SP Energy Networks 2015 2023 Business Plan



Similar documents
SP Energy Networks Business Plan

NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission PLC, Scottish Hydro Electric Transmission Limited

SP Energy Networks Business Plan

NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission Limited, Scottish Hydro Electric Transmission Limited

Undergrounding high voltage electricity transmission. The technical issues

RCP2 Portfolio Overview Document

Lifecycle Strategy DISPOSAL AND DIVESTMENT

SHE Transmission. 2015_10_30 Transmission Losses Strategy Rev 2.0 October 2015

Respecting the environment

CONNECTING YOU TO SPECIALIST ELECTRICAL SUPPORT services

How To Monitor Water Penetration In A Cable Screen

COMPLIANCE REVIEW OF 2006/07 ASSET MANAGEMENT PLAN. Top Energy Limited

NETWORK OUTPUT MEASURES CONSULTATION

Carbon Management Plan

ELECTRICAL INSULATION TESTING OF HV EQUIPMENT UP TO 33kV

Max. Length of HTS Cables in the Future

Integrated Development and Assessment of New Thermoplastic High Voltage Power Cable Systems

Vision 2050 An Asset Management Strategy. Jaclyn Cantler Manager, Transmission Planning, PHI

Asset Management Strategy

Stephen G. Whitley, Senior Vice President & Chief Operating Officer

environment briefing02

SP Energy Networks Business Plan

ScottishPower Distribution Cables & Equipment. Metal Theft

Asset Management Plans

Assessing, Maintaining & Replacing Fluid Filled Cable Systems at PEPCO

AMSC s Superconductor Cable Technologies for Electric Utilities

PFT Solutions. Fluid Filled Cable Leak Detection

Presentation to CIGRE Next Generation Network. Visit of Seine substation

AORC Technical meeting 2014

SUPERCONDUCTING CABLE SYSTEMS

Response, Reliability and Results in the delivery of leak detection services

TEC Capital Asset Management Standard January 2011

LAC 67-2 rev3 - Annex B

ASSET MANAGEMENT LCNI 2014 Wednesday 22 nd October. Jennifer Woodruff Innovation & Low Carbon Networks Engineer

Utilities and existing services

State, trends and evolutions of HV/EHV power cables systems and contributions of SC B1 to their ongoing progress

Fault location on power cables. Fault location on power cables

Water Mains Rehabilitation Framework (NI) Northern Ireland Water

Explaining and avoiding faults Increasing availability

We appreciate your feedback

MV, HV AND EHV SWITCHGEAR TESTING & COMMISSIONING

4 IX D N E P P A Installation methods Current-carrying capacity and voltage drop for cables Reference method IET Wiring Matters

Interfacing electrification and system reliability. Earthing of AC and DC railways 4,10,13

Maintenance Strategy 2015 Owner: Kevin Bullimore Head of Infrastructure Next review 2020

EFFICIENT ELECTRICAL ENERGY TRANSMISSION AND DISTRIBUTION INTERNATIONAL ELECTROTECHNICAL COMMISSION

SOL PLAATJE LOCAL MUNICIPALITY

Service Level Agreement/Specification

Undergrounding high voltage electricity transmission lines. The technical issues

Electric heat tracing

Cable Size Selection for Energy Efficiency

Network Standard Advice No. 1420C 9/6/2011

JUBILEE TECHNICAL TRAINING CENTRE TAKORADI POLYTECHNIC 2015 TRAINING PROGRAMMES

SF 6 Gas Insulated Switchgear Type SDF for 170 kv

Enhance Power Equipment Reliability with Predictive Maintenance Technologies

FIXED CHARGE: This is a cost that goes towards making the service available, including

E-Highway2050 WP3 workshop April 15 th, 2014 Brussels

Page 1 of 24. To present the Asset Management Policy 2014 for Council adoption.

