National Grid Electricity Transmission s RIIO-T1 business plan overview

Size: px
Start display at page:

Download "National Grid Electricity Transmission s RIIO-T1 business plan overview"

Transcription

1 MARCH 2012 National Grid Electricity Transmission s RIIO-T1 business plan overview Connecting a sustainable future UK ELECTRICITY TRANSMISSION

2 Contents 01 Introduction 02 The structure of our plan 03 Context 05 Our key challenges 07 Stakeholder engagement 08 Our planned expenditure 10 How our plan has changed 11 Outputs 12 Safety 14 Reliability and availability 17 Environment 19 Customer satisfaction 21 Customer connections 23 How we will deliver 25 Innovation 26 Managing uncertainty 28 Financing our plan 30 Impact on customer charges 31 Impact on consumer bills 32 Summary of key data 33 Who we are

3 Introduction This document sets out National Grid Electricity Transmission s (NGET) business plan through to the end of the RIIO-T1 period in Our plan has been developed in conjunction with our stakeholders and we would like to thank all of you for your time and commitment throughout this process. This will be our first business plan under RIIO the new regulatory framework introduced by Ofgem. The goal of RIIO is to ensure reliable and sustainable energy networks that give consumers today s and tomorrow s value for money. Informed by our stakeholders views, our plan puts our customers at its heart and addresses five key requirements: we will continue to operate a safe and reliable network whilst facilitating a lower carbon future, as well as managing our own environmental footprint. Sustainable Safe Innovation Customer Reliable Our plan considers the needs of investors as we ensure we can attract adequate capital to finance our growing business and deliver our agreed outputs. This is all underpinned by the need to ensure affordability for consumers. Innovation will be a crucial tool in ensuring we can deliver the required investments efficiently. We demonstrate within our business plan how we will challenge ourselves to drive down the cost of delivery, utilising benchmarking to demonstrate efficiency and working with other companies to develop and adopt best practice. Our plan is based on the Gone Green scenario and anticipates over 30 gigawatts (GW) of new customer connections during the RIIO-T1 period. As this is just one view of the future, however, we have modelled alternative outcomes in order to ensure that neither we nor consumers face windfall gains or losses if reality should differ. We have proposed a series of regulatory mechanisms to adjust our revenue to reflect what actually happens. Operating a safe, reliable and efficient network has always been at the heart of our operations. This, along with our role in facilitating a low carbon future and shaping UK and European energy policy, will continue to be our core priorities. Our business plan reflects this. We look forward to evolving the network and the way we manage it to meet our customers and wider stakeholders needs over the coming decade. Affordable Financeable Nick Winser Executive Director, UK Electricity Transmission s RIIO-T1 business plan 01

4 The structure of our plan This document provides an overview of our business plan. More comprehensive information is available in the detailed annexes that comprise our overall plan. These annexes are summarised below. This document:- Overview Summarises the elements of our plan that are of most interest to our stakeholders Detailed plan The detail behind our baseline plan, split into sections to aid readability How we will deliver The adaptability and deliverability of our plans, including key challenges such as workforce renewal and growth Managing risk & uncertainty Key risks we have identified and the proposed mechanisms to deal with future uncertainties Outputs The outputs we will deliver and how we will measure their delivery European context Our role in Europe and the benefits and challenges that Europe brings Innovation strategy Our innovation strategy (incorporating R&D, partnering strategy and grass roots innovation) Stakeholder engagement process The process followed to gather stakeholder views and how they shaped our plan Finance The proposed finance package to allow us to fund our investment plan Future of Energy Our longer term view of energy to 2050 Efficiency & value for money Demonstrating how we test efficiency and use benchmarking to lower the cost of delivery Assumptions and glossary Asset guide Network Development Plan Network Availability Policy OUR PLAN 02

5 Context The energy industry between now and 2050 is set to change dramatically, driven by the need to provide secure, affordable and low-carbon energy. The path to low-carbon energy is driven by the UK Government targets for emissions and renewable energy, which aim to deliver an 80% reduction in greenhouse gas emissions, compared with 1990 levels, by In recent decades, energy policy and electricity industry regulation have largely been defined by the balance of two key drivers: affordability and security of supply. None of the challenges associated with these two drivers are likely to diminish in the future. We still need to connect new customers, renew and maintain our assets and operate our network in an economic and efficient manner, ensuring security of supply is maintained and a competitive market is facilitated. Existing electricity network Interconnectors Potential wind farm sites Potential nuclear sites In recent years, environmental sustainability and the needs of future consumers have been firmly added to this agenda. This will stimulate a transformation over the next decade. For example, approximately 25% of today s generation plant is expected to be decommissioned by New generation is required to fill this gap, and low-carbon generation is needed to enable the UK to meet its climate change targets. Gone Green The Gone Green electricity generation and demand scenario takes a holistic approach to meeting government climate change targets. Our business plan, including our proposed uncertainty mechanisms, is based on delivering the network needed to fully meet the government s energy security and environmental goals for 2020 and facilitates the connection of generation and demand assumed in the Gone Green scenario. Ireland Norway Netherlands Belgium During the business plan period we will be dealing with a large amount of change in the generation mix. With much of the existing nuclear plant coming to the end of its life, and coal and oil capacity limited as a result of the Large Combustion Plant Directive (LCPD), the majority of new power generation is forecast to come from Combined Cycle Gas Turbine (CCGT) and offshore wind generation, with new nuclear plants and more interconnection with Europe playing a greater role towards the end of RIIO-T1. France France Electricity Transmission s RIIO-T1 business plan 03

6 Context (continued) GW / / / / / / / / / / /31 Our business plan has to be flexible enough to cope with this uncertainty whilst being definite enough to be a useful indication of our activity and future spending. We have built our baseline plan on the industry-tested Gone Green scenario, which was supported by our stakeholders. Due to the range of credible outcomes over the next decade, we will need to be able to flex our plan. We have therefore proposed a number of uncertainty mechanisms tools that will deal with future changes in the most appropriate manner.? Want to know more? Refer to our Managing risk and uncertainty annex Gas Coal Hydro Nuclear Wind Marine Oil Biomass Interconnector Net Capacity Change Gone Green assumes that 40GW of new generation will connect across Great Britain between now and 2020/21 (which is a little under half the current installed capacity), with around 22GW of existing generation anticipated to close over the same period. Want to know more? Refer to our Future of Energy annex Adaptability and flexibility In light of the uncertainty regarding the exact demands our customers will place on our services over the next decade, our investment programme will need to be flexible. As our customers requirements evolve, we will alter the scope and timing of investments as more detailed information emerges, accelerating or delaying, creating or removing projects. Changes could be triggered by new requests for connections, customers changing their connection timescales or by market reform.? Operational context Today s transmission grid is designed to handle large, stable and predictable sources of generation, but the new sources which often depend on nature are inevitably less predictable and much less controllable. We will need to adapt to this fundamental change. Doing so will mean balancing, minute by minute, less predictable supplies of renewable energy with more flexible sources such as gas-fired power stations and stable sources such as nuclear plants. This will result in an increase in balancing activities, a rise in the level of operating reserve needed to maintain system frequency and a requirement for active and timely control of more sophisticated network assets. In order to achieve this, our plan is designed to deliver enhanced system operation capability. 04

7 Our key challenges We will deliver our plan in the face of considerable uncertainty, adapting and innovating as our customers needs evolve. We will do this while maintaining our high levels of operational performance and efficiency. In order to do this there are a number of major challenges we need to overcome. Expanding and renewing the transmission network Many of our electricity assets in use today were built in the 1950s or 60s and are now reaching the end of their useful technical lives. They need replacing, refurbishing or more extensive maintenance. Of the 13.6 billion capital expenditure programme proposed in our eight year business plan, roughly 40% is for replacing existing equipment. The other 60% will be invested in facilitating the connection of new sources of demand and generation, including new nuclear plants, wind farms and gas-fired power stations. Securing planning permission for our major infrastructure projects The Planning Act (2008) requires us to do more work earlier in the planning process including more engineering design and wider consultation before planning permission can be sought. Although we welcome the fact that the planning process is more predictable, this makes the process longer and more expensive. Because the Planning Act is relatively new, the effect it will have on major projects is not yet fully known. We will need to deal with the challenges of the new Act at the same time as increasing the number of planning applications we make as our investment grows throughout the RIIO-T1 period. Given the current level of interest in new infrastructure amongst many of our stakeholders, we will be dealing with these challenges against a backdrop of increased public scrutiny and greater levels of local consultations. Upgrading our critical IT systems Our complex network relies heavily on a small number of critical IT systems which help us to operate and manage it 24 hours a day, 365 days a year. The hardware for these systems needs to be upgraded approximately every five years to ensure that it can be supported. These upgrades will allow us to build in the flexibility that we will need to efficiently operate the transmission network of the future, as well as increasing our cyber security. It is certain, however, that we will incur costs at an earlier stage of our construction programme, as we develop a wider range of options earlier for the consultation process. The UK should have a state of the art control centre for the challenges that they are facing. Stakeholder comment, November 2011 Electricity Transmission s RIIO-T1 business plan 05

