1 Section Page 1 of 4 PART 1 - GENERAL 1.1 DESCRIPTION OF WORK The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified. 1.2 QUALITY ASSURANCE The CONTRACTOR shall provide certification that the pipe to be installed meets the requirements of the Florida Department of Transportation Standard Specifications for Road and Bridge Construction, dated 2007, Section PRODUCT HANDLING Pipe and appurtenances shall be inspected at point of delivery. Material found to be defective due to manufacture or damage in shipment shall be rejected. Tests as specified in the applicable material standard may be performed to ensure conformance with the standard. PART 2 MATERIALS AND EQUIPMENT 2.1 MATERIALS Pipe shall meet the requirements of ASTM C 76M and Section 449 of the Florida Department of Transportation Standard Specifications, 2007 Edition. All pipe shall be Class III. PART 3 EXECUTION 3.1 INSTALLATION A. ALIGNMENT AND GRADE The pipelines shall be laid and maintained to lines and grades established by the Drawings and Specifications, with basins, manholes and pipe ends at the required locations unless otherwise approved by the ENGINEER. Prior to excavation, investigation shall be made to the extent necessary to determine the location to existing underground structures and conflicts. Care shall be exercised to avoid damage to existing structures. When obstructions, not shown on the Drawings, are encountered during the progress of the work and interfere so that an alteration of the Drawings is required, the ENGINEER will alter the Drawings or order a deviation in line and grade or arrange for removal, relocation, or reconstruction of the obstructions. When crossing existing pipelines or other structures, alignment and grade shall be adjusted as necessary, with the approval of the ENGINEER, to provide clearance as required by federal, state, or local regulations or as deemed necessary by the ENGINEER to prevent future damage or contamination of either structure. B. TRENCH CONSTRUCTION

2 Section Page 2 of 4 The trench shall be excavated to the required alignment, depth, and width. Trench preparation shall proceed in advance of pipe installation for only as far as necessary to allow proper pipe installation. The width of the trench at the top of the pipe shall be ample to permit the pipe to be laid and joined properly and allow the backfill to be placed as specified. Holes for the joints shall be provided at each joint but shall not be larger than necessary for joint assembly and assurance that the pipe barrel will lie flat on the trench bottom. Other than noted previously, the trench bottom shall be true and even in order to provide support for the full length of the pipe barrel, except that a slight depression may be provided to allow withdrawal of pipe slings or other lifting tackle. When excavation or rock is encountered, all rock shall be removed to provide a clearance of at least 6 inches below and on each side of all pipe, valves and fittings for pipe sizes 24 inches or smaller, and 9 inches for pipe sizes 30 inches and larger. When excavation is completed, a bed of sand, crushed stone, or earth that is free from stones, large clods, or frozen earth shall be placed on the bottom of the trench to the previously mentioned depths, leveled and tamped. These clearances and bedding procedures shall also be observed for pieces of concrete or masonry and other debris or subterranean structures, such as masonry walls, piers, or foundations that my be encountered during excavation. This installation procedure shall be followed when gravel formations containing loose boulders greater than 8 inches in diameter are encountered. In all cases, the specified clearances shall be maintained between the bottom of all pipe and appurtenances and any part, projection, or pint of rock, boulder, or stones of sufficient size and placement which, in the opinion of the ENGINEER, could cause a fulcrum point. Should the trench pass over a sewer or other previous excavation, the trench bottom shall be sufficiently compacted to provide support equal to that of the native soil or conform to other regulatory requirements in a manner that will prevent damage to the existing installation. When the sub-grade is found to be unstable or to include ashes, cinders, refuse, organic material, or other unsuitable material, such material shall be removed, to a minimum of at least 3 inches, or to the depth ordered by the ENGINEER and replaced under the directions of the ENGINEER with clean, stable backfill material. The bedding shall be consolidated and leveled in order that the pipe may be installed as specified. When the bottom of the trench or the sub-grade is found to consist of material that is unstable to such a degree that, in the judgment of the ENGINEER it cannot be removed, a foundation for the pipe and/or appurtenances shall be constructed using piling, timber, concrete, or other materials at the direction of the ENGINEER. C. PIPE INSTALLATION

3 Section Page 3 of 4 Proper implements, tools, and facilities shall be provided and used for the safe and convenient performance of the work. All pipe shall be lowered carefully into the trench by means of a derrick, ropes, or other suitable tools or equipment in such a manner as to prevent damage to pipeline material and protective coatings and linings. Under no circumstances shall pipeline materials be dropped off or dumped into the trench. The trench should be dewatered prior to installation of the pipe. Pipe, fittings, and other appurtenances shall be examined carefully for damage and other defects immediately before installation. Defective materials shall be marked and held for inspection by the ENGINEER who may prescribe corrective repairs or reject the materials. Joint surfaces shall be wiped clean and dry and be free from dirt, sand, grit, or any foreign material before the pipe is laid. Both the bell and spigot of the pipe sections shall be cleaned just prior to joining. Foreign material shall be prevented from entering the pipe while it is being placed in the trench. During laying operations, no debris, tools, clothing, or other materials shall be placed in the pipe. As each length of pipe is placed in the trench, the joint shall be assembled and the pipe brought to correct line and grade. The pipe shall be secured in place with approved backfill material. At times when pipe laying is not in progress, the open ends of pipe shall be closed by a watertight plug or other means approved by the ENGINEER. When practical, the plug shall remain in place until the trench is pumped completely dry. Care shall be taken to prevent pipe flotation should the trench fill with water. Trench width at the top of pipe, bedding conditions, and backfill placement and compaction shall be such that design loadings on the pipe will not be exceeded. Joint Assembly. Pipe joints shall be assembled in accordance with the Manufacturer s instructions. The bell and spigot of the pipe sections to be joined shall be cleaned prior to joining. A thin layer of a lubricant supplied by the pipe manufacturer shall be applied to the surfaces of the bell, spigot, and gasket. After lubrication, the gasket shall be installed in the spigot groove. The stretch in the gasket should be equalized by inserting a smooth rod under the gasket and moving the rod completely around the full circumference of the spigot. During joint make up, the pipe being lowered into the trench shall be supported so that the jointing effort is a straight in pull. After assembly, position of the gasket shall be checked for conformance to manufacturer s recommended tolerances. Any deviation shall be corrected by disassembly, removal of gasket and reassembly with installation of a new gasket. Pipe Deflection. When it is necessary to deflect pipe from a straight line in either the vertical or horizontal plane, or where long radius curves are permitted, the amount of deflection shall not exceed that recommended by the Manufacturer. Beveled end pipe may be used for additional deflection.

