Construction Management Statement. Introduction. Contents

Size: px
Start display at page:

Download "Construction Management Statement. Introduction. Contents"

Transcription

1 Construction Management Statement Project Name Dee Point Primary School Introduction On all Morgan Sindall projects, the safety and welfare of all is of paramount importance. This document concentrates on how we interface with the existing site operations and how we manage those interfaces to safeguard the pupils, staff, general public, construction work force and the project as a whole. The following key topics have been identified which will be developed in more detail and agreed prior to the works commencing on site: Contents Key Programme Dates Site Access & Traffic Management Site Boundary Site Compound Site Accommodation Parking Strategy Logistics Management Waste Minimisation Major Plant & Equipment Community Relations Considerate Constructor Key Educational Matters Environmental Considerations Site Housekeeping Hours of Working Construction Phasing Plans Key Programme Dates Start Site Mobilisation 13 th July 2015 New School Building Operational 5 th September 2016 Demolition & External Landscaping Complete December 2016 The Key dates above are subject to planning approval and discharge of any relevant conditions. Site Access & Traffic Management The main access to site will be from Blacon Point Road via Western Avenue. Highway signage will be erected on the surrounding road network warning all site users of the construction site entrances and exits. (See site access route map appended). On arrival at the site boundary there will be a Morgan Sindall representative to meet all visitors, operatives and delivery vehicles. Personnel access onto the construction site will be controlled by a logistics supervisor. This will ensure no unauthorized personnel enter onto site and that everyone can be accounted for at the end of each working shift. Advanced notice will be required from our supply chain partners and their suppliers for all multiple or abnormally sized deliveries, such deliveries will be scheduled so as not to interfere with the existing school operations or cause congestion to the adjacent roads. All material and sub-contract orders placed with our supply chain will include the details of the restricted delivery hours. There will be no construction vehicle movements into or out of the site during the school start and finish times i.e. between 08:30 to 09:15 and 14:45 and 15:30.

2 Site Boundary A 2.4m high timber hoarding will segregate our construction site from the school and the public areas. The accurate positioning and setting out of the site hoarding and fencing will be agreed prior to installation. Where the existing school security fence is of appropriate height and condition, we will look utilise this on site; this will be branded with Morgan Sindall signage and debris netting where required. The proposed site boundary will not impact on any fire exits / routes from the existing buildings and the necessary liaison with the Fire Authority will be made to familiarise them with our proposals and ensure that the current fire fighting access routes are suitably maintained. Site Compound To enable safe site operations, a site compound area is instrumental to afford the unloading, storage and distribution of materials. Site accommodation will be segregated from the works area and unloading zone by pedestrian barrier fence, to ensure site staff and operatives safety is maintained. Lay down areas for materials will be designated and managed to ensure materials are kept clean and damage is avoided. This prevents impact on the programme due to the need to re-order materials. If possible, it will be our intention to derive temporary power and water supplies from the existing site infrastructure this would be a separately metered source. A temporary foul drainage connection will be made into the existing foul water drainage system on site. Road sweeping will take place on a regular basis during the groundwork activities to the site compound to eliminate mud and debris being transferred onto the surrounding highway network. The approaching roads and footpaths will also be swept on a regular basis during the works. Tree protection will be established using demountable wire mesh fencing, positioned to protect both foliage and root zones of retained trees during the construction phase. On completion of the project the site compound will be removed and the permanent surface will be constructed. Site Accommodation The Morgan Sindall site accommodation will comprise of: project offices, meeting room, kitchen and Induction / first aid room. The accommodation will also include welfare facilities housing: canteen rooms, toilet block & drying rooms with lockers. Supply chain partners will have the use of Morgan Sindall welfare facilities. All cabins will be uniform, clean and presentable in appearance, fire rated and of high security. There will be a visiting cleaner employed by Morgan Sindall to carry out cleaning duties and maintenance of the site offices and welfare facilities.

3 Parking Strategy Due to the site constraints there will be only a limited number of car or crew bus parking places on site. There are no local car parks, therefore on street parking will be strictly in accordance with the Highway Code. Morgan Sindall s logistics manager will patrol the surrounding streets twice a week, to ensure our site operatives vehicles are parked in accordance with the Highway Code. All supply chain partners will have been informed of the site restrictions during tender stage and a parking code of conduct which supplements the Highway Code will be written into the subcontract order. We will encourage shared transport, crew buses and public transport to limit vehicles arriving at site. Logistics Management We recognise the importance of controlling the construction traffic on accessing and egressing the site along with the interface with the existing school users and local residents, therefore it is our intention to deploy a logistics supervisor to control the construction traffic and to ensure there is no congestion caused at the entrance / exit to site during the construction works. This person will take full responsibility of controlling the road sweeping operations, ensuring all the approaching roads and footpaths are kept clean at all times and ensure the site is kept in a clean and tidy condition throughout all phases of the construction works. The supervisor will be a qualified slinger / banksman and will assist in the safe unloading of wagons; this will be carried out by means of a forklift truck or crane. The safe unloading of wagons will be carried out with the aid of air bags, nets or lanyard system. Materials will be stored in a manner so as to ensure they are not contaminated by weather or site dirt, where required, materials will be stored off the ground and covered. Our preferred method of erection will be to crane / lift the materials into position directly from delivery trailers where possible. Waste Minimisation A Site Waste Management Plan (SWMP) will be developed prior to works starting on site, which will include the establishment of a waste zone; housing skips for waste segregation prior to removal from site and storage of packaging to be removed from site for reuse or recycling. We use Smartwaste (online BRE tool) for SWMP s and unless the client has stipulated otherwise we use the same platform. Below is an example from one of our live sites Northway Primary School:

