CONSTRUCTION MANAGER S WEEKLY PROGRESS REPORT
|
|
- Lucas Shelton
- 8 years ago
- Views:
Transcription
1 Volkert Field Office 80 M Street SE, Suite 725 Washington, DC RIVERSMART WASHINGTON - CONSTRUCTION RIVERSMART MACFARLAND, RIVERSMART LAFAYETTE AND GREEN ALLEYS CHEVY CHASE D.C. Contract No.: DCKA-2013-C-0160 CONSTRUCTION MANAGER S WEEKLY PROGRESS REPORT 8/3/2014 8/10/2014 Project Website: MacFarland-Allison St Underdrain installation Chevy Chase- Core sample #2, pervious concrete
2 EXECUTIVE SUMMARY Project Descriptions: The RiverSmart MacFarland project is along portions of Georgia Avenue, Allison Street, and Iowa Avenue and some of the nearby alleys. Work includes construction of facilities to reduce stormwater volume runoff. Work includes the construction of permeable paving and bioretention areas. Permeable paving in alleys, roads, and parking lanes provides on-site drainage and infiltration for storm water. Bioretention areas, also called rain gardens, in tree areas and curb bump-outs use landscaped planting areas to hold storm water and infiltrate into the soil. When constructed, the storm water flow will be monitored and measured to calculate the stormwater runoff reduction and evaluate its effectiveness for use in other neighborhoods. The RiverSmart Lafayette project covers areas along 33rd, Rittenhouse, Quesada, 32nd and Patterson Streets. Work includes construction of permeable paving and bioretention areas. Permeable paving in alleys, roads, and parking lanes provide on-site infiltration areas for storm water. Bioretention areas, also called rain gardens, in tree areas and curb bump-outs use landscaped plantings to hold storm water and infiltrate into the soil. The Green Alleys Chevy Chase project reconstructs the alleys between Rittenhouse St., Broad Branch Rd., 34th Place, 33rd Street and Quesada St. The entire alley will be constructed using full width pervious concrete, center strip of pervious concrete, and standard concrete. This project reduces the quantity of storm water runoff and improves the water quality prior to it entering the Districts storm sewer system. Proposed work will include but not be limited to: Bioretention areas, or rain gardens in tree box areas Permeable paving in alleys, roads, and parking lanes Curb bump-outs
3 DAILY WORK PERFORMED Field construction activities performed during this period: Monday 8/4/14: MacFarland: The contractor began work on Iowa Avenue NW, STA and STA with construction of two driveway entrances. The contractor demolished existing concrete pavement, removed debris, compacted subgrade and graded surface to slope. Then, poured concrete for driveway and embedded fabric wire mesh into concrete. Afterwards, finished the bottom part of driveway concrete to slope to gutter pan. A sample of concrete was taken and six cylinders made for testing strength of concrete at DDOT. In addition, began construction of PPF 2 and PPF 34 with construction of two Entrance Driveways by saw cutting and demolition of pavement. Also, tree protection for seven trees on the east bound lane of Allison St from St to St was placed. Lastly, in sections PPF7 and PPF 39, removed and reinstalled brick pavers to meet contract specifications under the direction of Bob of Eagle Bay. Chevy Chase: The contractor did not work on site this day. A work attempt by the contractor on Alley 6 was stopped by the inspector due to the conflict with the public notice which was based on the contractor s schedule. Tuesday 8/5/14: MacFarland: The contractor continued construction of PPF 2, work this day was from St to St Work began with hard surface and common excavation, followed by installation of Geotextile fabric to the gutter side of excavations and waterproof membrane to roadway side of excavation with. #8 stone filter layer was placed as well as #2 stone. Lastly, 6 inch PVC perforated drain pipe was installed. Chevy Chase: The contractor did not work on site this day. Wednesday 8/6/14: MacFarland: The contractor continued work on PPF 2 between STA to STA The remaining section, was excavated and the contractor completed the placement of Geotextile & water proofing Geomembrane., double washed #8, #2 & #57 stone in addition to the underdrain pipes at the location. The crew then moved to PPF 34 and began demolition of pavement. Chevy Chase: The contractor started the construction of the permeable interlocking concrete pavers, Alley 6, located between Quesada Street, at STA and Rittenhouse Street, at STA The contractor began the operation with a 5.0' wide saw cut and demolition of the existing pavement from STA to STA Thursday 8/7/14: MacFarland: The contractor continued working on PPF 34 with hard surface excavation and common Excavation this day. Chevy Chase: The contractor continued the construction of the permeable interlocking concrete paver Alley 6 located between Quesada Street, NW at STA and Rittenhouse Street, NW at STA Hard and common excavation was completed and placement waterproofing Geomembrane and double washed #2 stone was started. In addition, a technician from Craig Testing Laboratories of Maryland, Inc. (CTL) arrived on site at 8:00 am to cut cores for pervious concrete previously poured areas.
