Pipeline Construction: Quality Issues and Solutions Action Plans. Training Guidance for Welding & Coating Workers & Inspectors



Similar documents
9. QUALITY CONTROL/QUALITY ASSURANCE

Pipeline Construction: Quality Issues and Solutions Action Plans

Specification for Pipe Coating Repairs Offshore

A. The CONTRACTOR shall provide pipe coating, complete and in place, in accordance with the Contract Documents.

NCCER Progress Blvd., Alachua, FL Tel: (888) Task Number Item Date(s) Recorded By

POLYURETHANE LINING AND COATING ON PIPE RAW WATER

C.A.T.S. Capabilities

INSPECTION AND CONSTRUCTION MANAGEMENT CAPABILITIES

CQR-1 CONTRACTOR QUALITY REQUIREMENTS for CONSTRUCTION SERVICES

Specification for Fabrication of Pipeline End Manifold

Reproduced with the permission of the American Welding Society (AWS), Miami, Florida - 09/15/ Stud Welding

NW Natural & Pipeline Safety

STANDARD SPECIFICATION SECTION STEEL PIPE, FUSION-BONDED EPOXY LINED AND COATED

SECTION WATER STORAGE TANK PAINTING

PFMEA Process Failure Mode and Effects Analysis. James Davis, General Dynamics

BODY OF KNOWLEDGE API-570 AUTHORIZED PIPING INSPECTOR CERTIFICATION EXAMINATION

SPECIAL INSPECTION AND TESTING AGREEMENT INTERNATIONAL BUILDING CODE

STATEMENT OF WORK (SOW) On-Call Certified Welding Inspections and Nondestructive Testing

COATING & WRAPPING OF UNDERGROUND PIPING

Specification for Fusion Bonded Epoxy for External Pipeline Coating

Section 8.1 Volume I QUALITY ASSURANCE PROGRAM OF PRECAST PRESTRESSED CONCRETE PRODUCTS

GENERAL WELDING & FABRICATING, INC. 991 Maple Road Elma, New York 14059

SECTION 560 COATING NEW STRUCTURAL STEEL

Welding of Boilers, Pressure Vessels and Pressure Piping

Butt Fusion Welding of HDPE Pipes Work Procedure

ENERGY STAR Program Requirements Product Specification for Data Center Storage. Draft 2 Test Method March 2013

Field Welding Inspection Guide

1.2 For piping systems that operate at hoop stress of 20% or more of the Specified Minimum Yield Strength the following shall apply.

NAPCA BULLETIN APPLICATION PROCEDURES FOR CONCRETE WEIGHT COATING APPLIED BY THE COMPRESSION METHOD TO STEEL PIPE

STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENT 1078

PRODUCTS&SERVICES. Depliant PWT ok indd 3 23/04/

TABLE OF CONTENTS 2 Heavy-Wall Seamless & Welded Carbon Steel Pipe. 4 Alloy Pipe & Tube. 6 Chrome-Moly Pipe. 7 Low-Temp Pipe

Oil and Gas Pipeline Design, Maintenance and Repair

Pressure Testing (Hydrostatic / Pneumatic) Safety Guidelines

Fire Alarm System Submissions

FIELD ACCEPTANCE OF FIELD WELDING GUIDE

Qualified Contractor Management System

CCTV INSPECTION OF SEWER LINES. A. Section Sanitary Gravity Sewer Lines. B. Section Sanitary Gravity Sewer Line Testing

Autobody/Collision and Repair Technology/Technician CIP Task Grid

NDT Procedure for Liquid Penetrant Inspection

Stick MIG TIG Sub Arc Spot Other S M A G M A W G T A W S A W Resistance. A S M E MIL-STD-248 Navy Apprvd Cust Apprvd Revision

Trenching and Excavation Safety

BODY OF KNOWLEDGE API-653 ABOVEGROUND STORAGE TANK INSPECTOR CERTIFICATION EXAMINATION November 2015, March 2016 and July 2016 (Replaces October 2013)

Heat Exchanger Thin Film Foul Release Applications Corrosion Resistant Protective Coatings Grit Blast Surface Prep of Tubular Equipment

