1 1 Site Location, Design and Attributes The Primary Data Center shall be physically located on Oahu, Hawaii. 2 Site Location, Design and Attributes The Primary Data Center shall be located at least 1 mile outside the tsunami inundation zone and/or a 10 feet above the evacuation zone level above sea level 3 Site Location, Design and Attributes The Primary Data Center shall be at least 1 mile outside of defined hurricane/flood zones (e.g. the 100-year flood plain). 4 Site Location, Design and Attributes The Primary Data Center shall ideally be constructed with a seismic importance factor of 1.5 or greater than standard (i.e., ability to withstand 1.5 times the appropriate USGS 1988 or 1997 Zones). 5 6 Site Location, Design and Attributes Site Location, Design and Attributes The Primary Data Center shall ideally be constructed to withstand up to 150 mph wind speeds. The Primary Data Center shall be located far enough from the designated DR site (i.e. the Kalanimoku Building in downtown Honolulu, 1151 Punchbowl Street, Honolulu, Hawaii 96813) so that it is unlikely to be affected by the same disaster event. 7 Site Location, Design and Attributes The Primary Data Center shall be easily accessible from Honolulu's major highways and should be within commuting distance from Honolulu. (e.g. not more than 60 minute commute from downtown). 8 Site Location, Design and Attributes The Primary Data Center shall ideally be built away from sources of vibration and high-risk facilities sources, such as gas stations, fuel storage depots, hazardous material dumps, airports and rail lines. 9 Site Location, Design and Attributes The Primary Data Center shall ideally be built on a site large enough to suitable large site which can accommodate the structure, adequate parking and an appropriate secure set back from other properties. A security fence should enclose the entire site. 10 Site Location, Design and Attributes The Primary Data Center shall ideally be built on an adequate site adequate for at-grade development to be used for parking, water storage, fuel storage, generators, etc. 11 Site Location, Design and Attributes The Primary Data Center shall ideally be a purpose-built standalone structure sized to accommodate the required computer room capacity, required operational staff and supporting mechanical, electrical and power infrastructure. 12 Site Location, Design and Attributes The Primary Data Center shall have two separate and physically diverse fiber optic and copper building entrance facilities connecting the facility to carrier fiber optic facilities. Ideally both Hawaiian Telecom (HT) and Oceanic Cable will connect through both entrance facilities. 13 Site Location, Design and Attributes The Primary Data Center shall ideally have fiber optic connectivity to as many carriers as possible to allow carrier diversity. It shall also ideally have fiber optic connectivity to at least two Hawaiian Telecom Central offices. It will also connect to Time Warner Cable s fiber optic network via two different and fully diverse fiber optic paths. 14 The Primary Data Center shall be configured as a Ring node on the Hawaiian Institutional Network. This is a fiber optic based network which utilizes dark fiber provided by Time Warner Cable (Oceanic) and State-provided DWDM electronics to provide gigabit or higher speed connectivity among more than 300 different state and educational facilities. 15 Site Location, Design and Attributes The Primary Data Center shall have two different and diverse paths for connecting to the State's High Speed Dark Fiber Optic Ring. (as specified above) 16 Site Location, Design and Attributes The Primary Data Center shall ideally be equipped with multiple independent telecommunications carrier rooms (one for each entrance conduit for each major carrier). 17 Site Location, Design and Attributes The Primary Data Center shall provide dedicated and secured physical storage and staging areas. Storage and staging space shall be approximately 10-15% of the size of the computer room space. If a modular build out is proposed, the unused portions of the computer room may be use for this purpose so long as it will physically walled off and secured separately. 18 The Primary Data Center shall have docking facilities for power, data, water and air conditioning external connections. 19 Site Location, Design and Attributes The State desires that Primary Data Center shall ideally provide adequate office space for a Network Operating Center (NOC), Security Operations Center (SOC) and help desk. This space shall have the capacity to support operational personnel and will include appropriate amenities common in Class A office space (e.g. break room, restrooms, conference rooms, etc.). If this amount of space cannot be accompodated, the State's minimum requirement is for dedicated workspace for 5-10 personnel and access to meeting facilities. 20 The Primary Data Center shall have all entries protected by entry controls to ensure that only authorized personnel are allowed access, whether the facility is multi-tenant or single tenant facility The Primary Data Center shall be secured using a card key access system that is administered by the State The Primary Data Center shall have access points (such as delivery and loading areas and other points where unauthorized persons may enter the premises) that are controlled and isolated from information processing facilities (isolated from State equipment and data). 23 The State shall be able to authorize/approve all access to the State's physical hosting area (e.g. rooms or cages where State equipment is located or stored). 24 Access to the Primary Data Center shall be restricted to authorized personnel, whether single or multi-tenant facility.
