1 Last Update: November, 2015 A. Conduits: Consultant s Handbook Page 1 of 7 1. All conductors for each and every electrical system shall be installed in a raceway except communications and A/V systems which shall have stubs to open ceilings and open cable. 2. Minimum size of conduits shall be per NEC, and increased as necessary for installation conditions such as bends, insulation, etc. Use 3/4" minimum. 3. Separate conduit systems shall be provided for: a. Each lighting system b. Convenience outlets c. Each power system by voltage level d. Each different system as further defined: 01. Communications (voice and data) 02. Fire Alarm 03. Emergency lighting and EXIT signage 04. Emergency power 05. Control systems 06. Building Automation Control Systems e. Except by special permission, separate conduits are required for each feeder, each equipment branch circuit, and for all special systems 4. Common conduits will be acceptable for: a. Branch circuits originating from the same panel for lighting and outlets b. Motor branch circuits, or for a motor circuit and its associated control wiring. c. Lighting power and lighting control wiring can be in the same conduit provided the insulation to the control wiring is greater than the highest voltage in the conduit 5. All conduits shall be concealed except as follows: a. Electrical and mechanical equipment spaces 6. All conduits shall bear the Underwriter's Label. 7. All conduits shall be of U.S. manufacture. 8. Where GRC or IMC enters a box or other fitting through a knockout, an approved double locknut and bushing shall be provided. 9. Conduit bushings shall be threaded type, having insulated inserts equal to O.Z., steel, type "B". Bushings for feeder conduits shall be grounding type, having lay-in type lug. Threadless bushings may be used in special instances only, 10. Six 1" spare conduits up and two 1" spare conduits down shall be installed from each flush mounted light and power panelboard and terminated in space above or at respective ceilings in 4"
2 Page 2 of 7 square boxes with blank covers, two conduits per box. None are required out bottom of panels of slab on grade. B. Electrical Metallic Tubing (EMT or Thinwall) 1. Feeder conduits may be EMT. 2. EMT will be installed with steel compression or set screw, insulated throat, concrete tight type couplings and connectors. Other type fittings will not be acceptable. C. Rigid Heavy Wall Conduit (Rigid or Intermediate Metal Conduit (IMC)) : 1. Rigid heavy wall conduit shall be installed in the following locations: a. All poured walls (1" minimum concrete cover) b. Under slab or underground and encased in 3 minimum concrete, except where located four or more inches below bottom of lowest slab in granular fill c. Exposed exterior locations (rigid only) d. All exterior masonry constructions e. Where exposed to mechanical injury f. All explosion proof work (rigid only) g. "Vaportight" and "watertight" work h. Do not install within floor slabs or slabs on grade. 2. Rigid heavy wall conduit shall be installed in the following manner: a. Square cut and reamed after cutting threads. b. Coupled with Erickson Couplings in lieu of running threads. c. Installed with joints sealed with conductive, waterproof conduit joint compound (where underground or in concrete walls), equal to T & B "KOPR-SHIELD" or Sherwin Williams "ZINC-CLAD". d. Installed in accordance with Underwriter's Laboratories Standard UL6 for Rigid and UL/242 for IMC. e. Installed with double locknuts and bushings except for threaded hubs. f. Used for sleeves except where sheet metal is approved elsewhere. g. Installed with all threaded fittings (the use of set screw or compression type not acceptable) h. Where exiting or entering a concrete slab, extend Rigid or IMC at least 36" before adapting to EMT. i. Where Rigid or IMC enters a junction box or any enclosure within 60" of exiting or entering a concrete slab, the Rigid or IMC shall be continuous into the enclosure. D. Rigid Non-Metallic Conduit (PVC): 1. Conduit shall be heavy wall, rigid, schedule 40, PVC, Carlon "Plus 40" or equal and may be installed under floor slabs for branch circuits or feeders.
3 Page 3 of 7 2. In general for underground site lighting branch circuits only, no concrete encasement is required. Other types of installations may require concrete encasement as directed by the Owner or by NEC. 3. Entire installation shall be watertight. 4. Where exiting or entering a concrete slab, PVC shall be adapted to Rigid or IMC at least 12" prior to exiting or entering the slab. 5. 5" or 6" schedule 40 encased in concrete for ductbanks. Coordinate with BSU for further instruction and for BSU standard ductbank details. E. Skeletal Conduit Systems: 1. Conduits shall be 10 feet lengths of 4 EMT separated at 10-foot intervals as necessary to clear walls, obstructions, etc. 2. Connectors or bushings are not required. Ream and smooth cut ends to prevent cable damage. 3. Provide two supports for conduit sections on 6 foot spacing. 4. Provide sleeves through walls where shown, full size or sized as shown. Patch walls around sleeves per NEC section Seal each sleeve with appropriate fire stop. F. Flexible Metallic Conduits: 1. Greenfield (hot dipped galvanized) is to be used in dry locations only. 2. Used for final connections to all recessed fixtures. Installed in adequate lengths (6 maximum) for fixture servicing and convenient removal. 3. Flex connectors shall be UL listed for grounding, squeeze type, malleable iron with insulated throat, one or two screw type as O-Z/Gedney, T & B, Raco or approved equal (set screw type, die-cast or screw-in type are not acceptable). 4. Flexible conduit fittings with external ground connection may be required under special circumstances as shown on Drawings, listed in Job Scope or as directed by the Owner s Representative. G. Flexible Liquid-Tight Metallic Conduit "Sealtite" 1. To be used in damp or wet locations, including exterior, water softener, brine handling and equipment located within air chamber of air handling equipment, with NEC grounding. 2. To be used for final connections to all motors, 3 ft. maximum length, unless otherwise approved. 3. Liquid tight fittings shall be UL listed for grounding, ferrule and sleeve type with insulated throat as O-Z/Gedney 4Q series, T & B, Appleton ST or approved equal. 4. 1/2" minimum allowable size. 5. Supported within 3 ft. of motor terminals. H. Fittings: 1. Conduit Bodies: a. "LBD" and Mogul size for 1" and larger conduits. b. Cast ferrous material for exterior, watertight and vapor tight locations with gaskets at covers.