4 Friday 8/8/14: MacFarland: The contractor continued work on PPF 34 and PPF 2 at various locations within these areas which was split into three (3) sections. Section 1, STA to STA was filled with #57 stone and compacted, also, edge curb forming was started. Section 2, STA to STA , all excavation up to subgrade was completed and will be filled with stone after Lateral gas lines have been inspected by Washington Gas. Section 3, STA to STA , a Test Pit was dug, followed by common excavation and stone placement. Lastly, Edge curb concrete was poured for PPF 2 and Section 1 PPF 34. A sample of concrete was taken from the middle of the pour and four cylinders made for strength testing at DDOT Lab. Chevy Chase: The contractor continued the construction of the permeable interlocking concrete paver Alley 6 located between Quesada Street, NW at STA and Rittenhouse Street, NW at STA The contractor completed the hard and common excavations and started the placement waterproofing Geomembrane and double washed #2 stone between STA and STA In addition, a Test Pit was conducted to locate a sewer service line. Saturday 8/9/14: MacFarland: No work this day Chevy Chase: No work this day.
5 PHOTOS OF WORK PERFORMED THIS PERIOD MacFarland- Allison St, Stone placement and compaction. MacFarland-Demolition of pavement, Allison St.
6 Lafayette- demolition of pavement, Alley 6 Chevy Chase PPF34, placement of Geotextile and aggregate
APPENDIX F. RESIDENTIAL WATER QUALITY PLAN: ALLOWABLE BMP OPTIONS
APPENDIX F. RESIDENTIAL WATER QUALITY PLAN: ALLOWABLE BMP OPTIONS The following section provides descriptions, advantages, limitations, and schematics of allowable best management practices (BMPs) for
More informationCASFM Stormwater Quality Field Trip June 23rd, 2011
CASFM Stormwater Quality Field Trip June 23rd, 2011 The 2011 CASFM Stormwater field trip included 42 attendees coming from as far south as Colorado Springs up to the Denver area and another 12 who joined
More informationInterlocking Concrete Pavement Institute (ICPI) Model Stormwater Ordinance for Permeable Interlocking Concrete Pavements August 2010
Interlocking Concrete Pavement Institute (ICPI) Model Stormwater Ordinance for Permeable Interlocking Concrete Pavements August 2010 Background What are permeable interlocking concrete pavements (PICP)?
More informationPROJECT COST ESTIMATE ASSUMPTIONS AND EXCLUSIONS
C PROJECT ESTIMATE ASSUMPTIONS AND EXCLUSIONS In support of the alternatives development process, preliminary cost estimates were prepared for each of the three Candidate Build Alternatives. The cost estimates
More informationPorous Pavement Alternatives Cost Analysis
Porous Pavement Alternatives Cost Analysis Prepared by Century West Engineering for Metro This cost analysis compares the construction costs of six different types of pavement for three different scenarios.
