Triton Knoll Offshore Wind Farm Limited Electrical System. Outline Traffic Management Plan

Size: px
Start display at page:

Download "Triton Knoll Offshore Wind Farm Limited Electrical System. Outline Traffic Management Plan"

Transcription

1 Triton Knoll Offshore Wind Farm Limited Electrical System Outline Traffic Management Plan October 2014

2

3 RWE Innogy UK Triton Knoll TMP Copyright 2014 RWE Innogy UK Ltd All pre-existing rights reserved. This document is supplied on and subject to the terms and conditions of the Contractual Agreement relating to this work, under which this document has been supplied, in particular: Confidentiality This document is confidential. Liability In preparation of this document RWE Innogy UK has made reasonable efforts to ensure that the content is accurate, up to date and complete for the purpose for which it was contracted. RWE Innogy UK makes no warranty as to the accuracy or completeness of material supplied by the client or their agent. Other than any liability on RWE Innogy UK detailed in the contracts between the parties for this work RWE Innogy UK shall have no liability for any loss, damage, injury, claim, expense, cost or other consequence arising as a result of use or reliance upon any information contained in or omitted from this document. Any persons intending to use this document should satisfy themselves as to its applicability for their intended purpose. The user of this document has the obligation to employ safe working practices for any activities referred to and to adopt specific practices appropriate to local conditions.

4 RWE Innogy UK Triton Knoll TMP CONTENTS 1. Introduction Purpose of the outline TMP Scope of outline TMP Structure of final TMP Enforcement of final TMP 3 2. Triton Knoll Electrical System Project Description Cable Route Landfall Intermediate Electrical Compound Substation Cable route construction and installation Open-cut trenching Horizontal Directional Drilling (HDD) Other Crossings Construction programme 5 3. General Principles Pre and post construction surveys Monitoring 7 4. Construction Traffic Construction access routes for HGV construction traffic Construction access route signage Site Access Timing and phasing of construction traffic Abnormal loads Pedestrian Management Temporary road closures and diversions Signage Contractors travel and parking 8

5 1. Introduction Triton Knoll Offshore Wind Farm Limited (TKOWFL) was granted development consent for the Triton Knoll array in July The array will be located approximately 33km off the Lincolnshire coast, shown in Figure 1.1. This outline Traffic Management Plan (TMP) relates to the onshore Triton Knoll Electrical System (TKES) works for the TKOWF, located within the districts of East Lindsey and Boston Borough, in the County of Lincolnshire Purpose of the outline TMP The outline TMP will set out key traffic management measures that will form the basis for discussions with Boston Borough Council, East Lindsey District Council, Lincolnshire County Council and interested members of the community regarding the approach that will be taken by TKOWFL to managing the potential impacts of construction traffic during the construction phase of the Electrical System. The final TMP will: Take into account route surveys, assessment and evaluations undertaken to date; Identify any road improvement works required; Include detailed management measures to control numbers, types and timings of vehicle movements; Identify practical and viable construction access routes; and Give consideration to noise sensitive receptors and the mitigation measures set out in the Noise and Vibration Management Scheme, a document that will form part of the Electrical System Code of Construction Practice. An updated outline TMP will be included in the Electrical System application for development consent. The draft Development Consent Order will include a requirement for a TMP to be agreed with the Local Authorities before works start on site and construction to be undertaken in accordance with the agreed TMP. The final TMP will be written in accordance with the outline TMP. The final TMP will be produced by the contractor appointed to undertake the TKES works and agreed with the relevant local authorities (Boston Borough Council, East Lindsey District Council and Lincolnshire County Council) prior to the start of relevant phases of work. TKOWFL will work with all contractors, sub-contractors and their suppliers to ensure compliance with the relevant provisions of the final TMP. These requirements will be incorporated into the construction work contracts for the onshore elements of the TKES. TKOWFL will work with the relevant Local Authorities to ensure appropriate resourcing is in place during the construction phase to monitor compliance with the provisions of the final TMP Scope of outline TMP This outline TMP relates to the onshore elements of the TKES for the proposed Triton Knoll Offshore Wind Farm (TKOWF), landward of Mean Low Water Spring. This document does not relate to offshore works seaward of Mean Low Water Springs, or any works above Mean Low Water Springs that are principally marine activities. The outline TMP sets out a series of construction vehicle management controls in one cohesive document for the onshore works and formalises commitment made to the Local Authorities and statutory consultees in the Environmental Statement Structure of final TMP The following sections set out the principles for the final TMP. Feedback on the principles set out in this document is welcomed from consultees and members of the public. Regard will be had to any feedback received in finalising the outline TMP that will be submitted as part of the application for the TKES works.

6 1.4. Enforcement of final TMP 2. Triton Knoll Electrical System Project Description The onshore elements of the TKES works comprise the following: Cable Route Up to 6 underground HVAC circuits will be laid from the landfall north of Anderby Creek, to the North of Skegness, Lincolnshire, to the National Grid substation at Bicker Fen, near Boston, Lincolnshire (approximately 60km). This route has been subject to a selection and refinement. Temporary Work Areas (TWAs) locations have been identified to allow easy access to and from the cable route. The locations of the TWAs have been chosen to minimise impact on local residents, businesses and the environment. The TWAs will be utilised to store and distribute materials required for each section of the cable route and for welfare facilities. There are a significant number of natural breaks in the cable route caused by major roads, railways, rivers and major drains hence a high number of TWAs are required. TWAs along the cable route are approximately 0.5 ha 1.5 ha. The cable corridor will be up to 60m wide. This includes space for: Fencing of the route; Cable circuit trenches; Temporary construction haul road; Temporary drainage; Separate storage of topsoil and subsoil (to retain integrity) on both outer edges of the corridor. The cables will be installed in plastic ducts laid in cable trenches. Jointing bays will be required approximately every 600m- 1,000m along the route to join lengths of cables Landfall TKOWFL has identified an area just north of Anderby Creek, Lincolnshire as the landfall area. The landfall area currently includes sections of two adjacent fields set either side of an existing privately owned raised access track. The exact location of the landfall infrastructure and associated TWA is subject to further detailed assessment, but will ultimately be sited entirely within just one of these fields. The existing access track from Roman Bank to the landfall site will be improved to allow access for construction vehicles. Up to six offshore transmission cables will come ashore at the landfall location at Anderby Creek. The offshore cables will be joined to the onshore transmission cables in underground Transition Joint Bays (TJBs). Horizontal Directional Drilling (HDD) will be utilised to install cable ducts for the cables under the sea defences to minimise disturbance, with the offshore cables pulled through the ducts to the TJBs Intermediate Electrical Compound An onshore Intermediate Electrical Compound is required approximately mid-way along the cable route, to provide system stability and improved efficiency of transmission. The location of this has been subject to consultation. The site includes space for the above ground infrastructure, drainage, landscaping, permanent and temporary access roads and a TWA Substation