4 Section Page 4 of 4 END OF SECTION

5 PART 1 - GENERAL REQUIREMENTS 1.1 SUMMARY Embry-Riddle Aeronautical University PRESSURE PIPE CLEANING Section Page 1 of 2 This work includes materials and methods to clean new potable water, reuse water, raw water, sanitary and stormwater pressure pipe lines of 6 inches or greater inside diameter by use of a pig and the flushing and cleaning of pressure pipelines less than 6 inches in diameter. 1.2 REFERENCES The requirements of the City Utilities Department Standard Details, latest edition shall apply. 1.3 SUBMITTALS The CONTRACTOR shall submit planned procedures to the CITY for review prior to beginning work. The CITY Utilities Department staff will advise as to whether or not the pipe cleaning and pigging procedures will be acceptable. 1.4 CONTRACTOR RESPONSIBILITIES A. The CONTRACTOR shall secure and pay for all necessary equipment, including cleaning pigs as required, to ensure the pipe is cleaned. Potable water pipe cleaning shall be completed and accepted by the CITY before any effort is made to disinfect the piping. B. CONTRACTOR shall furnish all labor, materials, instruments, fuel, incidentals, and expendables required for cleaning the piping JOB CONDITIONS A. The CONTRACTOR shall review the field conditions prior to placing a bid for this project and evaluate the cleaning schedule that will be required. B. The CITY s approval is required to clean a portion of the new piping system prior to moving on to another section. PART 2 PRODUCTS (Not Applicable) PART 3 - EXECUTION 3.1 PREPARATION

6 PRESSURE PIPE CLEANING Section Page 2 of 2 The CONTRACTOR shall obtain advance approval from the CITY coordinate the pigging and flushing operation due to the additional water resource demand on the CITY system. 3.2 PIGGING & FLUSHING A. Cleaning of lines less than 6 inches inside diameter shall be accomplished by thorough flushing of the line using a CITY approved water source. Cleaning of lines 6 inches inside diameter or greater shall be accomplished using a flexible polyurethane foam pipeline cleaner, commonly known as a "Pig", manufactured for cleaning pressure lines. The pig shall be new and have a turning pattern, for use in water systems. It shall have a resilient peripheral surface that engages with the inner cylindrical wall of the pipe to maintain a sliding seal. The pig may have one or more sealing surfaces. This seal is maintained for propelling and must be abrasive resistant. B. When necessary, the pig shall also have abilities to scratch, scrape, plow and jet to assist in cleaning and flushing the pipe of debris. The pig shall rotate for longer wear and be able to reduce itself to a minimum of 65% of its original cross-sectional area. It must then be able to return to its original form while maintaining its seal and ability to clean. C. The pig shall have the ability to negotiate- fabricated mitered bends, short radius bends, short radius elbows, tees, crosses, and multi-dimensional pipe sizes and valves. D. Follow manufacturer's recommendations for use of "pig" in cleaning the line and conduct flushing and cleaning with CITY s representative in attendance. After passing through the pipeline the CITY s representative shall determine if subsequent pigging and flushing must be performed. E. The field pigging operation shall clearly establish that the piping is adequately cleaned. F. All pipe and fittings used to launch and receive the pigs shall be removed at no additional cost to the CITY. The cost for constructing the pig launch and receiving piping shall be included as part of the pipe installation cost unless a separate line item is found in the bid form. 3.3 WATER FOR FLUSHING & TESTING The CONTRACTOR shall procure and pay for the additional water required for potable water line disinfection and all other pressure pipe cleaning and disinfection system tests if the initial tests fail to pass. END OF SECTION

A. Contractor shall furnish, to the Engineer, all materials certifications available from the manufacturer for all required materials.

A. Contractor shall furnish, to the Engineer, all materials certifications available from the manufacturer for all required materials. PART 1 GENERAL 1.1 SCOPE A. This item shall include the work necessary for the installation of storm sewer line construction. B. Reference Section 3800 Trenching and Backfill and the General Conditions,

More information

Section 02702 SEWER PIPE INSTALLATION AND TESTING

Section 02702 SEWER PIPE INSTALLATION AND TESTING PART 1 - GENERAL Section 02702 SEWER PIPE INSTALLATION AND TESTING 1-1. SCOPE. This section covers the installation and testing of all sewer pipe furnished under the following specification sections: Concrete

More information

SECTION 15062 POLYVINYL CHLORIDE GRAVITY SEWER PIPE AND FITTINGS

SECTION 15062 POLYVINYL CHLORIDE GRAVITY SEWER PIPE AND FITTINGS SECTION 15062 POLYVINYL CHLORIDE (PVC) GRAVITY SEWER PIPE AND FITTINGS PART 1 GENERAL 1.01 DESCRIPTION This section designates the requirements for the manufacture and installation of polyvinyl chloride,

More information

TABLE OF CONTENTS SECTION 200 UNDERGROUND PIPE CONSTRUCTION

TABLE OF CONTENTS SECTION 200 UNDERGROUND PIPE CONSTRUCTION TABLE OF CONTENTS SECTION 200 UNDERGROUND PIPE CONSTRUCTION Starts on Page 200 EXCAVATION... 2 201 PIPE BEDDING... 3 202 LAYING OF PIPE... 4 203 COVER MATERIAL... 5 204 INSULATION... 6 205 BACKFILLING...

More information

SECTION 33 31 00.11 GRAVITY SANITARY SEWERS

SECTION 33 31 00.11 GRAVITY SANITARY SEWERS SECTION 33 31 00.11 GRAVITY SANITARY SEWERS PART 1: GENERAL 1.01 SCOPE A. Gravity sanitary sewers and appurtenances. 1.02 SUBMITTALS A. Conform to requirements of Section 01 33 00 Submittals. B. Submit

More information

Bethel Township Municipal Authority (BTMA) RESIDENTIAL SEWER CONNECTION MANUAL

Bethel Township Municipal Authority (BTMA) RESIDENTIAL SEWER CONNECTION MANUAL 155 E. Front Street (rear) Lititz, PA 17543 Phone (717) 625-1930 Fax (717) 625-1931 Bethel Township Municipal Authority (BTMA) RESIDENTIAL SEWER CONNECTION MANUAL CONSTRUCTION SPECIFICATIONS AND DETAILS

More information

SECTION POLYVINYL CHLORIDE PIPE, AWWA C900/C905

SECTION POLYVINYL CHLORIDE PIPE, AWWA C900/C905 SECTION 02670 POLYVINYL CHLORIDE PIPE, AWWA C900/C905 PART 1 GENERAL 1.01 SUMMARY A. Section Includes: 1. Furnish and install AWWA C900 PVC, DR 18 for 4 through 12 size and AWWA C905 PVC, DR 25 for 14

More information

SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.

SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250. 02150-1 of 6 SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING 02150.01 GENERAL A. Description Removal or abandonment of existing utilities and underground structures shall include, but not necessarily

More information

SECTION 4 EXCAVATION, TRENCHING AND BACKFILLING 4.01 SCOPE OF WORK

SECTION 4 EXCAVATION, TRENCHING AND BACKFILLING 4.01 SCOPE OF WORK 4.01 SCOPE OF WORK The work covered by this section shall consist of furnishing all materials, equipment and labor for the excavating, trenching, backfilling, and bore and jack required to install or repair

More information

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS While its use is not required, this checklist has been prepared to provide the field inspector a summary

More information

SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701)

SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701) SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701) 55-1 GENERAL The Contractor shall perform all work required by the plans for construction of pipe for storm drains, precast polymer trench drains

More information

DIVISION 2 - SEWERAGE AND DRAINAGE SECTION 02720 - STORM DRAIN SYSTEMS PART 1 - GENERAL

DIVISION 2 - SEWERAGE AND DRAINAGE SECTION 02720 - STORM DRAIN SYSTEMS PART 1 - GENERAL DIVISION 2 - SEWERAGE AND DRAINAGE SECTION 02720 - STORM DRAIN SYSTEMS PART 1 - GENERAL 1.01 DESCRIPTION A. Furnish and install all storm drains, including manholes, inlets, service lines and other appurtenant

More information

DIVISION 4300 STORM DRAINAGE

DIVISION 4300 STORM DRAINAGE DIVISION 4300 STORM DRAINAGE SECTION 4305 STORM SEWER PART 1 - GENERAL 1.01 SCOPE This section covers the construction of storm sewers for the collection and transport of stormwater runoff. 1.02 REFERENCES

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 1100 SLIP-LINING SANITARY SEWERS

San Antonio Water System Standard Specifications for Construction ITEM NO. 1100 SLIP-LINING SANITARY SEWERS ITEM NO. 1100 SLIP-LINING SANITARY SEWERS 1100.1 DESCRIPTION: This item shall consist of slip-lining sanitary sewer pipe, which is accomplished by pulling or pushing liner pipe into existing sewers by

More information

Section 2100-Trenching and Tunneling

Section 2100-Trenching and Tunneling SECTION 5200 - STORM SEWER PART 1 - GENERAL 1.01 SCOPE: This Section covers installation of storm sewer mains and culverts. Topics include permits and fees, trench widths, pipe laying, bedding, initial

More information

SECTION LS 2530 SANITARY SEWERS. A. General: Submit the following in accordance with The General Conditions.

SECTION LS 2530 SANITARY SEWERS. A. General: Submit the following in accordance with The General Conditions. SECTION LS 2530 SANITARY SEWERS PART 1 GENERAL 1.1 SUBMITTALS A. General: Submit the following in accordance with The General Conditions. 1. Product data for drainage piping specialties. 2. Shop drawings

More information

SECTION TRENCHING AND BACKFILLING. 1. Section , Temporary Environmental Controls. 2. Section , Excavation and Fill.

SECTION TRENCHING AND BACKFILLING. 1. Section , Temporary Environmental Controls. 2. Section , Excavation and Fill. SECTION 31 23 33 TRENCHING AND BACKFILLING PART 1 GENERAL 1.01 SECTION INCLUDES A. This WORK shall consist of all labor, equipment, and materials necessary for excavation, trenching, and backfilling for

More information

STANDARD SPECIFICATIONS SECTION 02701 INSTALLATION OF GRAVITY SEWER PIPELINES. 1. Trenching, Backfilling and Compacting: 02223

STANDARD SPECIFICATIONS SECTION 02701 INSTALLATION OF GRAVITY SEWER PIPELINES. 1. Trenching, Backfilling and Compacting: 02223 STANDARD SPECIFICATIONS SECTION 02701 INSTALLATION OF GRAVITY SEWER PIPELINES PART 1 - GENERAL A. Description This section describes the installation of gravity sewer pipelines fabricated of vitrified

More information

32-02.05 Precast Manhole Sections and Castings. These items shall conform to Section 31, "Storm Drain Installation," of these Standard Provisions.

32-02.05 Precast Manhole Sections and Castings. These items shall conform to Section 31, Storm Drain Installation, of these Standard Provisions. SECTION 32: SANITARY SEWER INSTALLATION 32-01 SCOPE. The Work shall consist of furnishing and installing sewer mains, manholes, laterals, cleanout fittings and appurtenances; and testing, flushing and

More information

Section 2 Specification 2.18 Concrete and/or Corrugated Steel Storm Sewer TABLE OF CONTENTS

Section 2 Specification 2.18 Concrete and/or Corrugated Steel Storm Sewer TABLE OF CONTENTS TABLE OF CONTENTS 2.18 CONCRETE AND/OR CORRUGATED STEEL STORM SEWER... 1 2.18.1 GENERAL... 1 2.18.2 MATERIALS... 1 2.18.2.1 Storm Sewer Pipe... 1 2.18.2.2 Cement Mortar... 1 2.18.2.3 Granular Materials...

More information

SECTION 6 SANITARY SEWER MAIN 6.01 SCOPE

SECTION 6 SANITARY SEWER MAIN 6.01 SCOPE 6.01 SCOPE The work covered by this section of the specifications consists of the furnishing of all plant, labor, materials, equipment and supervision and performing all operations involved in the construction

More information

SECTION 51 PIPE INSTALLATION FOR WATER MAINS

SECTION 51 PIPE INSTALLATION FOR WATER MAINS SECTION 51 PIPE INSTALLATION FOR WATER MAINS 51. 1 GENERAL Pipe shall be installed in accordance with the manufacturer's specifications and instructions for the type of pipe used and applicable AWWA standards,

More information

Wastewater Capital Projects Management Standard Construction Specification

Wastewater Capital Projects Management Standard Construction Specification CITY AND COUNTY OF DENVER ENGINEERING DIVISION Wastewater Capital Projects Management Standard Construction Specification 10.1 Precast Concrete Pipe 10.1.1 General This section covers material requirements,

More information

3. Contractor shall ensure that all permits are obtained prior to any construction. Contractor shall be responsible for all utility fees.

