18 DEMOLITION SEQUENCE High School, Junior High School & Intermediate School Additions & Renovations, Kaufman Independent School District 17

19 FOR SECURITY REASONS, THE FLOOR PLANS HAVE BEEN REMOVED. PLEASE CONTACT THE DISTRICT FOR COPIES NORMAN JUNIOR HIGH - FLOOR PLAN High School, Junior High School & Intermediate School Additions & Renovations, Kaufman Independent School District 18

20 JUNIOR HIGH - ELEVATION High School, Junior High School & Intermediate School Additions & Renovations, Kaufman Independent School District 19

21 INTERMEDIATE SCHOOL ADDITIONS & RENOVATIONS

22 Lucille Nash Intermediate School Introduction Lucille Nash Intermediate School is one of several schools planned to be renovated as part of the November 2014 Bond as a way to: Provide additional instructional space for future growth Increase safety and security Increase Student Capacity The growth in Kaufman ISD is expected to continue, which necessitates additional instructional space at this campus. In order to achieve this, two additional classrooms will be provided as well as additional restrooms. Access to the exterior will be maintained, and circulation will be improved via the new cross-corridor between the existing and new construction. Safety and Security As the administration area is located to the side of the main entry, there is not a way to control entry to the facility. A new controlled vestibule will be added, alongside surveillance cameras and access control on all exterior doors. Additional exterior lighting will be added to increase safety as well. HIGH SCHOOL, JUNIOR HIGH & INTERMEDIATE SCHOOL ADDITIONS & RENOVATIONS KAUFMAN INDEPENDENT SCHOOL DISTRICT NARRATIVE High School, Junior High School & Intermediate School Additions & Renovations, Kaufman Independent School District 21

23 FOR SECURITY REASONS, THE FLOOR PLANS HAVE BEEN REMOVED. PLEASE CONTACT THE DISTRICT FOR COPIES NASH INTERMEDIATE SCHOOL- FLOOR PLAN High School, Junior High School & Intermediate School Additions & Renovations, Kaufman Independent School District 22

24 MASTER SCHEDULE Pre-Design Phase Conceptual Design Phase Jan. START COMPLETE START COMPLETE Feb. Mar. Apr. May June July Aug. Sept. Oct. Nov. Dec. January - December January - December Schematic Design Phase Design Development Construction Document START PHASE I START COMPLETE START COMPLETE COMPLETE START BOARD PRESENTATION COMPLETE Jurisdictional Review Bid & Award Construction Observation Services PHASE I PHASE I COMPLETE COMPLETE PHASE I START KHS COMPLETE START START SUBSTANTIAL COMPLETION KHS PHASE I COMPLETE START NASH ES SUBSTANTIAL COMPLETION NASH ES SUBSTANTIAL COMPLETION KHS & NJH COMPLETE START FIRST DAY NJH OF SCHOOL SCHEDULE High School, Junior High School & Intermediate School Additions & Renovations, Kaufman Independent School District 23

25

SCHEMATIC DESIGN PRESENTATION

SCHEMATIC DESIGN PRESENTATION April 13, 2015 SCHEMATIC DESIGN PRESENTATION HIGH SCHOOL, JUNIOR HIGH SCHOOL & INTERMEDIATE SCHOOL ADDITIONS & RENOVATIONS KAUFMAN INDEPENDENT SCHOOL DISTRICT Kaufman ISD Dr. Lori Blaylock Superintendent

More information

SCHEMATIC DESIGN PRESENTATION ACTON ELEMENTARY SCHOOL

SCHEMATIC DESIGN PRESENTATION ACTON ELEMENTARY SCHOOL March 16, 2015 SCHEMATIC DESIGN PRESENTATION ACTON ELEMENTARY SCHOOL DUNCANVILLE INDEPENDENT SCHOOL DISTRICT Acknowledgments 2 Narrative 3 The Process 4 Site Analysis 6 Site Plan 7 ACTON ELEMENTARY SCHOOL

More information

DESIGN DEVELOPMENT PRESENTATION

DESIGN DEVELOPMENT PRESENTATION October 26, 2015 DESIGN DEVELOPMENT PRESENTATION NEW SHIRLEY HALL MIDDLE SCHOOL & JOE M. TISON MIDDLE SCHOOL ADDITIONS AND RENOVATION WEATHERFORD INDEPENDENT SCHOOL DISTRICT Acknowledgments 3 Narrative

More information

SCHEMATIC DESIGN PRESENTATION NEW JOSHUA MIDDLE SCHOOL

SCHEMATIC DESIGN PRESENTATION NEW JOSHUA MIDDLE SCHOOL June 15, 2015 SCHEMATIC DESIGN PRESENTATION NEW JOSHUA MIDDLE SCHOOL JOSHUA INDEPENDENT SCHOOL DISTRICT Acknowledgments 2 Narrative 3 The Process 4 Site Analysis 5 Independent School District Site Plan

More information

Performing Arts Wing. Existing Auditorium. Library. Student Entry. Omni Room Athletics/JROTC. Dance Bus Drop

Performing Arts Wing. Existing Auditorium. Library. Student Entry. Omni Room Athletics/JROTC. Dance Bus Drop Choir Band Performing Arts Wing Arts Courtyard Drama Liberal Arts Wing Team Arts Prefunction Loading Area Team Existing Auditorium Heritage Hall Auditorium Lobby Administration Library Visitor Entry Team