7 A new onshore substation is required adjacent to the existing Bicker Fen substation. The location of this has been subject to consultation. The site includes space for the above ground infrastructure, drainage, landscaping, permanent and temporary access roads and a TWA Cable route construction and installation A number of methods will be used for construction and installation of the cables. Prior to construction a crossing schedule will be produced which will identify every crossing on the cable route and give the preferred crossing methodology. A detailed ditch survey will be carried out prior to construction. Method Statements will be produced for each crossing method used. A draft crossing schedule can be found in Volume 2, Annex 5.1 of the Triton Knoll Electrical System Preliminary Environmental Information. The following methods will principally be used for cable route construction and installation: Open-cut trenching Open-cut trenching will be used to install the majority of the cable in relatively unconstrained areas. A trench will be excavated for each cable circuit, with ducts installed prior to the trench being back-filled. Cables will be pulled through the ducts from jointing pits Horizontal Directional Drilling (HDD) HDD will be used at the landfall to minimise impacts on sea defences and at crossings of railways, major drainage ditches and rivers as well as all public highways. The detailed methodology for each crossing will be determined following pre-construction surveys and consulted on with the relevant authorities. Table 2.1: Relevant Authorities for HDD sites Crossing Type Sea Defences Railways Watercourses Highways Relevant Authority Environment Agency Lincolnshire County Council Network Rail Environment Agency Internal Drainage Boards Lincolnshire County Council Highways Authority Other Crossings Where HDD is not used for the crossings of private roads, drains, ditches and other obstacles, a pre-construction survey will be undertaken to determine the methodology to be used. Ditches may be flumed and cable ducts installed underneath the flumed ditch. Private roads may be open cut, with provision made for access where required.

8 2.3. Construction programme Construction periods for the various elements of the TKES are shown in Table 2-1.

9 Table 2-1 Triton Knoll Electrical System construction periods Triton Knoll Electrical System Component Landfall Onshore cable circuits Intermediate Electrical Compound Substation Pre-construction and Construction Work Up to 13.5 months of activity over a 36 month period Up to 42 months of activity over a 54 month period Up to 46 months of activity over a 54 month period Up to 65 months of activity over a 71 month period Works Included This covers all associated works including: Site investigation works, pre-construction archaeological and ecological surveys and mitigation; Site mobilisation including erection of fencing, and welfare and plant delivery; Earthworks and drainage works; Transition joint bay construction and HDD bores and duct installation Cable pulling, cable jointing and commissioning; and Demobilisation, including removal of temporary work area. This covers all associated works including: Site investigation works, pre-construction archaeological and ecological surveys and mitigation; Site mobilisation, fencing and welfare and plant delivery; Earthworks and drainage works; HDD, duct installation, cable pulling, joint bay construction, cable jointing and commissioning; and Demobilisation and landscaping. This covers all associated works including: Site investigation works, pre-construction archaeological and ecological surveys and mitigation; Site mobilisation, fencing and welfare and plant delivery; Earthworks and drainage works; Installation of electrical infrastructure, commissioning; and Demobilisation including site restoration. This covers all associated works including: Site investigation works, pre-construction archaeological and ecological surveys and mitigation; Site mobilisation, fencing and welfare and plant delivery; Earthworks and drainage works; Installation of electrical infrastructure, commissioning; and Demobilisation and landscaping. 3. General Principles 3.1. Pre and post construction surveys Prior to the start, and following completion, of the construction works, road condition surveys will be undertaken and agreed with the Highways Authority. These surveys will inform any works that may be required to rectify specific damage to the road network as a direct result of construction work

10 The pre-construction survey will be used to identify road surface irregularities which will require remediation to mitigate vibration impacts for the Noise and Vibration Management Scheme Monitoring As part of the ongoing process for ensuring that impacts due to the construction traffic are minimised, a monitoring strategy will be established between the TKWF and the relevant local authorities. Each contractor will be required to comply with the final TMP and the TK Environmental Clerk of Works will be required to monitor compliance and report breaches. In addition, a public hotline will be made available to members of the public. The hotline number will be published within the local newspaper for the area, so that the general public can voice their queries or complaints. 4. Construction Traffic 4.1. Construction access routes for HGV construction traffic The routes for HGV construction traffic to construction access points, incorporating any specific routes or locations to avoid and any temporary speed limit orders, will be agreed with the relevant Local Authority and set out in the final TMP. HGV traffic will use A roads wherever possible with B roads and minor roads used primarily to access the TWAs. Certain exclusions will apply in agreement with the highway authority in order to avoid congested or sensitive locations. This will include: Avoiding substation traffic passing through Boston; Using the A16 rather than the A52 around Skegness; and Using the IEC haul road to avoid Orby. All delivery contractors and construction staff will be instructed to use the agreed construction access routes, with compliance with the final TMP being a condition of supply contracts. A log of regular drivers will be maintained, including records of agreements with organisations and the drivers to demonstrate their understanding of the prescribed access route Construction access route signage Construction access routes will have temporary signs posted along the proposed routes, with the nature and placement of signage to be agreed with the relevant Local Authority or the Highways Authority. Signage will also be placed at the exit of construction site access points to instruct construction traffic to follow the designated route. TKOWFL will review the environmental performance of the main construction contractors as part of the tender selection process Site Access The site access points will be agreed with the relevant Local Authority and set out in the final TMP. The contractors appointed to undertake the TKES works will submit the detailed design and specifications for the site access locations to the relevant authorities prior to works commencing on site. All TWA s will have sufficient areas available at all times for all vehicles to enter in a forward gear and to be accepted directly.