2 25 26 The Primary Data Center shall protect hardware at all facilities from unauthorized physical access. The State desires a Primary Data Center which has biometric scanning options to support identity and access management for key State personnel 27 The Primary Data center shall have 24*7*365 on-site security guards monitoring the facility/grounds and admitting authorized personnel. 28 The Primary Data Center shall have 24*7*365 onsite personnel available to provide physical access to State equipment in case of emergency or to support other needs defined by the State 29 The Primary Data Center shall have video monitoring and recording of common access areas/entrances and high security zones where sensitive data is stored. Video recordings should be available for review for a minimum of 90 days. The State should have full access to this video when required. 30 Entry and exit of the Primary Data Center's physical hosting area shall be logged, records shall be reviewable by State and its auditors and records shall be maintained for reporting purposes for a minimum of 36 months. The log shall comply with regulatory requirements identified by the State (IRS, PCI, HIPPA, DOJ, etc.) 31 The Primary Data Center's Security office shall log all equipment delivery and removal from the Data Center and the log shall be available for State review, as requested. 32 The Primary Data Center security office shall monitor, review and respond to access violations and log security alerts and notification activity. Notification to the State of all attempted, or successful, physical access violations shall be made as soon as they are identified by the Service Provider. 33 The Primary Data Center shall be accessible by trucks and other large vehicles delivering equipment in to/out of facility and have dedicated loading docks for equipment delivery access. A dedicated loading dock for the State is preferred. 34 In a multi-tenant facility, dedicated entrances for State personnel are desired, but not required. A system where security and physical access controls are shared is acceptable. However, only State personnel should be able to access areas of the data center used by the State (computer rooms, telecom rooms, storage areas, offices, etc.) 35 The State desires a Primary Data Center with its own separate and dedicated entrances, including loading docks in a multitenant facility. While the state prefers a single tenant facility, multi-tenant facilities which offer superior values will be considered. 36 Computer Room The Primary Data Center shall locate all State IT assets within one contiguous space that is physically enclosed and accessible only to authorized State or State-authorized service provider personnel. If multiple spaces are required due to facility constraints they should each be physically secured with walls (including cages to permit air circulation) and electronic access controls and dedicated to the State. 37 Computer Room The Primary Data Center computer room should be large enough to accommodate the State s identified long term growth projections. 38 Computer Room The Primary Data Center shall locate State-used racks within walled (or caged) areas dedicated exclusively for State use. 39 Computer Room The Primary Data Center shall ideally be capable of meeting the State s floor loading requirements of 350 pounds per square foot. 40 Computer Room The Primary Data Center facility shall have load bearing capabilities for the proposed raised floor or slab constructions. 41 Computer Room The Primary Data Center shall provide standard racks as required by the State. These racks will be wired with power, fiber optic connectivity and low voltage wiring as specified by the State s standardized design row/module design. 42 Computer Room In the Primary Data Center power and data cabling shall be in separate trays. Ideally these trays shall be overhead. Ideally under floor (e.g. under the raised from, assuming raised floor is proposed) should be dedicated to cooling. This assumes that the Respondent proposes underfloor cooling. This is "hot topic" in the data center industry with some data center providers option to forgo raised floor and even where raised floor is used to not utilize it for cooling. Top down cooling proposal using cold/hot aisle containment schemes are pefectly acceptable to the state. 43 Computer Room The Primary Data Center shall have computer room wiring trays that provide capacity for both copper and fiber optic connectivity between racks. 44 Computer Room The Primary Data Center shall be equipped with a 10,000 square foot computer room. This computer room will accommodate all of the State's IT equipment. It will also accommodate power distribution equipment and computer room air handlers. This may be sub-divided to provide separate secure space for telecommunications equipment.
3 45 The State's long term data center capacity models assume that up to 325 standard sized cabinet units may be required over the expected year life of the Primary Data Center facility. This estimate includes a 33.33% contingency factor. 46 The State's expected ramp for cabinets is as follows: - Year 1- up to 100 cabinets - Year 2- Additional 50 cabinets - Year 3 Additional 50 cabinets - Years 4-5- Additional 50 cabinets - In subsequent years the State expects consolidation and transformation activities to be complete and to be able to use lifecycle management activities to manage to this capacity. - This ramp schedule does not include contingency (see above) 47 The Primary Data Center shall ideally be equipped be to handle a maximum IT equipment power load of mw (including contingency - see above). This would represent the power draw of all of the State's IT equipment. It would not include cooling, power distribution/protection overhead and facility overhead (lighting, etc.) power draws. The ramp to get this this power draw will be similar to cabinet ramp described above. Ideally the facility will support a cost effective modular approach to power distribution and protection which will allow this capacity to be built out as the need is clearly demonstrated. 48 Computer Room The Primary Data Center shall have humidity, temperature, and static controls. Anti-static flooring shall be used to prevent excess static build up. Ideally, anti-static flooring will be used to prevent excess static build-up. As an alternative to anti-static floor other option, other equally or more effective solutions such as ensure tactile grounding equipment is used when handing equipment internals are acceptable. 49 Computer Room The Primary Data Center shall maintain air temperature and humidity as measured at the equipment rack in the recommendable range as recommended by the American Society of Heating, Refrigerating and Air-Conditioning Engineers (ASHRAE) or equipment manufacturers. 50 Computer Room The Primary Data Center shall provide a dedicated and secured (State use only) LAN/SAN cabling and cross-connections area for State equipment hosted in the Data Center. 51 Power Systems, Cooling Systems and Other Critical Systems The Primary Data Center shall be built to a Tier 3 standard (e.g. continuous availability with no single points of failure ). Certification of the facility (not just the design) as Tier 3 by an independent 3rd party is desirable, but not required. The State's primary design goal is for a facility with N+1 redundancy for major systems and an overall design goal for continuous operation over extended periods (e.g. no downtime for facility maintenance or addition of new capacity over 5-7 year periods). 52 Power Systems, Cooling Systems and Other Critical Systems The Data Center infrastructure shall use a modular design and build out approach which will allow the State to add additional data center power and cooling capacity in increments of 400kw to 560kw (IT protected load) as they are needed. This requirement envisions that, to the extent possible and economical, all components would have modular expansion capability (e.g., computer room floor, racks, computer room air handling, power distribution, UPS, backup generators and cooling plant). 