MAIN STREET IMPROVEMENTS Water, Sewer, Stormwater and Streetscape Improvements
|
|
- Monica Ferguson
- 8 years ago
- Views:
Transcription
1 MAIN STREET IMPROVEMENTS Water, Sewer, Stormwater and Streetscape Improvements Presentation July 23, 2014 A. Morton Thomas and Associates, Inc. 800 King Farm Boulevard, 4 th Floor Rockville, Maryland
2 The AMT Team Working with the City to design and prepare construction documents for Main Street Improvements A. Morton Thomas and Associates, Inc. Geo-Technology Associates, Inc. Goel Services Extensive experience with streetscape projects Extensive urban design experience Full-service design team Recent experience with City of Salisbury 2
3 The AMT Team Experience 3
4 Project Vision Return Vibrancy Timeless, Memorable, & Inviting Create a Destination Link Marina & Central Greenway Enhance Architecture Create Continuity, Safety, & Parking 4
5 Project Goals Revitalize the Main Street corridor Create inviting, safe environment Provide access for pedestrians, bikes and vehicles Create a link between downtown and marina 5
6 Project Masterplan Project Limits 6
7 Project Overview Replace or improve: o water mains o sewer mains and o storm drain structures Design innovative SWM treatments Upgrade traffic control at Division St. Streetscape / landscape features Pavement repairs and replacement Reconstruct sidewalk and ramps $1.3 million $1.8 million $1.9 million 7
8 Multi Use Corridor Corridor to include: o travel lanes o bike lanes/ striping o sidewalk o on-street parking o landscape features 8
9 Multi Use Corridor West Main Street 9
10 Multi Use Corridor West Main Street 10
11 Multi Use Corridor East Main Street 11
12 Multi Use Corridor East Main Street 12
13 Multi Use Corridor East Main Street 13
14 Multi Use Corridor Walkable Street 14
15 Streetscape Features - Trees 15
16 Streetscape Features Planting 16
17 Streetscape Features Planting 17
18 Streetscape Features Furnishings 18
19 Streetscape Features Lighting 19
20 Streetscape Features Lighting 20
21 Streetscape Features Surface Treatment 21
22 Streetscape Features Water Features 22
23 Division Street Plaza 23
24 Drainage Move / Upgrade inlets Inspect System to determine condition of pipes Slope roadway to drain Eliminate ponding 24
25 Stormwater Management 25
26 Utilities Pipe Inspection 26
27 Water and Sewer Pipes PHASE 2 ONLY Replace All Water Pipes Repair or Replace Sanitary Sewer Pipes No disruption of service Add graphic of a section of the road showing the utilities in color 27
28 Plaza: Main Street and Division Street New signal at Division St Improve cross walk signing and striping Provide pedestrian countdown signals Use decorative support posts 28
29 Construction Schedule and Impacts Expect to begin construction Fall phased in this order Phase 2: Division St. to Rte. 13 Phase 1: Market St to Division St. Phase 3: Plaza Construction will: Maintain 2 way traffic Maintain access to businesses at all times Maintain pedestrian access Eliminate on-street parking periodically Provide advance warning of disruptions 29
30 Questions? 30
Walkable Communities Florida Department of Transportation State Safety Office Pedestrian and Bicycle Program April 1995 www.dot.state.fl.us/safety Twelve Steps for an Effective Program Page 1 Twelve Steps
More informationTopic 2 11/28/2012 Blocks & Street Network
TOPIC 2 Blocks & Street Network Implementation Note: 1. Some recommendations are summarized in the tables herein. For complete recommendation language, please see the. 2. Recommendations referenced in
More informationin Marina Del Rey Prepared by: County of Los Angeles Department of Public Works
Planned Public Works Projects in Marina Del Rey Prepared by: County of Los Angeles Department of Public Works Planned Projects in Marina Del Rey Waterline Projects Phase II Phase III Roadway Projects Admiralty
More informationENGINEERING SOLUTIONS FOR DESIGNING YOUR SAFE ROUTES
How to Get Started ENGINEERING SOLUTIONS FOR DESIGNING YOUR SAFE ROUTES Design Elements Selecting appropriate design treatments for school neighborhoods creates environments that address the needs of all
More informationFY 2011 OHIO SMALL CITIES COMMUNITY DEVELOPMENT BLOCK GRANT COMPREHENSIVE DOWNTOWN REVITALIZATION PROGRAM
CITYOFOBERLIN OHIO CITY OF OBERLIN, OHIO FY 2011 OHIO SMALL CITIES COMMUNITY DEVELOPMENT BLOCK GRANT COMPREHENSIVE DOWNTOWN REVITALIZATION PROGRAM Background In October, 2011, the City of Oberlin Planning
More informationOVERVIEW PROJECT SUMMARY
OVERVIEW Cesar Chavez showcases how to successfully redesign a primary arterial route into a neighborhood destination, improving modal share, water sensitive design, biodiversity and safety whilst maintaining
More informationKENTUCKY TRANSPORTATION CABINET. Department of Rural and Municipal Aid. Office of Local Programs
KENTUCKY TRANSPORTATION CABINET Department of Rural and Municipal Aid Office of Local Programs Office of Local Programs Transportation Enhancements Safe Routes to School Congestion Mitigation and Air Quality
More informationVISION, DESIGN PRINCIPLES & OVERALL PLANNING STRATEGY
3 VISION, DESIGN PRINCIPLES & OVERALL PLANNING STRATEGY The overall planning strategy for the Bank Street CDP is to ensure that future development is undertaken in a coordinated and planned approach, supported
More informationBEST PRACTICES. Smart Transportation is a key concept for the Paoli Roadway Improvement Project.
