2 Table of contents 1. Purpose 2. Scope 3. Duty of care 4. Lifesaving rules; An overview 5. Roles and responsibilities 4.1 Operating centre manager (OCM) 4.2 Project director (PD) 4.3 Job manager (JM) 4.4 Staff 6. Procedures 7. References 8. Definitions

3 1. Purpose The purpose of this document is to set out the minimum requirements for GHD staff, visitors and contractors engaged on behalf of GHD to safely assess and manage works at height. Consideration must be given to existing client measures for controlling work at height when visiting any site which is controlled by another party. 2. Scope This procedure applies to all GHD employees, contractors and visitors for the purpose of carrying out work activities sanctioned by the practice management group where GHD is engaged in the role of engineering, procurement and construction management. GHD has a duty to provide a safe work place and protect life and property to all staff requiring access to or entering a GHD controlled site or office. 3. Duty of care GHD has a duty of care to control any risks associated with work at height under the Model work health and safety Act: As such, GHD shall aim to eliminate risks from work at height wherever possible. Where this is not possible, GHD shall aim to minimise risks so far as is reasonably practicable. 4. Lifesaving Rules; An overview The aim of this procedure is to control the risks associated with hot work in the workplace. It aims to identify controls which can assist to identify, eliminate, control and otherwise minimise risks to people, premises and the environment which may arise from hot works. 1. Avoid hot works as the first option 2. Anyone undertaking or supervising hot works must be trained to do so 3. An emergency response plan must be in place 4. A safety plan must detail controls for the works being undertaken 5. The environment will be checked before work and monitored during work 6. No works shall take place where oxygen levels are outside of 19.6%- 22.8% in the atmosphere. 7. The smallest possible quantities of hazardous substances shall be used to perform the task 8. Fire resistant barriers shall be in place 9. Permit to work must be implemented 10. Where isolation of services or equipment is needed, a lock out/tag out system shall be implemented 11. All affected parties shall attend a pre start meeting 12. The GHD job manager shall act as coordinator of activities 13. Barriers and signage must be in place 14. Health monitoring shall be in place where there is any risk of exposure 15. PPE shall be provided relevant to identified risks

4 Work at height permit process Does the proposed job involve: Works which present the risk of a fall between levels, or objects falling between levels Yes No Not work at height Access equipment required? No Yes Permit to work required Does the contractors safety plan meet the requirements of all SOP minimum standards? Yes implement pre work controls No Contractor to review and resubmit safety plan Are barriers in place? Fixed scaffold verified as safe by a licensed contractor? OR Access equipment fit for purpose and in place? Emergency procedures (including rescue plan) in place? Issue work at height permit alongside other permits required Pre start meeting all site made aware of no go zone Go to work Changed condition STOP WORK and surrender permit Works complete Make safe and surrender permit

5 5. Roles and responsibilities OC manager Support the project director to resource the works Project director Ensure funds and preliminary information is gathered with support of the client. Implementation of the HSE project systems. Ensure that staff are trained and competent for their roles Development of permit to work system, Job manager Review of contractors Safe systems of work Implement Lock out/ Tag out system Inducting new staff, visitors and contractors to project hazards Act as liaison to all trades affected by hot works Pre start briefings Issue of permit to work Undertake pre work assessment of hot work risks Contractor Implement emergency procedures Submission of documentation to GHD. Ability to prove the use of only competent staff. Select smallest quantities of hazardous substances needed to complete the task Monitor exposure levels in the workplace Arrange for health monitoring Supply of PPE Incorporation into the GHD permit to work system Be inducted project Staff Attend pre start meetings Assist in creation of safety plans Only operate in areas where they are trained Creation of the permit to work and lock out / tag out system HSE function Review safe systems of work as required Attend pre start meetings as required 6. Procedures This standard operating procedure draws guidance from ging_the_risk_of_falls_at_workplaces.pdf. When operating on a GHD site, the Job manager shall first establish if the need for work at height can be eliminated. GHD shall aim to eliminate work at height wherever reasonably practicable. When any work at height is being conducted on a GHD managed or operated site, the GHD Job manager shall first consider the hierarchy of controls when assessing any contractor safety plan. Where it is deemed that any work at height must take place which involves the use of equipment or plant to reach the working height, or where there is a risk of falls to a hazardous area, a permit to work shall be issued. Any site or project controlled and operated by GHD shall relay all known hazardous conditions to any sub-contractor prior to any work at height taking place. The project manager shall provide this information through induction to the project. This shall include

6 high risk areas which have previously been identified from site establishment and are deemed No go areas. From this, a safe system of work (or safe work method statement for high risk works as described in the Model WHS act) shall be established to complete the task by the person responsible for undertaking the works and their supervisor. In the case of a GHD undertaking works on a GHD site, the safe system of work shall be developed by the employee undertaking. Safe systems of work shall be in the form of a task specific risk assessment. Any safe system of work involving work at height shall list controls for; Safe access (This shall include selection of access equipment) Competency required for operators (Licensed scaffolder MANDATORY FOR SCAFFOLDS OF 4M AND OVER, plant operator) Monitoring of work conditions (Scaffold checks pre work, after changes and periodic, equipment checks) Isolation of other parties from height risks (See barriers ) Emergency planning (In line with site emergency plans ) Safe egress from the area Communication methods Any safety plans shall also list controls relating specifically to the task to be performed, including measures to protect workers and all other parties from associated risks. Any operative involved in work at height activities must have specific training and licensing to their role. The GHD job manager shall consult all effected workers through a pre start meeting. This shall highlight the hazards associated with the task, and the controls in place. As a minimum standard, when any work at height is to be undertaken, the area below shall have a barrier in place to restrict access by non-essential workers. When undertaking work at height to complete an associated high risk activity, a separate permit shall be issued in line with the relevant SOP. Any work at height which also involves hot work as a minimum standard must take place from a fixed stationary platform. Review of contractors risk assessment Before any works may begin, or any permit to work issued, the GHD job manager shall review the contractors proposed methodology. When work at height is involved, the following controls shall be implemented as a minimum standard. Where work can be performed at ground level, this shall be the first option. If part of the task can be performed at ground level to minimise work at height, this shall be implemented. A fixed platform shall be the first consideration as a working platform. Any fixed platform shall be erected and maintained by a licensed scaffolder. Forms of access to be considered as preferable shall be, Elevated work platforms, mobile tower scaffolds, enclosed work baskets. Ladders shall be used as a means of access and egress only and must be secured. Any work platform shall be enclosed by a fixed top and middle rail with a toe board in line with local standards.

