CONSTRUCTION METHOD STATEMENT FOR DEMOLITION AND NEW BUILD OF 13 NO. HOUSES AT LIME GROVE SCHOOL SITE BATH
2
Construction Method Statement INTRODUCTION The site is currently a disused school with various derelict boarded up buildings on it. Initial demolition of the school building will need to take place and once planning consents are in place a demolition contractor has been appointed. The demolition contractor will also be the Principal Contractor while demotion works are carried out. In the interests of being environmentally friendly, all existing concrete and brick rubble will be crushed and reused on site. SITE SET UP The extent of the site compound will be as shown in Appendix 1 In the interest of protection for the general public, it will be our intention to have full protective hoarding and screens around the site. ACCESS AND EGRESS The existing gate to the school will be kept in place for access and egress purposes. With regard to members of the public using the adjacent footpath to the south boundary a banksman will be in place to control traffic accessing and leaving the site TREE PROTECTION All tree protection measures will be in place to approved drawings prior to any operations taking on site. 3
Construction Method Statement DELIVERIES It is our intention to bring all deliveries along the A36 Pulteney Road turning into Pulteney Grove then left into Lime Grove Gardens avoiding Lime Grove due to the narrowness of the road, as shown in Appendix 2. All deliveries to site will take place on rigid axle lorries only due to residents parking on the road in Lime Grove Gardens. It is also our intention to avoid deliveries during rush hour to alleviate congestion for the local residents. CONTRACTORS PARKING All contractors parking will be on-site or in the pay and display car park outside of Bath Cricket Club. Absolutely no parking will be allowed by sub-contactors on any the adjacent roads. PILING None 4
Construction Method Statement GROUNDWORKS Groundworks will be carried out by supply and fix contractors, to be appointed, once planning for the development has been received. The above conditions will be set out in the Terms of Engagement. It is also envisaged that while the groundworkers are on site the groundworker will be the Principal Contractor and Bloor Homes will be the client. Once development has reached oversite stage and on-site road and footpaths completed, Bloor Homes will take over as Principal Contractor and our own employed manager will be on site on a permanent basis. All contractors and sub-contractors will be expected to have passed Bloor Homes standard competency checks and where necessary references will be taken and checked. COMMUNICATION AND LIAISING Throughout the project Bloor Homes and all their staff and contractors will maintain a high level of liaison and communication with all relevant parties to ensure the programme can be carried out with least amount of disruption to our neighbours, their property and the general public. The proposed site manager for this development will be Mr John Mumford who has worked in Bath previously on similar projects. WHEEL WASHING If required, a wheel wash may be put in place at the entrance to the site. 5
Construction Method Statement WASTE MANAGEMENT A full waste management plan will be put in place once planning is granted. DISC CUTTING All contractors and sub-contractors are made fully aware of their responsibilities and where necessary, dampening down measures will be put in place. PROPOSED ORDER OF BUILD Plots 1, 2, 5, 12, 13, 11, 10, 9, 8, 7, 6, 4 and 3. ESTIMATE OF CONTRACTORS ON SITE We estimate no more than 25 contractors on site any one time including: 4 Groundworkers 1 Forklift driver 1 Labourer 3 Carpenters 2 Plumbers 8 Bricklayers 2 Electricians 6
Construction Method Statement PROGRAMME OF WORKS It is estimated that the whole project would take no longer than 14 months. HOURS OF WORKING Hours of working will be: 8am to 5pm Monday to Friday 8am to 1pm Saturday No Sunday or Bank Holiday work. The site will be a Considerate Contractor Site Construction Director Mr John Gibbons Contracts Manager Mr Phil Lloyd Head Office Telephone Number 01793 835600 7
Appendix 1 8
ACCOMMODATION SCHEDULE TYPE A (1622 Sq Ft) 4 TYPE B (1960 Sq Ft) 2 TYPE C (1490 Sq Ft) 5 TYPE D (754 Sq Ft) 2 TOTAL 13 Notes: EXISTING TREES- TO BE RETAINED 1. Plot 5 will be used for an office, canteen and toilets. 2. Below plot 5 the garages of plots 1, 2, 3 and 4 will be used as storage. 3. Sub-contract parking to the rear garden of plot 3 and in front of garden 1-4. 4. Turning area for lorries in front of gardens 6, 7 and 8. 5. Banksman with be in attendance at all time to direct lorry movement Legend: P11 P10 P10 P12 P12 P13 P13 P11 P12 P13 Lorry Turning Area Sub-Contract Parking Compound and Welfare Storage Turning Area with Banksman Pedestrian Access Traffic Route Cross Over Point EXISTING RETAINING WALL 6 P6 P7 P9 P8 4 3 P5 P3 P4 P2 P1 2 TYPE D 5 EXISTING RETAINING WALL 1 Job. Former Lime Grove School Bath (13 units) Title. Traffic Management Plan Scale. Date. 1:500@A2 19.01.12 Drawn. Checked. TDO THIS DRAWING AND THE BUILDING WORKS DEPICTED ARE THE COPYRIGHT OF BLOOR HOMES LIMITED AND MAY NOT BE REPRODUCED OR AMENDED EXCEPT BY WRITTEN PERMISSION. NO LIABILITY WILL BE ACCEPTED FOR AMENDMENTS MADE BY OTHER PERSONS DO NOT SCALE THIS DRAWING, USE FIGURED DIMENSIONS ONLY, IF IN DOUBT ASK. R BLOOR HOMES LIMITED 3 STANTON COURT, SOUTH MARSTON PARK SWINDON, SN3 4YH TELEPHONE 01793 835600 FACSIMILE 01793 835601 LIME GROVE SCHOOL, BATH Drawing No. BHS91.TM01