ENVIRONMENTAL MANAGEMENT PLAN :-



Similar documents
Project Details-Minor Minerals ( Rajula Building Stone)

Project Details-Minor Minerals (Other Than Sand)

Project Details- Minor Minerals (Other Than Sand)

Project Details- Minor Minerals (Other Than Sand)

ENVIRONMENT MANAGEMENT PLAN

Environmental Management Plan

ENVIRONMENT MANAGEMENT PLAN

PRE FEASIBILITY REPORT

ENVIRONMENT MANAGEMENT PLAN

ENVIRONMENT MANAGEMENT PLAN

Environment Management Plan

Project Details - Riverbed Sand Mining Project

ENVIRONMENT MANAGEMENT PLAN

Environment Management Plan

Environmental Management Plan

CHANDAM7AIL,P SAND DEPOSIT

Project Details - Riverbed Sand Mining Project

ENVIRONMENT MANAGEMENT PLAN

PROPOSED TERMS OF REFERENCE

EnVirOnMEnT ManaGEMEnT PLan. FOr. M/S. LiME STOnE MinE OF. Dhirajlal Panchanbhai Vachhani. area. PrOPOSEd PrOdUCTiOn: TPa

ENVIRONMENT MANAGEMENT PLAN

ENVIRONMENT MANAGEMENT PLAN

ENVIRONMENT MANAGEMENT PLAN

ENVIRONMENT MANAGEMENT PLAN

PRE-FEASIBILITY CUM EMP REPORT FOR SAND EXTRACTION PROJECT (FROM RIVER PURNA PAT) FOR. KESHAVBHAI RATANJIBHAI PATEL 150 MT/day

ENVIRONMENTAL MANAGEMENT PLAN

TERMS OF REFERENCE FOR SCOPING OF EIA STUDY

Proposed Terms of Reference for EIA studies

TERMS OF REFERENCE FOR THE RAPID EIA STUDY FOR SHIVKAR LIGNITE BLOCK, DIST. BARMER, RAJASTHAN

TERMS OF REFERENCE. BEFORE CONSTRUCTION: Sl No TOR RESPONSE 1. Legalities of the land: Is the land The Project is clear from all angles.

TERMS OF REFERENCE FOR THE RAPID EIA STUDY

GUIDANCE DOCUMENT FOR PREPARATION AND SUBMISSION OF ENVIRONMENTAL MANAGEMENT PLAN (EMP) 1.0 INTRODUCTION TO GUIDANCE DOCUMENT

Proposed Terms of Reference for EIA studies

PRE-FEASIBILITY CUM DETAIL PROJECT REPORT FOR SAND EXTRACTION. PROJECT- 50 MT/Day (FROM RIVER VALMIKI) VILL:VEDCHHI,TAL:VALOD,DIST:TAPI

Building Stone Quarry

Environment Management Plan

Environment Management Plan


Pre- FEASIBILITY REPORT

PRE-FEASIBILITY REPORT

ENVIRONMENTAL MANAGEMENT PLAN. Nilaya Hills/ Heights Promoted by M/s RBS Developers (Group Housing & Commercial Building Project)

2. PRE-FEASIBILITY REPORT

Executable EMP for Residential & Commercial Project by Ms. Abisky Ritkriti Keshavnagar LLP

ENVIROMENT MANAGEMENT PLAN FOR DEVGAON SAND STONE DEPOSIT AREA 2.00 HECTARE TEHSIL RITHI DISTT- KATNI (M.P)

PRE - FEASIBILITY REPORT

2. PRE-FEASIBILITY REPORT

Pre- FEASIBILITY REPORT

PRE-FEASIBILITY CUM DETAIL PROJECT REPORT FOR SAND EXTRACTION PROJECT: 300 MT/DAY (FROM RIVER TAPI PAT)

PRE- FEASIBILITY STUDY REPORT. M/s. SAI MINERALS

ENVIRONMENTAL MANAGEMENT PLAN

How To Conduct An Environmental Impact Assessment

The Terms of reference (ToR) for conducting Rapid EIA study for the proposed project is described below:

Arya Geo-Tech Services Amit Mishra (Geologist) Regd. No. RQP/DGMMP/66/2013,Valid upto 29/07/2018 Kabara Colony, Nagpur Road Distt.-Chhindwara (M.P.

Package Treatment Plant Policy and Procedure

Final Environmental Impact Assessment of Smt. Singam Bhavani Laterite Mining ADDITIONAL STUDIES

PRE- FEASIBILITY STUDY REPORT

Fauna- No particular type of fauna finds except snakes, hynus & Jackals, wild cat, wildhen etc. are found in and around the area.

