Legacy Trail Extension Feasibility Study. Preliminary Cost Estimate
|
|
|
- Osborne McCoy
- 10 years ago
- Views:
Transcription
1 Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 25,800' + Separated Trail length ~ 13,700' = Total Length ~ 39,500' or 7.5 miles) Clear and grub AC $30, $1,500,000 Clear all nuisance plants full width Cut and fill (single trail) CY $10 20,000 $200,000 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $10 10,600 $106,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $150 4,400 $660,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $150 2,670 $400,500 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $22 33,600 $739,200 6" bank run shell Base (dbl. trail) SY $22 33,500 $737,000 6" bank run shell Subbase (single trail) SY $11 5,000 $55,000 Build base as needed in poor soils Subbase (dbl. trail) SY $11 10,000 $110,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $20 5,000 $100,000 Chain link type as needed Ped/bike railing LF $70 1,500 $105,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $25, $900,000 Border trees and bushes as needed Sod, seeding SY $3 130,000 $390,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $60,000 1 $60,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $6, $192,000 drainage pipe and structures Pond/swale construction EA $30,000 6 $180,000 pond/swale construction SubTotal $7,024,200
2 Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $1,125,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $375,000 Est. 0.5 contam. sites per mile Surface water remediation MI $100, $375,000 Est. 0.5 sites per mile Steel and tie/timber credit MI -$50, $375,000 Est. 0.5 contam. sites per mile SubTotal $1,725,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10, $130,000 all road intersections SubTotal $1,095,500 Shelters Approach paths EA $2,000 8 $16,000 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $6,000 8 $48,000 foundation cost Landscaping EA $5,000 8 $40,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work EA $8,000 8 $64,000 general site prep. SubTotal $44,000 $352,000
3 Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges Main A LS $525,000 1 $525,000 Prefab. Steel Truss bridge with foundations Main B LS $325,000 1 $325,000 Prefab. Steel Truss bridge with foundations SubTotal $850,000 Utilities Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,270,000 Mobilization 3.0% $380,000 MOT 2.0% $250,000 Geotech and misc. Testing 2.0% $250,000 Additional items 4.0% $510,000 Contingency 10.0% $1,270,000 Asbuilts, close-out 2.0% $250,000 SubTotal $4,180,000 Project Cost Estimate Total $16,846,700
4 ( This Page Blank.)
5 Rails-with-Trails Option Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 17,800' + Separated Trail length ~ 21,700' = Total Length ~ 39,500' or 7.5 miles) Clearing and grubbing AC $38, $1,900,000 Clear all nuisance plants full width Cut and fill (single trail) CY $12 15,800 $189,600 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $13 22,000 $286,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $180 3,050 $549,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $180 4,240 $763,200 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $27 33,600 $907,200 6" bank run shell Base (dbl. trail) SY $28 48,200 $1,349,600 6" bank run shell Subbase (single trail) SY $14 15,800 $221,200 Build base as needed in poor soils Subbase (dbl. trail) SY $14 24,000 $336,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $24 5,000 $120,000 Chain link type as needed Ped/bike railing LF $84 1,500 $126,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $30, $1,080,000 Border trees and bushes as needed Sod, seeding SY $4 130,000 $455,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $75,000 1 $75,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $7, $240,000 drainage pipe and structures Pond/swale construction EA $36,000 6 $216,000 pond/swale construction SubTotal $9,403,300
6 Rails-with-Trails Option Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $75,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $750,000 Est. 1 contam. Location per mile Surface water remediation MI $100, $750,000 Est. 1 Location per mile Steel and tie/timber credit MI -$50, $25,000 Est. 1 contam. Location per mile SubTotal $1,775,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10,000 0 $0 all road intersections SubTotal $965,500 Shelters Approach paths EA $2,400 8 $19,200 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $7,200 8 $57,600 foundation cost Landscaping EA $6,000 8 $48,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work, benches, trash can, etc. EA $8,000 8 $64,000 general site prep. SubTotal $46,600 $372,800
7 Rails-with-Trails Option Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges (2) over Philippi Creek Main A LS $625,000 1 $625,000 Prefab. Steel Truss bridge with foundations Main B LS $390,000 1 $390,000 Prefab. Steel Truss bridge with foundations SubTotal $1,015,000 Utilities at Trail Heads and Shelters w/ Water Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,520,000 Mobilization 3.0% $450,000 MOT 3.0% $450,000 Geotech and misc. Testing 2.0% $300,000 Additional items 4.0% $610,000 Contingency 10.0% $1,520,000 Asbuilts, close-out 2.0% $300,000 SubTotal $5,150,000 Project Cost Estimate Total $20,301,600
8 Cost Unit Descriptions UNIT AC CY EA LF LS MI NM SF SY TN DESCRIPTION Acre Cubic Yard Each Linear Foot Lump Sum Mile Net Mile Square Foot Square Yard Ton
9 Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 25,800' + Separated Trail length ~ 13,700' = Total Length ~ 39,500' or 7.5 miles) Clear and grub AC $30, $1,500,000 Clear all nuisance plants full width Cut and fill (single trail) CY $10 20,000 $200,000 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $10 10,600 $106,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $150 4,400 $660,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $150 2,670 $400,500 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $22 33,600 $739,200 6" bank run shell Base (dbl. trail) SY $22 33,500 $737,000 6" bank run shell Subbase (single trail) SY $11 5,000 $55,000 Build base as needed in poor soils Subbase (dbl. trail) SY $11 10,000 $110,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $20 5,000 $100,000 Chain link type as needed Ped/bike railing LF $70 1,500 $105,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $25, $900,000 Border trees and bushes as needed Sod, seeding SY $3 130,000 $390,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $60,000 1 $60,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $6, $192,000 drainage pipe and structures Pond/swale construction EA $30,000 6 $180,000 pond/swale construction SubTotal $7,024,200
10 Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $1,125,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $375,000 Est. 0.5 contam. sites per mile Surface water remediation MI $100, $375,000 Est. 0.5 sites per mile Steel and tie/timber credit MI -$50, $375,000 Est. 0.5 contam. sites per mile SubTotal $1,725,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10, $130,000 all road intersections SubTotal $1,095,500 Shelters Approach paths EA $2,000 8 $16,000 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $6,000 8 $48,000 foundation cost Landscaping EA $5,000 8 $40,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work EA $8,000 8 $64,000 general site prep. SubTotal $44,000 $352,000
11 Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges Main A LS $525,000 1 $525,000 Prefab. Steel Truss bridge with foundations Main B LS $325,000 1 $325,000 Prefab. Steel Truss bridge with foundations SubTotal $850,000 Utilities Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,270,000 Mobilization 3.0% $380,000 MOT 2.0% $250,000 Geotech and misc. Testing 2.0% $250,000 Additional items 4.0% $510,000 Contingency 10.0% $1,270,000 Asbuilts, close-out 2.0% $250,000 SubTotal $4,180,000 Project Cost Estimate Total $16,846,700
12 ( This Page Blank.)
13 Rails-with-Trails Option Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 17,800' + Separated Trail length ~ 21,700' = Total Length ~ 39,500' or 7.5 miles) Clearing and grubbing AC $38, $1,900,000 Clear all nuisance plants full width Cut and fill (single trail) CY $12 15,800 $189,600 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $13 22,000 $286,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $180 3,050 $549,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $180 4,240 $763,200 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $27 33,600 $907,200 6" bank run shell Base (dbl. trail) SY $28 48,200 $1,349,600 6" bank run shell Subbase (single trail) SY $14 15,800 $221,200 Build base as needed in poor soils Subbase (dbl. trail) SY $14 24,000 $336,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $24 5,000 $120,000 Chain link type as needed Ped/bike railing LF $84 1,500 $126,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $30, $1,080,000 Border trees and bushes as needed Sod, seeding SY $4 130,000 $455,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $75,000 1 $75,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $7, $240,000 drainage pipe and structures Pond/swale construction EA $36,000 6 $216,000 pond/swale construction SubTotal $9,403,300
14 Rails-with-Trails Option Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $75,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $750,000 Est. 1 contam. Location per mile Surface water remediation MI $100, $750,000 Est. 1 Location per mile Steel and tie/timber credit MI -$50, $25,000 Est. 1 contam. Location per mile SubTotal $1,775,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10,000 0 $0 all road intersections SubTotal $965,500 Shelters Approach paths EA $2,400 8 $19,200 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $7,200 8 $57,600 foundation cost Landscaping EA $6,000 8 $48,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work, benches, trash can, etc. EA $8,000 8 $64,000 general site prep. SubTotal $46,600 $372,800
15 Rails-with-Trails Option Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges (2) over Philippi Creek Main A LS $625,000 1 $625,000 Prefab. Steel Truss bridge with foundations Main B LS $390,000 1 $390,000 Prefab. Steel Truss bridge with foundations SubTotal $1,015,000 Utilities at Trail Heads and Shelters w/ Water Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,520,000 Mobilization 3.0% $450,000 MOT 3.0% $450,000 Geotech and misc. Testing 2.0% $300,000 Additional items 4.0% $610,000 Contingency 10.0% $1,520,000 Asbuilts, close-out 2.0% $300,000 SubTotal $5,150,000 Project Cost Estimate Total $20,301,600
16 Cost Unit Descriptions UNIT AC CY EA LF LS MI NM SF SY TN DESCRIPTION Acre Cubic Yard Each Linear Foot Lump Sum Mile Net Mile Square Foot Square Yard Ton
17 Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 25,800' + Separated Trail length ~ 13,700' = Total Length ~ 39,500' or 7.5 miles) Clear and grub AC $30, $1,500,000 Clear all nuisance plants full width Cut and fill (single trail) CY $10 20,000 $200,000 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $10 10,600 $106,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $150 4,400 $660,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $150 2,670 $400,500 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $22 33,600 $739,200 6" bank run shell Base (dbl. trail) SY $22 33,500 $737,000 6" bank run shell Subbase (single trail) SY $11 5,000 $55,000 Build base as needed in poor soils Subbase (dbl. trail) SY $11 10,000 $110,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $20 5,000 $100,000 Chain link type as needed Ped/bike railing LF $70 1,500 $105,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $25, $900,000 Border trees and bushes as needed Sod, seeding SY $3 130,000 $390,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $60,000 1 $60,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $6, $192,000 drainage pipe and structures Pond/swale construction EA $30,000 6 $180,000 pond/swale construction SubTotal $7,024,200
18 Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $1,125,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $375,000 Est. 0.5 contam. sites per mile Surface water remediation MI $100, $375,000 Est. 0.5 sites per mile Steel and tie/timber credit MI -$50, $375,000 Est. 0.5 contam. sites per mile SubTotal $1,725,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10, $130,000 all road intersections SubTotal $1,095,500 Shelters Approach paths EA $2,000 8 $16,000 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $6,000 8 $48,000 foundation cost Landscaping EA $5,000 8 $40,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work EA $8,000 8 $64,000 general site prep. SubTotal $44,000 $352,000
19 Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges Main A LS $525,000 1 $525,000 Prefab. Steel Truss bridge with foundations Main B LS $325,000 1 $325,000 Prefab. Steel Truss bridge with foundations SubTotal $850,000 Utilities Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,270,000 Mobilization 3.0% $380,000 MOT 2.0% $250,000 Geotech and misc. Testing 2.0% $250,000 Additional items 4.0% $510,000 Contingency 10.0% $1,270,000 Asbuilts, close-out 2.0% $250,000 SubTotal $4,180,000 Project Cost Estimate Total $16,846,700
20 ( This Page Blank.)
21 Rails-with-Trails Option Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 17,800' + Separated Trail length ~ 21,700' = Total Length ~ 39,500' or 7.5 miles) Clearing and grubbing AC $38, $1,900,000 Clear all nuisance plants full width Cut and fill (single trail) CY $12 15,800 $189,600 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $13 22,000 $286,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $180 3,050 $549,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $180 4,240 $763,200 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $27 33,600 $907,200 6" bank run shell Base (dbl. trail) SY $28 48,200 $1,349,600 6" bank run shell Subbase (single trail) SY $14 15,800 $221,200 Build base as needed in poor soils Subbase (dbl. trail) SY $14 24,000 $336,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $24 5,000 $120,000 Chain link type as needed Ped/bike railing LF $84 1,500 $126,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $30, $1,080,000 Border trees and bushes as needed Sod, seeding SY $4 130,000 $455,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $75,000 1 $75,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $7, $240,000 drainage pipe and structures Pond/swale construction EA $36,000 6 $216,000 pond/swale construction SubTotal $9,403,300
22 Rails-with-Trails Option Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $75,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $750,000 Est. 1 contam. Location per mile Surface water remediation MI $100, $750,000 Est. 1 Location per mile Steel and tie/timber credit MI -$50, $25,000 Est. 1 contam. Location per mile SubTotal $1,775,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10,000 0 $0 all road intersections SubTotal $965,500 Shelters Approach paths EA $2,400 8 $19,200 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $7,200 8 $57,600 foundation cost Landscaping EA $6,000 8 $48,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work, benches, trash can, etc. EA $8,000 8 $64,000 general site prep. SubTotal $46,600 $372,800
23 Rails-with-Trails Option Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges (2) over Philippi Creek Main A LS $625,000 1 $625,000 Prefab. Steel Truss bridge with foundations Main B LS $390,000 1 $390,000 Prefab. Steel Truss bridge with foundations SubTotal $1,015,000 Utilities at Trail Heads and Shelters w/ Water Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,520,000 Mobilization 3.0% $450,000 MOT 3.0% $450,000 Geotech and misc. Testing 2.0% $300,000 Additional items 4.0% $610,000 Contingency 10.0% $1,520,000 Asbuilts, close-out 2.0% $300,000 SubTotal $5,150,000 Project Cost Estimate Total $20,301,600
24 Cost Unit Descriptions UNIT AC CY EA LF LS MI NM SF SY TN DESCRIPTION Acre Cubic Yard Each Linear Foot Lump Sum Mile Net Mile Square Foot Square Yard Ton
25 Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 25,800' + Separated Trail length ~ 13,700' = Total Length ~ 39,500' or 7.5 miles) Clear and grub AC $30, $1,500,000 Clear all nuisance plants full width Cut and fill (single trail) CY $10 20,000 $200,000 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $10 10,600 $106,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $150 4,400 $660,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $150 2,670 $400,500 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $22 33,600 $739,200 6" bank run shell Base (dbl. trail) SY $22 33,500 $737,000 6" bank run shell Subbase (single trail) SY $11 5,000 $55,000 Build base as needed in poor soils Subbase (dbl. trail) SY $11 10,000 $110,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $20 5,000 $100,000 Chain link type as needed Ped/bike railing LF $70 1,500 $105,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $25, $900,000 Border trees and bushes as needed Sod, seeding SY $3 130,000 $390,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $60,000 1 $60,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $6, $192,000 drainage pipe and structures Pond/swale construction EA $30,000 6 $180,000 pond/swale construction SubTotal $7,024,200
26 Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $1,125,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $375,000 Est. 0.5 contam. sites per mile Surface water remediation MI $100, $375,000 Est. 0.5 sites per mile Steel and tie/timber credit MI -$50, $375,000 Est. 0.5 contam. sites per mile SubTotal $1,725,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10, $130,000 all road intersections SubTotal $1,095,500 Shelters Approach paths EA $2,000 8 $16,000 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $6,000 8 $48,000 foundation cost Landscaping EA $5,000 8 $40,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work EA $8,000 8 $64,000 general site prep. SubTotal $44,000 $352,000
27 Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges Main A LS $525,000 1 $525,000 Prefab. Steel Truss bridge with foundations Main B LS $325,000 1 $325,000 Prefab. Steel Truss bridge with foundations SubTotal $850,000 Utilities Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,270,000 Mobilization 3.0% $380,000 MOT 2.0% $250,000 Geotech and misc. Testing 2.0% $250,000 Additional items 4.0% $510,000 Contingency 10.0% $1,270,000 Asbuilts, close-out 2.0% $250,000 SubTotal $4,180,000 Project Cost Estimate Total $16,846,700
28 ( This Page Blank.)