SECTION CEMENT-MORTAR LINED AND COATED STEEL PIPE

OPERATING INSTRUCTIONS

Catch Basin Rehabilitation Road Commission for Oakland County, Michigan

XYZ Contract Company Industrial Hygiene Program

Using StrongPIPE Hybrid FRP for PCCP Rehab in Miami-Dade System

49 CFR 192 Transportation of Natural and Other Gas By Pipeline: Minimum Federal Safety Standards

Wecryl Waterproofing System under surfacing supplied by others

NDT Procedure for Liquid Penetrant Inspection TRINITY NDT. An ISO 9001:2008 Certified Company

EMERGENCY EGRESS LIGHTING POWER SUPPLY PART NO COMPONENT MAINTENANCE MANUAL WITH ILLUSTRATED PARTS LIST

FIELD COATING OF STEEL PIPE AND FITTINGS INSTALLED UNDERGROUND AND IN SUBSURFACE STRUCTURES

Guidelines for Securing by Welding of Chain Cable Studs in Service Guidance for Anchoring Equipment in Service

COATINGS MANUAL HRSD 9.0 THIRD PARTY INSPECTION GUIDELINES. 9.1 The Value of Third Party Inspection. 9.2 When to Use Third Party Inspection

CITY OF BEVERLY RULES AND REGULATIONS - SEWER SYSTEM TESTING. General

Owner-User Pressure Equipment Integrity Management Requirements

Application of Welding Standards in Hong Kong. S. K. Babu Laboratory Manager - Foundation Techniques Ltd

SECTION PRECAST CONCRETE STRUCTURES

Welding Fire Protection Piping 101

Guide Specification STAYFLEX CORROSION CONTROL AND THERMAL INSULATION SYSTEM

ACCREDITATION CRITERIA FOR INSPECTION PROGRAMS FOR MANUFACTURERS OF METAL BUILDING SYSTEMS AC472

PIPING SYSTEM - ABRASIVE SLURRIES Engineering Standard Specification. 96 B. Riutta

Structures Construction Pre-Work Checklist PRE-WORK SHEET FOR PROJECT MANAGERS

Technical Services. Product MM INCH Installation direction Seams treatment GTI CONNECT (interlocking)

ACCREDITATION CRITERIA FOR FABRICATOR INSPECTION PROGRAMS FOR STRUCTURAL STEEL. AC172 February 2015 (Effective April 1, 2015)

External Wrapping of Steel Riser Pipe. Case Study HJ3 CS200902

Specification of the cooling- water-piping for SESAME Storage Ring and the Radio-Frequency System

PIPELINE FIELD JOINT COATING AND FIELD REPAIR OF LINEPIPE COATING

How to Build a Printed Circuit Board. Advanced Circuits Inc 2004

STEEL fabrication quality SySTEmS guideline

SMALL GAS OPERATOR OPERATION AND MAINTENANCE PLAN

Example ESD Control Program Document Based on ANSI/ESD S

A comprehensive range

a. Are the foundry s employees trained and familiar with portions of the system applicable to their position?

SECTION 36 - CAST-IN-PLACE CONCRETE PIPE (CIPCP) TABLE OF CONTENTS

Duplex Stainless Steel Fabrication. Gary M. Carinci TMR Stainless Consultant for International Molybdenum Association

Compliance Case Study #3 Manual Processes, Performance, Responsibilities, and Training

Summary of Changes in. ASME Section IX, 2000 Addenda

PIPELINE INSPECTION COMPANY LTD. Portable Holiday Detectors. OPERATING INSTRUCTIONS SPY PORTABLE HOLIDAY DETECTORS Models 780, 785, & 790

TANK FABRICATION. Automated Solutions for Your Tank Fabrication Project. Bug-o Systems

Surveillance Report. Bascule span to the Railway bridge Jernbanebroen over Limfjorden

INDIAN STANDARDS FOR NATURAL GAS PIPELINE SYSTEM

725-R-599 PIPE LINING. (Revised ) SECTION 725, BEGIN LINE 1, INSERT AS FOLLOWS: SECTION 725 SLIP LINING OF EXISTING PIPE

SUPPLIER QUALITY SYSTEM AUDIT

WHAT EVERY ENGINEER SHOULD KNOW ABOUT WELDING

Electric Heat Tracing INSTALLATION PROCEDURES

TABLE OF CONTENT

City Of Ottawa High Voltage Substation Inspection, Maintenance Rev July 17 and Testing, ROPEC Page 1