PRE- FEASIBILITY REPORT

STANDARD TEMPLATE FOR EVALUATION OF ALL PROJECTS / ACTIVITIES. 2 Name of the organization/owner. M/s.N.R.Global Granite

A Developer s Guide: Watershed-Wise Development

PROPOSED TERMS OF REFERENCE

Introduction to Waste Treatment Technologies. Contents. Household waste

Environment Impact Assessment study:

For Building Stone Quarry

Project Details-Minor Minerals (Sand Stone)

SAMPLE FRACTION MITIGATION CONTINGENCY PLAN FOR DIRECTIONAL DRILLING

Environment Management Plan. Residential & Commercial project

COMPLIANCE STATUS OF CONDITIONS IMPOSED IN ENVIRONMENTAL CLEARANCE FOR 8.5 MTPA BAUXITE MINING VIDE LETTER NO J-11015/650/2007-IA.II(M),DTD

ENVIRONMENTAL SITE MANAGEMENT & REHABILITATION AWARENESS COURSE management level

How To Plan A Buffer Zone

ABANDONMENT COST, FINANCIAL ASSURANCE AND PRESENTATION OF THE DOCUMENT. Abandonment cost :

ENVIRONMENT MANAGEMENT PLAN

ENVIRONMENTAL MANAGEMENT PLAN

Form -1 Mining Plan & Pre-feasibility Report

PRE-FEASIBILITY REPORT

Project Details-Minor Minerals (Black Trap)

FORM -1 MINING PLAN & PRE-FEASIBILITY REPORT. FOR QUARRYING OF ROUGH STONE (Extent: Ha)-B2 Project

RISK ASSESSMENT. STONE QUARRY (2.40 Ha)

APPENDIX 4. Risk Tables

Ratdi Limestone (Building) Mine Location Near Village- Ratdi, Taluka & district Porbandar, (Gujarat) Latitude. 9.0m RL.

TOR for Synthetic Organic Chemicals ToR for EIA studies in respect of the synthetic organic chemicals industry may include, but not limited to the

Climate Change and Sri Lanka. Ajith Silva Director/ Policy and Planning Ministry of Environment and Natural Resources Sri Lanka

PROPOSAL FOR HOUSTON COUNTY BAN ON SILICA SAND MINING / PROCESSING ACTIVITY. Introduction and Assumptions

NEWMONT GHANA GOLD LTD. AHAFO SOUTH PROJECT COMPLETION AUDIT TERMS OF REFERENCE ENVIRONMENTAL, HEALTH, AND SAFETY

THE NATURAL RESOURCES AND ENVIRONMENT ORDINANCE (CAP LAWS OF SARAWAK, 1958 Ed.)

KITSAULT MINE PROJECT ENVIRONMENTAL ASSESSMENT. Section Summary of Commitments

Environment Impact Assessment of Thermal Power Plant for Sustainable Development

ENVIRONMENTAL MANAGEMENT PLAN

It s hard to avoid the word green these days.

ENVIRONMENTAL MANAGEMENT PLAN

STORMWATER POLLUTION PREVENTION PLAN TEMPLATE. 1.0 SITE DESCRIPTION 1.1 Project Name and Location Date

Annexure-A. No additional land used. acquired for any activity of project without obtaining proper permission. v For controlling fugitive natural dust

Appendix I. Form 1 BASIC INFORMATION GRANITE MINING PROJECT VILLAGE KHARDA KI DHANI, TEHSIL ROHAT, DISTRICT PALI, RAJASTHAN

The Ministry of Environment and Forest says No Discharge from Red Mud Pond in Lanjigarh

About Pure Earth and the Toxic Site Identification Program

Rural dwellings including bed and breakfast accommodation

MLD: Domestic Maritime Transport Project

Transcription:

ENVIRONMENTAL MANAGEMENT PLAN :- The Environment Management Plan (EMP) is required to ensure sustainable development in the area of the proposed project. Hence it needs to be all encompassive plan for which the industry, Government, Regulating agencies like Pollution Control Board working in the region and more importantly the population of the area need to extend their co-operation and contribution. It has been evaluated that the project area will not be affected significantly with proposed project. measures at the source level and an overall Management Plan at the site level are elicited so as to improve the surrounding environment. The following mitigation measures will be taken in order to synchronize the economic development of the project area with the environmental protection of the region. The construction phase impacts are mostly short term restricted to the plot area and not envisaged on the larger scale. In the operational phase the environmental impacts are due to continuous operation of the project, hence, the emphasis in the Environment Management Plan (EMP) is to minimize such impacts. The emphasis on the EMP development is on the following. * measures for each of the activities causing the environmental impact. * Monitoring plans for checking activities and environmental parameters and monitoring responsibilities * Role responsibilities and resource allocation for monitoring. Following sections describes the environment management plan proposed for site clearing and mining phases. MITIGATION MEASURES :- Each of the activities during production phase is critically reviewed for suggestion of mitigation measures. Based on this the Table 1 to 6 gives the mitigation measures for the activities considered to be causing significant environmental impacts during production phase of every year.