29 Rails-with-Trails Option Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 17,800' + Separated Trail length ~ 21,700' = Total Length ~ 39,500' or 7.5 miles) Clearing and grubbing AC $38, $1,900,000 Clear all nuisance plants full width Cut and fill (single trail) CY $12 15,800 $189,600 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $13 22,000 $286,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $180 3,050 $549,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $180 4,240 $763,200 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $27 33,600 $907,200 6" bank run shell Base (dbl. trail) SY $28 48,200 $1,349,600 6" bank run shell Subbase (single trail) SY $14 15,800 $221,200 Build base as needed in poor soils Subbase (dbl. trail) SY $14 24,000 $336,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $24 5,000 $120,000 Chain link type as needed Ped/bike railing LF $84 1,500 $126,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $30, $1,080,000 Border trees and bushes as needed Sod, seeding SY $4 130,000 $455,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $75,000 1 $75,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $7, $240,000 drainage pipe and structures Pond/swale construction EA $36,000 6 $216,000 pond/swale construction SubTotal $9,403,300
30 Rails-with-Trails Option Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $75,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $750,000 Est. 1 contam. Location per mile Surface water remediation MI $100, $750,000 Est. 1 Location per mile Steel and tie/timber credit MI -$50, $25,000 Est. 1 contam. Location per mile SubTotal $1,775,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10,000 0 $0 all road intersections SubTotal $965,500 Shelters Approach paths EA $2,400 8 $19,200 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $7,200 8 $57,600 foundation cost Landscaping EA $6,000 8 $48,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work, benches, trash can, etc. EA $8,000 8 $64,000 general site prep. SubTotal $46,600 $372,800
31 Rails-with-Trails Option Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges (2) over Philippi Creek Main A LS $625,000 1 $625,000 Prefab. Steel Truss bridge with foundations Main B LS $390,000 1 $390,000 Prefab. Steel Truss bridge with foundations SubTotal $1,015,000 Utilities at Trail Heads and Shelters w/ Water Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,520,000 Mobilization 3.0% $450,000 MOT 3.0% $450,000 Geotech and misc. Testing 2.0% $300,000 Additional items 4.0% $610,000 Contingency 10.0% $1,520,000 Asbuilts, close-out 2.0% $300,000 SubTotal $5,150,000 Project Cost Estimate Total $20,301,600
32 Cost Unit Descriptions UNIT AC CY EA LF LS MI NM SF SY TN DESCRIPTION Acre Cubic Yard Each Linear Foot Lump Sum Mile Net Mile Square Foot Square Yard Ton
33 Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 25,800' + Separated Trail length ~ 13,700' = Total Length ~ 39,500' or 7.5 miles) Clear and grub AC $30, $1,500,000 Clear all nuisance plants full width Cut and fill (single trail) CY $10 20,000 $200,000 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $10 10,600 $106,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $150 4,400 $660,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $150 2,670 $400,500 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $22 33,600 $739,200 6" bank run shell Base (dbl. trail) SY $22 33,500 $737,000 6" bank run shell Subbase (single trail) SY $11 5,000 $55,000 Build base as needed in poor soils Subbase (dbl. trail) SY $11 10,000 $110,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $20 5,000 $100,000 Chain link type as needed Ped/bike railing LF $70 1,500 $105,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $25, $900,000 Border trees and bushes as needed Sod, seeding SY $3 130,000 $390,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $60,000 1 $60,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $6, $192,000 drainage pipe and structures Pond/swale construction EA $30,000 6 $180,000 pond/swale construction SubTotal $7,024,200
34 Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $1,125,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $375,000 Est. 0.5 contam. sites per mile Surface water remediation MI $100, $375,000 Est. 0.5 sites per mile Steel and tie/timber credit MI -$50, $375,000 Est. 0.5 contam. sites per mile SubTotal $1,725,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10, $130,000 all road intersections SubTotal $1,095,500 Shelters Approach paths EA $2,000 8 $16,000 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $6,000 8 $48,000 foundation cost Landscaping EA $5,000 8 $40,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work EA $8,000 8 $64,000 general site prep. SubTotal $44,000 $352,000
35 Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges Main A LS $525,000 1 $525,000 Prefab. Steel Truss bridge with foundations Main B LS $325,000 1 $325,000 Prefab. Steel Truss bridge with foundations SubTotal $850,000 Utilities Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,270,000 Mobilization 3.0% $380,000 MOT 2.0% $250,000 Geotech and misc. Testing 2.0% $250,000 Additional items 4.0% $510,000 Contingency 10.0% $1,270,000 Asbuilts, close-out 2.0% $250,000 SubTotal $4,180,000 Project Cost Estimate Total $16,846,700
36 ( This Page Blank.)
37 Rails-with-Trails Option Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 17,800' + Separated Trail length ~ 21,700' = Total Length ~ 39,500' or 7.5 miles) Clearing and grubbing AC $38, $1,900,000 Clear all nuisance plants full width Cut and fill (single trail) CY $12 15,800 $189,600 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $13 22,000 $286,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $180 3,050 $549,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $180 4,240 $763,200 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $27 33,600 $907,200 6" bank run shell Base (dbl. trail) SY $28 48,200 $1,349,600 6" bank run shell Subbase (single trail) SY $14 15,800 $221,200 Build base as needed in poor soils Subbase (dbl. trail) SY $14 24,000 $336,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $24 5,000 $120,000 Chain link type as needed Ped/bike railing LF $84 1,500 $126,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $30, $1,080,000 Border trees and bushes as needed Sod, seeding SY $4 130,000 $455,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $75,000 1 $75,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $7, $240,000 drainage pipe and structures Pond/swale construction EA $36,000 6 $216,000 pond/swale construction SubTotal $9,403,300
38 Rails-with-Trails Option Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $75,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $750,000 Est. 1 contam. Location per mile Surface water remediation MI $100, $750,000 Est. 1 Location per mile Steel and tie/timber credit MI -$50, $25,000 Est. 1 contam. Location per mile SubTotal $1,775,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10,000 0 $0 all road intersections SubTotal $965,500 Shelters Approach paths EA $2,400 8 $19,200 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $7,200 8 $57,600 foundation cost Landscaping EA $6,000 8 $48,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work, benches, trash can, etc. EA $8,000 8 $64,000 general site prep. SubTotal $46,600 $372,800
39 Rails-with-Trails Option Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges (2) over Philippi Creek Main A LS $625,000 1 $625,000 Prefab. Steel Truss bridge with foundations Main B LS $390,000 1 $390,000 Prefab. Steel Truss bridge with foundations SubTotal $1,015,000 Utilities at Trail Heads and Shelters w/ Water Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,520,000 Mobilization 3.0% $450,000 MOT 3.0% $450,000 Geotech and misc. Testing 2.0% $300,000 Additional items 4.0% $610,000 Contingency 10.0% $1,520,000 Asbuilts, close-out 2.0% $300,000 SubTotal $5,150,000 Project Cost Estimate Total $20,301,600
40 Cost Unit Descriptions UNIT AC CY EA LF LS MI NM SF SY TN DESCRIPTION Acre Cubic Yard Each Linear Foot Lump Sum Mile Net Mile Square Foot Square Yard Ton
41 Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 25,800' + Separated Trail length ~ 13,700' = Total Length ~ 39,500' or 7.5 miles) Clear and grub AC $30, $1,500,000 Clear all nuisance plants full width Cut and fill (single trail) CY $10 20,000 $200,000 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $10 10,600 $106,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $150 4,400 $660,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $150 2,670 $400,500 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $22 33,600 $739,200 6" bank run shell Base (dbl. trail) SY $22 33,500 $737,000 6" bank run shell Subbase (single trail) SY $11 5,000 $55,000 Build base as needed in poor soils Subbase (dbl. trail) SY $11 10,000 $110,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $20 5,000 $100,000 Chain link type as needed Ped/bike railing LF $70 1,500 $105,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $25, $900,000 Border trees and bushes as needed Sod, seeding SY $3 130,000 $390,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $60,000 1 $60,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $6, $192,000 drainage pipe and structures Pond/swale construction EA $30,000 6 $180,000 pond/swale construction SubTotal $7,024,200
42 Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $1,125,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $375,000 Est. 0.5 contam. sites per mile Surface water remediation MI $100, $375,000 Est. 0.5 sites per mile Steel and tie/timber credit MI -$50, $375,000 Est. 0.5 contam. sites per mile SubTotal $1,725,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10, $130,000 all road intersections SubTotal $1,095,500 Shelters Approach paths EA $2,000 8 $16,000 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $6,000 8 $48,000 foundation cost Landscaping EA $5,000 8 $40,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work EA $8,000 8 $64,000 general site prep. SubTotal $44,000 $352,000
43 Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges Main A LS $525,000 1 $525,000 Prefab. Steel Truss bridge with foundations Main B LS $325,000 1 $325,000 Prefab. Steel Truss bridge with foundations SubTotal $850,000 Utilities Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,270,000 Mobilization 3.0% $380,000 MOT 2.0% $250,000 Geotech and misc. Testing 2.0% $250,000 Additional items 4.0% $510,000 Contingency 10.0% $1,270,000 Asbuilts, close-out 2.0% $250,000 SubTotal $4,180,000 Project Cost Estimate Total $16,846,700
44 ( This Page Blank.)
45 Rails-with-Trails Option Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 17,800' + Separated Trail length ~ 21,700' = Total Length ~ 39,500' or 7.5 miles) Clearing and grubbing AC $38, $1,900,000 Clear all nuisance plants full width Cut and fill (single trail) CY $12 15,800 $189,600 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $13 22,000 $286,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $180 3,050 $549,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $180 4,240 $763,200 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $27 33,600 $907,200 6" bank run shell Base (dbl. trail) SY $28 48,200 $1,349,600 6" bank run shell Subbase (single trail) SY $14 15,800 $221,200 Build base as needed in poor soils Subbase (dbl. trail) SY $14 24,000 $336,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $24 5,000 $120,000 Chain link type as needed Ped/bike railing LF $84 1,500 $126,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $30, $1,080,000 Border trees and bushes as needed Sod, seeding SY $4 130,000 $455,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $75,000 1 $75,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $7, $240,000 drainage pipe and structures Pond/swale construction EA $36,000 6 $216,000 pond/swale construction SubTotal $9,403,300
46 Rails-with-Trails Option Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $75,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $750,000 Est. 1 contam. Location per mile Surface water remediation MI $100, $750,000 Est. 1 Location per mile Steel and tie/timber credit MI -$50, $25,000 Est. 1 contam. Location per mile SubTotal $1,775,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10,000 0 $0 all road intersections SubTotal $965,500 Shelters Approach paths EA $2,400 8 $19,200 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $7,200 8 $57,600 foundation cost Landscaping EA $6,000 8 $48,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work, benches, trash can, etc. EA $8,000 8 $64,000 general site prep. SubTotal $46,600 $372,800
47 Rails-with-Trails Option Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges (2) over Philippi Creek Main A LS $625,000 1 $625,000 Prefab. Steel Truss bridge with foundations Main B LS $390,000 1 $390,000 Prefab. Steel Truss bridge with foundations SubTotal $1,015,000 Utilities at Trail Heads and Shelters w/ Water Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,520,000 Mobilization 3.0% $450,000 MOT 3.0% $450,000 Geotech and misc. Testing 2.0% $300,000 Additional items 4.0% $610,000 Contingency 10.0% $1,520,000 Asbuilts, close-out 2.0% $300,000 SubTotal $5,150,000 Project Cost Estimate Total $20,301,600
48 Cost Unit Descriptions UNIT AC CY EA LF LS MI NM SF SY TN DESCRIPTION Acre Cubic Yard Each Linear Foot Lump Sum Mile Net Mile Square Foot Square Yard Ton
49 Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 25,800' + Separated Trail length ~ 13,700' = Total Length ~ 39,500' or 7.5 miles) Clear and grub AC $30, $1,500,000 Clear all nuisance plants full width Cut and fill (single trail) CY $10 20,000 $200,000 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $10 10,600 $106,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $150 4,400 $660,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $150 2,670 $400,500 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $22 33,600 $739,200 6" bank run shell Base (dbl. trail) SY $22 33,500 $737,000 6" bank run shell Subbase (single trail) SY $11 5,000 $55,000 Build base as needed in poor soils Subbase (dbl. trail) SY $11 10,000 $110,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $20 5,000 $100,000 Chain link type as needed Ped/bike railing LF $70 1,500 $105,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $25, $900,000 Border trees and bushes as needed Sod, seeding SY $3 130,000 $390,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $60,000 1 $60,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $6, $192,000 drainage pipe and structures Pond/swale construction EA $30,000 6 $180,000 pond/swale construction SubTotal $7,024,200
50 Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $1,125,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $375,000 Est. 0.5 contam. sites per mile Surface water remediation MI $100, $375,000 Est. 0.5 sites per mile Steel and tie/timber credit MI -$50, $375,000 Est. 0.5 contam. sites per mile SubTotal $1,725,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10, $130,000 all road intersections SubTotal $1,095,500 Shelters Approach paths EA $2,000 8 $16,000 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $6,000 8 $48,000 foundation cost Landscaping EA $5,000 8 $40,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work EA $8,000 8 $64,000 general site prep. SubTotal $44,000 $352,000
51 Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges Main A LS $525,000 1 $525,000 Prefab. Steel Truss bridge with foundations Main B LS $325,000 1 $325,000 Prefab. Steel Truss bridge with foundations SubTotal $850,000 Utilities Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,270,000 Mobilization 3.0% $380,000 MOT 2.0% $250,000 Geotech and misc. Testing 2.0% $250,000 Additional items 4.0% $510,000 Contingency 10.0% $1,270,000 Asbuilts, close-out 2.0% $250,000 SubTotal $4,180,000 Project Cost Estimate Total $16,846,700
52 ( This Page Blank.)
53 Rails-with-Trails Option Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 17,800' + Separated Trail length ~ 21,700' = Total Length ~ 39,500' or 7.5 miles) Clearing and grubbing AC $38, $1,900,000 Clear all nuisance plants full width Cut and fill (single trail) CY $12 15,800 $189,600 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $13 22,000 $286,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $180 3,050 $549,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $180 4,240 $763,200 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $27 33,600 $907,200 6" bank run shell Base (dbl. trail) SY $28 48,200 $1,349,600 6" bank run shell Subbase (single trail) SY $14 15,800 $221,200 Build base as needed in poor soils Subbase (dbl. trail) SY $14 24,000 $336,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $24 5,000 $120,000 Chain link type as needed Ped/bike railing LF $84 1,500 $126,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $30, $1,080,000 Border trees and bushes as needed Sod, seeding SY $4 130,000 $455,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $75,000 1 $75,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $7, $240,000 drainage pipe and structures Pond/swale construction EA $36,000 6 $216,000 pond/swale construction SubTotal $9,403,300
54 Rails-with-Trails Option Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $75,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $750,000 Est. 1 contam. Location per mile Surface water remediation MI $100, $750,000 Est. 1 Location per mile Steel and tie/timber credit MI -$50, $25,000 Est. 1 contam. Location per mile SubTotal $1,775,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10,000 0 $0 all road intersections SubTotal $965,500 Shelters Approach paths EA $2,400 8 $19,200 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $7,200 8 $57,600 foundation cost Landscaping EA $6,000 8 $48,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work, benches, trash can, etc. EA $8,000 8 $64,000 general site prep. SubTotal $46,600 $372,800
55 Rails-with-Trails Option Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges (2) over Philippi Creek Main A LS $625,000 1 $625,000 Prefab. Steel Truss bridge with foundations Main B LS $390,000 1 $390,000 Prefab. Steel Truss bridge with foundations SubTotal $1,015,000 Utilities at Trail Heads and Shelters w/ Water Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,520,000 Mobilization 3.0% $450,000 MOT 3.0% $450,000 Geotech and misc. Testing 2.0% $300,000 Additional items 4.0% $610,000 Contingency 10.0% $1,520,000 Asbuilts, close-out 2.0% $300,000 SubTotal $5,150,000 Project Cost Estimate Total $20,301,600
56 Cost Unit Descriptions UNIT AC CY EA LF LS MI NM SF SY TN DESCRIPTION Acre Cubic Yard Each Linear Foot Lump Sum Mile Net Mile Square Foot Square Yard Ton
57 Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 25,800' + Separated Trail length ~ 13,700' = Total Length ~ 39,500' or 7.5 miles) Clear and grub AC $30, $1,500,000 Clear all nuisance plants full width Cut and fill (single trail) CY $10 20,000 $200,000 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $10 10,600 $106,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $150 4,400 $660,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $150 2,670 $400,500 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $22 33,600 $739,200 6" bank run shell Base (dbl. trail) SY $22 33,500 $737,000 6" bank run shell Subbase (single trail) SY $11 5,000 $55,000 Build base as needed in poor soils Subbase (dbl. trail) SY $11 10,000 $110,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $20 5,000 $100,000 Chain link type as needed Ped/bike railing LF $70 1,500 $105,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $25, $900,000 Border trees and bushes as needed Sod, seeding SY $3 130,000 $390,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $60,000 1 $60,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $6, $192,000 drainage pipe and structures Pond/swale construction EA $30,000 6 $180,000 pond/swale construction SubTotal $7,024,200
58 Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $1,125,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $375,000 Est. 0.5 contam. sites per mile Surface water remediation MI $100, $375,000 Est. 0.5 sites per mile Steel and tie/timber credit MI -$50, $375,000 Est. 0.5 contam. sites per mile SubTotal $1,725,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10, $130,000 all road intersections SubTotal $1,095,500 Shelters Approach paths EA $2,000 8 $16,000 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $6,000 8 $48,000 foundation cost Landscaping EA $5,000 8 $40,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work EA $8,000 8 $64,000 general site prep. SubTotal $44,000 $352,000
59 Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges Main A LS $525,000 1 $525,000 Prefab. Steel Truss bridge with foundations Main B LS $325,000 1 $325,000 Prefab. Steel Truss bridge with foundations SubTotal $850,000 Utilities Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,270,000 Mobilization 3.0% $380,000 MOT 2.0% $250,000 Geotech and misc. Testing 2.0% $250,000 Additional items 4.0% $510,000 Contingency 10.0% $1,270,000 Asbuilts, close-out 2.0% $250,000 SubTotal $4,180,000 Project Cost Estimate Total $16,846,700
60 ( This Page Blank.)