HIGH- AND EXTRA-HIGH-VOLTAGE GLOBAL CABLE SYSTEM SOLUTIONS Rely On Our Experience... Experience Our Capabilities

Guidance for Stationary Refrigeration & Air- Conditioning

Cable Condition Monitoring to Improve Reliability

Electrical switchgear and safety: A concise guide for users

National Grid Electricity Transmission s RIIO-T1 business plan overview

SMART ASSET MANAGEMENT MAXIMISE VALUE AND RELIABILITY

THE PATHWAY TO POWER HIGH-VOLTAGE CABLES

Government Degree on the Safety of Nuclear Power Plants 717/2013

ESB Networks Response. ERGEG Consultation. Voltage Quality Regulation in Europe

Executive summary 2. 1 Introduction 4

Our data centres have been awarded with ISO 27001:2005 standard for security management and ISO 9001:2008 standard for business quality management.

A NEW METHOD FOR DEVELOPING THE MOST COST- EFFECTIVE REHABILITATION PROGRAMS FOR OUR AGEING SEWER NETWORKS

NIA Project Registration and PEA Document

Western Power transmission and distribution annual asset management report. prepared by Asset Management Division

Gulf Cable & Electrical Ind. Co.

Building Services Engineering Technician

Product brochure Multi Functional Switchgear PASS M kv Flexible and compact switchgear solutions for windfarms

Link-Up. Solid Fuel Association Guide to Central Heating.

Interaction between business context and an appropriate WACC for ESBN

DOMESTIC ELECTRICAL INSTALLATION CERTIFICATE (Requirements for Electrical Installations BS 7671 IEE Wiring Regulations)

SP Transmission RIIO-T1 Business Plan

Asset management for power cable systems - Total cost optimization based on the Application of diagnostics -

electrical services

PD Monitor GIS. 24/7 Partial Discharge (PD) monitoring system for Gas Insulated Switchgear. Benefits NEW PRODUCT

REPLACEMENT AIR CONDITIONING UNITS FOR BRITISH EMBASSY RESIDENCE

Electricity North West Carbon Footprint Report

Fundamentals of Modern Electrical Substations Part 1: Mission of Electrical Substations and their Main Components

ACCESSORIES FOR HV CABLES WITH EXTRUDED INSULATION

INTRODUCTION INDUSTRIAL INSTALLATIONS AND ERECTIONS QUALITY THAT EXCELS

Summary of Electric Transmission Assessment Report

Hydraulic control unit series

Attachment SA Power Networks: Asset Management Plan Substation Transformers 2014 to 2025

LONG TERM FINANCIAL PLAN (INTERIM) 2012/13 to 2022/23

D Session 2004 CIGRÉ. 50 kv. 150 kv. Condition Assessment of High Voltage Power Cables. The Netherlands. E. Gulski * F.J.

Two different types of cables are used in primary airfield lighting circuits: - unshielded cables and - shielded cables

Practical Transformers: Operation, Maintenance and Testing

For the Design, Installation, Commissioning & Maintenance of Fixed Gaseous Fire Suppression Systems

T A B L E T 1 T E S T S A N D I N S P E C T I O N C A B L E P C U T A N D P C U T - A

Transcription:

SP Energy Networks 2015 2023 Business Plan Updated March 2014 Annex 132kV Cable Strategy SP Energy Networks 27 March 2014

132kV Cable Strategy March 2014 Issue Date Issue No. Document Owner Amendment Details 17 th March 2014 1.0 Jane Wilkie First Issue

1. Scope 3 2. Table of linkages 3 3. Executive Summary 4 4. Introduction 5 5. Network Strategy 5 6. Investment Strategy and Plans 6 6.1. 132kV Cable Investment Strategy and Plans 6 6.2. Gas compression cable 6 6.3. Pressurised Oil Filled Cable 7 6.4. Health Index Outputs Deterioration and Criticality 7 6.4.1. Health Index Outputs 7 6.4.2. Criticality Index 7 6.4.3. Cable Heat maps 9 6.4.4. Cable Asset Age Profile 10 7. Appendix 1 10 7.1. Gas Compression Cable Systems Failure Mechanisms 10 2

1. Scope This Annex covers our strategy for the replacement and refurbishment of 132kV cable assets through the ED1 period. 2. Table of linkages This strategy supports our ED1 Business Plan. For ease of navigation, the following table links this strategy to other relevant parts of our plan. Document SP Energy Networks Business Plan 2015-2023 SP Energy Networks Business Plan 2015-2023 - Annexes SP Energy Networks Business Plan 2015-2023 - Annexes Chapter / Section Chapter C6 - Expenditure Annex C6 Expenditure Supplementary Annex SPEN Annex C6 Asset Health and Criticality Strategy SPEN 3

