HAZELWOOD HIGH SCHOOLS SCHEMATIC DESIGN PRESENTATION

Size: px
Start display at page:

Download "HAZELWOOD HIGH SCHOOLS SCHEMATIC DESIGN PRESENTATION"

Transcription

1 HAZELWOOD HIGH SCHOOLS SCHEMATIC DESIGN PRESENTATION 1

2 AGENDA Hazelwood 1 st Planning Process High School Program Schematic Designs Schedule 2

3 HAZELWOOD 1 ST GOALS Life, health and safety improvements Improving wiring for up-to-date technology Updating heating and air conditions systems Modernizing science labs and classrooms Replacing hazardous floor tile Replace chalk boards with marker boards New or expanded libraries Providing elevators to improve access 3

4 PLANNING PROCESS Prepared Classroom Utilization Analysis Identified areas for facility improvement Science consultant: Tours Workshops Design Guidelines Education specifications review by Learning Facilitators and teachers of: Science, Technology, Engineering & Mathematics (STEM) Library 4

5 PLANNING PROCESS Meetings with Executive Management Team Meetings with High School Management Team Conceptual Design reviewed by Learning Leadership Team Schematic Design Package 5

6 HSD S.T.E.M. / SCIENCE COMMITTEE Joni Pukala Cindy Bober Brett Barron Jim Wright Matt McClellan Christina Hughes Jim Patterson Kevin Fischer Jennifer Bolla Cheryol Mitchell Jacqueline Kelly Kashina Bell Gail Stewart Carrie Launius Cathy French Darrell Strong Tom Mangogna Dwight Lindhorst 6

7 HIGH SCHOOL PROGRAM Science Technology Engineering & Math (S.T.E.M.) Studios Science (Physics, Chemistry, Biology) Project Lead The Way (PLTW) Health Occupations Industrial Technology Robotics design and storage spaces 7

8 HIGH SCHOOL PROGRAM Student Services Reconfigured main office to enhance public access and consolidate functions Relocated satellite administrative areas to improve building supervision Improved access to guidance counselors Upgrade nurse area Distribute teacher workrooms 8

9 HIGH SCHOOL PROGRAM Special School District (SSD) Life skills General classrooms Support spaces Individual education program / testing room Changing room 9

10 HIGH SCHOOL PROJECTS Building additions and major renovations (Varies per site) Library STEM Studios & Science Labs Various classrooms Student services General improvements Replace chalk boards with marker boards Upgrade classroom power and data infrastructure Repaint hallway lockers Extensive repainting of school Heating and air conditioning upgrades 10

11 HIGH SCHOOL PROJECTS Enhance Safety Security vestibule (adjacent to administration) Controlled after hour access Fire alarm modernization Replace hazardous floor tile New interior signage Accessibility improvements Additional elevators Fine arts at East HS and West HS Locker room Pool 11

12 HAZELWOOD WEST HIGH SCHOOL SCHEMATIC DESIGN 12

13 SCOPE OF WORK Hazelwood West High School 53,000 SF building addition (1 & 3 story) 100,000 SF major building renovation Other project features: New entrance/front image New, centralized main stair Food service circulation/commons upgrade Staff restrooms on each level 13

14 SCHEMATIC DESIGN Major Renovations (In Color) New Addition New Elevator for Visual/Performing Arts ENTRY LEVEL (First Floor) Main Entry 14

15 SCHEMATIC DESIGN New Elevator New Central Stair Library Nurse Guidance Main Entry Administration ENTRY LEVEL (First Floor) 15

16 SCHEMATIC DESIGN Athletics Control Points Commons Library Auditorium Main Entry Administration ENTRY LEVEL (First Floor) 16

17 SCHEMATIC DESIGN Teacher Work Room STEM Studio STEM Physics & Chemistry (Renovated & New Addition) Library Commons Upgraded Main Entry SSD ENTRY LEVEL (First Floor) 17

18 SCHEMATIC DESIGN Major Renovations New Addition New Elevator for Visual/Performing Arts SECOND FLOOR Main Entry Below 18

19 SCHEMATIC DESIGN Teacher Work Room New Elevator Instructional & Learning Coach Offices Satellite Administration New Central Stair Journalism (14) New Classrooms SECOND FLOOR 19

20 SCHEMATIC DESIGN Health Occupations STEM Studio STEM Biology (Existing & New) and Biomedical with Forensics Library SECOND FLOOR 20

21 SCHEMATIC DESIGN New Addition LOWER LEVEL 21

22 SCHEMATIC DESIGN Teacher Work Room Student Services (Satellite Administration) STEM Studio STEM Library Physics & Engineering LOWER LEVEL 22

23 SITE IMPACT Existing quantity of parking spaces maintained New entry plaza and entrance 23

24 BUILDING IMAGE Before After 24

25 BUILDING IMAGE (FROM PARKING LOT) Insulated Composite Metal Panels Brick Insulated Glass 25

26 BUILDING IMAGE Before After 26

27 BUILDING IMAGE After 27

28 HAZELWOOD CENTRAL HIGH SCHOOL SCHEMATIC DESIGN 28

29 SCOPE OF WORK Hazelwood Central High School 23,000 SF Science lab addition 60,000 SF Major building renovation Other project features: Linked B, C and D Halls together to improve building safety, security and passing period times Replace folding partitions and accordion walls with permanent walls 29

30 EXISTING FIRST FLOOR 30

31 SCHEMATIC DESIGN FIRST FLOOR 31

32 EXISTING SECOND FLOOR 32

33 SCHEMATIC DESIGN SECOND FLOOR 33

34 SCHEMATIC DESIGN CHS LIBRARY

35 SCHEMATIC DESIGN COURTYARD VIEW BETWEEN C & D HALL

36 SCHEMATIC DESIGN COURTYARD VIEW BETWEEN B & C HALL

37 SCHEMATIC DESIGN VIEW FROM E-HALL, BETWEEN B & C HALL

38 SCHEMATIC DESIGN VIEW FROM E-HALL, BETWEEN C & D HALL

39 HAZELWOOD EAST HIGH SCHOOL SCHEMATIC DESIGN 39

40 SCOPE OF WORK Hazelwood East High School 45,200 SF new building additions Entrances, classrooms, athletics/pe, library & STEM studio 65,400 SF of major renovations Other project features: New entrance/front image Provide sprinklers at students commons area Accessible theater entrance Accessible restrooms at auditorium and gymnasium Dedicated vehicular drop off Drainage repairs 40

