FALLING OBJECTS EXCESSIVE NOISE CHAINSAW & CHIPPER WORK AT HEIGHTS MANUAL HANDLING



Similar documents
Tremline Pty Ltd trading as The Hills Bark Blower

Risk Assessment: An introduction

WHS Contractor Management Procedure

EVENT RISK ASSESSMENT EXAMPLE / 04

RISK RATING SAFE WORK METHOD STATEMENT 1 HIGH 2 MEDIUM 3LOW. I approve the use of this Safe Work Method Statement: NAME: POSITION: Department Manager

Risk Assessment Tool (example only)

Chainsaw Training and Certification Program

Section 2 Hazard Assessment and Risk Control Table of Contents

SAFE WORK PROCEDURE SWP 015 WORKING AT HEIGHT SEPTEMBER 2013 DOC. NO. D13/248399

7. PRINCIPAL STEPS 8. POTENTIAL HAZARDS 9. RECOMMENDED CONTROLS

Hazard Management Tool

Hazard Identification, Risk Assessment And Control Procedure

Contractor s Safe Working Agreement

HAZARD IDENTIFICATION AND RISK ASSESSMENT PROCEDURES FOR DEEP SOUTH CRANE & RIGGING

WORKPLACE INDUCTION FOR CONSTRUCTION WORKPLACES INFORMATION SHEET 1

Tree Trimming, Removal & Replacement Policy Township of Springwater

SITE CONTRACTOR PROCEDURES

Job safety analysis Installing wall frames and roof trusses on-site

Kidd Mine Barricade Standards

POLICY ON OCCUPATIONAL HEALTH AND SAFETY RISK MANAGEMENT

Pollution Incident Response Plan

Excavation & Trenching Procedure

Contractor Environment, Health and Safety Management Plan

Night Games & Camp Fire

Entry Level Award in Workplace Hazard Awareness

MD 52 WASTE MANAGEMENT AUTHORITY CORPORATE HEALTH AND SAFETY PROGRAM

CONSTRUCTION SAFETY. NOTE: Barriers, guards, and warning signs are required to ensure safety against existing hazards.

Installation Instructions for Alarm Module Kit A043F059

Scaffold Standard (Standard to Managing and Appointing Scaffolding Contractors on University College London (UCL) Projects) Management Standard

GHD EPCM Standard operating procedure Working at height May 2013 v1

WHS Induction Series. 36 Toolbox Talks. Contents

The Tomato Plant Company Ltd. Method Statement and Risk Assessment Loads requiring lifting

CONTRACTOR INDUCTION HANDBOOK

Work Permits. A Health and Safety Guideline for Your Workplace. When is a Work Permit Needed? What is a Work Permit? Why use a Work Permit?

Example risk assessment for a motor vehicle mechanical repair workshop

Working at a height of two metres or more while carrying out general work activities or construction works

Temporary Worker Safety Checklist

CAER Construction and Environmental Resource

Team Skills Challenge Event # 1 Plant Layout Score Sheet

Job Hazard/Safety Analysis For the Housekeeper

Tech Shop Safety Level 2 - FN Tech Shop / Tool Safety Operations. (Fermilab machines not covered in course FN000258)

Uncontrolled if Printed

TEMPORARY EMPLOYEES SAFETY PROCEDURES

Independent Contractor Policy

Unit Title: Unit purpose and aim

Unit Title: Unit purpose and aim

Step 4. Monitor / Review Control Measures

Curtain Guards Made of PVC and designed to protect the operator from the risk of airborne chips or tool fragments.

GEORGIA INSTITUTE OF TECHNOLOGY ENVIRONMENTAL HEALTH AND SAFETY PERSONAL PROTECTIVE EQUIPMENT

OCCUPATIONAL HEALTH AND SAFETY RISK ASSESSMENT PROGRAM FOR AGRICULTURE

Job Hazard/Safety Analysis For the Grounds Keeper

Injury / Incident Investigation

A: SIGNIFICANT RISKS Initial Risk Rating H/M/L B: KEY CONTROL MEASURES ACTION

SPECIFIC SAFETY OBLIGATIONS FOR CONTRACTORS ENGAGED WITH THE CITY OF BUNBURY.

WHS CONTRACTOR MANAGEMENT PROCEDURE

Fact Sheet: Slips, trips and falls

A. a security guard B. a competent scaffold erector C. your boss D. the ship repair manager

WHS CONTRACTOR MANAGEMENT PROCEDURE

RISK RATING SAFE WORK METHOD STATEMENT 1 HIGH 2 MEDIUM 3LOW. I approve the use of this Safe Work Method Statement: NAME: POSITION: Department Manager

Notes. Material 1. Personal Protective Equipment 2.

