Cable Consulting International

Size: px
Start display at page:

Download "Cable Consulting International"

Transcription

1 Cable Consulting International Brian Gregory BSc, CEng, MIEEE, FIEE Technical Director Alan Williams BSc, CEng, MIEE Senior Consultant 1

2 FEASIBILITY STUDY for 500 kv AC UNDERGROUND CABLES for use in THE EDMONTON REGION of ALBERTA, CANADA for the AESO Cable Consulting International 2

3 Topics Feasibility study Study contributors 500 kv Study project functional requirements Feasibility of 500kV underground cables Feasibility of power rating Supplier capability and experience 500 kv project size Project specific requirements Reliability Power losses Estimated costs Project risks Project schedule Recommendations for next steps Summary 3

4 Study contributors Feasibility study Principle investigators: CCI (Cable Consulting International) The findings and recommendations are CCI s Contributors: AESO (Alberta Electric System Operator) HPT (Heartland Project Team) Manufacturers Other consultants also contributed. Their names appear in the Appendices 4

5 AESO Provided the generic 500 kv Study Project to CCI Functional requirements Studies on electrical system Effect of reactive compensation Net Present Value of the Life cycle costs Cost of losses 5

6 CCI Performed the generic 500 kv Study Project: Visited Tokyo 500 kv cable circuit with AESO and HPT Scoping study: Costs and details from prospective suppliers Civil design: for the HPT to prepare costs Analysed manufacturers proposals State of the art Feasibility, risks, next steps Prepared report 6

7 HPT Contributions to the generic 500 kv Study Project: Typical routes Installation type Project schedule Total estimated capital cost 7

8 500kV cable systems suppliers Provided: Cable system designs Ampacity calculations Cable Accessories Trench configurations Technical design data Budgetary costs: Cables Accessories Delivery to Canada Supervision of installation Jointing Site testing To remain confidential: presented in a non-attributable manner Feasibility study 8

9 500 kv Study Project: Suppliers approached ABB Areva Brugg Exsym J-Power Systems LS Cable Nexans NKT Okonite Prysmian Siemens Silec Sudkabel Taihan Viscas 9

10 500 kv study project: functional requirements Generic study Route length: 65 km Two circuits: 3,000 MW Based on Heartland Project Applicable to 500 kv studies in Edmonton region of Alberta 10

11 500 kv study project route 11

12 Courtesy Prysmian 400 kv transition station 12

13 3,000 MW total: normal operation Feasibility study 13

14 3,000 MW total: contingency operation Feasibility study 14

15 Design loads for two circuits Feasibility study Load conditions: Peak load at any time: 3,000 MW total Average load over a year: 2,000 MW total Design of transmission system: Must take: peak load* Losses calculated on: average load * The cable must not exceed its design temperature at 3,000 MW 15

16 Feasibility of 500 kv underground cables 16

17 Feasibility of underground cables: conclusions Is an underground cable system feasible? Yes Underground 500 kv cable is technically feasible Cross linked polyethylene (XLPE) cable is best choice Proviso: manufacturers must validate cable and accessories on test to: IEC 62067: Accelerated aging prequalification for one year Special low ambient temperature test 17

18 500 kv cable types considered Feasibility study XLPE extruded SCFF LPP taped 18

19 500 kv XLPE cable has benefits of: Lowest losses of conventional cable types Solid (unpressurised) insulation: No possibility of fluid leakage from cable Lower maintenance Reduced risk of fire Alternative cable is SCFF (Self Contained Fluid Filled): Becoming obsolete Risk of fluid leakage 19

20 Other technologies evaluated: Gas insulated Line (GIL) Not yet proven for burial in long length circuits Some environmental concern Feasible alternative for tunnel (long length) Courtesy Siemens 20

21 Other technologies evaluated: Feasibility study High Temperature Superconducting Cable (HTS) Not yet sufficiently developed for high power, long length circuits with joints Courtesy NKT 21

22 Feasibility of power rating 22

23 Feasibility of power rating Can a cable system carry the 3,000 MW needed? Yes Suppliers design proposals: Largest standard conductor size: 2,500 mm 2 copper Two groups of cables per circuit Most efficient installation method: direct buried Typical design: Up to four trenches x three cables per trench = twelve cables (Study also evaluated scenarios with fewer groups of cables) 23

24 3,000 MW: Contingency operation Feasibility study 24

25 Six cables required per circuit: To carry 3,000 MW peak load in contingency operation 1,500 MW maximum per group of three cables 25

26 3,000 MW: Normal operation Feasibility study 26

27 Supplier Capability & Experience Has the cable system been used before at 500 kv? Yes, the cable has been used before at 500 kv But, no evidence to date that the offered joint types have been fully proven Three installations of 2,500 mm 2 cable with joints to date Three suppliers have this 500 kv experience 400 kv experience is a good indicator of prospective supplier capability Examples follow 27

28 500 kv, 2,500 mm 2, Tokyo tunnel: 2 x 40 km routes (240 km) Commissioned in 2000, 9 years good experience 4 suppliers In a warm, dry tunnel Courtesy Viscas 500 kv cable is available Courtesy J-Power Systems Extrusion moulded joint no longer offered 28

29 500 kv, 2,500 mm 2, Shanghai tunnel: 2 x 17 km routes (102 km of cable) To be commissioned in suppliers 2 types of prefabricated joint Feasibility study Courtesy Viscas Prefabricated joints on proving test Courtesy Viscas Pulling 500 kv cable into tunnel 29

30 500 kv, 2,500 mm 2, 2 routes in Russia, in tunnel 2 x 0.8 km routes (4.6 km of cable) Commissioned in 2008 and supplier 6 prefabricated joints Courtesy Nexans Outdoor terminations Courtesy Nexans Gas immersed terminations 30

31 400 kv, 1,200-2,500 mm 2, experience Cumulative 351 circuit km (1,053 km cable) 34 projects completed or under construction 21.3 km,1,600 mm 2, direct buried, installed km, 2,500 mm 2, direct buried, installed km, 2,500 mm 2, tunnel, installed 2005 Courtesy Brugg Prefabricated one piece joint mould Courtesy LS Cable Prefabricated composite joint 31

32 500 kv Project size How big is the 500 kv study project? It would be one of the largest in the world: 4 groups of cable in 20 km route require 240 km of cable ~360 joints. Equal to 40 km Tokyo circuit First application of buried, long length, large conductor 500 kv cable with joints. 400 kv buried experience is relevant. 500 kv is the highest voltage for XLPE to date 3,000 MW is a high power level. The combination of voltage and power requires a cable size at the top end of standard manufacturing ranges. Such cables are available 32

33 Project specific requirements 33

34 500 kv Project specific requirements Feasibility study Location specific: Crossing of route obstructions Highways: multi-lane and banked Pipelines: petrochemical, heated? Wetlands and streams Obstructions are normal for cable routes, but ability to maintain ampacity needs to be confirmed Low ambient temperatures Direct buried joints: -15 o C design Outdoor terminations: -50 o C design Lack of low temperature experience from suppliers. Concern about elasticity of the rubber insulation in accessories 34