11 4.4. Timing and phasing of construction traffic It is proposed that the permitted delivery hours are the same as the construction working times. Construction working hours are set as: Monday Sunday Exceptions will be approved in writing by the relevant local authority. Phasing will be used to reduce peak daily vehicle movements by timing activities and deliveries to avoid cumulative effects for different parts of the TKES construction and where possible limit the cumulative effects with other developments. Community events and other factors will also be considered in the planning of major deliveries Abnormal loads The construction of the TKES will require the delivery of a number of abnormal loads. These deliveries will be small in number; each delivery will be planned in advance, escorted and managed such that any impacts are minimised. Such arrangements will be secured through the final Traffic Management Plan Pedestrian Management TKOWFL will maintain access for pedestrians wherever possible. Specific locations where pedestrian management will be required will be identified in the final TMP and where possible location specific management methods will be confirmed Temporary road closures and diversions TKOWFL has identified roads that may need to be temporarily closed and any diversions needed as a result of the TKES works. These will be identified in the development consent order submitted as part of the application following discussion with the relevant authorities Signage Any temporary signage required at access points and other works will be agreed with the relevant authority Contractors travel and parking The TMP will include provisions relating to contractors travel and parking. These provisions will be agreed with the Highways Authority to manage construction workers' traffic. The construction site will be in operation from 07:00 to 19:00. Construction workers will typically arrive before 07:00 and leave after 19:00. Therefore, personnel movements are typically limited to being outside of the traditional peak hours of 08:00-09:00 and 17:00-18:00. Provision for car parking for construction staff and visitors will be provided within the TWA and no car parking will take place on any other area outside of the site. Temporary car parking arrangements will be made at the start of the enabling works and following the creation of the TWAs, car parking will take place within a designated part of the TWA. Car parking will not be allowed on the site access road or any other areas that could cause delays for traffic turning into the site.

12 Figure 1.1: Site location of Triton Knoll Offshore Wind Farm.

13

TRITON KNOLL ELECTRICAL SYSTEM CONSULTATION: QUESTIONNAIRE

TRITON KNOLL ELECTRICAL SYSTEM CONSULTATION: QUESTIONNAIRE RWE Innogy UK TRITON KNOLL ELECTRICAL SYSTEM CONSULTATION: QUESTIONNAIRE The Planning Act 2008 requires developers to undertake pre-application consultation before submitting an application for a Development

More information

Galloper Wind Farm Project. Traffic Management Plan May 2013 Draft v1 Document Reference GWF/TMP/100513. Galloper Wind Farm Limited

Galloper Wind Farm Project. Traffic Management Plan May 2013 Draft v1 Document Reference GWF/TMP/100513. Galloper Wind Farm Limited Galloper Wind Farm Project Traffic Management Plan May 2013 Draft v1 Document Reference GWF/TMP/100513 Galloper Wind Farm Limited Document title Galloper Wind Farm Project Traffic Management Plan Status

More information

Gas to the West INFORMATION LEAFLET. gastothewest.com. info@gastothewest.com. www

Gas to the West INFORMATION LEAFLET. gastothewest.com. info@gastothewest.com. www Gas to the West INFORMATION LEAFLET 0800 975 2322 gastothewest.com @ info@gastothewest.com Gas to the West 1. INTRODUCTION This Gas to the West Project is a major energy infrastructure project to extend

More information

Alphington sewer replacement

Alphington sewer replacement Alphington sewer replacement Frequently asked questions We understand you might have some questions for us so here are a few to provide you with more information. You are also welcome to call us on 1800

More information

Construction Traffic Management Plan

Construction Traffic Management Plan Introduction This (CTMP) has been prepared in order to discharge Condition 20 of planning permission ref 07/02879/EFUL for the enabling site works associated with the wider Bath Western Riverside development.

More information

THIS PAGE INTENTIONALLY LEFT BLANK

THIS PAGE INTENTIONALLY LEFT BLANK THIS PAGE INTENTIONALLY LEFT BLANK Construction Traffic Management Plan 2 Contents 1. Introduction... 4 1.1 Conditions of Consent... 4 2. Goals of the CTMP... 6 2.1 Objectives... 6 2.2 Predicted Construction

More information

TRAFFIC MANAGEMENT PLAN

TRAFFIC MANAGEMENT PLAN TRAFFIC MANAGEMENT PLAN For: The construction and operation of a Photovoltaic (PV) Facility in Dabenoris, South Africa Prepared for: Alternative Energy Solutions (Pty) Ltd PO Box 4939 Tygervalley, South

More information

CONSTRUCTION TRAFFIC MANAGEMENT PLAN Issue 2, V5, 11/11/13

CONSTRUCTION TRAFFIC MANAGEMENT PLAN Issue 2, V5, 11/11/13 Note: Please refer to the end of this document for guidance notes about completing this form Q1. What is the full postal address of the site? Your response Q2. Planning reference and revision number (if

More information

CHAPTER 24: ENVIRONMENTAL MANAGEMENT

CHAPTER 24: ENVIRONMENTAL MANAGEMENT Central Eyre Iron Project Environmental Impact Statement CHAPTER 24: ENVIRONMENTAL MANAGEMENT CHAPTER 24 ENVIRONMENTAL MANAGEMENT COPYRIGHT Copyright Iron Road Limited, 2015 All rights reserved This document

More information

University Arms Hotel, Cambridge

University Arms Hotel, Cambridge Traffic Management Plan For University Arms Hotel, Cambridge Prepared By: James Batterbee Number: M1342 / Rev B Date: 29 th August 2014 CONTENTS: (1) INTRODUCTION (2) VEHICLE ACCESS & EGRESS AND PEDESTRIAN

More information

PROPOSED RESIDENTIAL DEVELOPMENT LAND OFF MACCLESFIELD OLD ROAD, BUXTON. Construction Management Plan

PROPOSED RESIDENTIAL DEVELOPMENT LAND OFF MACCLESFIELD OLD ROAD, BUXTON. Construction Management Plan PROPOSED RESIDENTIAL DEVELOPMENT LAND OFF MACCLESFIELD OLD ROAD, BUXTON Construction Management Plan May 2013 CONTENTS Page No: 1.0 INTRODUCTION 1 2.0 PROJECT ORGANISATION AND RESPONSIBILITIES 2 2.1 Client

More information

Traffic Management Plan - Depot Procedure

Traffic Management Plan - Depot Procedure Traffic Management Plan - Depot Procedure Date: 1/8/13 Version: TMPDPGWT001 Status: Approved 1. Purpose This procedure outlines the traffic management plan which must be followed for the Depots. 2. Scope

More information

Construction Traffic Management Plan

Construction Traffic Management Plan Construction Traffic Management Plan Proposed Additional Classroom Accommodation for Woolacombe Primary School Produced for and on behalf of Built Environments Team Devon County Council NPS South West

More information

Construction Management Statement. Introduction. Contents

Construction Management Statement. Introduction. Contents Construction Management Statement Project Name Dee Point Primary School Introduction On all Morgan Sindall projects, the safety and welfare of all is of paramount importance. This document concentrates

