1 AT&T Internet Data Center Site Specification San Diego Koll (San Diego, CA) Site Biography Market Area: San Diego, CA Location: San Diego, CA Address: 5732 Pacific Center Blvd CLLI,POP, NPA/NXX Code: SANDKCACN, SNDGCABM, 858/450 History of Facility: Upgraded facility built to AT&T Internet Data Center and Industry IDC standards as outlined in the Uptime Institute Report. Other high technology companies surround this facility. Center Amenities: Customer Lounge Facilities Customer Conference Room Customer Briefing/Visit Request: If you would like to schedule a Domestic IDC Tour, click here to use the scheduler If you are not a Certified Tour Manager and would like to schedule a visit to a Domestic IDC, please contact your local Enterprise Hosting Specialist. For the Corporate Briefing Center in Bedminster, NJ, use the BriefingEdge Online Visit Scheduling System Gross Sq. Ft.: 68,600 Total Net Square Feet: 40,600 SAS70: This site is subject to annual SAS70 Type 2 auditing. Network Internet (Front-end) IP Capacity: Minimum of two (2) 10 Gigabit Ethernet WAN uplinks to the AT&T IP Network Redundancy: Administrative (Back-end) Access: Redundant and path-diverse entrances and exits. Dual access routers connect the Internet Data Center to the AT&T IP Network via multiple network access points. Access the AT&T Back-End Connectivity Guide for options 1
2 Architectural Section Building Raised Floor Specifications Loading and Receiving Dock Power Watts / Square Foot Electrical Redundancy There is no raised floor for this site Loading dock facilities are available. Onsite security personnel monitor access to the loading dock. Customer shipments to the IDC require customer site ID # on all shipping labels. The facility is constructed to support 120 w/sf. The Internet Datacenter has two (2) 4000 AMP, 480 volt commercial power services feed for each building, fed from two separate power grids. Standby Generator Systems Uninterrupted Power Supply Grounding Architecture Commercial Power Contingency Arrangements Environmental Controls A/C Distribution A/C System A/C Redundancy Architecture A/C Contingency Arrangements Fire Suppression There are three (3) 1500kW diesel generators providing standby power to building A. Each generator has 2500-gallon fuel oil storage tank built into the base (7500 gallons reserve). Building B has two 1750 kw diesel generators, each with a 5000 gallon belly-tank, providing standby power to Bldg. B, plus, the use of Generator #3 from Bldg. A as a swing generator that can be used by either building as needed. In addition to the belly fuel storage tanks on each generator, all five generators are fed from two 16,000-gallon on-site, aboveground, fuel storage tanks with UPS power to the fuel pump. Geographically diverse fuel vendors are under contract to deliver fuel should refueling be necessary. There are two (2)-UPS systems; one consists of two redundant systems operating in parallel with three (3) - 400kW/500kVA modules each. Power is supplied to the UPS systems through commercial power feeders and standby generators. The UPS system is designed to support its full load for 15 minutes via its internal battery plant. This facility has enhanced data center grounding system. A perimeter ground ring is tied into driven ground rods. The UPS systems, equipment cabinets, racks and associated metal parts are tied into the ground ring. In case of a commercial power failure, the standby generators provide power to the Data Center within one minute of a commercial power outage. The one-minute gap is covered by the UPS system. During an extended commercial power outage, the diesel generators can provide power for a minimum of 72 hours using the fuel stored at the site. The quantity of generators represents N+1 redundancy in the generator plant. There are connection points, processes and procedures to hook up additional portable generators from AT&T s fleet of portable equipment to further ensure generator capacity and redundancy. There are eight (8) chillers, each with two 61 ton compressors (122 tons total/chiller), and eight air handling units (each backed up by two chillers) located around the perimeter, delivering conditioned air to equipment cabinets/ racks through supply air ducts and diffusers. 122-ton chillers supply chilled water to the air handling units. Conditioned air from the air handling units is discharged from overhead ducts. Designed to N+1 specifications required Industry Tier 4 Standards as outlined in the Uptime Institute Report. If a chiller fails, a standby chiller will carry the load until the chiller is fixed. The standby chiller is designed to operate continuously. The Center has pre-action dry pipe fire suppression system. In the data center equipment area. Nonequipment areas have wet sprinkler system. The Center has a state-of-the-art VESDA (air sampling) smoke detection and alarm system. It is 100 times more sensitive than conventional fire detection systems. Detectors are grouped into zones. When one or more detectors in different zones detect smoke, the fire alarm panel opens the deluge valve to fill the sprinkler piping with water. In the event of an actual fire, the seal on the sprinkler heads will melt and discharge water on the affected area. Water will not be discharged in unaffected areas. 2
