DRILLED SHAFT CONSTRUCTION

Size: px
Start display at page:

Download "DRILLED SHAFT CONSTRUCTION"

Transcription

1 DRILLED SHAFT CONSTRUCTION West Tower Arthur Ravenel Jr. Bridge Photograph courtesy of Marvin Tallent, Palmetto Bridge Constructors Concrete Mix Design Considerations Dry Construction Method Wet Construction Method Casing Construction Method Equipment Inspection and Testing Slide 1 of 51

2 CONCRETE MIX DESIGN CONSIDERATIONS SCDOT Class 4000DS (see SCDOT 701) Aggregate Type Min. Cement Content (lbs/cy) Min. 28 day f'c (psi) % Fine to Coarse Aggregate Ratio Max. W/C Ratio Crushed : Stone : Type G or Type D w/ Type F Admixture Required Slump: 7-9 inches Nominal Coarse Aggregate: ¾ inch Slide 2 of 51

3 CONCRETE MIX DESIGN CONSIDERATIONS MassDOT LRFD Design Manual (2009) Section The minimum clearance between reinforcing bars shall be and is equal to 5 times the maximum coarse aggregate size (3 8 ) for both, the longitudinal bars as well as the spiral confinement reinforcement, to allow for better concrete consolidation during placement. Concrete mix design and workability shall be consistent for tremie or pump placement. In particular, the concrete slump should be 8 inches ± 1 inch for tremie or slurry construction and 7 inches ± 1 inch for all other conditions. Slide 3 of 51

4 CONCRETE MIX DESIGN CONSIDERATIONS Figure 1. Concrete Flow Under Tremie Placement (Brown and Schindler, 2007). Figure 3. Restriction of Lateral Flow (Brown and Schindler, 2007). Slide 4 of 51

5 CONCRETE MIX DESIGN CONSIDERATIONS Figure 5. Effects of Loss of Workability during Concrete Placement (Brown and Schindler, 2007). Figure 9-1. Free Fall Concrete Placement in a Dry Excavation (FHWA NHI ). Slide 5 of 51

6 CONCRETE MIX DESIGN CONSIDERATIONS Self Consolidating Concrete (SSC) Project for SCDOT (S&ME 2005). Slide 6 of 51

7 DRY METHOD (SCDOT ) Less than 6 inches of water per hour Sides and Bottom Remain Stable (Engineer can order 4 hours wait period) Loose material & water can be satisfactorily removed Temporary casing can be used Photograph courtesy of GPE Inc. Slide 7 of 51

8 STABLE vs. UNSTABLE SOILS Unstable Caving Soils Cohesive Soils Stable Non-Caving Soils Cohesive Soils Unstable caving soils prevent maintaining hole stability Water table Stable non-caving soils maintain hole stability Figures courtesy of FHWA NHI Drilled Shaft Foundation Inspection Course Slide 8 of 51

9 WATER TABLE AT OR BELOW THE SHAFT TIP ELEVATION Water table Stable Non-Caving Soils Cohesive Soils Water table Generally, soils cave at the water table preventing hole stability Water table below shaft tip does not impact hole stability Figures courtesy of FHWA NHI Drilled Shaft Foundation Inspection Course Slide 9 of 51

10 DRY METHOD CONSTRUCTION PROCESS Drill the shaft excavation Clean shaft by removing the cuttings & seepage water Position the reinforcing cage Clean & Place the concrete Drill Inspect Position Place Competent, Non-Caving Soils Figures courtesy of FHWA NHI Drilled Shaft Foundation Inspection Course Slide 10 of 51

11 DRY METHOD CONSTRUCTION PROCESS Continuous Operation. No delays > 12 hrs. No entering non-cased excavations. DRILL (SCDOT ) Photographs courtesy of WPC Inc. Slide 11 of 51

12 DRY METHOD CONSTRUCTION PROCESS CLEAN & INSPECT Photographs courtesy of WPC Inc. Slide 12 of 51

13 DRY METHOD CONSTRUCTION PROCESS INSPECTION OF EXCAVATION (SCDOT ) Need SCDOT Qualified Inspectors EXCAVATION CLEANLINESS (SCDOT D) 50% of Base has < ½ inch of sediment AND Maximum depth of sediment < 1 ½ inches Slide 13 of 51

14 DRY METHOD CONSTRUCTION PROCESS POSITION (SCDOT ) Spacers needed for 5 inch min. annulus. Spacer interval < 10 ft. Photographs courtesy of WPC Inc. Slide 14 of 51

15 DRY METHOD CONSTRUCTION PROCESS PLACE (SCDOT ) ASAP after reinforcement placement. Must be completed in 2 hours (unless approved). Tremie preferred. Tremie ID > 6 x Max. Aggregate Size AND > 10 inches. Tremie Embedment > 10 ft. Concrete flow: Positive pressure and continuous. Photograph courtesy of WPC Inc. Slide 15 of 51

16 DRY METHOD CONSTRUCTION PROCESS PLACE (SCDOT ) Photograph courtesy of WPC Inc. Freefall > 75 ft not permitted. Freefall Max. Aggregate Size ¾ inch, 7-9 inch slump. Freefall still needs chute. Must have tremie onsite. SCDOT can always order tremie. Slide 16 of 51

17 WET METHOD CONSTRUCTION PROCESS USE WHEN A DRY EXCAVATION CANNOT BE MAINTAINED SCDOT More than 6in in one hour = Wet Less than 6in in one hour = Dry Figure courtesy of FHWA NHI Drilled Shaft Foundation Inspection Course Slide 17 of 51

18 WET METHOD CONSTRUCTION PROCESS WHEN THE SIDES AND BOTTOM WHEN LOOSE MATERIAL AND OF THE HOLE CANNOT REMAIN WATER CANNOT BE STABLE SATISFACTORILY REMOVED Figures courtesy of FHWA NHI Drilled Shaft Foundation Inspection Course Slide 18 of 51

19 WET METHOD CONSTRUCTION PROCESS Drill Drill the shaft excavation Stabilize the hole (Plain water, slurry) Clean shaft by removing the cuttings & seepage water Position the reinforcing cage Place the concrete Stabilize Clean Position Place Figures courtesy of FHWA NHI Drilled Shaft Foundation Inspection Course Slide 19 of 51

20 WET METHOD CONSTRUCTION PROCESS There are two forms of wet shaft construction: Static Process Circulation Process Slide 20 of 51

21 Drill down to the piezometric level Slurry introduced Drilling Completed DRILLED DEEP FOUNDATIONS WET METHOD: STATIC PROCESS Hole Hole drilled cleaned to Drill completion of down slurry to & Slurry Piezometric depth cuttings added with to level hole slurry Cuttings are lifted from the hole Temporary surface casing installed (optional) Slurry Slurry Slurry Figures courtesy of FHWA NHI Drilled Shaft Foundation Inspection Course Piezometric level Piezometric level Piezometric level level Slide 21 of 51