7 The use of fall restraint systems shall be used for any works involving a risk of falling of 3 metres or below, and only when other options have been deemed reasonably impracticable. Fall arrest systems shall be used only as a final resort and must have a provision of rescue in the event of falls in the contractor safety plan. Any fall rescue plan must provide trained and competent people to perform the task. Where plant is to be brought onto site, it must conform to the requirements set in the Contractor, plant and equipment selection SOP alongside any requirements of the Environment SOP. Any anchor points or lifting equipment (Including harnesses, lanyards and anchor points must meet the criteria stated in the SOP Lifting equipment. When working in an area where work at height is being undertaken, all workers shall wear a safety helmet and safety capped boots as a minimum requirement. Where there is a risk to existing plant, equipment or facilities resulting from objects falling from height, all tools and equipment shall be secured to an anchor point capable of supporting them in the event of them falling from the work platform. This may be secured to a worker in the case of hand tools, on the provision that it would not impact upon the restraint system in place. In the event of any incident or injury to a field operative, GHD incident reporting procedures will be followed. 7. References Model work health and safety Act: ned_spaces.pdf Model Code of Practice Managing the risks of falls at workplaces ging_the_risk_of_falls_at_workplaces.pdf GHD documents and forms: Standard operating procedure Permit to work Standard operating procedure Barriers Standard operating procedure Emergency plans Standard operating procedure Contractors, plant and equipment selection Standard operating procedure Environment Standard operating procedure Lifting equipment

8 8. Definitions Work at height Works which present the risk of a fall between levels, or objects falling between levels Emergency plan: Arrangements for assistance in the event of an emergency, in this case, recovery of a person and arrangements for treatment following injury or exposure. Lock out/ Tag out; A system of isolating services of equipment which prevents accidental re activation Permit to work; A system which imposes controls and conditions for completion of a task, specifically related to high risk works.

PORT HEDLAND PORT AUTHORITY

PORT HEDLAND PORT AUTHORITY PORT HEDLAND PORT AUTHORITY Working at Heights Procedure PR-OHS021 Document Users : All Contractors All Port Users Port Hedland Port Authority Position Responsible For Keeping Document Current : Safety

More information

SECTION 2 HAZARDOUS WORK. CLASSIC STANDARD 2.04 Working at Heights

SECTION 2 HAZARDOUS WORK. CLASSIC STANDARD 2.04 Working at Heights SECTION 2 HAZARDOUS WORK CLASSIC STANDARD 2.04 Working at Heights 1 Purpose The purpose of this standard is to document Rio Tinto Aluminium Mining & Refining Weipa s requirements to minimise, and where

More information

Document ref: MG(M)201 Version no: 01 Page no: 1 / 12. Contractor rules

Document ref: MG(M)201 Version no: 01 Page no: 1 / 12. Contractor rules Page no: 1 / 12 Contractor rules Table of Contents Purpose... 2 Scope... 2 1. Responsibilities... 2 2. Planning Stage... 3 3. Site induction, emergency procedures and documentation... 3 4. Risk Assessment

More information

THE UNIVERSITY OF SHEFFIELD WORK AT HEIGHT POLICY

THE UNIVERSITY OF SHEFFIELD WORK AT HEIGHT POLICY THE UNIVERSITY OF SHEFFIELD WORK AT HEIGHT POLICY CONTENTS Page No 1 INTRODUCTION 2 2 LEGISLATION 2 3 HIERARCHY OF CONTROL 2 4 WORK AT HEIGHT POLICY 3 5 ROLES AND RESPONSIBILITIES 3 6 RISK ASSESSMENTS

More information

RISK RATING SAFE WORK METHOD STATEMENT 1 HIGH 2 MEDIUM 3LOW. I approve the use of this Safe Work Method Statement: NAME: POSITION: Department Manager

RISK RATING SAFE WORK METHOD STATEMENT 1 HIGH 2 MEDIUM 3LOW. I approve the use of this Safe Work Method Statement: NAME: POSITION: Department Manager RISK RATING 1 HIGH 2 MEDIUM 3LOW SAFE WORK METHOD STATEMENT Title: : Working at Height above 2trs Ref No: 1 I approve the use of this Safe Work Method Statement: NAME: POSITION: Department Manager SIGNATURE:

More information

WORK AT HEIGHT UNIT 4

WORK AT HEIGHT UNIT 4 WORK AT HEIGHT UNIT 4 WHAT IS WORKING AT HEIGHT? The Working At Height Regulations 2005 define working at height as:- Any work above or below ground level where a fall would result in personal injury.