3. Contractor shall ensure that all permits are obtained prior to any construction. Contractor shall be responsible for all utility fees. The following shall serve as the minimum requirements for contractors performing work in relation to the Authority s potable water and sanitary sewer system(s), appurtenances and service connections. General:

More information

SECTION 02400 - STORM DRAIN SYSTEM

SECTION 02400 - STORM DRAIN SYSTEM SECTION 02400 - STORM DRAIN SYSTEM CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Reference Standards... 1 1.04 Quality Assurance... 1 1.05 Measurement And

More information

DESIGN AND CONSTRUCTION GUIDELINES AND STANDARDS DIVISION 33 UTILITIES 33 00 00 SITE UTILITIES

DESIGN AND CONSTRUCTION GUIDELINES AND STANDARDS DIVISION 33 UTILITIES 33 00 00 SITE UTILITIES SECTION INCLUDES Domestic Water Fire Water Service Water Well Sanitary Sewer Storm Drains Foundation Drainage RELATED SECTIONS 03 30 00 Concrete 21 00 00 Fire Suppression - Sprinklers 22 00 00 Plumbing

More information

SECTION 02732 BUILDING SEWERS. B. Connection of building sanitary drainage system to municipal sewers.

SECTION 02732 BUILDING SEWERS. B. Connection of building sanitary drainage system to municipal sewers. SECTION 02732 BUILDING SEWERS PART 1 GENERAL 1.01 SECTION INCLUDES A. Lateral piping, fittings, and accessories. B. Connection of building sanitary drainage system to municipal sewers. 1.02 REGULATORY

More information

SECTION XXIII EXCAVATION AND BACKFILLING

SECTION XXIII EXCAVATION AND BACKFILLING SECTION XXIII EXCAVATION AND BACKFILLING This section includes guidelines for excavation and backfilling of utilities and structures. A. DEFINITIONS 1. Open areas: Those areas that do not include building

More information

Beacon Hill Sewer District Standard Specifications

Beacon Hill Sewer District Standard Specifications Beacon Hill Sewer District Standard Specifications Residential Gravity Side Sewer Including Design Criteria and Standard Construction Drawings Residential Gravity Side Sewer Design Criteria 1. Provisions

More information

Model Specification 509 DRISCOPLEX 4200 and DRISCOPLEX 4300 Gravity Flow Sanitary Sewer

Model Specification 509 DRISCOPLEX 4200 and DRISCOPLEX 4300 Gravity Flow Sanitary Sewer Model Specification 509 DRISCOPLEX 4200 and DRISCOPLEX 4300 Gravity Flow Sanitary Sewer The user may choose to adopt part or all of this Model Specification; however, the user should ensure that all parts

More information

SECTION 15200 GRAVITY SANITARY SEWERS. A. Gravity sanitary sewers and appurtenances, including stacks and service connections.

SECTION 15200 GRAVITY SANITARY SEWERS. A. Gravity sanitary sewers and appurtenances, including stacks and service connections. SECTION 15200 GRAVITY SANITARY SEWERS PART 1 GENERAL.01 SCOPE A. Gravity sanitary sewers and appurtenances, including stacks and service connections..02 SUBMITTALS A. Conform to requirements of Section

More information

SECTION 33 11 00.11 POLYVINYL CHLORIDE (PVC) PIPE

SECTION 33 11 00.11 POLYVINYL CHLORIDE (PVC) PIPE SECTION 33 11 00.11 POLYVINYL CHLORIDE (PVC) PIPE PART 1: GENERAL 1.01 SECTION INCLUDES PVC pressure pipe and fabricated fittings in nominal sizes 4-inches through 12-inches with cast iron pipe equivalent

More information

The Manitoba Water Services Board SECTION 022180 Standard Construction Specifications PIPE EXCAVATION, BEDDING AND BACKFILL Page 1 of 11

The Manitoba Water Services Board SECTION 022180 Standard Construction Specifications PIPE EXCAVATION, BEDDING AND BACKFILL Page 1 of 11 Page 1 of 11 Part 1 General 1.1 DESCRIPTION OF WORK.1 The work described herein shall consist of the excavation of trenches (or excavation of tunnels); the supply and placing of bedding and backfill materials;

More information

Section 402. STORM SEWERS

Section 402. STORM SEWERS 402.02 Section 402. STORM SEWERS 402.01. Description. This work consists of constructing storm sewers of the size and class required, including excavation, bedding, and backfill. 402.02. Materials. Provide

More information

CHAPTER 6 - SANITARY SEWER

CHAPTER 6 - SANITARY SEWER CHAPTER 6 - SANITARY SEWER 6.1 GENERAL This section covers the requirements for PVC plastic sewer pipe materials and installation in sanitary sewer construction. 6.2 PIPE PVC gravity sewer pipe and fittings

More information

B. Trenching, Backfilling, and Compacting: STD SPEC 02223. A. Submit submittal packages in accordance with Standard Specification Section 01300

B. Trenching, Backfilling, and Compacting: STD SPEC 02223. A. Submit submittal packages in accordance with Standard Specification Section 01300 STANDARD SPECIFICATION SECTION 15065 PLASTIC (PVC) GRAVITY SEWER PIPE PART 1 - GENERAL 1.01 DESCRIPTION A. This section includes materials, installation, and testing of PVC gravity sewer pipe conforming

More information

TABLE OF CONTENTS SECTION 300 STORM SEWER

TABLE OF CONTENTS SECTION 300 STORM SEWER TABLE OF CONTENTS SECTION 300 STORM SEWER Starts on Page 300 GENERAL... 2 301 MATERIALS... 2 302 CONSTRUCTION PROCEDURES... 5 303 TESTING... 5 304 ABANDONMENT OF EXISTING STORM SEWER FACILITIES... 6 305

More information

SECTION 33 41 03 POLYVINYL CHLORIDE (PVC) PIPE

SECTION 33 41 03 POLYVINYL CHLORIDE (PVC) PIPE SECTION 33 41 03 POLYVINYL CHLORIDE (PVC) PIPE PART 1 GENERAL 1.01 SECTION INCLUDES A. This section includes all labor, materials, equipment, and incidentals required and installation of Polyvinyl Chloride