41 SCHEMATIC DESIGN NEW MAIN ENTRANCE LIBRARY VESTIBULE AND ELEVAROR ADMINISTRATION NURSE NEW GYM ACCESSIBLE RESTROOMS GYM STORAGE LOCKERS FIRST FLOOR 41

42 SCHEMATIC DESIGN CLASSROOM AND TEACHER WORKROOM HEALTH OCCUPATION CLASSROOM HOME REPAIR & PLTW CLASSROOMS STEM STUDIO AND ROBOTICS STORAGE SECOND FLOOR 42

43 SCHEMATIC DESIGN JOURNALISM GUIDANCE OFFICES & STUDENT CAREER CENTER SPECIAL SCHOOL DISTRICT CLASSROOMS SATELLITE ADMIN. OFFICES SATELLITE ADMIN. OFFICES STEM STUDIOS THIRD FLOOR 43

44 SCHEMATIC DESIGN ACCESSIBLE SWIMMING POOL CHANGING ROOM MULTIPURPOSE ROOMS LOCKERS ATHLETIC STORAGE 44 LOCKER ROOM FLOOR

45 BUILDING IMAGE BEFORE NEW LIBRARY 45

46 BUILDING IMAGE AFTER NEW LIBRARY COMPOSITE METAL PANELS INSULATED GLASS SPLIT FACE BLOCK COMPOSITE METAL PANELS INSULATED GLASS SPLIT FACE BLOCK 46

47 ENTRY PLAZA BEFORE ENTRANCE PLAZA 47

48 ENTRY PLAZA AFTER 48 ENTRANCE PLAZA

49 NEW AUXILIARY GYM BEFORE NEW GYM 49

50 NEW AUXILIARY GYM AFTER COMPOSITE METAL PANELS INSULATED GLASS SPLIT FACE BLOCK NEW GYM 50

51 SITE IMPACT New vehicular dropoff New entry plaza New accessible secondary entrances for theater and gymnasium 51

52 HAZELWOOD HIGH SCHOOLS SCHEMATIC DESIGN SCHEDULE 52

53 SCHEDULE Schematic Design Approval Issue for Permits & Let for Bidding Bids Approved / Begin Construction Construction Complete Hazelwood Central High School Hazelwood East High School Hazelwood West High School Nov Nov Nov Feb Mar Apr Apr Apr May 2012 Summer 2013 Summer 2014 Summer

54 HAZELWOOD HIGH SCHOOLS SCHEMATIC DESIGN PRESENTATION 54

Centinela Valley Union High School District. Measure CV Masterplan Update June 2011

Centinela Valley Union High School District. Measure CV Masterplan Update June 2011 Centinela Valley Union High School District Measure CV Masterplan Update June 2011 Hawthorne High School (Phase 1) Hawthorne High School Phase 1: Science, Engineering, and Media Arts Center (Funded) 3

More information

Mequon - Thiensville School District Long Range Facilities Plan Monthly Project Schedule

Mequon - Thiensville School District Long Range Facilities Plan Monthly Project Schedule Mequon - Thiensville School District Long Range Facilities Plan Monthly Project Schedule Homestead HS Sept.'15 Oct'15 Nov'15 Dec'15 Jan'16 Feb'16 Repair Asphalt @ Main Garage Replace Exterior Hollow Metal

More information

Schematic Design Presentation S. Dallas Dance, Superintendent October 22, 2013 OVERLEA HIGH SCHOOL

Schematic Design Presentation S. Dallas Dance, Superintendent October 22, 2013 OVERLEA HIGH SCHOOL Schematic Design Presentation S. Dallas Dance, Superintendent October 22, 2013 0 Overlea High School - Facility Summary Facility Opened: Auditorium Addition: Activity Room Addition: School Rated Capacity

More information

1/9/2015 P:\130217-03\Project Management\Program\Ripon Space Program - 7 January 2015.xlsx

1/9/2015 P:\130217-03\Project Management\Program\Ripon Space Program - 7 January 2015.xlsx MIDDLE SCHOOL Administration Office Principal's Office 200 1 200 Desk, conference table for 4-6 Conference Room 250 1 250 Conference table for 12 Open Office Area 250 1 250 2 Workstations Mail / copier

More information

SCHEMATIC DESIGN PRESENTATION ACTON ELEMENTARY SCHOOL

SCHEMATIC DESIGN PRESENTATION ACTON ELEMENTARY SCHOOL March 16, 2015 SCHEMATIC DESIGN PRESENTATION ACTON ELEMENTARY SCHOOL DUNCANVILLE INDEPENDENT SCHOOL DISTRICT Acknowledgments 2 Narrative 3 The Process 4 Site Analysis 6 Site Plan 7 ACTON ELEMENTARY SCHOOL

More information

November 3, 2015 Bond and District Additional Assistance Election Information

November 3, 2015 Bond and District Additional Assistance Election Information November 3, 2015 Bond and District Additional Assistance Election Information Proposition 432 - $22 million General Obligation Bond 150+ facility projects across all schools Building renovations and improvements

More information

CALLOWAY COUNTY SCHOOLS DISTRICT FACILITIES PLAN

CALLOWAY COUNTY SCHOOLS DISTRICT FACILITIES PLAN DISTRICT "SHELL" SUBMISSION DATE: 4/17/13 (delete following Hearing) KDE "SHELL" RESUBMISSION DATE: 4/19/13 (delete following Hearing) KBE APPROVAL DATE: JUNE 2013 CALLOWAY COUNTY SCHOOLS DISTRICT FACILITIES

More information

HOUSTON ELEMENTARY SCHOOL

HOUSTON ELEMENTARY SCHOOL INITIAL YEAR BUILT 1962 BUILDING AREA 59,900 SF CURRENT PROGRAM CAPACITY 507 ENROLLMENT 2008 291 WARD 7 PROPOSED PROGRAM CAPACITY 325 Site Plan HOUSTON - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

SCHEMATIC DESIGN PRESENTATION NEW JOSHUA MIDDLE SCHOOL

SCHEMATIC DESIGN PRESENTATION NEW JOSHUA MIDDLE SCHOOL June 15, 2015 SCHEMATIC DESIGN PRESENTATION NEW JOSHUA MIDDLE SCHOOL JOSHUA INDEPENDENT SCHOOL DISTRICT Acknowledgments 2 Narrative 3 The Process 4 Site Analysis 5 Independent School District Site Plan