More information

Scaffold Standard (Standard to Managing and Appointing Scaffolding Contractors on University College London (UCL) Projects) Management Standard

Scaffold Standard (Standard to Managing and Appointing Scaffolding Contractors on University College London (UCL) Projects) Management Standard Scaffold Standard (Standard to Managing and Appointing Scaffolding Contractors on University College London (UCL) Projects) Management Standard UNIVERSITY COLLEGE LONDON Engineering, Maintenance & Infrastructure

More information

COURSE INFORMATION SHEET

COURSE INFORMATION SHEET Course ID: HGT - WRKHT COURSE OVERVIEW WORKING AT HEIGHTS Working at Heights is an approved Ontario Ministry of Labour (MOL) program (Approved Training Program ID # WAH56789). This program was designed

More information

Good Practice Guide. The Selection of Access Methods to Install and Dismantle Safety Netting

Good Practice Guide. The Selection of Access Methods to Install and Dismantle Safety Netting Good Practice Guide The Selection of Access Methods to Install and Dismantle Safety Netting FASET is the trade association for the safety net rigging and temporary safety systems industry. This document

More information

Work at Height. John Frontczak Construction Manager Facilities Engineering. 2011 Chevron Corporation. All rights reserved.

Work at Height. John Frontczak Construction Manager Facilities Engineering. 2011 Chevron Corporation. All rights reserved. Today Work at Height John Frontczak Construction Manager Facilities Engineering Agenda Definition and Requirements Fall Prevention Scaffolding Safety Fall Protection Fall-Arrest System Rescue Plan Training

More information

Safety Systems Review Facilities Management Guidance and specification Version 1 2014

Safety Systems Review Facilities Management Guidance and specification Version 1 2014 Safety Systems Review Facilities Management Guidance and specification Version 1 2014 Membership Training Qualifications Audit and Consultancy Policy and Opinion Awards Contents Page Safety Systems Review

More information

WORKING IN CONFINED SPACES GUIDELINES

WORKING IN CONFINED SPACES GUIDELINES WORKING IN CONFINED SPACES GUIDELINES Contents 1 Introduction... 2 2 Scope... 2 3 Definitions... 2 4 Responsibilities... 3 4.1 Permit Authoriser... 3 4.2 Permit Receiver... 3 4.3 Responsible UOW Officer...

More information

WORKING AT HEIGHT GUIDELINES. Version II

WORKING AT HEIGHT GUIDELINES. Version II WORKING AT HEIGHT GUIDELINES Version II 21 st September 2011 WORKING AT HEIGHT GUIDELINES EXECUTIVE SUMMARY Working at height is where an individual is carrying out work in any place in the course of obtaining

More information

Golden Safety Rules booklet. No one gets hurt, no incidents

Golden Safety Rules booklet. No one gets hurt, no incidents Golden Safety Rules booklet No one gets hurt, no incidents The Golden Safety Rules exist to keep you safe There s nothing more important than your safety and that of your workmates. That s why we ve adopted

More information

Working at Height. Procedure

Working at Height. Procedure Procedure *All Forth Valley College Health, Safety and Welfare Procedures are covered under the overarching Health, Safety and Welfare Policy. Status: Date of version: Reviewed by: Author/Contact Person;

More information

68 Metal Industry Guidelines for Safe Work

68 Metal Industry Guidelines for Safe Work 3 68 Metal Industry Guidelines for Safe Work section 3 high-risk 3 activities Metal Industry Guidelines for Safe Work 69 section 3 high risk activities 3.1 working at heights Falls from heights have been

More information

SAFE WORK ON ROOFS PART 1: COMMERCIAL AND INDUSTRIAL BUILDINGS. making a difference CODE OF PRACTICE 2009. New South Wales Government

SAFE WORK ON ROOFS PART 1: COMMERCIAL AND INDUSTRIAL BUILDINGS. making a difference CODE OF PRACTICE 2009. New South Wales Government SAFE WORK ON ROOFS PART 1: COMMERCIAL AND INDUSTRIAL BUILDINGS CODE OF PRACTICE 2009 making a difference New South Wales Government Disclaimer This publication may contain occupational health and safety

More information

WORKPLACE INDUCTION FOR CONSTRUCTION WORKPLACES INFORMATION SHEET 1

WORKPLACE INDUCTION FOR CONSTRUCTION WORKPLACES INFORMATION SHEET 1 WORKPLACE INDUCTION FOR CONSTRUCTION WORKPLACES INFORMATION SHEET 1 Overview This Information Sheet provides advice for persons conducting a business or undertaking (PCBUs) including builders and principal

More information

WORK AT HEIGHT. STFC Safety Code No 9. Rev. 1.4, Issued April, 2015

WORK AT HEIGHT. STFC Safety Code No 9. Rev. 1.4, Issued April, 2015 WORK AT HEIGHT STFC Safety Code No 9 Rev. 1.4, Issued April, 2015 Note - This document may have been superseded by a more recent version. Revisions 1 Initial Launch November 2007 1.1 Amendments to training

More information

Tremline Pty Ltd trading as The Hills Bark Blower

Tremline Pty Ltd trading as The Hills Bark Blower JSA No: Rev: 10011 Date: 10010 ABN 1 07 880 6 Website: wwwbarkblowercomau Job Number Start Time: Vehicle : Max Length Hose Date: Company Name: Product: Quantities Depth Job site address: Description of

More information

Fall Protection, Title 29 Code of Federal Regulations (CFR) Part 45, Subpart M, Fall Protection, 1926.500, 1926.501, 1926.502, and1926.