4 Page 4 of 7 c. As manufactured by Appleton, Pyle National or Crouse Hinds or Killark. 2. Expansion Fittings: a. Installed in each run of conduit that crosses a building expansion joint. b. Provided with bonding straps. c. As manufactured by O.Z. or approved equal. 3. Conduit Seals (Vapor and Water): a. Installed in each run of conduit between different temperature zones likely to cause condensation and circulation of moisture. b. Installed in each run of conduit between a hazardous location and a non-hazardous (per NEC) location likely to cause the spread of vapors, dust, etc. c. Filled with proper sealing compound in accessible locations. d. Installed in walls where conduits enter/leave below grade. OZ/Gedney Type "FSK", Link Seal LS series or equal. 4. Conduit Hubs: a. Conduit hubs shall be installed for all GRC or IMC terminations to sheet metal type enclosures for installations requiring a watertight or dust tight seal. b. Hubs shall have insulated throat and recessed O-Ring seal. c. Hubs shall be as O-Z/Gedney, T & B, Myers or approved equal I. Conduits Penetrating Roof: 1. One conduit per sleeve 2. Minimum height of sleeve not less than 12" above roof membrane 3. Provided rain shield on conduit overlapping sleeve a minimum of 2 inches 4. Secure rain shield to conduit with stainless steel pressure clamps 5. Provide flashing as required J. Outlet Boxes 1. General: a. Every switch, light, wall receptacle, signal device, telephone outlet, etc., shall be provided with an outlet box. b. "Through wall" and "Handy boxes" are not acceptable c. Boxes installed Back to Back or within 12 center to center, penetrating opposite sides of wall construction, and installed in a fire resistive and/or fire rated wall shall not be permitted. d. Outlet boxes installed in stud walls shall be supported across both studs with hanger such as Erico Caddy RBS or SGB series. Hangers that support from only one stud such as Erico Caddy HS3 are not allowed. 2. Sizing:
5 Page 5 of 7 a. All boxes shall be sized in accordance with NEC. b. Four inch square x 2 1/8 deep for 2 or more conduits or devices with appropriate device rings. c. Four inch octagon or square boxes for fixture outlets. d. Communications outlets shall typically be deep 4 square boxes with single gang extension rings and 1 EMT stubbed out to corridor skeletal system gaps. Conduit stubs shall be deburred only. Do not terminate with bushings. e. Utilize extra (3 1/2") deep four inch square boxes with appropriate device rings in electronic classrooms where shown on BSU standard electronic classroom rough-in details. Conduit stubs for these boxes may need to be up to 2. Coordinate with BSU. 3. Approved Manufacturers: a. Appleton b. Steel City c. Raco K. Surface Raceways 1. Metal Raceways. Use only with Owner's permission and specifically shown on the drawings: a. All surface metal raceways and fittings shall be as manufactured by the Wiremold Co., West Hartford, CT, and Hubbell or approved equal. Factory finished color shall be selected by BSU during design, b. One Piece Surface Metal Raceways: 01. Wiremold #500 or #700 Series and fittings or Hubbell equal c. Two Piece Surface Metal Raceways: 01. Wiremold #2100 Series or Hubbell equal 02. Wiremold #3000, #DS4000, #6000 Series or Hubbell equal 2. #3000 = 2-3/4" W x 1-7/32" D 3. #DS4000 Designer Series or #4000 series. Confirm with BSU which to use in a given application. 4. #6000 = 4-3/4" W x 3-9/16" D a. Where two-piece raceway covers pass through walls, floors, and/or ceilings, the cover shall be cut on both sides of the wall, floor or ceiling (maximum of 6 from edge of penetration) to permit removal of the cover on each side of the obstruction. 5. Non-Metal Raceways. Use only with Owner's permission and specifically shown on the drawings: a. All surface non-metallic raceways and fittings shall be as manufactured by the Panduit Co. or Hubbell. b. One Piece Non-Metallic Surface Raceway: 01. Panduit Type L c. Two Piece Surface Non-Metallic Raceways: 01. Panduit Type T Series
6 02. Hubbell Basetrak, series Page 6 of 7 d. Where two-piece raceway covers pass through walls, floors, and/or ceilings, the cover shall be cut on both sides of the wall, floor or ceiling (maximum of 6 from edge of penetration) to permit removal of the cover on each side of the obstruction. 6. Troughs: a. All troughs and fittings shall be as manufactured by Square D, Hoffman or approved equal.
