TRAFFIC IMPACT ANALYSIS
|
|
|
- Solomon Jenkins
- 10 years ago
- Views:
Transcription
1 TRAFFIC IMPACT ANALYSIS Presenter Gerry Harter, PE, Area Traffic Engineer Acting Transportation and Land Use Director
2 Why a TIA? Roads are a critical public resource and a major investment of public funds Traffic impacts from trips generated by development can cause disruption in traffic flow and traffic congestion which can lead to roads becoming less safe. TIAs help to ensure development impacts do not overburden the taxpayer. TIAs can be applied by public officials to balance: o o Property owners right to access the highway to use their land Roadway users right to mobility, safety, and efficient expenditure of public funds. 2
3 So taxpayers do not have to pay for this. TIA Study to determine how to prevent this 3
4 Benefit of the TIA Study to the Community Turn lanes and tapers Maintain through traffic flow. 4
5 Benefit of the TIA Study to the Community Entrances away from intersections and interchange ramps Intersection signal R-O-W for road widening Improve sight distance Interparcel connection Entrance design Subdivision connectivity Consolidate existing entrances. 5
6 TIA Touch Points During Local Land Use Actions Chapter 527 VDOT Permitting Process Local LUA 527/TIA Permits 6
7 Local Land Use Approval Process The rezoning of property is the earliest point in the local land review process that offers flexibility in design details By evaluating the proposal Impacts on the transportation network can be identified Measures to address the impacts can be determined Locality can request a TIA at this stage. GREAT TIME FOR VDOT PARTNERING! Conditional zoning - opportunity for applicant to proffer both on-site and off-site transportation improvements to mitigate impacts GREAT TIME FOR VDOT PARTNERING 7
8 Local Land Use Approval Process Site plan and subdivision plat review Examine details on the design and layout of the development GREAT TIME FOR VDOT PARTNERING! VDOT offers assistance to localities in the review of: The transportation portion of comprehensive plans Rezoning requests, and Site plans and subdivision plats. AT THIS STAGE, VDOT IS ADVISORY ONLY 8
9 Chapter Traffic Impact Analysis Land development proposals to be submitted Substantially affect transportation on state controlled highways based on traffic volume 5,000 trips per day (standard threshold) 400 trips per day and at least equals existing traffic on road (for residential development only, low volume road threshold) Dependent upon Submission type Comprehensive Plan or Plan Amendment Rezoning or Special Use Permit Location Within 3,000 ft of connection to VDOT highway (for non-vdot localities) Exception: Rezoning that does not increase trips (daily and peak hour) over those allowed under existing zoning 9
10 Traffic Impact Analysis Sample Developments That May Meet Thresholds ITE Land Use Low Volume Standard Description Code Variable (400 Trips) (5,000 Trips) Residential Single Family Detached 210 dwelling units 40 du 550 du Apartment 220 dwelling units 60 du 670 du Other Light Industrial 110 square feet not applicable 690,000 sf High School 530 students not applicable 2,900 st Hospital 610 beds not applicable 420 bds General Office Building 710 square feet not applicable 560,000 sf Shopping Center 820 square feet not applicable 40,000 sf Home Improvement Superstore 862 square feet not applicable 170,000 sf These are estimates that have been rounded and are not official thresholds. They are offered as examples only. 10
11 Chapter 527 TIA Regulations A 527 TIA study prepared per the methodology can still be requested by the locality. VDOT will provide a written response to locality/developer: Summarize key findings of the study Comments on recommended highway improvements Advise on needed compliance with other VDOT regulations Comments on suggested improvements to other travel modes. 11
12 527 -Traffic Impact Analysis Comp plan submission not required to include TIA; rezoning is required to include a TIA Published local study standards can be used, if certified by District Scope of study dependent upon amount of traffic generated but generally includes: Existing and proposed land use Existing traffic and Level of Service (LOS) Expected future traffic and LOS (without proposed development) Expected future traffic and LOS (with proposed development) Recommendations for traffic impact mitigation measures 12
