CULVER LINE REHABILITATION PRESENTATION TO COMMUNITY BOARD 6 TRANSPORTATION COMMITTEE NOVEMBER 15, 2007

Size: px
Start display at page:

Download "CULVER LINE REHABILITATION PRESENTATION TO COMMUNITY BOARD 6 TRANSPORTATION COMMITTEE NOVEMBER 15, 2007"

Transcription

1 CULVER LINE REHABILITATION PRESENTATION TO COMMUNITY BOARD 6 TRANSPORTATION COMMITTEE NOVEMBER 15, 2007

2 Culver Line Background Line opened in 1933 Viaduct located between Carroll St. Station and 4 th Av 9 th St Station High point of structure is 90 as it spans the Gowanus Canal our tracks primarily ballast Concrete encased steel structure Served by and G Lines

3 Structural rehabilitation of mile-long Culver Viaduct

4 Current Conditions - Viaduct ailed deck waterproofing - Concrete spalling and exposed steel

5 Wrapped Structure

6 Elevation View

7 Current Conditions - Viaduct At Smith 9 th St. Station

8 4 Track Railroad

9 OCEAN PARKWAY VIADUCT Current Conditions - Signals 4 th Avenue Interlocking

10 Similar Work: Ocean Pkwy. Station

11 Similar Work: Ocean Pkwy. Station

12 Similar Work: Ocean Pkwy. Station

13 Installation of Deck Slab at Ocean Pkwy.

14 Installation of Deck Waterproofing at Ocean Pkwy. Station

15 Installation of New Low-Vibration Track at Ocean Pkwy. Station

16 Similar Work: lushing Line New Switches

17 Similar Work: lushing Line New Switches

18 Canopy at Smith 9 th Sts. Station

19 Smith-9 th St Station Station Overview South Bound Platform North Bound Platform Gowanus Canal Upper Intermediate Landing Control House Lower Intermediate Landing 9th Street Smith Street

20 n.t.s. South Elevation-Day View

21 n.t.s. South Elevation-Night View

22

23 4 th Av. 9 th St. Station

24 Existing Exterior Elevation 4 th Avenue Station

25 Existing Platform

26 Proposed Restoration

27

28

29 Church Av B4 B4 B3 B3 B2 B2 B1 B1 Culver Viaduct Existing Service To Manhattan N Work Area Bergen Bergen St St Carroll Carroll St St 7 Av Av St-Prospect Prospect Park Park ourth Av Line Smith Smith-9 9 Sts Sts 4 Av Av ort ort Hamilton Hamilton Pkwy Pkwy Legend Platform 9 St St MR Portal Portal lower lower level level G G B5 Work Area To Coney Island 11/2007 upper upper level level

30 lower level upper level B4 B4 B3 B St-Prospect Prospect Park Park Church Av ort ort Hamilton Hamilton Pkwy Pkwy B1 B1 B2 B2 Culver Viaduct Phase 1 Approx. 15 Months To Manhattan N Carroll Carroll St St Smith Smith-9 9 Sts Sts 4 Av Av-9 9 St St 7 Av Av Bergen Bergen St St 9 St St ourth Av Line MR G Project Award: all 2008 Gextended to Church Av for duration of project Service normal Portal Portal G Platform B5 Legend Track Out of Service Structural Work Area G G To Coney Island lower lower level level upper upper level level

31 15 15 St-Prospect Prospect Park Park Church Av ort ort Hamilton Hamilton Pkwy Pkwy B1 B1 B2 B2 B3 B3 B4 B4 Culver Viaduct Phase 2A Approx. 4 Months To Manhattan N Northbound local track out of service, G on northbound express track between Church Av and Smith-9 Sts Only southbound service to 15-Prospect Park and ort Hamilton Pkwy 4 Av northbound service via temporary platform Smith-9 Sts Station closed for station rehab (shuttle bus provided) G G Bergen Bergen St St Carroll Carroll St St 4 Av Av-9 9 St St 7 Av Av 9 St St ourth Av Line MR Smith Smith-9 9 Sts Sts Closed Closed G Platform Legend Closed Platform Temporary Platform Track Out of Service Hardrail Connection New Switch To Coney Island Backride lower level upper level upper upper level level lower lower level level

32 Smith-9 Sts Station Rehabilitation Shuttle Bus During Station Closure SOUTH BROOKLYN SACKETT ST 1 PL Carroll Park 2 PL COURT ST G CARROLL ST SMITH ST 2 ST UNION ST RED HOOK W 9 ST GARNET ST G Gowanus Canal 2 AV Northbound Shuttle Bus to 2nd St Red Hook Recreational Area Southbound Shuttle Bus to 4th Av Subway Station Shuttle Bus Stop Gowanus Creek 9 ST 10 ST 3 AV MR 4 AV PARK SLOPE 5 AV n Shuttle Bus Stop and Terminal 10 ST 5 AV

33 Culver Viaduct Phase 2B Approx. 8 Months To Manhattan N Gback on local northbound track, except at Smith-9 Sts Service normal south of Smith-9 Sts Smith-9 Sts reopened after 5 months of this phase (total closure 9 months) Reopened Smith-9 Sts has G-only service northbound via temporary platform and G service southbound Bergen Bergen St St 9 St St Carroll Carroll St St 7 Av Av St-Prospect Prospect Park Park ourth Av Line MR lower lower level level upper upper level level 4 Av Av-9 9 St St Church Av ort ort Hamilton Hamilton Pkwy Pkwy B1 B1 B2 B2 B3 B3 B4 B4 G lower level Smith Smith-9 9 Sts Sts G-Only Only n/b n/b G Platform Temporary Platform Track Out of Service Hardrail Connection Legend upper level G To Coney Island

