1 Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 25,800' + Separated Trail length ~ 13,700' = Total Length ~ 39,500' or 7.5 miles) Clear and grub AC $30, $1,500,000 Clear all nuisance plants full width Cut and fill (single trail) CY $10 20,000 $200,000 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $10 10,600 $106,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $150 4,400 $660,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $150 2,670 $400,500 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $22 33,600 $739,200 6" bank run shell Base (dbl. trail) SY $22 33,500 $737,000 6" bank run shell Subbase (single trail) SY $11 5,000 $55,000 Build base as needed in poor soils Subbase (dbl. trail) SY $11 10,000 $110,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $20 5,000 $100,000 Chain link type as needed Ped/bike railing LF $70 1,500 $105,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $25, $900,000 Border trees and bushes as needed Sod, seeding SY $3 130,000 $390,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $60,000 1 $60,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $6, $192,000 drainage pipe and structures Pond/swale construction EA $30,000 6 $180,000 pond/swale construction SubTotal $7,024,200

2 Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $1,125,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $375,000 Est. 0.5 contam. sites per mile Surface water remediation MI $100, $375,000 Est. 0.5 sites per mile Steel and tie/timber credit MI -$50, $375,000 Est. 0.5 contam. sites per mile SubTotal $1,725,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10, $130,000 all road intersections SubTotal $1,095,500 Shelters Approach paths EA $2,000 8 $16,000 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $6,000 8 $48,000 foundation cost Landscaping EA $5,000 8 $40,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work EA $8,000 8 $64,000 general site prep. SubTotal $44,000 $352,000

3 Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges Main A LS $525,000 1 $525,000 Prefab. Steel Truss bridge with foundations Main B LS $325,000 1 $325,000 Prefab. Steel Truss bridge with foundations SubTotal $850,000 Utilities Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,270,000 Mobilization 3.0% $380,000 MOT 2.0% $250,000 Geotech and misc. Testing 2.0% $250,000 Additional items 4.0% $510,000 Contingency 10.0% $1,270,000 Asbuilts, close-out 2.0% $250,000 SubTotal $4,180,000 Project Cost Estimate Total $16,846,700

4 ( This Page Blank.)

5 Rails-with-Trails Option Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 17,800' + Separated Trail length ~ 21,700' = Total Length ~ 39,500' or 7.5 miles) Clearing and grubbing AC $38, $1,900,000 Clear all nuisance plants full width Cut and fill (single trail) CY $12 15,800 $189,600 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $13 22,000 $286,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $180 3,050 $549,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $180 4,240 $763,200 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $27 33,600 $907,200 6" bank run shell Base (dbl. trail) SY $28 48,200 $1,349,600 6" bank run shell Subbase (single trail) SY $14 15,800 $221,200 Build base as needed in poor soils Subbase (dbl. trail) SY $14 24,000 $336,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $24 5,000 $120,000 Chain link type as needed Ped/bike railing LF $84 1,500 $126,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $30, $1,080,000 Border trees and bushes as needed Sod, seeding SY $4 130,000 $455,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $75,000 1 $75,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $7, $240,000 drainage pipe and structures Pond/swale construction EA $36,000 6 $216,000 pond/swale construction SubTotal $9,403,300

6 Rails-with-Trails Option Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $75,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $750,000 Est. 1 contam. Location per mile Surface water remediation MI $100, $750,000 Est. 1 Location per mile Steel and tie/timber credit MI -$50, $25,000 Est. 1 contam. Location per mile SubTotal $1,775,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10,000 0 $0 all road intersections SubTotal $965,500 Shelters Approach paths EA $2,400 8 $19,200 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $7,200 8 $57,600 foundation cost Landscaping EA $6,000 8 $48,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work, benches, trash can, etc. EA $8,000 8 $64,000 general site prep. SubTotal $46,600 $372,800

7 Rails-with-Trails Option Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges (2) over Philippi Creek Main A LS $625,000 1 $625,000 Prefab. Steel Truss bridge with foundations Main B LS $390,000 1 $390,000 Prefab. Steel Truss bridge with foundations SubTotal $1,015,000 Utilities at Trail Heads and Shelters w/ Water Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,520,000 Mobilization 3.0% $450,000 MOT 3.0% $450,000 Geotech and misc. Testing 2.0% $300,000 Additional items 4.0% $610,000 Contingency 10.0% $1,520,000 Asbuilts, close-out 2.0% $300,000 SubTotal $5,150,000 Project Cost Estimate Total $20,301,600

8 Cost Unit Descriptions UNIT AC CY EA LF LS MI NM SF SY TN DESCRIPTION Acre Cubic Yard Each Linear Foot Lump Sum Mile Net Mile Square Foot Square Yard Ton

9 Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 25,800' + Separated Trail length ~ 13,700' = Total Length ~ 39,500' or 7.5 miles) Clear and grub AC $30, $1,500,000 Clear all nuisance plants full width Cut and fill (single trail) CY $10 20,000 $200,000 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $10 10,600 $106,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $150 4,400 $660,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $150 2,670 $400,500 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $22 33,600 $739,200 6" bank run shell Base (dbl. trail) SY $22 33,500 $737,000 6" bank run shell Subbase (single trail) SY $11 5,000 $55,000 Build base as needed in poor soils Subbase (dbl. trail) SY $11 10,000 $110,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $20 5,000 $100,000 Chain link type as needed Ped/bike railing LF $70 1,500 $105,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $25, $900,000 Border trees and bushes as needed Sod, seeding SY $3 130,000 $390,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $60,000 1 $60,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $6, $192,000 drainage pipe and structures Pond/swale construction EA $30,000 6 $180,000 pond/swale construction SubTotal $7,024,200

10 Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $1,125,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $375,000 Est. 0.5 contam. sites per mile Surface water remediation MI $100, $375,000 Est. 0.5 sites per mile Steel and tie/timber credit MI -$50, $375,000 Est. 0.5 contam. sites per mile SubTotal $1,725,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10, $130,000 all road intersections SubTotal $1,095,500 Shelters Approach paths EA $2,000 8 $16,000 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $6,000 8 $48,000 foundation cost Landscaping EA $5,000 8 $40,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work EA $8,000 8 $64,000 general site prep. SubTotal $44,000 $352,000

11 Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges Main A LS $525,000 1 $525,000 Prefab. Steel Truss bridge with foundations Main B LS $325,000 1 $325,000 Prefab. Steel Truss bridge with foundations SubTotal $850,000 Utilities Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,270,000 Mobilization 3.0% $380,000 MOT 2.0% $250,000 Geotech and misc. Testing 2.0% $250,000 Additional items 4.0% $510,000 Contingency 10.0% $1,270,000 Asbuilts, close-out 2.0% $250,000 SubTotal $4,180,000 Project Cost Estimate Total $16,846,700

12 ( This Page Blank.)

13 Rails-with-Trails Option Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 17,800' + Separated Trail length ~ 21,700' = Total Length ~ 39,500' or 7.5 miles) Clearing and grubbing AC $38, $1,900,000 Clear all nuisance plants full width Cut and fill (single trail) CY $12 15,800 $189,600 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $13 22,000 $286,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $180 3,050 $549,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $180 4,240 $763,200 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $27 33,600 $907,200 6" bank run shell Base (dbl. trail) SY $28 48,200 $1,349,600 6" bank run shell Subbase (single trail) SY $14 15,800 $221,200 Build base as needed in poor soils Subbase (dbl. trail) SY $14 24,000 $336,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $24 5,000 $120,000 Chain link type as needed Ped/bike railing LF $84 1,500 $126,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $30, $1,080,000 Border trees and bushes as needed Sod, seeding SY $4 130,000 $455,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $75,000 1 $75,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $7, $240,000 drainage pipe and structures Pond/swale construction EA $36,000 6 $216,000 pond/swale construction SubTotal $9,403,300

14 Rails-with-Trails Option Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $75,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $750,000 Est. 1 contam. Location per mile Surface water remediation MI $100, $750,000 Est. 1 Location per mile Steel and tie/timber credit MI -$50, $25,000 Est. 1 contam. Location per mile SubTotal $1,775,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10,000 0 $0 all road intersections SubTotal $965,500 Shelters Approach paths EA $2,400 8 $19,200 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $7,200 8 $57,600 foundation cost Landscaping EA $6,000 8 $48,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work, benches, trash can, etc. EA $8,000 8 $64,000 general site prep. SubTotal $46,600 $372,800

15 Rails-with-Trails Option Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges (2) over Philippi Creek Main A LS $625,000 1 $625,000 Prefab. Steel Truss bridge with foundations Main B LS $390,000 1 $390,000 Prefab. Steel Truss bridge with foundations SubTotal $1,015,000 Utilities at Trail Heads and Shelters w/ Water Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,520,000 Mobilization 3.0% $450,000 MOT 3.0% $450,000 Geotech and misc. Testing 2.0% $300,000 Additional items 4.0% $610,000 Contingency 10.0% $1,520,000 Asbuilts, close-out 2.0% $300,000 SubTotal $5,150,000 Project Cost Estimate Total $20,301,600

16 Cost Unit Descriptions UNIT AC CY EA LF LS MI NM SF SY TN DESCRIPTION Acre Cubic Yard Each Linear Foot Lump Sum Mile Net Mile Square Foot Square Yard Ton

17 Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 25,800' + Separated Trail length ~ 13,700' = Total Length ~ 39,500' or 7.5 miles) Clear and grub AC $30, $1,500,000 Clear all nuisance plants full width Cut and fill (single trail) CY $10 20,000 $200,000 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $10 10,600 $106,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $150 4,400 $660,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $150 2,670 $400,500 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $22 33,600 $739,200 6" bank run shell Base (dbl. trail) SY $22 33,500 $737,000 6" bank run shell Subbase (single trail) SY $11 5,000 $55,000 Build base as needed in poor soils Subbase (dbl. trail) SY $11 10,000 $110,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $20 5,000 $100,000 Chain link type as needed Ped/bike railing LF $70 1,500 $105,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $25, $900,000 Border trees and bushes as needed Sod, seeding SY $3 130,000 $390,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $60,000 1 $60,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $6, $192,000 drainage pipe and structures Pond/swale construction EA $30,000 6 $180,000 pond/swale construction SubTotal $7,024,200

18 Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $1,125,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $375,000 Est. 0.5 contam. sites per mile Surface water remediation MI $100, $375,000 Est. 0.5 sites per mile Steel and tie/timber credit MI -$50, $375,000 Est. 0.5 contam. sites per mile SubTotal $1,725,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10, $130,000 all road intersections SubTotal $1,095,500 Shelters Approach paths EA $2,000 8 $16,000 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $6,000 8 $48,000 foundation cost Landscaping EA $5,000 8 $40,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work EA $8,000 8 $64,000 general site prep. SubTotal $44,000 $352,000

19 Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges Main A LS $525,000 1 $525,000 Prefab. Steel Truss bridge with foundations Main B LS $325,000 1 $325,000 Prefab. Steel Truss bridge with foundations SubTotal $850,000 Utilities Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,270,000 Mobilization 3.0% $380,000 MOT 2.0% $250,000 Geotech and misc. Testing 2.0% $250,000 Additional items 4.0% $510,000 Contingency 10.0% $1,270,000 Asbuilts, close-out 2.0% $250,000 SubTotal $4,180,000 Project Cost Estimate Total $16,846,700

20 ( This Page Blank.)

21 Rails-with-Trails Option Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 17,800' + Separated Trail length ~ 21,700' = Total Length ~ 39,500' or 7.5 miles) Clearing and grubbing AC $38, $1,900,000 Clear all nuisance plants full width Cut and fill (single trail) CY $12 15,800 $189,600 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $13 22,000 $286,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $180 3,050 $549,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $180 4,240 $763,200 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $27 33,600 $907,200 6" bank run shell Base (dbl. trail) SY $28 48,200 $1,349,600 6" bank run shell Subbase (single trail) SY $14 15,800 $221,200 Build base as needed in poor soils Subbase (dbl. trail) SY $14 24,000 $336,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $24 5,000 $120,000 Chain link type as needed Ped/bike railing LF $84 1,500 $126,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $30, $1,080,000 Border trees and bushes as needed Sod, seeding SY $4 130,000 $455,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $75,000 1 $75,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $7, $240,000 drainage pipe and structures Pond/swale construction EA $36,000 6 $216,000 pond/swale construction SubTotal $9,403,300

22 Rails-with-Trails Option Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $75,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $750,000 Est. 1 contam. Location per mile Surface water remediation MI $100, $750,000 Est. 1 Location per mile Steel and tie/timber credit MI -$50, $25,000 Est. 1 contam. Location per mile SubTotal $1,775,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10,000 0 $0 all road intersections SubTotal $965,500 Shelters Approach paths EA $2,400 8 $19,200 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $7,200 8 $57,600 foundation cost Landscaping EA $6,000 8 $48,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work, benches, trash can, etc. EA $8,000 8 $64,000 general site prep. SubTotal $46,600 $372,800

23 Rails-with-Trails Option Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges (2) over Philippi Creek Main A LS $625,000 1 $625,000 Prefab. Steel Truss bridge with foundations Main B LS $390,000 1 $390,000 Prefab. Steel Truss bridge with foundations SubTotal $1,015,000 Utilities at Trail Heads and Shelters w/ Water Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,520,000 Mobilization 3.0% $450,000 MOT 3.0% $450,000 Geotech and misc. Testing 2.0% $300,000 Additional items 4.0% $610,000 Contingency 10.0% $1,520,000 Asbuilts, close-out 2.0% $300,000 SubTotal $5,150,000 Project Cost Estimate Total $20,301,600

24 Cost Unit Descriptions UNIT AC CY EA LF LS MI NM SF SY TN DESCRIPTION Acre Cubic Yard Each Linear Foot Lump Sum Mile Net Mile Square Foot Square Yard Ton

25 Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 25,800' + Separated Trail length ~ 13,700' = Total Length ~ 39,500' or 7.5 miles) Clear and grub AC $30, $1,500,000 Clear all nuisance plants full width Cut and fill (single trail) CY $10 20,000 $200,000 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $10 10,600 $106,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $150 4,400 $660,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $150 2,670 $400,500 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $22 33,600 $739,200 6" bank run shell Base (dbl. trail) SY $22 33,500 $737,000 6" bank run shell Subbase (single trail) SY $11 5,000 $55,000 Build base as needed in poor soils Subbase (dbl. trail) SY $11 10,000 $110,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $20 5,000 $100,000 Chain link type as needed Ped/bike railing LF $70 1,500 $105,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $25, $900,000 Border trees and bushes as needed Sod, seeding SY $3 130,000 $390,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $60,000 1 $60,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $6, $192,000 drainage pipe and structures Pond/swale construction EA $30,000 6 $180,000 pond/swale construction SubTotal $7,024,200

26 Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $1,125,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $375,000 Est. 0.5 contam. sites per mile Surface water remediation MI $100, $375,000 Est. 0.5 sites per mile Steel and tie/timber credit MI -$50, $375,000 Est. 0.5 contam. sites per mile SubTotal $1,725,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10, $130,000 all road intersections SubTotal $1,095,500 Shelters Approach paths EA $2,000 8 $16,000 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $6,000 8 $48,000 foundation cost Landscaping EA $5,000 8 $40,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work EA $8,000 8 $64,000 general site prep. SubTotal $44,000 $352,000

27 Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges Main A LS $525,000 1 $525,000 Prefab. Steel Truss bridge with foundations Main B LS $325,000 1 $325,000 Prefab. Steel Truss bridge with foundations SubTotal $850,000 Utilities Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,270,000 Mobilization 3.0% $380,000 MOT 2.0% $250,000 Geotech and misc. Testing 2.0% $250,000 Additional items 4.0% $510,000 Contingency 10.0% $1,270,000 Asbuilts, close-out 2.0% $250,000 SubTotal $4,180,000 Project Cost Estimate Total $16,846,700

28 ( This Page Blank.)

29 Rails-with-Trails Option Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 17,800' + Separated Trail length ~ 21,700' = Total Length ~ 39,500' or 7.5 miles) Clearing and grubbing AC $38, $1,900,000 Clear all nuisance plants full width Cut and fill (single trail) CY $12 15,800 $189,600 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $13 22,000 $286,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $180 3,050 $549,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $180 4,240 $763,200 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $27 33,600 $907,200 6" bank run shell Base (dbl. trail) SY $28 48,200 $1,349,600 6" bank run shell Subbase (single trail) SY $14 15,800 $221,200 Build base as needed in poor soils Subbase (dbl. trail) SY $14 24,000 $336,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $24 5,000 $120,000 Chain link type as needed Ped/bike railing LF $84 1,500 $126,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $30, $1,080,000 Border trees and bushes as needed Sod, seeding SY $4 130,000 $455,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $75,000 1 $75,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $7, $240,000 drainage pipe and structures Pond/swale construction EA $36,000 6 $216,000 pond/swale construction SubTotal $9,403,300

30 Rails-with-Trails Option Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $75,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $750,000 Est. 1 contam. Location per mile Surface water remediation MI $100, $750,000 Est. 1 Location per mile Steel and tie/timber credit MI -$50, $25,000 Est. 1 contam. Location per mile SubTotal $1,775,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10,000 0 $0 all road intersections SubTotal $965,500 Shelters Approach paths EA $2,400 8 $19,200 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $7,200 8 $57,600 foundation cost Landscaping EA $6,000 8 $48,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work, benches, trash can, etc. EA $8,000 8 $64,000 general site prep. SubTotal $46,600 $372,800

31 Rails-with-Trails Option Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges (2) over Philippi Creek Main A LS $625,000 1 $625,000 Prefab. Steel Truss bridge with foundations Main B LS $390,000 1 $390,000 Prefab. Steel Truss bridge with foundations SubTotal $1,015,000 Utilities at Trail Heads and Shelters w/ Water Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,520,000 Mobilization 3.0% $450,000 MOT 3.0% $450,000 Geotech and misc. Testing 2.0% $300,000 Additional items 4.0% $610,000 Contingency 10.0% $1,520,000 Asbuilts, close-out 2.0% $300,000 SubTotal $5,150,000 Project Cost Estimate Total $20,301,600

32 Cost Unit Descriptions UNIT AC CY EA LF LS MI NM SF SY TN DESCRIPTION Acre Cubic Yard Each Linear Foot Lump Sum Mile Net Mile Square Foot Square Yard Ton

33 Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 25,800' + Separated Trail length ~ 13,700' = Total Length ~ 39,500' or 7.5 miles) Clear and grub AC $30, $1,500,000 Clear all nuisance plants full width Cut and fill (single trail) CY $10 20,000 $200,000 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $10 10,600 $106,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $150 4,400 $660,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $150 2,670 $400,500 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $22 33,600 $739,200 6" bank run shell Base (dbl. trail) SY $22 33,500 $737,000 6" bank run shell Subbase (single trail) SY $11 5,000 $55,000 Build base as needed in poor soils Subbase (dbl. trail) SY $11 10,000 $110,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $20 5,000 $100,000 Chain link type as needed Ped/bike railing LF $70 1,500 $105,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $25, $900,000 Border trees and bushes as needed Sod, seeding SY $3 130,000 $390,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $60,000 1 $60,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $6, $192,000 drainage pipe and structures Pond/swale construction EA $30,000 6 $180,000 pond/swale construction SubTotal $7,024,200

34 Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $1,125,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $375,000 Est. 0.5 contam. sites per mile Surface water remediation MI $100, $375,000 Est. 0.5 sites per mile Steel and tie/timber credit MI -$50, $375,000 Est. 0.5 contam. sites per mile SubTotal $1,725,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10, $130,000 all road intersections SubTotal $1,095,500 Shelters Approach paths EA $2,000 8 $16,000 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $6,000 8 $48,000 foundation cost Landscaping EA $5,000 8 $40,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work EA $8,000 8 $64,000 general site prep. SubTotal $44,000 $352,000

35 Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges Main A LS $525,000 1 $525,000 Prefab. Steel Truss bridge with foundations Main B LS $325,000 1 $325,000 Prefab. Steel Truss bridge with foundations SubTotal $850,000 Utilities Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,270,000 Mobilization 3.0% $380,000 MOT 2.0% $250,000 Geotech and misc. Testing 2.0% $250,000 Additional items 4.0% $510,000 Contingency 10.0% $1,270,000 Asbuilts, close-out 2.0% $250,000 SubTotal $4,180,000 Project Cost Estimate Total $16,846,700

36 ( This Page Blank.)

