Introduction to The Trans Bay Cable Project
|
|
|
- Mavis Carroll
- 10 years ago
- Views:
Transcription
1 Introduction to The Trans Bay Cable Project
2 We ve come a long way 1
3 But thanks to the advances of two men and 2
4 The Battle of Currents 3
5 Utilities are able to choose the most effective and efficient means for their unique power transmission challenges. 4
6 HVDC Basics
7 Uses of HVDC HVDC has two main purposes Back-to-back interconnections Useful for connecting mismatched AC Networks Can convert Hz Point-to-point connections Connects remote generation to load centers Bulk power transmission over long distances 6
8 LCC vs. VSC LCC (Line Commutated Converter) Thyristor (Turn on capability only) Active Power Control Only AC Filters No Black Start Capability Higher Capacity Large Footprint VSC (Voltage Sourced Converter) IGBT (Turn on/off) Active and Reactive Control No AC Filtration Black Start Capable More Flexible Small Footprint 7
9 Why TBC Post the 1998 blackout event and part of the CAISO long term plan, the CAISO put into place a team called the San Francisco Stakeholder Study Group (SFSSG). The CAISO and the SFSSG proposed the following long term projects to meet the need of the energy demands of San Francisco: Status Quo Upgrade and replace existing facilities Trans Bay Cable Project Moraga-Potrero 230 kv Line Tesla-Potrero 230 kv Line In summary Trans Bay Cable was a fast, affordable, effective solution to solve the long term energy needs of San Francisco.
10 TBC was originally slated to be an LCC facility Available land in the city proved challenging Smaller footprint of VSC reduced amount of land required and cut costs 9
11 TBC Selected Siemens Modular Multilevel Converter HVDC PLUS Smoother waveform Each module is a discrete voltage source Each arm has 216 sub-modules (16 spares) 10
12 11
13
14 Pittsburg 230-kV AC Cable System Simplified Project One-Line Diagram PG&E Pittsburg 230-kV Substation +200-kV DC Cable PG&E Potrero 115-kV Substation POI Pittsburg Converter Station Potrero Converter Station POI Potrero 115-kV AC Cable System -200-kV DC Cable
15 DC Cable Route Pittsburg (Potrero) San Francisco
16 Pittsburg Converter Station
17 Pittsburg Converter Station Transformers Converter Hall DC Reactors AC Reactors Control & Protection Room Condensers (cooling fans)
18 Potrero Converter Station
19 Potrero Converter Station Transformers Converter Hall DC Reactors AC Reactors Control & Protection Room Condensers (cooling fans) TBC_OP_INS_11.PPTX(EMD)
20 Operational Performance
21 Operational Performance SEU FEU Avail Utilization % 0.2% 97.0% 92.8% % 0.81% 97.64% 96.92% % 0.48% 96.3% 86.4% Utilization is based on average MW per day CAISO has recently started to aggressively use TBC for power flow management within SF and peninsula lower MW average per day leverages flexibility and agility of VSC system
22 Technology Operations
23 AC DC Converter Hall
24 Trans Bay Cable Specifics Active power is controllable between 0MW and 400MW in increments of 1MW. Reactive power can be generated/absorbed within limits at each Converter Station, independent of the other Converter Station. ±145MVAr at Pittsburg (at full active power) ±170MVAr at Potrero (at full active power) Smoother waveform, lower harmonics, less filtering, smaller footprint Low system losses. Independent and fully controllable reactive power
25 Q Absorbed from POI (MVAr) Q Absorbed from POI (MVAr) Q Deliverer d to POI (MVAr) Q Deliverer d to POI (MVAr) Project Real and Reactive Power Capability Operation in RED AREA Available at Expense of Real Power Transmission (0,+300 ) (0,+300 ) Operation in RED AREA Available at Expense of Real Power Transmission (-418,+145) (+400,+170 ) P Extracted from Pittsburg POI (MW) P Delivered to Potrero POI (MW) (-418,0) (+400,0 ) (-418,-145) (+400,-170) P/Q at Pittsburg POI (0,-300) (0,-300) P/Q at Potrero POI
26 OPERATOR
27 Project O&M Structure TBC LLC owner Siemens Operator TBC Operations LLC 24hr Site O&M 26
28 CABLE
29 Fibre Optic Cable XLPE Cable 53 miles Burial depth 6ft Follows deep water channel Numerous infrastructure crossings Interfaces with multiple bay agencies 28
30 Ship: Giulio Verne (Deep Water Cable Installer) Hydroplow
31 Submarine cable laying ship
32 Submarine cable laying
33 Asset Monitor Details Re: Shipping Lanes In Area 32
34 Change in Utilization? 33