22 WET METHOD: CIRCULATION PROCESS Hole is drilled Slurry level maintained at the ground surface Cuttings and sand, is circulated to the surface, where it is cleaned and reintroduced down the hole. Figures courtesy of FHWA NHI Drilled Shaft Foundation Inspection Course Piezometric level Piezometric level Slurry, with sand & Hole cuttings drilled is to re-circulated completion for processing depth withand reintroduced slurry level into hole. maintained at Hole ground cleaned level Temporary surface casing install (optional) Slurry Processor Slurry Processor Slide 22 of 51

23 WET METHOD CONSTRUCTION PROCESS SLURRY (SCDOT ) Photographs courtesy of FHWA NHI Drilled Shaft Foundation Inspection Course Slide 23 of 51

24 WET METHOD CONSTRUCTION PROCESS TYPES OF SLURRY Natural mineral clays Bentonite, attapulgite and sepiolite Bentonite is the most common Attapulgite and sepiolite are typically used in saltwater environments Must be hydrated Slide 24 of 51

25 WET METHOD CONSTRUCTION PROCESS SLURRY COMPARISONS Best Application Mixability Mix Water Sensitivity Mineral Cohesionless Difficult - Must be Hydrated Saltwater Sensitive Polymer Cohesive & Argillaceous Rock Easy Yes/No "Caking" Ability Best OK Suspension Ability Best OK Slide 25 of 51

26 WET METHOD CONSTRUCTION PROCESS CONTROLLING SLURRY Control tests are used to maintain proper slurry condition. Tests are conducted for: Density- the slurry weight Viscosity- flow: consistency ph- acidity: alkalinity Sand Content Slide 26 of 51

27 WET METHOD CONSTRUCTION PROCESS CONTROLLING SLURRY SCDOT MINERAL SLURRY ACCEPTABLE RANGES Property (Units) Value Introduction Value Concreting Test Method Density (pcf) * Density Balance Viscosity (sec/qt) Marsh Cone ph ph paper ph meter * Add 2 pcf in saltwater ** Sand Slide 27 of 51

28 WET METHOD CONSTRUCTION PROCESS CONTROLLING SLURRY FOR BOREHOLE STABILITY Proper Dosage and Solids Content for Proper Flowability and Cake Properties Thorough Mixing / Adequate Time for Hydration (Bentonite / Polymers) Maintenance of Head in Borehole Maintenance of ph, Hardness, Salts Minimize Pressures from Tools Slide 28 of 51

29 WET METHOD CONSTRUCTION PROCESS IMPROPER SLURRY CONTROL Fails to properly suspend and facilitate the removal of sediments and cuttings Does not control caving Does not control swelling of soils Hinders slurry displacement during concrete placement Leads to a dirty hole Slide 29 of 51

30 WET METHOD CONSTRUCTION PROCESS DIRTY HOLE Figures courtesy of FHWA IF Drilled Shafts: Construction Procedures and Design Methods. Slide 30 of 51

31 WET METHOD CONSTRUCTION PROCESS SLURRY EXAMPLES Poor Slurry Job Excellent Slurry Job Photographs courtesy of FHWA NHI Drilled Shaft Foundation Inspection Course Slide 31 of 51

32 CASING CONSTRUCTION METHOD SCDOT & Where an open hole cannot be maintained. Where soil or rock deformation will occur. Where constructing shafts below the water table or caving overburden. SCDOT Types: Construction (712.11B) & Temporary (712.11C) Photograph courtesy of FHWA NHI Drilled Shaft Foundation Inspection Course Slide 32 of 51

33 CASING CONSTRUCTION METHOD Photograph courtesy of WPC Inc. SCDOT Smooth, clean, watertight, w/ample strength Oversized must be approved by SCDOT. Temporary: Fresh concrete > 5 ft above hydrostatic pressure. Construction: Installed as one continuous unit. Welds are only approved connection. Slide 33 of 51

34 CASING CONSTRUCTION METHOD MassDOT LRFD Design Manual (2009) Section The Designer shall consider the intended method of construction (temporary or permanent casing, slurry drilling, etc.) and the resulting impact on the stiffness and resistance of the shaft. 4. When a drilled shaft is constructed with a permanent casing, the skin friction along the permanently cased portion of the shaft should be neglected. Slide 34 of 51

35 CASING CONSTRUCTION METHOD TELESCOPING CASING Not Permitted by SCDOT (see C) Photograph courtesy of FHWA NHI Drilled Shaft Foundation Inspection Course Slide 35 of 51

36 CASING METHOD: CONSTRUCTION PROCESS Drill the shaft excavation Install casing through caving soils and seal Clean shaft by removing the cuttings & seepage water Position the reinforcing cage Drill Case Clean Position Place Caving Soils Figures courtesy of FHWA NHI Drilled Shaft Foundation Inspection Course Slide 36 of 51

37 CASING CONSTRUCTION METHOD CONSTRUCTION (a.k.a. PERMANENT) CASING EXAMPLES Figures courtesy of FHWA IF Drilled Shafts: Construction Procedures and Design Methods. Slide 37 of 51

38 CASING CONSTRUCTION METHOD CONSTRUCTION (a.k.a. PERMANENT) CASING EXAMPLES Figures courtesy of FHWA IF Drilled Shafts: Construction Procedures and Design Methods. Slide 38 of 51

39 FULL-DEPTH CASING PROCESS Installation of Casing Drilling ahead of casing Remove casing Figures courtesy of FHWA NHI Drilled Shaft Foundation Inspection Course Figure 1. Concrete Flow Under Tremie Placement. Competent Soil Competent Competent Soil Soil Caving Soil Caving Caving Soil Soil Competent Soil Competent Competent Soil Soil Vibratory Driver Vibratory Driver Casing Water Table Casing Installation Remove Drilling casing ahead of Casing of casing Water Table Slide 39 of 51

40 CASING CONSTRUCTION METHOD TEMPORARY CASING REMOVAL (a) Prior to lifting casing (b) As Casing is Lifted. Figure 9-4. Concrete Pressure Head Requirement during Casing Extraction (FHWA NHI ). Slide 40 of 51

41 DRILLED SHAFT EQUIPMENT TERMINOLOGY Kelly Table Power Unit Crane Tool Photograph courtesy of FHWA NHI Drilled Shaft Foundation Inspection Course Slide 41 of 51

42 DRILLED SHAFT EQUIPMENT EARTH AUGERS Single Flight Double Flight Double Cut Triple Cut Earth augers are generally used in sands and cohesive materials. Photographs courtesy of FHWA NHI Drilled Shaft Foundation Inspection Course Slide 42 of 51

