Overview of the 500MW EirGrid East-West Interconnector, considering System Design and Execution-Phase Issues



Similar documents
HV Submarine Cable Systems Design, Testing and Installation

Submarine Power Cables. State-of-the-art production facility, more than 100 years of experience and reference installations around the world.

factsheet High Voltage Direct Current electricity technical information

Magnus Callavik, ABB Power Systems, HVDC, Västerås, Sweden Phone: +46(0)

E-Highway2050 WP3 workshop April 15 th, 2014 Brussels

HVDC Light Cables. Submarine and land power cables

PB POWER ISLAND OF IRELAND CAVAN-TYRONE AND MEATH-CAVAN 400KV PROJECTS PRELIMINARY BRIEFING NOTE OVERHEAD AND UNDERGROUND ENERGY TRANSMISSION OPTIONS

HVDC Technology for Large Scale Offshore Wind Connections

Offshore Wind China 2010 Bergen, 15th March Olivier Angoulevant Nexans Norway AS

2012 San Francisco Colloquium

Brochure Introducing HVDC

Offshore Wind. IEEE Boston PES - November 16, 2010

An Introduction to High Voltage Direct Current (HVDC) Underground Cables

Viking Link Interconnector

factsheet High Voltage Direct Current Electricity technical information

Curriculum Vitae Fredrik Rüter 1 December 2014

Offshore Work Packages

Introduction to The Trans Bay Cable Project

Konti Skan Replacement of Cable 1

Recent Siemens HVDC Activities Yuriy Kazachkov Siemens PTI

HVDC Light, a tool for electric power transmission to distant loads

Summary of Electric Transmission Assessment Report

2012 San Francisco Colloquium

POWER TRANSMISSION FROM OFFSHORE WIND FARMS

HVDC-VSC: transmission technology of the future

Voltage Source HVDC Overview Mike Barnes Tony Beddard

Optimization of the coupled grid connection of offshore wind farms

Feasibility Study of Deep Water Power Cable Systems. Enrico Colombo CESI S.p.A

8 Strait of Belle Isle Marine Cable Crossing

HVDC Light & SVC Light Reference list

Electricity market drivers

NSW Submarine Power. Cables for the future, delivered today.

THE NEPTUNE REGIONAL TRANSMISSION SYSTEM 500 kv HVDC PROJECT

Electrical Considerations for HVDC Transmission Lines. Joe Mooney, PE

Undergrounding high voltage electricity transmission. The technical issues

HVDC Light It s time to connect

Triton Knoll Offshore Wind Farm Limited Electrical System. Outline Traffic Management Plan

CCI Cable Consulting International Ltd PO Box 1, Sevenoaks TN14 7EN United Kingdom

CHAPTER VIII LINE PLANT SYSTEM COMMUNICATION THROUGH RE CABLE

Grid connection of near shore wind farms

High Voltage Direct Current Transmission

Network Interconnection of Offshore Wind

Oahu Wind Integration and Transmission Study (OWITS) Hawaiian Islands Transmission Interconnection Project

Control Development and Modeling for Flexible DC Grids in Modelica

NSW Submarine Power. Cables for the future, delivered today

HVDC Light and development of Voltage Source Converters

OFFSHORE WIND FARM ELECTRICAL CONNECTION OPTIONS. W.Grainger 1 and N.Jenkins 2 SYNOPSIS

Trends und Innovationen für ein Energiesystem der Zukunft Prof. Dr. Michael Weinhold, CTO Energy Management Division, Siemens AG Fraunhofer ISE,

Project description. Power Electronics for Reliable and Energy efficient Renewable Energy Systems

Cost Benefit Methodology for Optimal Design of Offshore Transmission Systems

Smart Grid and Renewable Energy Grid Integration. Jian Sun, Professor and Director Department of ECSE & Center for Future Energy Systems

ESB Networks Response. ERGEG Consultation. Voltage Quality Regulation in Europe

AORC Technical meeting 2014

Developing Ocean Energy in Ireland. Belmullet Wave Energy Test Site

SHE Transmission. 2015_10_30 Transmission Losses Strategy Rev 2.0 October 2015

A Deeper Insight into Fault Location on Long Submarine Power Cables

Dynamic Reactive Compensation MV STATCOM

Renewable Energy Grid Integration

SUPPLIERS INFORMATION SESSIONS MARITIME LINK PROJECT. Contract for Submarine Cable Design, Supply and. Contract No. E11-18