3 Architectural Section - continued Security Building Access: Security staffing 24x7, closed circuit monitors, secure key-card access, biometrics scanner, a mantrap, and alarmed doors. Guards maintain access from the loading dock and access requires a card key. Security personnel also monitor the building and use an electronic watch monitoring system that identifies when and where guards have patrolled. AT&T maintains a current list of authorized personnel. AT&T maintains all keys for cabinets and cages in a lock box on site. Customers are not allowed in managed spaces. Site Monitoring: 24x7 monitoring is performed on site and remotely. Shipping & Receiving: No unidentified packages will be accepted. Onsite security personnel monitor access to the loading dock. Customer shipments to the IDC require customer site ID # on all shipping labels. Operations Staffing: Internet Data Center technicians and building engineers are available 24x7. Remote Hands: Available 24x7. See AT&T Enterprise Hosting Service Guide for details 3
4 Risk Assessment General Information Site Description: The site is located in a region of Seismic Activity. The building meets current seismic code. There are no major faults in the area. Building Description: The Web Hosting Facility is located in a three story building which originally functioned as a research and corporate data center, which has been totally re-purposed for data center use, (no corporate data functions remain). The building was constructed in The building has structural steel moment resisting space frame construction with cast-in-place concrete floor slabs. The building has a brick face and glass exterior Floors designed for the following live loads: Battery rooms 300 psf. Electrical rooms 200 psf, Mechanical rooms 200 psf, Web Hosting raised floor areas 150 psf. General Condition: Building appears to be in good condition. No significant signs of distress have been observed. Earthquakes Hazard Assessment Seismic zone 2 Ground Shaking Hazard: very low Soil Liquefaction Hazard: very low Soil Compaction Hazard: very low Fault Rupture Hazard: none Tsunami Hazard: none Landslide Hazard: none Risk Assessment - continued Building Risk Assessment: Web Hosting Building There is very low potential steel frame connection damage, due to the low seismic zone. No life safety hazards identified Equipment Risk Assessment: Equipment Anchorage Description Risk Assessment Data Center Racks Anchored to raised floor tile and tiles locked to raised floor framing w/ unistrut. Overhead Auxiliary Framing Suspended racking braced per AT&T Standards Raised Access Flooring Web Host Area Only CRAC Units PDUs Units are anchored to the concrete floor slab via steel stands through the raised floor. Units are anchored to the concrete floor slab via steel stands through the raised floor. 4
5 UPS Units are anchored to structural concrete floor slab. Switchgear Units are anchored to structural concrete floor slab. Electrical conduits Units are supported per AT&T Standards, Run underground outside building. Chillers Units sit on spring isolators which are anchored to secure and fenced roof dunnage. Chilled Water Piping All piping is supported per ANSI B31.9 Generators Units are anchored to concrete foundation on structural concrete pads. Regional Disaster Effects on Site Loss of Power: Power supplied by dual utility feed, two (2) feeders. Standby generators can maintain power supply 48 hour diesel fuel storage on site Network Connectivity: Two diversely routed telecom duct banks provided. Summary: Site is in general well prepared to resist the effects of an earthquake. Seismic activity (earthquake) is a very remote possibility at this location. Windstorms Hazard Assessment: Factory Mutual Design Wind Speed: 90 mph (3 second gust) Factory Mutual Ground Roughness Exposure Category: B Overall, lateral wind loads during a windstorm are more severe than earthquake loads at this site. Historic windstorm risk is very low for this location. Regional Disaster Effects on Site - continued 5
6 Building Risk Assessment: The building is assessed to have a low risk for wind damage. Equipment Risk Assessment: Interior equipment is adequately protected against the effects of a windstorm. Exterior equipment is adequately anchored to resist the effects of a windstorm. Regional Disaster Effects on Site Loss of Power: See Earthquake Risk Above Network Connectivity: See Earthquake Risk Summary: Site is in general well prepared to resist the effects of a windstorm. Flooding Hazard Assessment: Site is located above the 100-year flood plain level. Flooding is not considered to be a significant hazard for this site. Man-Made Hazards Crime Critical site equipment is fenced to protect outdoor equipment. Site has security guard coverage 24 hours a day, 7 days a week, year-round. Security system monitors property, gates, and all doors (interior and exterior). Controlled entry into data centers via biometric controls Considered to be a low risk Sabotage: Exterior exposure is limited and protected. 6
AT&T Internet Data Center Site Specification - Phoenix Area (Mesa, AZ)
AT&T Internet Data Center Site Specification - Phoenix Area (Mesa, AZ) Site Biography Market Area: Phoenix, Mesa, Tempe, Chandler, Scottsdale, AZ Location: Mesa, AZ 85201 Address: 1301 University Blvd.