13 Traffic Impact Analysis Required elements (cont d) Default assumptions and methodology Data collection (avoid holidays, inclement weather) Trip generation (rates vs. equations based upon ITE methodology) Internal capture rates (residential with others, hotel with office, office with retail) Pass-by trip rates (per ITE Trip Generation Handbook) Allow alternate trip generation for Small Area Plans (EPA-MXD methodology) Level of service calculation (HCM methodology for vehicles, Transit Capacity and Quality of Service Manual for transit) Modal split (bike/ped facilities, proximity to transit service) 24VAC
14 VDOT Permitting Process Permits allow users to perform work within our roadways and rights of ways. 1. A permit is required for any type of utility activity occurring within the right-of-way. 2. A permit is required to install any entrance onto a state highway. 3. A permit is required to perform surveying operations within the right-of-way. 4. A permit is required for any agricultural and commercial use and occupancy of the right-of-way. 5. A permit is required for any miscellaneous activity or use of the right-of-way except for mailboxes and newspaper boxes (see 24VAC ) and public service signs (24VAC ). 14
15 TIAs and Entrance Permits What is the relationship between TIAs and commercial entrance permits? VDOT can request a TIA in order to determine impacts of development during the permitting process. 24VAC Commercial Entrance Design At the request of the district, the permit applicant shall furnish a report that documents the impact of expected traffic movements 15
16 TIAs During Permit Stage If VDOT has not heard about the project until the permit stage, it is more difficult to plan appropriate mitigation measures for transportation impacts. Many times the site plans, rezonings, CUPs, and subdivisions have already been approved by the planning commission and/or the governing body making changes to the site plan difficult. Typically, local governments are disengaged at this stage since they have completed all of their processes. Causes unnecessary delays in commercial entrance permit approval process. More costs and time at end of process when developer was least expecting it. 16
17 TIAs During Permit Stage Suggestions Engage VDOT as a partner in the process as early as possible. If a TIA is needed to mitigate impacts, have the land development applicant prepare it earlier in the process. Also, ensure that it meets VDOT s expectations as well so that all information is provided avoiding additional delays. VDOT is available in an advisory role and would be happy to assist during the land use action. 17
18 Conclusion TIAs are vital to the mobility and safety of the travelling public TIAs provide information to help ensure that development mitigates their impacts on the road system. TIAs are required for Chapter 527 rezonings, Should be part of the local land development review process, May be required by VDOT during entrance permit review. Chapter 527 provides a thorough traffic impact analysis methodology for rezonings that fall under 527. Localities can request TIAs for non-527 land use actions. TIA methodology can be different for non-527 developments. The traffic impacts of development should be considered as early in the process as possible. 18
19 QUESTIONS / COMMENTS For more information on the state law, regulations and traffic impact analysis studies See the VDOT web site, Info Center tab, Transportation and Land Use 19
Transportation Impact Assessment Guidelines
Transportation Impact Assessment Guidelines Preface The following TIA Guidelines have been developed jointly by the City s Planning and Growth Management and Public Works and Services departments in an
City of Rockville Regional Development Impacts: Transportation Capacity Analysis. June, 2013
City of Rockville Regional Development Impacts: Transportation Capacity Analysis June, 2013 Purpose and Need Response to Council and Public Evaluate use of more advanced traffic analysis methodology and
TRAFFIC IMPACT ANALYSIS (TIA)
GUIDELINES FOR TRAFFIC IMPACT ANALYSIS (TIA) FOR REZONING APPLICATIONS AND OTHER DEVELOPMENT APPROVALS REQUIRING TRANSPORTATION IMPACT ANALYSIS IN SUMTER COUNTY, FLORIDA July 17, 2007 PURPOSE AND APPLICABILITY
TRANSPORTATION IMPACT ANALYSIS PROCEDURES MANUAL
TRANSPORTATION IMPACT ANALYSIS PROCEDURES MANUAL INTRODUCTION The Town of Harrisburg is committed to establishing an interconnected, multimodal transportation system that increases mobility, safety, connectivity,
TRAFFIC IMPACT ANALYSIS