43 DRILLED SHAFT EQUIPMENT ROCK AUGERS Rock augers are generally used in soft to hard rock formations. Tapered Geometry Conical (Bullet) Carbide Teeth Photograph courtesy of FHWA NHI Drilled Shaft Foundation Inspection Course Slide 43 of 51

44 DRILLED SHAFT EQUIPMENT ROCK BITS This is typical of rock bits designed for drilling in hard to very hard rock. Circulating bit Replaceable Roller Bits Photograph courtesy of FHWA NHI Drilled Shaft Foundation Inspection Course Slide 44 of 51

45 DRILLED SHAFT EQUIPMENT DRILLING BUCKET Side Cutting Teeth Gouging Teeth Ripping Teeth Photograph courtesy of FHWA NHI Drilled Shaft Foundation Inspection Course Slide 45 of 51

46 DRILLED SHAFT EQUIPMENT CLEANOUT (MUCK) BUCKET This is typical of a cleanout (muck) bucket used to cleanout the cuttings and sediments from the bottom of the shaft. Photograph courtesy of FHWA NHI Drilled Shaft Foundation Inspection Course 6-51 Slide 46 of 51

47 DEEP FOUNDATION DESIGN GEOMATERIAL PROPERTIES NEEDED Table Geomaterial Properties Required for Drained and Undrained Axial Resistances (FHWA NHI ). Slide 47 of 51

48 DEEP FOUNDATION DESIGN AXIAL CAPACITY Q total = Q skin + Q tip Where: Q total = Ultimate Pile Capacity Q skin = Skin Friction (i.e. Side) Capacity Q tip = Tip (i.e. Toe) Capacity Slide 48 of 51

49 DEEP FOUNDATION DESIGN AXIAL CAPACITY Q skin = f s A skin Q toe = q p A toe Where: f s = Unit Skin Friction A skin = Pile Skin Area Where: q p = Unit End Bearing A toe = Pile Toe (i.e. Tip) Area Slide 49 of 51

50 DEEP FOUNDATION DESIGN GENERALIZED LOAD TRANSFER BEHAVIOR Q skin = R s Q toe = R b Figure 13-1 (FHWA NHI ). Slide 50 of 51

51 REFERENCES SCDOT Standard Specifications for Highway Construction (2000). SCDOT Foundation Certification Program Notes. FHWA IF Drilled Shafts: Construction Procedures and Design Methods. FHWA NHI Drilled Shafts: Construction Procedures and LRFD Design Methods NHI Course Drilled Shaft Foundation Inspection. Slide 51 of 51

SECTION 411 DRILLED PIERS

SECTION 411 DRILLED PIERS Section Payment will be made under: Pay Item Foundation Excavation Foundation Excavation for Bent No. at Station Foundation Excavation for End Bent No. at Station Pay Unit Cubic Yard Lump Sum Lump Sum

More information

TECHNICAL SPECIFICATIONS CEMENT-BENTONITE SLURRY TRENCH CUTOFF WALL

TECHNICAL SPECIFICATIONS CEMENT-BENTONITE SLURRY TRENCH CUTOFF WALL TECHNICAL SPECIFICATIONS CEMENT-BENTONITE SLURRY TRENCH CUTOFF WALL SCOPE This section of the specifications includes requirements for the Slurry Trench Cutoff Wall and related work as indicated on the

More information

SHAFT CONSTRUCTION IN TORONTO USING SLURRY WALLS

SHAFT CONSTRUCTION IN TORONTO USING SLURRY WALLS SHAFT CONSTRUCTION IN TORONTO USING SLURRY WALLS Vince Luongo Petrifond Foundation Co., Ltd. PROJECT DESCRIPTION The York Durham Sanitary System (YDSS) Interceptor in the Town of Richmond Hill located

More information

Tremie Concrete CM 420 CM 420 CM 420 CM 420. Temporary Structures. Tremie Concrete

Tremie Concrete CM 420 CM 420 CM 420 CM 420. Temporary Structures. Tremie Concrete Tremie Concrete Underwater concrete plays an important role in the construction of offshore structures. It may be used to tie together various elements in composite action (i.e., to tie piling to the footing).

More information

Design and Construction of Auger Cast Piles

Design and Construction of Auger Cast Piles Design and Construction of Auger Cast Piles 101 th Annual Road School 2015 3/11/2015 Malek Smadi, Ph.D., P.E. Principal Engineer - GEOTILL - Fishers, IN msmadi@geotill.com - www.geotill.com CONTENTS 1.

More information

California Department of Transportation Doyle Drive Test Program Contract No. 04A3362

California Department of Transportation Doyle Drive Test Program Contract No. 04A3362 California Department of Transportation Doyle Drive Test Program Deep Soil Mixing (DSM) /Cutter Soil Mixing (CSM) Testing Report By Malcolm Drilling Company, Inc. 3524 Breakwater Ave., Suite 108 Hayward,

More information

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS July 14, 2015 1.0 GENERAL BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS This work shall consist of furnishing all materials, equipment, labor, and incidentals necessary for conducting bi-directional

More information

A. Casing: Steel cylinder used to resist earth and water pressures, to serve as concrete form, and to protect personnel.

A. Casing: Steel cylinder used to resist earth and water pressures, to serve as concrete form, and to protect personnel. SECTION 31 63 29 DRILLED CONCRETE PIERS (CAISSONS) PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division-1 Specification

More information

Anirudhan I.V. Geotechnical Solutions, Chennai

Anirudhan I.V. Geotechnical Solutions, Chennai Anirudhan I.V. Geotechnical Solutions, Chennai Often inadequate In some cases, excess In some cases, disoriented Bad investigation Once in a while good ones Depends on one type of investigation, often

More information

Lab 1 Concrete Proportioning, Mixing, and Testing

Lab 1 Concrete Proportioning, Mixing, and Testing Lab 1 Concrete Proportioning, Mixing, and Testing Supplemental Lab manual Objectives Concepts Background Experimental Procedure Report Requirements Discussion Prepared By Mutlu Ozer Objectives Students

More information

High Strain Dynamic Load Testing of Drilled Shafts

High Strain Dynamic Load Testing of Drilled Shafts Supplemental Technical Specification for High Strain Dynamic Load Testing of Drilled Shafts SCDOT Designation: SC-M-712 (9/15) September 3, 2015 1.0 GENERAL This work shall consist of performing high-strain

More information

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS Page 1 of 9 SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS 1. GENERAL REQUIREMENTS 1. Description of Work: This work consists of furnishing all materials, equipment and

