Transmission technologies for collective offshore wind farm connections
|
|
|
- Willa Douglas
- 10 years ago
- Views:
Transcription
1 Transmission technologies for collective offshore wind farm connections H. Brakelmann, K. Burges Abstract: Offshore wind farms under development have capacities of 4 MW and higher and are likely to be located - km off the cost or the nearest grid connection point. Because of technology constraints, conventional HAC cable designs and configurations have serious disadvantages as for example high transmission losses and extensive space requirements. The proposed transmission concept overcomes major advantages and, hence, offers a technically and economically viable option for collective connection of offshore wind projects to onshore networks. The comparison with alternative DC technologies in the same capacity range shows promising characteristics. Index Terms HAC, XLPE, cables, offshore, wind farms, transmission systems I. BACKGROUND AND STATE-OF-THE-ART Currently, in the German waters of the North and the Baltic Sea offshore wind parks are under development with typical capacities of 4 MW in the initial pilot phase. In the final stage capacities of up to 5 MW per wind farm are intended. The distance to the onshore transmission network is up to 5 km. The situation in other European countries as the UK or Belgium is similar. The costs and losses associated with the high voltage (H) transmission link between the offshore wind farms and the point of common coupling will play a decisive role for the economics of those projects. Concerning the transmission link, different approaches are being discussed. Three-phase AC cables and the required auxiliary components (compensation) are proven and available in commercial markets. However, transfer capacities of three phase XLPE AC cables are limited, most of all as a consequence of restrictions of their physical dimensions. Figure shows the cross section of a typical 5 / 7 k cable. Key data indicating the technically feasible maximum are a copper cross section of about mm, a cable diameter of more than 3 mm and a specific weight of about kg/m. The resulting capacity of such a cable is limited to about 5 MA, depending on the distance. For typical wind farms currently under development in Europe, this results in connections using cables which are laid one by one in two separate trenches. The copper cross section of cables for 45 k, currently H. Brakelmann is with the Universität Duisburg-Essen, Department ETS, Bismarckstraße 8, Gebäude BE,, D-4757 Duisburg, Germany. ( [email protected]). K. Burges is with the Ecofys GmbH, Stralauer Platz 34, 43 Berlin, Germany. ( [email protected]). being introduced to the market, will be restricted to about 8mm, resulting in a maximum capacity of about 35 MA. Nexans [] proposed to use single core 4-k XLPE cables. The cross section of the conductor would be about mm and the copper armouring should have a similar cross section. The maximum capacity for a 5 km line according to [] is about 9 MA. The concept requires three parallel cable trenches to be implemented one by one. One problem of such a configuration is the high current induced in the armouring. If the cables are buried with technically relevant distance in between (5 m or more) these shield currents easily are of the same magnitude as the currents in the inner conductor. The disadvantages of such a configuration are evident: heavy and expensive cables, and compared to three core cables much higher losses. Summarising, with state-of-the-art technology the technically feasible capacity limit for AC offshore transmission is about 37 MA for 3 core cables and about MA in case of 3 single core cables []. Higher capacities inevitably require more parallel cable routes. Alternatively, DC concepts have been discussed already for several years. Conventional, current source converters (CSC) based on thyristor switches have already been applied for long distance, bulk electricity transport up to high voltage and power levels (e.g. bipolar + 45 k, MA, Figure ). Concepts adapted to offshore wind energy have been proposed (e.g. by AREA [3]) but for a number of technical and economical reasons prospects are questionable. Figure : typical three core XLPE submarine cable for 5/7 k, 3** mm; left ABB (FXBT), right: Nexans (TKFA)
2 Figure : +/- 45 k/ mm - HDC-submarine cable (oil paper) of ABB; maximum capacity bipolar: MW The capacity of commercial IGBT based voltage source (SC) converters has been increased significantly during the last years. Converter capacities up to 5 MW emerge in the market [], though from a limited number of suppliers (HDC light, HDC plus). Using state-of-the-art single core XLPE DC cables (see Figure 3) with a rated voltage of +5 k and a cross section of mm, the maximum capacity per circuit would be about 4 MW. This would be sufficient for most offshore wind projects currently under development in the North Sea. Recently, ABB announced introduction of ±3 k DC cables with a transmission capacity up to MW and availability of DC converter modules of the same size. The two DC cables would be laid simultaneously in one trench. Limitations of this technology are the substantial costs for the power converters, respective space requirements, in particular offshore, and the conversion losses amounting for about 3% per converter, depending on loading. Figure 3: +/-5-k XLPE-DC cable (source: ABB) The number of potential projects under development in the North Sea results in substantial space requirements for cable routes. This is critical as the coastal areas are sensitive, to a large extent declared as natural parks and as such more or less protected. Consequently, planning and licensing of offshore routes is a complex and time consuming process with an uncertain result. For that reason, high capacity offshore collectors have been proposed. These should transmit the capacity of a number of offshore wind farms to shore via one single route. However, the required capacity of such a collective transmission line had to be MA and because of the technology limitations explained above, only DC concepts with their inherent disadvantages may be considered. Otherwise the transmission link will consist of numerous, parallel AC cables with little advantage compared to individual connections [9]. II. SIX PHASE, BIPOLAR AC SYSTEM The concept discussed here uses two conductors for each phase of the supplying AC system [7]. The adjacent conductors may be laid simultaneously e.g. using one vessel with two turntables. In case of limited cross sections these conductors can be integrated in one cable (similar to the Mǿllheroj-HDC-configuration). Each pair of conductors related to one phase are supplied with AC current of opposite polarity, e.g. with a phase angle of 8 (see Figure 4). The resulting six phase system may be considered as a bipolar conventional 3 phase AC system. Figure 4: configuration of the six single core submarine cables (source ABB) The voltages in the individual cables in Figure 4 can be described as: L = L ; L = L ; L3 = L3 With the two AC systems with opposite phase angle: L L3 L L3 a = e = a = a = a = a j L L L L The voltages of opposite polarity may be achieved by using a transformer with a tap at the middle of the secondary windings (Figure 5) or by connecting two transformers with anti-parallel windings (Figure 6). The latter are common practice in combination with power converters. At the adjacent end of the cable identical transformers are to be connected in the same manner. Figure 5: two single core cables supplied by the secondary windings of a transformer with middle tap (only one pair of cables shown) U -U
