1 PRE FEASIBILITY REPORT for PROPOSED PROJECT FOR SOIL MINING of M/s. BHAVINKUMAR VINODBHAI LAD SURVEY NO. 98, MOJE ANCHELI, TAL. BARDOLI, DIST. SURAT, GUJARAT 1
2 CONTENTS Sr. Description Page No. No. 1. Executive Summary 3 2. Introduction of the Project/Background information 8 3. Project Description 9 4. Site Analysis Planning Brief Proposed Infrastructure Rehabilitation and Resettlement (R & R) Plan Project Schedule & Cost Estimates Analysis of Proposal (Final Recommendations) 15 2
3 1.0 EXECUTIVE SUMMARY 1.1 Company Profile Introduction M/s. Bhavinkumar Vinodbhai Lad has proposed to operate soil mining on Sr. No. 98, Village. Ancheli, Tal. Bardoli, Dist. Surat, Gujarat. The unit is seeking permission for permission (Quarry lease) to extract the soil mineral from area of ha. 1.2 Project Details The proposed mine will be having ha lease area for production of 55,000 MTPA Soil. Project work for mining activity would be taken up after obtaining EC from SEAC Gandhinagar. Salient features of the project are placed below Project Soil Mining in area of ha 2. Location Sr. No. 98, Village. Ancheli,Tal. Bardoli, Dist. Surat, Gujarat 3. Project Proponent Mr. Bhavinkumar Vinodbhai Lad (Owner) 4. Lease hold Area ha 5. Geological Reserves Total reserve: Approx. 1,62,380 (5 m) 6. Extractable Reserves Total reserve: Approx. 1,62,380 (5 m) 7. Total waste m 3 Nil 8. Method of Mining Conventional Open cast 9. Mining Equipment Diesel hydraulic shovels in combination with dumpers 10. Existing Quarry Depth (m). New project 11. Final Quarry Depth (m) Total Volume of Over Burden Nil 13. Water Requirement 9 KLD 14. Manpower requirement Rate of Production 55,000 MTPA 16. Life of Project 3 year (Approximate) 3
4 1.3 Green Belt Development Unit will carry out tree plan along the road side & periphery. 1.4 Power & Fuel Requirement Fuel: No Fuel is required in Mining activity. Energy: No energy is required in Mining activity. 1.5 Water Requirement and Wastewater Generation & Treatment The unit requires 9 M3/day of water. Out of this 8 M3/day will be used for purpose for sprinkling in dust generated areas for air pollution control and plantation areas. This will be drawn from accumulated mine water from sumps after settling. About 1 M3/day will be used for drinking water purpose and for use in office and other establishment. This will be drawn from Bore well (Nearby village). WATER CONSUMPTION SUMMARY Category Water Consumption (KL/day) (a) Domestic 1.0 (b) Industrial: Other (Plantation + Dust Suppression) 8.0 TOTAL (b) 8.0 GRAND TOTAL (a + b) 9.0 4
5 1.6 Air Pollution Source and Control Management The principal sources of Air pollution due to the project of stone mine are: Dust Particulates. (Dust may occur as fugitive dust from excavation & from haul roads.) Gaseous pollutants The sources of dust generation in the mine are: a. Extraction of soil by Shovels. b. Movement of HEMM, such as Shovels, dumpers etc. c. Loading and unloading operation, d. Soil conveying, e. Material handling operation in the Mining, Gas emission can occur as a result of: a. Emission of SO 2 from diesel driven mining equipments, compressors, etc. Impact: The Particulate Matter (PM10) especially that below 5 micron size is a serious air pollutant, which can lead to lung disorder and other diseases like Bronchitis, Emphysema, Bronchial Asthma, Irritation of mucus membranes of eyes etc. Mitigate Measures for Air Quality: The principal sources of air pollution in the area will arise from dust generation due to removal of soil by shovels, movement of HEMM, Material handling operations, wind erosion etc. Gaseous emission may occur due to operation of diesel driven mining equipments, generator sets etc. Above adverse impacts on air quality will be effectively controlled both by preventive and suppressive measures like keeping haul roads as per standards, blacks topping of permanent haul roads and service roads, frequent water spraying or sprinkling on the roads, periphery of mine, 5
6 However, the Air pollution from the mining operations shall be effectively controlled by, Material will be stacked at lower depth & at identified place. Regular water sprinkling is carried out. Development of haul roads as per the standards, black topping of roads wherever necessary to avoid or eliminate air borne dust. Development of green barriers around mine and around the industrial area, along the roads, etc. Avoiding overloading of dumpers. Frequent water spraying / sprinkling on the roads, stock piles, OB dumps and transfer points where dust is produced. Improved maintenance of machinery for reducing gaseous and noise pollution. Speed of the vehicles will be maintained within the prescribed limits. Condition of all trucks will be well maintained. Old age trucks will not be utilized. Only P.U.C. certified vehicle will be used. Provision of dust filters / mask to workers working at highly dust prone and affected areas. Using sharp teeth for shovels and other soil excavation equipment, and also periodical replacements. 1.7 Impact on Noise Quality Mining operations such as excavation, loading and dumping, activities etc. will generate significant noise especially in the work environments unless proper remedial measures are adopted. Prolonged exposure to a high noise level is harmful to the human auditory system and can create mental fatigue, rebellious attitude, annoyance, and carelessness, which may lead to neglect of work and also result in accidents. Noise will be produced due to operation and movement of Heavy Earth Moving Machinery, various other allied equipment and transport vehicles. The impact on the surrounding 6
