1 16600 Underground Electrical Duct Bank This document provides design standards only, and is not intended for use, in whole or in part, as a specification. Do not copy this information verbatim in specifications or in notes on drawings. Refer questions and comments regarding the content and use of this document to the Yale University Project Manager. CONTENTS A. Summary B. System Design and Performance Requirements C. Submittals D. Product Standards E. Manufacturers F. Materials G. Accessories or Special Features H. Special Requirements I. Installation Guidelines J. Quality Control K. Startup and Training Change History Date Description of Change Pages / Sections Modified Change Approver Initials 10/17/14 Amend text in section E (Manufacturers), paragraph #2 (Manhole Covers) to update vendor 10/17/14 Amend text in section F (Materials), paragraph #1 (Ductbank) subparagraph a. for clarity 10/17/14 Amend text in section H (Special Requirements), paragraphs #1 and #7 for correction. 10/17/14 Amend text in section I (Installation Guidelines) paragraphs #6. & #11. 10/17/14 Add paragraphs #12 & #13 to section I (Installation Guidelines) , E. #2. (Underground Electrical Duct Bank; Manufacturers) , F. #1. a (Underground Electrical Duct Bank; Materials) 3> , H. #1. & #7. (Underground Electrical Duct Bank; Special Requirements) , I. #6. & #11. (Underground Electrical Duct Bank; Installation Guidelines) , I. #12. & #13. (Underground Electrical Duct Bank; Installation Guidelines) A. Summary This section summarizes the design criteria for underground exterior electrical distribution systems. B. System Design and Performance Requirements 1. The minimum allowable concrete duct compressive strength is 5,000 psi at 28 days. 2. Design all underground electrical raceways and duct banks for seismic zone Steel reinforcement ASTM A-615, grade 60 minimum cover to steel reinforcement 1. Subdivision 16600: Underground Electrical Duct Bank 1
2 Section 16600: Underground Electrical Duct Bank 4. Vault shall be designed to meet ASTM C857 and ACI 318 with AASHTO HS-20 loading. 5. Construction joint shall be sealed with BUTYL rubber resin or equivalent. C. Submittals Submit the following design and construction documents to Yale University. 1. Design Documents Plan and profile views of all design drawings Maximum wire pulling tension calculations for proposed conduits 2. Construction Documents Product data on manholes, hand holes, and fittings Equipment and machinery proposed for bending metal conduit D. Product Standards The following products are standard for Yale University: Underwriters Laboratories ANSI/NEMA 70: National Electrical Code National Electrical Manufacturers Association (NEMA) TC6: PVC and ABS Plastic Utilities for Underground Installations National Fire Protection Association (NFPA) 70: National Electrical Code (NEC) National Electrical Contractors Association, Inc. (NECA) 5055: Standard of Installation E. Manufacturers Subject to compliance with the design requirements, manufacturers offering products that may be incorporated in the work include, but are not limited to, the following. 1. Pre-cast Manholes Arrow, Ditullio, Rotondo, or a Yale University approved equivalent 2. Manhole Covers Campbell Foundry 1108 or a Yale University approved equivalent with the word Electrical cast into the upper surface. The cover opening shall be 36 diameter as a minimum. All new covers shall have manhole numbers welded on surfaces (TIG Weld). Subdivision 16600: Underground Electrical Duct Bank 2
3 Section 16600: Section 16600: Underground Electrical Duct Bank F. Materials 1. Ductbank 2. Manhole a. Use 5 schedule 40 (encased in concrete by 2 minimum) or schedule 80, rigid, nonmetallic conduit in straight sections, unless otherwise noted or specified. Use rigid galvanized steel 5 conduit for bends, kicks, sweeps, elbows, offsets, and within five feet of ductbank wall penetrations. b. All conduits penetrating to the wall of manhole shall have end bells, or if not, conduits shall have grounding bushing attached to ground rod. There shall be a minimum of two ground rods per manhole. a. All electrical devices in the electrical manholes, such as plugs, receptacles, outlets, switches and terminal blocks, shall be made by Hubbell Marine Grade products. b. Lighting fixtures in electrical manholes shall be made of Simkar OV451 with polycarbonate lens, wet location stainless steel latches and fittings, and low temperature universal ballasts with 2-32 watt T8 lamps and with T8 ballast. c. Install fault indicator on all feeders using Power Delivery Products Cat # with auto reset and trip with 4 hours delay. G. Accessories or Special Features 1. All end seals, gland seals, and anchors must be designed and factory prefabricated to prevent the ingress of moisture into the system. 2. All subassemblies must be designed to allow for complete draining and drying of the conduit system. 3. Anchors must be manufactured to minimize the heat transfer from the carrier pipe to the jackets. H. Special Requirements 1. Provide heavy duty non-metallic cable racks with demountable insulated cable brackets by Underground Devices, Inc in all manholes. 2. Provide a sump at the bottom of each manhole with sump pump wired to a ground fault outlet. The sump pump discharge must be piped to an adjacent storm sewer or to the surface. Cords for the sump pump shall be Type OW. 3. Pulling wiring irons shall be on all walls and floor. 4. Each manhole shall have a ground bus with two separate connections to ground rods. Subdivision 16600: Underground Electrical Duct Bank 3