53 The State expects that the average power density of standard cabinets (including server, storage, mainframe, cross connect and network types) will be approximately kw. 54 Power Systems, Cooling Systems and Other Critical Systems The Primary Data Center shall be capable of handing high density cabinets of up to 12 kilowatts per cabinet without requiring the addition of specialized in row or in rack cooling. These racks will not constitute more than 5-10% of total racks and may be concentrated in a high density zone or spread across the computer room. 55 Power Systems, Cooling Systems and Other Critical Systems The Primary Data Center shall be designed for a low Power Usage Effectiveness (PUE) due to the State's concern regarding its environment/carbon footprint and the extremely high and highly variable cost of energy in HI. A PUE of 1.3 or less is desired. 56 Power Systems, Cooling Systems and Other Critical Systems The Primary Data Center should be designed so that specialized in rack or in/over row cooling can be easily and non disruptively added when super high density cooling is required to support very high density cabinets. The State prefers no row cooling if possible and would like guidance on this preference. 57 Power Systems, Cooling Systems and Other Critical Systems The Primary Data Center should be able to increase cooling and power capacity, as needed (while maintaining availability and redundancy requirements). 58 Power Systems, Cooling Systems and Other Critical Systems All of the Primary Data Center's critical systems should be provisioned to provide Tier 3 level of redundancy as defined by the Uptime Institute. Minor variances from this specification may be acceptable, but must be disclosed. At a minimum, the following systems should be configured as at least N+1 - UPS Capacity - Generators - Chillers/Cooling Towers - Chilled Water Distribution Systems - Computer Room Air Handlers - UPS Room Air Handlers
4 59 Power Systems, Cooling Systems and Other Critical Systems The Primary Data Center shall be able to meet published manufacturer s guidelines and manufacturers recommendations regarding temperature, humidity and power. 60 Power Systems The Primary Data Center shall have power feeds that are protected from short-term power failures by UPS systems, with capacity to supply stable power and transition to standby generator power automatically after any power failure event without service interruption. 61 The Primary Data Center shall have the two separate power feeds (A&B) from separate operating power plants. 62 The Primary Data Center shall have standby generators that provide at least N+1 redundancy. 63 That Primary Data Center shall have standby generators that include a minimum of 96 hours of onsite fuel storage. Fuel storage tanks shall be buried or otherwise secured against hurricane force winds and flooding if appropriate. 64 Power Systems The Primary Data Center shall have fuel delivery agreements to supply standby generators with more fuel as required to insure uninterrupted power in the event of extended outages. 65 Power Systems The Primary Data Center shall have UPS protection and back-up power generation capacity able to supports for the computer room (e.g. all of the State IT and telecommunications equipment) and supporting systems including but not limited to climate control systems, lighting, NOC/consoles, critical network elements, and phone systems. 66 Power Systems The Primary Data Center power (e.g. equipment loads on computer room floor and cooling) shall be protected from long-term power failures by standby generators. The generators will be sized to carry the entire computer room electrical load as well as any critical systems (e.g. Air Handlers, Chillers, Pumps, Fans, UPS cooling, Life/Safety, etc.) required to operate the facility when the main power has been disrupted. The generators will be tested weekly. The transfer process will be tested monthly or quarterly as required by the State. 67 Power Systems The Hawaii electric rate structure includes significant penalties when sudden or unexpected power spikes occur. For this reason, any transfer switch must include the ability to gradually switch from generator power to utility power after a power outage event has been resolved. 68 Power Systems The Primary Data Center shall have UPS systems that will be at least N+1 redundant. UPS systems should be modular to allow for minimum capacity to be configured upon commission, but with an easy and non-disruptive capacity upgrade path. 69 Power Systems The Primary Data Center shall have UPS input switchboards that include Transient Voltage Surge Suppression (TVSS). 70 The Primary Data Centers shall have a separate data center communications room with cross connects and access to outside cabling conduits. 71 Power Systems The Primary Data Centers will ideally have separate rooms for UPS systems and batteries. If only 2 UPS rooms are provided then 2N UPS redundancy must be provided. Cooling systems in UPS rooms shall be a minimum of N+1 redundant to ensure uninterrupted service in case of break down or preventative maintenance. 72 Power Systems The Primary Data Center should use modern, high efficiency UPS s and PDU/Power busses for power conversion and distribution. Losses due to conversion under normal loading conditions should be <5%. 73 Power Systems The Primary Data Center shall have power distribution that is accomplished by Data Center class equipment (UPS's, PDU's, Transfer Switches, etc.) 74 Power Systems The Primary Data Center shall not use air or water side economizers to reduce power utilization. Although HI power rates are highly variable and be as high as $.55 per kwh, HI s relatively high average temperature and humidity do not typically justify economizer costs. The state is open to using economizers or other cooling methods if they are proven to be effective in HI. 75 Power Systems The Primary Data Center shall have all power systems configured as N+1 with no single points of failure. This shall include the provision of A and B side UPS protected power to each rack in the computer room. 76 Power Systems The Primary Data Center shall provide 3-phase power feeds to racks as required by State. Each rack shall have dual power feeds from different sources (e.g. PDU s and UPS s) Power Systems Power Systems The Primary Data Center shall have all electrical connections that are lockable (twist-lock or other). The Primary Data Center shall have all cabinets that fed from an independent breaker of at least 30-Amp. 79 Cooling Systems The Primary Data Center shall have heat rejection equipment, such as chillers, chilled water piping, pumps and cooling towers which shall be at least N+1 redundant to ensure uninterrupted service in case of break down or preventative maintenance. 80 Cooling Systems Any proposed supplemental cooling fans or units such as in-row or overhead cooling units required for high density shall also be N+1 redundant.
5 81 Cooling Systems The Primary Data Center shall have air handling systems that provide 24*7*365 cooling and humidity control with a minimum N+1 redundancy to ensure uninterrupted service in case of break down or preventative maintenance. Where "n" is six or more for Computer Room Air Conditioning (CRAC) units, air handlers, chillers or cooling towers, a minimum of N+ 2 redundancies is required. 82 Other Critical Systems The Primary Data Center shall have a fire detection system in place. (e.g. VESDA, smoke and/or heat detectors). 83 Other Critical Systems The Primary Data Center shall have a water leakage detection system in place to detect possible water damage due to leakage or flooding. 84 Other Critical Systems Ideally, The Primary Data Centers shall have monitoring systems or shall be able to install an independent environmental monitoring system connected to its Network Operation Center (NOC). 85 Other Critical Systems The Primary Data Center facility, including UPS rooms, shall be protected by a pre-action, dry-pipe sprinkler system.