More information

SECTION 33 05 16.13 PRECAST CONCRETE UTILITY STRUCTURES

SECTION 33 05 16.13 PRECAST CONCRETE UTILITY STRUCTURES SECTION 33 05 16.13 PRECAST CONCRETE PART 1 - GENERAL 1.01 SECTION INCLUDES A. This item shall consist of the construction of both sanitary and storm sewer precast concrete manholes in accordance with

More information

ARTICLE VI (ALTERNATE) STANDARD SPECIFICATIONS. for (PVC) SANITARY SEWER MAIN CONSTRUCTION

ARTICLE VI (ALTERNATE) STANDARD SPECIFICATIONS. for (PVC) SANITARY SEWER MAIN CONSTRUCTION ARTICLE VI (ALTERNATE) STANDARD SPECIFICATIONS for (PVC) SANITARY SEWER MAIN CONSTRUCTION VI(A).1 General VI(A).2 Materials and Equipment VI(A).3 Installation of Sanitary Sewer Mains VI(A).4 Laying of

More information

SECTION 15076 CEMENT-MORTAR LINED AND COATED STEEL PIPE

SECTION 15076 CEMENT-MORTAR LINED AND COATED STEEL PIPE SECTION 15076 CEMENT-MORTAR LINED AND COATED (CML&C) STEEL PIPE PART 1 GENERAL 1.01 DESCRIPTION This section designates the requirements for steel pipe fabrication, test in shop, installation of steel

More information

SECTION 36 - CAST-IN-PLACE CONCRETE PIPE (CIPCP) TABLE OF CONTENTS

SECTION 36 - CAST-IN-PLACE CONCRETE PIPE (CIPCP) TABLE OF CONTENTS SECTION 36 - CAST-IN-PLACE CONCRETE PIPE (CIPCP) TABLE OF CONTENTS Section Page 36-1 GENERAL... 36.1 36-2 PIPEMAKING EQUIPMENT... 36.1 36-3 TRENCH EXCAVATION... 36.1 36-4 SPECIAL FOUNDATION TREATMENT...

More information

SECTION 08000 STORM DRAINAGE TABLE OF CONTENTS

SECTION 08000 STORM DRAINAGE TABLE OF CONTENTS SECTION 08000 STORM DRAINAGE 08010 DESIGN A. Location B. Sizing TABLE OF CONTENTS 08020 MATERIALS A. Pipe Materials B. Structure Materials C. Installation D. Inlets and Outlets 08030 INSPECTIONS AND TESTING

More information

SECTION 02630 STORM DRAINAGE SYSTEM

SECTION 02630 STORM DRAINAGE SYSTEM SECTION 02630 PART 1 - GENERAL 1.01 DESCRIPTION A. Section includes specifications for storm drainage systems including modifications and connections to existing storm drainage systems. 1.02 REFERENCE

More information

Section C-1 Pipes and Fittings

Section C-1 Pipes and Fittings Section C-1 Pipes and Fittings C1.00 Work Included The work under this Division of the Specifications shall include all labor, materials, and equipment necessary to furnish and install all piping, pipelines,

More information

SECTION 206 EXCAVATION FOR STRUCTURES

SECTION 206 EXCAVATION FOR STRUCTURES SECTION 206 EXCAVATION FOR STRUCTURES 206.1 Description. This work shall consist of the necessary excavation for the foundations of all structures, removal and disposal of all excavated material, backfilling

More information

Sanitary Sewer Mains and Services

Sanitary Sewer Mains and Services Sewer Title Sanitary Sewer Mains and Services STitle Sewer Table of Contents "CORRECTIVE PERIOD & INSPECTION FOR SANITARY SEWERS & SERVICES"... 1 1. TERM OF GUARANTEE... 1 2. CONTRACTOR LICENSE AND PERMITS...

More information

Electric Engineering Division FIBER CONDUIT RULES AND REGULATIONS

Electric Engineering Division FIBER CONDUIT RULES AND REGULATIONS Electric Engineering Division FIBER CONDUIT RULES AND REGULATIONS TABLE OF CONTENTS I. RULES AND REGULATIONS A. TABLE OF CONTENTS... 2 B. TERMS AND DEFINITIONS... 3 C. DEVELOPER S/CONTRACTOR S RESPONSIBILITIES...

More information

SECTION 33 41 00 REINFORCED CONCRETE PIPE. A. The following is a list of SPECIFICATIONS, which may be related to this section:

SECTION 33 41 00 REINFORCED CONCRETE PIPE. A. The following is a list of SPECIFICATIONS, which may be related to this section: SECTION 33 41 00 REINFORCED CONCRETE PIPE PART 1 GENERAL 1.01 SECTION INCLUDES A. This section includes construction of reinforced concrete pipe for storm drainage, culverts, and sanitary sewer, including

More information

STORM DRAIN DESIGN AND CONSTRUCTION STANDARDS & SPECIFICATIONS 400 SERIES

STORM DRAIN DESIGN AND CONSTRUCTION STANDARDS & SPECIFICATIONS 400 SERIES CITY OF PETALUMA STORM DRAIN DESIGN AND CONSTRUCTION STANDARDS & SPECIFICATIONS 400 SERIES AUGUST 1999 Revised 10/98 City of Petaluma Petaluma, California STORM DRAIN INSTALLATION DETAIL

More information

CW EXCAVATION BEDDING AND BACKFILL TABLE OF CONTENTS

CW EXCAVATION BEDDING AND BACKFILL TABLE OF CONTENTS February 2005 DIVISION 3 - CW 2030 R7 CW 2030 - EXCAVATION BEDDING AND BACKFILL TABLE OF CONTENTS 1. DESCRIPTION...1 1.1 General...1 1.2 Definitions...1 1.3 Referenced Standard Construction Specifications...1

More information

Installation Guide. Recommendations for Installation of IPS & PIP Pressure Pipe

Installation Guide. Recommendations for Installation of IPS & PIP Pressure Pipe Installation Guide Recommendations for Installation of IPS & PIP Pressure Pipe INDEX Index......... 1 Diamond Plastic Pipe....... 2 PVC Installation Guide...... 2 Handling & Storage....... 2 Receiving

More information

SECTION 6000 - EXCAVATION, TRENCHING AND BACKFILLING (Pipeline Construction)

SECTION 6000 - EXCAVATION, TRENCHING AND BACKFILLING (Pipeline Construction) SECTION 6000 - EXCAVATION, TRENCHING AND BACKFILLING (Pipeline Construction) 6001 SCOPE. This section covers excavation and trenching work and shall include the necessary clearing, grubbing, and preparation