7 population in the buffer zone will be minimal from propagated noise levels from the mining area, due to adoption of following control measures. 1. The operator's cabin of equipments like dumpers, shovel, etc. would be made sound Proof. 2. Proper and regular maintenance of equipments may lead to less noise generation. 3. Manufacturers of equipment will be advised to provide in built mechanism for reducing sound emissions. 4. Where noise level exposure is more, workers will be provided with earmuffs. 5. Regular health check up of workers will be undertaken. 6. Accordingly, noise level status of operational machinery may be displayed on the Machines to enable control measures to be taken in this respect. This will enable to know the extent of noise level and to control the time to which the worker is exposed to higher noise levels. 1.8 Hazardous Waste Management No any kind of Hazardous waste will be generated during mining activity. 7
8 2.0 INTRODUCTION OF THE PROJECT/BACKGROUND INFORMATION 2.1 Identification of the project and project proponent. In case of mining project, a copy of mining lease/letter of intent should be given. Identification of the project Proposed project for Soil Mining activity. Identification of the project proponent Mr. Bhavinkumar Vinodbhai Lad (Owner) Mo. No Address: House No. 6, Shailesh nagar society, Kabil pore, Navsari Brief description of nature of the Project Proposed project for Soil Mining activity. 2.3 Need for the project and its importance to the country and or region The objective is to be achieved by: Infrastructural development. To generate local employment Opportunities of employment to the eligible people from the ethnic population. 2.4 Demands Supply Gap It will be supporting economic and infrastructural development in the State. It will help in meeting the increasing demand of soil required for development of the locality and the State. 2.5 Imports vs. Indigenous production Not applicable. 2.6 Export possibility Not Applicable. 8
9 2.7 Domestic/Export Markets Not Applicable. 2.8 Employment Generation (Direct and Indirect) due to project Approximately 15 people get direct & indirect employment due to the project activity. The mining and associated activities offer opportunities of employment to the eligible people from the ethnic population. 3.0 Project Description 3.1 Type of Project including interlinked and interdependent projects, if any. Proposed project for Soil Mining activity Category: 1 (a). Lease area < 5 Ha. Thus, project falls under category B (B2) No interlinked project has been submitted. 3.2 Location (map showing general location, specific location and project boundary & project site layout) with coordinates. Map showing general location 9
10 Project Site Layout Land Area Breakup No Detail Area (m 2 ) 1 Total land Details of alternate sites considered and the basis of selecting the proposed site, particularly the environmental considerations gone into should be highlighted. Major factors involved in the selection of site are listed below: Site is very well connected by road Proximity to Raw Material suppliers Availability of water for industrial use After excavation pond will become deeper, broaden & source of water for local villagers (by rain water harvesting programme). 10
11 3.4 Size or Magnitude of Operation Please refer Section 1.2, Page No Project Description with process details (a schematic diagram/flow chart showing the project layout, components of the project etc. should be given) Please refer Annexure Raw material required along with estimated quantity, likely source, marketing area of final products. Mode of transport of raw materials and finished products. No such raw material will be utilised in mining activity. 3.7 Resource optimization/recycling and reuse envisaged in the project, if any, should be briefly outlined. Not Applicable. 3.8 Availability of water its source, energy/power requirement and source should be given. Fuel: Not Required. Energy: Not Required. Water Source The entire water requirement will be met through bore well. 3.9 Schematic representations of the feasibility drawing which give information of EIA purpose. Not Applicable. 11
