Guideline for Energy Efficient Electrical systems for building. Presentation by TERI



Similar documents
Understanding Power Factor and How it Affects Your Electric Bill. Presented by Scott Peele PE

DHANALAKSHMI COLLEGE OF ENGINEERING DEPARTMENT OF ELECTRICAL AND ELECTRONICS ENGINEERING EE ELECTRICAL MACHINES II UNIT-I SYNCHRONOUS GENERATOR

Electricity Terminology. Simplifying energy management

Digital Energy ITI. Instrument Transformer Basic Technical Information and Application

Reactive Power and Importance to Bulk Power System OAK RIDGE NATIONAL LABORATORY ENGINEERING SCIENCE & TECHNOLOGY DIVISION

STATEMENT OF CHARGING METHODOLOGY FOR USE OF ELECTRICITY NORTH WEST LIMITED S ELECTRICITY DISTRIBUTION NETWORK

Variable Frequency Drives - a Comparison of VSI versus LCI Systems

Basics of Electricity

ELECTRICITY TARIFF (Effective from September 1, 1999.)

For a phase-to-phase voltage between 100 V and 1000 V. The standard ratings are: 400 V V V (at 50 Hz)

Power Plant Electrical Distribution Systems

ODISHA ELECTRICITY REGULATORY COMMISSION BIDYUT NIYAMAK BHAVAN UNIT-VIII, BHUBANESWAR *****************

AUTOMATIC TRANSFER SWITCH. Changeover Type from 250A to 2500A

TRANSMISSION SERVICE RATE SCHEDULE Effective from 1 April 2015

Wind-Diesel Hybrid System Options for Alaska. Steve Drouilhet National Renewable Energy Laboratory Golden, CO

NORTHERN IRELAND ELECTRICITY Ltd STATEMENT OF CHARGES FOR USE OF. THE NORTHERN IRELAND ELECTRICITY Ltd ELECTRICITY DISTRIBUTION SYSTEM

Simulation of Cable Overloading Problem on a University Distribution System

Green Power Connection Net Energy Metering Engineering Review Process in Delaware and Speeding Up the Application Fee Process

Tariff Booklet The Tata Power Company Limited (W ith effect from May 1,2007) THE TATA POWER COMPANY LIMITED TARIFF BOOKLET

ESB Networks Response. ERGEG Consultation. Voltage Quality Regulation in Europe

Product Data Bulletin

Opportunity of Energy Saving in electrical path is lesser as compared to other areas

Fundamentals of Modern Electrical Substations Part 1: Mission of Electrical Substations and their Main Components

INTRODUCTION Tariff Objective Factors

Designed for uptime. Defining data center availability via a tier classification system

TARIFF SCHEDULES FOR HIGH TENSION CONSUMERS. Table of Contents

NO-BREAK KS 7e. Concentrated Energy kva (50Hz) 3000 kva (60Hz) DIESEL ROTARY UNINTERRUPTIBLE POWER SUPPLY SYSTEM

Electric Power Distribution

Product brochure Multi Functional Switchgear PASS M kv Flexible and compact switchgear solutions for windfarms

INDEX S. No. PARTICULARS Note:

FACT SHEET. BSES, Delhi - Distribution Network. Power Systems Consultancy from ABB

AC Power. by Prof. Dr. Osman SEVAİOĞLU Electrical and Electronics Engineering Department

ANCILLARY EQUIPMENT AND ELECTRICAL EQUIPMENT Power Supply Systems and Electrical Equipment for Desalination Plants - Y.M. Hamud and A.H.

SHE Transmission. 2015_10_30 Transmission Losses Strategy Rev 2.0 October 2015

GENERATOR SELECTION. a. Three phase - 120/208V, 3 phase, 4W wye; 277/408, 3 phase, 4W wye; * 120/240V 3 phase, 4W Delta

ODISHA ELECTRICITY REGULATORY COMMISSION BIDYUT NIYAMAK BHAVAN UNIT-VIII, BHUBANESWAR ***************** Secy/Tariff/ Date..03.