7 L. Mounting Heights Consultant s Handbook Page 7 of 7 Table 1 MOUNTING HEIGHT SCHEDULE Device Reference Height Switches floor - center + 4'-0" Outlets floor center + 1'-6" Plugstrip floor center + 4'-0" Dimmer floor center + 4'-0" Wall Speaker ceiling - top +/- 1'-0" (verify) Telephone Outlet floor center + 1'-6" Wall Phone floor - center + 4'-0" Wall Phones - Handicapped floor - center + 3'-4" Fire Alarm Station floor - center + 4'-0" Safety Switch floor - top + 6'-0" Motor Starter floor - top + 6'-0" Relay Panel floor - top + 6'-0" Branch Circuit Panel floor - top + 6'-0" Push Button floor - center + 4'-0" Control Station floor - center + 4'-0" Microphone Outlet floor - bottom + 1'-6" Clock ceiling - top +/- 1'-0" (verify) Bells ceiling - top +/- 1'-0" (verify) Control Station for Electric Operated Doors floor - center + 3'-0" Note: All references are from finished floor or ceiling to the device box.
All work must conform to the National Electric Code, latest edition, and all other applicable codes and regulations.
DIVISION 16 ELECTRICAL SECTION 16100 - ELECTRICAL PART 1 - GENERAL SCOPE All electrical work as shown on the drawings and as necessary to provide a complete electrical system. Include primary service,
ELECTRICAL GUIDELINES FOR SINGLE-FAMILY HOME OWNERS:
ELECTRICAL GUIDELINES FOR SINGLE-FAMILY HOME OWNERS: Chapter 12 of the Burlington Code of ordinances allows owner occupants of single family homes to do their own wiring if they choose. If you choose to
Electrical for Detached Garages: Updated Feb 19, 2016 for 2015 CE Code in force Jan. 1, 2016. Underground branch circuit feeding a detached garage:
Electrical for Detached Garages: Updated Feb 19, 2016 for 2015 CE Code in force Jan. 1, 2016 * Garage construction requires permits (electrical, building) * Permits must be applied for at the time. * Dial
2014 NEC Guide Lines for Home Owner Doing Electrical Work on their Property
2014 NEC Guide Lines for Home Owner Doing Electrical Work on their Property A brief summary of the most used code references for residential wiring State of Idaho Division of Building Safety Electrical
READ THIS MANUAL BEFORE PROCEEDING WITH THE INSTALLATION. FAILURE TO FOLLOW THE INSTALLATION INSTRUCTIONS MAY VOID YOUR WARRANTY!
READ THIS MANUAL BEFORE PROCEEDING WITH THE INSTALLATION. FAILURE TO FOLLOW THE INSTALLATION INSTRUCTIONS MAY VOID YOUR WARRANTY! The main power to any existing system must be disconnected prior to the
The National Armored Cable Manufacturers Association Presents. Installation Standard for Types AC and MC Cables
The National Armored Cable Manufacturers Association Presents Installation Standard for Types AC and MC Cables An ANSI Standard Original document jointly produced by NECA and NACMA as Standard for Installing
OPEN ITEMS LIST - CONSTRUCTION Project Name: East Central Middle School - Jackson County CLA#: 11003
OPEN ITEMS LIST - CONSTRUCTION Project Name: East Central Middle School - Jackson County CLA#: 11003 No. Discipline Sent to Name Item Date Noted Date Resolved How item was resolved Electrical Contractor
FIREFINDER XLS ADDRESSABLE FIRE ALARM SYSTEM SECTION 13851
FIREFINDER XLS ADDRESSABLE FIRE ALARM SYSTEM SECTION 13851 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and
Conduit Fittings & Accessories Directional Drilling Conduit Utility Duct Telephone Duct Residential Boxes
CANTEX INC. 301 Commerce Ste 2700 Fort Worth, Texas 76102 817-215-7000 Fax: 817-215-7001 Conduit Fittings & Accessories Directional Drilling Conduit Utility Duct Telephone Duct Residential Boxes YOUR FULL
Electrical Code Regulation
Electrical Code Regulation St. Clair County has adopted the 2005 National Electrical Code in its entirety for the unincorporated areas of the county and all communities that have contracted with the county
ELECTRICAL CONTRACTORS THE UNIVERSITY OF TENNESSEE KNOXVILLE, TENNESSEE SECTION 16050 PAGE 1
KNOXVILLE, TENNESSEE SECTION 16050 PAGE 1 PART 1 - GENERAL 1.01 RELATED DOCUMENTS: SECTION 16050 A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division-1
RESIDENTIAL ELECTRICAL REQUIREMENTS (REVISED 3/28/2008) PERMIT REQUIREMENTS:
RESIDENTIAL ELECTRICAL REQUIREMENTS (REVISED 3/28/2008) PERMIT REQUIREMENTS: Signed completed Electrical Permit application form. Minnesota law requires all electrical work is to be performed by licensed,
CONTENTS. Yale University Design Standards. Underground Electrical Duct Bank. A. Summary. B. System Design and Performance Requirements
16600 Underground Electrical Duct Bank This document provides design standards only, and is not intended for use, in whole or in part, as a specification. Do not copy this information verbatim in specifications