8 Our key challenges (continued) Finding and developing enough people with the right skills Over the next decade, we will build a larger, smarter and more flexible electricity transmission network. Doing this will require more people with specialist skills, people who are currently recruited from all around the world and for whom there is a great deal of competition. In addition, around 600 electricity staff just under one quarter of our current workforce will retire between now and And although staff turnover remains relatively low at around 3% per year, it nevertheless means that a further 800 employees will leave during the course of the business plan period. To replace these people and further grow our workforce, we anticipate recruiting and training around 2,000 new employees by the end of the RIIO-T1 period. To ensure we can be flexible enough to facilitate the 2020 targets, we need to start recruiting now as it can take up to four years to fully train a new starter. We are recruiting via a wide range of channels and are developing our training schemes to make sure our employees have the skills we need. We are also doing what we can to increase the number of potential recruits. This includes expanding our apprentice and graduate recruitment programmes as well as working with schools to encourage more children to study science, technology, engineering and mathematics. Managing commodity price volatility Independent, specialist advisors forecast that prices for commodities such as fuel, materials and specialist labour will rise faster than general inflation. This is a result of increasing worldwide competition for these resources. Our business plan presents evidence of these potential cost increases and explains the actions we will take to mitigate the impact this has on the cost of running our business. Europe As one of the driving forces behind the creation of the European Network of Transmission System Operators for Electricity (ENTSO-E), we put a great deal of effort into influencing the way the European energy industry is regulated. Europe will have an increasing effect on the UK s energy regulation and legislation in the coming years, as signalled by the development of European Network Codes. We will work towards our aim that regulation should maximise the benefits to UK consumers while minimising the cost to them by, among other things, ensuring that generation, transmission and supply companies have the right incentives to innovate and invest. A concern raised at more than one event was the shortage of people with relevant skills to meet future energy needs Comments from stakeholder workshops, March-May

9 Stakeholder engagement Change on the scale we are talking about affects everyone, and we have listened hard in order to produce this business plan. We have always sought stakeholders views, but they have now become an integral part of the way we do business and make decisions. This is a permanent change, not just for RIIO-T1. Under the banner of Talking Networks, we have been proactively engaging with our stakeholders on topics related to our RIIO-T1 business plan. We promised our stakeholders we would discuss our future challenges and plans with them, listen to what they had to say, and act on what they told us. Talking Networks builds on our regular stakeholder engagement activities, through which we have been engaging with our stakeholders for many years on the critical energy challenges facing the UK and Europe as well as on our day-to-day operational activities. These take the form of many different types of engagement, from energy industry discussions through our Transporting Britain s Energy process to community engagement in relation to new infrastructure projects. In the course of developing our business plan, we held 16 workshops, talking directly to several hundred stakeholders with a broad range of interests. We also carried out three consultations, held dozens of bilateral meetings and explored consumers attitudes to transmission. The stakeholders we consulted included consumers (current and future bill payers) and consumer representative groups, government, other regulators (e.g. the Health and Safety Executive (HSE) and the Environment Agency (EA)), the energy sector, environmental organisations, and academic experts. These sessions were facilitated by an independent third party so that we could be sure we were not unwittingly influencing, misunderstanding or misinterpreting what our stakeholders were saying. There has been a positive reaction to our Talking Networks process and the transparency with which we have developed our plan. We will continue to build on our stakeholder engagement activities, liaising with our stakeholders throughout the RIIO-T1 period. We have welcomed the open and transparent way in which the business plans have been developed. EdF, November 2011 consultation response? Want to know more? Refer to our Stakeholder engagement process annex or visit Electricity Transmission s RIIO-T1 business plan 07

10 Our planned expenditure Over the period we anticipate 16.4 billion of totex (total expenditure, i.e. capex plus opex) will be required to deliver the outputs agreed with stakeholders. Our actual spend will be driven by user requirements and we are proposing uncertainty mechanisms to adjust revenues in line with what becomes reality. RIIO-T1 investment profile Total forecast expenditure over the RIIO-T1 period m, 09/10 prices Customer-driven capital expenditure Non customer-driven capital expenditure Strategic Wider Works* 2013/ / / / / / / /21 Total 1,042 1,308 1,191 1, , , ,356 System Operator capital expenditure Total operating expenditure Total ,828 2,088 2,318 2,248 2,281 2,050 2,080 1,791 1,540 * Strategic Wider Works are defined as projects over 500m which are dealt with via within-period cost determination 08

11 In order to deliver the outputs, our plan contains a number of key activities. These can be grouped into five core categories and form the foundations upon which we operate to optimise efficient delivery and drive our choices of delivery model and organisational structure. Load-related activities (customer-driven) Load-related investment is driven by changes in the pattern of generation and demand, both through direct interaction with customers via connection applications, and through the need to ensure that the interconnected transmission system fulfils certain security requirements, given the anticipated background of generation and demand. Our plan is based on Gone Green (see page 3) and anticipates connection of over 30GW of new generation, resulting in total load-related investment in the business plan period of 7.8bn, which equates to 48% of our plan. Investment in Strategic Wider Works (projects greater than 500m) is forecast to be 1.4bn. Non load-related activities (non customer-driven replacing and maintaining our assets) Non load-related expenditure is driven primarily by the need to manage the ongoing safety, reliability and environmental performance of our asset base. The potential customer impact associated with the deteriorating safety, reliability and environmental performance of assets reaching the end of their useful life continues to drive a programme of replacement, refurbishment and maintenance. The forecast total for non load-related investment in the business plan period is 6.4bn (made up of 5.3bn capex and 1.1bn opex) which represents 39% of our business plan. System operation The costs associated with our system operation function are predominantly driven by the resources and IT solutions that we require to safely and economically run the network, whilst still maintaining reliability. During the business plan period, the total spend for direct opex is forecast to be 367m and investments in IT systems (for asset health purposes and enhanced capability) are forecast at 271m. We also plan to invest 42m to improve the resilience of our data centres. Expenditure on system operation represents 4% of our total baseline plan. Network planning and support Network planning and support activities represent 4% ( 730m) of our plan and are those activities which provide the expert technical assistance required to plan and deliver construction and maintenance work. Business support Business support activities represent 5% ( 758m) of our plan and are defined as operational services such as IT, property management, HR and finance which are provided across National Grid with Electricity Transmission s proportion allocated using an agreed regulatory methodology. These support functions aid the delivery of our core activities, and maintain the longterm health of our business by providing key services such as financial control, transactional processing, recruitment and IT support. Want to know more? Refer to our Detailed plan annexes? Electricity Transmission s RIIO-T1 business plan 09

12 How our plan has changed Since our July 2011 submission, we have updated our business plan following feedback from Ofgem and other stakeholders. The key updates agreed with Ofgem are: Updates to reflect the Gone Green 2011 scenario Alignment of our 2011/12 and 2012/13 forecasts to reflect our actual expenditure and latest forecast These updates have had the following impact on our business plan headline numbers: billion July 2011 March 2012 Capex Opex Creating a new outputs annex, which: Links expenditure to outputs Assesses the impact of delivering more or less in order to justify our baseline plan as the best outcome for consumers Provides more information on our environmental strategy Developing our new Innovation strategy annex, which provides more information on our overall approach to innovation, including commercial innovation. Totex As part of the development of our updated plan, we have also addressed stakeholders feedback on other areas of our initial submission. This has included: Developing our stakeholder annex: To demonstrate a wider range of stakeholder views To engage more with the voluntary sector and local communities To explain the implications of our uncertainty mechanisms on charging volatility To show more clearly how stakeholders have influenced our plans Developing our Detailed plan annex to demonstrate the linkages between capital and operational expenditure. Further justifying our finance proposals by: Providing more detail on the link between risk and the cost of equity Justifying our requirement for 7.5% cost of equity Providing the rationale for our proposed notional dividend policy 10

13 Outputs During the RIIO-T1 period, we will deliver agreed levels of outputs for safety, reliability and availability, our environmental impact, customer satisfaction and customer connections. In developing the outputs we will deliver over the next decade, we have actively sought stakeholders views on what they want from our network over the period. The following pages examine each of the RIIO outputs in turn. We explain the key elements that contribute to delivery of each output, including what we already do to deliver these and what we will do in the future. For each output, we describe what was included in our July 2011 business plan, what our stakeholders have told us is important to them, and what we are proposing in our updated March 2012 submission. We list the primary and secondary deliverables in each area and explain how we will be funded and, where appropriate, incentivised to meet our targets over the business plan period. Most of our activities contribute to several outputs, so we have mapped costs to the most significant outputs that each activity delivers. For example, the money we spend on maintaining our assets contributes to the safety and environmental outputs, but the main reason for the work is to maintain reliability. These costs are therefore split, with 50% allocated to reliability, 35% to safety and 15% to the environmental output. The chart below shows the proportion of our totex costs associated with each output. Not surprisingly, maintaining reliability is our biggest focus. Mapping costs to outputs Following our July 2011 submission, Ofgem and our other stakeholders told us they wanted to see better linkage between our costs and outputs. As a result, each of the following output sections includes our forecast expenditure for RIIO-T1. In assessing how much of our proposed spending can be attributed to each of the outputs, we have made some broad assumptions. Electricity Transmission s RIIO-T1 business plan 11