3. Executive Summary Our 132kV cable is a critical asset and essential to provide our customers with reliable electricity supplies. We only invest in proactive 132kV cable replacement when the cable condition and performance result in unacceptable risk to reliability or the environment. Replacing 132kV cable in city centres is a significant undertaking requiring road closures with disruption to residents and commuters and requires careful management. We therefore only replace it when absolutely necessary. For the ED1 period we have only two Health Index 5 cable circuits in Merseyside which require replacement. 1. 132kV Gas compression cable: We plan to replace 5.0 km of gas compression cable between Lister Drive and Wavertree, with a modern XLPE equivalent. 2. 132kV Oil Filled cable: We plan to replace 10.9 km of oil filled cable between Kirkby and Bootle, with a modern XLPE equivalent. Delivery of our cable programme is essential to delivering reliable network performance and is fundamental to delivering our stated output to reduce oil leaks by 50% through the replacement of poorly performing 132kV cable in SPM. Asset Replacement, Refurbishment Total length DPRC5 D5 pa Total Total length ED1 pa RIIO-ED1 Total Km m m Km m m % change 132kV Cable SPM 23.6 3.8 19.0 19.4 2.3 18.6-39% 4

4. Introduction 132kV cable assets in SPM are one of three types:- Gas compression cables Oil filled cables XLPE cables Gas compression cables were generally installed from the early 1950s to the mid 1960s and oil filled cables were installed from the 1950s through to the late 1990s. From the late 1990s onwards a new type of non-pressurised XLPE cable was installed. It is not possible to ascertain the actual condition of cable buried underground, so as a proxy for condition we use fault rates and oil leakage rates to determine the health index of our cable assets. Our investment plan for RIIO-ED 1 involves replacement of assets which are Health index 5. The delivery of our key outputs and value for money for the customer is central to our plan. Environment - to reduce oil leaks by 50% through the replacement of poorly performing 132kV cable in SPM Performance to manage the risk associated with failure of critical 132kV cable circuits through removal of poorly performing cable 5. Network Strategy The investment strategy for the 132kV network aims to ensure an optimum level of investment by adopting a prioritised and targeted project specific approach. This is necessary to effectively manage the business risk and ensure long term sustainability, utilising appropriate engineering interventions and risk management. Specifically our strategy aims to: Maintain safety, integrity and performance of the network as its age increases whilst ensuring long term sustainability and support network growth. To intervene prior to asset failure: When asset performance and reliability fall below acceptable operational limits and cannot be restored without an unacceptable financial risk and / or system risk exposure. Minimise failures, through interventions targeted on assets at or approaching of end of life (Health Index 5): Utilising engineering condition or type information, as appropriate. Target investment based on an assessment of risk through probability (Asset Health) and criticality: Taking account of factors such as public and staff safety, strategic importance, customer sensitivity to supply disturbances, asset performance and environmental considerations. 5

6. Investment Strategy and Plans 6.1. 132kV Cable Investment Strategy and Plans We have a total population of 246km of 132kV cable and we plan to replace 6% in RIIO ED1. We plan to address the age and risk through the replacement of two poorly performing Health Index 5 cables. 4 3 2 1 SPM 132kV Underground Cable Replacement (p.a. average volume) DPCR5 ED1 ED2 0 Based on our analysis, the following numbers of units are planned for replacement during ED1 as they are currently in critical condition and approaching end of life. Cable Voltage 132kV SPM 15.9km Within the additions planned for ED1 there is 3.5 km of new cable required as a consequence of 132kV substation plant replacement. Our most critical cable circuits will be addressed during ED1 resulting in a reduction of forecast ED2 interventions. 6.2. Gas compression cable By the end of DPCR5 we will have 5.0 km of British manufactured gas compression cable remaining, which is classed as a Health Index 5. We will continue to have 6.4km of German manufactured gas compression cable which was installed in the 1990s which is performing reliably and is currently classed as a Health Index 2. Within our two license areas over the last 15 years we have progressively been removing unreliable Enfield type gas compression cable. The design, construction and installation of this type of cable in the 1950s and 60s has been found to be prone to failure and has been recognised as a problem across the industry. This type of cable system relies on gas pressure in the pipeline in which it is laid being maintained. It suffers faults in both the cable itself due to depressurisation of the pipeline and the terminations which have porcelain sealing ends which have a risk of failing explosively. More detail on the failure mechanism of this cable type is provided in an Appendix to this annex. The SPM cables have had rating restrictions applied to reduce the risk of failures. Of this type of cable remaining in SPM, two of the circuits are being removed in DPCR5 and Lister Drive Wavertree will be removed in ED1. 6