More information

HAZELWOOD HIGH SCHOOLS SCHEMATIC DESIGN PRESENTATION

HAZELWOOD HIGH SCHOOLS SCHEMATIC DESIGN PRESENTATION HAZELWOOD HIGH SCHOOLS SCHEMATIC DESIGN PRESENTATION 1 AGENDA Hazelwood 1 st Planning Process High School Program Schematic Designs Schedule 2 HAZELWOOD 1 ST GOALS Life, health and safety improvements

More information

1/9/2015 P:\130217-03\Project Management\Program\Ripon Space Program - 7 January 2015.xlsx

1/9/2015 P:\130217-03\Project Management\Program\Ripon Space Program - 7 January 2015.xlsx MIDDLE SCHOOL Administration Office Principal's Office 200 1 200 Desk, conference table for 4-6 Conference Room 250 1 250 Conference table for 12 Open Office Area 250 1 250 2 Workstations Mail / copier

More information

Schematic Plan Submittal, 21 November, 2011 Roesling Nakamura Terada Architects

Schematic Plan Submittal, 21 November, 2011 Roesling Nakamura Terada Architects To r r e y P i n e s H i g h S c h o o l M a s t e r P l a n Schematic Plan Submittal, 21 November, 2011 Roesling Nakamura Terada Architects I n t r o d u c t i o n 1.0 INTRODUCTION The vision for the

More information

Schematic Design Presentation S. Dallas Dance, Superintendent October 22, 2013 OVERLEA HIGH SCHOOL

Schematic Design Presentation S. Dallas Dance, Superintendent October 22, 2013 OVERLEA HIGH SCHOOL Schematic Design Presentation S. Dallas Dance, Superintendent October 22, 2013 0 Overlea High School - Facility Summary Facility Opened: Auditorium Addition: Activity Room Addition: School Rated Capacity

More information

JMS Phone List. dial and small conference capability

JMS Phone List. dial and small conference capability JMS Phone List Main office desk multi line console console can view all lines Main office desk multi line Main office fax line? POTS as currently Principal's office desk multi line extension and private

More information

Dear Keller High School Families,

Dear Keller High School Families, Dear Keller High School Families, As we near the close of the 2014-15 school year, I am so proud of our community of learners for committing to the vision of KHS and its Tradition of Excellence! I would

More information

Centinela Valley Union High School District. Measure CV Masterplan Update June 2011

Centinela Valley Union High School District. Measure CV Masterplan Update June 2011 Centinela Valley Union High School District Measure CV Masterplan Update June 2011 Hawthorne High School (Phase 1) Hawthorne High School Phase 1: Science, Engineering, and Media Arts Center (Funded) 3

More information

Frequently Asked Questions

Frequently Asked Questions Byron Area Schools Frequently Asked Questions Bond Proposal How did this come about? For several years the Byron Area Schools Board of Education has included upgrading facilities as one of the district

More information

DISTRICT-WIDE ELEMENTARY PROGRAMMING

DISTRICT-WIDE ELEMENTARY PROGRAMMING DISTRICT-WIDE ELEMENTARY PROGRAMMING PREPARED BY: GIBRALTAR DESIGN SUBMITTED TO: BOARD OF SCHOOL TRUSTEES School Board Meeting September 17, 2015 2015 Gibraltar Design, Inc. Table of Contents SECTION I.

More information

Bensalem High School Renovation 2014-2016

Bensalem High School Renovation 2014-2016 Bensalem High School Renovation 2014-2016 Design Problems Inability to close off sections of the building during evening and weekend events. Concerns about the efficiency of staffing and supplying three

More information

HERMANTOWN COMMUNITY SCHOOLS. New High School Addition End of DD Design Review

HERMANTOWN COMMUNITY SCHOOLS. New High School Addition End of DD Design Review HERMANTOWN COMMUNITY SCHOOLS New High School Addition End of DD Design Review SITE AERIAL HIGH SCHOOL ELEMENTARY SCHOOL BUS GARAGES HOCKEY ARENA / DISTRICT OFFICE SITE FORCES EXISTING BUILDING INFORMATION

More information

PAGE INTENTIONALLY LEFT BLANK

PAGE INTENTIONALLY LEFT BLANK PAGE INTENTIONALLY LEFT BLANK TABLE OF CONTENTS I. Introduction 1 Page II. Documentation of Existing Educational Programs 1 and Instructional Space III. State Square Footage Standards 2 IV. Space Allocation

More information

Mequon - Thiensville School District Long Range Facilities Plan Monthly Project Schedule

Mequon - Thiensville School District Long Range Facilities Plan Monthly Project Schedule Mequon - Thiensville School District Long Range Facilities Plan Monthly Project Schedule Homestead HS Sept.'15 Oct'15 Nov'15 Dec'15 Jan'16 Feb'16 Repair Asphalt @ Main Garage Replace Exterior Hollow Metal

More information

RSU 21 Board of Directors considering major renovation projects

RSU 21 Board of Directors considering major renovation projects RSU 21 Board of Directors considering major renovation projects On Monday, September 16, the RSU 21 Board reviewed proposals to renovate three schools within the district: Kennebunk High School, Mildred

More information

SELECTED SPECIAL EVENTS PROJECTS

SELECTED SPECIAL EVENTS PROJECTS 1 5 SELECTED SPECIAL EVENTS PROJECTS 3 1 DONNA AND MARVIN SCHWATZ CENTER FOR PERFORMING ARTS, ATLANTA, GEORGIA, USA. COBB ENERGY PERFORMING ARTS CENTRE, COBB COUNTY, GEORGIA, USA. 3 OLYMPIC AQUATIC CENTER,