More information

SAN DIEGO GAS & ELECTRIC COMPANY SOUTH BAY SUBSTATION RELOCATION PROJECT TRAFFIC MANAGEMENT PLAN SEPTEMBER 2014

SAN DIEGO GAS & ELECTRIC COMPANY SOUTH BAY SUBSTATION RELOCATION PROJECT TRAFFIC MANAGEMENT PLAN SEPTEMBER 2014 SAN DIEGO GAS & ELECTRIC COMPANY SOUTH BAY SUBSTATION RELOCATION PROJECT TRAFFIC MANAGEMENT PLAN SEPTEMBER 2014 Traffic Management Plan TABLE OF CONTENTS 1 INTRODUCTION... 1 2 OBJECTIVES... 1 3 APPLICABLE

More information

1. Purpose and scope. 2. SEPA's role in hydropower and planning

1. Purpose and scope. 2. SEPA's role in hydropower and planning Page no: 1 of 10 1. Purpose and scope 1.1 The purpose of this note is to provide guidance on the approach that we will take when dealing with hydropower development management consultations. We welcome

More information

Development Management Report

Development Management Report Committee and Date Central Planning Committee 5 th April 2012 Item 13 Public Development Management Report Responsible Officer: Stuart Thomas email: stuart.thomas@shropshire.gov.uk Tel: 01743 252665 Fax:

More information

HS2 Phase One Planning Forum Highways Sub-group. Meeting #2 November 2014

HS2 Phase One Planning Forum Highways Sub-group. Meeting #2 November 2014 HS2 Phase One Planning Forum Highways Sub-group Meeting #2 November 2014 Agenda Schedules 4 part 1 Highways Accesses Schedule 16 Road traffic routes Schedule 16 Mud control measures Schedule 24 Lorry ban

More information

Undergrounding high voltage electricity transmission. The technical issues

Undergrounding high voltage electricity transmission. The technical issues Undergrounding high voltage electricity transmission The technical issues This is an interactive PDF document with clickable links from the contents to all sections and back and also to URL and email links.

More information

Construction Management Statement. Residential development at Bywell House, St Mary s Hill, Ascot

Construction Management Statement. Residential development at Bywell House, St Mary s Hill, Ascot Construction Management Statement Residential development at Bywell House, St Mary s Hill, Ascot Parking of Vehicles of Site Personnel, Operatives and Visitors Site staff, visitors to the development and

More information

Part 1 Checklist. Feasibility 2. Investigation 9. Design 18. Construction 26

Part 1 Checklist. Feasibility 2. Investigation 9. Design 18. Construction 26 Part 1 Checklist Process Page 2 9 Design 18 26 Page 1 FEASIBILITY 1. Establishment 1.1 Establishment Recognise problem, need or opportunity. Formulate goal and objectives. Prepare project charter. Obtain

More information

CONSTRUCTION SEQUENCE & PROGRAMME

CONSTRUCTION SEQUENCE & PROGRAMME CONSTRUCTION SEQUENCE & PROGRAMME 2 CONTENTS 1.0 Introduction 7 2.0 Key activities 8 2.1 Airport related activities 2.2 Construction of new roads and accesses 2.3 Earthworks zone a 2.4 Earthworks zone

More information

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND TELECOMMUNICATION CABLES IN THE VICINITY OF TRANSPORTATION FACILITIES

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND TELECOMMUNICATION CABLES IN THE VICINITY OF TRANSPORTATION FACILITIES APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND TELECOMMUNICATION CABLES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE JURISDICTION OF ALBERTA TRANSPORTATION 1.0 Application Procedures 2.0

More information

Event Planning Guidance Notes EVENT PLANNING GUIDANCE NOTES

Event Planning Guidance Notes EVENT PLANNING GUIDANCE NOTES EVENT PLANNING GUIDANCE NOTES 1 Event Planning Guidance Notes Important issues This documentation is not a full and authoritative statement of the law, statutory guidance or best practice in planning,

More information

E19: SUSTAINABLE PLACEMENT OF SURPLUS EXCAVATED MATERIAL

E19: SUSTAINABLE PLACEMENT OF SURPLUS EXCAVATED MATERIAL HIGH SPEED TWO INFORMATION PAPER E19: SUSTAINABLE PLACEMENT OF SURPLUS EXCAVATED MATERIAL This paper outlines the approach to sustainable placement of surplus excavated material for Phase One of the HS2

More information

Engineering Policy 146. Severe Weather Management Plans

Engineering Policy 146. Severe Weather Management Plans Engineering Policy 146 Severe Weather Management Plans January 2014 Contents Engineering Policy... 1 1 Policy statement... 1 2 Applicability... 1 3 Context... 1 4 Objectives and benefits... 1 5 Consultation...

More information

Construction Traffic Management Plan

Construction Traffic Management Plan Construction Traffic Management Plan Proposed Additional Accommodation for SWDPLS Shinners Bridge Dartington Produced for and on behalf of Built Environments Team Devon County Council NPS South West Ltd

More information

Federation of Piling Specialists

Federation of Piling Specialists Federation of Piling Specialists COMPANY NAME CONTRACT NAME TENDER REF SCHEDULE OF ATTENDANCES AND FACILITIES TO BE PROVIDED BY THE CLIENT TO A STEEL SHEET PILING SPECIALIST For the purposes of this document

More information

APPLICATION FOR PLANNING PERMISSION FOR A SOIL TREATMENT FACILITY AT KINGS CLIFFE LANDFILL SITE, STAMFORD, NORTHAMPTONSHIRE

APPLICATION FOR PLANNING PERMISSION FOR A SOIL TREATMENT FACILITY AT KINGS CLIFFE LANDFILL SITE, STAMFORD, NORTHAMPTONSHIRE APPLICATION FOR PLANNING PERMISSION FOR A SOIL TREATMENT FACILITY AT KINGS CLIFFE LANDFILL SITE, STAMFORD, NORTHAMPTONSHIRE DESIGN AND ACCESS STATEMENT Report Reference: AU/KC/SPH/1449/01/D&A/FIN Baddesley

More information

Logo here. TRAFFIC MANAGEMENT PLAN Ref : xxxx Dated xxxxxx. Enter details. Delivery Address: Enter details

Logo here. TRAFFIC MANAGEMENT PLAN Ref : xxxx Dated xxxxxx. Enter details. Delivery Address: Enter details Logo here Ref : xxxx Dated xxxxxx Mandatory H&S 905 Rev 1: xxxxx Page 1 of 1 Project: Project No: Date: Prepared by: Enter details Enter details Enter details Enter details Delivery Address: Enter details

More information

Liquid Effluent Treatment Plant (LETP) Land Clean-Up

Liquid Effluent Treatment Plant (LETP) Land Clean-Up Liquid Effluent Treatment Plant (LETP) Land Clean-Up Frequently Asked Questions What is proposed? Magnox Ltd is proposing to remove the redundant Liquid Effluent Treatment Plant (LETP) at Harwell and to

More information

Experience from the first large scale tidal turbine EIA in Europe. How do we work towards effective and proportionate EIA?