Smart Transportation Smart Transportation is a key concept for the Paoli Roadway Improvement Project. PennDOT s Smart Transportation Guidebook (2008) outlines a comprehensive approach to transportation
More informationGuiding Principles. McCauley Area Focused Urban Design Plan. 1 Connect: Chinatown and Little Italy with downtown and surrounding areas
McCauley Area Guiding Principles 1 Connect: Chinatown and Little Italy with downtown and surrounding areas 2 Strengthen: Cultural character in Chinatown and Little Italy 3 Develop: Strong East West pedestrian
More informationDowntown Tampa Transportation Vision
Downtown Tampa Transportation Vision Executive Summary August 1, 2006 Hillsborough County Metropolitan Planning Organization County Center, 18 th Floor Tampa, Florida 33602 813-272-5940 www.hillsboroughmpo.org
More informationTable of Contents ALPHABETIZED LIST OF CIP PROJECTS... 1 CIP 5 YEAR SUMMARY BY CATEGORY... 18 SMART CITY CIP 5 YEAR SUMMARY BY VISION...
Table of Contents ALPHABETIZED LIST OF CIP PROJECTS... 1 CIP 5 YEAR SUMMARY BY VISION... 5 CIP 5 YEAR SUMMARY BY CATEGORY... 18 SMART CITY CIP 5 YEAR SUMMARY BY VISION... 33 CAPITAL IMPROVEMENT PROJECTS
More informationFlood Mitigation Strategy for the Milwaukee 30 th Street Corridor Redevelopment Program
Flood Mitigation Strategy for the Milwaukee 30 th Street Corridor Redevelopment Program Eric Loucks, P.E., D.WRE Kumar Gali, P.E. June 4, 2015 Outline MMSD Service Area Problem and Challenges Solution
More informationDraft Non Transportation Performance Measures Including Related Qualitative Assessment of Example Sections
Draft Non Transportation Performance Measures Including Related Qualitative Assessment of Example Sections Phil Erickson Community Design + Architecture Mike Johnson HDR Engineering CTF Charrette Approach
More information8.1.3 General Design Guidelines. The following guidelines shall be used when designing inlets along a street section:
. Introduction Presented in this chapter are the criteria and methodology for design and evaluation of storm sewer inlets located in Town of Castle Rock. The review of all planning submittals will be based
More informationPROJECT COST ESTIMATE ASSUMPTIONS AND EXCLUSIONS
C PROJECT ESTIMATE ASSUMPTIONS AND EXCLUSIONS In support of the alternatives development process, preliminary cost estimates were prepared for each of the three Candidate Build Alternatives. The cost estimates
More informationEngineering. 2006 2007 2007 2008 2008 2008 Major Service Actual Budget Projected Request Executive Adopted
Engineering Agency Number: 53 Budget Function: Public Works and Transportation The Engineering Division is responsible for the design, supervision and inspection of all street, highway, sidewalk and bike
More informationThe Bond Release Process for New Subdivision Developments: An Overview for Homeowners Associations DRAFT 6-4-08. Revised 9-25-08
The Bond Release Process for New Subdivision Developments: An Overview for Homeowners Associations DRAFT 6-4-08. Revised 9-25-08 Fairfax County requires developers to post a performance bond if they are
More informationInterlocking Concrete Pavement Institute (ICPI) Model Stormwater Ordinance for Permeable Interlocking Concrete Pavements August 2010
Interlocking Concrete Pavement Institute (ICPI) Model Stormwater Ordinance for Permeable Interlocking Concrete Pavements August 2010 Background What are permeable interlocking concrete pavements (PICP)?