12 4.0 Site Analysis 4.0 Site Analysis 4.1 Connectivity Site is very well connected by road & rail Availability of power evacuation facilities Availability of water for industrial use 4.2 Land Form, Land Use and Land Ownership Government land (Pond). Please refer annexure 1 for land possession documents. 4.3 Topography (along with map) Land is flate & Height from Mean Sea Level is 93 feet. 4.4 Existing land use pattern (agriculture, non agriculture, forest, water bodies (including area under CRZ)), shortest distances from the periphery of the project to periphery of the forests, national park, wild life sanctuary, eco sensitive areas, water bodies (distance from HFL of the river), CRZ. In case of the notified industrial area, a copy of the Gazette notification should be given. The project area is with elevation mostly ranging between 93 m to 96 feet above MSL. Physical geography of surrounding area is shown in fig. given bellow. 12
13 4.5 Existing Infrastructure Site is very well connected by road. 4.6 Soil Classification Soil testing is not carried out. 4.7 Climatic data from secondary sources Not Compiled. 4.8 Social infrastructure available Not Required. 5.0 Planning Brief 5.1 Planning Concept (type of industries, facilities, transportation etc) Town and Country planning/development authority classification. Type of Industry: Proposed project for soil mining. 5.2 Population Projection Not Required. 5.3 Land use planning (breakup along with green belt etc.) Total Area ha. Mining Area ha. 5.4 Assessment of Infrastructure Demand (Physical & Social) Not Required. 5.5 Amenities/Facilities Not Required. 13
14 6.0 Proposed Infrastructure 6.1 Processing Zone Not Applicable 6.2 Non Processing Zone Not Applicable 6.3 Green Belt Unit will carry out tree plantation along the road side & periphery of mining. 6.4 Social Infrastructure Not required. 6.5 Connectivity (Traffic and Transportation Road/ Rail/Metro/ Water ways etc) Site is very well connected by road & railway. 6.6 Drinking water Management (Source & Supply of water) Water requirement will meet through the bore well of nearby village. 6.7 Sewerage System Domestic water will be allowed in soakpit/ septic tank. 6.8 Solid Waste Management Not applicable 7.0 Rehabilitation and Resettlement (R & R) Plan 7.1 Policy to be adopted (central/state) in respect of the project affected including home ousters, land ousters and landless laborers (a brief outline to be given) There is no habitation on the proposed project area and it is a pond owned by the Government. Hence, R & R policy is not applicable to this project. There shall be no displacement of any population in project area. 14
15 8. Project Schedule & Cost Estimates 8.1 Likely date of start of construction and likely date of completion (Time schedule for the project to be given). We will start mining after getting environmental clearance. 8.2 Estimated Project cost along with analysis in terms of economic viability of the project. Total costs of the project will Rs. 2.0 lac. Capital cost of air & water pollution control system and environmental monitoring equipments will be Rs. 25 thousand. 9. Analysis of Proposal (Final Recommendations) 9.1 Financial and social benefits with special emphasis on the benefit to be local people including tribal population, if any, in the area. Approximately 15 people get direct & indirect employment due to the project activity. The mining and associated activities offer opportunities of employment to the eligible people from the ethnic population. 15
PRE- FEASIBILITY STUDY REPORT. M/s. SAI MINERALS
PRE- FEASIBILITY STUDY REPORT FOR M/s. SAI MINERALS BLACK TRAP MINING (AREA 04-00-00 HECTARE) OF APPLICANT (Mr. AMARJITSINH R. VARACHHIYA) (PARTNER) AT SURVEY NO: 13, AT: ASHNAVI, TAL: JHAGADIA, DIST:
More informationPRE- FEASIBILITY STUDY REPORT
PRE- FEASIBILITY STUDY REPORT FOR RAJNIKANT GORDHANBHAI CHANIYARA PROPOSED BLACK TRAP MINING (AREA 03-00-53 HECTARE) OF APPLICANT (Mr.Rajnikant Gordhanbhai chaniyara) (PAWOR OF ATTORNEY) AT BLOCK NO: 66
More information2. PRE-FEASIBILITY REPORT
2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The proposed project is Building stone quarry having lease area of 1.214 ha and falls under Category- A as per EIA Notification 2006 and its amendments of
More informationPRE FEASIBILITY REPORT
PRE FEASIBILITY REPORT FOR M/S. AMRUT STONE QUARRY (AREA 2.57 HECTARE) OF APPILCANT MR. RAJNIKANT BHAGWANJIBHAI KATHIRIYA (Partner) AT BLOCK NO: 98,VILL: ZAB, TAL: MANDVI, DIST: SURAT 394163 GUJARAT. 1
More information2. PRE-FEASIBILITY REPORT
2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The proposed project is Building stone quarry having lease area of 0.809 ha and falls under Category- A as per EIA Notification 2006 and its amendments of
More informationPRE - FEASIBILITY REPORT
PRE - FEASIBILITY REPORT FOR OBTAINING PRIOR ENVIRONMENT CLEARANCE TO Building Stone MINING ACTIVITY FOR CATEGORY B3 UNDER THE EIA NOTIFICATION 3006 AMENDED ON 31/05/3013 TO 1.97.58 SHREE SHAH ENGINEERING
More informationPRE-FEASIBILITY REPORT
PRE-FEASIBILITY REPORT OF MASONRY STONE (CHEJA PATTHAR) MINING PROJECT (ML Area: 1.0 ha, M.L. No. 65/2011, Production Capacity-1, 11,780 TPA) Near Village: Gangora, Tehsil: Pahari, District: Bharatapur