AT&T Internet Data Center Site Specification Chicago Area (Lisle, IL)
AT&T Internet Data Center Site Specification Chicago Area (Lisle, IL) Site Biography Market Area: Chicago, IL Location: Lisle, IL 60532 Address: 4513 Western Avenue CLLI,POP, NPA/NXX Code: LSLEILAA, EQLAILAA
How To Visit An Internet Data Center
AT&T Internet Data Center Site Specification Atlanta Area (Lithia Springs, GA) Site Biography Market Area: Atlanta and surrounding areas (Georgia, Alabama, Tennessee, Florida, North and South Carolina
AT&T Internet Data Center Site Specification New York III (Secaucus, NJ)
AT&T Internet Data Center Site Specification New York III (Secaucus, NJ) Site Biography Market Area: New York City, New Jersey, Upstate NY and Lower Connecticut Location: Secaucus, NJ 07094 Address: 15
AT&T Internet Data Center Site Specification Washington-DC Area (Ashburn, VA)
AT&T Internet Data Center Site Specification Washington-DC Area (Ashburn, VA) Site Biography Market Area: Washington, DC Area Location: Ashburn, VA 20147-6011 Address: All deliveries should be sent to
AT&T Internet Data Center Site Specification Dallas Area (Allen, Tx)
AT&T Internet Data Center Site Specification Dallas Area (Allen, Tx) Site Biography Market Area: Dallas and Fort Worth Areas of Texas Location: Allen, Tx 75013 Address: 900 Ventura Drive CLLI, POP, NPA/NXX
100 Locust Avenue, Berkeley Heights, New Jersey P R O P E R T Y O F F E R I N G
100 Locust Avenue, Berkeley Heights, New Jersey P R O P E R T Y O F F E R I N G The Opportunity Jones Lang LaSalle, Inc. (the Broker ) is please to offer the fee simple interest in 100 Locust Avenue (the
NeuStar Ultra Services Physical Security Overview
NeuStar Ultra Services Physical Security Overview Mission-critical network operations must have the highest standards of quality, security and reliability. NeuStar Ultra Services currently locates its
NORTHERN VIRGINIA ONE (NoVa) DATA CENTER OVERVIEW
VAZATA 9651 Hornbaker Road Manassas, VA 20109 VAZATA.COM VAZATA's NoVa One data center located at 9651 Hornbaker Road in Manassas, Virginia is engineered from the ground up to deliver highly reliable and
X-tier Data Facility. Prepared by X-tier SAE Corporation
X-tier Data Facility Company Profile X-tier Corporation X-tier is based in Leawood, Kansas. X-tier provides business agnostic, security hardened, custom and turnkey Cloudbased software systems, services,
LEVEL 3 DATA CENTER SERVICES IN OMAHA, NEBRASKA HIGH AVAILABILITY ENTERPRISE COMPUTING BUSINESS DEMANDS IT. LEVEL 3 DELIVERS IT.
LEVEL 3 DATA CENTER SERVICES IN OMAHA, NEBRASKA HIGH AVAILABILITY ENTERPRISE COMPUTING BUSINESS DEMANDS IT. LEVEL 3 DELIVERS IT. THE SCALE TO SUPPORT GLOBAL ENTERPRISE IT Designed and equipped to meet
san francisco//usa data center specifications tel: +61 2 9948 8888 fax: +61 2 9948 1111 internet + intellectual property + intelligence
internet + intellectual property + intelligence We thank you for the opportunity to work with you regarding your colocation needs in San Francisco, USA. We can colocate standard rack-mountable servers
Experience Matters...
Experience Matters... Travelport Data Center offers confidence and space to meet your demanding IT needs Transwestern presents the Travelport Data Center in Denver, Colorado totaling 267,000 SF with 121,600
N O W A V A I L A B L E
N O W A V A I L A B L E 5 0, 0 0 0 S F P O W E R E D S H E L L D A T A C E N T E R I I Data Center Park Catawba County, North Carolina S P E C I F I C A T I O N S Contact Doug Hollidge for more information
COMMODITIZING THE DATA CENTER MARKET
COMMODITIZING THE DATA CENTER MARKET Site Summary The building at 1360 Kifer Road has approximately 94,500 SF of server and support space and is currently divided into two independent data center areas.