4 Section 16600: Underground Electrical Duct Bank 5. Maintain a minimum grade of 4" in 100 feet, either from one manhole, hand hole, or pull box to the next, or from a high point between them, depending on surface contour. 6. Pipe bends must have at least a 10' radius. 7. Manhole and vault shall be sized per design requirements. Number of cables, splices, elbows, etc, but minimum size shall be 8 x11 x7 high. 8. All grounding wires shall be 4/0 AWG as a minimum. 9. Fiberglass ladder shall be installed in each manhole. I. Installation Guidelines 1. Pipe bedding: Where possible, provide a uniform pipe bedding of granular material conforming to the requirements of SW, SP, or SP-SW soil classifications for on-site material. If suitable material is not available, backfill the trench with sand. Using a material similar to the bedding, backfill the entire trench width evenly in 6" lifts to 6" above the top of the pipe. Compact the lifts to at least a 95% Standard Proctor density, meeting ASTM D1556 standards at optimum moisture (or as recommended by the soils engineer). Backfill the remaining trench in lifts not to exceed 12" up to the sub-grade height for the surface condition encountered. Compact the lifts to a 95% Standard Proctor density, meeting ASTM D1556 standards at optimum moisture (or as recommended by the soils engineer). Backfilling and compacting above the sub-grade must be determined by the soils engineer or by the recommended paving design for the project. Salvage existing topsoil and reuse it, where possible, as directed by Yale University grounds personnel. Replacement topsoil must meet Yale University grounds personnel requirements. 2. Leave a nylon fish tape in all spare conduits. 3. All conduits entering a building structure must terminate with a threaded end that will accept a lock nut, connector, or grounding bushing. 4. Bury all ducts at least 30" below grade, unless otherwise noted. The top of the ductbank must be dyed red with warning tape. Maintain 12" of vertical and horizontal separation with other piping systems. 5. Unless noted otherwise, encase conduits with 3,000 psi concrete, with 4-5 steel reinforcing steel re-bars running the length of ductbank. In addition #5 reinforcing steel wraps is required every 5 feet for the entire run of the ductbank. Subdivision 16600: Underground Electrical Duct Bank 4
5 Section 16600: Section 16600: Underground Electrical Duct Bank 6. For each manhole, place a plaque on the manhole wall adjacent to the duct. Indicate the name of the manhole at the other end and the distance to the next structure. Plaques shall be made by Seton Cat # MO929, with a red back ground and white letters indicating manhole numbers. 7. Where duct banks enter buildings, vaults, or other structures, dowel into the concrete wall with #5 reinforcing steel at the four corners of the duct bank (minimum) and every 12" around the perimeter of the duct bank. Extend the dowels at least to the depth of the wall and the same distance into the duct bank. 8. Empty raceways must have a permanent removable cap over each end. 9. Install a metal lined, plastic, 6" wide warning tape 18" above all raceways and duct banks. 10. Furnish and install a Danger High Voltage sign at each manhole, cable chamber, junction box, pull box, and vault. 11. Install #4/0 bare copper ground cable the length of the duct bank to be used to connect the manholes to grounding system. 12. New manholes shall have a plaque visible upon entry to manhole with the manhole number. Plaque shall be red with white lettering. 13. New manholes shall have a plaque at each compass point, north, south east and west, visible upon entry to the manhole with compass point, the next destination/source (building or manhole) of the cables leaving/entering that face of the manhole as well as the distance to that location. J. Quality Control Work on exterior electrical distribution systems must conform to the following quality control standards. 1. Testing Laboratory a. Yale University will retain the services of a qualified, independent testing laboratory to perform soil compaction tests, as directed, during construction. b. All materials within the scope of Underwriters Laboratories must conform to UL standards and have an applied UL listing mark. 2. Testing Methodology and Extent a. Inspect and test in accordance with NETA-ATS requirements, except section 4. b. Perform inspections and tests listed in NETA-ATS, section Subdivision 16600: Underground Electrical Duct Bank 5
6 Section 16600: Underground Electrical Duct Bank K. Startup and Training 1. A final inspection of electrical systems is required before final payment. 2. Contractors must provide competent instructors to train Yale University personnel in the care, adjustment, and operation of all parts of the electrical system. End of Section Subdivision 16600: Underground Electrical Duct Bank 6
3. Contractor shall ensure that all permits are obtained prior to any construction. Contractor shall be responsible for all utility fees.
The following shall serve as the minimum requirements for contractors performing work in relation to the Authority s potable water and sanitary sewer system(s), appurtenances and service connections. General:
More informationSECTION 16402 UNDERGROUND ELECTRIC SERVICE
SECTION 16402 UNDERGROUND ELECTRIC SERVICE PART 1 GENERAL 1.1 SUMMARY A. Description of System 1. Furnish all labor, materials, and equipment for below grade work external to buildings as required, and
More informationElectric Engineering Division FIBER CONDUIT RULES AND REGULATIONS
Electric Engineering Division FIBER CONDUIT RULES AND REGULATIONS TABLE OF CONTENTS I. RULES AND REGULATIONS A. TABLE OF CONTENTS... 2 B. TERMS AND DEFINITIONS... 3 C. DEVELOPER S/CONTRACTOR S RESPONSIBILITIES...