3 3 Trafo Trafo Yy Yy Yy6 Figure 6: six-phase bipolar cable system, supplied by two conventional AC transformers in Yy and Yy6 configuration y l Figure 7 shows the pair of cables L- and L-, buried close to each other. Obviously, the current I in the conductor of the first cable (L-) running to the load returns via the conductor of the second cable (L-). A single pair of cables according to Figure 7 represents a two phase AC system transmitting instantaneous power pulsating with twice the frequency of the connected power system. The instantaneous power of the resulting bipolar sixphase AC system, however, is constant and just equals the active power. With n representing the nominal voltage of the individual 3 phase system, the resulting transmitted power S according to Figure 6 is: S 3 I. = n III. COLLECTIE OFFSHORE TRANSMISSION CONCEPT The configuration being assessed below consists of the following elements (see Figure 7): - platforms with offshore substations of individual offshore wind farms (); - the collection platform (); - and the offshore transmission line to the connection point with the onshore grid (3). The concept uses the 4 k AC cable design proposed by Nexans with integrated return conductor []. For the assumed transmission capacity of MW a copper cross section of mm would be required. Compensation is applied at both ends of the transmission line only. Alternatively, the two DC concepts (voltage source converter SC using IGBTs and current source converter CSC using thyristor valves) may be considered. The distances y and l in Figure 7 are assumed being 7 km and km, respectively. Küste shoreline Figure 7: collective offshore bipolar AC transmission concept 3 A. Losses The weighted average losses of the alternatives have been assessed and are summarised in Table. The calculation of averages is based on typical conditions for offshore projects in the German economic zone [3], [4]. TABLE : AERAGE LOSSES OF 4 K BIPOLAR AC TRANSMISSION AND DC ALTERNATIES (ALL MW, KM) Loss category Cable: Dielectric oltage related Current related Converter (incl. HAC bipolar, 4 k, 6** mm transformer) Transformer oltage related Current related HDC SC, 3 k, 4*5 mm Average losses [MW] 3.9 *% 4 HDC CSC, 3 k, 4*5 mm 3.9 *.8% Compensation 5. Total The figures in Table indicate that the conversion losses associated with the DC concepts clearly exceed those of the bipolar AC concept. Figure 8 generalizes these findings for varying distances. The figure indicates that the DC technologies are superior to the bipolar AC concept from a loss perspective only for distances above 35 5 km.
4 4 P 5 MW 4 3 HDC light SC HDC classic CSC HAC m. ZK K Mio. 5 5 HDC light SC HAC m. ZK HDC classic CSC km ( km 5) y (l) Figure 8: average losses for offshore transmission technologies as function of distance (dashed line for HAC bipolar: including compensation at platform half way) The net present value of the losses over a years period (assumed interest of 5%, average revenue of 7 /MWh) is estimated to be about M. The values for the AC, HDC SC and HDC CSC alternatives are 34 M and 9 M B. Cost implications For an economic comparison of the options not only the net present value of the losses but also the investment costs need to be considered. By nature, it is difficult to acquire representative data on component prices and implementation costs [6]. Hence, the outcomes show a significant uncertainty and the comparison is indicatively only, though still allowing conclusions. The (SC) DC options may become competitive for offshore distances above km. Still, the number of project being planned so far from shore in Europe is quite limited, at least in the current stage of development. Those remote projects are faced to significant additional risks (accessibility) and technology challenges (e.g. water depth). From the financing perspective also technology risks related to the transmission concept itself have to be taken into account. From that perspective the AC concept clearly offers advantages as it relies exclusively on components and technologies proven in decades of industrial operation. For the DC concepts performance at the required scale and under offshore conditions still has to be demonstrated. The manner, how those additional risks are valued by investors should not be underestimated km (7 9 3 km 5) y (l) Figure 9: comparison of transmission options with respect to costs (investments plus net present value of transmission losses) depending on distance to shore I. SUMMARY AND OUTLOOK The proposed transmission system uses six single core cables connected to two conventional AC systems with opposite polarity. Those six-phase bipolar AC systems offer the opportunity to lay one pair of cables simultaneously in one trench. Because the sum of the currents in one pair of cables is zero, the resulting magnetic field is negligible and, hence, the three pairs of cables are magnetically decoupled. This concept allows usage of maximum voltages and conductor cross sections. This results in substantially enhanced capacities for offshore AC connections. The losses of the proposed configuration will be significantly lower than those associated with conventional AC submarine cables [6] or alternative DC technologies. The extra effort is limited. On the one hand, an additional or modified transformer is required on both ends of the cable. On the other hand, compared to conventional configurations, the amount of compensation capacity required doubles. As with conventional single core cables, three trenches are required, each for a one pair of cables, and the distance between the trenches has to be approximately the water depth. Of course, the construction effort and time are significantly higher than in the case of a single three core AC cables. However, both configurations are hardly comparable because of their dramatically differing capacity. At a distance of several kilometers the armourings of a pair of cables have to be connected electrically, in order to allow the capacitive and dielectric currents compensating each other. In this way, these currents do not run via the lead shield. For the connection of the shields, pre-fabricated joints for corrosions protection can be used.