37 Rails-with-Trails Option Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 17,800' + Separated Trail length ~ 21,700' = Total Length ~ 39,500' or 7.5 miles) Clearing and grubbing AC $38, $1,900,000 Clear all nuisance plants full width Cut and fill (single trail) CY $12 15,800 $189,600 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $13 22,000 $286,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $180 3,050 $549,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $180 4,240 $763,200 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $27 33,600 $907,200 6" bank run shell Base (dbl. trail) SY $28 48,200 $1,349,600 6" bank run shell Subbase (single trail) SY $14 15,800 $221,200 Build base as needed in poor soils Subbase (dbl. trail) SY $14 24,000 $336,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $24 5,000 $120,000 Chain link type as needed Ped/bike railing LF $84 1,500 $126,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $30, $1,080,000 Border trees and bushes as needed Sod, seeding SY $4 130,000 $455,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $75,000 1 $75,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $7, $240,000 drainage pipe and structures Pond/swale construction EA $36,000 6 $216,000 pond/swale construction SubTotal $9,403,300

38 Rails-with-Trails Option Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $75,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $750,000 Est. 1 contam. Location per mile Surface water remediation MI $100, $750,000 Est. 1 Location per mile Steel and tie/timber credit MI -$50, $25,000 Est. 1 contam. Location per mile SubTotal $1,775,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10,000 0 $0 all road intersections SubTotal $965,500 Shelters Approach paths EA $2,400 8 $19,200 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $7,200 8 $57,600 foundation cost Landscaping EA $6,000 8 $48,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work, benches, trash can, etc. EA $8,000 8 $64,000 general site prep. SubTotal $46,600 $372,800

39 Rails-with-Trails Option Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges (2) over Philippi Creek Main A LS $625,000 1 $625,000 Prefab. Steel Truss bridge with foundations Main B LS $390,000 1 $390,000 Prefab. Steel Truss bridge with foundations SubTotal $1,015,000 Utilities at Trail Heads and Shelters w/ Water Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,520,000 Mobilization 3.0% $450,000 MOT 3.0% $450,000 Geotech and misc. Testing 2.0% $300,000 Additional items 4.0% $610,000 Contingency 10.0% $1,520,000 Asbuilts, close-out 2.0% $300,000 SubTotal $5,150,000 Project Cost Estimate Total $20,301,600

40 Cost Unit Descriptions UNIT AC CY EA LF LS MI NM SF SY TN DESCRIPTION Acre Cubic Yard Each Linear Foot Lump Sum Mile Net Mile Square Foot Square Yard Ton

41 Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 25,800' + Separated Trail length ~ 13,700' = Total Length ~ 39,500' or 7.5 miles) Clear and grub AC $30, $1,500,000 Clear all nuisance plants full width Cut and fill (single trail) CY $10 20,000 $200,000 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $10 10,600 $106,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $150 4,400 $660,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $150 2,670 $400,500 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $22 33,600 $739,200 6" bank run shell Base (dbl. trail) SY $22 33,500 $737,000 6" bank run shell Subbase (single trail) SY $11 5,000 $55,000 Build base as needed in poor soils Subbase (dbl. trail) SY $11 10,000 $110,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $20 5,000 $100,000 Chain link type as needed Ped/bike railing LF $70 1,500 $105,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $25, $900,000 Border trees and bushes as needed Sod, seeding SY $3 130,000 $390,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $60,000 1 $60,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $6, $192,000 drainage pipe and structures Pond/swale construction EA $30,000 6 $180,000 pond/swale construction SubTotal $7,024,200

42 Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $1,125,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $375,000 Est. 0.5 contam. sites per mile Surface water remediation MI $100, $375,000 Est. 0.5 sites per mile Steel and tie/timber credit MI -$50, $375,000 Est. 0.5 contam. sites per mile SubTotal $1,725,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10, $130,000 all road intersections SubTotal $1,095,500 Shelters Approach paths EA $2,000 8 $16,000 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $6,000 8 $48,000 foundation cost Landscaping EA $5,000 8 $40,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work EA $8,000 8 $64,000 general site prep. SubTotal $44,000 $352,000

43 Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges Main A LS $525,000 1 $525,000 Prefab. Steel Truss bridge with foundations Main B LS $325,000 1 $325,000 Prefab. Steel Truss bridge with foundations SubTotal $850,000 Utilities Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,270,000 Mobilization 3.0% $380,000 MOT 2.0% $250,000 Geotech and misc. Testing 2.0% $250,000 Additional items 4.0% $510,000 Contingency 10.0% $1,270,000 Asbuilts, close-out 2.0% $250,000 SubTotal $4,180,000 Project Cost Estimate Total $16,846,700

44 ( This Page Blank.)

45 Rails-with-Trails Option Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 17,800' + Separated Trail length ~ 21,700' = Total Length ~ 39,500' or 7.5 miles) Clearing and grubbing AC $38, $1,900,000 Clear all nuisance plants full width Cut and fill (single trail) CY $12 15,800 $189,600 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $13 22,000 $286,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $180 3,050 $549,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $180 4,240 $763,200 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $27 33,600 $907,200 6" bank run shell Base (dbl. trail) SY $28 48,200 $1,349,600 6" bank run shell Subbase (single trail) SY $14 15,800 $221,200 Build base as needed in poor soils Subbase (dbl. trail) SY $14 24,000 $336,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $24 5,000 $120,000 Chain link type as needed Ped/bike railing LF $84 1,500 $126,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $30, $1,080,000 Border trees and bushes as needed Sod, seeding SY $4 130,000 $455,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $75,000 1 $75,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $7, $240,000 drainage pipe and structures Pond/swale construction EA $36,000 6 $216,000 pond/swale construction SubTotal $9,403,300

46 Rails-with-Trails Option Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $75,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $750,000 Est. 1 contam. Location per mile Surface water remediation MI $100, $750,000 Est. 1 Location per mile Steel and tie/timber credit MI -$50, $25,000 Est. 1 contam. Location per mile SubTotal $1,775,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10,000 0 $0 all road intersections SubTotal $965,500 Shelters Approach paths EA $2,400 8 $19,200 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $7,200 8 $57,600 foundation cost Landscaping EA $6,000 8 $48,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work, benches, trash can, etc. EA $8,000 8 $64,000 general site prep. SubTotal $46,600 $372,800

47 Rails-with-Trails Option Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges (2) over Philippi Creek Main A LS $625,000 1 $625,000 Prefab. Steel Truss bridge with foundations Main B LS $390,000 1 $390,000 Prefab. Steel Truss bridge with foundations SubTotal $1,015,000 Utilities at Trail Heads and Shelters w/ Water Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,520,000 Mobilization 3.0% $450,000 MOT 3.0% $450,000 Geotech and misc. Testing 2.0% $300,000 Additional items 4.0% $610,000 Contingency 10.0% $1,520,000 Asbuilts, close-out 2.0% $300,000 SubTotal $5,150,000 Project Cost Estimate Total $20,301,600

48 Cost Unit Descriptions UNIT AC CY EA LF LS MI NM SF SY TN DESCRIPTION Acre Cubic Yard Each Linear Foot Lump Sum Mile Net Mile Square Foot Square Yard Ton

49 Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 25,800' + Separated Trail length ~ 13,700' = Total Length ~ 39,500' or 7.5 miles) Clear and grub AC $30, $1,500,000 Clear all nuisance plants full width Cut and fill (single trail) CY $10 20,000 $200,000 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $10 10,600 $106,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $150 4,400 $660,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $150 2,670 $400,500 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $22 33,600 $739,200 6" bank run shell Base (dbl. trail) SY $22 33,500 $737,000 6" bank run shell Subbase (single trail) SY $11 5,000 $55,000 Build base as needed in poor soils Subbase (dbl. trail) SY $11 10,000 $110,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $20 5,000 $100,000 Chain link type as needed Ped/bike railing LF $70 1,500 $105,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $25, $900,000 Border trees and bushes as needed Sod, seeding SY $3 130,000 $390,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $60,000 1 $60,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $6, $192,000 drainage pipe and structures Pond/swale construction EA $30,000 6 $180,000 pond/swale construction SubTotal $7,024,200

50 Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $1,125,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $375,000 Est. 0.5 contam. sites per mile Surface water remediation MI $100, $375,000 Est. 0.5 sites per mile Steel and tie/timber credit MI -$50, $375,000 Est. 0.5 contam. sites per mile SubTotal $1,725,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10, $130,000 all road intersections SubTotal $1,095,500 Shelters Approach paths EA $2,000 8 $16,000 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $6,000 8 $48,000 foundation cost Landscaping EA $5,000 8 $40,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work EA $8,000 8 $64,000 general site prep. SubTotal $44,000 $352,000

51 Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges Main A LS $525,000 1 $525,000 Prefab. Steel Truss bridge with foundations Main B LS $325,000 1 $325,000 Prefab. Steel Truss bridge with foundations SubTotal $850,000 Utilities Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,270,000 Mobilization 3.0% $380,000 MOT 2.0% $250,000 Geotech and misc. Testing 2.0% $250,000 Additional items 4.0% $510,000 Contingency 10.0% $1,270,000 Asbuilts, close-out 2.0% $250,000 SubTotal $4,180,000 Project Cost Estimate Total $16,846,700

52 ( This Page Blank.)

53 Rails-with-Trails Option Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 17,800' + Separated Trail length ~ 21,700' = Total Length ~ 39,500' or 7.5 miles) Clearing and grubbing AC $38, $1,900,000 Clear all nuisance plants full width Cut and fill (single trail) CY $12 15,800 $189,600 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $13 22,000 $286,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $180 3,050 $549,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $180 4,240 $763,200 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $27 33,600 $907,200 6" bank run shell Base (dbl. trail) SY $28 48,200 $1,349,600 6" bank run shell Subbase (single trail) SY $14 15,800 $221,200 Build base as needed in poor soils Subbase (dbl. trail) SY $14 24,000 $336,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $24 5,000 $120,000 Chain link type as needed Ped/bike railing LF $84 1,500 $126,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $30, $1,080,000 Border trees and bushes as needed Sod, seeding SY $4 130,000 $455,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $75,000 1 $75,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $7, $240,000 drainage pipe and structures Pond/swale construction EA $36,000 6 $216,000 pond/swale construction SubTotal $9,403,300

54 Rails-with-Trails Option Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $75,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $750,000 Est. 1 contam. Location per mile Surface water remediation MI $100, $750,000 Est. 1 Location per mile Steel and tie/timber credit MI -$50, $25,000 Est. 1 contam. Location per mile SubTotal $1,775,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10,000 0 $0 all road intersections SubTotal $965,500 Shelters Approach paths EA $2,400 8 $19,200 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $7,200 8 $57,600 foundation cost Landscaping EA $6,000 8 $48,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work, benches, trash can, etc. EA $8,000 8 $64,000 general site prep. SubTotal $46,600 $372,800

55 Rails-with-Trails Option Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges (2) over Philippi Creek Main A LS $625,000 1 $625,000 Prefab. Steel Truss bridge with foundations Main B LS $390,000 1 $390,000 Prefab. Steel Truss bridge with foundations SubTotal $1,015,000 Utilities at Trail Heads and Shelters w/ Water Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,520,000 Mobilization 3.0% $450,000 MOT 3.0% $450,000 Geotech and misc. Testing 2.0% $300,000 Additional items 4.0% $610,000 Contingency 10.0% $1,520,000 Asbuilts, close-out 2.0% $300,000 SubTotal $5,150,000 Project Cost Estimate Total $20,301,600

56 Cost Unit Descriptions UNIT AC CY EA LF LS MI NM SF SY TN DESCRIPTION Acre Cubic Yard Each Linear Foot Lump Sum Mile Net Mile Square Foot Square Yard Ton

57 Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 25,800' + Separated Trail length ~ 13,700' = Total Length ~ 39,500' or 7.5 miles) Clear and grub AC $30, $1,500,000 Clear all nuisance plants full width Cut and fill (single trail) CY $10 20,000 $200,000 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $10 10,600 $106,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $150 4,400 $660,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $150 2,670 $400,500 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $22 33,600 $739,200 6" bank run shell Base (dbl. trail) SY $22 33,500 $737,000 6" bank run shell Subbase (single trail) SY $11 5,000 $55,000 Build base as needed in poor soils Subbase (dbl. trail) SY $11 10,000 $110,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $20 5,000 $100,000 Chain link type as needed Ped/bike railing LF $70 1,500 $105,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $25, $900,000 Border trees and bushes as needed Sod, seeding SY $3 130,000 $390,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $60,000 1 $60,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $6, $192,000 drainage pipe and structures Pond/swale construction EA $30,000 6 $180,000 pond/swale construction SubTotal $7,024,200

58 Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $1,125,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $375,000 Est. 0.5 contam. sites per mile Surface water remediation MI $100, $375,000 Est. 0.5 sites per mile Steel and tie/timber credit MI -$50, $375,000 Est. 0.5 contam. sites per mile SubTotal $1,725,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10, $130,000 all road intersections SubTotal $1,095,500 Shelters Approach paths EA $2,000 8 $16,000 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $6,000 8 $48,000 foundation cost Landscaping EA $5,000 8 $40,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work EA $8,000 8 $64,000 general site prep. SubTotal $44,000 $352,000

59 Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges Main A LS $525,000 1 $525,000 Prefab. Steel Truss bridge with foundations Main B LS $325,000 1 $325,000 Prefab. Steel Truss bridge with foundations SubTotal $850,000 Utilities Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,270,000 Mobilization 3.0% $380,000 MOT 2.0% $250,000 Geotech and misc. Testing 2.0% $250,000 Additional items 4.0% $510,000 Contingency 10.0% $1,270,000 Asbuilts, close-out 2.0% $250,000 SubTotal $4,180,000 Project Cost Estimate Total $16,846,700

60 ( This Page Blank.)

61 Rails-with-Trails Option Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 17,800' + Separated Trail length ~ 21,700' = Total Length ~ 39,500' or 7.5 miles) Clearing and grubbing AC $38, $1,900,000 Clear all nuisance plants full width Cut and fill (single trail) CY $12 15,800 $189,600 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $13 22,000 $286,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $180 3,050 $549,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $180 4,240 $763,200 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $27 33,600 $907,200 6" bank run shell Base (dbl. trail) SY $28 48,200 $1,349,600 6" bank run shell Subbase (single trail) SY $14 15,800 $221,200 Build base as needed in poor soils Subbase (dbl. trail) SY $14 24,000 $336,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $24 5,000 $120,000 Chain link type as needed Ped/bike railing LF $84 1,500 $126,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $30, $1,080,000 Border trees and bushes as needed Sod, seeding SY $4 130,000 $455,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $75,000 1 $75,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $7, $240,000 drainage pipe and structures Pond/swale construction EA $36,000 6 $216,000 pond/swale construction SubTotal $9,403,300

62 Rails-with-Trails Option Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $75,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $750,000 Est. 1 contam. Location per mile Surface water remediation MI $100, $750,000 Est. 1 Location per mile Steel and tie/timber credit MI -$50, $25,000 Est. 1 contam. Location per mile SubTotal $1,775,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10,000 0 $0 all road intersections SubTotal $965,500 Shelters Approach paths EA $2,400 8 $19,200 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $7,200 8 $57,600 foundation cost Landscaping EA $6,000 8 $48,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work, benches, trash can, etc. EA $8,000 8 $64,000 general site prep. SubTotal $46,600 $372,800

63 Rails-with-Trails Option Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges (2) over Philippi Creek Main A LS $625,000 1 $625,000 Prefab. Steel Truss bridge with foundations Main B LS $390,000 1 $390,000 Prefab. Steel Truss bridge with foundations SubTotal $1,015,000 Utilities at Trail Heads and Shelters w/ Water Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,520,000 Mobilization 3.0% $450,000 MOT 3.0% $450,000 Geotech and misc. Testing 2.0% $300,000 Additional items 4.0% $610,000 Contingency 10.0% $1,520,000 Asbuilts, close-out 2.0% $300,000 SubTotal $5,150,000 Project Cost Estimate Total $20,301,600

64 Cost Unit Descriptions UNIT AC CY EA LF LS MI NM SF SY TN DESCRIPTION Acre Cubic Yard Each Linear Foot Lump Sum Mile Net Mile Square Foot Square Yard Ton

65 Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 25,800' + Separated Trail length ~ 13,700' = Total Length ~ 39,500' or 7.5 miles) Clear and grub AC $30, $1,500,000 Clear all nuisance plants full width Cut and fill (single trail) CY $10 20,000 $200,000 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $10 10,600 $106,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $150 4,400 $660,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $150 2,670 $400,500 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $22 33,600 $739,200 6" bank run shell Base (dbl. trail) SY $22 33,500 $737,000 6" bank run shell Subbase (single trail) SY $11 5,000 $55,000 Build base as needed in poor soils Subbase (dbl. trail) SY $11 10,000 $110,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $20 5,000 $100,000 Chain link type as needed Ped/bike railing LF $70 1,500 $105,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $25, $900,000 Border trees and bushes as needed Sod, seeding SY $3 130,000 $390,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $60,000 1 $60,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $6, $192,000 drainage pipe and structures Pond/swale construction EA $30,000 6 $180,000 pond/swale construction SubTotal $7,024,200

66 Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $1,125,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $375,000 Est. 0.5 contam. sites per mile Surface water remediation MI $100, $375,000 Est. 0.5 sites per mile Steel and tie/timber credit MI -$50, $375,000 Est. 0.5 contam. sites per mile SubTotal $1,725,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10, $130,000 all road intersections SubTotal $1,095,500 Shelters Approach paths EA $2,000 8 $16,000 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $6,000 8 $48,000 foundation cost Landscaping EA $5,000 8 $40,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work EA $8,000 8 $64,000 general site prep. SubTotal $44,000 $352,000

67 Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges Main A LS $525,000 1 $525,000 Prefab. Steel Truss bridge with foundations Main B LS $325,000 1 $325,000 Prefab. Steel Truss bridge with foundations SubTotal $850,000 Utilities Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,270,000 Mobilization 3.0% $380,000 MOT 2.0% $250,000 Geotech and misc. Testing 2.0% $250,000 Additional items 4.0% $510,000 Contingency 10.0% $1,270,000 Asbuilts, close-out 2.0% $250,000 SubTotal $4,180,000 Project Cost Estimate Total $16,846,700

68 ( This Page Blank.)