35 Proving of performance 35

36 Proving of performance Feasibility study Should performance of cable system be proven before being supplied? Yes, both electrical and mechanical prequalification tests and low temperature tests must be performed Proving tests: these are normal before supply Prequalification test: one year Type test: 6 weeks Special proving tests: low temperature tests to be formulated 36

37 Proving of performance Feasibility study Courtesy Nexans Prequalification test Courtesy Sudkabel Type test 37

38 Reliability 38

39 Reliability Would XLPE cable system be reliable? Feasibility study Yes, Subject to performing proving tests and quality control in manufacture and installation Recommended proving and quality tests must be done Utilities are demonstrating confidence in reliability and maintenance by installing XLPE. They reduce risk by requiring high standards of design to installation Statistics of cable systems: Repair time 29 days. Faults : 1 x 10 km group per year Dig in faults 25% of above Majority of internal failures accessories Reliability analysis needed for all equipment Service experience of XLPE cable is comparatively short and needs to be monitored 39

40 Power losses 40

41 41

42 Fixed and Variable Losses Cable Overhead line Variable Losses Variable Losses Low load Fixed Losses High load Low load Fixed Losses High load Increasing transmitted load Increasing transmitted load 42

43 Power losses 43

44 Power losses There is a Cross over load where: cable losses = overhead line losses This occurs at approximately 1,700 MW Above1,700 MW Cable losses are lower than overhead line losses Below 1,700 MW Cable losses are higher than overhead line losses 44

45 Estimated costs How much would the 500 kv underground cable system cost? Different scenarios have different estimated costs: 45

46 Cost scenarios Feasibility study 65 km route with some underground cable: Underground route 10 km or 20 km Groups of Cables 3 or 4 Installation options: Unstaged all at same time Staged: Stage 1 some installed initially Stage 2 balance installed later Compared with all-overhead line 46

47 Scenario 1: FOUR Groups of Cables - Unstaged: all installed at start Feasibility study Full capacity at start: 3,000 MW 1,500 MW 1,500 MW 47

48 Scenario 1: FOUR Groups of Cables - Unstaged: all installed at start Feasibility study Full capacity at start: n-1 redundancy: 3,000 MW 1 group per circuit 2 groups total 750 MW 750 MW 750 MW 750 MW 48

49 Scenario 1: FOUR Groups of Cables - Unstaged : all installed at start Feasibility study Full capacity at start: n-1 redundancy: 3,000 MW 1 group per remaining circuit 1 groups total 1,500 MW 750 MW 750 MW 49

50 Scenario 1: FOUR Groups of Cables - Unstaged: all installed at start Feasibility study Full capacity at start: n-1 redundancy: 3,000 MW 0 group per remaining circuit 0 groups total 1,500 MW 1,500 MW 50

51 Scenario 1: FOUR Groups of Cables - Unstaged: all installed at start Feasibility study 1 x OHL circuit out of service 3,000 MW 1,500 MW 1,500 MW 51

52 Scenario 2: FOUR Groups of Cables total - Staged: 2 groups installed at start Half capacity at start: 2 further groups later 1,500 MW 750 MW 750 MW 52

53 Scenario 2: FOUR Groups of Cables total - Staged: 2 groups installed at start Half capacity at start: n-1 redundancy: 1,500 MW 1 group total 750 MW 750 MW future future 53

54 Scenario 2: FOUR Groups of Cables total - Staged: 2 groups installed at start Half capacity at start: n-1 redundancy: 1,500 MW 0 group total 1,500 MW future future 54

55 Scenario 3: THREE Groups of Cables total - Unstaged: All installed at start Full capacity at start: 3,000 MW Includes GIS switches 1,000 MW 1,000 MW 1,000 MW 55

56 Scenario 3: THREE Groups of Cables total - Unstaged: All installed at start Full capacity at start: n-1 redundancy: 3,000 MW 1 group total 1,000 MW 1,000 MW 1,000 MW 56

57 Scenario 3: THREE Groups of Cables total - Unstaged: All installed at start Full capacity at start: n-1 redundancy: 3,000 MW 0 groups 1,500 MW 1,500 MW 57

58 Scenario 3: THREE Groups of Cables total - Unstaged: All installed at start 1 x OHL circuit out of service 3,000 MW Includes GIS switches 1,000 MW 1,000 MW 1,000 MW 58

59 Scenario 4: THREE Groups of Cables total - Staged: 2 groups installed at start Half capacity at start: 1 group installed later 1,500 MW Includes GIS switches 750 MW 750 MW 59

60 Scenario 4: THREE Groups of Cables total - Staged: 2 groups installed at start Half capacity at start: n-1 redundancy: 1,500 MW 1 group total 750 MW 750 MW future 60

61 Scenario 4: THREE Groups of Cables total - Staged: 2 groups installed at start Half capacity at start: n-1 redundancy: 1,500 MW 0 group total 1,500 MW future 61

62 Scenario 4: THREE Groups of Cables total - Staged: 2 groups installed at start 1 x OHL circuit out of service 1,500 MW Includes GIS switches 750 MW 750 MW 62

63 Estimates of cost: types of costs Costs estimates prepared in TWO different ways Estimated capital costs: Initial purchase cost Estimated Net Present Value of life cycle costs A single number that expresses the estimated 40 year stream of costs in terms of an equivalent lump sum paid today Includes all costs for: constructing, owning, operating and maintaining the system (including spares) cost of energy losses All cost estimates in 2009 $ million CAD 63

64 Estimated capital project cost: 65 km (2009 $ million CAD) Unstaged 10 km cable 20 km cable OHL Scenario: 1 4 groups 3 groups 4 groups 3 groups

65 Estimated capital project cost: 65 km (2009 $ million CAD) Unstaged and Staged (Stage 1 and Stage 2) 10 km cable 20 km cable OHL Scenario: groups 3 groups 4 groups 3 groups

66 Estimated capital project cost: 65 km (2009 $ million CAD) Unstaged and Staged (Stage 1 and Stage 2) 10 km cable 20 km cable OHL 4 groups 3 groups 4 groups 3 groups Scenario:

67 Estimated capital project cost: 65 km (2009 $ million CAD) Unstaged and Staged (Stage 1 and Stage 2) 10 km cable 20 km cable OHL 4 groups 3 groups 4 groups 3 groups Scenario:

68 Estimated capital project cost: 65 km (2009 $ million CAD) Unstaged and Staged (Stage 1 and Stage 2) 10 km cable 20 km cable OHL 4 groups 3 groups 4 groups 3 groups Scenario:

69 Estimated NPV of life-cycle cost: 65 km route Unstaged and Staged PV of power losses in red 10 km cable 20 km cable OHL Staged Staged Staged Staged 4 groups 3 groups 4 groups 3 groups Scenario:

70 Estimated capital cost for 65 km route: by component (include 2x double circuit) X 2 X 2 X 2 Full length 70

71 Estimated capital cost: by component Feasibility study (2009 $ million CAD) 20 km cable, 4 groups, Staged Installation (example) X 2 X 2 X 2 Full length Stage 2 Stage 1 71