Step Voltage Regulators

Design of electrical power system for a 1000MW nuclear power generating station

Yam Hong 施 耐 德 電 機 亞 太 日 本 區 (APJ) 三 相 關 鍵 電 源 市 場 開 發 經 理. Schneider Electric - Division - Name Date

Sai Om Journal of Science, Engineering & Technology A Peer Reviewed International Journal ENERGY AUDITING FOR INDUSTRIES

Model Renewable Energy Wheeling Agreement under Renewable Energy Certificate (REC) scheme

Qualitative Analysis of Power Distribution Configurations for Data Centers

PacifiCorp Original Sheet No. 476 FERC Electric Tariff, Substitute 6 th Rev Volume No. 11 APPENDIX 2 TO SGIP

EEL303: Power Engineering I - Tutorial 4

The electrical energy produced at the gen

The function of a power station is to deliver

Business Energy Efficiency. Webinar August 29, 2012

Simple Methods for Calculating Short Circuit Current Without a Computer By Dennis McKeown, PE GE Senior System Application Engineer

Inverter / Charger Installation General Operations and AC and DC Connections

Interconnection of Generators to EDI s Distribution System

7. Reactive energy compensation

Portland General Electric Company P.U.C. Oregon No. E-18 Original Sheet No. C-1 RULE C CONDITIONS GOVERNING CUSTOMER ATTACHMENT TO FACILITIES

Best Practice Guide BPGCS007

Request for Payment Instructions Wholesale Distribution Access Tariff (WDAT) Attachment I - GIP

I USE OF SYSTEM CHARGES EFFECTIVE FROM 1 APRIL 2015

may be prescribed by the Government, under the provisions of the sub section (1) of section 127 of the Act;

PG&E Transmission Interconnection Handbook. Section L3: SUBSTATION DESIGN FOR LOAD-ONLY ENTITIES AND TRANSMISSION-ONLY ENTITIES

UTILITIES DEPARTMENT NORTH CAMPUS DISASTER RECOVERY PLAN

Technical Data. back-up time in minutes 100% load % load

Photovoltaic Solar Energy Unit EESFB

ABB PSPS Erich Steinmann; Generator control-2013

Brochure. Electric generators to power the world

Motor Efficiency and Power Factor ME 416/516

Tariff Development II: REVIEW of Basic Allocation and Rate Design Principles

Rules for Classification and Construction Additional Rules and Guidelines

Primary and Secondary Electrical Distribution Systems

Earth Fault Detection Basics in Theory

ATTACHMENT F. Electric Utility Contact Information Utility Name. For Office Use Only

Power Quality Paper #3

South African Distribution Code

ENA Customer Guide to Electricity Supply

First Revised Sheet No. D-13.01

Module Title: Electrotechnology for Mech L7

Hyperlinks are Inactive

Jemena Electricity Networks (VIC) Ltd - Network Tariffs For The 2015 Calendar Year (Exclusive of GST)

Modular architecture for high power UPS systems. A White Paper from the experts in Business-Critical Continuity

FIXED CHARGE: This is a cost that goes towards making the service available, including

Short Circuit Current Calculations

1150 hp motor design, electromagnetic and thermal analysis

The Facts About Harmonics and Power Factor. Power Quality: Harmonics & Power Factor Correction

Chapter 3 AUTOMATIC VOLTAGE CONTROL

ENERGY COST SAVINGS IN MUNICIPAL WATER PUMPING SYSTEMS-NEED FOR WEB INTERACTIVE TOOL

Transmission Related Station Power Use at Substations

Minimizing Impact of Electric Utility Outages with Backup Generation

Chapter 4.5: Electric Motors, Variable Speed Drives

Effective: September 10, 2006 Vermont Attachment 1 to Rule Public Service Board Page 1 of 6

Data center power dynamics within the settings of regional power grid

LIMITING SHORT-CIRCUIT CURRENTS IN MEDIUM-VOLTAGE APPLICATIONS

Contactless Power Transfer : Inductive charging of EV

Standards in Marine Power Systems. APEC 2014 Session IS2.1 Power Electronic Standards Roger Dougal University of South Carolina Columbia, SC 29208

Rule Fast Track Analysis for National Life Insurance Co.

Pass Through Costs for Business Electricity Customers from 1 st October 2015

Power Quality Standards for Electric Service

Connecting to the network information pack Version 2

POWER FACTOR CORRECTION

Three phase circuits

SA Power Networks Network Tariffs - Residential APPLIES TO USAGE FROM 1 JULY 2015

Modeling of PV Based Distributed Generator Systems with Diverse Load Patterns

Starting Current Reduction of Residential HVAC System and Peak-Load Impact of Power System: A Case Study

Totally Integrated Power SIESTORAGE. The modular energy storage system for a reliable power supply.

Transcription:

Guideline for Energy Efficient Electrical systems for building Presentation by TERI

Objective of study The study highlights how BBMP can implement energy efficiency measures in building in co-ordination with BESCOM. Achieve energy efficient and reliable electrical system design for buildings. Also the guide line should have compliance with the existing BESCOM regulations.