TRANSPORTATION Section 6-1 TRAFFIC IMPACT ANALYSIS The Town Of Buckeye Arizona Engineering Design Standards Section 6-1 Adopted December 2012 TABLE OF CONTENTS 6-1.000 GENERAL INFORMATION:...3 6-1.001
PROFFER STATEMENT REZONING TLZM 2013-0001 LEEGATE November 1, 2013
PROFFER STATEMENT REZONING TLZM 2013-0001 LEEGATE November 1, 2013 Leegate LLC and Stanley Martin Companies, LLC, owner and applicant, (the Applicant ) of certain property described as Loudoun County Tax
Guidelines for the Preparation of Transportation Impact Studies 8 th Revision
Guidelines for the Preparation of Transportation Impact Studies 8 th Revision Halifax Regional Municipality Traffic and Right of Way Transportation and Public Works P.O. Box 1749 Halifax, Nova Scotia B3J
9988 REDWOOD AVENUE PROJECT TRAFFIC IMPACT ANALYSIS. April 24, 2015
9988 REDWOOD AVENUE PROJECT TRAFFIC IMPACT ANALYSIS April 24, 2015 Kunzman Associates, Inc. 9988 REDWOOD AVENUE PROJECT TRAFFIC IMPACT ANALYSIS April 24, 2015 Prepared by: Bryan Crawford Carl Ballard,
The Bond Release Process for New Subdivision Developments: An Overview for Homeowners Associations DRAFT 6-4-08. Revised 9-25-08
The Bond Release Process for New Subdivision Developments: An Overview for Homeowners Associations DRAFT 6-4-08. Revised 9-25-08 Fairfax County requires developers to post a performance bond if they are
TABLE OF CONTENTS TABLES FIGURES
TABLE OF CONTENTS Introduction...1 1. On-Site Stacking...2 2. Number of School Driveways...2 3. School Driveway Standards...3 3A. Driveway Spacing...3 3B. Driveway Location...4 3C. Driveway Lane Widths
Appendix E Traffic Impact Analysis
Appendix E Traffic Impact Analysis 2010 Facility Master Plan Factoria Recycling and Transfer Station November 2010 2010 Facility Master Plan Factoria Recycling and Transfer Station November 2010 Department
Transportation Impact Analysis and Mitigation Plan Procedures Manual
Transportation Impact Analysis and Mitigation Plan Procedures Manual February 2011 Table of Contents 1 Overview 1 2 Applicability of Traffic Impact Analysis and Mitigation Requirements 2 21 General Applicability:2
Goals & Objectives. Chapter 9. Transportation
Goals & Objectives Chapter 9 Transportation Transportation MISSION STATEMENT: TO PROVIDE A TRANSPORTATION NETWORK CAPABLE OF MOVING PEOPLE AND GOODS EFFICIENTLY AND SAFELY. T he transportation system
City of Kamloops Notre Dame Corridor Access Plan
FINAL REPORT This report is prepared for the sole use of ICBC. No representations of any kind are made by Urban Systems Ltd. or its employees to any party with whom Urban Systems Ltd. does not have a contract.
TRAFFIC IMPACT ANALYSIS HANDBOOK VOLUME I METHODOLOGIES & REQUIREMENTS
TRAFFIC IMPACT ANALYSIS HANDBOOK VOLUME I METHODOLOGIES & REQUIREMENTS Downtown panoramic photo provided by 1stACT Silicon Valley (blank below this line) Volume I Methodologies and Requirements TABLE OF
TRANSPORTATION IMPACT ANALYSIS (TIA) Guidelines
TRANSPORTATION IMPACT ANALYSIS (TIA) Guidelines Methodology For Development Applications Requiring a TIA in Volusia County, Florida TIA Guidelines As adopted on November 24, 2009 (The Volusia Transportation
INTRODUCTION TO ZONING DISTRICT REGULATIONS
INTRODUCTION TO ZONING DISTRICT REGULATIONS Classification of Zoning Districts Zoning districts in Dorchester County are categorized as Suburban Urban, Suburban Transition, or Rural. These districts are
REZONING 16-000009 & PRELIMINARY PLAT 16-000005
REZONING 16-000009 & PRELIMINARY PLAT 16-000005 REZONING REQUEST AND REVISED PRELIMINARY PLAT FOR THE BLUFFS AT WINDCASTLE - 4165 FAREDALE LANE Application: Engineer: Developer: Property Owner: Current
COUNTY OF ALBEMARLE PLANNING STAFF REPORT SUMMARY. Staff: Claudette Grant
COUNTY OF ALBEMARLE PLANNING STAFF REPORT SUMMARY Project Name: ZMA 2013-00004 Hollymead Town Center Block VI Planning Commission Public Hearing: July 29, 2014 Staff: Claudette Grant Board of Supervisors
May 18, 2015. Ms. Courtney O'Neill Associate Planner City of Margate 5790 Margate Blvd. Margate, Florida 33063
May 18, 2015 Ms. Courtney O'Neill Associate Planner City of Margate 5790 Margate Blvd. Margate, Florida 33063 Re: Atlantic Margate Medical Center 6101 W. Atlantic Blvd. and 513 Melaleuca Drive Margate,
TH 23 Access Management Study Richmond to Paynesville
TH 23 Access Management Study Richmond to Paynesville Prepared For: Minnesota Department of Transportation District 8 Prepared By: Short Elliott Hendrickson Inc. July 2015 Table of Contents I. Introduction...