5 5 The extra effort is justified by the following benefits: The proposed AC concept allows using single core cables, with the associated possibilities to apply highest, technically feasible voltages (> 5k) and conductor cross sections. Respective cable technologies are proven and rely on conventional designs. The option of offshore collectors may become technically and economically feasible and would be based on conventional, commercial and reliable HAC components. The AC option seems to be superior to alternative DC concepts from an efficiency as well as from a cost perspective. Further analysis of costs and cost trends is recommended in order to reduce uncertainties in this respect. Magnetic fields along the cable route are negligible because of the vicinity of the conductors. Compasses and other instrumentation of ships are not affected and impact on marine flora and fauna is extremely unlikely. Of course, there is a variety of open questions. All collective connection options imply co-ordinated planning of projects, synchronisation of timing, possible early investments and, hence, the risk of stranded investments. From that perspective, they will require a supportive regulative and policy framework. Otherwise the barriers for implementation, in particular from the perspective of individual project developers may be prohibitive. On the other hand, collective connections in the GW range require strong nodes where connecting with the onshore networks. This may restrict application in certain areas or, on the other hand, may require strategic planning and development of the onshore transmission network. Planning implications as well as the potential synergies may even have dimension affecting neighbouring control areas and, hence, requires a European scope. The implications of strong connections for design and system operation need to be analysed more in detail, in particular in the light of security of supply standards. As the dynamic characteristics of the technology options clearly differ, also aspects fault response and dynamic stability have to be analysed more in detail. Additionally, the benefits of collective connections may be related to completely different aspects than their costs and drawbacks, e.g. reduced spatial requirements for offshore cable routes versus investment risks and energy market regulation. The question how to balance these different aspects and to derive balanced regulative framework conditions is a challenge for policy makers.. REFERENCES [] G.E. Balog e.a, Energy transmission on long three core/three foil XLPE power cables,jicable 3 [] D. Wensky, Gleichstrom-Netzanbindung großer Offshore-Windparksew (5) H. 9, S [3] AREA, Überlegene elektrische Lösungen für den Windenergiemarkt [4] H. Brakelmann, F. Richert, Bemessung der Energiekabel zur Netzanbindung von Offshore-Windfarmen, ew 4, H.4, S [5] H. Brakelmann, F. Richert, Bemessung der Landkabel für die Netzanbindung von Windfarmenerscheint im Bulletin des SE (5) [6] H. Brakelmann, Drehstrom-Netzanbindung großer Offshore-Windparks Wirkungsgrade und Grenzen, H. WIND-KRAFT Journal () H. 5, S [7] H. Brakelmann, K. Burges, M. Jensen and T. Schütte: Bipolar transmission systems with XLPE HAC submarine cables, 6. Int. Workshop on Large Scale Integration of Wind Power and Transmission Networks for Offshore Windfarms, October 6, Delft, pp [8] B.R. Oswald, ergleichende Studie zu Stromübertragungstechniken im Höchstspannungsnetz, FORWIND-Studie, 5, [9] Econnect Study on the Development of the offshore grid for Connection of the Round Two Wind Farms, Department of Industry and Trade, London, January 5 [] Schütte, Th.; Ström, M; Gustavsson, B.: Erzeugung und Übertragung von Windenergie mittels Sonderfrequenz. In: Elektrische Bahnen /, S , mit Berichtigung in Elektrische Bahnen -/, S. 74. [] Brakelmann, H. Steinbrich, K.: Frequenzreduzierte Energieübertragung und -verteilung mit Kabeln, Bull. SE () H., S [] Jensen, M.: Konzepte zum projektübergreifenden Anschluss großer Offshore-Windparks an das Übertragungsnetz, Dena-Kongreß, Berlin, May 5 [3] Offshore Forum Windenergie: orschlag zu einem Offshore-Grid in der Nordsee, March 7 [4] Brakelmann, H.: Bipolare HAC- und HDC-Hochleistungs- Übertragungssysteme mit PE-isolierten See- und Landkabeln, Energiewirtschaftliche Tagesfragen, (to be published, June 6)
HVDC Light Cables. Submarine and land power cables
HV Light Cables Submarine and land s The HV Light s to offshore platform The light and robust HV Light s can be laid with very cost effecient methods HV Light System HV Light is a transmission system in
POWER TRANSMISSION FROM OFFSHORE WIND FARMS
POWER TRNSMISSION FROM OFFSHORE WIND FRMS Thorsten Völker University of pplied Sciences Bremerhaven Germany BSTRCT The future for wind power generation in Germany is offshore wind energy. The preferred
Brochure Introducing HVDC
Brochure Introducing HVDC ABB and HVDC The world s first commercial high-voltage direct current (HVDC) link, situated between the Swedish mainland and the island Gotland, was delivered by ABB already in
HV Submarine Cable Systems Design, Testing and Installation