More information

SANITARY SEWER MANHOLE CONSTRUCTION 2.2 PORTLAND CEMENT AND PORTLAND CEMENT CONCRETE (PCC):

SANITARY SEWER MANHOLE CONSTRUCTION 2.2 PORTLAND CEMENT AND PORTLAND CEMENT CONCRETE (PCC): PART 1 GENERAL 1.1 SCOPE: A. This item includes the work necessary for the construction and installation of sanitary sewer manholes. B. The Contractor may, at his option, use cast-in-place type manholes,

More information

SECTION PRECAST CONCRETE UTILITY STRUCTURES. 1. Trench excavation, backfill, and compaction; Section

SECTION PRECAST CONCRETE UTILITY STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 03400-1 of 8 SECTION 03400 PRECAST CONCRETE UTILITY STRUCTURES 03400.01 GENERAL A. Description Precast concrete utility structures shall include, but not necessarily be limited to, furnishing and installing

More information

TECHNICAL SPECIFICATIONS GRAVITY AND PRESSURE SEWER LINE AND MATERIALS

TECHNICAL SPECIFICATIONS GRAVITY AND PRESSURE SEWER LINE AND MATERIALS TECHNICAL SPECIFICATIONS GRAVITY AND PRESSURE SEWER LINE AND MATERIALS Scope of Work Work performed under this contract shall consist of furnishing and installing, complete and ready for service, the sewer

More information

SUBDRAINS AND FOOTING DRAIN COLLECTORS. A. Construct subdrains, subdrain cleanouts and outlets, and footing drain collectors.

SUBDRAINS AND FOOTING DRAIN COLLECTORS. A. Construct subdrains, subdrain cleanouts and outlets, and footing drain collectors. SUBDRAINS AND FOOTING DRAIN COLLECTORS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Subdrains B. Subdrain Cleanouts and Outlets C. Footing Drain Collectors D. Storm Sewer Service and Connections 1.02 DESCRIPTION

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS

San Antonio Water System Standard Specifications for Construction ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS 1103.1 DESCRIPTION: 1. Repair of sanitary sewer lines by replacing short lengths of failed pipe with new pipe. 2. Repair of service laterals located

More information

LS 2540 SEWER LATERALS AND INSPECTION TEES

LS 2540 SEWER LATERALS AND INSPECTION TEES LS 2540 SEWER LATERALS AND INSPECTION TEES A. Summary B. Submittals C. Site Information D. Sewer Pipe and Fittings E. Lateral Locations F. Lateral Installation G. Inspection Tee Installation H. Removal

More information

STANDARD SPECIFICATIONS SECTION 02512 CLEANING AND LINING WATER MAINS

STANDARD SPECIFICATIONS SECTION 02512 CLEANING AND LINING WATER MAINS STANDARD SPECIFICATIONS SECTION 02512 CLEANING AND LINING WATER MAINS PART 1 GENERAL 1.1 DESCRIPTION A. Section includes requirements for cleaning and lining existing cast iron and ductile iron water mains

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 816 STEEL PIPE INSTALLATION

San Antonio Water System Standard Specifications for Construction ITEM NO. 816 STEEL PIPE INSTALLATION ITEM NO. 816 STEEL PIPE INSTALLATION 816.1 DESCRIPTION: This item shall consist of steel pipe installation in accordance with these specifications and as directed by the Engineer. 816.2 SUBMITTALS: Contractor

More information

CHAPTER 4 INSTALLATION OF PIPE AND TESTING OF PIPE BACKFILL

CHAPTER 4 INSTALLATION OF PIPE AND TESTING OF PIPE BACKFILL CHAPTER 4 INSTALLATION OF PIPE AND TESTING OF PIPE BACKFILL Why talk about pipe in a Soils and Aggregate School? Pipe-soil interaction is critical to successful performance of system Treatment of soils

More information

SANITARY SEWER SYSTEMS

SANITARY SEWER SYSTEMS SANITARY SEWER SYSTEMS I. Sanitary sewer size and slope design. A. Minimum size is 8 inch. B. Minimum flow velocity is 2 feet per second, 2 fps. C. Maximum flow velocity shall be 11 fps. D. Larger lines

More information

WASHINGTON COUNTY SANITARY SERVICE LATERAL MATERIAL AND INSTALLATION GUIDE. Established By: THE BOARD OF COUNTY COMMISSIONERS WASHINGTON COUNTY, OHIO

WASHINGTON COUNTY SANITARY SERVICE LATERAL MATERIAL AND INSTALLATION GUIDE. Established By: THE BOARD OF COUNTY COMMISSIONERS WASHINGTON COUNTY, OHIO WASHINGTON COUNTY SANITARY SERVICE LATERAL MATERIAL AND INSTALLATION GUIDE Established By: THE BOARD OF COUNTY COMMISSIONERS WASHINGTON COUNTY, OHIO Commissioners Mr. Timothy C. Irvine, President Ms. Cora

More information

SECTION 02763 POINT REPAIRS TO SANITARY SEWERS. A. Repairs to existing sewer lines by replacing short lengths of failed pipe.

SECTION 02763 POINT REPAIRS TO SANITARY SEWERS. A. Repairs to existing sewer lines by replacing short lengths of failed pipe. SECTION 02763 PART 1 G E N E R A L 1.01 SECTION INCLUDES A. Repairs to existing sewer lines by replacing short lengths of failed pipe. 1.02 UNIT PRICES A. Measurement for point repairs is on a unit price

More information

Civil. 2. City of Seattle Supplement to the Specification for Road, Bridge and Municipal Construction, most current addition.