Cable Consulting International

HVDC. A firewall against disturbances in high-voltage grids. Lennart Carlsson

Integrated Development and Assessment of New Thermoplastic High Voltage Power Cable Systems

Current valve. for AC 24 V pulse/pause control of electrical loads up to 30 kw

Babcock & Brown. Trans Bay Cable Project. Presentation To California Energy Commission Transmission Workshop. August 23, 2004

and vice versa. This conversion is the key challenge for HVDC transmission and the HVDC story can be divided

Topics. HVDC Fundamentals

A Live Black-start Capability test of a Voltage Source HVDC Converter

HVDC PLUS and SVC PLUS: Reliable and Cost-effective Power Transmission Solutions with Modular Multilevel Converters

CO-ORDINATION OF PARALLEL AC-DC SYSTEMS FOR OPTIMUM PERFORMANCE

Product brochure Multi Functional Switchgear PASS M kv Flexible and compact switchgear solutions for windfarms

Transmission technologies for collective offshore wind farm connections

EuroAsia Interconnector Project Submarine power cable

LIPA. The. Long Island Power Authority links to the PJM Interconnection with an undersea/underground HVDC link. 20

Estimation of electrical losses in Network Rail Electrification Systems

Transmissão em Corrente Contínua

Gulf Cable & Electrical Ind. Co.

Offshore Wind OPERATIONS & MAINTENANCE. A National Renewables Infrastructure Plan Stage 2 Information Paper

Survey of Offshore Wind Farm Project in EU and Their Connecting Grid Systems

environment briefing02

Turnkey cable solutions to better deploy your windfarm infrastructure

Pipelines and seabed intervention

TRANSMISSION OPTIONS FOR OFFSHORE WIND FARMS IN THE UNITED STATES

ABB PSPS Erich Steinmann; Generator control-2013

INTRODUCTION TO HARMONIC ASSESSMENT IN POWER SYSTEMS

JLT Specialty Limited is a member of the Jardine Lloyd Thompson Group of companies. Jardine Lloyd Thompson Group plc is an international group of

Transmissão em Corrente Contínua em Ultra-Alta Tensão

London Array Off-Shore Wind Farm

XLPE PRODUCTION PLANT FOR THIRUVALLA UNIT OF TRACO CABLE LTD

uhvnet Universities High Voltage Network

SOUTHERN MARYLAND ELECTRIC COOPERATIVE, INC. HUGHESVILLE, MD

Polish Offshore Grid SA

The electrical energy produced at the gen

Three Gorges - Changzhou HVDC : Ready to Bring Bulk Power to East

Removal of EP SP High Voltage Cable

DELHI METRO RAIL CORPORATION LIMITED. (A Joint Venture of Govt. of India & GNCTD) MASS RAPID TRANSPORT SYSTEM PHASE III. Contract: - CE -16 VOLUME-6

Offshore wind farm electrical engineering (when considering the operation of array cabling at voltages of 66kV)

Network Standard Advice No. 1420C 9/6/2011

A Post Bipole III Concepts Review

Transcription:

Overview of the 500MW EirGrid East-West Interconnector, considering System Design and Execution-Phase Issues J Egan, P O Rourke EirGrid Plc, Republic of Ireland john.egan@eirgrid.com paul.o rouke@eirgrid.com Dr R Sellick, P Tomlinson, B Johnson ABB Ltd, United Kingdom robert.sellick@gb.abb.com pete.tomlinson@gb.abb.com bernard.johnson@gb.abb.com S Svensson ABB AB, Sweden svante.g.svensson@se.abb.com Abstract- The EirGrid East-West Interconnector between Ireland and Wales, which uses ABB s HVDC Light Voltage- Sourced Converter (VSC) technology, is to date the world s most powerful VSC scheme, it is the first commercial VSC project connected to Ireland, and it is the first HVDC Light scheme to use ±200kV cables. Ireland has plans to expand wind power generation and the link will facilitate the addition of renewables and provide the possibility to export or import energy to / from the UK market. The new link also enhances security of supply in the Irish grid, allows both Ireland and the UK access to more competition and provides black-start capabilities. This paper presents an overview of the EirGrid East-West Interconnector project, considering the Converter topology, System Design, Overview of the VSC technology used, and some of the significant execution-phase site works issues. Index Terms-- HVDC Light, VSC, Cable Installation HVDC technology was selected due to the overall cable length. HVDC Light in particular was used due to the controllability offered. Additional benefits provided by the HVDC Light technology are: black start, a way of restoring power after a blackout without the aid of external energy sources active AC voltage support Benefits The EirGrid East-West Interconnector to the UK is vital for Ireland. It helps ensure that Ireland is able to access more energy into the future, as follows [2]: I. INTRODUCTION Background The 500 MW EirGrid East-West Interconnector HVDC Light transmission system connects the grids of Ireland and Wales. This is the first HVDC Light project to use ±200 kv cables and the link is about 260 km long [1]. ABB was responsible for system engineering including design, supply and installation of the converter stations and the sea and land cables. Ireland plans to expand wind power generation and the link facilitates development of renewable energy and allows for the export and import of energy between Ireland and the UK market. The link also enhances security of supply of the Irish grid and allows both Ireland and the UK access to more competition [2]. Fig. 1. EWIC Project