HV Submarine Cable Systems Design, Testing and Installation CIGRE Ireland Technical Seminar 6 th October 2010 Robert Donaghy Senior Consultant Engineer, ESB International Presentation Overview Applications
E-Highway2050 WP3 workshop April 15 th, 2014 Brussels
E-Highway2050 WP3 workshop April 15 th, 2014 Brussels High voltage underground and subsea cable technology options for future transmission in Europe Ernesto Zaccone, Chairman Europacable High Voltage Systems
Power System for Offshore Wind Power
Wind-Kraft Journal. German Offshore. 1. Auflage 2008. S. 2-3 und Wind-Kraft Journal. German Offshore. 5. Auflage 2008. S. 38-39. Outlook in the future of German North Sea 2020 ower System for Offshore
HVDC Technology for Large Scale Offshore Wind Connections
HVDC Technology for Large Scale Offshore Wind Connections Nandan Mahimkar, Gunnar Persson,Claes Westerlind, ABB AB, SE-771 80, Ludvika, Sweden, [email protected], [email protected],[email protected],
Network Interconnection of Offshore Wind
Network Interconnection of Offshore Wind Prepared for REOLTEC Carlos Aguirre Madrid, December 3rd Experience you can trust. Introducing KEMA A trusted independent partner providing advise throughout the
Offshore Wind China 2010 Bergen, 15th March 2010. Olivier Angoulevant Nexans Norway AS
Offshore Wind China 2010 Bergen, 15th March 2010 Olivier Angoulevant Nexans Norway AS At the core of performance At the core of performance : a worldwide leader Worldwide leader in cables, cabling systems
Product brochure Multi Functional Switchgear PASS M00 72.5 kv Flexible and compact switchgear solutions for windfarms
Product brochure Multi Functional Switchgear PASS M00 72.5 kv Flexible and compact switchgear solutions for windfarms The future of Wind Farms As offshore wind farms move towards deploying higher capacity
Optimization of the coupled grid connection of offshore wind farms
Optimization of the coupled grid connection of offshore wind farms Dirk Schoenmakers Graduation project at Evelop Netherlands BV Technical University of Eindhoven September 2008 Supervisors: TU Eindhoven
AMSC s Superconductor Cable Technologies for Electric Utilities
International Workshop 2014 AMSC s Superconductor Cable Technologies for Electric Utilities Michael Ross, P.E. Managing Director of Superconductor Power Systems AMSC Corporate Facts Headquartered in MA,
factsheet High Voltage Direct Current electricity technical information
factsheet High Voltage Direct Current electricity technical information Introduction High voltage direct current (HVDC) technology is one of the technical options National Grid can consider for the future
Submarine Power Cables. State-of-the-art production facility, more than 100 years of experience and reference installations around the world.
Submarine Power Cables State-of-the-art production facility, more than 100 years of experience and reference installations around the world. Reliable submarine power cables ABB is one of the world s most
Magnus Callavik, ABB Power Systems, HVDC, 721 64 Västerås, Sweden Phone: +46(0)21323226. e-mail: [email protected]
HVDC GRIDS FOR OFFSHORE AND ONSHORE TRANSMISSION Magnus Callavik, ABB Power Systems, HVDC, 721 64 Västerås, Sweden Phone: +46(0)21323226. e-mail: [email protected] SUMMARY The objective with this
Cost Benefit Methodology for Optimal Design of Offshore Transmission Systems
Centre for Sustainable Electricity and Distributed Generation Cost Benefit Methodology for Optimal Design of Offshore Transmission Systems Predrag Djapic and Goran Strbac July 2008 FUNDED BY BERR URN 08/1144
Cable Consulting International
Cable Consulting International Brian Gregory BSc, CEng, MIEEE, FIEE Technical Director www.cableconsulting.net Alan Williams BSc, CEng, MIEE Senior Consultant 1 FEASIBILITY STUDY for 500 kv AC UNDERGROUND
QUALITY CONTROL Prepared: V. van Gastel / team TenneT Reviewed: M. Müller 23.06.2015 Approved: F. Wester 23.06.2015 1. BACKGROUND MATERIAL...
POSITION PAPER STAKE HOLDER CONSULTATION PROCESS OFFSHORE GRID NL Type: Position paper Work stream Technical Topic: T.2 Number of J-Tubes Filename ONL 15-060-T2_ J tubes_ bays_pp_v2 Version 3 - Public
Polish Offshore Grid SA
OFFSHORE GRID DEVELOPMENT 1 Offshore wind farm development in selected European countries Country Installed capacity by the end of 2010 [MW] Approved projects [MW] 2020 targets [MW] UK 1.341 2.591 13.000
HVDC Light, a tool for electric power transmission to distant loads
Presented at VI Sepope Conference, Salvador, Brazil, May 1998 HVDC Light, a tool for electric power transmission to distant loads by Gunnar Asplund Kjell Eriksson* Ove Tollerz ABB Power Systems AB ABB
factsheet High Voltage Direct Current Electricity technical information
factsheet High Voltage Direct Current Electricity technical information Introduction High voltage direct current (HVDC) technology is one of the technical options National Grid can consider for the future
2012 San Francisco Colloquium
2012 San Francisco Colloquium http : //www.cigre.org HVDC and Power Electronic Systems for Overhead Line and Insulated Cable Applications B4-8 Trans Bay Cable A Breakthrough of VSC Multilevel Converters
NSW Submarine Power. Cables for the future, delivered today.
