SULLIVAN COUNTY JAIL PROJECT JANUARY 21, 2016



Similar documents
Sullivan County Jail: Cost Analysis of Boarding Out vs. Building New

Guideline for Construction Reimbursement Rates (a) 7. Educational Facility Site, Construction, and Reimbursement

REQUEST FOR QUALIFICATIONS PLANNING, DESIGN AND CONSTRUCTION ARCHITECTURAL SERVICES FOR THE NEW COUNTY DETENTION CENTER

SCHEMATIC DESIGN PRESENTATION ACTON ELEMENTARY SCHOOL

Analysis One Code Desc. Transaction Amount. Fiscal Period

NEW YORK STATE OFFICE OF PARKS, RECREATION AND HISTORIC PRESERVATION HISTORIC HOMEOWNERSHIP REHABILITATION TAX CREDIT APPLICATION: PART 1

ISSUE BRIEF. Understanding the Hospital Planning, Design, and Construction Process. Introduction. Background. Phase 1: Project Definition and Planning

REQUEST FOR PROPOSALS

RADGOV, Inc West Cypress Creek Road, Suite 415, Ft. Lauderdale, FL Tel: (954) Fax: (954)

County of Los Angeles Consolidated Correctional Treatment Facilities June 09, 2015

REQUEST FOR BOARD ACTION HENDERSON COUNTY BOARD OF COMMISSIONERS. ATTACHMENTS: 1. Construction Management Update

Review of Janitorial Services Contract at the Fort Lauderdale-Hollywood International Airport (RLI # AV-2)

Indicators for Florida School District Best Financial Management Practices

New York State Office and Historic Homeownership Rehabilitation Tax Credit

TULSA COUNTY CRIMINAL JUSTICE AUTHORITY

How To Tax Property In Denton

COUNTY OF OSWEGO INFRASTRUCTURE, FACILITIES AND TECHNOLOGY COMMITTEE

Request for Proposal East Tower Nursing Unit and Infrastructure Upgrade Grossmont Hospital

Program: Facilities and Construction Management. Program Based Budget Facilities and Construction Management. Page 81

How To Get A Drug Sentence In New York

Division of Criminal Justice Services Office of Justice Research and Performance Drug Law Reform Preliminary Update on Early Implementation

DCAS Commissioner Edna Wells Handy. Inside This Issue: Citywide Shared Services

Yamhill County Personnel Monthly Salaries

BOROUGH OF HADDONFIELD CAMDEN COUNTY NEW JERSEY ARCHITECTURAL SERVICES RELATED TO THE HADDONFIELD LIBRARY REQUEST FOR PROPOSAL

OCI ASSOCIATES OVERVIEW

5-Minute Primer for Commercial Building Energy Audits

SCHEMATIC DESIGN PRESENTATION NEW JOSHUA MIDDLE SCHOOL

ITEM QUANTITY UNIT UNIT AMOUNT UNIT AMOUNT AMOUNT

Capital Projects Town Hall Meeting

LIVE BETTER. LIVE GREEN.

BOND MEASURE E CONTRACTOR OUTREACH

DAVIESS COUNTY SCHOOLS DISTRICT FACILITIES PLAN

228 S. Mariposa Ave. Los Angeles, CA 90004

This Request for Proposal consists of providing the Phone System and Phones for Philadelphia Works.

How To Plan A School District

CITY OF BAYTOWN Building Inspections

BCOE Payroll Calendar. Monday Tuesday Wednesday Thursday Friday Jun Jul Full Force Calc

Request for Qualifications

Homewyse 2010 Home Ownership Cost Report

REQUEST FOR PROPOSAL MECHANICAL, ELECTRICAL, PLUMBING ENGINEERING SERVICES VARIOUS BUILDING RENOVATIONS AND NEW CONSTRUCTION

SANTA CLARA COUNTY REENTRY SERVICES SEAMLESS SYSTEM OF SERVICES, SUPPORT AND SUPERVISION Ready to Change: Promoting Safety and Health for the Whole

LAUREA MAGISTRALE - CURRICULUM IN INTERNATIONAL MANAGEMENT, LEGISLATION AND SOCIETY. 1st TERM (14 SEPT - 27 NOV)

