ALLOCATE RESOURCES STEP 6 By: Charlie Jackson (Hill International) & Hannah E. Schumacher (Kitchell Contractors)
|
|
|
- Marian Barbra Chase
- 10 years ago
- Views:
Transcription
1 ALLOCATE RESOURCES STEP 6 By: Charlie Jackson (Hill International) & Hannah E. Schumacher (Kitchell Contractors) Abstract: Many Contract Documents are now requiring the use of the latest version of Primavera software (P6 ) due to its enterprise capabilities and its use of latest technologies including the capabilities to interact other software applications; therefore it is important for the Scheduler to understand how to use this software most efficiently in their battle to complete their projects in a timely manner. Primavera s latest release of P6 contains many features that can assist in developing schedules quickly and efficiently. However, a new or in-experienced user would be overwhelmed in the struggle to prepare the schedule using P6 and these advanced features without proper training or Basic Training. This paper will focus on the authors experiences and their lessons learned regarding the effective use of P6 in the schedule development process as they apply to the TCM Planning and Scheduling development processes (TCM 7.2). AACE International s Total Cost Framework (TCM 7.2) outlines the twelve (12) steps for Schedule Planning and Development as follows: 1. Plan for Schedule Planning and Development 2. Identify Activities 3. Develop Activity Logic 4. Estimate Durations 5. Establish Schedule Requirements 6. Allocate Resources 7. Optimize Schedule 8. Establish Schedule Control Basis 9. Review and Validate Schedule 10. Document and Communicate Schedule 11. Submit Schedule Deliverables, and 12. Develop and Maintain Methods and Tools. [1] Allocate Resources Estimating Activity Resources is the process of estimating the type and quantities of material, people, equipment, or supplies to perform each activity. [2]. If the contract documents require resource and/or cost loading, the Scheduler must assign resources to the activities. Even if the contract does not require resource / cost loading, it is good practice; by assigning (i.e. loading) resources for each activity, available resources can be scheduled in accordance with resource consumption limitations (i.e., money, labor hours, etc) by resource leveling or balancing [1]. 1
2 When considering activity resource development and assignment the determination must be made either contractually or internally what types of resources will be tracked and will costs be associated to each resource or tracked independently. Secondly will resources be updated based on activity work performance and will payment be based on percentage complete. If this is the case, the user and/or project team must consider the amount of time that is required to not only input resource/cost data but the time involved to manage and report resource updates. Resources in Primavera P6 are global in that a single Resource dictionary houses all projects resources. This dictionary is hierarchical in its structure which allows for controls to be in place for overall resource management. Resources are global in that a single resource (dependent upon user access) can be assigned to multiple activities within across multiple projects within the EPS. In P6 cost loading is typically defined at the resource level. Dependent upon the requirements of both the organization and the project contract, cost loading is achieved as either a lump sum nonlabor resource or a price per unit labor/material resource. Three areas or levels within P6 contain the settings which govern resource allocation, costing, and updating options. It is important that the user be aware of these settings prior to defining the resource and allocating resource units/costs. Once a resource is assigned to an activity, any changes to the resource settings will apply to new assignments only. The first of the three areas which contain settings governing resource allocation is the resource itself. These default global settings, specific to each resource, affect the resource regardless of the project and the activity to which it is assigned. Secondly, the project also contains default settings which affect all resources within the specific project. And finally the activity specific settings affect the individual resources assigned to that activity. To control these settings within each of the three levels, a basic understanding of P6 and each option with its function is required. The first setting is Calculate Units from Costs. By definition, costs are recalculated whenever resource unit quantities are modified. By default, this setting, found at the resource level (Resource Details, Details tab) and at the Activity location (Activity Details, Resources tab, columns), applies to any new resource assignment. This option is not used for resources requiring lump sum loading where units/time are not considered. A second setting that should be understood is Auto Compute Actuals. By definition, resource actual and remaining units as well as start and finish dates are updated automatically based on the activity s planned dates, budgeted units, and percent complete. This option can only be modified at the resource level (Resource Details, Details tab) and therefore applies to the resource globally across its activity assignments. The nomenclature for this setting should not be confused with what appears to be the same option at the Activity level. Although the naming convention is identical, another setting for updating activity information (found in the columns in the Activity window) is used in conjunction with the Apply Actuals option within Primavera P6. 2