More informationHARRIS TEETER AT LADY S ISLAND CITY OF BEAUFORT DRB CONCEPTUAL PROJECT NARRATIVE Submittal Date: September 2, 2015 Meeting Date: September 10, 2015
HARRIS TEETER AT LADY S ISLAND CITY OF BEAUFORT DRB CONCEPTUAL PROJECT NARRATIVE Submittal Date: September 2, 2015 Meeting Date: September 10, 2015 PROPOSED REDEVELOPMENT The project consists of demolishing
More informationBETTER STREETS PLAN SAN FRANCISCO POLICIES AND GUIDELINES FOR THE PEDESTRIAN REALM DRAFT PLAN RELEASE PACKET JUNE 2008. inside:
SAN FRANCISCO BETTER STREETS PLAN POLICIES AND GUIDELINES FOR THE PEDESTRIAN REALM DRAFT PLAN RELEASE PACKET JUNE 2008 inside: LETTER FROM MAYOR GAVIN NEWSOM EXECUTIVE SUMMARY SAN FRANCISCO PLANNING DEPARTMENT
More informationFairlington Community Center
Williamsburg Boulevard Green Street Project June 13, 2012 Williamsburg Middle School Relevant Outreach November 12, 2008: Introduction to Little Pimmit Run Watershed Retrofits Workshop, Yorktown High School
More informationStreet Audit Tool: Web 2.0 Tools
Name: Email: Instructions: Auditor Information (1) Use all three tools for your assessment (2) If the tool can not determine the criteria, check (3) Indicate the tools used (4) Rate the effectiveness of
More informationALKS SIDEW II. TK TK TK TK TK TK TK TK 40 BOSTON COMPLETE STREETS GUIDELINES DRAFT - JULY 2011 BOSTON TRANSPORTATION DEPARTMENT
40 Sidewalk Materials Materials and Sidewalk Zones Permeable Pavement Accessibility The key components of sidewalk construction are material selection and installation. These two aspects should come together
More informationPLANNED UNIT DEVELOPMENT & SIDEWALK WAIVER REQUEST STAFF REPORT Date: November 7, 2013
PLANNED UNIT DEVELOPMENT & SIDEWALK WAIVER REQUEST STAFF REPORT Date: November 7, 2013 NAME LOCATION Audubon Properties, LLC. 4700 & 4960 Dauphin Island Parkway West side of Dauphin Island Parkway, 580
More informationMississippi Drive Kickoff Event. 8/31/2015 & 9/1/2015 Meeting Minutes. Blue Zones: Dan Burden Presentation (Rotary Club Meeting)
Mississippi Drive Kickoff Event 8/31/2015 & 9/1/2015 Meeting Minutes Blue Zones: Dan Burden Presentation (Rotary Club Meeting) Cedar Street new sidewalk/ada Target speed down to 20 MPH (Dan Burden) One
More informationKansas City s Overflow Control Program
Kansas City s Overflow Control Program Kansas City Water Services Water Wastewater Stormwater 2 Water Services Department 1000 Positions 835 Employees 3 Utilities FY 13/14 Budget = $307 million Water Wastewater
More informationToronto's New Soil and Tree-based Standards for Boulevards
2013 ISA Annual Meeting Toronto, August 3-7, 2013 Toronto's New Soil and Tree-based Standards for Boulevards Extended Abstract May 16, 2013 Introduction In 2012, the city of Toronto embarked on a process
More informationBond Release Process for New Subdivision Developments in Fairfax County
Bond Release Process for New Subdivision Developments in Fairfax County An Overview for Homeowners Associations A Fairfax County, Va., publication April 2009 For more information or to request this document
More informationCITY OF ROANOKE AND TOWN OF VINTON, VIRGINIA. RSTP Funds Joint Application FOR
CITY OF ROANOKE AND TOWN OF VINTON, VIRGINIA RSTP Funds Joint Application FOR Tinker Creek Pedestrian Bridge: Tinker Creek and Glade Creek Greenways Connection Date: September 15, 2014 RSTP Project Profile
More informationLOCATIONS OF UTILITIES IN PUBLIC RIGHTS-OF-WAY Examples from various Cities
LOCATIONS OF UTILITIES IN PUBLIC RIGHTS-OF-WAY Examples from various Cities American Public Works Association Utilities & Public Right of Way Committee February 29, 2000 Table o of Contents Index...Page
More informationPUBLIC WORKS DESIGN, SPECIFICATIONS & PROCEDURES MANUAL LINEAR INFRASTRUCTURE