14 Outputs: Safety Safety is at the core of our business and is a top priority for us. We will continue to mitigate risks and strive to eradicate injuries. Our business plan enables us to comply with our statutory duties and maintain our focus on safety as a priority. Attendees felt that National Grid places a strong emphasis on, and performs well in the area of safety. They expressed a desire to see this continue Comments from stakeholder workshop, December 2010 An important contributor to staff and public safety is the condition of our assets. Assets are designed and constructed to be as safe as practicable throughout their lifetime. We take all necessary steps to prevent major accidents and have tested mitigation plans in place to limit consequences should they occur. Asset condition is managed in the long-term by a combination of maintenance, refurbishment and replacement activities. We take a risk and criticality approach to our asset replacement investment, which assesses the condition of an asset and the consequences of its failure in order to prioritise investment. Physical Security The UK Government (DECC), working closely with the Centre for the Protection of National Infrastructure, has designated a number of our sites and critical IT systems as Critical National Infrastructure. Our security strategy allows for effective and appropriate security measures to be employed to safeguard our assets and provides for the enhanced protection necessary to ensure the continued safe operation of our IT systems. Our proposal in July 2011 What stakeholders said What is in our March 2012 plan We will ensure compliance with relevant legislation Stakeholders agreed, stating that safety is not negotiable Our plan is designed to comply with all applicable legislation 12

15 The following table outlines the key deliverables in relation to the safety output, how it will be funded and our anticipated investment over the RIIO-T1 period. Output Safety Primary deliverable Compliance with all applicable safety legislation regarding operation of the electricity transmission network and all people potentially impacted by it (including staff, contractors, customers and members of the general public) Secondary deliverable Maintaining the current level of network risk (NOMs) through maintenance and the use of our asset health and criticality approach to replacement Funding and incentives Ex ante allowance Financial exposure to under/over delivery against NOMs targets (to be agreed) Relevant uncertainty mechanisms None applicable How stakeholders can assess our performance Compliance with Health and Safety Legislation Total forecast expenditure for safety over the RIIO-T1 period ( m, 09/10 prices) 2013/ / / / / / / /21 Total ,269 Want to know more? Refer to our Outputs annex? Electricity Transmission s RIIO-T1 business plan 13

16 Outputs: Reliability and availability Stakeholders have told us that the reliability of the transmission network is important and it is not appropriate for this to be reduced. They recognise that this has an associated cost. We have documented our approach to maintaining availability of the transmission network within our draft Network Availability Policy. We will continue to meet the connection dates sought by generation customers by completing the local works required for the generator to connect to the transmission system in a timely manner. Wider works may be required to fully secure the network and allow efficient ongoing operation of the network; constraint costs may be incurred while the wider works are being delivered. Energy Not Supplied The primary output within reliability is minimisation of Energy Not Supplied, which incorporates the number and duration of supply interruptions. We are already incentivised on this and over the business plan period we are aiming to maintain Energy Not Supplied at current levels. This represents a considerable challenge as network risk is forecast to rise over the same period. Network Output Measures The condition and performance of our assets deteriorate with age and use. Maintenance can help manage the associated risk; however, there will come a point where replacement or refurbishment is required to maintain reliability. Our asset health and criticality indices Network Output Measures (NOMs) consider reliability as well as safety and environmental impacts. The NOMs methodology scores the consequences of asset failure in terms of the potential impact on the network. By understanding the distribution of asset condition and criticality across the network and how that relates to average circuit unreliability and Energy Not Supplied, we can manage our large asset population effectively. NOMs allow us to forecast the future network risk based on what we know about how assets degrade over time. We are therefore able to draw conclusions about future reliability and Energy Not Supplied and adjust our asset management strategy accordingly. We need to balance replacement, refurbishment and maintenance activities with works to connect new customers. 14

17 Our proposal in July 2011 What stakeholders said What is in our March 2012 plan We will utilise the Gone Green generation and demand background as our baseline assumption and have modelled credible alternatives to this scenario Stakeholders questioned some of the assumptions but supported Gone Green as the most appropriate scenario for our baseline plan Our plan is based on Gone Green, updated for our March 2012 submission. Alternative scenarios have been developed to identify a credible range of outcomes. Our asset management framework is designed to maintain the integrity of the network Stakeholders said that reliability levels should be maintained We will use NOMs to monitor and maintain the integrity of the network and help prioritise expenditure of 6.4bn We will further discuss the benefits and risks of a targeted N-1 security standard with stakeholders so they can make an informed choice Stakeholders did not support a blanket change to the security standards but supported trials of targeted N-1 operation Our plan provides for targeted N-1 operation. The lessons learnt will be monitored and shared through the SQSS review group. We will enhance our smart operation to cope with the challenges facing the industry Stakeholders said the network is already smart but it needs to be smarter. Smart actions should not detract from investment where it is needed and should not be restricted to assets. We are evolving innovative ways of working and implementing technology to become smarter, whilst ensuring reliability and security are maintained We will create a Network Development Policy, stating the steps we will follow to identify required wider works Stakeholders accepted the proposals, not being able to identify an alternative. Some questioned whether our scenarios are comprehensive enough. Our Network Development Policy forms part of this submission. We are investigating combining some of our consultation processes and continuously review our scenarios in conjunction with stakeholders. We will invest 262m in new IT systems and the maintenance of existing systems to enhance control room capability Stakeholders were supportive of this approach and keen that it is progressed quickly We have included 271m of investment in our plan to deliver enhanced IT capability including some expenditure deferred from 2012/13 Electricity Transmission s RIIO-T1 business plan 15

18 Reliability and availability (continued) The following table outlines the key deliverables in relation to the reliability and availability output, how it will be funded and our anticipated investment over the RIIO-T1 period. Output Reliability and availability Primary deliverable Maintenance of the current level of Energy Not Supplied, with a target of 316MWh per annum for the RIIO-T1 period and complying with our Network Availability Policy Secondary deliverable Maintaining the current level of network risk (NOMs) through maintenance and the use of our asset health and criticality approach to replacement Provision of boundary capacity to meet customers requirements Funding and incentives Ex ante allowance for replacement/refurbishment of high Replacement Priority assets Financial incentive on Energy Not Supplied (at 16 per KWh) Financial incentive (penalty only) against Network Availability Policy Financial exposure to under/over delivery against NOMs targets Exposure to the consequences of non/under-delivery via SO incentives (BSIS) Ex ante allowance for boundary capacity to meet the Gone Green scenario Relevant uncertainty mechanisms (see page 27 for more details) Wider reinforcement works Real Price Effects Demand-related infrastructure Local generation connection Critical National Infrastructure Climate change EU and GB market facilitation How stakeholders can assess our performance An annual report will be created under Licence Condition 17 detailing our performance against the Energy Not Supplied target BSIS quarterly updates at Operational Fora Information within the Seven Year Statement Total forecast expenditure for reliability and availability over the RIIO-T1 period ( m, 09/10 prices) 2013/ / / / / / / /21 Total 1,334 1,470 1,374 1,348 1,186 1,255 1, , Want to know more? Refer to our Outputs annex?

19 Outputs: Environment Our plan supports the decarbonisation of the electricity sector and puts us on track to deliver our environmental legislative obligations. The impact of our operations in the local communities we serve is another key environmental consideration. We are consulting stakeholders about this outside of this business plan submission process. Facilitating the connection of low-carbon energy Stakeholders see this as our main environmental priority. Whilst we cannot prioritise the connection of renewable sources of generation, we will meet our connection obligations throughout the RIIO-T1 period to enable low-carbon sources to connect as quickly as possible. Our business carbon footprint The greatest contributor to our direct emissions is the leakage of SF 6 from our switchgear. The volume of assets on our network containing SF 6 will increase throughout the business plan period. We therefore propose that our target for SF 6 leakage is based on the number of assets installed, with a best practice target leakage rate of 0.5% for all new switchgear, leading to an overall reduction in leakage as a percentage of the total mass installed. As a group, we have traced previously published and verifiable data back to 1990 to define our baseline emission level as 19.6 million tonnes of carbon dioxide equivalent. We are committed to reducing our emissions by 80% by 2050, compared to 1990 levels. Visual amenity In September 2011 we published our latest approach to the routeing of new transmission lines. This states that we will carry out full and thorough stakeholder consultation in relation to every new route, taking this into consideration with the applicable technical considerations in order to determine the best route possible for each individual case. Additionally, we are currently carrying out research to determine consumers willingness to pay to mitigate the effect on visual amenity of existing infrastructure and expect to publish the results of this research in Summer Our proposal in July 2011 What stakeholders said What is in our March 2012 plan We will act to minimise our impact on the environment both directly through reducing our own emissions and through our role in facilitating the decarbonisation of energy Most stakeholders saw our primary role as facilitating the connection of renewable energy, although some were interested in our own business carbon footprint Our plan facilitates the connection of around 24GW of renewable and low-carbon generation, which will support the decarbonisation of the electricity network. We will minimise our business carbon footprint, evaluating short-term reductions against longer-term benefits. We included a provision for a nominal 10% of new electricity lines to be built underground, with an uncertainty mechanism in place to reflect the outcome of each individual consultation process Stakeholders were concerned that 10% was a target and therefore the number was too low We discussed our plan with stakeholders, explaining that 10% is a nominal figure and that the uncertainty mechanism will flex funding up and down depending on the outcome of each individual planning application. We have not changed this assumption since July Electricity Transmission s RIIO-T1 business plan 17