Fall Protection, Title 29 Code of Federal Regulations (CFR) Part 45, Subpart M, Fall Protection, 1926.500, 1926.501, 1926.502, and1926. STANDARDS Fall Protection, Title 29 Code of Federal Regulations (CFR) Part 45, Subpart M, Fall Protection, 1926.500, 1926.501, 1926.502, and1926.503 1.0 Purpose This document meets the requirements outlined

More information

WHS Contractor Management Procedure

WHS Contractor Management Procedure Wudinna District Council 1. Overview Wudinna District Council as part of its commitment under its Policy recognises its obligation to: Ensure, so far as is reasonably practicable, the health and safety

More information

WHS Contractor Management Procedure

WHS Contractor Management Procedure Procedure Approved: 09/07/2013 Next Review: 09/07/2015 1. Overview The District council of Mount Remarkable Council is committed to engaging quality Contractors who have a sound understanding and commitment

More information

Procedural Guidance for Roof Access/Roof Work

Procedural Guidance for Roof Access/Roof Work University of Central Lancashire Safety, Health & Environment Section Procedural Guidance for Roof Access/Roof Work Document Number: FM/HSE 001 Revision Number: 2 Review Date: August 2005 Reviewed by:

More information

HEALTH AND SAFETY POLICY LEWIS & RABY ENGINEERS LTD

HEALTH AND SAFETY POLICY LEWIS & RABY ENGINEERS LTD HEALTH AND SAFETY POLICY LEWIS & RABY ENGINEERS LTD Birchall Road Knowsley Industrial Estate Liverpool L33 7TG TABLE OF CONTENTS STATEMENT OF SAFETY POLICY... 3 STATEMENT OF INTENT... 4 HEALTH & SAFETY

More information

Working at height A brief guide

Working at height A brief guide Working at height A brief guide Introduction This brief guide describes what you, as an employer, need to do to protect your employees from falls from height. It will also be useful to employees and their

More information

NZQA registered unit standard 23229 version 4 Page 1 of 6

NZQA registered unit standard 23229 version 4 Page 1 of 6 Page 1 of 6 Title Use safety harness system when working at height Level 3 Credits 4 Purpose People credited with this unit standard are able to: demonstrate knowledge of the hazards associated with wearing

More information

Working at a height of two metres or more while carrying out general work activities or construction works

Working at a height of two metres or more while carrying out general work activities or construction works 1. Working at Heights 2. Scope / Description of Job Working at a height of two metres or more while carrying out general work activities or construction works 3. Critical Safety Issues A fall from any

More information

Programme-Based Engagement (ProBE) for Fall From Heights. Statistics

Programme-Based Engagement (ProBE) for Fall From Heights. Statistics Programme-Based Engagement (ProBE) for Fall From Heights Statistics For the past ten years, falling from height has been the number one cause of death in workplaces in Singapore. It has accounted for 34%

More information

CONTRACTOR SAFETY MANAGEMENT PROCEDURE

CONTRACTOR SAFETY MANAGEMENT PROCEDURE CONTRACTOR SAFETY MANAGEMENT PROCEDURE Version 1.0 TRIM file number Short description Relevant to Authority Responsible officer Responsible office Date introduced July 20, 2015 Date(s) modified June 11,

More information

WHS CONTRACTOR MANAGEMENT PROCEDURE

WHS CONTRACTOR MANAGEMENT PROCEDURE WHS CONTRACTOR MANAGEMENT PROCEDURE Version No: Issued 3.0 18/11/2013 15/11/2018 1. Overview The District Council of Peterborough as part of its commitment under its WHS Contractor Management policy, recognises

More information

Names and Contact Numbers of Competent Rescuers Assigned to Job (Please print)

Names and Contact Numbers of Competent Rescuers Assigned to Job (Please print) Emergency Plan For Rescue from Heights Department of Facilities Management Occupational Health and Safety Shop Performing Work Date Work Order No. Job Location Job Description Height of work platform /

More information

Hazard Identification, Risk Assessment And Control Procedure

Hazard Identification, Risk Assessment And Control Procedure Hazard Identification, Risk Assessment And Control Procedure 1. Purpose 1.1 To ensure that there is a formal process for hazard identification, risk assessment and control to effectively manage hazards

More information

Pre-Qualification Questionnaire Checklist

Pre-Qualification Questionnaire Checklist Pre-Qualification Questionnaire Checklist Thank you for your interest in becoming an Approved Contractor with Christchurch Airport. To ensure efficient processing of your application please utilise the

More information

WHS CONTRACTOR MANAGEMENT PROCEDURE

WHS CONTRACTOR MANAGEMENT PROCEDURE 1. Overview The Port Augusta City Council as part of its commitment under its WHS Contractor Management policy, recognises its obligation to: Ensure, so far as is reasonably practicable, the health and

More information

32-421 Eskom Life Saving Rules 39-47 Implementation of the Eskom Life Saving Rules

32-421 Eskom Life Saving Rules 39-47 Implementation of the Eskom Life Saving Rules 32-421 Eskom Life Saving Rules 39-47 Implementation of the Eskom Life Saving Rules LIFE SAVING RULES WHY DO WE HAVE THEM? Life Saving Rules are Non-negotiable Rules All Eskom Employees, Agents, Consultants,

More information

OCCUPATIONAL HEALTH AND SAFETY RISK ASSESSMENT PROGRAM FOR AGRICULTURE

OCCUPATIONAL HEALTH AND SAFETY RISK ASSESSMENT PROGRAM FOR AGRICULTURE OCCUPATIONAL HEALTH AND SAFETY RISK ASSESSMENT PROGRAM FOR AGRICULTURE Definitions of Commonly Used Terms in Risk Management Hazard: anything, including a work practice or procedure, that causes, or has

More information

Confined Space Management Procedure

Confined Space Management Procedure 1. Overview The District Council of Mount Remarkable as part of its commitment under its Hazardous Work Policy, recognises its obligation to eliminate, or where that is not reasonably practicable, minimise,

More information

Fall Protection Guidelines

Fall Protection Guidelines OCT 2015 1 of 6 Fall Protection Guidelines 1.0 PURPOSE To establish the requirements and procedures to protect employees and other persons conducting work from hazards associated with falling from one

More information

Method Statement. Risk Assessment

Method Statement. Risk Assessment Method Statement Risk Assessment Client: Location: Page 1 of 6 Health and Safety Method Statement and Risk Assessment Customer & Address: Site Address: Description of Works: Method Statement: Risk Assessment:

More information

Working at Height. A printed or saved copy is an UNCONTROLLED copy. Check that it is the latest available version before use.