REGION OF PEEL PUBLIC WORKS DESIGN, SPECIFICATIONS & PROCEDURES MANUAL LINEAR INFRASTRUCTURE Storm Sewer Design Criteria REVISED July 2009 PUBLIC WORKS STORM SEWER DESIGN CRITERIA TABLE OF CONTENTS 1.0
More informationDE 8 Concept Plan and Operations Study. Dover Safety Advisory and Transportation Committee October 23, 2007
DE 8 Concept Plan and Operations Study Dover Safety Advisory and Transportation Committee October 23, 2007 Purpose Develop a concept plan describing the aesthetic qualities of the corridor as a gateway
More informationCITY COUNCIL WORKSHOP MAY 24, 2016
1 CITY COUNCIL WORKSHOP MAY 24, 2016 Capital Budget FY 2016-2017 & 2017-2018 Robert Ovadia, PE, City Engineer 2 Overview FY 2015-16 Accomplishments Projects Completed during FY 2015-16 Projects Under Construction
More informationDRAFT MAINTAINING HOUSTON S STREETS REPAIR, REHABILITATION, RECONSTRUCTION. Using the Full Range of Tools for a Challenging Job
MAINTAINING HOUSTON S STREETS REPAIR, REHABILITATION, RECONSTRUCTION Using the Full Range of Tools for a Challenging Job Report To: TTI Committee May 13, 2014 1 Pavement Management - Suggested Treatments
More informationSTORM WATER PROJECT COST ESTIMATES & LOCATION MAPS. Appendix F
STORM WATER PROJECT COST ESTIMATES & LOCATION MAPS Appendix F RIVERDALE CITY CAPITAL FACILITIES PLAN STORM DRAINAGE Engineer's Cost Estimate January 2009 Project Name: 4400 South Street - Piping and Collection
More informationInfrastructure assets are distinguished from other capital assets because they normally:
4. REPORTING 4.2 Government-Wide Financial Statements 4.2.6 Infrastructure Reporting 4.2.6.10 Governments are required to report all of their capital assets in the statement of net position. Infrastructure
More informationExtreme Wet Weather in Brookfield. How to Keep Your Basement Dry During Heavy Rains and Floods
Extreme Wet Weather in Brookfield How to Keep Your Basement Dry During Heavy Rains and Floods Relating Stormwater Drainage to Sewer Backups Brookfield has two separate sewer systems Storm sewer system
More informationReview Public Input Report Jenn Toothaker. Approval of Meeting Summaries: May 21, May 23, May 30, & June 20, 2013 Meetings
Call to the Audience Guidelines 2 Call to the Audience opportunities Must fill out participant card Participants called in the order cards are received 3 minutes allowed per participant CTF Facilitator
More informationSEMINOLE PRATT WHITNEY ROAD & NORTHLAKE BLVD. FREQUENTLY ASKED QUESTIONS
UPDATED: 01/31/14 SEMINOLE PRATT WHITNEY ROAD & NORTHLAKE BLVD. FREQUENTLY ASKED QUESTIONS Q. 1. What are the County s plans for Seminole Pratt Whitney Road between SR 80 (Southern Blvd) and the Bee Line
More informationLegacy Trail Extension Feasibility Study. Preliminary Cost Estimate
Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 25,800' + Separated Trail length ~ 13,700' = Total Length ~ 39,500' or 7.5
More informationSANITARY SEWER PROJECT COST ESTIMATES & LOCATION MAPS. Appendix D
SANITARY SEWER PROJECT COST ESTIMATES & LOCATION MAPS Appendix D RIVERDALE CITY CAPITAL FACILITIES PLAN SANITARY SEWER Engineer's Cost Estimate January 2009 Project Name: Riverdale Road - Rumbi Grill -
More informationODOT Major Construction, Bikeways and Enhancements Report for Lucas County. (State Fiscal Years 2007 to 2010)
Bikeways and Enhancements Report for Lucas County (State Fiscal Years 2007 to 2010) Statewide Construction Summary by Major Work Type (in Millions) WORK TYPE SFY 2007 SFY 2008 SFY 2009 SFY 2010 TOTAL #
More informationCONSTRUCTION MANAGER S WEEKLY PROGRESS REPORT
Volkert Field Office 80 M Street SE, Suite 725 Washington, DC 20003 RIVERSMART WASHINGTON - CONSTRUCTION RIVERSMART MACFARLAND, RIVERSMART LAFAYETTE AND GREEN ALLEYS CHEVY CHASE D.C. Contract No.: DCKA-2013-C-0160