72 Project risks 72

73 Project risks What are the project specific risks? There are three risks: Feasibility study 1) Inability of 500 kv accessories to operate at Edmonton winter temperature Preventative Gather low temperature information from manufacturers Draft low temperature test specification Require manufacturers to perform this test Remedial Install joints at greater depth This may require an additional group of cables to meet 3,000 MW requirement Install cables in tunnel with controlled air temperature 73

74 Project risks What are the project specific risks? Feasibility study 2) Uncertainty of actual minimum winter temperature Preventative Field trials to measure ground temperature Remedial: Increase accessory design temperature margins Evaluate trace heating Install cables in tunnel 74

75 Project risks What are the project specific risks? Feasibility study 3) Long time required to repair cable in winter Preventative Specify the maximum winter repair time requirement to suppliers in the Request for Quotation Develop a winter repair procedure Design and build mobile heated habitat* for winter repair use Perform trials to prove the winter repair procedure Install more groups of cable to allow longer repair time Remedial Contingency switch the load onto parallel circuit Repair the accessory when the ambient temperature rises *Note: use of mobile jointing habitats is normal in temperate climates 75

76 Project schedule 76

77 Project schedule How long would it take to manufacture and install? 10 km, 4 groups Unstaged 57 months Staged (stage 1 only) 46 months 10 km, 3 groups Unstaged 57 months Staged (stage 1 only) 46 months 20 km, 4 groups Unstaged 57 months Staged (stage 1 only) 57 months 20 km, 3 groups Unstaged 57 months Staged (stage 1 only) 57 months 77

78 Recommendations for next steps 78

79 Recommended Next steps What are the next steps in evaluating underground cable? Refine and optimize cable system: Investigate joint low temperature protection by installation at greater depth Detailed designs for obstruction crossings. Is ampacity OK? Quantify reliability and availability for all circuit components Refine accuracy of the cost estimates Discussions with cable suppliers to agree: Normal proving tests Specific proving tests Discussions with cable suppliers on schedule shortening: Is evidence available for 500kV XLPE : Existing electrical and mechanical prequalification and type tests Ongoing installations and tests Low temperature test and service experience 79

80 Summary 80

81 Summary What are the main findings? Feasibility study 500kV, 3,000 MW, underground cable is feasible The power rating is feasible for normal burial depth. A study of specific obstruction crossings is required: Dimensions and temperatures Their effect on circuit power ampacity XLPE insulated cable is the best choice. Service and test experience exists for 500kV XLPE cable and terminations in temperate climates. No evidence exists of tests on joints at Edmonton low winter temperatures Evidence of tests is essential. (Continued) 81

82 Summary What are the main findings? Feasibility study Edmonton low winter ambient temperature is a project specific risk to the joints and terminations. Low temperature testing is essential. Ground temperature with depth to be measured: Winter Summer Cable optimization: ampacity benefits of: Cyclic rating study Lower summer ground temperatures at depth 82

83 83

HV Submarine Cable Systems Design, Testing and Installation

HV Submarine Cable Systems Design, Testing and Installation HV Submarine Cable Systems Design, Testing and Installation CIGRE Ireland Technical Seminar 6 th October 2010 Robert Donaghy Senior Consultant Engineer, ESB International Presentation Overview Applications

More information

State, trends and evolutions of HV/EHV power cables systems and contributions of SC B1 to their ongoing progress

State, trends and evolutions of HV/EHV power cables systems and contributions of SC B1 to their ongoing progress 0611-048-Mep229 12/12/06 6:44 Page 22 State, trends and evolutions of HV/EHV power cables systems and contributions of SC B1 to their ongoing progress Reinhard SCHROTH, Chairman of SC B1 2002-2006 High

More information

Stephen G. Whitley, Senior Vice President & Chief Operating Officer

Stephen G. Whitley, Senior Vice President & Chief Operating Officer Peter T. Brandien Vice President, System Operations To: Stephen G. Whitley, Senior Vice President & Chief Operating Officer From: Peter T. Brandien Re: Discussion of Cable Technologies Under Evaluation

More information

MV CABLE TYPE C 33-226

MV CABLE TYPE C 33-226 MV CABLE TYPE C 33-226 Standards : CENELEC HD 620 C 33-226 Rated voltage Rated voltage : 12/20 (24) kv Design 1 Stranded aluminium, class 2 conductor 2 Extruded conducting screen on conductor 3 XLPE insulation

More information

AMSC s Superconductor Cable Technologies for Electric Utilities

AMSC s Superconductor Cable Technologies for Electric Utilities International Workshop 2014 AMSC s Superconductor Cable Technologies for Electric Utilities Michael Ross, P.E. Managing Director of Superconductor Power Systems AMSC Corporate Facts Headquartered in MA,

More information

E-Highway2050 WP3 workshop April 15 th, 2014 Brussels

E-Highway2050 WP3 workshop April 15 th, 2014 Brussels E-Highway2050 WP3 workshop April 15 th, 2014 Brussels High voltage underground and subsea cable technology options for future transmission in Europe Ernesto Zaccone, Chairman Europacable High Voltage Systems

More information

Analytical Report RF high voltage cable accessories market

Analytical Report RF high voltage cable accessories market Analytical Report RF high voltage cable accessories market High voltage cable accessory market of Russia, development trends Cable accessories are special devices aimed to connect cables mechanically and

More information

Integrated Development and Assessment of New Thermoplastic High Voltage Power Cable Systems

Integrated Development and Assessment of New Thermoplastic High Voltage Power Cable Systems 21, rue d Artois, F-75008 PARIS B1-215 CIGRE 2012 http : //www.cigre.org Integrated Development and Assessment of New Thermoplastic High Voltage Power Cable Systems Mike FAIRHURST (1), Ankit GOWADIA (1),

More information

HIGH-CAPACITY HIGH TEMPERATURE SUPERCONDUCTING POWER CABLES

HIGH-CAPACITY HIGH TEMPERATURE SUPERCONDUCTING POWER CABLES HIGH-CAPACITY HIGH TEMPERATURE SUPERCONDUCTING POWER CABLES Jean-Maxime SAUGRAIN NEXANS Corporate VP Technical IASS Workshop Postdam May 13, 2011 Rationale High-capacity High Temperature Superconducting

More information

HIGH- AND EXTRA-HIGH-VOLTAGE GLOBAL CABLE SYSTEM SOLUTIONS Rely On Our Experience... Experience Our Capabilities

HIGH- AND EXTRA-HIGH-VOLTAGE GLOBAL CABLE SYSTEM SOLUTIONS Rely On Our Experience... Experience Our Capabilities HIGH- AND EXTRA-HIGH-VOLTAGE GLOBAL CABLE SYSTEM SOLUTIONS Rely On Our Experience... Experience Our Capabilities RELY ON OUR EXPERIENCE... EXPERIENCE OUR CAPABILITIES For close to half a century, Silec

More information

Summary of Electric Transmission Assessment Report

Summary of Electric Transmission Assessment Report Summary of Electric Transmission Assessment Report January 2010 Assessment and Analysis of the State-Of-the-Art High-Voltage Electric Transmission Systems with Specific Focus on High-Voltage Direct Current

More information

Undergrounding high voltage electricity transmission. The technical issues

Undergrounding high voltage electricity transmission. The technical issues Undergrounding high voltage electricity transmission The technical issues This is an interactive PDF document with clickable links from the contents to all sections and back and also to URL and email links.