More information

Frequently Asked Questions

Frequently Asked Questions Byron Area Schools Frequently Asked Questions Bond Proposal How did this come about? For several years the Byron Area Schools Board of Education has included upgrading facilities as one of the district

More information

MURCH ELEMENTARY SCHOOL

MURCH ELEMENTARY SCHOOL INITIAL YEAR BUILT 1929 BUILDING AREA 47,700 SF CURRENT PROGRAM CAPACITY 479 ENROLLMENT 2008 491 WARD 3 PROPOSED PROGRAM CAPACITY 500 Site Plan MURCH - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5

More information

ORANGE UNIFIED SCHOOL DISTRICT SCHOOL FACILITIES MASTER PLAN NEEDS ASSESSMENT

ORANGE UNIFIED SCHOOL DISTRICT SCHOOL FACILITIES MASTER PLAN NEEDS ASSESSMENT 1. SAFETY, HEALTH, CODE 1.1 Structural Requirements, Seismic Stability 1.1.1 Primary Structure 1.1.2 Ceilings 1.1.3 Cabinets, Equipment 1.1.4 Portables 1.2 Fire / Life Safety 1.2.1 Corridor, Separation

More information

PAGE INTENTIONALLY LEFT BLANK

PAGE INTENTIONALLY LEFT BLANK PAGE INTENTIONALLY LEFT BLANK TABLE OF CONTENTS I. Introduction 1 Page II. Documentation of Existing Educational Programs 1 and Instructional Space III. State Square Footage Standards 2 IV. Space Allocation

More information

21 st CENTURY HIGH SCHOOLS

21 st CENTURY HIGH SCHOOLS 21 st CENTURY HIGH SCHOOLS 1 CO-LABS & ACTIVITIES What is a Co-Lab? A collaborative workshop session with stakeholder groups. These sessions were designed to examine opportunities and define parameters

More information

PLUMMER ELEMENTARY SCHOOL

PLUMMER ELEMENTARY SCHOOL INITIAL YEAR BUILT 1959 BUILDING AREA 69,400 SF CURRENT PROGRAM CAPACITY 481 ENROLLMENT 2008 228 WARD 7 PROPOSED PROGRAM CAPACITY 325 Site Plan PLUMMER - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

FIRE EXTINGUISHER DORM #1 SYMPHONY

FIRE EXTINGUISHER DORM #1 SYMPHONY FIRE EXTINGUISHER DORM #1 SYMPHONY 101 ABC (Dry Chem) Basement (Downbeat Café Pool Tables) 102 ABC (Dry Chem) Hall Men s room (Downbeat Café) 103 ABC (Dry Chem) Hallway across chiller (Downbeat Café) 104

More information

BUNKER HILL ELEMENTARY SCHOOL

BUNKER HILL ELEMENTARY SCHOOL INITIAL YEAR BUILT 1970 BUILDING AREA 98,200 SF CURRENT PROGRAM CAPACITY 332 ENROLLMENT 2008 387 WARD 5 PROPOSED PROGRAM CAPACITY 750 Site Plan BUNKER HILL - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

BOARD OF EDUCATION Attachment: Discussion 10. PALO ALTO UNIFIED SCHOOL DISTRICT Date: 01.26.16

BOARD OF EDUCATION Attachment: Discussion 10. PALO ALTO UNIFIED SCHOOL DISTRICT Date: 01.26.16 BOARD OF EDUCATION Attachment: Discussion 10 PALO ALTO UNIFIED SCHOOL DISTRICT Date: 01.26.16 TO: FROM: SUBJECT: Glenn Max McGee, Superintendent Bob Golton, Bond Program Manager Submittal of Plans to Division

More information

DESIGN DEVELOPMENT PRESENTATION

DESIGN DEVELOPMENT PRESENTATION October 26, 2015 DESIGN DEVELOPMENT PRESENTATION NEW SHIRLEY HALL MIDDLE SCHOOL & JOE M. TISON MIDDLE SCHOOL ADDITIONS AND RENOVATION WEATHERFORD INDEPENDENT SCHOOL DISTRICT Acknowledgments 3 Narrative

More information

Items in red were complete 2-22-10. Items in green were complete on 8-2-11. Lined out items are Life Safety Codes.

Items in red were complete 2-22-10. Items in green were complete on 8-2-11. Lined out items are Life Safety Codes. Office of Safe and Orderly Schools Facility Safety Assessment Dennis Meador, School Facilities Supervisor Mark Hobson, School Facilities Supervisor Division of School Building September 18 19, 2007 Items

More information

MEASURE G-2010 EXHIBIT B FULL TEXT BALLOT PROPOSITION OF THE SAN JOSE EVERGREEN COMMUNITY COLLEGE DISTRICT BOND MEASURE ELECTION NOVEMBER 2, 2010

MEASURE G-2010 EXHIBIT B FULL TEXT BALLOT PROPOSITION OF THE SAN JOSE EVERGREEN COMMUNITY COLLEGE DISTRICT BOND MEASURE ELECTION NOVEMBER 2, 2010 MEASURE G-2010 EXHIBIT B FULL TEXT BALLOT PROPOSITION OF THE SAN JOSE EVERGREEN COMMUNITY COLLEGE DISTRICT BOND MEASURE ELECTION NOVEMBER 2, 2010 To better prepare San Jose City College/ Evergreen Valley

More information

Schematic Plan Submittal, 21 November, 2011 Roesling Nakamura Terada Architects

Schematic Plan Submittal, 21 November, 2011 Roesling Nakamura Terada Architects To r r e y P i n e s H i g h S c h o o l M a s t e r P l a n Schematic Plan Submittal, 21 November, 2011 Roesling Nakamura Terada Architects I n t r o d u c t i o n 1.0 INTRODUCTION The vision for the

More information

Cherokee Trail High School 25901 East Arapahoe Road Aurora, Colorado 80016

Cherokee Trail High School 25901 East Arapahoe Road Aurora, Colorado 80016 Cherokee Trail High School 25901 East Arapahoe Road Aurora, Colorado 80016 Year Opened 2003 Current Square Footage 391,000 Site Acreage 86.22 cherokeetrail.cherrycreekschools.org $279,200 Asphalt and concrete