WELDING TECHNOLOGY DEGREES AND CERTIFICATES. Welding Technology Degree. Shielded Metal Arc Plate and Pipe (270 hours) Certificate

TIG WELDING TIPS by Tom Bell

Glass & Hard Plastic Control

BRIDGE FIELD PAINTING, REPAINTING, 412 AND PAINT RESIDUE CONTAINMENT. A. Field Painting, Bridge Repainting and Residue Containment:

PPG SUPPLIER DEVELOPMENT ASSESSMENT

Workers. There are many different jobs in a steel mill. As with most industries, the main jobs fall into a list of categories, such as:

GENERAL RUBBER LINING PRINCIPLES

Transcription:

Final October 26, 2012 Pipeline Construction: Quality Issues and Solutions Action Plans Training Guidance for Welding & Coating Workers & Inspectors

Training Guidance for Welding & Coating Workers & Inspectors Table of Contents Team Members... ii Summary and Introduction...1 Table 1 Welding QA/QC ITP...2 Table 2 Weld Joint / Pipe Coating QA/QC ITP...4 Table 3 Tie In Coating Transition Area QA/QC ITP...6 Welding QA/QC ITP Pocket Guide...8 Weld Joint / Pipe Coating QA/QC ITP Pocket Guide...9 Tie In Coating Transition Area QA/QC ITP Pocket Guide... 10 Table 4 Issues Identified During PHMSA Inspection of 35 Construction Projects... 11 The INGAA Foundation Pipeline Training Guidance for Welding & Coating Workers & Inspectors i

Team Members Paul R Amato, Iroquois Pipeline, Group Lead Tarry Hutton, NiSource David McMurray, Wilcrest Cliff McPherson, Panhandle Craig Meier, Sunland Construction Kirk Peterman, Panhandle The INGAA Foundation Pipeline Training Guidance for Welding & Coating Workers & Inspectors ii

Summary and Introduction Construction specifications, establish specific requirements for completing field construction activities in a manner compliant with codes and the s special requirements. However, these specifications and procedures are lengthy documents often written in contract language. As a result, contractors and operators often develop their own interpretations and documentation to train skilled construction workers. As an outcome of the INGAA Foundation s October 15, 2009 Pipeline Construction, Fabrication, Testing Workshop these guidelines were developed. The objective of this guideline is to develop simple but effective training guidance for construction management and workers to ensure consistent and compliant construction practices. These guidelines identify some minimum general key elements that should be considered during construction inspections. Project specific requirements should still be followed. Tables 1, 2 and 3 provide inspection guidance templates that align with these elements to assist the inspectors as follows: Table 1 is an inspection and test plan (ITP) for QA/QC of welders and weld inspection. Table 2 is an ITP guidance document on key QA/QC elements for weld joint and pipe coating workers and inspectors; Table 3 is an ITP guidance document for QA/QC for tie-in coating transition areas; and Pocket guides for tables 1, 2 and 3 have been developed for printing and easy use in the field by welding and coating workers and inspectors. These are attached. Table 4 is a listing of the construction, coating and welding inspection issues compiled by PHMSA during its inspection of 35 projects. The issue areas in this table relate to PHMSA s determinations and are an important advisory to welding and coating workers and inspectors. These Key Elements / Templates may be used as a check list or reminder to verify an understanding of the key issues and associated documentation, where needed, is complete for those issues. For example, Qualification ( OQ ) requirements are mentioned. Although this white paper does not specify the OQ documentation requirements, the intent is to remind inspectors they should review the necessary OQ documentation for each project to ensure they are adequate (e.g. there already is a Field Verification Report). Therefore this document is not intended to place additional documentation burdens but remind the inspector to check OQ paperwork. It also should be noted these key elements are not to replace the complete project specific documentation. They are intended to be focus points and / or simple guides to be used. The Acceptance Criteria are guidelines to be used in the absence of Company specific requirements. They are not an effort to supersede or establish existing criteria. The Project and applicable codes & standards are to be used for actual criteria for the specific projects. The following pages provide an example of Key Elements / Templates for Welding and Field Applied Coating. The INGAA Foundation Pipeline Training Guidance for Welding & Coating Workers & Inspectors 1