20 Environment (continued) The following table outlines the key deliverables in relation to the environment output, how it will be funded and our anticipated investment over the RIIO-T1 period. Output Environment Primary deliverable Compliance with SF 6 leakage targets based on installed assets. New assets will have a best practice target leakage rate of 0.5% per annum. Secondary deliverable Minimisation of losses from our network, balancing short-term increases with the longerterm benefits of energy industry decarbonisation Maintaining the current level of network risk (NOMs) through maintenance and the use of our asset health and criticality approach to replacement Proportionately maintaining our current business carbon footprint in the face of the increasing volume of SF 6 equipment on the network Funding and incentives Financial exposure to under/over delivery against NOMs targets (to be agreed) Symmetrical financial incentive based on SF 6 emissions and the social cost of carbon Reputational incentives based on network losses and percentage of new renewable energy connections (being consulted on by Ofgem) Fund for undergrounding existing lines Relevant uncertainty mechanisms (see page 27 for more details) Planning requirements Climate change How stakeholders can assess our performance Compliance with legislation, annual publication of our SF 6 leakage statistics Total forecast expenditure for the environment over the RIIO-T1 period ( m, 09/10 prices) 2013/ / / / / / / /21 Total ,591 Want to know more? Refer to our Outputs annex? 18

21 Outputs: Customer satisfaction To deliver our part in meeting the UK s climate change targets, we need to be a flexible organisation that is in tune with the market environment and with our customers. Customer research helps us understand our customers perspective of our performance and helps us continuously improve our customer service levels. Feedback is important to us and as such we introduced a formal survey in 2009 to help identify potential improvements to our customer service levels. This survey will be further enhanced throughout the RIIO-T1 period. Our work in this area is underpinned by our customer commitment, which articulates for ourselves and our customers what is expected in the delivery of our services. There are, however, times when we get it wrong and so we have introduced a formal complaints process that provides an independent escalation route in the event that customers do not receive a satisfactory resolution to their concerns through their normal dayto-day contacts. Our proposal in July 2011 What stakeholders said What is in our March 2012 plan We will introduce a customer complaints process Stakeholders felt that tracking customer complaints is a good measure of customer service We have implemented a complaints process and customer commitment to drive improvements in our service We will improve our website Stakeholders said our website is difficult to navigate We have started work on website improvements and these will be released incrementally over the next 12 months We will consider stakeholder requirements in relation to predictability of charges Stability is the preference, but if unachievable, charges must be predictable and transparent We have adjusted our financing proposals to make revenue recovery smoother over the period and are progressing developments to improve the transparency and predictability of charges Following our July 2011 plan, we discussed a customer survey as the tool to measure customer satisfaction Stakeholders were wary that customer satisfaction would be measured by surveys alone. The survey itself must not be a resource burden on stakeholders. We continue to work with Ofgem and the other TOs on the format of the survey Electricity Transmission s RIIO-T1 business plan 19

22 Customer satisfaction (continued) The following table outlines the key deliverables in relation to the customer satisfaction output, how it will be funded and our anticipated investment over the RIIO-T1 period. Output Customer satisfaction Primary deliverable Improved levels of customer satisfaction and, along with Ofgem, other TOs and stakeholders, further development of a customer and stakeholder satisfaction survey Secondary deliverable Not applicable Funding and incentives Ex ante allowance for staff and systems Financial incentive based on annual customer survey (in the range of +/-1% of total annual revenue) Discretionary reward for outstanding stakeholder engagement (up to 0.5% of total annual revenue) Relevant uncertainty mechanisms (see page 27 for more details) Planning requirements EU and GB market facilitation How stakeholders can assess our performance Publication of survey results and our stakeholder engagement submission Total forecast expenditure for customer satisfaction over the RIIO-T1 period ( m, 09/10 prices) 2013/ / / / / / / /21 Total ? Want to know more? Refer to our Outputs or Stakeholder engagement process annex or visit our Customer Commitment website: CustomerCommitment/ 20

23 Outputs: Customer connections One of our obligations is to meet any reasonable customer request for connection to the network. Once a formal application is received, we have a requirement to respond within three months with a connection offer and date. We engage in early and regular discussions with customers throughout the connections process and assist potential developers in preparation of a shortlist of development options by offering advice on likely connection times and complexity. We assist customers in completing our application form for a new connection. This results in an increase in applications proceeding to final signature and a reduction in speculative applications. Customers welcome this approach, acknowledging the improvement this has made to the process. We will continue to seek improvement to the process throughout the business plan period. Our proposal in July 2011 What stakeholders said What is in our March 2012 plan We will comply with our connections licence obligations Supported by stakeholders We will comply with our connections licence obligations We will continue to work with our customers to make the connections process accessible and easily navigable Stakeholders supported further development of the process We will continue to work with our customers to make the connections process accessible and easily navigable Electricity Transmission s RIIO-T1 business plan 21

24 Customer connections (continued) The following table outlines the key deliverables in relation to the customer connections output, how it will be funded and our anticipated investment over the RIIO-T1 period. Output Customer connections Primary deliverable Meeting our licence obligations to deliver timely connections Secondary deliverable Not applicable Funding and incentives Ex ante funding for a team to carry out the connections process Penalty for not meeting connections licence obligations Relevant uncertainty mechanisms None applicable How stakeholders can assess our performance Quarterly connections report Total forecast expenditure for customer connections over the RIIO-T1 period ( m, 09/10 prices) 2013/ / / / / / / /21 Total ,401 Want to know more? Refer to our Outputs annex? 22

25 How we will deliver To provide the outputs our stakeholders want, we will continue to optimise our structure and deliver work efficiently. Deliverability We need to make decisions on delivery model, organisational structure and our preferred balance between cost and risk. We have weighed up the benefits of alternative delivery models for our main activities and have explored the trade-off between activities to deliver required outputs. Delivery models Delivery models cover the way we organise ourselves within the business as well as the choices we make about the mix of work completed in-house and delivered by third parties. We take a variety of factors into account such as the complexity of the work, where the expertise sits, the need for flexibility and economic factors when assessing whether insourcing or outsourcing is most appropriate. For example, we use competitive tendering where the highly-specialised nature of the work means that retaining the skills and equipment in-house is not efficient, such as for our cable tunnel projects. Conversely, we use alliance models for long-term predictable work in order to leverage economies of scale and drive learning and year-on-year improvements. Throughout the business plan period, we will continue to review and evolve our practices, seeking to continually improve and find innovative ways of working. Equitable trade-offs In undertaking our operations, we make a number of trade-offs between different costs, risks and benefits. The main trade-offs within our business are the interactions between our Transmission Owner (TO) and System Operator (SO) functions and balancing capital and operational costs in relation to asset replacement, refurbishment and maintenance. As TO and SO, our risk profile is different to networks which are TO only. This is considered within our risk and uncertainty analysis and our finance package.? Want to know more? Refer to our Managing risk and uncertainty and Finance annexes We assess the optimum balance between trading off the higher costs of investment (capital expenditure) with the costs of maintenance and condition monitoring (operational expenditure) and the risk of failure. For example, over the current price control period we have been able to use the latest condition information and performance data together with the outputs of research projects to extend technical asset lives for certain types of equipment. We will continue to assess these trade-offs to ensure we are achieving the optimum result. Electricity Transmission s RIIO-T1 business plan 23

26 How we will deliver (continued) Efficiency We anticipate that we will be entering a phase of steep capital and workload growth, delivering investments required by our customers whilst operating and maintaining an increasing asset base. As such, the majority of our costs are increasing and a growing element of our forecast efficiencies will take the form of delivering more for the same through productivity initiatives, mitigation of upward pressures and spend to save transformation programmes, along with more traditional cost reduction methods. Innovation will be critical in ensuring the efficient delivery of our challenging plans. For operational expenditure, we have embedded an average long-term efficiency level of 1.6% per annum. This efficiency level is challenging and is at the top end of historical utility averages and regulatory precedent. As demonstrated below, the embedded efficiency (which we expect to deliver through avoided cost efficiencies due to forecast workload growth) will help to offset upward cost pressures. We test ourselves through mature industry benchmarking studies such as ICTSO and ITOMS which take place every two years. Membership of these organisations also allows us to discuss best practice with other member companies, and to collaborate where this is mutually beneficial. At the highest level, 98% of our current cost base has either been market tested via competitive tenders or benchmarked in the last four years. Non-load related capex and maintenance Load related capex and connections System operation Network planning and support Business support Volume of our expenditure benchmarked / market tested Alliances Market tested Benchmarked Not tested million Offsetting upward cost pressures Other 22 IS capabilities 26 Resourcing 24 Asset condition 17 Asset growth 26 Real prices 43 Efficiencies /11 Upward cost pressures Efficiencies 2020/21 We are a long-term business. The scale of asset replacement and system reinforcement needed gives us an opportunity to invest in the latest technology to deliver long-term value. We are currently incentivised to focus on the lowest cost choice from a capex and opex perspective. This may not always be the right approach as it does not consider future stakeholders needs. We have therefore developed a Whole Life Value process that focuses on all the different aspects of stakeholder needs on a systematic basis. This framework supports our investment and policy decisions, with the aim of creating an enduring value over the lifetime of our assets.? Want to know more? Refer to our How we will deliver and Efficiency and value for money annexes 24