69 Rails-with-Trails Option Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 17,800' + Separated Trail length ~ 21,700' = Total Length ~ 39,500' or 7.5 miles) Clearing and grubbing AC $38, $1,900,000 Clear all nuisance plants full width Cut and fill (single trail) CY $12 15,800 $189,600 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $13 22,000 $286,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $180 3,050 $549,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $180 4,240 $763,200 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $27 33,600 $907,200 6" bank run shell Base (dbl. trail) SY $28 48,200 $1,349,600 6" bank run shell Subbase (single trail) SY $14 15,800 $221,200 Build base as needed in poor soils Subbase (dbl. trail) SY $14 24,000 $336,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $24 5,000 $120,000 Chain link type as needed Ped/bike railing LF $84 1,500 $126,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $30, $1,080,000 Border trees and bushes as needed Sod, seeding SY $4 130,000 $455,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $75,000 1 $75,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $7, $240,000 drainage pipe and structures Pond/swale construction EA $36,000 6 $216,000 pond/swale construction SubTotal $9,403,300

70 Rails-with-Trails Option Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $75,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $750,000 Est. 1 contam. Location per mile Surface water remediation MI $100, $750,000 Est. 1 Location per mile Steel and tie/timber credit MI -$50, $25,000 Est. 1 contam. Location per mile SubTotal $1,775,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10,000 0 $0 all road intersections SubTotal $965,500 Shelters Approach paths EA $2,400 8 $19,200 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $7,200 8 $57,600 foundation cost Landscaping EA $6,000 8 $48,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work, benches, trash can, etc. EA $8,000 8 $64,000 general site prep. SubTotal $46,600 $372,800

71 Rails-with-Trails Option Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges (2) over Philippi Creek Main A LS $625,000 1 $625,000 Prefab. Steel Truss bridge with foundations Main B LS $390,000 1 $390,000 Prefab. Steel Truss bridge with foundations SubTotal $1,015,000 Utilities at Trail Heads and Shelters w/ Water Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,520,000 Mobilization 3.0% $450,000 MOT 3.0% $450,000 Geotech and misc. Testing 2.0% $300,000 Additional items 4.0% $610,000 Contingency 10.0% $1,520,000 Asbuilts, close-out 2.0% $300,000 SubTotal $5,150,000 Project Cost Estimate Total $20,301,600

72 Cost Unit Descriptions UNIT AC CY EA LF LS MI NM SF SY TN DESCRIPTION Acre Cubic Yard Each Linear Foot Lump Sum Mile Net Mile Square Foot Square Yard Ton

73 Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 25,800' + Separated Trail length ~ 13,700' = Total Length ~ 39,500' or 7.5 miles) Clear and grub AC $30, $1,500,000 Clear all nuisance plants full width Cut and fill (single trail) CY $10 20,000 $200,000 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $10 10,600 $106,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $150 4,400 $660,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $150 2,670 $400,500 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $22 33,600 $739,200 6" bank run shell Base (dbl. trail) SY $22 33,500 $737,000 6" bank run shell Subbase (single trail) SY $11 5,000 $55,000 Build base as needed in poor soils Subbase (dbl. trail) SY $11 10,000 $110,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $20 5,000 $100,000 Chain link type as needed Ped/bike railing LF $70 1,500 $105,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $25, $900,000 Border trees and bushes as needed Sod, seeding SY $3 130,000 $390,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $60,000 1 $60,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $6, $192,000 drainage pipe and structures Pond/swale construction EA $30,000 6 $180,000 pond/swale construction SubTotal $7,024,200

74 Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $1,125,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $375,000 Est. 0.5 contam. sites per mile Surface water remediation MI $100, $375,000 Est. 0.5 sites per mile Steel and tie/timber credit MI -$50, $375,000 Est. 0.5 contam. sites per mile SubTotal $1,725,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10, $130,000 all road intersections SubTotal $1,095,500 Shelters Approach paths EA $2,000 8 $16,000 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $6,000 8 $48,000 foundation cost Landscaping EA $5,000 8 $40,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work EA $8,000 8 $64,000 general site prep. SubTotal $44,000 $352,000

75 Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges Main A LS $525,000 1 $525,000 Prefab. Steel Truss bridge with foundations Main B LS $325,000 1 $325,000 Prefab. Steel Truss bridge with foundations SubTotal $850,000 Utilities Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,270,000 Mobilization 3.0% $380,000 MOT 2.0% $250,000 Geotech and misc. Testing 2.0% $250,000 Additional items 4.0% $510,000 Contingency 10.0% $1,270,000 Asbuilts, close-out 2.0% $250,000 SubTotal $4,180,000 Project Cost Estimate Total $16,846,700

76 ( This Page Blank.)

77 Rails-with-Trails Option Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 17,800' + Separated Trail length ~ 21,700' = Total Length ~ 39,500' or 7.5 miles) Clearing and grubbing AC $38, $1,900,000 Clear all nuisance plants full width Cut and fill (single trail) CY $12 15,800 $189,600 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $13 22,000 $286,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $180 3,050 $549,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $180 4,240 $763,200 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $27 33,600 $907,200 6" bank run shell Base (dbl. trail) SY $28 48,200 $1,349,600 6" bank run shell Subbase (single trail) SY $14 15,800 $221,200 Build base as needed in poor soils Subbase (dbl. trail) SY $14 24,000 $336,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $24 5,000 $120,000 Chain link type as needed Ped/bike railing LF $84 1,500 $126,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $30, $1,080,000 Border trees and bushes as needed Sod, seeding SY $4 130,000 $455,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $75,000 1 $75,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $7, $240,000 drainage pipe and structures Pond/swale construction EA $36,000 6 $216,000 pond/swale construction SubTotal $9,403,300

78 Rails-with-Trails Option Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $75,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $750,000 Est. 1 contam. Location per mile Surface water remediation MI $100, $750,000 Est. 1 Location per mile Steel and tie/timber credit MI -$50, $25,000 Est. 1 contam. Location per mile SubTotal $1,775,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10,000 0 $0 all road intersections SubTotal $965,500 Shelters Approach paths EA $2,400 8 $19,200 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $7,200 8 $57,600 foundation cost Landscaping EA $6,000 8 $48,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work, benches, trash can, etc. EA $8,000 8 $64,000 general site prep. SubTotal $46,600 $372,800

79 Rails-with-Trails Option Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges (2) over Philippi Creek Main A LS $625,000 1 $625,000 Prefab. Steel Truss bridge with foundations Main B LS $390,000 1 $390,000 Prefab. Steel Truss bridge with foundations SubTotal $1,015,000 Utilities at Trail Heads and Shelters w/ Water Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,520,000 Mobilization 3.0% $450,000 MOT 3.0% $450,000 Geotech and misc. Testing 2.0% $300,000 Additional items 4.0% $610,000 Contingency 10.0% $1,520,000 Asbuilts, close-out 2.0% $300,000 SubTotal $5,150,000 Project Cost Estimate Total $20,301,600

80 Cost Unit Descriptions UNIT AC CY EA LF LS MI NM SF SY TN DESCRIPTION Acre Cubic Yard Each Linear Foot Lump Sum Mile Net Mile Square Foot Square Yard Ton

81 Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 25,800' + Separated Trail length ~ 13,700' = Total Length ~ 39,500' or 7.5 miles) Clear and grub AC $30, $1,500,000 Clear all nuisance plants full width Cut and fill (single trail) CY $10 20,000 $200,000 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $10 10,600 $106,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $150 4,400 $660,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $150 2,670 $400,500 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $22 33,600 $739,200 6" bank run shell Base (dbl. trail) SY $22 33,500 $737,000 6" bank run shell Subbase (single trail) SY $11 5,000 $55,000 Build base as needed in poor soils Subbase (dbl. trail) SY $11 10,000 $110,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $20 5,000 $100,000 Chain link type as needed Ped/bike railing LF $70 1,500 $105,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $25, $900,000 Border trees and bushes as needed Sod, seeding SY $3 130,000 $390,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $60,000 1 $60,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $6, $192,000 drainage pipe and structures Pond/swale construction EA $30,000 6 $180,000 pond/swale construction SubTotal $7,024,200

82 Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $1,125,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $375,000 Est. 0.5 contam. sites per mile Surface water remediation MI $100, $375,000 Est. 0.5 sites per mile Steel and tie/timber credit MI -$50, $375,000 Est. 0.5 contam. sites per mile SubTotal $1,725,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10, $130,000 all road intersections SubTotal $1,095,500 Shelters Approach paths EA $2,000 8 $16,000 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $6,000 8 $48,000 foundation cost Landscaping EA $5,000 8 $40,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work EA $8,000 8 $64,000 general site prep. SubTotal $44,000 $352,000

83 Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges Main A LS $525,000 1 $525,000 Prefab. Steel Truss bridge with foundations Main B LS $325,000 1 $325,000 Prefab. Steel Truss bridge with foundations SubTotal $850,000 Utilities Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,270,000 Mobilization 3.0% $380,000 MOT 2.0% $250,000 Geotech and misc. Testing 2.0% $250,000 Additional items 4.0% $510,000 Contingency 10.0% $1,270,000 Asbuilts, close-out 2.0% $250,000 SubTotal $4,180,000 Project Cost Estimate Total $16,846,700

84 ( This Page Blank.)

85 Rails-with-Trails Option Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 17,800' + Separated Trail length ~ 21,700' = Total Length ~ 39,500' or 7.5 miles) Clearing and grubbing AC $38, $1,900,000 Clear all nuisance plants full width Cut and fill (single trail) CY $12 15,800 $189,600 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $13 22,000 $286,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $180 3,050 $549,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $180 4,240 $763,200 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $27 33,600 $907,200 6" bank run shell Base (dbl. trail) SY $28 48,200 $1,349,600 6" bank run shell Subbase (single trail) SY $14 15,800 $221,200 Build base as needed in poor soils Subbase (dbl. trail) SY $14 24,000 $336,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $24 5,000 $120,000 Chain link type as needed Ped/bike railing LF $84 1,500 $126,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $30, $1,080,000 Border trees and bushes as needed Sod, seeding SY $4 130,000 $455,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $75,000 1 $75,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $7, $240,000 drainage pipe and structures Pond/swale construction EA $36,000 6 $216,000 pond/swale construction SubTotal $9,403,300

86 Rails-with-Trails Option Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $75,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $750,000 Est. 1 contam. Location per mile Surface water remediation MI $100, $750,000 Est. 1 Location per mile Steel and tie/timber credit MI -$50, $25,000 Est. 1 contam. Location per mile SubTotal $1,775,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10,000 0 $0 all road intersections SubTotal $965,500 Shelters Approach paths EA $2,400 8 $19,200 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $7,200 8 $57,600 foundation cost Landscaping EA $6,000 8 $48,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work, benches, trash can, etc. EA $8,000 8 $64,000 general site prep. SubTotal $46,600 $372,800

87 Rails-with-Trails Option Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges (2) over Philippi Creek Main A LS $625,000 1 $625,000 Prefab. Steel Truss bridge with foundations Main B LS $390,000 1 $390,000 Prefab. Steel Truss bridge with foundations SubTotal $1,015,000 Utilities at Trail Heads and Shelters w/ Water Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,520,000 Mobilization 3.0% $450,000 MOT 3.0% $450,000 Geotech and misc. Testing 2.0% $300,000 Additional items 4.0% $610,000 Contingency 10.0% $1,520,000 Asbuilts, close-out 2.0% $300,000 SubTotal $5,150,000 Project Cost Estimate Total $20,301,600

88 Cost Unit Descriptions UNIT AC CY EA LF LS MI NM SF SY TN DESCRIPTION Acre Cubic Yard Each Linear Foot Lump Sum Mile Net Mile Square Foot Square Yard Ton

89 Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 25,800' + Separated Trail length ~ 13,700' = Total Length ~ 39,500' or 7.5 miles) Clear and grub AC $30, $1,500,000 Clear all nuisance plants full width Cut and fill (single trail) CY $10 20,000 $200,000 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $10 10,600 $106,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $150 4,400 $660,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $150 2,670 $400,500 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $22 33,600 $739,200 6" bank run shell Base (dbl. trail) SY $22 33,500 $737,000 6" bank run shell Subbase (single trail) SY $11 5,000 $55,000 Build base as needed in poor soils Subbase (dbl. trail) SY $11 10,000 $110,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $20 5,000 $100,000 Chain link type as needed Ped/bike railing LF $70 1,500 $105,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $25, $900,000 Border trees and bushes as needed Sod, seeding SY $3 130,000 $390,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $60,000 1 $60,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $6, $192,000 drainage pipe and structures Pond/swale construction EA $30,000 6 $180,000 pond/swale construction SubTotal $7,024,200

90 Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $1,125,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $375,000 Est. 0.5 contam. sites per mile Surface water remediation MI $100, $375,000 Est. 0.5 sites per mile Steel and tie/timber credit MI -$50, $375,000 Est. 0.5 contam. sites per mile SubTotal $1,725,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10, $130,000 all road intersections SubTotal $1,095,500 Shelters Approach paths EA $2,000 8 $16,000 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $6,000 8 $48,000 foundation cost Landscaping EA $5,000 8 $40,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work EA $8,000 8 $64,000 general site prep. SubTotal $44,000 $352,000

91 Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges Main A LS $525,000 1 $525,000 Prefab. Steel Truss bridge with foundations Main B LS $325,000 1 $325,000 Prefab. Steel Truss bridge with foundations SubTotal $850,000 Utilities Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,270,000 Mobilization 3.0% $380,000 MOT 2.0% $250,000 Geotech and misc. Testing 2.0% $250,000 Additional items 4.0% $510,000 Contingency 10.0% $1,270,000 Asbuilts, close-out 2.0% $250,000 SubTotal $4,180,000 Project Cost Estimate Total $16,846,700

92 ( This Page Blank.)

93 Rails-with-Trails Option Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 17,800' + Separated Trail length ~ 21,700' = Total Length ~ 39,500' or 7.5 miles) Clearing and grubbing AC $38, $1,900,000 Clear all nuisance plants full width Cut and fill (single trail) CY $12 15,800 $189,600 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $13 22,000 $286,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $180 3,050 $549,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $180 4,240 $763,200 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $27 33,600 $907,200 6" bank run shell Base (dbl. trail) SY $28 48,200 $1,349,600 6" bank run shell Subbase (single trail) SY $14 15,800 $221,200 Build base as needed in poor soils Subbase (dbl. trail) SY $14 24,000 $336,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $24 5,000 $120,000 Chain link type as needed Ped/bike railing LF $84 1,500 $126,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $30, $1,080,000 Border trees and bushes as needed Sod, seeding SY $4 130,000 $455,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $75,000 1 $75,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $7, $240,000 drainage pipe and structures Pond/swale construction EA $36,000 6 $216,000 pond/swale construction SubTotal $9,403,300

94 Rails-with-Trails Option Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $75,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $750,000 Est. 1 contam. Location per mile Surface water remediation MI $100, $750,000 Est. 1 Location per mile Steel and tie/timber credit MI -$50, $25,000 Est. 1 contam. Location per mile SubTotal $1,775,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10,000 0 $0 all road intersections SubTotal $965,500 Shelters Approach paths EA $2,400 8 $19,200 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $7,200 8 $57,600 foundation cost Landscaping EA $6,000 8 $48,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work, benches, trash can, etc. EA $8,000 8 $64,000 general site prep. SubTotal $46,600 $372,800

95 Rails-with-Trails Option Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges (2) over Philippi Creek Main A LS $625,000 1 $625,000 Prefab. Steel Truss bridge with foundations Main B LS $390,000 1 $390,000 Prefab. Steel Truss bridge with foundations SubTotal $1,015,000 Utilities at Trail Heads and Shelters w/ Water Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,520,000 Mobilization 3.0% $450,000 MOT 3.0% $450,000 Geotech and misc. Testing 2.0% $300,000 Additional items 4.0% $610,000 Contingency 10.0% $1,520,000 Asbuilts, close-out 2.0% $300,000 SubTotal $5,150,000 Project Cost Estimate Total $20,301,600

96 Cost Unit Descriptions UNIT AC CY EA LF LS MI NM SF SY TN DESCRIPTION Acre Cubic Yard Each Linear Foot Lump Sum Mile Net Mile Square Foot Square Yard Ton

97 Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 25,800' + Separated Trail length ~ 13,700' = Total Length ~ 39,500' or 7.5 miles) Clear and grub AC $30, $1,500,000 Clear all nuisance plants full width Cut and fill (single trail) CY $10 20,000 $200,000 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $10 10,600 $106,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $150 4,400 $660,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $150 2,670 $400,500 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $22 33,600 $739,200 6" bank run shell Base (dbl. trail) SY $22 33,500 $737,000 6" bank run shell Subbase (single trail) SY $11 5,000 $55,000 Build base as needed in poor soils Subbase (dbl. trail) SY $11 10,000 $110,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $20 5,000 $100,000 Chain link type as needed Ped/bike railing LF $70 1,500 $105,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $25, $900,000 Border trees and bushes as needed Sod, seeding SY $3 130,000 $390,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $60,000 1 $60,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $6, $192,000 drainage pipe and structures Pond/swale construction EA $30,000 6 $180,000 pond/swale construction SubTotal $7,024,200

98 Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $1,125,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $375,000 Est. 0.5 contam. sites per mile Surface water remediation MI $100, $375,000 Est. 0.5 sites per mile Steel and tie/timber credit MI -$50, $375,000 Est. 0.5 contam. sites per mile SubTotal $1,725,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10, $130,000 all road intersections SubTotal $1,095,500 Shelters Approach paths EA $2,000 8 $16,000 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $6,000 8 $48,000 foundation cost Landscaping EA $5,000 8 $40,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work EA $8,000 8 $64,000 general site prep. SubTotal $44,000 $352,000

99 Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges Main A LS $525,000 1 $525,000 Prefab. Steel Truss bridge with foundations Main B LS $325,000 1 $325,000 Prefab. Steel Truss bridge with foundations SubTotal $850,000 Utilities Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,270,000 Mobilization 3.0% $380,000 MOT 2.0% $250,000 Geotech and misc. Testing 2.0% $250,000 Additional items 4.0% $510,000 Contingency 10.0% $1,270,000 Asbuilts, close-out 2.0% $250,000 SubTotal $4,180,000 Project Cost Estimate Total $16,846,700

100 ( This Page Blank.)

