Interaction between business context and an appropriate WACC for ESBN
|
|
|
- Baldric Norman
- 10 years ago
- Views:
Transcription
1 Interaction between business context and an appropriate WACC for ESBN A REPORT PREPARED FOR ESB NETWORKS September 2013 Frontier Economics Ltd, London.
2
3 Confidential July 2013 Frontier Economics i Interaction between business context and an appropriate WACC for ESBN Executive Summary 1 1 Introduction 7 2 Precedent for the interaction between the broader business context and allowed WACC 9 3 Implications of regulatory precedent for ESBN 15 4 Practical application of regulatory precedent to ESB Networks 17 5 Conclusions and Recommendations 23 Contents
4 ii Frontier Economics July 2013 Confidential Interaction between business context and an appropriate WACC for ESBN Figure 1. The impact of re-profiling capex on ESBN's equity return 4 Figure 2. Overview of risk-return calibration 10 Figure 3. Estimated RoRE ranges in RIIO-T1 and RIIO-GD1 12 Figure 4. Estimated RORE ranges in PR3 compared to Ofgem max/min 13 Figure 5. The impact of re-profiling capex on ESBN's equity return 21 Tables & Figures
5 Confidential July 2013 Frontier Economics 1 Executive Summary There have been major changes to the context within which ESBN operates since the third price control (PR3) for ESB Networks (ESBN) was concluded: there have been reductions in GDP and reductions in electricity consumption, as well as reduced connections of renewables generation. These have led ESBN to propose a significant cut in the capex programme agreed at PR3, with projected spend falling from 4.2bn to 2.4bn. This reduction had as its principal objective the reduction of pressure on DUOS charges and hence on end customer bills; and there have been on-going changes to the financial market conditions which influence the cost of raising finance to invest in the network. At the time PR3 was agreed, this was expected. In particular, the CER indicated that they would carry out a mid term review ; and ESBN have asked Frontier Economics to consider the impact of the first of these changes, and in particular to assess the extent to which any review needs to take into account changes in the wider business context in setting an appropriate level of WACC. To address this question we have considered the following three key issues: regulatory precedent, in particular from GB, in relation to the linkages between the broader context of the business and the allowed WACC; the implications of this precedent for ESBN s mid-term review; and considerations in relation the practical application of this precedent, given the details of ESBN s situation. The key conclusion of our analysis is that the re-profiling of ESB Networks capex is likely to have had significant knock on effects on ESB Network s ability to achieve its opex allowances and its incentive targets. This would in turn result in a price control package that is much more asymmetric than that agreed at PR3 based on their data, ESB Networks faces considerably greater downside risk now than had been envisioned when PR3 was agreed. In order to re-calibrate the price control so as to bring it back in line with the original PR3 symmetric determination, we recommend that as part of any review the CER should consider a mix of: increasing ESB Network s WACC to re-balance the overall PR3 package; and/or increasing ESB Network s opex allowance and developing a revised capex delivery incentive in line with the re-profiled capex package. Executive Summary
6 2 Frontier Economics July 2013 Confidential Finally, we note that failure to undertake any recalibration would effectively imply putting in place a package which is inconsistent with the CER s view at the start of PR3 of the appropriate balance of risk and reward. Or put another way, it would represent a decision to increase the risk on ESBN without any corresponding increase in reward. It is clear that such a move would be viewed negatively by the investment community, and would impact significantly on cost of capital because it would undermine the perceived predictability of the regime. We summarise the findings on which these conclusions and recommendations are based below. Regulatory precedent Regulators have explicitly recognised the links between exposure to uncertainty in relation to regulatory incentives and the allowed WACC and its components. In particular, following the completion of the new RIIO regulatory framework, Ofgem set out explicitly how they would take linkages between likely incentive performance (including opex and capex performance relative to allowance) and WACC into account in considering the financeability of network companies. In describing RIIO, Ofgem recognises that the potential scale of penalties and rewards for output delivery has a particularly close relationship with a network company s cost of capital 1. If companies are subject to greater risk through the regimes for output delivery, they may require a higher WACC to compensate. Ofgem uses Return on Regulated Equity (RoRE) analysis to calibrate the overall price control settlement to achieve this balance. RoRE looks at the returns to equity which each company can make, taking into account: baseline allowed revenue and estimated efficient costs; reasonable upside and downside risks from opex and capex incentives; reasonable upside and downside risks from other incentives. Ofgem states they regard an appropriately calibrated price control package as one in which RoRE upside (i.e. the reward available for the best-performing companies) provides the potential for double-digit returns on (notional) equity, and RoRE downside (i.e. the penalties that would apply to the worst-performing companies) is at or below the cost of debt 2. Put another way, Ofgem is saying they believe the price control settlement should be viewed as a whole, and all the elements should be calibrated to achieve particular outcomes in terms of the overall financial risk faced by the companies. 1 Ofgem RIIO handbook, pp Ofgem RIIO-T1 final proposals, Finance document, p36 Executive Summary
7 Confidential July 2013 Frontier Economics 3 Implications of regulatory precedent for ESBN Based on this precedent, it is reasonable to view PR3 as a package, consisting of both baseline remuneration for opex and capex, and performance incentives in relation to opex and capex efficiency, and a range of broader outputs. As a result of the reduced capex programme, it is likely that risk to which ESBN is exposed has increased. Specifically, reducing capex could result in: increased and more uncertain opex - ESBN have identified planned maintenance and fault repair opex gaps relative to PR3 allowances; and reduced likelihood of hitting broader incentive targets (including capex delivery). Comparing an Ofgem-style RoRE analysis at the time of PR3 with how things stand now, we observe that risks are more asymmetric. ESBN faces a lower upside and a greater downside than at the time of PR3, as a result of reduced likelihood of hitting opex and broader incentive targets. Following the logic of Ofgem s RoRE analysis if the overall PR3 settlement was deemed to have been appropriately calibrated by the CER, it would now be in need of recalibration, as the likely position in relation to incentives has changed. Failure to undertake any recalibration would effectively imply putting in place a package which is inconsistent with the CER s view at the start of PR3 of the appropriate balance of risk and reward. Or put another way, it would represent a decision to increase the risk on ESBN without any corresponding increase in reward. It is clear that such a move would be viewed negatively by the investment community. Far from representing the results of a pre-announced mid-term WACC review to reflect updated capital market conditions, it would be the equivalent of, midway through the price control, reopening the settlement and imposing significantly more challenging cost targets in unsignalled and unexpected way. Any such move would impact significantly on cost of capital because it would undermine the perceived predictability of the regime. The risks which investors thought they were buying into at the start of PR3 would be deliberately made larger and more asymmetric by the CER. We note that in relation to the recent Competition Commission (CC) enquiry in the Northern Ireland gas networks sector, the CC noted in relation to regulatory uncertainty that both Fitch and Moody s take the predictability of the regulatory regime into account when setting credit ratings, hence we consider that there is clear effect on the cost of debt. Executive Summary