More informationCorridor Goals and Objectives
Corridor Goals and Objectives This chapter presents the goals and objectives, developed by the Corridor Study Committee, that serve as the purpose and intent of the Corridor Plan. This plan covers a twenty
More informationPavement Asset Management Guidance Section 5.3: Condition Surveying and Rating - Drainage
Pavement Asset Management Guidance Section 5.3: Condition Surveying and Rating - Drainage December 2014 Document Information Title Author Description Pavement Asset Management Guidance, Section 5.3: Condition
More informationA Developer s Guide: Watershed-Wise Development
A Developer s Guide: Watershed-Wise Development Environmental Protection What is a watershed? It does not matter how far away you build from a creek, lake, or the ocean, you are in a watershed. Another
More informationMaintenance Management and Asset Management
Defining and Understanding the Difference Between Maintenance Management and Asset Management Dr. Simon Lewis AgileAssets, Inc. 12th AASHTO-TRB Maintenance Management Conference Annapolis Maryland, July
More informationNorth Avenue Corridor Study. Advisory Committee Meeting #5 June 11, 2014
North Avenue Corridor Study Advisory Committee Meeting #5 June 11, 2014 Agenda Welcome and introductions Concept refinement and evaluation: Public meeting and web survey General cross-section concepts
More informationProject Rankings. Fiscal Year 2015 2019 Capital Improvement Plan
Fiscal Year 2015 2019 Capital Improvement Plan Project Rankings 99 CIP Ranking Worksheet 101 104 Final Ranking Scores The following matrix shows all of the projects within the five-year period that were
More informationFor more information, visit: rethinkingstreets.com
For more information, visit: rethinkingstreets.com 37 Arterial Rehab Busy, multi-lane streets, often referred to as arterials, crisscross the landscape of our cities and suburbs. Alongside these wide thoroughfares,
More informationPost-Construction Stormwater Management Checklist* (5,000 SF or Greater)
Applicability: Required for projects that create and/or replace 5,000 square feet or greater of impervious surface (i.e. asphalt roads, concrete structures, building area, sidewalks, etc.). Impervious
More informationCASFM Stormwater Quality Field Trip June 23rd, 2011
CASFM Stormwater Quality Field Trip June 23rd, 2011 The 2011 CASFM Stormwater field trip included 42 attendees coming from as far south as Colorado Springs up to the Denver area and another 12 who joined
More informationGuidelines for. Permeable Pavement
What is permeable pavement? Guidelines for Permeable Pavement When rainwater falls on conventional pavement, such as concrete, it accumulates and then flows across and off of this impervious surface as
More informationDraft Goals and Objectives Wadena Comprehensive Plan City of Wadena, Minnesota. Land Use Goals:
Draft Goals and Objectives Wadena Comprehensive Plan City of Wadena, Minnesota Land Use Goals: 1. Growth in Wadena will be undertaken in such a manner as to create a full range of living, working, shopping,
More informationSCHOOL OF ARCHITECTURE & COMMUNITY DESIGN COLLEGE OF THE ARTS UNIVERSITY OF SOUTH FLORIDA
SCHOOL OF ARCHITECTURE & COMMUNITY DESIGN COLLEGE OF THE ARTS UNIVERSITY OF SOUTH FLORIDA PROJECT OVERVIEW OVERVIEW The FCCD+R, in coordination with the FDOT District 7, are to facilitate numerous meetings
More informationSEPTEMBER 2015 SCOPE OF WORK. MONTGOMERY COUNTY PLANNING DEPARTMENT M-NCPPC MontgomeryPlanning.org
SEPTEMBER 2015 SCOPE OF WORK MONTGOMERY COUNTY PLANNING DEPARTMENT M-NCPPC MontgomeryPlanning.org table of contents table of contents... 1 introduction... 2 planning context... 2 purpose of master plan...