101 Rails-with-Trails Option Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 17,800' + Separated Trail length ~ 21,700' = Total Length ~ 39,500' or 7.5 miles) Clearing and grubbing AC $38, $1,900,000 Clear all nuisance plants full width Cut and fill (single trail) CY $12 15,800 $189,600 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $13 22,000 $286,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $180 3,050 $549,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $180 4,240 $763,200 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $27 33,600 $907,200 6" bank run shell Base (dbl. trail) SY $28 48,200 $1,349,600 6" bank run shell Subbase (single trail) SY $14 15,800 $221,200 Build base as needed in poor soils Subbase (dbl. trail) SY $14 24,000 $336,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $24 5,000 $120,000 Chain link type as needed Ped/bike railing LF $84 1,500 $126,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $30, $1,080,000 Border trees and bushes as needed Sod, seeding SY $4 130,000 $455,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $75,000 1 $75,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $7, $240,000 drainage pipe and structures Pond/swale construction EA $36,000 6 $216,000 pond/swale construction SubTotal $9,403,300

102 Rails-with-Trails Option Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $75,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $750,000 Est. 1 contam. Location per mile Surface water remediation MI $100, $750,000 Est. 1 Location per mile Steel and tie/timber credit MI -$50, $25,000 Est. 1 contam. Location per mile SubTotal $1,775,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10,000 0 $0 all road intersections SubTotal $965,500 Shelters Approach paths EA $2,400 8 $19,200 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $7,200 8 $57,600 foundation cost Landscaping EA $6,000 8 $48,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work, benches, trash can, etc. EA $8,000 8 $64,000 general site prep. SubTotal $46,600 $372,800

103 Rails-with-Trails Option Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges (2) over Philippi Creek Main A LS $625,000 1 $625,000 Prefab. Steel Truss bridge with foundations Main B LS $390,000 1 $390,000 Prefab. Steel Truss bridge with foundations SubTotal $1,015,000 Utilities at Trail Heads and Shelters w/ Water Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,520,000 Mobilization 3.0% $450,000 MOT 3.0% $450,000 Geotech and misc. Testing 2.0% $300,000 Additional items 4.0% $610,000 Contingency 10.0% $1,520,000 Asbuilts, close-out 2.0% $300,000 SubTotal $5,150,000 Project Cost Estimate Total $20,301,600

104 Cost Unit Descriptions UNIT AC CY EA LF LS MI NM SF SY TN DESCRIPTION Acre Cubic Yard Each Linear Foot Lump Sum Mile Net Mile Square Foot Square Yard Ton

105 Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 25,800' + Separated Trail length ~ 13,700' = Total Length ~ 39,500' or 7.5 miles) Clear and grub AC $30, $1,500,000 Clear all nuisance plants full width Cut and fill (single trail) CY $10 20,000 $200,000 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $10 10,600 $106,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $150 4,400 $660,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $150 2,670 $400,500 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $22 33,600 $739,200 6" bank run shell Base (dbl. trail) SY $22 33,500 $737,000 6" bank run shell Subbase (single trail) SY $11 5,000 $55,000 Build base as needed in poor soils Subbase (dbl. trail) SY $11 10,000 $110,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $20 5,000 $100,000 Chain link type as needed Ped/bike railing LF $70 1,500 $105,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $25, $900,000 Border trees and bushes as needed Sod, seeding SY $3 130,000 $390,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $60,000 1 $60,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $6, $192,000 drainage pipe and structures Pond/swale construction EA $30,000 6 $180,000 pond/swale construction SubTotal $7,024,200

106 Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $1,125,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $375,000 Est. 0.5 contam. sites per mile Surface water remediation MI $100, $375,000 Est. 0.5 sites per mile Steel and tie/timber credit MI -$50, $375,000 Est. 0.5 contam. sites per mile SubTotal $1,725,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10, $130,000 all road intersections SubTotal $1,095,500 Shelters Approach paths EA $2,000 8 $16,000 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $6,000 8 $48,000 foundation cost Landscaping EA $5,000 8 $40,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work EA $8,000 8 $64,000 general site prep. SubTotal $44,000 $352,000

107 Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges Main A LS $525,000 1 $525,000 Prefab. Steel Truss bridge with foundations Main B LS $325,000 1 $325,000 Prefab. Steel Truss bridge with foundations SubTotal $850,000 Utilities Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,270,000 Mobilization 3.0% $380,000 MOT 2.0% $250,000 Geotech and misc. Testing 2.0% $250,000 Additional items 4.0% $510,000 Contingency 10.0% $1,270,000 Asbuilts, close-out 2.0% $250,000 SubTotal $4,180,000 Project Cost Estimate Total $16,846,700

108 ( This Page Blank.)

109 Rails-with-Trails Option Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 17,800' + Separated Trail length ~ 21,700' = Total Length ~ 39,500' or 7.5 miles) Clearing and grubbing AC $38, $1,900,000 Clear all nuisance plants full width Cut and fill (single trail) CY $12 15,800 $189,600 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $13 22,000 $286,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $180 3,050 $549,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $180 4,240 $763,200 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $27 33,600 $907,200 6" bank run shell Base (dbl. trail) SY $28 48,200 $1,349,600 6" bank run shell Subbase (single trail) SY $14 15,800 $221,200 Build base as needed in poor soils Subbase (dbl. trail) SY $14 24,000 $336,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $24 5,000 $120,000 Chain link type as needed Ped/bike railing LF $84 1,500 $126,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $30, $1,080,000 Border trees and bushes as needed Sod, seeding SY $4 130,000 $455,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $75,000 1 $75,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $7, $240,000 drainage pipe and structures Pond/swale construction EA $36,000 6 $216,000 pond/swale construction SubTotal $9,403,300

110 Rails-with-Trails Option Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $75,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $750,000 Est. 1 contam. Location per mile Surface water remediation MI $100, $750,000 Est. 1 Location per mile Steel and tie/timber credit MI -$50, $25,000 Est. 1 contam. Location per mile SubTotal $1,775,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10,000 0 $0 all road intersections SubTotal $965,500 Shelters Approach paths EA $2,400 8 $19,200 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $7,200 8 $57,600 foundation cost Landscaping EA $6,000 8 $48,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work, benches, trash can, etc. EA $8,000 8 $64,000 general site prep. SubTotal $46,600 $372,800

111 Rails-with-Trails Option Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges (2) over Philippi Creek Main A LS $625,000 1 $625,000 Prefab. Steel Truss bridge with foundations Main B LS $390,000 1 $390,000 Prefab. Steel Truss bridge with foundations SubTotal $1,015,000 Utilities at Trail Heads and Shelters w/ Water Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,520,000 Mobilization 3.0% $450,000 MOT 3.0% $450,000 Geotech and misc. Testing 2.0% $300,000 Additional items 4.0% $610,000 Contingency 10.0% $1,520,000 Asbuilts, close-out 2.0% $300,000 SubTotal $5,150,000 Project Cost Estimate Total $20,301,600

112 Cost Unit Descriptions UNIT AC CY EA LF LS MI NM SF SY TN DESCRIPTION Acre Cubic Yard Each Linear Foot Lump Sum Mile Net Mile Square Foot Square Yard Ton

113 Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 25,800' + Separated Trail length ~ 13,700' = Total Length ~ 39,500' or 7.5 miles) Clear and grub AC $30, $1,500,000 Clear all nuisance plants full width Cut and fill (single trail) CY $10 20,000 $200,000 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $10 10,600 $106,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $150 4,400 $660,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $150 2,670 $400,500 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $22 33,600 $739,200 6" bank run shell Base (dbl. trail) SY $22 33,500 $737,000 6" bank run shell Subbase (single trail) SY $11 5,000 $55,000 Build base as needed in poor soils Subbase (dbl. trail) SY $11 10,000 $110,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $20 5,000 $100,000 Chain link type as needed Ped/bike railing LF $70 1,500 $105,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $25, $900,000 Border trees and bushes as needed Sod, seeding SY $3 130,000 $390,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $60,000 1 $60,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $6, $192,000 drainage pipe and structures Pond/swale construction EA $30,000 6 $180,000 pond/swale construction SubTotal $7,024,200

114 Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $1,125,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $375,000 Est. 0.5 contam. sites per mile Surface water remediation MI $100, $375,000 Est. 0.5 sites per mile Steel and tie/timber credit MI -$50, $375,000 Est. 0.5 contam. sites per mile SubTotal $1,725,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10, $130,000 all road intersections SubTotal $1,095,500 Shelters Approach paths EA $2,000 8 $16,000 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $6,000 8 $48,000 foundation cost Landscaping EA $5,000 8 $40,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work EA $8,000 8 $64,000 general site prep. SubTotal $44,000 $352,000

115 Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges Main A LS $525,000 1 $525,000 Prefab. Steel Truss bridge with foundations Main B LS $325,000 1 $325,000 Prefab. Steel Truss bridge with foundations SubTotal $850,000 Utilities Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,270,000 Mobilization 3.0% $380,000 MOT 2.0% $250,000 Geotech and misc. Testing 2.0% $250,000 Additional items 4.0% $510,000 Contingency 10.0% $1,270,000 Asbuilts, close-out 2.0% $250,000 SubTotal $4,180,000 Project Cost Estimate Total $16,846,700

116 ( This Page Blank.)

117 Rails-with-Trails Option Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 17,800' + Separated Trail length ~ 21,700' = Total Length ~ 39,500' or 7.5 miles) Clearing and grubbing AC $38, $1,900,000 Clear all nuisance plants full width Cut and fill (single trail) CY $12 15,800 $189,600 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $13 22,000 $286,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $180 3,050 $549,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $180 4,240 $763,200 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $27 33,600 $907,200 6" bank run shell Base (dbl. trail) SY $28 48,200 $1,349,600 6" bank run shell Subbase (single trail) SY $14 15,800 $221,200 Build base as needed in poor soils Subbase (dbl. trail) SY $14 24,000 $336,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $24 5,000 $120,000 Chain link type as needed Ped/bike railing LF $84 1,500 $126,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $30, $1,080,000 Border trees and bushes as needed Sod, seeding SY $4 130,000 $455,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $75,000 1 $75,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $7, $240,000 drainage pipe and structures Pond/swale construction EA $36,000 6 $216,000 pond/swale construction SubTotal $9,403,300

118 Rails-with-Trails Option Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $75,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $750,000 Est. 1 contam. Location per mile Surface water remediation MI $100, $750,000 Est. 1 Location per mile Steel and tie/timber credit MI -$50, $25,000 Est. 1 contam. Location per mile SubTotal $1,775,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10,000 0 $0 all road intersections SubTotal $965,500 Shelters Approach paths EA $2,400 8 $19,200 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $7,200 8 $57,600 foundation cost Landscaping EA $6,000 8 $48,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work, benches, trash can, etc. EA $8,000 8 $64,000 general site prep. SubTotal $46,600 $372,800

119 Rails-with-Trails Option Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges (2) over Philippi Creek Main A LS $625,000 1 $625,000 Prefab. Steel Truss bridge with foundations Main B LS $390,000 1 $390,000 Prefab. Steel Truss bridge with foundations SubTotal $1,015,000 Utilities at Trail Heads and Shelters w/ Water Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,520,000 Mobilization 3.0% $450,000 MOT 3.0% $450,000 Geotech and misc. Testing 2.0% $300,000 Additional items 4.0% $610,000 Contingency 10.0% $1,520,000 Asbuilts, close-out 2.0% $300,000 SubTotal $5,150,000 Project Cost Estimate Total $20,301,600

120 Cost Unit Descriptions UNIT AC CY EA LF LS MI NM SF SY TN DESCRIPTION Acre Cubic Yard Each Linear Foot Lump Sum Mile Net Mile Square Foot Square Yard Ton

121 Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 25,800' + Separated Trail length ~ 13,700' = Total Length ~ 39,500' or 7.5 miles) Clear and grub AC $30, $1,500,000 Clear all nuisance plants full width Cut and fill (single trail) CY $10 20,000 $200,000 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $10 10,600 $106,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $150 4,400 $660,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $150 2,670 $400,500 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $22 33,600 $739,200 6" bank run shell Base (dbl. trail) SY $22 33,500 $737,000 6" bank run shell Subbase (single trail) SY $11 5,000 $55,000 Build base as needed in poor soils Subbase (dbl. trail) SY $11 10,000 $110,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $20 5,000 $100,000 Chain link type as needed Ped/bike railing LF $70 1,500 $105,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $25, $900,000 Border trees and bushes as needed Sod, seeding SY $3 130,000 $390,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $60,000 1 $60,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $6, $192,000 drainage pipe and structures Pond/swale construction EA $30,000 6 $180,000 pond/swale construction SubTotal $7,024,200

122 Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $1,125,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $375,000 Est. 0.5 contam. sites per mile Surface water remediation MI $100, $375,000 Est. 0.5 sites per mile Steel and tie/timber credit MI -$50, $375,000 Est. 0.5 contam. sites per mile SubTotal $1,725,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10, $130,000 all road intersections SubTotal $1,095,500 Shelters Approach paths EA $2,000 8 $16,000 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $6,000 8 $48,000 foundation cost Landscaping EA $5,000 8 $40,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work EA $8,000 8 $64,000 general site prep. SubTotal $44,000 $352,000

123 Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges Main A LS $525,000 1 $525,000 Prefab. Steel Truss bridge with foundations Main B LS $325,000 1 $325,000 Prefab. Steel Truss bridge with foundations SubTotal $850,000 Utilities Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,270,000 Mobilization 3.0% $380,000 MOT 2.0% $250,000 Geotech and misc. Testing 2.0% $250,000 Additional items 4.0% $510,000 Contingency 10.0% $1,270,000 Asbuilts, close-out 2.0% $250,000 SubTotal $4,180,000 Project Cost Estimate Total $16,846,700

124 ( This Page Blank.)

125 Rails-with-Trails Option Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 17,800' + Separated Trail length ~ 21,700' = Total Length ~ 39,500' or 7.5 miles) Clearing and grubbing AC $38, $1,900,000 Clear all nuisance plants full width Cut and fill (single trail) CY $12 15,800 $189,600 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $13 22,000 $286,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $180 3,050 $549,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $180 4,240 $763,200 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $27 33,600 $907,200 6" bank run shell Base (dbl. trail) SY $28 48,200 $1,349,600 6" bank run shell Subbase (single trail) SY $14 15,800 $221,200 Build base as needed in poor soils Subbase (dbl. trail) SY $14 24,000 $336,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $24 5,000 $120,000 Chain link type as needed Ped/bike railing LF $84 1,500 $126,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $30, $1,080,000 Border trees and bushes as needed Sod, seeding SY $4 130,000 $455,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $75,000 1 $75,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $7, $240,000 drainage pipe and structures Pond/swale construction EA $36,000 6 $216,000 pond/swale construction SubTotal $9,403,300

126 Rails-with-Trails Option Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $75,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $750,000 Est. 1 contam. Location per mile Surface water remediation MI $100, $750,000 Est. 1 Location per mile Steel and tie/timber credit MI -$50, $25,000 Est. 1 contam. Location per mile SubTotal $1,775,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10,000 0 $0 all road intersections SubTotal $965,500 Shelters Approach paths EA $2,400 8 $19,200 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $7,200 8 $57,600 foundation cost Landscaping EA $6,000 8 $48,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work, benches, trash can, etc. EA $8,000 8 $64,000 general site prep. SubTotal $46,600 $372,800

127 Rails-with-Trails Option Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges (2) over Philippi Creek Main A LS $625,000 1 $625,000 Prefab. Steel Truss bridge with foundations Main B LS $390,000 1 $390,000 Prefab. Steel Truss bridge with foundations SubTotal $1,015,000 Utilities at Trail Heads and Shelters w/ Water Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,520,000 Mobilization 3.0% $450,000 MOT 3.0% $450,000 Geotech and misc. Testing 2.0% $300,000 Additional items 4.0% $610,000 Contingency 10.0% $1,520,000 Asbuilts, close-out 2.0% $300,000 SubTotal $5,150,000 Project Cost Estimate Total $20,301,600

128 Cost Unit Descriptions UNIT AC CY EA LF LS MI NM SF SY TN DESCRIPTION Acre Cubic Yard Each Linear Foot Lump Sum Mile Net Mile Square Foot Square Yard Ton

129 Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 25,800' + Separated Trail length ~ 13,700' = Total Length ~ 39,500' or 7.5 miles) Clear and grub AC $30, $1,500,000 Clear all nuisance plants full width Cut and fill (single trail) CY $10 20,000 $200,000 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $10 10,600 $106,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $150 4,400 $660,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $150 2,670 $400,500 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $22 33,600 $739,200 6" bank run shell Base (dbl. trail) SY $22 33,500 $737,000 6" bank run shell Subbase (single trail) SY $11 5,000 $55,000 Build base as needed in poor soils Subbase (dbl. trail) SY $11 10,000 $110,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $20 5,000 $100,000 Chain link type as needed Ped/bike railing LF $70 1,500 $105,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $25, $900,000 Border trees and bushes as needed Sod, seeding SY $3 130,000 $390,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $60,000 1 $60,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $6, $192,000 drainage pipe and structures Pond/swale construction EA $30,000 6 $180,000 pond/swale construction SubTotal $7,024,200

130 Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $1,125,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $375,000 Est. 0.5 contam. sites per mile Surface water remediation MI $100, $375,000 Est. 0.5 sites per mile Steel and tie/timber credit MI -$50, $375,000 Est. 0.5 contam. sites per mile SubTotal $1,725,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10, $130,000 all road intersections SubTotal $1,095,500 Shelters Approach paths EA $2,000 8 $16,000 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $6,000 8 $48,000 foundation cost Landscaping EA $5,000 8 $40,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work EA $8,000 8 $64,000 general site prep. SubTotal $44,000 $352,000

131 Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges Main A LS $525,000 1 $525,000 Prefab. Steel Truss bridge with foundations Main B LS $325,000 1 $325,000 Prefab. Steel Truss bridge with foundations SubTotal $850,000 Utilities Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,270,000 Mobilization 3.0% $380,000 MOT 2.0% $250,000 Geotech and misc. Testing 2.0% $250,000 Additional items 4.0% $510,000 Contingency 10.0% $1,270,000 Asbuilts, close-out 2.0% $250,000 SubTotal $4,180,000 Project Cost Estimate Total $16,846,700

132 ( This Page Blank.)