More information

DRAPER ELEMENTARY SCHOOL

DRAPER ELEMENTARY SCHOOL INITIAL YEAR BUILT 1953 BUILDING AREA 54,000 SF CURRENT PROGRAM CAPACITY 250 ENROLLMENT 2008 84 WARD 8 PROPOSED PROGRAM CAPACITY 325 Site Plan DRAPER - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5

More information

SODA SPRINGS JOINT SCHOOL DISTRICT NO. 150 RECOMMENDED REPAIRS, REPLACEMENT, AND ADDITIONS OPINIONS OF PROBABLE COST

SODA SPRINGS JOINT SCHOOL DISTRICT NO. 150 RECOMMENDED REPAIRS, REPLACEMENT, AND ADDITIONS OPINIONS OF PROBABLE COST SODA SPRINGS JOINT SCHOOL DISTRICT NO. 150 RECOMMENDED REPAIRS, REPLACEMENT, AND ADDITIONS OPINIONS OF PROBABLE COST SODA SPRINGS HIGH SCHOOL REPAIRS AND UPGRADES SITE Construction Estimate = $100,000

More information

PATTERSON ELEMENTARY SCHOOL

PATTERSON ELEMENTARY SCHOOL INITIAL YEAR BUILT 1945 BUILDING AREA 78,300 SF CURRENT PROGRAM CAPACITY 368 ENROLLMENT 2008 463 WARD 8 PROPOSED PROGRAM CAPACITY 500 Site Plan PATTERSON - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

HERMANTOWN COMMUNITY SCHOOLS. New High School Addition End of DD Design Review

HERMANTOWN COMMUNITY SCHOOLS. New High School Addition End of DD Design Review HERMANTOWN COMMUNITY SCHOOLS New High School Addition End of DD Design Review SITE AERIAL HIGH SCHOOL ELEMENTARY SCHOOL BUS GARAGES HOCKEY ARENA / DISTRICT OFFICE SITE FORCES EXISTING BUILDING INFORMATION

More information

Article 11. Window Replacement Project Norman E. Day & Col. John Robinson Elementary Schools

Article 11. Window Replacement Project Norman E. Day & Col. John Robinson Elementary Schools Article 11 Window Replacement Project Norman E. Day & Col. John Robinson Elementary Schools MSBA Accelerated Repair Program Program targets replacement of roofs, windows, doors, and boilers Goal is to

More information

Performing Arts Wing. Existing Auditorium. Library. Student Entry. Omni Room Athletics/JROTC. Dance Bus Drop

Performing Arts Wing. Existing Auditorium. Library. Student Entry. Omni Room Athletics/JROTC. Dance Bus Drop Choir Band Performing Arts Wing Arts Courtyard Drama Liberal Arts Wing Team Arts Prefunction Loading Area Team Existing Auditorium Heritage Hall Auditorium Lobby Administration Library Visitor Entry Team

More information

ORANGE UNIFIED SCHOOL DISTRICT SCHOOL FACILITIES MASTER PLAN NEEDS ASSESSMENT

ORANGE UNIFIED SCHOOL DISTRICT SCHOOL FACILITIES MASTER PLAN NEEDS ASSESSMENT 1. SAFETY, HEALTH, CODE 1.1 Structural Requirements, Seismic Stability 1.1.1 Primary Structure 1.1.2 Ceilings 1.1.2 Water damage in many classrooms. Replace tiles. 1.1.3 Cabinets, Equipment 1.1.4 Portables

More information

DAVIESS COUNTY SCHOOLS DISTRICT FACILITIES PLAN

DAVIESS COUNTY SCHOOLS DISTRICT FACILITIES PLAN DISTRICT "SHELL" SUBMISSION DATE: 11/13/12 questions 11/26/12 (delete following Hearing) KDE "SHELL" RESUBMISSION DATE: 11/19/12 revised 11/26/12 (delete following Hearing) KBE APPROVAL DATE: FEBRUARY

More information

Bond Priorities. Repairs and Maintenance. School Safety. Capacity

Bond Priorities. Repairs and Maintenance. School Safety. Capacity Replace old windows, boilers, heating and air conditioning system. Improve accessibility for disabled persons. Keyless entry lock systems, redesign of school entrance, and wireless access throughout building.

More information

HAMILTON SCHOOL. 1401 Brentwood Parkway, N.E., Washington, DC INITIAL YEAR BUILT 1968 BUILDING AREA

HAMILTON SCHOOL. 1401 Brentwood Parkway, N.E., Washington, DC INITIAL YEAR BUILT 1968 BUILDING AREA INITIAL YEAR BUILT 1968 BUILDING AREA 187,700 SF CURRENT PROGRAM CAPACITY N/A ENROLLMENT 2008 129 WARD 5 PROPOSED PROGRAM CAPACITY N/A Site Plan HAMILTON - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

DESIGN DEVELOPMENT PRESENTATION

DESIGN DEVELOPMENT PRESENTATION June 16, 2015 DESIGN DEVELOPMENT PRESENTATION HIGH SCHOOL, JUNIOR HIGH SCHOOL & INTERMEDIATE SCHOOL ADDITIONS & RENOVATIONS KAUFMAN INDEPENDENT SCHOOL DISTRICT Acknowledgments 2 Kaufman HS & Norman JHS

More information

Repair Project for April 7, 2009

Repair Project for April 7, 2009 Repair Project for April 7, 2009 Scope of the Project HVAC Upgrades Roof Replacement Window Replacement/Exterior Openings Science Lab Renovations New Fire Alarm/Electrical AAB (accessibility) Upgrades

More information

Facilities Advisory Committee Recommendations. Presentation to the Administrative Council May 22, 2013

Facilities Advisory Committee Recommendations. Presentation to the Administrative Council May 22, 2013 Facilities Advisory Committee Recommendations Presentation to the Administrative Council May 22, 2013 Harun Biswas (Chair) Kara Mullen Caroline Clower Rasheen Hunter Gid Rowell John Shiffert Cindy Lauer

More information

Public Building Commission of Chicago. Board Meeting August 20, 2013

Public Building Commission of Chicago. Board Meeting August 20, 2013 Public Building Commission of Chicago Board Meeting August 20, 2013 Board Meeting August 20, 2013 Recent Events Enrico Tonti Elementary School Kindergarten Modular Opening August 5, 2013 Board Meeting