More informationGuidelines for. Permeable Pavement
What is permeable pavement? Guidelines for Permeable Pavement When rainwater falls on conventional pavement, such as concrete, it accumulates and then flows across and off of this impervious surface as
More informationSolutions Library Solution 4: Permeable Pavement
SOILS TREES RAINGARDENS Solutions Library Solution 4: "Think like water. Go with the flow." -Frances Kato, Issaquah School District Student 59 60 How Works? Explanation of Diagram The most significant
More informationDivision 2 Section 32 14 13.19 Section 02795
Note: The text must be edited to suit specific project requirements. It should be reviewed by a qualified civil or geotechnical engineer, or landscape architect familiar with the site conditions. Edit
More informationPermeable Pavement Operation & Maintanence Guide
Permeable Pavement Operation & Maintanence Guide Permeable pavement at Olympic Park, Waitakere Final Construction result What are permeable pavements? Permeable pavements are hard surface paving systems
More informationPermeable Pavement Construction Guide
Permeable Pavement Construction Guide Permeable pavement at Olympic Park, Waitakere Final Construction result What are permeable pavements? Permeable pavements are hard surface paving systems that reduce
More informationALKS SIDEW II. TK TK TK TK TK TK TK TK 40 BOSTON COMPLETE STREETS GUIDELINES DRAFT - JULY 2011 BOSTON TRANSPORTATION DEPARTMENT
40 Sidewalk Materials Materials and Sidewalk Zones Permeable Pavement Accessibility The key components of sidewalk construction are material selection and installation. These two aspects should come together
More informationSUDAS Revision Submittal Form
SUDAS Revision Submittal Form Status Date: As of 3/13/15 Topic: Permeable interlocking pavers Manual: Design & Specs Manual Location: Design Section 5L-1; Spec Section 7080 Requested Revision: Reason for
More informationGuidelines for Control of Water Runoff on Small Lots. Revised 6/09
Guidelines for Control of Water Runoff on Small Lots Revised 6/09 Table of Contents Introduction and Purpose 3 Administrative Procedures 3 Plan Submittal Requirements 3 General Design Criteria 4 Dry Wells
More informationSECTION 32 14 13.19 PERMEABLE INTERLOCKING CONCRETE PAVEMENT (1995 MasterFormat Section 02795)
SECTION 32 14 13.19 PERMEABLE INTERLOCKING CONCRETE PAVEMENT (1995 MasterFormat Section 02795) Note: This guide specification for U.S. applications describes construction of permeable interlocking concrete
More informationStormwater/Wetland Pond Construction Inspection Checklist
: Construction Inspection ChecklistsTools Stormwater/Wetland Pond Construction Inspection Checklist Project: Location: Site Status: Date: Time: Inspector: SATISFACTORY/ UNSATISFACTORY COMMENTS Pre-Construction/Materials
More informationBuilding Your Interlocking Concrete Pavement to Last a Lifetime
Building Your Interlocking Concrete Pavement to Last a Lifetime A Guide for Consumers Contents Building Your Interlocking Concrete Pavement to Last a Lifetime.... 3 What Does Installation Involve?....
More informationGREEN INFRASTRUCTURE DESIGNS BIOSWALE/HYBRID DITCH
GREEN INFRASTRUCTURE DESIGNS BIOSWALE/HYBRID DITCH JULY 2015 BIOSWALE/HYBRID DITCH SCALABLE TOOL AND DESIGN TEMPLATE This tool and associated design files are one section of a larger toolkit: Green Infrastructure
More informationG3 GRANT LID RETROFIT FOR THE ASHLAND MUNICIPAL PARKING LOT
G3 GRANT LID RETROFIT FOR THE ASHLAND MUNICIPAL PARKING LOT GREEN STREETS GREEN JOBS GREEN TOWNS PROJECT INFORMATION: Location: Ashland, VA Project Type: Design and Construction Restoration Practice: Bioretention,
More informationUpdates on Pervious Pavement Design and Construction. Jason T. Peterein, P.E. June 19, 2012
Updates on Pervious Pavement Design and Construction Jason T. Peterein, P.E. June 19, 2012 Program Outline Pervious Pavement Basics Pervious Pavement Construction Maintenance MSD Regulations Update Permeable
More informationPermeable Pavement Treatment Capacity
Permeable Pavement Treatment Capacity April 20 2011 This investigation will analyze the pollutant removal capacity of various types of permeable paving techniques. Daniel Sullivan Joseph Fleury Contents
More informationPermeable Interlocking Concrete Pavement (PICP) A Low Impact Development Tool Training for Schools and Universities
Permeable Interlocking Concrete Pavement (PICP) A Low Impact Development Tool Training for Schools and Universities Presented by: Interlocking Concrete Pavement Institute The Low Impact Development Center,
More informationPervious Pavers. By: Rich Lahren. Hebron Brick & Block Supply