More information

Specification Guidelines: Allan Block Modular Retaining Wall Systems

Specification Guidelines: Allan Block Modular Retaining Wall Systems Specification Guidelines: Allan Block Modular Retaining Wall Systems The following specifications provide Allan Block Corporation's typical requirements and recommendations. At the engineer of record's

More information

PTS HELICAL PIERS INSTALLATION SPECIFICATIONS NOTICE

PTS HELICAL PIERS INSTALLATION SPECIFICATIONS NOTICE FORM A PTS HELICAL PIERS INSTALLATION SPECIFICATIONS NOTICE The following suggested specifications are written as a guide to assist the specifier in writing his own specifications. Specific circumstances

More information

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 11/5/13)

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 11/5/13) Page 1 of 7 STONE STRONG SYSTEMS SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised ) PART 1: GENERAL 1.01 Description A. Work includes furnishing and installing precast modular blocks

More information

Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation

Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation Jeff R. Hill, P.E. Hayward Baker Inc. 111 W. Port Plaza Drive Suite 600 St. Louis, MO 63146 314-542-3040 JRHill@HaywardBaker.com

More information

ALLOWABLE LOADS ON A SINGLE PILE

ALLOWABLE LOADS ON A SINGLE PILE C H A P T E R 5 ALLOWABLE LOADS ON A SINGLE PILE Section I. BASICS 5-1. Considerations. For safe, economical pile foundations in military construction, it is necessary to determine the allowable load capacity

More information

Drilling Problems. pull

Drilling Problems. pull Drilling Problems Pipe Sticking Lost Circulation Hole Deviation Pipe Failures Borehole Instability Mud Contamination Formation Damage Hole Cleaning H S General Equipment & Personnel Pipe Sticking Can not

More information

RIPRAP From Massachusetts Erosion and Sediment Control Guidelines for Urban and Suburban Areas http://www.mass.gov/dep/water/laws/policies.

RIPRAP From Massachusetts Erosion and Sediment Control Guidelines for Urban and Suburban Areas http://www.mass.gov/dep/water/laws/policies. RIPRAP From Massachusetts Erosion and Sediment Control Guidelines for Urban and Suburban Areas http://www.mass.gov/dep/water/laws/policies.htm#storm Definition: A permanent, erosion-resistant ground cover

More information

Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations

Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations Nathan A. Ingraffea, P.E., S.E. Associate, KPFF Consulting Engineers, Portland, Oregon, USA Abstract The use of steel sheet

More information

BUTE Department of Construction Management and Technology

BUTE Department of Construction Management and Technology BUTE Department of Construction Management and Technology 02.10.2012 Definition 1: Foundation: The structure, that transmits the load of the building to the soil Definition 2: Load bearing soil (strata):

More information

COMPENDIUM OF INDIAN STANDARDS ON SOIL ENGINEERING PART 2

COMPENDIUM OF INDIAN STANDARDS ON SOIL ENGINEERING PART 2 (PREVIEW) SP 36 (Part 2) : 1988 COMPENDIUM OF INDIAN STANDARDS ON SOIL ENGINEERING PART 2 IS 1893 : 1979 (Reaffirmed 1987) CODE OF PRACTICE FOR SUBSURFACE INVESTIGATION FOR FOUNDATIONS 1.1 This code deals

More information

Geotechnical Measurements and Explorations Prof. Nihar Ranjan Patra Department of Civil Engineering Indian Institute of Technology, Kanpur

Geotechnical Measurements and Explorations Prof. Nihar Ranjan Patra Department of Civil Engineering Indian Institute of Technology, Kanpur Geotechnical Measurements and Explorations Prof. Nihar Ranjan Patra Department of Civil Engineering Indian Institute of Technology, Kanpur Lecture No. # 13 (Refer Slide Time: 00:18) So last class, it was

More information

Load Testing of Drilled Shaft Foundations in Limestone, Nashville, TN Dan Brown, P.E., Ph.D.

Load Testing of Drilled Shaft Foundations in Limestone, Nashville, TN Dan Brown, P.E., Ph.D. Dan A. Brown and Associates Consulting Geotechnical Engineers 300 Woodland Rd. (423)942-8681 Sequatchie, TN 37374 fax:(423)942-8687 Load Testing of Drilled Shaft Foundations in Limestone, Nashville, TN

More information

PROPERTIES AND MIX DESIGNATIONS 5-694.200

PROPERTIES AND MIX DESIGNATIONS 5-694.200 September 1, 2003 CONCRETE MANUAL 5-694.200 5-694.210 PROPERTIES OF CONCRETE PROPERTIES AND MIX DESIGNATIONS 5-694.200 Inspectors should familiarize themselves with the most important properties of concrete:

More information

INDIRECT METHODS SOUNDING OR PENETRATION TESTS. Dr. K. M. Kouzer, Associate Professor in Civil Engineering, GEC Kozhikode

INDIRECT METHODS SOUNDING OR PENETRATION TESTS. Dr. K. M. Kouzer, Associate Professor in Civil Engineering, GEC Kozhikode INDIRECT METHODS SOUNDING OR PENETRATION TESTS STANDARD PENETRATION TEST (SPT) Reference can be made to IS 2131 1981 for details on SPT. It is a field edtest to estimate e the penetration e resistance

More information

Strength and Workability Characteristics of Concrete by Using Different Super Plasticizers

Strength and Workability Characteristics of Concrete by Using Different Super Plasticizers International Journal of Materials Engineering 12, 2(1): 7-11 DOI: 1.923/j.ijme.11.2 Strength and Workability Characteristics of Concrete by Using Different Super Plasticizers Venu Malagavelli *, Neelakanteswara

More information

The Impact Of Cementing On Proper Well Control

The Impact Of Cementing On Proper Well Control The Impact Of Cementing On Proper Well Control Lee Dillenbeck Senior Advisor, Cementing Chevron ETC Drilling and Completions 2010 Chevron Learning Objectives Explain the main reasons for cementing wells

More information

NOTE: FOR PROJECTS REQUIRING CONTRACTOR MIX DESIGN, THE DESIGN PROCEDURES ARE SPECIFIED IN THE SPECIAL PROVISIONS OF THE CONTRACT.