More information

Bensalem High School Renovation 2014-2016

Bensalem High School Renovation 2014-2016 Bensalem High School Renovation 2014-2016 Design Problems Inability to close off sections of the building during evening and weekend events. Concerns about the efficiency of staffing and supplying three

More information

NYC Department of Education Building Condition Assessment Survey 2014-2015 2015-02-10 08:37AM 2015-02-23 08:14AM. Description

NYC Department of Education Building Condition Assessment Survey 2014-2015 2015-02-10 08:37AM 2015-02-23 08:14AM. Description School: InspectionId Asset Data Inspection Type Building Assessment Survey 204-205 P.S. 83 - MANHATTAN, 49 EAST 66 STREET, MANHATTAN, NY, 002 Time In Last Edited 352 ELECTRICAL 205-02-0 08:37AM 205-02-23

More information

FRANCIS L. CARDOZO HIGH SCHOOL 1200 CLIFTON STREET NW WASHINGTON, DC 20009

FRANCIS L. CARDOZO HIGH SCHOOL 1200 CLIFTON STREET NW WASHINGTON, DC 20009 FRANCIS L. CARDOZO HIGH SCHOOL 1200 CLIFTON STREET NW WASHINGTON, DC 20009 FRANCIS L. CARDOZO HIGH SCHOOL SCHOOL HISTORY Francis L. Cardozo High School, located at 1200 Clifton Street and bounded by Florida

More information

NYC Department of Education Building Condition Assessment Survey 2014-2015 P.S. 64 (OLD 71) - MANHATTAN, 600 EAST 6 STREET, MANHATTAN, NY, 10009

NYC Department of Education Building Condition Assessment Survey 2014-2015 P.S. 64 (OLD 71) - MANHATTAN, 600 EAST 6 STREET, MANHATTAN, NY, 10009 School: InspectionId Asset Data Inspection Type Building Assessment Survey 204-205 P.S. 64 (OLD 7) - MANHATTAN, 600 EAST 6 STREET, MANHATTAN, NY, 0009 Time In Last Edited 095 ELECTRICAL 205-0-6 08:45AM

More information

NYC Department of Education Building Condition Assessment Survey 2014-2015 2014-12-12 08:48AM 2014-12-17 10:39AM. Description Mechanical Room Basement

NYC Department of Education Building Condition Assessment Survey 2014-2015 2014-12-12 08:48AM 2014-12-17 10:39AM. Description Mechanical Room Basement School: InspectionId Asset Data Inspection Type Building Assessment Survey 204-205 P.S. 86 - BRONX, 2756 RESERVOIR AVENUE, BRONX, NY, 0468 Time In Last Edited 0677 ELECTRICAL 204-2-2 08:48AM 204-2-7 0:39AM

More information

Board of Regents Meeting June 16-17, 2005 Agenda Item #11 Arizona State University EXECUTIVE SUMMARY Page 1 of 5

Board of Regents Meeting June 16-17, 2005 Agenda Item #11 Arizona State University EXECUTIVE SUMMARY Page 1 of 5 EXECUTIVE SUMMARY Page 1 of 5 ACTION ITEM: Academic Renovations and Deferred Maintenance Phase I, Revised Revised Project Implementation Approval, (ASU). ISSUE: ASU requests Revised Revised Project Implementation

More information

NORTH PENN HIGH SCHOOL RENOVATIONS

NORTH PENN HIGH SCHOOL RENOVATIONS NORTH PENN HIGH SCHOOL RENOVTIONS PRELIMINRY SCOPE, BUDGET & PHSING CONSIDERTIONS 401 EST HNCOCK STREET LNSDLE, P 19446 PREPRED BY BONNETT SSOCITES INCORPORTED 220 BLDWIN TOWER, 1510 CHESTER PIKE EDDYSTONE,

More information

BUILD NYC RESOURCE CORPORATION PROJECT COST/BENEFIT ANALYSIS January 7, 2016

BUILD NYC RESOURCE CORPORATION PROJECT COST/BENEFIT ANALYSIS January 7, 2016 BUILD NYC RESOURCE CORPORATION PROJECT COST/BENEFIT ANALYSIS January 7, 2016 APPLICANT The Chapin School, Ltd. 100 East End Avenue New York, New York 10028 PROJECT LOCATION 100 East End Avenue New York,

More information

Policy on Repair and Renovation Funding

Policy on Repair and Renovation Funding Policy on Repair and Renovation Funding I. POLICY STATEMENT Auburn University s (the University s) Policy on Repair and Renovation Funding provides guidance and direction regarding the use of Repair and

More information

Five-Year Capital Plan Request FY 2015-16 through FY 2019-20

Five-Year Capital Plan Request FY 2015-16 through FY 2019-20 Section Contents Five-Year Capital Plan Request FY 2015-16 through FY 2019-20 Project Funding Type Total ($ 000s) Critical Maintenance for Community Colleges bonded $417,500 Health and Safety bonded $91,088

More information

Scituate Public Facilities Master Plan Final Report to the Board of Selectmen

Scituate Public Facilities Master Plan Final Report to the Board of Selectmen Scituate Public Facilities Master Plan Final Report to the Board of Selectmen Assessment and Recommendations November 18, 2014 by Scituate Public Facilities Master Planning Committee AGENDA Objectives

More information

New Jersey City University Gilligan Student Union Center

New Jersey City University Gilligan Student Union Center New Jersey City University Gilligan Student Union Center The RBA Group worked with New Jersey City University in a major renovation of their Gilligan Student Union building. We were contracted to reassess,

More information

Board Seminar Facilities. School Year 2012-2013. Submitted by Joseph L. Lisa-Director of Facilities

Board Seminar Facilities. School Year 2012-2013. Submitted by Joseph L. Lisa-Director of Facilities Board Seminar Facilities School Year 2012-2013 Submitted by Joseph L. Lisa-Director of Facilities High School Installed new fence for Pre-K activities by weight room. Installed new rails and side walks

More information

Building Condition Assessment Report

Building Condition Assessment Report C2 - Nurses Resident (aka Administration) Building Condition Assessment Report Asset Address Address Construction Year Size (Gross Floor Area) Asset Type Floors Above Ground Inspection Date C2 - Nurses

More information

Chicago Public Schools

Chicago Public Schools Ames Middle School 1920 N Hamlin Ave 1997 Completed The scope of this project is to construct a new school $16,913,379 2014 Construction The intent of this project is to expand existing Ames middle school