More informationConduit Fittings & Accessories Directional Drilling Conduit Utility Duct Telephone Duct Residential Boxes
CANTEX INC. 301 Commerce Ste 2700 Fort Worth, Texas 76102 817-215-7000 Fax: 817-215-7001 Conduit Fittings & Accessories Directional Drilling Conduit Utility Duct Telephone Duct Residential Boxes YOUR FULL
More informationElectrical for Detached Garages: Updated Feb 19, 2016 for 2015 CE Code in force Jan. 1, 2016. Underground branch circuit feeding a detached garage:
Electrical for Detached Garages: Updated Feb 19, 2016 for 2015 CE Code in force Jan. 1, 2016 * Garage construction requires permits (electrical, building) * Permits must be applied for at the time. * Dial
More informationREQUIREMENTS AND SPECIFICATIONS FOR HIGH VOLTAGE CUSTOMER BUILT FACILITIES PEPCO ENGINEERING
REQUIREMENTS AND SPECIFICATIONS FOR HIGH VOLTAGE CUSTOMER BUILT FACILITIES PEPCO ENGINEERING Revised October, 2013 TABLE OF CONTENTS 1.0 INTRODUCTION... 3 2.0 REQUIRED DRAWINGS... 3 2.1 Site Plan... 3
More informationMerrimac Municipal Light Department. Residential Developments Policy
Merrimac Municipal Light Department Residential Developments Policy General: This document provides specific instructions for the provision of underground electrical facilities associated with the construction
More informationMOBILE HOME SERVICE REQUIREMENTS GAS
ELECTRIC AND GAS 1.0 INDEX 1.0 INDEX 2.0 PURPOSE 3.0 GENERAL 4.0 REFERENCE MATERIAL 5.0 TYPICAL UNDERGROUND UTILITY LAYOUT 6.0 METER PAD DETAILS 7.0 GENERAL INSTALLATION PROCEDURES 8.0 PEDESTAL SPECIFICATIONS
More informationSECTION 02630 STORM DRAINAGE SYSTEM
SECTION 02630 PART 1 - GENERAL 1.01 DESCRIPTION A. Section includes specifications for storm drainage systems including modifications and connections to existing storm drainage systems. 1.02 REFERENCE
More informationSUBDRAINS AND FOOTING DRAIN COLLECTORS. A. Construct subdrains, subdrain cleanouts and outlets, and footing drain collectors.
SUBDRAINS AND FOOTING DRAIN COLLECTORS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Subdrains B. Subdrain Cleanouts and Outlets C. Footing Drain Collectors D. Storm Sewer Service and Connections 1.02 DESCRIPTION
More informationUnderground Service Requirements and Instructions
This packet includes all FKEC underground service requirements, instructions, procedures and drawings. If you are considering underground power service please review this document in its entirety (3 page
More informationSECTION 02400 - STORM DRAIN SYSTEM
SECTION 02400 - STORM DRAIN SYSTEM CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Reference Standards... 1 1.04 Quality Assurance... 1 1.05 Measurement And
More informationSan Antonio Water System Standard Specifications for Construction ITEM NO. 854 SANITARY SEWER LATERALS
San Antonio Water System Standard Specifications for Construction ITEM NO. 854 SANITARY SEWER LATERALS 854.1 DESCRIPTION: This item shall govern sanitary sewer laterals installed in accordance with these
More informationSECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701)
SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701) 55-1 GENERAL The Contractor shall perform all work required by the plans for construction of pipe for storm drains, precast polymer trench drains
More informationSection 2100-Trenching and Tunneling
SECTION 5200 - STORM SEWER PART 1 - GENERAL 1.01 SCOPE: This Section covers installation of storm sewer mains and culverts. Topics include permits and fees, trench widths, pipe laying, bedding, initial
More informationState of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS
State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS While its use is not required, this checklist has been prepared to provide the field inspector a summary
More informationSpecification Standards Communications Underground Ducts, Raceways and Structures 27 05 43
PART 1: GENERAL 1.01 SCOPE OF WORK A. The work required under this Section consist of all primary, secondary, Information Technology underground ducts and raceway, including manholes and handholes for
More information2014 NEC Guide Lines for Home Owner Doing Electrical Work on their Property
2014 NEC Guide Lines for Home Owner Doing Electrical Work on their Property A brief summary of the most used code references for residential wiring State of Idaho Division of Building Safety Electrical
More informationHOUSTON COMMUNITY COLLEGE HCC ALIEF CAMPUS MAIN BUILDING, FIRST, SECOND & FOURTH FLOORS RENOVATION ISSUE DATE: 10.17.12
SECTION 27 05 26 - GROUNDING AND BONDING FOR COMMUNICATIONS SYSTEMS PART 1 - GENERAL 1.1 SUMMARY A. This Section includes grounding and bonding products, design requirements and installation for communications
More informationSECTION 02720 SANITARY SEWER AND STORM DRAIN SYSTEMS
SECTION 02720 SANITARY SEWER AND STORM DRAIN SYSTEMS PART 1 GENERAL 1.01 SECTION INCLUDES A. The requirements for pipe material and installation in sewer and drainage collection systems. All materials
More informationSECTION 33 41 13 PUBLIC STORM UTILITY DRAINAGE PIPING
SECTION 33 41 13 PUBLIC STORM PART 1 - GENERAL 1.01 SECTION INCLUDES A. Storm drainage piping, fittings, and accessories at proposed station areas and locations other than under and immediately adjacent
More informationSECTION 33 05 16.13 PRECAST CONCRETE UTILITY STRUCTURES
SECTION 33 05 16.13 PRECAST CONCRETE PART 1 - GENERAL 1.01 SECTION INCLUDES A. This item shall consist of the construction of both sanitary and storm sewer precast concrete manholes in accordance with
More informationAT&T Specifications Trenching Conduit Boxes and M anholes Aerial Entrance Masts Service Cabinets Bonding and Grounding
AT&T Specifications Trenching Conduit Boxes and M anholes Aerial Entrance Masts Service Cabinets Bonding and Grounding A Guide for California Developers of Com m ercial Property This guide consists of
More informationAll work must conform to the National Electric Code, latest edition, and all other applicable codes and regulations.