6.3. Pressurised Oil Filled Cable We use a five year moving average leakage rate as a proxy for oil cable condition and assign a health index relative to this. In general, those cables with minimal leakage only require maintenance to ensure that degradation is minimised and that they continue to operate safely and reliably. As part of our management of the environment, we have a well-established programme of use of PFT (PerFluoroCarbon) tracers to expedite oil leakage fault repairs, on a targeted basis. Cables which are exhibiting a random cumulative leakage rate, consistent with an end of life characteristic, will be targeted for replacement. The insulation within oil filled cables (unlike paper insulated cables), does not deteriorate over time as long as the hydraulic system maintains its capability to retain pressure. Condition assessments therefore focus, on the components of the system which ensure that oil pressure is maintained within design limits. The necessary maintenance procedures can be summarised as follows: Sheath tests to confirm the integrity of the anti-corrosion serving. Tests to confirm the functionality of the pressure monitoring equipment and alarms. Tests to confirm the integrity and functionality of the earthing and bonding system. Regular pressure gauge checks to identify deviations from normal pressure. 6.4. Health Index Outputs Deterioration and Criticality 6.4.1. Health Index Outputs Considering the 5 year average oil leakage rate results in 16.8km being classed as Health Index 5. The 16.8 km of category 5 circuits comprises of three circuits: Rainhill to St Helens 5.2 km Capenhurst A to Hooton Park 1 0.7 km Kirkby to Gillmoss T1 to Fazakerley to Bootle 10.9 km While the Capenhurst A to Hooton Park 1 circuit is a category 5 due to the oil leakages looking at the last five years, repairs have been carried out on this cable and there have been no leakages in the last two years. This indicates that oil leaks have been localised and have now been repaired, rather than a general deterioration of the cable insulation. The Kirkby/Gillmoss/Fazakerley/Bootle circuit has an oil leakage rate that is 10 times worse than the average in SPM and accounts for 50% of the total oil leakage from all our 132kV cables. The Rainhill to St Helens circuit is being replaced in DPCR5 and the Kirkby-Gillmoss- Fazakerley-Bootle circuit is planned for RIIO-ED1. 6.4.2. Criticality Index Asset criticality is measured in terms of the stakeholder impact resulting from a failure of asset function. There are three elements to criticality: Safety based on the exposure and proximity to the public and personnel 7

Environment based on the environmental exposure from the asset and the sensitivity of the geographical area local to the asset. System based on the impact of the distribution system not delivering services to stakeholders or the smooth operation of the UK services and economy Financial based on e.g. the cost to repair/ replace or public relations The criticality in each element is assigned a level of Very High, High, Medium or Low. The overall asset criticality is based on the highest of the 3 assessments. The criticality, or site importance, of each cable is assessed first. A matrix of HI and CI interventions indicating oil and gas cable disposals in HI and CI volumes between the start and end of ED1 is also provided. The relative risk measures for each asset category with and without investment are also profiled in the graphs below. 132kV Gas cable HI and CI movement HI1 HI2 HI3 HI4 HI5 Total CI CI1 0 0 0 0 0 0 CI2 0 0 0 0-5 -5 CI3 0 0 0 0 0 0 CI4 0 0 0 0 0 0 Total HI 0 0 0 0-5 -5 132kV Oil cable HI and CI movement HI1 HI2 HI3 HI4 HI5 Total CI CI1 0 0 0 0 0 0 CI2 0 0 0 0-8.3-8.3 CI3 0 0 0 0 0.0 0.0 CI4 0 0 0 0-2.6-2.6 Total HI 0 0 0 0-10.9-10.9 8

