Comment #1: Provide an interchange at Route 7 and Farm Market Road/White Gate Road. This was studied in the late 1990 s.



Similar documents
SEMINOLE PRATT WHITNEY ROAD & NORTHLAKE BLVD. FREQUENTLY ASKED QUESTIONS

Section 6 Traffic Analysis

The partnership has selected three intersections where enforcement, education, and engineering initiatives are being implemented to improve safety:

Maryland Invests $845 Million in New Highway and Bridge Projects

Alternatives to the Circ Project Prioritization Methodology Prepared for Circ Task Force July 28, 2011

CAPACITY AND LEVEL-OF-SERVICE CONCEPTS

SR-18 Corridor Improvements in Wood County

7.2 Warrants and Planning Considerations

DISTRICT 3 TRAFFIC MANAGEMENT PLAN CHECKLIST

Transportation Management Plan Template

Definitions. For the purposes of this rule chapter the following definitions shall apply unless the context clearly shows otherwise:

Nashville Area MPO Regional Freight Study fast action projects

FHWA Colorado Division Control of Access to the Interstate and its Right-of-Way February 2005

How To Design A Crash Investigation Site

CHAPTERTWO. Alternatives 2.1 ALTERNATIVES DEVELOPMENT PROCESS

Managing Public Use of Freeway Emergency Access Gates and Median Crossovers

Accident Analysis of Sheridan Road between Isabella Street and South Boulevard

8+ %!0"% 8+1!%"'$%,$"$

9988 REDWOOD AVENUE PROJECT TRAFFIC IMPACT ANALYSIS. April 24, 2015

I-25 / Rio Bravo Interchange

CHAPTER 500 TRAFFIC INTERCHANGES

Goals & Objectives. Chapter 9. Transportation

Highway 138 Corridor Solutions Study Roseburg, Oregon. Technical Memorandum #4: Concept Development and Screening DRAFT

Site Layout & Traffic Plan

Downtown Louisville Two-Way Street Study

Engagement with the community will be in accordance with Council s Community Participation Policy.

Executive Summary. Transportation Needs CHAPTER. Existing Conditions

The Need for Traffic Incident Management

3 Tappan Zee Bridge Rehabilitation Options

First Transit Contra Flow Lane in Downtown San Francisco

Corridor Goals and Objectives

Alternatives Design Report. Draft

ENGINEERING SOLUTIONS FOR DESIGNING YOUR SAFE ROUTES

11 p.m. to. Tuesday, June. will remain open. 14. closed

PRIORITIZATION PROCESSES

Mobility Management Plan Study of the Busch Boulevard Corridor

Improving Access in Florida International University Biscayne Bay Campus Executive Summary

Chapter Forty-seven. RURAL TWO-LANE/MULTILANE STATE HIGHWAYS (New Construction/Reconstruction) BUREAU OF DESIGN AND ENVIRONMENT MANUAL

Spot Safety Project Evaluation

TH 23 Access Management Study Richmond to Paynesville

CHAPTER 27 New Public Road Connections. Table of Contents

Blacklands Corridor Feasibility Study. Public Meeting November 7, 2013 McClendon Elementary School Nevada, TX

Welcome Welcome to the public exhibition for development at Bowman Field. This exhibition provides an overview of the proposals for the site.

Transportation Policy and Design Strategies. Freight Intensive. Level of Freight Presence

Median Bus Lane Design in Vancouver, BC: The #98 B-Line

1. REPORT CONTEXT Description of the development (include all of the following that are known at the time of the application):

Informational Workshop Public Meeting Kanawha Falls Bridge Project

North Avenue Corridor Study. Advisory Committee Meeting #5 June 11, 2014

Incident Management Response Plan Hampton Roads Highway Incident Management Committee

EXHIBIT A Accessible Truck Routes Map

CHAPTER 13. Transportation Systems Management & Operations

Temporary Traffic Control for Building and Maintaining Single and Multi-Lane Roundabouts

DE 8 Concept Plan and Operations Study. Dover Safety Advisory and Transportation Committee October 23, 2007

FHWA Minnesota Division Guidance for the Preparation of a FHWA INTERSTATE ACCESS REQUEST

Disputed Red Light Accidents: A Primer on Signal Control. Jon B. Landerville, MSME, PE Edward C. Fatzinger, MSME, PE Philip S.