More informationGeneral Obligation Bond Projects FYE 2013-2018
General Obligation Bond Projects FYE 2013-2018 2009 City of Norman Community Survey Final Report 2011 CTP Survey Results Storm Drainage and Street Widening Projects Combined Storm Water/Transportation
More informationAGENCY COORDINATION AND PUBLIC INVOLVEMENT
5 AGENCY COORDINATION AND PUBLIC INVOLVEMENT 5.1 AGENCY COORDINATION As part of the planning process for the Oregon Avenue Final EA, DDOT conducted an agency coordination program. This coordination included
More informationMoving Ruston Forward. City of Ruston Infrastructure Maintenance and Improvements
Moving Ruston Forward City of Ruston Infrastructure Maintenance and Improvements MLK Extension Project will be done in conjunction with proposed water and sewer improvements Connect Martin Luther King
More informationLS 2540 SEWER LATERALS AND INSPECTION TEES
LS 2540 SEWER LATERALS AND INSPECTION TEES A. Summary B. Submittals C. Site Information D. Sewer Pipe and Fittings E. Lateral Locations F. Lateral Installation G. Inspection Tee Installation H. Removal
More informationGreen Infrastructure for Great Cities
Green Infrastructure for Great Cities FHWA Ecological Webinar Richard M. Daley Mayor Janet L. Attarian, AIA, LEED AP, Project Director Streetscape and Sustainable Design Program Sustainable Streets The
More informationPremature Storm Drainage System Repairs and Replacement
Premature Storm Drainage System Repairs and Replacement Stewart Edwards Program Manager Design Management Team Charlotte-Mecklenburg Storm Water Services April 8, 2015 Date Agenda Storm Water Infrastructure
More informationLincoln Downtown Master Plan Update
Lincoln Downtown Master Plan Update Table of Contents Executive Summary........................................... 1 Complete Streets Framework.................................... 3 Promenade Creating
More informationCITY OF VISTA STANDARD DRAWINGS (PRELIMINARY, FOR REVIEW)
CITY OF VISTA STANDARD DRAWINGS (PRELIMINARY, FOR REVIEW) January, 2013 THIS SHEET INTENTIONALLY LEFT BLANK TABLE OF CONTENTS DRAINAGE STRUCTURES DRN-01 Corrugated metal pipe drop inlet DNR-02 Storm Drain
More informationRESOLUTION NO. 1539 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF BONNEY LAKE, PIERCE COUNTY, WASHINGTON, APPROVING THE 192 ND CORRIDOR STUDY AND DIRECTING THE MAYOR TO PROCEED WITH PARTIAL DESIGN AND
More informationInfrastructure and Growth Leadership Advisory Group Ideas and Approaches Survey
Infrastructure and Growth Leadership Advisory Group Ideas and Approaches Survey In its second meeting, the Infrastructure and Growth Leadership Advisory Group expanded and refined the list of approaches/ideas
More informationLAKE SHORE DRIVE CTA RED LINE BROADWAY SHERIDAN FOSTER ARGYLE. Pedestrian Access Advisory Committee. April 25, 2014
FOSTER LAKE SHORE DRIVE CTA RED LINE BROADWAY SHERIDAN ARGYLE ARGYLE STREET STREETSCAPE - S-1-323 Pedestrian Access Advisory Committee BROADWAY ARGYLE CTA RED LINE WINTHROP KENMORE SHERIDAN Broadway -
More informationMICHIGAN S LANDSCAPE ARCHITECTS
MICHIGAN S LANDSCAPE ARCHITECTS protecting the health, safety, and welfare of our citizens site design land use planning master planning streetscape design brownfield redevelopment guidelines and regulations
More informationAlternatives to the Circ Project Prioritization Methodology Prepared for Circ Task Force July 28, 2011
Alternatives to the Circ Project Prioritization Methodology Prepared for Circ Task Force July 28, 2011 CCRPC staff has developed a draft methodology described below and detailed in the attached pages for
More informationAssessing Paved Trails for Compliance with Standards and Best Practices
Assessing Paved Trails for Compliance with Standards and Best Practices Session Presenters: Kristin Maravilla, Planner/Designer Masters in Landscape Architecture (UC Berkeley) Masters in City and Regional
More informationCITY OF BRAMPTON STREET CORRIDOR MASTER PLAN
1.0 INTRODUCTION... 1 1.1 Purpose of Document... 1 1.2 Master Plan Goal...1 1.3 Design Objectives... 2 1.4 Design Approach... 2 2.0 PROJECT SCOPE...2 2.1 City Context 2 2.2 Regional Context 2 3.0 DESIGN
More informationChapter 22. Lump Sum Project Guidelines
Chapter 22 Lump Sum Project Guidelines 22.1 General...22-1 22.2 Project Selection...22-3 22.3 Plans Preparation...22-5 22.4 Preliminary Estimate...22-7 22.5 Specifications...22-9 22.6 Contracts Administration...22-11
More informationAPPENDIX C INLETS. The application and types of storm drainage inlets are presented in detail in this Appendix.