8 4 Frontier Economics July 2013 Confidential Implications for the calibration of ESBN s price control package We have estimated the impact of reduced capex, and the effect on ESBN s opex and incentive performance, on the RoRE calibration of ESBN s PR3 package. We have estimated RoRE based on PR3 3 and re-estimated RoRE based on ESBN s revised view of the opex and incentive performance it could achieve given the reduction in capex. ESBN consider that, as a result of the re-profiling of capex, the capex delivery target is no longer achievable, and there is no longer any scope to beat the opex target. The impact of these changes on RoRE is set out in the Figure below. Figure 1. The impact of re-profiling capex on ESBN's equity return Return on Regulated Equity 16% 14% 12% 10% 8% 6% 4% Headline return from price control Addition / reduction in return from capex and opex incentives Addition / reduction in return from other incentives Ofgem view of GB RIIO T1 max Ofgem view of GB RIIO T1 min 2% 0% PR3 initial settlement PR3 with reprofiled capex The left-hand column shows the potential range of ESBN s equity return when PR3 was agreed. This shows that the settlement was largely symmetric, although it allowed for a potentially larger range of outcomes than Ofgem s view of the RIIOT1 settlement (we note in this regard that estimating credible ranges of performance in relation to multiple incentive schemes is inevitably subjective). 3 Our estimate of RORE is based on ESB Network s central estimate that at PR3 it was reasonable to consider scenario s in when ESBN might beat its opex allowance by 10% or esceed its opex allowance by 10%. Executive Summary
9 Confidential July 2013 Frontier Economics 5 The right-hand column shows the impact of the capex re-profiling on the potential range of ESBN s equity return. The Figure shows that the revised package is much less symmetric than the original PR3 package with the downside risks now substantially greater than the potential upside. The upside under the revised package has declined by over 4%, and the downside risk has increased slightly. While ESBN s minimum equity return exceeds Ofgem s view of the maximum, it is no longer possible for ESBN to achieve the level of return that the best performing UK companies can expect to earn. Recommendations The key conclusion of our analysis is that: the re-profiling of ESB Networks capex has had significant knock on effects on ESB Network s ability to achieve its opex allowances and its incentive targets; and this has resulted in a price control package that is much more asymmetric than that agreed at PR3 ESB Networks faces considerably greater downside risk now than had been envisioned when PR3 was agreed. In order to re-calibrate the price control so as to bring it back in line with the original PR3 symmetric determination, we recommend that as part of any review the CER should consider a mix of: increasing ESB Network s WACC to re-balance the overall PR3 package; and/or increasing ESB Network s opex allowance and developing a revised capex delivery incentive in line with the re-profiled capex package. Executive Summary
10
11 Confidential July 2013 Frontier Economics 7 1 Introduction Following the conclusion of discussions on the third price control (PR3) for ESB Networks (ESBN), there have been two major changes to the context within which ESBN operates: first, there have been substantial reductions in GDP and commensurate reductions in domestic and industry electricity consumption, as well as reduced connections of renewables generation. These have led ESBN to propose to the CER a significant cut in the capex programme agreed at PR3, with projected spend falling from 4.2bn to 2.4bn. This reduction had as its principal objective the reduction of pressure on DUOS charges and hence on end customer bills; and second, there have been ongoing changes to the financial market conditions which influence the cost of raising finance to invest in the network. At the time PR3 was agreed, this was expected. In particular, the CER indicated that they would carry out a mid term review of the WACC agreed with ESBN. This was because the WACC was set at a high level to reflect uncertainty around financial market conditions at that point in time; and The second of the changes and an estimation of the appropriate level of WACC for the second half of ESBN s price control is being addressed elsewhere. ESBN have asked Frontier Economics to consider the first, and in particular to assess the extent to which any mid-term WACC review needs to take into account changes in the wider business context in setting an appropriate level of WACC. At the outset, it is important to understand the scale of the changes in business context. In PR3, the CER provided for a very significant capital expenditure programme of 4.2 billion across the transmission and distribution businesses. Since 2011, GDP has grown considerably more slowly than anticipated. Given the strong correlation between economic growth and energy demand, the impact has been that outturn demand has been significantly below that envisaged when the PR3 determination was arrived at. For example, new connections have reduced by two thirds from c. 30,000 pa to 10,000 pa, whilst electricity demand is significantly below forecast. Delivery of the allowed capex programme (even allowing for reduced loadrelated capex in line with reduced demand) would have led to very substantial increases in DUOS charges for customers. In consequence, we understand that ESBN approached the CER with a proposal to defer a substantial element of the Introduction
12 8 Frontier Economics July 2013 Confidential capex programme to PR4 in order to alleviate the impact of higher DUOS charges. ESBN proposed a revised capex programme of 2.4 billion, representing a 40% reduction in capex for the period. While an element of the proposal relates to capex that may not now be required due to lower outturn demand (e.g. generator connections and new business) a substantial element relates to capex that will still be required but which is deferred to future periods in order to alleviate pressure on DUOS charges. For example, we understand that this includes over 400 million of planned distribution re-enforcement expenditure, almost 150 million of asset replacement expenditure and almost 200 million of non-network expenditure. This deferral of investment has been risk assessed to determine the most efficient mix of CAPEX deferral and OPEX minimisation while maintaining reliability and safety of the network. It is the scale of impact of these changes which make it important to understand how they may interact with the mid-term WACC review. In the remainder of this document, we therefore present: in Section 2, regulatory precedent, in particular from GB, in relation to the linkages between the broader context of the business and the allowed WACC; in Section 3, the conceptual implications of this regulatory precedent for ESBN s mid-term WACC review; in Section 4, some considerations in relation the practical application of this precedent, given the details of ESBN s situation; and in Section 5, a brief summary of our findings and our recommendations. Introduction
13 Confidential July 2013 Frontier Economics 9 2 Precedent for the interaction between the broader business context and allowed WACC In this chapter we set out the precedent for the interaction between the broader business context and allowed WACC. In many ways, the reduction in the scale of capex being undertaken by ESBN could be considered likely to reduce ESBN s WACC, as the cashflow risk faced by a company is a function of, among other things, the scale of investment being undertaken. Lower levels of investment may be taken as meaning lower levels of cashflow risk and hence a lower WACC. However, there are other factors which move in the opposite direction, depending on the nature of the capital expenditure which has been cut. In particular: if this capex is non-load related, deferring it may result in opex becoming more unpredictable, as the cost of repair may be more difficult to predict than that of replace. It may also lead to higher levels of network opex, and hence more difficulty in hitting stringent regulatory opex targets; and if the capex is targeted at other incentivised outputs (e.g. customer satisfaction), it may result in worse than expected performance on specific incentive targets. Other regulators have explicitly recognised the links between the exposure of regulated entities to uncertainty in relation to regulatory incentives and the allowed WACC and its components. In particular, following the completion of the design process for the new RIIO regulatory framework, Ofgem went to some effort to set out explicitly how they would take linkages between likely incentive performance and WACC into account in considering the financeability of network companies. A schematic of the process they set out in Figure 2. Precedent for the interaction between the broader business context and allowed WACC