Working at Height. A printed or saved copy is an UNCONTROLLED copy. Check that it is the latest available version before use. A printed or saved copy is an UNCONTROLLED copy. Check that it is the latest available version before use. Title: Number: WORKING AT HEIGHT GM-11-031-02 Version Number: 22.0 Date Revised: 03 September

More information

Health & Safety In Our Venues

Health & Safety In Our Venues SAFETY AS A SERVICE Health & Safety In Our Venues A guide for event organisers and providers to event organisers Because things are better LIVE Contents 1 Background... 2 1.1 Changes to New Zealand s health

More information

Asbestos Policy ASBESTOS POLICY. Version 2 / Jun 2015 Page 1 of 11 Asbestos Policy

Asbestos Policy ASBESTOS POLICY. Version 2 / Jun 2015 Page 1 of 11 Asbestos Policy ASBESTOS POLICY Version 2 / Jun 2015 Page 1 of 11 Asbestos Policy This is a controlled document. It should not be altered in any way without the express permission of the author or their representative.

More information

WorkSafe Guidance Document FALL PROTECTION IN RESIDENTIAL CONSTRUCTION

WorkSafe Guidance Document FALL PROTECTION IN RESIDENTIAL CONSTRUCTION WorkSafe Guidance Document FALL PROTECTION IN RESIDENTIAL CONSTRUCTION WorkSafe Guidance Document Fall Protection in Residential Construction Table of Contents Executive Summary... 1 Introduction... 1

More information

FALL PROTECTION WORK PLAN

FALL PROTECTION WORK PLAN FALL PROTECTION WORK PLAN INSTRUCTIONS A written fall protection work plan must be implemented by each employer on a job site where a fall hazard of 10 feet or greater exists, in accordance with OSHA Standards.

More information

HEALTH & SAFETY HANDBOOK. No Body GetsHurt. Our Safety Slogan is:

HEALTH & SAFETY HANDBOOK. No Body GetsHurt. Our Safety Slogan is: HEALTH & SAFETY HANDBOOK Our Safety Slogan is: No Body GetsHurt CONTENTS Page(s) Introduction 1 Health & Safety Policy 2 What happens if you get Injured at work 3 Chemicals 4 Company Vehicles 4 Compressed

More information

Approved Contractor Application (SAFE Form B)

Approved Contractor Application (SAFE Form B) Approved Contractor Application (SAFE Form B) 1. Business Information Company Name: Postal Address: Physical Address: (If differs from Postal) Phone: Mobile: Email Address: Number of Employees: 2. Key

More information

SITE SPECIFIC FALL PROTECTION PLAN

SITE SPECIFIC FALL PROTECTION PLAN 1 THIS PLAN IS SPECIFIC TO: PROJECT & ADDRESS 1.1 THIS PLAN IS SPECIFIC TO THE FOLLOWING AREA(S) ON SITE: Parkade level: Typical level: Other: Between G/L: 1.2 THIS PLAN IS APPLICABLE TO THE FOLLOWING

More information

CONTRACTOR INDUCTION HANDBOOK

CONTRACTOR INDUCTION HANDBOOK CONTRACTOR INDUCTION HANDBOOK POLICY The health and safety of all school employees and contractor employees is a vital concern at the school. Contract personnel will be treated in a manner consistent with

More information

Cristal Mining East. Mine Safety Management Plan

Cristal Mining East. Mine Safety Management Plan Doc No: AP_ME_4.4.04007 Revision: 3 Series: Management Plan Location: Mining East Cristal Mining East Mine Safety Management Plan Next Review: Nov-2015 Owner: J. Sulicich Revision Date: Nov-2014 Approver:

More information

SG19:10 NASC. A Guide to Formulating a Rescue Plan. NOTE: Scaffolders who need to use a harness should never work alone. 1 of 8 1.

SG19:10 NASC. A Guide to Formulating a Rescue Plan. NOTE: Scaffolders who need to use a harness should never work alone. 1 of 8 1. SG19:10 A Guide to Formulating a Rescue Plan 1. INTRODUCTION The legal requirement for rescue is specified in the Work at Height Regulations 2005 and require every employer in selecting work equipment

More information

Excavation & Trenching Procedure

Excavation & Trenching Procedure Excavation & Trenching 1. Overview The will ensure, as far as is reasonably practicable, that the conduct of work relating to excavation and trenching will not be harmful to the health and safety of employees

More information

Fall Protection. Office of Risk Management. uottawa.ca. Guide

Fall Protection. Office of Risk Management. uottawa.ca. Guide Fall Protection Guide Office of Risk Management.ca 1 Contents SCOPE... 1 INTENT... 1 LEGISLATION AND REQUIREMENTS... 1 RESPONSABILITIES... 2 Supervisors... 2 Workers... 2 Facilities... 2 HAZARD CONTROL...