4 The SWMP will consist of a series of targets to ensure that the project team and supply chain stay focused throughout the project to keep waste levels to a minimum. Weekly updates and monthly reports are produced to monitor performance against targets; these reports are shared with the SHEQ team within Morgan Sindall who will archive as a record of how Morgan Sindall have minimised their impact on the environment. Major Plant & Equipment Bulk muck shift and foundation excavation will be carried out using a excavator. Concrete to foundations will be placed where possible by direct discharge from ready mix trucks, where this is not possible the excavator will be used. Erection of the steel frame will be undertaken utilising a mobile crane, the crane will at all times be positioned within the construction area. Steel will be unloaded from delivery vehicles within the construction site area. Mobile elevating working platforms will be used on the building envelope where the finishes are predominantly curtain walling and render; scaffolding will be used for areas of brickwork. Community Relations Considerate Constructor A Liaison and Communication Strategy will be developed with the school to ensure that good relations are maintained, we have found that this has proven invaluable with similar recent projects. During informal fortnightly meetings with the school management team, short term look-ahead information about the project will be explained and followed by a question and answer session; we have found that this involvement and approach mitigates the effects of the construction activities. Morgan Sindall is an Associate Member of the Considerate Constructors Scheme and therefore all our projects are registered with the scheme; the site would then be monitored by a third party experienced industry professional to assess performance against a five point code of considerate practice. Categories include: enhancing the appearance, respecting the community, protecting the environment, securing everyone s safety and caring for the workforce. Traffic route planning for construction vehicles will be adopted; this will direct all site traffic on route to and from the site to use routes that minimise public disruption / conflict. We will actively engage with the school to involve them in construction related events such as: Mural painting and viewing panels within site hoarding Donation towards local charities / charity events Weekly blogs Key Educational Matters A critical success factor will be the need for the school and site management to communicate effectively and work as a collaborative team. Communication and timely decision making will be the cornerstone in safeguarding the school operations, progress of the project and safety of all concerned.

5 This would be achieved through the fortnightly informal meetings forming part of our Liaison and Communication Strategy. This may include setting up a project website for staff and students to log onto, displaying a live webcam, latest project news, progress and the intended works on the project. This facility has been a great success on recent projects. The planning of the construction work and the site set up has taken into account the effect on the daily operations of the school including the movement of staff and visitors. Key issues include: Separation of logistics, entry and egress points to the site Detailed discussion have taken place with the school to verify the most used routes by the pedestrians in and around the school so as to avoid wherever possible site traffic conflict Securing site perimeter fencing / hoarding to prevent unauthorised access Project website accessible by school users to enable viewing of the site works On-going review once the site has been established to ensure refinement and improvement where necessary Environmental Considerations To ensure that the works progress with the minimum disruption to the surrounding area and its neighbours especially those located immediately adjacent to the site; all works will comply with the Morgan Sindall Health, Safety and Environmental Policy. Giving particular consideration to the constraints of the project we would address noise, dust, vibration and summarise our solutions below: Noise The Considerate Constructors Scheme is a national initiative, set up by the construction industry to encourage best practice beyond statutory requirements in the main areas of the environment, the workforce and general public. As Associate Members of this scheme, we will always be proactive and maintain open dialogue with those affected by our works through regular meetings to ensure we do not disrupt any special planned activities or critical working arrangements that may be adversely affected by noise. Existing noise levels will be fully recorded and logged prior to commencing the works and be diligently monitored throughout the duration of the site works. Equipment selection, materials and systems will contribute to noise control strategy together with the careful timing of inherently noisy activities such as breaking out the existing surface finishes. The timing of such operations will be carried out by prior agreement with the school and if necessary will be conducted out of hours or at weekends or holidays. Noise reduction measures include: Comply or surpass recommendations of BS Effective silencing of plant and processes, including the use of well-maintained plant Enforce a 5mph site speed limit Use of mains electricity in place of generators where practicable Personal radios banned from site Sirens / bells for emergency use only Base line noise survey will be carried out prior to the work Process / plant utilisation method statements to take account of noise control including the switching off of machinery during idling time, work breaks etc. Dust We will consider the spread and effect of airborne dust during the works at every supply chain preorder interview and ensure mitigation / prevention strategy is agreed and presented within the method statements for every applicable trade and operation. Following the pre-order interview, method statements will be reviewed by Morgan Sindall and finalised

6 by a sign off by the site manager to ensure compliance with the requirements to prevent / mitigate environmental nuisances such as dust. The installation of a wind sock on the site will be used as highly visual indicator of the wind direction. The sock affords site management and operatives a quick indication of wind direction which will be used as an aid in monitoring the displacement of dust. Further dust reduction measures include: Consideration at material procurement stage to reduce the need for the cutting of materials and then only allowing site cutting in designated areas Dampening down of dust generating activities Covered wagons to be used for the transportation of dust generating materials Existing roads will be kept clean and maintained The management of dust-generating activities to be stated in appropriate method statements together with control measures Speed limits as previously noted Vibration Any plant on site will be audited and whilst in use, will maintain a 5mph speed limit around the working environment. We may also consider the use of temporary speed bumps and crossings to minimise the speed and movement of site traffic. Vibration reduction measures include: Omit / limit vibrating activities where possible Control working hours of vibrating activities Tracked vehicles to be routed away from neighbouring buildings and wheeled machines to be used wherever practicable Light Pollution Site lighting will only be utilised when necessary, and of sufficient intensity to progress the works and maintain security Floodlights will be located to provide the necessary site illumination with lamp-heads directed so as not to shine onto / into adjacent properties and therefore not be a nuisance, in particular to the adjacent buildings. Ground and Watercourse Contamination Method statements for the works will be devised to take account of contamination risk and the effective management of that risk All materials / processes will be handled / undertaken strictly in accordance with the suppliers / manufacturers recommendations All bulk solid, granular, liquid materials will only be stored on site in (limited) quantities necessary to meet the requirements of the construction process All liquid materials will be stored in suitable containers, adequately bunded to comply with Health, Safety and Environmental legislation / recommendations Sensitive areas will be subjected to specific protection regimes Spillage reaction / clean-up plans will be in place to be undertaken by a trained squad of personnel Specialist cleaning equipment will be placed in key locations around site to minimise any spillage should it occur

