HV Submarine Cable Systems Design, Testing and Installation

Similar documents
Offshore Wind China 2010 Bergen, 15th March Olivier Angoulevant Nexans Norway AS

E-Highway2050 WP3 workshop April 15 th, 2014 Brussels

Konti Skan Replacement of Cable 1

Feasibility Study of Deep Water Power Cable Systems. Enrico Colombo CESI S.p.A

An Introduction to High Voltage Direct Current (HVDC) Underground Cables

HVDC Light Cables. Submarine and land power cables

Overview of the 500MW EirGrid East-West Interconnector, considering System Design and Execution-Phase Issues

Submarine Power Cables. State-of-the-art production facility, more than 100 years of experience and reference installations around the world.

State, trends and evolutions of HV/EHV power cables systems and contributions of SC B1 to their ongoing progress

CIEMADeS 4th INTERNATIONAL CONFERENCE

Gulf Cable & Electrical Ind. Co.

factsheet High Voltage Direct Current electricity technical information

NSW Submarine Power. Cables for the future, delivered today.

8 Strait of Belle Isle Marine Cable Crossing

Offshore Work Packages

factsheet High Voltage Direct Current Electricity technical information

NSW Submarine Power. Cables for the future, delivered today

Cable Consulting International

Fault location on power cables. Fault location on power cables

Undergrounding high voltage electricity transmission. The technical issues

Cables, Cable Laying & Accessories Manual

HIGH-CAPACITY HIGH TEMPERATURE SUPERCONDUCTING POWER CABLES

PB POWER ISLAND OF IRELAND CAVAN-TYRONE AND MEATH-CAVAN 400KV PROJECTS PRELIMINARY BRIEFING NOTE OVERHEAD AND UNDERGROUND ENERGY TRANSMISSION OPTIONS

Pipelines and seabed intervention

AORC Technical meeting 2014

Turnkey cable solutions to better deploy your windfarm infrastructure

A Deeper Insight into Fault Location on Long Submarine Power Cables

6 ELECTRICAL PARAMETERS

SUPPLIERS INFORMATION SESSIONS MARITIME LINK PROJECT. Contract for Submarine Cable Design, Supply and. Contract No. E11-18

Permanent Reservoir Monitoring (PRM) System Installation: The Installers Perspective

Why Submarine Cables?

environment briefing02

Medium-voltage cables for reliable windpark infrastructure

Max. Length of HTS Cables in the Future

CHAPTER VIII LINE PLANT SYSTEM COMMUNICATION THROUGH RE CABLE

SUITABILITY OF DIFFERENT TEST VOLTAGES FOR ON-SITE TESTING OF XLPE CABLE SYSTEMS

London Array. Operations and Maintenance

Optimization of the coupled grid connection of offshore wind farms

Sub sea Cable Technology

Contents. 1. PROFILE p2. 2. SERVICES 2.1 Offshore Support Services p 4 Offshore support p 6 ROV operations p 8

How To Monitor Water Penetration In A Cable Screen

Offshore wind farm electrical engineering (when considering the operation of array cabling at voltages of 66kV)

MV CABLE TYPE C

Cable Laying and Repair - Cable Ship Operations

Stephen G. Whitley, Senior Vice President & Chief Operating Officer

HYDROGRAPHIC INFORMATION AND THE SUBMARINE CABLE INDUSTRY

Hvor svært kan det være udnyt din viden med omhu!

High Voltage Systems. Today. The history of cables

Developing Ocean Energy in Ireland. Belmullet Wave Energy Test Site

Overview of Submarine Cable Route Planning & Cable Route Survey Activities. Graham Evans Director EGS Survey Group

Curriculum Vitae Fredrik Rüter 1 December 2014

Product brochure Multi Functional Switchgear PASS M kv Flexible and compact switchgear solutions for windfarms

Offshore Wind. IEEE Boston PES - November 16, 2010

CCI Cable Consulting International Ltd PO Box 1, Sevenoaks TN14 7EN United Kingdom

CABLE MONITORING SOLUTION


HVDC Light, a tool for electric power transmission to distant loads

APPLICATION ORIENTED DESIGN OF CABLES

OFFSHORE WIND FARM ELECTRICAL CONNECTION OPTIONS. W.Grainger 1 and N.Jenkins 2 SYNOPSIS

Removal of EP SP High Voltage Cable

and to mutually agree mitigation measures to reduce identified concerns and risks to acceptable levels.