14 10 Frontier Economics July 2013 Confidential Figure 2. Overview of risk-return calibration Source: Ofgem, RIIO handbook There are three specific aspects to Ofgem s process which are important to recognise here, highlighted in the above figure: first, the definition of the potential scale of penalties and rewards for outputs; second, the illustration of the range of returns possible; and third, the estimation of the weighted average cost of capital. We discuss each in detail below, before drawing conclusions for ESBN s situation from Ofgem s approach. Definition of penalties and rewards In their description of the RIIO model, Ofgem recognises that the potential scale of penalties and rewards for output delivery has a particularly close relationship with a network company s cost of capital 4. If companies are subject to greater risk through the regimes for output delivery, they may require a higher WACC to compensate. They note that the way in which this balance is achieved will vary. For some outputs, the strength of incentive will effectively be a subjective regulatory judgement. This means that the regulator may set it at a level which itself balances a reasonable allowed return for the company with continuing incentivise 4 Ofgem RIIO handbook, pp Precedent for the interaction between the broader business context and allowed WACC
15 Confidential July 2013 Frontier Economics 11 the company to deliver things which are in customers interests. In contrast, for other incentives, there may be empirical data (e.g. on customer willingness to pay) which will allow the incentive mechanism to be specified with greater objectivity. In this situation, it may be appropriate to use this data to set the strength of the incentive, and to seek to achieve balance either via changes to other related incentive mechanisms, or directly in the cost of capital itself. Illustration of range of returns Ofgem uses Return on Regulated Equity (RoRE) analysis to calibrate the overall price control settlement to achieve this balance. This RoRE analysis looks at the returns to equity which each network company is capable of making, taking into account: baseline allowed revenue and estimated efficient costs; reasonable upside and downside risks from operating cost and capex incentives (under Ofgem s regime, collectively termed totex incentives); and reasonable upside and downside risks from other incentives. Ofgem states they regard an appropriately calibrated price control package as one in which RoRE upside (i.e. the reward available for the best-performing companies) provides the potential for double-digit returns on (notional) equity, and RoRE downside (i.e. the penalties that would apply to the worst-performing companies) is at or below the cost of debt 5. Put another way, Ofgem is saying that they believe the price control settlement should be viewed as a whole, and all the elements should be calibrated to achieve particular outcomes in terms of the overall financial risk faced by the companies. If the range of possible financial outcomes is too narrow, the company will be exposed to too little incentive to perform in customers interests, and may have a WACC which is too high. If the range of financial outcomes is too large, the company may need to be remunerated for it through a premium to the cost of capital estimated using standard techniques or parameters. The outputs from Ofgem s RIIO-T1 and RIIO-GD1 RoRE analysis are presented at Figure 3 6. This figure shows: the baseline return on equity for each of the companies, with the Scottish electricity transmission companies at around 7%, National Grid 5 Ofgem RIIO-T1 final proposals, Finance document, p36 6 We note that this approach to analysis should not be considered new or specific to the RIIO regime. It was also used by Ofgem during the last electricity distribution price control under the old RPI-X regime in Precedent for the interaction between the broader business context and allowed WACC
16 12 Frontier Economics July 2013 Confidential Electricity Transmission (NGET) at 7%, National Grid Gas Transmission (NGGT) at 6.8%, and the gas distribution companies slightly lower still; the opex and capex incentives (a combination of the IQI additional income, totex and where relevant repex bars); and the incentives on other metrics. Figure 3. Estimated RoRE ranges in RIIO-T1 and RIIO-GD1 Source: Ofgem It is notable from the graph that: the ranges which Ofgem analyses are broadly symmetric in other words, the incentive regimes which they have put in place provide equal possibility of upside or downside risk for the companies; and as Ofgem themselves state, performance against totex allowances has the largest impact on overall return on equity. We have applied the same methodology as that described above to data provided by ESBN 7 to assess the calibration of ESBN s original PR3 package. This is 7 We have relied upon ESB Network s views of the likely range of opex performance. We recognise that it is a matter of judgement as to how wide the likely bands of potential under-or overperformance may be. Precedent for the interaction between the broader business context and allowed WACC
17 Confidential July 2013 Frontier Economics 13 shown in the figure below, which also shows Ofgem s view of maximum and minimum equity return ranges for RIIO-T1. Figure 4. Estimated RORE ranges in PR3 compared to Ofgem max/min Return on Regulated Equity 16.0% 14.0% 12.0% 10.0% 8.0% 6.0% 4.0% 2.0% Addition / reduction in return from other incentives Addition / reduction in return from capex and opex incentives Headline return from price control Ofgem view of GB RIIO T1 max Ofgem view of GB RIIO T1 min 0.0% PR3 initial settlement The Figure shows that, like Ofgem, the CER set a relatively symmetric package at PR3. ESBN s view on capex, is that it anticipated largely being in line with the allowance set, with little scope for either over/under performance. On Opex, ESBN estimated at PR3 that the likely scope for over/underperformance was 10%. On incentives, the CER noted that the package was largely symmetric, stating that In the CER s view the targets which have been approved here are challenging yet achievable, and will encourage the DSO to maintain or improve its performance. Overall, this shows that, had ESBN maximised performance over PR3, there was a potential to earn an equity return of up to 14%. This is in line with the Ofgem view that an appropriately calibrated price control package as one in which RoRE upside (i.e. the reward available for the best-performing companies) provides the potential for double-digit returns on (notional) equity. Estimation of WACC and other financial parameters Within the context of this overall approach to setting a price control, Ofgem uses a relatively standard approach to estimating the allowed cost of capital of a network company. They calculate an allowed return on equity using a range of Precedent for the interaction between the broader business context and allowed WACC
18 14 Frontier Economics July 2013 Confidential models including CAPM, and they calculate an allowed cost of debt using a benchmark index. The notional gearing assumed by Ofgem sets the relative proportions of equity and debt which are assumed to be used to finance each network company. Ofgem notes that there is scope for companies within the same sector to have different levels of notional gearing where there is a significant difference in the risks facing them. In other words, if the regulatory regime exposes a company to greater risk, it may be reasonable to assume a lower notional gearing, as other things being equal, the company would require a larger equity buffer to achieve an investment grade credit rating. Indeed, under RIIO-T1, NGET and NGGT were given different notional gearings reflecting different views on risk. Precedent for the interaction between the broader business context and allowed WACC
19 Confidential July 2013 Frontier Economics 15 3 Implications of regulatory precedent for ESBN Based on the regulatory precedent set out in the previous chapter, it would be reasonable to view the PR3 settlement put in place by the CER as a package, consisting of a baseline set of remuneration for operating costs and investment, with performance incentives in relation to opex and capex efficiency on one hand, and a range of broader outputs on the other. As a result of the scaling back of the capex programme, it is likely that the level of risk to which ESBN is exposed has increased. Specifically, as we have noted above, reducing capex could result in: increased opex; more uncertain opex; and reduced likelihood of hitting some broader incentive targets (in particular the capex delivery targets). If the CER compares what an Ofgem-style RoRE analysis would have looked like at the time of striking PR3 and as things stand now, two changes can therefore be observed: the risks are more asymmetric ESBN now faces a lower upside and a greater downside than at the time of PR3, as a result of reduced likelihood of hitting opex and broader incentive targets; and the overall risk is greater, as a result of greater opex uncertainty. Ofgem tends to apply symmetric incentive arrangements with a standard assessment of the WACC. This would perhaps suggest that strongly asymmetric targets would not be consistent with such an approach. However, even more fundamentally, following the logic of Ofgem s RoRE analysis, if the overall PR3 settlement was deemed to have been appropriately calibrated by both ESBN and the CER, it would now be in need of recalibration, as the likely position in relation to incentives has changed. This recalibration could involve an increase in ESBN s WACC, relative to that estimated using a standard CAPM method, to take into account the higher, asymmetric risks faced. Alternatively, it could involve a reduction in ESBN s notional gearing, to reflect risks faced, or a reformulation of allowances to make them symmetric once more Failure to undertake any recalibration would effectively imply putting in place a package which is inconsistent with the CER s view at the start of PR3 of the appropriate balance of risk and reward. Or put another way, it would represent a Implications of regulatory precedent for ESBN