Experience from the first large scale tidal turbine EIA in Europe. How do we work towards effective and proportionate EIA? Independent, integrated thinking Experience from the first large scale tidal turbine EIA in Europe How do we work towards effective and proportionate EIA? Liz Foubister IEMA Webinar 30 th July 2014 What

More information

Viking Link Interconnector

Viking Link Interconnector Viking Link Interconnector Public information event for Bicker Parish Why we re here today We re here today to introduce the Viking Link project, to explain what we want to build and to answer any questions

More information

JOB DESCRIPTION. Position Title and Number: Senior Procurement Officer (100618) Health, Wellbeing & Commissioning

JOB DESCRIPTION. Position Title and Number: Senior Procurement Officer (100618) Health, Wellbeing & Commissioning JOB DESCRIPTION Position Title and Number: Senior Procurement Officer (100618) Grade: Department: Section: Responsible to: Responsible for: SO2 People Directorate Health, Wellbeing & Commissioning Team

More information

Wellington Inner City Improvements National War Memorial Park (Pukeahu) Certification Review

Wellington Inner City Improvements National War Memorial Park (Pukeahu) Certification Review Wellington Inner City Improvements National War Memorial Park (Pukeahu) Air Quality (Dust) Certification Review 22 November 2012 [CAQMP1 TR] Prepared in association with: Document produced by: Apecx PO

More information

environment briefing02

environment briefing02 PRODUCED BY THE SAFETY, HEALTH & ENVIRONMENT GROUP OF THE ENERGY NETWORKS ASSOCIATION - JULY 2006 environment briefing02 transporting electricity Overhead Lines or Underground Cables? Introduction The

More information

WHS Contractor Management Procedure

WHS Contractor Management Procedure Wudinna District Council 1. Overview Wudinna District Council as part of its commitment under its Policy recognises its obligation to: Ensure, so far as is reasonably practicable, the health and safety

More information

Who is National Grid?

Who is National Grid? Who is National Grid? National Grid is a leading international energy infrastructure business In the UK, our business includes electricity and gas transmission networks and gas distribution networks. We

More information

Health and safety policy

Health and safety policy 1. General statement of intent The Company recognises and accepts its responsibilities as an employer to ensure, so far as is reasonably practicable, the health, safety and welfare of its employees and

More information

DESCRIPTION OF WORK:

DESCRIPTION OF WORK: DEPARTMENT OF PUBLIC WORKS COUNTY OF HENRICO P.O. BOX 27032 RICHMOND, VIRGINIA 23273 PERMIT NO. One (1) copy of application and four (4) copies of plans are hereby made to the Director of Public Works

More information

HIGHWAYS ACT 1980 SECTION 171 : LICENCE APPLICATION PACK. Consent to deposit building materials and making of excavations in the Public Highway

HIGHWAYS ACT 1980 SECTION 171 : LICENCE APPLICATION PACK. Consent to deposit building materials and making of excavations in the Public Highway HIGHWAYS ACT 1980 SECTION 171 : LICENCE APPLICATION PACK Consent to deposit building materials and making of excavations in the Public Highway All Correspondence to : Reading Borough Council Highways Department

More information

Environment Committee 11 January 2016

Environment Committee 11 January 2016 Environment Committee 11 January 2016 Title Whole Life Costing of Footway Maintenance Treatments and Scheme Prioritisation Report of Wards Status Urgent Key Enclosures Commissioning Director, Environment

More information

A2 Pepperhill to Cobham Highway Widening project, UK

A2 Pepperhill to Cobham Highway Widening project, UK Further information Skanska AB www.skanska.com Contact Noel Morrin, Senior Vice President Sustainability noel.morrin@skanska.se A2 Pepperhill to Cobham Highway Widening project, UK Case Study 40 Aspects

More information

Cathkin Relief Road Planning Statement

Cathkin Relief Road Planning Statement Cathkin Relief Road Planning Statement The Proposal This statement sets out the background to the Cathkin Relief Road project currently being progressed by South Lanarkshire Council. The project will provide

More information

Utilities and existing services

Utilities and existing services Construction Services Building standards for mechanical and electrical installations Utilities and existing services October 2012 Directorate: Environment Construction Services - Building standards for

More information

Port Traffic Management Plan

Port Traffic Management Plan 0. Contents Section Topic 1 Introduction 2 Objectives 3 Responsibilities 4 Speed Limits 5 Signage 6 Traffic Flows 7 Maintenance 8 Key Control for Emergency Gates 9 North Wall Access 10 Review Procedure

More information

Inquiring Minds Want to Know: Questions Landowners Should Ask in Negotiations with Companies Seeking Easements

Inquiring Minds Want to Know: Questions Landowners Should Ask in Negotiations with Companies Seeking Easements Inquiring Minds Want to Know: Questions Landowners Should Ask in Negotiations As a property owner, you should make a decision about granting an easement based on the same level of information available

More information

Firth of Forth Offshore Wind Farm Zone. Offshore and Onshore Project Information

Firth of Forth Offshore Wind Farm Zone. Offshore and Onshore Project Information Firth of Forth Offshore Wind Farm Zone Offshore and Onshore Project Information May 2012 Introduction Seagreen Wind Energy Limited (Seagreen) is a 50/50 joint venture between SSE and Fluor (UK) Limited.