3 A third setting that should be understood is Link Actual and Actual this Period Units and Cost. By definition, resource costs/units are updated when either Actual or Actual this Period are updated. This option must be selected when using Financial Periods and Store Period Performance. Found at only the project level (Project Details, Calculations tab) this option applies to all resource assignments within the project. Other considerations relating to resource assignments include activity types. As discussed previously, milestones cannot have assigned resources and therefore cannot be cost loaded. Duration Types Each activity s Duration Type defines how resource modifications adjust the activity s duration, its budgeted resource quantities, and/or its resource production by period. When an activity s duration type is Fixed Duration and Units, P6 will recalculate the units per time for each of the activity s resource assignments when either the activity s duration or its budgeted units are updated. When an activity s duration type is Fixed Duration and Units/Time, P6 will recalculate the budgeted units when either the activity s duration or production rate (units/time) is updated. When an activity s duration type is Units, P6 will recalculate either the activity s duration or production rate (units/time) when the budgeted units are updated. Figure 10: Three factors determining Duration Type As mentioned previously, costs are allocated to each activity as either a lump sum resource cost or based on price/unit resources. When cost loading the P6 schedule, Financial Periods are then used to store actual period performance as opposed to spreading actual work performance across the timeline. These financial periods are set at the globally across the enterprise by the System Administrator (under the Admin menu, Financial Periods option). They are set at periodic intervals for cost/production tracking. Cost Accounts Cost Accounts can be established within P6 (Enterprise menu, Cost Accounts) to identify organizational accounting codes to specific resource/cost times within the schedule and across the enterprise. They are typically created by the Cost Engineer or Controls Engineer. This hierarchical structure is associated to each activity at the resource level (Activity Detail, Resources tab, Cost Accounts column). 3
4 Resource Curves and Future Bucket Planning Resource Curves (under the Enterprise menu, Resource Curves option) define how resource units/costs are distributed across an activity s duration. They are associated to each activity s resource (Activity Details, Resources tab, Curves column). Primavera P6 also offers future bucket planning for resource units/cost forecasting, where distributions are manually entered in the Resource Usage Spreadsheet for future resource projections. These manually spread distributions are displayed in the Activity details, resource curves column as manual. Percent Complete Types When determining the process of updating resources and the contractual and/or internal requirements for resource/payment obligations, the user must consider the means of updating each resource at the activity level. When payment is based on work performance, the user must consider how each activity s update will affect the resource cost/quantities for that activity. Work performance in P6 is updated automatically (unless specified) in Primavera using percent complete. There are three percent complete types at the activity level: duration percent complete, physical percent complete, and units percent complete. Duration percent complete is directly associated to the activity s Original Duration and Remaining Duration. This default setting within P6 is used to update resource costs/units. However, when payment is based on work performance and stored materials, duration percent complete might not reflect actual costs to date. Percent Complete = (Original Duration Remaining Duration) / Original Duration * 100. Eq 1 Physical percent complete is a manually entered (or resource entered) percentage of work. This percentage type has no correlation with the activity s duration or units complete. At this time this option cannot be used to update resource costs/units. Units percent complete is directly associated with the activity s labor and nonlabor resources. This option can be used to update resource costs/units. Percent Complete = Actual Units / At Completion Units * 100. Eq 2 In most instances where work performance in the schedule is directly tied to payment, the use of either Duration percent or Units percent (when associated with a Lump Sum activity) cannot be used. The user should be aware that actuals will need to be manually entered at the resource level within each activity. NOTE: Part 7 Optimize Schedule to be posted next week. Subscribe to our blog if you don t want to miss it or follow us on If you have questions regarding this series or the products and the services we offer, please feel free to us at [email protected] or call us at (800) REFERENCES: 1. AACE International Chapter 7.2. Schedule Planning and Development. Total Cost Management Framework A Process for Applying the Skills and Knowledge of Cost Engineering, First Edition. Pages(s) AACE International, Morgantown, WV