61 Rails-with-Trails Option Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 17,800' + Separated Trail length ~ 21,700' = Total Length ~ 39,500' or 7.5 miles) Clearing and grubbing AC $38, $1,900,000 Clear all nuisance plants full width Cut and fill (single trail) CY $12 15,800 $189,600 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $13 22,000 $286,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $180 3,050 $549,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $180 4,240 $763,200 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $27 33,600 $907,200 6" bank run shell Base (dbl. trail) SY $28 48,200 $1,349,600 6" bank run shell Subbase (single trail) SY $14 15,800 $221,200 Build base as needed in poor soils Subbase (dbl. trail) SY $14 24,000 $336,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $24 5,000 $120,000 Chain link type as needed Ped/bike railing LF $84 1,500 $126,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $30, $1,080,000 Border trees and bushes as needed Sod, seeding SY $4 130,000 $455,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $75,000 1 $75,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $7, $240,000 drainage pipe and structures Pond/swale construction EA $36,000 6 $216,000 pond/swale construction SubTotal $9,403,300
62 Rails-with-Trails Option Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $75,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $750,000 Est. 1 contam. Location per mile Surface water remediation MI $100, $750,000 Est. 1 Location per mile Steel and tie/timber credit MI -$50, $25,000 Est. 1 contam. Location per mile SubTotal $1,775,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10,000 0 $0 all road intersections SubTotal $965,500 Shelters Approach paths EA $2,400 8 $19,200 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $7,200 8 $57,600 foundation cost Landscaping EA $6,000 8 $48,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work, benches, trash can, etc. EA $8,000 8 $64,000 general site prep. SubTotal $46,600 $372,800
63 Rails-with-Trails Option Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges (2) over Philippi Creek Main A LS $625,000 1 $625,000 Prefab. Steel Truss bridge with foundations Main B LS $390,000 1 $390,000 Prefab. Steel Truss bridge with foundations SubTotal $1,015,000 Utilities at Trail Heads and Shelters w/ Water Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,520,000 Mobilization 3.0% $450,000 MOT 3.0% $450,000 Geotech and misc. Testing 2.0% $300,000 Additional items 4.0% $610,000 Contingency 10.0% $1,520,000 Asbuilts, close-out 2.0% $300,000 SubTotal $5,150,000 Project Cost Estimate Total $20,301,600
64 Cost Unit Descriptions UNIT AC CY EA LF LS MI NM SF SY TN DESCRIPTION Acre Cubic Yard Each Linear Foot Lump Sum Mile Net Mile Square Foot Square Yard Ton
65 Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 25,800' + Separated Trail length ~ 13,700' = Total Length ~ 39,500' or 7.5 miles) Clear and grub AC $30, $1,500,000 Clear all nuisance plants full width Cut and fill (single trail) CY $10 20,000 $200,000 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $10 10,600 $106,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $150 4,400 $660,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $150 2,670 $400,500 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $22 33,600 $739,200 6" bank run shell Base (dbl. trail) SY $22 33,500 $737,000 6" bank run shell Subbase (single trail) SY $11 5,000 $55,000 Build base as needed in poor soils Subbase (dbl. trail) SY $11 10,000 $110,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $20 5,000 $100,000 Chain link type as needed Ped/bike railing LF $70 1,500 $105,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $25, $900,000 Border trees and bushes as needed Sod, seeding SY $3 130,000 $390,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $60,000 1 $60,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $6, $192,000 drainage pipe and structures Pond/swale construction EA $30,000 6 $180,000 pond/swale construction SubTotal $7,024,200
66 Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $1,125,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $375,000 Est. 0.5 contam. sites per mile Surface water remediation MI $100, $375,000 Est. 0.5 sites per mile Steel and tie/timber credit MI -$50, $375,000 Est. 0.5 contam. sites per mile SubTotal $1,725,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10, $130,000 all road intersections SubTotal $1,095,500 Shelters Approach paths EA $2,000 8 $16,000 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $6,000 8 $48,000 foundation cost Landscaping EA $5,000 8 $40,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work EA $8,000 8 $64,000 general site prep. SubTotal $44,000 $352,000
67 Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges Main A LS $525,000 1 $525,000 Prefab. Steel Truss bridge with foundations Main B LS $325,000 1 $325,000 Prefab. Steel Truss bridge with foundations SubTotal $850,000 Utilities Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,270,000 Mobilization 3.0% $380,000 MOT 2.0% $250,000 Geotech and misc. Testing 2.0% $250,000 Additional items 4.0% $510,000 Contingency 10.0% $1,270,000 Asbuilts, close-out 2.0% $250,000 SubTotal $4,180,000 Project Cost Estimate Total $16,846,700
68 ( This Page Blank.)
69 Rails-with-Trails Option Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 17,800' + Separated Trail length ~ 21,700' = Total Length ~ 39,500' or 7.5 miles) Clearing and grubbing AC $38, $1,900,000 Clear all nuisance plants full width Cut and fill (single trail) CY $12 15,800 $189,600 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $13 22,000 $286,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $180 3,050 $549,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $180 4,240 $763,200 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $27 33,600 $907,200 6" bank run shell Base (dbl. trail) SY $28 48,200 $1,349,600 6" bank run shell Subbase (single trail) SY $14 15,800 $221,200 Build base as needed in poor soils Subbase (dbl. trail) SY $14 24,000 $336,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $24 5,000 $120,000 Chain link type as needed Ped/bike railing LF $84 1,500 $126,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $30, $1,080,000 Border trees and bushes as needed Sod, seeding SY $4 130,000 $455,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $75,000 1 $75,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $7, $240,000 drainage pipe and structures Pond/swale construction EA $36,000 6 $216,000 pond/swale construction SubTotal $9,403,300
70 Rails-with-Trails Option Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $75,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $750,000 Est. 1 contam. Location per mile Surface water remediation MI $100, $750,000 Est. 1 Location per mile Steel and tie/timber credit MI -$50, $25,000 Est. 1 contam. Location per mile SubTotal $1,775,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10,000 0 $0 all road intersections SubTotal $965,500 Shelters Approach paths EA $2,400 8 $19,200 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $7,200 8 $57,600 foundation cost Landscaping EA $6,000 8 $48,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work, benches, trash can, etc. EA $8,000 8 $64,000 general site prep. SubTotal $46,600 $372,800
71 Rails-with-Trails Option Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges (2) over Philippi Creek Main A LS $625,000 1 $625,000 Prefab. Steel Truss bridge with foundations Main B LS $390,000 1 $390,000 Prefab. Steel Truss bridge with foundations SubTotal $1,015,000 Utilities at Trail Heads and Shelters w/ Water Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,520,000 Mobilization 3.0% $450,000 MOT 3.0% $450,000 Geotech and misc. Testing 2.0% $300,000 Additional items 4.0% $610,000 Contingency 10.0% $1,520,000 Asbuilts, close-out 2.0% $300,000 SubTotal $5,150,000 Project Cost Estimate Total $20,301,600
72 Cost Unit Descriptions UNIT AC CY EA LF LS MI NM SF SY TN DESCRIPTION Acre Cubic Yard Each Linear Foot Lump Sum Mile Net Mile Square Foot Square Yard Ton
73 Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 25,800' + Separated Trail length ~ 13,700' = Total Length ~ 39,500' or 7.5 miles) Clear and grub AC $30, $1,500,000 Clear all nuisance plants full width Cut and fill (single trail) CY $10 20,000 $200,000 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $10 10,600 $106,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $150 4,400 $660,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $150 2,670 $400,500 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $22 33,600 $739,200 6" bank run shell Base (dbl. trail) SY $22 33,500 $737,000 6" bank run shell Subbase (single trail) SY $11 5,000 $55,000 Build base as needed in poor soils Subbase (dbl. trail) SY $11 10,000 $110,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $20 5,000 $100,000 Chain link type as needed Ped/bike railing LF $70 1,500 $105,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $25, $900,000 Border trees and bushes as needed Sod, seeding SY $3 130,000 $390,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $60,000 1 $60,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $6, $192,000 drainage pipe and structures Pond/swale construction EA $30,000 6 $180,000 pond/swale construction SubTotal $7,024,200
74 Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $1,125,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $375,000 Est. 0.5 contam. sites per mile Surface water remediation MI $100, $375,000 Est. 0.5 sites per mile Steel and tie/timber credit MI -$50, $375,000 Est. 0.5 contam. sites per mile SubTotal $1,725,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10, $130,000 all road intersections SubTotal $1,095,500 Shelters Approach paths EA $2,000 8 $16,000 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $6,000 8 $48,000 foundation cost Landscaping EA $5,000 8 $40,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work EA $8,000 8 $64,000 general site prep. SubTotal $44,000 $352,000
75 Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges Main A LS $525,000 1 $525,000 Prefab. Steel Truss bridge with foundations Main B LS $325,000 1 $325,000 Prefab. Steel Truss bridge with foundations SubTotal $850,000 Utilities Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,270,000 Mobilization 3.0% $380,000 MOT 2.0% $250,000 Geotech and misc. Testing 2.0% $250,000 Additional items 4.0% $510,000 Contingency 10.0% $1,270,000 Asbuilts, close-out 2.0% $250,000 SubTotal $4,180,000 Project Cost Estimate Total $16,846,700
76 ( This Page Blank.)
77 Rails-with-Trails Option Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 17,800' + Separated Trail length ~ 21,700' = Total Length ~ 39,500' or 7.5 miles) Clearing and grubbing AC $38, $1,900,000 Clear all nuisance plants full width Cut and fill (single trail) CY $12 15,800 $189,600 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $13 22,000 $286,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $180 3,050 $549,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $180 4,240 $763,200 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $27 33,600 $907,200 6" bank run shell Base (dbl. trail) SY $28 48,200 $1,349,600 6" bank run shell Subbase (single trail) SY $14 15,800 $221,200 Build base as needed in poor soils Subbase (dbl. trail) SY $14 24,000 $336,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $24 5,000 $120,000 Chain link type as needed Ped/bike railing LF $84 1,500 $126,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $30, $1,080,000 Border trees and bushes as needed Sod, seeding SY $4 130,000 $455,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $75,000 1 $75,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $7, $240,000 drainage pipe and structures Pond/swale construction EA $36,000 6 $216,000 pond/swale construction SubTotal $9,403,300
78 Rails-with-Trails Option Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $75,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $750,000 Est. 1 contam. Location per mile Surface water remediation MI $100, $750,000 Est. 1 Location per mile Steel and tie/timber credit MI -$50, $25,000 Est. 1 contam. Location per mile SubTotal $1,775,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10,000 0 $0 all road intersections SubTotal $965,500 Shelters Approach paths EA $2,400 8 $19,200 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $7,200 8 $57,600 foundation cost Landscaping EA $6,000 8 $48,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work, benches, trash can, etc. EA $8,000 8 $64,000 general site prep. SubTotal $46,600 $372,800
79 Rails-with-Trails Option Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges (2) over Philippi Creek Main A LS $625,000 1 $625,000 Prefab. Steel Truss bridge with foundations Main B LS $390,000 1 $390,000 Prefab. Steel Truss bridge with foundations SubTotal $1,015,000 Utilities at Trail Heads and Shelters w/ Water Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,520,000 Mobilization 3.0% $450,000 MOT 3.0% $450,000 Geotech and misc. Testing 2.0% $300,000 Additional items 4.0% $610,000 Contingency 10.0% $1,520,000 Asbuilts, close-out 2.0% $300,000 SubTotal $5,150,000 Project Cost Estimate Total $20,301,600
80 Cost Unit Descriptions UNIT AC CY EA LF LS MI NM SF SY TN DESCRIPTION Acre Cubic Yard Each Linear Foot Lump Sum Mile Net Mile Square Foot Square Yard Ton
81 Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 25,800' + Separated Trail length ~ 13,700' = Total Length ~ 39,500' or 7.5 miles) Clear and grub AC $30, $1,500,000 Clear all nuisance plants full width Cut and fill (single trail) CY $10 20,000 $200,000 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $10 10,600 $106,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $150 4,400 $660,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $150 2,670 $400,500 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $22 33,600 $739,200 6" bank run shell Base (dbl. trail) SY $22 33,500 $737,000 6" bank run shell Subbase (single trail) SY $11 5,000 $55,000 Build base as needed in poor soils Subbase (dbl. trail) SY $11 10,000 $110,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $20 5,000 $100,000 Chain link type as needed Ped/bike railing LF $70 1,500 $105,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $25, $900,000 Border trees and bushes as needed Sod, seeding SY $3 130,000 $390,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $60,000 1 $60,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $6, $192,000 drainage pipe and structures Pond/swale construction EA $30,000 6 $180,000 pond/swale construction SubTotal $7,024,200
82 Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $1,125,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $375,000 Est. 0.5 contam. sites per mile Surface water remediation MI $100, $375,000 Est. 0.5 sites per mile Steel and tie/timber credit MI -$50, $375,000 Est. 0.5 contam. sites per mile SubTotal $1,725,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10, $130,000 all road intersections SubTotal $1,095,500 Shelters Approach paths EA $2,000 8 $16,000 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $6,000 8 $48,000 foundation cost Landscaping EA $5,000 8 $40,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work EA $8,000 8 $64,000 general site prep. SubTotal $44,000 $352,000
83 Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges Main A LS $525,000 1 $525,000 Prefab. Steel Truss bridge with foundations Main B LS $325,000 1 $325,000 Prefab. Steel Truss bridge with foundations SubTotal $850,000 Utilities Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,270,000 Mobilization 3.0% $380,000 MOT 2.0% $250,000 Geotech and misc. Testing 2.0% $250,000 Additional items 4.0% $510,000 Contingency 10.0% $1,270,000 Asbuilts, close-out 2.0% $250,000 SubTotal $4,180,000 Project Cost Estimate Total $16,846,700
84 ( This Page Blank.)
85 Rails-with-Trails Option Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 17,800' + Separated Trail length ~ 21,700' = Total Length ~ 39,500' or 7.5 miles) Clearing and grubbing AC $38, $1,900,000 Clear all nuisance plants full width Cut and fill (single trail) CY $12 15,800 $189,600 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $13 22,000 $286,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $180 3,050 $549,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $180 4,240 $763,200 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $27 33,600 $907,200 6" bank run shell Base (dbl. trail) SY $28 48,200 $1,349,600 6" bank run shell Subbase (single trail) SY $14 15,800 $221,200 Build base as needed in poor soils Subbase (dbl. trail) SY $14 24,000 $336,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $24 5,000 $120,000 Chain link type as needed Ped/bike railing LF $84 1,500 $126,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $30, $1,080,000 Border trees and bushes as needed Sod, seeding SY $4 130,000 $455,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $75,000 1 $75,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $7, $240,000 drainage pipe and structures Pond/swale construction EA $36,000 6 $216,000 pond/swale construction SubTotal $9,403,300
86 Rails-with-Trails Option Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $75,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $750,000 Est. 1 contam. Location per mile Surface water remediation MI $100, $750,000 Est. 1 Location per mile Steel and tie/timber credit MI -$50, $25,000 Est. 1 contam. Location per mile SubTotal $1,775,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10,000 0 $0 all road intersections SubTotal $965,500 Shelters Approach paths EA $2,400 8 $19,200 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $7,200 8 $57,600 foundation cost Landscaping EA $6,000 8 $48,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work, benches, trash can, etc. EA $8,000 8 $64,000 general site prep. SubTotal $46,600 $372,800
87 Rails-with-Trails Option Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges (2) over Philippi Creek Main A LS $625,000 1 $625,000 Prefab. Steel Truss bridge with foundations Main B LS $390,000 1 $390,000 Prefab. Steel Truss bridge with foundations SubTotal $1,015,000 Utilities at Trail Heads and Shelters w/ Water Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,520,000 Mobilization 3.0% $450,000 MOT 3.0% $450,000 Geotech and misc. Testing 2.0% $300,000 Additional items 4.0% $610,000 Contingency 10.0% $1,520,000 Asbuilts, close-out 2.0% $300,000 SubTotal $5,150,000 Project Cost Estimate Total $20,301,600
88 Cost Unit Descriptions UNIT AC CY EA LF LS MI NM SF SY TN DESCRIPTION Acre Cubic Yard Each Linear Foot Lump Sum Mile Net Mile Square Foot Square Yard Ton
89 Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 25,800' + Separated Trail length ~ 13,700' = Total Length ~ 39,500' or 7.5 miles) Clear and grub AC $30, $1,500,000 Clear all nuisance plants full width Cut and fill (single trail) CY $10 20,000 $200,000 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $10 10,600 $106,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $150 4,400 $660,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $150 2,670 $400,500 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $22 33,600 $739,200 6" bank run shell Base (dbl. trail) SY $22 33,500 $737,000 6" bank run shell Subbase (single trail) SY $11 5,000 $55,000 Build base as needed in poor soils Subbase (dbl. trail) SY $11 10,000 $110,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $20 5,000 $100,000 Chain link type as needed Ped/bike railing LF $70 1,500 $105,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $25, $900,000 Border trees and bushes as needed Sod, seeding SY $3 130,000 $390,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $60,000 1 $60,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $6, $192,000 drainage pipe and structures Pond/swale construction EA $30,000 6 $180,000 pond/swale construction SubTotal $7,024,200
90 Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $1,125,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $375,000 Est. 0.5 contam. sites per mile Surface water remediation MI $100, $375,000 Est. 0.5 sites per mile Steel and tie/timber credit MI -$50, $375,000 Est. 0.5 contam. sites per mile SubTotal $1,725,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10, $130,000 all road intersections SubTotal $1,095,500 Shelters Approach paths EA $2,000 8 $16,000 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $6,000 8 $48,000 foundation cost Landscaping EA $5,000 8 $40,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work EA $8,000 8 $64,000 general site prep. SubTotal $44,000 $352,000
91 Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges Main A LS $525,000 1 $525,000 Prefab. Steel Truss bridge with foundations Main B LS $325,000 1 $325,000 Prefab. Steel Truss bridge with foundations SubTotal $850,000 Utilities Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,270,000 Mobilization 3.0% $380,000 MOT 2.0% $250,000 Geotech and misc. Testing 2.0% $250,000 Additional items 4.0% $510,000 Contingency 10.0% $1,270,000 Asbuilts, close-out 2.0% $250,000 SubTotal $4,180,000 Project Cost Estimate Total $16,846,700
92 ( This Page Blank.)