MONTGOMERY COLLEGE JOB CLASS SPECIFICATION

Request for Proposal for Construction Management Services

4. Q: Is there a walkthrough for this procurement? A: No, there will not be a walkthrough for this procurement.

CORPORATE OVERVIEW. Our Mission and Our Name

Schematic Design: Quality Management Phase Checklist Project Phase Checklist Series

HAZELWOOD HIGH SCHOOLS SCHEMATIC DESIGN PRESENTATION

9/19/2014. Facility Design with the Patients at the Center. Learning Objectives: A remarkable project

Scituate Public Facilities Master Plan Final Report to the Board of Selectmen

31289 ADOPTED BOARD OF TRUSTEES COMMUNITY COLLEGE DISTRICT NO. 508 JANUARY, , 2012

MINIMUM REQUIREMENTS FOR TENNESSEE MOTOR VEHICLE DEALER LICENSE

Estimated Cost of Repair

Tax Year 2015 Personal Exemptions and Deductions

Guidelines for Determining Architect/Engineer Fees for Public Works Building Projects (effective July 1, 2015)

State of Louisiana Residential Rehabilitation Tax Credit RS 47: Program Guidance

Court Security. FACT SHEET April Court Security. Page 1 of 7

Website. King County Council District # WA State Legislative District # Date Incorporated. Federal Tax ID. WA State UBI#

Records: Cubic ft.: 25 No. of Items: 53 vols., 5 boxes, and 60 reels of microfilm

Schematic Design Presentation S. Dallas Dance, Superintendent October 22, 2013 OVERLEA HIGH SCHOOL

20-Year Statute of Limitations on the Time to Collect State Tax Liabilities

Maplewood at Cheshire County, Westmoreland, NH CONCEPTUAL PLANS AND COST ESTIMATES Request for Proposals. Design and Engineering

Capital One Financial Data Center

AT&T Global Network Client for Windows Product Support Matrix January 29, 2015

RFP ALTERNATE #1 SECURITY SYSTEMS Page 1 of 13

Transcription:

SULLIVAN COUNTY JAIL PROJECT JANUARY 21, 2016

AGENDA 1. 2. 3. 4. Introduction & Project Summary Project Team Review of Project History Moving Forward

01 INTRODUCTION & PROJECT SUMMARY

PROJECT SUMMARY Not yet serviced LaBella s County Project Experience 2006 County Selection Process Initial County Approved Program & Budget Independent Cost Analysis Understanding the Cost Projections New York State Experience Our Commitment to Sullivan County

LABELLA CORE VALUES Honesty & Integrity Understanding of Client s Mission Adding Value to the Community Providing Leadership & Resources Responsible to Deliver Results Developing Long Term Relationships Robert Healy, President, Sergio Esteban, CEO, Robert Pepe, CFO

02 PROJECT TEAM

PROJECT TEAM LaBella Associates BBL Shumaker Carter Goble Lee Principal In Charge Project Manager Architecture Structural Engineering Environmental Consulting Security Control HVAC Engineering Plumbing & Fire Protection Planning/SEQRA Cost Estimating Scheduling Constructability Civil and Site Engineering Programming Transitional Service

Suffolk County Jail Replacement Phase I 380 Cells, 60- bed dorm $155 Million Future Phase II 360 cells, administration and supports spaces, kitchen remodel, vocational and programming space COUNTY EXPERTS

Delaware County Jail 100 cell direct supervision facility Sheriff s administration, probation office, emergency management $20 Million COUNTY EXPERTS

Monroe County Jail Expansion Additional 424 cells Enhanced circulation, support services $53 Million COUNTY EXPERTS

NYS COMMISSON OF CORRECTION Chairman Beilein Commissioner Loughren Commissioner Harrison-Ross, M.D. Understanding of NYS Minimum Standard Interactive process Success with approval process

STAFF EFFICIENCY A single post can require more than 5 staff FTE 24 Hours per day 7 Days per week

COST FACTORS Total expenses over the life of the bond Capital Costs Approximately 10% Operating Costs Approximately 90%

BBL Project Experience

BBL Project Experience

Carter Goble Lee

03 REVIEW OF PROJECT HISTORY

It is the mission of this project to replace the existing Jail facility with a newly constructed modern County Jail facility. The facility shall be sited, designed, and constructed to provide best overall value to the County and to the taxpayers. The facility will be designed with oversight from NYS Commission of Corrections. PROJECT MISSION & GOALS