More information

Application by National Grid Gas plc for the River Humber Gas Pipeline replacement (the application)

Application by National Grid Gas plc for the River Humber Gas Pipeline replacement (the application) Application by National Grid Gas plc for the River Humber Gas Pipeline replacement (the application) Examining Authority s (ExA) Record of Unaccompanied Inspection of Sites to Which the Application or

More information

GREATER LINCOLN AREA MAJOR INFRASTRUCTURE PROJECTS

GREATER LINCOLN AREA MAJOR INFRASTRUCTURE PROJECTS GREATER LINCOLN AREA MAJOR INFRASTRUCTURE PROJECTS COMMUNICATIONS PLAN 1 2 LINCOLN MAJOR SCHEMES COMMUNICATION PLAN Scope This document sets out the aims, roles and responsibilities of Lincolnshire County

More information

7 Guiding delivery - next steps: efficient transport network management

7 Guiding delivery - next steps: efficient transport network management 7 Guiding delivery - next steps: efficient transport network management Council Plan priorities 2011-2014: making places easier to reach; a resilient economy Making the best use of existing roads for the

More information

Construction Phase Traffic Management Plan

Construction Phase Traffic Management Plan Construction Phase Traffic Management Plan The Construction Phase Traffic Management Plan is in connection with the application for the development of a single Wind Turbine and Ancillary Works on land

More information

WELCOME TO THE BAD Á CHEÒ WIND FARM EXHIBITION

WELCOME TO THE BAD Á CHEÒ WIND FARM EXHIBITION WELCOME TO THE BAD Á CHEÒ WIND FARM EXHIBITION Thank you for taking the time to attend The purpose of this exhibition is to explain why we have identified this site for a potential wind farm development

More information

REPORT FOR: Traffic and Road Safety Advisory Panel

REPORT FOR: Traffic and Road Safety Advisory Panel REPORT FOR: Traffic and Road Safety Advisory Panel Date of Meeting: 3 October 2012 Subject: INFORMATION REPORT - NETWORK MANAGEMENT DUTY 2011/12 Responsible Officer: John Edwards - Interim Corporate Director,

More information

ROAD OPENING LICENCE APPLICATION FORM PLEASE READ ALL PARTS AND SECTIONS OF THIS FORM IN ADVANCE OF COMPLETING THE APPLICATION

ROAD OPENING LICENCE APPLICATION FORM PLEASE READ ALL PARTS AND SECTIONS OF THIS FORM IN ADVANCE OF COMPLETING THE APPLICATION ROAD OPENING LICENCE APPLICATION FORM PLEASE READ ALL PARTS AND SECTIONS OF THIS FORM IN ADVANCE OF COMPLETING THE APPLICATION N.B. WORK MUST NOT COMMENCE UNTIL LICENCE IS ISSUED June 2014 Roads Section

More information

ENVIRONMENTAL & SOCIAL IMPACT ASSESSMENT (ESIA) FOR PRINOS OFFSHORE DEVELOPMENT PROJECT ANNEX 15: TRAFFIC MANAGEMENT PLAN

ENVIRONMENTAL & SOCIAL IMPACT ASSESSMENT (ESIA) FOR PRINOS OFFSHORE DEVELOPMENT PROJECT ANNEX 15: TRAFFIC MANAGEMENT PLAN : Pioneer in integrated consulting services March 2016 PRINOS OFFSHORE DEVELOPMENT PROJECT THIS PAGE IS LEFT INTENTIONALLY BLANK Page ii Environmental Consultant: LDK Engineering Consultants SA Date: 04/03/2016

More information

Construction Logistics Plan Guidance

Construction Logistics Plan Guidance Construction Logistics Plan Guidance For planners MAYOR OF LONDON Transport for London Section 1 Introduction Contents Section 1 Introduction 3 Section 2 Policy background 6 Section 3 Typical contents

More information

Frequently asked questions July 2014

Frequently asked questions July 2014 Carlton Main Sewer Frequently asked questions July 2014 We understand you might have some questions for us, so we ve prepared a selection of FAQs to provide you with some general information. If you would

More information

Purpose of the Local Liaison Committee

Purpose of the Local Liaison Committee Agenda 1. Welcome, introductions and purpose of the Local Liaison Committee 2. Introduction to the scheme 3. Progress update 4. Elect a chair for future meetings 5. Agree agenda and terms of reference

More information

Once an assessment has been made, the decision on whether the scheme will be put forward to the Panels will be reported to you.

Once an assessment has been made, the decision on whether the scheme will be put forward to the Panels will be reported to you. New TRO Requests Introduction and Application Form Essex Highways has delegated on-street parking, including lines, signs and restrictions, to the North Essex Parking Partnership (NEPP) in the North of

More information

LANGHOPE RIG WINDFARM TRAFFIC MANAGEMENT AND HAULAGE ROUTE SCHEME

LANGHOPE RIG WINDFARM TRAFFIC MANAGEMENT AND HAULAGE ROUTE SCHEME LANGHOPE RIG WINDFARM TRAFFIC MANAGEMENT AND HAULAGE ROUTE SCHEME Rev No. : Revision Description : Date : 0 For Information 1 Draft Prepared for Scottish Borders Council (SBC) comments 2 Draft Post SBC

More information

North-South 400 kv Interconnection Development

North-South 400 kv Interconnection Development North-South 400 kv Interconnection Development (TMP) February 2015 TOBIN CONSULTING ENGINEERS REPORT PROJECT: North-South 400 kv Interconnection Development CLIENT: COMPANY: EirGrid plc The Oval 160 Shelbourne

More information

LT McGuinness Site 10 Development, Wellington Waterfront. Construction Traffic Management Plan. 7 October 2014

LT McGuinness Site 10 Development, Wellington Waterfront. Construction Traffic Management Plan. 7 October 2014 LT McGuinness Site 10 Development, Wellington Waterfront Construction Traffic Management Plan 7 October 2014 TDG Ref: 12950 141007 ltm ctmp final report.docx LT McGuinness Site 10 Development, Wellington

More information

Guideline: Works that interfere with water in a watercourse watercourse diversions. September 2014

Guideline: Works that interfere with water in a watercourse watercourse diversions. September 2014 Guideline: Works that interfere with water in a watercourse watercourse diversions September 2014 This publication has been compiled by the Department of Natural Resources and Mines. State of Queensland,

More information

CONSTRUCTION TRAFFIC MANAGEMENT PLAN V11, 26/09/12

CONSTRUCTION TRAFFIC MANAGEMENT PLAN V11, 26/09/12 If the project you are constructing was subject to planning permission and a condition requiring a Construction Traffic Management Plan (CTMP) was applied to the planning consent, this condition will need

More information

CONSTRUCTION TRAFFIC MANAGEMENT PLAN

CONSTRUCTION TRAFFIC MANAGEMENT PLAN CONSTRUCTION TRAFFIC MANAGEMENT PLAN IN SUPPORT OF THE PROPOSED ERECTION OF A SINGLE WIND TURBINE WITH MAXIMUM BLADE TIP HEIGHT OF 67M, FORMATION OF NEW VEHICULAR ACCESS, ACCESS TRACK AND ASSOCIATED INFRASTRUCTURE

More information

DRAFT PLANNING THE OPENING OF A ROAD PROJECT GUIDELINE 1

DRAFT PLANNING THE OPENING OF A ROAD PROJECT GUIDELINE 1 DRAFT PLANNING THE OPENING OF A ROAD PROJECT GUIDELINE 1 Guideline: DRAFT Planning the opening of a road project guideline Version: 1.1 Issue: September 2009 Approved By: Phil Margison General Manager,

More information

Who are we? *Based on an average annual domestic household electricity consumption of 4,700KWh (DECC).

