16300 MEDIUM VOLTAGE DISTRIBUTION



Similar documents
MEDIUM VOLTAGE DISTRIBUTION

Medium Voltage Electrical Distribution

REQUIREMENTS AND SPECIFICATIONS FOR HIGH VOLTAGE CUSTOMER BUILT FACILITIES PEPCO ENGINEERING

2a. IEM Indoor Metal Clad Medium Voltage Switchgear 15KV a. Section INDOOR METAL CLAD MEDIUM VOLTAGE SWTICHGEAR (Std.

Customer Substation Manual 08/05/02

CONTENTS. Yale University Design Standards. Underground Electrical Duct Bank. A. Summary. B. System Design and Performance Requirements

Cable Selection for Medium Voltage Capacitor Banks and Harmonic Filter Banks

Uptown Campus, Primary Electric Master Plan - Program Study State University of New York At Albany, SUCF Project No V.

Hyperlinks are Inactive

3. TYPES OF SERVICE AVAILABLE. 3.1 Scope

Submit shop drawings for equipment provided under this section Shop drawings shall indicate:

CONSOLIDATED EDISON CO. OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY DISTRIBUTION ENGINEERING DEPARTMENT NETWORK SYSTEMS SECTION

CONSOLIDATED EDISON CO. OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY DISTRIBUTION ENGINEERING DEPARTMENT SUBSTATION & EQUIPMENT SECTION

IRRIGATION PUMPING Table of Contents - Section 900

Grounding & Bonding Why it is done And How to Install Properly

Approved Meter Sockets and Cabinets

REQUIREMENTS FOR CUSTOMER-OWNED PRIMARY SERVICES SUPPLIED AT 4 kv TO 35 kv PRIMARY GUIDE

METER REQUIREMENTS GENERAL REQUIREMENTS SECTION D

Table of Contents. TransformerIQ FAQs 1

Customer Low-Voltage Switchboards Service Cable Terminal Compartment Arrangements and Clearances

INDUSTRIAL AND COMMERCIAL SERVICE TRANSFORMER & METERING INSTALLATION SPECIFICATION

STREETLIGHT SYSTEM GROUNDING AND BONDING

SECTION UNDERGROUND ELECTRIC SERVICE

This section applies to the design and installation of transformers.

DIVISION 26 - ELECTRICAL SECTION CABLES FOR INSTRUMENTATION

SECTION POWER MONITOR FOR ELECTRICAL, STEAM CONDENSATE, AND WATER PART I - GENERAL

Underground Service Requirements and Instructions

Engineers Edge, LLC PDH & Professional Training

All work must conform to the National Electric Code, latest edition, and all other applicable codes and regulations.

Fusible Disconnect Switch

SECTION SIGNAL WIRE AND CABLE

FFI. Advances in Medium and Low Voltage Power Distribution ESS Metron Expo and Technical Seminars. Presented By: Greg Pelster & Robert Schmid

Secondary Unit Substations

Electrical Distribution System Study

Electrical for Detached Garages: Updated Feb 19, 2016 for 2015 CE Code in force Jan. 1, Underground branch circuit feeding a detached garage:

Electrical Service Guidelines

ELECTRIC SYSTEM BULLETIN No. 754/759

ELECTRICAL SERVICE REQUIREMENTS FOR MOBILE HOME DEVELOPMENTS

SUPPLEMENT TO SPECIFICATIONS FOR ELECTRICAL INSTALLATIONS

2014 NEC Guide Lines for Home Owner Doing Electrical Work on their Property

Element D Services Electrical

Lightning Arresters P KVA P KVA. Description & Installation

QUESTIONS and ANSWERS RFB , Metal Clad Switchgear and Power Control Room

Requirements for Electrical Installations

2.4 kv to 34.5 kv SP-1099

Primary and Secondary Electrical Distribution Systems

800 Communications Circuits

Grounding Practice at Data and Communications Centers. David Brender, P.E., CPQ National Program Manager Copper Development Association Inc.

The National Armored Cable Manufacturers Association Presents. Installation Standard for Types AC and MC Cables

What are the basic electrical safety issues and remedies in solar photovoltaic installations?