Subject: County of Los Angeles Data Center Space Requirement
Subject: County of Los Angeles Data Center Space Requirement The County of Los Angeles, Chief Executive Office, Real Estate Division (CEO-RED) is issuing this Property Search for the purchase of a vacant,
More informationAT&T Internet Data Center Site Specification - Phoenix Area (Mesa, AZ)
AT&T Internet Data Center Site Specification - Phoenix Area (Mesa, AZ) Site Biography Market Area: Phoenix, Mesa, Tempe, Chandler, Scottsdale, AZ Location: Mesa, AZ 85201 Address: 1301 University Blvd.
More informationOPERATOR - FACILITY ADDRESS - DATE
. Facility Criteria (RFP).0 Location Characteristics Criteria Requirements 1 Ownership and Management: Please identify the owner(s) and managers of the property and indicate if there is on-site management.
More informationHow To Visit An Internet Data Center
AT&T Internet Data Center Site Specification Atlanta Area (Lithia Springs, GA) Site Biography Market Area: Atlanta and surrounding areas (Georgia, Alabama, Tennessee, Florida, North and South Carolina
More informationDATA CENTERS. VAZATA Headquarters: 6900 Dallas Parkway, Suite 800 Plano, TX 75024 VAZATA.COM
DATA CENTERS VAZATA Headquarters: 6900 Dallas Parkway, Suite 800 Plano, TX 75024 VAZATA.COM DAL II MARSH LANE CARROLLTON TX OVERVIEW VAZATA s Dallas Data Center II (Dal II) is located at 2440 Marsh Lane
More informationAT&T Internet Data Center Site Specification San Diego Koll (San Diego, CA)
AT&T Internet Data Center Site Specification San Diego Koll (San Diego, CA) Site Biography Market Area: San Diego, CA Location: San Diego, CA 92121 Address: 5732 Pacific Center Blvd CLLI,POP, NPA/NXX Code:
More informationAT&T Internet Data Center Site Specification Chicago Area (Lisle, IL)
AT&T Internet Data Center Site Specification Chicago Area (Lisle, IL) Site Biography Market Area: Chicago, IL Location: Lisle, IL 60532 Address: 4513 Western Avenue CLLI,POP, NPA/NXX Code: LSLEILAA, EQLAILAA
More informationAT&T Internet Data Center Site Specification Washington-DC Area (Ashburn, VA)
AT&T Internet Data Center Site Specification Washington-DC Area (Ashburn, VA) Site Biography Market Area: Washington, DC Area Location: Ashburn, VA 20147-6011 Address: All deliveries should be sent to
More information100 Locust Avenue, Berkeley Heights, New Jersey P R O P E R T Y O F F E R I N G
100 Locust Avenue, Berkeley Heights, New Jersey P R O P E R T Y O F F E R I N G The Opportunity Jones Lang LaSalle, Inc. (the Broker ) is please to offer the fee simple interest in 100 Locust Avenue (the
More informationAT&T Internet Data Center Site Specification Dallas Area (Allen, Tx)
AT&T Internet Data Center Site Specification Dallas Area (Allen, Tx) Site Biography Market Area: Dallas and Fort Worth Areas of Texas Location: Allen, Tx 75013 Address: 900 Ventura Drive CLLI, POP, NPA/NXX
More informationOur data centres have been awarded with ISO 27001:2005 standard for security management and ISO 9001:2008 standard for business quality management.
AIMS is Malaysia and South East Asia s leading carrier neutral data centre operator and managed services provider. We provide international class data storage and ancillary services, augmented by an unrivaled
More informationNORTHERN VIRGINIA ONE (NoVa) DATA CENTER OVERVIEW
VAZATA 9651 Hornbaker Road Manassas, VA 20109 VAZATA.COM VAZATA's NoVa One data center located at 9651 Hornbaker Road in Manassas, Virginia is engineered from the ground up to deliver highly reliable and
More informationISOMEDIA COLOCATION WWW.ISOMEDIA.COM/COLOCATION
ISOMEDIA COLOCATION WWW.ISOMEDIA.COM/COLOCATION Your business needs a robust infrastructure that is secure, cost effective and reliable in order to remain competitive in today s market. ISOMEDIA s colocation
More informationAT&T Internet Data Center Site Specification New York III (Secaucus, NJ)
AT&T Internet Data Center Site Specification New York III (Secaucus, NJ) Site Biography Market Area: New York City, New Jersey, Upstate NY and Lower Connecticut Location: Secaucus, NJ 07094 Address: 15
More informationLocation. Central Business District. Ataturk Airport IFC. Sabiha Gökçen Airport
Welcome Zenium Istanbul One provides 12,000 square metres of high specification technical space across three purpose-built data centers. It is Turkey s first wholesale data center offering; the data halls
More informationN O W A V A I L A B L E
N O W A V A I L A B L E 5 0, 0 0 0 S F P O W E R E D S H E L L D A T A C E N T E R I I Data Center Park Catawba County, North Carolina S P E C I F I C A T I O N S Contact Doug Hollidge for more information
More informationsan francisco//usa data center specifications tel: +61 2 9948 8888 fax: +61 2 9948 1111 internet + intellectual property + intelligence
internet + intellectual property + intelligence We thank you for the opportunity to work with you regarding your colocation needs in San Francisco, USA. We can colocate standard rack-mountable servers
More informationOur data centres have been awarded with ISO 27001:2005 standard for security management and ISO 9001:2008 standard for business quality management.
AIMS is Malaysia and South East Asia s leading carrier neutral data centre operator and managed services provider. We provide international class data storage and ancillary services, augmented by an unrivaled
More informationContents Error! Bookmark not defined. Error! Bookmark not defined. Error! Bookmark not defined.
We Do It Better. Contents Introduction...3 Service and Support...3 Data Center Details...4 Security...4 Location...4 Power...4 Humidification...5 AC...5 Cooling...6 Datacenter Features...6 SAS 70...6 PCI
More informationLEVEL 3 DATA CENTER SERVICES IN OMAHA, NEBRASKA HIGH AVAILABILITY ENTERPRISE COMPUTING BUSINESS DEMANDS IT. LEVEL 3 DELIVERS IT.