B. Related Sections: 1. Section 26 05 33 - Raceway and Boxes for Electrical Systems.
SECTION 262726 - WIRING DEVICES PART 1 - GENERAL 1.1 SUMMARY A. Section includes wall switches; wall dimmers; receptacles; multioutlet assembly; and device plates and decorative box covers. B. Related
GROWTH MANAGEMENT DEPARTMENT 201 SE 3 rd ST, (Second Floor), Ocala, FL 34471 (352) 629-8421; FAX: (352) 629-8264
BUILDING CODE GUIDELINES FOR ELECTRICAL INSPECTIONS Building Code compliance is the obligation of design professionals and/or contractors. Plan Review and Inspection Guidelines are intended to be used
800 Communications Circuits
ARTICLE 800 Communications Circuits INTRODUCTION TO ARTICLE 800 COMMUNICATIONS CIRCUITS This article has its roots in telephone technology. Consequently, it addresses telephone and related systems that
METER REQUIREMENTS GENERAL REQUIREMENTS SECTION D
12 - ELECTRIC SERVICE HANDBOOK SECTION D METER REQUIREMENTS This chapter gives you information on Central Lincoln s metering requirements. It's divided into three sections: General requirements This section
ADDENDUM NO. 2 TO PROJECT NO. 43153
ADDENDUM NO. 2 TO PROJECT NO. 43153 CONSTRUCTION WORK, MECHANICAL WORK, PLUMBING WORK, ELECTRICAL WORK PROVIDE VISITOR CENTER BUILDING AND SITE IMPROVEMENTS FIVE RIVERS ENVIRONMENTAL EDUCTION CENTER 56
18 AWG thru 8 AWG Not greater than 100/30 100/30. 6 AWG thru 1/0 AWG Not greater than 200/60 100/30
Commercial Products COMMERCIAL PRODUCTS: RIGID AND IMC FITTINGS s Used to support cables in vertical raceways or risers. Relieves the strain that would be placed on terminations, the interior of panels,
Conduit Tubing Electrical Metallic Tubing (EMT) Intermediate Metal Conduit (IMC) Hot-Dip Galvanized Steel Rigid Metal Conduit (RMC)
Conduit Tubing Electrical Metallic Tubing (EMT) Intermediate Metal Conduit (IMC) Hot-Dip Galvanized Steel Rigid Metal Conduit (RMC) Download Buy American Brochure Includes 2011 National Electrical Code
4 Installation Requirements
4 Installation Requirements 9 4.1 Code Reference The authority having jurisdiction should be referenced to determine what law, ordinance or code shall apply in the use of flexible duct. Ducts conforming
SECTION 16402 UNDERGROUND ELECTRIC SERVICE
SECTION 16402 UNDERGROUND ELECTRIC SERVICE PART 1 GENERAL 1.1 SUMMARY A. Description of System 1. Furnish all labor, materials, and equipment for below grade work external to buildings as required, and
CONSOLIDATED EDISON CO. OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003 DISTRIBUTION ENGINEERING DEPARTMENT SUBSTATION & EQUIPMENT SECTION
CONSOLIDATED EDISON CO. OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003 DISTRIBUTION ENGINEERING DEPARTMENT SUBSTATION & EQUIPMENT SECTION SPECIFICATION EO-5023 REVISION 3 MARCH 2003 REQUIREMENTS FOR
ELECTRICAL SERVICE REQUIREMENTS FOR MOBILE HOME DEVELOPMENTS
Prepared by: ABB1 ELECTRICAL SERVICE REQUIREMENTS FOR MOBILE HOME DEVELOPMENTS 052521 Asset Type: Electric Metering Function: Construction Issued by: Quoc Hoang (QxH1) Date: 07-01-16 Rev. #06: This document
A. Shop Drawing submittals shall include, but not be limited to, the following:
SECTION 26 05 53 IDENTIFICATION FOR ELECTRICAL SYSTEMS PART 1 - GENERAL 1.1 RELATED DOCUMENTS: A. The Conditions of the Contract and applicable requirements of Divisions 0 and 1 and Section 26 00 01, Electrical
Minimum Standards for Data/Voice Infrastructure in New Building Construction
UNIVERSITY OF WATERLOO Minimum Standards for Data/Voice Infrastructure in New Building Construction 12/17/2012 Offices 1. Two Work Area Outlets (WAO) on opposite walls, each with 2 jacks 2. Each WAO shall
REQUIREMENTS AND SPECIFICATIONS FOR HIGH VOLTAGE CUSTOMER BUILT FACILITIES PEPCO ENGINEERING
REQUIREMENTS AND SPECIFICATIONS FOR HIGH VOLTAGE CUSTOMER BUILT FACILITIES PEPCO ENGINEERING Revised October, 2013 TABLE OF CONTENTS 1.0 INTRODUCTION... 3 2.0 REQUIRED DRAWINGS... 3 2.1 Site Plan... 3
Electrical Service Guidelines
Electrical Service Guidelines Middle Tennessee Electric Membership Corporation Revised: May 23, 2013 MTEMC's Electrical Guidelines TABLE OF CONTENTS Right-of-Way Clearance Guide 3 MTEMC Requirements 4
Residential Electrical Inspection. Checklist
443 Lafayette Road N. St. Paul, Minnesota 55155 www.doli.state.mn.us Residential Electrical Inspection (651) 284-5064 1-800-DIAL-DLI Fax: (651) 284-5743 TTY: (651) 297-4198 Checklist Generally, Minnesota
Element D Services Electrical
Service and PART 1 - GENERAL 1.01 OVERVIEW A. This Section includes design standards and requirements for electrical service and distribution. This is a design standard and is not intended to be used as
CTI TECHNICAL BULLETIN Number 9: A publication of the Cable Tray Institute
CTI TECHNICAL BULLETIN Number 9: A publication of the Cable Tray Institute Cable Tray Wiring Systems Have Many Cost Advantages Cost is usually a major consideration in the selection of a wiring system.