Chicago 1 (CHI-1) Data Center
215 W. Ohio St. 5th Floor Chicago, IL 60564 Call Us Toll-Free 1 (866) 817-2811 Follow Us @SingleHop Like Us facebook.com/singlehop Chicago 1 (CHI-1) Data Center Enterprise-Class, Downtown Chicago Facility
OPERATOR - FACILITY ADDRESS - DATE
. Facility Criteria (RFP).0 Location Characteristics Criteria Requirements 1 Ownership and Management: Please identify the owner(s) and managers of the property and indicate if there is on-site management.
19 Site Location, Design and Attributes. Site Location, Design and Attributes
1 Site Location, Design and Attributes The Primary Data Center shall be physically located on Oahu, Hawaii. 2 Site Location, Design and Attributes The Primary Data Center shall be located at least 1 mile
Data Centre Barrie, Ontario
COGECO DATA SERVICES DATA CENTRE Data Centre Barrie, Ontario Cogeco Data Services offers flexible, secure, connected and fully managed ICT solutions at its Flagship Data Centre in Barrie, Ontario Data
vcloud SERVICE Virtual Tech in partnership with Equinix - vcloud Service
vcloud SERVICES vcloud SERVICE Virtual Tech offers competitive pricing on vcloud hosted services at our world class Tier 4 data centre facility fully equipped with redundant power, cooling, internet connectivity
Strategic Data Centre Site Profiles. Data Centre Co-Location London East
Strategic Data Centre Site Profiles Data Centre Co-Location London East Document details Version: 1 Last Updated: 12/07/2013 Version 1.0 Page 1 of 5 Contents 1. LONDON EAST...3 1.1 LOCATION...3 1.2 TECHNICAL
DATA CENTERS. VAZATA Headquarters: 6900 Dallas Parkway, Suite 800 Plano, TX 75024 VAZATA.COM
DATA CENTERS VAZATA Headquarters: 6900 Dallas Parkway, Suite 800 Plano, TX 75024 VAZATA.COM OVERVIEW VAZATA's NoVa One data center located at 9651 Hornbaker Road in Manassas, Virginia is engineered from
Location. Central Business District. Ataturk Airport IFC. Sabiha Gökçen Airport
Welcome Zenium Istanbul One provides 12,000 square metres of high specification technical space across three purpose-built data centers. It is Turkey s first wholesale data center offering; the data halls
CyberFortress Data Center at Innovation Park Infrastructure and Topology Guide. Innovation Park Charlotte. NC 28262. DRAFT V0.
Innovation Park Charlotte. NC 28262 DRAFT V0.1 Page 2 CyberFortress Data Center at Innovation Park BECO South purchased Innovation Park in March 2010 and immediately launched a dramatic top-to-bottom $30M
Data Center Presentation
Data Center Presentation The NetSource Datacenter. Agenda General Layout of Data Center Policies and Procedures Designed to Latest Standards High Performance High Reliability High Security Design Details
Our Hosting Infrastructure. An introduction to our Platform, Data Centres and Data Security. www.in-tuition.net
Our Hosting Infrastructure An introduction to our Platform, Data Centres and Data Security www.in-tuition.net UK Infrastructure Infrastructure Overview Intuition Networks has provided managed Internet
Contents Error! Bookmark not defined. Error! Bookmark not defined. Error! Bookmark not defined.