5 2. Project Management Institute. Chapter 6: Project Time Management. A Guide to the Project Management Body of Knowledge (PMBOK ), Fourth Edition. Page(s) Project Management Institute, Newton Square, PA AACE International, Recommended Practice No 23R-02 Identification of Activities. AACE International, Morgantown, WV AACE International, Recommended Practice No 24R-03 Developing Activity Logic. AACE International, Morgantown, WV Winter, Ronald M., PSP and F. Burak Evrenosoglu, CCE PSP. PS.15, Much Ado About Dates Understanding P6 Date Information AACE International Transactions. AACE International, Morgantown, WV REPRINTED WITH THE PERMISSION OF THE AUTHORS AND AACE INTERNATIONAL, ENTITY OF FIRST PUBLICATION, 1265 SUNCREST TOWNE CENTRE DR., MORGANTOWN, WV USA. PHONE COST/ FAX: INTERNET: [email protected] COPYRIGHT 2010; ALL RIGHTS RESERVED. 5
IDENTIFY ACTIVITIES STEP 2 By: Charlie Jackson (Hill International) & Hannah E. Schumacher (Kitchell Contractors)
IDENTIFY ACTIVITIES STEP 2 By: Charlie Jackson (Hill International) & Hannah E. Schumacher (Kitchell Contractors) Abstract: Many Contract Documents are now requiring the use of the latest version of Primavera
Guidelines for Accessing and Using the VDOT Scheduling Application (Primavera P6)
Guidelines for Accessing and Using the VDOT Scheduling Application (Primavera P6) CONSTRUCTION DIVISION (SCHEDULING & CONTRACTS) 1. INTRODUCTION To establish standards and consistent scheduling practices
MS PROJECT FOR CONSTRUCTION SCHEDULERS
MS PROJECT FOR CONSTRUCTION SCHEDULERS Copyright January 25, 2011 by Ron Winter, PSP F. Burak Evrenosoglu, PE CCE PSP Presented at The AACE International 55 th Annual Meeting June 22, 2011 Disneyland Hotel,
LECTURE -08 INTRODUCTION TO PRIMAVERA PROJECT PLANNER (P6)
LECTURE -08 INTRODUCTION TO PRIMAVERA PROJECT PLANNER (P6) GOAL In this lecture, we ll learn: Background of Primavera Project Planner (P6) Getting Started P6 Interface Basic Navigation and Operation Setting
PROJECT PLANNING & SCHEDULING USING PRIMAVERA ENTERPRISE. In An. Established Project Environment PAUL EASTWOOD HARRIS
PROJECT PLANNING & SCHEDULING USING PRIMAVERA ENTERPRISE Planning and Progressing a Single Project Schedule With and Without Resources In An Established Project Environment BY PAUL EASTWOOD HARRIS Eastwood
Making CPM More Transparent By Ron Winter Ron Winter Consulting January 11, 2006
Making CPM More Transparent By Ron Winter Ron Winter Consulting January 11, 2006 ABSTRACT This paper presents several new ideas that users of CPM software should demand of their software suppliers to increase
Oracle Primavera P6 Enterprise Project Portfolio management Overview Programme Reference # 201A
Oracle Primavera P6 Enterprise Project Portfolio management Overview Programme Reference # 201A Programme Description: Dedicated one full day training module in a structured and professional manner to
PMO Metrics Recommendations
Introduction The purpose of this document is to recommend metrics to be used by the Project Management Office (PMO) to measure and analyze their project and PMO success. The metrics are divided into Project
Primavera Project Manager for the Enterprise Version 6.1 Custom Training Manual
Primavera Project Manager for the Enterprise Version 6.1 Custom Training Manual Course Contents June 27, 2003 This publication is produced as a custom training document for The University of North Carolina.
SCHEDULE PREPARATION
A STEP-BY-STEP GUIDE USING SOFTWARE DEVELOPMENT KIT (SDK) FOR PRIMAVERA VERSION 6.x SCHEDULE PREPARATION BY: JEOFFREY B. REYES Sr.Planning Engineer BUILDING WORKS / ROAD & INFRASTRUCTURE Jubail Industrial
LONG INTERNATIONAL. Andrew Avalon, P.E., PSP and Curtis W. Foster
Andrew Avalon, P.E., PSP and Curtis W. Foster LONG INTERNATIONAL Long International, Inc. 5265 Skytrail Drive Littleton, Colorado 80123-1566 USA Telephone: (303) 972-2443 Fax: (303) 200-7180 www.long-intl.com
Primavera P6 102 Training Manual. Prepared by. Bill Pepoon, Managing Partner Construction Science, LLC
Primavera P6 102 Training Manual Prepared by Bill Pepoon, Managing Partner Construction Science, LLC 1 Day I Introduction Setting up a new Project Activities Activity Types Activity Durations Work Breakdown
Activity Schedules in the NEC3 Engineering and Construction Contract
Activity Schedules in the NEC3 Engineering and Construction Contract Prepared by Dr Ron Watermeyer Briefing Note NEC3#2 March 2013 Overview This briefing note outlines the NEC3 provisions for a Activity
Oracle Primavera. P6 Resource Leveling Demo Script
Oracle Primavera P6 Resource Leveling Demo Script Script Team Information Role Name Email Primary Author L. Camille Frost [email protected] Contributor Reviewer Geoff Roberts [email protected]