Cable Supports. Requirements for Cable Supports in the National Electrical Code reads as follows:
QA1 General Information are used to support cables in vertical raceways or risers. Cable supports relieve the strain that would be placed on terminations, the interior of panels, or other devices to which
INSPECTION GUDELINES
GENERAL REQUIREMENTS Building permit and approved set of plans Building permit on the card is the same as on the route "If this is not the first inspection, read inspection records and notes on permit
Carlon Carflex Liquidtight Flexible Tubing
Carlon Carflex Liquidtight Flexible Tubing Carflex Carflex X-Flex Fittings Cord Grips Pre-Wired Whips www.carlon.com 3 Carflex Liquidtight Flexible Conduit Carflex Liquidtight Flexible Nonmetallic Conduit
How to Estimate the Cost of a Clean Room and Data Center Equipment Electrical Work. Section 2 Types of Methods of Measurements page 4
How to Estimate the Cost of a Clean Room and Data Center Equipment Electrical Work Table of Contents Section 1 Introduction page 3 Section 2 Types of Methods of Measurements page 4 Section 3 Project Specific
Residential Electrical Inspection Checklist
Residential Electrical Inspection Checklist Based on the 2008 National Electrical Code Generally, Minnesota law requires all electrical work to be performed by licensed, bonded and insured electrical contractors
Electrical Wiring Technical Bulletin
Electrical Wiring Technical Bulletin Overview In general, SIP construction is easier and more cost effective when things are planned and thought out before the panels are manufactured. This process will
SPECIFICATIONS FOR THE INSTALLATION OF FIRE ALARM SYSTEMS, SPRINKLER SYSTEMS, AND MASTER BOXES IN THE POQUONNOCK BRIDGE FIRE DISTRICT
SPECIFICATIONS FOR THE INSTALLATION OF FIRE ALARM SYSTEMS, SPRINKLER SYSTEMS, AND MASTER BOXES IN THE POQUONNOCK BRIDGE FIRE DISTRICT The purpose of these specifications is to insure that there are minimum
8146/5 Series Breaker Panelboards
8146/5 Series Breaker Panelboards DISTRIBUTION BREAKER PANELBOARDS FOR HAZARDOUS & CORROSIVE ENVIRONMENTS Breaker Panels Features: Wide variety of Flameproof branch circuit breakers for Zone 1 & Division
DESIGN AND CONSTRUCTION STANDARDS SPECIFICATION GUIDELINES 33 70 00
SECTION 33 70 00 - ELECTRICAL DISTRIBUTION CONCRETE ENCASED PRIMARY DUCTBANK SYSTEMS Duct Banks shall be installed by qualified electrical contractors. Provide type EB PVC 5 inch duct equal to Carlon #68716
ELECTRIC METERING COMMERCIAL & INDUSTRIAL
ELECTRIC METERING COMMERCIAL & 1.0 INDEX 1.0 INDEX 2.0 SCOPE 3.0 GENERAL REQUIREMENTS 4.0 METER LOCATIONS 5.0 UNDERGROUND TERMINATIONS 6.0 METERING TRANSFORMER ENCLOSURES 7.0 SINGLE CUSTOMER METER INSTALLATIONS
FIRE ALARM SYSTEM. A. Shop drawings shall be submitted as follows: 1. Manufacturer's published literature. for aspproval.
Polk School District Specifications for the New Fire Alarm in the Existing Building Eastside Elementary School FIRE ALARM SYSTEM 1.01 SUBMITTALS A. Shop drawings shall be submitted as follows: 1. Manufacturer's
SECTION 17400 ACCESS CONTROL SYSTEM. CONDITIONS OF THE CONTRACT AND DIVISION 1, as applicable, apply to this Section.
SECTION 17400 ACCESS CONTROL SYSTEM CONDITIONS OF THE CONTRACT AND DIVISION 1, as applicable, apply to this Section. PART 1 - GENERAL 1.1 RELATED WORK A. 16060 Grounding and Bonding B. 16070 Electrical
GENERAL ELECTRICAL REQUIREMENTS
GENERAL ELECTRICAL REQUIREMENTS RECEPTACLE SPACING Within 6-feet of the edge of any door HABITABLE Not more than 12-feet apart along wall ROOMS: At all wall spaces 24 or more wide Within 24 of edge of
Electrical Wiring Methods, Components and Equipment for General Use. Approved for Public Release; Further Dissemination Unlimited
Electrical Wiring Methods, Components and Equipment for General Use Approved for Public Release; Further Dissemination Unlimited At the completion of this unit you shall be able to: 1. Utilize section
HIGHLAND VALLEY SUPPLY, INC STANDARD TERMS AND CONDITONS OF SALE
Electrical Conduit & Fittings Catalog HIGHLAND VALLEY SUPPLY, INC STANDARD TERMS AND CONDITONS OF SALE Payment Terms: Payment terms are printed on every invoice. Invoices not paid in full by the net due
