Exterior Elevated Elements Inspection Guidelines
|
|
|
- Darrell Wilson
- 10 years ago
- Views:
Transcription
1 Exterior Elevated Elements Inspection Guidelines Planning and Development 1. Guideline Purpose These guidelines are intended to assist practicing professionals in complying with Berkeley Municipal Code (BMC) Section and to assist City of Berkeley Building and Safety Division staff with enforcing BMC Section , also known as the Exterior Elevated Elements Inspection Program (E3 Program). For more information please refer to the Frequently Asked Questions posted on the E3 Program webpage: 2. Program Scope The Berkeley City Council passed Ordinance No.7,431-N.S. adding Section to the Berkeley Housing Code requiring inspection of weather-exposed, exterior, elevated elements of buildings. The Ordinance requires inspection of exterior elevated elements every three years, and it applies to buildings containing R-1 and R-2 Occupancies, as defined by the California Building Code. The program applies to all such buildings regardless of their original construction date. The City delivered E3 Program notifications to building owners in August Building owners must file the Inspection Certification form with the office on or before January 14, 2016, and every three years thereafter. If building owners believe their building is exempt from the program, they must file the Exemption Declaration form on or before January 14, 2016 to be removed from the program's inventory. The program applies to the following elements located more than 30 inches above adjacent grade, constructed of wood or steel, and accessible to occupants, known collectively in this document as exterior elevated elements (E3s): 2.1. Balconies 2.2. Exterior walkways 2.3. Decks 2.4. Exterior stairs and landings 2.5. Guards and associated handrails serving any elements listed above E3s whose structural system is constructed of reinforced concrete are exempt from the program. E3s featuring a concrete topping slab as a wearing surface are subject to the program if the topping slab is supported by wood or steel framing. E3s located in areas accessible only to maintenance personnel, such as roofs, are not subject to the program. Figure 1 on page 6 is a sample illustration of E3s that are subject to the program. [email protected] Page 1 of 7 Fax: (510)
2 3. Program Purpose The program's purpose is to safeguard the public safety by maintaining the strength of structural components supporting E3s. Program objectives include the following: 3.1. Identify wood framed E3s exhibiting significant deterioration due to wood destroying organisms (fungal decay or insect infestation) Identify steel framed E3s exhibiting significant section loss due to corrosion Ascertain whether the extent of deterioration or corrosion poses a significant compromise to the load-carrying adequacy of structural components supporting E3s Attempt to locate the water source if wood destroying organism infestation or corrosion is observed in wood framing or steel framing respectively Remediate deficient components. Before assessing the building's E3s, confirm the applicability of the program to the building. If the building is not subject to the program, the building owner should file the Exemption Declaration form with the City. In this case, the City would not require assessment of the building's E3s. The inspection and condition assessment process is comprised of a Tier 1 screening and a Tier 2 evaluation and remediation. An overview of the Tier 1 screening and Tier 2 evaluation and remediation procedures is illustrated in Figure 2 on page Tier 1 Screening Procedure The Tier 1 screening by a licensed professional is comprised of two components: condition assessment of E3s' structural components and condition assessment of the waterproofing system Tier 1 Structural Screening The Tier 1 screening of structural components will most commonly entail the following: Visit the Site Visually review all E3s, and interior and exterior areas proximate thereto, as necessary Develop an Investigative Program In the case of E3s with soffit finishes, selectively identify locations for investigative openings to reveal concealed structural components. Finish removal need only be the minimum amount sufficient to ascertain whether or not wood structural components have suffered decay due to wood destroying organisms or whether or not steel structural components have suffered corrosion. Inspections should be conducted at the most probable locations where water intrusion may occur, for example at the intersection of horizontal and vertical assemblies, guardrail penetrations of the element assembly, floor drains where present, or other similar locations Create Investigative Openings Selectively create investigative openings to reveal concealed structural components and conditions. A building permit is not required for selective removal of finishes associated with investigative work. [email protected] Page 2 of 7 Fax: (510)