GE Wind Turbine Climbing Rules and Rescue from Height

WORKING IN CONFINED SPACES GUIDELINES

Revision Date Reviewed By Authorised By. A 31/01/14 R McKeen P FitzPatrick Review Date 31/01/15 Change Details No Change Task

JOB SAFETY ANALYSIS WORK SHEET WORKING AT HEIGHTS, ROOF OR GUTTER WORK

Risk assessment (appendix 2 of the Event Registration Form)

Health & Safety Policy For Locations Hosting Film Production Companies

E3902 Seeing Accidents Before They Happen Leader s Guide

BILL WHYTE FLOORCOVERINGS LTD UNIT 5 KINGS COURT KING ST LEYLAND LANCS PR269RL. Tel: METHOD STATEMENT

Completed by: Technical Staff & Academic Staff. Adel Mitry, Michael Morris, Meloni Muir, Sharon Herkes, Isabel Arnaiz. Current version 01

Safe Driver. Information Sheet

POTENTIAL HEALTH & SAFETY HAZARDS

Names and Contact Numbers of Competent Rescuers Assigned to Job (Please print)

Discharging of Scrap

HealthandSafetyOntario.ca. What is a work permit? Why use a work permit? Types of work permits. When is a work permit needed?

SAFETY SIGNAGE PROCEDURE

PITTSBURG TANK AND TOWER CO., INC.

Company Name Company Address Company Phone Number Company Fax Number

Workplace Transport Safety Reversing Vehicles Information Sheet What are the dangers associated with reversing vehicles? Why is reversing a problem?

Hazard Identification, Risk Assessment and Control Procedure

Cycling: Track, Road and Bike Path

BRITISH GEOLOGICAL SURVEY

Safety Training Needs Assessment

Hazard Management Tool

STONEBRIDGE COMMUNITY FUNDAY

FPICOT2221A Trim and cross cut felled trees

Activity risk assessment Assessment title: New Generic Office environment

Powered Industrial Truck Safety Program

WORKSAFE VICTORIA A HEALTH AND SAFETY SELF-ASSESSMENT CHECKLIST FOR SMALL BUSINESS

The Application of Rope Access Methods in the Construction, Inspection, Repair and Maintenance of Wind Turbines

THE UNIVERSITY OF SHEFFIELD WORK AT HEIGHT POLICY

Level 1 Award in Health and Safety in a Construction Environment

Originator Date Section ID Description of Change Reason for Change

SPILL RESPONSE PROCEDURE

HEALTH & SAFETY HANDBOOK. No Body GetsHurt. Our Safety Slogan is:

A&W WATER - SUPERIOR ENERGY SERVICES, INC.

Method Statement. Risk Assessment

Safety and Environmental Information for External Companies Koehler Oberkirch

Slip, Trip & Fall Prevention Handbook

Safety Systems Review Facilities Management Guidance and specification Version

SAFETY in the work area is a broad topic because of the

Transcription:

JOB NO: PROJECT: DATE: SWMS NO: SWMS 001.1 PREPARED BY: Ian Hartley REVISED BY: Nick Bragg & Cameron McNeil ACTIVITY: TREE REMOVAL & PRUNING SIGNED BY: REVISION DATE: December 2015 MINIMUM PERSONAL PROTECTIVE EQUIPMENT (PPE) REQUIREMENTS PERSONAL PROTECTIVE EQUIPMENT TO BE USED HIGH VISIBILITY CLOTHING STEEL CAP SAFETY BOOTS GLOVES EAR PROTECTION SAFETY HELMET SAFETY FACE SHIELD (stumpers) CHAIN SAW PANTS CHAPS / KEVLAR SAFETY HARNESS (WHEN WORKING AT HEIGHTS) EYE PROTECTION MAJOR HAZARDS MAJOR HAZARDS WORK AT HEIGHTS FALLING OBJECTS MANUAL HANDLING CHAINSAW & CHIPPER EXCESSIVE NOISE Page 1 of 12

