Underground Cable Temperature Monitoring in the Real World



Similar documents
Least Cost Cable System. Strategies to Reduce Cable and Infrastructure Costs When Transitioning to an All Conduit Systems

KNOW YOUR OPTIONS: 69 KV XLPE POWER CABLE

KNOW YOUR OPTIONS: 230 KV POWER CABLES

Section kv Power Cables

Uptown Campus, Primary Electric Master Plan - Program Study State University of New York At Albany, SUCF Project No V.

IEEE POWER ENGINEERING SOCIETY CHICAGO CHAPTER THE OKONITE COMPANY WEDNESDAY JANUARY 11, 2006 JIM FITZGERALD ENGINEERING LINGO

TELUS Residential Service Conduit Requirements for Stand Alone Homes and Duplexes in Fibre Only Communities

TAN δ (DELTA) CABLE TESTING OVERVIEW AND ANSWERS TO FREQUENTLY ASKED QUESTIONS. What Is Tan δ, Or Tan Delta?

AMSC s Superconductor Cable Technologies for Electric Utilities

Electric Engineering Division FIBER CONDUIT RULES AND REGULATIONS

Network Standard Advice No. 1420C 9/6/2011

Multiple Meter Installation Amperes Per Position -Single Phase, Self-contained

Electrical for Detached Garages: Updated Feb 19, 2016 for 2015 CE Code in force Jan. 1, Underground branch circuit feeding a detached garage:

BCTC/BC Hydroʹs operational experience with Distributed Temperature Sensing (DTS) Systems for Transmission Cables. Presented by

CABLE MONITORING SOLUTION

REQUIREMENTS AND SPECIFICATIONS FOR HIGH VOLTAGE CUSTOMER BUILT FACILITIES PEPCO ENGINEERING

National Science Foundation Funds Request

345 kv Underground Report

M. GELDON Brugg Kabel CZ. Ing. D. RÚŽEK PREdistribuce. Switzerland Czech Rep. Czech Rep. Czech Rep., Switzerland Germany

Errors Related to Cable Resistance Imbalance in Three Wire RTDs

CABLE TRENCH INSTALLATION GUIDE

Real Time Monitoring of Power Cables by Fibre Optic Technologies Tests, Applications and Outlook

CHUGACH ELECTRIC ASSOCIATION, INC. Anchorage, Alaska. February 10, 2014

16300 MEDIUM VOLTAGE DISTRIBUTION

Lightning Arresters P KVA P KVA. Description & Installation

HIGH- AND EXTRA-HIGH-VOLTAGE GLOBAL CABLE SYSTEM SOLUTIONS Rely On Our Experience... Experience Our Capabilities

Top Drive Service Loops. Conventional, Enhanced and Superior Solutions for Drilling Applications

Stephen G. Whitley, Senior Vice President & Chief Operating Officer

CTI TECHNICAL BULLETIN Number 9: A publication of the Cable Tray Institute

East Central College HANSEN HALL LEVEL 300/400 RENOVATIONS PACKAGE

Monitoring Underground Power Networks

Distributed Temperature Monitoring of Energy Transmission and Distribution Systems

WIRE AND CABLE ENGINEERING GUIDE

DISCUSSION OF CROSS-LINKED POLYETHYLENE INSULATED CABLES FOR UNDERGROUND PORTIONS OF THE MIDDLETOWN-NORWALK 345 kv PROJECTS.

MEASUREMENTS OF THRUST LOAD IN CABLE SYSTEMS SEMI-RIGIDLY INSTALLED IN DUCT / MANHOLE STRUCTURES

Industrial Cable Solutions for Variable Frequency Drives

GUIDELINES FOR UTILITY INSTALLATIONS Part 1 - Wire Lines and Communications Cables

100% EMI Emission Containment

Underground Service Requirements and Instructions

Civil. 2. City of Seattle Supplement to the Specification for Road, Bridge and Municipal Construction, most current addition.