3 Determine if Wood Destroying Pests, Organisms or Corrosion are Present If wood destroying organisms are identified on wood components or corrosion is identified on steel structural components, initiate Tier 2 structural evaluation as recommended below Patch Investigative Openings If no significant presence of wood destroying organisms or corrosion is identified, patch the openings to match the existing surface. The owner may wish to install vents and/or access openings to provide easy access for future inspections. Be mindful that the affected areas may be components of a fire rated assembly where located in close proximity to side or rear property lines and therefore subject to certain building code requirements. Note: A building permit is not required for patching of selectively removed finishes in-kind. Note: A building permit is required for the installation of vents and/or access openings Tier 1 Waterproofing System Screening Practically assessing the adequacy of the waterproofing system is difficult in many instances. The waterproofing barrier is often concealed by a wearing surface topping, in the case of balconies and walkways, or wall finish. At a minimum, the Tier 1 screening of the waterproofing system ought to include visual review of readily observable exposed surface areas, including topping membrane if surface-applied, and flashings for signs of active water intrusion. It is not necessary to replace the waterproofing system if it is performing adequately. If minor waterproofing defects are observed, but have not caused water intrusion or triggered a Tier 2 Evaluation and Remediation, these defects should be reported to the building owner with recommended maintenance measures File Certification Form If no significant presence of wood destroying organisms, corrosion or water intrusion are identified and after investigative openings are patched, file the Certification form with the City's office. 5. Tier 2 Evaluation and Remediation Procedure 5.1. Methods of Evaluation and Remediation When the Tier 1 screening determines that wood destroying organisms, corrosion or water intrusion are present, further evaluation and/or remediation are required. This process may consist of replacement of damaged components in-kind, an engineering analysis assessing whether or not the damaged components are structurally adequate, modification of the existing components to repair the damage, or any combination thereof. Analysis of, and modifications to, existing structural components requires a licensed structural or civil engineer or architect. [email protected] Page 3 of 7 Fax: (510)
4 5.2. Search for Documents Consider searching for the original building design drawings. Inquire about availability with the building owner and/or the City of Berkeley Tier 2 Evaluation and Remediation Structural Evaluation and Remediation Evaluate the original element design and extent of damage in order to determine the most practical and economic means of remediation. In most cases it would be advantageous to have a licensed engineer or architect perform a structural evaluation of the damaged components to determine their adequacy. In some circumstances, for example when the damage is significant or easily observable, the complete removal and replacement in-kind of damaged components can be a possible solution. The following types of remediation require a licensed engineer or architect: Modifications to existing structural systems, for example alterations to cantilever framing members that are not a complete replacement in-kind Complete removal and replacement of E3s Complete removal of E3s with associated restoration of building facade. Note: Replacement or retention of original materials and the use of original methods of construction is permitted provided such materials or methods complied with the building code provisions in effect at the time of original construction. Complete replacements will require conformance to current code requirements Waterproofing Remediation If water damage or signs of active water intrusion are observed, the licensed professional should make a reasonable attempt to locate the source(s) of water and remediate it prior to completion of the Certification Form. The exact method of determining leakage is up to the licensed professional; it may or may not include the following: Review of available original and prior modification construction documents Review slope to drain at surface and membrane levels Review drain/gutter/downspout function Review conditions at penetrations, fenestrations, changes in plane, etc. (e.g., door threshold, deck-to-wall flashing) Review function of existing concealed space ventilation if present Perform water testing, thermal imaging, and/or electronic leak detection (as appropriate for the existing building conditions) Determine moisture content of materials. [email protected] Page 4 of 7 Fax: (510)
5 Perform invasive testing to observe condition of concealed membrane system. Invasive testing may include isolated borescope openings or selective demolition of larger areas Prepare Remedial Design Develop the remediation design, prepare construction drawings and file a building permit application. Some forms of maintenance based remediation, for example application of preservatives or sealants, may not require a building permit Execute Remediation Work Perform the remedial work, restore building finishes and final building permits, as applicable File Certification Form After the remedial work is completed, file the Certification form with the City of Berkeley's office. One certification form must be filed for each separate building and a single professional must be responsible for certification of all E3s on the building. [email protected] Page 5 of 7 Fax: (510)