7 All waste materials will be controlled / sorted into the appropriate waste containers on site prior to removal by an authorised / licensed waste carrier Interceptors will be used to remove solids etc from any site discharges, which may, with the agreement of the Local Authority be made into the surface water drainage system Site Housekeeping Throughout the project we will encourage and enforce a Good Housekeeping regime and actively promote Pride in the Job. A strategy will be developed and incorporated into the site rules which will be sent to suppliers and supply chain partners alike. The strategy will also form an essential part of the supply chain / suppliers pre-order interview. We will ensure that all operatives engaged on the works are familiar with the work in progress, skilled at their task, aware of their duties and responsibilities to others and knowledgeable of the site rules. All persons working on site will attend the site safety induction and sign-up to the site rules. Special attention will be given to working adjacent to the existing school buildings, confined spaces and deep excavations. The work package specific method statement will be devised during the project in conjunction with the appropriate supply chain partner. All excavations and work areas will be adequately fenced and sign posted. Pedestrian routes through the site (for authorised personnel only) will be clearly marked and plant operators inducted as to the no-go status of these pedestrian routes. All personnel on site will wear full Personnel Protective Equipment at all times. Hours of Working Monday to Friday: 07:30 18:00hrs Saturday: 07:30 13:00hrs (Prior agreement with client s project manager) There will be no construction vehicle movements into or out of the site during the school start and finish times i.e. between 08:30 to 09:15 and 14:45 and 15:30. Extended working hours may be required for one off operations should the exception arise we will seek advance agreement from the Client s Project Manager.

Construction Management Statement. Residential development at Bywell House, St Mary s Hill, Ascot

Construction Management Statement. Residential development at Bywell House, St Mary s Hill, Ascot Construction Management Statement Residential development at Bywell House, St Mary s Hill, Ascot Parking of Vehicles of Site Personnel, Operatives and Visitors Site staff, visitors to the development and

More information

Site Layout & Traffic Plan

Site Layout & Traffic Plan Location Site address: Norbury Manor Business Enterprise College, Kensington Avenue, Thornton Heath, Croydon CR7 8BT. The new block will be constructed on the existing hard play area. The construction

More information

Construction Traffic Management Plan

Construction Traffic Management Plan Construction Traffic Management Plan Proposed Additional Classroom Accommodation for Woolacombe Primary School Produced for and on behalf of Built Environments Team Devon County Council NPS South West

More information

Demolition & Construction Management Plan

Demolition & Construction Management Plan Demolition & Construction Management Plan 72 76 Cadogan lane SW1 Demolition & Construction Management Plan Issue Date: March 2013 Contents: 1.0 Introduction 1.1 Objectives of the Plan 1.2 Project Overview

More information

University Arms Hotel, Cambridge

University Arms Hotel, Cambridge Traffic Management Plan For University Arms Hotel, Cambridge Prepared By: James Batterbee Number: M1342 / Rev B Date: 29 th August 2014 CONTENTS: (1) INTRODUCTION (2) VEHICLE ACCESS & EGRESS AND PEDESTRIAN

More information

Construction Site Set Up Requirements

Construction Site Set Up Requirements Process Code Number Revision COP A 035 B Document Title Construction Site Set Up Requirements B 1/11/10 SRC SAT DH Final A 1/10/10 SRC MI Draft comment Rev. Date Prepared Reviewed Approved Detail/Comment

More information

Construction Traffic Management Plan

Construction Traffic Management Plan Introduction This (CTMP) has been prepared in order to discharge Condition 20 of planning permission ref 07/02879/EFUL for the enabling site works associated with the wider Bath Western Riverside development.

More information

19-27 Young Street Development Kensington

19-27 Young Street Development Kensington 19-27 Young Street Development Kensington Construction Management Plan Resident Update Draft 2nd October 2013 υ Introduction An initial construction management meeting took place on Tuesday 10 th September

More information

Construction Traffic Management Plan

Construction Traffic Management Plan Construction Traffic Management Plan Proposed Additional Accommodation for SWDPLS Shinners Bridge Dartington Produced for and on behalf of Built Environments Team Devon County Council NPS South West Ltd

More information

PROPOSED RESIDENTIAL DEVELOPMENT LAND OFF MACCLESFIELD OLD ROAD, BUXTON. Construction Management Plan

PROPOSED RESIDENTIAL DEVELOPMENT LAND OFF MACCLESFIELD OLD ROAD, BUXTON. Construction Management Plan PROPOSED RESIDENTIAL DEVELOPMENT LAND OFF MACCLESFIELD OLD ROAD, BUXTON Construction Management Plan May 2013 CONTENTS Page No: 1.0 INTRODUCTION 1 2.0 PROJECT ORGANISATION AND RESPONSIBILITIES 2 2.1 Client

More information

CITY OF VINCENT CONSTRUCTION MANAGEMENT PLAN GUIDELINES

CITY OF VINCENT CONSTRUCTION MANAGEMENT PLAN GUIDELINES CITY OF VINCENT CONSTRUCTION MANAGEMENT PLAN GUIDELINES INTRODUCTION What is a Construction Management Plan? The City of Vincent requires careful management of construction involving excavation and retention

More information

Logo here. TRAFFIC MANAGEMENT PLAN Ref : xxxx Dated xxxxxx. Enter details. Delivery Address: Enter details

Logo here. TRAFFIC MANAGEMENT PLAN Ref : xxxx Dated xxxxxx. Enter details. Delivery Address: Enter details Logo here Ref : xxxx Dated xxxxxx Mandatory H&S 905 Rev 1: xxxxx Page 1 of 1 Project: Project No: Date: Prepared by: Enter details Enter details Enter details Enter details Delivery Address: Enter details

More information

Galloper Wind Farm Project. Traffic Management Plan May 2013 Draft v1 Document Reference GWF/TMP/100513. Galloper Wind Farm Limited