133 Rails-with-Trails Option Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 17,800' + Separated Trail length ~ 21,700' = Total Length ~ 39,500' or 7.5 miles) Clearing and grubbing AC $38, $1,900,000 Clear all nuisance plants full width Cut and fill (single trail) CY $12 15,800 $189,600 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $13 22,000 $286,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $180 3,050 $549,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $180 4,240 $763,200 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $27 33,600 $907,200 6" bank run shell Base (dbl. trail) SY $28 48,200 $1,349,600 6" bank run shell Subbase (single trail) SY $14 15,800 $221,200 Build base as needed in poor soils Subbase (dbl. trail) SY $14 24,000 $336,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $24 5,000 $120,000 Chain link type as needed Ped/bike railing LF $84 1,500 $126,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $30, $1,080,000 Border trees and bushes as needed Sod, seeding SY $4 130,000 $455,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $75,000 1 $75,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $7, $240,000 drainage pipe and structures Pond/swale construction EA $36,000 6 $216,000 pond/swale construction SubTotal $9,403,300

134 Rails-with-Trails Option Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $75,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $750,000 Est. 1 contam. Location per mile Surface water remediation MI $100, $750,000 Est. 1 Location per mile Steel and tie/timber credit MI -$50, $25,000 Est. 1 contam. Location per mile SubTotal $1,775,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10,000 0 $0 all road intersections SubTotal $965,500 Shelters Approach paths EA $2,400 8 $19,200 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $7,200 8 $57,600 foundation cost Landscaping EA $6,000 8 $48,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work, benches, trash can, etc. EA $8,000 8 $64,000 general site prep. SubTotal $46,600 $372,800

135 Rails-with-Trails Option Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges (2) over Philippi Creek Main A LS $625,000 1 $625,000 Prefab. Steel Truss bridge with foundations Main B LS $390,000 1 $390,000 Prefab. Steel Truss bridge with foundations SubTotal $1,015,000 Utilities at Trail Heads and Shelters w/ Water Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,520,000 Mobilization 3.0% $450,000 MOT 3.0% $450,000 Geotech and misc. Testing 2.0% $300,000 Additional items 4.0% $610,000 Contingency 10.0% $1,520,000 Asbuilts, close-out 2.0% $300,000 SubTotal $5,150,000 Project Cost Estimate Total $20,301,600

136 Cost Unit Descriptions UNIT AC CY EA LF LS MI NM SF SY TN DESCRIPTION Acre Cubic Yard Each Linear Foot Lump Sum Mile Net Mile Square Foot Square Yard Ton

137 Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 25,800' + Separated Trail length ~ 13,700' = Total Length ~ 39,500' or 7.5 miles) Clear and grub AC $30, $1,500,000 Clear all nuisance plants full width Cut and fill (single trail) CY $10 20,000 $200,000 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $10 10,600 $106,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $150 4,400 $660,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $150 2,670 $400,500 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $22 33,600 $739,200 6" bank run shell Base (dbl. trail) SY $22 33,500 $737,000 6" bank run shell Subbase (single trail) SY $11 5,000 $55,000 Build base as needed in poor soils Subbase (dbl. trail) SY $11 10,000 $110,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $20 5,000 $100,000 Chain link type as needed Ped/bike railing LF $70 1,500 $105,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $25, $900,000 Border trees and bushes as needed Sod, seeding SY $3 130,000 $390,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $60,000 1 $60,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $6, $192,000 drainage pipe and structures Pond/swale construction EA $30,000 6 $180,000 pond/swale construction SubTotal $7,024,200

138 Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $1,125,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $375,000 Est. 0.5 contam. sites per mile Surface water remediation MI $100, $375,000 Est. 0.5 sites per mile Steel and tie/timber credit MI -$50, $375,000 Est. 0.5 contam. sites per mile SubTotal $1,725,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10, $130,000 all road intersections SubTotal $1,095,500 Shelters Approach paths EA $2,000 8 $16,000 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $6,000 8 $48,000 foundation cost Landscaping EA $5,000 8 $40,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work EA $8,000 8 $64,000 general site prep. SubTotal $44,000 $352,000

139 Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges Main A LS $525,000 1 $525,000 Prefab. Steel Truss bridge with foundations Main B LS $325,000 1 $325,000 Prefab. Steel Truss bridge with foundations SubTotal $850,000 Utilities Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,270,000 Mobilization 3.0% $380,000 MOT 2.0% $250,000 Geotech and misc. Testing 2.0% $250,000 Additional items 4.0% $510,000 Contingency 10.0% $1,270,000 Asbuilts, close-out 2.0% $250,000 SubTotal $4,180,000 Project Cost Estimate Total $16,846,700

140 ( This Page Blank.)

141 Rails-with-Trails Option Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 17,800' + Separated Trail length ~ 21,700' = Total Length ~ 39,500' or 7.5 miles) Clearing and grubbing AC $38, $1,900,000 Clear all nuisance plants full width Cut and fill (single trail) CY $12 15,800 $189,600 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $13 22,000 $286,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $180 3,050 $549,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $180 4,240 $763,200 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $27 33,600 $907,200 6" bank run shell Base (dbl. trail) SY $28 48,200 $1,349,600 6" bank run shell Subbase (single trail) SY $14 15,800 $221,200 Build base as needed in poor soils Subbase (dbl. trail) SY $14 24,000 $336,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $24 5,000 $120,000 Chain link type as needed Ped/bike railing LF $84 1,500 $126,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $30, $1,080,000 Border trees and bushes as needed Sod, seeding SY $4 130,000 $455,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $75,000 1 $75,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $7, $240,000 drainage pipe and structures Pond/swale construction EA $36,000 6 $216,000 pond/swale construction SubTotal $9,403,300

142 Rails-with-Trails Option Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $75,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $750,000 Est. 1 contam. Location per mile Surface water remediation MI $100, $750,000 Est. 1 Location per mile Steel and tie/timber credit MI -$50, $25,000 Est. 1 contam. Location per mile SubTotal $1,775,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10,000 0 $0 all road intersections SubTotal $965,500 Shelters Approach paths EA $2,400 8 $19,200 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $7,200 8 $57,600 foundation cost Landscaping EA $6,000 8 $48,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work, benches, trash can, etc. EA $8,000 8 $64,000 general site prep. SubTotal $46,600 $372,800

143 Rails-with-Trails Option Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges (2) over Philippi Creek Main A LS $625,000 1 $625,000 Prefab. Steel Truss bridge with foundations Main B LS $390,000 1 $390,000 Prefab. Steel Truss bridge with foundations SubTotal $1,015,000 Utilities at Trail Heads and Shelters w/ Water Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,520,000 Mobilization 3.0% $450,000 MOT 3.0% $450,000 Geotech and misc. Testing 2.0% $300,000 Additional items 4.0% $610,000 Contingency 10.0% $1,520,000 Asbuilts, close-out 2.0% $300,000 SubTotal $5,150,000 Project Cost Estimate Total $20,301,600

144 Cost Unit Descriptions UNIT AC CY EA LF LS MI NM SF SY TN DESCRIPTION Acre Cubic Yard Each Linear Foot Lump Sum Mile Net Mile Square Foot Square Yard Ton

145 Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 25,800' + Separated Trail length ~ 13,700' = Total Length ~ 39,500' or 7.5 miles) Clear and grub AC $30, $1,500,000 Clear all nuisance plants full width Cut and fill (single trail) CY $10 20,000 $200,000 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $10 10,600 $106,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $150 4,400 $660,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $150 2,670 $400,500 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $22 33,600 $739,200 6" bank run shell Base (dbl. trail) SY $22 33,500 $737,000 6" bank run shell Subbase (single trail) SY $11 5,000 $55,000 Build base as needed in poor soils Subbase (dbl. trail) SY $11 10,000 $110,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $20 5,000 $100,000 Chain link type as needed Ped/bike railing LF $70 1,500 $105,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $25, $900,000 Border trees and bushes as needed Sod, seeding SY $3 130,000 $390,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $60,000 1 $60,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $6, $192,000 drainage pipe and structures Pond/swale construction EA $30,000 6 $180,000 pond/swale construction SubTotal $7,024,200

146 Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $1,125,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $375,000 Est. 0.5 contam. sites per mile Surface water remediation MI $100, $375,000 Est. 0.5 sites per mile Steel and tie/timber credit MI -$50, $375,000 Est. 0.5 contam. sites per mile SubTotal $1,725,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10, $130,000 all road intersections SubTotal $1,095,500 Shelters Approach paths EA $2,000 8 $16,000 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $6,000 8 $48,000 foundation cost Landscaping EA $5,000 8 $40,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work EA $8,000 8 $64,000 general site prep. SubTotal $44,000 $352,000

147 Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges Main A LS $525,000 1 $525,000 Prefab. Steel Truss bridge with foundations Main B LS $325,000 1 $325,000 Prefab. Steel Truss bridge with foundations SubTotal $850,000 Utilities Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,270,000 Mobilization 3.0% $380,000 MOT 2.0% $250,000 Geotech and misc. Testing 2.0% $250,000 Additional items 4.0% $510,000 Contingency 10.0% $1,270,000 Asbuilts, close-out 2.0% $250,000 SubTotal $4,180,000 Project Cost Estimate Total $16,846,700

148 ( This Page Blank.)

149 Rails-with-Trails Option Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 17,800' + Separated Trail length ~ 21,700' = Total Length ~ 39,500' or 7.5 miles) Clearing and grubbing AC $38, $1,900,000 Clear all nuisance plants full width Cut and fill (single trail) CY $12 15,800 $189,600 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $13 22,000 $286,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $180 3,050 $549,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $180 4,240 $763,200 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $27 33,600 $907,200 6" bank run shell Base (dbl. trail) SY $28 48,200 $1,349,600 6" bank run shell Subbase (single trail) SY $14 15,800 $221,200 Build base as needed in poor soils Subbase (dbl. trail) SY $14 24,000 $336,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $24 5,000 $120,000 Chain link type as needed Ped/bike railing LF $84 1,500 $126,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $30, $1,080,000 Border trees and bushes as needed Sod, seeding SY $4 130,000 $455,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $75,000 1 $75,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $7, $240,000 drainage pipe and structures Pond/swale construction EA $36,000 6 $216,000 pond/swale construction SubTotal $9,403,300

150 Rails-with-Trails Option Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $75,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $750,000 Est. 1 contam. Location per mile Surface water remediation MI $100, $750,000 Est. 1 Location per mile Steel and tie/timber credit MI -$50, $25,000 Est. 1 contam. Location per mile SubTotal $1,775,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10,000 0 $0 all road intersections SubTotal $965,500 Shelters Approach paths EA $2,400 8 $19,200 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $7,200 8 $57,600 foundation cost Landscaping EA $6,000 8 $48,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work, benches, trash can, etc. EA $8,000 8 $64,000 general site prep. SubTotal $46,600 $372,800

151 Rails-with-Trails Option Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges (2) over Philippi Creek Main A LS $625,000 1 $625,000 Prefab. Steel Truss bridge with foundations Main B LS $390,000 1 $390,000 Prefab. Steel Truss bridge with foundations SubTotal $1,015,000 Utilities at Trail Heads and Shelters w/ Water Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,520,000 Mobilization 3.0% $450,000 MOT 3.0% $450,000 Geotech and misc. Testing 2.0% $300,000 Additional items 4.0% $610,000 Contingency 10.0% $1,520,000 Asbuilts, close-out 2.0% $300,000 SubTotal $5,150,000 Project Cost Estimate Total $20,301,600

152 Cost Unit Descriptions UNIT AC CY EA LF LS MI NM SF SY TN DESCRIPTION Acre Cubic Yard Each Linear Foot Lump Sum Mile Net Mile Square Foot Square Yard Ton

153 Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 25,800' + Separated Trail length ~ 13,700' = Total Length ~ 39,500' or 7.5 miles) Clear and grub AC $30, $1,500,000 Clear all nuisance plants full width Cut and fill (single trail) CY $10 20,000 $200,000 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $10 10,600 $106,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $150 4,400 $660,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $150 2,670 $400,500 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $22 33,600 $739,200 6" bank run shell Base (dbl. trail) SY $22 33,500 $737,000 6" bank run shell Subbase (single trail) SY $11 5,000 $55,000 Build base as needed in poor soils Subbase (dbl. trail) SY $11 10,000 $110,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $20 5,000 $100,000 Chain link type as needed Ped/bike railing LF $70 1,500 $105,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $25, $900,000 Border trees and bushes as needed Sod, seeding SY $3 130,000 $390,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $60,000 1 $60,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $6, $192,000 drainage pipe and structures Pond/swale construction EA $30,000 6 $180,000 pond/swale construction SubTotal $7,024,200

154 Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $1,125,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $375,000 Est. 0.5 contam. sites per mile Surface water remediation MI $100, $375,000 Est. 0.5 sites per mile Steel and tie/timber credit MI -$50, $375,000 Est. 0.5 contam. sites per mile SubTotal $1,725,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10, $130,000 all road intersections SubTotal $1,095,500 Shelters Approach paths EA $2,000 8 $16,000 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $6,000 8 $48,000 foundation cost Landscaping EA $5,000 8 $40,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work EA $8,000 8 $64,000 general site prep. SubTotal $44,000 $352,000

155 Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges Main A LS $525,000 1 $525,000 Prefab. Steel Truss bridge with foundations Main B LS $325,000 1 $325,000 Prefab. Steel Truss bridge with foundations SubTotal $850,000 Utilities Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,270,000 Mobilization 3.0% $380,000 MOT 2.0% $250,000 Geotech and misc. Testing 2.0% $250,000 Additional items 4.0% $510,000 Contingency 10.0% $1,270,000 Asbuilts, close-out 2.0% $250,000 SubTotal $4,180,000 Project Cost Estimate Total $16,846,700

156 ( This Page Blank.)

157 Rails-with-Trails Option Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 17,800' + Separated Trail length ~ 21,700' = Total Length ~ 39,500' or 7.5 miles) Clearing and grubbing AC $38, $1,900,000 Clear all nuisance plants full width Cut and fill (single trail) CY $12 15,800 $189,600 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $13 22,000 $286,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $180 3,050 $549,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $180 4,240 $763,200 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $27 33,600 $907,200 6" bank run shell Base (dbl. trail) SY $28 48,200 $1,349,600 6" bank run shell Subbase (single trail) SY $14 15,800 $221,200 Build base as needed in poor soils Subbase (dbl. trail) SY $14 24,000 $336,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $24 5,000 $120,000 Chain link type as needed Ped/bike railing LF $84 1,500 $126,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $30, $1,080,000 Border trees and bushes as needed Sod, seeding SY $4 130,000 $455,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $75,000 1 $75,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $7, $240,000 drainage pipe and structures Pond/swale construction EA $36,000 6 $216,000 pond/swale construction SubTotal $9,403,300

158 Rails-with-Trails Option Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $75,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $750,000 Est. 1 contam. Location per mile Surface water remediation MI $100, $750,000 Est. 1 Location per mile Steel and tie/timber credit MI -$50, $25,000 Est. 1 contam. Location per mile SubTotal $1,775,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10,000 0 $0 all road intersections SubTotal $965,500 Shelters Approach paths EA $2,400 8 $19,200 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $7,200 8 $57,600 foundation cost Landscaping EA $6,000 8 $48,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work, benches, trash can, etc. EA $8,000 8 $64,000 general site prep. SubTotal $46,600 $372,800

159 Rails-with-Trails Option Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges (2) over Philippi Creek Main A LS $625,000 1 $625,000 Prefab. Steel Truss bridge with foundations Main B LS $390,000 1 $390,000 Prefab. Steel Truss bridge with foundations SubTotal $1,015,000 Utilities at Trail Heads and Shelters w/ Water Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,520,000 Mobilization 3.0% $450,000 MOT 3.0% $450,000 Geotech and misc. Testing 2.0% $300,000 Additional items 4.0% $610,000 Contingency 10.0% $1,520,000 Asbuilts, close-out 2.0% $300,000 SubTotal $5,150,000 Project Cost Estimate Total $20,301,600

160 Cost Unit Descriptions UNIT AC CY EA LF LS MI NM SF SY TN DESCRIPTION Acre Cubic Yard Each Linear Foot Lump Sum Mile Net Mile Square Foot Square Yard Ton

161 Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 25,800' + Separated Trail length ~ 13,700' = Total Length ~ 39,500' or 7.5 miles) Clear and grub AC $30, $1,500,000 Clear all nuisance plants full width Cut and fill (single trail) CY $10 20,000 $200,000 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $10 10,600 $106,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $150 4,400 $660,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $150 2,670 $400,500 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $22 33,600 $739,200 6" bank run shell Base (dbl. trail) SY $22 33,500 $737,000 6" bank run shell Subbase (single trail) SY $11 5,000 $55,000 Build base as needed in poor soils Subbase (dbl. trail) SY $11 10,000 $110,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $20 5,000 $100,000 Chain link type as needed Ped/bike railing LF $70 1,500 $105,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $25, $900,000 Border trees and bushes as needed Sod, seeding SY $3 130,000 $390,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $60,000 1 $60,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $6, $192,000 drainage pipe and structures Pond/swale construction EA $30,000 6 $180,000 pond/swale construction SubTotal $7,024,200

162 Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $1,125,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $375,000 Est. 0.5 contam. sites per mile Surface water remediation MI $100, $375,000 Est. 0.5 sites per mile Steel and tie/timber credit MI -$50, $375,000 Est. 0.5 contam. sites per mile SubTotal $1,725,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10, $130,000 all road intersections SubTotal $1,095,500 Shelters Approach paths EA $2,000 8 $16,000 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $6,000 8 $48,000 foundation cost Landscaping EA $5,000 8 $40,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work EA $8,000 8 $64,000 general site prep. SubTotal $44,000 $352,000

163 Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges Main A LS $525,000 1 $525,000 Prefab. Steel Truss bridge with foundations Main B LS $325,000 1 $325,000 Prefab. Steel Truss bridge with foundations SubTotal $850,000 Utilities Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,270,000 Mobilization 3.0% $380,000 MOT 2.0% $250,000 Geotech and misc. Testing 2.0% $250,000 Additional items 4.0% $510,000 Contingency 10.0% $1,270,000 Asbuilts, close-out 2.0% $250,000 SubTotal $4,180,000 Project Cost Estimate Total $16,846,700

164 ( This Page Blank.)