6 Figure 1 [email protected] Page 6 of 7 Fax: (510)
7 Figure 2 Start Is the building subject? No File Exemption Declaration Yes Tier 1 Screening (See Sections 4.1 & 4.2) Decay, corrosion or water intrusion are identified? No Restore Finishes and File Inspection Certification (See Sections & 4.3) Yes Tier 2 Evaluation and Remediation (See Section 5) No Design Repair (See Section 5.4) An engineering analysis determines that the component is adequate? (See Sections & 5.3.2) Replace In-Kind Yes Restore Finishes and File Inspection Certification Execute Remediation and Restore Finishes (See Section 5.5) File Inspection Certification (See Section 5.6) [email protected] Page 7 of 7 Fax: (510)
Building Condition Assessment: 215-219 West Lexington Street Baltimore, Maryland
KPA The Joint Venture of EBA Engineering, Inc. and Kennedy Porter & Associates, Inc. 4813 Seton Drive, Baltimore, MD 21215 Phone: (410-358-7171) Fax: (410)358-7213 Building Condition Assessment: Baltimore,
Certification: Building Plans Examiner. Exam ID: B3
Certification: Building Plans Examiner Exam ID: B3 Scope: A Building Plans Examiner will be responsible for reviewing submitted plans to determine if they meet the requirements of the various Building
Building Condition Assessment: 109-111 North Howard Street Baltimore, Maryland
KPA The Joint Venture of EBA Engineering, Inc. and Kennedy Porter & Associates, Inc. 4813 Seton Drive, Baltimore, MD 21215 Phone: (410-358-7171) Fax: (410)358-7213 Building Condition Assessment: Baltimore,
PETERSONS WATERFRONT CONDOMINIUMS
CONSULT DESIGN CONSTRUCT PETERSONS WATERFRONT CONDOMINIUMS 103 Park Street Chelan, Washington Findings Summary Report Prepared for: Petersons Waterfront Condominium Association March 21, 2014 J2 Project
PELHAM MEMORIAL HIGH SCHOOL STONE FAÇADE REPORT. November 2007
PELHAM MEMORIAL HIGH SCHOOL STONE FAÇADE REPORT November 2007 PURPOSE OF INVESTIGATION Determine possible locations of moisture intrusion into and through facade. Determine cause of horizontal and vertical
FOUNDATION INSULATING SYSTEM, INCLUDING WATERPROOFING AND DAMP PROOFING
FOUNDATION INSULATING SYSTEM, INCLUDING WATERPROOFING AND DAMP PROOFING insulation installed on foundation walls must be separated from the building interior with a code approved thermal barrier. Foam
ELIGIBLE REPAIR PROJECT PARAMETERS
THE DISTRICT MUNICIPALITY OF MUSKOKA ONTARIO RENOVATES PROGRAM FOR HOMEOWNERS ELIGIBLE REPAIR PROJECT PARAMETERS 1. To have your project considered and payment processed, all projects requiring a Building
Structure Survey Findings:
Structure Survey Findings: Visible portions of the following were observed: foundations; structure to walls, columns, floors, roofs, overhang posts, and columns; attached or firmly abutting decks, balconies,
Reference: BRM-00220488-A0 July 18 th, 2014. Cursory Visual Review of Various Below Grade Spaces and Exposed Foundation Walls
Reference: BRM-00220488-A0 July 18 th, 2014 Toronto Catholic District School Board 80 Sheppard Avenue East Toronto, Ontario M2N 6E8 Re: 1.0 Introduction Exp Services Inc. (exp) was retained by the Toronto
CITY OF BERKELEY BUILDING PERMIT DETAILED CHECKLIST
CITY OF BERKELEY DETAILED CHECKLIST This checklist will assist you in preparing plans for submittal with a building permit application. Alterations, additions and remodeling projects may not require all
Excerpts from the Canadian National Building Code (NBC)
Excerpts from the Canadian National Building Code (NBC) Reproduced here with Permission of the Copyright Owner, the National Research Council of Canada, Institute for Research in Construction. For more
Block Lofts Condominiums
Block Lofts Condominiums Building Envelope Condition Assessment 747 Ralph McGill Boulevard Atlanta, Georgia Presented to: Block Lofts Condominium Home Owners Association C/o Heritage Property Management
HEDDERMAN ENGINEERING, INC. www.heddermanengineering.com Office 281-355-9911, Fax 281-355-9903 [email protected]
HEDDERMAN ENGINEERING, INC. www.heddermanengineering.com Office 281-355-9911, Fax 281-355-9903 [email protected], 2011 TO: Mr. REF: CONDITION OF PROPERTY SURVEY Dear Mr. : At your request,
www.citiesinspection.com October 5, 2015 Dear Client,
www.citiesinspection.com October 5, 2015 Dear Client, On 9/14/2015, Cities Inspection Service, Inc. completed a building inspection of the property located at 123 Oak Street, Someplace, Minnesota for you.
The replacement or modification of existing windows shall comply with the following requirements:
City of La Habra Heights Building Division 1245 N. Hacienda Road La Habra Heights, CA 90631 Office: (562) 694-6302 ext. 228 Fax: (562) 690-5010 WINDOW REPLACEMENT 2010 CALIFORNIA RESIDENTIAL CODE (CRC)
Building Foundation and Structure
Building Foundation and Structure Overview The construction of the Hall of Waters building began in 1936, and was constructed over the original site of the Siloam and Sulpho-Saline Springs. The original