Galloper Wind Farm Project. Traffic Management Plan May 2013 Draft v1 Document Reference GWF/TMP/100513. Galloper Wind Farm Limited Galloper Wind Farm Project Traffic Management Plan May 2013 Draft v1 Document Reference GWF/TMP/100513 Galloper Wind Farm Limited Document title Galloper Wind Farm Project Traffic Management Plan Status

More information

CONSTRUCTION TRAFFIC MANAGEMENT PLAN Issue 2, V5, 11/11/13

CONSTRUCTION TRAFFIC MANAGEMENT PLAN Issue 2, V5, 11/11/13 Note: Please refer to the end of this document for guidance notes about completing this form Q1. What is the full postal address of the site? Your response Q2. Planning reference and revision number (if

More information

CONSTRUCTION TRAFFIC MANAGEMENT PLAN V11, 26/09/12

CONSTRUCTION TRAFFIC MANAGEMENT PLAN V11, 26/09/12 If the project you are constructing was subject to planning permission and a condition requiring a Construction Traffic Management Plan (CTMP) was applied to the planning consent, this condition will need

More information

CONSTRUCTION MANAGEMENT PLAN

CONSTRUCTION MANAGEMENT PLAN CONSTRUCTION MANAGEMENT PLAN for CHILDRENS CENTRE, PRIMARY CLASSROOM & REPLACEMENT PRESCHOOL AT CLYST ST MARY PRIMARY SCHOOL EXETER, DEVON EX5 1BG REVISION A 7 May 2010 1 P a g e Mansell have been appointed

More information

This document must be read in conjunction with the Permit to Work and Service Interruption Notice policy.

This document must be read in conjunction with the Permit to Work and Service Interruption Notice policy. UNIVERSITY OF HERTFORDSHIRE HIGHER EDUCATION CORPORATION SITE RULES FOR CONTRACTORS The University s Site Rules for Contractors are issued on the authority of the Director of Estates, Hospitality and Contract

More information

Abu Dhabi EHSMS Regulatory Framework (AD EHSMS RF)

Abu Dhabi EHSMS Regulatory Framework (AD EHSMS RF) Abu Dhabi EHSMS Regulatory Framework (AD EHSMS RF) EHS Regulatory Instrument Code of Practice EHS RI CoP 44.0 Traffic Management and Logistics Version 2.0 February 2012 ACKNOWLEDGEMENTS With gratitude

More information

BEHANS LAND RESTORATION LIMITED RESTORATION OF FORMER QUARRY BLACKHALL, CO. KILDARE OUTLINE CONTINGENCY PLAN MAY 2008

BEHANS LAND RESTORATION LIMITED RESTORATION OF FORMER QUARRY BLACKHALL, CO. KILDARE OUTLINE CONTINGENCY PLAN MAY 2008 BEHANS LAND RESTORATION LIMITED RESTORATION OF FORMER QUARRY BLACKHALL, CO. KILDARE OUTLINE CONTINGENCY PLAN MAY 2008 JBA Prepared by : John Barnett and Associates / SLR Consulting 7 Dundrum Business Park

More information

1. GENERAL STATEMENT OF COMPANY HEALTH, SAFETY AND ENVIRONMENTAL POLICY

1. GENERAL STATEMENT OF COMPANY HEALTH, SAFETY AND ENVIRONMENTAL POLICY 1. GENERAL STATEMENT OF COMPANY HEALTH, SAFETY AND ENVIRONMENTAL POLICY Dumfries Timber Co. Ltd. is committed to comply with our legal duties in order to provide a safe and healthy working environment

More information

CONSTRUCTION TRAFFIC MANAGEMENT PLAN (CTMP)

CONSTRUCTION TRAFFIC MANAGEMENT PLAN (CTMP) CONSTRUCTION TRAFFIC MANAGEMENT PLAN (CTMP) [Colston Budd Hunt & Kafes Pty Ltd AS AMENDED BY City of Sydney] 23 March 2010 1. PREAMBLE 1.1 This document constitutes the Demolition and Traffic Management

More information

Site Induction Presentation

Site Induction Presentation ABC Contracting Site Induction Presentation This presentation provides a mock site induction and serves to help those people in the process of preparing and delivering site inductions It is essential that

More information

Howard Primary School Construction Management Plan

Howard Primary School Construction Management Plan 2.1 Introduction Howard Primary School Construction Management Plan The Howard Primary school project covers the construction of a new three storey block next to a live school and includes alterations

More information

Pollution & Noise from Demolition & Construction Sites

Pollution & Noise from Demolition & Construction Sites CONTROL OF Pollution & Noise from Demolition & Construction Sites N oi se Co ns tru ct io n MAY 2008 THE LONDON BOROUGH 3 CONTENTS Part 1 Introduction Page 1. Background 4 2. Purpose of the code 5 3.

More information

Triton Knoll Offshore Wind Farm Limited Electrical System. Outline Traffic Management Plan

Triton Knoll Offshore Wind Farm Limited Electrical System. Outline Traffic Management Plan Triton Knoll Offshore Wind Farm Limited Electrical System Outline Traffic Management Plan October 2014 RWE Innogy UK Triton Knoll TMP Copyright 2014 RWE Innogy UK Ltd All pre-existing rights reserved.

More information

Rockhampton Office Brisbane Office Tarong Site. Barron Gorge Hydro PS Kareeya Hydro PS Mica Creek PS

Rockhampton Office Brisbane Office Tarong Site. Barron Gorge Hydro PS Kareeya Hydro PS Mica Creek PS Business Procedure Traffic Management Document Number OHS-PROC-130 This document applies to the following sites: All Sites Rockhampton Office Brisbane Office Tarong Site Barron Gorge Hydro PS Kareeya Hydro

More information

Devonport EfW CHP Facility. CEMP Proposal for Non Destructive Testing Activities. 1. Introduction

Devonport EfW CHP Facility. CEMP Proposal for Non Destructive Testing Activities. 1. Introduction Devonport EfW CHP Facility CEMP Proposal for Non Destructive Testing Activities. 1. Introduction This application is issued in compliance with the principles of the approved Construction Environmental

More information

ANNEX 2 Emergency / Pollution Incident Response Plan

ANNEX 2 Emergency / Pollution Incident Response Plan ANNEX 2 Emergency / Pollution Incident Response Plan Volume 5 of 5 Appendix 21.1 Annex 2 EPIRP Page 1 of 9 1 WIND FARM CONSTRUCTION ENVIRONMENTAL EMERGENCY / POLLUTION RESPONSE PLAN... 3 1.1 Policy...