14-97. 14-97.002 Definitions. For the purposes of this rule chapter the following definitions shall apply unless the context clearly shows otherwise:
14-97 14-97.001 Purpose. This rule chapter sets forth an access control classification system and access management standards to implement the State Highway System Access Management Act of 1988. The implementation
FHWA Colorado Division Control of Access to the Interstate and its Right-of-Way February 2005
FHWA Colorado Division Control of Access to the Interstate and its Right-of-Way February 2005 Background: It is in the national interest to maintain the Interstate System to provide the highest level of
Intersection Cost Comparison Spreadsheet User Manual ROUNDABOUT GUIDANCE VIRGINIA DEPARTMENT OF TRANSPORTATION
Intersection Cost Comparison Spreadsheet User Manual ROUNDABOUT GUIDANCE VIRGINIA DEPARTMENT OF TRANSPORTATION Version 2.5 i Virginia Department of Transportation Intersection Cost Comparison Spreadsheet
Table of Contents B.2 Traffic/Access - Parking
Table of Contents B.2 Traffic/Access - Parking 1. INTRODUCTION... 940 2. ENVIRONMENTAL SETTING... 940 a. Existing Parking Regulations and Requirements... 940 b. Parking Supply Baseline Conditions... 941
Transportation Policy and Design Strategies. Freight Intensive. Level of Freight Presence
Appendix G Transportation Policy and Design Strategies CONTEXT SENSITIVE SOLUTIONS To address the need to describe freight systems which account for the population distress which may result, an analysis
The Need for Traffic Incident Management
The Need for Traffic Incident Management With traffic incidents responsible for approximately 50-60% of the congestion delays motorists encounter on the nation s roadways every day, increased roadway capacity
Appendix J Santa Monica Travel Demand Forecasting Model Trip Generation Rates
Appendix J Santa Monica Travel Demand Forecasting Model Trip Generation Rates SANTA MONICA TRAVEL DEMAND FORECASTING MODEL TRIP GENERATION RATES SUBMITTED BY: 201 Santa Monica Blvd., Suite 500 Santa Monica,
Tier 1 Strategies. WV Route 14 Corridor Management Plan
1.1 1.2 1.3 1.4 Signal timing optimization system improvements. Improve geometry traffic control at high crash intersections. Construct intersection capacity improvement projects. Widen longer sections
Orange County Transportation Impact Fee Update FINAL REPORT
Transportation Impact Fee Update FINAL REPORT Prepared for: Transportation Planning Department 4200 S. John Young Parkway, Second Floor Orlando, FL 32839 ph (407) 836-8070 September 5, 2012 (amended November
TRANSPORTATION IMPACT ASSESSMENT (TIA) GUIDELINES. Section 1 Introduction
TRANSPORTATION IMPACT ASSESSMENT (TIA) GUIDELINES Section 1 Introduction MassDOT s mission is to deliver excellent customer service to people who travel in the Commonwealth, and to provide our nation's
Comment #1: Provide an interchange at Route 7 and Farm Market Road/White Gate Road. This was studied in the late 1990 s.