More information

New Jersey City University Gilligan Student Union Center

New Jersey City University Gilligan Student Union Center New Jersey City University Gilligan Student Union Center The RBA Group worked with New Jersey City University in a major renovation of their Gilligan Student Union building. We were contracted to reassess,

More information

May 2014 Texas School Bond Elections

May 2014 Texas School Bond Elections May 2014 Texas School Bond Elections What are the individual districts needs? New facilities Renovations Technology Central facilities How much tax revenue can the district generate? Depends on district

More information

CALLOWAY COUNTY SCHOOLS DISTRICT FACILITIES PLAN

CALLOWAY COUNTY SCHOOLS DISTRICT FACILITIES PLAN DISTRICT "SHELL" SUBMISSION DATE: 4/17/13 (delete following Hearing) KDE "SHELL" RESUBMISSION DATE: 4/19/13 (delete following Hearing) KBE APPROVAL DATE: JUNE 2013 CALLOWAY COUNTY SCHOOLS DISTRICT FACILITIES

More information

stadium designs BLRB architects TACOMA // SPOKANE // PORTLAND // BEND

stadium designs BLRB architects TACOMA // SPOKANE // PORTLAND // BEND stadium designs TACOMA // SPOKANE // PORTLAND // BEND about blrb architects Founded in 1953, BLRB is a mid-size regional firm with offices throughout the Northwest in Tacoma, Spokane, (Washington) Portland

More information

ARTS. presented by: TOM SHERRY HAMILTON ANDERSON ASSOCIATES

ARTS. presented by: TOM SHERRY HAMILTON ANDERSON ASSOCIATES DETROIT SCHOOL OF ARTS presented by: TOM SHERRY HAMILTON ANDERSON ASSOCIATES of DSA OVERVIEW ONE TEACHER S VISION DR. DENISE DAVIS-COTTON RECOGNIZED MILKEN EDUCATOR Picture of Old DSA FOUNDED IN 1992 RECEIVED

More information

PROGRAMMING RESPONSE. Flat Rock Elementary

PROGRAMMING RESPONSE. Flat Rock Elementary Flat Rock Elementary PROGRAMMING RESPONSE Powhatan County s last new elementary school was designed and built over 10 years ago. So, before designing their newest elementary, Flat Rock, a broad-based group

More information

Gregory-Portland Independent School District. G-PISD BOND ELECTION November 6, 2012. Information Guide

Gregory-Portland Independent School District. G-PISD BOND ELECTION November 6, 2012. Information Guide G-PISD BOND ELECTION November 6, 2012 Information Guide Información en Español Información sobre la emisión de bonos del Gregory- Portland Independent School, el dia 6 de Noviembre 20012, es disponible

More information

MEASURE G-2010 EXHIBIT B FULL TEXT BALLOT PROPOSITION OF THE SAN JOSE EVERGREEN COMMUNITY COLLEGE DISTRICT BOND MEASURE ELECTION NOVEMBER 2, 2010

MEASURE G-2010 EXHIBIT B FULL TEXT BALLOT PROPOSITION OF THE SAN JOSE EVERGREEN COMMUNITY COLLEGE DISTRICT BOND MEASURE ELECTION NOVEMBER 2, 2010 MEASURE G-2010 EXHIBIT B FULL TEXT BALLOT PROPOSITION OF THE SAN JOSE EVERGREEN COMMUNITY COLLEGE DISTRICT BOND MEASURE ELECTION NOVEMBER 2, 2010 To better prepare San Jose City College/ Evergreen Valley

More information

Centennial Building Campaign

Centennial Building Campaign T H E B U C K L E Y S C H O O L Centennial Building Campaign THE BUCKLEY SCHOOL HAS PURSUED EXCELLENCE in educating boys since it was founded in 9. Over the past decade, it has become clear to the Board

More information

FRANCIS L. CARDOZO HIGH SCHOOL 1200 CLIFTON STREET NW WASHINGTON, DC 20009

FRANCIS L. CARDOZO HIGH SCHOOL 1200 CLIFTON STREET NW WASHINGTON, DC 20009 FRANCIS L. CARDOZO HIGH SCHOOL 1200 CLIFTON STREET NW WASHINGTON, DC 20009 FRANCIS L. CARDOZO HIGH SCHOOL SCHOOL HISTORY Francis L. Cardozo High School, located at 1200 Clifton Street and bounded by Florida

More information

Bond Referendum Presentation. Dr. Ralph P. Ferrie, Superintendent of Schools May 12, 2014

Bond Referendum Presentation. Dr. Ralph P. Ferrie, Superintendent of Schools May 12, 2014 Bond Referendum Presentation Dr. Ralph P. Ferrie, Superintendent of Schools May 12, 2014 Mr. David Fowler President Floral Park- Bellerose Mr. David Del Santo Vice-President New Hyde Park Garden City Park

More information

Table of Contents. I Introduction 2. II Definitions & Area Calculation 2. III Room Numbering 7. IV Appendix A 9

Table of Contents. I Introduction 2. II Definitions & Area Calculation 2. III Room Numbering 7. IV Appendix A 9 Table of Contents I Introduction 2 II Definitions & Area Calculation 2 III Room Numbering 7 IV Appendix A 9 I. Introduction A. Purposes The purposes of this document are to: B. Benefits 1. Clarify and

More information

Guideline for Square Footage Requirements for Educational Facilities. 160-5-4-.16 (a) 4. Educational Facility Site, Construction, and Reimbursement

