Chapter 5 Project Scope Management (PMBOK Guide)
|
|
- Nathaniel Webb
- 7 years ago
- Views:
Transcription
1 Chapter 5 Project Scope Management (PMBOK Guide) h d j bi Mohammad A. Rajabi Dept. of Geomatics Eng., University of Tehran Tel: , Cell: marajabi@ut.ac.ir Homepage:
2 Table of Content Guide to PMBOK Mohammad A. Rajabi 2
3 Introduction Processes to ensure that all work required, and only the work required for completing the project successfully What is included/what is not included Collect requirement Define scope Create WBS Verify scope Control scope Guide to PMBOK Mohammad A. Rajabi 3
4 Guide to PMBOK Mohammad A. Rajabi 4
5 5.1 Collect Requirement Defining and documenting stakeholders Analyzing their requirements Guide to PMBOK Mohammad A. Rajabi 5
6 Inputs, Tools & Techniques, Outputs Guide to PMBOK Mohammad A. Rajabi 6
7 Data Flow Guide to PMBOK Mohammad A. Rajabi 7
8 Inputs Project charter High level requirements High level product description Stakeholder register Guide to PMBOK Mohammad A. Rajabi 8
9 Tools & Techniques Interviews Formal/informal, one on one Focus groups Pre qualified stakeholders & subject matter experts Facilitated workshop Cross functional stakeholders Group creativity techniques Guide to PMBOK Mohammad A. Rajabi 9
10 Tools & Techniques Brainstorming Nominal group technique (voting for the rank ideas) The Delphi techniques (experts answer questionnaires) Idea/mind mapping g( (commonality/differences) Affinity diagram (ideas sorted into groups) Group decision making techniques Unanimity Majority Plurality Dictatorship Guide to PMBOK Mohammad A. Rajabi 10
11 Tools & Techniques Questionnaires and surveys Observations Prototypes Guide to PMBOK Mohammad A. Rajabi 11
12 Outputs Requirement documentation Unambiguous (measurable & testable), Traceable, Consistent, Acceptable to key stakeholders Business needs Business/project objectives Functional/non functional requirements Acceptance criteria Business rules Impacts to other areas of organization Support & training requirements Assumptions & constraints Guide to PMBOK Mohammad A. Rajabi 12
13 Outputs Requirements Management Plans How requirement activities are planned, tracked & reported Configuration Management Requirement prioritization Product metrics Traceability structure Requirements Traceability Matrix Business needs, opportunities, goals, objectives Project objectives Project scope/wbs deliverables Product design Product development Test strategy/test scenarios High level requirements to more detailed requirements Guide to PMBOK Mohammad A. Rajabi 13
14 5.2 Define Scope Guide to PMBOK Mohammad A. Rajabi 14
15 Data Flow Guide to PMBOK Mohammad A. Rajabi 15
16 Inputs Project charter Requirements documentation Organizational Process Assets Policies, procedures, templates Project files from past projects Lesson learned Guide to PMBOK Mohammad A. Rajabi 16
17 Expert tjudgment Tools & Techniques Other units in the organization Consultants Stakeholders Professional/technical associations Industry groups Subject matter experts Product analysis Alternatives identification Facilitated workshops Guide to PMBOK Mohammad A. Rajabi 17
18 Outputs Project scope statement t t Scope description Acceptance criteria Deliverables Exclusions Constraints Assumptions Project document updates Stakeholder register Requirements documentation Requirements traceability matrix Guide to PMBOK Mohammad A. Rajabi 18
19 5.3 Create WBS Guide to PMBOK Mohammad A. Rajabi 19
20 Data Flow Guide to PMBOK Mohammad A. Rajabi 20
21 Inputs Project scope statement Requirements documentation Organizational process assets Policies, procedures, templates Project files from past projects Lesson learned Guide to PMBOK Mohammad A. Rajabi 21
22 Tools &Techniques Decomposition Identifying and analyzing deliverables Structuring and organizing the WBS Decomposing high level WBS into low level level components Developing and assigning i identification ifi i codes Verifying the degree of decomposition Guide to PMBOK Mohammad A. Rajabi 22
23 Sample WBS (by work package) Guide to PMBOK Mohammad A. Rajabi 23
24 Sample WBS (by phase) Guide to PMBOK Mohammad A. Rajabi 24
25 Sample WBS (by deliverables) Guide to PMBOK Mohammad A. Rajabi 25
26 Outputs WBS WBS dictionary Code of identifier Description of work Responsible organization List of scheduled d milestone Associated schedule activities Resources required Cost estimates Quality requirements Acceptance criteria i Technical references Contract information Guide to PMBOK Mohammad A. Rajabi 26