Proposed Truck Climbing Lane Route 7 Westbound Between West Market Street and Route 9 UPC# 58599, Project # 6007-053-133, P101 Date of Meeting: August 24, 2010 Time: 6:00PM to 8:00PM Location: Rust Library
Snohomish County Department Of Public Works (DPW) Rules Adopted Pursuant to the Rulemaking Requirements of Chapter 30.82 SCC Providing Detail and Specificity for the Traffic Mitigation and Concurrency
Traffic Impact Analysis Guidelines
Updated: January 2014 Traffic Impact Analysis Guidelines B U R E A U O F T R A F F I C O P E R A T I O N S T A B L E O F C O N T E N T S Preface... A1 to A5 Important Notice...B1 Traffic Impact Analysis
City of Yakima. Home Occupation. Application Packet
City of Yakima Home Occupation Application Packet It is important to your land use review that all parts of this application packet be completed. All narratives, when requested, must be completed with
Multi Modal Roadway Transportation Impact Fees and Asset Value
January 2010 SB 360 Article Series: Factors to be Considered in Transitioning from a Road Impact Fee to a Mobility Fee Contributing Authors: Steven A. Tindale, P.E., AICP Robert P. Wallace, P.E., AICP
CAPACITY AND LEVEL-OF-SERVICE CONCEPTS
CHAPTER 2 CAPACITY AND LEVEL-OF-SERVICE CONCEPTS CONTENTS I. INTRODUCTION...2-1 II. CAPACITY...2-2 III. DEMAND...2-2 IV. QUALITY AND LEVELS OF SERVICE...2-2 Service Flow Rates...2-3 Performance Measures...2-3
How To Design A Crash Investigation Site
CHAPTER 7 CRASH INVESTIGATION SITES December, 2000 7. Crash Investigation Sites (CIS) 7.1. Introduction and Usage The idea of "crash investigation sites" or areas outside of the freeway mainline where
Topic 2 11/28/2012 Blocks & Street Network
TOPIC 2 Blocks & Street Network Implementation Note: 1. Some recommendations are summarized in the tables herein. For complete recommendation language, please see the. 2. Recommendations referenced in
WESTFIELD-WASHINGTON ADVISORY PLAN COMMISSION December 7, 2015 1512-SPP-24 & 1512-ODP-24
Petition Number: Subject Site Address: Petitioner: Request: East side of Oak Road, north of 151 st Street Langston Development Co. Primary Plat and Overall Development Plan amendment review for Mapleridge
1. REPORT CONTEXT Description of the development (include all of the following that are known at the time of the application):
Transportation Assessment and Management Study Guidelines for Consultants INTRODUCTION This document is intended to provide guidelines for transportation consultants who produce Transportation reports
SECTION 16 TRAFFIC/SAFETY SECTIONS 16.1, 16.2 AND 16.3 ARE UNDER DEVELOPMENT
SECTION 16 TRAFFIC/SAFETY SECTIONS 16.1, 16.2 AND 16.3 ARE UNDER DEVELOPMENT 16.1-1 16.4 Intelligent Transportation Systems Introduction The ITS Engineering Unit is responsible for the design of all ITS
Texas Case Studies in Access Management. Ed Hard, TTI
Texas Case Studies in Access Management Ed Hard, TTI 8 th National Conference on Access Management August 15, 2006 Presentation Overview TxDOT Arterial Widenings, College Station, TX Processes for Median
Best Practices for Traffic Impact Studies
Best Practices for Traffic Impact Studies Final Report SPR 614 Prepared for Oregon Department of Transportation and Federal Highway Administration June 2006 Prepared by Technical Report Documentation
CHAPTER 4 EXISTING TRANSPORTATION MANAGEMENT
CHAPTER 4 EXISTING TRANSPORTATION MANAGEMENT TRANSPORTATION MANAGEMENT SYSTEMS Prior to 1991, the Missouri Department of Transportation (MoDOT) had begun development of several independent management systems.