March 19, 2014. Ms. Jean McDonald CAP Management 910 16th Street, Suite 1010 Denver, Colorado 80202
Ms. Jean McDonald CAP Management 910 16th Street, Suite 1010 Denver, Colorado 80202 Re: Prospector s Point Walkway/Façade Repairs Martin/Martin, Inc Project No.: 13.0358.S.02 Ms. McDonald: Per your request
INSPECTION FINDINGS. for. Paragon Condominiums 2102 W 31 st Avenue Denver, Colorado. Inspection Date: August 8, 2007. Perfonned By: Drew Schneider
INSPECTION FINDINGS for Paragon Condominiums 2102 W 31 st Avenue Denver, Colorado Inspection Date: August 8, 2007 Perfonned By: Drew Schneider INSPECTRUM 27691 Moffat Road Evergreen, CO 80439 303.697.0990
Self-Home Inspection Checklist
To be used as a first home visit for note taking. Visit www.homeinspectiondirect.com for more tips and information about buying a home and hiring a home inspector. This form in no way replaces a professional
Common Problems with Walls
Common Problems with Walls Common Problems with Walls There are problems and concerns that are shared by all walls and siding installations. In this article, we will learn about the following commonly
Roof Inspection. Summary Report
Phone: (561) 866 9956 www.real-estate-inspections.com Roof Inspection Summary Report Subject Property File Number: 05-15-RF-002 Inspector: Craig Milliken, PE CPM Real Estate Inspections, Inc. Date of Inspection:
Quality Assurance and Diagnostic Water Leakage Field Check of Installed Storefronts, Curtain Walls and Sloped Glazing Systems
Method of Test Committee Approval Product Group Approval Approved via 5/21/15 MOT CC Out for Ballot (#805-15) PUBLICATION NO. AAMA 501.2-XX DRAFT #2 DATED 5/21/15 Quality Assurance and Diagnostic Water
201 WATER STREET FORWARDERS MUSEUM AND VISITORS INFORMATION CENTRE
STRUCTURAL INSPECTION REPORT DRAFT 201 WATER STREET FORWARDERS MUSEUM AND VISITORS INFORMATION CENTRE TOWN OF PRESCOTT Date: November 2013 GENIVAR No.: 131-20617-00 2611 Queensview Drive, Suite 300, Ottawa,
Residential Decks. Planning and Development Services Department
Building Safety Division 8500 Santa Fe Drive Overland Park, KS 66212 (913) 895-6225 Fax (913) 895-5016 Email: [email protected] Planning and Development Services Department Residential Decks
Comment Form on Proposed Gut Rehabilitation Alternatives
Comment Form on Gut Rehabilitation Alternatives Name: Organization: Email: Instructions Submission: Please submit this form to [email protected] by October 10 th, 2012 with the subject line
Inspecting to a higher standard.
Inspecting to a higher standard. Rob Hopkin Silver Spring, MD 20902 Monday, June 2, 2014 ProTec Inspection Services Inc. 19736 Selby Ave Poolesville, MD 20837 301-972-8531 www.protec-inspections.com [email protected]
Residential Deck Safety, Construction, and Repair
Juneau Permit Center, 4 th Floor Marine View Center, (907)586-0770 This handout is designed to help you build your deck to comply with the 2006 International Residential Building code as modified by the
StuccoSpec Moisture Testing Inspection
e-mail - [email protected] StuccoSpec Moisture Testing Inspection Property Located At: 265 Elm Street, Anywhere, USA 01/27/02 Ordered by: Mr. & Mrs. John Doe #2 Song Sparrow Place, The Woodlands, T 77381281-364-0012
FIELD TESTING SERVICES
FIELD TESTING SERVICES Chris Leach Director of Testing Baton Rouge, Louisiana Destin, Florida Scott Leach David Nichols Field Testing Representative Field Testing Representative 17485 Opportunity Avenue
REVEWED BY: Ross Rogien B.O/P.R. ADDITIONAL REVIEW(S) REQ.-FIRE DEPT Y/N
PLAN REVIEW FOR: PROJECT NAME: OWNER: ARCH/DESIGNER: ADDRESS: Ph/Fx: Plans Dated: E-mail: Sealed By: Estimated Project Cost - $ REVEWED BY: Ross Rogien B.O/P.R. ADDITIONAL REVIEW(S) REQ.-FIRE DEPT Y/N
INSPECTION PROPERTY ADDRESS: Fort Bend County, Texas
5006 Cherry Ridge Road Richmond, Texas 77406 281-342-9944 [email protected] INSPECTION PROPERTY ADDRESS: INSPECTION PERFORMED FOR: XXXX Drive Fort Bend County, Texas Mr. and Mrs. New Construction
COMMONLY USED RESIDENTIAL BUILDING CODES
COMMONLY USED RESIDENTIAL BUILDING CODES INTERNATIONAL RESIDENTIAL CODE (2009) form revised 5/10 FOUNDATION 1. DESIGN OF FORMWORK. Section 1906.1 IBC 2009, Section R404.1.2.3.6 IRC 2009, ACI 318 Section
RDH Building Sciences Inc.
MAK LTR 2007 03 26 Proposal for Building Enclosure Consulting Services RDH Building Sciences Inc. 509 FAIRVIEW AVENUE N SEATTLE WA 98109-5507 TEL 206 324 2272 FAX 206 324 6339 [email protected] WWW.RDHBE.COM
ASHULIA APPARELS LTD. Client Summary Report
Revision : Issue 1 Date: 18 March 2014 ASHULIA APPARELS LTD Samad Mansion, Sec # 6, Block # kha, Road No# 1, Plot #14, Shenpara Parbata, Mirpur, Dhaka (23.8065N,90.3683E) 4th March 2014 Client Summary
MULTI-FAMILY, COMMERCIAL, INDUSTRIAL, AS GOVERNED BY THE BC BUILDING CODE PART 3
TOWN OF SIDNEY Multi-Family, Commercial, Industrial and Institutional Building Permit Guide The information provided is intended as a guide only and does not replace current bylaws and regulations. Complete
BUILDING PERMIT SPECIFICATIONS
BUILDING PERMIT SPECIFICATIONS The below noted requirements are based upon La Plata County Building Code. These specifications are not intended as a complete set of requirements, but are intended to provide
Photos showing the change in condition from 2006 to 2012 are located in Appendix A.