35 TBC Utilization 34
36 2013 Accumulated and Monthly Ramping 35
37 TBC s Plans for the Future
38 Quick Start Upgrade Siemens currently using Inelfe Project (Spain France Interconnect) as base design Upgrade to address lose of PG&E Martin substation Will bring Black Start functionality to the Trans Bay Cable Allows TBC to support up to ~350 MW of critical load in San Francisco Scheduled for Q completion 37
39 Questions? 38
Recent Siemens HVDC Activities Yuriy Kazachkov Siemens PTI
IEEE PES 2008 HVDC & FACTS Subcommittee Recent Siemens HVDC Activities Yuriy Kazachkov Siemens PTI 660MW 500kV in operation since July 2007 Commercial Operation Neptune RTS Costumer Project Name Location
2012 San Francisco Colloquium
2012 San Francisco Colloquium http : //www.cigre.org HVDC and Power Electronic Systems for Overhead Line and Insulated Cable Applications B4-8 Trans Bay Cable A Breakthrough of VSC Multilevel Converters
Topics. HVDC Fundamentals
Topics HVDC Fundamentals Conventional Converters Capacitor Commutated Converters Voltage Source Converters Reactive Power Requirements System Configurations Tapping Control basics High Power Transmission
Babcock & Brown. Trans Bay Cable Project. Presentation To California Energy Commission Transmission Workshop. August 23, 2004
Babcock & Brown Trans Bay Cable Project Presentation To California Energy Commission Transmission Workshop August 23, 2004 Trans Bay Cable Project General Project Description Estimated Project Benefits
MEMORANDUM. March 9, 2007
MEMORANDUM March 9, 2007 TO: FROM: SUBJECT: MEMBERS, PORT COMMISSION Hon. Anne Lazarus, President Hon. Kimberly Brandon, Vice President Hon. Rodney Fong Hon. Michael Hardeman Monique Moyer Executive Director
HVDC PLUS and SVC PLUS: Reliable and Cost-effective Power Transmission Solutions with Modular Multilevel Converters
HVDC PLUS and SVC PLUS: Reliable and Cost-effective Power Transmission Solutions with Modular Multilevel Converters C. Bartzsch, Dr. H. Huang, T. Westerweller - Siemens, Germany Dr. M. Davies - High Electrical
HVDC-VSC: transmission technology of the future
A bi-pole ± 285 kv HVDC line sandwiched between 3-phase 400 kv HVAC lines. HVDC-VSC: transmission technology of the future A new hybrid HVDC circuit technology using voltage source converters is only half
E-Highway2050 WP3 workshop April 15 th, 2014 Brussels
E-Highway2050 WP3 workshop April 15 th, 2014 Brussels High voltage underground and subsea cable technology options for future transmission in Europe Ernesto Zaccone, Chairman Europacable High Voltage Systems
factsheet High Voltage Direct Current electricity technical information
factsheet High Voltage Direct Current electricity technical information Introduction High voltage direct current (HVDC) technology is one of the technical options National Grid can consider for the future
Voltage Source HVDC Overview Mike Barnes Tony Beddard
Voltage Source HVDC Overview Mike Barnes Tony Beddard Note: This is a version with images removed which have copyrighted other than from the University of Manchester, for web publication. Should a conference
Magnus Callavik, ABB Power Systems, HVDC, 721 64 Västerås, Sweden Phone: +46(0)21323226. e-mail: [email protected]
HVDC GRIDS FOR OFFSHORE AND ONSHORE TRANSMISSION Magnus Callavik, ABB Power Systems, HVDC, 721 64 Västerås, Sweden Phone: +46(0)21323226. e-mail: [email protected] SUMMARY The objective with this
Generation Interconnection Feasibility Study Report-Web Version. PJM Generation Interconnection Request Queue Position Z1-055
Generation Interconnection Feasibility Study Report-Web Version For PJM Generation Interconnection Request Queue Position Z1-055 South Bend Generation Project March 2014 PJM Interconnection 2014. All rights
An Introduction to High Voltage Direct Current (HVDC) Underground Cables
Page 1 An Introduction to High Voltage Direct Current (HVDC) Underground Cables Brussels, 10 October 2011 An Introduction to High Voltage Direct Current (HVDC) Underground Cables Page 2 Table of content
HVDC Light, a tool for electric power transmission to distant loads
Presented at VI Sepope Conference, Salvador, Brazil, May 1998 HVDC Light, a tool for electric power transmission to distant loads by Gunnar Asplund Kjell Eriksson* Ove Tollerz ABB Power Systems AB ABB
Offshore Platform Powered With New Electrical Motor Drive System