27 Outputs Scope baseline Project scope statement WBS WBS dictionary Project document updates Guide to PMBOK Mohammad A. Rajabi 27
28 5.4 Verify Scope Guide to PMBOK Mohammad A. Rajabi 28
29 Data Flow Guide to PMBOK Mohammad A. Rajabi 29
30 Inputs Project Management Plan Project scope statement WBS WBS dictionary Requirement Documentation Requirement traceability Matrix Validated deliverables Guide to PMBOK Mohammad A. Rajabi 30
31 Tools & Techniques Inspection Measuring, examining, verifying work vs. requirements & acceptable criteria Guide to PMBOK Mohammad A. Rajabi 31
32 Outputs Acceptable deliverables Change requests Project document updates Guide to PMBOK Mohammad A. Rajabi 32
33 Control Scope Guide to PMBOK Mohammad A. Rajabi 33
34 Data Flow Guide to PMBOK Mohammad A. Rajabi 34
35 Inputs Project management plan Scope baseline Scope management plan Change management plan Configuration management plan Requirement management plan Work performance information Requirements documentation Requirements traceability matrix Organizational process assets Existing formal/informal scope control policies, procedures Monitoring/reporting methods Guide to PMBOK Mohammad A. Rajabi 35
36 Tools & Techniques Variance analysis Determining cause and degree of variance vs. scope baseline Corrective/preventive actions Guide to PMBOK Mohammad A. Rajabi 36
37 Outputs Work performance measurements Organizational Process Assets updates Causes of variances Corrective action chosen, reasons Lesson learned Change requests Project management plan updates Scope baseline updates Other baseline (cost, schedule, ) updates Project document updates Guide to PMBOK Mohammad A. Rajabi 37
Project Scope Management in PMBOK made easy
By Dr. TD Jainendrakumar The main objective of any project is to fulfill the scope of the project on time and within the budget. What is Project Scope? Scope refers to all the work involved in creating
More informationIT Project Management Methodology. Project Scope Management Support Guide
NATIONAL INFORMATION TECHNOLOGY AUTHORITY - UGANDA IT Project Management Methodology Project Scope Management Support Guide Version 0.3 Version Date Author Change Description 0.1 23 rd Mar, 2013 Gerald
More informationChapter 4 Project Integration Management (PMBOK Guide)
Chapter 4 Project Integration Management (PMBOK Guide) h d j bi Mohammad A. Rajabi Dept. of Geomatics Eng., University of Tehran Tel: +98 21 8833 4341, Cell: +98 912 132 5823 Email: marajabi@ut.ac.ir Homepage:
More informationPartnering for Project Success: Project Manager and Business Analyst Collaboration
Partnering for Project Success: Project Manager and Business Analyst Collaboration By Barbara Carkenord, CBAP, Chris Cartwright, PMP, Robin Grace, CBAP, Larry Goldsmith, PMP, Elizabeth Larson, PMP, CBAP,
More informationChapter 6. (PMBOK Guide)
Chapter 6 Project Time Management (PMBOK Guide) Mohammad A. Rajabi Dept. of Geomatics Eng., University it of Th Tehran Tel: +98 21 8833 4341, Cell: +98 912 132 5823 Email: marajabi@ut.ac.irac ir Homepage:
More informationQuick Reference Guide Interactive PDF Project Management Processes for a Project
Project Processes for a Project Click the Knowledge Area title (below and left in blue underline) to view the details of each Process Group. Project Process Groups and Knowledge Areas Mapping Project Process
More informationIntegration Mgmt / Initiating Process Group 4.1 Develop Project Charter
1 Mgmt / Initiating Process Group 4.1 Develop Project Charter Project statement of work Business case Agreements Facilitation techniques Project charter 26/02/2013 18:23:36 1 2 Mgmt / Planning Process
More informationChapter 7. (PMBOK Guide)
Chapter 7 Project Cost Management (PMBOK Guide) Mohammad A. Rajabi Dept. of Geomatics Eng., University it of Th Tehran Tel: +98 21 8833 4341, Cell: +98 912 132 5823 Email: marajabi@ut.ac.irac ir Homepage:
More informationThe 10 Knowledge Areas & ITTOs
This document is part of a series that explain the newly released PMBOK 5th edition. These documents provide simple explanation and summary of the book. However they do not replace the necessity of reading
More informationA Project Manager's Book of Forms. A Companion to the PMBOK Guide. 2nd Edition