More information

Working at Height. Procedure

Working at Height. Procedure Procedure *All Forth Valley College Health, Safety and Welfare Procedures are covered under the overarching Health, Safety and Welfare Policy. Status: Date of version: Reviewed by: Author/Contact Person;

More information

THIS PAGE INTENTIONALLY LEFT BLANK

THIS PAGE INTENTIONALLY LEFT BLANK THIS PAGE INTENTIONALLY LEFT BLANK Construction Traffic Management Plan 2 Contents 1. Introduction... 4 1.1 Conditions of Consent... 4 2. Goals of the CTMP... 6 2.1 Objectives... 6 2.2 Predicted Construction

More information

Health & Safety Policy For Locations Hosting Film Production Companies

Health & Safety Policy For Locations Hosting Film Production Companies Health & Safety Policy For Locations Hosting Film Production Companies Throughout this document, the location will be referred to as The Venue and the film production company as The Contractor. The following

More information

CORPORATE PROCUREMENT UNIT SITE & SECURITY PROCEDURES BOSTON SPA VERSION 9 SEPT12

CORPORATE PROCUREMENT UNIT SITE & SECURITY PROCEDURES BOSTON SPA VERSION 9 SEPT12 SITE PROCEDURES BSPA VERSION 9 PAGE 1 OF 9 CONTENTS PAGE 1. GENERAL INFORMATION 3 2. ACCESS 3 3. SECURITY 3 4. VEHICLE PARKING 4 5. PERMITS TO WORK 4 6. DELIVERY, UNLOADING AND STORAGE 4 7. HOURS OF WORK

More information

Environmental Site Inspection Checklist

Environmental Site Inspection Checklist Note : This form is designed for general use and may not be exhaustive. Modifications and additions may be necessary to suit individual projects and to address specific environmental issues and associated

More information

Scaffold Standard (Standard to Managing and Appointing Scaffolding Contractors on University College London (UCL) Projects) Management Standard

Scaffold Standard (Standard to Managing and Appointing Scaffolding Contractors on University College London (UCL) Projects) Management Standard Scaffold Standard (Standard to Managing and Appointing Scaffolding Contractors on University College London (UCL) Projects) Management Standard UNIVERSITY COLLEGE LONDON Engineering, Maintenance & Infrastructure

More information

CONSTRUCTION SEQUENCE & PROGRAMME

CONSTRUCTION SEQUENCE & PROGRAMME CONSTRUCTION SEQUENCE & PROGRAMME 2 CONTENTS 1.0 Introduction 7 2.0 Key activities 8 2.1 Airport related activities 2.2 Construction of new roads and accesses 2.3 Earthworks zone a 2.4 Earthworks zone

More information

WASTE Application Form - Dublin Waste to Energy SECTION J ACCIDENT PREVENTION & EMERGENCY RESPONSE

WASTE Application Form - Dublin Waste to Energy SECTION J ACCIDENT PREVENTION & EMERGENCY RESPONSE SECTION J ACCIDENT PREVENTION & EMERGENCY RESPONSE Describe the existing or proposed measures, including emergency procedures, to minimise the impact on the environment of an accidental emission or spillage.

More information

Construction Management Plan Template

Construction Management Plan Template Plan Template Planning Permit Number:... Date Planning Permit Issued:... Approval Stamp (Office Use only): Standard Plan Template Project details Company Operational Details.. Directors Name Company Name

More information

COSVR404 Erect and dismantle plant (cranes and rigs)

COSVR404 Erect and dismantle plant (cranes and rigs) Overview This standard is about interpreting information, adopting safe, healthy and environmentally responsible work practices, selecting materials, components, plant, tools and ancillary equipment, preparing

More information

Approval Services Unit

Approval Services Unit Approval Services Construction Management Plan Pro-Forma Commercial Properties Please complete the enclosed form and return to:- By Mail: Approval Services Unit City of Perth Council House 27 St Georges

More information

Development proposals will require to demonstrate, according to scale, type and location, that they:-

Development proposals will require to demonstrate, according to scale, type and location, that they:- Appendix 2 : Relevant Development Plan Policies Angus Local Plan Review 2009 Policy S1 : Development Boundaries (a) Within development boundaries proposals for new development on sites not allocated on

More information

CONTRACTOR SAFETY MANAGEMENT PROCEDURE

CONTRACTOR SAFETY MANAGEMENT PROCEDURE CONTRACTOR SAFETY MANAGEMENT PROCEDURE Version 1.0 TRIM file number Short description Relevant to Authority Responsible officer Responsible office Date introduced July 20, 2015 Date(s) modified June 11,

More information

Safety Systems Review Facilities Management Guidance and specification Version 1 2014

Safety Systems Review Facilities Management Guidance and specification Version 1 2014 Safety Systems Review Facilities Management Guidance and specification Version 1 2014 Membership Training Qualifications Audit and Consultancy Policy and Opinion Awards Contents Page Safety Systems Review

More information

CONSTRUCTION MANAGEMENT PLAN REQUIREMENTS MANUAL

CONSTRUCTION MANAGEMENT PLAN REQUIREMENTS MANUAL CONSTRUCTION MANAGEMENT PLAN REQUIREMENTS MANUAL This manual applies to all development projects within Pitkin County. A Construction Management Plan (CMP) shall be submitted for all projects in Pitkin