Offshore Platform Powered With New Electrical Motor Drive System Authors: Jan O. Lamell, M.Sc E.E. ABB Automation Technologies Presenters: Thomas Johansson, M.Sc E.E. ABB Automation Technologies Timothy
High Voltage Direct Current Transmission
Peter Kohnstam, 22 April 2013, United States Department of Energy High Voltage Direct Current Transmission siemens.com/answers HVDC Classic LCC Technology Page 2 HVDC Classic- Siemens Experience 2013 Hudson
POWER TRANSMISSION FROM OFFSHORE WIND FARMS
POWER TRNSMISSION FROM OFFSHORE WIND FRMS Thorsten Völker University of pplied Sciences Bremerhaven Germany BSTRCT The future for wind power generation in Germany is offshore wind energy. The preferred
Submarine Power Cables. State-of-the-art production facility, more than 100 years of experience and reference installations around the world.
Submarine Power Cables State-of-the-art production facility, more than 100 years of experience and reference installations around the world. Reliable submarine power cables ABB is one of the world s most
factsheet High Voltage Direct Current Electricity technical information
factsheet High Voltage Direct Current Electricity technical information Introduction High voltage direct current (HVDC) technology is one of the technical options National Grid can consider for the future
Summary of Electric Transmission Assessment Report
Summary of Electric Transmission Assessment Report January 2010 Assessment and Analysis of the State-Of-the-Art High-Voltage Electric Transmission Systems with Specific Focus on High-Voltage Direct Current
HV Submarine Cable Systems Design, Testing and Installation
HV Submarine Cable Systems Design, Testing and Installation CIGRE Ireland Technical Seminar 6 th October 2010 Robert Donaghy Senior Consultant Engineer, ESB International Presentation Overview Applications
Overview of the 500MW EirGrid East-West Interconnector, considering System Design and Execution-Phase Issues
Overview of the 500MW EirGrid East-West Interconnector, considering System Design and Execution-Phase Issues J Egan, P O Rourke EirGrid Plc, Republic of Ireland [email protected] paul.o [email protected]
Electrical Considerations for HVDC Transmission Lines. Joe Mooney, PE
Electrical Considerations for HVDC Transmission Lines Joe Mooney, PE POWER Engineers has met the standards and requirements of the Registered Continuing Education Program. Credit earned on completion of
Oahu Wind Integration and Transmission Study (OWITS) Hawaiian Islands Transmission Interconnection Project
Oahu Wind Integration and Transmission Study (OWITS) Hawaiian Islands Transmission Interconnection Project Dennis Woodford Electranix Corporation Winnipeg, Manitoba Canada NREL is a national laboratory
THE NEPTUNE REGIONAL TRANSMISSION SYSTEM 500 kv HVDC PROJECT
21, rue d Artois, F-75008 PARIS B4-118 CIGRE 2008 http : //www.cigre.org THE NEPTUNE REGIONAL TRANSMISSION SYSTEM 500 kv HVDC PROJECT E. STERN, J. NASH - NEPTUNE RTS, LLC (U.S.A.) C. SCHOENIGER, C. BARTZSCH
LIPA. The. Long Island Power Authority links to the PJM Interconnection with an undersea/underground HVDC link. 20 www.tdworld.com.
Prysmian cable-laying ship Giulio Verne. The LIPA By Christopher Hocker, Neptune Regional Transmission System; Richard M. Kessel, Long Island Power Authority; and John Duschang, Henningson, Durham & Richardson
Brochure Introducing HVDC
Brochure Introducing HVDC ABB and HVDC The world s first commercial high-voltage direct current (HVDC) link, situated between the Swedish mainland and the island Gotland, was delivered by ABB already in
IEEE PES HVDC Systems & Trans Bay Cable
IEEE PES HVDC Systems & Trans Bay Cable AC AC DC Cable March 16, 2005 IEEE PES HVDC Systems & Trans Bay Cable HVDC Transmission Project Description Trans Bay Cable Principles of HVDC Controllability, Reliability,
STATCOM Application at VELCO Essex Substation
STATCOM Application at VELCO Essex Substation Gregory Reed John Paserba Terrence Croasdaile Mitsubishi Electric Power Products, Inc. Warrendale, Pennsylvania, USA Masatoshi Takeda Naoki Morishima Yoshi
6. The estimated costs here do not include any applicable ITCC tax
General Notes and Clarifications: 1. The following estimated costs are based on past experiences and are intended to provide an order of magnitude of the total project cost given the major system components.