More informationM/s. Karshanbhai Bhagvanbhai Rabari
PRE FEASIBILITY REPORT FOR M/s. Karshanbhai Bhagvanbhai Rabari Black TRAP MINING (AREA 1.00 HECTARE) OF APPLICANT Mr. Karshanbhai Bhagvanbhai Rabari (Proprietor) AT Survey No. 194 Paikee, Vill: Thoriyali,
More informationENVIRONMENTAL MANAGEMENT PLAN :-
ENVIRONMENTAL MANAGEMENT PLAN :- The Environment Management Plan (EMP) is required to ensure sustainable development in the area of the proposed project. Hence it needs to be all encompassive plan for
More informationPRE-FEASIBILITY CUM EMP REPORT FOR SAND EXTRACTION PROJECT (FROM RIVER PURNA PAT) FOR. KESHAVBHAI RATANJIBHAI PATEL 150 MT/day
A PRE-FEASIBILITY CUM EMP REPORT FOR SAND EXTRACTION PROJECT (FROM RIVER PURNA PAT) FOR KESHAVBHAI RATANJIBHAI PATEL 150 MT/day VILL.:VIRPOR, TAL.: VALOD, DIST.: TAPI INDEX LIST OF CONTENTS CHAPTER DESCRIPTION
More informationPRE-FEASIBILITY CUM DETAIL PROJECT REPORT FOR SAND EXTRACTION PROJECT: 300 MT/DAY (FROM RIVER TAPI PAT)
A PRE-FEASIBILITY CUM DETAIL PROJECT REPORT FOR SAND EXTRACTION PROJECT: 300 MT/DAY (FROM RIVER TAPI PAT) OF PADMABEN JAYANTIBHAI OAD RESI. AT: VILL: GHALA, TAL: KAMREJ, DIST: SURAT INDEX LIST OF CONTENTS
More informationENVIRONMENT MANAGEMENT PLAN
ENVIRONMENT MANAGEMENT PLAN ENVIrONMENT MaNaGEMENT plan 1. INTRODUCTION: Shri Ratilal Ravji Solanki have a Blacktrap mining lease project for an area of 1.00.00 Ha located on Survey no. 984 paiki, Village:
More informationPRE FEASIBILITY REPORT
PRE FEASIBILITY REPORT In Respect Of MAHUMUHAN STONE MINE 9 OVER 2.00 ACRES (0.81 HECTARE) IN VILLAGE MAHUMUHAN, SORO TAHASIL OF BALASORE DISTRICT, ODISHA (FOR THE PERIOD: 2015 16 TO 2019 20) APPLICANT
More informationProject Details-Minor Minerals (Other Than Sand)
Project Details-Minor Minerals (Other Than Sand) Sr. No. Details Particulars ABOUT THE PROPOSAL 1. Name Of lease Holder M/s. Kirtikumar Samji Sengani 23 0'27.43"N 69 24'10.21"E 2. Location address Survey
More informationENVIRONMENT MANAGEMENT PLAN
ENVIRONMENT MANAGEMENT PLAN LIMESTONE 1. INTRODUCTION: The proposed Bagdhara Limestone area, near Village- Bagdhara, Taluka- Jamjodhpur and District-Jamnagar, Gujarat has been granted to Dipakkumar Anantray
More informationENVIRONMENT MANAGEMENT PLAN
ENVIRONMENT MANAGEMENT PLAN Page 33 ENVIRONMENT MANAGEMENT PLAN BLACK TRAP 1.0. INTRODUCTION: The proposed M/s. Black Trap Mine of Govindbhai Karshanbhai Ram area at near Vill.Chuldi, Tal.Malia-Hatina,
More informationHow To Conduct An Environmental Impact Assessment
Proposed Terms of Reference for EIA studies 1. Introduction The proposed expansion of Bulk Drugs & Intermediates manufacturing unit by M/s. Sri Krishna Pharmaceuticals Limited (Unit V). is located at Plot
More informationENVIRONMENT MANAGEMENT PLAN
ENVIRONMENT MANAGEMENT PLAN FOR VILLAGE TEHSIL DISTRICT AREA MINERAL : Makrohar : Mada : Singrauli (M.P.) : 1.00 hect : Metal Stone KHASRA No : 176,178 PRODUCTION CAP : 15375 Cu.mt/year Metal Stone APPLICANT
More informationENVIRONMENT MANAGEMENT PLAN
6. REHABILITATION AND RESETTLEMENT (R & R) PLAN Since the project is private land, there is no reserves forest or protected forest land within the applied area. There is no human settlements within the
More informationENVIRONMENT MANAGEMENT PLAN
ENVIRONMENT MANAGEMENT PLAN OF M/s Baghel Infrastructure Pvt. Ltd. AT Khasra No 1203/1 Vill- Makrohar, Tehsil-Mada, District-Singrauli (M.P.) Production Capacity: 8158Cu.mt/year Metal Stone Area 1.00 Hectare
More informationProject Details- Minor Minerals (Other Than Sand)
Project - Minor Minerals (Other Than Sand) Sr. ABOUT THE PROPOSAL 1. Name of Lease Holder M/s. ABDUL MUNAF MOHAMMEDMIYA MALEK Mr.Abdul Munaf Mohammedmiya malek (Proprietor) 2. Location address OPP Block
More informationENVIRONMENT MANAGEMENT PLAN
ENVIRONMENT MANAGEMENT PLAN 1 [Type the company name] ENVIRONMENT MANAGEMENT PLAN LIMESTONE (BUILDING) 1.0. INTRODUCTION: The proposed M/s. Building Lime Stone Mine of Shree Jitubhai Parbatbhai Chudashma
More informationPre- FEASIBILITY REPORT
Pre- FEASIBILITY REPORT In Respect Of JHILIMINDA SAND BED OVER 20.30 ACRES OR 8.215 HA IN VILLAGE JHILIMINDA, ATTABIRA TAHASIL OF BARGARH DISTRICT, ODISHA (For the Financial Year-2015-16 to 2019-20) Prepared
More informationEnvironment Management Plan
Environment Management Plan FOR Mining of Agariya Crusher stone Quarry Area-4.00,Hectare Kh No-141/3/1,141/4,141/5 At Village- Agariya, Tehsil: Gouharganj Distt. Raisen SHRI. ASHOK SHARMA S/O SHRI GANGAPRASAD
More informationPre-feasibility Report
1.0 INTRODUCTION EXECUTIVE SUMMARY Balanga Sand Bed over an area of 12.50Ac./5.06Ha. of, Sri Nilamani Behera is located in village Uthaninuagaon, under Tahasil- Badasahi in Mayurbhanj district of Odisha.
More informationEnvironment Management Plan
Environment Management Plan FOR Mining of Sildhara Flage Stone Quarry Area-.1.50,Hectare Kh No-87 At Village- Sildhara, Tehsil Panna, Distt.Panna MR.BRIJMOHAN SINGH S/O SHRI JAI RAM SINGH RESI-VILLAGE
More informationENVIRONMENT MANAGEMENT PLAN