ELECTRICAL SERVICE REQUIREMENTS FOR MOBILE HOME DEVELOPMENTS

By Anne Bartosewicz, Northeast Utilities, and J. Brett Williams and Jim Hogan, Burns & McDonnell

Fault location on power cables. Fault location on power cables

Underground Transmission Lines

Lucien Antonissen Key Account Manager LIOS Technology Germany

VDE Information. Degree of Pollution, Clearances and Creepage Distances and Insulating Materials

Radial Distribution Test Feeders

CONTENTS. Yale University Design Standards. Underground Electrical Duct Bank. A. Summary. B. System Design and Performance Requirements

Q: PLEASE STATE YOUR NAME AND BUSINESS ADDRESS. A: Gerry Sheerin. Sheerin Technical, 25 Eastville Avenue, Toronto, Ontario Canada

SECTION CABLE TRAYS FOR COMMUNICATIONS SYSTEMS

CABLE ASSET MANAGEMENT PREDICT WITH CERTAINTY. Kuljit Singh BSc Honours MIEE(IET,UK) 5 June 2014

Two different types of cables are used in primary airfield lighting circuits: - unshielded cables and - shielded cables

Session 14 Cable Support Systems

Grid Solutions. PROJECT MANAGEMENT SOLUTIONS for infrastructure projects from Border States. Border States

Grounding of Electrical Systems NEW CODE: Grounding and Bonding

Electrical Design Training Class Ampacity WSDOT Winter 2008 BZA

4 IX D N E P P A Installation methods Current-carrying capacity and voltage drop for cables Reference method IET Wiring Matters

Cable Selection for Medium Voltage Capacitor Banks and Harmonic Filter Banks

MEDIUM VOLTAGE DISTRIBUTION

AC and DC Drive System Installation Information

WHY CABLE TRAY? BECAUSE A CABLE TRAY WIRING SYSTEM PROVIDES SAFE AND DEPENDABLE WAYS TO SAVE NOW AND LATER

TECHNICAL SERVICE DEPARTMENT Technical Service Bulletin Inch PowerVent LED Indicator Explanations & Troubleshooting Table

How To Test For Safety On A Power Cable

LEAD FREE FIREX. Interlock Armored Cables TECK90 and MC Industrial Cables. w w w. n e x a n s e n e r g y. c o m

Cable Tray Selection-

Gulf Cable & Electrical Ind. Co.

PRIMARY SERVICE LINE: The Company's conductors which connect the supply line with a transformer located on private property.

3. TYPES OF SERVICE AVAILABLE. 3.1 Scope

Insulation Resistance Testing of Low Voltage Cables in the Field

History of Secondary Cable Designs

Distributed Temperature Sensing using Fibre-Optics (DTS Systems)

A Method to Detect and Locate Roof Leaks Using Conductive Tapes

Hyperlinks are Inactive

2 8 k V, 1 / C, T R X L P E I N S U L A T E D, F L A T S T R A P S H I E L D E D C A B L E, C O M P R E S S E D S T R A N D I N G

State, trends and evolutions of HV/EHV power cables systems and contributions of SC B1 to their ongoing progress

APPLICATION ORIENTED DESIGN OF CABLES

Protection Systems. A UTC Fire & Security Company F Linear Heat Detector FEATURES DESCRIPTION APPLICATIONS BENEFITS

Great Lakes Data Room Case Study

TEST PLAN SUPERSEDES: None

AORC Technical meeting 2014

MCR1900 Media Converter 19-Slot Chassis

Part 1 System Modeling & Studies for Existing Systems

DIVISION 26 - ELECTRICAL SECTION CABLES FOR INSTRUMENTATION

Section 21. Telecommunication Hardware. BuyLog Catalog 21-1

Optical Cable Pre-Construction Survey. Keywords Stationary Reel Method, empty innerducts, sub-ducts, microducts, Intermediate-feed manholes

Requirements for the Attachment of Communication Cable Facilities on PPL Poles

Optimum Climate Control For Datacenter - Case Study. T. Prabu March 17 th 2009

Gas Meter Clearances and Service Installation Requirements

GroundRod AC Substation Earthing Tutorial

CUSTOMER REQUIREMENTS AT POWER SUBSTATIONS

environment briefing02

Testing and Demonstration Results of the 350m Long HTS Cable System Installed in Albany, NY

All Wires and Cables Are Not Created Equal

Nexus Technology Review -- Exhibit A

Gas Meter Clearances and Service Installation Requirements

Current valve. for AC 24 V pulse/pause control of electrical loads up to 30 kw

Underground Commercial Electric Service

Electric Service Conversion Overhead-to-Underground. Minnesota

Calculation of Underground Cable Ampacity

Transcription:

Underground Cable Temperature Monitoring in the Real World

Executive Summary Background Brain Storming Possible Causes to Duct Bank Over Heating Mitigating Duct Bank Overheating DTS Installation for Duct Bank Temperature Monitoring October Heat Storm Wrap-Up

Background (Jan 2014) Hot conditions were first noticed by Troublemen performing switching operations during early morning hours. A new circuit was needed at the substation, so the ductbank was split in two. (May 2014) While work was being performed, elevated temperatures were again observed. A temperature of 183 F was measured in an empty conduit. Duct from substation cable trench.