20 16 Frontier Economics July 2013 Confidential decision to increase the risk on ESBN without any corresponding increase in reward. It is clear that such a move would be viewed negatively by the investment community. Far from representing the results of a pre-announced mid-term WACC review to reflect updated capital market conditions, it would be the equivalent of, midway through the price control, reopening the settlement and imposing significantly more challenging cost targets in unsignalled and unexpected way. Any such move would impact significantly on cost of capital because it would undermine the perceived predictability of the regime. The risks which investors thought they were buying into at the start of PR3 would be deliberately made larger and more asymmetric by the CER. We note that in relation to the recent Competition Commission (CC) enquiry in the Northern Ireland gas networks sector, the CC noted in relation to regulatory uncertainty that both Fitch and Moody s take the predictability of the regulatory regime into account when setting credit ratings, hence we consider that there is clear effect on the cost of debt. Implications of regulatory precedent for ESBN
21 Confidential July 2013 Frontier Economics 17 4 Practical application of regulatory precedent to ESB Networks 4.1 Introduction In the previous sections we have set out the appropriate conceptual approach to considering the extent to which any mid-term WACC review needs to take into account changes in the wider business context in setting an appropriate level of WACC. Whilst we understand that ESBN is confident it can still operate the networks in line with its license requirements, we suggest that the reduction in planned capex may have a number of important impacts when thinking about the ability of ESBN to achieve other elements of the PR3 package. In particular, our assessment of ESBN s revised capex programme suggests that the very significant reductions in planned capex may give rise to the following challenges which should be factored in to any assessment of the appropriate level of WACC: the likely need for increased opex; potentially significant increase in volatility and risk associated with opex expenditure; and greater risk in relation to meeting performance measures. We discuss each in turn below, before considering the implications for the calibration of ESBN s price control package. 4.2 Increased opex There is a well-recognised link and trade-off between opex and capex. Typically, as network reinforcement and refurbishment expenditures are carried out, O&M costs can be reduced. Network assets are newer and in need of less frequent inspection and maintenance, and reliance on individual assets to avoid failures may be reduced. Moreover, as such refurbishments are carried out, advantage can be taken of technological developments and improvements (e.g. SCADA, smart monitoring devices, etc.) to change work practices and reduce operating costs. The converse is also true if necessary reinforcements are not undertaken and asset renewal is deferred, pressures on O&M costs are likely to increase. At a minimum, one would anticipate an operator incurring higher inspection and monitoring costs in relation to a network run using older assets. Moreover, it is likely that, as some of the assets begin to fail, emergency response costs also Practical application of regulatory precedent to ESB Networks
22 18 Frontier Economics July 2013 Confidential increase. With reduced investment, it also becomes more difficult to take advantage of technological improvements to deliver efficiency savings. Overall, we suggest that the deferred capital programme (particularly those referring to asset replacement, network re-enforcement and non-network) is likely to put upward pressure on O&M costs. A concrete example of the types of costs referred to above relates to the impact of extending the life of old 38kV cables in Dublin. Deferring cable replacement may lead to higher than normal 38kV cable faults. To mitigate the higher potential for faults, greater amounts of cable testing and route inspections are being carried out to extend the life time of these assets. This would result in direct increases in opex as a result of the increased amount of time spent patrolling the network and carrying out maintenance. It also increases the risk of customer disturbance in fault situations and the subsequent costs of repairing and attending to faults, and electrician time involved in switching and isolating the network for work. There is also an associated opportunity cost of not doing other planned work. We understand that ESBN have already identified planned maintenance and fault repair opex gaps in opex outturn compared to the regulatory allowances set at PR3. ESBN estimate that the gap in opex associated with planned opex over the last two years has been over 20 million. In this context, it is also important to note that the CER, whilst recognising ESBN s efficiency in PR2, set extremely stretching opex efficiency targets for ESBN. With respect to PR2, the CER noted that: The DSO spent over its operating cost allowance by 12.3m or less than 1% of an over expenditure i.e. 1,272m versus 1,260m. This represents a significant achievement as the operating costs set by the CER were challenging and required significant increases in efficiency over the period For PR3, the CER determined that ESBN needed to find a further 150 million of efficiency savings in relation to its opex, and 175 million in relation to capex. We suggest that, given the deferral of capex, it may be materially more difficult for ESBN to achieve such stretching targets in context of network that is under greater stress. 4.3 More volatile opex In addition to the potential increase in opex as a result of the capex deferrals, there is also a risk that ESBN s opex will become more volatile. For example, when the life of existing assets is stretched due to deferred replacement, the risk of failure increases. Typically, the O&M costs are higher when assets are replaced due to failure than due to a planned replacement. Practical application of regulatory precedent to ESB Networks
23 Confidential July 2013 Frontier Economics 19 The higher volatility associated with ESBN s opex is likely to increase the risk facing the business (in terms of its ability to meet its opex allowances). Such risk was not factored in as part of the price control settlement, and needs to be given consideration. 4.4 Incentives As part of the PR3 settlement the CER agreed a package of incentives with ESBN. For distribution, the CER stated the following: The CER approves financial incentives for the DSO to improve quality of supply and customer service over the period. The incentives (with the exception of the worst served customer and capex delivery mechanisms, the details of which will be consulted on separately) are capped at 4% of annual revenue which equates to 151m over the period or an additional 0.5% to the allowed return on capital. Some additional incentive categories have been added and the CER believes that, while the targets are challenging, the incentives can be achieved by the DSO. The CER has included an annual provision of 8m for incentive payments within the allowed revenue on the expectation the DSO will at least achieve this level of incentive payment. We note that the capex delivery mechanism was worth an additional 8 million per year. So the total distribution incentive package was worth over 190 million to ESBN. It is important to note that a number of the incentives related directly to network security (i.e. the CML and CI incentives, alongside the customer satisfaction incentive), while 40 million of incentives related to the delivery of the capex programme (on which ESBN is no longer in a position to deliver). We understand that