165 Rails-with-Trails Option Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 17,800' + Separated Trail length ~ 21,700' = Total Length ~ 39,500' or 7.5 miles) Clearing and grubbing AC $38, $1,900,000 Clear all nuisance plants full width Cut and fill (single trail) CY $12 15,800 $189,600 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $13 22,000 $286,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $180 3,050 $549,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $180 4,240 $763,200 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $27 33,600 $907,200 6" bank run shell Base (dbl. trail) SY $28 48,200 $1,349,600 6" bank run shell Subbase (single trail) SY $14 15,800 $221,200 Build base as needed in poor soils Subbase (dbl. trail) SY $14 24,000 $336,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $24 5,000 $120,000 Chain link type as needed Ped/bike railing LF $84 1,500 $126,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $30, $1,080,000 Border trees and bushes as needed Sod, seeding SY $4 130,000 $455,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $75,000 1 $75,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $7, $240,000 drainage pipe and structures Pond/swale construction EA $36,000 6 $216,000 pond/swale construction SubTotal $9,403,300

166 Rails-with-Trails Option Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $75,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $750,000 Est. 1 contam. Location per mile Surface water remediation MI $100, $750,000 Est. 1 Location per mile Steel and tie/timber credit MI -$50, $25,000 Est. 1 contam. Location per mile SubTotal $1,775,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10,000 0 $0 all road intersections SubTotal $965,500 Shelters Approach paths EA $2,400 8 $19,200 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $7,200 8 $57,600 foundation cost Landscaping EA $6,000 8 $48,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work, benches, trash can, etc. EA $8,000 8 $64,000 general site prep. SubTotal $46,600 $372,800

167 Rails-with-Trails Option Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges (2) over Philippi Creek Main A LS $625,000 1 $625,000 Prefab. Steel Truss bridge with foundations Main B LS $390,000 1 $390,000 Prefab. Steel Truss bridge with foundations SubTotal $1,015,000 Utilities at Trail Heads and Shelters w/ Water Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,520,000 Mobilization 3.0% $450,000 MOT 3.0% $450,000 Geotech and misc. Testing 2.0% $300,000 Additional items 4.0% $610,000 Contingency 10.0% $1,520,000 Asbuilts, close-out 2.0% $300,000 SubTotal $5,150,000 Project Cost Estimate Total $20,301,600

168 Cost Unit Descriptions UNIT AC CY EA LF LS MI NM SF SY TN DESCRIPTION Acre Cubic Yard Each Linear Foot Lump Sum Mile Net Mile Square Foot Square Yard Ton

169 Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 25,800' + Separated Trail length ~ 13,700' = Total Length ~ 39,500' or 7.5 miles) Clear and grub AC $30, $1,500,000 Clear all nuisance plants full width Cut and fill (single trail) CY $10 20,000 $200,000 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $10 10,600 $106,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $150 4,400 $660,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $150 2,670 $400,500 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $22 33,600 $739,200 6" bank run shell Base (dbl. trail) SY $22 33,500 $737,000 6" bank run shell Subbase (single trail) SY $11 5,000 $55,000 Build base as needed in poor soils Subbase (dbl. trail) SY $11 10,000 $110,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $20 5,000 $100,000 Chain link type as needed Ped/bike railing LF $70 1,500 $105,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $25, $900,000 Border trees and bushes as needed Sod, seeding SY $3 130,000 $390,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $60,000 1 $60,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $6, $192,000 drainage pipe and structures Pond/swale construction EA $30,000 6 $180,000 pond/swale construction SubTotal $7,024,200

170 Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $1,125,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $375,000 Est. 0.5 contam. sites per mile Surface water remediation MI $100, $375,000 Est. 0.5 sites per mile Steel and tie/timber credit MI -$50, $375,000 Est. 0.5 contam. sites per mile SubTotal $1,725,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10, $130,000 all road intersections SubTotal $1,095,500 Shelters Approach paths EA $2,000 8 $16,000 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $6,000 8 $48,000 foundation cost Landscaping EA $5,000 8 $40,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work EA $8,000 8 $64,000 general site prep. SubTotal $44,000 $352,000

171 Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges Main A LS $525,000 1 $525,000 Prefab. Steel Truss bridge with foundations Main B LS $325,000 1 $325,000 Prefab. Steel Truss bridge with foundations SubTotal $850,000 Utilities Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,270,000 Mobilization 3.0% $380,000 MOT 2.0% $250,000 Geotech and misc. Testing 2.0% $250,000 Additional items 4.0% $510,000 Contingency 10.0% $1,270,000 Asbuilts, close-out 2.0% $250,000 SubTotal $4,180,000 Project Cost Estimate Total $16,846,700

172 ( This Page Blank.)

173 Rails-with-Trails Option Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 17,800' + Separated Trail length ~ 21,700' = Total Length ~ 39,500' or 7.5 miles) Clearing and grubbing AC $38, $1,900,000 Clear all nuisance plants full width Cut and fill (single trail) CY $12 15,800 $189,600 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $13 22,000 $286,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $180 3,050 $549,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $180 4,240 $763,200 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $27 33,600 $907,200 6" bank run shell Base (dbl. trail) SY $28 48,200 $1,349,600 6" bank run shell Subbase (single trail) SY $14 15,800 $221,200 Build base as needed in poor soils Subbase (dbl. trail) SY $14 24,000 $336,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $24 5,000 $120,000 Chain link type as needed Ped/bike railing LF $84 1,500 $126,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $30, $1,080,000 Border trees and bushes as needed Sod, seeding SY $4 130,000 $455,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $75,000 1 $75,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $7, $240,000 drainage pipe and structures Pond/swale construction EA $36,000 6 $216,000 pond/swale construction SubTotal $9,403,300

174 Rails-with-Trails Option Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $75,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $750,000 Est. 1 contam. Location per mile Surface water remediation MI $100, $750,000 Est. 1 Location per mile Steel and tie/timber credit MI -$50, $25,000 Est. 1 contam. Location per mile SubTotal $1,775,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10,000 0 $0 all road intersections SubTotal $965,500 Shelters Approach paths EA $2,400 8 $19,200 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $7,200 8 $57,600 foundation cost Landscaping EA $6,000 8 $48,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work, benches, trash can, etc. EA $8,000 8 $64,000 general site prep. SubTotal $46,600 $372,800

175 Rails-with-Trails Option Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges (2) over Philippi Creek Main A LS $625,000 1 $625,000 Prefab. Steel Truss bridge with foundations Main B LS $390,000 1 $390,000 Prefab. Steel Truss bridge with foundations SubTotal $1,015,000 Utilities at Trail Heads and Shelters w/ Water Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,520,000 Mobilization 3.0% $450,000 MOT 3.0% $450,000 Geotech and misc. Testing 2.0% $300,000 Additional items 4.0% $610,000 Contingency 10.0% $1,520,000 Asbuilts, close-out 2.0% $300,000 SubTotal $5,150,000 Project Cost Estimate Total $20,301,600

176 Cost Unit Descriptions UNIT AC CY EA LF LS MI NM SF SY TN DESCRIPTION Acre Cubic Yard Each Linear Foot Lump Sum Mile Net Mile Square Foot Square Yard Ton

177 Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 25,800' + Separated Trail length ~ 13,700' = Total Length ~ 39,500' or 7.5 miles) Clear and grub AC $30, $1,500,000 Clear all nuisance plants full width Cut and fill (single trail) CY $10 20,000 $200,000 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $10 10,600 $106,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $150 4,400 $660,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $150 2,670 $400,500 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $22 33,600 $739,200 6" bank run shell Base (dbl. trail) SY $22 33,500 $737,000 6" bank run shell Subbase (single trail) SY $11 5,000 $55,000 Build base as needed in poor soils Subbase (dbl. trail) SY $11 10,000 $110,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $20 5,000 $100,000 Chain link type as needed Ped/bike railing LF $70 1,500 $105,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $25, $900,000 Border trees and bushes as needed Sod, seeding SY $3 130,000 $390,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $60,000 1 $60,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $6, $192,000 drainage pipe and structures Pond/swale construction EA $30,000 6 $180,000 pond/swale construction SubTotal $7,024,200

178 Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $1,125,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $375,000 Est. 0.5 contam. sites per mile Surface water remediation MI $100, $375,000 Est. 0.5 sites per mile Steel and tie/timber credit MI -$50, $375,000 Est. 0.5 contam. sites per mile SubTotal $1,725,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10, $130,000 all road intersections SubTotal $1,095,500 Shelters Approach paths EA $2,000 8 $16,000 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $6,000 8 $48,000 foundation cost Landscaping EA $5,000 8 $40,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work EA $8,000 8 $64,000 general site prep. SubTotal $44,000 $352,000

179 Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges Main A LS $525,000 1 $525,000 Prefab. Steel Truss bridge with foundations Main B LS $325,000 1 $325,000 Prefab. Steel Truss bridge with foundations SubTotal $850,000 Utilities Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,270,000 Mobilization 3.0% $380,000 MOT 2.0% $250,000 Geotech and misc. Testing 2.0% $250,000 Additional items 4.0% $510,000 Contingency 10.0% $1,270,000 Asbuilts, close-out 2.0% $250,000 SubTotal $4,180,000 Project Cost Estimate Total $16,846,700

180 ( This Page Blank.)

181 Rails-with-Trails Option Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 17,800' + Separated Trail length ~ 21,700' = Total Length ~ 39,500' or 7.5 miles) Clearing and grubbing AC $38, $1,900,000 Clear all nuisance plants full width Cut and fill (single trail) CY $12 15,800 $189,600 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $13 22,000 $286,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $180 3,050 $549,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $180 4,240 $763,200 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $27 33,600 $907,200 6" bank run shell Base (dbl. trail) SY $28 48,200 $1,349,600 6" bank run shell Subbase (single trail) SY $14 15,800 $221,200 Build base as needed in poor soils Subbase (dbl. trail) SY $14 24,000 $336,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $24 5,000 $120,000 Chain link type as needed Ped/bike railing LF $84 1,500 $126,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $30, $1,080,000 Border trees and bushes as needed Sod, seeding SY $4 130,000 $455,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $75,000 1 $75,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $7, $240,000 drainage pipe and structures Pond/swale construction EA $36,000 6 $216,000 pond/swale construction SubTotal $9,403,300

182 Rails-with-Trails Option Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $75,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $750,000 Est. 1 contam. Location per mile Surface water remediation MI $100, $750,000 Est. 1 Location per mile Steel and tie/timber credit MI -$50, $25,000 Est. 1 contam. Location per mile SubTotal $1,775,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10,000 0 $0 all road intersections SubTotal $965,500 Shelters Approach paths EA $2,400 8 $19,200 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $7,200 8 $57,600 foundation cost Landscaping EA $6,000 8 $48,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work, benches, trash can, etc. EA $8,000 8 $64,000 general site prep. SubTotal $46,600 $372,800

183 Rails-with-Trails Option Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges (2) over Philippi Creek Main A LS $625,000 1 $625,000 Prefab. Steel Truss bridge with foundations Main B LS $390,000 1 $390,000 Prefab. Steel Truss bridge with foundations SubTotal $1,015,000 Utilities at Trail Heads and Shelters w/ Water Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,520,000 Mobilization 3.0% $450,000 MOT 3.0% $450,000 Geotech and misc. Testing 2.0% $300,000 Additional items 4.0% $610,000 Contingency 10.0% $1,520,000 Asbuilts, close-out 2.0% $300,000 SubTotal $5,150,000 Project Cost Estimate Total $20,301,600

184 Cost Unit Descriptions UNIT AC CY EA LF LS MI NM SF SY TN DESCRIPTION Acre Cubic Yard Each Linear Foot Lump Sum Mile Net Mile Square Foot Square Yard Ton

185 Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 25,800' + Separated Trail length ~ 13,700' = Total Length ~ 39,500' or 7.5 miles) Clear and grub AC $30, $1,500,000 Clear all nuisance plants full width Cut and fill (single trail) CY $10 20,000 $200,000 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $10 10,600 $106,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $150 4,400 $660,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $150 2,670 $400,500 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $22 33,600 $739,200 6" bank run shell Base (dbl. trail) SY $22 33,500 $737,000 6" bank run shell Subbase (single trail) SY $11 5,000 $55,000 Build base as needed in poor soils Subbase (dbl. trail) SY $11 10,000 $110,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $20 5,000 $100,000 Chain link type as needed Ped/bike railing LF $70 1,500 $105,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $25, $900,000 Border trees and bushes as needed Sod, seeding SY $3 130,000 $390,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $60,000 1 $60,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $6, $192,000 drainage pipe and structures Pond/swale construction EA $30,000 6 $180,000 pond/swale construction SubTotal $7,024,200

186 Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $1,125,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $375,000 Est. 0.5 contam. sites per mile Surface water remediation MI $100, $375,000 Est. 0.5 sites per mile Steel and tie/timber credit MI -$50, $375,000 Est. 0.5 contam. sites per mile SubTotal $1,725,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10, $130,000 all road intersections SubTotal $1,095,500 Shelters Approach paths EA $2,000 8 $16,000 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $6,000 8 $48,000 foundation cost Landscaping EA $5,000 8 $40,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work EA $8,000 8 $64,000 general site prep. SubTotal $44,000 $352,000

187 Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges Main A LS $525,000 1 $525,000 Prefab. Steel Truss bridge with foundations Main B LS $325,000 1 $325,000 Prefab. Steel Truss bridge with foundations SubTotal $850,000 Utilities Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,270,000 Mobilization 3.0% $380,000 MOT 2.0% $250,000 Geotech and misc. Testing 2.0% $250,000 Additional items 4.0% $510,000 Contingency 10.0% $1,270,000 Asbuilts, close-out 2.0% $250,000 SubTotal $4,180,000 Project Cost Estimate Total $16,846,700

188 ( This Page Blank.)

189 Rails-with-Trails Option Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 17,800' + Separated Trail length ~ 21,700' = Total Length ~ 39,500' or 7.5 miles) Clearing and grubbing AC $38, $1,900,000 Clear all nuisance plants full width Cut and fill (single trail) CY $12 15,800 $189,600 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $13 22,000 $286,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $180 3,050 $549,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $180 4,240 $763,200 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $27 33,600 $907,200 6" bank run shell Base (dbl. trail) SY $28 48,200 $1,349,600 6" bank run shell Subbase (single trail) SY $14 15,800 $221,200 Build base as needed in poor soils Subbase (dbl. trail) SY $14 24,000 $336,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $24 5,000 $120,000 Chain link type as needed Ped/bike railing LF $84 1,500 $126,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $30, $1,080,000 Border trees and bushes as needed Sod, seeding SY $4 130,000 $455,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $75,000 1 $75,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $7, $240,000 drainage pipe and structures Pond/swale construction EA $36,000 6 $216,000 pond/swale construction SubTotal $9,403,300

190 Rails-with-Trails Option Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $75,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $750,000 Est. 1 contam. Location per mile Surface water remediation MI $100, $750,000 Est. 1 Location per mile Steel and tie/timber credit MI -$50, $25,000 Est. 1 contam. Location per mile SubTotal $1,775,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10,000 0 $0 all road intersections SubTotal $965,500 Shelters Approach paths EA $2,400 8 $19,200 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $7,200 8 $57,600 foundation cost Landscaping EA $6,000 8 $48,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work, benches, trash can, etc. EA $8,000 8 $64,000 general site prep. SubTotal $46,600 $372,800

191 Rails-with-Trails Option Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges (2) over Philippi Creek Main A LS $625,000 1 $625,000 Prefab. Steel Truss bridge with foundations Main B LS $390,000 1 $390,000 Prefab. Steel Truss bridge with foundations SubTotal $1,015,000 Utilities at Trail Heads and Shelters w/ Water Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,520,000 Mobilization 3.0% $450,000 MOT 3.0% $450,000 Geotech and misc. Testing 2.0% $300,000 Additional items 4.0% $610,000 Contingency 10.0% $1,520,000 Asbuilts, close-out 2.0% $300,000 SubTotal $5,150,000 Project Cost Estimate Total $20,301,600

192 Cost Unit Descriptions UNIT AC CY EA LF LS MI NM SF SY TN DESCRIPTION Acre Cubic Yard Each Linear Foot Lump Sum Mile Net Mile Square Foot Square Yard Ton

193 Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 25,800' + Separated Trail length ~ 13,700' = Total Length ~ 39,500' or 7.5 miles) Clear and grub AC $30, $1,500,000 Clear all nuisance plants full width Cut and fill (single trail) CY $10 20,000 $200,000 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $10 10,600 $106,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $150 4,400 $660,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $150 2,670 $400,500 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $22 33,600 $739,200 6" bank run shell Base (dbl. trail) SY $22 33,500 $737,000 6" bank run shell Subbase (single trail) SY $11 5,000 $55,000 Build base as needed in poor soils Subbase (dbl. trail) SY $11 10,000 $110,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $20 5,000 $100,000 Chain link type as needed Ped/bike railing LF $70 1,500 $105,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $25, $900,000 Border trees and bushes as needed Sod, seeding SY $3 130,000 $390,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $60,000 1 $60,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $6, $192,000 drainage pipe and structures Pond/swale construction EA $30,000 6 $180,000 pond/swale construction SubTotal $7,024,200

194 Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $1,125,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $375,000 Est. 0.5 contam. sites per mile Surface water remediation MI $100, $375,000 Est. 0.5 sites per mile Steel and tie/timber credit MI -$50, $375,000 Est. 0.5 contam. sites per mile SubTotal $1,725,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10, $130,000 all road intersections SubTotal $1,095,500 Shelters Approach paths EA $2,000 8 $16,000 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $6,000 8 $48,000 foundation cost Landscaping EA $5,000 8 $40,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work EA $8,000 8 $64,000 general site prep. SubTotal $44,000 $352,000

195 Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges Main A LS $525,000 1 $525,000 Prefab. Steel Truss bridge with foundations Main B LS $325,000 1 $325,000 Prefab. Steel Truss bridge with foundations SubTotal $850,000 Utilities Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,270,000 Mobilization 3.0% $380,000 MOT 2.0% $250,000 Geotech and misc. Testing 2.0% $250,000 Additional items 4.0% $510,000 Contingency 10.0% $1,270,000 Asbuilts, close-out 2.0% $250,000 SubTotal $4,180,000 Project Cost Estimate Total $16,846,700

196 ( This Page Blank.)