Table 1 Welding QA/QC ITP (Page 1 Rev. 0) Item No. Activity Project Welding 1 Safety JSA Safety Manual Daily 1 Ensure ALL employees are wearing proper PPE for the relevant task at hand 2 Verify Weld 3 Verify Qualified Welders Project Welding Manual Specification 4 Pipe Inspection Specification Frequency Acceptance Criteria Project Responsibilities Action/Record As needed Applicable weld procedure Correct WPS and PQR for weld Contractor (QC) (QA) X X Tailgate safety 1 Appropriate P.P.E Complete & sign JSA X X Determine proper weld procedure & notify welders Verify WPS applies to essential variables Welder Foreman Report X X Verify welders qualified to procedure per Welder Qualification Log Welder Foreman Report Field Verification Report or similar (as needed) Prior to welding Welder Qualification Change of Log Welder and/or Verify Qualification Requirements (as applicable) Each joint Pipe free of debris X -- Swab each joint No record 5 Bevel Prep Weld s Each joint Clean bevel per Weld 6 Pre heat Weld s Each joint Minimum as specified and verified by temp stick or equivalent. 7 Line up Weld s Each joint Root opening 1/16 Seams 2-4 offset X X Buff bevel No record X X Pre heat bevel No record Temp stick X X Appropriate use of line up clamp No record High-low 1/16 & Weld 8 Inter-pass Temperature Weld s Each joint Minimum as specified and verified by temp stick or equivalent. X X Temp stick 1 Any employee that does not attend the morning JSA/Safety tailgate, needs to review and sign, prior to working The INGAA Foundation Pipeline Training Guidance for Welding & Coating Workers & Inspectors 2

Table 1 (Continued) (Page 2 Rev. 0) Item No. Activity Project Welding Frequency Acceptance Criteria Project Responsibilities Action/Record Contractor Representative 9 Speed of Travel 2 Weld s As Needed Range is inches/min per WPS/PQR -- X Stopwatch 10 Amperage 2 Weld s As Needed Range is amps per WPS/PQR -- X Multi meter 11 Volt 2 Weld s As Needed Range Volts per WPS -- X Multi meter 12 Repair of Defects- Cracks/Arc Burns Repair As Needed Welding Inspector approval X X Visual and NDE Inspection NDE report NDE Visual. Specific procedure for repair on repair if allowed by 13 Field Transitions 14 Weld Acceptance Specification Weld s & NDE As Needed Per operator specification depending on < or > 20% specified yield strength Each weld API 1104 B31.8 NDE s X X Visual and NDE Inspection NDE report -- X Visual and NDE Inspection NDE report 15 Check consumables and Welding Equipment Specification Daily Proper consumable storage Welding equipment in proper condition X X No record 2 Note: travel, amperage and volts vary for bead, hot pass and filler passes (inform welders to follow WPS) The INGAA Foundation Pipeline Training Guidance for Welding & Coating Workers & Inspectors 3

Table 2 Weld Joint / Pipe Coating QA/QC ITP (Page 1 Rev. 0) Item No. Activity Project Frequency Acceptance Criteria Contractor Action/Record (QC) (QA) 1 Safety JSA Prior to performing ANY duties the coating foreman must ID ALL Hazards 2 Applicator qualifications 3 Inspection & Surface prep, 4 Coating Application Safety Manual Daily 1 Ensure ALL employees are wearing proper PPE for the relevant task at hand Manufacturers Specifications Weld Joint Documentation - 2 per shift (minimum) Per Project Understanding of manufacturing installation techniques Verification of Qualification as applicable Inspection per occurrence Weld Joint Documentation - 2 per shift (minimum) Application per occurrence Test Pipe to see if nonvisible contaminates exist. Clean as per specification. Blasted to a NEAR WHITE finish Surface Profile will be checked and documented As per application specification. Pipe temperature should be 5 degrees above dew point. Pre-heat pipe as per specification X X Tailgate safety 1 Appropriate P.P.E (Including: Blasting Hood/Fresh Air Canister/Air Lines) Complete & sign JSA X X Demonstrates knowledge of manufacturing installation methods / techniques Field Verification report or equivalent X X Inspect & Examine pipe for non-visible contaminates. Blast and check profile Remove all Frayed/Loose coating near cutback Brush Blast existing FBE Daily coating foreman report. X X Document temperatures Do not handle, lower in, or backfill until completely cured Measure dew point temperature, surface preparation, relative humidity, pipe temperature and mill thickness Daily coating foreman report 1 Any employee that does not attend the morning JSA/Safety tailgate, needs to review and sign, prior to working The INGAA Foundation Pipeline Training Guidance for Welding & Coating Workers & Inspectors 4