Who are we? *Based on an average annual domestic household electricity consumption of 4,700KWh (DECC). Who are we? We re one of the world s leading power and gas companies. Here in the UK, we supply energy to more than 5 million customers, generate enough electricity for around 8 million homes and employ

More information

Rockhampton Office Brisbane Office Tarong Site. Barron Gorge Hydro PS Kareeya Hydro PS Mica Creek PS

Rockhampton Office Brisbane Office Tarong Site. Barron Gorge Hydro PS Kareeya Hydro PS Mica Creek PS Business Procedure Traffic Management Document Number OHS-PROC-130 This document applies to the following sites: All Sites Rockhampton Office Brisbane Office Tarong Site Barron Gorge Hydro PS Kareeya Hydro

More information

Site Layout & Traffic Plan

Site Layout & Traffic Plan Location Site address: Norbury Manor Business Enterprise College, Kensington Avenue, Thornton Heath, Croydon CR7 8BT. The new block will be constructed on the existing hard play area. The construction

More information

Traffic Management Plan

Traffic Management Plan China Civil Engineering Construction Corporation The Rarotonga Water Ring Mains Upgrade Project (Te Mato Vai) of the Cook Islands Traffic Management Plan Compilation: Chinese Civil Engineering Corporation

More information

Traffic Management Issue 1.0 Revision: v2 October 2014

Traffic Management Issue 1.0 Revision: v2 October 2014 Disclaimer IMPORTANT: The information in this guide is of a general nature, and should not be relied upon as individual professional advice. If necessary, legal advice should be obtained from a legal practitioner

More information

APPLICATION KIT AND GUIDELINES FOR ORGANISATIONS SEEKING TO UNDERTAKE WORKS WITHIN ROAD RESERVE LOW COMPLEXITY WORKS.

APPLICATION KIT AND GUIDELINES FOR ORGANISATIONS SEEKING TO UNDERTAKE WORKS WITHIN ROAD RESERVE LOW COMPLEXITY WORKS. Document No: 16-02-12A Issue Date: 09 December 2014 APPLICATION KIT AND GUIDELINES FOR ORGANISATIONS SEEKING TO UNDERTAKE WORKS WITHIN ROAD RESERVE LOW COMPLEXITY WORKS (An approved Traffic Management

More information

Abu Dhabi EHSMS Regulatory Framework (AD EHSMS RF)

Abu Dhabi EHSMS Regulatory Framework (AD EHSMS RF) Abu Dhabi EHSMS Regulatory Framework (AD EHSMS RF) EHS Regulatory Instrument Code of Practice EHS RI CoP 44.0 Traffic Management and Logistics Version 2.0 February 2012 ACKNOWLEDGEMENTS With gratitude

More information

201[X] No. INFRASTRUCTURE PLANNING. The Network Rail (Ipswich Chord) Order

201[X] No. INFRASTRUCTURE PLANNING. The Network Rail (Ipswich Chord) Order Regulation number: Regulation 5(2)(b) Document Ref: 5.1 Author Winckworth Sherwood LLP Date: 21 June 2011 Date of revision & version number: 1.0 21 June 2011 STATUTORY INSTRUMENTS 201[X] No. INFRASTRUCTURE

More information

WHS CONTRACTOR MANAGEMENT PROCEDURE

WHS CONTRACTOR MANAGEMENT PROCEDURE 1. Overview The Port Augusta City Council as part of its commitment under its WHS Contractor Management policy, recognises its obligation to: Ensure, so far as is reasonably practicable, the health and

More information

2015 No. 51 HEALTH AND SAFETY. The Construction (Design and Management) Regulations 2015

2015 No. 51 HEALTH AND SAFETY. The Construction (Design and Management) Regulations 2015 S T A T U T O R Y I N S T R U M E N T S 2015 No. 51 HEALTH AND SAFETY The Construction (Design and Management) Regulations 2015 Made - - - - 22nd January 2015 Laid before Parliament 29th January 2015 Coming

More information

Construction (Design and Management) Regulations 2007

Construction (Design and Management) Regulations 2007 MEETING Finance, Procurement and Property Committee AGENDA ITEM 14 MEETING DATE 9 th July 2007 DOCUMENT NUMBER FEP 1052 SUBJECT REPORT Construction (Design and Management) Regulations 2007 (12/06/07) by

More information

UNDERGROUND TELECOMMUNICATIONS CABLES ACROSS PRIVATE LAND

UNDERGROUND TELECOMMUNICATIONS CABLES ACROSS PRIVATE LAND FACT SHEET TELEPHONE 0800 327 646 I WEBSITE WWW.FEDFARM.ORG.NZ UNDERGROUND TELECOMMUNICATIONS CABLES ACROSS PRIVATE LAND BACKGROUND The Rural Broadband Initiative envisages substantially improved broadband

More information

SECTION IX SLIP LINING PIPELINES

SECTION IX SLIP LINING PIPELINES AN SECTION IX SLIP LINING PIPELINES February, 2008 TABLE OF CONTENTS SECTION IX - SLIP LINING PIPELINES 9.01.00 GENERAL...2 9.01.01 SCOPE... 2 9.02.00 MATERIAL...2 9.03.00 CONSTRUCTION...2 9.03.01 REQUIREMENTS...