Medium Voltage Products. ZN1 12 kv arc-proof air-insulated switchgear for primary distribution

Multiple Meter Installation Amperes Per Position -Single Phase, Self-contained

Grounding of Electrical Systems NEW CODE: Grounding and Bonding

Standards. 5 ANSI/TIA/EIA-569-A (CSA T530)

Maintenance Report MEDIUM VOLTAGE POWER STATION 500SC / 630SC / 800SC / 900SC / SC / SC / 1250SC / 1600SC / 1800SC / 2000SC

The Contractor shall furnish and install all shielded power cable suitable for use on this project.

4160: THE GREEN 480 MEDIUM VOLTAGE ELECTRICAL SYSTEMS

Cable Accessories. for Extruded Dielectric Cable 69kV - 230kV Rated. Catalog Python13

National Craft Assessment and Certification Program S P E C I F I C A T I O N S

UNIVERSITY OF WASHINGTON Facilities Services Design Guide. Electrical. Switchboards. Basis of Design. Design Evaluation

Solar Power Solutions

Section kv Power Cables

Application Bulletin NEC Reference Guide for SolarBridge-Enabled AC Module Installers

SPECIFICATIONS FOR THE INSTALLATION OF FIRE ALARM SYSTEMS, SPRINKLER SYSTEMS, AND MASTER BOXES IN THE POQUONNOCK BRIDGE FIRE DISTRICT

1 Town of Lyons Electrical Distribution System Design Standards

Addendum #2 Contract UK-11-13

MOBILE HOME SERVICE REQUIREMENTS GAS

ELECTRIC METERING COMMERCIAL & INDUSTRIAL

KNOW YOUR OPTIONS: 69 KV XLPE POWER CABLE

UNIFIED FACILITIES CRITERIA (UFC) EXTERIOR ELECTRICAL POWER DISTRIBUTION

Instructions For SF 6 Refill Kit

AT&T Specifications Trenching Conduit Boxes and M anholes Aerial Entrance Masts Service Cabinets Bonding and Grounding

HVL 5 38 kv Load Interrupter Switchgear. The Standard for Performance, Protection and Dependability

LEAD FREE FIREX. Interlock Armored Cables TECK90 and MC Industrial Cables. w w w. n e x a n s e n e r g y. c o m

Least Cost Cable System. Strategies to Reduce Cable and Infrastructure Costs When Transitioning to an All Conduit Systems

MEDIUM VOLTAGE. Michael Mosman, PE. CCG Facilities Integration Incorporated FACILITIES INTEGRATION INCORPORATED

NATUS NES / NES-H Draw-out Type Medium Voltage Switchgear Systems. Safe energy distribution that meets the highest industrial requirements

KNOW YOUR OPTIONS: 230 KV POWER CABLES

PRIMARY SERVICE LINE: The Company's conductors which connect the supply line with a transformer located on private property.

Union County Public Schools. Facilities Department. Electrical. Safe Work Practices

RESIDENTIAL ELECTRICAL REQUIREMENTS (REVISED 3/28/2008) PERMIT REQUIREMENTS:

EARTHING AND BONDING AT SECONDARY SUBSTATIONS

UNIVERSITY OF WASHINGTON Facilities Services Design Guide. Electrical. Metering and Monitoring. Basis of Design

TABLE OF CONTENT

How To Choose A Transformer

RAY-MAX Integrated Solar Power Strip

SECTION MEDIUM VOLTAGE CABLE

White Paper SolarEdge Three Phase Inverter System Design and the National Electrical Code. June 2015 Revision 1.5

CTI TECHNICAL BULLETIN Number 9: A publication of the Cable Tray Institute

GROWTH MANAGEMENT DEPARTMENT 201 SE 3 rd ST, (Second Floor), Ocala, FL (352) ; FAX: (352)

Short Circuit Current Calculations

SYSTEM 1850-SE SERVICE ENTRANCE CABLE SYSTEM

DESIGN AND CONSTRUCTION STANDARDS SPECIFICATION GUIDELINES

CONSTRUCTION, MATERIAL, AND WORK SPECIFICATIONS FOR NEW. 15/25kV PRIMARY UNDERGROUND DISTRIBUTION SYSTEMS UP TO 200 AMPS

01.4IB.51200B PowlVac-AR Arc Resistant Switchgear. 5kV & 15kV 1200A, 2000A, 3000A, & 4000A Forced Cooled. Powered by Safety