Table 2 (Continued) (Page 2 Rev. 0) Item No. Activity Project Frequency Acceptance Criteria Contractor Action/Record (QC) (QA) 5 Pipe Coating Inspection Weld Joint / Pipe Coating 6 Coating repair Weld Joint/Pipe Coating Each joint No damage All coated pipe shall be tested to locate holidays. After the holidays are patched, and just before pipe is lowered into the ditch-- reinspect. Check for appropriate coating thickness. Utilize holiday detector with voltage setting (FBE 2,000 volts DC, dual coat & two part epoxy 100 volts DC per mil of coating) shall be verified. The holiday detectors batteries must be checked daily and replaced/recharged if required. Calibrate holiday detector daily As needed Repair with patch stick, epoxy gun or two part epoxy in accordance with specifications. X X Visual Inspect Jeep X X Record as per operator requirements 7 Storage & Handling Specification Daily Maintained and stored in accordance with manufacturing specifications. X -- Ensure proper Storage - Any employee that does not attend the morning JSA/Safety tailgate, needs to review and sign, prior to working The INGAA Foundation Pipeline Training Guidance for Welding & Coating Workers & Inspectors 5

Table 3 Tie In Coating Transition Area QA/QC ITP (Page 1 Rev. 0) Item No. Activity Project Frequency Acceptance Criteria Contractor Action/Record (QC) (QA) 1 Safety JSA Prior to performing ANY duties the coating foreman must ID ALL Hazards Safety Manual Daily 1 Ensure ALL employees are wearing proper PPE for the relevant task at hand X X Tailgate safety 1 Appropriate P.P.E (Including: Blasting Hood/Fresh Air Canister/Air Lines) Complete & sign JSA Excavation safety review 2 Applicator qualifications Manufacturers Specifications Per Project Understanding of manufacturing installation techniques Verification of Qualification as applicable X X Demonstrates knowledge of manufacturing installation methods / techniques Field Verification report or equivalent 3 Inspection & Surface preparation, Transition Area from existing to new coating Documentation - 2 per shift (minimum) Inspection per occurrence Test Pipe to see if non-visible contaminates exist. Clean as per specification. Blasted to a NEAR WHITE finish Surface Profile will be checked and documented X X Inspect & Examine pipe for non-visible contaminates. Blast and check profile Remove all Frayed/Loose coating near cutback Brush Blast existing FBE Daily coating foreman report. 4 Coating Application Transition from existing to new coating Documentation - 2 per shift (minimum) Application per occurrence As per application specification. Pipe temperature should be 5 degrees above dew point. Pre-heat pipe as per specification. Pipe temperature should be 5 degrees above dew point Overcoat per operator specification X X Document temperatures Do not handle, lower in, or backfill until completely cured Measure dew point temperature, surface preparation, relative humidity, pipe temperature and mill thickness Daily coating foreman report 1 Any employee that does not attend the morning JSA/Safety tailgate, needs to review and sign, prior to working The INGAA Foundation Pipeline Training Guidance for Welding & Coating Workers & Inspectors 6