Smart Grid Strategy Creating a network for the future 6.4.3. Cable Heat maps The results from all the 132kV oil filled cable leakage rates is used to compile a cable heat map to inform replacement prioritisation, part of which is shown below. SPM 132kV Oil Filled Cables Litres per Year Litres Circuit Circuit Name Cable Section Region Circuit Length 03/04 04/05 05/06 06/07 07/08 08/09 2010 2011 2012 Total l/year l/km l/m/year Length (km) l/km/year Rainhill - St Helens St Helens Substation Merseyside 5050 772 83 398 490 749 3850 1673 809 7081 1416 1.402178218 0.280435644 5.1 280 Capenhurst A - Hooton Park 1 Isolator 203 - Tower CV1 Cheshire 740 985 35 1020 204 1.378378378 0.275675676 0.7 276 Kirby - Gillmoss T1 - Bootle 305 Kirby Substation Merseyside 10845 87 360 50 1548 10000 307 963 65 12883 2577 1.187920701 0.23758414 10.8 238 Bold - Kirby - Windle Kirby - C85A Merseyside 478 50 50 103 243 165 40 154 14 373 74.6 0.780334728 0.156066946 0.5 156 Bold - Rainhill 2 Rainhill - BZ14 Merseyside 571 234 27 261 52.2 0.45709282 0.091418564 0.6 91 Frodsham - Salt Un - Percival Lne - Ince Tower Q18A - Tower Q17A Cheshire 117 5 5 30 20 50 10 0.427350427 0.085470085 0.1 85 9

Smart Grid Strategy Creating a network for the future 6.4.4. Cable Asset Age Profile Currently SPM has an average age of 38.3 years which is above industry average for 132kV cable. 7. Appendix 1 7.1. Gas Compression Cable Systems Failure Mechanisms The behaviour and failure mechanisms of gas compression cable systems have been reported in the past 1,2. However, investigations of gas compression cable faults in the late 1990s and early 2000s have led to a revised understanding of the failure mechanisms experienced by Gas compression cables which are outlined in detail in a report from Cable Engineering Consultants³ and can be summarised as follows:- During normal operation of a gas compression cable system, it has become clear that impregnant moves along the cable cores. This fact was not appreciated during the design, installation and operation of these cables, however, it has now been found to play a significant role in end of life behaviour and failure mechanisms. Over a period of time, the impregnant can fill and distend the corrugated joint sleeves and the cable diaphragm sheaths so that they come into hard contact with the reinforcing components reducing their capability to accommodate any significant further expansion of the impregnant. If the load on the cable is now increased beyond it s historic level, the increased expansion of the impregnant can produce very high hydraulic pressures in those parts of the system where the expansion accommodation is limited by distension of the diaphragm components. The hydraulic pressure within the cable may then burst the reinforcing tapes, and the diaphragm sheaths, expanded oil will exit the cable via the rupture in the diaphragm sheath. On cooling the remaining impregnant contracts and the lost oil is replaced by nitrogen from the pipeline. As the nitrogen used to fill the pipelines is not specially dried, and it is known that some pipelines contain free water dating from the time of installation, the gas entering the dielectric introduces water into the cable core. Free gas is now present in the cable, along with water, causing the losses in the dielectric to be increased locally so the local temperature of the dielectric becomes higher than that along the general length of the cable. If the load on the cable is increased, 10

Smart Grid Strategy Creating a network for the future the heat generation is increased. If this additional heat generation is sufficient, in conjunction with the increased losses in the dielectric, to raise the dielectric temperature to a critical value the cable may be tripped into localised thermal instability leading to electrical failure. If a load is supplied by two gas compression cables, and one is removed from service then the load on the remaining cable is increased and the increased temperatures and pressures may result in the second cable bursting with the same results as described above. Changes of load and gas pressure are, therefore, to be avoided wherever possible on these cable systems and this leads to reduced operational flexibility for these network-critical assets. In summary, it is now believed the gas compression cable population has reached an end-of-life situation after 40 to 50 years service due to the combination of three factors, namely, inconsistent cable build during manufacture, latent installation damage and unforeseen behaviour of the impregnant during operation. 1. ACE Report No.81 (1981): 132kV Gas Compression Cable sealing end failures. 2. Gas Compression Cable Systems A Review of the current situation and recommendations for future action a 132kV (1988) DJ Skipper. 3. Cable Engineering Consults Gas Compression Cable Systems A review of current knowledge with regard to their operating principles, service history and failure mechanisms (2001) - BJ Harrison. 11