January 27, 2012 Ms. Theresa Gallavan Economic Development Director City of Lompoc 100 Civic Center Plaza Lompoc, California 93436 RE: Lompoc Theater Limited Visual Condition Assessment Dear Theresa: Representatives
Building Code Clarifications - 7. Fire Resistance
Building Code Clarifications - 7. Fire Resistance 7.1 (15-12-030) Use of combustibles in Type III construction roof assemblies Code Section (15-12-030) Use of Combustibles was revised on May 17, 2000,
Page & Turnbull imagining change in historic environments through design, research, and technology
DCI+SDE STRUCTURAL EVALUATIONS OFFICE BUILDING, TOOL SHED & WATER TANK, AND BLACKSMITH & MACHINE SHOP BUILDINGS SAN FRANCISCO, CALIFORNIA [14290] PRIMARY PROJECT CONTACT: H. Ruth Todd, FAIA, AICP, LEED
STRUCTURAL ASSESSMENT. Full Metal Jacket Building 0 Prince Street, Alexandria, VA
STRUCTURAL ASSESSMENT FOR Full Metal Jacket Building 0 Prince Street, Prepared by: ALPHA CORPORATION (Alpha) 1850 S. Loudoun Street, Suite 200 Winchester, VA 22601 540-723-0704 September 22, 2010 J. Michael
Facility Assessment for. 11801 East Main Street, Huntley, IL
Facility Assessment for 11801 East Main Street, Huntley, IL July 12, 2012 Prepared by: Dewberry Architects Inc. 25 S. Grove Avenue, Suite 500 Elgin, IL 60120 (847) 695-5840 The Village of Huntley requested
Finegan Inspection Services, Inc.
Finegan Inspection Services, Inc. Report Prepared For: Phone 513-683-0733 Fa 513-697-0163 Owners Property Address City, State, ZIP Phone FAX Owners Realtor Realty Company Phone FAX OWNER INFORMATION PROPERTY
PRE-PURCHASE INSPECTION REPORT
PRE-PURCHASE INSPECTION REPORT PREPARED FOR: PROPERTY ADDRESS: Waiheke Island DATE: 21 November 2012 Page 1 of 13 (a) This is a report of a visual only, non-invasive inspection of the areas of the building
Water Leak 1: Intrusion Policy
Water Leak 1: Intrusion Policy {Non-Casualty) 1. Determine Source of Leak Roof Leak- 11 See roof leak" Pressured Pipe leak- 11 See pressured pipe leak" Water Intrusion- See 11 see Water Intrusion leak"
2012 Ontario Building Code Requirements for New Construction. Bradford West Gwillimbury Building Division March 5, 2012
2012 Ontario Building Code Requirements for New Construction Bradford West Gwillimbury Building Division March 5, 2012 1 Ontario Building Code changes Applicable to permits applied for after December 31,
Minimum Housing and Health Standards
APPENDIX M.O. 57/2012 Minimum Housing and Health Standards Original version July 20, 1999. Revisions to Part lll, Housing Premises, sections 3 and 4, June 30, 2012 (all revisions are bolded and underlined).
Lighthouse Engineering, L.L.C.
Registered Engineering Firm (F: 9334) Phone: 214-577-1077 Fax: 214-224-0549 Website: www.lighthouseeng.com Email: [email protected] Thursday, September 04, 2014 TO: Our Client RE: Engineering Evaluation
Inspection Report. Dream Home Inspections. www.timinspects.com. 415 Second Ave. Frisco CO 80443-1789 (970) 368-2668
Inspection Report Property Address: 123 Dream Home Way Frisco, CO 80443 Prepared for: Inspector: Tim Nixon Tim Nixon Inspection date: 3/28/2014 1 of 9 General Information Property Information Address:
City of Fort Smith Building Permit Process Frequently Asked Questions
Question: W ho must obtain a building permit? City of Fort Smith Building Permit Process Frequently Asked Questions Answer: This answer is the same for residential or commercial building. Any owner or
Building Permit Application Packet. BUILDING CODES Adopted by La Plata County For Enforcement In The Unincorporated Areas Of La Plata County
Building Permit Application Packet The purpose of Building Codes is to establish the minimum requirements to safe guard the public health, safety and general welfare through structural strength, means