Guideline for Square Footage Requirements for Educational Facilities. 160-5-4-.16 (a) 4. Educational Facility Site, Construction, and Reimbursement Guideline for Square Footage Requirements for Educational Facilities 160-5-4-.16 (a) 4 Educational Facility Site, Construction, and Reimbursement Facilities Services Unit Effective Date: 05-30-12 Page

More information

Facilities Advisory Committee Recommendations. Presentation to the Administrative Council May 22, 2013

Facilities Advisory Committee Recommendations. Presentation to the Administrative Council May 22, 2013 Facilities Advisory Committee Recommendations Presentation to the Administrative Council May 22, 2013 Harun Biswas (Chair) Kara Mullen Caroline Clower Rasheen Hunter Gid Rowell John Shiffert Cindy Lauer

More information

Secondary Educational Visioning Meeting 1

Secondary Educational Visioning Meeting 1 Secondary Educational Visioning Meeting 1 SANTA BARBARA UNIFIED SCHOOL DISTRICT FACILITIES MASTER PLAN LPA PROJECT NO. 13200.10 DATE: April 1, 2014 TIME: 3:30-5:00 pm PLACE: District Office AGENDA Purpose

More information

We know what brings schools together.

We know what brings schools together. School Work We know what brings schools together. About Us Martin Gardner Architecture, P.C. has been providing excellence in design and building consulting services in eastern Iowa for nearly 30 years.

More information

Van Vleck ISD Bond Election

Van Vleck ISD Bond Election Van Vleck ISD Bond Election November 4, 2014 The Van Vleck ISD School Board called a bond election at their meeting on August 18 for $42.7 million. 2 School districts must ask voters for permission to

More information

Education, Entrepreneurship & Urban Revitalization

Education, Entrepreneurship & Urban Revitalization Education, Entrepreneurship & Urban Revitalization Over-The-Rhine Architecture, Urban Planning, and Economics students worked with Public school administrators to envision a new Entrepreneurial and a revitalized

More information

Items in red were complete 2-22-10. Items in green were complete on 8-2-11. Lined out items are Life Safety Codes.

Items in red were complete 2-22-10. Items in green were complete on 8-2-11. Lined out items are Life Safety Codes. Office of Safe and Orderly Schools Facility Safety Assessment Dennis Meador, School Facilities Supervisor Mark Hobson, School Facilities Supervisor Division of School Building September 18 19, 2007 Items

More information

Public Building Commission of Chicago. Board Meeting August 20, 2013

Public Building Commission of Chicago. Board Meeting August 20, 2013 Public Building Commission of Chicago Board Meeting August 20, 2013 Board Meeting August 20, 2013 Recent Events Enrico Tonti Elementary School Kindergarten Modular Opening August 5, 2013 Board Meeting

More information

Calculating School Capacity:

Calculating School Capacity: Calculating School Capacity: presented by: Amy Yurko, AIA ayurko@brainspaces.com Peter Brown, AIA, LEED AP pbrown@brainspaces.com Mary Cary, AIA Anchorage School District Local, State & National Perspectives

More information

21 st CENTURY HIGH SCHOOLS

21 st CENTURY HIGH SCHOOLS 21 st CENTURY HIGH SCHOOLS 1 CO-LABS & ACTIVITIES What is a Co-Lab? A collaborative workshop session with stakeholder groups. These sessions were designed to examine opportunities and define parameters

More information

Design and Construction Planning Process Strongsville City Schools

Design and Construction Planning Process Strongsville City Schools Design and Construction Planning Process Strongsville City Schools THANK YOU. OUR TEAM 50+ years experience Headquartered in Akron, Ohio Full-service A&E firm Over 400 professionals Employee owned OUR

More information

By James Britt, Elizabeth Erbes, Julie Rosin and Bill Good

By James Britt, Elizabeth Erbes, Julie Rosin and Bill Good connecting students, creating futures at central campus By James Britt, Elizabeth Erbes, Julie Rosin and Bill Good Central Campus... evolving as a 21st century educational environment... connecting students

More information

Request for Proposal for Construction Management Services

Request for Proposal for Construction Management Services Willmar Public Schools- ISD 347 611 5 th Street SW Willmar MN 56201 Dr. Jeffrey Holm, Superintendent Request for Proposal for Construction Management Services Willmar Public Schools is soliciting Construction

More information

Capital Projects Town Hall Meeting

Capital Projects Town Hall Meeting Capital Projects Town Hall Meeting Planning, Architectural & Engineering Services September 15, 2014 Agenda Project Updates Recently Completed and in Construction Projects in Design Projects in Planning

More information

November 3, 2015 Bond and District Additional Assistance Election Information

November 3, 2015 Bond and District Additional Assistance Election Information November 3, 2015 Bond and District Additional Assistance Election Information Proposition 432 - $22 million General Obligation Bond 150+ facility projects across all schools Building renovations and improvements

More information

Wenatchee Valley College Music and Arts Center Wenatchee, Washington 27, 696 SF

Wenatchee Valley College Music and Arts Center Wenatchee, Washington 27, 696 SF Wenatchee Valley College Music and Arts Center Wenatchee, Washington 27, 696 SF The MAC is a shared facility for the Music and Art programs, providing much-needed studio space for Art, and state-of-the-art,

More information

QUALIFIED SCHOOL CONSTRUCTION BONDS (QSCB) FIRST YEAR REVIEW

QUALIFIED SCHOOL CONSTRUCTION BONDS (QSCB) FIRST YEAR REVIEW QUALIFIED SCHOOL CONSTRUCTION BONDS (QSCB) FIRST YEAR REVIEW Slide 2: Quick Update Slides 3-4: Project Timeline Slides 5-19: Project Photographs Slides 20-29: Roof Photographs Slides 30-32: Budget Summary