Switchgear and Metal-Enclosed Bus

TSn SERIES Surge Protective Device

City of Riverside Building & Safety Division Phone: (951)

ELECTRICAL ENGINEERING DESIGN CRITERIA APPENDIX F

Chapter 9. Bonding and Grounding

Transcription:

16300 MEDIUM VOLTAGE PART 1: GENERAL 1.01 SYSTEM DESCRIPTION A. Most new loads will be served from the underground electric distribution system. This system is a primary open loop configuration served by a resistance grounded Delta source operating at 13.2 kv. Primary distribution switchgear and overcurrent devices shall be designed for 750 MVA of available fault current. It is important to note that bushings, insulators, and arrestors must be rated for a full 15kV to ground, not the 8kV typical of a grounded Wye system. 1.02 SUBMITTALS A. Products described in this section shall be submitted for review to Cornell University s Electrical Utility Engineer, before ordering equipment. PART 2: PRODUCTS 2.01 MEDIUM VOLTAGE CABLE A. 13.2 kv System: 1. Single conductor. 2. Copper conductor, standard sizes: #2/0, 350 kcmil, 500kcmil, 750kcmil. 3. 15 kv EPR insulation, 220-mil (133%), 105 degrees C. 4. Copper tape shield, 5-mil. 5. Extruded conductor screen and insulation screen. 6. PVC jacket, 80-mil minimum, rated for cable tray use. 7. Acceptable manufacturers: Okonite, Kerite, Southwire, Prysmian. B. 2.4 kv System: 1. Single conductor. 2. Copper conductor, standard sizes: #2, 350 kcmil. 3. 5 kv EPR insulation, 125 mils minimum (100%). 4. Non-shielded. 5. PVC jacket, 80-mil minimum, rated for cable tray use. 16300 MEDIUM VOLTAGE 06-30-11 PAGE 1 OF 7

NOTE: As existing 2.4KV cable is replaced it shall be replaced with 15kV cable as specified in section 2.01.A. 6. Acceptable manufactures: Okonite, Kerite Southwire, Prysmian C. Splicing: 1. 3M or Raychem cold shrink splice kits are approved for use by trained personnel. D. Arc Flash Tape: 1. 3M Scotch tape 77W is approved for use. Arc flash tape shall be used in the vicinity of adjacent circuits per mfg. recommendations. 2.02 DUCT BANKS A. No less than two - 5" schedule 40 PVC ducts per duct bank. B. The duct bank shall be encased in reinforced concrete with a minimum 3 cover over any ferrous material and full encapsulation of the PVC duct with a minimum of 4 cover on all sides. Where duct banks pass under heavy traffic areas a structural design review shall be made prior to release for installation. Compacted fill to support the duct bank or clean stone to aid drainage must be evaluated by engineering. C. A minimum of five feet of clearance shall be maintained from steam and condensate lines where parallel runs exist. D. The Contractor shall verify duct bank continuity by pulling a mandrel ½ smaller than the conduit I.D through each duct immediately after placing concrete and prior to pulling cable in. The contractor installing cable is responsible for verifying continuity in pre-existing duct banks. E. Plastic bell ends and plugs shall be used in the manhole and building. F. Install a 3/16" diameter nylon fish in all ducts. G. Minimum 48" bending radius required. Bend radius, total degrees of bend and pulling tension shall be calculated by the consultant and provided to the owner representative for review. H. Ductbank entrances to buildings shall be sealed with water stop such as Volclay or equivalent. Control joints, if required, shall be determined by the civil engineer of record. 16300 MEDIUM VOLTAGE 06-30-11 PAGE 2 OF 7