National Grid Gas Transmission s RIIO-T1 business plan overview

National Grid Gas Transmission s RIIO-T1 business plan overview MARCH 2012 National Grid Gas Transmission s RIIO-T1 business plan overview Connecting a sustainable future UK GAS TRANSMISSION Contents 01 Introduction 02 The structure of our plan 03 Context 05 Our key

More information

RIIO-T1: Decision on fast-tracking for SP Transmission Ltd and Scottish Hydro Electric Transmission Ltd

RIIO-T1: Decision on fast-tracking for SP Transmission Ltd and Scottish Hydro Electric Transmission Ltd To generators, shippers, suppliers, network companies, consumers and their representatives, the sustainable development community, investors and other interested parties Promoting choice and value for

More information

SP Energy Networks 2015 2023 Business Plan

SP Energy Networks 2015 2023 Business Plan Environmental Discretionary Reward Scheme 1 SP Energy Networks 2015 2023 Business Plan Executive summary SP Distribution Ltd SP Manweb plc July 2013 RIIO ED1 Business Plan 2015 to 2023 2 A Message from

More information

Duncan Burt Head of Commercial Operation National Grid. The Office of Gas and Electricity Markets 9 Millbank London SW1P 3GE

Duncan Burt Head of Commercial Operation National Grid. The Office of Gas and Electricity Markets 9 Millbank London SW1P 3GE National Grid House Warwick Technology Park Gallows Hill, Warwick CV34 6DA The Office of Gas and Electricity Markets 9 Millbank London SW1P 3GE 16 June 2015 Duncan Burt Head of Commercial Operation National

More information

Asset Management Policy March 2014

Asset Management Policy March 2014 Asset Management Policy March 2014 In February 2011, we published our current Asset Management Policy. This is the first update incorporating further developments in our thinking on capacity planning and

More information

NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission PLC, Scottish Hydro Electric Transmission Limited

NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission PLC, Scottish Hydro Electric Transmission Limited NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission PLC, Scottish Hydro Electric Transmission Limited TABLE OF CONTENTS 1.0 Purpose and Scope...2 1.1 Methodology Purpose...2 2.0

More information

SP Transmission RIIO-T1 Business Plan

SP Transmission RIIO-T1 Business Plan SP Transmission RIIO-T1 Business Plan July 2011 Contents Context Executive summary 1 1. Overview 3 1.1 Energy Market Reform 3 2. Capital investment, deliverability and associated outputs 4 2.1 Load Related

More information

NETWORK OUTPUT MEASURES CONSULTATION

NETWORK OUTPUT MEASURES CONSULTATION NETWORK OUTPUT MEASURES CONSULTATION Great Britain s electricity transmission network transmits high-voltage electricity from where it is produced to where it is needed throughout the country. It broadly

More information

This seeks to define Contracts for Difference (CfDs) and their relevance to energy related development in Copeland.

This seeks to define Contracts for Difference (CfDs) and their relevance to energy related development in Copeland. Contracts for Difference and Electricity Market Reform LEAD OFFICER: REPORT AUTHOR: John Groves Denice Gallen Summary and Recommendation: This seeks to define Contracts for Difference (CfDs) and their

More information

Innovation in Electricity Networks

Innovation in Electricity Networks OPPORTUNITIES IN ENERGY SG2 Innovation in Electricity Networks physical & digital network security Contents Introduction... 1 Innovation in electricity networks... 1 The smart grid opportunity... 2 Physical

More information

This document outlines Wales & West Utilities Business Plan for the next regulatory period from 2013-2021.

This document outlines Wales & West Utilities Business Plan for the next regulatory period from 2013-2021. This document outlines Wales & West Utilities Business Plan for the next regulatory period from 2013-2021. It has been prepared following extensive consultation with a wide range of stakeholders and reflects

More information

Sustainable Development Strategy

Sustainable Development Strategy Sustainable Development Strategy Our vision and strategy: A railway fit for the future 2013 2024 Document Ref: SBPT204 Version 0.71 Executive summary Network Rail exists to generate outstanding value for

More information

RIIO T1 Business Plan Update January 2012

RIIO T1 Business Plan Update January 2012 UPDATE RIIO T1 Business Plan Update January 2012 Executive Summary Purpose of this Document In accordance with Ofgem s fast-track process, this updated Executive Summary sets out SP Transmission Limited

More information

Network Rail Infrastructure Projects Joint Relationship Management Plan

Network Rail Infrastructure Projects Joint Relationship Management Plan Network Rail Infrastructure Projects Joint Relationship Management Plan Project Title Project Number [ ] [ ] Revision: Date: Description: Author [ ] Approved on behalf of Network Rail Approved on behalf

More information

Interaction between business context and an appropriate WACC for ESBN

Interaction between business context and an appropriate WACC for ESBN Interaction between business context and an appropriate WACC for ESBN A REPORT PREPARED FOR ESB NETWORKS September 2013 Frontier Economics Ltd, London. Confidential July 2013 Frontier Economics i Interaction

More information

National Grid Gas plc Annual Report and Accounts 2015/16. Company number 2006000

National Grid Gas plc Annual Report and Accounts 2015/16. Company number 2006000 National Grid Gas plc Annual Report and Accounts 2015/16 Company number 2006000 National Grid Gas plc Annual Report and Accounts 2015/16 Contents National Grid Gas plc Annual Report and Accounts 2015/16

More information

Middlesbrough Manager Competency Framework. Behaviours Business Skills Middlesbrough Manager

Middlesbrough Manager Competency Framework. Behaviours Business Skills Middlesbrough Manager Middlesbrough Manager Competency Framework + = Behaviours Business Skills Middlesbrough Manager Middlesbrough Manager Competency Framework Background Middlesbrough Council is going through significant

More information

ENA Submission to the Parliamentary Renewable and Sustainable Energy Group Inquiry into the access and management of renewables and the Grid

ENA Submission to the Parliamentary Renewable and Sustainable Energy Group Inquiry into the access and management of renewables and the Grid 1 ENA Submission to the Parliamentary Renewable and Sustainable Energy Group Inquiry into the access and management of renewables and the Grid 1.0 Introduction 1.1 Energy Networks Association (ENA) is

More information

NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission Limited, Scottish Hydro Electric Transmission Limited

NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission Limited, Scottish Hydro Electric Transmission Limited NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission Limited, Scottish Hydro Electric Transmission Limited TABLE OF CONTENTS 1.0 Purpose and Scope...2 1.1 Methodology Purpose...2

More information

SHE Transmission. 2015_10_30 Transmission Losses Strategy Rev 2.0 October 2015

SHE Transmission. 2015_10_30 Transmission Losses Strategy Rev 2.0 October 2015 SHE Transmission 2015_10_30 Transmission Losses Strategy Rev 2.0 October 2015 Summary This paper presents SHE Transmission s views and approach on the impact of transmission losses on the transmission

More information

June 2015. Position Paper Contribution to the debate on electricity market design and capacity markets

June 2015. Position Paper Contribution to the debate on electricity market design and capacity markets June 2015 Position Paper Contribution to the debate on electricity market design and capacity markets Eurogas is the association representing the European gas wholesale, retail and distribution sectors.

More information

1 PURPOSE AND SUMMARY 1.1 This report seeks approval to consult on the draft 2015/16 2019/20 Revenue Financial Plan.

1 PURPOSE AND SUMMARY 1.1 This report seeks approval to consult on the draft 2015/16 2019/20 Revenue Financial Plan. ITEM NO. 11(a) 2015/1 201/20 REVENUE FINANCIAL PLAN Report by the Chief Financial Officer SCOTTISH BORDERS COUNCIL 18 December 2014 1 PURPOSE AND SUMMARY 1.1 This report seeks approval to consult on the

More information

Growing the Green Economy

Growing the Green Economy Growing the Green Economy Labour Green Economy Paper.indd 1 05/02/2016 17:44 Our Plan Establish a green infrastructure fund worth 1bn. We recognise the need to fund immediate action on climate change.