EMERGENCY PROCEDURE 1 In the event of injury or emergency appropriate contact to be made with manager, site manager and emergency services ( if required ) by company provided phone with numbers readily available 2 If work is to be stopped then work area is to be shut down and made safe (major injury only) no further works to be undertaken until given go ahead from authorities 3 In the event of any incident staff must fill out incident/accident report and return to manager or ohs officer 4 Crew leader and at least one other person will be trained to minimum First Aid Level 2 CLASSIFICATION DESCRIPTION 1 Little risk with potential for personal injury or plant damage being assessed as very unlikely. 2 Moderate risk with the potential for minor injuries requiring first aid treatment or temporary disability. Possible minor structural damage to plant. 3 High Risk with the potential for death, permanent disability or injuries requiring medical attention. Possibility of major structural damage to plant. Page 2 of 12

SITE SPECIFIC REQUIREMENTS STEPS A PROCESS - List the sequence of steps needed to complete the activity Contractors arrival on site. B Contractors leaving site. POTENTIAL HAZARDS - For each step list the actual and potential hazard(s). Lack of consultation with all stakeholders. Lack of understanding of the site Unknown hazards. Cause distress to staff if leaving site without notification before CONTROL (use hierarchy of control) - For each High (Class 1) or Medium (Class 2) Risk identify control measure(s) to reduce the risk to Low (Class 3) 1 Crew to adhere to speed limits Inductions/Toolbox/prestarts as required Sign in to contractors register at Reception Sign onto SWMS Sign onto permits and pre start meeting 1 Sign off Permits Report to Manager on completion of days work Sign out of Contractors register after RESPONSIBLE PERSONS 1 Supervisor Crew Leader Crew members 1 Supervisor Crew Leader Crew members Page 3 of 12

HAZARD IDENTIFICATION, ASSESSMENT & CONTROL STEPS PROCESS - List the POTENTIAL HAZARDS - sequence of steps needed For each step list the actual and to complete the activity potential hazard(s). 1 Consultation and task assessment. 2 Check the work site for hazards and plan work task. Lack of consultation with all stakeholders. Lack of understanding of the required tasks. Unknown hazards. Incorrect personal protective equipment (PPE). Crew not trained or maintaining appropriate experience to perform task. Hanging branches and other debris. Poor housekeeping. Vehicle and pedestrian movements. Environmental conditions (wind, rain, heat, etc). Residents, cars, light poles before CONTROL (use hierarchy of control) - For each High (Class 1) or Medium (Class 2) Risk identify control measure(s) to reduce the risk to Low (Class 3) 1 Crew to complete hazard identification and control form for work task. Review all requirements of the OHS. Regs. (2007) High-risk work. Identify task hazard and risks. Identify and implement control in accordance with the Hierarchy of Controls. Identify appropriate PPE requirements e.g boots, hi-vis vests, protective clothing, ear muffs, helmets, glasses. Ensure staff have appropriate training and experience to perform task. Provide appropriate training prior to commencing works if required. 2 Adhere to speed limits on site Inspect site thoroughly & identify where light poles as located. Conduct hazard identification assessment and control form (HAC sheet). Identify traffic management requirements and establish traffic management plan if required. Install barricades to prevent unauthorized persons or residents entering worksite. Residents may require to shift vehicles to prevent obstruction to work site. Obtain appropriate PPE requirements e.g boots, hi-vis vests, protective clothing, ear muffs, helmets, glasses. after RESPONSIBLE PERSONS 1 Supervisor Crew Leader Page 4 of 12

STEPS PROCESS - List the sequence of steps needed to complete the activity 3 Establish and secure worksite. POTENTIAL HAZARDS - For each step list the actual and potential hazard(s). Hanging branches and other debris. Poor housekeeping. Vehicle / pedestrian movements before Identify weather conditions will be suitable for required tasks. CONTROL (use hierarchy of control) - For each High (Class 1) or Medium (Class 2) Risk identify control measure(s) to reduce the risk to Low (Class 3) 2 Implement work site hazard as per JSA s Implement traffic management plan. Issue all required PPE to relevant staff e.g boots, hi-vis vests, protective clothing, ear muffs, helmets, glasses.. Identify escape routes. Install barricades to prevent unauthorized persons entering worksite. after RESPONSIBLE PERSONS 4 Obtain all required equipment and move to work site. Strains, sprains and crush injuries. Cuts, grazes and bruises. Fuel and oil spills. Vehicle and pedestrian movements. 2 Conduct all manual handling tasks in accordance with appropriate process. Ensure all PPE e.g boots, hi-vis vests, protective clothing, ear muffs, helmets, glasses, long sleeves and long pants is of good condition, issued to all staff and being worn correctly. Remove / control all potential hazards within work site. Spill kit for fuel or oil spills Deploy safety observer to monitor movements of vehicle and pedestrians. Page 5 of 12