Section 6 Traffic Analysis
Section 6 Traffic Analysis Traffic Operations of the Preferred Network Alternative After the Preferred Network was identified and confirmed by local policy makers and area residents, detailed traffic analysis
CITY OF WEST PALM BEACH PLANNING BOARD Meeting Date: September 24, 2012 Planning Board Case No. 1248Q
CITY OF WEST PALM BEACH PLANNING BOARD Meeting Date: September 24, 2012 Planning Board Case No. 1248Q Morse Life Major Planned Development Amendment Location Aerial I. REQUEST Morse Campus outlined in
Ne w J e r s e y Tr a f f i c Co n g e s t i o n :
Ne w J e r s e y Tr a f f i c Co n g e s t i o n : A Growing Crisis January 2008 Cover photo : Route 3, Passaic County introduction A rising tide of traffic congestion threatens to increase roadway gridlock,
Chapter Thirty-five ACCESS CONTROL/ ACCESS MANAGEMENT BUREAU OF DESIGN AND ENVIRONMENT MANUAL
Chapter Thirty-five ACCESS CONTROL/ ACCESS MANAGEMENT BUREAU OF DESIGN AND ENVIRONMENT MANUAL Chapter Thirty-five ACCESS CONTROL/ACCESS MANAGEMENT Table of Contents Section Page 35-1 GENERAL CONCEPTS...
The Fresno COG Travel Demand Forecasting Model How the Pieces Fit Together
The Fresno COG Travel Demand Forecasting Model How the Pieces Fit Together Mike Bitner PE, Senior Transportation Planner Council of Fresno County Governments 1 COG Modeling Staff Mike Bitner Kathy Chung
D4 - D12 May 8, 2013 Public Hearing
D4 - D12 May 8, 2013 Public Hearing CITY OF VIRGINIA BEACH AMENDMENTS PERTAINING TO APPLICATION FEES REQUESTS: D4. An Ordinance to Amend Section 110 of the Chesapeake Bay Preservation Area Ordinance Pertaining
d. Building permits may only be approved if consistent with the approved development plan and land division for all units with common walls.
Section 20.920.060 Tier 2 Infill Standards. In addition to the Tier 1 standards and incentives, Tier 2 infill parcels and land divisions and the subsequent development on those Tier 2 infill parcels shall
Presentation to Knox County Commission Monday, February 23, 2015
The Northwest County Sector Plan Update Presentation to Knox County Commission Monday, February 23, 2015 COMMUNITIES OF THE NORTHWEST COUNTY SECTOR Ball Camp Cedar Bluff Last NW Sector Update: 2003 Land
University Pointe Opportunity Summary. Remaining in Phase I. University Pointe. Hwy. 29 & Brookside Lane Charlotte, NC.
250,000 Sq. Ft. Walmart Supercenter Anchored Development University Pointe Opportunity Summary Only 6,000 Sq. Ft. Remaining in Phase I University Pointe Hwy. 29 & Brookside Lane Charlotte, NC University
Near Westside Neighborhood and University Avenue Corridor Transportation Study. Public Workshop #2. September 12 and 23, 2013
Near Westside Neighborhood and University Avenue Corridor Transportation Study Public Workshop #2 September 12 and 23, 2013 Presentation Outline: Brief Review of Study Scope, Background, and Current Conditions
Draft Transportation Management Plan for Via Verdi Repair Project
for Via Verdi Repair Project prepared for City of Richmond This report was prepared by: This report was reviewed by: Ryan McClain, P.E. Fehr & Peers TABLE OF CONTENTS 1.0 INTRODUCTION & PROJECT DESCRIPTION...
3 Tappan Zee Bridge Rehabilitation Options
3 Tappan Zee Bridge Rehabilitation Options 3.1 Introduction This chapter describes possible options that rehabilitate and enhance the existing Tappan Zee Bridge. Four Rehabilitation Options have been developed:
Chapter 7 ZONING PLAN
Chapter 7 ZONING PLAN Introduction This Chapter opens with a general description of a zoning plan. It is followed by a brief explanation of the relationship between this Growth Management Plan and the
Mobile Restaurant Permit Application Checklist
Checklist 1. The food truck business owner completes Sections I - III on Page 2 of this Mobile Restaurant Permit Application. 2. Complete Section IV and obtain copies of the necessary documents listed
analysis needs be met at the push of a button?