ENVIRONMENT MANAGEMENT PLAN OF Shri Kuldeep Choudhary AT Khasra No.Part of 112 Vill.-Golpura, Tehsil-Gandhwani, District-Dhar (M.P.) Production Capacity: 4543 Cu.mt/year Basalt Stone&4543 Cu.mt/year Murram
More informationProject Details- Minor Minerals (Other Than Sand)
Project - Minor Minerals (Other Than Sand) Sr. ABOUT THE PROPOSAL 1. Name of Lease Holder M/s. KARMANBHAI JODHABHAI RABARI (Partner) 2. Location address Mr. Karmanbhai Jodhabhai Rabari Survey No- 194 Paikee,
More informationCHANDAM7AIL,P SAND DEPOSIT
1 RVER SAND QUARRY 11 ENVRONMENT MANEGMENT PLAN OF CHANDAM7AL,P SAND DEPOST VLLAGE- GHAWDAWAL, TEHSHL- LAltEAR DSTRCT- BMTUD, STATE- MADHYA PRADESH (MASRL4 NO- 1, 10, 15, AREA- 5.975 Hectare APPLCANT Sub
More informationPRE-FEASIBILITY CUM DETAIL PROJECT REPORT FOR SAND EXTRACTION. PROJECT- 50 MT/Day (FROM RIVER VALMIKI) VILL:VEDCHHI,TAL:VALOD,DIST:TAPI
A PRE-FEASIBILITY CUM DETAIL PROJECT REPORT FOR SAND EXTRACTION PROJECT- 50 MT/Day (FROM RIVER VALMIKI) VILL:VEDCHHI,TAL:VALOD,DIST:TAPI OF ABDUL MUNAF ABDUL KADAR SHAIKH (50 MT/DAY) (0-28-50 Hectors)
More informationEnVirOnMEnT ManaGEMEnT PLan. FOr. M/S. LiME STOnE MinE OF. Dhirajlal Panchanbhai Vachhani. area. PrOPOSEd PrOdUCTiOn:-36000 TPa
EnVirOnMEnT ManaGEMEnT PLan FOr M/S. LiME STOnE MinE OF dhirajlal PanChhanBhai VaChhani area (SUrVEY no.49 PaiKi, ViLL.Unadari, TaL.Una, dis.junagadh) PrOPOSEd PrOdUCTiOn:-36000 TPa PrOJECT COST: - 15
More informationENVIRONMENT MANAGEMENT PLAN
ENVIRONMENT MANAGEMENT PLAN FOR VILLAGE TEHSIL DISTRICT AREA MINERAL : Kothi : Pawai : Panna (M.P.) : 1.370 Hectare : Flagstone KHASRA No : 31 PRODUCTION CAP : Max 875 Cu.mt/year Flagstone APPLICANT Shri
More informationPre- FEASIBILITY REPORT
Pre- FEASIBILITY REPORT In Respect Of SRIPURA SAND BED-BOVER 35.25 ACRES OR 14.265 HA IN VILLAGE SRIPURA, JHARSUGUDA TAHASIL OF JHARSUGUDA DISTRICT, ODISHA (For the Financial Year-2015-16 to 2019-20) Prepared
More informationTERMS OF REFERENCE FOR SCOPING OF EIA STUDY
TERMS OF REFERENCE FOR SCOPING OF EIA STUDY Ours project is a proposed large scale unit and categorized as 5(h)-B as per the EIA notification 2006 of MoEFCC, New Delhi and subsequent amendments. Looking
More informationEnvironment Management Plan
Environment Management Plan FOR Mining of Crusher Stone Area 2.000 Hectare, Khasra No. 42/2 Village AT THANWARI Tehsil District State SEONI SEONI MADHYA PRADESH Proponent SHRI LAKHAN LAL S/O SHRI CHETAN
More informationEnvironment Management Plan
Environment Management Plan FOR Quarry Lease of Crusher Stone Area 1.437Hectare, Kh. No. 40/8 KA AT Village: BHAWANDA, Tehsil: SEONI MALWA Distt HOSHANGABAD (M. P.) Proponent M/S JYORI CONSTRUCTION COMPANY
More informationPRE FEASIBILITY REPORT
PRE FEASIBILITY REPORT ON NAFRI STONE QUARRY NO.2 (IN MAYURBHANJ DISTRICT OF ODISHA) Lease Area: 4.97 acres or 2.01 Ha. of Sri Shyamsundar Bhattar & Others Baripada EXECUTIVE SUMMARY CHAPTER 1 Nafri Stone
More informationProposed Terms of Reference for EIA studies
1 Proposed Terms of Reference for EIA studies Base line data collection will be collected for the Post-Monsoon season 2016 (September to November 2016) in study area and 10 kms radius from project site.
More informationPRE FEASIBILITY REPORT
PRE FEASIBILITY REPORT 19 1. EXECUTIVE SUMMARY This is a mining project proposal of obtaining Environmental Clearance for Slate Stone with production Capacity 7500 TPA (ROM), Near Village: Anandpura, Tehsil:
More informationPROPOSED TERMS OF REFERENCE
PROPOSED TERMS OF REFERENCE ABOUT THE PROJECT: Rampura Marble Mine (ML No.- 420/91) is proposed by M/s Continental Minerals Pvt. Ltd. The Mine Lease area consists of 3.0 ha, which is located at Khasra
More informationFinal Environmental Impact Assessment of Smt. Singam Bhavani Laterite Mining ADDITIONAL STUDIES
ADDITIONAL STUDIES 7.0 DISASTER MANAGEMENT PLAN It is presumed that the proposed mining process would be designed and engineered with all possible safety measures and standard code of practices. In spite
More information2x800 MW Thermal Power Project Near Village Paraspani, Tehsil Pathargama, Godda- District By Adani Power (Jharkhand) Limited
(IV) Proposed Terms of Reference for EIA Studies Project Category Project Proponent Location Paraspani Thermal Power Plant (2x800 MW) Coal based Thermal Power Project A [1(d) Thermal Power Plant 500 MW]
More informationPRE- FEASIBILITY REPORT
PRE- FEASIBILITY REPORT Applicant: M/s Regaliya Minerals Pvt. Ltd. Page 0 1.0 EXECUTIVE SUMMARY This mining project falls under Category A (presence of interstate boundary between Haryana and Rajasthan
More informationNIMAPALLI STONE QUARRY
EIA/ EMP NIMAPALLI STONE QUARRY Village : Nimapalli Tahasil : Purushottampur State : Odisha Lease Area - 4.046 Ha Screening Category B2 SRI SANJAY KUMAR NAYAK At- Pallyama, Dist : Ganjam (Odisha) CONTENTS
More informationForm -1 Mining Plan & Pre-feasibility Report
Form -1 Mining Plan & Pre-feasibility Report FOR QUARRYING OF GREY GRANITE (EXTENT 1.8.0Ha)-B2 PROJECT S.F.Nos 35/2D, 35/3, 35/2E (P)& 3/1A1 (P) Village Chendarapalli Taluk Krishnagiri District Krishnagiri