Submarine Power. Cables for the future, delivered today. NorddeutSChe Seekabelwerke GmbH () for Renewable Energies The submarine competence center within the General Cable Group After was founded in by
PB POWER ISLAND OF IRELAND CAVAN-TYRONE AND MEATH-CAVAN 400KV PROJECTS PRELIMINARY BRIEFING NOTE OVERHEAD AND UNDERGROUND ENERGY TRANSMISSION OPTIONS
ISLAND OF IRELAND CAVAN-TYRONE AND MEATH-CAVAN 400KV PROJECTS PRELIMINARY BRIEFING NOTE OVERHEAD AND UNDERGROUND ENERGY TRANSMISSION OPTIONS FEBRUARY 2008 PB POWER PB Power Page i EXECUTIVE SUMMARY General
Overview of the 500MW EirGrid East-West Interconnector, considering System Design and Execution-Phase Issues
Overview of the 500MW EirGrid East-West Interconnector, considering System Design and Execution-Phase Issues J Egan, P O Rourke EirGrid Plc, Republic of Ireland [email protected] paul.o [email protected]
NSW Submarine Power. Cables for the future, delivered today
NSW Submarine Power Cables for the future, delivered today NORDDEUTSCHE SEEKABELWERKE GMBH (NSW) The submarine competence center within the General Cable Group After NSW was founded in 1899 by Felten &
6 ELECTRICAL PARAMETERS
6 ELECTRICAL PARAMETERS For power, low voltage and medium voltage cables, cross section nominal areas are calculated in taking into account several parameters as: permissible current carrying capacities
Summary of Electric Transmission Assessment Report
Summary of Electric Transmission Assessment Report January 2010 Assessment and Analysis of the State-Of-the-Art High-Voltage Electric Transmission Systems with Specific Focus on High-Voltage Direct Current
HVDC-VSC: transmission technology of the future
A bi-pole ± 285 kv HVDC line sandwiched between 3-phase 400 kv HVAC lines. HVDC-VSC: transmission technology of the future A new hybrid HVDC circuit technology using voltage source converters is only half
Topics. HVDC Fundamentals
Topics HVDC Fundamentals Conventional Converters Capacitor Commutated Converters Voltage Source Converters Reactive Power Requirements System Configurations Tapping Control basics High Power Transmission
OFFSHORE WIND FARM ELECTRICAL CONNECTION OPTIONS. W.Grainger 1 and N.Jenkins 2 SYNOPSIS
OFFSHORE WIND FARM ELECTRICAL CONNECTION OPTIONS W.Grainger 1 and N.Jenkins 2 1 Border Wind Ltd, Hexham 2 Dept of Electrical Engineering and Electronics, UMIST SYNOPSIS The development of large scale offshore
Offshore Platform Powered With New Electrical Motor Drive System
Offshore Platform Powered With New Electrical Motor Drive System Authors: Jan O. Lamell, M.Sc E.E. ABB Automation Technologies Presenters: Thomas Johansson, M.Sc E.E. ABB Automation Technologies Timothy
Requirements for Offshore Grid Connections. in the. Grid of TenneT TSO GmbH
Requirements for Offshore Grid Connections in the Grid of TenneT TSO GmbH Bernecker Straße 70, 95448 Bayreuth Updated: 21 December 2012 1/10 Requirements for Offshore Grid Connections in the Grid of TenneT
Offshore Wind. IEEE Boston PES - November 16, 2010
Offshore Wind IEEE Boston PES - November 16, 2010 Offshore Wind A high-level overview of offshore wind project development identifying current technologies, challenges, risks and costs. Presented by: Brook
EDS 02-0027 11KV TRIPLEX CABLE
THIS IS AN UNCONTROLLED DOCUMENT, THE READER MUST CONFIRM ITS VALIDITY BEFORE USE Document Number: EDS 02-0027 ENGINEERING DESIGN STANDARD EDS 02-0027 11KV TRIPLEX CABLE Network(s): EPN, LPN, SPN Summary:
STENSEA. Stored Energy in Sea. The Feasibility of an Underwater Pumped Hydro Storage System. Dr. Andreas Garg Christoph Lay Robert Füllmann
STENSEA Stored Energy in Sea The Feasibility of an Underwater Pumped Hydro Storage System Presentation IRES, 12 November 2012 Dr. Andreas Garg Christoph Lay Robert Füllmann 1 Market Status Quo and Forecasts
CO-ORDINATION OF PARALLEL AC-DC SYSTEMS FOR OPTIMUM PERFORMANCE
CO-ORDINATION OF PARALLEL AC-DC SYSTEMS FOR OPTIMUM PERFORMANCE Ana Diez Castro & Rickard Ellström Ying Jiang Häfner Christer Liljegren Vattenfall Utveckling AB ABB Power Systems Gotlands Energiverk AB
TRANSMISSION OPTIONS FOR OFFSHORE WIND FARMS IN THE UNITED STATES
TRANSMISSION OPTIONS FOR OFFSHORE WIND FARMS IN THE UNITED STATES Sally D. Wright, PE Anthony L. Rogers, Ph.D. James F. Manwell, Ph.D. Anthony Ellis, M.S. Renewable Energy Research Lab University of Massachusetts
An Introduction to High Voltage Direct Current (HVDC) Underground Cables
Page 1 An Introduction to High Voltage Direct Current (HVDC) Underground Cables Brussels, 10 October 2011 An Introduction to High Voltage Direct Current (HVDC) Underground Cables Page 2 Table of content
Recent Siemens HVDC Activities Yuriy Kazachkov Siemens PTI
IEEE PES 2008 HVDC & FACTS Subcommittee Recent Siemens HVDC Activities Yuriy Kazachkov Siemens PTI 660MW 500kV in operation since July 2007 Commercial Operation Neptune RTS Costumer Project Name Location