can all of your traffic analysis needs be met at the push of a button? A SOLUTION FOR ALL TRAFFIC ANALYSIS NEEDS How do you conduct traffic studies, evaluate new development impacts, and time your signals
MEMORANDUM. Robert Nichols, Acting Corridor Design Manager Northgate Link Extension
MEMORANDUM DATE: September 23, 2014 TO: Robert Nichols, Acting Corridor Design Manager Northgate Link Extension FROM: SUBJECT: COPIES: Katherine Casseday, PE, PTOE, Casseday Consulting Tony Lo, PE, Parsons
A Case for Real-Time Monitoring of Vehicular Operations at Signalized Intersections
White Paper A Case for Real-Time Monitoring of Vehicular Operations at Signalized Intersections 10 1 0 1 0 TRAFINFO.COM TrafInfo Communications, Inc. 556 Lowell Street Lexington, MA 02420 www.trafinfo.com
Bond Release Process for New Subdivision Developments in Fairfax County
Bond Release Process for New Subdivision Developments in Fairfax County An Overview for Homeowners Associations A Fairfax County, Va., publication April 2009 For more information or to request this document
Mercer County Multi-Modal Transportation Plan Year 2025 Travel Demand Model
Mercer County Multi-Modal Transportation Plan Year 2025 Travel Demand Model Prepared For West Virginia Department of Transportation Transportation Planning Division Building 5, Room 824 1900 Kanawha Blvd.
The Northwest Arkansas Travel Demand Model
The Northwest Arkansas Travel Demand Model Creation and Results John McLarty Northwest Arkansas Regional Planning Commission Cristina Scarlat Center for Advanced Spatial Technologies What is a Travel Demand
The financial plan was prepared in conjunction with the Technical Working Group. Refer to Table 3-1: Funding and Implementation Plan.
3 Financial Plan The purpose of the financial plan is to identify funding options that would be likely sources of money to advance recommendations made by this study. The Capitol Region Transportation
SR-18 Corridor Improvements in Wood County
Public Meeting Information Package SR- Corridor Improvements in Wood County Thursday, May 19, 2011 10:00 a.m. to 1:00 p.m. Meeting Location: Hancock-Wood Electric Cooperative Building 1399 Business Park
County of San Diego, Planning & Development Services SECOND DWELLING UNIT
County of San Diego, Planning & Development Services ZONING DIVISION The Zoning Ordinance, Section 6156.x, allows the addition of a second dwelling unit to those properties zoned to allow the Family Residential
Simulating Traffic for Incident Management and ITS Investment Decisions
1998 TRANSPORTATION CONFERENCE PROCEEDINGS 7 Simulating Traffic for Incident Management and ITS Investment Decisions MICHAEL D. ANDERSON AND REGINALD R. SOULEYRETTE UTPS-type models were designed to adequately
Light Rail Transit in Phoenix
4. Presentation and Discussion: Phoenix Light Rail Implementation Wulf Grote Planning and Development Director, Phoenix Valley Metro Light Rail Transit in Phoenix Broadway Citizen s Task Force February
Highway Capacity and Quality of Service
A3A10: Committee on Highway Capacity and Quality of Service Secretary: Richard G. Dowling, Dowling Associates Highway Capacity and Quality of Service WAYNE K. KITTELSON, Kittelson & Associates, Inc. This
Traffic Signal Asset Management. Edward Fok USDOT/FHWA Resource Center
Traffic Signal Asset Management Edward Fok USDOT/FHWA Resource Center Fundamental Objectives 1. Preserve our assets and minimize their whole life costs. 2. Operate in a financially sustainable manner.