We Do It Better. Contents Introduction...3 Service and Support...3 Data Center Details...4 Security...4 Location...4 Power...4 Humidification...5 AC...5 Cooling...6 Datacenter Features...6 SAS 70...6 PCI
LEVEL 3 DATA CENTER SERVICES IN SAN FRANCISCO HOUSE POWER-INTENSIVE APPLICATIONS AND SUPPORT BUSINESS CONTINUITY
LEVEL 3 DATA CENTER SERVICES IN SAN FRANCISCO HOUSE POWER-INTENSIVE APPLICATIONS AND SUPPORT BUSINESS CONTINUITY THE SCALE TO SUPPORT GLOBAL ENTERPRISE IT THE SCALE TO SUPPORT FLEXIBLE ENTERPRISE IT It
DATACENTER COLOCATION. Flexible, Secure and Connected
DATACENTER COLOCATION Flexible, Secure and Connected Flexible Solutions for Your Requirements Contents Your Goals 2 Compound and Buildings 4 Security 6 Infrastructure 8 Free Choice 10 Good Reasons 12 Our
Safeguard your critical IT assets in a highly secure, fully redundant, environmentally-conditioned and constantly monitored hosting space to receive
Co-Location Services Safeguard your critical IT assets in a highly secure, fully redundant, environmentally-conditioned and constantly monitored hosting space to receive optimum performance 24x7. SERVICE
Powering the Cloud Desktop: OS33 Data Centers
OS33 Data Centers [email protected] (866) 796-0310 www.os33.com It is hard to overstate the importance of security and uptime, which is why we obsess over making sure that your corporate information assets
CHICAGO S PREMIERE DATA CENTER
CHICAGO S PREMIERE DATA CENTER White City collocation was founded in June, 2010 by a highly experienced industry executive in conjunction with several investment companies. The strategy of White City is
IBM Twin Data Center Complex Ehningen Peter John IBM BS [email protected]. 2011 IBM Corporation
IBM Twin Data Center Complex Ehningen Peter John IBM BS [email protected] Overview Profile IBM owned facility 6447 m² IT-Space Infrastructure concurrent maintainable (Tier Level 3) Feed-ins of Power
Data Center Overview Document
Overview NetSource is a Chicago area (Naperville) hosting company that owns and operates its own world class datacenter. The initial datacenter buildout was put into operation in 2007 and expanded in 2013.
Data Center CH1. Elk Grove Village, IL
Data Center CH1 Elk Grove Village, IL powerful/ efficient /reliable solutions > Data Center CH1 ABOUT DUPONT FABROS TECHOLOGY (DFT) DFT is a leading owner, developer, operator and manager of wholesale
colocation. perfected.
colocation. perfected. colocation perfected The expert team of COLO@ have the talent, tools, and facilities to power your operation all day, every day. Since 2008, COLO@ has been providing the critical
How To Write An Infrastructural Standard For Data Center Infrastructure
Infrastructure Standard for Data Centers ANSI/CSA/EIA/TIA-942 (PN-3-0092) Introduction When approved, the standard will be: ANSI/CSA/EIA/TIA-942 Telecommunications Infrastructure Standard for Data Centers
White paper. SAS Solutions OnDemand Hosting Overview
White paper SAS Solutions OnDemand Hosting Overview Contents Overview...1 Cary 1 Facility Specifications...2 Cary 2 Facility Specifications (SAS New Cloud Computing Center)...3 Charlotte 1 Facility Specifications...4
Data Center Commissioning: What you need to know
Data Center Commissioning: What you need to know Course # CXENERGY1511 AIA Provider # 50111116 AABC Commissioning Group CxEnergy Conference Henderson, NV April 30, 2015 Presented by: Judson H. Adams, P.E.,
Strategic Data Centre Site Profiles Data Centre Co-Location London North
Strategic Data Centre Site Profiles Data Centre Co-Location London North Document details Version: 1 Last Updated: 12/07/2013 Version 1.0 Page 1 of 6 Contents 1. LONDON NORTH...3 1.1 LOCATION...3 1.2 TECHNICAL
Datacenter Assessment
The Netmagic team has compiled this Checklist to help you evaluate, compare and select datacenter facilities to meet your hosting, business continuity and disaster recovery needs. Based on industry best
CyrusOne Global Data Center Solutions
CyrusOne Global Data Center Solutions 1649 W Frankford Road, Carrollton, TX 75007 + Leader in Global Data Center Colocation Built for tomorrow. Ready today. CyrusOne has quickly emerged as a global leader