Storm Drainage 13-C-1 APPENDIX C INLETS 1.0 Introduction The application and types of storm drainage inlets are presented in detail in this Appendix. 2.0 Inlet Locations Inlets are required at locations
More informationAccident Analysis of Sheridan Road between Isabella Street and South Boulevard
Accident Analysis of Sheridan Road between Isabella Street and South Boulevard Prepared for TranSystems Corporation for the City of Evanston Submitted by Regina Webster & Associates, Inc. Date: 08/15/2008
More informationS. BLOCK 68 REDEVELOPMENT PROJECT AREA
S. BLOCK 68 REDEVELOPMENT PROJECT AREA 1. Revitalization Project Description The Block 68 Redevelopment Project Area is located on the block bounded by 10 th, 11 th, M, and N Streets, and is comprised
More informationHow To Build A City Of Virginia Beach Arena
City of Virginia Beach Arena Infrastructure Preliminary Conceptual Cost Estimates Doug Smith, Deputy City Manager Carl Tewksbury, Kimley-Horn City Council Briefing July 8, 2014 July 8, 2014 Presentation
More informationImplementation Strategy
Implementation Strategy 6 The following implementation strategy defines strategic points of intervention for complete streets programming, including visioning, goal-setting, local agency plans, coordination
More informationJULY 24, 2009 WEST-END FLOODING INVESTIGATION ACTION PLAN. Presentation to Insurance Companies 19 January 2012
JULY 24, 2009 WEST-END FLOODING INVESTIGATION ACTION PLAN Presentation to Insurance Companies 19 January 2012 Topics of Discussion Investigation Levels of Service Cause of Flooding Analysis Undertaken
More informationEast Lake Park {xäñ Çz uâ Äw t à z{àxü véååâç àç
East Lake Park {xäñ Çz uâ Äw t à z{àxü véååâç àç December 2005 EAST LAKE PARK CONCEPTUAL MASTER PLAN DECEMBER 2005 ACKNOWLEDGEMENTS We would like to thank the Arthur M. Blank Family Foundation for their
More informationCity of Hilshire Village Pine Creek Ln Reconstruction
City of Hilshire Village Pine Creek Ln Reconstruction OVERVIEW The City will be soliciting bids for the Pine Creek Reconstruction Project with construction scheduled to begin in January 2015. This project
More informationImplementing a Work Order and. Asset Management System? Learning Objectives. What We Have. The City of Colleyville
A Small City s Story of Implementing a Work Order and Asset Management System American Public Works Association 2013 Congress August 28, 2013 Introductions Public Works Department City of Colleyville,
More informationBackground and Goals for the Project
City of Asheville, NC REQUEST FOR PROPOSALS Wilma Dykeman Riverway Environmental Analysis, Project Development, and Preliminary Design Submittal Address: Dan Baechtold, AICP City of Asheville Engineering
More informationBicycle riding is a great way to get into shape
Bicycle riding is a great way to get into shape and have fun. To remain safe on Illinois roads, it is important to follow the same traffic safety laws that govern vehicle drivers. No amount of bicycle
More information(Version 1.0 August 2014) Cover Letter. (See Paragraph 9 of Section 1A.10)
Cover Letter (See Paragraph 9 of Section 1A.10) (Note: No request to experiment is denied or rejected based on format or layout.) Title Page A Overview/Problem/Background Provide a statement(s) indicating
More informationCOPPER BEECH TOWNHOME DEVELOPMENT
COPPER BEECH TOWNHOME DEVELOPMENT This 28 acre, 30 Townhome development is slated to open doors in time for the 2007 2008 college school year. To accommodate this project s tight time line, Dennis Corporation
More informationUNIT PRICE LIST January 2009
UNIT PRICE LIST January 2009 1 INTRODUCTION The purpose of the Unit Price List is to provide a resource for the preparation of cost estimates for subdivisions and permit projects and should be used only