34 Culver Viaduct Phase 3A Approx. 5 Months To Manhattan N Carroll Carroll St St Smith Smith-9 9 Sts Sts G-only only s/b s/b 4 Av Av-9 9 St St 7 Av Av Bergen Bergen St St St-Prospect Prospect Park Park Church Av ort ort Hamilton Hamilton Pkwy Pkwy B1 B1 9 St St B2 B2 B3 B3 B4 B4 ourth Av Line MR G Platform Track Out of Service Legend Southbound local track out of service, G southbound on express track between Smith-9 Sts and Church Av Only northbound service to 15 St-Prospect Park and ort Hamilton Pkwy Temporary platforms at Smith-9 Sts and 4 Av for southbound service At Smith-9 Sts G-only service southbound lower lower level level upper upper level level Temporary Platform Hardrail Connection New Switch Backride G lower level upper upper level G To Coney Island

35 lower level upper upper level St-Prospect Prospect Park Park Church Av ort ort Hamilton Hamilton Pkwy Pkwy B1 B1 B2 B2 B4 B4 B3 B3 Culver Viaduct Phase 3B Approx. 10 Months To Manhattan N Carroll Carroll St St Smith Smith-9 9 Sts Sts G-only only s/b s/b 4 Av Av-9 9 St St 7 Av Av Bergen Bergen St St 9 St St ourth Av Line MR G Legend Platform Temporary Platform Track Out of Service Hardrail Connection Gback on local track south of Smith- 9 Sts, providing normal service Smith-9 Sts G-only service southbound via temporary platform Northbound service normal G G To Coney Island lower lower level level upper upper level level

36 B4 B4 B3 B St-Prospect Prospect Park Park B1 B1 B2 B2 ort ort Hamilton Hamilton Pkwy Pkwy Church Av Culver Viaduct Phase 4 3 Months To Manhattan N G Carroll Carroll St St Smith Smith-9 9 Sts Sts 4 Av Av-9 9 St St 7 Av Av Bergen Bergen St St 9 St St ourth Av Line MR G G Platform Legend Track Out of Service New Switch G Gback on local tracks, serving all stations G continues to be extended to Church Av lower level upper level To Coney Island lower lower level level upper upper level level

Project Information. New Hope - Lambertville Toll Bridge - Pavement Rehabilitation & Approach Bridges Repairs -

Project Information. New Hope - Lambertville Toll Bridge - Pavement Rehabilitation & Approach Bridges Repairs - Project Information Existing Conditions Cracked and settled pavement. Structural failure within the asphalt pavement section. Anticipated Project Elements Reconstruction of all asphalt pavement on US Route

More information

The Corporation of the TOWN OF MILTON

The Corporation of the TOWN OF MILTON The Corporation of the TOWN OF MILTON Report to: From: Mayor G. A. Krantz & Members of Council M. Paul Cripps, P. Eng., Director, Engineering Services Date: November 11, 2013 Report No. ENG-039-13 Subject:

More information

New York Building Congress

New York Building Congress New York Building Congress November 7, 2013 Frederick E. Smith, P.E. Senior Vice President and Chief Engineer, CPM What is NYCT 228 miles of structure 432 miles of tunnel lighting 722 miles of track (630

More information

Second Avenue Subway. Quarterly Public Workshop. October 21, 2015

Second Avenue Subway. Quarterly Public Workshop. October 21, 2015 Second Avenue Subway Quarterly Public Workshop October 21, 2015 1 Current Project Status Overall Construction Progress is 87.8% complete as of 10/1/2015. All 10 SAS Contracts have been awarded for Phase

More information

Service You Can Count On: An Inside Look at How the MTA Invests to Move Customers Safely and Reliably..info

Service You Can Count On: An Inside Look at How the MTA Invests to Move Customers Safely and Reliably..info Service You Can Count On: An Inside Look at How the MTA Invests to Move Customers Safely and Reliably.info February 2013 Reliable Service. It means you can depend on the MTA to get where you need to go,when

More information

3. TRANSIT SERVICES 3.1 BUSES

3. TRANSIT SERVICES 3.1 BUSES 3. TRANSIT SERVICES To provide competitive levels of mobility and access service, transit operations need to perform well on a number of service quality measures. Some of the most important are: Effective

More information

REBUILDING THE CTA FORREST CLAYPOOL, PRESIDENT CHRIS BUSHELL, SVP, INFRASTRUCTURE

REBUILDING THE CTA FORREST CLAYPOOL, PRESIDENT CHRIS BUSHELL, SVP, INFRASTRUCTURE REBUILDING THE CTA FORREST CLAYPOOL, PRESIDENT CHRIS BUSHELL, SVP, INFRASTRUCTURE Our Commitment: Increasing Investment Despite Lean Times Even while facing a $277M deficit, we are finding ways to rebuild

More information

Measuring the Street:

Measuring the Street: Measuring the Street: New Metrics for 21st Century Streets 1 Measuring the Street: New Metrics for 21st Century Streets New York City s streets are constantly called on to the meet new and varied needs

More information

GEORGE J. CAMBOURAKIS, P.E., C. ENG. PRESIDENT & CHIEF STRUCTURAL ENGINEER

GEORGE J. CAMBOURAKIS, P.E., C. ENG. PRESIDENT & CHIEF STRUCTURAL ENGINEER GEORGE J. CAMBOURAKIS, P.E., C. ENG. PRESIDENT & CHIEF STRUCTURAL ENGINEER Professional Experience: Pride and Passion in the Art of Structural Engineering since 1979. Professional Registration: Professional

More information

For Sale - $11,000,000 - Negotiable Excellent User Opportunity -

For Sale - $11,000,000 - Negotiable Excellent User Opportunity - 4770 White Plains Road Bronx, New York For Sale - $11,000,000 - Negotiable Excellent User Opportunity - Jerry Houlihan GHP Office Realty One West Red Oak Lane White Plains, New York 10604 Phone: 914.642.9300

More information

PROJECT WEBSITE: www.torranceca.gov/23009.htm. A. Project Map - see map attached at end of this document

PROJECT WEBSITE: www.torranceca.gov/23009.htm. A. Project Map - see map attached at end of this document (with Citywide Cross-Gutter Improvements and Crenshaw Blvd Repairs) COMMUNITY MEETING March 3, 2014 7:00 PM Bartlett Senior Citizens Center, Ritsema Hall - 2nd floor 1318 Cravens Avenue, Torrance, California