Energy security for a growing population Energy security means making sure there is enough highquality power to cater for a growing population that requires more and more electricity. Promotes competition in the electricity sector By connecting to the UK grid, Ireland has access to power from right across Europe. This will create a more competitive market and help reduce the price of electricity for consumers. Encourages the growth of renewable energy in Ireland Ireland can increase its reliability on wind generated electricity. This is because additional supplies can be imported as a back-up for wind power, to be used during calm days in Ireland. Likewise, when Ireland has excess electricity (including wind generated electricity) it can be exported to the UK. Allows Irish companies to trade power with the UK The interconnector is bidirectional, and it can import or export energy. This allows Irish energy companies to sell energy to the British market. Likewise energy can be purchased from the UK when it is cheaper or if there is insufficient generation in Ireland. Common System Topologies II. CONVERTER TOPOLOGY A schematic diagram of some common system topologies is shown in Fig. 2. These are briefly described below [4]: Symmetric Monopole: A single converter with mid-point ground between positive and negative voltage polarities. Asymmetric Monopole: A single converter with grounded neutral. This could be with either ground or metallic return. Bipole: A converter comprised of two monopoles. This could be with either ground or metallic neutral. Series Bridge Scheme: A converter comprised of monopoles in series. This could be with either ground or metallic return. Multi-Terminal: Multiple converters (more than two) connected to a DC network. The EirGrid East-West Interconnector is configured as a symmetric monopole. The main system design parameters are shown in Section III below. Comparison of VSC and LCC Technologies A brief summary of the differences between VSC and LCC technology is presented in Table 1 [3, 4, 5]. Table 1 Comparison of VSC and LCC Technology Technology Semiconductor (control) HVDC Classic (LCC) Thyristor (turn on only) HVDC Light (VSC) IGBT (turn on / off) Power Control Active only Active / reactive AC Filters Yes No Minimum Short- Circuit Ratio (SCR) > 2 0 Black Start Capability No Yes Fig. 2. Common System Topologies

VSC-HVDC was chosen for the EirGrid East-West Interconnector after a full evaluation process by EirGrid of available technologies. VSC-HVDC allows controllability, black-start and active / reactive power support, in addition to resolving the cable capacitance issue if the system was designed using AC. III. SYSTEM DESIGN The main technical parameters of the scheme are as follows: Connection point (Ireland) Woodland Sea cable landing: Rush North Beach, Co. Dublin Connection point (Wales) Deeside Sea cable landing: Barkby Beach, North Wales Operator: Technology EirGrid, Ireland Transmission capacity: 500 MW DC voltage: AC voltage: AC frequency: HVDC Light by ABB ± 200 kv 400 kv (both ends) 50Hz (both ends) DC Cable route length: 261.9 km parallel cables Submarine: 187.7 km Ireland: 44.3 km Wales: 29.9 km AC Cable route length: Ireland: Wales: 0.5 km 2.8 km The HVDC cable details are shown in Table 2. Table 2 Featured HVDC Cables Featured Cable Submarine Land Insulation Extruded polymer Extruded polymer Conductor area 1650mm 2 2210mm 2 Conductor material Copper Aluminium Armouring Steel - Diameter 117mm 107mm Mass 39 kg/m 12 kg/m The oil-free HVDC Light cables minimize the environmental impact on sea and on land. A typical flow graph of the HVDC link is shown in Fig. 3. IV. SITE WORKS AND CONSTRUCTION Site Layout A plan view of the Woodland Converter Station is shown in Fig. 4. The overall dimensions are approximately 110m x 190m with the main areas including the incoming AC connections and filter area, transformers and converter buildings. The Shotton converter station portion is identical, but the incoming AC substation is located at Deeside, approximately 3km away. Site Works Programme The key dates in the execution phase were as follows: Fig. 3. Typical Flow Graph HVDC Cable Ducting commences 11/2009 Construction Phase Confirmation 04/03/2010 Converter Station Civil Works Start 03/2011 Transformers In Position 12/2011 Main Equipment Installation 05/2012 Sea Cable Laying Complete 11/05/2012 Sea Jointing Complete 30/05/2012 HV Cable Test 06/2012