More information

PB POWER ISLAND OF IRELAND CAVAN-TYRONE AND MEATH-CAVAN 400KV PROJECTS PRELIMINARY BRIEFING NOTE OVERHEAD AND UNDERGROUND ENERGY TRANSMISSION OPTIONS

PB POWER ISLAND OF IRELAND CAVAN-TYRONE AND MEATH-CAVAN 400KV PROJECTS PRELIMINARY BRIEFING NOTE OVERHEAD AND UNDERGROUND ENERGY TRANSMISSION OPTIONS ISLAND OF IRELAND CAVAN-TYRONE AND MEATH-CAVAN 400KV PROJECTS PRELIMINARY BRIEFING NOTE OVERHEAD AND UNDERGROUND ENERGY TRANSMISSION OPTIONS FEBRUARY 2008 PB POWER PB Power Page i EXECUTIVE SUMMARY General

More information

Max. Length of HTS Cables in the Future

Max. Length of HTS Cables in the Future Max. Length of HTS Cables in the Future K. Schippl, Nexans Deutschland Industries, Hannover, Germany TOPICS: Limitation of the cable design: 1. Physical limitations 2. Shipping limitations 3. Maintenance

More information

Respecting the environment

Respecting the environment MAIN FEATURE CHAPTER I RESEARCH WITH AN EYE ON THE FUTURE Respecting the environment Low power losses and a lesser visual impact on the landscape make Gas-Insulated Lines (GIL) a very environmentally friendly

More information

EDS 02-0027 11KV TRIPLEX CABLE

EDS 02-0027 11KV TRIPLEX CABLE THIS IS AN UNCONTROLLED DOCUMENT, THE READER MUST CONFIRM ITS VALIDITY BEFORE USE Document Number: EDS 02-0027 ENGINEERING DESIGN STANDARD EDS 02-0027 11KV TRIPLEX CABLE Network(s): EPN, LPN, SPN Summary:

More information

Konti Skan Replacement of Cable 1

Konti Skan Replacement of Cable 1 Konti Skan Replacement of Cable 1 Presentation of the project 1 Agenda Background for the project Scope of Work for the cable delivery Eletrical Requirements Type Test Route description Time Schedule 2

More information

EFFICIENT ELECTRICAL ENERGY TRANSMISSION AND DISTRIBUTION INTERNATIONAL ELECTROTECHNICAL COMMISSION

EFFICIENT ELECTRICAL ENERGY TRANSMISSION AND DISTRIBUTION INTERNATIONAL ELECTROTECHNICAL COMMISSION EFFICIENT ELECTRICAL ENERGY TRANSMISSION AND DISTRIBUTION INTERNATIONAL ELECTROTECHNICAL COMMISSION EFFICIENT ELECTRICAL ENERGY TRANSMISSION AND DISTRIBUTION 1 EFFICIENT ELECTRICAL ENERGY TRANSMISSION

More information

SUPERCONDUCTING CABLE SYSTEMS

SUPERCONDUCTING CABLE SYSTEMS SUPERCONDUCTING CABLE SYSTEMS INTRODUCTION An aging and inadequate power grid is widely seen as one of the greatest obstacles to the restructuring of power markets in the United States, Europe and elsewhere.

More information

AORC Technical meeting 2014

AORC Technical meeting 2014 http : //www.cigre.org B1-1055 AORC Technical meeting 2014 220 kv Long Distance Underground HVAC Cable Circuit NAVEED RAHMAN Nexans Olex Melbourne, Australia SUMMARY In 2009, the Victorian state government

More information

Cable Selection for Medium Voltage Capacitor Banks and Harmonic Filter Banks

Cable Selection for Medium Voltage Capacitor Banks and Harmonic Filter Banks Cable Selection for Medium Voltage Capacitor Banks and Harmonic Filter Banks Introduction This document presents the fundamental aspects of cable and conductor selection for connecting pad mounted shunt

More information

DISCUSSION OF CROSS-LINKED POLYETHYLENE INSULATED CABLES FOR UNDERGROUND PORTIONS OF THE MIDDLETOWN-NORWALK 345 kv PROJECTS.

DISCUSSION OF CROSS-LINKED POLYETHYLENE INSULATED CABLES FOR UNDERGROUND PORTIONS OF THE MIDDLETOWN-NORWALK 345 kv PROJECTS. DISCUSSION OF CROSS-LINKED POLYETHYLENE INSULATED CABLES FOR UNDERGROUND PORTIONS OF THE MIDDLETOWN-NORWALK 345 kv PROJECTS December 20, 2004 David W. Forrest Rachel I. Mosier 1. EXECUTIVE SUMMARY CL&P

More information

Offshore Wind China 2010 Bergen, 15th March 2010. Olivier Angoulevant Nexans Norway AS

Offshore Wind China 2010 Bergen, 15th March 2010. Olivier Angoulevant Nexans Norway AS Offshore Wind China 2010 Bergen, 15th March 2010 Olivier Angoulevant Nexans Norway AS At the core of performance At the core of performance : a worldwide leader Worldwide leader in cables, cabling systems

More information

ScottishPower Distribution Cables & Equipment. Metal Theft

ScottishPower Distribution Cables & Equipment. Metal Theft ScottishPower Distribution Cables & Equipment Metal Theft April 2012 As an aid to deterring to metal theft this booklet has been put together to help identify the types of utility power cables and associated

More information

An Introduction to High Voltage Direct Current (HVDC) Underground Cables

An Introduction to High Voltage Direct Current (HVDC) Underground Cables Page 1 An Introduction to High Voltage Direct Current (HVDC) Underground Cables Brussels, 10 October 2011 An Introduction to High Voltage Direct Current (HVDC) Underground Cables Page 2 Table of content

More information

KNOW YOUR OPTIONS: 230 KV POWER CABLES

KNOW YOUR OPTIONS: 230 KV POWER CABLES KNOW YOUR OPTIONS: 230 KV POWER CABLES 71 CONDUCTOR MATERIAL AND SIZE Conductor material is a matter of both customer preference and required current carrying capacity At 230 kv, copper is most common

More information

Lucien Antonissen Key Account Manager LIOS Technology Germany

Lucien Antonissen Key Account Manager LIOS Technology Germany Lucien Antonissen Key Account Manager LIOS Technology Germany Content Company Markets DTS Controller Software Configuration RTTR Demonstration Q&A NKT Holding 2013 NKT Holding Nilfisk-Advance NKT Cables

More information

HVDC Light Cables. Submarine and land power cables

HVDC Light Cables. Submarine and land power cables HV Light Cables Submarine and land s The HV Light s to offshore platform The light and robust HV Light s can be laid with very cost effecient methods HV Light System HV Light is a transmission system in

More information

factsheet High Voltage Direct Current Electricity technical information

factsheet High Voltage Direct Current Electricity technical information factsheet High Voltage Direct Current Electricity technical information Introduction High voltage direct current (HVDC) technology is one of the technical options National Grid can consider for the future