APPLICATION LAFAYETTE METROPOLITAN PLANNING ORGANIZATION (MPO) SURFACE TRANSPORTATION PROGRAM (STP) FUNDS TRANSPORTATION IMPROVEMENT PROGRAM (TIP)

Department of Transport and Main Roads Road Priorities in North Queensland Region

Presentation to Community Task Force July 9, 2007

Stone Way N Rechannelization: Before and After Study. N 34th Street to N 50th Street

City of Kamloops Notre Dame Corridor Access Plan

Roadway Congestion 139, , ,700 NA 4,300 4,900. Table 7-2 Transportation Criteria - Roadway Congestion (2035)

LEGISLATIVE COUNCIL PANEL ON PLANNING, LANDS AND WORKS

APPENDIX F. Access Management Design Standards for Entrances and Intersections

Doing a little can accomplish a lot. Proposed Change of Municipal Class Environmental Assessment from Schedule from B to A+

CHAPTER 13. Transportation Systems Management & Operations

Executive Summary. Literature/Community Review. Traffic Flows and Projections. Final Report Truck Route System for Miami-Dade County CORRADINO

Chapter Thirty-five ACCESS CONTROL/ ACCESS MANAGEMENT BUREAU OF DESIGN AND ENVIRONMENT MANUAL

Seagull Intersection Layout. Island Point Road - A Case Study. Authors: John Harper, Wal Smart, Michael de Roos

M8 M73 M74 Motorway Improvements Project

2013 QUALITY/ LEVEL OF SERVICE HANDBOOK

BENNINGTON LOCAL ROADWAY NETWORK TRAFFIC ANALYSIS

AIR QUALITY TECHNICAL MEMORANDUM

Access Management Manual

TRANSPORTATION MANAGEMENT PLAN

Olympic Region Traffic Management Center. Olympic Radio

Ne w J e r s e y Tr a f f i c Co n g e s t i o n :

21101 &?I I2 P 3: 2 I. kz COZY c:oi*;: iiss:en. DOCEET COEi1 f3.x..

KENTUCKY TRANSPORTATION CABINET. Department of Rural and Municipal Aid. Office of Local Programs

Intersection Cost Comparison Spreadsheet User Manual ROUNDABOUT GUIDANCE VIRGINIA DEPARTMENT OF TRANSPORTATION

Sir Francis Drake Boulevard Rehabilitation Project Bicyclist and Pedestrian Intercept Interviews Report

Belmont Street Bridge Rehabilitation Project

Surface Transportation Program (STP)

MEMORANDUM. Robert Nichols, Acting Corridor Design Manager Northgate Link Extension

Draft Transportation Management Plan for Via Verdi Repair Project

Soapstone Connector Feasibility Study

Lawson Outline Plan External Traffic Analysis Working Paper

PROFFER STATEMENT REZONING TLZM LEEGATE November 1, 2013

28 CHAPTER 4 TRANSPORTATION. Chapter 4 Transportation

BEFORE-AND-AFTER STUDY OF THE EFFECTIVENESS OF RECTANGULAR RAPID-FLASHING BEACONS USED WITH SCHOOL SIGN IN GARLAND, TEXAS

PREFERRED ALTERNATIVE RECOMMENDATION FOR THE COLLEGE AVENUE SAFETY ENHANCEMENT (CASE) PROJECT COLUMBIA, MISSOURI

Comprehensive Mobility Project Development Process Capital Metro ¼-Cent Fund Analysis

Southern California International Gateway Project Description

Examples of Transportation Plan Goals, Objectives and Performance Measures

TRAFFIC IMPACT ANALYSIS

Major and Minor Schemes

EXPERIENCE WITH GEOGRAPHIC INFORMATION SYSTEMS (GIS) / MAPPING

1500 Hamilton Avenue Primrose Daycare Center Project

How To Modernize And Maintain Roads, Highways And Bridges In Maine

AGENCY COORDINATION AND PUBLIC INVOLVEMENT

Transcription:

Proposed Truck Climbing Lane Route 7 Westbound Between West Market Street and Route 9 UPC# 58599, Project # 6007-053-133, P101 Date of Meeting: August 24, 2010 Time: 6:00PM to 8:00PM Location: Rust Library 380 Old Waterford Road NW Leesburg, Virginia 20176 Summary of Verbal Comments and VDOT Responses Comment #1: Provide an interchange at Route 7 and Farm Market Road/White Gate Road. This was studied in the late 1990 s. An interchange at this location would be difficult to construct given the topography of the area, and would result in impacts to several surrounding homes. The construction costs would add roughly $50 million to the project. The estimated cost of the Route 7 Truck Climbing Lane Project is approximately $25 million. Currently, allocations to this project are approximately $20 million. Comment #2: This project will add congestion from Route 7 westbound to Route 9 interchange. Regardless of whether the project is built or not, traffic will continue to increase both on Route 7 and Route 9. Based on traffic modeling, the project will not add a significant amount of traffic (see traffic projections on VDOT Project Website). The project will improve operations at the Route 9 interchange and at the Route 7 on- and offramps through the addition of the following: Two additional turn lanes at the terminus of the off ramp from Route 7 westbound to Route 9 Additional extended dual left turn lanes from Route 9 southbound onto Route 7 eastbound Additional receiving lane on Route 7 eastbound on-ramp from Route 9 southbound New traffic signal at both the terminus of the Route 7 westbound off-ramp to Route 9 and at the intersection of Route 9 and Route 7 eastbound on-ramp Comment #3: Will this project impact future planned widening of Route 7 from 4-lanes to 6-lanes? The Loudoun County Comprehensive Plan calls for Route 7 to be widened from 4-lanes to 6- lanes, including through the project area. The project will not preclude future widening of Route 7.

Page 2 of 6 Comment #4: Due to the current heavy traffic volumes on Route 9, it is difficult for residents of Beacon Hill to turn from Beacon Hill Drive to Route 9, especially during peak periods. The addition of a new traffic light at the Route 9/Route 7 interchange will further compound the problem. VDOT will investigate the feasibility of a traffic signal as well as other improvements, including a roundabout, at the Beacon Hill Drive and Route 9 intersection based on current traffic counts and projected traffic data. The addition of turn lanes and traffic signals on the Route 9 interchange allow for improved traffic operations versus the current condition. Comment #5: Has emergency access been considered? If not, this will negatively effect emergency response times due to the closure of median breaks. The conceptual plan includes right-in/right-out access for emergency vehicles at Leeland Orchard Road and Beechnut Road. VDOT will investigate preserving some or all of the median breaks for emergency access. Any preserved median breaks will be blocked to prevent unauthorized use. This investigation will include coordination with the Loudoun County Department of Fire and Rescue Services to ensure adequate emergency access is maintained. Comment #6: Build connection from Leeland Orchard cul-de-sac directly to West Market Street or nearby Town of Leesburg roads. VDOT will investigate this proposal further if endorsed by the Town of Leesburg. The most technically feasible connections on the north side of the Route 7 corridor is Rosebrooke Court or Phillips Drive in the Normandy Village neighborhood. The most feasible connection on the south side is to connect Roxbury Hall Road to Kintyre Court and then connect Children s Center Road to Cannongate Drive in the Shenstone community. Comment #7: Would the project eliminate tree barriers? Would landscaping be included with the project? Based on conceptual plans, significant impacts to tree barriers are not anticipated, mainly due to the fact that the majority of paving will take place in the existing median. VDOT anticipates spending approximately 2% to 3% of the total construction costs on landscaping, which would be roughly $350,000 to $550,000. Comment #8: Why is right-in/right-out access not maintained at each intersection?

Page 3 of 6 In order to minimize construction costs and right of way expenses, much of the climbing lane construction will take place in the Route 7 median, rendering that median less effective and less safe as a refuge for cross traffic. Also, it will be more difficult for egressing vehicles to cross three lanes of free flowing traffic. Traffic signals are not an option because this segment of Route 7 is designated a Limited Access Freeway and signals will result in greater congestion than what is presently experienced. To address these competing needs, conceptual plans show that the existing median breaks on Route 7 between Route 9 and West Market Street would be closed, and robust measures put in place that would accommodate the resulting increase in U-turn movements at the Route 9 and West Market Street interchanges. These measures mainly consist of i) modifications to the two interchanges and ii) construction of acceleration and deceleration lanes at the remaining at-grade intersections. The purpose behind the closing of some of the intersections along this segment of Route 7 (Hidden Gap Road, Fort Johnston Road and Leeland Orchard Road in the westbound direction, and Beechnut Road in the eastbound direction) is to reduce the likelihood of crashes, via the elimination of conflict points that are created by the intersections, in a manner that minimizes the overall footprint of the project. If the intersections were to remain open, then acceleration lanes as well as lengthened deceleration lanes would need to be provided at each location. If all of the existing intersections were to remain open, then there will be a de facto 4 th lane along Route 7. This will result in excessive construction costs and right of way impacts due to the mountainous terrain in this area. Another factor to consider is the fact that this segment of Route 7 was formally designated a Limited Access facility when the current four lane highway was built in the early 1970s. It has the same status as the Route 7 Bypasses around Leesburg, Hamilton, Purcellville and Round Hill. Two of the main factors that drove the selection of which intersections to close were i) traffic volumes and ii) safe and convenient alternate means of access. Traffic counts from 2010 show that at Hidden Gap Road, there are only 17 vehicles entering Route 7 during the morning peak hour and 20 vehicles turning into Hidden Gap Road during the evening peak hour. Couple this light traffic volume with alternate access points via Farm Market Road as well as Beacon Hill Drive and the thinking was that traffic impacts to the rest of the Beacon Hill streets would be negligible. At Fort Johnston Road, there is one vehicle entering Route 7 and three vehicles enter Fort Johnston Road during the morning peak hour. At Leeland Orchard Road, there are seven vehicles entering Route 7 during the morning peak hour. Again, the low traffic volumes and proximity of an alternate access point make this approach desirable compared to the construction of acceleration and deceleration lanes if Fort Johnston Road and Leeland Orchard Road remained open.