More information

Queens Midtown Tunnel Repair, Restoration, Rehabilitation Projects. Manhattan Community Board 6 Transportation Committee - June 2, 2014

Queens Midtown Tunnel Repair, Restoration, Rehabilitation Projects. Manhattan Community Board 6 Transportation Committee - June 2, 2014 Queens Midtown Tunnel Repair, Restoration, Rehabilitation Projects Manhattan Community Board 6 Transportation Committee - June 2, 2014 Opened to traffic in 1940 Two parallel tubes (North & South), each

More information

Emergency Communication Bulletin 2010-11 School Year

Emergency Communication Bulletin 2010-11 School Year Emergency Communication Bulletin 2010-11 School Year NEWS SOURCES * SCHOOL CLOSURE MESSAGES * TRANSPORATION Do you know where you can find updated school closure information? School closure messages and

More information

Evanston Main Street Station TOD Plan and Study. Appendix A.1: Station Area Existing Conditions

Evanston Main Street Station TOD Plan and Study. Appendix A.1: Station Area Existing Conditions Evanston Main Street Station TOD Plan and Study Appendix A.1: Station Area Existing Conditions EvanstonMainStreetStation TODPlanandStudy A 1 AppendixA.1: ExistingConditions Table of Contents Station Locations

More information

REQUEST TO QUALIFY (RTQ) INFORMATION FOR

REQUEST TO QUALIFY (RTQ) INFORMATION FOR I. INTRODUCTION: REQUEST TO QUALIFY (RTQ) INFORMATION FOR GEORGE WASHINGTON BRIDGE REPLACEMENT OF THE PIP HELIX RAMP AND REHABILITATION OF UPPER LEVEL SPANS OVER NJ ANCHORAGE AND HUDSON TERRACE CONTRACT

More information

Disputes and Claims. 3 Processes Dispute Resolution and Administrative Claims Process

Disputes and Claims. 3 Processes Dispute Resolution and Administrative Claims Process Disputes and Claims 3 Processes Dispute Resolution and Administrative Claims Process Default Process C&MS 108.02 Partnering OR PN 108 -Dispute Review Board (DRB) Considered for use on projects over $20

More information

The Rehabilitation Alternative Huey P. Long Bridge Case Study. Bruce E. Peterson, P.E. Project Manager Modjeski and Masters, Inc.

The Rehabilitation Alternative Huey P. Long Bridge Case Study. Bruce E. Peterson, P.E. Project Manager Modjeski and Masters, Inc. The Rehabilitation Alternative Huey P. Long Bridge Case Study Bruce E. Peterson, P.E. Project Manager Modjeski and Masters, Inc. March 22, 2010 Replacement vs. Rehabilitation Project Background Introduction

More information

IDOT Suspends Non-Emergency Road Work for Fourth of July Holiday Weekend

IDOT Suspends Non-Emergency Road Work for Fourth of July Holiday Weekend State of Illinois Bruce Rauner, Governor Illinois Department of Transportation Randall S. Blankenhorn, Secretary FOR IMMEDIATE RELEASE: CONTACT: June 30, 2015 Brian Williamsen 309.671.4854 Carson Quinn

More information

Notice of Comment Period

Notice of Comment Period Notice of Comment Period Topic: Transportation Improvement Program Amendments Period: April 6, 2009 through April 17, 2009 Comment Period: The New York Metropolitan Transportation Council (NYMTC) announces

More information

5 ALTERNATIVE SOLUTIONS AND EVALUATION

5 ALTERNATIVE SOLUTIONS AND EVALUATION Page 23 5 ALTERNATIVE SOLUTIONS AND EVALUATION The process used for the assessment and evaluation of the alternatives follows the procedures of the Municipal Class EA, as described below: Identify a reasonable

More information

Land Area: - Status: Built 1968. Parking: Free Surface Spaces. Stories: 1

Land Area: - Status: Built 1968. Parking: Free Surface Spaces. Stories: 1 4100 1st Ave Building B Brooklyn, NY 11232 Status: Built 1910 Building Size: 242,400 SF Land Area: - Stories: 6 Space Avail: 19,000 SF Max Contig: 19,000 SF Smallest Space: 19,000 SF Rent/SF/Yr: $6.50

More information

GED PLUS PROGRAM DIRECTORY

GED PLUS PROGRAM DIRECTORY GED PLUS PROGRAM DIRECTORY BRONX BROOKLYN MANHATTAN QUEENS STATEN ISLAND GED Plus helps students earn their GED plus prepares them for college and career options. Students 18-21 years old can choose to

More information

Successful Approach to the Repair of Reinforced Concrete Support Structures in Delayed Coking Units

Successful Approach to the Repair of Reinforced Concrete Support Structures in Delayed Coking Units Successful Approach to the Repair of Reinforced Concrete Support Structures in Delayed Coking Units Thomas Kline Director- Concrete Repair Solutions STRUCTURAL TECHNOLOGIES, LLC Houston, Texas USA November

More information

Exhibit Book Metro-North Railroad Committee Meeting 3/23/2015. Table of Contents: April 26 Schedule Change - Page 2

Exhibit Book Metro-North Railroad Committee Meeting 3/23/2015. Table of Contents: April 26 Schedule Change - Page 2 Exhibit Book Metro-North Railroad Committee Meeting 3/23/2015 Table of Contents: April 26 Schedule Change - Page 2 Master Page # 1 of 5 - Metro-North Railroad Committee Meeting 3/23/2015 Memorandum Date:

More information

Brooklyn Directory of Youth Services. A Resource Guide for Locating Youth Services in Your Community

Brooklyn Directory of Youth Services. A Resource Guide for Locating Youth Services in Your Community Brooklyn Directory of Youth Services A Resource Guide for Locating Youth Services in Your Community June 2009 How to Use this Directory What is this directory for? The purpose of this directory is to help