DIVISION 16 ELECTRICAL SECTION 16100 - ELECTRICAL PART 1 - GENERAL SCOPE All electrical work as shown on the drawings and as necessary to provide a complete electrical system. Include primary service,
More informationBethel Township Municipal Authority (BTMA) RESIDENTIAL SEWER CONNECTION MANUAL
155 E. Front Street (rear) Lititz, PA 17543 Phone (717) 625-1930 Fax (717) 625-1931 Bethel Township Municipal Authority (BTMA) RESIDENTIAL SEWER CONNECTION MANUAL CONSTRUCTION SPECIFICATIONS AND DETAILS
More informationSECTION LS 2530 SANITARY SEWERS. A. General: Submit the following in accordance with The General Conditions.
SECTION LS 2530 SANITARY SEWERS PART 1 GENERAL 1.1 SUBMITTALS A. General: Submit the following in accordance with The General Conditions. 1. Product data for drainage piping specialties. 2. Shop drawings
More informationCOMMERCIAL CONDUIT RULES AND REGULATION
Electric Engineering Division COMMERCIAL CONDUIT RULES AND REGULATION S:\COO_ACM_US_Electric_Telecommunications\COO_ET_Engineering\Conduit Policies\Residential 1805 NE 30th Ave., Bldg. 400 Ocala, FL 34470-4875
More informationRESIDENTIAL ELECTRICAL REQUIREMENTS (REVISED 3/28/2008) PERMIT REQUIREMENTS:
RESIDENTIAL ELECTRICAL REQUIREMENTS (REVISED 3/28/2008) PERMIT REQUIREMENTS: Signed completed Electrical Permit application form. Minnesota law requires all electrical work is to be performed by licensed,
More information4 Installation Requirements
4 Installation Requirements 9 4.1 Code Reference The authority having jurisdiction should be referenced to determine what law, ordinance or code shall apply in the use of flexible duct. Ducts conforming
More informationC. Section 014510 TESTING LABORATORY SERVICE.
SECTION 014500 QUALITY CONTROL PART 1 GENERAL 1.01 RELATED REQUIREMENTS A. Drawings and General Provisions of Contract, including General and Special Conditions and other Division 1 Specification Sections,
More informationCITY OF SELMA, TEXAS Inspection Checklist: Commercial
Rev Y71004 The Permits and Inspections Department welcomes you to the City of Selma. The following information is provided to you as guidance through the inspection process. The City of Selma provides
More informationTS 813 GROUNDING AND BONDING TTD 813.001 TRAFFIC SIGNAL INSTALLATION AND CONTROLLER CABINET GROUNDING SYSTEM TTD 813.005 CONTROLLER CABINET GROUNDING
TORONTO TRANSPORTATION January 2012 TS 813 GROUNDING AND BONDING TABLE OF CONTENTS 1. DRAWINGS TTD 813.001 TRAFFIC SIGNAL INSTALLATION AND CONTROLLER CABINET GROUNDING SYSTEM TTD 813.005 CONTROLLER CABINET
More informationSECTION 08000 STORM DRAINAGE TABLE OF CONTENTS
SECTION 08000 STORM DRAINAGE 08010 DESIGN A. Location B. Sizing TABLE OF CONTENTS 08020 MATERIALS A. Pipe Materials B. Structure Materials C. Installation D. Inlets and Outlets 08030 INSPECTIONS AND TESTING
More informationDESIGN AND CONSTRUCTION STANDARDS SPECIFICATION GUIDELINES 33 70 00
SECTION 33 70 00 - ELECTRICAL DISTRIBUTION CONCRETE ENCASED PRIMARY DUCTBANK SYSTEMS Duct Banks shall be installed by qualified electrical contractors. Provide type EB PVC 5 inch duct equal to Carlon #68716
More informationChecklist for plans to Construct, Alter or Repair An Individual Subsurface Sewage Disposal System
Checklist for plans to Construct, Alter or Repair An Individual Subsurface Sewage Disposal System An application for the construction or alteration of an individual subsurface sewage disposal system shall
More informationSPECIFICATIONS FOR THE INSTALLATION OF FIRE ALARM SYSTEMS, SPRINKLER SYSTEMS, AND MASTER BOXES IN THE POQUONNOCK BRIDGE FIRE DISTRICT
SPECIFICATIONS FOR THE INSTALLATION OF FIRE ALARM SYSTEMS, SPRINKLER SYSTEMS, AND MASTER BOXES IN THE POQUONNOCK BRIDGE FIRE DISTRICT The purpose of these specifications is to insure that there are minimum
More information16300 MEDIUM VOLTAGE DISTRIBUTION
16300 MEDIUM VOLTAGE PART 1: GENERAL 1.01 SYSTEM DESCRIPTION A. Most new loads will be served from the underground electric distribution system. This system is a primary open loop configuration served
More informationELECTRICAL GUIDELINES FOR SINGLE-FAMILY HOME OWNERS:
ELECTRICAL GUIDELINES FOR SINGLE-FAMILY HOME OWNERS: Chapter 12 of the Burlington Code of ordinances allows owner occupants of single family homes to do their own wiring if they choose. If you choose to