93 Rails-with-Trails Option Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 17,800' + Separated Trail length ~ 21,700' = Total Length ~ 39,500' or 7.5 miles) Clearing and grubbing AC $38, $1,900,000 Clear all nuisance plants full width Cut and fill (single trail) CY $12 15,800 $189,600 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $13 22,000 $286,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $180 3,050 $549,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $180 4,240 $763,200 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $27 33,600 $907,200 6" bank run shell Base (dbl. trail) SY $28 48,200 $1,349,600 6" bank run shell Subbase (single trail) SY $14 15,800 $221,200 Build base as needed in poor soils Subbase (dbl. trail) SY $14 24,000 $336,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $24 5,000 $120,000 Chain link type as needed Ped/bike railing LF $84 1,500 $126,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $30, $1,080,000 Border trees and bushes as needed Sod, seeding SY $4 130,000 $455,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $75,000 1 $75,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $7, $240,000 drainage pipe and structures Pond/swale construction EA $36,000 6 $216,000 pond/swale construction SubTotal $9,403,300
94 Rails-with-Trails Option Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $75,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $750,000 Est. 1 contam. Location per mile Surface water remediation MI $100, $750,000 Est. 1 Location per mile Steel and tie/timber credit MI -$50, $25,000 Est. 1 contam. Location per mile SubTotal $1,775,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10,000 0 $0 all road intersections SubTotal $965,500 Shelters Approach paths EA $2,400 8 $19,200 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $7,200 8 $57,600 foundation cost Landscaping EA $6,000 8 $48,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work, benches, trash can, etc. EA $8,000 8 $64,000 general site prep. SubTotal $46,600 $372,800
95 Rails-with-Trails Option Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges (2) over Philippi Creek Main A LS $625,000 1 $625,000 Prefab. Steel Truss bridge with foundations Main B LS $390,000 1 $390,000 Prefab. Steel Truss bridge with foundations SubTotal $1,015,000 Utilities at Trail Heads and Shelters w/ Water Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,520,000 Mobilization 3.0% $450,000 MOT 3.0% $450,000 Geotech and misc. Testing 2.0% $300,000 Additional items 4.0% $610,000 Contingency 10.0% $1,520,000 Asbuilts, close-out 2.0% $300,000 SubTotal $5,150,000 Project Cost Estimate Total $20,301,600
96 Cost Unit Descriptions UNIT AC CY EA LF LS MI NM SF SY TN DESCRIPTION Acre Cubic Yard Each Linear Foot Lump Sum Mile Net Mile Square Foot Square Yard Ton
97 Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 25,800' + Separated Trail length ~ 13,700' = Total Length ~ 39,500' or 7.5 miles) Clear and grub AC $30, $1,500,000 Clear all nuisance plants full width Cut and fill (single trail) CY $10 20,000 $200,000 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $10 10,600 $106,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $150 4,400 $660,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $150 2,670 $400,500 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $22 33,600 $739,200 6" bank run shell Base (dbl. trail) SY $22 33,500 $737,000 6" bank run shell Subbase (single trail) SY $11 5,000 $55,000 Build base as needed in poor soils Subbase (dbl. trail) SY $11 10,000 $110,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $20 5,000 $100,000 Chain link type as needed Ped/bike railing LF $70 1,500 $105,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $25, $900,000 Border trees and bushes as needed Sod, seeding SY $3 130,000 $390,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $60,000 1 $60,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $6, $192,000 drainage pipe and structures Pond/swale construction EA $30,000 6 $180,000 pond/swale construction SubTotal $7,024,200
98 Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $1,125,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $375,000 Est. 0.5 contam. sites per mile Surface water remediation MI $100, $375,000 Est. 0.5 sites per mile Steel and tie/timber credit MI -$50, $375,000 Est. 0.5 contam. sites per mile SubTotal $1,725,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10, $130,000 all road intersections SubTotal $1,095,500 Shelters Approach paths EA $2,000 8 $16,000 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $6,000 8 $48,000 foundation cost Landscaping EA $5,000 8 $40,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work EA $8,000 8 $64,000 general site prep. SubTotal $44,000 $352,000
99 Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges Main A LS $525,000 1 $525,000 Prefab. Steel Truss bridge with foundations Main B LS $325,000 1 $325,000 Prefab. Steel Truss bridge with foundations SubTotal $850,000 Utilities Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,270,000 Mobilization 3.0% $380,000 MOT 2.0% $250,000 Geotech and misc. Testing 2.0% $250,000 Additional items 4.0% $510,000 Contingency 10.0% $1,270,000 Asbuilts, close-out 2.0% $250,000 SubTotal $4,180,000 Project Cost Estimate Total $16,846,700
100 ( This Page Blank.)
101 Rails-with-Trails Option Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 17,800' + Separated Trail length ~ 21,700' = Total Length ~ 39,500' or 7.5 miles) Clearing and grubbing AC $38, $1,900,000 Clear all nuisance plants full width Cut and fill (single trail) CY $12 15,800 $189,600 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $13 22,000 $286,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $180 3,050 $549,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $180 4,240 $763,200 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $27 33,600 $907,200 6" bank run shell Base (dbl. trail) SY $28 48,200 $1,349,600 6" bank run shell Subbase (single trail) SY $14 15,800 $221,200 Build base as needed in poor soils Subbase (dbl. trail) SY $14 24,000 $336,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $24 5,000 $120,000 Chain link type as needed Ped/bike railing LF $84 1,500 $126,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $30, $1,080,000 Border trees and bushes as needed Sod, seeding SY $4 130,000 $455,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $75,000 1 $75,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $7, $240,000 drainage pipe and structures Pond/swale construction EA $36,000 6 $216,000 pond/swale construction SubTotal $9,403,300
102 Rails-with-Trails Option Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $75,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $750,000 Est. 1 contam. Location per mile Surface water remediation MI $100, $750,000 Est. 1 Location per mile Steel and tie/timber credit MI -$50, $25,000 Est. 1 contam. Location per mile SubTotal $1,775,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10,000 0 $0 all road intersections SubTotal $965,500 Shelters Approach paths EA $2,400 8 $19,200 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $7,200 8 $57,600 foundation cost Landscaping EA $6,000 8 $48,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work, benches, trash can, etc. EA $8,000 8 $64,000 general site prep. SubTotal $46,600 $372,800
103 Rails-with-Trails Option Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges (2) over Philippi Creek Main A LS $625,000 1 $625,000 Prefab. Steel Truss bridge with foundations Main B LS $390,000 1 $390,000 Prefab. Steel Truss bridge with foundations SubTotal $1,015,000 Utilities at Trail Heads and Shelters w/ Water Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,520,000 Mobilization 3.0% $450,000 MOT 3.0% $450,000 Geotech and misc. Testing 2.0% $300,000 Additional items 4.0% $610,000 Contingency 10.0% $1,520,000 Asbuilts, close-out 2.0% $300,000 SubTotal $5,150,000 Project Cost Estimate Total $20,301,600
104 Cost Unit Descriptions UNIT AC CY EA LF LS MI NM SF SY TN DESCRIPTION Acre Cubic Yard Each Linear Foot Lump Sum Mile Net Mile Square Foot Square Yard Ton
105 Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 25,800' + Separated Trail length ~ 13,700' = Total Length ~ 39,500' or 7.5 miles) Clear and grub AC $30, $1,500,000 Clear all nuisance plants full width Cut and fill (single trail) CY $10 20,000 $200,000 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $10 10,600 $106,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $150 4,400 $660,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $150 2,670 $400,500 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $22 33,600 $739,200 6" bank run shell Base (dbl. trail) SY $22 33,500 $737,000 6" bank run shell Subbase (single trail) SY $11 5,000 $55,000 Build base as needed in poor soils Subbase (dbl. trail) SY $11 10,000 $110,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $20 5,000 $100,000 Chain link type as needed Ped/bike railing LF $70 1,500 $105,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $25, $900,000 Border trees and bushes as needed Sod, seeding SY $3 130,000 $390,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $60,000 1 $60,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $6, $192,000 drainage pipe and structures Pond/swale construction EA $30,000 6 $180,000 pond/swale construction SubTotal $7,024,200
106 Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $1,125,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $375,000 Est. 0.5 contam. sites per mile Surface water remediation MI $100, $375,000 Est. 0.5 sites per mile Steel and tie/timber credit MI -$50, $375,000 Est. 0.5 contam. sites per mile SubTotal $1,725,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10, $130,000 all road intersections SubTotal $1,095,500 Shelters Approach paths EA $2,000 8 $16,000 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $6,000 8 $48,000 foundation cost Landscaping EA $5,000 8 $40,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work EA $8,000 8 $64,000 general site prep. SubTotal $44,000 $352,000
107 Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges Main A LS $525,000 1 $525,000 Prefab. Steel Truss bridge with foundations Main B LS $325,000 1 $325,000 Prefab. Steel Truss bridge with foundations SubTotal $850,000 Utilities Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,270,000 Mobilization 3.0% $380,000 MOT 2.0% $250,000 Geotech and misc. Testing 2.0% $250,000 Additional items 4.0% $510,000 Contingency 10.0% $1,270,000 Asbuilts, close-out 2.0% $250,000 SubTotal $4,180,000 Project Cost Estimate Total $16,846,700
108 ( This Page Blank.)
109 Rails-with-Trails Option Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 17,800' + Separated Trail length ~ 21,700' = Total Length ~ 39,500' or 7.5 miles) Clearing and grubbing AC $38, $1,900,000 Clear all nuisance plants full width Cut and fill (single trail) CY $12 15,800 $189,600 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $13 22,000 $286,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $180 3,050 $549,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $180 4,240 $763,200 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $27 33,600 $907,200 6" bank run shell Base (dbl. trail) SY $28 48,200 $1,349,600 6" bank run shell Subbase (single trail) SY $14 15,800 $221,200 Build base as needed in poor soils Subbase (dbl. trail) SY $14 24,000 $336,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $24 5,000 $120,000 Chain link type as needed Ped/bike railing LF $84 1,500 $126,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $30, $1,080,000 Border trees and bushes as needed Sod, seeding SY $4 130,000 $455,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $75,000 1 $75,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $7, $240,000 drainage pipe and structures Pond/swale construction EA $36,000 6 $216,000 pond/swale construction SubTotal $9,403,300
110 Rails-with-Trails Option Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $75,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $750,000 Est. 1 contam. Location per mile Surface water remediation MI $100, $750,000 Est. 1 Location per mile Steel and tie/timber credit MI -$50, $25,000 Est. 1 contam. Location per mile SubTotal $1,775,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10,000 0 $0 all road intersections SubTotal $965,500 Shelters Approach paths EA $2,400 8 $19,200 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $7,200 8 $57,600 foundation cost Landscaping EA $6,000 8 $48,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work, benches, trash can, etc. EA $8,000 8 $64,000 general site prep. SubTotal $46,600 $372,800
111 Rails-with-Trails Option Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges (2) over Philippi Creek Main A LS $625,000 1 $625,000 Prefab. Steel Truss bridge with foundations Main B LS $390,000 1 $390,000 Prefab. Steel Truss bridge with foundations SubTotal $1,015,000 Utilities at Trail Heads and Shelters w/ Water Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,520,000 Mobilization 3.0% $450,000 MOT 3.0% $450,000 Geotech and misc. Testing 2.0% $300,000 Additional items 4.0% $610,000 Contingency 10.0% $1,520,000 Asbuilts, close-out 2.0% $300,000 SubTotal $5,150,000 Project Cost Estimate Total $20,301,600
112 Cost Unit Descriptions UNIT AC CY EA LF LS MI NM SF SY TN DESCRIPTION Acre Cubic Yard Each Linear Foot Lump Sum Mile Net Mile Square Foot Square Yard Ton
113 Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 25,800' + Separated Trail length ~ 13,700' = Total Length ~ 39,500' or 7.5 miles) Clear and grub AC $30, $1,500,000 Clear all nuisance plants full width Cut and fill (single trail) CY $10 20,000 $200,000 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $10 10,600 $106,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $150 4,400 $660,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $150 2,670 $400,500 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $22 33,600 $739,200 6" bank run shell Base (dbl. trail) SY $22 33,500 $737,000 6" bank run shell Subbase (single trail) SY $11 5,000 $55,000 Build base as needed in poor soils Subbase (dbl. trail) SY $11 10,000 $110,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $20 5,000 $100,000 Chain link type as needed Ped/bike railing LF $70 1,500 $105,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $25, $900,000 Border trees and bushes as needed Sod, seeding SY $3 130,000 $390,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $60,000 1 $60,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $6, $192,000 drainage pipe and structures Pond/swale construction EA $30,000 6 $180,000 pond/swale construction SubTotal $7,024,200
114 Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $1,125,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $375,000 Est. 0.5 contam. sites per mile Surface water remediation MI $100, $375,000 Est. 0.5 sites per mile Steel and tie/timber credit MI -$50, $375,000 Est. 0.5 contam. sites per mile SubTotal $1,725,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10, $130,000 all road intersections SubTotal $1,095,500 Shelters Approach paths EA $2,000 8 $16,000 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $6,000 8 $48,000 foundation cost Landscaping EA $5,000 8 $40,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work EA $8,000 8 $64,000 general site prep. SubTotal $44,000 $352,000
115 Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges Main A LS $525,000 1 $525,000 Prefab. Steel Truss bridge with foundations Main B LS $325,000 1 $325,000 Prefab. Steel Truss bridge with foundations SubTotal $850,000 Utilities Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,270,000 Mobilization 3.0% $380,000 MOT 2.0% $250,000 Geotech and misc. Testing 2.0% $250,000 Additional items 4.0% $510,000 Contingency 10.0% $1,270,000 Asbuilts, close-out 2.0% $250,000 SubTotal $4,180,000 Project Cost Estimate Total $16,846,700
116 ( This Page Blank.)
117 Rails-with-Trails Option Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 17,800' + Separated Trail length ~ 21,700' = Total Length ~ 39,500' or 7.5 miles) Clearing and grubbing AC $38, $1,900,000 Clear all nuisance plants full width Cut and fill (single trail) CY $12 15,800 $189,600 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $13 22,000 $286,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $180 3,050 $549,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $180 4,240 $763,200 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $27 33,600 $907,200 6" bank run shell Base (dbl. trail) SY $28 48,200 $1,349,600 6" bank run shell Subbase (single trail) SY $14 15,800 $221,200 Build base as needed in poor soils Subbase (dbl. trail) SY $14 24,000 $336,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $24 5,000 $120,000 Chain link type as needed Ped/bike railing LF $84 1,500 $126,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $30, $1,080,000 Border trees and bushes as needed Sod, seeding SY $4 130,000 $455,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $75,000 1 $75,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $7, $240,000 drainage pipe and structures Pond/swale construction EA $36,000 6 $216,000 pond/swale construction SubTotal $9,403,300
118 Rails-with-Trails Option Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $75,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $750,000 Est. 1 contam. Location per mile Surface water remediation MI $100, $750,000 Est. 1 Location per mile Steel and tie/timber credit MI -$50, $25,000 Est. 1 contam. Location per mile SubTotal $1,775,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10,000 0 $0 all road intersections SubTotal $965,500 Shelters Approach paths EA $2,400 8 $19,200 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $7,200 8 $57,600 foundation cost Landscaping EA $6,000 8 $48,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work, benches, trash can, etc. EA $8,000 8 $64,000 general site prep. SubTotal $46,600 $372,800
119 Rails-with-Trails Option Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges (2) over Philippi Creek Main A LS $625,000 1 $625,000 Prefab. Steel Truss bridge with foundations Main B LS $390,000 1 $390,000 Prefab. Steel Truss bridge with foundations SubTotal $1,015,000 Utilities at Trail Heads and Shelters w/ Water Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,520,000 Mobilization 3.0% $450,000 MOT 3.0% $450,000 Geotech and misc. Testing 2.0% $300,000 Additional items 4.0% $610,000 Contingency 10.0% $1,520,000 Asbuilts, close-out 2.0% $300,000 SubTotal $5,150,000 Project Cost Estimate Total $20,301,600
120 Cost Unit Descriptions UNIT AC CY EA LF LS MI NM SF SY TN DESCRIPTION Acre Cubic Yard Each Linear Foot Lump Sum Mile Net Mile Square Foot Square Yard Ton
121 Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 25,800' + Separated Trail length ~ 13,700' = Total Length ~ 39,500' or 7.5 miles) Clear and grub AC $30, $1,500,000 Clear all nuisance plants full width Cut and fill (single trail) CY $10 20,000 $200,000 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $10 10,600 $106,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $150 4,400 $660,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $150 2,670 $400,500 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $22 33,600 $739,200 6" bank run shell Base (dbl. trail) SY $22 33,500 $737,000 6" bank run shell Subbase (single trail) SY $11 5,000 $55,000 Build base as needed in poor soils Subbase (dbl. trail) SY $11 10,000 $110,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $20 5,000 $100,000 Chain link type as needed Ped/bike railing LF $70 1,500 $105,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $25, $900,000 Border trees and bushes as needed Sod, seeding SY $3 130,000 $390,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $60,000 1 $60,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $6, $192,000 drainage pipe and structures Pond/swale construction EA $30,000 6 $180,000 pond/swale construction SubTotal $7,024,200
122 Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $1,125,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $375,000 Est. 0.5 contam. sites per mile Surface water remediation MI $100, $375,000 Est. 0.5 sites per mile Steel and tie/timber credit MI -$50, $375,000 Est. 0.5 contam. sites per mile SubTotal $1,725,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10, $130,000 all road intersections SubTotal $1,095,500 Shelters Approach paths EA $2,000 8 $16,000 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $6,000 8 $48,000 foundation cost Landscaping EA $5,000 8 $40,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work EA $8,000 8 $64,000 general site prep. SubTotal $44,000 $352,000
123 Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges Main A LS $525,000 1 $525,000 Prefab. Steel Truss bridge with foundations Main B LS $325,000 1 $325,000 Prefab. Steel Truss bridge with foundations SubTotal $850,000 Utilities Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,270,000 Mobilization 3.0% $380,000 MOT 2.0% $250,000 Geotech and misc. Testing 2.0% $250,000 Additional items 4.0% $510,000 Contingency 10.0% $1,270,000 Asbuilts, close-out 2.0% $250,000 SubTotal $4,180,000 Project Cost Estimate Total $16,846,700
124 ( This Page Blank.)