197 Rails-with-Trails Option Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 17,800' + Separated Trail length ~ 21,700' = Total Length ~ 39,500' or 7.5 miles) Clearing and grubbing AC $38, $1,900,000 Clear all nuisance plants full width Cut and fill (single trail) CY $12 15,800 $189,600 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $13 22,000 $286,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $180 3,050 $549,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $180 4,240 $763,200 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $27 33,600 $907,200 6" bank run shell Base (dbl. trail) SY $28 48,200 $1,349,600 6" bank run shell Subbase (single trail) SY $14 15,800 $221,200 Build base as needed in poor soils Subbase (dbl. trail) SY $14 24,000 $336,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $24 5,000 $120,000 Chain link type as needed Ped/bike railing LF $84 1,500 $126,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $30, $1,080,000 Border trees and bushes as needed Sod, seeding SY $4 130,000 $455,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $75,000 1 $75,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $7, $240,000 drainage pipe and structures Pond/swale construction EA $36,000 6 $216,000 pond/swale construction SubTotal $9,403,300

198 Rails-with-Trails Option Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $75,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $750,000 Est. 1 contam. Location per mile Surface water remediation MI $100, $750,000 Est. 1 Location per mile Steel and tie/timber credit MI -$50, $25,000 Est. 1 contam. Location per mile SubTotal $1,775,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10,000 0 $0 all road intersections SubTotal $965,500 Shelters Approach paths EA $2,400 8 $19,200 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $7,200 8 $57,600 foundation cost Landscaping EA $6,000 8 $48,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work, benches, trash can, etc. EA $8,000 8 $64,000 general site prep. SubTotal $46,600 $372,800

199 Rails-with-Trails Option Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges (2) over Philippi Creek Main A LS $625,000 1 $625,000 Prefab. Steel Truss bridge with foundations Main B LS $390,000 1 $390,000 Prefab. Steel Truss bridge with foundations SubTotal $1,015,000 Utilities at Trail Heads and Shelters w/ Water Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,520,000 Mobilization 3.0% $450,000 MOT 3.0% $450,000 Geotech and misc. Testing 2.0% $300,000 Additional items 4.0% $610,000 Contingency 10.0% $1,520,000 Asbuilts, close-out 2.0% $300,000 SubTotal $5,150,000 Project Cost Estimate Total $20,301,600

200 Cost Unit Descriptions UNIT AC CY EA LF LS MI NM SF SY TN DESCRIPTION Acre Cubic Yard Each Linear Foot Lump Sum Mile Net Mile Square Foot Square Yard Ton

UNIT PRICE LIST January 2009

UNIT PRICE LIST January 2009 UNIT PRICE LIST January 2009 1 INTRODUCTION The purpose of the Unit Price List is to provide a resource for the preparation of cost estimates for subdivisions and permit projects and should be used only

More information

Description Quantity Cost Total Cost

Description Quantity Cost Total Cost APPENDIX: ITEMIZED CONSTRUCTION COST ESTIMATE Description Quantity Cost Total Cost 1 CASCADE FALLS 1a Existing Cascade Falls Upgrades Structural Repairs - Steps, Railing, Walls, Pool Lump Sum $500,000

More information

STORM WATER PROJECT COST ESTIMATES & LOCATION MAPS. Appendix F

STORM WATER PROJECT COST ESTIMATES & LOCATION MAPS. Appendix F STORM WATER PROJECT COST ESTIMATES & LOCATION MAPS Appendix F RIVERDALE CITY CAPITAL FACILITIES PLAN STORM DRAINAGE Engineer's Cost Estimate January 2009 Project Name: 4400 South Street - Piping and Collection

More information

Demo Existing Curb Demo Existing Asphalt Roadway Demo Asphalt Saw Cutting Protection Fence - 4 Snow Fence with T posts

Demo Existing Curb Demo Existing Asphalt Roadway Demo Asphalt Saw Cutting Protection Fence - 4 Snow Fence with T posts SECTION 00300 BID FORM S For additions and deletions to the Contract, the following unit prices shall be applicable for the specific items listed. Unit Prices shall be complete, in place including required

More information

A. Structures Quantity Item Price Cost @ $3,500 EA

A. Structures Quantity Item Price Cost @ $3,500 EA PRINCE WILLIAM COUNTY Department of Development Services Land Development Division UNIT PRICE LIST (Performance Bonds, Landscaping Escrows, and Siltation & Erosion Control Escrows) Revised: November 17,

More information

Figure 3 Pipe Cracking

Figure 3 Pipe Cracking The illustration shown below depicts the system analyzed. As-built drawings and survey information were not available; aerial photos and survey shots of inverts were used to determine the system s geometries.

More information

NOTICE TO CONTRACTORS. CALL ORDER 700 FEDERAL PROJECT NO. STPD-6-2(122) LOCATION: US-34/US-6,CULBERTSON-McCOOK COUNTIES: HITCHCOCK RED WILLOW

NOTICE TO CONTRACTORS. CALL ORDER 700 FEDERAL PROJECT NO. STPD-6-2(122) LOCATION: US-34/US-6,CULBERTSON-McCOOK COUNTIES: HITCHCOCK RED WILLOW NOTICE TO CONTRACTORS CALL ORDER 700 FEDERAL PROJECT NO. STPD-6-2(122) LOCATION: US-34/US-6,CULBERTSON-McCOOK COUNTIES: HITCHCOCK RED WILLOW The Nebraska Department of Roads will receive sealed bids in

More information

Chapter 22. Lump Sum Project Guidelines

Chapter 22. Lump Sum Project Guidelines Chapter 22 Lump Sum Project Guidelines 22.1 General...22-1 22.2 Project Selection...22-3 22.3 Plans Preparation...22-5 22.4 Preliminary Estimate...22-7 22.5 Specifications...22-9 22.6 Contracts Administration...22-11

More information

FY11 Sanitary Sewer Main Rehab and Point Repair Bid Tabulation

FY11 Sanitary Sewer Main Rehab and Point Repair Bid Tabulation 644-10-569 Page 1 of 9 1 FOR CLEANING AND TELEVISING EXISTING SEWERS, AS SPECIFIED, ANY REQUIRED CLEANING, ANY LOCATION, ANY LENGTH OF SEWER, COMPLETE IN PLACE, FOR VARIOUS PIPE DIAMETERS. A. EXISTING

More information

Los Angeles County Department Of Public Works. Land Development Division. Bond Calculation Sheets

Los Angeles County Department Of Public Works. Land Development Division. Bond Calculation Sheets Los Angeles County Department Of Public Works Land Development Division Bond Calculation Sheets Effective July 1, 2015 COUNTY OF LOS ANGELES DEPARTMENT OF PUBLIC WORKS LAND DEVELOPMENT DIVISION ROADS COST

More information

PROJECT COST ESTIMATE ASSUMPTIONS AND EXCLUSIONS

PROJECT COST ESTIMATE ASSUMPTIONS AND EXCLUSIONS C PROJECT ESTIMATE ASSUMPTIONS AND EXCLUSIONS In support of the alternatives development process, preliminary cost estimates were prepared for each of the three Candidate Build Alternatives. The cost estimates

More information

Roadway Cost Per Centerline Mile Revised June 2014

Roadway Cost Per Centerline Mile Revised June 2014 Rural Arterial From LRE MOT * Mobilization * Subtotal Total PE Design (15%) CEI (15%) Total Project ** New (2-Lane Roadway) with 5' Paved Shoulders $3,351,896 $335,190 $368,709 $4,055,794 $1,013,949 $5,069,743

More information

FY08 SEWER POINT REPAIRS BID TABULATION

FY08 SEWER POINT REPAIRS BID TABULATION 6-07-831 Page 1 of 12 1 FOR CLEANING AND TELEVISING EXISTING SEWERS, AS SPECIFIED, ANY REQUIRED CLEANING, ANY LOCATION, ANY LENGTH OF SEWER, COMPLETE IN PLACE, FOR VARIOUS PIPE DIAMETERS. A. EXISTING "

More information

SANITARY SEWER PROJECT COST ESTIMATES & LOCATION MAPS. Appendix D

SANITARY SEWER PROJECT COST ESTIMATES & LOCATION MAPS. Appendix D SANITARY SEWER PROJECT COST ESTIMATES & LOCATION MAPS Appendix D RIVERDALE CITY CAPITAL FACILITIES PLAN SANITARY SEWER Engineer's Cost Estimate January 2009 Project Name: Riverdale Road - Rumbi Grill -

More information

EXHIBIT A Accessible Truck Routes Map

EXHIBIT A Accessible Truck Routes Map EXHIBIT A Accessible Truck Routes Map ASHEVILLE, NORTH CAROLINA ROUTE: A ROUTE: B ROUTE: C ROUTE: D ROUTE: E EXHIBIT A EXHIBIT B Craven Street Improvements Map ASHEVILLE, NORTH CAROLINA EXHIBIT B EXHIBIT

More information

The unit costs are based on the trend line of the 3 low bids for the average quantity.

The unit costs are based on the trend line of the 3 low bids for the average quantity. Page 1 of 8 COST ESTIMATE GENERAL INSTRUCTIONS The unit costs are based on the trend line of the 3 low bids for the average quantity. Apply the Unit Costs to ordinary structures. Unit Costs should generally

More information

Jackson Gulch Outlet Canal Rehabilitation Project

Jackson Gulch Outlet Canal Rehabilitation Project Jackson Gulch Outlet Canal Rehabilitation Project Preliminary Budgetary Estimate for Rehabilitation February 2004 Prepared for the Mancos Water Conservancy District Jackson Gulch Reservoir 42888 County

More information

Walkable Communities Florida Department of Transportation State Safety Office Pedestrian and Bicycle Program April 1995 www.dot.state.fl.us/safety Twelve Steps for an Effective Program Page 1 Twelve Steps

More information

Riverside County Transportation Department Summary of Bids

Riverside County Transportation Department Summary of Bids Bids Open: 2 pm Date: Wednesday, March 4, 2015 BASE BID SCHEDULE 1 - Rudell Road Reconstruction Project NO. CODE CONTRACT PROJECT No. B3-0470 and C4-0069 COUNTY'S ESTIMATE 1 All American Asphalt Corona,

More information

MAIN STREET IMPROVEMENTS Water, Sewer, Stormwater and Streetscape Improvements

MAIN STREET IMPROVEMENTS Water, Sewer, Stormwater and Streetscape Improvements MAIN STREET IMPROVEMENTS Water, Sewer, Stormwater and Streetscape Improvements Presentation July 23, 2014 A. Morton Thomas and Associates, Inc. 800 King Farm Boulevard, 4 th Floor Rockville, Maryland 20850

More information

WILDCAT CANYON ROAD SPECIFICATION NO. 16-11001 SLIDE REPAIR BIDDER'S PROPOSAL (continued)

WILDCAT CANYON ROAD SPECIFICATION NO. 16-11001 SLIDE REPAIR BIDDER'S PROPOSAL (continued) BIDDER'S PROPOSAL (continued) Item Estimated No. Description Quantity Unit Unit Cost Total Cost BASE BID 1 Traffic Control 1 LS $ $ 2 Construction Area Signs 1 LS $ $ 3 Excavation Safety 1 LS $ $ 4 Reset

More information

FLORIDA DEPARTMENT OF TRANSPORTATION GUIDELINE FOR

FLORIDA DEPARTMENT OF TRANSPORTATION GUIDELINE FOR FLORIDA DEPARTMENT OF TRANSPORTATION GUIDELINE FOR ESTABLISHING CONSTRUCTION CONTRACT DURATION July 2010 DISCLAIMER: The following documentation as a whole was derived from Federal Highway Administration

More information

FDOT Specifications List

FDOT Specifications List FDOT Specifications List TABLE OF CONTENTS DIVISION II CONSTRUCTION DETAILS CLEARING CONSTRUCTION SITE 110 Clearing and Grubbing... 152 EARTHWORK AND RELATED OPERATIONS 120 Excavation and Embankment...

More information

MIAMI BLUFFS COMMUNITY ASSOCIATION LINE ITEM BUDGET (9058)

MIAMI BLUFFS COMMUNITY ASSOCIATION LINE ITEM BUDGET (9058) MIAMI BLUFFS COMMUNITY ASSOCIATION LINE ITEM BUDGET (9058) Contract 2006 Year Dec. YTD 2007 Year Dec. YTD 2008 Annual INCOME: Fee Income: Association Fee (605000) Builder Fee (605890) Prepaid Fees (601350)

More information

RED RIVER DIVERSION FARGO MOORHEAD METRO FLOOD RISK MANAGEMENT PROJECT, FEASIBILITY STUDY, PHASE 4

RED RIVER DIVERSION FARGO MOORHEAD METRO FLOOD RISK MANAGEMENT PROJECT, FEASIBILITY STUDY, PHASE 4 RED RIVER DIVERSION FARGO MOORHEAD METRO FLOOD RISK MANAGEMENT PROJECT, FEASIBILITY STUDY, PHASE 4 APPENDIX G COST ESTIMATES EXHIBIT J RAILROAD BRIDGE QUANTITIES Report for the US Army Corps of Engineers,

More information

Surface Transportation Program (STP)

Surface Transportation Program (STP) Project Name: Project Sponsor: FEDERAL FUNDS PROJECT APPLICATION TRANSPORTATION IMPROVEMENT PROGRAM 2008-2013 SALT LAKE and OGDEN/ LAYTON URBAN AREAS Surface Transportation Program (STP) Urban Surface

More information

ADDENDUM NO. 1. Manchester Boston Regional Airport, City of Manchester, NH

ADDENDUM NO. 1. Manchester Boston Regional Airport, City of Manchester, NH Hoyle, Tanner Project No. 093145 ADDENDUM NO. 1 Manchester Boston Regional Airport, City of Manchester, NH Construct Relocated Roadway Airport Service Rd. Outside Runway Object Free Area (ROFA); Construct

More information

SECTION 13 REPLACEMENT AND CLEANUP 13.01 SCOPE OF WORK

SECTION 13 REPLACEMENT AND CLEANUP 13.01 SCOPE OF WORK 13.01 SCOPE OF WORK Under this item, the Contractor will restore all lawns, trees, gardens, landscape plantings, sidewalks, ramps, trails, fences, commercial signs, water courses and sand, gravel, dirt,

More information

Helen Mercury Mine EE/CA OPINION OF PROBABLE COST

Helen Mercury Mine EE/CA OPINION OF PROBABLE COST G Cost Estimates Helen Mercury Mine EE/CA Alternative 2: Limited Action 3 Minor Road Improvements 4 Clear & Grub diversion channel areas 5 Surveying 6 Cleanup & Demobilization 7 Pull back of material 8

More information

Item No. 432S Portland Cement Concrete Sidewalks. 432S.1 Description

Item No. 432S Portland Cement Concrete Sidewalks. 432S.1 Description Item No. 432S Portland Cement Concrete Sidewalks 432S.1 This item shall govern the construction of Portland cement concrete sidewalks (Standard Detail No. 432S-1), as herein specified, on an approved subgrade

More information

Planning Level Cost Estimation Tool. User s Manual

Planning Level Cost Estimation Tool. User s Manual Planning Level Cost Estimation Tool User s Manual Atlanta Regional Commission Submitted By: User s Manual Table of Contents 1. INTRODUCTION... 1 2. OBJECTIVE... 1 3. FRAMEWORK OF THE TOOL... 2 4. HOW TO

More information

Preliminary Design Report Clay County, Florida Carpet n Drapes Culvert Repair and Rehabilitation July 21, 2006

Preliminary Design Report Clay County, Florida Carpet n Drapes Culvert Repair and Rehabilitation July 21, 2006 Clay County, Florida Carpet n Drapes Culvert Repair and Rehabilitation July 21, 2006 1.0 Background and Repair and Rehabilitation Recommendation Clay County has contracted Camp Dresser & McKee Inc. (CDM)

More information

CITY OF VISTA STANDARD DRAWINGS (PRELIMINARY, FOR REVIEW)

CITY OF VISTA STANDARD DRAWINGS (PRELIMINARY, FOR REVIEW) CITY OF VISTA STANDARD DRAWINGS (PRELIMINARY, FOR REVIEW) January, 2013 THIS SHEET INTENTIONALLY LEFT BLANK TABLE OF CONTENTS DRAINAGE STRUCTURES DRN-01 Corrugated metal pipe drop inlet DNR-02 Storm Drain

More information

MICHIGAN AIRPORT DEVELOPMENT PROGRAM PACKAGE MDOT Office of Aeronautics. Airport Capital Improvement Plan 2014-2018

MICHIGAN AIRPORT DEVELOPMENT PROGRAM PACKAGE MDOT Office of Aeronautics. Airport Capital Improvement Plan 2014-2018 MICHIGAN AIRPORT DEVELOPMENT PROGRAM PACKAGE MDOT Office of Aeronautics Airport Capital Improvement Plan 20142018 Prepared for: West Michigan Regional Airport Holland, Michigan August 2013 Contact: Mr.

More information

BMP-7. A sediment filter or an excavated impounding area around a storm drain drop inlet or curb inlet.

BMP-7. A sediment filter or an excavated impounding area around a storm drain drop inlet or curb inlet. BMP-7 BMP: STORM DRAIN INLET PROTECTION Definition A sediment filter or an excavated impounding area around a storm drain drop inlet or curb inlet. To prevent sediment from entering storm drainage systems

More information

BEST PRACTICES. Smart Transportation is a key concept for the Paoli Roadway Improvement Project.

BEST PRACTICES. Smart Transportation is a key concept for the Paoli Roadway Improvement Project. Smart Transportation Smart Transportation is a key concept for the Paoli Roadway Improvement Project. PennDOT s Smart Transportation Guidebook (2008) outlines a comprehensive approach to transportation

More information

APPENDIX C INLETS. The application and types of storm drainage inlets are presented in detail in this Appendix.