5 Inspect and start all equipment. (Continued) STEPS PROCESS - List the sequence of steps needed to complete the activity Strains, sprains and crush injuries. Cuts, grazes and bruises. Fuel and oil spills. Eye and ear damage. Entanglement, crush injuries and burns. Machinery and equipment failure. POTENTIAL HAZARDS - For each step list the actual and potential hazard(s). 5 (Continued) Vehicle / pedestrian movement Crew not trained / experienced to perform require task. 6 Climber/tower and crew to engage tree with all safety equipment and conduct tree pruning / removal activities. Strains, sprains and crush injuries. Cuts, grazes and bruises. Fatigue and dehydration. Fuel and oil spills. Eye and ear damage. Entanglement, crush injuries and burns. Machinery and equipment failure. Vehicle / pedestrian movement Personnel and objects falling 2 Conduct all manual handling tasks in accordance with appropriate process. Ensure all PPE e.g boots, hi-vis vests, protective clothing, ear muffs, helmets, glasses, long sleeves and long pants is of good condition, issued to all staff and being worn correctly. Spill kit for fuel or oil spills Employ safety observer to monitor movements of vehicle and pedestrians. Barricade area when working on or near roads Complete all pre start equipment and machinery checks. before CONTROL (use hierarchy of control) - For each High (Class 1) or Medium (Class 2) Risk identify control measure(s) to reduce the risk to Low (Class 3) Remove any faulty equipment or machinery from service. Start and operate all equipment in accordance with manufacturer s operator s manuals. Ensure staff have appropriate training and experience to perform task. As per list on page 9 3 Induct all crew members into site hazards and work plan. Conduct all manual handling tasks in accordance with appropriate process. Ensure all PPE e.g boots, hi-vis vests, protective clothing, ear muffs, helmets, glasses is of good condition, issued to all staff and being worn correctly. Deploy safety observer to monitor movements of vehicle and pedestrians. Operate all equipment in accordance with manufacturer s operator s manuals. Spill kit for fuel or oil spills Ensure staff have appropriate training and experience to perform task after RESPONSIBLE PERSONS Page 6 of 12

STEPS PROCESS - List the sequence of steps needed to complete the activity from height. Tree not dismantling in anticipated manner. Unanticipated weight loads and felling directions. Bites and stinging animals and insects. POTENTIAL HAZARDS - For each step list the actual and potential hazard(s). 6 (continued) Unanticipated weight loads and felling directions. Bites, stinging animals, insects. Tree condition of worse condition than anticipated. Environmental conditions (wind, rain, heat, etc). 7 Wood / branch Strains, sprains and crush chipping, debris injuries. removal and site Cuts, grazes and bruises. cleanup. Fatigue and dehydration. Eye and ear damage. Entanglement, crush injuries and burns. Machinery and equipment failure. Vehicle and pedestrian before All equipment and materials to be tethered to stop objects falling from heights as per Global EH&S Alert. Rest and rehydrate as required. Utilise effective methods of communication between all crew members. Ensure all equipment and personnel required at heights are properly secured. Conduct works in accordance with company procedures and policies and industry best practice. Identify weather conditions are suitable for required tasks. CONTROL (use hierarchy of control) - For each High (Class 1) or Medium (Class 2) Risk identify control measure(s) to reduce the risk to Low (Class 3) Ensure appropriate felling, pruning, rigging and lowering techniques are implemented. Constantly look for animals and insects within the work site. 3 Conduct all manual handling tasks in accordance with appropriate process. Ensure all PPE e.g boots, hi-vis vests, protective clothing, ear muffs, helmets, glasses is of good condition, issued to all staff and being worn correctly. Deploy safety observer to monitor movements of vehicle and pedestrians. Operate all equipment in accordance with manufacturer s operator s manuals. Ensure staff have appropriate training and experience to perform task Rest and rehydrate as required. after RESPONSIBLE PERSONS Page 7 of 12