More informationPLANNING DIVISION STAFF REPORT February 23, 2015. Summary. Background Information PREPARED FOR THE PLAN COMMISSION. Legistar File ID # 36810
PLANNING DIVISION STAFF REPORT PREPARED FOR THE PLAN COMMISSION Project Address: Application Type: Legistar File ID # 36810 Prepared By: Summary Conditional Use Timothy M. Parks, Planning Division Report
More informationSchenk-Atwood Neighborhood Business District Master Plan
Schenk-Atwood Neighborhood Business District Master Plan Prepared for the Schenk-Atwood Revitalization Association (SARA) and the City of Madison SCHREIBER/ANDERSON ASSOCIATES, INC. BEST Real Estate Group,
More informationCapacity Deficiency Project Application Jackson MPO Surface Transportation Program
Capacity Deficiency Project Application Jackson MPO Surface Transportation Program The following information must be completed for all Capacity Deficiency proposed Jackson MPO STP projects. MPO staff will
More informationDowntown Community Planning Council Meeting offebruary 18, 2015
- san diego Item #12 DATE ISSUED: ATTENTION: SUBJECT: February 13, 2015 Downtown Community Planning Council Meeting offebruary 18, 2015 Consideration of Support for Grant Applications for the San Diego
More informationFirst in Service First in Safety
7840 Nagle Avenue Morton Grove, Illinois 60053 847-470-5235 Fax - 847-965-9511 Wind Damage; Frequently Asked Questions: What can I do with branches that fall in my yard? Bring them out to the parkway;
More informationSurface Transportation Program (STP)
Project Name: Project Sponsor: FEDERAL FUNDS PROJECT APPLICATION TRANSPORTATION IMPROVEMENT PROGRAM 2008-2013 SALT LAKE and OGDEN/ LAYTON URBAN AREAS Surface Transportation Program (STP) Urban Surface
More informationGreen Streets, Places, and Spaces
Thursday October 23, 2014 Green Streets, Places, and Spaces Green Streets reduce stormwater runoff and improve a street s ecological performance. Often, strategies for sustainable stormwater management
More informationCD i -STREETS- Detail #
-STREETS- Detail # 3000 Vertical Curb, Gutter and Sidewalk 3010 Low-Profile Curb, Gutter and Sidewalk 3020 Rolled Curb, Gutter and Sidewalk 3030 Separated Sidewalk, Curb & Gutter 3040 Sidewalk Staged Construction
More informationTHE IMPLICATIONS OF ALTERNATIVE GROWTH PATTERNS ON INFRASTRUCTURE COSTS
City of Calgary THE IMPLICATIONS OF ALTERNATIVE GROWTH PATTERNS ON INFRASTRUCTURE COSTS REPORT APRIL 2, 2009 IBI GROUP REPORT City of Calgary EXECUTIVE SUMMARY Purpose of Report Calgary has seen record
More information01/31/13 ACHIEVING THE VISION FOR RESTON. Reston Master Plan Special Study Task Force
ACHIEVING THE VISION FOR RESTON Reston Master Plan Special Study Task Force The Reston Master Plan Special Study Task Force was appointed by Hunter Mill District Supervisor Catherine Hudgins to review
More informationWESTFIELD-WASHINGTON ADVISORY PLAN COMMISSION December 7, 2015 1512-SPP-24 & 1512-ODP-24
Petition Number: Subject Site Address: Petitioner: Request: East side of Oak Road, north of 151 st Street Langston Development Co. Primary Plat and Overall Development Plan amendment review for Mapleridge
More informationSECTION EIGHT BONDING REQUIREMENTS
SECTION EIGHT BONDING REQUIREMENTS 8-00 BONDING REQUIREMENTS 8-01 No building permit for any construction in the subdivision shall be issued nor any lot within the subdivision conveyed until a bond has
More informationIn 2005, the City of Pasadena, CA, USA, with the support of consultants,
Creating a Citywide Safe Routes to School Program: Pasadena, CA, USA s Step-by-Step Approach In 2005, the City of Pasadena, CA, USA, initiated development of a comprehensive Safe Routes to School Program.
More information