Brochure More information from http://www.researchandmarkets.com/reports/2326795/ A Project Manager's Book of Forms. A Companion to the PMBOK Guide. 2nd Edition Description: A compendium of ready made
More informationSTARTING A PROJECT. Sergey V. Nesterov MD, PhD, PMP
STARTING A PROJECT Sergey V. Nesterov MD, PhD, PMP QUESTIONS to ask at the start 1. What is the situation? 2. What do you need to do? 3. Why do you need to do it? 4. What will you do? 5. How will you do
More informationAgenda. 0 Agenda review 2 minutes. 0 Chapter of the week 50 minutes. 0 Q&A of chapter 10 minutes. 0 Break 10 minutes. 0 Exercises 25 minutes
Agenda 0 Instructor Introduction 3 minutes 0 Agenda review 2 minutes 0 Chapter of the week 50 minutes 0 Q&A of chapter 10 minutes 0 Break 10 minutes 0 Exercises 25 minutes 0 Round table 15 minutes 0 Closure
More informationProject Management Process. Prepared by Jay Knape
Project Management Process Prepared by Jay Knape PMI Project Project is... temporary endeavor undertaken to produce a unique products, service or result. UITS Project Definition For Columbus State University
More informationProject Integration Management
Integration Initiating ning Executing Monitoring & Controlling Closing 4.1 Develop Charter Statement Of Work Business Case 4.2 Develop 4.3 Direct and Manage Work 4.4 Monitor and Control Work 4.5 Perform
More informationProject Management Plan Template
Abstract: This is the project management plan document for . This is a controlled document and should be maintained in a configuration environment. Project Management Plan Template Contents REVISION
More informationProject Management Professional (PMP)
Project Management Professional (PMP) Duration: 5 days Course Objectives: PMI s Project Management Professional (PMP) credential is the most important industry-recognized certification for project managers.
More informationDevelop Project Charter. Develop Project Management Plan
Develop Charter Develop Charter is the process of developing documentation that formally authorizes a project or a phase. The documentation includes initial requirements that satisfy stakeholder needs
More informationhttp://www.io4pm.org IO4PM - International Organization for Project Management
THE ONLY BOOK CAN SIMPLY LEARN PROJECT MANAGEMENT! Page 1 Contents ABOUT THE AUTHOR... 3 WHAT IS PROJECT MANAGEMENT?... 5 ORGANIZATIONAL INFLUENCES AND PROJECT LIFECYCLE... 11 PROJECT MANAGEMENT PROCESSES...
More informationPROJECT MANAGEMENT PLAN CHECKLIST
PROJECT MANAGEMENT PLAN CHECKLIST The project management plan is a comprehensive document that defines each area of your project. The final document will contain all the required plans you need to manage,
More informationA Guide To The Project Management Body of Knowledge (PMBOK) Significant Changes from the 3 rd edition to the 4 th edition
A Guide To The Project Body of Knowledge (PMBOK) Significant Changes from the 3 rd edition to the 4 th edition Major Changes The adoption of the verb-noun format for process names Amplification as to Enterprise
More informationInput, Output and Tools of all Processes
1 CIS12-3 IT Project Management Input, Output and Tools of all Processes Marc Conrad D104 (Park Square Building) Marc.Conrad@luton.ac.uk 26/02/2013 18:22:06 Marc Conrad - University of Luton 1 2 Mgmt /
More informationPMP Project Management Professional Study Guide, Third Edition
PMP Project Management Professional Study Guide, Third Edition Joseph Phillips McGraw-Hill is an independent entity from the Project Management Institute, Inc. and is not affiliated with the Project Management
More informationBusiness Analyst Work Plan. Presented by: Billie Johnson, CBAP CSM
Business Analyst Work Plan Presented by: Billie Johnson, CBAP CSM Agenda Topic Introduction Overview of a Business Analysis Work Plan Initiating a Business Analysis Effort Components of the Business Analysis
More informationCourse Outline. Foundation of Business Analysis Course BA30: 4 days Instructor Led
Foundation of Business Analysis Course BA30: 4 days Instructor Led Prerequisites: No prerequisites - This course is suitable for both beginner and intermediate Business Analysts who would like to increase
More informationPMI Risk Management Professional (PMI-RMP ) - Practice Standard and Certification Overview
PMI Risk Management Professional (PMI-RMP ) - Practice Standard and Certification Overview Sante Torino PMI-RMP, IPMA Level B Head of Risk Management Major Programmes, Selex ES / Land&Naval Systems Division