More information

Project Rankings. Fiscal Year 2015 2019 Capital Improvement Plan

Project Rankings. Fiscal Year 2015 2019 Capital Improvement Plan Fiscal Year 2015 2019 Capital Improvement Plan Project Rankings 99 CIP Ranking Worksheet 101 104 Final Ranking Scores The following matrix shows all of the projects within the five-year period that were

More information

ENTRY FORM. DVASE 2015 Excellence in Structural Engineering Awards Program

ENTRY FORM. DVASE 2015 Excellence in Structural Engineering Awards Program ENTRY FORM DVASE 2015 Excellence in Structural Engineering Awards Program PROJECT CATEGORY (check one): Buildings under $2M Buildings Over $100M Buildings $2M-$10M X Other Structures Under $5M Buildings

More information

For Lease $19,500/Per Month

For Lease $19,500/Per Month Industrial Warehouse For Lease -10,000 SQFT 473 President Street, Brooklyn, NY Prepared by: For Lease $19,500/Per Month Coldwell Banker Reliable Commercial Division Office: (718)921-3100 Coldwell Banker

More information

Alternatives Evaluation Overview

Alternatives Evaluation Overview Alternatives Evaluation Overview 124 Alternatives were analyzed against the evaluation criteria Criteria and criteria weighting were set by the Community Task Force Ratings were quantitative and qualitative

More information

GED Plus Locations. Program Site name Address Borough. Bronx GED Plus Hub/Referral Center at Bronx Regional High 1010 Rev. James Polite Avenue Bronx

GED Plus Locations. Program Site name Address Borough. Bronx GED Plus Hub/Referral Center at Bronx Regional High 1010 Rev. James Polite Avenue Bronx Program Site name Address Borough Bronx GED Plus Hub/Referral Center at Bronx Regional High 1010 Rev. James Polite Avenue Bronx School GED Plus at Bronx Community College Future Now 2155 University Avenue

More information

Brooklyn 43 SAFE STREETS NYC

Brooklyn 43 SAFE STREETS NYC Brooklyn 43 SAFE STREETS NYC Grand Army Plaza Description Grand Army Plaza is a complex traffic circle where Flatbush and Vanderbilt Avenues, Eastern Parkway, Union Street and the Prospect Park Drive converge.

More information

Exterior Elevated Elements Inspection Guidelines

Exterior Elevated Elements Inspection Guidelines Exterior Elevated Elements Inspection Guidelines Planning and Development 1. Guideline Purpose These guidelines are intended to assist practicing professionals in complying with Berkeley Municipal Code

More information

Protected Bicycle Lanes in NYC

Protected Bicycle Lanes in NYC Protected Bicycle Lanes in NYC New York City Department of Transportation Polly Trottenberg, Commissioner September 2014 NEW YORK CITY DEPARTMENT OF TRANSPORTATION 1 Overview Since 2007, the New York City

More information

NORTH RED AND PURPLE MODERNIZATION PROJECT

NORTH RED AND PURPLE MODERNIZATION PROJECT RED AD PURPLE MDERIZATI PRJECT Environmental Impact Statement Scoping Information January 2011 ITRDUCTI The Chicago Transit Authority (CTA) is proposing to make improvements, subject to the availability

More information

19310 STONE OAK PKWY, STE. 201 SAN ANTONIO, TEXAS 78258 T: 210.402.6363 F: 210.402.6767 www.drakecommercial.com

19310 STONE OAK PKWY, STE. 201 SAN ANTONIO, TEXAS 78258 T: 210.402.6363 F: 210.402.6767 www.drakecommercial.com Multi-Family Land Sonoma Verde Kyle Seale Parkway San Antonio, Texas DRAKE COMMERCIAL GROUP DEBORAH BAUER TRAVIS BAUER 19310 STONE OAK PKWY, STE. 201 SAN ANTONIO, TEXAS 78258 T: 210.402.6363 F: 210.402.6767

More information

New York Office Visitors Guide A helpful guide for those planning to visit the New York Office of Sullivan & Cromwell LLP

New York Office Visitors Guide A helpful guide for those planning to visit the New York Office of Sullivan & Cromwell LLP New York Office Visitors Guide A helpful guide for those planning to visit the New York Office of Sullivan & Cromwell LLP INDEX Office Address, Phone & Fax Office Hours Airport Information Banking Courier

More information

Cost Reduction Opportunities

Cost Reduction Opportunities Cost Reduction Opportunities 9 December 2015 Presentation to MassDOT Board of Directors & MBTA Fiscal and Management Control Board Arup 2 A global, integrated, multidisciplinary firm of professionals 13,000

More information

The partnership has selected three intersections where enforcement, education, and engineering initiatives are being implemented to improve safety:

The partnership has selected three intersections where enforcement, education, and engineering initiatives are being implemented to improve safety: Hamilton-Finn Suite 310 Tel. (403) 207-6000 Road Safety 3016 5th Avenue N.E. Fax. (403) 273-3440 Consultants Ltd. Calgary, Alberta dawatt.dawatt.com www.hamiltonfinn.ca January 19, 2005 Mr. Don Szarko,

More information

BOARD OF DIRECTORS REPORT

BOARD OF DIRECTORS REPORT BOARD OF DIRECTORS REPORT To: Phil Washington, General Manager Date: From: Bruce Abel, Assistant General Manager of Bus Operations GM Date: April 9, 2012 Board Meeting Date: May 15, 2012 Subject: August

More information

Bruce Highway (Cooroy to Curra) Section A (Cooroy southern interchange to Sankeys Road)

Bruce Highway (Cooroy to Curra) Section A (Cooroy southern interchange to Sankeys Road) Bruce Highway (Cooroy to Curra) Section A (Cooroy southern interchange to Sankeys Road) Industry Briefing - 13 February 2013 Bruce Highway Upgrade (Cooroy to Curra) The Bruce Highway Upgrade (Cooroy to

More information

Guide to Smoking Cessation Programs in New York City. Still Smoking? The time to quit is now.