Page 4 of 6 Comment #9: Provide a signal at the intersection of Farm Market Road and Route 7, even if just for off-peak times. This was the site of a fatal crash within last year. VDOT will investigate safety improvements to this intersection. However, a traffic signal is not an option because this segment of Route 7 is designated a Limited Access Freeway and a signal in this location, with proportionally very few turning vehicles from side streets, will result in greater congestion than what is presently experienced. Comment #10: Restrict vehicles to maintain lane through this section of Route 7, west of the West Market Street interchange. There is already signage in place for slower vehicles to keep right. VDOT will continue to investigate alternatives for signage as well as pavement markings to maintain the most efficient traffic flow possible. Comment #11: Close the ramp from West Market Street to Route 7. This is not feasible as it will result in a significant degradation of the regional roadway network. Also, the climbing lane is warranted regardless of whether the ramp is closed or not. Comment #12: Remove the steep hill beginning at West Market Street. The steep grade results in vehicles (especially large trucks) reducing speed, which in turn slows surrounding traffic. This is not feasible as it will incur the massive right of way and construction impacts that VDOT is seeking to avoid by placing the climbing lane in the Route 7 median. Comment #13: Extend Winning Colors Place to Old Waterford Road. VDOT will investigate this proposal if endorsed by Loudoun County and the Town of Leesburg. Comment #14: Re-align new roadway approaching new intersection of Fort Johnston Road and Count Turf Place to build roadway close to fence line. This will reduce tree impacts and impacts to farm

Page 5 of 6 property. Opposed to VDOT taking land from southeast quadrant of new intersection of Fort Johnston Road and Count Turf Place. VDOT will work with the affected property owner on the best possible alignment of the extension of Fort Johnston Road to Alysheba Drive. Comment #15: This project increases traffic through the Beacon Hill community due to the additional traffic added from residents of Fort Johnston Road and Leeland Orchard Road. The Beacon Hill community is comprised of approximately 225 homes. There are approximately 20 homes total off of Fort Johnston Road and Leeland Orchard Road. Based on the number of residences, the amount of traffic generated by connecting these two cul-de-sac neighborhoods would be an increase of less than 10%. The roadway that would experience the majority of this traffic is only a 500 ft. long segment of Alysheba Drive between Farm Market Road and Count Turf Place, and there are no homes along this segment. Again, the low traffic volumes and proximity of an alternate access point make this approach desirable compared to the construction of acceleration and deceleration lanes if Fort Johnston Road and Leeland Orchard Road remained open. Please see response to Comment #8 for additional information. Comment #16: Motorists often mistake the Roxbury Hall Road intersection deceleration/right turn lane for the West Market Street on-ramp from Route 7 eastbound. This leads to crashes into the guardrail just east of the intersection of Route 7 and Roxbury Hall Road. Provide acceleration lane from Roxbury Hall Road to Route 7 eastbound. Extend right turn lane/deceleration lane from Route 7 eastbound onto Roxbury Hall Road. VDOT will investigate safety improvements to this intersection, including the feasibility of extending the deceleration/right turn lane and adding an acceleration lane. However, the addition of an acceleration lane from Roxbury Hall Road to Route 7 eastbound may create a conflict with weaving traffic exiting Route 7 to West Market Street. Comment #17: Provide a left-in from Route 7 westbound to Roxbury Hall Road (entrance to Church of the Nazarene of Leesburg). If this left-in access were restricted, as shown in current plan, this would have the greatest impact in terms of commute time versus all other movements within the project vicinity. VDOT will investigate the feasibility of this alternative.

Page 6 of 6 Comment #18: Provide soundwalls, especially for residents off of Farm Market Road. Since the project is federally funded, an environmental document will be prepared as required by the National Environmental Policy Act. The environmental document will include a detailed noise analysis and the need for soundwalls will be evaluated.