More informationKnowledge Area Inputs, Tools, and Outputs. Knowledge area Process group/process Inputs Tools Outputs
HUMAN RESOURCE MANAGEMENT Organizational planning Staff Acquisition Project interfaces such as organizational interfaces, technical interfaces and interpersonal interfaces. Staffing requirements Staffing
More informationPROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME >
PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME > Date of Issue: < date > Document Revision #: < version # > Project Manager: < name > Project Management Plan < Insert Project Name > Revision History Name
More information- ATTACHMENT - PROGRAM MANAGER DUTIES & RESPONSIBILITIES MARYLAND STATE POLICE W00B0400021
- ATTACHMENT - PROGRAM MANAGER DUTIES & RESPONSIBILITIES MARYLAND STATE POLICE W00B0400021 About this document this is a detailed description of typical Project Manager (PM) duties, responsibilities, and
More informationPMP Examination Tasks Puzzle game
PMP Examination Tasks Puzzle game Here is a great game to play to test your knowledge of the tasks you will be tested on in the actual examination. What we have done is take each of the domain tasks in
More informationRequirements Definition and Management Processes
Software Engineering G22.2440-001 Session 1 Sub-Topic 1 Requirements Definition & Management Processes and Tools Dr. Jean-Claude Franchitti New York University Computer Science Department Courant Institute
More informationTime Management. Herb Pollard III
Time Management A Small Business Perspective Herb Pollard III Project Manager for Time Management - Pollard PMI Slide 1 Introduction: Time Management - Pollard PMI Slide 2 Project Phases and the Areas
More informationAdvanced Project Management Training Course
Advanced Project Management Training Course 1-34 Advanced Project Management Crea/ng the Scope Baseline 2-34 Crea/ng the Scope Baseline Module 1 Introduction Module 2 Creating the Project Charter Module
More informationMaking project management indispensable for business results. Project Management 101
Making project management indispensable for business results. Project Management 101 Donald E. Moore, MBA, PMP, President of PMI NB Kelly Barter, Chapter Manager of PMI NB AGM April 28, 2011 Topics of
More informationATTACHMENT 3 SPS PROJECT SENIOR PROGRAM MANAGER (SPM) DUTIES & RESPONSIBILITIES
1. ROLE DEFINITIONS ATTACHMENT 3 SPS PROJECT SENIOR PROGRAM MANAGER (SPM) DUTIES & RESPONSIBILITIES The purpose of this section is to distinguish among the roles interacting with the SPM obtained through
More informationSoftware Engineering. Session 3 Main Theme Requirements Definition & Management Processes and Tools Dr. Jean-Claude Franchitti
Software Engineering Session 3 Main Theme Requirements Definition & Management Processes and Tools Dr. Jean-Claude Franchitti New York University Computer Science Department Courant Institute of Mathematical
More informationThe Plan s Journey From Scope to WBS to Schedule
The Plan s Journey From Scope to WBS to Schedule Presented by: Rick Clare, CBAP, PMP, OCP, CSM PM Centers USA, LLC. 2013 Company Background Consulting and Training (Virtual, Public and Private Training)
More informationChapter 01. PMP work book answers V3 2012. Exercise 01: Question Answer Question Answer
Chapter 01 Exercise 01: Question Answer Question Answer i. Procurement Management KA ii. Integration Management KA iii. Cost Management KA iv. HR Management KA v. Risk Management KA vi. Quality Management
More informationProject Risk Management
Project Risk Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Risk Management
More informationSCOPE MANAGEMENT PLAN <PROJECT NAME>
SCOPE MANAGEMENT PLAN TEMPLATE This Project Scope Management Plan Template is free for you to copy and use on your project and within your organization. We hope that you find this template useful and welcome
More informationProject Management Body of Knowledge (PMBOK) (An Overview of the Knowledge Areas)
Project Management Body of Knowledge (PMBOK) (An Overview of the Knowledge Areas) Nutek, Inc. 3829 Quarton Road, Suite 102 Bloomfield Hills, Michigan 48302, USA. Phone: 248-540-4827, Email: Support@Nutek-us.com
More informationBAL2-1 Professional Skills for the Business Analyst
1 BAL2-1 Professional Skills for the Business Analyst OVERVIEW This course trains participants to help business clients articulate their needs and wants, and to document them clearly, concisely, and completely.