B4-102 CROSS SOUND CABLE PROJECT SECOND GENERATION VSC TECHNOLOGY FOR HVDC
21, rue d'artois, F-75008 Paris http://www.cigre.org B4-102 Session 2004 CIGRÉ CROSS SOUND CABLE PROJECT SECOND GENERATION VSC TECHNOLOGY FOR HVDC B. D. RAILING G. MOREAU L. RONSTRÖM* J. J. MILLER P. BARD
Low Frequency AC Transmission System
, pp. 315-326 http://dx.doi.org/10.14257/ijsip.2015.8.5.32 Low Frequency AC Transmission System G. Sirisha Kumari 1 and K.Veerendranath 2 1 M. Tech student in EEE Department 2 Asst. Professor in EEE Department
Variable Frequency Drives - a Comparison of VSI versus LCI Systems
Variable Frequency Drives - a Comparison of VSI versus LCI Systems Introduction TMEIC is a leader in the innovative design and manufacture of large ac variable f requency drive systems. TMEIC has been
INTERNATIONAL JOURNAL OF ELECTRICAL ENGINEERING & TECHNOLOGY (IJEET)
INTERNATIONAL JOURNAL OF ELECTRICAL ENGINEERING & TECHNOLOGY (IJEET) International Journal of Electrical Engineering and Technology (IJEET), ISSN 0976 ISSN 0976 6545(Print) ISSN 0976 6553(Online) Volume
Offshore Wind. IEEE Boston PES - November 16, 2010
Offshore Wind IEEE Boston PES - November 16, 2010 Offshore Wind A high-level overview of offshore wind project development identifying current technologies, challenges, risks and costs. Presented by: Brook
FACTS. Solutions to optimise network performance GRID
Solutions to optimise network performance GRID Solutions to optimise your network Our worldwide presence: Better solutions for your network all around the world Tampere Philadelphia Stafford Konstanz Beijing
Power Transmission and Distribution. Shunt reactors for medium and highvoltage. From development to use
Power Transmission and Distribution Shunt reactors for medium and highvoltage networks: From development to use From the beginning up to today more quality and reliability for your network A safe power
Curriculum Vitae Fredrik Rüter 1 December 2014
Name RÜTER Fredrik Date of Birth 8 May 1960 Nationality Position Languages Coordinates Swedish Senior Consultant Swedish: mother tongue English: fluent (business, conversation, reading, writing) German,
EMTP STUDIES PERFORMED TO INSERT LONG AC CABLES IN THE FRENCH GRID
Tension (kv) Impedance (Ohms) EMTP STUDIES PERFORMED TO INSERT LONG AC CABLES IN THE FRENCH GRID frequency (Hz) Simon DESCHANVRES Yannick VERNAY RTE, CNER, Substations Department t (ms) EMTP-RV Users Group
Konti Skan Replacement of Cable 1
Konti Skan Replacement of Cable 1 Presentation of the project 1 Agenda Background for the project Scope of Work for the cable delivery Eletrical Requirements Type Test Route description Time Schedule 2
Trends und Innovationen für ein Energiesystem der Zukunft Prof. Dr. Michael Weinhold, CTO Energy Management Division, Siemens AG Fraunhofer ISE,
Trends und Innovationen für ein Energiesystem der Zukunft Prof. Dr. Michael Weinhold, CTO Energy Management Division, Siemens AG Fraunhofer ISE, Freiburg, 2. Juli, 2015 siemens.com/energy-management Agenda
2012 San Francisco Colloquium
2012 San Francisco Colloquium http : //www.cigre.org Advances in voltage source converter (VSC) technologies B4-6 500 kv VSC Transmission System for lines and cables B. JACOBSON, B. WESTMAN, M. P. BAHRMAN*
OFFSHORE WIND FARM ELECTRICAL CONNECTION OPTIONS. W.Grainger 1 and N.Jenkins 2 SYNOPSIS