125 Rails-with-Trails Option Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 17,800' + Separated Trail length ~ 21,700' = Total Length ~ 39,500' or 7.5 miles) Clearing and grubbing AC $38, $1,900,000 Clear all nuisance plants full width Cut and fill (single trail) CY $12 15,800 $189,600 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $13 22,000 $286,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $180 3,050 $549,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $180 4,240 $763,200 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $27 33,600 $907,200 6" bank run shell Base (dbl. trail) SY $28 48,200 $1,349,600 6" bank run shell Subbase (single trail) SY $14 15,800 $221,200 Build base as needed in poor soils Subbase (dbl. trail) SY $14 24,000 $336,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $24 5,000 $120,000 Chain link type as needed Ped/bike railing LF $84 1,500 $126,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $30, $1,080,000 Border trees and bushes as needed Sod, seeding SY $4 130,000 $455,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $75,000 1 $75,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $7, $240,000 drainage pipe and structures Pond/swale construction EA $36,000 6 $216,000 pond/swale construction SubTotal $9,403,300
126 Rails-with-Trails Option Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $75,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $750,000 Est. 1 contam. Location per mile Surface water remediation MI $100, $750,000 Est. 1 Location per mile Steel and tie/timber credit MI -$50, $25,000 Est. 1 contam. Location per mile SubTotal $1,775,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10,000 0 $0 all road intersections SubTotal $965,500 Shelters Approach paths EA $2,400 8 $19,200 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $7,200 8 $57,600 foundation cost Landscaping EA $6,000 8 $48,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work, benches, trash can, etc. EA $8,000 8 $64,000 general site prep. SubTotal $46,600 $372,800
127 Rails-with-Trails Option Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges (2) over Philippi Creek Main A LS $625,000 1 $625,000 Prefab. Steel Truss bridge with foundations Main B LS $390,000 1 $390,000 Prefab. Steel Truss bridge with foundations SubTotal $1,015,000 Utilities at Trail Heads and Shelters w/ Water Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,520,000 Mobilization 3.0% $450,000 MOT 3.0% $450,000 Geotech and misc. Testing 2.0% $300,000 Additional items 4.0% $610,000 Contingency 10.0% $1,520,000 Asbuilts, close-out 2.0% $300,000 SubTotal $5,150,000 Project Cost Estimate Total $20,301,600
128 Cost Unit Descriptions UNIT AC CY EA LF LS MI NM SF SY TN DESCRIPTION Acre Cubic Yard Each Linear Foot Lump Sum Mile Net Mile Square Foot Square Yard Ton
129 Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 25,800' + Separated Trail length ~ 13,700' = Total Length ~ 39,500' or 7.5 miles) Clear and grub AC $30, $1,500,000 Clear all nuisance plants full width Cut and fill (single trail) CY $10 20,000 $200,000 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $10 10,600 $106,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $150 4,400 $660,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $150 2,670 $400,500 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $22 33,600 $739,200 6" bank run shell Base (dbl. trail) SY $22 33,500 $737,000 6" bank run shell Subbase (single trail) SY $11 5,000 $55,000 Build base as needed in poor soils Subbase (dbl. trail) SY $11 10,000 $110,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $20 5,000 $100,000 Chain link type as needed Ped/bike railing LF $70 1,500 $105,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $25, $900,000 Border trees and bushes as needed Sod, seeding SY $3 130,000 $390,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $60,000 1 $60,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $6, $192,000 drainage pipe and structures Pond/swale construction EA $30,000 6 $180,000 pond/swale construction SubTotal $7,024,200
130 Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $1,125,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $375,000 Est. 0.5 contam. sites per mile Surface water remediation MI $100, $375,000 Est. 0.5 sites per mile Steel and tie/timber credit MI -$50, $375,000 Est. 0.5 contam. sites per mile SubTotal $1,725,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10, $130,000 all road intersections SubTotal $1,095,500 Shelters Approach paths EA $2,000 8 $16,000 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $6,000 8 $48,000 foundation cost Landscaping EA $5,000 8 $40,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work EA $8,000 8 $64,000 general site prep. SubTotal $44,000 $352,000
131 Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges Main A LS $525,000 1 $525,000 Prefab. Steel Truss bridge with foundations Main B LS $325,000 1 $325,000 Prefab. Steel Truss bridge with foundations SubTotal $850,000 Utilities Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,270,000 Mobilization 3.0% $380,000 MOT 2.0% $250,000 Geotech and misc. Testing 2.0% $250,000 Additional items 4.0% $510,000 Contingency 10.0% $1,270,000 Asbuilts, close-out 2.0% $250,000 SubTotal $4,180,000 Project Cost Estimate Total $16,846,700
132 ( This Page Blank.)
133 Rails-with-Trails Option Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 17,800' + Separated Trail length ~ 21,700' = Total Length ~ 39,500' or 7.5 miles) Clearing and grubbing AC $38, $1,900,000 Clear all nuisance plants full width Cut and fill (single trail) CY $12 15,800 $189,600 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $13 22,000 $286,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $180 3,050 $549,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $180 4,240 $763,200 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $27 33,600 $907,200 6" bank run shell Base (dbl. trail) SY $28 48,200 $1,349,600 6" bank run shell Subbase (single trail) SY $14 15,800 $221,200 Build base as needed in poor soils Subbase (dbl. trail) SY $14 24,000 $336,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $24 5,000 $120,000 Chain link type as needed Ped/bike railing LF $84 1,500 $126,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $30, $1,080,000 Border trees and bushes as needed Sod, seeding SY $4 130,000 $455,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $75,000 1 $75,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $7, $240,000 drainage pipe and structures Pond/swale construction EA $36,000 6 $216,000 pond/swale construction SubTotal $9,403,300
134 Rails-with-Trails Option Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $75,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $750,000 Est. 1 contam. Location per mile Surface water remediation MI $100, $750,000 Est. 1 Location per mile Steel and tie/timber credit MI -$50, $25,000 Est. 1 contam. Location per mile SubTotal $1,775,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10,000 0 $0 all road intersections SubTotal $965,500 Shelters Approach paths EA $2,400 8 $19,200 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $7,200 8 $57,600 foundation cost Landscaping EA $6,000 8 $48,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work, benches, trash can, etc. EA $8,000 8 $64,000 general site prep. SubTotal $46,600 $372,800
135 Rails-with-Trails Option Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges (2) over Philippi Creek Main A LS $625,000 1 $625,000 Prefab. Steel Truss bridge with foundations Main B LS $390,000 1 $390,000 Prefab. Steel Truss bridge with foundations SubTotal $1,015,000 Utilities at Trail Heads and Shelters w/ Water Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,520,000 Mobilization 3.0% $450,000 MOT 3.0% $450,000 Geotech and misc. Testing 2.0% $300,000 Additional items 4.0% $610,000 Contingency 10.0% $1,520,000 Asbuilts, close-out 2.0% $300,000 SubTotal $5,150,000 Project Cost Estimate Total $20,301,600
136 Cost Unit Descriptions UNIT AC CY EA LF LS MI NM SF SY TN DESCRIPTION Acre Cubic Yard Each Linear Foot Lump Sum Mile Net Mile Square Foot Square Yard Ton
137 Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 25,800' + Separated Trail length ~ 13,700' = Total Length ~ 39,500' or 7.5 miles) Clear and grub AC $30, $1,500,000 Clear all nuisance plants full width Cut and fill (single trail) CY $10 20,000 $200,000 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $10 10,600 $106,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $150 4,400 $660,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $150 2,670 $400,500 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $22 33,600 $739,200 6" bank run shell Base (dbl. trail) SY $22 33,500 $737,000 6" bank run shell Subbase (single trail) SY $11 5,000 $55,000 Build base as needed in poor soils Subbase (dbl. trail) SY $11 10,000 $110,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $20 5,000 $100,000 Chain link type as needed Ped/bike railing LF $70 1,500 $105,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $25, $900,000 Border trees and bushes as needed Sod, seeding SY $3 130,000 $390,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $60,000 1 $60,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $6, $192,000 drainage pipe and structures Pond/swale construction EA $30,000 6 $180,000 pond/swale construction SubTotal $7,024,200
138 Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $1,125,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $375,000 Est. 0.5 contam. sites per mile Surface water remediation MI $100, $375,000 Est. 0.5 sites per mile Steel and tie/timber credit MI -$50, $375,000 Est. 0.5 contam. sites per mile SubTotal $1,725,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10, $130,000 all road intersections SubTotal $1,095,500 Shelters Approach paths EA $2,000 8 $16,000 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $6,000 8 $48,000 foundation cost Landscaping EA $5,000 8 $40,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work EA $8,000 8 $64,000 general site prep. SubTotal $44,000 $352,000
139 Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges Main A LS $525,000 1 $525,000 Prefab. Steel Truss bridge with foundations Main B LS $325,000 1 $325,000 Prefab. Steel Truss bridge with foundations SubTotal $850,000 Utilities Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,270,000 Mobilization 3.0% $380,000 MOT 2.0% $250,000 Geotech and misc. Testing 2.0% $250,000 Additional items 4.0% $510,000 Contingency 10.0% $1,270,000 Asbuilts, close-out 2.0% $250,000 SubTotal $4,180,000 Project Cost Estimate Total $16,846,700
140 ( This Page Blank.)
141 Rails-with-Trails Option Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 17,800' + Separated Trail length ~ 21,700' = Total Length ~ 39,500' or 7.5 miles) Clearing and grubbing AC $38, $1,900,000 Clear all nuisance plants full width Cut and fill (single trail) CY $12 15,800 $189,600 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $13 22,000 $286,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $180 3,050 $549,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $180 4,240 $763,200 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $27 33,600 $907,200 6" bank run shell Base (dbl. trail) SY $28 48,200 $1,349,600 6" bank run shell Subbase (single trail) SY $14 15,800 $221,200 Build base as needed in poor soils Subbase (dbl. trail) SY $14 24,000 $336,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $24 5,000 $120,000 Chain link type as needed Ped/bike railing LF $84 1,500 $126,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $30, $1,080,000 Border trees and bushes as needed Sod, seeding SY $4 130,000 $455,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $75,000 1 $75,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $7, $240,000 drainage pipe and structures Pond/swale construction EA $36,000 6 $216,000 pond/swale construction SubTotal $9,403,300
142 Rails-with-Trails Option Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $75,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $750,000 Est. 1 contam. Location per mile Surface water remediation MI $100, $750,000 Est. 1 Location per mile Steel and tie/timber credit MI -$50, $25,000 Est. 1 contam. Location per mile SubTotal $1,775,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10,000 0 $0 all road intersections SubTotal $965,500 Shelters Approach paths EA $2,400 8 $19,200 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $7,200 8 $57,600 foundation cost Landscaping EA $6,000 8 $48,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work, benches, trash can, etc. EA $8,000 8 $64,000 general site prep. SubTotal $46,600 $372,800
143 Rails-with-Trails Option Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges (2) over Philippi Creek Main A LS $625,000 1 $625,000 Prefab. Steel Truss bridge with foundations Main B LS $390,000 1 $390,000 Prefab. Steel Truss bridge with foundations SubTotal $1,015,000 Utilities at Trail Heads and Shelters w/ Water Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,520,000 Mobilization 3.0% $450,000 MOT 3.0% $450,000 Geotech and misc. Testing 2.0% $300,000 Additional items 4.0% $610,000 Contingency 10.0% $1,520,000 Asbuilts, close-out 2.0% $300,000 SubTotal $5,150,000 Project Cost Estimate Total $20,301,600
144 Cost Unit Descriptions UNIT AC CY EA LF LS MI NM SF SY TN DESCRIPTION Acre Cubic Yard Each Linear Foot Lump Sum Mile Net Mile Square Foot Square Yard Ton
145 Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 25,800' + Separated Trail length ~ 13,700' = Total Length ~ 39,500' or 7.5 miles) Clear and grub AC $30, $1,500,000 Clear all nuisance plants full width Cut and fill (single trail) CY $10 20,000 $200,000 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $10 10,600 $106,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $150 4,400 $660,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $150 2,670 $400,500 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $22 33,600 $739,200 6" bank run shell Base (dbl. trail) SY $22 33,500 $737,000 6" bank run shell Subbase (single trail) SY $11 5,000 $55,000 Build base as needed in poor soils Subbase (dbl. trail) SY $11 10,000 $110,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $20 5,000 $100,000 Chain link type as needed Ped/bike railing LF $70 1,500 $105,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $25, $900,000 Border trees and bushes as needed Sod, seeding SY $3 130,000 $390,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $60,000 1 $60,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $6, $192,000 drainage pipe and structures Pond/swale construction EA $30,000 6 $180,000 pond/swale construction SubTotal $7,024,200
146 Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $1,125,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $375,000 Est. 0.5 contam. sites per mile Surface water remediation MI $100, $375,000 Est. 0.5 sites per mile Steel and tie/timber credit MI -$50, $375,000 Est. 0.5 contam. sites per mile SubTotal $1,725,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10, $130,000 all road intersections SubTotal $1,095,500 Shelters Approach paths EA $2,000 8 $16,000 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $6,000 8 $48,000 foundation cost Landscaping EA $5,000 8 $40,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work EA $8,000 8 $64,000 general site prep. SubTotal $44,000 $352,000
147 Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges Main A LS $525,000 1 $525,000 Prefab. Steel Truss bridge with foundations Main B LS $325,000 1 $325,000 Prefab. Steel Truss bridge with foundations SubTotal $850,000 Utilities Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,270,000 Mobilization 3.0% $380,000 MOT 2.0% $250,000 Geotech and misc. Testing 2.0% $250,000 Additional items 4.0% $510,000 Contingency 10.0% $1,270,000 Asbuilts, close-out 2.0% $250,000 SubTotal $4,180,000 Project Cost Estimate Total $16,846,700
148 ( This Page Blank.)
149 Rails-with-Trails Option Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 17,800' + Separated Trail length ~ 21,700' = Total Length ~ 39,500' or 7.5 miles) Clearing and grubbing AC $38, $1,900,000 Clear all nuisance plants full width Cut and fill (single trail) CY $12 15,800 $189,600 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $13 22,000 $286,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $180 3,050 $549,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $180 4,240 $763,200 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $27 33,600 $907,200 6" bank run shell Base (dbl. trail) SY $28 48,200 $1,349,600 6" bank run shell Subbase (single trail) SY $14 15,800 $221,200 Build base as needed in poor soils Subbase (dbl. trail) SY $14 24,000 $336,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $24 5,000 $120,000 Chain link type as needed Ped/bike railing LF $84 1,500 $126,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $30, $1,080,000 Border trees and bushes as needed Sod, seeding SY $4 130,000 $455,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $75,000 1 $75,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $7, $240,000 drainage pipe and structures Pond/swale construction EA $36,000 6 $216,000 pond/swale construction SubTotal $9,403,300
150 Rails-with-Trails Option Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $75,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $750,000 Est. 1 contam. Location per mile Surface water remediation MI $100, $750,000 Est. 1 Location per mile Steel and tie/timber credit MI -$50, $25,000 Est. 1 contam. Location per mile SubTotal $1,775,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10,000 0 $0 all road intersections SubTotal $965,500 Shelters Approach paths EA $2,400 8 $19,200 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $7,200 8 $57,600 foundation cost Landscaping EA $6,000 8 $48,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work, benches, trash can, etc. EA $8,000 8 $64,000 general site prep. SubTotal $46,600 $372,800
151 Rails-with-Trails Option Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges (2) over Philippi Creek Main A LS $625,000 1 $625,000 Prefab. Steel Truss bridge with foundations Main B LS $390,000 1 $390,000 Prefab. Steel Truss bridge with foundations SubTotal $1,015,000 Utilities at Trail Heads and Shelters w/ Water Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,520,000 Mobilization 3.0% $450,000 MOT 3.0% $450,000 Geotech and misc. Testing 2.0% $300,000 Additional items 4.0% $610,000 Contingency 10.0% $1,520,000 Asbuilts, close-out 2.0% $300,000 SubTotal $5,150,000 Project Cost Estimate Total $20,301,600
152 Cost Unit Descriptions UNIT AC CY EA LF LS MI NM SF SY TN DESCRIPTION Acre Cubic Yard Each Linear Foot Lump Sum Mile Net Mile Square Foot Square Yard Ton
153 Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 25,800' + Separated Trail length ~ 13,700' = Total Length ~ 39,500' or 7.5 miles) Clear and grub AC $30, $1,500,000 Clear all nuisance plants full width Cut and fill (single trail) CY $10 20,000 $200,000 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $10 10,600 $106,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $150 4,400 $660,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $150 2,670 $400,500 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $22 33,600 $739,200 6" bank run shell Base (dbl. trail) SY $22 33,500 $737,000 6" bank run shell Subbase (single trail) SY $11 5,000 $55,000 Build base as needed in poor soils Subbase (dbl. trail) SY $11 10,000 $110,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $20 5,000 $100,000 Chain link type as needed Ped/bike railing LF $70 1,500 $105,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $25, $900,000 Border trees and bushes as needed Sod, seeding SY $3 130,000 $390,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $60,000 1 $60,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $6, $192,000 drainage pipe and structures Pond/swale construction EA $30,000 6 $180,000 pond/swale construction SubTotal $7,024,200
154 Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $1,125,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $375,000 Est. 0.5 contam. sites per mile Surface water remediation MI $100, $375,000 Est. 0.5 sites per mile Steel and tie/timber credit MI -$50, $375,000 Est. 0.5 contam. sites per mile SubTotal $1,725,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10, $130,000 all road intersections SubTotal $1,095,500 Shelters Approach paths EA $2,000 8 $16,000 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $6,000 8 $48,000 foundation cost Landscaping EA $5,000 8 $40,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work EA $8,000 8 $64,000 general site prep. SubTotal $44,000 $352,000
155 Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges Main A LS $525,000 1 $525,000 Prefab. Steel Truss bridge with foundations Main B LS $325,000 1 $325,000 Prefab. Steel Truss bridge with foundations SubTotal $850,000 Utilities Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,270,000 Mobilization 3.0% $380,000 MOT 2.0% $250,000 Geotech and misc. Testing 2.0% $250,000 Additional items 4.0% $510,000 Contingency 10.0% $1,270,000 Asbuilts, close-out 2.0% $250,000 SubTotal $4,180,000 Project Cost Estimate Total $16,846,700
156 ( This Page Blank.)