More informationManaging IT Projects. Chapter 2 The PMI Framework
Managing IT Projects Chapter 2 The PMI Framework The PMI Framework The Project Management Institute,USA is an internationally acclaimed organization Devoted to Creation & sharing of knowledge in the area
More information5.1 Project Control Overview
5.1 Project Control Overview Project Control is a formal process in project management. In most respects, there is not a lot of room for creativity in the Control Phase of project management. The PMBOK
More informationPMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING
PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING 03-23-05 Christine Green, PMI PMBOK and Estimating EDS, Delivery
More informationSoftware Requirements, Third Edition
j Microsoft Software Requirements, Third Edition Karl Wiegers and Joy Beatty Contents Introduction Acknowledgments xxv xxxi PART I SOFTWARE REQUIREMENTS: WHAT, WHY, AND WHO Chapter 1 The essential software
More informationTime Management. Part 2 Work Breakdown Structure (WBS) Review. Richard Boser
Time Management Part 2 Work Breakdown Structure (WBS) Review Richard Boser WBS Planning Process PMBOK WBS is deliverable-oriented grouping of components that organizes and defines the total scope of the
More informationITS Projects Systems Engineering Process Compliance Checklist
ITS Projects Systems Engineering Process Compliance Checklist FHWA Final Rule (23 CFR 940) This checklist is to be completed by the MDOT or LPA Project Management Staff. Please refer to the accompanying
More informationThis alignment chart was designed specifically for the use of Red River College. These alignments have not been verified or endorsed by the IIBA.
Red River College Course Learning Outcome Alignment with BABOK Version 2 This alignment chart was designed specifically for the use of Red River College. These alignments have not been verified or endorsed
More informationCrosswalk Between Current and New PMP Task Classifications
Crosswalk Between Current and New PMP Task Classifications Domain 01 Initiating the Project Conduct project selection methods (e.g., cost benefit analysis, selection criteria) through meetings with the
More informationOverview of A Guide to the Project Management Body of Knowledge (PMBOK Guide) Fourth Edition
Overview of A Guide to the Project Management Body of Knowledge (PMBOK Guide) Fourth Edition Topics for Discussion PMI Foundational Standards Harmonization of PMI s Foundational Standards Top 10 changes
More informationPROJECT PLAN TEMPLATE
Treasury Board of Canada Secretariat Secrétariat du Conseil du Trésor du Canada Enhanced Management Framework for Information Management/Information Technology PROJECT PLAN TEMPLATE Document Revision Draft
More informationIntroduction to the ITS Project Management Methodology
Introduction to the ITS Project Management Methodology In September 1999 the Joint Legislative Committee on Performance Evaluation and Expenditure Review (PEER) produced a report entitled Major Computer
More information<name of project> Software Project Management Plan
The document in this file is adapted from the IEEE standards for Software Project Management Plans, 1058-1998, which conforms to the requirements of ISO standard 12207 Software Life Cycle Processes. Tailor
More informationCPET 545 SOA and Enterprise Applications. SOA Final Project Project Scope Management 11-13-2008
CPET 545 SOA and Enterprise Applications Examples of Tasks and Subtasks o SOA Project Plan (checklist) Statement of work Resources Schedule Risk plan SOA Final Project Project Scope Management 11-13-2008
More informationPerform Business Analysis Professionally. c o m p e t e n c e f o r g r o w t h
Perform Business Analysis Professionally R PMCC c o m p e t e n c e f o r g r o w t h 01 REGISTER 02 ENGAGE 03 CERTIFICATION Demand is growing for Professional Business Analysis SM The PMI-PBA highlights
More informationProject Time Management
Project Skills Team FME www.free-management-ebooks.com ISBN 978-1-62620-981-3 Copyright Notice www.free-management-ebooks.com 2014. All Rights Reserved ISBN 978-1-62620-981-3 The material contained within
More informationChapter 10. Project Communication Management. Mohammad A. Rajabi. Tel: +98 21 8833 4341, Cell: +98 912 132 5823. Homepage: http://www.marajabi.