More information

Procedure. Working at Heights. 1. Purpose. 2. Scope. 3. Definitions. 4. Planning. 4.1. QUT risk check. 4.2. Work at Height permit

Procedure. Working at Heights. 1. Purpose. 2. Scope. 3. Definitions. 4. Planning. 4.1. QUT risk check. 4.2. Work at Height permit Procedure Working at Heights 1. Purpose The purpose of this procedure is to establish compliance requirements and specify precautions to be taken during the conduct of work at height within QUT to prevent

More information

HEIGHT SAFETY EQUIPMENT MAINTENANCE, INSPECTION, RECERTIFICATION & TRAINING GUIDANCE

HEIGHT SAFETY EQUIPMENT MAINTENANCE, INSPECTION, RECERTIFICATION & TRAINING GUIDANCE HEIGHT SAFETY EQUIPMENT MAINTENANCE, INSPECTION, RECERTIFICATION & TRAINING GUIDANCE This guide focuses on the maintenance, inspection and testing of height safety equipment including fall arrest systems

More information

FALL PREVENTION PLAN FPP. Sharing of Safe Work at Height

FALL PREVENTION PLAN FPP. Sharing of Safe Work at Height FALL PREVENTION PLAN FPP Sharing of Safe Work at Height Howard How Boustead Singapore Limited The Group Established in 1828, Boustead Singapore is a progressive global infrastructure-related engineering

More information

Managing the risk of falls while working on roofs in housing construction

Managing the risk of falls while working on roofs in housing construction Workplace Health and Safety Queensland Managing the risk of falls while working on roofs in housing construction Where the risk of falling is 3 metres or more (or roof slope over 26 ) Before you start

More information

The Work at Height Regulations 2005 (as amended) A brief guide

The Work at Height Regulations 2005 (as amended) A brief guide The Work at Height Regulations 2005 (as amended) A brief guide Off work sick and worried about your job? Steps you can take to help your return to work Health and Safety The Work at Height Regulations

More information

Five Star Occupational Health and Safety Audit Specification document 2013

Five Star Occupational Health and Safety Audit Specification document 2013 Five Star Occupational Health and Safety Audit Specification document 2013 www.britsafe.org Membership Training Audit and Consultancy Policy and Opinion Awards Contents 1 Introduction to the Five Star

More information

FALL PROTECTION PROGRAM RESCUE PLAN

FALL PROTECTION PROGRAM RESCUE PLAN GLOBAL LEADER IN FALL PROTECTION Capital Safety 95 Derby Street Silverwater, NSW 2128 Tel: 02 8753 7600 Fax: 02 8753 7603 FALL PROTECTION PROGRAM RESCUE PLAN IMPORTANT: This document is intended to provide

More information

Part of the Arco family

Part of the Arco family Part of the Arco family Part of the Arco family Presented by: Mike Clayton Grad IOSH Technical Development Manager Total Access (UK) Ltd has been established as the leading provider of height safety and

More information

Question and answer brief for the construction industry on the Work at Height Regulations 2005

Question and answer brief for the construction industry on the Work at Height Regulations 2005 Question and answer brief for the construction industry on the Work at Height Regulations 2005 Introduction This question and answer brief includes some of the key issues about the new Work at Height Regulations

More information

CONFINED SPACE PROCEDURE

CONFINED SPACE PROCEDURE Document uncontrolled when printed Procedure ID no 0460/05 CONFINED SPACE PROCEDURE This procedure is applicable to: All Department of Education and Children's Services employees. DOCUMENT CONTROL Managed

More information

Level 1 Award in Health and Safety in a Construction Environment

Level 1 Award in Health and Safety in a Construction Environment Level 1 Award in Health and Safety in a Construction Environment Student notes (sample) www.britsafe.org Membership Training Qualifications Audit and Consultancy Audit and Policy Consultancy and Opinion

More information

FALL PROTECTION PROGRAM

FALL PROTECTION PROGRAM FALL PROTECTION PROGRAM Page 2 of 15 Table of Contents Applicability... 3 Overview... 3 Definitions... 3 Responsibilities... 5 Risk Assessment... 6 Risk Management... 7 Roof Access Procedure 10 Rescue

More information

Guide to manual tasks high impact function (HIF) audit 2010 March 2010

Guide to manual tasks high impact function (HIF) audit 2010 March 2010 Guide to manual tasks high impact function (HIF) audit 2010 March 2010 1 Adelaide Terrace, East Perth WA 6004 Postal address: Mineral House, 100 Plain Street, East Perth WA 6004 Telephone: (08) 9358 8002

More information

FALLING OBJECTS EXCESSIVE NOISE CHAINSAW & CHIPPER WORK AT HEIGHTS MANUAL HANDLING

FALLING OBJECTS EXCESSIVE NOISE CHAINSAW & CHIPPER WORK AT HEIGHTS MANUAL HANDLING JOB NO: PROJECT: DATE: SWMS NO: SWMS 001.1 PREPARED BY: Ian Hartley REVISED BY: Nick Bragg & Cameron McNeil ACTIVITY: TREE REMOVAL & PRUNING SIGNED BY: REVISION DATE: December 2015 MINIMUM PERSONAL PROTECTIVE

More information

Guidance Note GN049. Using portable ladders safely. WorkSafe Tasmania Department of Justice. Introduction and purpose

Guidance Note GN049. Using portable ladders safely. WorkSafe Tasmania Department of Justice. Introduction and purpose Guidance Note GN049 Using portable ladders safely Introduction and purpose The purpose of this guidance note is to answer the most common questions that WorkSafe Tasmania receives about using portable

More information

Accident/Incident Investigation & Reporting Procedure

Accident/Incident Investigation & Reporting Procedure Accident/Incident Investigation & 1. Overview The recognises its obligation to ensure that all accidents and incidents are reported, recorded and investigated. We are committed to identifying corrective