OFFSHORE WIND FARM ELECTRICAL CONNECTION OPTIONS W.Grainger 1 and N.Jenkins 2 1 Border Wind Ltd, Hexham 2 Dept of Electrical Engineering and Electronics, UMIST SYNOPSIS The development of large scale offshore
Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment
Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment March 20, 2009 Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment Table of Contents:
Optimization of the coupled grid connection of offshore wind farms
Optimization of the coupled grid connection of offshore wind farms Dirk Schoenmakers Graduation project at Evelop Netherlands BV Technical University of Eindhoven September 2008 Supervisors: TU Eindhoven
Project description. Power Electronics for Reliable and Energy efficient Renewable Energy Systems
Project description Title: Power Electronics for Reliable and Energy efficient Renewable Energy Systems OBJECTIVES Principal objective Provide competence and decision basis for enabling reliable and energy
Network Interconnection of Offshore Wind
Network Interconnection of Offshore Wind Prepared for REOLTEC Carlos Aguirre Madrid, December 3rd Experience you can trust. Introducing KEMA A trusted independent partner providing advise throughout the
HVDC Light Cables. Submarine and land power cables
HV Light Cables Submarine and land s The HV Light s to offshore platform The light and robust HV Light s can be laid with very cost effecient methods HV Light System HV Light is a transmission system in
DC TRANSMISSION BASED ON VOLTAGE SOURCE CONVERTERS
DC TRANSMISSION BASED ON VOLTAGE SOURCE CONVERTERS by Gunnar Asplund, Kjell Eriksson, Hongbo Jiang, Johan Lindberg, Rolf Pålsson, Kjell Svensson ABB Power Systems AB Sweden SUMMARY Voltage Source Converters
EuroAsia Interconnector Project Submarine power cable
EuroAsia Interconnector Project Submarine power cable Feasibility study status Executive summary Presented by: Yakov (Yasha) Hain, Senior Executive VP Israel Electric Corporation Ltd. Doing business with
Explosion proof housings for IGBT module based high power inverters in HVDC transmission application
Explosion proof housings for IGBT module based high power inverters in HVDC transmission application Markus Billmann 1) Dirk Malipaard 2) Dr. Herbert Gambach 3) 1) Fraunhofer Institute of Integrated Systems
Viking Link Interconnector
Viking Link Interconnector Public information event for Bicker Parish Why we re here today We re here today to introduce the Viking Link project, to explain what we want to build and to answer any questions
A Live Black-start Capability test of a Voltage Source HVDC Converter
CIGRÉ-676 2015 CIGRÉ Canada Conference 21, rue d Artois, F-75008 PARIS http : //www.cigre.org Winnipeg, Manitoba, August 31-September 2, 2015 A Live Black-start Capability test of a Voltage Source HVDC
HVDC PLUS Basics and Principle of Operation Answers for energy.
Technical article Authors: M. Davies, M. Dommaschk, J. Dorn, J. Lang, D. Retzmann, D. Soerangr HVDC PLUS Basics and Principle of Operation Answers for energy. Content 0. Preface 3 1. Introduction 4 2.
Reactive Power and Importance to Bulk Power System OAK RIDGE NATIONAL LABORATORY ENGINEERING SCIENCE & TECHNOLOGY DIVISION
Reactive Power and Importance to Bulk Power System OAK RIDGE NATIONAL LABORATORY ENGINEERING SCIENCE & TECHNOLOGY DIVISION Outline What is Reactive Power and where does it come from? Why is it important?