Pervious Pavers By: Rich Lahren Hebron Brick & Block Supply Stormwater Management and Control Issues Past emphasis was on flood control Today s emphasis is also on pollution More impermeable areas are
More informationCaltrans non-standard Special Provisions Pervious Concrete. David Akers Feb 28, 2012
Caltrans non-standard Special Provisions Pervious Concrete David Akers Feb 28, 2012 Section Paragraph Content 19 RSS 19-5.03B Changes title of the section 19-5.03B USAGE NOTES FOR PERVIOUS CONCRETE AND
More informationCity of Atlanta. Department of Watershed Management. Post-Development Stormwater Management Ordinance Summary of Revisions
City of Atlanta Department of Watershed Management Post-Development Stormwater Management Ordinance Summary of Revisions Cory Rayburn, CPESC Environmental Program Manager crayburn@atlantaga.gov Stormwater
More information(Source: Center for Neighborhood Technology)
(Source: aaees.org) (Source: Center for Neighborhood Technology) Purpose & Benefits Stormwater runoff reduction High pollutant removal Control localized drainage problems Attractive alternative for walkways
More informationUnderground Injection Control Storm Water Information
Underground Injection Control Storm Water Information Best Management Practices DEQ has reviewed the EPA definition of a subsurface fluid distribution system and the infiltration design best management
More informationPermeable Paving System with StormAbsorb Technology
Permeable Paving System with StormAbsorb Technology The water management solution. ideal for LEED projects 2 a better way to solve water management issues Increasingly, water management is an important
More informationPermeable Interlocking Concrete Pavements
Permeable Interlocking Concrete Pavements Program 000003 Revised 1-29-08 Permeable Interlocking Concrete Pavements This program is registered with the AIA/CES and ASLA CPE for continuing education professional
More informationStorm Drain Inlet Protection
Categories EC Erosion Control SE Sediment Control TC Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution Control Legend: Primary Category
More informationAdvancements in Permeable Pavements
Advancements in Permeable Pavements Engineers Workshop Saint Vincent College March 14 & 15 2013 Permeable Pavements There are several different words that are used to describe a pavement that water drains
More informationChagrin River Watershed Partners, Inc. Cost Analysis of Low Impact Development Best Management Practices
Chagrin River Watershed Partners, Inc. Cost Analysis of Low Impact Development Best Management Practices Amy H. Brennan (440) 975-3870 www.crwp.org abrennan@crwp.org Chagrin River Watershed Partners Formed
More informationPermeable Pavers. calstone.com. Permeable Interlocking Concrete Pavements (PICP s)
Permeable Pavers Permeable Interlocking Concrete Pavements (PICP s) CBC Title 24/ADA Compliant LEED Functional Optimum balance of surface infiltration and joint interlock Available in a 6 x 9 Quarry Stone
More informationPICP WINTER WORKSHOPS
PICP WINTER WORKSHOPS Designing, Constructing, Inspecting and Maintaining Excellence Join us for a free PICP workshop where Bob Bridges, Director of Sales for Eagle Bay SWM PAVE, will share his experiences
More informationBegin forwarded message:
From: To: Subject: Date: Attachments: Heather Scott Tully, Tania Fwd: Stalite Root Bridge Tuesday, November 17, 2015 8:58:01 AM Stalite_Root_Bridge_brochure[1].pdf Begin forwarded message: From: "Chuck
More informationSoakage Trenches. A better way to manage stormwater. Thinking Globally and Acting Locally
Soakage Trenches A better way to manage stormwater Thinking Globally and Acting Locally A partnership of the Scranton Sewer Authority, The Lackawanna River Corridor Association and the citizens of Scranton
More information4.1. Permeable Pavement Systems
4.1. Permeable Pavement Systems Permeable Pavement provides the structural support of conventional pavement, but allows stormwater to drain directly through the surface into the underlying stone base and
More informationCity of Hilshire Village Pine Creek Ln Reconstruction
City of Hilshire Village Pine Creek Ln Reconstruction OVERVIEW The City will be soliciting bids for the Pine Creek Reconstruction Project with construction scheduled to begin in January 2015. This project
More informationSPECIFICATIONS. INTERLOCKING CONCRETE POROUS PAVING UNITS or Permeable Interlocking Concrete Pavers (PICP)
SPECIFICATIONS INTERLOCKING CONCRETE POROUS PAVING UNITS or Permeable Interlocking Concrete Pavers (PICP) Part 1 General 1.1 CONFORMITY Conforms to the requirements of the general conditions of the contract.