PROJECT DESIGN SUMMARY AS OF JULY 2009 Base Project: Designed around 304 cells, 364 beds with 25% double cells 169,000 square feet Total project budget: $79.4 million Current Design: Total design 256 cells, 304 beds with 25% double cells Base Jail design 132,000 square feet Sheriff Road Patrol / Admin Bid Alternate 22,000 square feet

PROJECT DESIGN SUMMARY Other Project Features: Project includes core area to accommodate up to 500 beds Site work to accommodate up to 3 additional housing pods in the future Site design to accommodate bid alternate Sheriff's Administration & Road Patrol Off site project utilities included in project total (Not designed yet) On-site water tank included in project budget (Not designed yet)

SULLIVAN COUNTY JAIL SITE PLAN

SULLIVAN COUNTY JAIL PERSPECTIVE OVERVIEW

SULLIVAN COUNTY JAIL PERSPECTIVE OVERVIEW

SULLIVAN COUNTY JAIL OFF-SITE UTILITIES OPTION 1

SULLIVAN COUNTY JAIL OFF-SITE UTILITIES OPTION 2A AND 2B

SULLIVAN COUNTY JAIL OVERALL FLOOR PLAN SHERIFF ADMIN & ROAD PARTROL BID ALTERNATE

SULLIVAN COUNTY JAIL PARTIAL FLOOR PLAN NORTH CORE DEPARTMENT REDUCTIONS LOBBY/WAITING EDUCATION VISITATION MEDICAL SERVICES JAIL ADMINISTRATION - 1,220 SF - 605 SF - 175 SF - 540 SF - 3,185 SF

SULLIVAN COUNTY JAIL PARTIAL FLOOR PLAN EAST CORE DEPARTMENT REDUCTIONS BOOKING/PROCESSING MAINTANENCE/SHOP AREA - 860 SF - 395 SF

SULLIVAN COUNTY JAIL PARTIAL FLOOR PLAN HOUSING UNITS A & B DEPARTMENT REDUCTIONS HOUSING PODS B THRU F MECHANICAL AND STAIRS - 1,030 SF - 11,990 SF

SULLIVAN COUNTY JAIL SHERIFF ADMIN/ ROAD PATROL BID ALTERNATE

SULLIVAN COUNTY JAIL CONCEPTUAL RENDERING Booking

SULLIVAN COUNTY JAIL CONCEPTUAL RENDERING Visitation

SULLIVAN COUNTY JAIL CONCEPTUAL RENDERING Housing Unit/CO Station

04 MOVING FORWARD

REMAINING PROJECT ITEMS Finalize off-site utility approach and start design Approve sole source approach for the security & control system (Black Creek). Complete Project Labor Agreement Study (PLA) Finalize electrical approach with NYSE&G Provide estimate information to County for bonding project

INFLATIONARY ADJUSTMENTS / INFLATION TREND Inflation Trend 09 to Oct 13 Inflation Trend Oct. 13 to April 15 Market Trends - RLB 2 nd Qtr 15 Report NY Times 11-7-15

PROJECT COST ESTIMATE REMAINING PROJECT COSTS FOR BONDING $63.3 M Building Construction Cost $3.3 M Off-Site Utilities $3.2 M Inflation Cost between 2009 DD Estimate Bid (Proposed Bid Date of April/May 2016) $2.9 M Inflation to Mid-Point of Construction (Assumes 25 months from June 2015) $8.3 M Remaining Soft Costs $81.0 M Total $ Sheriff Admin & Road Patrol Bid Alternate Costs

COC Review Mtg & County Approval of Re-Design July 23, 2015 Committee Update Presentation Nov. 12, 2015 Submission of 98% Jail Documents to County Feb. 5, 2016 Final Construction Estimate Feb. 5, 2016 COC Final Review and Approval Mtg Mar. 15, 2016 Submission of 98% Sheriff Admin & Road Patrol Bid Alternate Documents to County Mar. 29, 2016 Out to Bid TBD (April/May 2016?) PROJECT SCHEDULE

QUESTION AND ANSWER