Guide to Smoking Cessation Programs in New York City. Still Smoking? The time to quit is now. Guide to s in New York City Still Smoking? The time to quit is now. Smoking made Beth sick for life. Now she has to take medication every day. Health This guide provides a list of quit-smoking (cessation)

More information

PROJECT MANAGEMENT OVERSIGHT

PROJECT MANAGEMENT OVERSIGHT December 2015 PROJECT MANAGEMENT OVERSIGHT Prepared by Department of Finance and Performance Management Executive Summary This semi annual Report on Project Management Oversight details Service Board efforts

More information

Maryland Invests $845 Million in New Highway and Bridge Projects

Maryland Invests $845 Million in New Highway and Bridge Projects Maryland Invests $845 Million in New Highway and Bridge Projects Completing Widening of MD 404 Talbot And Caroline Counties Top Regional Priority Queen Anne s, Talbot, and Caroline Counties Widening MD

More information

Site Development Information Worksheet for single family residential development

Site Development Information Worksheet for single family residential development Site Development Information Worksheet for single family residential development Project description: Address: Owner Name: Phone No. Date Signature & phone number of Individual who Completed this Worksheet

More information

Effect on structures. Uniform settlement - no concerns. Angular distortion - causes damage due to tensile strain

Effect on structures. Uniform settlement - no concerns. Angular distortion - causes damage due to tensile strain Effect on structures Uniform settlement - no concerns Angular distortion - causes damage due to tensile strain 1/500 - safe limit for no cracking of buildings 1/150 - potential structural damage 36 37

More information

CNR S SHORT TERM REHABILITATION

CNR S SHORT TERM REHABILITATION CNR S SHORT TERM REHABILITATION A Leader in Innovative Therapies A Member of the Beth Abraham Family of Health Services Center for Nursing and Rehabilitation Where Healing Hands Lead You Home CNR s innovative

More information

Seattle Public Schools Building Excellence IV Projects Under Construction

Seattle Public Schools Building Excellence IV Projects Under Construction Seattle Public Schools Building Excellence IV Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 13 Genesee

More information

Prequalified. Preapproved. Guide to Buying. Finances

Prequalified. Preapproved. Guide to Buying. Finances Guide to Buying Guide to Buying congratulations! This is the first step to walking into your very own home. citi habitats works to make the buying experience enjoyable. This guide will help you navigate

More information

HHC FEMA- Priority Mitigation Projects

HHC FEMA- Priority Mitigation Projects Bellevue Hospital Metropolatin Hospital Coler Specialty Hospital Coney Island Hospital HHC FEMA- Priority Mitigation Projects CM Consultant Services Informational Session 1:00 PM July 1, 2015 Agenda Introductions

More information

Mayors Welcome Strong Surrey Votes Yes Coalition Support. Yes Vote Would Vastly Improve Transit and Transportation in Fast Growing City

Mayors Welcome Strong Surrey Votes Yes Coalition Support. Yes Vote Would Vastly Improve Transit and Transportation in Fast Growing City Mayors Welcome Strong Surrey Votes Yes Coalition Support Yes Vote Would Vastly Improve Transit and Transportation in Fast Growing City February 11, 2015 Vancouver, BC The Mayors Council on Regional Transportation

More information

FY 2014 2023 STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM Transportation Authorities Project Descriptions

FY 2014 2023 STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM Transportation Authorities Project Descriptions Delaware River Joint Toll Bridge Commission Authority Easton Phillipsburg (Route 22) Toll Bridge Easton Phillipsburg (Route 22) Toll Bridge Rehabilitation Anticipated rehabilitation project elements include:

More information

March 19, 2014. Ms. Jean McDonald CAP Management 910 16th Street, Suite 1010 Denver, Colorado 80202

March 19, 2014. Ms. Jean McDonald CAP Management 910 16th Street, Suite 1010 Denver, Colorado 80202 Ms. Jean McDonald CAP Management 910 16th Street, Suite 1010 Denver, Colorado 80202 Re: Prospector s Point Walkway/Façade Repairs Martin/Martin, Inc Project No.: 13.0358.S.02 Ms. McDonald: Per your request

More information

Certification: Building Plans Examiner. Exam ID: B3

Certification: Building Plans Examiner. Exam ID: B3 Certification: Building Plans Examiner Exam ID: B3 Scope: A Building Plans Examiner will be responsible for reviewing submitted plans to determine if they meet the requirements of the various Building

More information

Flood Damage Mitigation And Insurance Costs

Flood Damage Mitigation And Insurance Costs Flood Damage Mitigation And Insurance Costs Friday, September 25, 2015 at 7:00 PM Saturday, September 26, 2015 at 10:00 AM This presentation was prepared by the Town of South Bethany using Federal Funds

More information

3. Observed Damage in Railway Viaducts

3. Observed Damage in Railway Viaducts Structural Damage of Tohoku Shinkansen Viaducts by the Off the Pacific Tohoku Earthquake First Report on March 16, 2011 Dr. Yoshikazu Takahashi, Associate Professor Disaster Prevention Research Institute,

More information

MTA Capital Program 2015-2019 Renew. Enhance. Expand.