Necessity of proper Electrical system design are: Safety of life and property including equipment. Reliability of system input supply and tolerance limit of interruptions Flexibility of plant distribution system Location of the plant sub-station and its deployment Data of electrical equipment, regulation and initial cost including capitalisation Simplicity /flexibility of operation and maintenance Overall cost including running cost Providing quality service Technical parameters and specifications in construction, installation, protection, operation and maintenance Adherence to laid down procedures with accountability

Guidelines on optimization of electrical load load in kw and demand in kva diversity factor load characteristics future expansion Future demand forecasting and planning (building expansion plans). Determination of the voltage level required for the building. Calculation of short circuit analysis and selection of correct rating for circuit breaker with review of selection of protective devices.

Classification of Voltage Preferences Industry Preferred Incoming Voltage Level Voltage Class as per I.E. Rule 100 MW and above Between (10-50 MW) 220 kv 132-66 kv Extra High Between (1 to 10 MW) 33-11 kv High Up to 50 kw 3 φ, 440 Volts Medium/Low

Guidelines on Transformer Rating and Selection Normally maximum efficiency; of the transformer is designed at the loading in the range of 45 to 50% of' its full load capacity. The building should be supplied from two independent sources, where continuity of supply is required. The capacity of the transformers should be so selected that if one of the transformers fails, the remaining transformer shall ensure supply to the equipments without undue overload.

ECBC recommended losses for oil cooled transformer Rating kva Max. losses at 50% loading kw Max. losses at 100% loading kw Total losses at 50% loading kw Total losses at 100% loading kw Up to 11 kv Up to 22 kv 100 0.5 1.8 0.6 1.8 160 0.8 2.2 0.8 2.6 200 0.9 2.7 0.9 3 250 1.1 3.3 NA NA 315 1.1 3.6 1.3 4.3 400 1.5 4.6 1.5 5.1 500 1.6 5.5 2 6.5 1000 2 6.6 2.3 7.6 1250 3 9.8 3.5 11.4 3.6 12 4 13.3 1600 4.5 15 4.9 16 2000 5.4 18.4 5.7 18.5 2500 6.5 22.5 7.1 23

Guidelines on selection of Electrical Motors IS 12615 for Energy Efficient motors is the benchmark figures for efficiency. High efficiency motors are usually manufactured from materials, which incur lower energy losses compared with standard motors. More care is taken with the design and geometry of the motor construction. The high efficiency motors have been improved in four areas: Longer core lengths of low loss steel laminations to reduce flux densities and iron losses Maximum utilization of the slots and generous conductor sizes in the stator and rotor to reduce copper losses Careful selection of slot numbers and tooth/slot geometry to reduce stray losses Less heat is produced by a more efficient motor so the cooling fan size is reduced. This leads to lower windage losses and therefore less waste power.

Guidelines on improvement of Power factor Methods of improving Power factor Streamlining of the process by improving the electrical performance of the plant. Replacing induction motors by synchronous motors of equal rating wherever possible. Replacement of under loaded motors with motors of correcr rating. Reduction of voltage of motors which are regularly under loaded. Restricting no load operation of motors. Improving motor repair quality. Replacement or relocation of under loaded transformers. Installation of Capacitors

continued Measurement of power factor by a direct-reading for Power factor meter for an instantaneous value a recording VAr meter, which allows a record over a period of time to be obtained. of current, voltage and power factor. Readings taken over an extended period provide a useful means of estimating an average value of power factor for an installation. Necessity of having good power factor Power factor improvement allows the use of smaller transformers, switchgear and cables, etc. as well as reducing power losses and voltage drop in an installation.

Guidelines on distribution system losses The distribution losses in the system are mainly on account of the losses in the cables and bus bars. The parameters that affect the cable losses are mainly cable resistance, power factor and voltage levels. Losses In-plant cable losses are in the range of 1% to 4 %.

continued Cable laying should be done strictly in accordance with carefully and systematically planned schedule. Drawing of this should be available at site and should be preserved at sub-stations. All cable ends should be suitably labelled to facilitate easy identification. In all control cables adequate number of spare cores should be included. For cables, use IS:1255-1958, IS:962-1965 and IS:3043-1966 standards.

Guidelines on Power back up systems Captive power generation offers the following advantages: Continuous availability of power, free from utility power breakdown and grid disturbances, etc., leading to better productivity, less interruptions in process restart etc., Good power system control obtained when operated in parallel with the utility supply system Possibility of heat and electrical energy generation (Cogeneration) resulting in energy conservation and reduced energy cost, Excess electrical energy generation can be supplied to the utility grid and earning income/ wheeling charges.