More information

Regular Public Meeting-Study Session June 23, 2011

Regular Public Meeting-Study Session June 23, 2011 Regular Public Meeting-Study Session June 23, 2011 Dr. Ruth Ann Marston presided over the PESD No. 1 Governing Board Meeting in the Phoenix Elementary School District Governing Board Room Other Board Members

More information

SCHEMATIC DESIGN PRESENTATION

SCHEMATIC DESIGN PRESENTATION April 13, 2015 SCHEMATIC DESIGN PRESENTATION HIGH SCHOOL, JUNIOR HIGH SCHOOL & INTERMEDIATE SCHOOL ADDITIONS & RENOVATIONS KAUFMAN INDEPENDENT SCHOOL DISTRICT Kaufman ISD Dr. Lori Blaylock Superintendent

More information

Designing a Facility: Making It a Place Where Every Student Succeeds

Designing a Facility: Making It a Place Where Every Student Succeeds American Association of School Librarians 12th National Conference and Exhibition October 6-9, 2005 Pittsburgh, Pennsylvania Designing a Facility: Making It a Place Where Every Student Succeeds Gail Formanack

More information

Building Description Project Description Estimated Cost Notes Total Deferred

Building Description Project Description Estimated Cost Notes Total Deferred Building Description Project Description Estimated Cost Notes Total Deferred Athletic Fields & Grounds Baseball dugouts 125,000 Surface level/inground? Relamp Baseball field 16,000 Relamp Softball field

More information

CONSTRUCTION UPDATE November 6, 2015

CONSTRUCTION UPDATE November 6, 2015 CONSTRUCTION UPDATE November 6, 2015 Donaldsonville High School Athletic Addition East Ascension High School Athletic Addition St. Amant High School Athletic Addition St. Amant High School Freshman Academy

More information

PUBLIC BUILDING COMMISSION OF CHICAGO. Alexander Graham Bell Elementary School Addition and Renovation

PUBLIC BUILDING COMMISSION OF CHICAGO. Alexander Graham Bell Elementary School Addition and Renovation WELCOME SANDRA CAUDILL, PRINCIPAL, ALEXANDER GRAHAM BELL ELEMENTARY SCHOOL CRAIG BENES, CHIEF OF SCHOOLS, RAVENSWOOD RIDGE NETWORK REMARKS AMEYA PAWAR, 47 th WARD ALDERMAN, CITY OF CHICAGO PBC PRESENTATION

More information

A001.01. Project Description/Project Title and Data: Building Area: (sf) Addition 28,142 Renovation 14,302. Cost per Square Foot: +/- $106.

A001.01. Project Description/Project Title and Data: Building Area: (sf) Addition 28,142 Renovation 14,302. Cost per Square Foot: +/- $106. Project Description/Project Title and Data: KEVIN I. SULLIVAN CAMPUS CENTER ADDITION & RENOVATION Medaille College - Buffalo, NY Functioning as Medaille College's campus heart, The Kevin I Sullivan Campus

More information

PARKVILLE HIGH SCHOOL LIMITED RENOVATION

PARKVILLE HIGH SCHOOL LIMITED RENOVATION PARKVILLE HIGH SCHOOL LIMITED RENOVATION DESIGN BRIEFING For Dr. Joe A. Hairston BALTIMORE COUNTY PUBLIC SCHOOLS August 11, 2009 Smolen 3 Emr + Associates Architects 1355 Piccard Drive, Suite 200 Rockville,

More information

QUALIFIED SCHOOL CONSTRUCTION BONDS (QSCB) FIRST YEAR REVIEW

QUALIFIED SCHOOL CONSTRUCTION BONDS (QSCB) FIRST YEAR REVIEW QUALIFIED SCHOOL CONSTRUCTION BONDS (QSCB) FIRST YEAR REVIEW Slide 2: Quick Update Slides 3-4: Project Timeline Slides 5-19: Project Photographs Slides 20-29: Roof Photographs Slides 30-32: Budget Summary

More information

Education, Entrepreneurship & Urban Revitalization

Education, Entrepreneurship & Urban Revitalization Education, Entrepreneurship & Urban Revitalization Over-The-Rhine Architecture, Urban Planning, and Economics students worked with Public school administrators to envision a new Entrepreneurial and a revitalized

More information

RSU 21 Board of Directors considering major renovation projects

RSU 21 Board of Directors considering major renovation projects RSU 21 Board of Directors considering major renovation projects On Monday, September 16, the RSU 21 Board reviewed proposals to renovate three schools within the district: Kennebunk High School, Mildred

More information

SELECTED SPECIAL EVENTS PROJECTS

SELECTED SPECIAL EVENTS PROJECTS 1 5 SELECTED SPECIAL EVENTS PROJECTS 3 1 DONNA AND MARVIN SCHWATZ CENTER FOR PERFORMING ARTS, ATLANTA, GEORGIA, USA. COBB ENERGY PERFORMING ARTS CENTRE, COBB COUNTY, GEORGIA, USA. 3 OLYMPIC AQUATIC CENTER,

More information

CAMPUS HIGH SCHOOL ADDITION AND RENOVATION

CAMPUS HIGH SCHOOL ADDITION AND RENOVATION LEGEND RENOVATION ADDITION DRIVE IMPROVEMENTS WIDEN BUS LOOP ROAD TO WEST PROVIDE SECURE ADMINISTRATION ENTRANCE REPLACE AGING ELECTRICAL PANELS RENOVATE SPACE FOR FIVE (5) SCIENCE CLASSROOMS CONVERT EXISTING

More information

Project Management Division

Project Management Division CAPITAL PROJECTS DEPARTMENT MONTHLY ACTIVITY REPORT February 2015 Project Management Division BELOW: Collins Construction crews complete recent exterior work and await delivery of exterior siding. Collins

More information

Why does the renovation and expansion of an EXISTING SCHOOL sometimes cost about the SAME or MORE than the construction of a NEW SCHOOL?