More informationDIVISION 2 - SEWERAGE AND DRAINAGE SECTION 02720 - STORM DRAIN SYSTEMS PART 1 - GENERAL
DIVISION 2 - SEWERAGE AND DRAINAGE SECTION 02720 - STORM DRAIN SYSTEMS PART 1 - GENERAL 1.01 DESCRIPTION A. Furnish and install all storm drains, including manholes, inlets, service lines and other appurtenant
More informationCCU Engineering Specifications. Section 003300 PRECAST CONCRETE PRODUCTS
CCU Engineering Specifications Section 003300 Effective Date: Nov. 1st, 2011 Page 1 of 5 PRECAST CONCRETE PRODUCTS PART 1 - GENERAL The following specification is intended for use for the design, selection
More information26 0533 Raceway and Boxes for Electrical Systems Page 1 of 7
Last Update: November, 2015 A. Conduits: Consultant s Handbook Page 1 of 7 1. All conductors for each and every electrical system shall be installed in a raceway except communications and A/V systems which
More informationThe National Armored Cable Manufacturers Association Presents. Installation Standard for Types AC and MC Cables
The National Armored Cable Manufacturers Association Presents Installation Standard for Types AC and MC Cables An ANSI Standard Original document jointly produced by NECA and NACMA as Standard for Installing
More informationCivil. 2. City of Seattle Supplement to the Specification for Road, Bridge and Municipal Construction, most current addition.
Design Guide Basis of Design This section applies to the design and installation of earthwork and backfill. Design Criteria No stockpiling of excavation materials is allowed unless the Geotechnical Engineer
More informationTown House 11265 Center Highway North Huntingdon, PA 15642
APPENDIX C SPECIFICATIONS FOR THE CONSTRUCTION OF BUILDING LATERAL SANITARY SEWERS DECEMBER 2004, INCLUDING AMENDMENTS ADOPTED ON FEBRUARY 6, 2008 AND APRIL 2, 2008; EFFECTIVE ON MAY 1, 2008 Town House
More informationSECTION 02530 STORM DRAINAGE STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.
02530-1 of 5 SECTION 02530 STORM DRAINAGE STRUCTURES 02530.01 GENERAL A. Description Storm drainage structure construction shall include, but not necessarily be limited to, furnishing and installing or
More informationSECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.
02150-1 of 6 SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING 02150.01 GENERAL A. Description Removal or abandonment of existing utilities and underground structures shall include, but not necessarily
More informationEXHIBIT "A. Technical Specifications for Water and Sewer Service Lines
EXHIBIT "A Technical Specifications for Water and Sewer Service Lines Water and Sewer Line Bedding and Backfill: Drawings show cross-section of trench, pipe laid on top of 6" min. bedding material, bedding
More informationSECTION 02763 POINT REPAIRS TO SANITARY SEWERS. A. Repairs to existing sewer lines by replacing short lengths of failed pipe.
SECTION 02763 PART 1 G E N E R A L 1.01 SECTION INCLUDES A. Repairs to existing sewer lines by replacing short lengths of failed pipe. 1.02 UNIT PRICES A. Measurement for point repairs is on a unit price
More informationDIVISION 26 - ELECTRICAL SECTION 26 05 20 CABLES FOR INSTRUMENTATION
DIVISION 26 - ELECTRICAL PART 1 - GENERAL 1.01 SUMMARY A. Section Includes 1. Instrumentation Cables 1.02 SUBMITTALS A. Submit in accordance with requirements of Section 01 33 00. B. Product Data: Submit
More informationSECTION 33 31 00.11 GRAVITY SANITARY SEWERS
SECTION 33 31 00.11 GRAVITY SANITARY SEWERS PART 1: GENERAL 1.01 SCOPE A. Gravity sanitary sewers and appurtenances. 1.02 SUBMITTALS A. Conform to requirements of Section 01 33 00 Submittals. B. Submit
More informationSECTION 18370 SIGNAL WIRE AND CABLE
SECTION 18370 PART 1 - GENERAL 1.01 DESCRIPTION A. Section includes requirements for all cable and wire required for signal and signal power system wiring to wayside shelters, junction boxes, and factory
More informationTABLE OF CONTENTS. PUD SERVICE TERRITORY & CONTACTS... Page 1. NEW SERVICE QUESTIONNAIRE... Page 2. GENERAL... Page 3
UNDERGROUND TABLE OF CONTENTS PUD SERVICE TERRITORY & CONTACTS... Page 1 NEW SERVICE QUESTIONNAIRE... Page 2 GENERAL... Page 3 TRENCHING SECONDARY (120/240 volts)... Page 3 CONDUITS FOR PUD-INSTALLED CONDUCTORS...