NOTE: FOR PROJECTS REQUIRING CONTRACTOR MIX DESIGN, THE DESIGN PROCEDURES ARE SPECIFIED IN THE SPECIAL PROVISIONS OF THE CONTRACT. September 1, 2003 CONCRETE MANUAL 5-694.300 MIX DESIGN 5-694.300 NOTE: FOR PROJECTS REQUIRING CONTRACTOR MIX DESIGN, THE DESIGN PROCEDURES ARE SPECIFIED IN THE SPECIAL PROVISIONS OF THE CONTRACT. 5-694.301

More information

Dr. Jesús Gómez, P.E. 36th Annual Conference on Deep Foundations, Boston, MA

Dr. Jesús Gómez, P.E. 36th Annual Conference on Deep Foundations, Boston, MA FHWA Hollow Bar Soil Nail (HBSN) Test Program Dr. Jesús Gómez, P.E. 36th Annual Conference on Deep Foundations, Boston, MA Outline Introduction and motivation Installation methods for testing Testing and

More information

Outline MICROPILES SUBJECT TO LATERAL LOADING. Dr. Jesús Gómez, P.E.

Outline MICROPILES SUBJECT TO LATERAL LOADING. Dr. Jesús Gómez, P.E. MICROPILES SUBJECT TO LATERAL LOADING Dr. Jesús Gómez, P.E. Micropile Design and Construction Seminar Las Vegas, NV April 3-4, 2008 Outline When are micropiles subject to lateral load? How do we analyze

More information

CEEN 162 - Geotechnical Engineering Laboratory Session 7 - Direct Shear and Unconfined Compression Tests

CEEN 162 - Geotechnical Engineering Laboratory Session 7 - Direct Shear and Unconfined Compression Tests PURPOSE: The parameters of the shear strength relationship provide a means of evaluating the load carrying capacity of soils, stability of slopes, and pile capacity. The direct shear test is one of the

More information

Construction of Quality Hot Mix Asphalt Pavements

Construction of Quality Hot Mix Asphalt Pavements 59 th Annual Asphalt Paving Conference Outline Best Practices for Pavement Construction Placement Best Practices Surface Prep Project planning Understanding the paver Factors affecting the screed Screed

More information

The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.

The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified. Section 33 0200- Page 1 of 4 PART 1 - GENERAL 1.1 DESCRIPTION OF WORK The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.

More information

Figure A-1. Figure A-2. continued on next page... HPM-1. Grout Reservoir. Neat Cement Grout (Very Flowable) Extension Displacement Plate

Figure A-1. Figure A-2. continued on next page... HPM-1. Grout Reservoir. Neat Cement Grout (Very Flowable) Extension Displacement Plate Addendum HELICAL PULLDOWN Micropile (HPM) Introduction The HPM is a system for constructing a grout column around the shaft of a standard Helical Screw Foundation (see Figure A1). To begin the process,

More information

SECTION 02466 DRILLED CONCRETE PIERS (CAISSONS)

SECTION 02466 DRILLED CONCRETE PIERS (CAISSONS) SECTION 02466 DRILLED CONCRETE PIERS (CAISSONS) PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division-1 Specification

More information

SECTION 623 CONCRETE BONDING COMPOUND, EPOXY MORTAR AND EPOXY POLYMER CONCRETE OVERLAY SECTION 623.10 CONCRETE BONDING COMPOUND.

SECTION 623 CONCRETE BONDING COMPOUND, EPOXY MORTAR AND EPOXY POLYMER CONCRETE OVERLAY SECTION 623.10 CONCRETE BONDING COMPOUND. SECTION 623 CONCRETE BONDING COMPOUND, EPOXY MORTAR AND EPOXY POLYMER CONCRETE OVERLAY SECTION 623.10 CONCRETE BONDING COMPOUND. 623.10.1 Description. This work shall consist of preparing the surface,

More information

ITEM #0702770 OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT

ITEM #0702770 OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT ITEM #0702770 OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT Description: This work shall consist of furnishing all materials, equipment and labor necessary for conducting an Osterberg Cell (O-Cell) Load

More information

STRUCTURES. 1.1. Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.

STRUCTURES. 1.1. Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL. STRUCTURES 1. General. Critical structures may impact the integrity of a flood control project in several manners such as the excavation for construction of the structure, the type of foundation, backfill

More information

SEDIMENT/STORMWATER MANAGEMENT BASIN CONSTRUCTION CHECKLIST

SEDIMENT/STORMWATER MANAGEMENT BASIN CONSTRUCTION CHECKLIST SEDIMENT/STORMWATER MANAGEMENT BASIN CONSTRUCTION CHECKLIST For permanent structures per Delaware SCS Pond Code 378 and Delaware Sediment and Stormwater Regulations KEY PROJECT INFORMATION Item meets standard

More information

SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701)

SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701) SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701) 55-1 GENERAL The Contractor shall perform all work required by the plans for construction of pipe for storm drains, precast polymer trench drains

More information

Saint Gobain Gyproc India Ltd. (Formerly India Gypsum Ltd.)

Saint Gobain Gyproc India Ltd. (Formerly India Gypsum Ltd.) Saint Gobain Gyproc India Ltd. (Formerly India Gypsum Ltd.) Gyproc Plasters The cracks in cement sand plaster are an inherent feature which cannot be completely prevented but can only be controlled and

More information

CIVL451. Soil Exploration and Characterization

CIVL451. Soil Exploration and Characterization CIVL451 Soil Exploration and Characterization 1 Definition The process of determining the layers of natural soil deposits that will underlie a proposed structure and their physical properties is generally

More information

SafetyBuletin. Concrete101 Aguidetounderstandingthequalitiesofconcrete andhowtheyaffectpumping

SafetyBuletin. Concrete101 Aguidetounderstandingthequalitiesofconcrete andhowtheyaffectpumping SafetyBuletin Concrete101 Aguidetounderstandingthequalitiesofconcrete andhowtheyaffectpumping Copyright 2008 v1.01 ACPA All rights reserved Manufacturer s recommendations supersede any and all information

More information

Specification for the Construction of Drilled Piers

Specification for the Construction of Drilled Piers ACI 336.1-01 Specification for the Construction of Drilled Piers Reported by ACI Committee 336 Edward J. Ulrich, Jr. Chairman Hugh S. Lacy Secretary Clyde N. Baker, Jr. Shraddhakar Harsh John F. Seidensticker

More information

Basics of Reinforced Concrete Design

Basics of Reinforced Concrete Design Basics of Reinforced Concrete Design Presented by: Ronald Thornton, P.E. Define several terms related to reinforced concrete design Learn the basic theory behind structural analysis and reinforced concrete

More information

METHOD OF STATEMENT FOR STATIC LOADING TEST

METHOD OF STATEMENT FOR STATIC LOADING TEST Compression Test, METHOD OF STATEMENT FOR STATIC LOADING TEST Tension Test and Lateral Test According to the American Standards ASTM D1143 07, ASTM D3689 07, ASTM D3966 07 and Euro Codes EC7 Table of Contents

More information

FOUNDATION DESIGN. Instructional Materials Complementing FEMA 451, Design Examples