LEVEL 3 DATA CENTER SERVICES IN OMAHA, NEBRASKA HIGH AVAILABILITY ENTERPRISE COMPUTING BUSINESS DEMANDS IT. LEVEL 3 DELIVERS IT. THE SCALE TO SUPPORT GLOBAL ENTERPRISE IT Designed and equipped to meet
More informationData Center Infrastructure & Managed Services Outline
Data Center Infrastructure & Managed Services Outline The 360 Technology Center Solutions Data Center is located in Lombard, IL, USA. We are 20 minutes outside of downtown Chicago. The 360TCS staff consists
More informationPacnet Hong Kong CloudSpace2 Technical Specifications. Upholding the Principles of Efficiency and Sustainability in Data Center Design
POWERING A CONNECTED ASIA Pacnet Hong Kong CloudSpace2 Technical Specifications Upholding the Principles of Efficiency and Sustainability in Data Center Design Our purpose-built, 5,000 m 2 Pacnet Hong
More informationhong kong//china data center specifications tel: +61 2 9948 8888 fax: +61 2 9948 1111 internet + intellectual property + intelligence
internet + intellectual property + intelligence We thank you for the opportunity to work with you regarding your colocation needs in Hong Kong, China. We can colocate standard rack-mountable servers or
More informationSite Preparation Management Co., Ltd. March 1st 2013 By Nara Nonnapha, ATD UPTIME
Site Preparation Management Co., Ltd. March 1st 2013 By Nara Nonnapha, ATD UPTIME 2 AGENDA SESSION -1 What is Data Center? SESSION -2 Equipment and Components SESSION -3 Standard in designing Data Center
More informationPOWERING A CONNECTED ASIA. Pacnet Hong Kong CloudSpace1 Technical Specifications. Asia s Pioneering Facility with Direct Subsea Cable Access
POWERING A CONNECTED ASIA Pacnet Hong Kong CloudSpace1 Technical Specifications Asia s Pioneering Facility with Direct Subsea Cable Access Our purpose-built, 300 m 2 Pacnet Hong Kong CloudSpace1 (HKCS1)
More informationData Center Checklist
Data Center Checklist The use of colocation and services has continued to increase, rapidly becoming the solution of choice for organizations requiring an efficient, secure, cost-effective way to manage
More informationSouth Asia s First Uptime Institute Certified TIER- IV IDC in Mumbai delivering 99.999% uptime
South Asia s First Uptime Institute Certified TIER- IV IDC in Mumbai delivering 99.999% uptime GPX India Pvt Ltd The Leader In Carrier Neutral TIER IV IDC s In Emerging Markets Incorporated in August 2002,
More informationScalable. Affordable. Flexible. Fast.
Modular Data Center Solutions Scalable. Affordable. Flexible. Fast. Build the data center you need today with the flexibility to meet tomorrow s challenges The only constant in business is change. Fluctuations
More informationData Centre Barrie, Ontario
COGECO DATA SERVICES DATA CENTRE Data Centre Barrie, Ontario Cogeco Data Services offers flexible, secure, connected and fully managed ICT solutions at its Flagship Data Centre in Barrie, Ontario Data
More informationvcloud SERVICE Virtual Tech in partnership with Equinix - vcloud Service
vcloud SERVICES vcloud SERVICE Virtual Tech offers competitive pricing on vcloud hosted services at our world class Tier 4 data centre facility fully equipped with redundant power, cooling, internet connectivity
More informationReduce the cost and delays associated with troubleshooting with the help of round-the-clock Service Desk Support.
Remote Support Reduce the cost and delays associated with troubleshooting with the help of round-the-clock Service Desk Support. SERVICE DEFINITION: REMOTE SUPPORT SERVICES ITI s Remote Support Service
More informationSafeguard your critical IT assets in a highly secure, fully redundant, environmentally-conditioned and constantly monitored hosting space to receive
Co-Location Services Safeguard your critical IT assets in a highly secure, fully redundant, environmentally-conditioned and constantly monitored hosting space to receive optimum performance 24x7. SERVICE
More informationOur Hosting Infrastructure. An introduction to our Platform, Data Centres and Data Security. www.in-tuition.net
Our Hosting Infrastructure An introduction to our Platform, Data Centres and Data Security www.in-tuition.net UK Infrastructure Infrastructure Overview Intuition Networks has provided managed Internet
More informationX-tier Data Facility. Prepared by X-tier SAE Corporation
X-tier Data Facility Company Profile X-tier Corporation X-tier is based in Leawood, Kansas. X-tier provides business agnostic, security hardened, custom and turnkey Cloudbased software systems, services,
More informationTitle: Design of a Shared Tier III+ Data Center: A Case Study with Design Alternatives and Selection Criteria
Tier 3+ 1 Title: Design of a Shared Tier III+ Data Center: A Case Study with Design Alternatives and Selection Criteria Abstract: Schoolcraft College is constructing a High Availability (HA) Data Center
More informationTechnical specifications. Containerized data centre NTR CDC 40f+
Technical specifications Containerized data centre NTR CDC 40f+ CONTENT 1 THE PURPOSE OF CDC... 3 2 BASIC PROPERTIES... 4 2.1 EXTERNAL DIMENSIONS... 4 2.2 INSTALLATION REQIREMENTS... 4 2.3 ELECTRICAL CONNECTION
More informationData Center Energy Profiler Questions Checklist
Data Center Energy Profiler Questions Checklist Step 1 Case Name Date Center Company State/Region County Floor Area Data Center Space Floor Area Non Data Center Space Floor Area Data Center Support Space
More informationSolveXia Business Continuity Planning
Business continuity planning is the term we use to describe all the steps we take at SolveXia to ensure that our service is up and running when you need it. As a 'Software as a Service' provider, our aim
More information7 Best Practices for Increasing Efficiency, Availability and Capacity. XXXX XXXXXXXX Liebert North America
7 Best Practices for Increasing Efficiency, Availability and Capacity XXXX XXXXXXXX Liebert North America Emerson Network Power: The global leader in enabling Business-Critical Continuity Automatic Transfer
More informationWorld s Greenest High Performance Data Center
World s Greenest High Performance Data Center EcoDataCenter Sustainability for future generations Our Services Colocation Data Center for Mission Critical Requirements Lockable racks, cages, private rooms
More informationDATA CENTERS. VAZATA Headquarters: 6900 Dallas Parkway, Suite 800 Plano, TX 75024 VAZATA.COM
DATA CENTERS VAZATA Headquarters: 6900 Dallas Parkway, Suite 800 Plano, TX 75024 VAZATA.COM OVERVIEW VAZATA's NoVa One data center located at 9651 Hornbaker Road in Manassas, Virginia is engineered from
More informationCOLOCATION PROVIDERS:
COLOCATION PROVIDERS: INTRO The benefits of colocation are well documented, and making the business case for going that route is often quite easy for many organizations. Once the decision has been made
More informationDATA CENTERS. VAZATA Headquarters: 6900 Dallas Parkway, Suite 800 Plano, TX 75024 VAZATA.COM
DATA CENTERS VAZATA Headquarters: 6900 Dallas Parkway, Suite 800 Plano, TX 75024 VAZATA.COM DAL I MIDWAY ROAD CARROLLTON TX OVERVIEW 4025 Midway Road is a full service, enterprise-class data center colocation
More informationDedicated Hosting Services
Dedicated Hosting Services Protect and manage your Servers/ Routers/ Switches/ storage devices/ security devices under a highly secure hosting space and get the finest performances out of them. SERVICE
More informationin other campus buildings and at remote campus locations. This outage would include Internet access at the main campus.