More information

Generic Risk Assessment: Working on Roofs (FMRA 0006)

Generic Risk Assessment: Working on Roofs (FMRA 0006) Generic Risk Assessment: Working on Roofs (FMRA 0006) Only staff and contractors who are Authorised by Facilities Management are allowed to access roof areas. Those who need access who are not Authorised

More information

Hazard Identification, Risk Assessment and Control (HIRAC) for Work at Height Risk, Health and Safety

Hazard Identification, Risk Assessment and Control (HIRAC) for Work at Height Risk, Health and Safety Hazard Identification, Assessment and Control (HIRAC) for Work at Height, Health and Safety A. Introduction Hazard identification and safety risk assessments should be conducted prior to carrying out any

More information

Contractor s Safe Working Agreement

Contractor s Safe Working Agreement Contractor s Safe Working Agreement This statement provides details on how I/we, the Trade Contractor will manage the health and safety hazards associated with my/our work. ASSESSING WORKPLACE HEALTH AND

More information

www.dol.govt.nz/prevent-falls/ PreventING falls from height Introduction How will worksites be targeted? Approach Who will be targeted?

www.dol.govt.nz/prevent-falls/ PreventING falls from height Introduction How will worksites be targeted? Approach Who will be targeted? PROACTIVE ENFORCEMENT APPROACH TO PREVENTING FALLS FROM HEIGHT Introduction Preventing falls is a priority for the Labour Group of the Ministry of Business, Innovation and Employment. From 1 July 2012,

More information

Work Health & Safety Policy Document Number: WH&S 023 003 Ver 1

Work Health & Safety Policy Document Number: WH&S 023 003 Ver 1 Work Health & Safety Policy Document Number: WH&S 023 003 Ver 1 Approved by: Senior Leadership Team Page 1 of 7 POLICY OWNER: Human Resources PURPOSE: To ensure, so far as is reasonably practicable, that

More information

HEALTH SAFETY & ENVIRONMENT MANAGEMENT SYSTEM

HEALTH SAFETY & ENVIRONMENT MANAGEMENT SYSTEM HEALTH SAFETY & ENVIRONMENT MANAGEMENT SYSTEM September 2011 OUR HEALTH, SAFETY AND ENVIRONMENT POLICY OUR PRINCIPLE OF DUE CARE We care about the wellbeing of our people and our impact on the environment.

More information

Quantum Risk Management Ltd t/a Quantum Compliance 23 Hanover Square, London W1S 1JB 34 Greenbox, Westonhall Road, Stoke Prior B60 4AL T:0800 644

Quantum Risk Management Ltd t/a Quantum Compliance 23 Hanover Square, London W1S 1JB 34 Greenbox, Westonhall Road, Stoke Prior B60 4AL T:0800 644 Contents Accident Investigation and Prevention 3 Asbestos Awareness 4 BOHS 901 Legionella - Management and Control of Building Hot and Cold Water Systems 5 BOHS 903 Legionella - Management and Control

More information

SITE CONTRACTOR PROCEDURES

SITE CONTRACTOR PROCEDURES SITE CONTRACTOR PROCEDURES Asset Collection Type B Assets are considered High risk ; the site activities must be in accordance with Graysonline contractor procedures and are to be collected by appointment

More information

Corporate Health and Safety Policy

Corporate Health and Safety Policy Corporate Health, Safety & Wellbeing Service Corporate Health and Safety Policy Contents 1. Introduction... 2 2. Policy Statement... 2 3. Scope... 3 4. Definition of Manager... 4 5. Responsibilities...

More information

No. Name of Legislation Applicable Issues and Requirements Demonstration of Compliance 1. Health and Safety at Work Act 1974

No. Name of Legislation Applicable Issues and Requirements Demonstration of Compliance 1. Health and Safety at Work Act 1974 The Police Treatment Centres Health and Safety Legal Compliance Register No. Name of Legislation Applicable Issues and Requirements Demonstration of Compliance 1. Health and Safety at Work Act 1974 2.

More information

Contractor Safety Management

Contractor Safety Management 1.0 Introduction Memorial University will ensure that a diligent contractor management process is established. This procedure establishes requirements for contract administration and oversight of contractor

More information

SUPPLY CHAIN PREQUALIFICATION PACKAGE

SUPPLY CHAIN PREQUALIFICATION PACKAGE SUPPLY CHAIN PREQUALIFICATION PACKAGE 2015 PREQUALIFICATION AS AN APPROVED SUBCONTRACTOR / SUPPLIER In order for your company to be registered as an approved Vendor with StructureTone Limited, we require

More information

Release 1. BSBWHS508A Manage WHS hazards associated with plant

Release 1. BSBWHS508A Manage WHS hazards associated with plant Release 1 BSBWHS508A Manage WHS hazards associated with plant BSBWHS508A Manage WHS hazards associated with plant Modification History Release Release 1 Comments This Unit first released with BSB07 Business

More information

Life Saving Rules SAFETY BY CHOICE, NOT BY CHANCE

Life Saving Rules SAFETY BY CHOICE, NOT BY CHANCE Life Saving Rules SAFETY BY CHOICE, NOT BY CHANCE Foreword from Kevin Reinhart The 12 Life Saving Rules are a part of Nexen s continued commitment to create a safe work environment for our employees. The

More information

Sample Checklist for Permit Required Confined Spaces Program

Sample Checklist for Permit Required Confined Spaces Program Sample Checklist for Permit Required Confined Spaces Program 29 CFR 1910.146 - Permit Required Confined Spaces for General Industry Item Description Yes No N/A Section C (General Requirements) 1. (1) -

More information

Fall Protection System: A system put in place to protect workers from falling. (i.e. installation of guardrails, fall arrest, fall restraint, etc.