CER has accepted this as part of the recent tariff discussions for 2013/4. It is also important to note that the CER has explicitly recognised the link between network investment and the achievement of quality standards in relation to network security: A historic period of underinvestment in the distribution network in Ireland has been followed in recent years by an increased level of expenditure on capital, maintenance and network renewal programmes from 2000 onwards. This has been required to cater for new connections during the recent boom and to make up for a previous lack of investment. This expenditure, coupled with the DSO s response to incentive mechanisms put in place by the CER, has greatly increased the quality of the electricity supply that customers receive. There are substantially fewer interruptions to supply (both planned and unplanned) and customers that are interrupted have their supply restored within a shorter timeframe. Over the period the average annual number of interruptions per hundred customers is expected to fall by 46% to in 2010, with the average annual duration of a customer being without supply falling by 71% to 153 minutes. It follows that, with investment in network reinforcement and asset replacements deferred, it will now be more difficult for ESBN to meet the targets set out in the incentive package than would have been anticipated when the package was Practical application of regulatory precedent to ESB Networks
24 20 Frontier Economics July 2013 Confidential agreed. Additionally, ESBN is no longer able to achieve the 40 million of incentives associated with capex delivery. While ESBN is not likely to move to the bottom of ranges on all of the incentive measures, there is a significant risk that these incentives are not now set in an unbiased way and that over time the expected outcome will be negative, or at least no longer positive. Given the materiality of the measures (worth c.0.63% on the equity return for distribution), as argued above, it is important than any such risk be factored in to the assessment of the overall setting of the amended WACC and overall price control package for ESBN for the remainder of the period. 4.5 Implications for the calibration of ESBN s price control package The sections above have set out the impacts of the revised capex programme on ESBN s ability to achieve its opex allowances and to perform against its other incentives (most notably its capex delivery incentive). To provide an indication of the impact of these changes on the RoRE calibration of ESBN s PR3 package, we have re-estimated RoRE based on ESBN s revised view of the opex and incentive performance it could achieve. Our approach has been to ask the following question: Assume PR3 had been determined on the basis of the revised capex package what would be the impact on ESBN s opex relative to allowance and on ESBN s ability to deliver on the incentive package? ESBN s assessment is that, in such a scenario the capex delivery target is clearly no longer achievable, and there is also no longer any scope to beat the opex target. In fact ESBN have estimated that the best they could do in terms of opex would be an overspend of at least 70 million relative to allowance. The impact of these changes on RoRE is set out in the Figure below. Practical application of regulatory precedent to ESB Networks
25 Confidential July 2013 Frontier Economics 21 Figure 5. The impact of re-profiling capex on ESBN's equity return Return on Regulated Equity 16% 14% 12% 10% 8% 6% 4% Headline return from price control Addition / reduction in return from capex and opex incentives Addition / reduction in return from other incentives Ofgem view of GB RIIO T1 max Ofgem view of GB RIIO T1 min 2% 0% PR3 initial settlement PR3 with reprofiled capex The left-hand column shows the potential range of ESBN s equity return when PR3 was agreed. This shows that the settlement was largely symmetric, although it allowed for a potentially larger range of outcomes than Ofgem s view of the RIIO-T1 settlement (we note that judging the credible minimum and maximum outturns across a range of interacting incentive schemes is inevitably subjective, and that therefore direct comparisons between different regulatory regimes and jurisdictions is likely to be difficult). The right-hand column shows the impact of the capex re-profiling on the potential range of ESBN s equity return. The Figure shows that the revised package is much less symmetric than the original PR3 package with the downside risks now substantially greater than the potential upside. The upside under the revised package has declined by over 4%, and the downside risk has increased slightly. One can also now see that while ESBN s minimum equity return exceeds the Ofgem view of the maximum for RIIO-T1, it is no longer possible for ESBN to achieve the level of return that Ofgem expects the best performing UK companies to earn. This implies that in order to re-calibrate the price control so as to bring it back in line with the original PR3 symmetric determination, as part of any review the CER should consider a mix of: Practical application of regulatory precedent to ESB Networks
26 22 Frontier Economics July 2013 Confidential increasing ESB Network s WACC to re-balance the overall PR3 package; and/or increasing ESB Network s opex allowance and developing a revised capex delivery incentive in line with the re-profiled capex package.
27 Confidential July 2013 Frontier Economics 23 5 Conclusions and Recommendations ESBN have asked Frontier to assess the extent to which a review should take into account changes in the wider business context in setting an appropriate WACC. Our key findings are that: Regulators have explicitly recognised the links between exposure to uncertainty in relation to regulatory incentives and the allowed WACC and its components. The most useful precedent is from the UK where following the completion of the new RIIO regulatory framework, Ofgem set out explicitly how they would take linkages between likely incentive performance and WACC into account in considering the financeability of network companies. In this context, it is reasonable to view PR3 as a package, consisting of both baseline remuneration for opex and capex, and performance incentives in relation to opex and capex efficiency, and a range of broader outputs. ESBN s revised capex programme is likely to have impacted on their ability to achieve opex and incentive performance targets. Consequently, it is likely that risk to which ESBN is exposed has increased. Following the logic of Ofgem s RoRE analysis, if the overall PR3 settlement was deemed to have been appropriately calibrated by the CER, it would now be in need of recalibration, as the likely position in relation to incentives has changed. Failure to undertake any recalibration would effectively imply putting in place a package which is inconsistent with the CER s view at the start of PR3 of the appropriate balance of risk and reward. It is clear that such a move would be viewed negatively by the investment community and would impact significantly on cost of capital because it would undermine the perceived predictability of the regime. Conclusions and Recommendations
28 24 Frontier Economics July 2013 Confidential 5.1 Recommendations In order to re-calibrate the price control so as to bring it back in line with the original PR3 symmetric determination, we recommend that as part of any review the CER should consider a mix of (a) increasing ESB Network s WACC to re-balance the overall PR3 package, and/or (b) increasing ESB Network s opex allowance and developing a revised capex delivery incentive in line with the re-profiled capex package. Conclusions and Recommendations
29 FRONTIER ECONOMICS EUROPE BRUSSELS COLOGNE LONDON MADRID Frontier Economics Ltd 71 High Holborn London WC1V 6DA Tel. +44 (0) Fax. +44 (0)
RIIO-T1: Decision on fast-tracking for SP Transmission Ltd and Scottish Hydro Electric Transmission Ltd
To generators, shippers, suppliers, network companies, consumers and their representatives, the sustainable development community, investors and other interested parties Promoting choice and value for
SP Energy Networks 2015 2023 Business Plan
Environmental Discretionary Reward Scheme 1 SP Energy Networks 2015 2023 Business Plan Executive summary SP Distribution Ltd SP Manweb plc July 2013 RIIO ED1 Business Plan 2015 to 2023 2 A Message from
RIIO-T1 & RIIO-GD1: UNCERTAINTY ISSUES
RIIO-T1 & RIIO-GD1: UNCERTAINTY ISSUES A REPORT FOR CENTRICA February 2011 Final report - for publication Submitted by: CEPA LLP CONTENTS Executive Summary... i 1. Introduction... 1 1.1. Purpose... 1 1.2.
RIIO-T1 business plan submission London Tuesday 6 September 2011
RIIO-T1 business plan submission London Tuesday 6 September 2011 Cautionary statement This presentation contains certain statements that are neither reported financial results nor other historical information.