Electrical Considerations for HVDC Transmission Lines. Joe Mooney, PE
Electrical Considerations for HVDC Transmission Lines Joe Mooney, PE POWER Engineers has met the standards and requirements of the Registered Continuing Education Program. Credit earned on completion of
Network Standard Advice No. 1420C 9/6/2011
Network Standard Advice No. 1420C 9/6/2011 TO: Customers, Service Providers and Ausgrid Staff. Advisory Note on Changes to the Use of 11kV Cable Types. Introduction This Network Standard Advice (NSA) provides
Curriculum Vitae Fredrik Rüter 1 December 2014
Name RÜTER Fredrik Date of Birth 8 May 1960 Nationality Position Languages Coordinates Swedish Senior Consultant Swedish: mother tongue English: fluent (business, conversation, reading, writing) German,
Offshore wind farm electrical engineering (when considering the operation of array cabling at voltages of 66kV)
Offshore wind farm electrical engineering (when considering the operation of array cabling at voltages of 66kV) 29 th January 2015 Lyndon Greedy / Hans Cleijne 1 SAFER, SMARTER, GREENER DNV GL Renewables
CHAPTER VIII LINE PLANT SYSTEM COMMUNICATION THROUGH RE CABLE
CHAPTER VIII LINE PLANT SYSTEM COMMUNICATION THROUGH RE CABLE 8.1 SYSTEM 8.1.1 Armoured, screened underground cables are used for control communication in electrified areas to limit induction effect. 8.2
SUPERCONDUCTING CABLE SYSTEMS
SUPERCONDUCTING CABLE SYSTEMS INTRODUCTION An aging and inadequate power grid is widely seen as one of the greatest obstacles to the restructuring of power markets in the United States, Europe and elsewhere.
Viking Link Interconnector
Viking Link Interconnector Public information event for Bicker Parish Why we re here today We re here today to introduce the Viking Link project, to explain what we want to build and to answer any questions
GroundRod AC Substation Earthing Tutorial
1 GroundRod AC Substation Earthing Tutorial 1. Functions of an earthing system The two primary functions of a safe earthing system are: To ensure that a person who is in the vicinity of earthed facilities
Qualitative Analysis of Power Distribution Configurations for Data Centers
Qualitative Analysis of Power Distribution Configurations for Data Centers White Paper #4 2007 The Green Grid. All rights reserved. No part of this publication may be used, reproduced, photocopied, transmitted,
2012 San Francisco Colloquium
2012 San Francisco Colloquium http : //www.cigre.org Advances in voltage source converter (VSC) technologies B4-6 500 kv VSC Transmission System for lines and cables B. JACOBSON, B. WESTMAN, M. P. BAHRMAN*
Contactless Power Transfer : Inductive charging of EV
Contactless Power Transfer : Inductive charging of EV 7-12-2010 P.Bauer Delft University of Technology Challenge the future EV have to be charged December 7, 2010 2 2 Chicken and egg problem December 7,
Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment
Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment March 20, 2009 Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment Table of Contents:
Feasibility Study of Deep Water Power Cable Systems. Enrico Colombo CESI S.p.A
Feasibility Study of Deep Water Power Cable Systems Enrico Colombo CESI S.p.A Layout of Presentation The Study Context, Objectives, Participants Study Approach & Methodology Assessments and Findings Implementation
Cost Benefit Methodology for Optimal Design of Offshore Transmission Systems
DTI Centre for Distributed Generation and Sustainable Electrical Energy Cost Benefit Methodology for Optimal Design of Offshore Transmission Systems Predrag Djapic and Goran Strbac Annex 25: Grid Integration
Respecting the environment
MAIN FEATURE CHAPTER I RESEARCH WITH AN EYE ON THE FUTURE Respecting the environment Low power losses and a lesser visual impact on the landscape make Gas-Insulated Lines (GIL) a very environmentally friendly
Voltage Source HVDC Overview Mike Barnes Tony Beddard
Voltage Source HVDC Overview Mike Barnes Tony Beddard Note: This is a version with images removed which have copyrighted other than from the University of Manchester, for web publication. Should a conference
Turnkey cable solutions to better deploy your windfarm infrastructure
Turnkey cable solutions to better deploy your windfarm infrastructure expertise supports your network s evolution Both on land and offshore, Nexans has the expertise to interconnect large wind turbines
How To Monitor Water Penetration In A Cable Screen
Detection and location of high voltage cable sheath damage with Water Penetration Monitoring*) Purpose of Monitoring System The expected lifetime of high voltage underground cables is more than 40 years,
Edmund Li. Where is defined as the mutual inductance between and and has the SI units of Henries (H).