Why does the renovation and expansion of an EXISTING SCHOOL sometimes cost about the SAME or MORE than the construction of a NEW SCHOOL? Why does the renovation and expansion of an EXISTING SCHOOL sometimes cost about the SAME or MORE than the construction of a NEW SCHOOL? 1. BASIC FACTS: The current Abington High School building is 111,831

More information

Election Type: Bond, BEST, Mill Levy District. Nov. 4: Pass/Fail. Bond, BEST, Mill Levy Override, Sales Tax. Comments (optional) Dollar Amount

Election Type: Bond, BEST, Mill Levy District. Nov. 4: Pass/Fail. Bond, BEST, Mill Levy Override, Sales Tax. Comments (optional) Dollar Amount Sources: School reports to CSFP, district websites and media reports BOND / BEST - CAPITAL OPERATIONS Adams 12 Five Star Bond Fail $220,000,000 Extending the useful life of existing school buildings, renovating

More information

STICKLEY AUDITORIUM RENOVATION Community and Stakeholder Presentation

STICKLEY AUDITORIUM RENOVATION Community and Stakeholder Presentation STICKLEY AUDITORIUM RENOVATION Community and Stakeholder Presentation APRIL 30, 2014 SCHEMATIC DESIGN PROGRESS Code Study Analysis: key issues and resolutions Seating Analysis of sightlines, seating and

More information

DISTRICT-WIDE ELEMENTARY PROGRAMMING

DISTRICT-WIDE ELEMENTARY PROGRAMMING DISTRICT-WIDE ELEMENTARY PROGRAMMING PREPARED BY: GIBRALTAR DESIGN SUBMITTED TO: BOARD OF SCHOOL TRUSTEES School Board Meeting September 17, 2015 2015 Gibraltar Design, Inc. Table of Contents SECTION I.

More information

SCHEMATIC AND PROJECT BUDGET APPROVAL EAST CAMPUS NURSING EDUCATION AND CLASSROOM

SCHEMATIC AND PROJECT BUDGET APPROVAL EAST CAMPUS NURSING EDUCATION AND CLASSROOM Shepherd University Board of Governors June 9, 2005 Agenda Item No. 9 SCHEMATIC AND PROJECT BUDGET APPROVAL EAST CAMPUS NURSING EDUCATION AND CLASSROOM In 1994 construction began on the Byrd Science and

More information

July 29, 2014. Revise Section 1.1 (BACKGROUND AND CONTEXT) to the following:

July 29, 2014. Revise Section 1.1 (BACKGROUND AND CONTEXT) to the following: ADDENDUM NO. 2 TO REQUEST FOR QUALIFICATIONS FOR NEW DEVELOPMENT OF OAKLAND UNIFIED SCHOOL DISTRICT PROPERTIES, INCLUDING THE PARCELS HOUSING THE PAUL ROBESON ADMINISTRATION BUILDING AND DEWEY HIGH SCHOOL

More information

We know what brings schools together.

We know what brings schools together. School Work We know what brings schools together. About Us Martin Gardner Architecture, P.C. has been providing excellence in design and building consulting services in eastern Iowa for nearly 30 years.

More information

Educational. Educational-Existing 1/28/2014. OCCUPANT LOADS [no change] Application. Application

Educational. Educational-Existing 1/28/2014. OCCUPANT LOADS [no change] Application. Application February 2014 Code Requirements and Inspections in Educational Occupancies Presented By: Barry W. Rickert Douglas M. Schanne Fire Marshal Training Program Supervisor Office of Education & Data Management

More information

Facility Summary. Facility Condition Summary. Seattle School District David T. Denny International Infrastructure. Facility Components

Facility Summary. Facility Condition Summary. Seattle School District David T. Denny International Infrastructure. Facility Components Infrastructure Facility Condition Summary Weighted Avg Condition Score Facility Components Systems Surveyor/ Date Done Comments G Sitework.9 Site Improvements Parking Pedestrian Paving Site Development

More information

Capital Projects Town Hall Meeting

Capital Projects Town Hall Meeting Capital Projects Town Hall Meeting Planning, Architectural & Engineering Services September 15, 2014 Agenda Project Updates Recently Completed and in Construction Projects in Design Projects in Planning

More information

Those tables are provided at the end of this section in the following order.

Those tables are provided at the end of this section in the following order. T e c h n i c a l M e m o r a n d u m Date Project Subject From To October 2008 Tennessee State University Campus Master Plan 4. Future Campus Requirements Paulien & Associates, Inc Tennessee State University

More information

Code Requirements for Existing Buildings

Code Requirements for Existing Buildings Code Requirements for Existing Buildings Kevin S. Hastings, P.E., LEED AP R. W. Sullivan, Inc. 529 Main St., Suite 203 Charlestown, MA (617) 523-8227 www.rwsullivan.com R.W. Sullivan Engineering (RWS)

More information

Centinela Valley Union High School District. Measure CV Program Update July 23, 2012

Centinela Valley Union High School District. Measure CV Program Update July 23, 2012 Centinela Valley Union High School District Measure CV Program Update July 23, 2012 Site Construction Progress Site Updates Hawthorne High School Lawndale High School Leuzinger High School 2 Hawthorne

More information

SOUTH DAKOTA BOARD OF REGENTS. Committee on Budget and Finance ******************************************************************************

SOUTH DAKOTA BOARD OF REGENTS. Committee on Budget and Finance ****************************************************************************** SOUTH DAKOTA BOARD OF REGENTS Committee on Budget and Finance AGENDA ITEM: III G DATE: October 9-10, 2013 ****************************************************************************** SUBJECT: South Dakota

More information

Higher Education Projects University of Illinois at Urbana-Champaign Gorski Reifsteck

Higher Education Projects University of Illinois at Urbana-Champaign Gorski Reifsteck Laboratories Bevier Hall Food Labs Renovation College of ACES Everitt Lab 4th Floor Remodel - Phase I Renovation College of Engineering MATSE Kiln House Renovation Phase I College of Engineering MATSE

More information

JMS Phone List. dial and small conference capability

JMS Phone List. dial and small conference capability JMS Phone List Main office desk multi line console console can view all lines Main office desk multi line Main office fax line? POTS as currently Principal's office desk multi line extension and private

More information

EAST LYME HIGH SCHOOL

EAST LYME HIGH SCHOOL Overview: 1971 N 1966 GYM 1966 CLASSROOM WING 1966 AUD. 1971 GYM 1998 1998 POOL EAST LYME HIGH SCHOOL Original 1966 Building: The original East Lyme High School was constructed in 1966 and was composed

More information

Van Vleck ISD Bond Election

Van Vleck ISD Bond Election Van Vleck ISD Bond Election November 4, 2014 The Van Vleck ISD School Board called a bond election at their meeting on August 18 for $42.7 million. 2 School districts must ask voters for permission to