More informationINDEX. Sec. No. Items Page Nos.
INDEX Sec. No. Items Page Nos. 1. Types of Pipe............... MSSP- 2 2. Concrete Pipe............... MSSP- 2 thru MSSP-3 3. ABS and PVC Truss Pipe............... MSSP- 3 4. ABS and PVC Solid Wall Pipe...............
More informationCABLE TRENCH INSTALLATION GUIDE
1.0 INDEX 1.0 INDEX 2.0 PURPOSE 3.0 GENERAL INFORMATION 4.0 PLANNING INFORMATION 5.0 CREW INFORMATION 6.0 CONTRACTOR INFORMATION 7.0 PRECASTED/ POURED-IN-PLACE TRENCH DRAWINGS 2.0 PURPOSE This standard
More information505.3.6 For a building with a crawl space, see Figure 10. 505-1
505 WATER SERVICE INSTALLATION 505.1 DEFINITION A service line is comprised of the piping and related appurtenances including the connection installed from the Des Moines Water Works water main to the
More informationGUIDELINES FOR UTILITY INSTALLATIONS Part 1 - Wire Lines and Communications Cables
Engineering Department SEPTEMBER, 2007 GUIDELINES FOR UTILITY INSTALLATIONS Part 1 - Wire Lines and Communications Cables General Requirements This section applies to all public and private utilities,
More informationSpecifications for Residential Property Owners Connection to New Public Sewer
Specifications for Residential Property Owners Connection to New Public Sewer Spalding Tract property owners are required to connect to the community sewer system when construction is complete and the
More informationThe work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.
Section 33 0200- Page 1 of 4 PART 1 - GENERAL 1.1 DESCRIPTION OF WORK The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.
More informationEFFECTIVE FEBRUARY 2014. note: drainage permit required to call for a dampproof inspection
EFFECTIVE FEBRUARY 2014 note: drainage permit required to call for a dampproof inspection 1. ROOF DRAINS/DECK DRAINS (INTERIOR ) All roof and deck drains within the perimeter of the building shall be APPROVED
More informationSANITARY SEWER SPECIFICATIONS
SANITARY SEWER SPECIFICATIONS OCTOBER 2003 HARVEST-MONROVIA WATER, SEWER, AND FIRE PROTECTION AUTHORITY SECTION 1.00 1.10 Purpose The purpose of this document is to assemble the sewer specifications, policies,
More informationSECTION 22 LIGHTNING PROTECTION SYSTEM
SECTION 22 LIGHTNING PROTECTION SYSTEM 22.01 SCOPE: A. These Specifications shall form a part of the Contract Documents and shall govern construction work for all buildings to be built or modified for
More information1 Town of Lyons Electrical Distribution System Design Standards
Town of Lyons Electrical Distribution System Material and Design INDEX 6.1 Design Criteria 6.11 Submissions 6.1.2 Method 6.1.3 Criteria 6.2 Specifications 6.2.1 Scope 6.2.2 General Requirements 6.2.3 Materials
More informationCONSOLIDATED EDISON CO. OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003 DISTRIBUTION ENGINEERING DEPARTMENT SUBSTATION & EQUIPMENT SECTION
CONSOLIDATED EDISON CO. OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003 DISTRIBUTION ENGINEERING DEPARTMENT SUBSTATION & EQUIPMENT SECTION SPECIFICATION EO-5023 REVISION 3 MARCH 2003 REQUIREMENTS FOR
More informationSECTION 33 31 00.13 ABANDONMENT OF SEWER MAINS
SECTION 33 31 00.13 ABANDONMENT OF SEWER MAINS PART 1: GENERAL 1.01 SECTION INCLUDES A. Abandonment in place, by cutting and capping, of existing sewers, junction structures, manholes, service lines, and
More informationELECTRIC METERING COMMERCIAL & INDUSTRIAL
ELECTRIC METERING COMMERCIAL & 1.0 INDEX 1.0 INDEX 2.0 SCOPE 3.0 GENERAL REQUIREMENTS 4.0 METER LOCATIONS 5.0 UNDERGROUND TERMINATIONS 6.0 METERING TRANSFORMER ENCLOSURES 7.0 SINGLE CUSTOMER METER INSTALLATIONS
More informationSPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 11/5/13)
Page 1 of 7 STONE STRONG SYSTEMS SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised ) PART 1: GENERAL 1.01 Description A. Work includes furnishing and installing precast modular blocks
More informationChapter 7 Plumbing Connections
Chapter 7 Plumbing Connections 7-1 General All plumbing equipment and installations must be designed, constructed, and installed in accordance with this code and where not specific, to the applicable provisions
More informationSection 02702 SEWER PIPE INSTALLATION AND TESTING
PART 1 - GENERAL Section 02702 SEWER PIPE INSTALLATION AND TESTING 1-1. SCOPE. This section covers the installation and testing of all sewer pipe furnished under the following specification sections: Concrete
More informationSPECIAL SPECIFICATION 5757 Power Duct System
2004 Specifications CSJ 0353-04-088 SPECIAL SPECIFICATION 5757 Power Duct System 1. Description. This Item shall govern for the furnishing and installing of all materials, equipment, and labor listed in