More information

Attachment 20.27 SA Power Networks: Network Program Deliverability Strategy

Attachment 20.27 SA Power Networks: Network Program Deliverability Strategy Attachment 20.27 SA Power Networks: Network Program Deliverability Strategy Network Program Deliverability Strategy 2015-20 Regulatory Control Period SA Power Networks www.sapowernetworks.com.au Internal

More information

Investing in renewable technologies CfD contract terms and strike prices

Investing in renewable technologies CfD contract terms and strike prices Investing in renewable technologies CfD contract terms and strike prices December 2013 Crown copyright 2013 You may re-use this information (not including logos) free of charge in any format or medium,

More information

RIIO-T1 business plan submission London Tuesday 6 September 2011

RIIO-T1 business plan submission London Tuesday 6 September 2011 RIIO-T1 business plan submission London Tuesday 6 September 2011 Cautionary statement This presentation contains certain statements that are neither reported financial results nor other historical information.

More information

AGENDA ITEM 5 AYRSHIRE SHARED SERVICE JOINT COMMITTEE 1 MAY 2015 AYRSHIRE ROADS ALLIANCE CUSTOMER SERVICE STRATEGY

AGENDA ITEM 5 AYRSHIRE SHARED SERVICE JOINT COMMITTEE 1 MAY 2015 AYRSHIRE ROADS ALLIANCE CUSTOMER SERVICE STRATEGY AYRSHIRE SHARED SERVICE JOINT COMMITTEE 1 MAY 2015 AYRSHIRE ROADS ALLIANCE CUSTOMER SERVICE STRATEGY Report by the Head of Roads Ayrshire Roads Alliance PURPOSE OF REPORT 1. The purpose of this report

More information

CHANGE MANAGEMENT PLAN

CHANGE MANAGEMENT PLAN Appendix 10 Blaby District Council Housing Stock Transfer CHANGE MANAGEMENT PLAN 1 Change Management Plan Introduction As part of the decision making process to pursue transfer, the Blaby District Council

More information

The Asset Management Landscape

The Asset Management Landscape The Asset Management Landscape ISBN 978-0-9871799-1-3 Issued November 2011 www.gfmam.org The Asset Management Landscape www.gfmam.org ISBN 978-0-9871799-1-3 Published November 2011 This version replaces

More information

Foratom event 29 April 2015

Foratom event 29 April 2015 Foratom event 29 April 2015 New nuclear in the UK and Electricity Market Reform Colin Parker Head of European Liaison - EDF Energy 1 April 2015 EDF Energy plc. All rights reserved. EDF Energy A UK energy

More information

HIGHWAY INFRASTRUCTURE ASSET MANAGEMENT STRATEGY

HIGHWAY INFRASTRUCTURE ASSET MANAGEMENT STRATEGY HIGHWAY INFRASTRUCTURE ASSET MANAGEMENT STRATEGY 16 November 2015 Highway Infrastructure Asset Management Strategy Contents Introduction 1.0 The Need for Asset Management 1.1. Background 1.2. Aims and

More information

Electricity Market Reform: Proposals for Implementation

Electricity Market Reform: Proposals for Implementation EMR Programme Team Department of Energy & Climate Change 4 th Floor Area D 3 Whitehall Place London SW1A 2AW 23 rd December 2013 Dear Sirs, Electricity Market Reform: Proposals for Implementation I am

More information

Government response to the CFD Counterparty and Electricity Settlements Company operational costs 2014/15 consultation

Government response to the CFD Counterparty and Electricity Settlements Company operational costs 2014/15 consultation Government response to the CFD Counterparty and Electricity Settlements Company operational costs 2014/15 consultation Consultation on the operational cost levies June 2014 Crown copyright 2014 URN 14D/182

More information

Electricity Market Reform:

Electricity Market Reform: Electricity Market Reform: Consultation on Low Carbon Contracts Company s and Electricity Settlements Company s operational costs 2015/16 Government Response January 2015 Crown copyright 2015 URN 15D/001

More information

EXPLANATORY MEMORANDUM TO THE CONTRACTS FOR DIFFERENCE (ELECTRICITY SUPPLIER OBLIGATIONS) REGULATIONS 2014. 2014 No. [XXXX]

EXPLANATORY MEMORANDUM TO THE CONTRACTS FOR DIFFERENCE (ELECTRICITY SUPPLIER OBLIGATIONS) REGULATIONS 2014. 2014 No. [XXXX] EXPLANATORY MEMORANDUM TO THE CONTRACTS FOR DIFFERENCE (ELECTRICITY SUPPLIER OBLIGATIONS) REGULATIONS 2014 2014 No. [XXXX] 1. This explanatory memorandum has been prepared by the Department for Energy

More information

CCS Roadmap. The regulatory framework

CCS Roadmap. The regulatory framework The regulatory framework April 2012 The regulatory framework We are: Ensuring that the CCS Commercialisation Programme provides practical experience with the regulatory framework and that the framework

More information

Appendix 10: Improving the customer experience

Appendix 10: Improving the customer experience Appendix 10: Improving the customer experience Scottish Water is committed to delivering leading customer service to all of our customers. This means we deliver the following activities: We will ensure

More information

LHT S ASSET MANAGEMENT STRATEGY 2015-20. It s My Home

LHT S ASSET MANAGEMENT STRATEGY 2015-20. It s My Home LHT S ASSET MANAGEMENT STRATEGY 2015-20 It s My Home 0 ASSET MANAGEMENT STRATEGY 2015-20 It s My Home Contents Page No 1. WHAT DOES OUR ASSET MANAGEMENT STRATEGY AIM TO DO? 2 2. WHY IS ASSET MANAGEMENT

More information

ANNEX B FEED-IN TARIFF WITH CONTRACTS FOR DIFFERENCE: DRAFT OPERATIONAL FRAMEWORK

ANNEX B FEED-IN TARIFF WITH CONTRACTS FOR DIFFERENCE: DRAFT OPERATIONAL FRAMEWORK ANNEX B FEED-IN TARIFF WITH CONTRACTS FOR DIFFERENCE: DRAFT OPERATIONAL FRAMEWORK 1 CONTENTS Introduction...3 Section A Price Setting...8 Section B CfD Allocation... 18 Section C CfD Terms Pre Commissioning...

More information

4. Comparison with DECC (2014) Estimated impacts of energy and climate change policies on energy prices and bills

4. Comparison with DECC (2014) Estimated impacts of energy and climate change policies on energy prices and bills Energy prices and bills - supplementary tables Contents: 1. Energy prices and bills 2. Assumptions 3. Scenarios to 2030 4. Comparison with DECC (2014) Estimated impacts of energy and climate change policies

More information

Future Trading Arrangements 3 rd Forum. Giuseppina Squicciarini 18/11/13

Future Trading Arrangements 3 rd Forum. Giuseppina Squicciarini 18/11/13 Future Trading Arrangements 3 rd Forum Giuseppina Squicciarini 18/11/13 Agenda 1. The FTA process so far 2. Outline of potential workstreams 3. Criteria for prioritisation 4. Scope and prioritisation of

More information

Relationship Manager (Banking) Assessment Plan

Relationship Manager (Banking) Assessment Plan 1. Introduction and Overview Relationship Manager (Banking) Assessment Plan The Relationship Manager (Banking) is an apprenticeship that takes 3-4 years to complete and is at a Level 6. It forms a key

More information

Delivering for our customers Our 2015 to 2020 business plan

Delivering for our customers Our 2015 to 2020 business plan Delivering for our customers Our 2015 to 2020 business plan 2nd December 2013 South East Water Delivering for our customers Our 2015 to 2020 business plan Priorities Service Outcomes Performance Incentives

More information

Our financing of the energy sector

Our financing of the energy sector RBS Sustainability Briefing Our financing of the energy sector rbs.com/sustainable RBS Sustainability Briefing About this document RBS is a UK-based banking and financial services company, headquartered

More information

Wind and solar reducing consumer bills An investigation into the Merit Order Effect

Wind and solar reducing consumer bills An investigation into the Merit Order Effect Switch for Good Wind and solar reducing consumer bills An investigation into the Merit Order Effect Executive summary Concerns over the cost of renewable subsidy schemes have led to significant policy

More information

TEC Capital Asset Management Standard January 2011

TEC Capital Asset Management Standard January 2011 TEC Capital Asset Management Standard January 2011 TEC Capital Asset Management Standard Tertiary Education Commission January 2011 0 Table of contents Introduction 2 Capital Asset Management 3 Defining

More information

Procurement and Contract Management Strategy 2013-2017

Procurement and Contract Management Strategy 2013-2017 Procurement and Contract Management Strategy 2013-2017 Title Owner Version 1 Distribution Procurement and Contract Management Strategy 2013 2017 Procurement and Performance Manager Corporate Issue date

More information

UK renewable energy an update

UK renewable energy an update UK renewable energy an update 30 October 2014 Robert Hull, Managing Director Renewable energy key challenges 1 2 3 Costs to Climate change: Risks to security consumers: decarbonising of supply: short affordability

More information

Environment and energy briefing from Burges Salmon published in the March 2014 issue of The In-House Lawyer:

Environment and energy briefing from Burges Salmon published in the March 2014 issue of The In-House Lawyer: Environment and energy briefing from Burges Salmon published in the March 2014 issue of The In-House Lawyer: Electricity market reform: an update on contracts for difference Electricity market reform:

More information

Dear Colleague, Summary

Dear Colleague, Summary System Operators, Transmission and Transportation System Owners, Generators, Shippers, Suppliers, Customers, Investors and other interested parties Date: 20 December 2013 Dear Colleague, Consultation on

More information

2017 19 TasNetworks Regulatory Proposal Expenditure Forecasting Methodology

2017 19 TasNetworks Regulatory Proposal Expenditure Forecasting Methodology 2017 19 TasNetworks Regulatory Proposal Expenditure Forecasting Methodology Version Number 1 26 June 2015 Tasmanian Networks Pty Ltd (ACN 167 357 299) Table of contents 1 Introduction... 1 2 Meeting our

More information

Introducing Gazprom Energy Stable, secure, reliable energy from one of the world s biggest names. With deals tailored around your needs, not ours.