More information

Environmental Policy. JRI Orthopaedics Limited

Environmental Policy. JRI Orthopaedics Limited JRI Orthopaedics Limited October 2014 Contents Clause 1. Policy Statement 1 2. Who is covered by the policy? 2 3. Organisation and Responsibilities 2 4. Training and Communication 3 5. Suppliers and Customers

More information

Construction Management Plan (CMP) Application

Construction Management Plan (CMP) Application About this form Principal Contractor (Applicant) Applicant Details (Person lodging application and main contact for CMP) DA and Site Details Development Consent for Works you are carrying out Construction

More information

Level 2 NVQ Diploma in Trowel Occupations (Construction) (6570-02) May 2014 Version 2.0

Level 2 NVQ Diploma in Trowel Occupations (Construction) (6570-02) May 2014 Version 2.0 QUALIFICATION HANDBOOK Level 2 NVQ Diploma in Trowel Occupations (Construction) (6570-02) May 2014 Version 2.0 Qualification at a glance Subject area City & Guilds number 6570 Age group approved 16-18,19+

More information

Release: 1. RIIOHS302A Implement traffic management plan

Release: 1. RIIOHS302A Implement traffic management plan Release: 1 RIIOHS302A Implement traffic management plan RIIOHS302A Implement traffic management plan Modification History Not applicable. Unit Descriptor This unit covers the competency required to implement

More information

TEMPORARY TRAFFIC MANAGEMENT Operate as a Traffic Controller (TC) for low volume and Level 1 roads

TEMPORARY TRAFFIC MANAGEMENT Operate as a Traffic Controller (TC) for low volume and Level 1 roads 1 of 8 level: 3 credit: 4 planned review date: October 2008 sub-field: purpose: Highway Construction and Maintenance This unit standard is for people who may be appointed, subject to guidance and monitoring

More information

Construction Phase Traffic Management Plan

Construction Phase Traffic Management Plan Construction Phase Traffic Management Plan The Construction Phase Traffic Management Plan is in connection with the application for the development of a single Wind Turbine and Ancillary Works on land

More information

Household waste & recycling storage requirements

Household waste & recycling storage requirements South Gloucestershire Council Guidance for Developers on Household waste & recycling storage requirements INTRODUCTION As part of the Council s aim to improve the quality of life for residents as well

More information

Traffic Management Plan - Depot Procedure

Traffic Management Plan - Depot Procedure Traffic Management Plan - Depot Procedure Date: 1/8/13 Version: TMPDPGWT001 Status: Approved 1. Purpose This procedure outlines the traffic management plan which must be followed for the Depots. 2. Scope

More information

Pollution Incident Response Plan

Pollution Incident Response Plan Pollution Incident Response Plan Introduction Schmidt Quarries is committed to ensuring all aspects of our quarrying activities comply with the environmental legislative requirements in NSW. This Pollution

More information

IALN11006400 /05 01 19.06.13. FAO: The Planning Department The Royal Borough of Windsor and Maidenhead Town Hall, St. Ives Road Maidenhead SL6 1RF

IALN11006400 /05 01 19.06.13. FAO: The Planning Department The Royal Borough of Windsor and Maidenhead Town Hall, St. Ives Road Maidenhead SL6 1RF IALN11006400 /05 01 19.06.13 FAO: The Planning Department The Royal Borough of Windsor and Maidenhead Town Hall, St. Ives Road Maidenhead SL6 1RF Dear Sir / Madam Re: 12/02994 BCA Sports Hall Condition

More information

A: SIGNIFICANT RISKS Initial Risk Rating H/M/L B: KEY CONTROL MEASURES ACTION

A: SIGNIFICANT RISKS Initial Risk Rating H/M/L B: KEY CONTROL MEASURES ACTION ELECTRICAL CONTRACTOR RISK ASSESSMENT AND KEY CONTROL MEASURES CONTRACTOR NAME: AEC Automation Ltd. NAME OF CONTRACT: A: SIGNIFICANT RISKS Initial Risk Rating H/M/L Slips, trips and falls. Manual handling.

More information

Pollution Incident Response Management Plan

Pollution Incident Response Management Plan Pollution Incident Response Management Plan POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN 1. Introduction This Pollution Incident Response Management Plan (PIRMP) has been prepared to describe the processes

More information

Event Planning Guidance Notes EVENT PLANNING GUIDANCE NOTES

Event Planning Guidance Notes EVENT PLANNING GUIDANCE NOTES EVENT PLANNING GUIDANCE NOTES 1 Event Planning Guidance Notes Important issues This documentation is not a full and authoritative statement of the law, statutory guidance or best practice in planning,

More information

CONTACTS: Mitchell Shire Council 57346200. M.S.C. Building Department 57346230. M.S.C. Health Department 57346238

CONTACTS: Mitchell Shire Council 57346200. M.S.C. Building Department 57346230. M.S.C. Health Department 57346238 CONTACTS: Mitchell Shire Council 57346200 M.S.C. Building Department 57346230 M.S.C. Health Department 57346238 M.S.C. Enforcement & Compliance Unit 57346274 Building Control Commission 92856458 USEFUL

More information

OUTLINE TENDER STAGE METHOD STATEMENT Removal of Asbestos Cement Roof & demolition of Building At Highbury Roundhouse. Ronald Road. London.