157 Rails-with-Trails Option Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 17,800' + Separated Trail length ~ 21,700' = Total Length ~ 39,500' or 7.5 miles) Clearing and grubbing AC $38, $1,900,000 Clear all nuisance plants full width Cut and fill (single trail) CY $12 15,800 $189,600 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $13 22,000 $286,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $180 3,050 $549,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $180 4,240 $763,200 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $27 33,600 $907,200 6" bank run shell Base (dbl. trail) SY $28 48,200 $1,349,600 6" bank run shell Subbase (single trail) SY $14 15,800 $221,200 Build base as needed in poor soils Subbase (dbl. trail) SY $14 24,000 $336,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $24 5,000 $120,000 Chain link type as needed Ped/bike railing LF $84 1,500 $126,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $30, $1,080,000 Border trees and bushes as needed Sod, seeding SY $4 130,000 $455,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $75,000 1 $75,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $7, $240,000 drainage pipe and structures Pond/swale construction EA $36,000 6 $216,000 pond/swale construction SubTotal $9,403,300
158 Rails-with-Trails Option Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $75,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $750,000 Est. 1 contam. Location per mile Surface water remediation MI $100, $750,000 Est. 1 Location per mile Steel and tie/timber credit MI -$50, $25,000 Est. 1 contam. Location per mile SubTotal $1,775,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10,000 0 $0 all road intersections SubTotal $965,500 Shelters Approach paths EA $2,400 8 $19,200 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $7,200 8 $57,600 foundation cost Landscaping EA $6,000 8 $48,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work, benches, trash can, etc. EA $8,000 8 $64,000 general site prep. SubTotal $46,600 $372,800
159 Rails-with-Trails Option Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges (2) over Philippi Creek Main A LS $625,000 1 $625,000 Prefab. Steel Truss bridge with foundations Main B LS $390,000 1 $390,000 Prefab. Steel Truss bridge with foundations SubTotal $1,015,000 Utilities at Trail Heads and Shelters w/ Water Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,520,000 Mobilization 3.0% $450,000 MOT 3.0% $450,000 Geotech and misc. Testing 2.0% $300,000 Additional items 4.0% $610,000 Contingency 10.0% $1,520,000 Asbuilts, close-out 2.0% $300,000 SubTotal $5,150,000 Project Cost Estimate Total $20,301,600
160 Cost Unit Descriptions UNIT AC CY EA LF LS MI NM SF SY TN DESCRIPTION Acre Cubic Yard Each Linear Foot Lump Sum Mile Net Mile Square Foot Square Yard Ton
161 Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 25,800' + Separated Trail length ~ 13,700' = Total Length ~ 39,500' or 7.5 miles) Clear and grub AC $30, $1,500,000 Clear all nuisance plants full width Cut and fill (single trail) CY $10 20,000 $200,000 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $10 10,600 $106,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $150 4,400 $660,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $150 2,670 $400,500 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $22 33,600 $739,200 6" bank run shell Base (dbl. trail) SY $22 33,500 $737,000 6" bank run shell Subbase (single trail) SY $11 5,000 $55,000 Build base as needed in poor soils Subbase (dbl. trail) SY $11 10,000 $110,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $20 5,000 $100,000 Chain link type as needed Ped/bike railing LF $70 1,500 $105,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $25, $900,000 Border trees and bushes as needed Sod, seeding SY $3 130,000 $390,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $60,000 1 $60,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $6, $192,000 drainage pipe and structures Pond/swale construction EA $30,000 6 $180,000 pond/swale construction SubTotal $7,024,200
162 Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $1,125,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $375,000 Est. 0.5 contam. sites per mile Surface water remediation MI $100, $375,000 Est. 0.5 sites per mile Steel and tie/timber credit MI -$50, $375,000 Est. 0.5 contam. sites per mile SubTotal $1,725,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10, $130,000 all road intersections SubTotal $1,095,500 Shelters Approach paths EA $2,000 8 $16,000 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $6,000 8 $48,000 foundation cost Landscaping EA $5,000 8 $40,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work EA $8,000 8 $64,000 general site prep. SubTotal $44,000 $352,000
163 Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges Main A LS $525,000 1 $525,000 Prefab. Steel Truss bridge with foundations Main B LS $325,000 1 $325,000 Prefab. Steel Truss bridge with foundations SubTotal $850,000 Utilities Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,270,000 Mobilization 3.0% $380,000 MOT 2.0% $250,000 Geotech and misc. Testing 2.0% $250,000 Additional items 4.0% $510,000 Contingency 10.0% $1,270,000 Asbuilts, close-out 2.0% $250,000 SubTotal $4,180,000 Project Cost Estimate Total $16,846,700
164 ( This Page Blank.)
165 Rails-with-Trails Option Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 17,800' + Separated Trail length ~ 21,700' = Total Length ~ 39,500' or 7.5 miles) Clearing and grubbing AC $38, $1,900,000 Clear all nuisance plants full width Cut and fill (single trail) CY $12 15,800 $189,600 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $13 22,000 $286,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $180 3,050 $549,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $180 4,240 $763,200 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $27 33,600 $907,200 6" bank run shell Base (dbl. trail) SY $28 48,200 $1,349,600 6" bank run shell Subbase (single trail) SY $14 15,800 $221,200 Build base as needed in poor soils Subbase (dbl. trail) SY $14 24,000 $336,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $24 5,000 $120,000 Chain link type as needed Ped/bike railing LF $84 1,500 $126,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $30, $1,080,000 Border trees and bushes as needed Sod, seeding SY $4 130,000 $455,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $75,000 1 $75,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $7, $240,000 drainage pipe and structures Pond/swale construction EA $36,000 6 $216,000 pond/swale construction SubTotal $9,403,300
166 Rails-with-Trails Option Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $75,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $750,000 Est. 1 contam. Location per mile Surface water remediation MI $100, $750,000 Est. 1 Location per mile Steel and tie/timber credit MI -$50, $25,000 Est. 1 contam. Location per mile SubTotal $1,775,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10,000 0 $0 all road intersections SubTotal $965,500 Shelters Approach paths EA $2,400 8 $19,200 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $7,200 8 $57,600 foundation cost Landscaping EA $6,000 8 $48,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work, benches, trash can, etc. EA $8,000 8 $64,000 general site prep. SubTotal $46,600 $372,800
167 Rails-with-Trails Option Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges (2) over Philippi Creek Main A LS $625,000 1 $625,000 Prefab. Steel Truss bridge with foundations Main B LS $390,000 1 $390,000 Prefab. Steel Truss bridge with foundations SubTotal $1,015,000 Utilities at Trail Heads and Shelters w/ Water Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,520,000 Mobilization 3.0% $450,000 MOT 3.0% $450,000 Geotech and misc. Testing 2.0% $300,000 Additional items 4.0% $610,000 Contingency 10.0% $1,520,000 Asbuilts, close-out 2.0% $300,000 SubTotal $5,150,000 Project Cost Estimate Total $20,301,600
168 Cost Unit Descriptions UNIT AC CY EA LF LS MI NM SF SY TN DESCRIPTION Acre Cubic Yard Each Linear Foot Lump Sum Mile Net Mile Square Foot Square Yard Ton
169 Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 25,800' + Separated Trail length ~ 13,700' = Total Length ~ 39,500' or 7.5 miles) Clear and grub AC $30, $1,500,000 Clear all nuisance plants full width Cut and fill (single trail) CY $10 20,000 $200,000 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $10 10,600 $106,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $150 4,400 $660,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $150 2,670 $400,500 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $22 33,600 $739,200 6" bank run shell Base (dbl. trail) SY $22 33,500 $737,000 6" bank run shell Subbase (single trail) SY $11 5,000 $55,000 Build base as needed in poor soils Subbase (dbl. trail) SY $11 10,000 $110,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $20 5,000 $100,000 Chain link type as needed Ped/bike railing LF $70 1,500 $105,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $25, $900,000 Border trees and bushes as needed Sod, seeding SY $3 130,000 $390,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $60,000 1 $60,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $6, $192,000 drainage pipe and structures Pond/swale construction EA $30,000 6 $180,000 pond/swale construction SubTotal $7,024,200
170 Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $1,125,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $375,000 Est. 0.5 contam. sites per mile Surface water remediation MI $100, $375,000 Est. 0.5 sites per mile Steel and tie/timber credit MI -$50, $375,000 Est. 0.5 contam. sites per mile SubTotal $1,725,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10, $130,000 all road intersections SubTotal $1,095,500 Shelters Approach paths EA $2,000 8 $16,000 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $6,000 8 $48,000 foundation cost Landscaping EA $5,000 8 $40,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work EA $8,000 8 $64,000 general site prep. SubTotal $44,000 $352,000
171 Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges Main A LS $525,000 1 $525,000 Prefab. Steel Truss bridge with foundations Main B LS $325,000 1 $325,000 Prefab. Steel Truss bridge with foundations SubTotal $850,000 Utilities Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,270,000 Mobilization 3.0% $380,000 MOT 2.0% $250,000 Geotech and misc. Testing 2.0% $250,000 Additional items 4.0% $510,000 Contingency 10.0% $1,270,000 Asbuilts, close-out 2.0% $250,000 SubTotal $4,180,000 Project Cost Estimate Total $16,846,700
172 ( This Page Blank.)
173 Rails-with-Trails Option Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 17,800' + Separated Trail length ~ 21,700' = Total Length ~ 39,500' or 7.5 miles) Clearing and grubbing AC $38, $1,900,000 Clear all nuisance plants full width Cut and fill (single trail) CY $12 15,800 $189,600 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $13 22,000 $286,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $180 3,050 $549,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $180 4,240 $763,200 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $27 33,600 $907,200 6" bank run shell Base (dbl. trail) SY $28 48,200 $1,349,600 6" bank run shell Subbase (single trail) SY $14 15,800 $221,200 Build base as needed in poor soils Subbase (dbl. trail) SY $14 24,000 $336,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $24 5,000 $120,000 Chain link type as needed Ped/bike railing LF $84 1,500 $126,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $30, $1,080,000 Border trees and bushes as needed Sod, seeding SY $4 130,000 $455,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $75,000 1 $75,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $7, $240,000 drainage pipe and structures Pond/swale construction EA $36,000 6 $216,000 pond/swale construction SubTotal $9,403,300
174 Rails-with-Trails Option Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $75,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $750,000 Est. 1 contam. Location per mile Surface water remediation MI $100, $750,000 Est. 1 Location per mile Steel and tie/timber credit MI -$50, $25,000 Est. 1 contam. Location per mile SubTotal $1,775,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10,000 0 $0 all road intersections SubTotal $965,500 Shelters Approach paths EA $2,400 8 $19,200 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $7,200 8 $57,600 foundation cost Landscaping EA $6,000 8 $48,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work, benches, trash can, etc. EA $8,000 8 $64,000 general site prep. SubTotal $46,600 $372,800
175 Rails-with-Trails Option Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges (2) over Philippi Creek Main A LS $625,000 1 $625,000 Prefab. Steel Truss bridge with foundations Main B LS $390,000 1 $390,000 Prefab. Steel Truss bridge with foundations SubTotal $1,015,000 Utilities at Trail Heads and Shelters w/ Water Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,520,000 Mobilization 3.0% $450,000 MOT 3.0% $450,000 Geotech and misc. Testing 2.0% $300,000 Additional items 4.0% $610,000 Contingency 10.0% $1,520,000 Asbuilts, close-out 2.0% $300,000 SubTotal $5,150,000 Project Cost Estimate Total $20,301,600
176 Cost Unit Descriptions UNIT AC CY EA LF LS MI NM SF SY TN DESCRIPTION Acre Cubic Yard Each Linear Foot Lump Sum Mile Net Mile Square Foot Square Yard Ton
177 Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 25,800' + Separated Trail length ~ 13,700' = Total Length ~ 39,500' or 7.5 miles) Clear and grub AC $30, $1,500,000 Clear all nuisance plants full width Cut and fill (single trail) CY $10 20,000 $200,000 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $10 10,600 $106,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $150 4,400 $660,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $150 2,670 $400,500 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $22 33,600 $739,200 6" bank run shell Base (dbl. trail) SY $22 33,500 $737,000 6" bank run shell Subbase (single trail) SY $11 5,000 $55,000 Build base as needed in poor soils Subbase (dbl. trail) SY $11 10,000 $110,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $20 5,000 $100,000 Chain link type as needed Ped/bike railing LF $70 1,500 $105,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $25, $900,000 Border trees and bushes as needed Sod, seeding SY $3 130,000 $390,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $60,000 1 $60,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $6, $192,000 drainage pipe and structures Pond/swale construction EA $30,000 6 $180,000 pond/swale construction SubTotal $7,024,200
178 Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $1,125,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $375,000 Est. 0.5 contam. sites per mile Surface water remediation MI $100, $375,000 Est. 0.5 sites per mile Steel and tie/timber credit MI -$50, $375,000 Est. 0.5 contam. sites per mile SubTotal $1,725,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10, $130,000 all road intersections SubTotal $1,095,500 Shelters Approach paths EA $2,000 8 $16,000 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $6,000 8 $48,000 foundation cost Landscaping EA $5,000 8 $40,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work EA $8,000 8 $64,000 general site prep. SubTotal $44,000 $352,000
179 Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges Main A LS $525,000 1 $525,000 Prefab. Steel Truss bridge with foundations Main B LS $325,000 1 $325,000 Prefab. Steel Truss bridge with foundations SubTotal $850,000 Utilities Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,270,000 Mobilization 3.0% $380,000 MOT 2.0% $250,000 Geotech and misc. Testing 2.0% $250,000 Additional items 4.0% $510,000 Contingency 10.0% $1,270,000 Asbuilts, close-out 2.0% $250,000 SubTotal $4,180,000 Project Cost Estimate Total $16,846,700
180 ( This Page Blank.)
181 Rails-with-Trails Option Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 17,800' + Separated Trail length ~ 21,700' = Total Length ~ 39,500' or 7.5 miles) Clearing and grubbing AC $38, $1,900,000 Clear all nuisance plants full width Cut and fill (single trail) CY $12 15,800 $189,600 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $13 22,000 $286,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $180 3,050 $549,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $180 4,240 $763,200 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $27 33,600 $907,200 6" bank run shell Base (dbl. trail) SY $28 48,200 $1,349,600 6" bank run shell Subbase (single trail) SY $14 15,800 $221,200 Build base as needed in poor soils Subbase (dbl. trail) SY $14 24,000 $336,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $24 5,000 $120,000 Chain link type as needed Ped/bike railing LF $84 1,500 $126,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $30, $1,080,000 Border trees and bushes as needed Sod, seeding SY $4 130,000 $455,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $75,000 1 $75,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $7, $240,000 drainage pipe and structures Pond/swale construction EA $36,000 6 $216,000 pond/swale construction SubTotal $9,403,300
182 Rails-with-Trails Option Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $75,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $750,000 Est. 1 contam. Location per mile Surface water remediation MI $100, $750,000 Est. 1 Location per mile Steel and tie/timber credit MI -$50, $25,000 Est. 1 contam. Location per mile SubTotal $1,775,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10,000 0 $0 all road intersections SubTotal $965,500 Shelters Approach paths EA $2,400 8 $19,200 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $7,200 8 $57,600 foundation cost Landscaping EA $6,000 8 $48,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work, benches, trash can, etc. EA $8,000 8 $64,000 general site prep. SubTotal $46,600 $372,800
183 Rails-with-Trails Option Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges (2) over Philippi Creek Main A LS $625,000 1 $625,000 Prefab. Steel Truss bridge with foundations Main B LS $390,000 1 $390,000 Prefab. Steel Truss bridge with foundations SubTotal $1,015,000 Utilities at Trail Heads and Shelters w/ Water Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,520,000 Mobilization 3.0% $450,000 MOT 3.0% $450,000 Geotech and misc. Testing 2.0% $300,000 Additional items 4.0% $610,000 Contingency 10.0% $1,520,000 Asbuilts, close-out 2.0% $300,000 SubTotal $5,150,000 Project Cost Estimate Total $20,301,600
184 Cost Unit Descriptions UNIT AC CY EA LF LS MI NM SF SY TN DESCRIPTION Acre Cubic Yard Each Linear Foot Lump Sum Mile Net Mile Square Foot Square Yard Ton
185 Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 25,800' + Separated Trail length ~ 13,700' = Total Length ~ 39,500' or 7.5 miles) Clear and grub AC $30, $1,500,000 Clear all nuisance plants full width Cut and fill (single trail) CY $10 20,000 $200,000 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $10 10,600 $106,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $150 4,400 $660,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $150 2,670 $400,500 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $22 33,600 $739,200 6" bank run shell Base (dbl. trail) SY $22 33,500 $737,000 6" bank run shell Subbase (single trail) SY $11 5,000 $55,000 Build base as needed in poor soils Subbase (dbl. trail) SY $11 10,000 $110,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $20 5,000 $100,000 Chain link type as needed Ped/bike railing LF $70 1,500 $105,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $25, $900,000 Border trees and bushes as needed Sod, seeding SY $3 130,000 $390,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $60,000 1 $60,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $6, $192,000 drainage pipe and structures Pond/swale construction EA $30,000 6 $180,000 pond/swale construction SubTotal $7,024,200
186 Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $1,125,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $375,000 Est. 0.5 contam. sites per mile Surface water remediation MI $100, $375,000 Est. 0.5 sites per mile Steel and tie/timber credit MI -$50, $375,000 Est. 0.5 contam. sites per mile SubTotal $1,725,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10, $130,000 all road intersections SubTotal $1,095,500 Shelters Approach paths EA $2,000 8 $16,000 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $6,000 8 $48,000 foundation cost Landscaping EA $5,000 8 $40,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work EA $8,000 8 $64,000 general site prep. SubTotal $44,000 $352,000
187 Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges Main A LS $525,000 1 $525,000 Prefab. Steel Truss bridge with foundations Main B LS $325,000 1 $325,000 Prefab. Steel Truss bridge with foundations SubTotal $850,000 Utilities Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,270,000 Mobilization 3.0% $380,000 MOT 2.0% $250,000 Geotech and misc. Testing 2.0% $250,000 Additional items 4.0% $510,000 Contingency 10.0% $1,270,000 Asbuilts, close-out 2.0% $250,000 SubTotal $4,180,000 Project Cost Estimate Total $16,846,700
188 ( This Page Blank.)