Duncan Burt Head of Commercial Operation National Grid. The Office of Gas and Electricity Markets 9 Millbank London SW1P 3GE
National Grid House Warwick Technology Park Gallows Hill, Warwick CV34 6DA The Office of Gas and Electricity Markets 9 Millbank London SW1P 3GE 16 June 2015 Duncan Burt Head of Commercial Operation National
The Implementation of the RIIO Framework
The Implementation of the RIIO Framework EPRG Winter Conference James Grayburn December 2014 Cambridge This presentation assesses Ofgem s implementation of RIIO framework following introduction of new
UTILITY REGULATOR WATER. Water & Sewerage Services Price Control 2015-21
Water & Sewerage Services Price Control 2015-21 Final Determination Annex A Financing Investment December 2014 Contents Page Water and Sewerage Services Price Control 2015-21 Final Determination Annex
Transmission Price Control Review: Updated Proposals and Smithers & Co. Ltd.: Report on the Cost of Capital. Response to consultation
Transmission Price Control Review: Updated Proposals and Smithers & Co. Ltd.: Report on the Cost of Capital Response to consultation Prepared by Ian Rowson, IMR Solutions On behalf of: BG Gas Services
National Grid Electricity Transmission s RIIO-T1 business plan overview
MARCH 2012 National Grid Electricity Transmission s RIIO-T1 business plan overview Connecting a sustainable future UK ELECTRICITY TRANSMISSION Contents 01 Introduction 02 The structure of our plan 03 Context
Monitoring and Treatment of Network Rail s Underspend and Efficiency: Policy Statement
Monitoring and Treatment of Network Rail s Underspend and Efficiency: Policy Statement January 2006 Published by the Office of Rail Regulation Contents Executive Summary...1 Context...1 Underspend framework...2
National Grid Gas Transmission s RIIO-T1 business plan overview
MARCH 2012 National Grid Gas Transmission s RIIO-T1 business plan overview Connecting a sustainable future UK GAS TRANSMISSION Contents 01 Introduction 02 The structure of our plan 03 Context 05 Our key
Thames Tideway Tunnel Cost of capital
Thames Tideway Tunnel Cost of capital CEPA briefing note 25 th August 2015 Introduction Thames Water over the past nine months has run a competitive licence application to appoint the Infrastructure Provider
Electricity network services. Long-term trends in prices and costs
Electricity network services Long-term trends in prices and costs Contents Executive summary 3 Background 4 Trends in network prices and service 6 Trends in underlying network costs 11 Executive summary
National Grid Electricity Transmission RIIO-T1: Initial Proposals consultation response Supplementary information Strategic Spares
National Grid Electricity Transmission RIIO-T1: Initial Proposals consultation response Supplementary information Strategic Spares Table of contents Executive summary... 2 Introduction... 4 Replenishment
EAST AYRSHIRE COUNCIL CABINET 21 OCTOBER 2009 TREASURY MANAGEMENT ANNUAL REPORT FOR 2008/2009 AND UPDATE ON 2009/10 STRATEGY
EAST AYRSHIRE COUNCIL CABINET 21 OCTOBER 2009 TREASURY MANAGEMENT ANNUAL REPORT FOR 2008/2009 AND UPDATE ON 2009/10 STRATEGY Report by Executive Head of Finance and Asset Management 1 PURPOSE OF REPORT
DTI Consultation on Proposals for a Special Administrator Regime for Energy Network Companies Ofgem s Response
DTI Consultation on Proposals for a Special Administrator Regime for Energy Network Companies Ofgem s Response June 2003 Introduction Ofgem welcomes the DTI consultation on proposals for a special administrator
Investment Strategy for Pensions Actuaries A Multi Asset Class Approach
Investment Strategy for Pensions Actuaries A Multi Asset Class Approach 16 January 2007 Representing Schroders: Neil Walton Head of Strategic Solutions Tel: 020 7658 2486 Email: [email protected]
NETWORK OUTPUT MEASURES CONSULTATION
NETWORK OUTPUT MEASURES CONSULTATION Great Britain s electricity transmission network transmits high-voltage electricity from where it is produced to where it is needed throughout the country. It broadly
Operating Leverage of EirGrid/ESBN Implications for PR4 Beta
Operating Leverage of EirGrid/ESBN Implications for PR4 Beta July 2015-1 - Europe Economics is registered in England No. 3477100. Registered offices at Chancery House, 53-64 Chancery Lane, London WC2A
Response to CER Consultation on Transmission Revenue for 2011 to 2015 (CER/10/102)
Response to CER Consultation on Transmission Revenue for 2011 to 2015 (CER/10/102) August 2010 ... 3 E XECUTIVE SUMMARY... 3 INTRODUCTION... 7 A TSO RESOURCED TO MEET THE EVOLVING NEEDS OF INDUSTRY AND
SP Transmission RIIO-T1 Business Plan
SP Transmission RIIO-T1 Business Plan July 2011 Contents Context Executive summary 1 1. Overview 3 1.1 Energy Market Reform 3 2. Capital investment, deliverability and associated outputs 4 2.1 Load Related
NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission PLC, Scottish Hydro Electric Transmission Limited
NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission PLC, Scottish Hydro Electric Transmission Limited TABLE OF CONTENTS 1.0 Purpose and Scope...2 1.1 Methodology Purpose...2 2.0
ENERGY ADVISORY COMMITTEE. Electricity Market Review: Return on Investment
ENERGY ADVISORY COMMITTEE Electricity Market Review: Return on Investment The Issue To review the different approaches in determining the return on investment in the electricity supply industry, and to
2017 19 TasNetworks Regulatory Proposal Expenditure Forecasting Methodology
2017 19 TasNetworks Regulatory Proposal Expenditure Forecasting Methodology Version Number 1 26 June 2015 Tasmanian Networks Pty Ltd (ACN 167 357 299) Table of contents 1 Introduction... 1 2 Meeting our
Domestic Customer Tariff Breakdown - RoI Note this is approximate due to tariff and consumption variations
Guide to Electricity price formation in Ireland and Northern Ireland The numbers The average household consumes 4,300 kwh 1 of electricity per annum in Ireland and 4,100 in Northern Ireland. At an average
The Profitability of BT s Regulated Services
The Profitability of BT s Regulated Services A REPORT PREPARED FOR VODAFONE November 2013 Frontier Economics Ltd, London. November 2013 Frontier Economics 1 Summary The analysis described below shows that
Determination of 2010 Transmission Allowed Revenue and Use of System Tariffs
Determination of 2010 Transmission Allowed Revenue and Use of System Tariffs DOCUMENT TYPE: REFERENCE: DATE PUBLISHED: QUERIES TO: Determination Paper CER/09/140 2 September 2009 Jamie Burke ([email protected])
PRELIMINARY DECISION CitiPower distribution determination 2016 20
PRELIMINARY DECISION CitiPower distribution determination 2016 20 Attachment 8 Corporate income tax October 2015 8-0 Attachment 8 Corporate income tax CitiPower determination 2016 20 Commonwealth of Australia
Regulatory aspects of Energy Investment Conditions in European Countries
CEER Memo on Regulatory aspects of Energy Investment Conditions in European Countries Ref: C14-IRB-23-03a 27-April-2015 Council of European Energy Regulators asbl Cours Saint-Michel 30a, Box F 1040 Brussels,
Rule change request. 18 September 2013
Reform of the distribution network pricing arrangements under the National Electricity Rules to provide better guidance for setting, and consulting on, cost-reflective distribution network pricing structures
EXPLANATORY MEMORANDUM TO THE CONTRACTS FOR DIFFERENCE (ELECTRICITY SUPPLIER OBLIGATIONS) REGULATIONS 2014. 2014 No. [XXXX]
EXPLANATORY MEMORANDUM TO THE CONTRACTS FOR DIFFERENCE (ELECTRICITY SUPPLIER OBLIGATIONS) REGULATIONS 2014 2014 No. [XXXX] 1. This explanatory memorandum has been prepared by the Department for Energy
Glossary of terms: RIIO-T1 and GD1 review
Glossary of terms: RIIO-T1 and GD1 review A Administrative burden Things that business must do or other administrative costs that businesses sustain due to a requirement from regulation. This may include
This document outlines Wales & West Utilities Business Plan for the next regulatory period from 2013-2021.