Table :- 1 Environment Management Plan :- Activity Environmental Site Clearing, Pollmarking and OB removal Air Water spraying PPE's is being used Land Well maintained vehicles are used. Metalled Road for vehicle movement. Top soil will be conserved and be utilized for riparian greenbelt. Water -- Noise -- Table :- 2 Environment Management Plan :- Activity Environmental Mining process Air Water sprinkling on haul roads. Plantation in periphery and along haul roads. Transportation by covered trucks. Ensure uses of personal protective equipments. (PPE's) Water No waste water management.

Excavation is restricted up to the water depth or 3 m, whichever is less, so as to prevent lowering of water table in riparian area. Land Adequate setback distance will be maintained to prevent bank erosion. No in-stream mining will be carried out. Manage proper storage of quarry solid wastes. Noise Use of only PUC certified vehicles. Only trained / approved transporters is given work for the transportation of sand. Ensure proper maintenance of machinery to reduce noise level. Table :- 3 Environment Management Plan :- Handling and Transportation of Waste materials and products.

Activity Environmental Storage of all the Waste materials and products. Air Water Separate demarcated area for storage of wastes. Land Proper facilities to prevent rain / storm water contamination. Metalled Road for vehicle movement to reduce fugitive emission. Land Top soil is being conserved and will be utilized for greenbelt on riparian area. Adequate setback distance is being maintained for prevention of bank erosion. Table :- 4 Environment Management Plan :- Other Facilities :- Activity Environmental Toilets Water Proper sewage disposal is ensured.

Development and maintenance of green belt Direct / Indirect Employment Air. Land Socioissue economic Development and maintenance of green belt will be ensured. Policy of local employment is continued. Environmental Monitoring Plan :- Environment monitoring plan is given in table 5 as follows : Table No. 5 Sr.No. Activity Schedule Air Pollution Monitoring 1 Ambient air monitoring of parameters specified by GPCB in their air consents from time to time within the Proposed premises Once every Calendar Year Water Pollution Monitoring 1 No waste water Produced N.A. Solid Waste Generation Monitoring / Record Keeping 1 Records of generation of quarry spoil and mud form particles of minerals and record of their dispatch to approved users. To be updated once in a month Expenditure on Environmental Matters :- The following table gives the expenditure to be incurred by Proponent on environmental matters. Table No. 6 Sr. No. Description Approximate recurring cost per Approximate Capital Cost

annum (Rs. In lacs) (Rs. In Lacs) 1 Air pollution control 0.30 0.50 2 Water pollution control 0.10 0.30 3 River bed protection 0.50 0.80 3 Environment monitoring and 0.30 -- management 4 Solid and hazardous waste 0.10 -- management 5 Noise pollution control 0.10 0.30 6 Occupational health 0.50 0.70 7 Green belt (Riparian vegetation) 0.80 1.00 Total 2.70 3.60 Table No. 7 : Riverbed vegetation (Riparian Green belt) Name of the trees Sensitive / tolerant to air pollution Height No. of Threes to be planted Amount to be Spent Neem Tolerant 10-15 m 60 Vad Tolerant 10-15 m 40 Peepal Tolerant 10-15 m 45 Cassia Fistula (Yellow Flower Tree) Tolerant 5-10 m 70 Total 225 00.80 Lacs 28. Measures proposed for protection of environmental attributes like riverbed, As per Table 1 to 7

riverbed vegetation, water, air, human health, etc. 29. Details on transportation route & Transportation route is in two parts. measures proposed for control of fugitive emission during transportation Approximate 0.20 km of length is in river bed which is of 4 m width and 0.48 km route is of kutcha road which is of 4 m width. Water sprinkling on kutcha road will be done twice a day for control of fugitive emission during transportation. Only covered trucks will be used for transportation. Vehicle speed will be restricted to 15 Km/Hour on kutcha road to reduce fugitive emission. 30 Details on transportation route 0.20 km route is on river bed. In table area/road sides in at least 20% of lease area, numbers & types of species and budgetary outlay for the same. no. 7 of EMP, proponent described the species and budgetary outlay for the riparian green belt and plantation on both the side of kutcha road. 31. Plan for restoration /reclamation The project is for excavation of sand only up to limited depth. During the monsoon, rain water reclaims pits by sediment transport. There is no need to make plan for restoration/ reclamation. The process of restoration/reclamation done by nature itself.