More information

North East Independent School District 2011 Bond Proposal

North East Independent School District 2011 Bond Proposal North East Independent School District 2011 Bond Proposal North East ISD Garrett J. Sullivan, Executive Director Construction Management & Engineering Department The Process Community Planning and Advisory

More information

2006 Bond. 2011 Bond. 11/12/2015 2015 Bond Timeline Report to Board of Trustees November 17, 2015

2006 Bond. 2011 Bond. 11/12/2015 2015 Bond Timeline Report to Board of Trustees November 17, 2015 2015 Bond Timeline Report to Board of Trustees November 17, 2015 2006 Bond $875k allocated to parking lot improvements on Shriner property Projects to be completed August 2016 Completes 2006 bond program

More information

High School Bond Budget Summary Sheet

High School Bond Budget Summary Sheet High School Bond Budget Summary Sheet Additional Funding Sources High School Budget Data Proposed Adjustments Potential Future Additions Bond Program Inf. Reserve Bond Program Contingency Other Comments

More information

CONSTRUCTION UPDATE. Thank you for your continued support! Noemi Avila-Zamudio Coordinator, Facilities Planning & Construction SEPTEMBER 2012

CONSTRUCTION UPDATE. Thank you for your continued support! Noemi Avila-Zamudio Coordinator, Facilities Planning & Construction SEPTEMBER 2012 CONSTRUCTION UPDATE WWW.SVUSD.ORG SEPTEMBER 2012 The 2012-2013 school year is proving to be another year filled with exciting, much needed Measure B building projects. Facilities Planning & Construction

More information

STICKLEY AUDITORIUM RENOVATION Community and Stakeholder Presentation

STICKLEY AUDITORIUM RENOVATION Community and Stakeholder Presentation STICKLEY AUDITORIUM RENOVATION Community and Stakeholder Presentation APRIL 30, 2014 SCHEMATIC DESIGN PROGRESS Code Study Analysis: key issues and resolutions Seating Analysis of sightlines, seating and

More information

INDIVIDUAL CAMPUS PLAN ASSESSMENT. No. of Non- Non-Instructional Area. Size Sq. Ft.

INDIVIDUAL CAMPUS PLAN ASSESSMENT. No. of Non- Non-Instructional Area. Size Sq. Ft. ED. SPEC. ELEMENTARY SCHOOL SPACE BUDGET Program Menchaca ES Page 1 of 6 INDIVIDUAL CAMPUS PLAN ASSESSMENT al s Non- al s Size Pre-Kindergarten / Kindergarten - Classrooms 8 8 925 7,400 (minimum or 25

More information

REQUEST FOR PROPOSALS

REQUEST FOR PROPOSALS REQUEST FOR PROPOSALS Design Build Services for Information Technology/ Security for Achievement Prep Public Charter School - Wahler Campus Redevelopment Project Issued: Friday, December 19 th, 2014 IMPORTANT

More information

Prepared for Massachusetts School Building Authority

Prepared for Massachusetts School Building Authority Prepared for Massachusetts School Building Authority 1 TURNER CONSTRUCTION COMPANY Firm Name: Turner Construction Company Principle Office: 375 Hudson Street New York, NY 10014 Contact Office: 2 Seaport

More information

Architecture for K-12 Clients

Architecture for K-12 Clients Architecture for K-12 Clients Chaminade College Prep Master Plan and Multiple Projects, Chaminade has retained the services of Hastings+Chivetta for more than three decades, beginning in the early 1970s.

More information

FREQUENTLY ASKED QUESTIONS

FREQUENTLY ASKED QUESTIONS FREQUENTLY ASKED QUESTIONS TORNADO REFUGE AREAS IN EXISTING INDIANA K-12 SCHOOLS This is intended to be a resource for school safety This is intended to be a helpful resource available to specialists and

More information

SQUARE FOOTAGE REQUIREMENTS FOR USE IN DEVELOPING THE LOCAL FACILITIES PLANS AND STATE CAPITAL OUTLAY APPLICATIONS FOR FUNDING

SQUARE FOOTAGE REQUIREMENTS FOR USE IN DEVELOPING THE LOCAL FACILITIES PLANS AND STATE CAPITAL OUTLAY APPLICATIONS FOR FUNDING SQUARE FOOTAGE REQUIREMENTS FOR USE IN DEVELOPING THE LOCAL FACILITIES PLANS AND STATE CAPITAL OUTLAY APPLICATIONS FOR FUNDING GEORGIA DEPARTMENT OF EDUCATION FACILITIES SERVICES UNIT December 8, 2003

More information

DAVIESS COUNTY SCHOOLS DISTRICT FACILITIES PLAN

DAVIESS COUNTY SCHOOLS DISTRICT FACILITIES PLAN DISTRICT "SHELL" SUBMISSION DATE: 11/13/12 questions 11/26/12 (delete following Hearing) KDE "SHELL" RESUBMISSION DATE: 11/19/12 revised 11/26/12 (delete following Hearing) KBE APPROVAL DATE: FEBRUARY

More information

PARKVILLE HIGH SCHOOL LIMITED RENOVATION

PARKVILLE HIGH SCHOOL LIMITED RENOVATION PARKVILLE HIGH SCHOOL LIMITED RENOVATION DESIGN BRIEFING For Dr. Joe A. Hairston BALTIMORE COUNTY PUBLIC SCHOOLS August 11, 2009 Smolen 3 Emr + Associates Architects 1355 Piccard Drive, Suite 200 Rockville,