Civil. 2. City of Seattle Supplement to the Specification for Road, Bridge and Municipal Construction, most current addition. Design Guide Basis of Design This section applies to the design and installation of earthwork and backfill. Design Criteria No stockpiling of excavation materials is allowed unless the Geotechnical Engineer

More information

SECTION 15056 DUCTILE-IRON PIPE AND FITTINGS

SECTION 15056 DUCTILE-IRON PIPE AND FITTINGS SECTION 15056 PART 1 GENERAL 1.01 DESCRIPTION This section includes materials and installation of ductile-iron pipe and fittings for potable and recycled water systems. A written request to use Ductile

More information

UFGS-02362 (August 2004) UNIFIED FACILITIES GUIDE SPECIFICATIONS

UFGS-02362 (August 2004) UNIFIED FACILITIES GUIDE SPECIFICATIONS USACE / NAVFAC / AFCEC / NASA UFGS-31 31 16.20 (April 2006) Change 2-11/14 ----------------------------- Preparing Activity: NAVFAC Replacing without change UFGS-02362 (August 2004) UNIFIED FACILITIES

More information

SECTION 7- STORM SEWER

SECTION 7- STORM SEWER SECTION 7- STORM SEWER 7.1. STORM SEWERS.... 7-1 7.2. SUMP DRAINS... 7-3 7.3. CATCH BASINS... 7-3 7.4. MANHOLES... 7-4 7.5. STORM SEWER CALCULATIONS... 7-4 7.6. CULVERTS AND BRIDGES... 7-5 7.7. OPEN CHANNELS...

More information

Standard Specification K105 Water Reticulation

Standard Specification K105 Water Reticulation Standard Specification K105 Water Reticulation INDEX K105.1 SCOPE OF WORK 3 K105.2 STANDARDS 3 K105.3 MATERIALS 3 K105.3.1 Pipes and Fittings 3 K105.3.2 Storage and Handling 4 K105.3.3 Bedding and Haunching

More information

TECHNICAL NOTE Culvert Sliplining and Lining of Casings with HPPipe

TECHNICAL NOTE Culvert Sliplining and Lining of Casings with HPPipe TECHNICAL NOTE Culvert Sliplining and Lining of Casings with HPPipe TN 5.14 February 2010 Introduction It may be at times necessary, in an aging infrastructure, to rehabilitate drainage and sanitary lines

More information

CCU Engineering Specifications. Section 003300 PRECAST CONCRETE PRODUCTS

CCU Engineering Specifications. Section 003300 PRECAST CONCRETE PRODUCTS CCU Engineering Specifications Section 003300 Effective Date: Nov. 1st, 2011 Page 1 of 5 PRECAST CONCRETE PRODUCTS PART 1 - GENERAL The following specification is intended for use for the design, selection

More information

SECTION 33 41 13 PUBLIC STORM UTILITY DRAINAGE PIPING

SECTION 33 41 13 PUBLIC STORM UTILITY DRAINAGE PIPING SECTION 33 41 13 PUBLIC STORM PART 1 - GENERAL 1.01 SECTION INCLUDES A. Storm drainage piping, fittings, and accessories at proposed station areas and locations other than under and immediately adjacent

More information

The Manitoba Water Services Board SECTION 027030 Standard Construction Specifications September 2013 Page 1 of 21

The Manitoba Water Services Board SECTION 027030 Standard Construction Specifications September 2013 Page 1 of 21 September 2013 Page 1 of 21 Part 1 General 1.1 DESCRIPTION OF WORK.1 The work described herein shall consist of the construction of sewers including: the supply and installation of pipe, saddles, tees,

More information

STANDARD SPECIFICATIONS FOR PRIVATE BUILDING SEWER LINES IN PUBLIC RIGHT-OF-WAY

STANDARD SPECIFICATIONS FOR PRIVATE BUILDING SEWER LINES IN PUBLIC RIGHT-OF-WAY STANDARD SPECIFICATIONS FOR PRIVATE BUILDING SEWER LINES IN PUBLIC RIGHT-OF-WAY Approved and adopted as Official Document Number 800576 this 10th day of December, 1980 Donald R. Boyd, P.E., Director Water

More information

This section includes materials, installation and testing of earthwork for excavations, fills and embankments for structures and sites.

This section includes materials, installation and testing of earthwork for excavations, fills and embankments for structures and sites. STANDARD SPECIFICATION SECTION 02200 EARTHWORK PART 1 - GENERAL 1.01 DESCRIPTION This section includes materials, installation and testing of earthwork for excavations, fills and embankments for structures

More information

OAR52 A-1 (September, 1981)

OAR52 A-1 (September, 1981) APPENDIX A SEWER PIPELINES (1) MINIMUM REQUIREMENTS FOR SEWER - PIPELINES (a) Capacity: Sewers shall be of such diameter as to pass without overflow, bypass, or back flow onto damageable property of a

More information

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS July 14, 2015 1.0 GENERAL BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS This work shall consist of furnishing all materials, equipment, labor, and incidentals necessary for conducting bi-directional

More information

SECTION 400 SANITARY SEWER SYSTEM

SECTION 400 SANITARY SEWER SYSTEM SECTION 400 SANITARY SEWER SYSTEM Section Title Page 401 General................................... 25 402 Materials.................................. 25 403 Design Requirements........................

More information

53.03 MATERIALS FOR SEWER LINER PIPE AND FITTINGS: The following materials are approved for installation in sanitary sewer lines:

53.03 MATERIALS FOR SEWER LINER PIPE AND FITTINGS: The following materials are approved for installation in sanitary sewer lines: Division 53: Slip-Lining of Existing Sewer Line 53.01 GENERAL: This section includes all labor, materials, transportation, equipment necessary to rehabilitate by means of Instituform deteriorated sections

More information

PVC FITTINGS & LATERALS FOR SOLID WALL PVC SEWER PIPE

PVC FITTINGS & LATERALS FOR SOLID WALL PVC SEWER PIPE DESIGN & INSTALLATION GUIDE FOR PVC FITTINGS & LATERALS FOR SOLID WALL PVC SEWER PIPE TABLE OF CONTENTS Introduction 2 Products 3 Main-Line Fittings & Service-Line Fittings 3-4 Connections to Dissimilar

More information

SECTION 9.02 BUILDING SUBSURFACE DRAINS (PERIMETER, ETC.)

SECTION 9.02 BUILDING SUBSURFACE DRAINS (PERIMETER, ETC.) CHAPTER 9 SEWER / STORM DRAIN / IRRIGATION LINES SECTION 9.01 GENERAL This section covers the requirements for piping materials and installation of Lehi City sewer, storm drainage and irrigation collection

More information

SECTION 02530 STORM DRAINAGE STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.