XLPE Land Cable Systems User s Guide. Rev 5

SUPERCONDUCTING CABLE SYSTEMS

Applications of Integrated Vessel-based LiDAR, Multibeam Bathymetry, and Geophysical Surveys for Geohazard Assessments and Site Characterization

The new 525 kv extruded HVDC cable system

COOK STRAIT SUBMARINE CABLE PROTECTION ZONE

Introduction to The Trans Bay Cable Project

Turnkey Submarine Cable Systems

Viking Link Interconnector

AMSC s Superconductor Cable Technologies for Electric Utilities

Overview of geophysical and geotechnical marine surveys for offshore wind transmission cables in the UK. September 2015

DISCUSSION OF CROSS-LINKED POLYETHYLENE INSULATED CABLES FOR UNDERGROUND PORTIONS OF THE MIDDLETOWN-NORWALK 345 kv PROJECTS.

ZHONGTIAN TECHNOLOGIES CO., LTD ZHONGTIAN TECHNOLOGIES SUBMARINE CABLE CO., LTD

COMPANY PROFILE PELICAN COMPANY LIMITED

EMTP STUDIES PERFORMED TO INSERT LONG AC CABLES IN THE FRENCH GRID

CONFLEX ELECTRIC CABLE

Transmission technologies for collective offshore wind farm connections

CABLE ASSET MANAGEMENT PREDICT WITH CERTAINTY. Kuljit Singh BSc Honours MIEE(IET,UK) 5 June 2014

Network Standard Advice No. 1420C 9/6/2011

KNOW YOUR OPTIONS: 69 KV XLPE POWER CABLE

KNOW YOUR OPTIONS: 230 KV POWER CABLES

AS COMPETITION PAPER 2008

Undergrounding high voltage electricity transmission lines. The technical issues

Unified requirements for systems with voltages above 1 kv up to 15 kv

THE NEPTUNE REGIONAL TRANSMISSION SYSTEM 500 kv HVDC PROJECT

Presentation to CIGRE Next Generation Network. Visit of Seine substation

Brochure Introducing HVDC

MEASUREMENTS OF THRUST LOAD IN CABLE SYSTEMS SEMI-RIGIDLY INSTALLED IN DUCT / MANHOLE STRUCTURES

Section kv Power Cables

Magnus Callavik, ABB Power Systems, HVDC, Västerås, Sweden Phone: +46(0)

Survey Sensors Hydrofest Ross Leitch Project Surveyor

FIRE RESISTANT CABLE CONSTRUCTION OF CABLES

Svenska Kraftnät s requirements for documentation in cable projects

An Overview of Seabed Surveys (High resolution Geophysical Site Surveys)

Network Interconnection of Offshore Wind

TRANSMISSION OPTIONS FOR OFFSHORE WIND FARMS IN THE UNITED STATES

MEDIUM VOLTAGE POWER CABLES

ENERGY. TECWATER S1BN8-F 0,6/1 kv. Cable for Water Application

Current Ratings. TABLE BEC 107. (Continued) Current ratings for 6350/11000 volts grade PILC/SWA/PVC cable to BS6480/69

Transcription:

HV Submarine Cable Systems Design, Testing and Installation CIGRE Ireland Technical Seminar 6 th October 2010 Robert Donaghy Senior Consultant Engineer, ESB International

Presentation Overview Applications Design Testing Installation Examples

Submarine Cable Applications Interconnections between grid systems Island connections Off-shore wind and wave power connections

Development of Submarine Cables 60-70s 1980s 1990s 2000- MV 3-core XLPE & EPR Large s/c core fluid filled up to 400kV 3-core dry type XLPE designs up to 145kV Long length XLPE 3-core & single core up to 400kV

Submarine Power Cable Types Rated Voltage Uo 33 kv ac 150 kv ac 420 kv ac 320 kv dc 450 kv dc Insulation XLPE, EPR XLPE Oil/paper or XLPE Extruded Mass Impregnated Typical application Supply of small islands, connection of offshore WTG Supply to large islands, offshore platform export cables Crossings of rivers, straits with large transmission capacity Long distance connections of offshore platforms or wind parks Interconnection of power grids over long distances Max. length 20-30 km 70-150 km <50 km >500 km >500 km Typical rating 30 MW 180 MW 700MW / 3 cables 1000 MW / cable pair 600 MW / cable

HV Cable Construction Conductor Insulation Sheath Fibre Optic Cores Armour Outer Serving