This document outlines Wales & West Utilities Business Plan for the next regulatory period from 2013-2021. It has been prepared following extensive consultation with a wide range of stakeholders and reflects
Government response: EMR consultation on industry code and licence modifications
Government response: EMR consultation on industry code and licence modifications June 2014 Crown copyright 2014 Copyright in the typographical arrangement and design rests with the Crown. This publication
Data Communications Company (DCC) price control guidance: process and procedures
Guidance document Contact: Tricia Quinn, Senior Economist Publication date: 27 July 2015 Team: Smarter Metering Email: [email protected] Overview: The Data and Communications Company (DCC) is required
Review of the Energy Savings Scheme. Position Paper
Review of the Energy Savings Scheme Position Paper October 2015 Contents Executive summary... 3 Energy Savings Scheme Review Report package... 3 Expanding to gas... 3 Target, penalties and duration...
National Grid Gas plc Annual Report and Accounts 2015/16. Company number 2006000
National Grid Gas plc Annual Report and Accounts 2015/16 Company number 2006000 National Grid Gas plc Annual Report and Accounts 2015/16 Contents National Grid Gas plc Annual Report and Accounts 2015/16
Water Charges Plan Decision Paper (Executive Summary)
Water Charges Plan Decision Paper (Executive Summary) DOCUMENT TYPE: REFERENCE: DATE PUBLISHED: QUERIES TO: Decision Paper CER/14/746 30 September 2014 [email protected] The Commission for Energy
CHESHIRE FIRE AUTHORITY SUBJECT : 2014-15 DRAFT BUDGET, COUNCIL TAX AND MEDIUM TERM FINANCIAL PLAN
CHESHIRE FIRE AUTHORITY Item 2 ITEM: 2 MEETING OF : FIRE AUTHORITY DATE : 12 FEBRUARY 2014 REPORT OF : CHIEF FIRE OFFICER AUTHOR : HEAD OF FINANCE SUBJECT : 2014-15 DRAFT BUDGET, COUNCIL TAX AND MEDIUM
Professional Indemnity Insurance Guide for FCA Regulated Firms (2015)
Professional Indemnity Insurance Guide for FCA Regulated Firms (2015) Nathan Sewell, CEO of Protean Risk, answers the Top 50 questions we are regularly asked as a specialist provider of Professional Indemnity
UK Government s Public Finance Plans and Fiscal Targets
UK Government s Public Finance Plans and Fiscal Targets Scottish Government June 2015 Overview This paper analyses the scope to make different choices about the UK s public finances, within the fiscal
POWER NI 2014 PRICE REVIEW: FINANCEABILITY AND ITS IMPLICATIONS FOR A REQUIRED PROFIT MARGIN
POWER NI 2014 PRICE REVIEW: FINANCEABILITY AND ITS IMPLICATIONS FOR A REQUIRED PROFIT MARGIN March 2013 Final report Submitted by: Cambridge Economic Policy Associates Ltd CONTENTS Executive summary...
A new electricity market for Northern Ireland and Ireland from 2016 - Integrated Single Electricity Market (I-SEM)
A new electricity market for Northern Ireland and Ireland from 2016 - Integrated Single Electricity Market (I-SEM) Non-technical summary High level design Draft Decision Paper SEM -14-047 June 2014 1 INTRODUCTION
Queensland Competition Authority SunWater Working Capital Allowance
Queensland Competition Authority SunWater Working Capital Allowance Final report 23 August 2011 Contents 1. Introduction 2 1.1 Context 2 1.2 Terms of reference 2 2. Working capital allowances 3 2.1 The
council tax support The story so far
council tax support The story so far Background Background 1 Funding 3 Collection rates and collection costs 7 Wider impacts and the future 9 Conclusions and recommendations 12 This report draws on emerging
Contract for Difference for non-uk Renewable Electricity Projects
Contract for Difference for non-uk Renewable Electricity Projects August 2014 Crown copyright 2014 URN 14D/291 You may re-use this information (not including logos) free of charge in any format or medium,
Shropshire Highways Draft Asset Management and Communications Strategy and Implications of Department for Transport Incentivised funding
Committee and Date Cabinet 14 th October 2015 Shropshire Highways Draft Asset Management and Communications Strategy and Implications of Department for Transport Incentivised funding Responsible Officer
NIGERIAN ELECTRICITY REGULATORY COMMISSION. Presentation at the ELECTRIC POWER INVESTORS FORUM
NIGERIAN ELECTRICITY REGULATORY COMMISSION Tariff Design and Regulation Presentation at the ELECTRIC POWER INVESTORS FORUM February 2011 OUTLINE Establishment and Functions of NERC MYTO as an Incentive
SP Energy Networks 2015 2023 Business Plan
SP Energy Networks 2015 2023 Business Plan Updated March 2014 Annex Heat pump and energy efficiency scenarios Frontier Economics 41 January 2014 1 Frontier Economics January 2014 Confidential Heat pump
Claim Estimates and WorkSafe Premiums
Claim Estimates and WorkSafe Premiums Introduction For employers with annual rateable remuneration of over $200,000 premiums for WorkSafe insurance are calculated taking into account their claims performance
for Analysing Listed Private Equity Companies
8 Steps for Analysing Listed Private Equity Companies Important Notice This document is for information only and does not constitute a recommendation or solicitation to subscribe or purchase any products.