More informationEnvironmental Management Plan
Environmental Management Plan FOR BOULDER, GRAVEL AND SAND MINOR MINERAL Mine lease area: 13.20 Ha Village Mandlai Tehsil Raipur Rani, District- Panchkula and State - Haryana Category of Project: B2 Lease
More informationForm -1 Mining Plan & Pre-feasibility Report
Form -1 Mining Plan & Pre-feasibility Report TO OBTAIN ENVIRONMENTAL CLEARANCE FOR QUARRYING OF BLACK GRANITE (DOLERITE) (EXTENT 2.81.0Ha)-B2 PROJECT IN S.F.Nos 9,80,258/2B,258/6A & 258/6B Village Naduvanapalli
More informationPRE-FEASIBILITY REPORT
PRE-FEASIBILITY REPORT FOR QUARRYING ROUGH STONE Over an Extent of 0.34.8 Hectares in S.F. No. 22/5A (Patta Land) in Kachchirayanpatti Village, Melur Taluk, Madurai District & Tamil Nadu State 1. EXECUTIVE
More informationThe Terms of reference (ToR) for conducting Rapid EIA study for the proposed project is described below:
Proposed Terms of Reference for EIA Study Objective: In order to identify the environmental impacts due to construction and operation of the proposed project and associated facilities, a study will be
More informationFORM - 1. Location/ Site alternatives under consideration : Block No. O : Contact Information : 98795 50353
FORM - 1 I. Basic Information Name of project : Ajaysinh Bhupatsinh Suratia (Black Trap) Location/ Site alternatives under consideration : Block. O : Size of Project Lagu Survey. 17, Mahi River at Aklacha,
More informationSustainable Resource Management Ltd
6.0 Predicted nvironmental Impacts 6. Stages and Impacts Considered An nvironmental Impact Analysis has been carried out whereby all the possible environmental, socio economic and health & safety aspects
More informationPre- FEASIBILITY REPORT
Pre- FEASIBILITY REPORT In Respect Of SARANKOTE STONE QUARRY OVER 2.40 ACRES OR 0.971 HA IN VILLAGE SARANKOTE, BARKOTE TAHASIL OF DEOGARH DISTRICT, ODISHA (For the Financial Year-2015-16 to 2019-20) Prepared
More informationEnvironmental Management Plan
Environmental Management Plan ENVIRONMENTAL MANAGEMENT PLAN An Environmental Management Plan is prepared for construction phase, post construction phase (commissioning & operation) and for post project
More informationFORM -1 MINING PLAN & PRE-FEASIBILITY REPORT. FOR QUARRYING OF ROUGH STONE (Extent: 3.00.0Ha)-B2 Project
FORM -1 MINING PLAN & PRE-FEASIBILITY REPORT FOR QUARRYING OF ROUGH STONE (Extent 3.00.0Ha)-B2 Project!!"# $%&'( )!*+ $*, % -!#( # )(!&.* /012 3345 36 7898 ;?DGGMN
More informationAPPLICATION (FORM-1, PRE-FEASIBILITY REPORT)
APPLICATION (FORM-1, PRE-FEASIBILITY REPORT) ENVIRONMENTAL CLEARANCE FOR STONE MINE (MINING LEASE AREA 0.40 Ha) AT Gut. 39, Village- Warkhed (Khurd), Tehsil- Shegaon, District- Buldhana, State-Maharashtra
More informationTAMIL NADU POLLUTION CONTROL BOARD FORM I
TAMIL NADU POLLUTION CONTROL BOARD FORM I Application for consent under Section 21 of the Air (Prevention and Control of Pollution) Act, 1981 as amended (Central Act 14 of 1981) (See Rule 7 of the Tamilnadu
More informationTERMS OF REFERENCE. BEFORE CONSTRUCTION: Sl No TOR RESPONSE 1. Legalities of the land: Is the land The Project is clear from all angles.
TERMS OF REFERENCE Name of the Project: M/s Suadela Constructions Pvt. Ltd. Address: Sy.No. 321/2B(P),321/2C(P),322/1,323/1(P),323/1(P),323/3,323/4,323/5(P), 323/6,323/7,325/1(P),325/2,327,328/1,328/2(P),328/3,328/4,330,331,332/2
More informationPre- FEASIBILITY REPORT
Pre- FEASIBILITY REPORT In Respect Of KAIPADAR NEW BUILDING STONE QUARRY (KHA) OVER 7.50 ACRES OR 3.00 HA IN VILLAGE KAIPADAR, KHURDA TAHASIL OF (For the Financial Year-2015-16 to 2019-20) Prepared on
More informationRISK ASSESSMENT. STONE QUARRY (2.40 Ha)
RISK ASSESSMENT FOR STONE QUARRY (2.40 Ha) Gat no. 85, A/p Karanjvihire, Tahsil Khed, District Pune, Maharashtra OF M/s Shankar Ramchandra Earthmovers Pvt. Ltd. Risk Assessment for Stone Quarry Mining
More informationENVIRONMENTAL MANAGEMENT PLAN
ENVIRONMENTAL MANAGEMENT PLAN CONTENTS OF ENVIRONMENTAL MANAGEMENT PLAN Chapter Title Page No. 1. INTRODUCTION 1-4 2. PROJECT PROPONENT 1 2.1 Project Location and Accessibility 1 2.2 Infrastructure and
More informationRatdi Limestone (Building) Mine Location Near Village- Ratdi, Taluka & district Porbandar, (Gujarat) Latitude. 9.0m RL.
PRE-FEASIBILITY REPORT 1. EXECUTIVE SUMMARY: Particulars Details Project Name Ratdi Limestone (Building) Mine Location Near Village- Ratdi, Taluka & district Porbandar, (Gujarat) Latitude 21 0 73 73.4
More informationForm 1 as per EIA Notification 2006 for Meyyur Rough Stone Quarry of Thiru.N.Suresh Meyyur Village, Tiruvannamalai Taluk and District and Tamilnadu
Form 1 as per EIA tification 2006 for Meyyur Rough Stone Quarry of Thiru.N.Suresh Meyyur Village, Tiruvannamalai Taluk and District and Tamilnadu Application Form for Obtaining Environmental Clearance
More informationPre- FEASIBILITY REPORT
Pre- FEASIBILITY REPORT In Respect Of KAIPADAR NEW BUILDING STONE QUARRY (GA) OVER 2.50 ACRES OR 1.00 HA IN VILLAGE KAIPADAR, KHURDA TAHASIL OF KHURDA DISTRICT, ODISHA (For the Financial Year-2015-16 to