About Injazat. Enterprise Cloud Services. Premier Data Center. IT Outsourcing. Learning and Development Services. Enterprise Application Services
About Injazat Injazat Data Systems is an industry-recognized market leader in the region for Information Technology Outsourcing, Cloud and Data Center Managed Services delivered from the region s 1st Tier
HealthcareBookings.com Security Set Up
HealthcareBookings.com Security Set Up Introduction... 2 Overview of the process for using HealthcareBookings.com... 2 Professionals... 2 Patients... 3 Passwords... 4 Hosting Security... 4 Overview of
South Asia s First Uptime Institute Certified TIER-IV IDC in Mumbai delivering 99.999% guaranteed uptime
South Asia s First Uptime Institute Certified TIER-IV IDC in Mumbai delivering 99.999% guaranteed uptime GPX India Pvt Ltd The Leader In Carrier Neutral TIER IV IDC s In Emerging Markets Incorporated in
House your data in a building constructed for only one express purpose protect the information inside. Twin Cities East Data
Protection is Central. Twin Cities East Data Center House your data in a building constructed for only one express purpose protect the information inside. Twin Cities East Data Center is nothing less than
ASX Australian Liquidity Centre. ASXCoLo
ASX Australian Liquidity Centre ASXCoLo Australian Liquidity Centre Location The ASX Australian Liquidity Centre is located at: Gore Hill Business Park 219-247 Pacific Highway Artarmon. NSW, 2064 The location
Datacenter Hosting and Cloud Computing Services
Datacenter Hosting and Cloud Computing Services Overview Background Founded in 1995, Lore Systems operates an international datacenter network which today includes full service 3+ datacenter facilities
Santa Clara, CA 95054
Leading-Edge Datacenter Facility Silicon Valley GENERAL In excess of 41,000 sq. ft. of raised floor 9 MVA of utility power into facility Purpose built Green Datacenter Sutton Roley Lic. 00793235 (408)
South Asia s First Uptime Institute Certified TIER- IV IDC in Mumbai delivering 99.999% uptime
South Asia s First Uptime Institute Certified TIER- IV IDC in Mumbai delivering 99.999% uptime GPX India Pvt Ltd The Leader In Carrier Neutral TIER IV IDC s In Emerging Markets Incorporated in August 2002,
DATA CENTERS. VAZATA Headquarters: 6900 Dallas Parkway, Suite 800 Plano, TX 75024 VAZATA.COM
DATA CENTERS VAZATA Headquarters: 6900 Dallas Parkway, Suite 800 Plano, TX 75024 VAZATA.COM DAL II MARSH LANE CARROLLTON TX OVERVIEW VAZATA s Dallas Data Center II (Dal II) is located at 2440 Marsh Lane
Building a Tier 4 Data Center on a Tier 1 Budget
Building a Tier 4 Data Center on a Tier 1 Budget A Walk Through of TIA-942 Peter P. Charland III, RCDD/NTS/WD, CET RTKL Associates Inc. March 27, 2008 BICSI South Central Region Meeting Denver, CO TIA-942
VOLICO. Colocation Hosting. Enterprise Hosting Solutions. 888 865 4261 [email protected] www.volico.com
888 865 4261 [email protected] www.volico.com Performance, reliability, and the peace of mind your business deserves Colocation Overview A Reliable and Secure Home Your Data Can Trust! Discover how Volico
Site Preparation Management Co., Ltd. March 1st 2013 By Nara Nonnapha, ATD UPTIME
Site Preparation Management Co., Ltd. March 1st 2013 By Nara Nonnapha, ATD UPTIME 2 AGENDA SESSION -1 What is Data Center? SESSION -2 Equipment and Components SESSION -3 Standard in designing Data Center
Our data centres have been awarded with ISO 27001:2005 standard for security management and ISO 9001:2008 standard for business quality management.
AIMS is Malaysia and South East Asia s leading carrier neutral data centre operator and managed services provider. We provide international class data storage and ancillary services, augmented by an unrivaled
Data Center Infrastructure & Managed Services Outline
Data Center Infrastructure & Managed Services Outline The 360 Technology Center Solutions Data Center is located in Lombard, IL, USA. We are 20 minutes outside of downtown Chicago. The 360TCS staff consists
Assessment of Existing Data Centers for Critical Facilities Round Table Group
Assessment of Existing Data Centers for Critical Facilities Round Table Group Chuck Shalley, P.E. Consulting Electrical Engineers BACKGROUND INFORMATION ASSIGNMENT Data Center Criteria Type Raised Floor