Investing in renewable technologies CfD contract terms and strike prices
Investing in renewable technologies CfD contract terms and strike prices December 2013 Crown copyright 2013 You may re-use this information (not including logos) free of charge in any format or medium,
We hope all the questions are understandable, If you have any difficulties please email
Appendix 2- FEEDBACK QUESTIONNAIRE (word format) Thank you for taking the time to respond to our questions We hope all the questions are understandable, If you have any difficulties please email Once the
Electricity Market Reform:
Electricity Market Reform: Consultation on Low Carbon Contracts Company s and Electricity Settlements Company s operational costs 2015/16 Government Response January 2015 Crown copyright 2015 URN 15D/001
Information Requirements: Business Plan. Trinidad & Tobago Electricity Commission
Information Requirements: Business Plan June 01, 2011 May 31, 2016 Trinidad & Tobago Electricity Commission November 2010 This document is one of a series of discussion papers exploring a specific aspect
Reliability Options in Ireland and Northern Ireland Obligations and Penalties
Reliability Options in Ireland and Northern Ireland Obligations and Penalties European Commission Technical Working Group on Energy: Subgroup on generation adequacy 14 April, Brussels Background Single
Principles and Trade-Offs when Making Issuance Choices in the UK
Please cite this paper as: OECD (2011), Principles and Trade-Offs when Making Issuance Choices in the UK, OECD Working Papers on Sovereign Borrowing and Public Debt Management, No. 2, OECD Publishing.
FRC Risk Reporting Requirements Working Party Case Study (Pharmaceutical Industry)
FRC Risk Reporting Requirements Working Party Case Study (Pharmaceutical Industry) 1 Contents Executive Summary... 3 Background and Scope... 3 Company Background and Highlights... 3 Sample Risk Register...
Financeability and financing the asset base a discussion paper
Water today, water tomorrow Financeability and financing the asset base a discussion paper www.ofwat.gov.uk About this document This document focuses on two of our primary duties, which are to: further
Lloyd s response to DEFRA consultation: Securing the future availability and affordability of home insurance in areas of flood risk
Lloyd s response to DEFRA consultation: Securing the future availability and affordability of home insurance in areas of flood risk Q1. Do you have any evidence of small businesses experiencing difficulty
Cost of Capital Presentation for ERRA Tariff Committee Dr. Konstantin Petrov / Waisum Cheng / Dr. Daniel Grote April 2009 Experience you can trust.
Cost of Capital Presentation for ERRA Tariff Committee Dr. Konstantin Petrov / Waisum Cheng / Dr. Daniel Grote April 2009 Experience you can trust. Agenda 1.Definition of Cost of Capital a) Concept and
A review of wholesale leased line pricing in the Bailiwick of Guernsey
A review of wholesale leased line pricing in the Bailiwick of Guernsey A REPORT PREPARED FOR THE OFFICE OF UTILITY REGULATION January 2007 Frontier Economics Ltd, London. i Frontier Economics January 2007
THAMESIDE financial planning
THAMESIDE financial planning OUR INVESTMENT APPROACH UNDERSTANDING INVESTMENT RISK An overview Thameside Financial Planning recognises the importance of working with you to understand, achieve and maintain
PEI: New Strategies for Risk Management in Private Equity
PEI: New Strategies for Risk Management in Private Equity Risk in non-traditional secondary strategies By Augustin Duhamel and Vidar Bergum, 17Capital Introduction As the private equity industry has matured,
The Levy Control Framework
Report by the Comptroller and Auditor General Department of Energy & Climate Change The Levy Control Framework HC 815 SESSION 2013-14 27 NOVEMBER 2013 4 Key facts The Levy Control Framework Key facts 2bn
IASB/FASB Meeting Week beginning 11 April 2011. Top down approaches to discount rates
IASB/FASB Meeting Week beginning 11 April 2011 IASB Agenda reference 5A FASB Agenda Staff Paper reference 63A Contacts Matthias Zeitler [email protected] +44 (0)20 7246 6453 Shayne Kuhaneck [email protected]
Innovation in Electricity Networks
OPPORTUNITIES IN ENERGY SG2 Innovation in Electricity Networks physical & digital network security Contents Introduction... 1 Innovation in electricity networks... 1 The smart grid opportunity... 2 Physical
The path to retirement success
The path to retirement success How important are your investment and spending strategies? In this VIEW, Towers Watson Australia managing director ANDREW BOAL reports on investing for retirement success
Framework for assessing capex and opex forecasts as part of a building blocks approach to revenue/price determinations
Framework for assessing capex and opex forecasts as part of a building blocks approach to revenue/price determinations June 2012 Pinar Bagci Toby Brown Paul Carpenter Philip Hanser The Brattle Group 201
Co-operative Energy, Co-operative House Warwick Technology Park, Warwick CV34 6DA.
Terms and Conditions May 2014 Co-operative Energy: General Terms and Conditions for Domestic Customers Only Applicable from 1st June 2014. Co-operative Energy Limited is a limited liability company registered
What next for UK auctions of renewable Contracts for Difference?
What next for UK auctions of renewable Contracts for Difference? In February we saw the results of the first competitive auction for Contracts for Difference (CfDs), the primary support mechanism for incentivising
Scottish Independence. Charting the implications of demographic change. Ben Franklin. I May 2014 I. www.ilc.org.uk
Scottish Independence Charting the implications of demographic change Ben Franklin I May 2014 I www.ilc.org.uk Summary By 2037 Scotland s working age population is expected to be 3.5% than it was in 2013
SP Energy Networks 2015 2023 Business Plan
SP Energy Networks 2015 2023 Business Plan Updated March 2014 Annex 132kV Cable Strategy SP Energy Networks 27 March 2014 132kV Cable Strategy March 2014 Issue Date Issue No. Document Owner Amendment Details
Response to direct consultation questions
Consultation on proposals for the levels of banded support under the Renewables Obligation for the period 2013-17 and the Renewables Obligation (Scotland) Order 2011 Response by RenewableUK RenewableUK
n/e/r/a INTERNATIONAL COMPARISON OF UTILITIES REGULATED POST TAX RATES OF RETURN IN: NORTH AMERICA, THE UK, AND AUSTRALIA A Report Prepared by NERA
INTERNATIONAL COMPARISON OF UTILITIES REGULATED POST TAX RATES OF RETURN IN: NORTH AMERICA, THE UK, AND AUSTRALIA A Report Prepared by NERA March 2001 Sydney Project Team: Greg Houston Tom Hird Nicola
MLC Investment Management. Constructing Fixed Income Portfolios in a Low Interest Rate Environment. August 2010
Constructing Fixed Income Portfolios in a Low Interest Rate Environment August 2010 Stuart Piper Portfolio Manager MLC Investment Management For Adviser Use Only 1 Important Information: This Information
The Real Economic Impact of a European Financial Transactions Tax
(Cover page) Red Tape Watch! The Real Economic Impact of a European Financial Transactions Tax July 2013 NEW DIRECTION Page 1 of 12 About Red Tape Watch! Analysing the economic impact of European Union
August 2000. A Review of the Development of Competition in the Industrial and Commercial Gas Supply Market
August 2000 A Review of the Development of Competition in the Industrial and Commercial Gas Supply Market Executive summary This document explains the conclusions of Ofgem s 1999 review of the development
Waste Transfer Pricing Methodology for the disposal of higher activity waste from new nuclear power stations
Waste Transfer Pricing Methodology for the disposal of higher activity waste from new nuclear power stations December 2011 Contents Contents... i Introduction... 1 Executive Summary... 1 Background...