APPENDIX C INLETS. The application and types of storm drainage inlets are presented in detail in this Appendix. Storm Drainage 13-C-1 APPENDIX C INLETS 1.0 Introduction The application and types of storm drainage inlets are presented in detail in this Appendix. 2.0 Inlet Locations Inlets are required at locations

More information

VILLAGE OF LOMBARD CONTRACT DOCUMENT NUMBER ST-09-06 BID PROPOSAL

VILLAGE OF LOMBARD CONTRACT DOCUMENT NUMBER ST-09-06 BID PROPOSAL VILLAGE OF LOMBARD CONTRACT DOCUMENT NUMBER ST-09-06 BID PROPOSAL I/We hereby agree to furnish to the Village of Lombard all necessary materials, equipment, and labor, to complete the North Industrial

More information

TABLE OF CONTENTS. Manhole, Frame, and Cover Installation (includes Drop Manhole) Additional Manhole Depth

TABLE OF CONTENTS. Manhole, Frame, and Cover Installation (includes Drop Manhole) Additional Manhole Depth TABLE OF CONTENTS NO. MP-1 MP-2 MP-3 MP-4 MP-4.01 MP-4.02 MP-4.03 MP-5 MP-5.01 MP-5.02 MP-5.03 MP-5.04 MP-5.05 MP-5.06 MP-5.07 MP-5.08 MP-5.11 MP-5.12 MP-5.13 MP-5.14 MP-5.15 MP-5.16 MP-5.18 MP-5.19 MP-5.20

More information

in Marina Del Rey Prepared by: County of Los Angeles Department of Public Works

in Marina Del Rey Prepared by: County of Los Angeles Department of Public Works Planned Public Works Projects in Marina Del Rey Prepared by: County of Los Angeles Department of Public Works Planned Projects in Marina Del Rey Waterline Projects Phase II Phase III Roadway Projects Admiralty

More information

Town of Elkton & Cecil Soil Conservation District Checklist for Joint Agency Review Stormwater Management / Erosion and Sediment Control

Town of Elkton & Cecil Soil Conservation District Checklist for Joint Agency Review Stormwater Management / Erosion and Sediment Control Town of Elkton & Cecil Soil Conservation District Checklist for Joint Agency Review Stormwater Management / Erosion and Sediment Control Project Name: Tax Map Parcel: Acreage: Plat: ADC Map & Grid Engineering

More information

Update on Previous Related Transportation Enhancement Grants

Update on Previous Related Transportation Enhancement Grants ROUND 16 ROUND 16 Update on Previous Related Transportation Enhancement Grants Pima County and City of Tucson staff are implementing the Pima County-Tucson Safe Routes to Schools Pilot Program. This program

More information

FDOT DBE CERTIFICATION NAICS CODE GUIDE WITH CAP SIZES

FDOT DBE CERTIFICATION NAICS CODE GUIDE WITH CAP SIZES NAICS CODE Highway, Street, and Bridge Construction SIZE CAP ($ MIL) 237310 Asphalt Roadway (includes 300, 320, 327, 330, 334, 336, 337, 338) Application of prime and tack coats, leveling surfaces and

More information

Facility Summary. Facility Condition Summary. Seattle School District David T. Denny International Infrastructure. Facility Components

Facility Summary. Facility Condition Summary. Seattle School District David T. Denny International Infrastructure. Facility Components Infrastructure Facility Condition Summary Weighted Avg Condition Score Facility Components Systems Surveyor/ Date Done Comments G Sitework.9 Site Improvements Parking Pedestrian Paving Site Development

More information

2006-2008 MHD BRIDGE SECTION WEIGHTED AVERAGE UNIT PRICES GUIDELINES FOR THE USE OF THE WEIGHTED AVERAGE UNIT PRICE TABULATION SHEETS

2006-2008 MHD BRIDGE SECTION WEIGHTED AVERAGE UNIT PRICES GUIDELINES FOR THE USE OF THE WEIGHTED AVERAGE UNIT PRICE TABULATION SHEETS 2006-2008 MHD BRIDGE SECTION WEIGHTED AVERAGE UNIT PRICES GUIDELINES FOR THE USE OF THE WEIGHTED AVERAGE UNIT PRICE TABULATION SHEETS GENERAL 10/16/2008 The listed average unit prices are based on the

More information

PROPERTY EVALUATION AND RESERVE FUND STUDY

PROPERTY EVALUATION AND RESERVE FUND STUDY PROPERTY EVALUATION AND RESERVE FUND STUDY COMPLEX NORTH & WEST AVENUES LAS VEGAS, NV Prepared for: HOMEOWNER S ASSOCIATION Prepared by: CRITERIUM ENGINEERS 22 Monument Square Portland, ME 04101 CONTENTS

More information

MONETARY GUARANTY PROCEDURE PACKAGE FREDERICK COUNTY, VIRGINIA

MONETARY GUARANTY PROCEDURE PACKAGE FREDERICK COUNTY, VIRGINIA MONETARY GUARANTY PROCEDURE PACKAGE FREDERICK COUNTY, VIRGINIA Department of Planning and Development 107 North Kent Street, Suite 202 Winchester, Virginia 22601 Phone: (540) 665-5651 Fax: (540) 665-6395

More information

Exhibit A Scope of Work

Exhibit A Scope of Work Exhibit A Scope of Work The agreement for S.P. 3116-142 (T.H. 169-Cross Range Expressway) includes final design plans for a 1.55 mile length of a 2 lane to 4 lane expansion project located 0.66 miles SW

More information

Chapter 3 SENSITIVE AREAS AND VEGETATED CORRIDORS

Chapter 3 SENSITIVE AREAS AND VEGETATED CORRIDORS Chapter 3 3.01 General Provisions 3.01.1 Introduction 3.01.2 Application and Interpretation of Chapter 3.01.3 Unbuildable Lots 3.01.4 Other Permits 3.01.5 Prohibited Activities 3.02 Service Provider Letter

More information

SECTION 02221 SELECTIVE DEMOLITION

SECTION 02221 SELECTIVE DEMOLITION SECTION 02221 PART 1 -GENERAL 1.01 DESCRIPTION This section includes all material, labor, machinery and supervision required to demolish and remove the following items where applicable and as noted on

More information

CID STREET INFRASTRUCTURE ASSESSMENT

CID STREET INFRASTRUCTURE ASSESSMENT ABSTRACT An evaluation of the street infrastructure in Foxberry Estates Phase 1, including pavement condition, verification of construction techniques, and subgrade quality. Recommendations and costs for

More information

CITY OF SAN ANTONIO. Issued By: Transportation and Capital Improvements Date Issued: February 10, 2016 ID NO.: 23-01472-05-03

CITY OF SAN ANTONIO. Issued By: Transportation and Capital Improvements Date Issued: February 10, 2016 ID NO.: 23-01472-05-03 CITY OF SAN ANTONIO Issued By: Transportation and Capital Improvements Date Issued: February 10, 2016 ID NO.: 23-01472-05-03 (010) FORMAL INVITATION FOR BIDS (IFB) to CONTRACT 2016-2017 TASK ORDER CONTRACT

More information

ADVERTISEMENT FOR BIDDERS

ADVERTISEMENT FOR BIDDERS ADVERTISEMENT FOR BIDDERS Sealed Bids will be received by the City of Lookout Mountain, Georgia, 1214 Lulu Lake Road, Lookout Mountain, Georgia 30103, Attention: Brad Haven, City Manager until: for the

More information

Developing Critical Path Method Scheduling (CPM)

Developing Critical Path Method Scheduling (CPM) Developing Critical Path Method Scheduling (CPM) Pretest 1. An activity which is on critical path has a planned duration of 5 days. What is the total float for the activity? a. 0 b. 1 c. 2 d. 3 Pretest

More information

SUMMARY OF PUBLIC WORK STANDARD SPECIFICATION REVISIONS 2016

SUMMARY OF PUBLIC WORK STANDARD SPECIFICATION REVISIONS 2016 SUMMARY OF PUBLIC WORK STANDARD SPECIFICATION REVISIONS 2016 102.5 Bid Deposits The City of Madison bid deposit form is required for all bids unless a Biennial Bid Bond is on file or check deposit is used.

More information

UNIVERSITY OF MISSISSIPPI FIXED ASSET CAPITALIZATION POLICY

UNIVERSITY OF MISSISSIPPI FIXED ASSET CAPITALIZATION POLICY UNIVERSITY OF MISSISSIPPI FIXED ASSET CAPITALIZATION POLICY The term capitalized fixed assets includes land, improvements to land, easements, buildings, building improvements, vehicles, machinery, furniture,

More information

Bond Release Process for New Subdivision Developments in Fairfax County

Bond Release Process for New Subdivision Developments in Fairfax County Bond Release Process for New Subdivision Developments in Fairfax County An Overview for Homeowners Associations A Fairfax County, Va., publication April 2009 For more information or to request this document

More information

Index. protection. excavated drop inlet protection (Temporary) 6.50.1 6.51.1. Block and gravel inlet Protection (Temporary) 6.52.1

Index. protection. excavated drop inlet protection (Temporary) 6.50.1 6.51.1. Block and gravel inlet Protection (Temporary) 6.52.1 6 Index inlet protection excavated drop inlet protection (Temporary) 6.50.1 HARDWARE CLOTH AND GRAVEL INLET PROTECTION Block and gravel inlet Protection (Temporary) sod drop inlet protection ROCK DOUGHNUT

More information

TOWN OF SURFSIDE UTILITY UPGRADE PROJECT Project Completion

TOWN OF SURFSIDE UTILITY UPGRADE PROJECT Project Completion TOWN OF SURFSIDE UTILITY UPGRADE PROJECT Project Completion Project Overview Sanitary Sewer System 2 Town of Surfside Project Overview Potable Water System 3 Town of Surfside Project Overview Storm Water

More information

CONSTRUCTION STORMWATER POLLUTION PREVENTION PLAN TEMPLATE

CONSTRUCTION STORMWATER POLLUTION PREVENTION PLAN TEMPLATE CONSTRUCTION STORMWATER POLLUTION PREVENTION PLAN TEMPLATE The following template may be used as a general guide for development of a Stormwater Pollution Prevention Plan (SWPPP) for construction activities.

More information

How To Build A Road In A Townhouse

How To Build A Road In A Townhouse FDOT DBE CERTIFICATION SPECIALTY/ SHEET WITH CAP SIZES Highway, Street, and Bridge Construction SIZE CAP ($ MIL) 237310 Asphalt Roadway $ 22.41 Application of prime and tack coats, leveling surfaces and

More information

1.0 INDEX TO SHEETS URGENT STORM DAMAGE REPAIR AVON PARK AIR FORCE RANGE LOCATION MAP LEGEND LOCATION MAP

1.0 INDEX TO SHEETS URGENT STORM DAMAGE REPAIR AVON PARK AIR FORCE RANGE LOCATION MAP LEGEND LOCATION MAP 5 INDEX TO SHEETS. NOTES AND TYPICAL SECTIONS. H. R. SMITH RD.CULVERT.3 0/5 END BARRIER ACCESS ROAD REPAIR. KISSIMMEE RD. AT MORGAN HOLE CR. ROAD REPAIR.5 RANGE INFRASTRUCTURE REPAIR N 0 000' 3 0,000'

More information

SOLD. Lot 1. 1 Mile: Population: 10,200 Median HH Income: $33,100. 3 Mile: Population: 80,200 Median HH Income: $34,900

SOLD. Lot 1. 1 Mile: Population: 10,200 Median HH Income: $33,100. 3 Mile: Population: 80,200 Median HH Income: $34,900 Walmart Outparcels For Sale College Station, TX Store # 1150 1815 Brothers Blvd FM 2818 W SOLD Texas Ave S/ Hwy 6 Longmire Dr Brothers Blvd Lot 1 For more information about this site, contact: Lot 1: ±2.41

More information

BUSINESS DEVELOPMENT INITIATIVE SMALL BUSINESS PROGRAM GUIDANCE FOR RESERVING CONTRACTS

BUSINESS DEVELOPMENT INITIATIVE SMALL BUSINESS PROGRAM GUIDANCE FOR RESERVING CONTRACTS Construction/Maintenance Contracts and Design/Build Low Bid Contracts 1. Districts are responsible for reviewing their work program and identifying contracts that are good candidates for the Business Development

More information

Herbicide Application. Irrigation System (Only) Sanitary System Testing & Inspections

Herbicide Application. Irrigation System (Only) Sanitary System Testing & Inspections NAICS Code Work Description Work Item 115310 - Support Activities for Forestry 221310 Water Supply and Irrigation Systems 221320 - Sewage Treatment Facilities 236118 Residential Remodelers 236220 Commercial

More information

MTA UNIVERSAL STATION PEDESTRIAN BRIDGE Los Angeles, CA. Project Manual and Specification 100% PE SUBMITTAL TABLE OF CONTENTS

MTA UNIVERSAL STATION PEDESTRIAN BRIDGE Los Angeles, CA. Project Manual and Specification 100% PE SUBMITTAL TABLE OF CONTENTS Los Angeles, CA Project Manual and Specification DIVISION 1 GENERAL CONDITIONS 01 01 10 STATEMENT OF WORK 01 11 00 SUMMARY OF THE WORK 01 14 05 METRO (OWNER) - DIRECTED STOPPAGES 01 20 00 PRICE AND PAYMENT

More information

CD i -STREETS- Detail #

CD i -STREETS- Detail # -STREETS- Detail # 3000 Vertical Curb, Gutter and Sidewalk 3010 Low-Profile Curb, Gutter and Sidewalk 3020 Rolled Curb, Gutter and Sidewalk 3030 Separated Sidewalk, Curb & Gutter 3040 Sidewalk Staged Construction

More information

Summary Form. Partner Information. Project Information. Primary Contact Name: David Cosgrove Phone: 303-823-8250 Email: davec@townoflyons.

Summary Form. Partner Information. Project Information. Primary Contact Name: David Cosgrove Phone: 303-823-8250 Email: davec@townoflyons. Summary Form Applicant Information Applicant Name: Town of Lyons Department of Parks, Recreation and Cultural Events Mailing Address: P.O. Box 49, Lyons CO 80540 Contact Name: David Cosgrove Telephone:

More information

City of Shelbyville Site Inspection Checklist

City of Shelbyville Site Inspection Checklist City of Shelbyville Site Inspection Checklist General Information Project Name: KYR10 Permit Number: Date: Project Location: Contractor: Conractor Representative: Inspector's Name: Title: Signature : Weather

More information

The Bond Release Process for New Subdivision Developments: An Overview for Homeowners Associations DRAFT 6-4-08. Revised 9-25-08

The Bond Release Process for New Subdivision Developments: An Overview for Homeowners Associations DRAFT 6-4-08. Revised 9-25-08 The Bond Release Process for New Subdivision Developments: An Overview for Homeowners Associations DRAFT 6-4-08. Revised 9-25-08 Fairfax County requires developers to post a performance bond if they are

More information

Preliminary Plan Application and Checklist

Preliminary Plan Application and Checklist ALL APPLICATIONS ARE DUE AT 12:00 NOON ON THE FILING DATE Office Use Only PRELIMINARY / REVISED PRELIMINARY PLAN $300.00 Fee Paid: $ Date Paid: ALL FIELDS HIGHLIGHTED IN RED ARE REQUIRED FIELDS Case No.:

More information

Data Center Due Diligence List

Data Center Due Diligence List Data Center Due Diligence List Name and address of site facility Date constructed Building owner/date purchased by current owner Name of previous owner Adjacent Property Descriptions North South East West

More information

Moving Ruston Forward. City of Ruston Infrastructure Maintenance and Improvements

Moving Ruston Forward. City of Ruston Infrastructure Maintenance and Improvements Moving Ruston Forward City of Ruston Infrastructure Maintenance and Improvements MLK Extension Project will be done in conjunction with proposed water and sewer improvements Connect Martin Luther King

More information

STORMWATER MANAGEMENT CHECKLIST

STORMWATER MANAGEMENT CHECKLIST STORMWATER MANAGEMENT CHECKLIST *This checklist must be completed and part of the Land Disturbing Permit submittal for review if the acreage disturbed is one (1) acre or more: I. SUPPORTING DATA Narrative

More information

TREE # 3 CRITICAL ROOT ZONE = 4,536 SF AREA IMPACTED = 50 SF % IMPACTED = 1 % 87.2 80.5 35' BL VALVE IN BOX POP-UP EMITTER 74.7 CLEAN OUT BACKWATER

TREE # 3 CRITICAL ROOT ZONE = 4,536 SF AREA IMPACTED = 50 SF % IMPACTED = 1 % 87.2 80.5 35' BL VALVE IN BOX POP-UP EMITTER 74.7 CLEAN OUT BACKWATER NOTES: 1. THE INSTALLATION OF EROSION AND SEDIMENTATION CONTROL MEASURES AND PRACTICES SHALL OCCUR PRIOR TO OR CONCURRENT WITH LAND-DISTURBING ACTIVITIES. 2. EROSION AND SEDIMENTATION CONTROL MEASURES

More information

DRAFT MAINTAINING HOUSTON S STREETS REPAIR, REHABILITATION, RECONSTRUCTION. Using the Full Range of Tools for a Challenging Job

DRAFT MAINTAINING HOUSTON S STREETS REPAIR, REHABILITATION, RECONSTRUCTION. Using the Full Range of Tools for a Challenging Job MAINTAINING HOUSTON S STREETS REPAIR, REHABILITATION, RECONSTRUCTION Using the Full Range of Tools for a Challenging Job Report To: TTI Committee May 13, 2014 1 Pavement Management - Suggested Treatments

More information

Storm Drain Inlet Protection - IP

Storm Drain Inlet Protection - IP Storm Drain Inlet Protection - IP DEFINITION A temporary protective device formed around a storm drain drop inlet to trap sediment. PURPOSE To prevent sediment from entering storm drainage systems, prior

More information

SITE-SPECIFIC BEST MANAGEMENT PRACTICES (SSBMP) PLAN/STORM WATER POLLUTION PREVENTION PLAN (SWPPP) REVIEW CHECKLIST

SITE-SPECIFIC BEST MANAGEMENT PRACTICES (SSBMP) PLAN/STORM WATER POLLUTION PREVENTION PLAN (SWPPP) REVIEW CHECKLIST This checklist may be used by applicants for encroachment permits, and contractors in development of Site Specific Best Management Practice (SSBMP) Plans or Storm Water Pollution Prevention Plans (SWPPP)

More information

Construction Site Inspection Checklist for OHC000004 By making use of some simple Best Management Practices (BMPs) a construction site operator can

Construction Site Inspection Checklist for OHC000004 By making use of some simple Best Management Practices (BMPs) a construction site operator can Construction Site Inspection Checklist for OHC000004 By making use of some simple Best Management Practices (BMPs) a construction site operator can do his or her share to protect Ohio's water resources

More information

Waterleaf ARB Application

Waterleaf ARB Application To: Waterleaf ARB Application Waterleaf Architectural Review Board c/o Property Management Systems, Inc. P.O. Box 1987 Yulee, FL 32097-1987 From: Name: Address: City, State, Zip: Phone: Fax: Lot Number:

More information

The fees listed below are stand-alone fees. Additional Developemnt Review or Stormwater fees may apply. 1.0. Fee Activity

The fees listed below are stand-alone fees. Additional Developemnt Review or Stormwater fees may apply. 1.0. Fee Activity MINOR & MISCELLANEOUS PERMITS The fees listed below are stand-alone fees. Additional Developemnt Review or Stormwater fees may apply. 1.0 Fee Activity Fee Description Fee 50% REDUCED FEES FOR SINGLE FAMILY

More information

Building, Plumbing, Electrical and Residential Water and Sewer Inspection Requirements

Building, Plumbing, Electrical and Residential Water and Sewer Inspection Requirements Building, Plumbing, Electrical and Residential Water and Sewer Inspection Requirements Charles County Government Planning and Growth Management P.O. Box 2150, La Plata, MD 20646 (301) 645-0692 Schedule

More information