Fall Protection System: A system put in place to protect workers from falling. (i.e. installation of guardrails, fall arrest, fall restraint, etc. SWP (6) FALL PROTECTION PROGRAM The following information on Fall Protection has been based around the BC OHS Regulations, standards, policies and guidelines. Prior to starting work outside of BC, the

More information

SAFE WORK PROCEDURE SWP 015 WORKING AT HEIGHT SEPTEMBER 2013 DOC. NO. D13/248399

SAFE WORK PROCEDURE SWP 015 WORKING AT HEIGHT SEPTEMBER 2013 DOC. NO. D13/248399 Operation Brief Description of Activity Limitations MORELAND CITY COUNCIL Operations Centre 7-9 Walter Street Hadfield Vic 3046 Tel: 8311 4300 Working at height Approved by the Walter Street OHS committee

More information

RESTRICTED ACCESS AND CONFINED SPACES

RESTRICTED ACCESS AND CONFINED SPACES Health & Safety Services Unit name goes here Safety Code of Practice 39 1 st Edition, July 2011 RESTRICTED ACCESS AND CONFINED SPACES University of Reading 2015 Page 1 Contents 1 Summary... 3 2 Introduction...

More information

OAKPARK SECURITY SYSTEMS LIMITED. Health & Safety Policy. Requests or suggestions for amendment to this procedure

OAKPARK SECURITY SYSTEMS LIMITED. Health & Safety Policy. Requests or suggestions for amendment to this procedure OAKPARK SECURITY SYSTEMS LIMITED Requests or suggestions for amendment to this procedure should be submitted to the owner of the process PROCESS OWNER: MANAGEMENT TEAM Current version: PREVIOUS VERSION

More information

OH&S Management Systems Audit Checklist (NAT, E3)

OH&S Management Systems Audit Checklist (NAT, E3) 3.1.2 3.1.1 Introduction OH&S Management Systems Audit Checklist (NAT, E3) This audit checklist is based on Element 3 (Implementation) of the National Self-Insurers OHS Audit Tool. For a full copy of the

More information

The Tomato Plant Company Ltd. Method Statement and Risk Assessment Loads requiring lifting

The Tomato Plant Company Ltd. Method Statement and Risk Assessment Loads requiring lifting The Tomato Plant Company Ltd Method Statement and Risk Assessment Loads requiring lifting Generic method statement & risk assessment for the removal of portable accommodation units and/or shipping containers

More information

CHAPTER 10. FALL PROTECTION PROGRAM

CHAPTER 10. FALL PROTECTION PROGRAM CHAPTER 10. FALL PROTECTION PROGRAM 1000 GENERAL. This chapter establishes policy for developing fall protection programs to protect all Federal Aviation Administration (FAA) personnel working at elevated

More information

ELECTRICAL SAFETY & ARC FLASH Handbook

ELECTRICAL SAFETY & ARC FLASH Handbook Electricity Forum Handbooks Electrical Safety and Arc Flash Handbook Series ELECTRICAL SAFETY & ARC FLASH Handbook Volume 10 Reprinted by permission of the publisher, Hurst Communications, from the Electrical

More information

WHS CONTRACTOR MANAGEMENT PROCEDURE

WHS CONTRACTOR MANAGEMENT PROCEDURE MANAGEMENT PROCEDURE 1. OVERVIEW The Flinders Ranges Council as part of its commitment under its WHS Contractor Management Policy, recognises its obligation to: Ensure, so far as is reasonably practicable,

More information

The Work At Height Safety Association

The Work At Height Safety Association The Work At Height Safety Association Technical Guidance Note 5 Guidance on rescue during work at height A series of informative notes for all industries involved with work at height or rescue. The information

More information

CONTRACTOR S MANAGEMENT PROCEDURE

CONTRACTOR S MANAGEMENT PROCEDURE CONTRACTOR S MANAGEMENT PROCEDURE S No Activity Responsibility 1 Pre-job meeting There shall be a pre-job meeting with contractor after award of contract in which following points shall be discussed and

More information

Event Management Guidelines. Month 2011. 1 Event Management Guidelines (Month, 2011)

Event Management Guidelines. Month 2011. 1 Event Management Guidelines (Month, 2011) Month 2011 1 (Month, 2011) Table of Contents Executive Summary... 2 More information... 2 Event Risk Assessment... 3 Event Checklist... 4 Event Details... 8 Event Contact List... 10 Event Task List...

More information

WHS Policies and Procedures Package

WHS Policies and Procedures Package WHS Policies and Procedures Package The following is an extract to highlight the style and layout of this publication, as well as a snapshot of the content. Some samples may not be included in their entirety

More information

TEMPLATE -PRINCIPAL CONTRACTOR CONSTRUCTION SAFETY & ENVIRONMENT MANAGEMENT PLAN

TEMPLATE -PRINCIPAL CONTRACTOR CONSTRUCTION SAFETY & ENVIRONMENT MANAGEMENT PLAN Note: Construction Safety Management Plan format may vary. Information must be clearly identifiable and easily found. It is the implementation of this plan that is important and audits of construction

More information

Life Saving Rules. Working Safely at EPCOR

Life Saving Rules. Working Safely at EPCOR Life Saving Rules Working Safely at EPCOR 1 Our Health and Safety Beliefs We believe: All incidents are preventable. HSE is integral to our work and the way we conduct business. HSE is serious and a shared

More information

Working on roofs. Planning roof work

Working on roofs. Planning roof work Health and Safety Working on a roof can be dangerous. Falls account for more deaths and serious injuries in construction than anything else and roofers account for 24% the biggest category of worker by

More information