1.1 SYSTEM DESCRIPTION.1 Data system includes data outlets and wiring for office and school applications.
Issued 2005/06/01 Section 16743 Data System Page 1 of 7 PART 1 GENERAL 1.1 SYSTEM DESCRIPTION.1 Data system includes data outlets and wiring for office and school applications..2 Data system equipment
East Central College 14434.03 HANSEN HALL LEVEL 300/400 RENOVATIONS PACKAGE
SECTION 260519 - BUILDING WIRE AND CABLE PART 1 - GENERAL 1.1 WORK INCLUDES A. Base and Alternate Bids: 1. Contractor Provide: a. Building wire and cable as shown on drawings or specified including feeders,
AMERICAN FITTINGS. Corporation. SPEC-grade. Rigid-IMC Connectors Compression Type - (No Thread)
Connectors / Compression Type Size Range: 1/2 to 5 Rigid-IMC Connectors Compression Type - (No Thread) Industrial specification grade, screw machined steel, zinc plated UL Listed RIN TIGHT and Concrete
ADOPTION OF THE NATIONAL ELECTRICAL CODE, 2005
ADOPTION OF THE NATIONAL ELECTRICAL CODE, 2005 That a certain code, three (3) copies of which are now on file and have been on file for a period of not less than 21 days in the office of the Village Clerk
American National Standard. Fittings, Cast Metal Boxes, and Conduit Bodies for Conduit, Electrical Metallic Tubing, and Cable
ANSI/NEMA FB 1-2012 Revision of ANSI FB 1-2007 American National Standard Fittings, Cast Metal Boxes, and Conduit Bodies for Conduit, Electrical Metallic Tubing, and Cable Secretariat: National Electrical
Residential Electrical Inspection. Checklist
Electrical Licensing and Inspection 443 Lafayette Road North St. Paul, Minnesota 55155-4342 www.doli.state.mn.us 651-284-5064 Fax: 651-284-5743 TTY: 651-297-4198 1-800-DIAL-DLI Residential Electrical Inspection
SPACE TYPE: AUTOMATED DATA PROCESSING CENTER (ADP) (MAINFRAME)
SPACE TYPE: AUTOMATED DATA PROCESSING CENTER (ADP) (MAINFRAME) Construction Criteria The unit costs for ADP Mainframe space types are based on the construction quality and design features in the following
**ATTENTION** WE DO NOT PROMOTE OR ENCOURAGE YOU TO DO YOUR OWN ELECTRICAL WIRING!!! IT IS BY FAR THE MOST DANGEROUS THING YOU CAN ATTEMPT
**ATTENTION** WE DO NOT PROMOTE OR ENCOURAGE YOU TO DO YOUR OWN ELECTRICAL WIRING!!! IT IS BY FAR THE MOST DANGEROUS THING YOU CAN ATTEMPT. YOU COULD PUT YOUR FAMILY AND WORLDLY POSSESSIONS IN DANGER!!!
Questions and Answers for Heating and A/C Contractors
1. How do we accomplish grounding of furnaces and / or water heaters on two wire circuits? 250.134 Equipment Fastened in Place or Connected by Permanent Wiring Methods (Fixed) Grounding. Unless grounded
Packaged Terminal Air Conditioner Wall Sleeve Installation
Installation & Maintenance Data IM 1196 Group: PTAC Part Number: 910141799 Date: October 2013 Packaged Terminal Air Conditioner Installation x 42" PGAN with Top-Mounted Hydronic Heat Note: Installation
Electrical. This section applies to the design and installation of building power distribution systems.
Basis of Design This section applies to the design and installation of building power distribution systems. Design Criteria This section contains the architectural, structural and mechanical provisions
Crawford Inspection Services C.C.B. # 76914 www.crawfordinspections.com
Crawford Inspection Services C.C.B. # 76914 www.crawfordinspections.com Portland Area PO Box 665 West Linn, OR 97068 Ph: (503) 650-6957 Salem Area 5434 River Rd. N; #192 Keizer, OR 97303 Ph: (503) 362-5809
SECTION 27 05 36 CABLE TRAYS FOR COMMUNICATIONS SYSTEMS
SECTION 27 05 36 CABLE TRAYS FOR COMMUNICATIONS SYSTEMS PART 1 GENERAL 1.01 DESCRIPTION A. The work covered by this section of the Specifications includes all labor necessary to perform and complete such
Please check with your local inspection authority for any additional requirements before installation.