More information

Division / Space Total SF Status

Division / Space Total SF Status Minnesota State Capitol - Interior Restoration Program of Requirements August 8, 2006 Division / Space Total SF Status 1 Attorney General's Executive Offices 5,330 Interview complete / Edits returned to

More information

TAMPA S UNIVERSITY MALL ANNOUNCES MAJOR REDEVELOPMENT PLANS. Construction is slated to begin as soon as first quarter 2016

TAMPA S UNIVERSITY MALL ANNOUNCES MAJOR REDEVELOPMENT PLANS. Construction is slated to begin as soon as first quarter 2016 PRESS RELEASE FOR IMMEDIATE RELEASE Contact: Elizabeth Cross Daniel Jimenez +1 305 428 6373 +407.839.3191 elizabeth.cross@cbre.com danieljimenez@cbre.com TAMPA S UNIVERSITY MALL ANNOUNCES MAJOR REDEVELOPMENT

More information

BOARD OF EDUCATION Attachment: Discussion 10. PALO ALTO UNIFIED SCHOOL DISTRICT Date: 01.26.16

BOARD OF EDUCATION Attachment: Discussion 10. PALO ALTO UNIFIED SCHOOL DISTRICT Date: 01.26.16 BOARD OF EDUCATION Attachment: Discussion 10 PALO ALTO UNIFIED SCHOOL DISTRICT Date: 01.26.16 TO: FROM: SUBJECT: Glenn Max McGee, Superintendent Bob Golton, Bond Program Manager Submittal of Plans to Division

More information

BUILD NYC RESOURCE CORPORATION PROJECT COST/BENEFIT ANALYSIS January 7, 2016

BUILD NYC RESOURCE CORPORATION PROJECT COST/BENEFIT ANALYSIS January 7, 2016 BUILD NYC RESOURCE CORPORATION PROJECT COST/BENEFIT ANALYSIS January 7, 2016 APPLICANT The Chapin School, Ltd. 100 East End Avenue New York, New York 10028 PROJECT LOCATION 100 East End Avenue New York,

More information

Schools Under Construction for N.I.S.D.

Schools Under Construction for N.I.S.D. October 2009 NORTHSIDE INDEPENDENT SCHOOL DISTRICT Schools Under Construction for N.I.S.D. Facilities Construction Vernon Dunagin, AIA Assist. Superintendent of Facilities & Operations Leroy San Miguel

More information

Planning a Soundproof Performance Building Within Budget. Education Session #5, Track 3 October 06, 2015, 11:15 AM 12:15 PM

Planning a Soundproof Performance Building Within Budget. Education Session #5, Track 3 October 06, 2015, 11:15 AM 12:15 PM Planning a Soundproof Performance Building Within Budget Education Session #5, Track 3 October 06, 2015, 11:15 AM 12:15 PM Presenters Eric Norman VP of Finance & Planning The Boston Conservatory Mimi Love

More information

Once you see it, you get it! A quick overview of projects..

Once you see it, you get it! A quick overview of projects.. Once you see it, you get it! A quick overview of projects.. Bank of Arizona, Scottsdale We re used to building in 22 months; Modular Technology built our 3 branches in just 5 months! Their quality is superior

More information

Those tables are provided at the end of this section in the following order.

Those tables are provided at the end of this section in the following order. T e c h n i c a l M e m o r a n d u m Date Project Subject From To October 2008 Tennessee State University Campus Master Plan 4. Future Campus Requirements Paulien & Associates, Inc Tennessee State University

More information

ADDENDUM NUMBER 1 February 27, 2015 JAMES CITY COUNTY REQUEST FOR PROPOSAL # 15-6921 Architectural Services for New Middle School Facility

ADDENDUM NUMBER 1 February 27, 2015 JAMES CITY COUNTY REQUEST FOR PROPOSAL # 15-6921 Architectural Services for New Middle School Facility ADDENDUM NUMBER 1 February 27, 2015 JAMES CITY COUNTY REQUEST FOR PROPOSAL # 15-6921 Architectural Services for New Middle School Facility This Addendum is forwarded to provide answers to offerors questions,

More information

Higher Education Projects University of Illinois at Urbana-Champaign Gorski Reifsteck

Higher Education Projects University of Illinois at Urbana-Champaign Gorski Reifsteck Laboratories Bevier Hall Food Labs Renovation College of ACES Everitt Lab 4th Floor Remodel - Phase I Renovation College of Engineering MATSE Kiln House Renovation Phase I College of Engineering MATSE

More information

MURCH ELEMENTARY SCHOOL

MURCH ELEMENTARY SCHOOL INITIAL YEAR BUILT 1929 BUILDING AREA 47,700 SF CURRENT PROGRAM CAPACITY 479 ENROLLMENT 2008 491 WARD 3 PROPOSED PROGRAM CAPACITY 500 Site Plan MURCH - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5

More information

A001.01. Project Description/Project Title and Data: Building Area: (sf) Addition 28,142 Renovation 14,302. Cost per Square Foot: +/- $106.