movements. Personnel and objects falling from height. Heavy lifting / dragging. Projectiles from chipper. Bites and stinging animals and insects. Stick injuries. Utilise effective methods of communication between all crew members. Conduct works in accordance with company procedures and policies and industry best practice. Identify weather conditions will be suitable for required tasks. Observe for biting / stinging animals and insects within the work site. Employ good site housekeeping and remove potential trip and stick injury hazards as they are observed. STEPS PROCESS - List the sequence of steps needed to complete the activity 8 Cutting of trunk wood and transporting to wood chipper. 9 Site cleanup and retrieval of equipment POTENTIAL HAZARDS - For each step list the actual and potential hazard(s). Strains, sprains and crush injuries. Cuts, grazes and bruises. Fatigue and dehydration. Eye and ear damage. Heavy lifting / dragging. Projectiles from chipper. Strains, sprains and crush injuries. Cuts, grazes and bruises. Fatigue and dehydration. Eye and ear damage. before CONTROL (use hierarchy of control) - For each High (Class 1) or Medium (Class 2) Risk identify control measure(s) to reduce the risk to Low (Class 3) 3 Conduct all manual handling tasks in accordance with appropriate process. Ensure all PPE e.g boots, hi-vis vests, protective clothing, ear muffs, helmets, glasses is of good condition, issued to all staff and being worn correctly. Operate all equipment in accordance with manufacturer s operator s manuals. Rest and rehydrate as required. Use appropriate numbers of personnel or mechanical aids for heavy lifting tasks. Reduce debris weight loads through size reduction. 2 Conduct all manual handling tasks in accordance with appropriate process. Ensure all PPE e.g boots, hi-vis vests, protective clothing, ear muffs, helmets, glasses is of good condition, issued to all staff and being worn correctly. Stow equipment in appropriate location after RESPONSIBLE PERSONS Page 8 of 12

Heavy lifting / dragging. Reduce debris weight loads through size reduction. All employees to make sure work area are left in a safe condition. All surplus material and rubbish to be cleaned up and put into trailer. LEGISLATION, CODES OF PRACTICE & STANDARDS LEGISLATION CODES OF PRACTICE STANDARDS Occupational Health & Safety Act 2004 Occupational Health & Safety Regulations 2007 Construction Regulations 2008 Dangerous Goods Act 1985 Road Management Act 2004 Code of practice - Safe work at Heights Code of practice - Manual Handling Code of Practice - Plant Code of Practice Amenity Tree Industry Code of Practice Working Safely With Trees AUS/NZ Standards 4576 Guidelines to Scaffolding AS 4373-2007 Pruning of Amenity Trees AS 1470-1986 Wealth and Safety at Work Principles and Practices AS 4970-2009 Protection of Trees on Development Sites PLANT & EQUIPMENT PLANT & EQUIPMENT TO BE USED Tipper / Chipper unit,ewp, utility, chainsaws, blowers, hedgers, climbing spurs and harness, climbing equipment hardware (karabiners, pulleys, ascenders, mellions, prussic loops, etc), ropes, lowering devices, hand held tools, traffic control devices, PPE., Spill Kit. Petrol / Oil fire extinguisher All equipment checked on a regular basis TRAINING & COMPETENCE Page 9 of 12

TRAINING / COMPETENCE REQUIRED All personnel to be suitably trained, experienced or inducted into the safe operation and maintenance of all plant and equipment used for the undertaking of daily work tasks to the satisfaction of Team Leader and General Manager.All training on Pegasus cards or matrix can be supplied if requested. All crews to have minimum 2 staff with first aid training (min level 2) HAZARDOUS MATERIALS HAZARDOUS MATERIAL MSDS ON FILE Bar Oil Diesel Two Stroke Oil Unleaded Petrol Hydraulic Oil HIERARCHY OF CONTROL ACTION DESCRIPTION Elimination This is the desired option when controlling risk, as by eliminating the hazard no further control is required. Substitution This option includes such actions as substituting a hazardous substance or chemical for a less hazardous one Isolation This option includes such actions as lock out tag out procedure Engineering This option includes such actions as the placement of a barrier or guard to protect workers from a process Administration This option is concerned with use of warning signs, training and procedures and is usually included in all of the above more desirable actions to control a hazard Page 10 of 12

PPE This option is most commonly used of all HOWEVER IT IS THE LEAST DESIRED as it does not remove the hazard and it requires the worker to wear the PPC&E EMPLOYEE SIGN OFF I have been involved in the development of this Work Method Statement and understand the requirements EMPLOYER EMPLOYEE SIGNATURE DATE CREW LEADER SAFETY SUPERVISOR SIGN OFF I have been involved in the development of this Safe Work Method Statement and understand the requirements Page 11 of 12

EMPLOYER EMPLOYEE SIGNATURE DATE Page 12 of 12