Chapter 10 Project Communication Management (PMBOK Guide) Mohammad A. Rajabi Dept. of Geomatics Eng., University it of Th Tehran Tel: +98 21 8833 4341, Cell: +98 912 132 5823 Email: marajabi@ut.ac.irac
More informationYour Agile Team s Indispensible Asset
Agile / Scrum Training Lean Software Development Agile Organizational Metrics Executive Coaching Improved Team Dynamics Improved Efficiency! Your Agile Team s Indispensible Asset The Agile Business Analyst
More informationChapter 5: Project Scope Management. Information Technology Project Management, Fifth Edition
Chapter 5: Project Scope Management Information Technology Project Management, Fifth Edition What is Project Scope Management? Scope refers to all the work involved in creating the products of the project
More information21. Earned Value deals with: a. EV Scope b. PV Time c. AC Cost 22. Portfolios are organized around business goals. 23. Take stern action against
PMP Short Notes Based on PMBOK Guide fifth edition By Dilip Chaturvedi,PMP Email id: info@justpmp.com To know about our training schedule, please visit www.justpmp.com 1. Communication is more complex
More informationFamily Computer Centre
PMP - Project Professional 35 Contact Hours Comprehensive Training Program Designed on the basis of Project Body of Knowledge (PMBOK Guide) Family Computer Centre Ground Floor, Al Rayyan Complex P. O Box:
More informationProject Management Master s Certificate Program
Project Management Master s Certificate Program The Master s Certificate in Project Management was created for professional project managers who want to advance their career to the next level. This certificate
More informationCertification Preparation Course LATVIKON (R.E.P.)Centre
PMP Certification Preparation Course LATVIKON (R.E.P.)Centre ABOUT THIS COURSE Your ability as a project manager to demonstrate best practices in Project Management both on the job and through professional
More informationA Comparison of PMI s PMBOK Guide Versions 4 & 3
PM WORLD TODAY FEATURED PAPER MAY 2009 A Comparison of PMI s PMBOK Guide Versions 4 & 3 By Germán Bernate The Project Management Institute PMI announced on December 31, 2008 the availability of PMBOK Version
More informationProject Lifecycle Management (PLM)
Project Lifecycle Management (PLM) Process or Tool? Why PLM? Project Definition Project Management NEW REQUEST/ INITIATIVES SUPPORT (Quick fixes) PROJECT (Start Finish) ONGOING WORK (Continuous) ENHANCEMENTS
More informationOverview of: A Guide to the Project Management Body of Knowledge (PMBOK Guide) Fourth Edition
Overview of A Guide to the Project Management Body of Knowledge (PMBOK Guide) Fourth Edition Overview of: A Guide to the Project Management Body of Knowledge (PMBOK Guide) Fourth Edition 1 Topics for Discussion
More informationPMI Risk Management Professional (PMI-RMP) Exam Content Outline
PMI Risk Management Professional (PMI-RMP) Exam Content Outline Project Management Institute PMI Risk Management Professional (PMI-RMP) Exam Content Outline Published by: Project Management Institute,
More informationThe purpose of this course is to provide practical assistance for defining and managing project scope.