More informationSection 402. STORM SEWERS
402.02 Section 402. STORM SEWERS 402.01. Description. This work consists of constructing storm sewers of the size and class required, including excavation, bedding, and backfill. 402.02. Materials. Provide
More informationSTANDARD SPECIFICATIONS FOR PRIVATE BUILDING SEWER LINES IN PUBLIC RIGHT-OF-WAY
STANDARD SPECIFICATIONS FOR PRIVATE BUILDING SEWER LINES IN PUBLIC RIGHT-OF-WAY Approved and adopted as Official Document Number 800576 this 10th day of December, 1980 Donald R. Boyd, P.E., Director Water
More informationDIVISION 4300 STORM DRAINAGE
DIVISION 4300 STORM DRAINAGE SECTION 4305 STORM SEWER PART 1 - GENERAL 1.01 SCOPE This section covers the construction of storm sewers for the collection and transport of stormwater runoff. 1.02 REFERENCES
More informationDESIGN AND INSTALLATION OF RESIDENTIAL FLEXIBLE DUCTWORK SYSTEMS
DESIGN AND INSTALLATION OF RESIDENTIAL FLEXIBLE DUCTWORK SYSTEMS A. SCOPE 1. This information is intended to assist contractors, installers and code officials in the proper design and installation of flexible
More informationBeacon Hill Sewer District Standard Specifications
Beacon Hill Sewer District Standard Specifications Residential Gravity Side Sewer Including Design Criteria and Standard Construction Drawings Residential Gravity Side Sewer Design Criteria 1. Provisions
More informationWastewater Collection System Supplemental Design Standards for Capital Improvement Program Projects
Wastewater Collection System Supplemental Design Standards for Capital Improvement Program Projects March 2013 i Metropolitan Sewer District of Greater Cincinnati Wastewater Collection System Supplemental
More informationGROWTH MANAGEMENT DEPARTMENT 201 SE 3 rd ST, (Second Floor), Ocala, FL 34471 (352) 629-8421; FAX: (352) 629-8264
BUILDING CODE GUIDELINES FOR ELECTRICAL INSPECTIONS Building Code compliance is the obligation of design professionals and/or contractors. Plan Review and Inspection Guidelines are intended to be used
More informationWastewater Capital Projects Management Standard Construction Specification
CITY AND COUNTY OF DENVER ENGINEERING DIVISION Wastewater Capital Projects Management Standard Construction Specification 10.1 Precast Concrete Pipe 10.1.1 General This section covers material requirements,
More informationSEPTIC SYSTEM CONSTRUCTION REQUIREMENTS ST. MARY S COUNTY HEALTH DEPARTMENT
SEPTIC SYSTEM CONSTRUCTION REQUIREMENTS ST. MARY S COUNTY HEALTH DEPARTMENT The following are minimum requirements for installation of conventional trench sewage disposal systems in St. Mary s County,
More information261000 Medium Voltage Electrical Distribution
Sections Included In This Standard: 1.1 General 1.2 Underground Cable 1.3 Medium Voltage Switches 1.4 Transformers 1.5 Electrical Manholes 1.6 Switch Vaults 1.7 Distribution Switchgear/Switchboards This
More information32-02.05 Precast Manhole Sections and Castings. These items shall conform to Section 31, "Storm Drain Installation," of these Standard Provisions.
SECTION 32: SANITARY SEWER INSTALLATION 32-01 SCOPE. The Work shall consist of furnishing and installing sewer mains, manholes, laterals, cleanout fittings and appurtenances; and testing, flushing and
More informationSECTION 15410 GROUND WATER STORAGE TANKS
SECTION 15410 GROUND WATER STORAGE TANKS PART 1 GENERAL.01 SCOPE A. Section Includes Requirements for designing, fabricating, and erecting a welded steel ground storage tank..02 SYSTEM DESCRIPTION A. Design
More informationELECTRIC DISTRIBUTION SYSTEMS ENERGY SERVICES DEPARTMENT TECHNICAL DESIGN AND CONSTRUCTION GUIDELINES AND STANDARDS
ELECTRIC DISTRIBUTION SYSTEMS ENERGY SERVICES DEPARTMENT TECHNICAL DESIGN AND CONSTRUCTION GUIDELINES AND STANDARDS JULY 2009 DIVISION 16 ELECTRICAL... 16050 General... 16111 Conduits-Primary Service (15
More informationSECTION 15076 CEMENT-MORTAR LINED AND COATED STEEL PIPE
SECTION 15076 CEMENT-MORTAR LINED AND COATED (CML&C) STEEL PIPE PART 1 GENERAL 1.01 DESCRIPTION This section designates the requirements for steel pipe fabrication, test in shop, installation of steel
More informationSECTION 31 20 00 EARTH MOVING
SECTION 31 20 00 PART 1 - GENERAL 1.01 DESCRIPTION A. This Section describes the requirements for excavating, filling, and grading for earthwork at Parking Structure, new exit stair and as required to
More informationA. Contractor shall furnish, to the Engineer, all materials certifications available from the manufacturer for all required materials.