Table 3 (Continued) (Page 2 Rev. 0) 5 Pipe Coating Weld Joint Each weld No damage Inspection All coated pipe shall be tested to locate holidays. After the holidays are patched, and just before pipe is lowered into the ditch-- reinspect. Check for appropriate coating thickness. Utilize holiday detector with voltage setting (FBE 2,000 volts DC, dual coat & two part epoxy 100 volts DC per mil of coating) shall be verified. The holiday detectors batteries must be checked daily and replaced/recharged if required. Calibrate holiday detector daily 6 Coating repair Weld Joint As needed Repair with patch stick, epoxy gun or two part epoxy in accordance with specifications. X X Visual Inspect Jeep X X Record as per operator requirements 7 Storage & Handling Specification Daily Maintained and stored in accordance with manufacturing specifications. X -- Ensure proper Storage 1 Any employee that does not attend the morning JSA/Safety tailgate, needs to review and sign, prior to working The INGAA Foundation Pipeline Training Guidance for Welding & Coating Workers & Inspectors 7

Welding QA/QC ITP Pocket Guide Welding QA/QC ITP Pocket Guide Activity Project Welding Frequency Acceptance Criteria Action / Record Safety JSA Safety Manual Daily Ensure ALL employees are wearing proper PPE for the relevant task at hand Applicable weld procedure Tailgate safety Appropriate PPE Complete & sign JSA Determine proper weld procedure & notify welders Verify Weld Project Welding Manual As needed Verify WPS applies to essential variables Correct WPS and PQR for weld Welder Foreman Report Verify Qualified Welders Complete Section Prior to welding Change of Welder and/or Welder Qualification Log Verify Qualification Requirements (as applicable) Pipe Inspection Each joint Pipe free of debris Bevel Prep Weld s Each joint Clean bevel per Weld Pre heat Weld s Each joint Line up Weld s Each joint Time between Bead/Root & Start of hot pass/2nd Bead Minimum of 250 F Verified by temp stick or equal. Root opening 1/16 Seams 2-4 offset High-low 1/16 & Weld Verify welders qualified to procedure per Welder Qualification Log Welder Foreman Report Field Verification Report or similar (as needed) Swab each joint No record Buff bevel No record Pre heat bevel No record Temp stick Use of line up clamp No record Weld s Each joint Max time is 5 minutes Stopwatch Welding QA/QC ITP Pocket Guide Page 2 Activity Project Welding Frequency Acceptance Criteria Action / Record Speed of Travel Weld s Each joint Range is inches/min per WPS / PQR Stopwatch Amperage Weld s Each joint Range is amps per WPS/PQR Multi meter Volt Weld s Each joint Range Volts per WPS Multi meter Max time between End of Hot Pass & Start of other Repair of Defects, Cracks / Arc Burns Field Transitions Weld Acceptance Check consumables and Welding Equipment Weld s As Needed Per operator specification Repair As Needed Welding Inspector Approval Specification Weld s As Needed Per Stated depending on < or > 20% specified yield strength & NDE Each weld B31.8 Daily API 1104 NDE s Proper consumable storage Welding equipment in proper condition Record as per operator requirements Visual and NDE Inspection NDE report NDE Visual. Specific procedure for repair on repair if allowed by Visual and NDE Inspection NDE report Visual and NDE Inspection NDE report Record as per operator requirements The INGAA Foundation Pipeline Training Guidance for Welding & Coating Workers & Inspectors 8