A001.01. Project Description/Project Title and Data: Building Area: (sf) Addition 28,142 Renovation 14,302. Cost per Square Foot: +/- $106. Project Description/Project Title and Data: KEVIN I. SULLIVAN CAMPUS CENTER ADDITION & RENOVATION Medaille College - Buffalo, NY Functioning as Medaille College's campus heart, The Kevin I Sullivan Campus

More information

Intertribal Education and Community Center

Intertribal Education and Community Center 106 108B 108A 110 114 107 112 111 109 116 116A 120AB 115 118 120A 120B 120 120C 119 122 120D 120E 120P 121 120F 120N 120G 123 120M 120H 120L 120I 124 120J 120K 125 105 125A Intertribal Education and Community

More information

SOUTH DAKOTA BOARD OF REGENTS. Committee on Budget and Finance ******************************************************************************

SOUTH DAKOTA BOARD OF REGENTS. Committee on Budget and Finance ****************************************************************************** SOUTH DAKOTA BOARD OF REGENTS Committee on Budget and Finance AGENDA ITEM: III G DATE: October 9-10, 2013 ****************************************************************************** SUBJECT: South Dakota

More information

How To Help Your School With A Health Care Program

How To Help Your School With A Health Care Program Metropolitan Learning Center School Services MLC provides services to support the development of the whole child. In addition to academic services, MLC provides a full service guidance, counseling and

More information

SAN DIEGO CITY SCHOOLS Institute for Learning Instructional Facilities Planning Department

SAN DIEGO CITY SCHOOLS Institute for Learning Instructional Facilities Planning Department SAN DIEGO CITY SCHOOLS Institute for Learning Instructional Facilities Planning Department RELOCATION OF THE CREATIVE, PERFORMING AND MEDIA ARTS MAGNET SCHOOL FROM FREMONT TO THE MACDOWELL CAMPUS January

More information

Agriculture & Business Multipurpose Classroom Building Prairie View A&M University. 100% Design Development Review Meeting.

Agriculture & Business Multipurpose Classroom Building Prairie View A&M University. 100% Design Development Review Meeting. OVERLAND PARTNERS ARCHITECTS Agriculture & Business Multipurpose Classroom Building Prairie View A&M University 100% Design Development Review Meeting May 22, 2013 AGENDA 10:00 10:15 Introductions / Outline

More information

The work has continued on final Phase 4 and is nearing completion.

The work has continued on final Phase 4 and is nearing completion. Updates-January 22, 2013 29369-Rehab Plaza Deck/Drainage Budget: $18,000,000, constr. Start 8/2009 The work has continued on final Phase 4 and is nearing completion. The main plaza area of phase 4 is now

More information

IMAGINE INDIANA LIFE SCIENCES ACADEMY WEST

IMAGINE INDIANA LIFE SCIENCES ACADEMY WEST 2.21.107 Introduction Imagine Indiana Life Sciences Academy West (Imagine ILSA West) is a charter elementary and middle school located on the west side of Indianapolis, Indiana. The school is the second

More information

ORANGE UNIFIED SCHOOL DISTRICT SCHOOL FACILITIES MASTER PLAN NEEDS ASSESSMENT

ORANGE UNIFIED SCHOOL DISTRICT SCHOOL FACILITIES MASTER PLAN NEEDS ASSESSMENT 1. SAFETY, HEALTH, CODE 1.1 Structural Requirements, Seismic Stability 1.1.1 Primary Structure 1.1.2 Ceilings 1.1.3 Cabinets, Equipment 1.1.4 Portables 1.2 Fire / Life Safety 1.2.1 Corridor, Separation

More information

FIRE EXTINGUISHER DORM #1 SYMPHONY

FIRE EXTINGUISHER DORM #1 SYMPHONY FIRE EXTINGUISHER DORM #1 SYMPHONY 101 ABC (Dry Chem) Basement (Downbeat Café Pool Tables) 102 ABC (Dry Chem) Hall Men s room (Downbeat Café) 103 ABC (Dry Chem) Hallway across chiller (Downbeat Café) 104

More information

1. PROJECT DESCRIPTIONS.

1. PROJECT DESCRIPTIONS. SAN ELIZARIO INDEPENDENT SCHOOL DISTRICT REQUEST FOR PROPOSALS FOR FOR CONSTRUCTION MANAGER AT RISK FOR NEW FIELDHOUSE AND STEM BUILDING ADDITION AT SAN ELIZARIO HIGH SCHOOL AND NEW SUPPORT SERVICES BUILDING

More information

The Hills at Southampton MUPDD Application Draft EIS APPENDIX B BUILDING ARCHITECTURE-RELATED DOCUMENTS

The Hills at Southampton MUPDD Application Draft EIS APPENDIX B BUILDING ARCHITECTURE-RELATED DOCUMENTS The Hills at Southampton MUPDD Application Draft EIS APPENDIX B BUILDING ARCHITECTURE-RELATED DOCUMENTS Appendix B-1 Clubhouse Floor Plans & Renderings The Hills at Southampton MUPDD Application Draft

More information

A Closer Look at the CMS Bond Request

A Closer Look at the CMS Bond Request Charlotte-Mecklenburg Schools 2013 Bond Referendum Our Children. Our Schools. Our Future. A Closer Look at the CMS Bond Request On Nov. 5, Mecklenburg County voters will decide on a $290 million bond referendum

More information

ALBUQUERQUE PUBLIC SCHOOLS Facility Design & Construction / Maintenance & Operations

ALBUQUERQUE PUBLIC SCHOOLS Facility Design & Construction / Maintenance & Operations ALBUQUERQUE PUBLIC SCHOOLS Facility Design & Construction / Maintenance & Operations MECHANICAL SYSTEMS DESIGN STANDARDS Appendix A RECOMMENDED HVAC SYSTEMS BY TYPE OF SPACE Matt Higgins Valentin Lucero

More information

BUILDING DATA. Facility Assessment Report, Garland Independent School District 3. Williams Stadium (Facility #913)

BUILDING DATA. Facility Assessment Report, Garland Independent School District 3. Williams Stadium (Facility #913) WILLIAMS STADIUM BUILDING DATA WILLIAMS STADIUM 510 Stadium Dr., Garland, TX 75040 Facility # 913 Year Built No. of Buildings No. of Portables 0 Approx. Total Square Footage Approx. Capacity Building

More information

Students were surveyed by Brailsford & Dunlavey in the fall of 2000 to determine their priorities for Commons program spaces.