DATA CENTER The current Campus Data Center is located within historic Founders Hall which is in a less-than ideal location for a variety of reasons, but is typical of an existing campus IT infrastructure
More informationAbout Injazat. Enterprise Cloud Services. Premier Data Center. IT Outsourcing. Learning and Development Services. Enterprise Application Services
About Injazat Injazat Data Systems is an industry-recognized market leader in the region for Information Technology Outsourcing, Cloud and Data Center Managed Services delivered from the region s 1st Tier
More informationNetwork Router Monitoring & Management Services
Network Router Monitoring & Management Services Get different parameters of routers monitored and managed, and protect your business from planned and unplanned downtime. SERVICE DEFINITION: NETWORK ROUTER
More informationCOMMODITIZING THE DATA CENTER MARKET
COMMODITIZING THE DATA CENTER MARKET Site Summary The building at 1360 Kifer Road has approximately 94,500 SF of server and support space and is currently divided into two independent data center areas.
More informationDepartment of Administration DATA CENTER Two Phase Approach Located at the State Defense Building
DATA CENTER Two Phase Approach Located at the State Defense Building July 17, 2015 Compiled by: Office of Facilities and Property Management 800 SW Jackson, Suite 600 Topeka, Kansas 66612-1216 i I. Programming
More informationChicago 1 (CHI-1) Data Center
215 W. Ohio St. 5th Floor Chicago, IL 60564 Call Us Toll-Free 1 (866) 817-2811 Follow Us @SingleHop Like Us facebook.com/singlehop Chicago 1 (CHI-1) Data Center Enterprise-Class, Downtown Chicago Facility
More informationData Centre Basiglio, Milan Flexible, advanced and efficient by design.
Data Centre Basiglio, Milan Flexible, advanced and efficient by design. TelecityGroup Via Francesco Sforza 13 Milano 3 City 20080 Basiglio MI Italy Tel: +39 02 36679500 it.info@telecity.com www.telecitygroup.it
More informationAttracting Data Centers to Your Market
Attracting Data Centers to Your Market A Presentation for: Presented by: Wendy McArthur, CB Richard Ellis OVERVIEW Introduction Qualify Requirement Site Selection Cost Marketing CB Richard Ellis Page 2
More informationData Center CH1. Elk Grove Village, IL
Data Center CH1 Elk Grove Village, IL powerful/ efficient /reliable solutions > Data Center CH1 ABOUT DUPONT FABROS TECHOLOGY (DFT) DFT is a leading owner, developer, operator and manager of wholesale
More informationEnergy-efficient data center achieves 2N reliability; MTU Onsite Energy generator sets provide critical backup
Press Release Contact: Gary Mason Tognum America Inc. Phone: +1 248 560 8480 E-mail: gary.mason@tognum.com Agency contact: Robert E. Sheldon, APR Creative Communications Consultants, Inc. Phone: +1 210
More informationCyberFortress Data Center at Innovation Park Infrastructure and Topology Guide. Innovation Park Charlotte. NC 28262. DRAFT V0.
Innovation Park Charlotte. NC 28262 DRAFT V0.1 Page 2 CyberFortress Data Center at Innovation Park BECO South purchased Innovation Park in March 2010 and immediately launched a dramatic top-to-bottom $30M
More informationSLA. Co-Managed. Do-It-Yourself
SLA Do-It-Yourself Co-Managed Co-Managed Fully Managed Operational Application Support DB Support Storage Planning Capacity planning Change Management Release Management Pro Services Systems Monitoring
More informationData Center Co- Location
Management Council of the Ohio Education Computer Network Request for Quote Data Center Co- Location March 6, 2013 Responses are due by 4:00 pm on March 20, 2013 General Information The Management Council
More informationData Center Overview Document
Overview NetSource is a Chicago area (Naperville) hosting company that owns and operates its own world class datacenter. The initial datacenter buildout was put into operation in 2007 and expanded in 2013.
More informationColocation. Introduction. Structure of the service. Service Description
Introduction IP-Only provides colocation services for customers with very high reliability and availability requirements. In combination with its transmission and IP services, IP-Only offers space in high-security
More informationServer Monitoring & Management Services
Server Monitoring & Management Services Monitor and manage your applications and servers under enterprise-class monitoring solutions, and protect your business from planned and unplanned downtime. ITI
More informationExperience Matters...