Fig. 4. Woodland Converter Station Land Cable Installation Issues For the cable installation there were some significant issues, notably the following: River Dee Horizontal Directional Drill (HDD) Railway Crossing HDD Transition Joint HDD Barkby Beach Proximity to 400kV Deeside National Grid Substation Seabed Conditions The marine route presented an extremely challenging mix of seabed conditions that required various cable installation techniques. - Irish shore end: A rock reef at the Irish shore required a 500m trench to be cut through it by heavy rock cutting equipment operated from jack-up barges. HDPE ducts were then installed in the trench before carefully backfilling the trench and winching the cables through the ducts from the land side. - Shallower waters: A barge with a vertical injector tool successfully laid & buried the cables in the shallower sandy / cobbles / clay seabed at each side. - Deep waters: New build cable laying vessel, the Lewek Connector, with the biggest cable capacity of any ship in existence, on its maiden cable laying project, laid the Challenges: Clear & challenging deadline Variable & very stiff seabed Permitting requirements Manufacturing capacity Cable jointing Crossings of existing utilities Weather Table 3 Offshore Cable Challenges Solutions: Multiple vessels operating simultaneously on different parts of the route. New build high capacity cable laying ship utilised. Works programmed early to allow for slippage. Mix of burial techniques utilised. Trenching & Jetting equipment on same vessel allowing flexibility. Permitting managed very proactively by Client and Contractor. Cable manufacture and cable laying carefully co-ordinated. Dedicated jointing vessel utilised Early engagement with existing asset owners followed by careful execution of the works resulted in all five crossings taking place successfully. Weather in 2011 was a particular issue. Robust vessel selection, careful planning and use of autumn / winter seasons as a contingency were all employed to maintain works on programme.

cables in the deepest section in one continual length. These cables were then buried using water jetting in sandier areas, and a mix of chain cutting and rock placement techniques in heavily compacted glacial clay, boulder and bedrock areas. Marine Installation Programming Issues In order to achieve an on time delivery for a most demanding work scope, challenges were carefully addressed in advance by both Client & Contractor working closely together. Refer to Table 3. Fig. 5. 2-Level Circuit Topology Civil Works Aspects The basic electromechanical designs at Woodland and Shotton Converter Stations are identical due to the similar electrical rating at each converter. It was elected to use an integrated design and construction approach with a single Civil Designer, to ensure commonality in the solutions that were designed and consistency in the materials that were selected to house the HV equipment. Fig. 6. 2-Level Switching Ground conditions were different for each converter. The Woodland site had a challenging topography and some issues with groundwater, typical of a greenfield site in this part of Ireland, where ground bearing foundations were selected to support the building loads. Shotton was a brownfield site, containing contaminated made ground associated with a former gas works, over the older reclaimed sands from the Dee estuary. These aspects, together with predominantly soft ground over the site, lead to the selection of driven piles that significantly reduced spoil generation. Materials that were excavated for the pile caps and other parts of the foundations were successfully retained in a corner of the site thus significantly reducing the amount of material taken to landfill and saving many vehicle movements on public roads. V. VOLTAGE-SOURCED CONVERTER (VSC) TECHNOLOGY Fig. 7. CTL Circuit Topology Two-Level Converter Technology For the VSC-HVDC scheme at the EirGrid East-West Interconnector project, the technology uses HVDC Light Generation 3, which is a 2-level converter. The 2-level converter topology is shown schematically in Fig. 5, with switching pattern as shown in Fig. 6. Continuous Development of Technology The VSC-HVDC technology is under continual development and improvement, and has been updated to a more modern design subsequent to the EirGrid East-West Interconnector project. Fig. 8. CTL Switching By contrast, the latest version of the technology (Generation 4) uses a cascaded two-level (CTL) design. The CTL converter topology is shown schematically in Fig. 7, with switching pattern as shown in Fig. 8.