NY-1 DATACENTER AT A GLANCE. NY-1 is a Tier III-rated, SAS SSAE16 and HIPAA-certified data center
NY-1 1.866.WEBAIR.1 WWW.NY1.WEBAIR.COM NY-1 LONG ISLAND S MOST SECURE, FULLY-REDUNDANT DATA CENTER ENTERPRISE COLOCATION, PRIVATE AND HYBRID CLOUD SOLUTIONS, AND MANAGED SERVICES. DATACENTER Enjoy the
LEVEL 3 DATA CENTER ASSESSMENT
Nationwide Services Corporate Headquarters 410 Forest Street Marlborough, MA 01752 USA Tel: 800-342-5332 Fax: 508-303-0579 www.eecnet.com LEVEL 3 DATA CENTER ASSESSMENT Submitted by: Electronic Environments
Data Center Due Diligence List
Data Center Due Diligence List Name and address of site facility Date constructed Building owner/date purchased by current owner Name of previous owner Adjacent Property Descriptions North South East West
Fire Pump Plan Review March 2010
Fire Pump Plan Review March 2010 Date of Review: / / Permit Number: Business/Building Name: Address of Project: Designer Name: Designer s Phone: Contractor: Contractor s Phone: Occupancy Classification:
Tier IV Enterprise - Class Data Center
Tier IV Enterprise - Class Data Center Colocation Cloud Hosting Broward Data Center Datasheet Managed Hosting Dedicated Servers www.volico.com Site Specification Security Site Specification Floor Space
VOLICO. Colocation Checklist. Key Data Center Evaluation Criteria
VOLICO Enterprise Hosting Solutions Colocation Checklist Key Data Center Evaluation Criteria Not all data centers are created equal. You need to know what to look for. Are they equipped with up-to-date
Network Router Monitoring & Management Services
Network Router Monitoring & Management Services Get different parameters of routers monitored and managed, and protect your business from planned and unplanned downtime. SERVICE DEFINITION: NETWORK ROUTER
LDeX Group. Colocation Solutions for High Expectations
LDeX Group Colocation Solutions for High Expectations LDeX1 Units 8 10 The Oxgate Centre, Oxgate Lane, London, NW2 7JA +44 (0)845 370 3510 [email protected] www.ldexgroup.co.uk 5 M VA LDeX1 delivers
Our data centres have been awarded with ISO 27001:2005 standard for security management and ISO 9001:2008 standard for business quality management.
AIMS is Malaysia and South East Asia s leading carrier neutral data centre operator and managed services provider. We provide international class data storage and ancillary services, augmented by an unrivaled
colocation. perfected. Overview
colocation. perfected. Overview Welcome to COLO@ colocation perfected our network The expert team of COLO@ have the talent, tools, and facilities to power your operation all day, every day. Since 2008,
SYSTRUST CERTIFICATION REPORT FOR COLLOCATION AND DATA CENTER HOSTING SERVICES FOR THE PERIOD FROM JANUARY 1, 2013 TO DECEMBER 31, 2013
SYSTRUST CERTIFICATION REPORT FOR COLLOCATION AND DATA CENTER HOSTING SERVICES FOR THE PERIOD FROM JANUARY 1, 2013 TO DECEMBER 31, 2013 TABLE OF CONTENTS SECTION I: INDEPENDENT PRACTITIONERS TRUST SERVICES
Earthquakes and Data Centers
7x24 Exchange Fall Symposium September 11, 2013 Hilton Bellevue Andrew W. Taylor, Ph.D., S.E., FACI Earthquake Hazards 2 September 11, 2013 1 Cascadia Earthquake Sources Figure Credit: Craig Weaver, Pacific
Frankfurt Data Centre Overview
Technical Services Briefing Document Frankfurt Data Centre Overview Version 2.1 Contents Introduction... 3 TelecityGroup Data Centre in Frankfurt... 4 Data Centre Characteristics... 4 Technologies in Use
Appendix B. 2010 Florida Building Code Building Section 423.25 Public Shelter Design Criteria
Appendix B 2010 Florida Building Code Building Section 423.25 Public Shelter Design Criteria 423.25 Public shelter design criteria. 423.25.1 New facilities. New educational facilities for school boards
Current as of 11/10/08 1 of 1
BEST PRACTICES STANDARDS FOR SCHOOLS UNDER CONSTRUCTION OR BEING PLANNED FOR CONSTRUCTION I. Site Layout A. School buildings shall be provided with a securable perimeter. A securable perimeter means that
Web Hosting Features
Web Hosting Features Included with all website production packages Our web-hosting facilities are geared towards serving those clients whos websites we have created. To ensure maximum performance and flexibility
colocation. perfected.