INDUCTANCE MUTUAL INDUCTANCE If we consider two neighbouring closed loops and with bounding surfaces respectively then a current through will create a magnetic field which will link with as the flux passes
Oahu Wind Integration and Transmission Study (OWITS) Hawaiian Islands Transmission Interconnection Project
Oahu Wind Integration and Transmission Study (OWITS) Hawaiian Islands Transmission Interconnection Project Dennis Woodford Electranix Corporation Winnipeg, Manitoba Canada NREL is a national laboratory
Offshore Work Packages
Rampion Offshore Wind Farm Offshore Work Packages Meet The Buyer Naren Mistry, Engineering Manager 26 th Feb 2014 Rampion Offshore Project Scope Design, manufacture, transportation and Installation: Up
WHITEPAPER. Cable and Connector for Hiperface dsl motor drive applications
WHITEPAPER Cable and Connector for Hiperface dsl motor drive applications information for cable manufacturers Version 02 Content Information for cable manufacturers...3 Communication...3 Crosstalk & shielding...3
Comparison of GIS and AIS systems for urban supply networks
Comparison of GIS and AIS systems for urban supply networks Studies carried out by ABB show that for urban supply networks the combination of HV gas-insulated switchgear (GIS) and HV cable has important
Medium-voltage cables for reliable windpark infrastructure
Medium-voltage cables for reliable windpark infrastructure exans, worldwide leader in cables and cabling systems As a global expert in cables and cabling systems, Nexans brings an extensive range of advanced
NSW Submarine Telecom Systems. Turnkey solutions for the future, delivered today.
Submarine Telecom Systems. Turnkey solutions for the future, delivered today. Norddeutsche Seekabelwerke GmbH () The submarine competence center within the General Cable Group After was founded in 1899
HIGH-CAPACITY HIGH TEMPERATURE SUPERCONDUCTING POWER CABLES
HIGH-CAPACITY HIGH TEMPERATURE SUPERCONDUCTING POWER CABLES Jean-Maxime SAUGRAIN NEXANS Corporate VP Technical IASS Workshop Postdam May 13, 2011 Rationale High-capacity High Temperature Superconducting
The electrical energy produced at the gen
300 300 Principles of Power System CHAPTER CHAPTER 12 Distribution Systems General 12.1 Distribution System 12.2 Classification of Distribution Systems 12.3 A.C. Distribution 12.4 D.C. Distribution 12.5
Grid connection of near shore wind farms
Grid connection of near shore wind farms methods, preconditions and results Rene Starup 5. Marts 2015 1 Topics Methods Preconditions Technical and socio-economic analysis 5. Marts 2015 2 60, 150 and 400
G019.A (4/99) UNDERSTANDING COMMON MODE NOISE
UNDERSTANDING COMMON MODE NOISE PAGE 2 OF 7 TABLE OF CONTENTS 1 INTRODUCTION 2 DIFFERENTIAL MODE AND COMMON MODE SIGNALS 2.1 Differential Mode signals 2.2 Common Mode signals 3 DIFFERENTIAL AND COMMON
EFFICIENT ELECTRICAL ENERGY TRANSMISSION AND DISTRIBUTION INTERNATIONAL ELECTROTECHNICAL COMMISSION
EFFICIENT ELECTRICAL ENERGY TRANSMISSION AND DISTRIBUTION INTERNATIONAL ELECTROTECHNICAL COMMISSION EFFICIENT ELECTRICAL ENERGY TRANSMISSION AND DISTRIBUTION 1 EFFICIENT ELECTRICAL ENERGY TRANSMISSION
Electrical Collection and Transmission Systems for Offshore Wind Power
National Renewable Energy Laboratory Innovation for Our Energy Future A national laboratory of the U.S. Department of Energy Office of Energy Efficiency & Renewable Energy Electrical Collection and Transmission
Fundamentals of Modern Electrical Substations Part 1: Mission of Electrical Substations and their Main Components
Fundamentals of Modern Electrical Substations Part 1: Mission of Electrical Substations and their Main Components Course No: E02-010 Credit: 2 PDH Boris Shvartsberg, Ph.D., P.E., P.M.P. Continuing Education
Power Voltage Transformers for Air Insulated Substations. THE PROVEN POWER.