PB POWER ISLAND OF IRELAND CAVAN-TYRONE AND MEATH-CAVAN 400KV PROJECTS PRELIMINARY BRIEFING NOTE OVERHEAD AND UNDERGROUND ENERGY TRANSMISSION OPTIONS
ISLAND OF IRELAND CAVAN-TYRONE AND MEATH-CAVAN 400KV PROJECTS PRELIMINARY BRIEFING NOTE OVERHEAD AND UNDERGROUND ENERGY TRANSMISSION OPTIONS FEBRUARY 2008 PB POWER PB Power Page i EXECUTIVE SUMMARY General
HVDC Technology for Large Scale Offshore Wind Connections
HVDC Technology for Large Scale Offshore Wind Connections Nandan Mahimkar, Gunnar Persson,Claes Westerlind, ABB AB, SE-771 80, Ludvika, Sweden, [email protected], [email protected],[email protected],
Three Gorges - Changzhou HVDC : Ready to Bring Bulk Power to East
The 4 th International Conference on Power Transmission & Distribution Technology 2003 14-16 October, 2003, Changsha 2003 Three Gorges - Changzhou HVDC : Ready to Bring Bulk Power to East Abhay Kumar Mats
HVDC Transmission Line Project for Moving ERCOT Wind Into SERC
HVDC Transmission Line Project for Moving ERCOT Wind Into SERC ERCOT RPG Meeting August 13, 2010 Agenda Pattern Energy Group SERC and ERCOT Market Drivers Southern Cross Project Overview Project Development
MINISTERIE VAN ECONOMISCHE ZAKEN GENERAL COST COMPARISON BETWEEN UNDERGROUND CABLES AND O.H. LINE SYSTEMS FOR H.V. TRANSMISSION
MINISTERIE VAN ECONOMISCHE ZAKEN GENERAL COST COMPARISON BETWEEN UNDERGROUND CABLES AND O.H. LINE SYSTEMS FOR H.V. TRANSMISSION REPORT ON NETWORK RELIABILITY ASPECTS OF THE CHOICE LINE VERSUS CABLE FOR
Renewable Energy Grid Integration
Renewable Energy Grid Integration Jian Sun Professor and Director Grid Integration Issues Cost, Reliability & Efficiency of Grid Interface Grid Congestion, Weak Grids Variability of Renewable Production
COMPARISON OF THE FACTS EQUIPMENT OPERATION IN TRANSMISSION AND DISTRIBUTION SYSTEMS
COMPARISON OF THE FACTS EQUIPMENT OPERATION IN TRANSMISSION AND DISTRIBUTION SYSTEMS Afshin LASHKAR ARA Azad University of Dezfoul - Iran [email protected] Seyed Ali NABAVI NIAKI University of Mazandaran
Limiting Grid Disturbances of Renewable Power Sources b.m.o Modern Power Electronics Paper ID FT3-5.2; 25.10.2006, 16h30-17h00
Limiting Grid Disturbances of Renewable Power Sources b.m.o Modern Power Electronics Paper ID FT3-5.2; 25.10.2006, 16h30-17h00 Reinhard Zingel, Converteam GmbH, Culemeyerstr.1, 12277 Berlin ETG2006 ID
CO-ORDINATION OF PARALLEL AC-DC SYSTEMS FOR OPTIMUM PERFORMANCE
CO-ORDINATION OF PARALLEL AC-DC SYSTEMS FOR OPTIMUM PERFORMANCE Ana Diez Castro & Rickard Ellström Ying Jiang Häfner Christer Liljegren Vattenfall Utveckling AB ABB Power Systems Gotlands Energiverk AB
Offshore Wind China 2010 Bergen, 15th March 2010. Olivier Angoulevant Nexans Norway AS
Offshore Wind China 2010 Bergen, 15th March 2010 Olivier Angoulevant Nexans Norway AS At the core of performance At the core of performance : a worldwide leader Worldwide leader in cables, cabling systems
HVDC. A firewall against disturbances in high-voltage grids. Lennart Carlsson
A firewall against disturbances in high-voltage grids Lennart Carlsson Interconnections between grids are desirable because they not only permit economies through the sharing of reserves, but they also
B4-207. Konti-Skan 1 HVDC Pole Replacement
21, rue d'artois, F-75008 Paris http://www.cigre.org B4-207 Session 2004 CIGRÉ Konti-Skan 1 HVDC Pole Replacement P L Sorensen 1, B Franzén 2, J D Wheeler 3, R E Bonchang 3, C D Barker 3, R M Preedy 3,
HVDC Transmission for Rural Alaska
HVDC Transmission for Rural Alaska STAKEHOLDERS ADVISORY GROUP SECOND MEETING January 14, 2010 ANCHORAGE, ALASKA Joel D. Groves, P.E. polarconsult alaska, inc. ENGINEERS - PLANNERS - ENERGY CONSULTANTS
Submarine Cable Power Transmission using DC High-Voltage Three-Level Converters
Submarine Cable Power Transmission using DC High-Voltage Three-Level Converters João Antunes, IST ([email protected]) Astract This paper is about multilevel converters used in High Voltage Direct Current
HVDC Light and development of Voltage Source Converters
1 HVDC Light and development of Voltage Source Converters K. Eriksson, ABB Utilities Abstract- On March 10, 1997 was transmitted on the 3 MW HVDC Light transmission between Hellsjön and Grängesberg in
Knowing the FACTS. FACTS that enhance power quality in rail feeder systems
Knowing the FACTS FACTS that enhance power quality in rail feeder systems ROLF GRÜNBAUM, PER HALVARSSON, BJÖRN THORVALDSSON The increase in traffic on existing tracks combined with new high-speed rail
Generation Interconnection System Impact Study Report. For. PJM Generation Interconnection Request Queue Position X1-114.