MTA Capital Program 2015-2019 Renew. Enhance. Expand. MTA Capital Program 2015-2019 Renew. Enhance. Expand. CAPITAL PROGRAM mta.info/capital As Proposed to the MTA Board October 28, 2015 MTA Capital Program 2015-2019 Renew. Enhance. Expand. CAPITAL PROGRAM

More information

Paving Capitalization Work Categories and Treatments

Paving Capitalization Work Categories and Treatments Statement of ODOT Infrastructure Capitalization Policy Government Accounting Standards Board (GASB) 34 requires public agencies to capitalize infrastructure assets on their financial statements for periods

More information

Traffic Signal Priority (TSP) and Automatic Vehicle Tracking System (AVTS) For Calgary Transit Buses

Traffic Signal Priority (TSP) and Automatic Vehicle Tracking System (AVTS) For Calgary Transit Buses Traffic Signal Priority (TSP) and Automatic Vehicle Tracking System (AVTS) For Calgary Transit Buses (Project #2001-06) Calgary Transit Transit Planning 2004 July Introduction The purpose of this report

More information

KOSCIUSZKO BRIDGE PROJECT BRIDGE PRIMER

KOSCIUSZKO BRIDGE PROJECT BRIDGE PRIMER KOSCIUSZKO BRIDGE PROJECT BRIDGE PRIMER The New York State Department of Transportation (NYSDOT) is preparing an Environmental Impact Statement (EIS) to evaluate alternatives for the rehabilitation or

More information

BM1. Between Mill Basin, Brooklyn, and Midtown/Downtown, Manhattan. Express Weekday & Saturday Service. Bus Timetable. Effective Summer 2016

BM1. Between Mill Basin, Brooklyn, and Midtown/Downtown, Manhattan. Express Weekday & Saturday Service. Bus Timetable. Effective Summer 2016 Bus Timetable Effective Summer 2016 MTA Bus Company BM1 Express Weekday & Saturday Service Between Mill Basin, Brooklyn, and Midtown/Downtown, Manhattan If you think your bus operator deserves an Apple

More information

HISTOREMIX. A new spin on a classic structure

HISTOREMIX. A new spin on a classic structure HISTOREMIX A new spin on a classic structure The pioneering spirit of this Daniel Burnham designed building (1907) is alive in the iconic structure, which is once again making a bold statement in the Central

More information

Access-A-Ride Designated Pick-up/Drop-off Locations

Access-A-Ride Designated Pick-up/Drop-off Locations Access-A-Ride Designated Pick-up/Drop-off Locations February 2010 Location Beacon Theater Beth Israel Medical Center Beth Israel Medical Center / Phillips Ambulatory Care Center Beth Israel North Beth

More information

School Construction Authority Architecture & Engineering

School Construction Authority Architecture & Engineering SCOPING GUIDELINES 1.0 GENERAL GUIDELINES 2.0 BUILDING ENVELOPE SCOPING GUIDELINES 3.0 CATEGORIES AND COMPONENTS: The Flood Elimination/Below Grade Capital Category may include some or all of the following

More information

ACEC-Illinois 2013 ENGINEERING EXCELLENCE AWARDS HONOR AWARD WINNERS

ACEC-Illinois 2013 ENGINEERING EXCELLENCE AWARDS HONOR AWARD WINNERS Studies, Research and Consulting Hanson Professional Services Inc. / Parsons Corp. Illinois High-Speed Rail Tier 1 EIS Owner: Illinois Department of Transportation, Division of Public and Intermodal Transportation

More information

MEMORANDUM. 1509 West Swann Avenue, Suite 225 Tampa, Florida 33606 Phone (813) 258-8818 Fax (813) 258-8525

MEMORANDUM. 1509 West Swann Avenue, Suite 225 Tampa, Florida 33606 Phone (813) 258-8818 Fax (813) 258-8525 1509 West Swann Avenue, Suite 225 Tampa, Florida 33606 Phone (813) 258-8818 Fax (813) 258-8525 To: From: Date: Subject: Mr. Thomas Gibson, City of St. Petersburg Jeffrey D. Malyszek, PE and Deborah C.

More information

APPENDIX D SUBSTANCE ABUSE TREATMENT FACILITIES

APPENDIX D SUBSTANCE ABUSE TREATMENT FACILITIES APPENDIX D FACILITY Manhattan SUBSTANCE ABUSE TREATMENT FACILITIES ADDRESS/PHONE SERVICES Beth Israel Stuyvesant Square Chemical Dependency Bernstein Pavilion 1-9 Nathan D. Perlman Place New York, NY 10003

More information

RED RIVER DIVERSION FARGO MOORHEAD METRO FLOOD RISK MANAGEMENT PROJECT, FEASIBILITY STUDY, PHASE 4

RED RIVER DIVERSION FARGO MOORHEAD METRO FLOOD RISK MANAGEMENT PROJECT, FEASIBILITY STUDY, PHASE 4 RED RIVER DIVERSION FARGO MOORHEAD METRO FLOOD RISK MANAGEMENT PROJECT, FEASIBILITY STUDY, PHASE 4 APPENDIX G COST ESTIMATES EXHIBIT J RAILROAD BRIDGE QUANTITIES Report for the US Army Corps of Engineers,

More information

MTA Capital Program 2010-2014

MTA Capital Program 2010-2014 MTA Capital Program 2010-2014 Amendment as approved by the MTA Board July 2013 Background: 2010-2014 Capital Program Plan Adoption and Prior Amendments On April 28, 2010, the MTA Board approved a proposed

More information

Welcome! Purpose of Tonight s Meeting. Informational Open House to discuss two City projects: Goal is to LISTEN TO YOU

Welcome! Purpose of Tonight s Meeting. Informational Open House to discuss two City projects: Goal is to LISTEN TO YOU Purpose of Tonight s Meeting Informational Open House to discuss two City projects: Fairchild Street Subway Phase I Engineering: Immediate need to replace subway Bowman Avenue Feasibility Study Future

More information

Kingsbury Run Greenway Project

Kingsbury Run Greenway Project Kingsbury Run Greenway Project Slavic Village Development & Burton, Bell, Carr Project Goals Create Conceptual Plans and Cost Estimate. Coordinate with other ongoing and future projects in the area. Description

More information

3.1 Historical Considerations

3.1 Historical Considerations 3. Recommended Scope of Bridge improvements 3.1 Historical Considerations In the fall of 2000, an outside consultant, Fraser Design, suggested that the existing 4 th St. Bridge is potentially eligible

More information

South East of Process Main Building / 1F. North East of Process Main Building / 1F. At 14:05 April 16, 2011. Sample not collected

