Financing hydropower Introduction to the Specifics of Small Hydro Power Plants



Similar documents
Assessment of hydropower resources

Analytical Approach for Cost Estimation of Low Head Small Hydro Power Schemes

Clean Development Mechanism Project Opportunities in Indonesia

Micro-Hydro. Module Introduction. Tokyo Electric Power Co. (TEPCO)

XAYABURI HYDRO POWER PLANT, LAO PDR

National Electric Power Regulatory Authority

CHAPTER 3 RESEARCH DESIGN

Project Finance Structuring: Case Study - Nam Theun 2

Frequently Asked Questions (FAQs) on Hydropower

Pöyry renewable energy. Energy through small hydropower

: Promoters Contribution : Term Loan Total Profitability at optimum level. : Optimum Utilization(3 rd Year)

Hydro Power Projections Report. Jennifer Palmer

HYDROMATRIX Jebel Aulia - Sudan

Handbook for Developing MICRO HYDRO In British Columbia

NOTE. Note on the pumped storage potential of the Onslow-Manorburn depression, New Zealand

Manage water resources for on site hydro-electricity generation

Hydropower in Rwanda: Ongoing Initiatives & New Investment Opportunities. Yves Muyange Director General Energy Water & Sanitation Authority

Hydroelectric Power Plant - Los Cóndores. Santiago, April 2014

Pico Power: A Boon for Rural Electrification

Compact - Effi cient - Reliable. DIVE-Turbine An innovative turbine concept for small hydro power plants.

Guide on how to refurbish low head small hydro sites

Swiss Resource Centre and Consultancies for Development

AN ECONOMICAL AND TECHNICAL CASE STUDY FOR A SMALL HYDROPOWER SYSTEM

Sample Micro Hydro Initial Report

Micro-hydro Power. Introduction. What is hydropower? System types. Power the entire farm Generate power to sell back to the national grid

Technical Consultant

SMALL HYDRO PROJECT ANALYSIS

A Green Sector Overview

MICRO HYDRO FOR THE FARM AND HOME

What are the Benefits?

1.1 Introduction. Chapter 1: Feasibility Studies: An Overview

1. Purpose and scope. 2. SEPA's role in hydropower and planning

A CASE-STUDY OF CUA_DAT CFRD IN VIETNAM

IUCN Guidelines to Avoid Impacts of Water Resources Projects on Dams and Other Water Infrastructure

MICRO-HYDROPOWER NEED FOR ENERGY FOR RURAL DEVELOPMENT. By: Payman Hassan Rashed

Sensitivity Analysis for Small Hydropower Plant (SHP)

Flood mitigation program for Gatun lake. Programa de mitigación de inundaciones del lago Gatún

HydroHelp 1 AN EXCEL PROGRAM DEVELOPED FOR TURBINE-GENERATOR SELECTION FOR HYDROELECTRIC SITES

Sewerage Management System for Reduction of River Pollution

Amir Bashirzadeh Tabrizi, Nassir Gifani. TOOSSAB Consulting Engineers Company

Exploring the Possibilities of Small Hydropower Development Utilizing NRCS-Assisted Flood Control Dams

Integrating End-User and Grid Focused Batteries and Long-Term Power-to-Gas Storage for Reaching a 100 % Renewable Energy Supply

Technology Fact Sheet for Mitigation B. Small Hydropower Technology i 1. Introduction 1.1. Historical - All over the World, hydropower sector is

The River Devoll Project

Overview of Tekeze hydroelectric power plant General

Design and manufacturing of Crossflow, Pelton, Kaplan and Francis turbines

Tunnelling and underground works in PPC hydro projects: Contracting practices & construction management Ioannis Thanopoulos Dr.

Consulting Boards for Large Civil Engineering Projects

Economics Training Series Introductory Course. Cost Estimation

Feasibility Study Mzimvubu Water Project

A Guide to the Management of Tailings Facilities. Second Edition, 2011

ENGINEERING COMPETENCY CLAIMS

Technical Approach and Methodology

Chattichai WAISURASINGHA 1*, Prinya CHINDAPRASIRT 1, Winai SRI-AMPORN 1 and Sinee CHUANGCHAM 2

ENVIRONMENTAL MITIGATION AT HYDROELECTRIC PROJECTS Volume 1. Current Practices for Instream Flow Needs, Dissolved Oxygen, and Fish Passage

Wind Farm Project Finance

CHAPTER 3 STORM DRAINAGE SYSTEMS

E N G I N E E R I N G

Búrfell. hydropower station

Environmental and Social Review Summary

Technical Due Diligence what do we look out for?