Brain Storming Possible Causes 1. Neutral Imbalance 2. Load Factor 3. Vault Blower 4. Soil Conditions 5. Over Crowding

Possible Causes 1. Neutral Imbalance West Wall inside M5586490 from Sub (Line Side) Panther 12kv - Gnd 9 amps Gazelle 12kv - Gnd 16 amps Cougar 12kv - Gnd 12.5 amps Elephant 12kv - Gnd 14.8 amps Jaguar 12kv - Gnd 6 amps Bison 12kv - Gnd 3 amps East Wall inside M5586490 (Load Side) Panther 12kv - Gnd 13 amps Elephant 12kv - Gnd 11.5 amps Gazelle12kv - Gnd 14.7amps Bison12kv - Gnd 14amps Cougar 12kv - Gnd 4.4amps Jaguar 12kv - Gnd 10.7amps

Possible Causes 2. Load Factor Monthly load factor was calculated for all phases of each circuit. The highest load factor from the three phases was then used as that respective circuit s load factor during simulations. Circuit Name January Monthly Load Factor July Monthly Load Factor Phase A Phase B Phase C Phase A Phase B Phase C Bison 0.723 0.725 0.730 0.717 0.700 0.708 Cheetah 0.745 0.733 0.732 0.558 0.565 0.555 Cougar 0.606 0.606 0.614 0.598 0.591 0.601 Elephant 0.574 0.576 0.569 0.756 0.753 0.764 Gazelle 0.663 0.667 0.668 0.726 0.717 0.720 Leopard 0.723 0.721 0.731 0.391 0.378 0.387 Lynx 0.503 0.482 0.529 0.402 0.459 0.456 Panther 0.509 0.502 0.499 0.671 0.666 0.663

Possible Causes 3. Vault Blower Not working since 2010. Was not the hottest vault.

Possible Causes 4. Soil Conditions Hired consultant to measure: Soil thermal resistivity, Ambient temperature, and Moisture content.

Possible Causes 4. Soil Conditions Industry Standards ICEA P-53-426 (WC 50-1976) a. Earth thermal resistivity-60, 90 and 120 C-cm/w, designated as 60 RHO through 120 RHO. AEIC CG6-2005, Section 6.1 IEEE 835-1994 (R2006)

Possible Causes 4. Soil Conditions Soil around old and new installation was tested for thermal resistivity. Maximum reading around existing conduit was found to be 353 C cm/w. Maximum reading around new conduit was found to be 250 C cm/w. A large amount of trees were present in the area of the duct banks. Large trees are known to dry out the soil, thereby increasing the soil thermal resistivity. Issue 1: Poor Soil Conditions Location Run Comments Thermal Resistivity ( C-cm/W ) Soil Percent Tempera Moisture ture (%) ( C) 1 1 Side Wall 230 25.5 0.8 1 2 Side Wall 251 26.3 1.0 1 3 Bottom of Trench 80.7 24.8 5.5 2 1 Side Wall 98.2 30.0 7.0 2 2 Side Wall 95.7 30.1 7.0 2 3 Side Wall 100 29.9 na 2 4 Bottom of Trench 117 30.1 5.4 Location Run Comments Thermal Resistivity ( C-cm/W ) Soil Percent Tempera Moisture ture (%) ( C) 1 1 North Side Wall 353 34.6 0.8 1 2 East Side Wall 319 33.7 0.9 1 3 South Side Wall 310 33.7 1.3 2 1 South Side Wall 183 38.3 3.6 2 2 East Side Wall 224 38.6 3.6 2 3 North Side Wall 243 36.3 2.4 3 1 South Side Wall 138 52.2 3.1 3 2 East Side Wall 335 46.6 3.8 3 3 North Side Wall 104 41.7 4.0

Possible Causes 5. Over Crowding of Duct Banks Existing Duct Banks: Original duct banks crossed at two locations First crossing was at a small angle, which allows the highest of mutual heating Second crossing was at 90 degrees, which allows the least amount of mutual heating Transition Duct Bank Six circuits in one duct bank Issue 2: Over Crowding of Duct Banks Issue Existing Duct Banks Transition Duct Bank

Possible Causes 5. Over Crowding of Duct Banks In the transition design, 6 circuits were together in one duct bank. High temperature of 195.4 C Issue 2: Over Crowding of Duct Banks

Solution 1: Soil Mitigation with Slurry Backfill With Native Soil Backfill Temperatures are above 90 C With 1-sack slurry Backfill All temperatures are below 90 C

Solution 1: Soil Mitigation with Slurry Backfill In order to mitigate the high thermal resistivity of the soil, a slurry backfill was used to replace the soil above the new cable duct bank installations. A thermal resistivity of 60 C cm/w was used for the slurry back fill.