More informationSECTION 32 14 13.19 PERMEABLE INTERLOCKING CONCRETE PAVEMENT (1995 MasterFormat Section 02795)
SECTION 32 14 13.19 PERMEABLE INTERLOCKING CONCRETE PAVEMENT (1995 MasterFormat Section 02795) Note: This guide specification for U.S. applications describes construction of permeable interlocking concrete
More informationPervious Pavement SYSTEMS THINKING. THE NEW DESIGN PROBLEM and the Role of the Civil Engineer. LOW IMPACT DEVELOPMENT Introduction
Pervious Pavement Options and Design Guidelines (with LID example projects) SYSTEMS THINKING Need to think differently about the problem Whole System Design Site & Project Relationships Integrated Design
More informationSECTION 02795 UNI PERMEABLE INTERLOCKING CONCRETE PAVEMENT
SECTION 02795 UNI PERMEABLE INTERLOCKING CONCRETE PAVEMENT Note: This guide specification is intended for use in the U.S. It describes construction of permeable interlocking concrete pavers on a permeable,
More informationSection 600 Incidental Construction
Table of Contents 1. Pipe Culverts... 600-1 A. Endwalls, Inlets, Manholes, and Spring Boxes... 600-5 2. Grade Adjustment of Existing Miscellaneous Structures... 600-8 3. Rebuilt Miscellaneous Structures...
More informationVILLAS OF TRADITIONS AT GREY OAKS
Report of Turnover Survey VILLAS OF TRADITIONS AT GREY OAKS Grey Oaks Development Naples, Collier County, Florida Forge Engineering Project Number 2907-001.01 March 2015 Richard P..Lundberg, P.E cn=richard
More informationAppendix 6. Permeable Alley Preliminary Evaluation
Appendix 6 Permeable Alley Preliminary Evaluation ACHD Alley Retrofit Project Initial Evaluation Site Selection, Design, and Construction (October 2014) The purpose of this document is to characterize
More informationInstalling Porous Pavement Waukesha County Dept. of Parks & Land Use Storm Water BMP Design and Installation Workshop March 11, 2009
Installing Porous Pavement Waukesha County Dept. of Parks & Land Use Storm Water BMP Design and Installation Workshop March 11, 2009 Presented by Willie Gonwa, P.E., Ph.D. West Allis, Wisconsin Porous
More informationStorm Drain Inlet Protection
Objectives EC Erosion Control SE Sediment Control TR Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution Control Legend: Primary Objective
More informationSECTION 02221 SELECTIVE DEMOLITION
SECTION 02221 PART 1 -GENERAL 1.01 DESCRIPTION This section includes all material, labor, machinery and supervision required to demolish and remove the following items where applicable and as noted on
More informationesign interloc SUMMER 2014 PICP Residential Rebates Increasing Job Site Efficiency Preventing Bans on Charity Car Washes
THE OFFICIAL PUBLICATION OF THE INTERLOCKING CONCRETE PAVEMENT INSTITUTE interloc esign PICP Residential Rebates Increasing Job Site Efficiency Preventing Bans on Charity Car Washes volume 21 number 3
More informationSE-10 STORM DRAIN INLET PROTECTION. Objectives
STORM DRAIN INLET PROTECTION SE-10 Objectives Erosion Control - EC Sediment Control - SE Tracking Control - TC Wind Erosion Control - WE Non-Storm Water Management - NS Waste and Materials Management -
More informationCONCRETE SEGMENTAL RETAINING WALL SYSTEM
CONCRETE SEGMENTAL RETAINING WALL SYSTEM PART 1: GENERAL SPECIFICATIONS 1.01 Work Included A. Work shall consist of furnishing and constructing a Rockwood Classic 8 with PCS unit segmental retaining wall
More informationCity of Shelbyville Site Inspection Checklist
City of Shelbyville Site Inspection Checklist General Information Project Name: KYR10 Permit Number: Date: Project Location: Contractor: Conractor Representative: Inspector's Name: Title: Signature : Weather
More informationAUSTRALIAN PAVING CENTRE
AUSTRALIAN PAVING CENTRE The Concept 02 The concept of Ecopave permeable paving is already well established in many countries where development threatens already over-stretched drainage and river systems.
More informationStorm Drain Inlet Protection
Source: Caltrans Construction Site Best Management Practices Manual, 2003. Description Applications Installation and Implementation Requirements Devices installed at storm drain inlets to detain and/or
More informationOhio Department of Transportation Division of Production Management Office of Geotechnical Engineering. Geotechnical Bulletin PLAN SUBGRADES
Ohio Department of Transportation Division of Production Management Office of Geotechnical Engineering Geotechnical Bulletin GB 1 PLAN SUBGRADES Geotechnical Bulletin GB1 was jointly developed by the Offices
More informationSECTION 02530 STORM DRAINAGE STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.