South East of Process Main Building / 1F. North East of Process Main Building / 1F. At 14:05 April 16, 2011. Sample not collected At 14:05 April 16, 2011 At 13:55 April 16, 2011 At 14:20 April 16, 2011 ND ND 3.6E-01 ND ND 3.6E-01 1.3E-01 9.1E-02 5.0E-01 ND 3.7E-02 4.5E-01 ND ND 2.2E-02 ND 3.3E-02 4.5E-01 At 11:37 April 17, 2011 At

More information

Appendix J Transportation Management Plan Report. Traffic Operational Analysis Report

Appendix J Transportation Management Plan Report. Traffic Operational Analysis Report Appendix J Transportation Management Plan Report Traffic Operational Analysis Report Transportation Management Plan Report VIRGINIA AVENUE TUNNEL RECONSTRUCTION PROJECT WASHINGTON, DC PRELIMINARY TRANSPORTATION

More information

Manhattan Free and Low Cost English Classes. Program Name/ website Address/Directions Contact Class Information

Manhattan Free and Low Cost English Classes. Program Name/ website Address/Directions Contact Class Information Updated: 3/31/2015 *Informations are subject to change, please contact program for most updated information* If information needs to be update please contact info@aaari.info Manhattan Free and Low Cost

More information

Now available on your iphone!

Now available on your iphone! Now available on your iphone! 1 2 3 4 West 53rd Street Columbus Avenue West 64th Str West 77th Street West 76th Street West 75th Street West 74th Street West 73rd Street West 72nd Street West 71st

More information

AGENDA. The following projects/items will be discussed, in approximately this order, at approximately the times listed.

AGENDA. The following projects/items will be discussed, in approximately this order, at approximately the times listed. NHDOT Natural Resource Agency Coordination Meeting Wednesday, December 16, 2015 John O. Morton Building, 7 Hazen Drive, Concord, NH 9:00 am, Bureau of Environment Conference Room (Room 161) AGENDA The

More information

Sewalls Falls Road Bridge. Cultural Resource Meeting April 4, 2013

Sewalls Falls Road Bridge. Cultural Resource Meeting April 4, 2013 Sewalls Falls Road Bridge Cultural Resource Meeting April 4, 2013 Meeting Purpose Review of the project process to date Project replacement vs. rehabilitation Review of recent public process Review of

More information

Building History Berea City School District

Building History Berea City School District Photo Currently Not Available Berea - Midpark High School 165 East Bagley Rd. Principal: Mr. Vincenzo Ruggiero http://www.berea.k12.oh.us/domain/169 ORIGINAL 21.0 1928 68,203 Auditorium 1928 12,118 Addition

More information

Design Changes in Queens Revision 14-4M

Design Changes in Queens Revision 14-4M MTA Long Island Rail Road East Side Access Design Changes in Queens Revision 14-4M Environmental Analysis November 2005 United States Department of Transportation Federal Transit Administration Metropolitan

More information

HEAVY MOVABLE STRUCTURES, INC. 12 TH BIENNIAL SYMPOSIUM NW 17 TH AVENUE BRIDGE REHABILITATION OVER THE MIAMI RIVER MIAMI-DADE COUNTY

HEAVY MOVABLE STRUCTURES, INC. 12 TH BIENNIAL SYMPOSIUM NW 17 TH AVENUE BRIDGE REHABILITATION OVER THE MIAMI RIVER MIAMI-DADE COUNTY HEAVY MOVABLE STRUCTURES, INC. 12 TH BIENNIAL SYMPOSIUM November 3-6, 2008 NW 17 TH AVENUE BRIDGE REHABILITATION OVER THE MIAMI RIVER MIAMI-DADE COUNTY John Low, P.Eng. Hardesty & Hanover, LLP CARIBE ROYALE

More information

Every Which Way But Direct!

Every Which Way But Direct! A Review of Service Diversion Communication Bronx Service Affected No Bronx-bound (241 St-bound) trains at this station 2 WEEKDAYS 10:45 AM to 3 PM Mon to Fri February 2014 S M T W T F S 2 3 4 5 6 7 8

More information

Record of Work Experiences Trade Qualifier or Pre-Apprenticeship Credits ROOFER

Record of Work Experiences Trade Qualifier or Pre-Apprenticeship Credits ROOFER Department of Advanced Education and Skills Apprenticeship and Trades Certification Division Record of Work Experiences Trade Qualifier or Pre-Apprenticeship Credits ROOFER Note to Apprenticeship Applicants

More information

IH-635 MANAGED LANES PROJECT, SEG. 3.2

IH-635 MANAGED LANES PROJECT, SEG. 3.2 IH-635 MANAGED LANES PROJECT, SEG. 3.2 Location: Dallas, Texas Owner: Texas Department of Transportation Client: Ferrovial Agroman Construction Cost: $1 Billion Construction Completion Date: December,

More information

The Evacuation Of NY Downtown Hospital Prior To Hurricane Sandy

The Evacuation Of NY Downtown Hospital Prior To Hurricane Sandy The Evacuation Of NY Downtown Hospital Prior To Hurricane Sandy Al Villacara, DMD Director, System Emergency Preparedness & NYP/Lower Manhattan Hospital Division C ing The Whole Response: Community, Collaboration,

More information

Cross Harbor Freight Tunnel: Add Subway To Staten Island and More!

Cross Harbor Freight Tunnel: Add Subway To Staten Island and More! Cross Harbor Freight Tunnel: Add Subway To Staten Island and More! The Brooklyn Historic Railway Association (BHRA) applauds the Port Authority s endeavour to build a rail tunnel under New York Harbor.

More information

Leaky Homes Financial Assistance Package (FAP) Repair plan example

Leaky Homes Financial Assistance Package (FAP) Repair plan example LEAKY HOMES FINANCIAL ASSISTANCE PACKAGE FACT SHEET Repair Plan Example - June 2014 Page 1 Leaky Homes Financial Assistance Package (FAP) Repair plan example Introduction This repair plan example is intended

More information

Below is a list of neighborhood sites where someone will prepare your taxes for FREE. Refer to the Key for important eligibility information.