Scope Definition and Scope Management Purpose - To provide practical assistance for defining and managing project scope. This course will focus on tips for creating a scope statement rather than a step-by-step
More informationTools for Project Management, Workshops and Consulting
Tools for Project Management, Workshops and Consulting A must-have compendium of essential tools and techniques by Nicolai Andler Second revised and enlarged edition, 2011 Brief contents/overview of tools
More informationDesign Document Version 0.0
Software Development Templates Design Document Version 0.0 Description of Project DOCUMENT NO: VERSION: CONTACT: EMAIL: Ivan Walsh DATE: 4/13/2004 Distribution is subject to copyright. Design Document
More information2-Day Workshop Project JumpStart The Workshop Designed to Launch Projects Faster
2-Day Workshop Project JumpStart The Workshop Designed to Launch Projects Faster Traditional Classroom / Onsite Course No. 665 Duration: 2 days Credits: 14 PDUs / 1.4 CEUs Prerequisites Twelve hours of
More informationBusiness Analyst Community. AmerisourceBergen
Business Analyst Community AmerisourceBergen Introduction Results-oriented leader with proven success in managing and leading successful business analysis communities. With 18 years of business experience
More informationSOFT 423: Software Requirements
SOFT 423: Software Requirements Week 3 Class 1 Finish Elicitation & Start Analysis SOFT 423 Winter 2015 1 Last Class Questionnaires Document Inspection Requirements Stripping Use Cases Scenarios SOFT 423
More informationOrganization. Project Name. Project Overview Plan Version # Date
Project Overview Plan Template Organization Project Name Project Overview Plan Version # Date REVISION HISTORY VERSION # REVISION DATE COMMENT 1 APPROVALS: Authorized Signature DATE 2 Table of Contents
More informationPMI PMP & CAPM sertifikacija
PMI PMP & CAPM sertifikacija Priprema članova PMI Serbia Chapter-a Project Integration Management припремио: 28.Јануар 2014. Београд Милан Шмигић, ПМП board@pmi-serbia.rs www.pmi-serbia.rs PMBOK Intro
More informationPMP SAMPLE QUESTIONS BASED ON PMBOK 5TH EDITION
PMP SAMPLE QUESTIONS http://www.tutorialspoint.com/pmp-exams/pmp_sample_questions.htm Copyright tutorialspoint.com BASED ON PMBOK 5TH EDITION Here are 200 more objective type sample questions and their
More informationApplication of Standard Project Management Processes in Fiber Optic Cable Plant Project Management. Introduction. Alfred Sankara, DigiBridge TelCo
Application of Standard Project Management Processes in Fiber Optic Cable Plant Project Management Alfred Sankara, DigiBridge TelCo Introduction The Project Management Institute (PMI) is the world's leading
More informationProject Management Standards: A Review of Certifications/Certificates
Project Standards: A Review of Certifications/Certificates Standards for Project Supporting Certification and Certificates Certificate Certification The Project Body of Knowledge PMBOK Guide Projects in
More informationDraft Requirements Management Plan
BAO111: Core Competencies for the Business Analyst Draft Requirements Management Plan 1.0 INTRODUCTION 1.1 Purpose This document outlines requirements roles and responsibilities, presents a stakeholder
More informationProject Management. Training Courses
Project Management Certification and Training Courses Table of Contents Page On Site Training 4 Custom Course Development and Training 5 Project Management Training and Certification Courses Project Management
More informationA STRUCTURED APPROACH TO ORGANIZATIONAL IMPROVEMENT
http://www.psu.edu/president/pia/innovation/ INNOVATION INSIGHT SERIES NUMBER 7 A STRUCTURED TO ORGANIZATIONAL IMPROVEMENT Penn State s IMPROVE model is a structured approach to facilitate problem solving,
More informationInitiating Forms COPYRIGHTED MATERIAL 1.0 INITIATING PROCESS GROUP
1 Initiating Forms 1.0 INITIATING PROCESS GROUP The purpose of the initiating process group is to authorize a project, provide a high-level definition of the project, and identify stakeholders. There are
More informationMinnesota Health Insurance Exchange (MNHIX)
Minnesota Health Insurance Exchange (MNHIX) 1.2 Plan September 21st, 2012 Version: FINAL v.1.0 11/9/2012 2:58 PM Page 1 of 87 T A B L E O F C O N T E N T S 1 Introduction to the Plan... 12 2 Integration
More informationModule 3: The Project Planning Stage
Overview Once you've initiated the project and gathered all relevant information, you'll then begin planning your project. The planning stage depends on the size of your project, how much information you
More information44-76 mix 2. Exam Code:MB5-705. Exam Name: Managing Microsoft Dynamics Implementations Exam
44-76 mix 2 Number: MB5-705 Passing Score: 800 Time Limit: 120 min File Version: 22.5 http://www.gratisexam.com/ Exam Code:MB5-705 Exam Name: Managing Microsoft Dynamics Implementations Exam Exam A QUESTION
More informationProject Management Certificate (IT Professionals)
Project Management Certificate (IT Professionals) Whether your field is architecture or information technology, successful planning involves a carefully crafted set of steps to planned and measurable goals.