FOUNDATION DESIGN. Instructional Materials Complementing FEMA 451, Design Examples FOUNDATION DESIGN Proportioning elements for: Transfer of seismic forces Strength and stiffness Shallow and deep foundations Elastic and plastic analysis Foundation Design 14-1 Load Path and Transfer to

More information

Earth Pressure and Retaining Wall Basics for Non-Geotechnical Engineers

Earth Pressure and Retaining Wall Basics for Non-Geotechnical Engineers PDHonline Course C155 (2 PDH) Earth Pressure and Retaining Wall Basics for Non-Geotechnical Engineers Instructor: Richard P. Weber, P.E. 2012 PDH Online PDH Center 5272 Meadow Estates Drive Fairfax, VA

More information

PILE FOUNDATIONS FM 5-134

PILE FOUNDATIONS FM 5-134 C H A P T E R 6 PILE FOUNDATIONS Section I. GROUP BEHAVIOR 6-1. Group action. Piles are most effective when combined in groups or clusters. Combining piles in a group complicates analysis since the characteristics

More information

INSITU TESTS! Shear Vanes! Shear Vanes! Shear Vane Test! Sensitive Soils! Insitu testing is used for two reasons:!

INSITU TESTS! Shear Vanes! Shear Vanes! Shear Vane Test! Sensitive Soils! Insitu testing is used for two reasons:! In-situ Testing! Insitu Testing! Insitu testing is used for two reasons:! To allow the determination of shear strength or penetration resistance or permeability of soils that would be difficult or impossible

More information

Module 1 : Site Exploration and Geotechnical Investigation. Lecture 4 : In-situ tests [ Section 4.1: Penetrometer Tests ] Objectives

Module 1 : Site Exploration and Geotechnical Investigation. Lecture 4 : In-situ tests [ Section 4.1: Penetrometer Tests ] Objectives Lecture 4 : In-situ tests [ Section 4.1: Penetrometer Tests ] Objectives In this section you will learn the following Penetrometer Tests Standard penetration test Static cone penetration test Dynamic cone

More information

Quality Assurance Concepts. Outline

Quality Assurance Concepts. Outline Quality Assurance Concepts Peter C. Taylor Outline What is quality? Who cares? How do we get it? What is the important stuff? 1 Defining Quality Simple Definition (Philip Crosby) Quality: Conformance to

More information

Safe & Sound Bridge Terminology

Safe & Sound Bridge Terminology Safe & Sound Bridge Terminology Abutment A retaining wall supporting the ends of a bridge, and, in general, retaining or supporting the approach embankment. Approach The part of the bridge that carries

More information

vulcanhammer.net This document downloaded from

vulcanhammer.net This document downloaded from This document downloaded from vulcanhammer.net since 1997, your source for engineering information for the deep foundation and marine construction industries, and the historical site for Vulcan Iron Works

More information

Moving Small Mountains Vesuvius Dam Rehab

Moving Small Mountains Vesuvius Dam Rehab Moving Small Mountains Vesuvius Dam Rehab Susan L. Peterson, P.E., regional dams engineer, Eastern Region, Bedford, IN Note: The following article, Moving Small Mountains Vesuvius Dam Rehab, by Sue Peterson,

More information

How To Design A Foundation

How To Design A Foundation The Islamic university - Gaza Faculty of Engineering Civil Engineering Department CHAPTER (2) SITE INVESTIGATION Instructor : Dr. Jehad Hamad Definition The process of determining the layers of natural

More information

The Installation and Load Testing of Drilled Shafts

The Installation and Load Testing of Drilled Shafts Presentation to the North American Chinese Geotechnical Engineers Association The Installation and Load Testing of Drilled Shafts at Clarksville, Virginia by James M. Sheahan, P.E. HDR Engineering, Inc.

More information

Pavement Thickness. esign and RCC-Pave Software. Roller-Compacted Concrete Pavement: Design and Construction. October 24, 2006 Atlanta, Georgia

Pavement Thickness. esign and RCC-Pave Software. Roller-Compacted Concrete Pavement: Design and Construction. October 24, 2006 Atlanta, Georgia Roller-Compacted Concrete Pavement: Design and Construction Pavement Thickness esign and RCC-Pave Software Gregory E. Halsted, P.E. Pavements Engineer Portland Cement Association October 24, 2006 Atlanta,

More information

Eurocode 7 - Geotechnical design - Part 2 Ground investigation and testing

Eurocode 7 - Geotechnical design - Part 2 Ground investigation and testing Brussels, 18-20 February 2008 Dissemination of information workshop 1 Eurocode 7 - Geotechnical design - Part 2 Ground investigation and testing Dr.-Ing. Bernd Schuppener, Federal Waterways Engineering

More information

Module 7 (Lecture 24 to 28) RETAINING WALLS

Module 7 (Lecture 24 to 28) RETAINING WALLS Module 7 (Lecture 24 to 28) RETAINING WALLS Topics 24.1 INTRODUCTION 24.2 GRAVITY AND CANTILEVER WALLS 24.3 PROPORTIONING RETAINING WALLS 24.4 APPLICATION OF LATERAL EARTH PRESSURE THEORIES TO DESIGN 24.5

More information

How To Model A Shallow Foundation

How To Model A Shallow Foundation Finite Element Analysis of Elastic Settlement of Spreadfootings Founded in Soil Jae H. Chung, Ph.D. Bid Bridge Software Institute t University of Florida, Gainesville, FL, USA Content 1. Background 2.

More information

Stormwater/Wetland Pond Construction Inspection Checklist

Stormwater/Wetland Pond Construction Inspection Checklist : Construction Inspection ChecklistsTools Stormwater/Wetland Pond Construction Inspection Checklist Project: Location: Site Status: Date: Time: Inspector: SATISFACTORY/ UNSATISFACTORY COMMENTS Pre-Construction/Materials

More information

NorthEast Transportation Training and Certification Program (NETTCP) Course Registration Form

NorthEast Transportation Training and Certification Program (NETTCP) Course Registration Form (NETTCP) Course Registration Form Interim Certification (Cost $300 members / $425 non-members) HMA Plant Technician* HMA Paving Inspector* Soils & Aggregate Inspector* Soils & Aggregate Lab Technician*

More information

KWANG SING ENGINEERING PTE LTD

KWANG SING ENGINEERING PTE LTD KWANG SING ENGINEERING PTE LTD 1. INTRODUCTION This report represents the soil investigation works at Aljunied Road / Geylang East Central. The objective of the soil investigation is to obtain soil parameters

More information

Structures Construction Pre-Work Checklist PRE-WORK SHEET FOR PROJECT MANAGERS

Structures Construction Pre-Work Checklist PRE-WORK SHEET FOR PROJECT MANAGERS Structures Construction Pre-Work Checklist PRE-WORK SHEET FOR PROJECT MANAGERS 1 Proposal & Plans Received? 2 Review Proposal, highlight important facts. Know proposal well to be able to find answers quickly.