More information

Asset Protection Agreement Templates - Customer Explanatory Notes. Explanatory Notes on Asset Protection Agreement

Asset Protection Agreement Templates - Customer Explanatory Notes. Explanatory Notes on Asset Protection Agreement Asset Protection Agreement Templates - Customer Explanatory Notes Explanatory Notes on Asset Protection Agreement Clause Heading Background The Asset Protection Agreement is intended for use where the

More information

CITY OF VINCENT CONSTRUCTION MANAGEMENT PLAN GUIDELINES

CITY OF VINCENT CONSTRUCTION MANAGEMENT PLAN GUIDELINES CITY OF VINCENT CONSTRUCTION MANAGEMENT PLAN GUIDELINES INTRODUCTION What is a Construction Management Plan? The City of Vincent requires careful management of construction involving excavation and retention

More information

Construction Site Set Up Requirements

Construction Site Set Up Requirements Process Code Number Revision COP A 035 B Document Title Construction Site Set Up Requirements B 1/11/10 SRC SAT DH Final A 1/10/10 SRC MI Draft comment Rev. Date Prepared Reviewed Approved Detail/Comment

More information

720 Contour Grading. General. References. Resources. Definitions

720 Contour Grading. General. References. Resources. Definitions 720 Contour Grading General Contour grading directs water to a desired point, prevents erosion, provides noise deflection, provides visual fit of the facility into the landscape, and protects desirable

More information

OSU Extension FACT SHEET

OSU Extension FACT SHEET OHIO STATE UNIVERSITY EXTENSION! OSU Extension FACT SHEET Ohio State University Extension, 2120 Fyffe Road, Columbus, OH 43210 Shale Oil and Gas Development Fact Sheet Series A Landowner s Guide to Understanding

More information

The Construction (Design and Management) Regulations 2007

The Construction (Design and Management) Regulations 2007 STATUTORY INSTRUMENTS 2007 No. 320 HEALTH AND SAFETY The Construction (Design and Management) Regulations 2007 Made - - - - - 7th February 2007 Laid before Parliament 15th February 2007 Coming into force

More information

SPECIFICATION NET LINE 1 - Wilkinson Street Diamond Crossing (WSDC) re-ballast

SPECIFICATION NET LINE 1 - Wilkinson Street Diamond Crossing (WSDC) re-ballast General Requirements: The existing fixed diamond crossing at the Armstrong Way / Wilkinson Street junction (NG7 7NW) has become contaminated with material from roadway run-off and requires re-ballasting

More information

INTERIM ADVICE NOTE 65/05 DESIGN OF VEHICLE RECOVERY OPERATIONS AT ROAD WORKS

INTERIM ADVICE NOTE 65/05 DESIGN OF VEHICLE RECOVERY OPERATIONS AT ROAD WORKS INTERIM ADVICE NOTE 65/05 DESIGN OF VEHICLE RECOVERY OPERATIONS AT ROAD WORKS The Purpose of this document is to provide the Project Sponsor / Designer with comprehensive guidance on the range of issues

More information

Appendix E. Traffic Management Plan

Appendix E. Traffic Management Plan Appendix E Traffic Management Plan Corrib Onshore Gas Pipeline Traffic Management Plan May 2010 TOBIN CONSULTING ENGINEERS Prepared by TOBIN Consulting Engineers for and on behalf of Shell E&P Ireland

More information

Business Separation Statement of Compliance

Business Separation Statement of Compliance Business Separation Statement of Compliance SP Transmission plc SP Distribution plc SP Manweb plc 1 Introduction This document sets out the practices, procedures and systems that SP Transmission, SP Distribution

More information

Developing Ocean Energy in Ireland. Belmullet Wave Energy Test Site

Developing Ocean Energy in Ireland. Belmullet Wave Energy Test Site Developing Ocean Energy in Ireland Belmullet Wave Energy Test Site Where does our energy come from? Most of the energy we use in Ireland comes from fossil fuels such as oil, coal, peat and gas. We burn

More information

Demolition Works Measures for Public Safety

Demolition Works Measures for Public Safety Re-issued under new categorization in August 2009 as Practice Note for Authorized Persons, Registered Structural Engineers and Registered Geotechnical Engineers APP-21 Buildings Department Practice Note

More information

Permit No. Permit Fee: $295.00. Permit Expires (D+90 days): Business Name: Applicants Name: Telephone Number: E-mail Address:

Permit No. Permit Fee: $295.00. Permit Expires (D+90 days): Business Name: Applicants Name: Telephone Number: E-mail Address: City of Woodland Park Internet Service Provider (IPS) Permit for Installation of Telecommunication Infrastructure within City Owned Rights-of-Way (up to five locations per single permit) Permit No. Permit

More information

EXPRESSIONS of INTEREST

EXPRESSIONS of INTEREST EXPRESSIONS of INTEREST Noise, Stock and Bylaws Control Services Request for an Expressions of Interest to provide "Out of Hours" Local Regulatory Services including Noise, Stock and Bylaws Control Services.

More information

BOARD NOTICE COUNCIL FOR THE BUILT ENVIRONMENT. Notice No... 2011

BOARD NOTICE COUNCIL FOR THE BUILT ENVIRONMENT. Notice No... 2011 BOARD NOTICE COUNCIL FOR THE BUILT ENVIRONMENT Notice No.... 2011 NOTICE IN TERMS OF THE COUNCIL FOR THE BUILT ENVIRONMENT ACT, 2000 (ACT NO. 43 OF 2000) The Council for the Built Environment has under

More information

CONSTRUCTION TRAFFIC MANAGEMENT PLAN (CTMP)

CONSTRUCTION TRAFFIC MANAGEMENT PLAN (CTMP) CONSTRUCTION TRAFFIC MANAGEMENT PLAN (CTMP) [Colston Budd Hunt & Kafes Pty Ltd AS AMENDED BY City of Sydney] 23 March 2010 1. PREAMBLE 1.1 This document constitutes the Demolition and Traffic Management

More information

Figure 5.6a Construction worksites and corridor access Note: Indicative only, subject to detailed design.

Figure 5.6a Construction worksites and corridor access Note: Indicative only, subject to detailed design. A 0 NORTH 200 metres George Lane worksite North Strathfield Station worksite Strath eld Triangle A B Existing rail corridor Proposed underpass approach New/extended bridge Worksites Existing track Proposed

More information

Need for the scheme. The project will bring a number of benefits to road users including:

Need for the scheme. The project will bring a number of benefits to road users including: Introduction Welcome to our Project Bank Account (PBA) industry briefing event for the A96 Inveramsay Bridge Improvement Project, which is the first Scottish road infrastructure project to use a PBA. The

More information

SUFFOLK COASTAL DISTRICT COUNCIL DOMESTIC FLOOD PROTECTION POLICY

SUFFOLK COASTAL DISTRICT COUNCIL DOMESTIC FLOOD PROTECTION POLICY SUFFOLK COASTAL DISTRICT COUNCIL DOMESTIC FLOOD PROTECTION POLICY 1. Introduction 1.1 The Council recognises the threat to local communities from flooding following severe weather events and as a result

More information

The Mersey Gateway Project

The Mersey Gateway Project The Mersey Gateway Project The Mersey Gateway Project is a major scheme to build a new six-lane toll bridge over the River Mersey in the north west of England. It will link the towns of Runcorn and Widnes

More information