02530-1 of 5 SECTION 02530 STORM DRAINAGE STRUCTURES 02530.01 GENERAL A. Description Storm drainage structure construction shall include, but not necessarily be limited to, furnishing and installing or
More informationGreen Infrastructure for Single Family Residences
Green Infrastructure for Single Family Residences CITY OF ATLANTA STORMWATER GUIDELINES Prepared for CITY OF ATLANTA, GEORGIA DEPARTMENT OF WATERSHED MANAGEMENT NOVEMBER 2012 Prepared by AMEC Environment
More informationhttp://facilities.gwu.edu/greenroof/october/
Page 1 of 9 Green Roof - October 2008 Facilities Alerts Getting Work Done > On Saturday, October 25, 2008 several members of the GW community came together to install the Green Roof. Below, is a description
More informationFairlington Community Center
Williamsburg Boulevard Green Street Project June 13, 2012 Williamsburg Middle School Relevant Outreach November 12, 2008: Introduction to Little Pimmit Run Watershed Retrofits Workshop, Yorktown High School
More informationDesign, Construction and Maintenance of Permeable Pavements Case Studies and Technical Resources Robert Bowers, P. Eng.
Design, Construction and Maintenance of Permeable Pavements Case Studies and Technical Resources Robert Bowers, P. Eng. Source: CH2M Hill The Presenter Robert Bowers, P.Eng., LEED GA rbowers@icpi.org Director
More informationOperations and Maintenance
Seattle Public Utilities Green Stormwater Infrastructure: O&M Program Operations and Maintenance O&M Maintenance Took Kit 1. Landscape Maintenance Manual 2. GSI/LID Maintenance Manual for ROW 3. Identifiable
More informationCivil. 2. City of Seattle Supplement to the Specification for Road, Bridge and Municipal Construction, most current addition.
Design Guide Basis of Design This section applies to the design and installation of earthwork and backfill. Design Criteria No stockpiling of excavation materials is allowed unless the Geotechnical Engineer
More informationSECTION 02100 SITE PREPARATION
SECTION 02100 SITE PREPARATION PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and General Provisions of Contract, including General Conditions and Supplementary Conditions and Division 1 through Division
More informationGREEN ROOFS. Location. Design SMALL COMMERCIAL GUIDE CITY OF ATLANTA, GEORGIA DEPARTMENT OF WATERSHED MANAGEMENT
SMALL COMMERCIAL GUIDE CITY OF ATLANTA, GEORGIA DEPARTMENT OF WATERSHED MANAGEMENT GREEN ROOFS A green roof is a system consisting of waterproofing material, growing medium, and vegetation, and is used
More informationPermeable Interlocking Concrete Pavements. The Stormwater Problem
Permeable Interlocking Concrete Pavements The Stormwater Problem 1 Stormwater Management Objectives Water Quantity Accommodate water volumes & peak flows Water Quality Control pollutant levels A Low Impact
More informationSTANDARD AND SPECIFICATIONS FOR STORM DRAIN INLET PROTECTION
STANDARD AND SPECIFICATIONS FOR STORM DRAIN INLET PROTECTION Design Criteria Drainage Area The drainage area for storm drain inlets shall not exceed one acre. The crest elevations of these practices shall
More informationSummary and Description of 2014 Enhancements to New Jersey Model Stormwater Control Ordinance for Municipalities
Summary and Description of 2014 Enhancements to New Jersey Model Stormwater Control Ordinance for Municipalities This document summarizes and provides explanation for the purpose and intent of major recommended
More informationStorm Water Runoff. Managing. A Self-Assessment Guide for Wisconsin Businesses. Storm water runoff is coming. This guide provides businesses
Managing Storm Water Runoff A Self-Assessment Guide for Wisconsin Businesses Storm water runoff is coming under increasing scrutiny as both a source of pollutants to our lakes and streams, and as a cause
More informationBEST PRACTICES. Smart Transportation is a key concept for the Paoli Roadway Improvement Project.
Smart Transportation Smart Transportation is a key concept for the Paoli Roadway Improvement Project. PennDOT s Smart Transportation Guidebook (2008) outlines a comprehensive approach to transportation
More informationSECTION 32 14 00 PERVIOUS INTERLOCKING CERAMIC PAVERS
SECTION 32 14 00 PERVIOUS INTERLOCKING CERAMIC PAVERS Pervious interlocking pavers.doc Note: This guide specification for U.S. applications describes construction of permeable interlocking ceramic pavers
More informationVehicle Tracking Pad
Stormwater Quality Best Management Practices Construction Sites s When to use: Where construction vehicles leave active construction areas onto surfaces where runoff is not checked by sediment controls
More informationUnit Price Averages Reports
Unit Price Averages Reports 12/7/2015 UNIT PRICE AVERAGES REPORT Disclaimer The information provided in the following Unit Price Averages Report is only for the use of Alberta Infrastructure & Transportation
More informationMinimizes sediment and debris from entering storm drains that lead to waterways and watercourses.