189 Rails-with-Trails Option Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 17,800' + Separated Trail length ~ 21,700' = Total Length ~ 39,500' or 7.5 miles) Clearing and grubbing AC $38, $1,900,000 Clear all nuisance plants full width Cut and fill (single trail) CY $12 15,800 $189,600 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $13 22,000 $286,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $180 3,050 $549,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $180 4,240 $763,200 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $27 33,600 $907,200 6" bank run shell Base (dbl. trail) SY $28 48,200 $1,349,600 6" bank run shell Subbase (single trail) SY $14 15,800 $221,200 Build base as needed in poor soils Subbase (dbl. trail) SY $14 24,000 $336,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $24 5,000 $120,000 Chain link type as needed Ped/bike railing LF $84 1,500 $126,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $30, $1,080,000 Border trees and bushes as needed Sod, seeding SY $4 130,000 $455,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $75,000 1 $75,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $7, $240,000 drainage pipe and structures Pond/swale construction EA $36,000 6 $216,000 pond/swale construction SubTotal $9,403,300
190 Rails-with-Trails Option Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $75,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $750,000 Est. 1 contam. Location per mile Surface water remediation MI $100, $750,000 Est. 1 Location per mile Steel and tie/timber credit MI -$50, $25,000 Est. 1 contam. Location per mile SubTotal $1,775,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10,000 0 $0 all road intersections SubTotal $965,500 Shelters Approach paths EA $2,400 8 $19,200 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $7,200 8 $57,600 foundation cost Landscaping EA $6,000 8 $48,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work, benches, trash can, etc. EA $8,000 8 $64,000 general site prep. SubTotal $46,600 $372,800
191 Rails-with-Trails Option Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges (2) over Philippi Creek Main A LS $625,000 1 $625,000 Prefab. Steel Truss bridge with foundations Main B LS $390,000 1 $390,000 Prefab. Steel Truss bridge with foundations SubTotal $1,015,000 Utilities at Trail Heads and Shelters w/ Water Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,520,000 Mobilization 3.0% $450,000 MOT 3.0% $450,000 Geotech and misc. Testing 2.0% $300,000 Additional items 4.0% $610,000 Contingency 10.0% $1,520,000 Asbuilts, close-out 2.0% $300,000 SubTotal $5,150,000 Project Cost Estimate Total $20,301,600
192 Cost Unit Descriptions UNIT AC CY EA LF LS MI NM SF SY TN DESCRIPTION Acre Cubic Yard Each Linear Foot Lump Sum Mile Net Mile Square Foot Square Yard Ton
193 Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 25,800' + Separated Trail length ~ 13,700' = Total Length ~ 39,500' or 7.5 miles) Clear and grub AC $30, $1,500,000 Clear all nuisance plants full width Cut and fill (single trail) CY $10 20,000 $200,000 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $10 10,600 $106,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $150 4,400 $660,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $150 2,670 $400,500 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $22 33,600 $739,200 6" bank run shell Base (dbl. trail) SY $22 33,500 $737,000 6" bank run shell Subbase (single trail) SY $11 5,000 $55,000 Build base as needed in poor soils Subbase (dbl. trail) SY $11 10,000 $110,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $20 5,000 $100,000 Chain link type as needed Ped/bike railing LF $70 1,500 $105,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $25, $900,000 Border trees and bushes as needed Sod, seeding SY $3 130,000 $390,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $60,000 1 $60,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $6, $192,000 drainage pipe and structures Pond/swale construction EA $30,000 6 $180,000 pond/swale construction SubTotal $7,024,200
194 Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $1,125,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $375,000 Est. 0.5 contam. sites per mile Surface water remediation MI $100, $375,000 Est. 0.5 sites per mile Steel and tie/timber credit MI -$50, $375,000 Est. 0.5 contam. sites per mile SubTotal $1,725,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10, $130,000 all road intersections SubTotal $1,095,500 Shelters Approach paths EA $2,000 8 $16,000 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $6,000 8 $48,000 foundation cost Landscaping EA $5,000 8 $40,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work EA $8,000 8 $64,000 general site prep. SubTotal $44,000 $352,000
195 Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges Main A LS $525,000 1 $525,000 Prefab. Steel Truss bridge with foundations Main B LS $325,000 1 $325,000 Prefab. Steel Truss bridge with foundations SubTotal $850,000 Utilities Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,270,000 Mobilization 3.0% $380,000 MOT 2.0% $250,000 Geotech and misc. Testing 2.0% $250,000 Additional items 4.0% $510,000 Contingency 10.0% $1,270,000 Asbuilts, close-out 2.0% $250,000 SubTotal $4,180,000 Project Cost Estimate Total $16,846,700
196 ( This Page Blank.)
197 Rails-with-Trails Option Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 17,800' + Separated Trail length ~ 21,700' = Total Length ~ 39,500' or 7.5 miles) Clearing and grubbing AC $38, $1,900,000 Clear all nuisance plants full width Cut and fill (single trail) CY $12 15,800 $189,600 Move cut and fill soil. Add as needed. Cut and fill (dbl. trail) CY $13 22,000 $286,000 Move cut and fill soil. Add as needed. Asphalt path (single trail) TN $180 3,050 $549,000 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Asphalt path (dbl. trail) TN $180 4,240 $763,200 2" thick = 2"*110#/SY*45,000'/3*15'/3/2000 Base (single trail) SY $27 33,600 $907,200 6" bank run shell Base (dbl. trail) SY $28 48,200 $1,349,600 6" bank run shell Subbase (single trail) SY $14 15,800 $221,200 Build base as needed in poor soils Subbase (dbl. trail) SY $14 24,000 $336,000 Build base as needed in poor soils Striping NM $4, $48,000 Per standards - center and skip Signage - all MI $4, $30,000 Avg. 20 signs per $200 ea. Fence LF $24 5,000 $120,000 Chain link type as needed Ped/bike railing LF $84 1,500 $126,000 Railing on gravity wall and steep slopes Furniture MI $3, $22,500 Benches, trash cans, bike racks, etc. Landscaping AC $30, $1,080,000 Border trees and bushes as needed Sod, seeding SY $4 130,000 $455,000 cover all disturbed areas Conduit w/ comm. Fiber LF $5 40,000 $200,000 single run, full length Emergency phones EA $ $9,000 emergency solar phone Gravity wall LF $ $280,000 At deep cuts. Environ. protection LS $75,000 1 $75,000 Silt fence, inlet prot., etc. Drainage structures & pipe EA $7, $240,000 drainage pipe and structures Pond/swale construction EA $36,000 6 $216,000 pond/swale construction SubTotal $9,403,300
198 Rails-with-Trails Option Contamination Testing & Removal Corridor Testing LS $225,000 1 $225,000 Contam. Test every 500' x 5 sta. RR rail and tie removal MI $150, $75,000 Remove rails & ties - 95% contam. Soil remediation MI $100, $750,000 Est. 1 contam. Location per mile Surface water remediation MI $100, $750,000 Est. 1 Location per mile Steel and tie/timber credit MI -$50, $25,000 Est. 1 contam. Location per mile SubTotal $1,775,000 Intersections Mast arm / signals assemblies EA $22, $352,000 7 roadway intersections Signage & Striping LS $4, $52,000 additional signage at intersections Median EA $15,000 7 $105,000 reconstruct per plans Street lighting LS $1, $19,500 intersection lighting all Approach curb and ramps EA $3, $78,000 2 sides of 13 intersections Removal of conc. & asph. + Replace LS $10,000 5 $50,000 correcting roadway as needed Power supply w/ UPS EA $10,000 8 $80,000 power for signals Controller assembly EA $20,000 8 $160,000 controllers for signals Detection EA $5,000 9 $45,000 vehicle detection Conduit and wire - complete EA $3,000 8 $24,000 wiring at signals Remove RR signals & arms LS $10,000 0 $0 all road intersections SubTotal $965,500 Shelters Approach paths EA $2,400 8 $19,200 additional trail length - complete Shelter building EA $20,000 8 $160,000 structure cost Shelter foundation EA $7,200 8 $57,600 foundation cost Landscaping EA $6,000 8 $48,000 trees, shrubs, sod, mulch Lighting EA $2,000 8 $16,000 site lights Signage EA $1,000 8 $8,000 site signs Site work, benches, trash can, etc. EA $8,000 8 $64,000 general site prep. SubTotal $46,600 $372,800
199 Rails-with-Trails Option Trail Heads Entrance roads EA $40,000 4 $160,000 vehicle road costs Parking LS $40,000 4 $160,000 parking Shelter building EA $120,000 4 $480,000 structure cost Restroom building EA $60,000 4 $240,000 bathroom cost Landscaping LS $10,000 4 $40,000 trees, shrubs, sod, mulch Lighting LS $10,000 4 $40,000 site lights Signage LS $5,000 4 $20,000 site signs Clearing & grubbing LS $10,000 4 $40,000 clear site Site work - misc. LS $25,000 4 $100,000 general site prep. Site electrical LS $20,000 4 $80,000 site electrical - all SubTotal $340,000 $1,360,000 Bridges (2) over Philippi Creek Main A LS $625,000 1 $625,000 Prefab. Steel Truss bridge with foundations Main B LS $390,000 1 $390,000 Prefab. Steel Truss bridge with foundations SubTotal $1,015,000 Utilities at Trail Heads and Shelters w/ Water Water - potable EA $20,000 6 $120,000 water at 6 stations Sewer EA $20,000 5 $100,000 bathrooms at 4 Trail Heads + 1 shelter Reclaim (irrigation) EA $10,000 4 $40,000 irrigation at 4 Trail Heads SubTotal $260,000 Project - General Design and Survey 10.0% $1,520,000 Mobilization 3.0% $450,000 MOT 3.0% $450,000 Geotech and misc. Testing 2.0% $300,000 Additional items 4.0% $610,000 Contingency 10.0% $1,520,000 Asbuilts, close-out 2.0% $300,000 SubTotal $5,150,000 Project Cost Estimate Total $20,301,600
200 Cost Unit Descriptions UNIT AC CY EA LF LS MI NM SF SY TN DESCRIPTION Acre Cubic Yard Each Linear Foot Lump Sum Mile Net Mile Square Foot Square Yard Ton
UNIT PRICE LIST January 2009
UNIT PRICE LIST January 2009 1 INTRODUCTION The purpose of the Unit Price List is to provide a resource for the preparation of cost estimates for subdivisions and permit projects and should be used only
Description Quantity Cost Total Cost
APPENDIX: ITEMIZED CONSTRUCTION COST ESTIMATE Description Quantity Cost Total Cost 1 CASCADE FALLS 1a Existing Cascade Falls Upgrades Structural Repairs - Steps, Railing, Walls, Pool Lump Sum $500,000
STORM WATER PROJECT COST ESTIMATES & LOCATION MAPS. Appendix F
STORM WATER PROJECT COST ESTIMATES & LOCATION MAPS Appendix F RIVERDALE CITY CAPITAL FACILITIES PLAN STORM DRAINAGE Engineer's Cost Estimate January 2009 Project Name: 4400 South Street - Piping and Collection
Demo Existing Curb Demo Existing Asphalt Roadway Demo Asphalt Saw Cutting Protection Fence - 4 Snow Fence with T posts
SECTION 00300 BID FORM S For additions and deletions to the Contract, the following unit prices shall be applicable for the specific items listed. Unit Prices shall be complete, in place including required
A. Structures Quantity Item Price Cost @ $3,500 EA
PRINCE WILLIAM COUNTY Department of Development Services Land Development Division UNIT PRICE LIST (Performance Bonds, Landscaping Escrows, and Siltation & Erosion Control Escrows) Revised: November 17,
Figure 3 Pipe Cracking
The illustration shown below depicts the system analyzed. As-built drawings and survey information were not available; aerial photos and survey shots of inverts were used to determine the system s geometries.
NOTICE TO CONTRACTORS. CALL ORDER 700 FEDERAL PROJECT NO. STPD-6-2(122) LOCATION: US-34/US-6,CULBERTSON-McCOOK COUNTIES: HITCHCOCK RED WILLOW
NOTICE TO CONTRACTORS CALL ORDER 700 FEDERAL PROJECT NO. STPD-6-2(122) LOCATION: US-34/US-6,CULBERTSON-McCOOK COUNTIES: HITCHCOCK RED WILLOW The Nebraska Department of Roads will receive sealed bids in
Chapter 22. Lump Sum Project Guidelines
Chapter 22 Lump Sum Project Guidelines 22.1 General...22-1 22.2 Project Selection...22-3 22.3 Plans Preparation...22-5 22.4 Preliminary Estimate...22-7 22.5 Specifications...22-9 22.6 Contracts Administration...22-11
FY11 Sanitary Sewer Main Rehab and Point Repair Bid Tabulation
644-10-569 Page 1 of 9 1 FOR CLEANING AND TELEVISING EXISTING SEWERS, AS SPECIFIED, ANY REQUIRED CLEANING, ANY LOCATION, ANY LENGTH OF SEWER, COMPLETE IN PLACE, FOR VARIOUS PIPE DIAMETERS. A. EXISTING
Los Angeles County Department Of Public Works. Land Development Division. Bond Calculation Sheets
Los Angeles County Department Of Public Works Land Development Division Bond Calculation Sheets Effective July 1, 2015 COUNTY OF LOS ANGELES DEPARTMENT OF PUBLIC WORKS LAND DEVELOPMENT DIVISION ROADS COST
PROJECT COST ESTIMATE ASSUMPTIONS AND EXCLUSIONS
C PROJECT ESTIMATE ASSUMPTIONS AND EXCLUSIONS In support of the alternatives development process, preliminary cost estimates were prepared for each of the three Candidate Build Alternatives. The cost estimates
Roadway Cost Per Centerline Mile Revised June 2014
Rural Arterial From LRE MOT * Mobilization * Subtotal Total PE Design (15%) CEI (15%) Total Project ** New (2-Lane Roadway) with 5' Paved Shoulders $3,351,896 $335,190 $368,709 $4,055,794 $1,013,949 $5,069,743
FY08 SEWER POINT REPAIRS BID TABULATION
6-07-831 Page 1 of 12 1 FOR CLEANING AND TELEVISING EXISTING SEWERS, AS SPECIFIED, ANY REQUIRED CLEANING, ANY LOCATION, ANY LENGTH OF SEWER, COMPLETE IN PLACE, FOR VARIOUS PIPE DIAMETERS. A. EXISTING "
SANITARY SEWER PROJECT COST ESTIMATES & LOCATION MAPS. Appendix D
SANITARY SEWER PROJECT COST ESTIMATES & LOCATION MAPS Appendix D RIVERDALE CITY CAPITAL FACILITIES PLAN SANITARY SEWER Engineer's Cost Estimate January 2009 Project Name: Riverdale Road - Rumbi Grill -
EXHIBIT A Accessible Truck Routes Map
EXHIBIT A Accessible Truck Routes Map ASHEVILLE, NORTH CAROLINA ROUTE: A ROUTE: B ROUTE: C ROUTE: D ROUTE: E EXHIBIT A EXHIBIT B Craven Street Improvements Map ASHEVILLE, NORTH CAROLINA EXHIBIT B EXHIBIT
The unit costs are based on the trend line of the 3 low bids for the average quantity.
Page 1 of 8 COST ESTIMATE GENERAL INSTRUCTIONS The unit costs are based on the trend line of the 3 low bids for the average quantity. Apply the Unit Costs to ordinary structures. Unit Costs should generally
Jackson Gulch Outlet Canal Rehabilitation Project
Jackson Gulch Outlet Canal Rehabilitation Project Preliminary Budgetary Estimate for Rehabilitation February 2004 Prepared for the Mancos Water Conservancy District Jackson Gulch Reservoir 42888 County
Walkable Communities Florida Department of Transportation State Safety Office Pedestrian and Bicycle Program April 1995 www.dot.state.fl.us/safety Twelve Steps for an Effective Program Page 1 Twelve Steps
Riverside County Transportation Department Summary of Bids
Bids Open: 2 pm Date: Wednesday, March 4, 2015 BASE BID SCHEDULE 1 - Rudell Road Reconstruction Project NO. CODE CONTRACT PROJECT No. B3-0470 and C4-0069 COUNTY'S ESTIMATE 1 All American Asphalt Corona,
MAIN STREET IMPROVEMENTS Water, Sewer, Stormwater and Streetscape Improvements
MAIN STREET IMPROVEMENTS Water, Sewer, Stormwater and Streetscape Improvements Presentation July 23, 2014 A. Morton Thomas and Associates, Inc. 800 King Farm Boulevard, 4 th Floor Rockville, Maryland 20850
WILDCAT CANYON ROAD SPECIFICATION NO. 16-11001 SLIDE REPAIR BIDDER'S PROPOSAL (continued)
BIDDER'S PROPOSAL (continued) Item Estimated No. Description Quantity Unit Unit Cost Total Cost BASE BID 1 Traffic Control 1 LS $ $ 2 Construction Area Signs 1 LS $ $ 3 Excavation Safety 1 LS $ $ 4 Reset
FLORIDA DEPARTMENT OF TRANSPORTATION GUIDELINE FOR
FLORIDA DEPARTMENT OF TRANSPORTATION GUIDELINE FOR ESTABLISHING CONSTRUCTION CONTRACT DURATION July 2010 DISCLAIMER: The following documentation as a whole was derived from Federal Highway Administration
FDOT Specifications List
FDOT Specifications List TABLE OF CONTENTS DIVISION II CONSTRUCTION DETAILS CLEARING CONSTRUCTION SITE 110 Clearing and Grubbing... 152 EARTHWORK AND RELATED OPERATIONS 120 Excavation and Embankment...