Specifications for Residential Overhead Electric Service Installation This brochure addresses most typical residential overhead service installations. Variances for the following specifications must be
MONTGOMERY COUNTY EXECUTIVE REGULATION Offices of the County Executive. 101 Monroe Street. Rockville, Maryland 20850
Montgomery County Regulation on: ADOPTION OF THE 2008 NATIONAL ELECTRICAL CODE DEPARTMENT OF PERMITTING SERVICES Issued by County Executive Regulation # 15-09 Authority: Code Section 17-2 and 17-3 Supersedes:
SECTION 23 05 29 - HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT
SECTION 23 05 29 - HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Pipe hangers and supports. 2. Hanger rods. 3. Inserts. 4. Flashing. 5. Equipment
BENDING CONDUIT / TUBING Jan 2012 USING HAND BENDERS
BENDING CONDUIT / TUBING Jan 2012 USING HAND BENDERS By Bill Bamford Provided by: Resources for Electricians The ability to bend conduit and tubing (raceways) is a requirement for all electricians. This
University of North Carolina at Charlotte Design and Construction Manual Section 2, Division 26 Electrical SECTION 2 DIVISION 26 ELECTRICAL
SECTION 2 DIVISION 26 ELECTRICAL DIVISION 26 - ELECTRICAL Note: This is a guide for Designers only. Contents shall not be used in lieu of specifications as part of the Designer s contract documents SECTION
SECTION 16110 CONDUITS, RACEWAYS, FITTINGS AND CABLE TRAYS
SECTION 16110 CONDUITS, RACEWAYS, FITTINGS AND CABLE TRAYS PART 1 - GENERAL 1.01 REQUIREMENTS A. The general provisions of the Contract, including General and Supplementary Conditions and General Requirements,
TYPICAL WIRING OF METER SOCKET FOR SINGLE PHASE, THREE WIRE OVERHEAD SERVICE
TYPICAL WIRING OF METER SOCKET FOR SINGLE PHASE, THREE WIRE OVERHEAD SERVICE A. GENERAL NOTES: Service entrance line and load conductors, conduit straps, weatherhead, lock nuts, bushings, connectors, and
Pathways For Electronic Safety and Security Addendum 5, June 21, 2012 Section 28 05 28 Page 1 of 18
PART 1 - GENERAL 1.1 SCOPE OF WORK SECTION 28 05 28 PATHWAYS FOR ELECTRONIC SAFETY AND SECURITY A. Provide electronic security systems pathways as specified in this Section and as shown diagrammatically
DESIGN AND INSTALLATION OF RESIDENTIAL FLEXIBLE DUCTWORK SYSTEMS
DESIGN AND INSTALLATION OF RESIDENTIAL FLEXIBLE DUCTWORK SYSTEMS A. SCOPE 1. This information is intended to assist contractors, installers and code officials in the proper design and installation of flexible
AT&T. PARTNER Plus Door Phone. Installation and Operation Manual
AT&T PARTNER Plus Door Phone Installation and Operation Manual Copyright 1990 AT&T All Rights Reserved Printed in U.S.A. CIC# 999-500-317 OII722050-051 Issue 1 October 1990 PARTNER Plus Door Phone is a
Entrances to and from Electrical Equipment Rooms
Electrical Code Requirements for Commercial and Residential Buildings Presented by Bob Nuzzi State Electrical Inspector Entrances to and from Electrical Equipment Rooms 2005 NEC Section 110.26(C)(2) Large
BERTHOLD ELECTRIC GENERATOR CONNECTION CABINET
BERTHOLD ELECTRIC GENERATOR CONNECTION CABINET Berthold Electric Company s Generator Connection Cabinet provides a quick and convenient station to connect a portable generator to a facility s main service
DIVISION 26 - ELECTRICAL SECTION 26 05 20 CABLES FOR INSTRUMENTATION
DIVISION 26 - ELECTRICAL PART 1 - GENERAL 1.01 SUMMARY A. Section Includes 1. Instrumentation Cables 1.02 SUBMITTALS A. Submit in accordance with requirements of Section 01 33 00. B. Product Data: Submit
Electrical Grounding. Appendix C
Appendix C Electrical Grounding Low-Voltage Equipment Grounding The most frequently cited Office of Safety and Health Administration (OSHA) electrical violation is improper occupational grounding of equipment
SECTION 08360 SECTIONAL OVERHEAD DOORS 521 SERIES ALUMINUM SECTIONAL OVERHEAD DOORS
SECTION 08360 SECTIONAL OVERHEAD DOORS 521 SERIES ALUMINUM SECTIONAL OVERHEAD DOORS Display hidden notes to specifier by using Tools / Options / View / Hidden Text. On newer versions of Microsoft Word
OASIS-PLUS 120V READ ALL INSTRUCTIONS BEFORE OPERATING READ ALL INSTRUCTIONS BEFORE OPERATING OZONE IS A POWERFUL OXIDIZER AND MUST BE USED WITH CARE
OASIS-PLUS 120V INFORMATION & OPERATING INSTRUCTIONS READ ALL INSTRUCTIONS BEFORE OPERATING READ ALL INSTRUCTIONS BEFORE OPERATING OZONE IS A POWERFUL OXIDIZER AND MUST BE USED WITH CARE 56041852 WARNING:
CABLE TRENCH INSTALLATION GUIDE
1.0 INDEX 1.0 INDEX 2.0 PURPOSE 3.0 GENERAL INFORMATION 4.0 PLANNING INFORMATION 5.0 CREW INFORMATION 6.0 CONTRACTOR INFORMATION 7.0 PRECASTED/ POURED-IN-PLACE TRENCH DRAWINGS 2.0 PURPOSE This standard
Mechanical, Plumbing, and Fire Protection Conditions
Mechanical, Plumbing, and Fire Protection Conditions Mechanical Conditions The mechanical systems within the building consist of a combination of the original 1926 systems and renovations that occurred
ROOF DRAINS TABLE OF CONTENTS
Pictorial Index Product Recommendations Roof Drain Selection Factors Sizing Placement Material & Characteristics Pipe Connection Commonly Specified Options Typical Installations TABLE OF CONTENTS ROOF
Trial Exams C. Standards and Regulations. Examination No: GH-08-C- 1 hour and 5 minutes plus 10 minutes reading time