4.5-p DRAIN INLET PROTECTION Alternative Names: DI protection, Drop Inlet Protection DESCRIPTION Storm drain inlet (DI) protection slows and ponds stormwater, and filters sediment and debris before it
More informationAGENCY COORDINATION AND PUBLIC INVOLVEMENT
5 AGENCY COORDINATION AND PUBLIC INVOLVEMENT 5.1 AGENCY COORDINATION As part of the planning process for the Oregon Avenue Final EA, DDOT conducted an agency coordination program. This coordination included
More informationOperation & Maintenance Document Templates
Appendix G Operation & Maintenance Document Templates The following templates are provided to assist project applicants in preparing stormwater treatment measure maintenance plans, which municipalities
More informationBeseck Switching Station Inspection
Page 1 of 5 Docket No. 272 Development and Management Plan Inspection The Connecticut Light and Power Company Certificate of Environmental Compatibility and Public Need for the construction of a new 345-kV
More informationDEVELOPMENT OF AN ASCE STANDARD FOR PERMEABLE INTERLOCKING CONCRETE PAVEMENT
DEVELOPMENT OF AN ASCE STANDARD FOR PERMEABLE INTERLOCKING CONCRETE PAVEMENT David K. Hein, P. Eng. Vice-President, Applied Research Associates Inc., 5401 Eglinton Avenue West, Suite 204, Toronto, ON,
More informationTree Pits Operation & Maintenance Guide
Tree Pits Operation & Maintenance Guide What are tree pits? Tree pits collect stormwater runoff from small carpark areas or roads. Runoff filters through the tree roots and surrounding soil mix, trapping
More informationSECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.
02150-1 of 6 SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING 02150.01 GENERAL A. Description Removal or abandonment of existing utilities and underground structures shall include, but not necessarily
More informationPICP Construction. Why PICPs The Big Picture. Key things to know about PICPs
PICP Construction Permeable Interlocking Concrete Pavement Presenter: Frank Gandora, President Creative Hardscape Why PICPs The Big Picture Germany was first to develop PICPs 2005 Clean Water Act Federal
More informationTable 4.9 Storm Drain Inlet Protetion Applicable for
BMP C220: Storm Drain Inlet Protection Purpose To prevent coarse sediment from entering drainage systems prior to permanent stabilization of the disturbed area. Conditions of Use Type of Inlet Protection
More informationIndividual Residential Property Credit
NORTHEAST OHIO REGIONAL SEWER DISTRICT Stormwater Management Program Individual Residential Property Credit Revised 12/11/12 why stormwater management? flooding POLLUTION EROSION The inability to effectively
More informationLS 2540 SEWER LATERALS AND INSPECTION TEES
LS 2540 SEWER LATERALS AND INSPECTION TEES A. Summary B. Submittals C. Site Information D. Sewer Pipe and Fittings E. Lateral Locations F. Lateral Installation G. Inspection Tee Installation H. Removal
More informationBurnsville Stormwater Retrofit Study
Burnsville Stormwater Retrofit Study Prepared for City of Burnsville June 2006 4700 West 77 th Street Minneapolis, MN 55435-4803 Phone: (952) 832-2600 Fax: (952) 832-2601 Burnsville Stormwater Retrofit
More informationLID-01 Permeable Paving Systems
Greenville County Technical Specification for LID-01 Permeable Paving Systems 1.0 Permeable Paving Systems 1.1 Description Permeable Paving Systems are a best management practice that captures stormwater
More informationChapter 3 CULVERTS. Description. Importance to Maintenance & Water Quality. Culvert Profile
Chapter 3 CULVERTS Description A culvert is a closed conduit used to convey water from one area to another, usually from one side of a road to the other side. Importance to Maintenance & Water Quality
More informationLocal Road Assessment and Improvement Drainage Manual
Local Road Assessment and Improvement Drainage Manual Donald Walker, T.I.C. Director, author Lynn Entine, Entine & Associates, editor Susan Kummer, Artifax, design Transportation Information Center University
More information40-9 PERMEABLE INTERLOCKING CONCRETE PAVEMENT
40-9 PERMEABLE INTERLOCKING CONCRETE PAVEMENT 40-9.01 GENERAL 40-9.01A Summary Section 40-9 includes specifications for furnishing and installing concrete pavers for permeable interlocking concrete pavement
More informationCONCRETE SEGMENTAL RETAINING WALL SYSTEM
CONCRETE SEGMENTAL RETAINING WALL SYSTEM PART 1: GENERAL SPECIFICATIONS 1.01 Work Included A. Work shall consist of furnishing and constructing a Rockwood Vintage TM unit segmental retaining wall (SRW)
More informationa guide to PREVENTING HOME FLOODING DURING STORMS
DISTRICT OF COLUMBIA WATER AND SEWER AUTHORITY a guide to PREVENTING HOME FLOODING DURING STORMS DCWATER.COM Updated August 15, 2012 Flooding can damage District homes and businesses. It results when the
More informationCONSTRUCTION STORMWATER POLLUTION PREVENTION PLAN TEMPLATE
CONSTRUCTION STORMWATER POLLUTION PREVENTION PLAN TEMPLATE The following template may be used as a general guide for development of a Stormwater Pollution Prevention Plan (SWPPP) for construction activities.