colocation. perfected. colocation perfected The expert team of COLO@ have the talent, tools, and facilities to power your operation all day, every day. Since 2008, COLO@ has been providing the critical
Subject: County of Los Angeles Data Center Space Requirement
Subject: County of Los Angeles Data Center Space Requirement The County of Los Angeles, Chief Executive Office, Real Estate Division (CEO-RED) is issuing this Property Search for the purchase of a vacant,
UC Berkeley Data Center Overview
UC Berkeley Data Center Overview Shelton Waggener Associate Vice Chancellor & Chief Information Office [email protected] August 2006 Berkeley s Data Center Opened July 2004 Our Previous Facility (don
MOBILE FIRE - RESCUE DEPARTMENT FIRE CODE ADMINISTRATION
MOBILE FIRE - RESCUE DEPARTMENT FIRE CODE ADMINISTRATION Fire Pump Plan Review 2009 International Fire Code and NFPA 20 Date of Review / / BLD201 - Project Address: Project Name: Contractor s Business
SECTION 8 Industrial Facilities Field Investigation
SECTION 8 Industrial Facilities Field Investigation Types of Data to Be Collected and Recorded Warehouses, manufacturing facilities, energy-producing facilities, and factories should be inspected for performance
Data Center Management
Data Center Management How Cisco IT Operates, Manages, and Protects Its Data Center A Cisco on Cisco Case Study: Inside Cisco IT 1 Overview The Cisco IT Operations Data Center on the San Jose, California
NEW JERSEY CENTER OF EXCELLENCE
Overview NEW JERSEY Page 1 The Plant (CUP) provides electricity via a cogeneration system, chilled water for environmental cooling, steam for heating, and compressed air primarily for HVAC control Serves
DATA CENTRE DATA CENTRE MAY 2015
DATA CENTRE DATA CENTRE MAY 2015 CONCERTHOUSE MUSIC Concerthouse Music Data Centre services are located in the Equinix Internet Business Exchange (IBX ) Centre at Mascot. This IBX offers the highest level
Development Services City of Lawrence, KS
Development Services City of Lawrence, KS Building Planning Table R301.2 (1) Climatic & Geographic Design Criteria Building Planning The design criteria for wind speed increased from 90 MPH to 115 MPH.
Establishment of State s Second Data Center. Business Continuity and Disaster Recovery. North Carolina. Office of Information Technology Services
Establishment of State s Second Data Center North Carolina Office of Information Technology Services National Association of State Chief Information Officers 2008 Recognition Awards Nomination June 2,
NY2 21 CRITICAL MEGAWATTS 280,000 SQUARE FEET WWW.CORESITE.COM
CLOUD-ENABLED DATA CENTER 21 CRITICAL MEGAWATTS 280,000 SQUARE FEET WWW.CORESITE.COM NEW YORK CAMPUS The optimal location to propel your business SYMS WAY EMERSON LN EQ SECAUCUS HARTZ WAY SECAUCUS RD AMERICAN
Scalable. Affordable. Flexible. Fast.
Modular Data Center Solutions Scalable. Affordable. Flexible. Fast. Build the data center you need today with the flexibility to meet tomorrow s challenges The only constant in business is change. Fluctuations
ISOMEDIA COLOCATION WWW.ISOMEDIA.COM/COLOCATION
ISOMEDIA COLOCATION WWW.ISOMEDIA.COM/COLOCATION Your business needs a robust infrastructure that is secure, cost effective and reliable in order to remain competitive in today s market. ISOMEDIA s colocation
AFS Center. Data Center Info. Arizona Facility Services 2331 West Alameda Dr Tempe, AZ 85282 (602) 385-8100 Main (602) 385-8101 Fax
AFS Center Data Center Info 2331 West Alameda Dr Tempe, AZ 85282 (602) 385-8100 Main (602) 385-8101 Fax A. General Facility Information The AFS Center is located on the south side of Alameda Drive, just
COLOCATION PROVIDERS:
COLOCATION PROVIDERS: INTRO The benefits of colocation are well documented, and making the business case for going that route is often quite easy for many organizations. Once the decision has been made
Our data centres have been awarded with ISO 27001:2005 standard for security management and ISO 9001:2008 standard for business quality management.
AIMS is Malaysia and South East Asia s leading carrier neutral data centre operator and managed services provider. We provide international class data storage and ancillary services, augmented by an unrivaled
1301 Fannin. Houston Data Center & Office Facility
1301 Fannin & Office Facility 1301 FANNIN Building Features Building Location Building Typical Floor plans Systems Infrastructure Amenities BUILDING FEATURES YEAR BUILT/RENOVATED: 1984/2009 TOTAL LEASE
THE MULTI-TENANT DATA CENTER
THE MULTI-TENANT DATA CENTER IS IT RIGHT FOR YOUR ORGANIZATION? Josh Rabina Sentinel Data Center 1 AGENDA Introductions The Multi Tenant Data Center What is It? What is Driving Adoption (i.e. Value Proposition)?