OUTLINE TENDER STAGE METHOD STATEMENT Removal of Asbestos Cement Roof & demolition of Building At Highbury Roundhouse. Ronald Road. London. OUTLINE TENDER STAGE METHOD STATEMENT Removal of Asbestos Cement Roof & demolition of Building At Highbury Roundhouse. Ronald Road. London. N5 1XB Document Control Revision No. Date Approved Signature

More information

TRAFFIC MANAGEMENT PLAN

TRAFFIC MANAGEMENT PLAN TRAFFIC MANAGEMENT PLAN For: The construction and operation of a Photovoltaic (PV) Facility in Dabenoris, South Africa Prepared for: Alternative Energy Solutions (Pty) Ltd PO Box 4939 Tygervalley, South

More information

Site inspection: Workplace transport checklist

Site inspection: Workplace transport checklist Site inspection: Workplace transport checklist The following checklist is a guide to what employers should consider when assessing the risk from vehicles in the workplace. It may not be comprehensive for

More information

Method Statement Ground & Gardens Maintenance Service

Method Statement Ground & Gardens Maintenance Service CONFORMED COPY Method Statement Ground & Gardens Maintenance Service Revision History Revision Date Reviewer Status 23 March 2007 Project Co Final Version Table of Contents 1 Objectives... 3 2 Management

More information

THE UNIVERSITY OF SHEFFIELD WORK AT HEIGHT POLICY

THE UNIVERSITY OF SHEFFIELD WORK AT HEIGHT POLICY THE UNIVERSITY OF SHEFFIELD WORK AT HEIGHT POLICY CONTENTS Page No 1 INTRODUCTION 2 2 LEGISLATION 2 3 HIERARCHY OF CONTROL 2 4 WORK AT HEIGHT POLICY 3 5 ROLES AND RESPONSIBILITIES 3 6 RISK ASSESSMENTS

More information

Workplace Transport Safety Reversing Vehicles Information Sheet What are the dangers associated with reversing vehicles? Why is reversing a problem?

Workplace Transport Safety Reversing Vehicles Information Sheet What are the dangers associated with reversing vehicles? Why is reversing a problem? Workplace Transport Safety Reversing Vehicles Information Sheet This information sheet aims to raise awareness of the dangers caused by reversing vehicles in the workplace. It provides basic information,

More information

Monitoring programmes and resources

Monitoring programmes and resources Unit 3: P lanning construction work processes and efficient use of resources in construction and the. 34 Monitoring programmes and resources This topic guide explores how to monitor construction project

More information

CITY OF WHITEHORSE Construction Management Plan G U I D E L I N E S

CITY OF WHITEHORSE Construction Management Plan G U I D E L I N E S CITY OF WHITEHORSE Construction Management Plan G U I D E L I N E S Contents A. Introduction B. Components of a Construction Management Plan C. Construction Management Plan Approval Process D. Further

More information

AVOIDANCE OF ELECTRICAL HAZARDS WHEN WORKING NEAR OVERHEAD ELECTRIC LINES

AVOIDANCE OF ELECTRICAL HAZARDS WHEN WORKING NEAR OVERHEAD ELECTRIC LINES overhead 23/11/04 2:28 PM Page 1 AVOIDANCE OF ELECTRICAL HAZARDS WHEN WORKING NEAR OVERHEAD ELECTRIC LINES ESB Code 9803203 overhead 23/11/04 2:28 PM Page 2 overhead 23/11/04 2:28 PM Page 3 Page 1 of 20

More information

This document is meant to be a starting point for any company wanting to implement the safety passport scheme for their contractors on site.

This document is meant to be a starting point for any company wanting to implement the safety passport scheme for their contractors on site. Introduction This document is meant to be a starting point for any company wanting to implement the safety passport scheme for their contractors on site. It was put together by members of the Food & Drink

More information

GENERAL GUIDE FOR WORKPLACE TRAFFIC MANAGEMENT

GENERAL GUIDE FOR WORKPLACE TRAFFIC MANAGEMENT 1 This General Guide provides information on how to manage traffic risks at a workplace. It is supported by specific guidance material on traffic management for shopping centres, construction workplaces,

More information

Fire Alarm system Installation Guide

Fire Alarm system Installation Guide Fire Alarm system Installation Guide Fire Alarm System Categories Systems designed for Protection of Property only, fall into two classifications P1 or P2. but a manual system is also needed, then this

More information

Example risk assessment for cold storage warehousing

Example risk assessment for cold storage warehousing Example risk assessment for cold storage warehousing Setting the scene Frozen Foods Ltd provide cold storage and distribution facilities (at temperatures between -18 and -30 C) at three locations. They

More information

Risk Assessment / Safety Checklist

Risk Assessment / Safety Checklist Risk Assessment / Safety Checklist For Events USC has a duty to provide a safe and healthy environment for those visiting USC to the extent that it is reasonably practical. To ensure USC provides a safe

More information

Federation of Piling Specialists

Federation of Piling Specialists Federation of Piling Specialists COMPANY NAME CONTRACT NAME TENDER REF SCHEDULE OF ATTENDANCES AND FACILITIES TO BE PROVIDED BY THE CLIENT TO A STEEL SHEET PILING SPECIALIST For the purposes of this document

More information

Abu Dhabi EHSMS Regulatory Framework (AD EHSMS RF)

Abu Dhabi EHSMS Regulatory Framework (AD EHSMS RF) Abu Dhabi EHSMS Regulatory Framework (AD EHSMS RF) Technical Guideline Audit and Inspection Version 2.0 February 2012 Table of Contents 1. Introduction... 3 2. Definitions... 3 3. Internal Audit... 3 3.1

More information

LT McGuinness Site 10 Development, Wellington Waterfront. Construction Traffic Management Plan. 7 October 2014

LT McGuinness Site 10 Development, Wellington Waterfront. Construction Traffic Management Plan. 7 October 2014 LT McGuinness Site 10 Development, Wellington Waterfront Construction Traffic Management Plan 7 October 2014 TDG Ref: 12950 141007 ltm ctmp final report.docx LT McGuinness Site 10 Development, Wellington

More information

Unit Title: Unit purpose and aim

Unit Title: Unit purpose and aim Unit Title: Preparing and Operating Sideloader Forklifts to Lift and Transfer Loads in the Workplace Level: 2 Credit value: 16 Guided learning hours: 53 Unit expiry date: 31/10/2014 Unit purpose and aim

More information

Caravan Parks and Camping Sites. Flood Evacuation Plan Guidance for owners and operators of sites in Kent

Caravan Parks and Camping Sites. Flood Evacuation Plan Guidance for owners and operators of sites in Kent Caravan Parks and Camping Sites Flood Evacuation Plan Guidance for owners and operators of sites in Kent Prepared by the Kent Resilience Team Telephone: 01622 212409 E-mail@ [email protected] Version

More information

ENVIRONMENTAL ASPECTS REGISTER (ISO 14001)

ENVIRONMENTAL ASPECTS REGISTER (ISO 14001) ENVIRONMENTAL ASPECTS REGISTER (ISO 14001) 1. Scope The scope of this Environmental Aspects Register covers the following operational areas: Aberdeen Region (A); Cumbernauld Region (C); Warrington Region

More information

WORKING IN CONFINED SPACES GUIDELINES

WORKING IN CONFINED SPACES GUIDELINES WORKING IN CONFINED SPACES GUIDELINES Contents 1 Introduction... 2 2 Scope... 2 3 Definitions... 2 4 Responsibilities... 3 4.1 Permit Authoriser... 3 4.2 Permit Receiver... 3 4.3 Responsible UOW Officer...