Power Voltage Transformers for Air Insulated Substations THE PROVEN POWER. Introduction Trench Power Voltage Transformers (Power VTs) combine the attributes of an inductive voltage transformer with the
environment briefing02
PRODUCED BY THE SAFETY, HEALTH & ENVIRONMENT GROUP OF THE ENERGY NETWORKS ASSOCIATION - JULY 2006 environment briefing02 transporting electricity Overhead Lines or Underground Cables? Introduction The
Planar versus conventional transformer
Planar versus conventional transformer Majid Dadafshar, Principal Engineer Gerard Healy, Field Application Engineer Pulse, a Technitrol Company Power Division Usually the first step on any power supply
FACTS. Solutions to optimise network performance GRID
Solutions to optimise network performance GRID Solutions to optimise your network Our worldwide presence: Better solutions for your network all around the world Tampere Philadelphia Stafford Konstanz Beijing
Cable Solutions for Servo and Variable Frequency Drives (VFD)
Cable Solutions for Servo and Variable Frequency Drives (VFD) Electric drive systems with continuous torque and speed control are widespread today. They allow an optimal adjustment of the drive with respect
Estimation of electrical losses in Network Rail Electrification Systems
Estimation of electrical losses in Network Rail Electrification Systems Page 1 of 16 Contents 1. BACKGROUND...3 2. PURPOSE...3 3. SCOPE...3 4. DEFINITIONS & ABBREVIATIONS...4 5. NETWORK RAIL INFRASTRUCTURE
Nordex SE. Nordex goes Offshore
Nordex SE Nordex goes Offshore Hannover, April 2011 Content 1. Offshore Wind Market 2. Nordex Offshore History & Future 3. Competition & Technical Development 4. The N150/6000 2 Strong growth prospects
Survey of Offshore Wind Farm Project in EU and Their Connecting Grid Systems
Survey of Offshore Wind Farm Project in EU and Their Connecting Grid Systems July 2012 Brieuc Hamon Research Associate, Global Energy Network Institute (GENI) [email protected] Under the supervision
WIND TURBINE TECHNOLOGY
Module 2.2-2 WIND TURBINE TECHNOLOGY Electrical System Gerhard J. Gerdes Workshop on Renewable Energies November 14-25, 2005 Nadi, Republic of the Fiji Islands Contents Module 2.2 Types of generator systems
SingleNet Single Cable Control System
Single Cable Control System Economical, Reliable and Expandable Two-Wire Single Cable System DRIP/MICRO IRRIGATION PRODUCTS Single Cable Control System System Manager or Irrigation Controller Controls
SICK AG WHITEPAPER. Information for cable manufacturers Note-2_03
SICK AG WHITEPAPER Cable and connector for HIPERFACE DSL motor drive applications Information for cable manufacturers Note-2_03 Juergen Funkhaenel Application Engineer at SICK STEGMANN GmbH Donaueschingen
Konti Skan Replacement of Cable 1
Konti Skan Replacement of Cable 1 Presentation of the project 1 Agenda Background for the project Scope of Work for the cable delivery Eletrical Requirements Type Test Route description Time Schedule 2
Low Frequency AC Transmission System
, pp. 315-326 http://dx.doi.org/10.14257/ijsip.2015.8.5.32 Low Frequency AC Transmission System G. Sirisha Kumari 1 and K.Veerendranath 2 1 M. Tech student in EEE Department 2 Asst. Professor in EEE Department
Introduction to The Trans Bay Cable Project
Introduction to The Trans Bay Cable Project We ve come a long way 1 But thanks to the advances of two men and 2 The Battle of Currents 3 Utilities are able to choose the most effective and efficient means
Experience in transporting energy through subsea power cables: The case of Iceland
Experience in transporting energy through subsea power cables: The case of Iceland Svandís Hlín Karlsdóttir Faculty of Industrial Engineering, Mechanical Engineering and Computer Science University of
Project description. Power Electronics for Reliable and Energy efficient Renewable Energy Systems
Project description Title: Power Electronics for Reliable and Energy efficient Renewable Energy Systems OBJECTIVES Principal objective Provide competence and decision basis for enabling reliable and energy
Study to Determine the Limit of Integrating Intermittent Renewable (wind and solar) Resources onto Pakistan's National Grid
Pakistan Study to Determine the Limit of Integrating Intermittent Renewable (wind and solar) Resources onto Pakistan's National Grid Final Report: Executive Summary - November 2015 for USAID Energy Policy
Top Drive Service Loops. Conventional, Enhanced and Superior Solutions for Drilling Applications
Top Drive Service Loops Conventional, Enhanced and Superior Solutions for Drilling Applications Linking the future As the worldwide leader in the cable industry, Prysmian Group believes in the effective,
London Array Off-Shore Wind Farm
London Array Off-Shore Wind Farm 1 Jamie R Mathlin Construction Manager Off-Shore Sub-Stations Project Commissioning Manager 27 Years Experience in the Power Industry Grid Trained Electrical Engineer 10
Transmissão em Corrente Contínua
Transmissão em Corrente Contínua Panorama Atual e Perspectivas Futuras no Brasil Multi-Terminal HVDC Classic Some Considerations Brazilian SC B4 Paulo Fischer de Toledo, ABB Basic considerations Traditional
Power transformers. Special transformers Railway
Power transformers Special transformers Railway A leader in railway systems Our compact and low-weight transformers fully comply with the customer s specifications. The products are developed together
Dynamic Reactive Compensation MV STATCOM
PCS 6000 Leaflet Dynamic Reactive Compensation MV STATCOM Providing stability, security, and reliability to the grid. Installing a STATCOM at one or more suitable points on the network is a powerful and
SIMULATING HYBRID ENERGY GRIDS IN SMART CITIES FOCUS ON ELECTRIC ENERGY SYSTEMS
Sawsan Henein AIT Austrian Institute of Technology Electric Energy Systems Research Group SIMULATING HYBRID ENERGY GRIDS IN SMART CITIES FOCUS ON ELECTRIC ENERGY SYSTEMS Sustainable Places 2015 Savona,