More informationProposed Terms of Reference for EIA studies
Proposed Terms of Reference for EIA studies 1(a): STANDARD TERMS OF REFERENCE FOR CONDUCTING ENVIRONMENT IMPACT ASSESSMENT STUDY FOR NON-COAL MINING PROJECTS AND INFORMATION TO BE INCLUDED IN EIA/EMP REPORT
More informationPRE FEASIBILITY REPORT
PRE FEASIBILITY REPORT. 23 TABLE OF CONTENT Sr. No. Content Page No. 1.0 Executive Summary 25 2.0 Introduction of Project and Background Information 26 3.0 Project Description 28 4.0 Site Analysis 33 5.0
More informationPROPOSED TERMS OF REFERENCE
Annexure-IV PROPOSED TERMS OF REFERENCE 1.0 Proposed Scope of Work for EIA Study The components of the EIA study include: Detailed description of all elements of the project activities (existing and proposed
More informationPRE-FEASIBILITY REPORT
PRE-FEASIBILITY REPORT S. NO. CONTENTS PAGE NO. 1.0 EXECUTIVE SUMMARY 1.1 ENVIRONMENTAL MANAGEMENT PLAN 2 1.1.1 AIR QUALITY MANAGEMENT 2 1.1.2 WATER QUALITY MANAGEMENT 2 1.1.3 NOISE QUALITY MANAGEMENT
More informationPRE-FEASIBILITY REPORT
PRE-FEASIBILITY REPORT OF MASONRY MINING PROJECT (M.L. No. 107/02, ML Area: 1.0 ha) At Near Village-Banar Tehsil- Kotputli District - Jaipur (Raj.) PROJECT PROPONENT R/o Navratan Apartment, Plot No. 7A,
More informationENVIRONMENT MANAGEMENT PLAN
1.0 INTRODUCTION ENVIRONMENT MANAGEMENT PLAN The Environment Management Plan has been developed with a view to bring down the levels of impacts during proposed mining activities In each of the areas of
More informationPre- FEASIBILITY REPORT
Pre- FEASIBILITY REPORT In Respect Of (For the Financial Year-2015-16 to 2019-20) Prepared on Behalf of SRI ANTARYAMI BISWAL Chhend, Rourkela, Dist-Sundargarh, Odisha PREPARED BY The Techno Chamber, Plot
More informationProject Name: Nangal (M.L. No. 134/03) Masonary Stone Mine PRE- FEASIBILITY REPORT
PRE- FEASIBILITY REPORT 1.0 EXECUTIVE SUMMARY 1.1 Executive Summary The proposed mining project falls under Category A Project or activity 1(a) as per EIA Notifications 2006 and amended thereof due to
More informationCONTENT LIST PRE-FEASIBILITY REPORT S. NO. CONTENTS PAGE NO. 1.0 EXECUTIVE SUMMARY 1
CONTENT LIST PRE-FEASIBILITY REPORT S. NO. CONTENTS PAGE NO. 1.0 EXECUTIVE SUMMARY 1 2.0 INTRODUCTION OF THE PROJECT/ BACKGROUND INFORMATION 3 (i) IDENTIFICATION OF PROJECT & PROJECT PROPONENT 3 (ii) BRIEF
More informationINDEX 1.0 EXECUTIVE SUMMARY... 23
INDEX 1.0 EXECUTIVE SUMMARY... 23 2.0 INTRODUCTION OF THE PROJECT/ BACKGROUND INFORMATION 24 2.1 IDENTIFICATION OF PROJECT AND PROJECT PROPONENT... 24 2.2 BRIEF DESCRIPTION OF THE NATURE OF PROJECT...
More informationApplication Form for Obtaining Environmental Clearance from State Level Environment Impact Assessment Authority (SEIAA) Tamilnadu
Form 1 as per EIA tification 2006 for Vengadampatti Part-2 Rough Stone, Jelly and Gravel Quarry of Tmt. B.Lakshmi Rajam, Vengadampatti Part-2 Village, Alangulam Taluk, Tirunelveli District and Tamilnadu
More informationProject Details-Minor Minerals ( Rajula Building Stone)
Project Details-Minor Minerals ( Rajula Building Stone) Sr.No. Details Particulars PROPOSAL 1. Name of Lease Holder Dineshbhai Laljibhai Sarvaiya 2. Location address At Village : Rajula, Ta : Rajula, Dist
More informationTOR for Synthetic Organic Chemicals ToR for EIA studies in respect of the synthetic organic chemicals industry may include, but not limited to the
TOR for Synthetic Organic Chemicals ToR for EIA studies in respect of the synthetic organic chemicals industry may include, but not limited to the following: 1 Executive summary of the project giving a
More informationPRE FEASIBILITY REPORT & ENVIRONMENT MANAGEMENT PLAN
PRE FEASIBILITY REPORT & ENVIRONMENT MANAGEMENT PLAN Of COLOUR GRANITE MINE 1.000 HA SURVEY NO: 186/1 OF KUPPIGANIPALLI VILLAGE, GUDUPALLI MANDAL, CHITTOOR DISTRICT, ANDHRA PRADESH. Proposed By M/s. SREE
More informationBASIC CHECKLIST REQUIRED FOR SUBMISSION OF APPLICATION PARTICULARS
2 BASIC CHECKLIST REQUIRED FOR SUBMISSION OF APPLICATION SR. NO. PARTICULARS YES/ NO Page no. 1 2 3 Is the application contain covering letter by the project proponent addressed to Member Secretary, SEIAA?
More informationPRE FEASIBILITY REPORT
PRE FEASIBILITY REPORT PATHARPUNJI STONE QUARRY (PLOT-14) Village: Patharpunji Tahasil: Sheragada, District: Ganjam, State: Odisha Lease Area 1.080 Ha Screening Category B2 Sri Ramesh Swain S/o-Charan
More informationRISK ASSESSMENT REPORT
RISK ASSESSMENT REPORT Submitted by: M/s D.D. Bricks Co. Prop. : Harbhagwan Village: Mohan Ke Uttar Tehsil: Guru Harsahai District: Ferozepur, Punjab (M): 0-99993-38601 Construction, operation or decommissioning
More informationProject Name: Chanawda & Bijasna (M.L. No. 209/09) Masonary Stone PRE- FEASIBILITY REPORT
Project Name: Chanawda & Bijasna (M.L. No. 209/09) Masonary Stone PRE- FEASIBILITY REPORT 1.0 EXECUTIVE SUMMARY 1.1 Executive Summary The proposed mining project falls under Category A Project or activity
More informationS/o Vishnudas Chakraborty, residence at R/o Narsinghgarh, District Rajgarh (M.P.).