Experience Matters... Travelport Data Center offers confidence and space to meet your demanding IT needs Transwestern presents the Travelport Data Center in Denver, Colorado totaling 267,000 SF with 121,600
More informationGreen Data Centre Design
Green Data Centre Design A Holistic Approach Stantec Consulting Ltd. Aleks Milojkovic, P.Eng., RCDD, LEED AP Tommy Chiu, EIT, RCDD, LEED AP STANDARDS ENERGY EQUIPMENT MATERIALS EXAMPLES CONCLUSION STANDARDS
More informationIntroducing UNSW s R1 Data Centre
Introducing UNSW s R1 Data Centre R1-DC Our New High Density Data Centre Right here Right now - Welcome to our newest UNSW Data Centre R1-DC R1 Location on UNSW Randwick campus. Keeping it in the family
More informationSYSTRUST CERTIFICATION REPORT FOR COLLOCATION AND DATA CENTER HOSTING SERVICES FOR THE PERIOD FROM JANUARY 1, 2013 TO DECEMBER 31, 2013
SYSTRUST CERTIFICATION REPORT FOR COLLOCATION AND DATA CENTER HOSTING SERVICES FOR THE PERIOD FROM JANUARY 1, 2013 TO DECEMBER 31, 2013 TABLE OF CONTENTS SECTION I: INDEPENDENT PRACTITIONERS TRUST SERVICES
More informationZone B: comprises of NOC room, reception area, Help Desk area, Call Centre, Testing/Monitoring room. This zone requires approximately 1500 sq. feet.
Annexure 1 Best practices and Guidelines to Physical Security of the State Data Centre The Data Centre should ideally be built in a central location within the building complex. An approximate area of
More informationData Center Presentation
Data Center Presentation The NetSource Datacenter. Agenda General Layout of Data Center Policies and Procedures Designed to Latest Standards High Performance High Reliability High Security Design Details
More informationOur data centres have been awarded with ISO 27001:2005 standard for security management and ISO 9001:2008 standard for business quality management.
AIMS is Malaysia and South East Asia s leading carrier neutral data centre operator and managed services provider. We provide international class data storage and ancillary services, augmented by an unrivaled
More informationTIA-942 Data Centre Standards Overview WHITE PAPER
TIA-942 Data Centre Standards Overview WHITE PAPER TIA-942 Data Centre Standards Overview For the past 20 years, cabling standards have been the cornerstone of ensuring proper design, installation, and
More informationSouth Asia s First Uptime Institute Certified TIER-IV IDC in Mumbai delivering 99.999% guaranteed uptime
South Asia s First Uptime Institute Certified TIER-IV IDC in Mumbai delivering 99.999% guaranteed uptime GPX India Pvt Ltd The Leader In Carrier Neutral TIER IV IDC s In Emerging Markets Incorporated in
More informationsingapore//singapore data center specifications tel: +61 2 9948 8888 fax: +61 2 9948 1111 internet + intellectual property + intelligence
internet + intellectual property + intelligence We thank you for the opportunity to work with you regarding your colocation needs in Singapore. We can colocate standard rack-mountable servers or other
More informationColocation Buyer s Guide and Checklist. A 5-10-15 Playbook for Technology Managers
Colocation Buyer s Guide and Checklist A 5-10-15 Playbook for Technology Managers Deciding how to manage IT infrastructure is not easy. This document will help determine if colocation makes sense for your
More informationIBM Twin Data Center Complex Ehningen Peter John IBM BS peter.john@de.ibm.com. 2011 IBM Corporation
IBM Twin Data Center Complex Ehningen Peter John IBM BS peter.john@de.ibm.com Overview Profile IBM owned facility 6447 m² IT-Space Infrastructure concurrent maintainable (Tier Level 3) Feed-ins of Power
More informationHouse your data in a building constructed for only one express purpose protect the information inside. Twin Cities East Data
Protection is Central. Twin Cities East Data Center House your data in a building constructed for only one express purpose protect the information inside. Twin Cities East Data Center is nothing less than
More informationHow To Write An Infrastructural Standard For Data Center Infrastructure
Infrastructure Standard for Data Centers ANSI/CSA/EIA/TIA-942 (PN-3-0092) Introduction When approved, the standard will be: ANSI/CSA/EIA/TIA-942 Telecommunications Infrastructure Standard for Data Centers
More informationManaging Cooling Capacity & Redundancy In Data Centers Today
Managing Cooling Capacity & Redundancy In Data Centers Today About AdaptivCOOL 15+ Years Thermal & Airflow Expertise Global Presence U.S., India, Japan, China Standards & Compliances: ISO 9001:2008 RoHS
More informationDATACENTER COLOCATION. Flexible, Secure and Connected
DATACENTER COLOCATION Flexible, Secure and Connected Flexible Solutions for Your Requirements Contents Your Goals 2 Compound and Buildings 4 Security 6 Infrastructure 8 Free Choice 10 Good Reasons 12 Our
More informationBuilding a data center. C R Srinivasan Tata Communications
Building a data center C R Srinivasan Tata Communications Introduction Data Center as defined by TIA 942 A building or a portion of a building whose primary function is to house a computer room and its
More informationAutomation's Modular Containerized Datacenter Solutions
SAFE Automation's Modular Containerized Datacenter Solutions Automation's SAFE (Secure, Autonomous, Flexible, Efficient) Modular Containerized Datacenter offers a fast, flexible and efficient solution
More informationRecommendations for Measuring and Reporting Overall Data Center Efficiency
Recommendations for Measuring and Reporting Overall Data Center Efficiency Version 2 Measuring PUE for Data Centers 17 May 2011 Table of Contents 1 Introduction... 1 1.1 Purpose Recommendations for Measuring
More informationData Center Due Diligence List
Data Center Due Diligence List Name and address of site facility Date constructed Building owner/date purchased by current owner Name of previous owner Adjacent Property Descriptions North South East West
More informationData Center Trend: Distributed Power in the White Space
Data Center Trend: Distributed Power in the White Space By Jason Anderson Product Line Manager Eaton Executive summary Cloud computing vendors and colocation data centers make every effort to maximize
More informationThe Pros and Cons of Modular Systems
The Pros and Cons of Modular Systems Kevin Brown, Vice President Global Data Center Offer Schneider Electric Schneider Electric 1 Foundational BUSINESS OVERVIEW Rev 2 Desired characteristics of pre-fabricated
More informationSubject: ITN for Redundant High Speed Communications (Part II) Off Campus Equipment Location. Proposed Board Action
AGENDA ITEM: VIII D (ii) Florida Polytechnic University Board of Trustees August 26, 2013 Subject: ITN for Redundant High Speed Communications (Part II) Off Campus Equipment Location Proposed Board Action
More informationAustralian Government Data Centre Strategy 2010-2025
Australian Government Data Centre Strategy 2010-2025 Better Practice Guide: Data Centre Power June 2013 17/06/2013 4:12 PM 17/06/2013 4:12 PM Contents Contents 2 1. Introduction 3 Scope 3 Policy Framework
More informationEVALUATING DATA CENTER AND COLOCATION HIGH-AVAILABILITY SERVICE DELIVERY. A FORTRUST White Paper. March, 2013. www.fortrustdatacenter.