Feasibility Study Requirements. Qatar Development Bank

Mini & Micro Hydro Power Generation. EBARA Hatakeyama Memorial Fund Tokyo, Japan

S.1 Introduction to the Case Study on Micro-Hydro Power Plants

Workshop on Rehabilitation of Hydropower

USAID ENERGY POLICY PROGRAM SITE VISIT REPORT STATUS OF 4 RUN OF RIVER HYDROPOWER PROJECTS. October 2013

VERBUND AG,

MICRO-HYDRO POWER. Technical

eeef - European Energy Efficiency Fund

China s Small Hydropower in Rural Energy Development

A Conceptual Software System for Water Allocation, Planning and Catchment Management

EXHIBIT A SCOPE OF WORK Montgomery Reservoir Improvements

Simple project evaluation spreadsheet model

Short-cut design of small hydroelectric plants

Hydroelectric Power (3 Semester Hours)

FACT SHEET 6: HYDRO ELECTRICITY

4 Water supply description

Tanzania: Lower Kihansi Hydropower Station / Hydropower plants

Annex 1 Tool for the demonstration and assessment of additionality

Minihydro to boost local economic growth The case of Nepal

OPINION OF THE EUROPEAN CENTRAL BANK

HYDRO POWER GENERATION

Electricity Generation from Renewable Energy in Sri Lanka: Future Directions

BÜYÜKDÜZ HYDROELECTRIC POWER PLANT, TURKEY

CHAPTER VII CONSTRUCTION QUALITY CONTROL INSPECTION PROGRAM 1

MICRO HYDRO POWER GENERATING EQUIPMENT

Economic Analysis and Economic Decisions for Energy Projects

CHAPTER 2 HYDRAULICS OF SEWERS

2008 Total Dissolved Gas Management Plan

Establishing the feasibility of your proposed mining venture

D 4.4 Report on the feasibility analysis for most technically acceptable locations

Rating Methodology for Domestic Life Insurance Companies

Contractor s Estimation of Cost and Bidding Strategy. Construction Project Management_Kumar Neeraj Jha

Transcription:

EFSE Annual Meeting 2012, Tiblisi GGF Technical Workshop on Small Hydro Power Financing hydropower Introduction to the Specifics of Small Hydro Power Plants May 2012 01 June 2012 Arnsburger Str. 64, 60385 Frankfurt, Germany Tel +49-69-943188-0, Fax +49-69-943188-18 Internet: www.macsonline.de

Introduction to the specifics of Small Hydro Power Plants (SHPP) Structure of the Presentation 1. General Overview: Small Hydro Power Plants 2. The major planning steps 3. Hydrology: the basis for SHPP planning 4. First approximation of SHPP layout and electricty generation 5. Optimisation of SHPP 6. Determination of budgetary investment cost 7. SHPP bankable documents 8. Environmental and Social Impact Assessment 1

1. General Overview: Small Hydro Power Plants 1. General Overview: Small Hydro Power Plants 2. The major planning steps 3. Hydrology: the basis for SHPP planning 4. First approximation of SHPP layout and electricty generation 5. Optimization of SHPP 6. Determination of budgetary investment cost 7. SHPP bankable documents 8. Environmental and Social Impact Assessment 2

Small Hydro Power (SHPP) scheme Small Hydro Power Plant Usually < 10 MW installed capacity (under GGF financing SHPP projects < 30 MW are eligible) Run-of-river type SHPP Weir or low dam Electricity generation costs < EUR 96/MWh 3