PUBLIC SCHOOL FACILITIES ELEMENT
PUBLIC SCHOOL FACILITIES ELEMENT GOALS, OBJECTIVES AND POLICIES JULY 2006 Prepared By: The City of Miami Gardens Planning and Zoning Department 1515 NW 167 th Street, Building 5, Suite 200 Miami Gardens,
Traffic Impact Study for the 3817-45 North Broadway Mixed-Use Development Chicago, Illinois. Prepared by
Traffic Impact Study for the Chicago, Illinois repared by March 30, 2015 1. Introduction This report summarizes the methodologies, results and findings of a traffic impact study conducted by Kenig, Lindgren,
Preliminary Plan Application and Checklist
ALL APPLICATIONS ARE DUE AT 12:00 NOON ON THE FILING DATE Office Use Only PRELIMINARY / REVISED PRELIMINARY PLAN $300.00 Fee Paid: $ Date Paid: ALL FIELDS HIGHLIGHTED IN RED ARE REQUIRED FIELDS Case No.:
AREA: 0.16 acres NUMBER OF LOTS: 1 FT. NEW STREET: 0 LF
FILE NO.: Z-9020 NAME: Hometown Tax Service Short-form PD-O LOCATION: Located at 3008 West 12 th Street DEVELOPER: Mark Green 65 Westfield Loop Little Rock, AR 72210 SURVEYOR: Kittler-Roberts Group, LLP
City Code of ANN ARBOR, MICHIGAN Chapter 55 Zoning
ARTICLE II. USE REGULATIONS 5:10.2. R1A, R1B, R1C, R1D single family dwelling district (1) Intent. (a) These single family residential districts are designed to provide an environment of predominantly
Forecasting Demand for Demand Forecasting. Abstract
MORISON,James Beattie Transportation Engineer City of Calgary Transportation Planning FUNG,Yu Han Transportation Planner City of Calgary Transportation Planning District 7 (CANADA) ITE conference, Victoria
SECTION 6: TRANSPORTATION
6.0 INTRODUCTION SECTION 6: TRANSPORTATION This section covers the design of the transportation system including but not limited to roadways, lanes, sidewalks and pathways located within road right of
APPENDIX A Dallas-Fort Worth Region Transportation System Management Strategies and Projects
APPENDIX A Transportation System Management Strategies and Projects Transportation System Transportation System Management Projects Management Strategies Traffic Signalization and Control New Signal Installation
A Short Course on Techniques for Determining Construction Related Road User Costs
TEXAS TRANSPORTATION INSTITUTE A Short Course on Techniques for Determining Construction Related Road User Costs prepared by TEXAS TRANSPORTATION INSTITUTE THE TEXAS A&M UNIVERSITY SYSTEM 701 NORTH POST
Construction Traffic Management Plan
Introduction This (CTMP) has been prepared in order to discharge Condition 20 of planning permission ref 07/02879/EFUL for the enabling site works associated with the wider Bath Western Riverside development.
FILE NO.: Z-6915-C. Gamble Road Short-form PCD and Land Alteration Variance Request
FILE NO.: Z-6915-C NAME: Gamble Road Short-form PCD and Land Alteration Variance Request LOCATION: Located on the Northwest corner of Chenal Parkway and Gamble Road DEVELOPER: Davis Properties P.O. Box
PRE APPLICATION CONFERENCE - INTRODUCTION
CITY OF AUBURN Planning & Development Department Auburn City Hall Annex, 2 nd Floor 1 East Main Street Auburn, WA 98001 Tel: 253.931.3090 Fax: 253.804.3114 [email protected] www.auburnwa.gov PRE-APPLICATION
30 Years of Smart Growth
30 Years of Smart Growth Arlington County s Experience with Transit Oriented Development in the Rosslyn-Ballston Metro Corridor A Presentation by the Arlington County Department of Community Planning,
Brookdale Site. CB6 Update April 1, 2015
Brookdale Site CB6 Update April 1, 2015 Summary Timeline / Process How does DSNY operate now? Garage project and frequently asked questions Project facts Impact to emergency vehicle access Traffic congestion
Accident Analysis of Sheridan Road between Isabella Street and South Boulevard
Accident Analysis of Sheridan Road between Isabella Street and South Boulevard Prepared for TranSystems Corporation for the City of Evanston Submitted by Regina Webster & Associates, Inc. Date: 08/15/2008
Corridor Goals and Objectives
Corridor Goals and Objectives This chapter presents the goals and objectives, developed by the Corridor Study Committee, that serve as the purpose and intent of the Corridor Plan. This plan covers a twenty