More informationPROJECT MANAGEMENT PROFESSIONAL CERTIFIED ASSOCIATE IN PROJECT MANAGEMENT (PMP & CAPM) EXAM PREPARATION WORKSHOP
TSE015 PROJECT MANAGEMENT PROFESSIONAL CERTIFIED ASSOCIATE IN PROJECT MANAGEMENT (PMP & CAPM) EXAM PREPARATION WORKSHOP Course Outline I. Introduction and Course Objectives A. About PMI B. PMP and CAPM
More informationTHE PROJECT MANAGEMENT KNOWLEDGE AREAS
THE PROJECT MANAGEMENT KNOWLEDGE AREAS 4. Project Integration Management 5. Project Scope Management 6. Project Time Management 7. Project Cost Management 8. Project Quality Management 9. Project Human
More informationPROJECT RISK MANAGEMENT
PROJECT RISK MANAGEMENT DEFINITION OF A RISK OR RISK EVENT: A discrete occurrence that may affect the project for good or bad. DEFINITION OF A PROBLEM OR UNCERTAINTY: An uncommon state of nature, characterized
More informationCPM -100: Principles of Project Management
CPM -100: Principles of Project Management Lesson E: Risk and Procurement Management Presented by Sam Lane samlane@aol.com Ph: 703-883-7149 Presented at the IPM 2002 Fall Conference Prepared by the Washington,
More informationTHE PROJECT MANAGEMENT PROCESS FROM A QUALITY MANAGEMENT PROFESSIONAL S PERSPECTIVE:
THE PROJECT MANAGEMENT PROCESS FROM A QUALITY MANAGEMENT PROFESSIONAL S PERSPECTIVE: More Than Just the Project Quality Management Knowledge Area for Successful Project Management ASQ BLUE RIDGE SECTION
More informationVALLIAMMAI ENGINEERING COLLEGE S.R.M. Nagar, Kattankulathur DEPARTMENT OF COMPUTER SCIENCE AND ENGINEERING
VALLIAMMAI ENGINEERING COLLEGE S.R.M. Nagar, Kattankulathur DEPARTMENT OF COMPUTER SCIENCE AND ENGINEERING Sub Code : CP7007 Sub Name: SOFTWARE REQUIREMENTS ENGINEERING Branch / Year : ME CSE / I Year
More informationComparing PMBOK Guide 4 th Edition, PMBOK Guide 5 th Edition and ISO 21500
Project Training Company Comparing PMBOK Guide 4 th Edition, Edition and STS Sauter Training & Simulation S.A. Avenue de la Gare 10 1003 Lausanne Switzerland Web: www.sts.ch E-mail: office@sts.ch Phone:
More informationCDC UNIFIED PROCESS PRACTICES GUIDE
Document Purpose The purpose of this document is to provide guidance on the practice of Requirements Definition and to describe the practice overview, requirements, best practices, activities, and key
More informationExamination SUBJECT. Version:
SUBJET Version: 1 Which of the following statements best describes Business nalysis? Business nalysis provides the reasoning for initiating a project. Business nalysis is the strategic part of the project
More informationPMP/CAPM Prep course. Anwers to all questions with rationale
2 Fmwk&Int. 1 C PMBOK 2012, 1.2 - What is a project 2 Fmwk&Int. 2 D PMBOK 2012, 3.7 Closing Process Group 2 Fmwk&Int. 3 D PMBOK 2012, 1.4 - Relationships Among Project/Program/Portfolio Mgmt 2 Fmwk&Int.
More informationRequirements Management John Hrastar
Requirements Management John Hrastar NASA Project Management Conference March 30-31, 2004 University of Maryland Conference Center Introduction Three aspects of requirements management Requirements in
More informationProject Management for Everyone
Project Management for Everyone Contact Information Adam Donaldson, PMP Business Management & Analysis Group Phone: (202) 994-6867 Cell: (240) 472-2171 Email: adonald@gwu.edu Objectives Basic understanding
More informationProject Management Professional (PMP) Examination Content Outline
Project Management Professional (PMP) Examination Content Outline Project Management Institute Project Management Professional (PMP) Examination Content Outline June 2015 Published by: Project Management
More information