EVALUATING DATA CENTER AND COLOCATION HIGH-AVAILABILITY SERVICE DELIVERY A FORTRUST White Paper March, 2013 When companies evaluate potential data centers and colocation service providers, they normally
More informationDatacentre Studley. Dedicated managed environment for mission critical services. Six Degrees Group www.6dg.co.uk
Dedicated managed environment for mission critical services www.6dg.co.uk Our datacentres are the core of our business. At we own and manage 30,000 square feet of highly available, geographically diverse
More informationDigital Chicago. 600 south FeDeraL - chicago 9333 9377 grand ave - FranKLin ParK 350 east cermak - chicago
Digital Chicago 600 south FeDeraL - chicago 9333 9377 grand ave - FranKLin ParK 350 east cermak - chicago The Digital Chicago portfolio consists of three state-of-the-art data center facilities: 600 South
More informationData Centre Stockholm II, Sweden Flexible, advanced and efficient by design.
Data Centre Stockholm II, Sweden Flexible, advanced and efficient by design. Equinix Telecity Kvastvägen 25-29 128 62 Sköndal Stockholm Sweden Tel: +46 (0) 8 799 3800 se.info@telecity.com www.telecitygroup.se
More informationUpgrading the PRS datacentres: space requirement. S. S. Mathur, GM-IT, CRIS
Upgrading the PRS datacentres: space requirement S. S. Mathur, GM-IT, CRIS PRS / UTS scenario: then and now Year 2000 PRS: 600 locations UTS: 0 locations Year 2008 PRS 1600 locations E-ticketing Passengers
More informationKEEN - Reliable Infrastructure, Built to Last
KEEN - Reliable Infrastructure, Built to Last 2 KEEN--Reliable Infrastructure, Built to Last A strong network infrastructure is the underpinning of the Knowledge Elements Education Network (KEEN). It is
More informationSanta Clara, CA 95054
Leading-Edge Datacenter Facility Silicon Valley GENERAL In excess of 41,000 sq. ft. of raised floor 9 MVA of utility power into facility Purpose built Green Datacenter Sutton Roley Lic. 00793235 (408)
More informationData Center Industry Leaders Reach Agreement on Guiding Principles for Energy Efficiency Metrics
On January 13, 2010, 7x24 Exchange Chairman Robert Cassiliano and Vice President David Schirmacher met in Washington, DC with representatives from the EPA, the DOE and 7 leading industry organizations
More informationLEVEL 3 DATA CENTER ASSESSMENT
Nationwide Services Corporate Headquarters 410 Forest Street Marlborough, MA 01752 USA Tel: 800-342-5332 Fax: 508-303-0579 www.eecnet.com LEVEL 3 DATA CENTER ASSESSMENT Submitted by: Electronic Environments
More informationShould You Move to a Public Colocation Facility?
Should You Move to a Public Colocation Facility? Written by Eric Rosenberry Every organization I have worked at has done battle with our long lasting enemies, Space, Power, and Cooling (not to mention
More informationDatacenter Hosting and Cloud Computing Services
Datacenter Hosting and Cloud Computing Services Overview Background Founded in 1995, Lore Systems operates an international datacenter network which today includes full service 3+ datacenter facilities
More informationData Center Colocation Build vs. Buy
Data Center Colocation Build vs. Buy Comparing the total cost of ownership of building your own data center vs. buying third-party colocation services Executive Summary As businesses grow, the need for
More informationCURBING THE COST OF DATA CENTER COOLING. Charles B. Kensky, PE, LEED AP BD+C, CEA Executive Vice President Bala Consulting Engineers
CURBING THE COST OF DATA CENTER COOLING Charles B. Kensky, PE, LEED AP BD+C, CEA Executive Vice President Bala Consulting Engineers OVERVIEW Compare Cooling Strategies in Free- Standing and In-Building
More informationNeuStar Ultra Services Physical Security Overview
NeuStar Ultra Services Physical Security Overview Mission-critical network operations must have the highest standards of quality, security and reliability. NeuStar Ultra Services currently locates its
More informationDATA CENTRES UNDERSTANDING THE ISSUES TECHNICAL ARTICLE
DATA CENTRES UNDERSTANDING THE ISSUES TECHNICAL ARTICLE Molex Premise Networks EXECUTIVE SUMMARY The term data centre usually conjures up an image of a high-tech IT environment, about the size of a football
More informationData Center Designs and Hospital Operations
Data Center Designs and Hospital Operations Designing for Data Center Availability and the Effect on Daily Operations Joe Harris, PE, RCDD Senior Engineer, AECOM Data Centers and Hospitals June 10, 2015
More information