Introducing Gazprom Energy Stable, secure, reliable energy from one of the world s biggest names. With deals tailored around your needs, not ours. Introducing Gazprom Energy Stable, secure, reliable energy from one of the world s biggest names. With deals tailored around your needs, not ours. About us Gazprom Energy customers receive a long lasting

More information

Renewable Energy for Kent

Renewable Energy for Kent Design + Planning Building Engineering Renewable Energy for Kent Part I: Overview and Action Plan April 2012 Updated Version 1 Committing a Path The development of low carbon and renewable energy sources

More information

Electricity market reform: policy overview

Electricity market reform: policy overview Electricity market reform: policy overview May 2012 Contents Introduction... 3 Electricity Market Reform... 6 The Move to EMR... 21 Costs and Benefits of EMR... 24 EMR in the Devolved Administrations...

More information

Security of electricity supply

Security of electricity supply Security of electricity supply Definitions, roles & responsibilities and experiences within the EU Thomas Barth Chairman of Energy Policy & Generation Committee EURELECTRIC Outline Security of Supply a

More information

Report on the EMR Delivery Body s performance of its functions in relation to the Capacity Market

Report on the EMR Delivery Body s performance of its functions in relation to the Capacity Market Report on the EMR Delivery Body s performance of its functions in relation to Report Publication date: 19 June 2015 Team: EMR Team Contact: Sujitra Krishnanandan; Matthew Pearson Tel: 020 3263 9832; 020

More information

Data Communications Company (DCC) price control guidance: process and procedures

Data Communications Company (DCC) price control guidance: process and procedures Guidance document Contact: Tricia Quinn, Senior Economist Publication date: 27 July 2015 Team: Smarter Metering Email: tricia.quinn@ofgem.gov.uk Overview: The Data and Communications Company (DCC) is required

More information

EMR: Consultation on industry code and licence modifications

EMR: Consultation on industry code and licence modifications EMR: Consultation on industry code and licence modifications January 2014 Department of Energy and Climate Change 3 Whitehall Place London SW1A 2AW Telephone: 0300 068 4000 Website: https://www.gov.uk/government/organisations/department-of-energy-climate-change

More information

QUALITY OF SERVICE DISCRETIONARY REWARD SCHEME GAS DISTRIBUTION NETWORK OPERATORS ENTRY FORM

QUALITY OF SERVICE DISCRETIONARY REWARD SCHEME GAS DISTRIBUTION NETWORK OPERATORS ENTRY FORM QUALITY OF SERVICE DISCRETIONARY REWARD SCHEME GAS DISTRIBUTION NETWORK OPERATORS ENTRY FORM Please note that the deadline for receipt of applications is 5pm, 15 May 2009. GDN DETAILS: (please complete)

More information

ESB Input to consultation by the Northern Ireland Authority for Utility Regulation (NIAUR) on the NI Energy Efficiency Levy

ESB Input to consultation by the Northern Ireland Authority for Utility Regulation (NIAUR) on the NI Energy Efficiency Levy Alison Farr Social and Environmental Branch Utility Regulator Queens House Queen Street Belfast BT1 6ER 24 November 2008 ESB Input to consultation by the Northern Ireland Authority for Utility Regulation

More information

Summary of the Impact assessment for a 2030 climate and energy policy framework

Summary of the Impact assessment for a 2030 climate and energy policy framework Summary of the Impact assessment for a 2030 climate and energy policy framework Contents Overview a. Drivers of electricity prices b. Jobs and growth c. Trade d. Energy dependence A. Impact assessment

More information

Norwegian position on the proposed EU framework for climate and energy policies towards 2030

Norwegian position on the proposed EU framework for climate and energy policies towards 2030 Norwegian position on the proposed EU framework for climate and energy policies towards 2030 The EU plays an important role as a global leader in climate policy and has a fundamental interest in strengthening

More information

PROJECT MANAGEMENT FRAMEWORK

PROJECT MANAGEMENT FRAMEWORK PROJECT MANAGEMENT FRAMEWORK DOCUMENT INFORMATION DOCUMENT TYPE: DOCUMENT STATUS: POLICY OWNER POSITION: INTERNAL COMMITTEE ENDORSEMENT: APPROVED BY: Strategic document Approved Executive Assistant to

More information

UK Future Energy Scenarios. UK gas and electricity transmission

UK Future Energy Scenarios. UK gas and electricity transmission UK Future Energy Scenarios UK gas and electricity transmission JULY 2014 03 UK Future Energy Scenarios July 2014 Welcome to our 2014 edition of the UK Future Energy Scenarios (UK FES) document. This annual

More information

Customers and Other Interested Parties Direct Dial: 020 7901 7000 Email: gb.markets@ofgem.gov.uk

Customers and Other Interested Parties Direct Dial: 020 7901 7000 Email: gb.markets@ofgem.gov.uk System Operators, Transmission System Owners, Promoting choice and value for Generators, Suppliers, Traders, all gas and electricity customers Customers and Other Interested Parties Direct Dial: 020 7901

More information

IT Outsourcing. Third Time Lucky? Winter 2014/15 INSIGHTS

IT Outsourcing. Third Time Lucky? Winter 2014/15 INSIGHTS INSIGHTS IT Outsourcing Third Time Lucky? Coeus Consulting looks at whether the emerging third generation sourcing models are the end of the journey or is a fourth generation on the way? Winter 2014/15

More information

Helping our clients win in the changing world of work:

Helping our clients win in the changing world of work: Helping our clients win in the changing world of work: Recruitment Process: Why Outsource? A Manpower Insights Paper The future of RPO looks strong despite or perhaps aided by the current global recession.

More information

REPORT BY THE COMPTROLLER AND AUDITOR GENERAL HC 535 SESSION 2013-14 5 JULY 2013. Department for Culture, Media & Sport. The rural broadband programme

REPORT BY THE COMPTROLLER AND AUDITOR GENERAL HC 535 SESSION 2013-14 5 JULY 2013. Department for Culture, Media & Sport. The rural broadband programme REPORT BY THE COMPTROLLER AND AUDITOR GENERAL HC 535 SESSION 2013-14 5 JULY 2013 Department for Culture, Media & Sport The rural broadband programme 4 Key facts The rural broadband programme Key facts

More information

People & Organisational Development Strategy

People & Organisational Development Strategy 2013-2018 People & Organisational Development Strategy Delivering excellent research Delivering an excellent student experience Enhancing global reach and reputation 1. Introduction Glasgow 2020: A global

More information

Customer Management Strategy (2014-2017)

Customer Management Strategy (2014-2017) Customer Management Strategy (2014-2017) Version 1.1 Page 1 Foreword As technology improves, the demand for Council services to be available online and accessible 24/7 will increase as our customers choose

More information

People Strategy 2013/17

People Strategy 2013/17 D a t a L a b e l : P U B L I C West Lothian Council People Strategy 2013/17 Contents 1 Overview 2 2 Council Priorities 8 3 Strategy Outcomes 10 1 Engaging and motivating our employees 13 2 Recognised

More information

National Grid EMR Electricity Capacity Report

National Grid EMR Electricity Capacity Report National Grid National Grid EMR Electricity Capacity Report 1 June 2015 Report with results from work undertaken by National Grid for DECC in order to support the development of Capacity Market volume

More information

THE CHANGING COST OF UK ENERGY THE CHANGING COST

THE CHANGING COST OF UK ENERGY THE CHANGING COST THE CHANGING COST OF UK ENERGY THE CHANGING COST OF UK ENERGY 0b THE CHANGING COST OF UK ENERGY 0c RWE NPOWER ENERGY EXPLAINED CONTENTS 01 Introduction 02 CEO foreword 04 Energy bill for an average UK

More information

Learning & Development Framework for the Civil Service

Learning & Development Framework for the Civil Service Learning & Development Framework for the Civil Service 2011-2014 Table of Contents 1. Introduction & Background... 1 2. Key Objectives and Actions arising... 3 3. Framework Objectives... 4 3.1 Prioritise

More information

How are companies currently changing their facilities management delivery model...?