More information

Assessing, Maintaining & Replacing Fluid Filled Cable Systems at PEPCO

Assessing, Maintaining & Replacing Fluid Filled Cable Systems at PEPCO April 2, 2014 Assessing, Maintaining & Replacing Fluid Filled Cable Systems at PEPCO Todd Goyette, P.E., POWER Engineers Mousa Hejazi, P.E., Pepco Holdings Inc. 1 Pepco Quick Facts First incorporated in

More information

Section 5 161 kv Power Cables

Section 5 161 kv Power Cables Know Your Options: 161 kv Power Cable 61 material and size material is a matter of both customer preference and required current carrying capacity Copper conductor common for larger loads When both copper

More information

CABLE MONITORING SOLUTION

CABLE MONITORING SOLUTION POWER CABLE MONITORING SOLUTION Kuljit Singh BSc Honours MIEE(IET,UK) Dan Watley Ph. D, B.A MEng (UK), MIEEE, UK 8-9 November 2011 PREDICT WITH CERTAINTY Definition DTS: Distributed Temperature Sensor

More information

factsheet High Voltage Direct Current electricity technical information

factsheet High Voltage Direct Current electricity technical information factsheet High Voltage Direct Current electricity technical information Introduction High voltage direct current (HVDC) technology is one of the technical options National Grid can consider for the future

More information

KNOW YOUR OPTIONS: 69 KV XLPE POWER CABLE

KNOW YOUR OPTIONS: 69 KV XLPE POWER CABLE Know Your Options: 69 kv XLPE Power Cable 3 material and size material is a matter of both customer preference and required current carrying capacity Copper conductor common for larger loads When both

More information

CABLE ACCESSORIES 110-220 kv

CABLE ACCESSORIES 110-220 kv CABLE ACCESSORIES 110-220 kv Termination 110 kv Technical description Termination MKB 126 / 145 with composite type insulator uses for cable line joints with other elements of power-supply systems. Termination

More information

CCI Cable Consulting International Ltd PO Box 1, Sevenoaks TN14 7EN United Kingdom

CCI Cable Consulting International Ltd PO Box 1, Sevenoaks TN14 7EN United Kingdom TITLE: Cable Manufacturing Capability Study REPORT No: ER519 Rev 3 CUSTOMER: The Crown Estate AUTHOR: David Notman BSc, CEng, MIET DATE: Executive Summary In January 2012, Cable Consulting International

More information

Discussion Group C32D: Support of transmission cables in manholes

Discussion Group C32D: Support of transmission cables in manholes Discussion Group C32D: Support of transmission cables in manholes IEEE Insulated Conductors Committee Meeting May 22-25, 2011 St. Petersburg Beach, Florida 1 Agenda This Meeting Introduction Review of

More information

Top Drive Service Loops. Conventional, Enhanced and Superior Solutions for Drilling Applications

Top Drive Service Loops. Conventional, Enhanced and Superior Solutions for Drilling Applications Top Drive Service Loops Conventional, Enhanced and Superior Solutions for Drilling Applications Linking the future As the worldwide leader in the cable industry, Prysmian Group believes in the effective,

More information

Feasibility Study of Deep Water Power Cable Systems. Enrico Colombo CESI S.p.A

Feasibility Study of Deep Water Power Cable Systems. Enrico Colombo CESI S.p.A Feasibility Study of Deep Water Power Cable Systems Enrico Colombo CESI S.p.A Layout of Presentation The Study Context, Objectives, Participants Study Approach & Methodology Assessments and Findings Implementation

More information

RCP2 Portfolio Overview Document

RCP2 Portfolio Overview Document RCP2 Portfolio Overview Document Portfolio: Expenditure Class: Base Capex Expenditure Category: Grid Replacement & Refurbishment As at date: 15 November 2013 Expenditure Forecast Real 2012/13 NZ$ (m) 2015-2016

More information

ACCESSORIES FOR HV CABLES WITH EXTRUDED INSULATION

ACCESSORIES FOR HV CABLES WITH EXTRUDED INSULATION ACCESSORIES FOR HV CABLES WITH EXTRUDED INSULATION Ref: WG 21.06 (TB 177) JTF 21.15 (TB 210) TF B1.10 (Electra 212) Henk Geene Presentation overview Accessories function Accessory design Accessory types

More information

Gulf Cable & Electrical Ind. Co.

Gulf Cable & Electrical Ind. Co. CONTENTS INTRODUCTION PRODUCT RANGE I PRODUCT DATA TABLES XLPE INSULATED 600/1000V CABLES Two Core Cables CU/XLPE/PVC/LC/PVC/SWA/PVC 1 Three Core Cables CU/XLPE/PVC/LC/PVC/SWA/PVC 2 Four Core Cables CU/XLPE/PVC/LC/PVC/SWA/PVC

More information

CABLE ASSET MANAGEMENT PREDICT WITH CERTAINTY. Kuljit Singh BSc Honours MIEE(IET,UK) 5 June 2014

CABLE ASSET MANAGEMENT PREDICT WITH CERTAINTY. Kuljit Singh BSc Honours MIEE(IET,UK) 5 June 2014 CABLE ASSET MANAGEMENT PREDICT WITH CERTAINTY Kuljit Singh BSc Honours MIEE(IET,UK) 5 June 2014 Definitions International Workshop 2014 DTS: Distributed Temperature Sensor DCR: Dynamic Cable Ratings (

More information

345 kv Underground Report

345 kv Underground Report POWER ENGINEERS, INC. February 24, 2010 345 kv Underground Report PROJECT NUMBER: 117910 PROJECT CONTACT: Mike Mueller Richard C. Mues, PE EMAIL: mike.mueller@powereng.com rmues@powereng.com PHONE: 314-851-4050

More information

QUALITY CONTROL Prepared: V. van Gastel / team TenneT Reviewed: M. Müller 23.06.2015 Approved: F. Wester 23.06.2015 1. BACKGROUND MATERIAL...

QUALITY CONTROL Prepared: V. van Gastel / team TenneT Reviewed: M. Müller 23.06.2015 Approved: F. Wester 23.06.2015 1. BACKGROUND MATERIAL... POSITION PAPER STAKE HOLDER CONSULTATION PROCESS OFFSHORE GRID NL Type: Position paper Work stream Technical Topic: T.2 Number of J-Tubes Filename ONL 15-060-T2_ J tubes_ bays_pp_v2 Version 3 - Public

More information

By Manitoba Hydro, March 4 th 2013

By Manitoba Hydro, March 4 th 2013 Rebuttal to Bipole III Coalition underground cable report Potential Use of Underground Cables for Sections of the Planned 500 kvdc Bipole III Overhead Line in Manitoba By Manitoba Hydro, March 4 th 2013

More information

High Voltage Cable Systems

High Voltage Cable Systems High Voltage Cable Systems Cables and Accessories up to 550 kv Completing the picture nkt cables part of a world, counting on reliable and available electrical power Today a world without electrical power

More information

High Voltage Systems. Today. The history of cables

High Voltage Systems. Today. The history of cables High Voltage Cables High Voltage Systems Today Prysmian Cables and Systems B.V. is part of the Prysmian Group, a leading player in the industry of high-technology cables and systems for energy and telecommunications,

More information

The new 525 kv extruded HVDC cable system

The new 525 kv extruded HVDC cable system The new 525 kv extruded HVDC cable system World s most powerful extruded cable system Anders Gustafsson, Markus Saltzer, Andreas Farkas, Hossein Ghorbani, Tobias Quist, Marc Jeroense High Voltage Cables

More information

Network Standard Advice No. 1420C 9/6/2011

Network Standard Advice No. 1420C 9/6/2011 Network Standard Advice No. 1420C 9/6/2011 TO: Customers, Service Providers and Ausgrid Staff. Advisory Note on Changes to the Use of 11kV Cable Types. Introduction This Network Standard Advice (NSA) provides

More information

For business. Wiring your business for broadband. What happens when copper is required?