SHPP Project: map segment 4

Hydro power is a mature technology make use of the experience! A design solution has been realised for almost any specific condition: what has been published and which design solution has stood the test of time?» Use proven design solutions, study operating projects with similar head and design flow One of its specifics: it requires the input from various fields of profession (hydrology, geology, ecology, civil- electrical- and mechanical engineering + economist).» It can be very costly to try to safe on inputs from experts who s task is to make the experience gained over decades availble for the planning process If planned properly, hydropower offers the lowest generation cost of all RE technologies at a very low risk and over an extremely long life time (>80 years)» Use high quality equipment (turbine/generator and gates!) able to withstand adverse conditions over the entire project lifetime 5

2. The major planning steps 1. General Overview: Small Hydro Power Plants 2. The major planning steps 3. Hydrology: the basis for SHPP planning 4. First approximation of SHPP layout and electricty generation 5. Optimization of SHPP 6. Determination of budgetary investment cost 7. SHPP bankable documents 8. Environmental and Social Impact Assessment 6

Three major planning steps not to be missed 1. Project formulation and layout» Hydrological study (flow duration, flood conditions, dry/wet year conditons)» Basic topographical overview (possible head, access conditions, existing roads)» Preliminary assessment of slope stability and sediment loads» Basic project layout with first approximation of electricity generation 2. Engineering design and layout optimisation» Pre-design of hydraulic structures with cost estimations» Optimisation of sizing» Evaluation of layout alternatives 3. Definition of project layout» Detailed field investigations» Detailed engineering design and bill of quantities» Budgetary quotations for equipment 7

3. Hydrology: the basis for SHPP planning 1. General Overview: Small Hydro Power Plants 2. The major planning steps 3. Hydrology: the basis for SHPP planning 4. First approximation of SHPP layout and electricty generation 5. Optimization of SHPP 6. Determination of budgetary investment cost 7. SHPP bankable documents 8. Environmental and Social Impact Assessment 8

Hydrology - the basis for planning The hydrological study determines how much water will be available for electricity generation over the year» hence provides the basis for the optimal sizing and the generation of the plant The reliability of its result is crucial to the plant s financial viability requires a high degree of professional experience to interprete any available run off data correctly Daily run-off data over several years is the core data base the hydrological study needs to be meaningful.» Supporting information is precipitation data and geological formation of the watershed in question As the planning process of a SHPP can extend over more than a year, it is highly recommended to start immediately with automated discharge measurements at the intended intake site to optain first hand data.» Appropriate data loggers are available (http://www.geoscientific.com/dataloggers/aquarod_freeze_tolerant_water_level_recorder.html) 9

Hydrological study - Deliverables Average flow duration curve as basis for the average annual generation and determination of the optimal design discharge Flow duration curve of the driest year for the sensitivity analysis to check whether the loan can be served even during dry spells Correction factor considering quality of data base to assess the sensitivity against variation of the water availability and the influence against missing or vague data Residual flow as a requirement from the ecological point of view Estimated flood events and water levels to design the hydraulic structures safely 10

Example of Flow Duration Curve, interpreted shaded area: flow available for power generation if maximum turbine capacity is 2.3 m³/s (104 kw) Optimum design discharge (60 days economic optimum) Residual flow 11

4. First approximation of SHPP layout and electricty generation 1. General Overview: Small Hydro Power Plants 2. The major planning steps 3. Hydrology: the basis for SHPP planning 4. First approximation of SHPP layout and electricty generation 5. Optimization of SHPP 6. Determination of budgetary investment cost 7. SHPP bankable documents 8. Environmental and Social Impact Assessment 12

First approximation of the average annual electricity generation 1. Choice of Q design based on the flow duration curve (Q 60 for a start) 2. Choice of penstock diameter (5% head loss for a start) and determination of the net head as function of the turbine flow 3. Choice of turbine type and number of units 4. Total efficiency of conversion equipment as a function of the turbine flow (use supplier data) 5. With this information calculate annual generation (first approximation) 13

SHPP Intake 14

SHPP Penstock 15

Choice of Turbine for SHPP 16

Hydro Power Physics at a glance: calculation of electricity generation W t = H n * Q * g * η tot * t W t = electricity generation in time span t (kwh, MWh, GWh) H n = net head (m) as f(q) Q = average flow through the turbine in time span t (m³/s) g = gravity = 9,81 (m/s²) η tot = η tur * η gen * η trans all a f(size, type and Q/Q design ) t = time span (hours) at which Q is available 17