More information

This document aims to inform developers and architects of Waste and Recycling Service requirements in the London Borough of Hounslow.

This document aims to inform developers and architects of Waste and Recycling Service requirements in the London Borough of Hounslow. GUIDANCE FOR PLANNING APPLICATIONS: RECYCLING & NON RECYCLING PROVISION FOR NEW DEVELOPMENTS WITHIN THE LONDON BOROUGH OF HOUNSLOW FOR RESIDENTIAL & COMMERCIAL SITES This document aims to inform developers

More information

Demolition Works Measures for Public Safety

Demolition Works Measures for Public Safety Re-issued under new categorization in August 2009 as Practice Note for Authorized Persons, Registered Structural Engineers and Registered Geotechnical Engineers APP-21 Buildings Department Practice Note

More information

APPLICATION FOR PLANNING PERMISSION FOR A SOIL TREATMENT FACILITY AT KINGS CLIFFE LANDFILL SITE, STAMFORD, NORTHAMPTONSHIRE

APPLICATION FOR PLANNING PERMISSION FOR A SOIL TREATMENT FACILITY AT KINGS CLIFFE LANDFILL SITE, STAMFORD, NORTHAMPTONSHIRE APPLICATION FOR PLANNING PERMISSION FOR A SOIL TREATMENT FACILITY AT KINGS CLIFFE LANDFILL SITE, STAMFORD, NORTHAMPTONSHIRE DESIGN AND ACCESS STATEMENT Report Reference: AU/KC/SPH/1449/01/D&A/FIN Baddesley

More information

SBR FIRE RISK ASSESSMENT

SBR FIRE RISK ASSESSMENT SBR FIRE RISK ASSESSMENT Report of audit and inspection Premises Details Occupier Premises Address Premises Description Times premises are in use Use and maximum no. people present The British School of

More information

HEALTH AND SAFETY POLICY LEWIS & RABY ENGINEERS LTD

HEALTH AND SAFETY POLICY LEWIS & RABY ENGINEERS LTD HEALTH AND SAFETY POLICY LEWIS & RABY ENGINEERS LTD Birchall Road Knowsley Industrial Estate Liverpool L33 7TG TABLE OF CONTENTS STATEMENT OF SAFETY POLICY... 3 STATEMENT OF INTENT... 4 HEALTH & SAFETY

More information

Excavation & Trenching Procedure

Excavation & Trenching Procedure Excavation & Trenching 1. Overview The will ensure, as far as is reasonably practicable, that the conduct of work relating to excavation and trenching will not be harmful to the health and safety of employees

More information

2. Permit to Establish or Alter a Memorial or Place of Interment

2. Permit to Establish or Alter a Memorial or Place of Interment Melbourne Chevra Kadisha Cemeteries Trust Site Requirements Registration 1. Monumental mason master registration Prior to lodging any work requests with MCKCT, you will need to be registered to work within

More information

RAVENSCOTE JUNIOR SCHOOL. Security POLICY. Headteacher

RAVENSCOTE JUNIOR SCHOOL. Security POLICY. Headteacher RAVENSCOTE JUNIOR SCHOOL Security POLICY 2015 Date of Approval Date of Review Signed Mr D Harris Signed Mrs J. Brill Headteacher Chair of Governors Ravenscote Junior School Security Policy At Ravenscote

More information

SMS0045 Construction Health and Safety Policy and Procedures

SMS0045 Construction Health and Safety Policy and Procedures SMS0045 Construction Health and Safety Policy and Procedures March 2015 Version 8 Please note that for projects utilising a CDM Co-ordinator under the transitional arrangements of CDM 2015 (between 6 April

More information

WORKING AT HEIGHT GUIDELINES. Version II

WORKING AT HEIGHT GUIDELINES. Version II WORKING AT HEIGHT GUIDELINES Version II 21 st September 2011 WORKING AT HEIGHT GUIDELINES EXECUTIVE SUMMARY Working at height is where an individual is carrying out work in any place in the course of obtaining

More information

Merton Parking Service CCTV Enforcement Manual

Merton Parking Service CCTV Enforcement Manual Merton Parking Service CCTV Enforcement Manual Version 1.3 April 2013 Introduction Legislation Data protection Health & Safety CCCTV camera equipment Mobile CCTV vehicles CCTV control room CCTV evidence

More information

Whistler Village Construction Management Strategy

Whistler Village Construction Management Strategy Whistler Village Construction Management Strategy Purpose: To mitigate the impacts of construction activity on the Whistler Village resort experience and on Village businesses and property owners. Objectives:

More information

Risk Management Guidelines

Risk Management Guidelines Fire Prevention on Construction Sites The Joint Code of Practice on the Protection from Fire of Construction Sites and Buildings Undergoing Renovation Introduction In response to increasing numbers and

More information

Proposed (Concrete Cutting And Drilling) Environmental Management Plan

Proposed (Concrete Cutting And Drilling) Environmental Management Plan SAMPLE ENVIRONMENTAL MANAGEMENT PLAN This EMP is designed for (Concrete Cutting and drilling), however you may insert your business activities with only minor changes needed. This EMP should become part

More information