RISK ASSESSMENT The Crusher stone deposit lease area is located at Village Badodiya Jagir, Tehsil - Narsinghgarh, District - Rajgarh (M.P.). 02.00 Ha quarry lease area with production of 3306 cubic meter/year
More informationAPPENDIX I. (See Paragraph-6) FORM 1
APPENDIX I (See Paragraph-6) FORM 1 (I) Basic Information S.. Item Details 1. Name of the Project/s Dankari Granite Black Stone Quarry 2. Sl. in the schedule Sairat case no- 91/ 12-13 3. Proposed capacity
More informationAPPENDIX 4. Risk Tables
APPENDIX 4 Tables Preliminary Qualitative Criteria The qualitative risk assessment criteria have been developed to identify key risks to the environment, society, heritage and business reputation. The
More informationProject Name: Chinawda (M.L. No. 276/03) Masonary Stone Mine PRE- FEASIBILITY REPORT
PFR PRE- FEASIBILITY REPORT 1.0 EXECUTIVE SUMMARY 1.1 Executive Summary The proposed mining project falls under Category A Project or activity 1(a) as per EIA Notifications 2006 and amended thereof due
More informationPROPOSAL FOR HOUSTON COUNTY BAN ON SILICA SAND MINING / PROCESSING ACTIVITY. Introduction and Assumptions
PROPOSAL FOR HOUSTON COUNTY BAN ON SILICA SAND MINING / PROCESSING ACTIVITY Introduction and Assumptions 1. The existing section 27 Mineral Extraction of the Zoning Ordinance would remain and continue
More informationForm-1, Prefeasibility Report, Mining Plan for Rough Stone for S.F.Nos.: 332/1, 321/1 &
Form-1, Prefeasibility Report, Mining Plan for Rough Stone for S.F.s.: 332/1, 321/1 & 321/3, THIRUPAIR Village, ULUNDURPET Taluk, VILUPPURAM District Tamil Nadu of THIRU.R. VIJAYAKUMAR. (Extent 0.83.50
More informationSTANDARD TEMPLATE FOR EVALUATION OF ALL PROJECTS / ACTIVITIES. 2 Name of the organization/owner. M/s.N.R.Global Granite
STANDARD TEMPLATE FOR EVALUATION OF ALL PROJECTS / ACTIVITIES S.No Information required Information to be furnished by the proponents 1 Name of the project or activity Black Granite Mines 2 Name of the
More informationTERMS OF REFERENCE FOR THE RAPID EIA STUDY FOR SHIVKAR LIGNITE BLOCK, DIST. BARMER, RAJASTHAN
1. GENERAL TERMS OF REFERENCE FOR THE RAPID EIA STUDY FOR SHIVKAR LIGNITE BLOCK, DIST. BARMER, RAJASTHAN The main objective of the EIA study is to assess the positive and negative impacts likely to accrue
More informationForm-1, Prefeasibility Report, Mining Plan for Rough Stone for S.F.No: 421/4(Part), LEMBALAKUDI Village, THIRUMAYAM Taluk, PUDUKKOTTAI
Form-1, Prefeasibility Report, Mining Plan for Rough Stone for S.F.: 421/4(Part), LEMBALAKUDI Village, THIRUMAYAM Taluk, PUDUKKOTTAI District Tamil Nadu of Thiru. S. APPAZ. (Extent 1.21.5Ha) FORM -1 (I)
More informationNUAGADA STONE QUARRY Village: Nuagada,Tahasil: Hinjilicut,District: Ganjam, State: Odisha
PRE FEASIBILITY REPORT NUAGADA STONE QUARRY Village: Nuagada,Tahasil: Hinjilicut,District: Ganjam, State: Odisha Sri Kailash Chandra Goud At-Sompur PO- Hinjilicut Dist: Ganjam (Odisha) Chapter -1 1.1 EXECUTIVE
More informationAPPENDIX I (See Paragraph -6) FORM I
APPENDIX I (See Paragraph -6) FORM I (I) Basic Information: Sl.. Item Details 1 Name of the project/s Removal of sand from Sand bar SB-G2 2 S.. in the schedule G 3 Proposed capacity / area/length / tonnage
More informationAppendix I. Form 1 BASIC INFORMATION GRANITE MINING PROJECT VILLAGE KHARDA KI DHANI, TEHSIL ROHAT, DISTRICT PALI, RAJASTHAN
Appendix I Form 1 BASIC INFORMATION GRANITE MINING PROJECT VILLAGE KHARDA KI DHANI, TEHSIL ROHAT, DISTRICT PALI, RAJASTHAN AREA: 1.0 HECT (NON FOREST LAND) ML: 56/2000 PRODUCTION CAPACITY: 46,653 TPA PROJECT
More informationDefinition of Tower from the Bradley County Zoning Resolution
Definition of Tower from the Bradley County Zoning Resolution 43. TOWER. Any outdoor structure designed and constructed to support one (1) or more transmitting or receiving devices for telephone, radio
More informationENVIRONMENTAL MANAGEMENT PLAN. Nilaya Hills/ Heights Promoted by M/s RBS Developers (Group Housing & Commercial Building Project)
ENVIRONMENTAL MANAGEMENT PLAN Of Nilaya Hills/ Heights Promoted by M/s RBS Developers (Group Housing & Commercial Building Project) at Khasra Nos. 1353Min,1354Min,1355, 1356, 1358, 1357, 1587 Ka, 1587Kha,
More informationRISK ASSESSMENT REPORT
RISK ASSESSMENT REPORT Submitted by: Rakesh Kumar, Partner M/s Maluka Bricks Industry Village Maluka, Sub-Tehsil Bhagta Bhaika, Tehsil & District Bathinda. (Punjab) (M): 0-98141-22141 1 ACTIVITY 2 1. Construction,
More informationPre Feasibility Report
Pre Feasibility Report On Proposed to install 4.0 MTPA Coal Washery At Survey No. 83/2, 14, 15, 23, 24, 26 31 Mouza Sasti (Panderpauni) Tahsil Rajura, District Chandrapur. Submitted to MINISTRY OF ENVIRONMENT,
More informationAbout Pure Earth and the Toxic Site Identification Program
About and the Toxic Site Identification Program is a New York based not-for-profit organization that partners with governments, NGOs and community groups to solve life-threatening pollution problems in
More informationAPPLICATION (FORM-1, PRE-FEASIBILITY REPORT)
APPLICATION (FORM-1, PRE-FEASIBILITY REPORT) Environmental Clearance For Minor Mineral Mine Rampuri Stone Mine Mining Lease Area: 4.85Ha, Proposed Production: 50,107 TPA Quartzite AT Village- Rampuri,
More informationProposal for a RECOMMENDATION OF THE EUROPEAN COMMISSION
EUROPEAN COMMISSION Brussels, XXX [ ] (2013) XXX draft Proposal for a RECOMMENDATION OF THE EUROPEAN COMMISSION Providing minimum principles for the exploration and production of hydrocarbons (especially
More information