How are companies currently changing their facilities management delivery model...? Interserve and Sheffield Hallam University market research 2012 Page 2 www.commercial.interserve.com How are companies currently changing their facilities management delivery model...? we have a strategy

More information

Review of the Approach to Capital Investments

Review of the Approach to Capital Investments Review of the Approach to Capital Investments September 2011 This paper examines the RIC s current approach to assessing capital expenditure (Capex), reviews T&TEC s actual Capex and compares this with

More information

HOW EMR MAKES THE CASE FOR ENERGY EFFICIENCY MORE ATTRACTIVE. Smart businesses are seeing EMR as an opportunity, not just an overhead.

HOW EMR MAKES THE CASE FOR ENERGY EFFICIENCY MORE ATTRACTIVE. Smart businesses are seeing EMR as an opportunity, not just an overhead. HOW EMR MAKES THE CASE FOR ENERGY EFFICIENCY MORE ATTRACTIVE. Smart businesses are seeing EMR as an opportunity, not just an overhead. WELCOME Many businesses are currently focused on the cost that Electricity

More information

Our financing of the energy sector in 2013

Our financing of the energy sector in 2013 Our financing of the energy sector in 213 rbs.com/sustainable About this document This report is the fourth Our financing of the energy sector briefing that we have produced since 21. The aim remains the

More information

Decarbonising electricity generation. Policy paper

Decarbonising electricity generation. Policy paper Decarbonising electricity generation Samuela Bassi, Chris Duffy and James Rydge Policy paper April 2013 Centre for Climate Change Economics and Policy Grantham Research Institute on Climate Change and

More information

Procurement Strategy 2013-2017 Delivering Social Value for our Community

Procurement Strategy 2013-2017 Delivering Social Value for our Community Procurement Strategy 2013-2017 Delivering Social Value for our Community Making Bath & North East Somerset an even better place to live, work and visit 1 Picture courtesy of Bath & News Media Group Our

More information

ELECTRICITY MARKET REFORM SHAPING THE FUTURE GB POWER MARKET

ELECTRICITY MARKET REFORM SHAPING THE FUTURE GB POWER MARKET ELECTRICITY MARKET REFORM SHAPING THE FUTURE GB POWER MARKET A Pöyry briefing note Electricity Market Reform (EMR) proposals, intended to deliver the transition to a decarbonised electricity sector, have

More information

LABORATORY OUTSOURCING

LABORATORY OUTSOURCING June 2009 LABORATORY OUTSOURCING Intertek s EVP of Analytical Services, Dr. Andrew Swift, discusses laboratory outsourcing and explains how dedicated analytical service providers are stepping up to support

More information

PR18 working paper Working paper 3: Initial views on the regulatory framework for Network Rail s system operator function

PR18 working paper Working paper 3: Initial views on the regulatory framework for Network Rail s system operator function PR18 working paper Working paper 3: Initial views on the regulatory framework for Network Rail s system operator function Date of publication: 7 June 2016 Overview This paper is part of a series of working

More information

Business Policy of CEZ Group and ČEZ, a. s.

Business Policy of CEZ Group and ČEZ, a. s. Business Policy of CEZ Group and ČEZ, a. s. Contents: Introduction 1. CEZ Group mission and vision 2. Scope of business of CEZ Group 3. Business concept Guiding principles Trade Generation Electricity

More information

Consultation on changes to Feed-in Tariff accreditation

Consultation on changes to Feed-in Tariff accreditation Consultation on changes to Feed-in Tariff accreditation Removing preliminary accreditation from the Feedin Tariff 21 July 2015 Department of Energy and Climate Change 3 Whitehall Place London SW1A 2AW

More information

Change Management Practitioner Competencies

Change Management Practitioner Competencies 1 change-management-institute.com Change Management Institute 2008 Reviewed 2010, 2012 Change Management Practitioner Competencies The Change Management Practitioner competency model sets an independent

More information

ANNEX D ELECTRICITY MARKET REFORM: UPDATE ON THE EMISSIONS PERFORMANCE STANDARD

ANNEX D ELECTRICITY MARKET REFORM: UPDATE ON THE EMISSIONS PERFORMANCE STANDARD ANNEX D ELECTRICITY MARKET REFORM: UPDATE ON THE EMISSIONS PERFORMANCE STANDARD Contents Excutive Summary... 3 Background... 3 Level and Compliance... 4 Administration - Monitoring and Enforcment arrangements...

More information

Tasmanian Transmission Revenue Proposal

Tasmanian Transmission Revenue Proposal Tasmanian Transmission Revenue Proposal An overview for Tasmanian electricity consumers Regulatory control period 1 July 2014 30 June 2019 Tasmanian Networks Pty Ltd About TasNetworks We are Tasmania s

More information

Group Principal Risks Report. June 2015

Group Principal Risks Report. June 2015 Group Principal Risks Report June 2015 5. Commodity Prices 7. Energy Affordability 8. Funding Shortfall 11. Human and Relationship Capital Management 12. Industry and Company Transformation 15. Infrastructure

More information

Monitoring Highways England The monitoring framework

Monitoring Highways England The monitoring framework Monitoring Highways England The monitoring framework October 2015 Contents Executive summary 4 Roads reform 4 ORR s role in monitoring Highways England 5 What we will do next 10 1. Overview of this document

More information

Annex B: Strike price methodology July 2013

Annex B: Strike price methodology July 2013 July 2013 URN 13D/189 Contents Introduction... 3 Overview of methodology for deriving a CfD strike price... 3 Strike Prices during the cross-over period with the RO (2014/15 2016/17)... 4 Comparison of

More information

Customer requirements. Asset management planning Inspection and assessment Route asset planning Annual work plans Contracting strategy

Customer requirements. Asset management planning Inspection and assessment Route asset planning Annual work plans Contracting strategy Section 8 Output monitoring Inputs Customer requirements Safety standards Outputs and funding SRA and Government Policy Network stewardship strategy Asset and operational policies Maintenance & renewal

More information

Impact Assessment (IA)

Impact Assessment (IA) Title: Renewables Obligation Transition IA No: DECC0086 Lead department or agency: Department of Energy and Climate Change Other departments or agencies: Summary: Intervention and Options Total Net Present

More information

SEPA's New Legal Rules and Regulations in South East Scotland

SEPA's New Legal Rules and Regulations in South East Scotland CONSULTATION ON SEPA S PROPOSED ENVIRONMENTAL REGULATION (SCOTLAND) CHARGING SCHEME 2016 Date: June 2015 Published by: Scottish Environment Protection Agency Strathallan House Castle Business Park Stirling

More information

The role of coal in the UK generation industry. Philip Garner - Director General of the Confederation of UK Coal Producers

The role of coal in the UK generation industry. Philip Garner - Director General of the Confederation of UK Coal Producers The role of coal in the UK generation industry Philip Garner - Director General of the Confederation of UK Coal Producers Recent History In 1983 there were 170 underground mines owned by the National Coal

More information

The economic competitiveness of nuclear energy

The economic competitiveness of nuclear energy How competitive is nuclear energy? by J.H. Keppler* The economic competitiveness of nuclear energy will be crucial for determining its future share in world electricity production. In addition, the widespread

More information

Disclaimer: All costs contained within this report are indicative and based on latest market information. 16 th March 2015

Disclaimer: All costs contained within this report are indicative and based on latest market information. 16 th March 2015 Disclaimer: All costs contained within this report are indicative and based on latest market information 16 th March 2015 FD SUMMARY The make up of the electricity bill is changing, with non-commodity

More information

IMPACT OF GB S ELECTRICITY MARKET REFORM ON INTERCONNECTIONS, CONSEQUENCES ON NORDIC MARKET Michel Martin, 3 April 2014

IMPACT OF GB S ELECTRICITY MARKET REFORM ON INTERCONNECTIONS, CONSEQUENCES ON NORDIC MARKET Michel Martin, 3 April 2014 IMPACT OF GB S ELECTRICITY MARKET REFORM ON INTERCONNECTIONS, CONSEQUENCES ON NORDIC MARKET Michel Martin, 3 April 2014 PÖYRY MANAGEMENT CONSULTING ENERGY Pöyry offices (c) grafikdienst.com Pöyry Management

More information

Guidelines for the Application of Asset Management in Railway Infrastructure Organisations

Guidelines for the Application of Asset Management in Railway Infrastructure Organisations Guidelines for the Application of Asset Management in Railway Infrastructure Organisations INTERNATIONAL UNION OF RAILWAYS (UIC) 16 rue Jean Rey - F-75015 PARIS Tel: +33 (0)1 44 49 20 20 Fax: +33 (0)1

More information

ELECTRICITY MARKET REFORM (EMR) & THE ENERGY BILL INENCO OVERVIEW

ELECTRICITY MARKET REFORM (EMR) & THE ENERGY BILL INENCO OVERVIEW ELECTRICITY MARKET REFORM (EMR) & THE ENERGY BILL INENCO OVERVIEW February 2014 ELECTRICITY MARKET REFORM (EMR) & THE ENERGY BILL The Energy Bill is the government s flagship energy policy. There have

More information