Generation Interconnection System Impact Study Report For PJM Generation Interconnection Request Queue Position X1-114 Sandyston January 2012 Preface The intent of the System Impact Study is to determine
HVDC 2000 a new generation of high-voltage DC converter stations
HVDC 2000 a new generation of high-voltage DC converter stations Improved performance and robustness, shorter lead times and faster delivery, plus reduced maintenance needs, were the development goals
Siemens presents new DC grid connection for offshore wind farms Siemens AG 2015 All rights reserved. siemens.com/grid-access-solutions
Higher cost efficiency in Wind Power Transmission Siemens presents new DC grid connection for offshore wind farms siemens.com/grid-access-solutions is leading in offshore grid access To date Siemens has
SOUTHERN MARYLAND ELECTRIC COOPERATIVE, INC. HUGHESVILLE, MD
SOUTHERN MARYLAND ELECTRIC COOPERATIVE, INC. HUGHESVILLE, MD HOLLAND CLIFF HEWITT ROAD 230 KV TRANSMISSION LINE PROJECT ELECTRIC ALTERNATIVE EVALUATION STUDY BLACK & VEATCH CORPORATION B&V Project 146026(G)
Power Feeding Equipment for Optical Submarine Cable Systems
Power Feeding Equipment for Optical Submarine Cable Systems KANEKO Tomoyuki, CHIBA Yoshinori, KUNIMI Kaneaki, NAKAMURA Tomotaka Abstract A submarine cable system is fed power from power feeding equipment
Cross-Tie Transmission Line. Ravikanth Varanasi Principal Transmission Planner
Cross-Tie Transmission Line Ravikanth Varanasi Principal Transmission Planner Overview ~213 mile 500-kV transmission line between PacifiCorp s proposed Clover 500 kv substation with NV Energy s Robinson
The design and performance of Static Var Compensators for particle accelerators
CERN-ACC-2015-0104 [email protected] The design and performance of Static Var Compensators for particle accelerators Karsten Kahle, Francisco R. Blánquez, Charles-Mathieu Genton CERN, Geneva, Switzerland,
The stable way. Synchronous condenser solutions. siemens.com/energy/facts
The stable way Synchronous condenser solutions siemens.com/energy/facts Bringing grids in line with new requirements Global climate change poses new challenges for power generation and transmission. Innovative
Project Management GCC Interconnection Project
GCC Interconnection Authority Project Management GCC Interconnection Project Saleh H. Al-Awaji, Awaji, PhD March 2007 1 Project Background Gulf Cooperation Council (GCC) between Kuwait, Saudi Arabia, Bahrain,
Current valve. for AC 24 V pulse/pause control of electrical loads up to 30 kw
4 937 DESIO Current valve for AC 24 V pulse/pause control of electrical loads up to 30 kw SEA45.1 Use The current valve is used for the control of electric heating elements in heating, ventilation and
Smart Grid and Renewable Energy Grid Integration. Jian Sun, Professor and Director Department of ECSE & Center for Future Energy Systems
Smart Grid and Renewable Energy Grid Integration Jian Sun, Professor and Director Department of ECSE & Center for Future Energy Systems 1 How Smart Can We Make This Grid? 2 Smart Grid Drivers Need to Use
GCCIA Phase 1. Making interconnection in the Gulf a reality GRID
GCCIA Phase 1 Making interconnection in the Gulf a reality GRID 1 Making interconnection in the Gulf a reality GCCIA Phase 1 Gulf Cooperation Council International Authority The GCCIA is an organisation
HVDC Light & SVC Light Reference list
& Reference list ABB & Projects Worldwide 37 1 Hällsjön 2 Hagfors 3 Gotland 4 Directlink 5 Tjæreborg 6 Eagle Pass 7 Trierer Stahlwerk 8 Cross Sound Cable 9 Murraylink 10 Outokumpu Stainless 11 Evron 12