More informationDESCRIPTION OF STORMWATER STRUCTURAL CONTROLS IN MS4 PERMITS
DESCRIPTION OF STORMWATER STRUCTURAL CONTROLS IN MS4 PERMITS Phase I MS4 permits require continuous updating of the stormwater system inventory owned and operated by the MS4. They also include inspection
More informationC. Section 014510 TESTING LABORATORY SERVICE.
SECTION 014500 QUALITY CONTROL PART 1 GENERAL 1.01 RELATED REQUIREMENTS A. Drawings and General Provisions of Contract, including General and Special Conditions and other Division 1 Specification Sections,
More informationCONSTRUCTION PERMIT REQUIREMENTS
CONSTRUCTION PERMIT REQUIREMENTS Any work to be done in the City right-of-way (ROW), in a utility easement, and certain work on private property, requires an Engineering Inspection Permit from the Department
More informationSECTION 32 14 13.19 PERMEABLE INTERLOCKING CONCRETE PAVEMENT
PART 1 GENERAL 1.1 SECTION INCLUDES SECTION 32 14 13.19 PERMEABLE INTERLOCKING CONCRETE PAVEMENT A. The requirements for construction of permeable interlocking concrete pavement: 1. Install the interlocking
More informationSection 2100-Trenching and Tunneling
SECTION 5200 - STORM SEWER PART 1 - GENERAL 1.01 SCOPE: This Section covers installation of storm sewer mains and culverts. Topics include permits and fees, trench widths, pipe laying, bedding, initial
More informationWaukesha County. Municipal Separate Storm Sewer System (MS4) Permit. 2008 Annual Report to the Land Use Parks & Environment Committee
Waukesha County Municipal Separate Storm Sewer System (MS4) Permit 2008 Annual Report to the Land Use Parks & Environment Committee What is an MS4 permit? 1972 Clean Water Act (Water pollution control):
More informationSEDIMENT/STORMWATER MANAGEMENT BASIN CONSTRUCTION CHECKLIST
SEDIMENT/STORMWATER MANAGEMENT BASIN CONSTRUCTION CHECKLIST For permanent structures per Delaware SCS Pond Code 378 and Delaware Sediment and Stormwater Regulations KEY PROJECT INFORMATION Item meets standard
More informationGUIDE SPECIFICATIONS FOR CONSTRUCTION OF AQUAPAVE PERMEABLE STORMWATER MANAGEMENT SYSTEM
GUIDE SPECIFICATIONS FOR CONSTRUCTION OF AQUAPAVE PERMEABLE STORMWATER MANAGEMENT SYSTEM SECTION 32 14 13.19 AquaPave Permeable Interlocking Concrete Pavement Note: This guide specification is for the
More informationBMP 6.4.6: Dry Well / Seepage Pit
BMP 6.4.6: Dry Well / Seepage Pit A Dry Well, or Seepage Pit, is a variation on an Infiltration system that is designed to temporarily store and infiltrate rooftop runoff. Key Design Elements Fllow Infiltration
More informationAPPLICATION FOR DEMOLITION & RIGHT-OF OF-WAY PERMIT
APPLICATION FOR DEMOLITION & RIGHT-OF OF-WAY PERMIT City of Swartz Creek 8083 Civic Drive Swartz Creek, MI 48473 810-635-4464 Fee Received: $ Date: / / Receipt No: Demolition Permit (including Right of
More information