Below is a list of neighborhood sites where someone will prepare your taxes for FREE. Refer to the Key for important eligibility information. Below is a list of neighborhood sites where someone will prepare your taxes for FREE. Refer to the Key for important eligibility information. Key Sites with this icon are Volunteer Income Tax Assistance

More information

FIRE ALARM /FIRE PROTECTION OUTAGE/IMPAIRMENT RESPONSE GUIDELINE

FIRE ALARM /FIRE PROTECTION OUTAGE/IMPAIRMENT RESPONSE GUIDELINE Page 1 of 10 FIRE ALARM /FIRE PROTECTION OUTAGE/IMPAIRMENT RESPONSE GUIDELINE SYSTEM TESTING 1. Testing of the Fire Alarm and Fire Protection Systems 1.1. The Building Engineer, Electrician, Plumber (or

More information

HUDSON YARDS PROJECT. G r e g K e l l y P r e s i d e n t a n d C E O, U. S., C e n t r a l a n d S o u t h A m e r i c a

HUDSON YARDS PROJECT. G r e g K e l l y P r e s i d e n t a n d C E O, U. S., C e n t r a l a n d S o u t h A m e r i c a HUDSON YARDS PROJECT G r e g K e l l y P r e s i d e n t a n d C E O, U. S., C e n t r a l a n d S o u t h A m e r i c a G R O W T H V S. O T H E R U. S. C I T I E S NEW YORK GREW TO BECOME A WORLD CAPITAL

More information

REHABILITATION OF NOVOARBATSKY BRIDGE IN MOSCOW

REHABILITATION OF NOVOARBATSKY BRIDGE IN MOSCOW 2005 New York City Bridge Conference September 12-13, 2005 REHABILITATION OF NOVOARBATSKY BRIDGE IN MOSCOW The Novoarbatsky Bridge across the Moskva River had been built in 1957 Plan of the bridge Steel

More information

3 Tappan Zee Bridge Rehabilitation Options

3 Tappan Zee Bridge Rehabilitation Options 3 Tappan Zee Bridge Rehabilitation Options 3.1 Introduction This chapter describes possible options that rehabilitate and enhance the existing Tappan Zee Bridge. Four Rehabilitation Options have been developed:

More information

PENNDOT 3D MODELING FOR STRUCTURES WORKSHOP. Presented by: Steven Pletcher and Chris Daniels, P.E. October 21, 2014

PENNDOT 3D MODELING FOR STRUCTURES WORKSHOP. Presented by: Steven Pletcher and Chris Daniels, P.E. October 21, 2014 PENNDOT 3D MODELING FOR STRUCTURES WORKSHOP Presented by: Steven Pletcher and Chris Daniels, P.E. October 21, 2014 Agenda Introduction G.A. & F.C. Wagman History Process used to prepare 3D models Estimating

More information

Muddy River Flood Risk Management & Environmental Restoration Project Phase 1 Construction Activities Next 90 Days August 2015

Muddy River Flood Risk Management & Environmental Restoration Project Phase 1 Construction Activities Next 90 Days August 2015 Muddy River Flood Risk Management & Environmental Restoration Project Phase 1 Construction Activities Next 90 Days August 2015 General: The Muddy River Flood Risk Management (FRM) & Environmental Restoration

More information

BINGHAMTON FLOOD DAMAGE REDUCTION PROJECT

BINGHAMTON FLOOD DAMAGE REDUCTION PROJECT BINGHAMTON FLOOD DAMAGE REDUCTION PROJECT Department of Environmental Conservation Region 7 Counties: Broome, Cayuga, Chenango, Cortland, Madison, Onondaga, Oswego, Tioga, Tompkins Operated and Maintained

More information

SUBJECT: SEE BELOW DATE: May 12, 2015 SUBJECT: ACTIONS RELATED TO THE THREE CREEKS TRAIL PEDESTRIAN BRIDGE PROJECT

SUBJECT: SEE BELOW DATE: May 12, 2015 SUBJECT: ACTIONS RELATED TO THE THREE CREEKS TRAIL PEDESTRIAN BRIDGE PROJECT COUNCIL AGENDA: 5/19/15 ITEM: 4.5 CITY OF SAN IPSE CAPITAL OF SILICON VALLEY Memorandum TO: HONORABLE MAYOR AND CITY COUNCIL FROM: Barry Ng Harry Freitas Angel Rios, Jr. SUBJECT: SEE BELOW DATE: Approved

More information

Summary of Potential Storm Drain Projects and Programs

Summary of Potential Storm Drain Projects and Programs Summary of Potential Storm Drain Projects and Programs CAPITAL IMPROVMENTS PUMP STATION UPGRADES The storm runoff from a large portion of Palo Alto cannot flow by gravity into one of the local creeks.

More information

Fulton County and Surrounding Communities. Social & Healthcare. Resource Book. Provided to you by Graham Health System

Fulton County and Surrounding Communities. Social & Healthcare. Resource Book. Provided to you by Graham Health System Fulton County and Surrounding Communities Social & Healthcare Resource Book Provided to you by Graham Health System Emergency Response System 2 Carelink Graham Home Medical 101 S. Main St., Canton, IL

More information

Historic Bridges of Frederick County. Frederick County, Maryland Division of Public Works Department of Highways and Transportation (301) 600-1687

Historic Bridges of Frederick County. Frederick County, Maryland Division of Public Works Department of Highways and Transportation (301) 600-1687 Historic Bridges of Frederick County Frederick County, Maryland Division of Public Works Department of Highways and Transportation (301) 600-1687 Frederick County s Bridges We have 212 bridges over 20

More information

Standard Designs & Details - Drawings. Drawing Number Rev Title Click Click

Standard Designs & Details - Drawings. Drawing Number Rev Title Click Click Drawing Number Rev Title Click Click NR/CIV/SD/101 A rickwork and masonry repairs Specification for the Works NR/CIV/SD/102 A rickwork and masonry repairs Standard brickwork bonds NR/CIV/SD/103 A rickwork

More information