Students were surveyed by Brailsford & Dunlavey in the fall of 2000 to determine their priorities for Commons program spaces. I-1 2.0 INTRODUCTION 2.1 BACKGROUND Located in the rapidly growing Inland Empire area of Southern California (Riverside and San Bernardino Counties), the University of California, Riverside is well positioned

More information

A Self-Audit of Your Current Campus Security Systems

A Self-Audit of Your Current Campus Security Systems A Self-Audit of Your Current Campus Security Systems Security Solutions for Education, Business & Public Safety Free Consultations on ID Card Systems, Access Control, Call Recording, Video Surveillance,

More information

FINE & PERFORMING ARTS CENTER LARAMIE COUNTY COMMUNITY COLLEGE

FINE & PERFORMING ARTS CENTER LARAMIE COUNTY COMMUNITY COLLEGE LEVEL ONE RECONNAISSANCE SUBMITTAL FINE & PERFORMING ARTS CENTER LARAMIE COUNTY COMMUNITY COLLEGE MAY 1, 2015 ARCHITECTS AND DESIGNERS May 1, 2015 Mr. Tim Macnamara, Director Physical Plan Laramie County

More information

Off white sheetrock May 07 no asbestos found. Bralley Annex sheetrock office/room 106 May 07 removed pipe insulation mechanical room Mar 05 removed

Off white sheetrock May 07 no asbestos found. Bralley Annex sheetrock office/room 106 May 07 removed pipe insulation mechanical room Mar 05 removed Buildings and Building Materials Locations of Building Materials Report Date Status ACT/Admisions Building sheet rock hallways and stairwells Oct 02 removed ceiling texture 2nd and 6th floor men's restrooms,

More information

HOUSTON ELEMENTARY SCHOOL

HOUSTON ELEMENTARY SCHOOL INITIAL YEAR BUILT 1962 BUILDING AREA 59,900 SF CURRENT PROGRAM CAPACITY 507 ENROLLMENT 2008 291 WARD 7 PROPOSED PROGRAM CAPACITY 325 Site Plan HOUSTON - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

CAMPUS HIGH SCHOOL ADDITION AND RENOVATION

CAMPUS HIGH SCHOOL ADDITION AND RENOVATION LEGEND RENOVATION ADDITION DRIVE IMPROVEMENTS WIDEN BUS LOOP ROAD TO WEST PROVIDE SECURE ADMINISTRATION ENTRANCE REPLACE AGING ELECTRICAL PANELS RENOVATE SPACE FOR FIVE (5) SCIENCE CLASSROOMS CONVERT EXISTING

More information

HAMILTON SCHOOL. 1401 Brentwood Parkway, N.E., Washington, DC INITIAL YEAR BUILT 1968 BUILDING AREA

HAMILTON SCHOOL. 1401 Brentwood Parkway, N.E., Washington, DC INITIAL YEAR BUILT 1968 BUILDING AREA INITIAL YEAR BUILT 1968 BUILDING AREA 187,700 SF CURRENT PROGRAM CAPACITY N/A ENROLLMENT 2008 129 WARD 5 PROPOSED PROGRAM CAPACITY N/A Site Plan HAMILTON - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

District Information

District Information Bond 2010 District Information 95.5% College Bound 2009 College Readiness Award from Texas ACT Council #1 Ranked Traditional High School in San Antonio by Children at Risk 458 AP test takers/ 875 tests

More information

PLUMMER ELEMENTARY SCHOOL

PLUMMER ELEMENTARY SCHOOL INITIAL YEAR BUILT 1959 BUILDING AREA 69,400 SF CURRENT PROGRAM CAPACITY 481 ENROLLMENT 2008 228 WARD 7 PROPOSED PROGRAM CAPACITY 325 Site Plan PLUMMER - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

COMPREHENSIVE FACILITIES MASTER PLANNING. Presented By: Kevin A. MacQuarrie, Principal

COMPREHENSIVE FACILITIES MASTER PLANNING. Presented By: Kevin A. MacQuarrie, Principal COMPREHENSIVE FACILITIES MASTER PLANNING Presented By: Kevin A. MacQuarrie, Principal STRATEGIC GOALS AND VISION Student Achievement Safe Schools Communication Budget Project Creek Watch Math Team Health

More information

V I S I O N 2 0 2 0 REV. 1

V I S I O N 2 0 2 0 REV. 1 V I S I O N 2 0 2 0 F A C I L I T I E S M A S T E R P L A N COAST COMMUNITY COLLEGE DISTRICT : CAMBRIDGE WEST PARTNERSHIP LLC : HPI ARCHITECTURE REV. 1 J u l y 2 0 1 5 T a b l e o f C o n t e n t s GOLDEN

More information

Heritage Foundation of Newfoundland and Labrador Building Report St. Bride s College, Littledale

Heritage Foundation of Newfoundland and Labrador Building Report St. Bride s College, Littledale Heritage Foundation of Newfoundland and Labrador Building Report St. Bride s College, Littledale Artist s concept of St. Bride s College, Littledale, 220 Waterford Bridge Road, 1965 Researcher: Deborah

More information