Voltage Stability Improvement using Static Var Compensator in Power Systems
Leonardo Journal of Sciences ISSN 1583-0233 Issue 14, January-June 2009 p. 167-172 Voltage Stability Improvement using Static Var Compensator in Power Systems Department of Electrical/Computer Engineering,
Updated SYSTEM IMPACT STUDY OF NEW ENGLAND AREA
CROSS SOUND CABLE PROJECT 330MW HVdc INTERCONNECTION BETWEEN NEW HAVEN, CONNECTICUT AND SHOREHAM, NY Updated SYSTEM IMPACT STUDY OF NEW ENGLAND AREA Subordinate Status Removal and Amendment of Approved
UNINTERRUPTIBLE POWER SUPPLIES >9900AUPS UNINTERRUPTIBLE POWER SUPPLIES
UNINTERRUPTIBLE POWER SUPPLIES 9900A >9900AUPS UNINTERRUPTIBLE POWER SUPPLIES 9900A The 9900A UPS system uses the most advanced IGBT in both the converter and inverter with Digital Signal Processor (DSP)
Control Development and Modeling for Flexible DC Grids in Modelica
Control Development and Modeling for Flexible DC Grids in Modelica Andreas Olenmark 1 Jens Sloth 2 Anna Johnsson 3 Carl Wilhelmsson 3 Jörgen Svensson 4 1 One Nordic AB, Sweden, [email protected].
California s Energy Future
California s Energy Future 1 Sunrise Powerlink Commitment and Imperial Valley Renewable Energy Projects Project Name Technology Location Contract Capacity (MW) Flowing across Sunrise Today (MW) Project
High-Megawatt Converter Technology Workshop for Coal-Gas Based Fuel Cell Power Plants January 24, 2007 at NIST
Session 4a Enjeti 1 High-Megawatt Converter Technology Workshop for Coal-Gas Based Fuel Cell Power Plants January 24, 2007 at NIST Dr. Prasad Enjeti TI TI Professor Power Electronics Laboratory College
Alternate Arm Converter Operation of the Modular Multilevel Converter
Alternate Arm Converter Operation of the Modular Multilevel Converter Yashoda.R.Perkar 1, Santhosh Kumar Rayarao 2 P.G. Student, Department of Electrical Engineering, MSS s College of, Jalna, India Asst.
Economic Comparison of HVAC and HVDC Solutions for Large Offshore Wind Farms under Special Consideration of Reliability. Lazaros P.
Economic Comparison of HVAC and HVDC Solutions for Large Offshore Wind Farms under Special Consideration of Reliability Lazaros P. Lazaridis Master s Thesis XETS/ESS0505 Royal Institute of Technology Department
Kinetic energy recovery on railway systems with feedback to the grid
Kinetic energy recovery on railway systems with feedback to the grid Authors: J.M. ORTEGA, METRO DE BILBAO;S:A: H. IBAIONDO, A. ROMO. INGETEAM TRACTION,S.A. 1. Introduction The increasing concern with
Siemens Integrated Substation Condition Monitoring System. Circuit Breaker Monitoring
Siemens Integrated Substation Condition Monitoring System Circuit Breaker Monitoring System Description Introduction The Circuit Breaker Monitor [CBM] is only one example of the way that the Substation
System Protection Schemes in Eastern Denmark
System Protection Schemes in Eastern Denmark Joana Rasmussen COWI A/S, Energy Department System Protection Schemes in Eastern Denmark 1.Advanced system protection schemes are investigated and perspectives
1. Introduction. 2. Components. 3. Optical Specifications. 4. Electric Specifications. 5. Dimension. 6. Operating Environment. 7.
SPECIFICATIONS Super Model: XHS-220S1 Class Solar Simulator 1. Introduction 2. Components 3. Optical Specifications 4. Electric Specifications 5. Dimension 6. Operating Environment 7. Warranty SAN-EI ELECTRIC
INTRODUCTION TO HARMONIC ASSESSMENT IN POWER SYSTEMS
INTRODUCTION TO HARMONIC ASSESSMENT IN POWER SYSTEMS LIST OF CONTENT 1. INTRODUCTION... 1 2. HARMONIC VOLTAGE ASSESSMENT REQUIREMENT IN THE UK... 2 3. THE ASSESSMENT... 2 3.1. SYSTEM MODELLING...3 3.2.