SECTION 02530 STORM DRAINAGE STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250. 02530-1 of 5 SECTION 02530 STORM DRAINAGE STRUCTURES 02530.01 GENERAL A. Description Storm drainage structure construction shall include, but not necessarily be limited to, furnishing and installing or

More information

City of Regina Standard Construction Specification SECTION 1320 SEWERMAIN TESTING

City of Regina Standard Construction Specification SECTION 1320 SEWERMAIN TESTING 1.0 GENERAL 1.1 Scope 2.0 PRODUCTS 1.1.1 The work shall consist of testing wastewater and/or storm mains to ensure construction conforms to the proper line, grade, cross section and performance. 2.1 The

More information

SECTION 03400 PRECAST CONCRETE STRUCTURES

SECTION 03400 PRECAST CONCRETE STRUCTURES PART 1 GENERAL 1.01 SCOPE OF WORK A. Furnish all labor, materials, and equipment required to install precast concrete manholes, sanitary leaching rings, pump station, valve chamber, structures, frames,

More information

CW 2130 - GRAVITY SEWERS TABLE OF CONTENTS

CW 2130 - GRAVITY SEWERS TABLE OF CONTENTS August 2010 CW 2130 - GRAVITY SEWERS TABLE OF CONTENTS 1. DESCRIPTION... 1 1.1 General... 1 1.2 Definitions... 1 1.3 Referenced Standard Construction Specifications... 1 1.4 Referenced Standard Details...

More information

SECTION TRENCHING, BACKFILLING AND COMPACTING

SECTION TRENCHING, BACKFILLING AND COMPACTING SECTION 02221 TRENCHING, BACKFILLING AND COMPACTING PART 1 GENERAL 1.01 SUMMARY A. This section addresses excavation and trenching; including subsurface drainage, dewatering, preparation of subgrade, pipe

More information

SPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION

SPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION SPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION 1. SCOPE Pipe subsoil drains shall be constructed in accordance with this specification and in conformity with the lines, grades and cross-sections shown

More information

INDEX. Sec. No. Items Page Nos.

INDEX. Sec. No. Items Page Nos. INDEX Sec. No. Items Page Nos. 1. General............... GWM- 2 2. Method of Construction............... GWM- 2 3. Basis of Payment............... GWM- 2 4. Material Testing............... GWM- 3 5. Excavation...............

More information

MDWASD 8/1999 SECTION 02315 TRENCHING AND BACKFILLING FOR PIPING SYSTEMS

MDWASD 8/1999 SECTION 02315 TRENCHING AND BACKFILLING FOR PIPING SYSTEMS PART 1 - GENERAL 1.01 WORK INCLUDED SECTION 02315 TRENCHING AND BACKFILLING FOR PIPING SYSTEMS A. The work included under this Section consists of excavating, backfilling and compaction as required for

More information

SECTION WATER MAINS. 1. Protection of the environment; Section Trench excavation, backfill, and compaction; Section

SECTION WATER MAINS. 1. Protection of the environment; Section Trench excavation, backfill, and compaction; Section 02551-1 of 13 SECTION 02551 WATER MAINS 02551.01 GENERAL A. Description Water main installation shall include, but not necessarily be limited to, furnishing and installing water pipe, fittings, and appurtenances

More information

SECTION 15125 HIGH DENSITY POLYETHYLENE (HDPE) PIPE AND FITTINGS FOR WATER DISTRIBUTION AND TRANSMISSION

SECTION 15125 HIGH DENSITY POLYETHYLENE (HDPE) PIPE AND FITTINGS FOR WATER DISTRIBUTION AND TRANSMISSION SECTION 15125 HIGH DENSITY POLYETHYLENE (HDPE) PIPE AND FITTINGS FOR WATER DISTRIBUTION AND TRANSMISSION PART 1 GENERAL.01 SECTION INCLUDES Furnishing and installing 4 inch through 16 inch high density

More information

Specification for Pipe Bursting Gravity Sewer Mains with HDPE Pipe

Specification for Pipe Bursting Gravity Sewer Mains with HDPE Pipe Specification for Pipe Bursting Gravity Sewer Mains with HDPE Pipe 1. GENERAL The following supplemental sewer main specifications are intended to address the installation of high-density polyethylene

More information

550 PIPE CULVERTS, SEWERS AND DRAINS

550 PIPE CULVERTS, SEWERS AND DRAINS 551.01 550 PIPE CULVERTS, SEWERS AND DRAINS 551 GENERAL 551.01 Description 551.02 Materials 551.03 Excavation 551.04 Protection of Excavation 551.05(a) Bedding for Rigid Pipe 551.05(b) Bedding for Non-Rigid

More information

SECTION 2400 SANITARY SEWER LINES 1.00 GENERAL

SECTION 2400 SANITARY SEWER LINES 1.00 GENERAL SECTION 2400 SANITARY SEWER LINES 1.00 GENERAL 1.01 Scope. Work under this section shall include furnishing all materials, labor and tools necessary to perform all installation, cleaning and testing of

More information

SECTION 31 20 00 EARTH MOVING

SECTION 31 20 00 EARTH MOVING SECTION 31 20 00 PART 1 - GENERAL 1.01 DESCRIPTION A. This Section describes the requirements for excavating, filling, and grading for earthwork at Parking Structure, new exit stair and as required to

More information

SANITARY SEWERS S.1 GENERAL CONSIDERATIONS TYPE OF SEWERS

SANITARY SEWERS S.1 GENERAL CONSIDERATIONS TYPE OF SEWERS S.1 GENERAL CONSIDERATIONS SANITARY SEWERS S.1.1 TYPE OF SEWERS The CITY will approve PLANS for new sewer systems and extensions only when designed as separate systems in which precipitation, runoff, and

More information

SECTION 02720 SANITARY SEWER AND STORM DRAIN SYSTEMS

SECTION 02720 SANITARY SEWER AND STORM DRAIN SYSTEMS SECTION 02720 SANITARY SEWER AND STORM DRAIN SYSTEMS PART 1 GENERAL 1.01 SECTION INCLUDES A. The requirements for pipe material and installation in sewer and drainage collection systems. All materials

More information

MS-6/2009 Model Specification and Checklist for Polyethylene (PE) Pipe for the Sliplining of Sewers

MS-6/2009 Model Specification and Checklist for Polyethylene (PE) Pipe for the Sliplining of Sewers MS-6/2009 Model Specification and Checklist for Polyethylene (PE) Pipe for the Sliplining of Sewers The Plastics Pipe Institute March 2009 1 DISCLAIMER This guideline has been prepared by the Plastics

More information

Minimum Design Criteria for the permitting of Gravity Sewers

Minimum Design Criteria for the permitting of Gravity Sewers Minimum Design Criteria for the permitting of Gravity Sewers Adopted by the Division of Water Quality on February 12, 1996 Updated to 15A NCAC 2T Regulations on March 2008 1,400 copies of this document

More information