2.03 MANHOLES A. Duct bank entrances to manholes shall be sealed with water stop such as Volclay. B. Pulling irons shall be located on the opposite wall and one foot below the horizontal projection of the lowest duct for each duct bank entering the manhole. C. A manhole ground lug shall be connected to two driven 8' electrodes in corners of the manhole. D. All manhole penetrations shall be sealed and water tight. E. The manhole shall have an effective gravity drain with a minimum 3 diameter pipe protected by a trash screen with ½ holes. The screen shall have an effective surface area greater than two times the pipe diameter. F. A 36" non-vented round manhole cover with drop rings is required. Cover shall be centered in manhole to maximize use of cable racks. G. The minimum size is: 8' Long x 6' Wide x 7' High. Larger manholes may be required at the discretion of the Cornell Utilities Department. H. Vaults shall be rated AASHTO H25. 2.04 PRIMARY SWITCHGEAR AND TRANSFORMERS A. LOOP SWITCH 1. Taps into the building 13.2 KV distribution system are accomplished using pad-mounted or vault-mounted switches. In applications where a convenient tap-in point is not available, a distribution switch is required. The switch requires two switched ways for the incoming and outgoing loop feeders, one switched way for the building load, and at least one spare switched way. Distribution switchgear is not permitted to be located in manholes. Rooms containing distribution switches shall have emergency lighting and power. 2. Vault-Style SF6 Switch Ratings: a. Voltage: 15.5 kv b. Continuous Current & Loadbreak: 600 amps c. BIL: 110 kv d. Momentary Current Withstand: 40,000 amps e. One Second Withstand: 25,000 amps f. Close & Latch: 40,000 amps g. Operations at 600 amps: 1,000 minimum h. Bushings: 600 amp apparatus i. Acceptable Manufacturers: G&W RAM Style Switch 16300 MEDIUM VOLTAGE 06-30-11 PAGE 3 OF 7

3. Pad-mounted Switch Ratings: a. Voltage: 14.4 kv b. Continuous Current & Loadbreak: 600 amps c. BIL: 95 kv d. Momentary Current Withstand: 22,400 amps minimum e. One Second Withstand: 14,000 amps minimum f. Close & Latch: 22,400 amps g. Acceptable Manufacturers: S&C PME with Mini-Rupter Switch or Vista Switch h. Dead front B. TRANSFORMERS 1. Dry-type transformers (for interior applications): a. Rooms must be accessible from both inside and outside of the building. The outside entrance must be large enough to allow installation and removal of the primary switchgear, transformer, and secondary switchgear. Dry-transformer unit substations (close coupled) are preferred over separate equipment. Transformer rooms shall be ventilated to the outside and shall have emergency lighting and power. b. Transformers shall carry a minimum primary BIL of 95 kv. c. A temperature rise of 80 deg. C is preferred. Temperature rise of 115 deg. C is acceptable only in areas with dedicated outside ventilation ducting. Transformer design sizing based on forced-air ratings is not permitted. 150 deg. C rise is not acceptable. d. Minimum efficiency rating of NEMA TP-1 is required. 2. Pad-mounted Transformers (for outdoor applications): a. New outdoor locations must be approved by the Campus Planning Office. b. Pad-mount transformers shall be oil-filled. c. Concrete pads shall be provided with footers to prevent pad movement. Concrete pads shall be designed with a pit under the primary cable compartment to provide a minimum of 36" of exposed cable under the primary bushing. Concrete pads shall contain a grounding electrode consisting of a minimum of two ground rods and a length of bare copper conductor encased in concrete. 16300 MEDIUM VOLTAGE 06-30-11 PAGE 4 OF 7

d. Transformer primary over-current protection shall consist of drywell, load-break, current limiting, fuses on transformers 500 KVA and smaller. A separate, fused primary interrupter switch (as detailed in 2.04.C below) or vacuum interrupter shall be used with larger transformers. A complete set of spare fuses shall be supplied. e. Primary bushings shall consist of 600 amp dead-break bushing inserts with a minimum 15kV single phase to ground rating. f. Primary and secondary compartments shall be separated by a steel bulkhead. g. Temperature rise shall be 55/65 deg. C. 3. All transformers shall be protected with surge arresters. Arrester rating shall be 18 KV rated, 15.5kV MCOV, for the 13.2 KV system. Arrestors may be placed in primary switch where appropriate. C. PRIMARY OVERCURRENT PROTECTION 1. The primary switchgear protecting an indoor (or outdoor greater than 500 KVA) transformer bank shall consist of a fused, air-insulated, load-break switch. The switch shall be an S&C Mini-Rupter. The fuses and fuse holders shall be S & C SM-5S. One set of spare power fuses shall be provided. D. METERING 1. Metering for MV distribution shall consist of panelboard style, revenue grade digital power meter/analyzer with the following requirements. a. Measurements: True RMS 3-phase voltage, current and power, harmonics, K-factor, symmetrical components, and sag/swell data; b. Communications: DNP 3.0 protocols, Ethernet ports, GPS synchronized meter clock, and remote alarm notification; Allen Bradley PM 3000 M6 with Ethernet on feeder breakers and PM 3000 M8 shall be used in distribution substations. c. Data Logging: Sequence of events and min/max logging, scheduled event-driven logging of up to 32 parameters concurrently on-board data logging features; d. Set Points: Setpoint on any parameter or condition for 1 second; e. Outputs: Serial port communications connection; f. Security: Multi-user, multilevel security, customizable up to 16 users with multiple levels of access; 16300 MEDIUM VOLTAGE 06-30-11 PAGE 5 OF 7