Trial Exams C Standards and Regulations Examination No: GH-08-C- This test is intended to gauge your knowledge of essential information contained within AS/CA S009:2013. To qualify for an allpication to
HMI display Installation Guide
HMI display Installation Guide Product Description Specifications Important Information o Package Contents o Related Documents o Accessories Cautions and Warnings Mounting and Dimensions o BAC-DIS-ENC
Top Commercial / Residential Electrical Requirements *
Department of Community Development Building Division 4800 West 92 nd Avenue Westminster, Colorado 80031 For Information call (303) 658-2075 Fax (303) 706-3922 www.westminsterpermits.com Top Commercial
Fire Alarm System Plans Review Checklist Property location Date of Review
Fire Alarm System Plans Review Checklist Property location Date of Review 1. Is application completed in entirety? 2. Are the plans review fee submitted with the application? 3. Does floor plan include
CEILING CASSETTE FAN COIL UNIT
CEILING CASSETTE FAN COIL UNIT Operation and Installation Manual MHCFC4W-04, 08, 12, 16 Four way ceiling cassette fan coil unit Please read this manual before using the fan coil unit. Installation and
Chapter 3 Pre-Installation, Foundations and Piers
Chapter 3 Pre-Installation, Foundations and Piers 3-1 Pre-Installation Establishes the minimum requirements for the siting, design, materials, access, and installation of manufactured dwellings, accessory
EFFECTIVE FEBRUARY 2014. note: drainage permit required to call for a dampproof inspection
EFFECTIVE FEBRUARY 2014 note: drainage permit required to call for a dampproof inspection 1. ROOF DRAINS/DECK DRAINS (INTERIOR ) All roof and deck drains within the perimeter of the building shall be APPROVED
Solar Panel Installations
Solar Panel Installations Page 1 of 6 SINGLE-FAMILY RESIDENTIAL CHECKLIST City of Hayward Development Services Department Revised: 7-09-15 PERMIT REQUIREMENTS Permits are required for all solar panel installations.
PALM BEACH COUNTY AMENDMENTS TO THE NATIONAL ELECTRICAL CODE, 1999 EDITION
PALM BEACH COUNTY AMENDMENTS TO THE NATIONAL ELECTRICAL CODE, 1999 EDITION CODING: Words underlined are additions to the 1999 NEC Words stricken are deletions to the 1999 NEC Adopted by Ordinance 99-73
FOUNDATION INSULATING SYSTEM, INCLUDING WATERPROOFING AND DAMP PROOFING
FOUNDATION INSULATING SYSTEM, INCLUDING WATERPROOFING AND DAMP PROOFING insulation installed on foundation walls must be separated from the building interior with a code approved thermal barrier. Foam
3. Contractor shall ensure that all permits are obtained prior to any construction. Contractor shall be responsible for all utility fees.
The following shall serve as the minimum requirements for contractors performing work in relation to the Authority s potable water and sanitary sewer system(s), appurtenances and service connections. General:
Errata NFPA 70. Proposed 2014 Edition
Errata NFPA 70 National Electrical Code (Report on Proposals) Reference: 12-109 (Log #1618) Panel Meeting Action Proposed 2014 Edition The National Electrical Code Technical Correlating Committee notes
Significant Changes in the 2011 NEC Prepared by Bryan Holland City of North Port
Significant Changes in the 2011 NEC Prepared by Bryan Holland City of North Port Code-Wide Code Change Section 90.5(C). Fine Print Notes are now referred to as "Informational Notes." The purpose, intent,
COMMERCIAL COOKING HOODS, VENTILATION & FIRE SUPPRESSION SYSTEM GUIDELINES AND PROCEDURES
COMMERCIAL COOKING HOODS, VENTILATION & FIRE SUPPRESSION SYSTEM GUIDELINES AND PROCEDURES These guidelines are to be used for ALL commercial cooking hoods, ventilation systems and related fire suppression
Session 14 Cable Support Systems
Session 14 Cable Support Systems Cable Support Systems in the IEC World A new IEC Standard, IEC61537 2001 has been developed If full details of the cabling layout are available then the likely cable load
Envelope INSULATION BATT (2) Avoid Using Batt Insulation With Metal Framing. Pressure or Friction Fit
R-H-DI1 INSULATION BATT NR-E-IB1 Avoid Using Batt Insulation With Metal Framing Batt insulation should not be used with metal framing systems. Although it is common to see fiberglass batt insulation installed
NEW SERVICE INSTALLATION STEPS. Common Slow Downs. Other Necessary Steps
NEW SERVICE INSTALLATION STEPS Here is the step-by-step process required to fulfill your service installation request. Please take a few minutes to review the steps, become familiar with key milestones
FIX TURE CARRI ERS. 140(a) MPB-2011-USA
FIXTURE CARRIERS STRUCTURAL FEET The feet are heavy duty cast ductile iron and invertible. No distinction is necessary between right and left hand. Each foot wraps around the specially formed edge of the
CLEANOUT FEATURES. KLEENATRON II Features CLEANOUTS
CLEANOUT FEATURES KLEENATRON II Features JOSAM KLEENATRON II Cleanouts incorporate features developed to meet the latest in building construction methods. These features ensure the specifier, installer
Carlon Zip Box Blue Switch and Outlet Boxes
Carlon Zip Box Blue Switch and Outlet Boxes Nonmetallic: Adjustable One-Gang 2-, 3-, 4-Gang Old Work Ceiling Boxes SuperBlue Hard Shell Covers Metallic: Adjustable Ceiling Boxes Innovative Solutions For