Weld Joint / Pipe Coating QA/QC ITP Pocket Guide Weld Joint / Pipe Coating QA/QC ITP Pocket Guide Activity Project Frequency Acceptance Criteria Action / Record Safety JSA Prior to performing ANY duties the coating foreman must ID ALL Hazards Applicator qualifications Inspection & Surface preparation Coating Application Safety Manual Manufacturers Specifications Weld Joint Weld Joint Daily Per Project Documentation -2 per shift (minimum) Inspection per occurrence Documentation -2 per shift (minimum) Application per occurrence Ensure ALL employees are wearing proper PPE for the relevant task at hand Understanding of manufacturing installation techniques Verification of Qualification as applicable Test Pipe to see if non-visible contaminates exist. Clean as per specification. Blasted to a NEAR WHITE finish Surface Profile will be checked and documented As per application specification. Pipe temperature has to be 5 degrees above dew point. Pre-heat pipe as per specification Tailgate safety Appropriate PPE (Including: Blasting Hood/Fresh Air Canister/Air lines) Complete & sign JSA Demonstrates knowledge of manufacturing installation methods / techniques Field Verification report or equivalent Inspect & Examine pipe for non-visible contaminates. Blast and check profile Remove all Frayed/Loose coating near cutback Brush Blast existing FBE Daily coating foreman report. Document temperatures Do not handle, lower in, or backfill until completely cured Measure dew point temperature, surface preparation, relative humidity, pipe temperature and mill thickness Daily coating foreman report Weld Joint / Pipe Coating QA/QC ITP Pocket Guide Page 2 Activity Project Frequency Acceptance Criteria Action / Record No damage All coated pipe shall be tested to locate holidays. After the holidays are patched, and just before pipe is lowered into the ditch--reinspect. Visual Inspect Pipe Coating Inspection Weld joint / pipe coating Each joint Check for appropriate coating thickness. Utilize holiday detector with voltage setting (FBE 2,000 volts DC, dual coat & two part epoxy 100 volts DC per mil of coating) shall be verified. Jeep The holiday detectors batteries must be checked and replaced/recharged if required daily. Coating repair Weld joint / pipe coating As needed Calibrate holiday detector daily Repair with patch stick, epoxy gun or two part epoxy in accordance with specifications. Record as per operator requirements Storage & Handling Weld joint / pipe coating Daily Maintained and stored in accordance with manufacturing specifications. Ensure proper Storage The INGAA Foundation Pipeline Training Guidance for Welding & Coating Workers & Inspectors 9

Tie In Coating Transition Area QA/QC ITP Pocket Guide Tie In Coating Transition Area QA/QC ITP Pocket Guide Activity Project Frequency Acceptance Criteria Action / Record Safety JSA Prior to performing ANY duties the coating foreman must ID ALL Hazards Applicator qualifications Inspection & Surface prep Coating Application Safety Manual Manufacturers Specifications Transition Area from existing to new coating Transition from existing to new coating Daily Per Project Documentation -2 per shift (minimum) Inspection per occurrence Documentation -2 per shift (minimum) Application per occurrence Ensure ALL employees are wearing proper PPE for the relevant task at hand Understanding of manufacturing installation techniques Verification of Qualification as applicable Test Pipe to see if non-visible contaminates exist. Clean as per specification. Blasted to a NEAR WHITE finish Surface Profile will be checked and documented As per application specification. Pipe temperature has to be 5 degrees above dew point. Overcoat will start and finish a minimum distance away from the transition area Pre-heat pipe as per specification Pipe temperature has to be 5 degrees above dew point Overcoat per operator specification Tailgate safety Appropriate PPE (Including: Blasting Hood/Fresh Air Canister/Air Lines) Complete & sign JSA Excavation safety review Demonstrates knowledge of manufacturing installation methods / techniques Field Verification report or equivalent Inspect & Examine pipe for non-visible contaminates. Blast and check profile Remove all Frayed/Loose coating near cutback Brush Blast existing FBE Daily coating foreman report. Document temperatures Do not handle, lower in, or backfill until completely cured Measure dew point temperature, surface preparation, relative humidity, pipe temperature and mill thickness Daily coating foreman report Tie In Coating Transition Area QA/QC ITP Pocket Guide Page 2 Activity Project Frequency Acceptance Criteria Action / Record No damage Visual Inspect All coated pipe shall be tested to locate holidays. After the holidays are patched, and just before pipe is lowered into the ditch. Pipe Coating Inspection Each weld Check for appropriate coating thickness. Utilize holiday detector with voltage setting (FBE 2,000 volts DC, dual coat & two part epoxy 100 volts DC per mil of coating) shall be verified. Jeep The holiday detectors batteries must be checked and replaced/recharged if required daily. Calibrate holiday detector daily Coating repair Weld Joint As needed Repair with patch stick, epoxy gun or two part epoxy in accordance with specifications. Record as per operator requirements Storage & Handling Daily Maintained and stored in accordance with manufacturing specifications. Ensure proper Storage The INGAA Foundation Pipeline Training Guidance for Welding & Coating Workers & Inspectors 10

Table 4 Issues Identified During PHMSA Inspection of 35 Construction Projects The INGAA Foundation Pipeline Training Guidance for Welding & Coating Workers & Inspectors 11

The INGAA Foundation Pipeline Training Guidance for Welding & Coating Workers & Inspectors 12