More information

APPENDIX B. I. Background Information

APPENDIX B. I. Background Information APPENDIX B GUIDELINES FOR IDENTIFYING AND REPAIRING LOCALIZED AREAS OF DISTRESS IN AC PAVEMENTS PRIOR TO CAPITAL PREVENTIVE MAINTENANCE OR REHABILITATION REPAIRS I. Background Information A. AC Pavement

More information

Engineered, Time-Tested Foundation Repairs for Settlement in Residential and Light Commercial Structures. The Leading Edge.

Engineered, Time-Tested Foundation Repairs for Settlement in Residential and Light Commercial Structures. The Leading Edge. TM TM Engineered, Time-Tested Foundation Repairs for Settlement in Residential and Light Commercial Structures. SM The Leading Edge. 10 One Major Causes of foundation settlement or more conditions may

More information

Table of Contents 16.1 GENERAL... 16.1-1. 16.1.1 Overview... 16.1-1 16.1.2 Responsibilities... 16.1-1

Table of Contents 16.1 GENERAL... 16.1-1. 16.1.1 Overview... 16.1-1 16.1.2 Responsibilities... 16.1-1 Table of Contents Section Page 16.1 GENERAL... 16.1-1 16.1.1 Overview... 16.1-1 16.1.2 Responsibilities... 16.1-1 16.1.2.1 Geotechnical Section/Bridge Bureau Coordination... 16.1-1 16.1.2.2 Geotechnical

More information

USE OF CONE PENETRATION TEST IN PILE DESIGN

USE OF CONE PENETRATION TEST IN PILE DESIGN PERIODICA POLYTECHNICA SER. CIV. ENG. VOL. 47, NO. 2, PP. 189 197 (23) USE OF CONE PENETRATION TEST IN PILE DESIGN András MAHLER Department of Geotechnics Budapest University of Technology and Economics

More information

Foundation Code compliance and Best Practices By Michael Coello

Foundation Code compliance and Best Practices By Michael Coello Foundation Code compliance and Best Practices By Michael Coello Background Graduated cum laude in 1992 with a Bachelor of Science degree in finance from University of Wisconsin - Parkside Started poured

More information

SECTION 31 20 00 EARTH MOVING

SECTION 31 20 00 EARTH MOVING SECTION 31 20 00 PART 1 - GENERAL 1.01 DESCRIPTION A. This Section describes the requirements for excavating, filling, and grading for earthwork at Parking Structure, new exit stair and as required to

More information

THE OBJECTIVES OF ROUTINE ROAD CUTS AND FILLS

THE OBJECTIVES OF ROUTINE ROAD CUTS AND FILLS Chapter 11 Slope Stabiliza bilization and Stability of Cuts and Fills THE OBJECTIVES OF ROUTINE ROAD CUTS AND FILLS are 1) to create space for the road template and driving surface; 2) to balance material

More information

Foundation Experts, LLC Specializes in Foundation Repair and Waterproofing

Foundation Experts, LLC Specializes in Foundation Repair and Waterproofing 1 Most basements show some signs of leaking and cracking. Through the years, problems with water, poor soils, grading, drainage and possible settling affect the integrity of a basement. Being able to recognize

More information

How To Prepare A Geotechnical Study For A Trunk Sewer Project In Lincoln, Nebraska

How To Prepare A Geotechnical Study For A Trunk Sewer Project In Lincoln, Nebraska APPENDIX B Geotechnical Engineering Report GEOTECHNICAL ENGINEERING REPORT Preliminary Geotechnical Study Upper Southeast Salt Creek Sanitary Trunk Sewer Lincoln Wastewater System Lincoln, Nebraska PREPARED

More information

Mining with Paste Fill

Mining with Paste Fill Mining with Paste Fill Mehmet Yumlu, Principal Mining Engineer AMC Consultants Pty Ltd AusIMM Cobar Mining Seminar AMC Con nsultants Pty Ltd Outline Introduction ti What is Paste Fill? Why Using Paste

More information

SECTION 33 31 00.13 ABANDONMENT OF SEWER MAINS

SECTION 33 31 00.13 ABANDONMENT OF SEWER MAINS SECTION 33 31 00.13 ABANDONMENT OF SEWER MAINS PART 1: GENERAL 1.01 SECTION INCLUDES A. Abandonment in place, by cutting and capping, of existing sewers, junction structures, manholes, service lines, and

More information

vulcanhammer.net This document downloaded from

vulcanhammer.net This document downloaded from This document downloaded from vulcanhammer.net since 1997, your source for engineering information for the deep foundation and marine construction industries, and the historical site for Vulcan Iron Works

More information

1 Mobilisation and demobilisation 1 Deep boring sum 2 Cone penetration tests sum 3 Miscellenous tests sum

1 Mobilisation and demobilisation 1 Deep boring sum 2 Cone penetration tests sum 3 Miscellenous tests sum Malaysian Civil Engineering Standard Method of Measurement (MyCESMM) CLASS D: SITE INVESTIGATION WORK Measurement covered under other classes: Excavation not carried out for the purpose of soil investigation

More information

System. Stability. Security. Integrity. 150 Helical Anchor

System. Stability. Security. Integrity. 150 Helical Anchor Model 150 HELICAL ANCHOR System PN #MBHAT Stability. Security. Integrity. 150 Helical Anchor System About Foundation Supportworks is a network of the most experienced and knowledgeable foundation repair

More information

USE OF MICROPILES IN TEXAS BRIDGES. by John G. Delphia, P.E. TxDOT Bridge Division Geotechnical Branch

USE OF MICROPILES IN TEXAS BRIDGES. by John G. Delphia, P.E. TxDOT Bridge Division Geotechnical Branch USE OF MICROPILES IN TEXAS BRIDGES by John G. Delphia, P.E. TxDOT Bridge Division Geotechnical Branch DEFINITION OF A MICROPILE A micropile is a small diameter (typically less than 12 in.), drilled and

More information

Properties of Fresh Concrete

Properties of Fresh Concrete Properties of Fresh Concrete Introduction The potential strength and durability of concrete of a given mix proportion is very dependent on the degree of its compaction. It is vital, therefore, that the

More information

Installation PowerPoint for Grasscrete Formers

Installation PowerPoint for Grasscrete Formers Installation PowerPoint for Grasscrete Formers 1 This document describes the two single-use tools utilized to create the Grasscrete product. The original Former is a vacuum formed light gauge plastic mold