RRIO Checklist. Use of checklist: Definitions: Limitations
CITY OF SEATTLE RENTAL REGISTRATION AND INSPECTION ORDINANCE (RRIO) RRIO Checklist Use of checklist: Property owners will use the RRIO Checklist to confirm that their rental housing properties and units
Florida Building Code 2004 SECTION 1009 STAIRWAYS AND HANDRAILS
Florida Building Code 2004 SECTION 1009 STAIRWAYS AND HANDRAILS 1009.1 Stairway width. The width of stairways shall be determined as specified in Section 1005.1, but such width shall not be less than 44
Structural Assessment Report
Report Dallas Township Elementary School Dallas, Pennsylvania (JBCI Project No. 144911) 1655 Suburban Station Building 1617 John F. Kennedy Boulevard Philadelphia PA 19103 215 665 0497 5 Sandwood Drive
Home Inspection Report
Home Inspection Report Report Number: 144 For The Property Located On: 123 Any Street 27587 Prepared For Exclusive Use By: Mr. Sample N/A,,, Report Prepared By: Edward Carapezza; License No.: 3447 Inspector
Single Family Residential Building Permit Questions & Answers
Single Family Residential Building Permit Questions & Answers Prepared by Dept. of Public Works Revised 07/01/13 200 East Park Street Edwardsville, IL 62025 (618) 692-7535 (618) 692-7505(Fax) Hours: Monday
The Lambton County Homeowner's BUILDING PERMIT INFORMATION GUIDE
The Lambton County Homeowner's BUILDING PERMIT INFORMATION GUIDE BUILDING SERVICES DEPARTMENT 789 Broadway Street, Box 3000 Wyoming, ON N0N 1T0 Telephone: 519 845-0801 Toll-free: 1-866-324-6912 Fax: 519
Leaky Homes Financial Assistance Package (FAP) Repair plan example
LEAKY HOMES FINANCIAL ASSISTANCE PACKAGE FACT SHEET Repair Plan Example - June 2014 Page 1 Leaky Homes Financial Assistance Package (FAP) Repair plan example Introduction This repair plan example is intended
University of Missouri Hospitals and Clinics. Structural Repair and Protection of Post-tensioned Parking Garage
University of Missouri Hospitals and Clinics Structural Repair and Protection of Post-tensioned Parking Garage 1 University of Missouri Project The University of Missouri Health Care Patient and Visitor
TITLE: MASONRY PARAPET WALLS AND FLAT ROOF REQUIREMENTS 11/1/09
TITLE: MASONRY PARAPET WALLS AND FLAT ROOF REQUIREMENTS 11/1/09 PMT GUIDE # 10 Book of Order Section G-10.0102o: "The session is responsible for the mission and government of the particular church. It
Repair of Spalling and Leaking Clay Brick Building Walls
B etter buildings Repair of Spalling and Leaking Clay Brick Building Walls Overview A few years after being built in Waterloo in 1980, a condominium of three, six-storey buildings showed severe spalling
SINGLE FAMILY RESIDENCE HURRICANE MITIGATION APPLICATION
SINGLE FAMILY RESIDENCE HURRICANE MITIGATION APPLICATION As of October 1, 2007, this mitigation form must be submitted as part of the roofing permit application package. Secondary water barrier (if applicable)
The Building Group First Tuesdays First Saint Paul s Lutheran Church 1301 North LaSalle Street, Chicago, Illinois
Wiss, Janney, Elstner Associates, Inc. 10 South LaSalle Street, Suite 2600 Chicago, Illinois 60603 312.372.0555 tel 312.372.0873 fax www.wje.com The Building Group First Tuesdays October 2, 2012 Jason
CLIENT. Inspection Report. 271 Front St. Alert Bay, B.C. Island Building Inspections V ANCOUVER I SLAND B. C.
CLIENT Inspection Report 271 Front St. Alert Bay, B.C. Island Building Inspections 2013 V ANCOUVER I SLAND B. C. Elevation Photos For the Property at 271 Front Street Alert Bay, BC ELEVATION PICTURES Front
Braselton Bros. Store Redevelopment 5134 HWY 53 BRASELTON, GA 30548 LEVEL 0 - DEMO & NEW PLAN. Room. Room. Room. Room. Room. Room. Room. Room.