Single Core Three Core Pros Lighter weight Smaller Diameter Longer lengths Possibly fewer factory & field joints Higher current rating Improved security, can add a 4th cable Voltage rating up to 400 kv and greater Reduced repair costs and spares Pros Reduced magnetic field Lower sheath circulating currents and voltages Lower installation costs One trench on seabed Lower protection costs Includes optional Fibre Optic Cable Cons Higher magnetic field Greater installation costs Individual seabed trenching increases costs Protection costs increased Sheath current must be considered Cons Lower current rating Heavier Large diameter Security of cable system decreased All three phases have to be repaired after a fault

Electrical Design Voltage level (U 0 /U) Rated transmitted power (kva) Short circuit current (ka) & duration (s) Load factor Maximum losses allowed

Transmission Capacity Limits Power* 1200 MW Un=400 kv 1000 MW 800 MW 600 MW 400 MW Un=230 kv Un=150 kv 200 MW Un=132 kv 0 MW 0 km 50 km 100 km 150 km 200 km 250 km 300 km 350 km 400 km * With compensation, based on 3-core 1,000mm² conductor, 400kV is 1-core 1,200mm² (ref. Nexans) Cable Length

Key Design Data Ambient temperature (seabed & land) Burial depth Particular burial/protection requirement at shore approach (deeper burial, directional drill pipe ) Axial spacing of cables Thermal resistivity of seabed & land Length of submarine cable Water depths

Connections to Floating Platforms Application specific Mechanical performance: movements and vibrations Hang-off arrangements on platform Corrosion protection and grounding conditions

Route Survey Hydrographic & geophysical survey Sea bed bathymetry Tide data Level, met ocean data Locate existing cables & obstacles Multi-beam echo sounder Side scan sonar Sub-bottom profiling Core Sampling Water depth profile Corridor width Risk of damage to cables Burial depth/protection requirement Shore landing point selection Environmental assessment Consents, Foreshore Licence Profile along cable route

Sea Bed 3D Bathymetric Profile Existing Cable Proposed Cable

Shore Landing Near shore civil works Directional drill, pulling through pipes Mechanical protection of cables Space for Sea/land transition joint Parallel routing of cables Environmental considerations Sand dune movements Erosion concern

Factory Joints Accessories Repair Joints Terminations Transition Joints

Testing Prequalification / Development Tests Type Tests Routine Tests Sample Tests After-Installation Tests

CIGRE WG B1-27 Test recommendations for long AC extruded submarine cables 150-500 kv (now also to cover 36-150kV) Addresses particular requirements of submarine cable systems: Water tightness of conductor and under metallic sheath Armouring Mechanical forces during installation of cable and joints Water tightness of rigid joints Delivery lengths and weights Routine tests of cable and joints challenges in testing long lengths

CIGRE WG B1-27 Recommendations More stringent approach Partial Discharge measurement in factory joints Extended frequency range for ac tests: 10 500 Hz External water pressure test of rigid sea & repair joints Scheme for mechanical tests for repair joints Tests for visual inspection of submarine cables Range of approval for type tests modified: factory joints, mechanical testing etc Prequalification and Extended Qualification Factory joints still to be qualified

In the old days Cable Laying Vessels

Now Cable Laying Vessels

Cable Laying

Cable Laying Vessels Shallow draft barges

Protection Anchoring Fishing Dropped objects

m Penetration of smaller anchors & fishing gear vs. soil hardness 1 T anchor 1 3/4 500 kg anchor 400 kg anchor 200 kg anchor 1/2 Otter trawl 1/4 Beam trawl Hard Soft

Embedment by water jetting Cable buried in hard to soft sediments to 0.5 3.0m 2.5 m

Protection Embedment

Cork Harbour Project One of the first 220kV XLPE submarine projects in the world Two circuits: Single core 1 x 1,600mm² copper, 570MVA rating 3.5km length: Aghada-Raffeen 220kV 4.5km length: Glanagow-Raffeen 220kV Continuous manufacturing lengths up to 4.5km Shallow water: 10 metres (1st crossing), 30 metres (2 nd crossing) Crossing main shipping channel of major port Submarine cable embedment by water jetting

3km 3.3km 0.5km 6km Legend 220kV Submarine Cable 220kV Land Cable 4.6km 1.4km

Cork Harbour 220kV: Feb 2010 Picture Area Cable Laying Vessel Cable shore landing

SEAI Wave Energy Test Site 2 x 15km 20kV subsea cables 2 x 7km 20kV subsea cables

Ireland Wales East West Interconnector 186km Marine Route 45km Land Cable in Ireland 30km in Wales Converter Stations at Woodland & Deeside

Thank you for your attention