g. Acceptable manufacturers: Allen Bradley PM 3000. 2. Instrument transformers used for metering shall meet ANSI accuracy class 0.6 or better. E. GROUNDING 1. A continuous grounding system shall be provided for grounding of primary cable shields, switchgear and transformer frames and transformer secondary neutrals. The grounding system shall meet the requirements of the NEC Article 250. In addition, a #4/0 copper grid shall be installed in the vault floor and be bonded to the building grounding electrode system. 2. A minimum #2/0 grounding conductor shall be installed in each MV cable conduit with each MV cable circuit. PART 3: EXECUTION 3.01 INSTALLATION A. All medium voltage cable pulling, splicing, and terminating for building services shall be done in accordance with the cable manufacturer s guidelines. Hi Pot tests shall be performed in accordance with IEEE standard 400. Cable pulling tensions and linear feet must be recorded. B. Cable that is pulled in and will not be terminated within 24 hours must have adequate end protection and be sealed from the elements with approved MV tape, shrink tube or similar product intended for that use. C. In cases where a contractor must work on medium voltage systems, the following shall apply: 1. Operation of Switching Equipment: a. Contractors shall not operate medium voltage circuit breakers, distribution switches, and other switching equipment except to de-energize a circuit in the event of an emergency. Cornell linemen will perform all live switching operations. 16300 MEDIUM VOLTAGE 06-30-11 PAGE 6 OF 7

2. Work on New Systems: a. Contractors may perform all necessary work on new systems installed by the Contractor, without the necessity for supervision or assistance of Cornell personnel. The Contractor is expected to follow standard deenergizing, locking-out, testing, grounding, and tagging procedures before handling any medium or low voltage equipment. Any connection to existing equipment shall require the contractor and Cornell personnel to adhere to the following procedure. Once a system has been energized and put into service, it shall be considered to be existing equipment. 3. Work on Existing Systems: a. Any time a Contractor must make a connection to or work on an existing system, the following procedures shall be used to ensure the safety of all personnel involved: 1) Cornell linemen will operate all switching equipment as required to de-energize a circuit in preparation for work. A representative of the Contractor shall be present during all switching and both the Contractor s electrician and a Cornell lineman shall install locks on all switches as required to prevent accidental switch operation. Each switch shall be tagged to inform others of the work being done. Manhole switches are never operated with personnel in the manhole. Cornell linemen have and use remote switching devices. 2) Cornell lineman will test a circuit to ensure that it is dead before any contact is made with the circuit. After testing, grounds will be installed by Cornell linemen to ensure the circuit is dead and cannot become energized. The Contractor may also install grounding equipment. 3) A Contractor shall not work on any existing cable without first having a Cornell lineman verify that the correct cable has been selected and the cable is de-energized. Cornell linemen will make the first cut into any existing cable system prior to Contractor splicing or terminating. This is to ensure that the Contractor does not select and cut into an energized cable. A cable terminated on each end into a G&W switch with a pothead cannot remain grounded at all times during splicing. Cornell linemen will perform the switching, locking, tagging, and testing procedure before cutting into the cable and grounding each phase. The Contractor may then proceed with work. 16300 MEDIUM VOLTAGE 06-30-11 PAGE 7 OF 7