For business. Wiring your business for broadband. What happens when copper is required? For business Wiring your business for broadband Your cabling requirements are dependent on the size and complexity of your business. Smaller businesses should follow the wiring recommendations for residential

More information

MEASUREMENTS OF THRUST LOAD IN CABLE SYSTEMS SEMI-RIGIDLY INSTALLED IN DUCT / MANHOLE STRUCTURES

MEASUREMENTS OF THRUST LOAD IN CABLE SYSTEMS SEMI-RIGIDLY INSTALLED IN DUCT / MANHOLE STRUCTURES MEASUREMENTS OF THRUST LOAD IN CABLE SYSTEMS SEMI-RIGIDLY INSTALLED IN DUCT / MANHOLE STRUCTURES Riccardo BODEGA, Prysmian Cables and Systems, The Netherlands, riccardo.bodega@prysmian.com Henk GEENE,

More information

Oahu Wind Integration and Transmission Study (OWITS) Hawaiian Islands Transmission Interconnection Project

Oahu Wind Integration and Transmission Study (OWITS) Hawaiian Islands Transmission Interconnection Project Oahu Wind Integration and Transmission Study (OWITS) Hawaiian Islands Transmission Interconnection Project Dennis Woodford Electranix Corporation Winnipeg, Manitoba Canada NREL is a national laboratory

More information

Comparison of GIS and AIS systems for urban supply networks

Comparison of GIS and AIS systems for urban supply networks Comparison of GIS and AIS systems for urban supply networks Studies carried out by ABB show that for urban supply networks the combination of HV gas-insulated switchgear (GIS) and HV cable has important

More information

Q: PLEASE STATE YOUR NAME AND BUSINESS ADDRESS. A: Gerry Sheerin. Sheerin Technical, 25 Eastville Avenue, Toronto, Ontario Canada

Q: PLEASE STATE YOUR NAME AND BUSINESS ADDRESS. A: Gerry Sheerin. Sheerin Technical, 25 Eastville Avenue, Toronto, Ontario Canada DIRECT TESTIMONY OF GERRY SHEERIN, P. ENG ON BEHALF OF PIEDMONT ENVIRONMENTAL COUNCIL BEFORE THE STATE CORPORATION COMMISSION OF VIRGINIA CASE NOS. PUE-00-0001 AND PUE-00-000 1 1 1 1 1 1 1 1 1 Q: PLEASE

More information

Submarine Power Cables. State-of-the-art production facility, more than 100 years of experience and reference installations around the world.

Submarine Power Cables. State-of-the-art production facility, more than 100 years of experience and reference installations around the world. Submarine Power Cables State-of-the-art production facility, more than 100 years of experience and reference installations around the world. Reliable submarine power cables ABB is one of the world s most

More information

Electrical for Detached Garages: Updated Feb 19, 2016 for 2015 CE Code in force Jan. 1, 2016. Underground branch circuit feeding a detached garage:

Electrical for Detached Garages: Updated Feb 19, 2016 for 2015 CE Code in force Jan. 1, 2016. Underground branch circuit feeding a detached garage: Electrical for Detached Garages: Updated Feb 19, 2016 for 2015 CE Code in force Jan. 1, 2016 * Garage construction requires permits (electrical, building) * Permits must be applied for at the time. * Dial

More information

Vision 2050 An Asset Management Strategy. Jaclyn Cantler Manager, Transmission Planning, PHI

Vision 2050 An Asset Management Strategy. Jaclyn Cantler Manager, Transmission Planning, PHI 1 Vision 2050 An Asset Management Strategy Jaclyn Cantler Manager, Transmission Planning, PHI 2 Agenda Case for Change About Vision 2050 Status Closing System Design Cybersecurity Interface with distributed/dispersed

More information

Grid connection of near shore wind farms

Grid connection of near shore wind farms Grid connection of near shore wind farms methods, preconditions and results Rene Starup 5. Marts 2015 1 Topics Methods Preconditions Technical and socio-economic analysis 5. Marts 2015 2 60, 150 and 400

More information

NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission Limited, Scottish Hydro Electric Transmission Limited

NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission Limited, Scottish Hydro Electric Transmission Limited NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission Limited, Scottish Hydro Electric Transmission Limited TABLE OF CONTENTS 1.0 Purpose and Scope...2 1.1 Methodology Purpose...2

More information

environment briefing02

environment briefing02 PRODUCED BY THE SAFETY, HEALTH & ENVIRONMENT GROUP OF THE ENERGY NETWORKS ASSOCIATION - JULY 2006 environment briefing02 transporting electricity Overhead Lines or Underground Cables? Introduction The

More information

IEC and IEEE Standards for High-Voltage Switchgear and Controlgear Present Situation and Future Evolution

IEC and IEEE Standards for High-Voltage Switchgear and Controlgear Present Situation and Future Evolution IEC and IEEE Standards for High-Voltage Switchgear and Controlgear Present Situation and Future Evolution Denis Dufournet Chairman IEC TC 17 & SC17A Fellow IEEE Senior Expert Areva T&D Mumbai, January,

More information

Overhead lines in Ireland

Overhead lines in Ireland Overhead lines in Ireland The value in Cigré Jarlath Doyle Abstract The main theme of my presentation is to give a brief overview of the valuable information and influence Cigré has and is having on the

More information

How To Test For Safety On A Power Cable

How To Test For Safety On A Power Cable T H E M A G A Z I N E O F 7 x 2 4 E X C H A N G E I N T E R N AT I O N A L A Green Approach to Building a Superior Data Center S P R I N G 0 9 BUILD FOR TODAY. EXPAND ON DEMAND. Modularity in the data

More information

Removal of EP 20 10 00 02 SP High Voltage Cable

Removal of EP 20 10 00 02 SP High Voltage Cable TN 018: 2014 Technical Note For queries regarding this document standards@asa.transport.nsw.gov.au www.asa.transport.nsw.gov.au TN 018: 2014 Issued date 12 March 2014 Effective dates 12 March 2014 Subject:

More information

LEAD FREE FIREX. Interlock Armored Cables TECK90 and MC Industrial Cables. w w w. n e x a n s e n e r g y. c o m

LEAD FREE FIREX. Interlock Armored Cables TECK90 and MC Industrial Cables. w w w. n e x a n s e n e r g y. c o m FIREX Interlock Armored Cables TECK90 and MC Industrial Cables LEAD FREE O V E R 1 8 0 Y E A R S O F E X P E R I E N C E 866-663-9267 w w w. n e x a n s e n e r g y. c o m Interlock Armored Cables Introduction....2

More information

XLPE Land Cable Systems User s Guide. Rev 5

XLPE Land Cable Systems User s Guide. Rev 5 XLPE Land Cable Systems User s Guide Rev 5 CONTENT XLPE Land Cable Systems Introduction... 3 Design, installation and testing... 4 XLPE cables... 4 Cable accessories... 4 Installation of XLPE cable systems...