Example: annual production (1. approximation) with Qdesign = 3.6 m³/s Exceedance Flow Residual flow Available flow Turbine flow Q/Qd Eff. Tot. Net head Power Generation % m³/s m³/s m³/s m³/s % % m kw GWh 8.3 6.15 0.0468 6.11 3.60 100.0 86.5 111.5 3,406 2.49 16.7 4.84 0.0468 4.79 3.60 100.0 86.5 111.5 3,406 2.49 25.0 3.88 0.0468 3.84 3.60 100.0 86.5 111.5 3,406 2.49 33.3 3.11 0.0468 3.07 3.07 85.2 87.6 111.9 2,949 2.15 41.7 2.63 0.0468 2.58 2.58 71.7 86.9 112.2 2,471 1.80 50.0 2.16 0.0468 2.11 2.11 58.6 86.6 112.5 2,015 1.47 58.3 1.65 0.0468 1.60 1.60 44.4 86.9 112.7 1,536 1.12 66.7 1.16 0.0468 1.12 1.12 31.0 87.2 112.9 1,077 0.79 75.0 0.83 0.0468 0.78 0.78 21.8 86.2 112.9 749 0.55 83.3 0.53 0.0468 0.48 0.48 13.3 83.6 113.0 444 0.32 91.7 0.39 0.0468 0.34 0.34 9.5 81.7 113.0 310 0.23 100.0 0.31 0.0468 0.27 0.27 7.4 80.3 113.0 236 0.17 Average annual generation 16.06 18

5. Optimization of SHPP 1. General Overview: Small Hydro Power Plants 2. The major planning steps 3. Hydrology: the basis for SHPP planning 4. First approximation of SHPP layout and electricty generation 5. Optimization of SHPP 6. Determination of budgetary investment cost 7. SHPP bankable documents 8. Environmental and Social Impact Assessment 19

Optimising the sizing of the SHPP After the first approximation an optimisation of the sizing of the SHPP needs to be done to obtain the most economic installed capacity. This requires the following steps: 1. Based on the data from the flow duration curve the exceedance and the flow are listed. 2. The investment cost of the entire plant is determined as a function of Q design This requires that a formula is developed for the cost of each component in relation to the design flow (see example for E&M equipment later) 3. Varying the Q design and the penstock diameter will vary the investment cost but at the same time the generation and with this the revenue. That Q design which yields the highest NPV will result in the most economic size, the plant should be designed for. This optimisation step is very often omitted resulting in SHPP too big for the river or the available potential is under-utilised. 20

The planning process and its optimisation 21

Electro mechancial equipment approximate cost As first approximation the cost for the electro-mechanical equipment can be expressed by the formula below The formula includes a scope of delivery of all components needed from end of penstock to 35 kv feed in i.e turbine inlet valve, turbine, generator, governor, LV control, transformer, MV switchgear, reflecting 2010 prices Where : I E+M (Euro) = 50,000 x H 0,529 x Q 0,74 H = net head (m) Q = design flow (m³/s) 22

6. Determination of budgetary investment cost 1. General Overview: Small Hydro Power Plants 2. The major planning steps 3. Hydrology: the basis for SHPP planning 4. First approximation of SHPP layout and electricty generation 5. Optimization of SHPP 6. Determination of budgetary investment cost 7. SHPP bankable documents 8. Environmental and Social Impact Assessment 23

Determining the budgetary investment cost as a basis for seeking appropriate financing of the SHPP Once the optimum Q design is determined the investment cost can be determined in more detail: The engineering design of the civil works component will yield a bill of quantity (quantities of excavation, concrete, reinforcement steel, back filling etc).» With the help of unit costs for these quantities the cost for the civil works components can be determined to a high degree of accuracy. For all items which will be purchased, like gates, penstock and E&M equipment, budgetary quotations need to be requested from renowned suppliers. These kind of quotations can be received rather easily as they are not binding for the supplier. It is accepted practice that the price quoted can fluctuate ±15% For planning and construction supervision use for first approximation To consider any contingencies account for 10% of total investment at this stage 24