VI. SUMMARY AND CONCLUSIONS The EirGrid East-West Interconnector represents a significant milestone in the development of the VSC technology. It is the first project to use ±200kV cables, and has the world s longest HVDC cable section without a joint. At commissioning the 500MW rating made the EirGrid East- West Interconnector project the world s most powerful VSC converter. The converter is also the first commercial VSC-HVDC project connected to both the United Kingdom and to Ireland. VII. ACKNOWLEDGEMENTS The authors wish to thank EirGrid for permission to present the project, and also ABB colleagues in Stone, UK and Ludvika, Sweden for their support in writing this paper, especially Chris Barber for assistance with the diagrams. VIII. REFERENCES [1] East-West Interconnector Connecting Ireland and Britain, http://www.abb.com/industries/ap/db0003db004333/a60fb5e59414e817c125 774a002f365b.aspx [2] http://www.eirgridprojects.com/projects/east-westinterconnector / overview [3] List of HVDC Projects, Wikipedia, http://en. wikipedia.org /wiki/list_of_hvdc_projects [4] J Arillaga, High Voltage Direct Current Transmission, 2nd Edition, The Institution of Electrical Engineers, ISBN 0 85296 941 4. [5] It s time to connect (with offshore wind supplement), Rev 6, ABB AB Grid Systems HVDC, Ludvika, Sweden, (04/2010), http://www.abb.com/hvdc IX. AUTHOR PROFILES John Egan joined EirGrid in 2009 and is currently the Senior lead project engineer for the 500MW EirGrid East- West Interconnector project. John has a degree in Electrical Engineering from University College Dublin and is an active member of the Cigre working group on HVDC commissioning. John was primarily responsible for all detailed engineering design reviews from initial design through to site works, system testing, acceptance and performance testing, Grid Code compliance in UK & Ireland for the EirGrid East-West Interconnector project. Paul O Rourke joined EirGrid in 2008 and was the Marine Project Manager for almost 5 years, before being appointed to the role of Project Director for the final months of the project. In his role as Marine Project Manager, he lead the project from route selection & permitting right through to procurement of EPC Contractor and supervision of the marine works. Paul has a Bachelor s Degree in Electrical Engineering from University College Dublin, a Master s Degree in Engineering from the Dublin Institute of Technology, and prior to working for EirGrid worked for Siemens Energy in the UK. Dr Rob Sellick joined ABB in 2011 and is currently Engineering Design Manager for Grid Systems. Rob is a Chartered Engineer, has a PhD in Electrical Engineering from the University of Cape Town and is a Member of the Institution of Engineering and Technology. Rob joined ABB as Lead Plant Systems Engineer, bringing 15 years of experience in AC and HVDC substations. He is currently involved in the engineering design of UK transmission system reinforcements and HVDC interconnectors. Bernard Johnson Bernard Johnson joined ABB in 2003, and has been working in the Power systems business for almost 20 years. His projects experience has been gained from working with prestigious clients including Jaguar Cars, cutting edge Pathology systems, EMU Traction systems for the Channel Tunnel Trains, as well as large coal and gas power station EPC contracts. More recently Bernard was the Planning Manager at the inception of the National Grid Electrical Alliance, and is now Planning Manager for ABB Grid Systems UK. Pete Tomlinson has been with ABB since 2006 and is presently Civil Construction Manager for Grid Systems, and also has over 5 years experience in the civil aspects of AC substation design and construction. Holding an MSc in Civil Engineering Design and Management, Peter has worked extensively in both Civil Design and Site Construction both in the UK and abroad over the last 14 years. His current focus includes informing stakeholders how to achieve well planned and innovative civil works for HVDC and Offshore Wind projects. Svante Svensson started with ABB HVDC in 1974 directly after gaining a Masters degree in Electrical Power Engineering from the Royal Technical University. He has had many different positions within the ABB s HVDC unit, but mostly as a Project Manager for projects worldwide.