More information

M. GELDON Brugg Kabel CZ. Ing. D. RÚŽEK PREdistribuce. Switzerland Czech Rep. Czech Rep. Czech Rep., Switzerland Germany

M. GELDON Brugg Kabel CZ. Ing. D. RÚŽEK PREdistribuce. Switzerland Czech Rep. Czech Rep. Czech Rep., Switzerland Germany 21, rue d Artois, F-75008 PARIS Paper number CIGRE 2012 http : //www.cigre.org 6 characters (to be provided later) Correlation between calculated transmission capacity and actual one D. WALD* Eifelkabel

More information

HIGH VOLTAGE XLPE CABLE SYSTEMS. Technical User Guide

HIGH VOLTAGE XLPE CABLE SYSTEMS. Technical User Guide HIGH VOLTAGE XLPE CABLE SYSTEMS Technical User Guide Content 1. General information on High Voltage XLPE Cable Systems 1.1. Introduction 1.2. Cable selection process 1.3. Service life 3 3 3 4 2. Cable

More information

CHAPTER VIII LINE PLANT SYSTEM COMMUNICATION THROUGH RE CABLE

CHAPTER VIII LINE PLANT SYSTEM COMMUNICATION THROUGH RE CABLE CHAPTER VIII LINE PLANT SYSTEM COMMUNICATION THROUGH RE CABLE 8.1 SYSTEM 8.1.1 Armoured, screened underground cables are used for control communication in electrified areas to limit induction effect. 8.2

More information

Power transformers. Generator step-up and system intertie power transformers Securing high-quality AC transmission

Power transformers. Generator step-up and system intertie power transformers Securing high-quality AC transmission Power transformers Generator step-up and system intertie power transformers Securing high-quality AC transmission Generator step-up transformers Built to withstand continuous full load Generator step-up

More information

Chemical resistance Accidental

Chemical resistance Accidental Industrial flexible cable, insulation and outer sheath in elastomer Description Application TITANEX flexible cable is intended for installations with moving equipment, electric appliances and for building

More information

Voltage Drop (Single-Phase)

Voltage Drop (Single-Phase) Voltage Drop (Single-Phase) To Find: To Find Voltage Drop Formula: 2 x K x L x I V.D. = ------------------- C.M. Variables: C.M. = Circular Mill Area (Chapter 9, Table 8) To Find Voltage Drop Percentage

More information

CONFLEX ELECTRIC CABLE

CONFLEX ELECTRIC CABLE CONFLEX ELECTRIC CABLE CONFLEX - 0.6/1kV Flexible VSD/EMC Cables Applications WW VSD/EMC cables are manufactured for use where electrical interference distorts signal transmission in electric motors. Standard

More information

Corporate Profile ROYAL. MODERN ROYAL ELECTRIC Ideal Power Solution MRE ELECTRICAL, INSTRUMENTATION & COMMUNICATION SYSTEMS

Corporate Profile ROYAL. MODERN ROYAL ELECTRIC Ideal Power Solution MRE ELECTRICAL, INSTRUMENTATION & COMMUNICATION SYSTEMS Corporate Profile MODERN ROYAL ELECTRIC Ideal Power Solution ROYAL MRE ELECTRICAL, INSTRUMENTATION & COMMUNICATION SYSTEMS MAJOR STOCKIST >>> CATHODIC PROTECTION CABLES >>> LOW VOLTAGE CABLES >>> MEDIUM

More information

Fault location on power cables. Fault location on power cables

Fault location on power cables. Fault location on power cables Fault location on power cables Fault location on power cables Contents: 1. Introduction 2. Construction of power cables 3. Cable faults 01. Introduction Fault location on communication and power cables

More information

THE PATHWAY TO POWER HIGH-VOLTAGE CABLES

THE PATHWAY TO POWER HIGH-VOLTAGE CABLES THE PATHWAY TO POWER HIGH-VOLTAGE CABLES TABLE OF CONTENTS HIGH-VOLTAGE CABLES 3 Advantages of XLPE-insulated cable systems 3 PROPOSAL 4 Cable systems 4 Providing System Solutions 4 Continuous temperature

More information

Totally Integrated Power SIESTORAGE. The modular energy storage system for a reliable power supply. www.siemens.com/siestorage

Totally Integrated Power SIESTORAGE. The modular energy storage system for a reliable power supply. www.siemens.com/siestorage Totally Integrated Power SIESTORAGE The modular energy storage system for a reliable power supply www.siemens.com/siestorage Totally Integrated Power (TIP) We bring power to the point. Our products, systems,

More information

MEDIUM VOLTAGE CE-BF SWITCHBOARDS. UP TO 40.5 kv. CE - BF - C - en - REV.00 2012.4

MEDIUM VOLTAGE CE-BF SWITCHBOARDS. UP TO 40.5 kv. CE - BF - C - en - REV.00 2012.4 CE - BF - C - en - REV.00 2012.4 APPLICATION CE-BF Switchbords up to 40.5 kv are designed for use in public and industrial distribution system up to 40,5KV for the operation and protection of lines, transformers,

More information

R=Required by Lab S=May be subcontracted IEC SYSTEM FOR CONFORMITY TESTING AND CERTIFICATION OF ELECTRICAL EQUIPMENT COMMITTEE OF TESTING LABORATORIES

R=Required by Lab S=May be subcontracted IEC SYSTEM FOR CONFORMITY TESTING AND CERTIFICATION OF ELECTRICAL EQUIPMENT COMMITTEE OF TESTING LABORATORIES IEC SYSTEM FO CONFOMITY TESTING AND CETIFICATION OF ELECTICAL EQUIPMENT COMMITTEE OF TESTING LABOATOIES TESTING AND MEASUING EQUIPMENT/ALLOWED SUBCONTACTING Power cables with extruded insulation and their

More information

SUITABILITY OF DIFFERENT TEST VOLTAGES FOR ON-SITE TESTING OF XLPE CABLE SYSTEMS

SUITABILITY OF DIFFERENT TEST VOLTAGES FOR ON-SITE TESTING OF XLPE CABLE SYSTEMS SUITABILITY OF DIFFERENT TEST VOLTAGES FOR ON-SITE TESTING OF XLPE CABLE SYSTEMS Michael Hensel HIGHVOLT Prüftechnik Dresden GmbH 2 3 Content 1 Introduction Test parameters and their significance Differences