MIAMI BLUFFS COMMUNITY ASSOCIATION LINE ITEM BUDGET (9058)
MIAMI BLUFFS COMMUNITY ASSOCIATION LINE ITEM BUDGET (9058) Contract 2006 Year Dec. YTD 2007 Year Dec. YTD 2008 Annual INCOME: Fee Income: Association Fee (605000) Builder Fee (605890) Prepaid Fees (601350)
RED RIVER DIVERSION FARGO MOORHEAD METRO FLOOD RISK MANAGEMENT PROJECT, FEASIBILITY STUDY, PHASE 4
RED RIVER DIVERSION FARGO MOORHEAD METRO FLOOD RISK MANAGEMENT PROJECT, FEASIBILITY STUDY, PHASE 4 APPENDIX G COST ESTIMATES EXHIBIT J RAILROAD BRIDGE QUANTITIES Report for the US Army Corps of Engineers,
Surface Transportation Program (STP)
Project Name: Project Sponsor: FEDERAL FUNDS PROJECT APPLICATION TRANSPORTATION IMPROVEMENT PROGRAM 2008-2013 SALT LAKE and OGDEN/ LAYTON URBAN AREAS Surface Transportation Program (STP) Urban Surface
ADDENDUM NO. 1. Manchester Boston Regional Airport, City of Manchester, NH
Hoyle, Tanner Project No. 093145 ADDENDUM NO. 1 Manchester Boston Regional Airport, City of Manchester, NH Construct Relocated Roadway Airport Service Rd. Outside Runway Object Free Area (ROFA); Construct
SECTION 13 REPLACEMENT AND CLEANUP 13.01 SCOPE OF WORK
13.01 SCOPE OF WORK Under this item, the Contractor will restore all lawns, trees, gardens, landscape plantings, sidewalks, ramps, trails, fences, commercial signs, water courses and sand, gravel, dirt,
Helen Mercury Mine EE/CA OPINION OF PROBABLE COST
G Cost Estimates Helen Mercury Mine EE/CA Alternative 2: Limited Action 3 Minor Road Improvements 4 Clear & Grub diversion channel areas 5 Surveying 6 Cleanup & Demobilization 7 Pull back of material 8
Item No. 432S Portland Cement Concrete Sidewalks. 432S.1 Description
Item No. 432S Portland Cement Concrete Sidewalks 432S.1 This item shall govern the construction of Portland cement concrete sidewalks (Standard Detail No. 432S-1), as herein specified, on an approved subgrade
Planning Level Cost Estimation Tool. User s Manual
Planning Level Cost Estimation Tool User s Manual Atlanta Regional Commission Submitted By: User s Manual Table of Contents 1. INTRODUCTION... 1 2. OBJECTIVE... 1 3. FRAMEWORK OF THE TOOL... 2 4. HOW TO
Preliminary Design Report Clay County, Florida Carpet n Drapes Culvert Repair and Rehabilitation July 21, 2006
Clay County, Florida Carpet n Drapes Culvert Repair and Rehabilitation July 21, 2006 1.0 Background and Repair and Rehabilitation Recommendation Clay County has contracted Camp Dresser & McKee Inc. (CDM)
CITY OF VISTA STANDARD DRAWINGS (PRELIMINARY, FOR REVIEW)
CITY OF VISTA STANDARD DRAWINGS (PRELIMINARY, FOR REVIEW) January, 2013 THIS SHEET INTENTIONALLY LEFT BLANK TABLE OF CONTENTS DRAINAGE STRUCTURES DRN-01 Corrugated metal pipe drop inlet DNR-02 Storm Drain
MICHIGAN AIRPORT DEVELOPMENT PROGRAM PACKAGE MDOT Office of Aeronautics. Airport Capital Improvement Plan 2014-2018
MICHIGAN AIRPORT DEVELOPMENT PROGRAM PACKAGE MDOT Office of Aeronautics Airport Capital Improvement Plan 20142018 Prepared for: West Michigan Regional Airport Holland, Michigan August 2013 Contact: Mr.
BMP-7. A sediment filter or an excavated impounding area around a storm drain drop inlet or curb inlet.
BMP-7 BMP: STORM DRAIN INLET PROTECTION Definition A sediment filter or an excavated impounding area around a storm drain drop inlet or curb inlet. To prevent sediment from entering storm drainage systems
BEST PRACTICES. Smart Transportation is a key concept for the Paoli Roadway Improvement Project.
Smart Transportation Smart Transportation is a key concept for the Paoli Roadway Improvement Project. PennDOT s Smart Transportation Guidebook (2008) outlines a comprehensive approach to transportation
APPENDIX C INLETS. The application and types of storm drainage inlets are presented in detail in this Appendix.
Storm Drainage 13-C-1 APPENDIX C INLETS 1.0 Introduction The application and types of storm drainage inlets are presented in detail in this Appendix. 2.0 Inlet Locations Inlets are required at locations
VILLAGE OF LOMBARD CONTRACT DOCUMENT NUMBER ST-09-06 BID PROPOSAL
VILLAGE OF LOMBARD CONTRACT DOCUMENT NUMBER ST-09-06 BID PROPOSAL I/We hereby agree to furnish to the Village of Lombard all necessary materials, equipment, and labor, to complete the North Industrial
TABLE OF CONTENTS. Manhole, Frame, and Cover Installation (includes Drop Manhole) Additional Manhole Depth
TABLE OF CONTENTS NO. MP-1 MP-2 MP-3 MP-4 MP-4.01 MP-4.02 MP-4.03 MP-5 MP-5.01 MP-5.02 MP-5.03 MP-5.04 MP-5.05 MP-5.06 MP-5.07 MP-5.08 MP-5.11 MP-5.12 MP-5.13 MP-5.14 MP-5.15 MP-5.16 MP-5.18 MP-5.19 MP-5.20
in Marina Del Rey Prepared by: County of Los Angeles Department of Public Works
Planned Public Works Projects in Marina Del Rey Prepared by: County of Los Angeles Department of Public Works Planned Projects in Marina Del Rey Waterline Projects Phase II Phase III Roadway Projects Admiralty
Town of Elkton & Cecil Soil Conservation District Checklist for Joint Agency Review Stormwater Management / Erosion and Sediment Control
Town of Elkton & Cecil Soil Conservation District Checklist for Joint Agency Review Stormwater Management / Erosion and Sediment Control Project Name: Tax Map Parcel: Acreage: Plat: ADC Map & Grid Engineering
Update on Previous Related Transportation Enhancement Grants
ROUND 16 ROUND 16 Update on Previous Related Transportation Enhancement Grants Pima County and City of Tucson staff are implementing the Pima County-Tucson Safe Routes to Schools Pilot Program. This program
FDOT DBE CERTIFICATION NAICS CODE GUIDE WITH CAP SIZES
NAICS CODE Highway, Street, and Bridge Construction SIZE CAP ($ MIL) 237310 Asphalt Roadway (includes 300, 320, 327, 330, 334, 336, 337, 338) Application of prime and tack coats, leveling surfaces and
Facility Summary. Facility Condition Summary. Seattle School District David T. Denny International Infrastructure. Facility Components
Infrastructure Facility Condition Summary Weighted Avg Condition Score Facility Components Systems Surveyor/ Date Done Comments G Sitework.9 Site Improvements Parking Pedestrian Paving Site Development
2006-2008 MHD BRIDGE SECTION WEIGHTED AVERAGE UNIT PRICES GUIDELINES FOR THE USE OF THE WEIGHTED AVERAGE UNIT PRICE TABULATION SHEETS
2006-2008 MHD BRIDGE SECTION WEIGHTED AVERAGE UNIT PRICES GUIDELINES FOR THE USE OF THE WEIGHTED AVERAGE UNIT PRICE TABULATION SHEETS GENERAL 10/16/2008 The listed average unit prices are based on the
PROPERTY EVALUATION AND RESERVE FUND STUDY
PROPERTY EVALUATION AND RESERVE FUND STUDY COMPLEX NORTH & WEST AVENUES LAS VEGAS, NV Prepared for: HOMEOWNER S ASSOCIATION Prepared by: CRITERIUM ENGINEERS 22 Monument Square Portland, ME 04101 CONTENTS
MONETARY GUARANTY PROCEDURE PACKAGE FREDERICK COUNTY, VIRGINIA
MONETARY GUARANTY PROCEDURE PACKAGE FREDERICK COUNTY, VIRGINIA Department of Planning and Development 107 North Kent Street, Suite 202 Winchester, Virginia 22601 Phone: (540) 665-5651 Fax: (540) 665-6395
Exhibit A Scope of Work
Exhibit A Scope of Work The agreement for S.P. 3116-142 (T.H. 169-Cross Range Expressway) includes final design plans for a 1.55 mile length of a 2 lane to 4 lane expansion project located 0.66 miles SW
Chapter 3 SENSITIVE AREAS AND VEGETATED CORRIDORS
Chapter 3 3.01 General Provisions 3.01.1 Introduction 3.01.2 Application and Interpretation of Chapter 3.01.3 Unbuildable Lots 3.01.4 Other Permits 3.01.5 Prohibited Activities 3.02 Service Provider Letter
SECTION 02221 SELECTIVE DEMOLITION
SECTION 02221 PART 1 -GENERAL 1.01 DESCRIPTION This section includes all material, labor, machinery and supervision required to demolish and remove the following items where applicable and as noted on
CID STREET INFRASTRUCTURE ASSESSMENT
ABSTRACT An evaluation of the street infrastructure in Foxberry Estates Phase 1, including pavement condition, verification of construction techniques, and subgrade quality. Recommendations and costs for
CITY OF SAN ANTONIO. Issued By: Transportation and Capital Improvements Date Issued: February 10, 2016 ID NO.: 23-01472-05-03
CITY OF SAN ANTONIO Issued By: Transportation and Capital Improvements Date Issued: February 10, 2016 ID NO.: 23-01472-05-03 (010) FORMAL INVITATION FOR BIDS (IFB) to CONTRACT 2016-2017 TASK ORDER CONTRACT
ADVERTISEMENT FOR BIDDERS
ADVERTISEMENT FOR BIDDERS Sealed Bids will be received by the City of Lookout Mountain, Georgia, 1214 Lulu Lake Road, Lookout Mountain, Georgia 30103, Attention: Brad Haven, City Manager until: for the
Developing Critical Path Method Scheduling (CPM)
Developing Critical Path Method Scheduling (CPM) Pretest 1. An activity which is on critical path has a planned duration of 5 days. What is the total float for the activity? a. 0 b. 1 c. 2 d. 3 Pretest
SUMMARY OF PUBLIC WORK STANDARD SPECIFICATION REVISIONS 2016
SUMMARY OF PUBLIC WORK STANDARD SPECIFICATION REVISIONS 2016 102.5 Bid Deposits The City of Madison bid deposit form is required for all bids unless a Biennial Bid Bond is on file or check deposit is used.
UNIVERSITY OF MISSISSIPPI FIXED ASSET CAPITALIZATION POLICY
UNIVERSITY OF MISSISSIPPI FIXED ASSET CAPITALIZATION POLICY The term capitalized fixed assets includes land, improvements to land, easements, buildings, building improvements, vehicles, machinery, furniture,
Bond Release Process for New Subdivision Developments in Fairfax County
Bond Release Process for New Subdivision Developments in Fairfax County An Overview for Homeowners Associations A Fairfax County, Va., publication April 2009 For more information or to request this document
Index. protection. excavated drop inlet protection (Temporary) 6.50.1 6.51.1. Block and gravel inlet Protection (Temporary) 6.52.1
6 Index inlet protection excavated drop inlet protection (Temporary) 6.50.1 HARDWARE CLOTH AND GRAVEL INLET PROTECTION Block and gravel inlet Protection (Temporary) sod drop inlet protection ROCK DOUGHNUT
TOWN OF SURFSIDE UTILITY UPGRADE PROJECT Project Completion
TOWN OF SURFSIDE UTILITY UPGRADE PROJECT Project Completion Project Overview Sanitary Sewer System 2 Town of Surfside Project Overview Potable Water System 3 Town of Surfside Project Overview Storm Water
CONSTRUCTION STORMWATER POLLUTION PREVENTION PLAN TEMPLATE
CONSTRUCTION STORMWATER POLLUTION PREVENTION PLAN TEMPLATE The following template may be used as a general guide for development of a Stormwater Pollution Prevention Plan (SWPPP) for construction activities.
How To Build A Road In A Townhouse
FDOT DBE CERTIFICATION SPECIALTY/ SHEET WITH CAP SIZES Highway, Street, and Bridge Construction SIZE CAP ($ MIL) 237310 Asphalt Roadway $ 22.41 Application of prime and tack coats, leveling surfaces and
1.0 INDEX TO SHEETS URGENT STORM DAMAGE REPAIR AVON PARK AIR FORCE RANGE LOCATION MAP LEGEND LOCATION MAP
5 INDEX TO SHEETS. NOTES AND TYPICAL SECTIONS. H. R. SMITH RD.CULVERT.3 0/5 END BARRIER ACCESS ROAD REPAIR. KISSIMMEE RD. AT MORGAN HOLE CR. ROAD REPAIR.5 RANGE INFRASTRUCTURE REPAIR N 0 000' 3 0,000'
SOLD. Lot 1. 1 Mile: Population: 10,200 Median HH Income: $33,100. 3 Mile: Population: 80,200 Median HH Income: $34,900
Walmart Outparcels For Sale College Station, TX Store # 1150 1815 Brothers Blvd FM 2818 W SOLD Texas Ave S/ Hwy 6 Longmire Dr Brothers Blvd Lot 1 For more information about this site, contact: Lot 1: ±2.41
BUSINESS DEVELOPMENT INITIATIVE SMALL BUSINESS PROGRAM GUIDANCE FOR RESERVING CONTRACTS
Construction/Maintenance Contracts and Design/Build Low Bid Contracts 1. Districts are responsible for reviewing their work program and identifying contracts that are good candidates for the Business Development
Herbicide Application. Irrigation System (Only) Sanitary System Testing & Inspections
NAICS Code Work Description Work Item 115310 - Support Activities for Forestry 221310 Water Supply and Irrigation Systems 221320 - Sewage Treatment Facilities 236118 Residential Remodelers 236220 Commercial
MTA UNIVERSAL STATION PEDESTRIAN BRIDGE Los Angeles, CA. Project Manual and Specification 100% PE SUBMITTAL TABLE OF CONTENTS
Los Angeles, CA Project Manual and Specification DIVISION 1 GENERAL CONDITIONS 01 01 10 STATEMENT OF WORK 01 11 00 SUMMARY OF THE WORK 01 14 05 METRO (OWNER) - DIRECTED STOPPAGES 01 20 00 PRICE AND PAYMENT
CD i -STREETS- Detail #
-STREETS- Detail # 3000 Vertical Curb, Gutter and Sidewalk 3010 Low-Profile Curb, Gutter and Sidewalk 3020 Rolled Curb, Gutter and Sidewalk 3030 Separated Sidewalk, Curb & Gutter 3040 Sidewalk Staged Construction
Summary Form. Partner Information. Project Information. Primary Contact Name: David Cosgrove Phone: 303-823-8250 Email: davec@townoflyons.
Summary Form Applicant Information Applicant Name: Town of Lyons Department of Parks, Recreation and Cultural Events Mailing Address: P.O. Box 49, Lyons CO 80540 Contact Name: David Cosgrove Telephone:
City of Shelbyville Site Inspection Checklist
City of Shelbyville Site Inspection Checklist General Information Project Name: KYR10 Permit Number: Date: Project Location: Contractor: Conractor Representative: Inspector's Name: Title: Signature : Weather
The Bond Release Process for New Subdivision Developments: An Overview for Homeowners Associations DRAFT 6-4-08. Revised 9-25-08
The Bond Release Process for New Subdivision Developments: An Overview for Homeowners Associations DRAFT 6-4-08. Revised 9-25-08 Fairfax County requires developers to post a performance bond if they are
Preliminary Plan Application and Checklist
ALL APPLICATIONS ARE DUE AT 12:00 NOON ON THE FILING DATE Office Use Only PRELIMINARY / REVISED PRELIMINARY PLAN $300.00 Fee Paid: $ Date Paid: ALL FIELDS HIGHLIGHTED IN RED ARE REQUIRED FIELDS Case No.:
Data Center Due Diligence List
Data Center Due Diligence List Name and address of site facility Date constructed Building owner/date purchased by current owner Name of previous owner Adjacent Property Descriptions North South East West
Moving Ruston Forward. City of Ruston Infrastructure Maintenance and Improvements
Moving Ruston Forward City of Ruston Infrastructure Maintenance and Improvements MLK Extension Project will be done in conjunction with proposed water and sewer improvements Connect Martin Luther King
STORMWATER MANAGEMENT CHECKLIST
STORMWATER MANAGEMENT CHECKLIST *This checklist must be completed and part of the Land Disturbing Permit submittal for review if the acreage disturbed is one (1) acre or more: I. SUPPORTING DATA Narrative
TREE # 3 CRITICAL ROOT ZONE = 4,536 SF AREA IMPACTED = 50 SF % IMPACTED = 1 % 87.2 80.5 35' BL VALVE IN BOX POP-UP EMITTER 74.7 CLEAN OUT BACKWATER
NOTES: 1. THE INSTALLATION OF EROSION AND SEDIMENTATION CONTROL MEASURES AND PRACTICES SHALL OCCUR PRIOR TO OR CONCURRENT WITH LAND-DISTURBING ACTIVITIES. 2. EROSION AND SEDIMENTATION CONTROL MEASURES
DRAFT MAINTAINING HOUSTON S STREETS REPAIR, REHABILITATION, RECONSTRUCTION. Using the Full Range of Tools for a Challenging Job
MAINTAINING HOUSTON S STREETS REPAIR, REHABILITATION, RECONSTRUCTION Using the Full Range of Tools for a Challenging Job Report To: TTI Committee May 13, 2014 1 Pavement Management - Suggested Treatments
Storm Drain Inlet Protection - IP
Storm Drain Inlet Protection - IP DEFINITION A temporary protective device formed around a storm drain drop inlet to trap sediment. PURPOSE To prevent sediment from entering storm drainage systems, prior
SITE-SPECIFIC BEST MANAGEMENT PRACTICES (SSBMP) PLAN/STORM WATER POLLUTION PREVENTION PLAN (SWPPP) REVIEW CHECKLIST
This checklist may be used by applicants for encroachment permits, and contractors in development of Site Specific Best Management Practice (SSBMP) Plans or Storm Water Pollution Prevention Plans (SWPPP)
Construction Site Inspection Checklist for OHC000004 By making use of some simple Best Management Practices (BMPs) a construction site operator can
Construction Site Inspection Checklist for OHC000004 By making use of some simple Best Management Practices (BMPs) a construction site operator can do his or her share to protect Ohio's water resources
Waterleaf ARB Application
To: Waterleaf ARB Application Waterleaf Architectural Review Board c/o Property Management Systems, Inc. P.O. Box 1987 Yulee, FL 32097-1987 From: Name: Address: City, State, Zip: Phone: Fax: Lot Number:
The fees listed below are stand-alone fees. Additional Developemnt Review or Stormwater fees may apply. 1.0. Fee Activity
MINOR & MISCELLANEOUS PERMITS The fees listed below are stand-alone fees. Additional Developemnt Review or Stormwater fees may apply. 1.0 Fee Activity Fee Description Fee 50% REDUCED FEES FOR SINGLE FAMILY
Building, Plumbing, Electrical and Residential Water and Sewer Inspection Requirements
Building, Plumbing, Electrical and Residential Water and Sewer Inspection Requirements Charles County Government Planning and Growth Management P.O. Box 2150, La Plata, MD 20646 (301) 645-0692 Schedule