More information

EXCAVATOR SAFETY TRAINING

EXCAVATOR SAFETY TRAINING EXCAVATOR SAFETY TRAINING INSPECTION CHECKLIST INSPECTION AREA INSPECTION RESULTS Sat. Unsat. N/A Comments Carrier & Car Body Rotation system Tracks Rollers Frame, welds, bolts Drive system Upper Structure

More information

Washington 98102-3699, mike.bailey@hartcrowser.com

Washington 98102-3699, mike.bailey@hartcrowser.com LESSONS LEARNED FROM A STONE COLUMN TEST PROGRAM IN GLACIAL DEPOSITS Barry S. Chen 1, P.E., Member, Geo-Institute and Michael J. Bailey 2, P.E., Member, Geo-Institute ABSTRACT A stone column test program

More information

product manual HS-4210 HS-4210_MAN_09.08 Digital Static Cone Penetrometer

product manual HS-4210 HS-4210_MAN_09.08 Digital Static Cone Penetrometer HS-4210_MAN_09.08 product manual HS-4210 Digital Static Cone Penetrometer Introduction This Manual covers the measurement of bearing capacity using the Humboldt Digital Static Cone Penetrometer (DSCP).

More information

PDCA Driven-Pile Terms and Definitions

PDCA Driven-Pile Terms and Definitions PDCA Driven-Pile Terms and Definitions This document is available for free download at piledrivers.org. Preferred terms are descriptively defined. Potentially synonymous (but not preferred) terms are identified

More information

Comprehensive Design Example 2: Foundations for Bulk Storage Facility

Comprehensive Design Example 2: Foundations for Bulk Storage Facility Comprehensive Design Example 2: Foundations for Bulk Storage Facility Problem The project consists of building several dry product storage silos near an existing rail siding in an open field presently

More information

New construction Repairing failed or old foundations Retrofit foundations Permanent battered piers Machinery/equipment foundations

New construction Repairing failed or old foundations Retrofit foundations Permanent battered piers Machinery/equipment foundations from New construction foundations don t have to be a headache. The CHANCE Helical Pier Foundation System gives you the performance of concrete without the drawbacks and liabilities of driven piles and

More information

Current opportunities of sprayed waterproofing membrane. Frank Clement Technical Manager Sprayable Membranes MEYCO Global Underground Construction

Current opportunities of sprayed waterproofing membrane. Frank Clement Technical Manager Sprayable Membranes MEYCO Global Underground Construction Current opportunities of sprayed waterproofing membrane Frank Clement Technical Manager Sprayable Membranes MEYCO Global Underground Construction 1 What would we like to achieve? 2 What is desired? 3 and

More information

SPECIFICATION FOR DYNAMIC CONSOLIDATION / DYNAMIC REPLACEMENT

SPECIFICATION FOR DYNAMIC CONSOLIDATION / DYNAMIC REPLACEMENT SPECIFICATION FOR DYNAMIC CONSOLIDATION / DYNAMIC REPLACEMENT 1.0 SOIL IMPROVEMENT 1.1 General Soil Investigation Information are provided in Part B1 annex as a guide to the Contractor for his consideration

More information

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS While its use is not required, this checklist has been prepared to provide the field inspector a summary

More information

AIR RELEASE, CLEANOUT, AND SEWER MANHOLES

AIR RELEASE, CLEANOUT, AND SEWER MANHOLES AIR RELEASE, CLEANOUT, AND SEWER MANHOLES **From Hartford IM BLDG(10) DESCRIPTION. This work shall consist of the construction of air release, cleanout, and sanitary sewer manholes; and the furnishing

More information

DIVISION 300 BASES SECTION 304 AGGREGATE BASE COURSE DESCRIPTION MATERIALS CONSTRUCTION REQUIREMENTS

DIVISION 300 BASES SECTION 304 AGGREGATE BASE COURSE DESCRIPTION MATERIALS CONSTRUCTION REQUIREMENTS 304.06 DIVISION 300 BASES SECTION 304 AGGREGATE BASE COURSE DESCRIPTION 304.01 This work consists of furnishing and placing one or more courses of aggregate and additives, if required, on a prepared subgrade.

More information

Table 4.9 Storm Drain Inlet Protetion Applicable for

Table 4.9 Storm Drain Inlet Protetion Applicable for BMP C220: Storm Drain Inlet Protection Purpose To prevent coarse sediment from entering drainage systems prior to permanent stabilization of the disturbed area. Conditions of Use Type of Inlet Protection

More information

STANDARD AND SPECIFICATIONS FOR STORM DRAIN INLET PROTECTION

STANDARD AND SPECIFICATIONS FOR STORM DRAIN INLET PROTECTION STANDARD AND SPECIFICATIONS FOR STORM DRAIN INLET PROTECTION Design Criteria Drainage Area The drainage area for storm drain inlets shall not exceed one acre. The crest elevations of these practices shall

More information

Guidelines For Sealing Groundwater Wells

Guidelines For Sealing Groundwater Wells Guidelines For Sealing Groundwater Wells Government of Newfoundland and Labrador Department of Environment and Conservation Water Resources Management Division Government of Newfoundland and Labrador Department

More information

PLUMBING MAINTENANCE WORK FOR TOILETS IN HEAD OFFICE, SUPPLYCO ESTIMATE

PLUMBING MAINTENANCE WORK FOR TOILETS IN HEAD OFFICE, SUPPLYCO ESTIMATE Sl.No. PLUMBING MAINTENANCE WORK FOR TOILETS IN HEAD OFFICE, SUPPLYCO ESTIMATE Description of item Qty Unit Rate Amount 1 Demolishing tile work/cement concrete/( carefully taking out the closet and other

More information

Index. protection. excavated drop inlet protection (Temporary) 6.50.1 6.51.1. Block and gravel inlet Protection (Temporary) 6.52.1

Index. protection. excavated drop inlet protection (Temporary) 6.50.1 6.51.1. Block and gravel inlet Protection (Temporary) 6.52.1 6 Index inlet protection excavated drop inlet protection (Temporary) 6.50.1 HARDWARE CLOTH AND GRAVEL INLET PROTECTION Block and gravel inlet Protection (Temporary) sod drop inlet protection ROCK DOUGHNUT

More information

SECTION 15125 HIGH DENSITY POLYETHYLENE (HDPE) PIPE AND FITTINGS FOR WATER DISTRIBUTION AND TRANSMISSION

SECTION 15125 HIGH DENSITY POLYETHYLENE (HDPE) PIPE AND FITTINGS FOR WATER DISTRIBUTION AND TRANSMISSION SECTION 15125 HIGH DENSITY POLYETHYLENE (HDPE) PIPE AND FITTINGS FOR WATER DISTRIBUTION AND TRANSMISSION PART 1 GENERAL.01 SECTION INCLUDES Furnishing and installing 4 inch through 16 inch high density

More information