More information

Undergrounding high voltage electricity transmission lines. The technical issues

Undergrounding high voltage electricity transmission lines. The technical issues Undergrounding high voltage electricity transmission lines The technical issues Contents Introduction 03 National Grid electricity transmission 03 an overview Section 1 Insulating underground cables 04

More information

How To Monitor Water Penetration In A Cable Screen

How To Monitor Water Penetration In A Cable Screen Detection and location of high voltage cable sheath damage with Water Penetration Monitoring*) Purpose of Monitoring System The expected lifetime of high voltage underground cables is more than 40 years,

More information

Simulation of Cable Overloading Problem on a University Distribution System

Simulation of Cable Overloading Problem on a University Distribution System Advance in Electronic and Electric Engineering. ISSN 2231-1297, Volume 3, Number 6 (2013), pp. 765-770 Research India Publications http://www.ripublication.com/aeee.htm Simulation of Cable Overloading

More information

Development of a 500-kV DC XLPE Cable System

Development of a 500-kV DC XLPE Cable System by Satoru Maruyama *, Noboru Ishii *, Michihiro Shimada *, Shinji Kojima * 2, Hideo Tanaka * 3, Mitsumasa Asano * 4, Tetsuya Yamanaka * 4, and Shin ichi Kawakami * 4 This paper describes development work

More information

Cables, Cable Laying & Accessories Manual

Cables, Cable Laying & Accessories Manual Distribution Business Cables, Cable Laying & Accessories Manual Database ref: File Ref: Title Page & Revision Log For Cables & Access v4 - Nov 2003.doc Manual Name: Cables & Accessories Manual Version

More information

SHE Transmission. 2015_10_30 Transmission Losses Strategy Rev 2.0 October 2015

SHE Transmission. 2015_10_30 Transmission Losses Strategy Rev 2.0 October 2015 SHE Transmission 2015_10_30 Transmission Losses Strategy Rev 2.0 October 2015 Summary This paper presents SHE Transmission s views and approach on the impact of transmission losses on the transmission

More information

Preliminary Information Memorandum. Thanet Offshore Transmission Assets. July 2009

Preliminary Information Memorandum. Thanet Offshore Transmission Assets. July 2009 Preliminary Information Memorandum Thanet Offshore Transmission Assets July 2009 SUMMARY In April 2009 Ofgem distributed a teaser document, UK Offshore Transmission Investment Opportunity, to investors

More information

IEEE POWER ENGINEERING SOCIETY CHICAGO CHAPTER THE OKONITE COMPANY WEDNESDAY JANUARY 11, 2006 JIM FITZGERALD ENGINEERING LINGO

IEEE POWER ENGINEERING SOCIETY CHICAGO CHAPTER THE OKONITE COMPANY WEDNESDAY JANUARY 11, 2006 JIM FITZGERALD ENGINEERING LINGO IEEE POWER ENGINEERING SOCIETY CHICAGO CHAPTER THE OKONITE COMPANY WEDNESDAY JANUARY 11, 2006 JIM FITZGERALD ENGINEERING LINGO WHEN YOU HEAR AN ENGINEER SAY A NUMBER OF DIFFERENT APPROACHES ARE BEING IMPLEMENTED

More information

Cable Care. ABB Power Cables Service Products

Cable Care. ABB Power Cables Service Products Cable Care ABB Power Cables Service Products 2 ABB Power Cables Service Products ABB Power Cables Minimize revenue losses in case of a fault High preparedness with ABB Cable Care ensures efficient repair

More information

Presentation to CIGRE Next Generation Network. Visit of Seine substation

Presentation to CIGRE Next Generation Network. Visit of Seine substation Presentation to CIGRE Next Generation Network Visit of Seine substation Projet Seine 30 août 2012 Contents 0. Presentation of RTE 1. Power supply of «Ile-de-France» and Paris 2. 225 kv Paris substations

More information

Power Voltage Transformers for Air Insulated Substations. THE PROVEN POWER.

Power Voltage Transformers for Air Insulated Substations. THE PROVEN POWER. Power Voltage Transformers for Air Insulated Substations THE PROVEN POWER. Introduction Trench Power Voltage Transformers (Power VTs) combine the attributes of an inductive voltage transformer with the

More information

RGI Cable Workshop Understanding Underground Cables 13 and 14 February in Spreitenbach, Switzerland A workshop kindly hosted by Swissgrid

RGI Cable Workshop Understanding Underground Cables 13 and 14 February in Spreitenbach, Switzerland A workshop kindly hosted by Swissgrid RGI Cable Workshop Understanding Underground Cables 13 and 14 February in Spreitenbach, Switzerland A workshop kindly hosted by Swissgrid During the 1.5 day workshop, more than 70 participants from industry,

More information

Assessment of the Technical Issues relating to Significant Amounts of EHV Underground Cable in the All-island Electricity Transmission System

Assessment of the Technical Issues relating to Significant Amounts of EHV Underground Cable in the All-island Electricity Transmission System Assessment of the Technical Issues relating to Significant Amounts of EHV Underground Cable in the All-island Electricity Transmission System Summary Report November 2009 Technical Report on using EHV

More information

ABB i-bus EIB / KNX Analogue Input AE/S 4.2

ABB i-bus EIB / KNX Analogue Input AE/S 4.2 Product Manual ABB i-bus EIB / KNX Analogue Input AE/S 4.2 Intelligent Installation Systems This manual describes the functionality of Analogue Input AE/S 4.2. Subject to changes and errors excepted. Exclusion

More information

Ampacity simulation of a high voltage cable to connecting off shore wind farms

Ampacity simulation of a high voltage cable to connecting off shore wind farms Ampacity simulation of a high voltage cable to connecting off shore wind farms Eva Pelster 1, Dr. David Wenger 1 1 Wenger Engineering GmbH, Einsteinstr. 55, 89077 Ulm, mail@wenger-engineering.com Abstract:

More information

IESO Supply Deliverability Guidelines

IESO Supply Deliverability Guidelines PUBLIC IMO_GDL_0021 IESO Supply Deliverability Guidelines Issue 3.0 This document is to be used to evaluate long-term system adequacy and connection assessments Public Disclaimer The posting of documents

More information

Cable Size Selection for Energy Efficiency

Cable Size Selection for Energy Efficiency Cable Size Selection for Energy Efficiency Introduction The traditional method for determining the appropriate cable size for a particular installation involves the selection of the smallest size conductor

More information

Cable Accessories. for Extruded Dielectric Cable 69kV - 230kV Rated. Catalog Python13

Cable Accessories. for Extruded Dielectric Cable 69kV - 230kV Rated. Catalog Python13 Cable Accessories for Extruded Dielectric Cable 69kV - 230kV Rated Components used in cable systems 100% Tested Factory Molded For outdoor applications through 230kV For gas insulated substations and transformers

More information

ELECTRICAL INSULATION TESTING OF HV EQUIPMENT UP TO 33kV

ELECTRICAL INSULATION TESTING OF HV EQUIPMENT UP TO 33kV 1. SCOPE This document details PowerSystems requirements for electrical testing of HV Equipment up to and including 33kV. 2. ISSUE RECORD This is a Reference document. The current version of Controlled

More information