Modes of operation of DG sets Standby Power supply Mode (Emergency Power Supply): Captive power generation set utilised in this mode shall meet the plant part load or total load requirement during the failure of utility power supply. Peak Loading Mode The specific energy generation ( SEGR) of the DG sets varies with size and loading on the DG sets. A SEGR of 4 kwh/l is said to be an efficient design.

UPS An uninterruptible power supply, or battery back-up, is an electrical apparatus that provides emergency power to a load when the input power source, typically the utility mains, fails. A UPS differs from an auxiliary or emergency power system or standby generator in that it will provide instantaneous or near-instantaneous protection from input power interruptions by means of one or more attached batteries and associated electronic circuitry. The efficiency level of the inverters varies from 92-95 % based on the capacity.

Guidelines on Power Quality Ranges Line-to-Line rms. Values Standard Nominal A.C. System Voltages Tolerance on Declared Voltage Voltage adopted for the system I 50 V < u < 1000 V Three phase - 415 V Single phase - 240 V ± 6 % Distribution system II A 1 kv < u < 52 kv 3.3, 6.6, 11, 33 kv 0.06-0.09 Subtransmission II B 52 kv < u < 66, 132, 220 kv ± 12.5 % Transmission 300 kv III C U > 300 kv 400 kv ± 12.5 % Transmission

continued The voltage ranges in which the AC installations are classified (as per IS: 12360-1988) Phase to phase voltage imbalances by even 2.5 % of the nominal voltage can reduce motor efficiency up to 10 %. The limit of negative phase sequence as per IEC34-1 is 2% of the voltage.

Mandatory clause to be included in the Revised BESCOM regulation The power factor of the building shall not be less than 0.95 The transformer losses at 50% and 100 % load shall be in accordance with the conditions specified in ECBC 2007.

Compliance Requirement - Transformer Provide transformer loss at 50% and 100% load

Compliance Requirement - Transformer S No Type Rated kva Actual loss at 50 % load ECBC recom mend ed loss at 50% load Actual loss at100 % load ECBC recom mende d loss at 100% load Note Test certificate from the manufacturer showing above specification needs to be submitted

Power Factor Correction All electricity supplies exceeding 100A, 3 phases shall maintain their power factor between 0.95 lag and unity at the point of connection. Presently in Bangalore city, there are penalties for LT connections with PF less than 0.85, a surcharge of 2 paise per unit consumed will be levied for every reduction of PF by 0.01 below 0.85.However, and in respect of LT installations the surcharge is limited to a maximum of 30paise per unit. It is proposed to increase the PF to such installations to 0. 95 to reduce the Transmission and Distribution losses. Any LT connection having a PF of less than 0.95 a levy has to be charged as prevailing earlier. BESCOM has agreed to implement penalty if the PF maintained is less than 0.95.

Mandatory use of energy efficient transformers Under this project use of energy efficient Transformer, for buildings with HT supply has been made as a mandatory regulation. BESCOM to take the initiative to check at the time of giving electricity connection that ECBC compliant transformers are installed in new buildings, with HT Power supply

Mandatory Energy audit for commercial buildings above 600kVA BESCOM can provide incentives for commercial establishment to carryout energy audit and reduce the energy consumption. The incentive mechanism can be structured in a way that the present energy consumption before commissioning the audit represents the baseline figures. Any reduction in energy consumption after implementation of the energy saving recommendations within a reasonable time frame should have an incentive to the extant of actual reduction in kwh for the same operating conditions.

Tariff slabs related to Energy Performance Index in place of units. It is being proposed to BESCOM to revise the structure and introduce tariff slabs related to Energy Performance Index in place of units.

Existing tariff structutre Tariff Schedule LT-3(i) (Low Tension) Applicable to All offices, Police Stations, Commercial Complexes, Information Technology (IT) enabled services, I.T. based medical transcription centers Fixed charges per month Fixed charges Rs. 35 per KW Energy Charges For the first 50 units 505 paise/unit For the balance units 600 paise/unit

Proposed tariff structure Tariff Schedule LT-3(i) (Low Tension) Applicable to All offices, Police Stations, Commercial Complexes, Information Technology (IT) enabled services, I.T. based medical transcription centers Fixed charges per month Fixed charges Rs. 35 per KW Energy Charges If consumption is below EPI 505 paise/unit If consumption is higher than EPI 600 paise/unit

Thank You