More information

School Board Proposed Capital Improvements Program. Fiscal Years 2014-2023

School Board Proposed Capital Improvements Program. Fiscal Years 2014-2023 School Board Proposed Capital Improvements Program Fiscal Years 2014-2023 TABLE OF CONTENTS Summary Page 1 Capital Projects Pages 2-6 Capital Projects Description Pages 7-14 SCHOOL BOARD PROPOSED CAPITAL

More information

AGENDA. BUILDING AND GROUNDS COMMITTEE MEETING April 21, 2015 6:30 PM School Board Room

AGENDA. BUILDING AND GROUNDS COMMITTEE MEETING April 21, 2015 6:30 PM School Board Room AGENDA BUILDING AND GROUNDS COMMITTEE MEETING April 21, 2015 6:30 PM School Board Room 1. Call to order at 6:30 p.m. 2. Review of Three Year Life Safety Recommendations from EGM Architects 3. Review of

More information

FREQUENTLY ASKED QUESTIONS

FREQUENTLY ASKED QUESTIONS FREQUENTLY ASKED QUESTIONS TORNADO REFUGE AREAS IN EXISTING INDIANA K-12 SCHOOLS This is intended to be a resource for school safety This is intended to be a helpful resource available to specialists and

More information

ARTS. presented by: TOM SHERRY HAMILTON ANDERSON ASSOCIATES

ARTS. presented by: TOM SHERRY HAMILTON ANDERSON ASSOCIATES DETROIT SCHOOL OF ARTS presented by: TOM SHERRY HAMILTON ANDERSON ASSOCIATES of DSA OVERVIEW ONE TEACHER S VISION DR. DENISE DAVIS-COTTON RECOGNIZED MILKEN EDUCATOR Picture of Old DSA FOUNDED IN 1992 RECEIVED

More information

Number Northern Arizona University Facility Services Section Page. Effective April 1, 2011

Number Northern Arizona University Facility Services Section Page. Effective April 1, 2011 Facility Services Section Page Recharge Services, Maintenance and Construction PURPOSE 1 of 6 The purpose of this policy is to set forth standards for chargeable services for maintenance and construction

More information

Request for Proposal for Construction Management Services

Request for Proposal for Construction Management Services Willmar Public Schools- ISD 347 611 5 th Street SW Willmar MN 56201 Dr. Jeffrey Holm, Superintendent Request for Proposal for Construction Management Services Willmar Public Schools is soliciting Construction

More information

OHLONE COMMUNITY COLLEGE BOND MEASURE G

OHLONE COMMUNITY COLLEGE BOND MEASURE G Monthly Report OHLONE COMMUNITY COLLEGE BOND MEASURE G Fremont, California June 2014 TABLE OF CONTENTS 1. Executive Summary 2. Safety Status 3. Schedule Status 4. Design Progress 5. Construction Progress

More information

TD AMERITRADE Park Omaha

TD AMERITRADE Park Omaha TD AMERITRADE Park Omaha November 19, 2009 Report No. 6 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY MONTHLY CONSTRUCTION PROGRESS REPORT Metropolitan Entertainment

More information

The University of Akron Main Campus Biennium 1 July 2016- June 2018. Priority Project Budget Description 1 Electrical Infrastructure Loop

The University of Akron Main Campus Biennium 1 July 2016- June 2018. Priority Project Budget Description 1 Electrical Infrastructure Loop The University of Akron Main Campus Biennium 1 July 2016- June 2018 1 Electrical Infrastructure Loop $2,400,000 Scope: Replace center campus deteriorated 4,160 volt cable and duct bank with 23,000 volt

More information

Yale Arts Complex. The design results from the integration of programmatic, structural and mechanical needs. It includes

Yale Arts Complex. The design results from the integration of programmatic, structural and mechanical needs. It includes New Haven, Connecticut 1 2 Yale University s Rudolph Building formerly known as the Art and Architecture Building was designed in 1963 by the modern master and then chair of the School of Architecture,

More information

ALBUQUERQUE PUBLIC SCHOOLS Facility Design & Construction / Maintenance & Operations

ALBUQUERQUE PUBLIC SCHOOLS Facility Design & Construction / Maintenance & Operations ALBUQUERQUE PUBLIC SCHOOLS Facility Design & Construction / Maintenance & Operations MECHANICAL SYSTEMS DESIGN STANDARDS Appendix A RECOMMENDED HVAC SYSTEMS BY TYPE OF SPACE Matt Higgins Valentin Lucero

More information

Ridgewood Public Schools

Ridgewood Public Schools Ridgewood Public Schools Summary of FY16 Budget Budget Supports Academics Extra-Curricular Activities Maintenance of Buildings & Grounds /Construction Budget Detail Tax Levy Tax Levy vs Home Assess. Impact

More information

RESOLUTION NO. 2003-04-13

RESOLUTION NO. 2003-04-13 RESOLUTION NO. 2003-04-13 RESOLUTION OF THE BOARD OF TRUSTEES OF THE CITRUS COMMUNITY COLLEGE DISTRICT ORDERING AN ELECTION, AND ESTABLISHING SPECIFICATIONS OF THE ELECTION ORDER WHEREAS, the Board of

More information

Construction Technologies Career Field Pathways and Course Structure

Construction Technologies Career Field Pathways and Course Structure Courses in Structural Systems (DD) Construction Technologies Career Field Pathways and Course Structure PATHWAY COURSES SUBJECT CODE Construction Technology-Core and Sustainable Construction 1 178000 Carpentry

More information

Springfield Township Board of Education March 10, 2015 Referendum Questions and Answers (updated 2/19/2015)

Springfield Township Board of Education March 10, 2015 Referendum Questions and Answers (updated 2/19/2015) Springfield Township Board of Education March 10, 2015 Referendum Questions and Answers (updated 2/19/2015) What is a referendum? New Jersey school districts hold public referendum votes to seek approval

More information

REGIONAL UNIVERSITY SYSTEM OF OKLAHOMA

REGIONAL UNIVERSITY SYSTEM OF OKLAHOMA REGIONAL UNIVERSITY SYSTEM OF OKLAHOMA AGENDA REGULAR BOARD MEETING June 21, 2012 University of Central Oklahoma Nigh University Center 3 rd Floor, Robert S. Kerr Room Edmond, Oklahoma REG IONAL UNIVERSITY

More information