Description Euro Budgetary investment cost Such a budgetary investment cost should be sufficient to approach FI s to investigate the possibility of finiancing the project It forms an integral part of the bankable document and could look like this Note: cost items are backed by budgetary quotations! Head works Civil works 290,000 Hydro-mechanic equipment 20,000 Desander Civil works 69,000 Hydromechanic equipment 25,000 Channel 599,000 Tunnel 150,000 Forebay Civil works 53,000 Hydromechanic equipment 14,000 Penstock Civil works 31,000 Structural steelworks 126,000 Powerhouse Civil works 140,000 Electromechanical equipment 2,446,000 Transmission line and connection 36,000 Access road 20,000 TOTAL 4,019,000 Contingency 10% 402,000 Planning and construction supervision 232,000 Total investment 4,653,000 25

7. SHPP bankable documents 1. General Overview: Small Hydro Power Plants 2. The major planning steps 3. Hydrology: the basis for SHPP planning 4. First approximation of SHPP layout and electricty generation 5. Optimization of SHPP 6. Determination of budgetary investment cost 7. SHPP bankable documents 8. Environmental and Social Impact Assessment 26

Bankable documents documents required for financing The documents accompanying any loan application should contain at least: Feasibility study:» This study determines the final technological choice and scope and proves its technical, economic and environmental feasibility, Financing strategy / business plan:» This is the presentation of the financing strategy, availability of project sponsors equity participation and debt service coverage capacity, Legal documentation:» All project related permits, licenses and contracts, including the budgetary quotations.» Documentation on the project sponsor 27

Feasibility Study and its objectives An expert analysis of the likelihood of success of the project in a technical and economical sense.» presents the project layout as a result of the evaluation of design alternatives» calculates the average annual electricity generation and the revenues» gives information how the budgetary investment cost was determined» evaluates the economic and financial profitability and its sensitivity against changes in the assumptions» assesses the environmental and social impacts 28

Feasibility study minimum content 1. General Description of the Project (location and layout, activities done so far) 2. Field investigations (topographical, hydrological, geological studies) 3. Design Flow and Annual Electricity Generation 4. Engineering Design and budgetary investment cost (Project layout, and specifications, investment and operating cost, annual generation) 5. Implementation Plan 6. Economic Project Evaluation 7. Financial Project Evaluation 8. Sensitivity Analysis 9. Assessment of the Expected Environmental and Social Impacts 29

Results of the Economic Evaluation Calculation of the net present value (NPV) obtained by calculating at a constant interest rate and separately for each year the differences of all economic costs and benefits of the project. Calculation of the internal rate of return (IRR) defined as the interest rate at which the present value of inflows is equal to the present value of outflows. Calculation of the dynamic unit electricity generation costs obtained by dividing the present value of costs by the present value of electricity production. 30

Business Plan Projection of the revenues, expenses, and cash flows to be generated by the project along with supporting assumptions.» The Business Plan complements the feasibility study by outlining the retained financial strategy and demonstrating that the project will generate sufficient cash for the debt service and the remuneration of equity capital and envisaged investment» Financing plan» Projection of the financial statements for the project 31

Delivery models of SHPP implementation Turnkey:» Common approach: single contractor takes care of plant design, civil construction tendering for E&M equipment Partnership:» Combination of capabilities and shared risk BOO (Build own operate)» SHPP owner sells rights to the project to a developer who pays annual royalty 32

8. Environmental and Social Impact Assessment 1. General Overview: Small Hydro Power Plants 2. The major planning steps 3. Hydrology: the basis for SHPP planning 4. First approximation of SHPP layout and electricty generation 5. Optimization of SHPP 6. Determination of budgetary investment cost 7. SHPP bankable documents 8. Environmental and Social Impact Assessment 33

Environmental and social impact assessment (ESIA) For all SHPP projects an ESIA is obligatory covering the expected positive and potential negative environmental and social impacts of the proposed project and the related mitigation activities.» This regards the construction and the operation of the SHPP» Emphasis will have to be put on the following parameters: Residual flow of the river safeguarding functioning of flora and fauna (particular fish population) Proper construction and operation procedures assuring work safety Proper awareness of the potential impact of the SHPP project on potentially endangered species and the development and implementation of adequate mitigation activities Development and implementation of an adequate Environmental and Social Action and Monitoring plan 34

Thank you for your attention 35