1.d 2.d 3.d 4.d 1.d 2.d 3.d 4.d REMOVE, REPAIR, & REPLACE EXISTING STOREFRONT SYSTEMS D.1 D.2 REMOVE, REPAIR, & REPLACE EXISTING STOREFRONT SYSTEMS D.1 D.2 REMOVE STAIR & INFILL WALL C.1 REMOVE DOOR &
The Uniform Building Inspection Report Condensed
The Uniform Building Inspection Report Condensed Single Family Residence:, Scottsdale, AZ Condensed Report Version Prepared for: John Doe Inspection Date: 9/19/2005, 1:00:00 AM Report Number: 091805s Inspection
Chapter 3 Pre-Installation, Foundations and Piers
Chapter 3 Pre-Installation, Foundations and Piers 3-1 Pre-Installation Establishes the minimum requirements for the siting, design, materials, access, and installation of manufactured dwellings, accessory
Prestige Home Inspection LLC
Cover Page Prestige Home Inspection LLC IAC2/ESA - Mold Assessment and Water Damage Report 555 W. Brook ave., Client's town MI, 48059 Inspection prepared for: Client's name Inspection Date: 10/15/2012
Patio Covers / Carports
Patio Covers / Carports Building Guides for Homeowners Why Do I need a Permit? D I D Y O U K N O W? As owner-builder you are the responsible party of record on such a permit. If your work is being performed
29 Broadway- 14 th Fl Tel: 212.888.8334 New York NY 10006 Fax: 212.419.1939. Due Diligence Report. New York, New York
Due Diligence Report New York, New York Prepared for Mr. On February 8, 2010 P a g e 1 Table of Contents PAGE 3.. GENERAL INFORMATION PAGE 4 FILINGS PERMITS AND ENCUMBRANCES PAGE 6. CORE AND SHELL PAGE
University of California - Santa Barbara West Campus Point Faculty Housing
University of California - Santa Barbara West Campus Point Faculty Housing Reconstruction Guidelines and Considerations to Correct Exterior Building Envelope Weatherproofing Defects and Recommended Upgrades
WATER LEAKAGE IN GLAZED CURTAIN WALL SYSTEMS:
WATER LEAKAGE IN GLAZED CURTAIN WALL SYSTEMS: BY WILLIAM D. SMITH Figure 1 Four Corporate Center, Franklin, TN. Architect: Little & Associates,Charlotte, NC. Gen. Contractor: Ray Bell Const. Co., Nashville,
Residential Building Permits
LANE COUNTY PUBLIC WORKS Residential Building Permits LAND MANAGEMENT DIVISION 3050 N. DELTA HWY, EUGENE OR 97408 i CONTACT PHONE NUMBERS: Building Program: (541) 682-4651 Inspection Requests: (888) 299-2821
Sample Drawing Package for One and Two Family Dwelling Applications
Sample Drawing Package for One and Two Family Dwelling Applications For a full list of submission requirements, refer to the relevant checklist for your application found on our website: http://vancouver.ca/home-property-development/application-forms-and-checklists.aspx
WOOD DESTROYING PESTS AND ORGANISMS INSPECTION REPORT
Building Address: WOOD DESTROYING PESTS AND ORGANISMS INSPECTION REPORT 1648 Sedona Terrace, San Jose, CA 95116 05/16/2011 5 First Choice Inspections 447 Chilberg Ct. San Jose CA 95133 Phone: (800) 381-6911
Name of course: Residential Construction Site Management (RCSM) Level 1
Name of course: Residential Construction Site Management (RCSM) Level 1 Core (required courses) or Optional (elective course): Required Delivery Method: This is an online course only with no classroom
October 30, 2014. Mr. & Mrs. Daniel Vick 101 Southwind Cove Benton, AR. Report of Findings, Structural Investigation, Benton, Arkansas, Dear Mr.
117 S. Market St. Benton, AR 72015 * 501-315-2626 * Fax 501-315-0024 October 30, 2014 Mr. & Mrs. Daniel Vick 101 Southwind Cove Benton, AR Re: Report of Findings,, Benton, Arkansas, Dear Mr. Vick: This
DESIGNERS GUIDE TO DOMESTIC CONSERVATORIES
WBCA 403 DESIGNERS GUIDE TO DOMESTIC CONSERVATORIES A guide to assist those intending to install or who are involved in installing conservatories. Includes information about: conservatory and component
How To Repair A Boat Landing Deck With A Boat Bed
RESIDENTIAL INSULATED SHEATHING INSTALLATION GUIDE Residential Insulated Sheathing Installation Guide ROXUL COMFORTBOARD IS Table of Contents Slab-on-grade-to Above Grade Wall...1 Foundation Wall at Footing
Lighthouse Engineering, L.L.C.
Wednesday, August 20, 2014 Lighthouse Engineering, L.L.C. Michael Gandy, P.E. Registered Professional Engineer (TX: 95672) Registered Engineering Firm (F: 9334) Phone: 214-577-1077 Fax: 214-224-0549 Website:
OTTAWA CIVIC CENTRE & NORTH SIDE STANDS LANSDOWNE PARK FRANK CLAIR STADIUM STRUCTURAL ADEQUACY REPORT 2007
OTTAWA CIVIC CENTRE & NORTH SIDE STANDS at LANSDOWNE PARK FRANK CLAIR STADIUM STRUCTURAL ADEQUACY REPORT 2007 for CITY OF OTTAWA REAL PROPERTY ASSET MANAGEMENT prepared by ADJELEIAN ALLEN RUBELI LIMITED
Chapter 2: Foundations
Chapter 2: Foundations Crawlspace [V502.1.2] Vents. Vents in the crawlspace help keep floor insulation and floor framing dry. Crawlspace vents also reduce the potential for radon buildup under the floor.