Solution 2: Re-Routing of Duct Bank Duct Bank was re-routed to reduce overcrowding. Trees were removed to make room for the duct bank route. New Vault Trees Removed

Solution 2: Re-Routing of Duct Bank New duct banks were routed towards the outside, furthest away from the trees and other duct banks.

Validation of Solutions How do we know if the separation of duct banks and the use of the slurry backfill addressed the heating issues?

Distributed Temperature Sensor (DTS) Fiber Cable: 24 Multi Mode 62.5/125mil Length: ~2600 ft One Continuous Loop Standard SCE fiber cable Zones: Control trench, power cable trench, north duct bank, south duct bank, and fiber well. Conduit: 2 inch Power to control cable trench. 5 inch Control trench to fiber well. 3 1/c 1000 kcmil, TR-XLPE 220 mils V5621760 DTS MEER 12kV SWITCHRACK No. 1 CAP BK No. 2 CAP BK FIBER WELL FIBER SPLICE SUBSTATION FENCE

Benefits of Distributed Temperature Sensor (DTS) System Thermal Study are an estimate of the thermal characteristics of the cable, ductbank, ambient temperature, soil conditions and loading. Soil thermal properties cannot be known throughout a duct bank run, without taking multiple measurements throughout the run. No other method of determining the actual cable temperature in the middle of the duct bank. Knowing the temperature of the cable: Make better, more accurate decisions in real time. Extend the life of cable by monitoring the cables temperature. Possible increase of current capacity, by loading the cable up to the actual loading limits, rather than an estimate.

Duct Bank Performance Monitoring (DTS) The DTS system was implemented to monitor cable temperatures inside the duct banks. Utilizes a fiber optic cable to monitor temperatures along the entire length of the duct bank. DTS and Computer Rack Fiber splice in power cable trench

Fiber Route Temperature Profile

October Heat Storm - Temperatures Max Ambient Temperature Data in Garden Grove for October 2014

Heat Storm Circuit Loading -North For SCE Internal Use Only 23

Duct Bank Temperature Performance Validation Measured Duct Bank Model Cable Detail Model Calculated DTS Temperature was as expected. (63 deg. C measured & 65 deg.c calculated.) Improved duct bank design, slurry back fill & tree removal prevent duct bank overheating (Conductor Temperature ~ 68.8*C during heat wave at 103 deg. F) 24

Wrap Up - Conclusion Predominant causal factors in the Lampson overheated duct bank condition are the high soil thermal resistivity and the overcrowding of the duct banks. The corrective actions implemented have mitigated both causal factors: Splitting the circuits into two paths (4 circuits and 3 circuits) and cable placement in the duct arrangement to address the circuit density. Adding slurry to address the soil thermal resistivity issue. The DTS system has proven that the integrated solution of splitting the duct bank and adding slurry backfill prevented overheating during the October heat wave.

Wrap Up Lessons Learned / Challenges Installing the fiber cable in the same duct as power cables. Damage may occur during installation. Small clearances in duct. Communication fiber cable requirements / standards are higher than needed for monitoring cable temperature. Paying more attention to the contractors, they work fast and may not have the same goals as you do. Cost was small to add fiber cable to an existing power cable pull. Fiber splicing Coordinating non electrical crews. Fiber cables are normal treated as separate installations Setting up computer for DTS Cost is of the project is in the DTS unit.

Wrap Up Future Needs Possible installation of fiber cable in highly loaded circuit sections (ie. Substation getaways, highly loaded customers, etc.) Installing fiber cable at the same time as power cable is reasonably low cost.

References CYMCAP 6.2, rev2 Duct Bank Modeling Software IEEE 442- Guide for Soil Thermal Resistivity Measurements SENSA-Distributed Temperature Sensor SCE Circuit Loading Data Thermal Images Provided by SCE Troubleman Santa Ana,CA AEIC CG6-2005, Section 6.1 Guide for Establishing The Maximum Operating Temperatures of Extruded Dielectric Insulated Shielded Power Cables IEEE 835 IEEE Standard Power Cable Ampacity Tables ICEA P-53-426 (WC-50) Ampacities Including Effect of Shield Losses for Single Conductor Solid Dielectric Power Cable 15 kv through 69 kv