PART 1 GENERAL 1.1 SCOPE A. This item shall include the work necessary for the installation of storm sewer line construction. B. Reference Section 3800 Trenching and Backfill and the General Conditions,
More informationIRRIGATION PUMPING Table of Contents - Section 900
IRRIGATION PUMPING Table of Contents - Section 900 PARAGRAPH 900.1 GENERAL 1 900.2 METERING REQUIREMENTS 1 900.3 CUSTOMER S CONTROL EQUIPMENT 2 900.4 SERVICE CONDUCTOR REQUIREMENTS 2 900.5 RECOMMENDATIONS
More informationDESIGN AND CONSTRUCTION GUIDELINES AND STANDARDS DIVISION 33 UTILITIES 33 00 00 SITE UTILITIES
SECTION INCLUDES Domestic Water Fire Water Service Water Well Sanitary Sewer Storm Drains Foundation Drainage RELATED SECTIONS 03 30 00 Concrete 21 00 00 Fire Suppression - Sprinklers 22 00 00 Plumbing
More informationUtilities and existing services
Construction Services Building standards for mechanical and electrical installations Utilities and existing services October 2012 Directorate: Environment Construction Services - Building standards for
More informationThermwire. Selection Guide. Freeze Protection Heating Cable. Thermwire -Wrap. Pre-Assembled. Thermwire-Comp. Thermwire-Melt.
Thermwire Freeze Protection Heating Cable Selection Guide Pipe Freeze Protection Heating Cable Pre-Assembled Pipe Freeze Protection Heating Cable with Attached Cord & Plug Thermwire-Comp Refrigeration
More informationSTRUCTURES. 1.1. Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.
STRUCTURES 1. General. Critical structures may impact the integrity of a flood control project in several manners such as the excavation for construction of the structure, the type of foundation, backfill
More informationHIGHLAND VALLEY SUPPLY, INC STANDARD TERMS AND CONDITONS OF SALE
Electrical Conduit & Fittings Catalog HIGHLAND VALLEY SUPPLY, INC STANDARD TERMS AND CONDITONS OF SALE Payment Terms: Payment terms are printed on every invoice. Invoices not paid in full by the net due
More informationReticulation sewers in basements Technical guidelines
Reticulation sewers in basements Technical guidelines Overview What These guidelines explain our technical requirements for laying sewers in building basements. The scope of the guide is restricted to
More informationUtility Distribution Systems
Utility Distribution Systems 6/2012 A0011037 1 WARRANTY This equipment is warranted to be free from defects in materials and workmanship, under normal use and service, for a period of 12 months from date
More informationREAD THIS MANUAL BEFORE PROCEEDING WITH THE INSTALLATION. FAILURE TO FOLLOW THE INSTALLATION INSTRUCTIONS MAY VOID YOUR WARRANTY!
READ THIS MANUAL BEFORE PROCEEDING WITH THE INSTALLATION. FAILURE TO FOLLOW THE INSTALLATION INSTRUCTIONS MAY VOID YOUR WARRANTY! The main power to any existing system must be disconnected prior to the
More informationSECTION 221413 FACILITY STORM DRAINAGE PIPING
SECTION 221413 FACILITY STORM DRAINAGE PIPING PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01
More informationAIR RELEASE, CLEANOUT, AND SEWER MANHOLES
AIR RELEASE, CLEANOUT, AND SEWER MANHOLES **From Hartford IM BLDG(10) DESCRIPTION. This work shall consist of the construction of air release, cleanout, and sanitary sewer manholes; and the furnishing
More informationCHAPTER 6 - SANITARY SEWER
CHAPTER 6 - SANITARY SEWER 6.1 GENERAL This section covers the requirements for PVC plastic sewer pipe materials and installation in sanitary sewer construction. 6.2 PIPE PVC gravity sewer pipe and fittings
More informationSIERRA LAKES COUNTY WATER DISTRICT P.O. Box 1039, Soda Springs, CA 95728-1039 (7300 Short Road, Serene Lakes)
SIERRA LAKES COUNTY WATER DISTRICT P.O. Box 1039, Soda Springs, CA 95728-1039 (7300 Short Road, Serene Lakes) Maintenance Office Administrative Office Billing Office 530-426-7802 530-426-7800 916-332-4872
More informationOPEN ITEMS LIST - CONSTRUCTION Project Name: East Central Middle School - Jackson County CLA#: 11003
OPEN ITEMS LIST - CONSTRUCTION Project Name: East Central Middle School - Jackson County CLA#: 11003 No. Discipline Sent to Name Item Date Noted Date Resolved How item was resolved Electrical Contractor
More informationResidential Electrical Inspection. Checklist
443 Lafayette Road N. St. Paul, Minnesota 55155 www.doli.state.mn.us Residential Electrical Inspection (651) 284-5064 1-800-DIAL-DLI Fax: (651) 284-5743 TTY: (651) 297-4198 Checklist Generally, Minnesota
More information