2. What building projects are exempted? (permit not required)
BUILDING AND SAFETY DEPARTMENT 1. What building projects require a permit? Following is a list of projects that require building permits based on Appendix chapter 1 of the California Building Code and
SECTION 3 ONM & J STRUCTURAL ANALYSIS
Historic Boynton Beach High School Existing Building Assessment City of Boynton Beach February 10, 2011 SECTION 3 ONM & J STRUCTURAL ANALYSIS STRUCTURAL ENGINEERS SPECIAL INSPECTORS STRUCTURAL CONDITION
BELL ASSOCIATES ARCHITECTURE PLANNING
BELL ASSOCIATES ARCHITECTURE PLANNING Roger Bell dip. arch. tech. Bsc. CAD Rogerstown, Rush, Co. Dublin. Muchgrange, Greenore, Co. Louth E [email protected] T 01-8430267 T 042 938 3865 M 087 2371984
G. Common Defects in Buildings - Leakage
F. Common Defects in Buildings - Structural 32. Recently, some concrete chips have fallen from the ceiling in my kitchen. There are rusty steel bars and the area in question measures about 300 x 400mm.
MAJOR 2015 MN RESIDENTIAL CODE CHANGES Effective Date: January 24 th, 2015
MAJOR 2015 MN RESIDENTIAL CODE CHANGES Effective Date: January 24 th, 2015 **Disclaimer: This document is to serve as informational purposes only. This is not a code book or a final interpretation of the
HEDDERMAN ENGINEERING, INC. 3011 Carrie Cove Ct., Spring, TX 77386 281-355-9911, fax 281-355-9903 [email protected]
HEDDERMAN ENGINEERING, INC. 3011 Carrie Cove Ct., Spring, TX 77386 281-355-9911, fax 281-355-9903 [email protected] 2007 TO: Mr. REF: CONDITION OF PROPERTY SURVEY Dear Mr. : At your request,
Foundation Evaluation Report for PROPERTY ADDRESS Houston, Texas 77089. August 30, 2012. Prepared for:
A Full Service Real Estate Inspection & Engineering Firm for Houston, Texas 77089 August 30, 2012 Prepared for: CLIENT S NAME MAILING ADDRESS Houston, Texas 77089 Prepared by: Charles J. Jenkins, P.E.
WOOD DESTROYING PESTS AND ORGANISMS INSPECTION REPORT
Building : WOOD DESTROYING PESTS AND ORGANISMS INSPECTION REPORT 1621 Vineyard Ave # 2, Los Angeles, CA 90019 05/08/2014 5 Estate Termite, Inc. 2537 W. Beverly Blvd #202 Montebello CA 90640 Phone: (800)
NATIONAL FLOOD INSURANCE PROGRAM (NFIP) SUBSTANTIAL DAMAGE/ SUBSTANTIAL IMPROVEMENT (50% RULE)
NATIONAL FLOOD INSURANCE PROGRAM (NFIP) SUBSTANTIAL DAMAGE/ SUBSTANTIAL IMPROVEMENT (50% RULE) If your home or business is located within a 100-year floodplain and it was constructed through a County Building
10DBMC International Conference On Durability of Building Materials and Components LYON [France] 17 20 April 2005
10DBMC International Conference On Durability of Building Materials and Components Wall Cladding System Durability Lessons Learned from the Premature Deterioration of Wood-Framed Construction Clad with
RACKING AND ATTACHMENT CRITERIA FOR EFFECTIVE MEMBRANE ROOF SYSTEM INTEGRATION Public Version 1: July 9, 2012
RACKING AND ATTACHMENT CRITERIA FOR EFFECTIVE MEMBRANE ROOF SYSTEM INTEGRATION Public Version 1: July 9, 2012 Commercial rooftops represent the most available, sustainable and secure real estate for new
Number of Sides Required to Have a Handrail
Excerpt from 2012 B.C. Building Code HANDRAILS & GUARDS 9.8.7. Handrails 9.8.7.1. Required Handrails 1) Except as provided in Sentences (2) to (4), handrails shall be installed on stairs and ramps in accordance
C I T Y O F P E A R S A L L
The Largest City Between San Antonio and Laredo COMMUNITY DEVELOPMENT C I T Y O F P E A R S A L L A Business-Friendly, Family-Oriented Community Building Department Application Information (Please read
5006 Cherry Ridge Road Richmond, Texas 77406 281-342-9944 [email protected] LIMITATIONS AND DISCLAIMERS
5006 Cherry Ridge Road Richmond, Texas 77406 281-342-9944 [email protected] INSPECTION PROPERTY ADDRESS: INSPECTION PERFORMED FOR: XXXX Court Richmond, Texas Mr. Foundation Concerns INSPECTION DATE:
http://www.iccsafe.org/
Sections R311 and R312 from the 2006 International Residential Code These sections of Chapter 3 of the 2006 International Residential Code for One and Two Family Dwellings (R311 and R312) including the
WINDOW AND DOOR REPLACEMENT REQUIREMENTS
WINDOW AND DOOR REPLACEMENT REQUIREMENTS Should you have any questions after reading the following information, please call the Building Inspection Department at 651-439-4439 to discuss the topics of concern.
COMMON FOR ARCHITECTS AND ENGINEERS Excerpts from HB 2284, 82 nd R
Legislation passed by the 82 nd legislature has modified the Texas Engineering Practice Act and the Texas Architect Practice Act. In order to give the public a clearer understanding of these changes, the