Primavera P6 Enterprise Project Portfolio Management Certified Implementation Specialist
Oracle 1z0-535 Primavera P6 Enterprise Project Portfolio Management Certified Implementation Specialist Version: 6.0 QUESTION NO: 1 Select the true statement regarding Global Preferences in Primavera P6
PROJECT PLANNING & SCHEDULING USING PRIMAVERA P6 TM. in an PAUL EASTWOOD HARRIS
PROJECT PLANNING & SCHEDULING USING PRIMAVERA P6 TM For all industries including Versions 4 to 6 Planning and Progressing Project Schedules With and Without Roles and Resources in an Established Enterprise
Sample book with only two chapters
PLANNING AND CONTROL USING ORACLE PRIMAVERA P6 Versions 8.2 to 15.1 EPPM WEB Enterprise Portfolio Project Management Planning and Progressing Project Schedules With and Without Roles and Resources in an
Session: Tue 1110 to 1225. How to Cost Load a schedule. OR Understanding the SDEF
Session: Tue 1110 to 1225 How to Cost Load a schedule for USACE s QCS/RMS OR Understanding the SDEF (understanding the SDEF) Introduction David Long Sr. Project Controls Specialist With 20+ years of Scheduling
Project Cost Management
Project Cost Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points To Note Please
Project Procurement Management
Project Procurement Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note
CRITICAL PATH METHOD (CPM) SCHEDULES
96 CRITICAL PATH METHOD (CPM) SCHEDULES How-to for Reading, Understanding, and Using CPM Schedules (without Direct Primavera Access.) 1 Objectives Learn to read, understand, and use CPM schedules (without
Simple Earned Value (Using MS Project 2010)
Simple Earned Value (Using MS Project 2010) This document outlines a Simple Earned Value technique, a technique which sticks to a simple 0/100% Milestone approach with some Level of effort tasks maintained
AACE International Recommended Practices
AACE International Recommended Practice No. 52R-06 TIME IMPACT ANALYSIS AS APPLIED IN CONSTRUCTION TCM Framework: 6.4 Forensic Performance Assessment, 7.2 Schedule Planning and Development, 10.2 Forecasting,
MODEL SCHEDULING SPECIFICATION
MODEL SCHEDULING SPECIFICATION Introduction (Not part of the specification) Before implementation, we recommend that your contract and this provision be reviewed and modified to ensure compatibility with
Administration. Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT 2010 AND PMBOK GUIDE FOURTH EDITION training course presented by
Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT 2010 AND PMBOK GUIDE FOURTH EDITION training course presented by Paul E Harris Administration Evacuation Timings, meals and facilities Mobile phones
EXHIBIT 2-2-C PROGRESS SCHEDULES
EXHIBIT 2-2-C PROGRESS SCHEDULES PART 1 GENERAL 1.01 SUMMARY A. The work specified in this section consists of furnishing transportation, labor, materials, equipment and incidentals necessary for preparation,
Project Management Guidelines
Project Management Guidelines Overview Section 86-1506 (5) directs the NITC to adopt guidelines regarding project planning and management. The goal of project management is to achieve the objectives of
UNIFIED FACILITIES GUIDE SPECIFICATIONS ************************************************************************** SECTION TABLE OF CONTENTS
USACE / NAVFAC / AFCEC / NASA UFGS-01 32 16.00 20 (February 2015) Change 2-11/15 ----------------------------------- Preparing Activity: NAVFAC Superseding UFGS-01 32 16.00 20 (November 2009) UNIFIED FACILITIES
TRICKS AND TRAPS PRESENTATION
Welcome to the Eastwood Harris Pty Ltd Primavera P6 Version 7 TRICKS AND TRAPS PRESENTATION Copyright of Eastwood Harris Pty Ltd Page 1 Purpose of the Presentation To demonstrate the P6 Version 7 bars
CDC UNIFIED PROCESS JOB AID
Purpose The purpose of this document is to provide guidance on the practice of using Microsoft Project and to describe the practice overview, requirements, best practices, activities, and key terms related
CPM Scheduling with Primavera Unifier
CPM Scheduling with Primavera Unifier Don McNatty, PSP March 26, 2014 2014 Technical Webinar Series Thank you for joining today s technical webinar Mute all call in phones are automatically muted in order
Introduction to Microsoft Project 2010
Introduction to Microsoft Project 2010 This document provides an introduction in using Microsoft Project 2010. Microsoft Project is a project management application that contains a set of tools to help
IJSRD - International Journal for Scientific Research & Development Vol. 3, Issue 10, 2015 ISSN (online): 2321-0613
IJSRD - International Journal for Scientific Research & Development Vol. 3, Issue 10, 2015 ISSN (online): 2321-0613 Planning, Scheduling and Resource Optimization for A Villa by using Ms-Project 2010 Mr.
Oracle Project Portfolio Management Integration Pack for Primavera P6 and Oracle E-Business Suite 3.1 - Implementation Guide
Oracle Project Portfolio Management Integration Pack for Primavera P6 and Oracle E-Business Suite 3.1 - Implementation Guide Release 3.1 Part No. E20507-02 June 2011 Oracle Project Portfolio Management
Project Initiation and Revision Training Manual. Table of Contents
for Engineering and Construction v.4.1 Project Initiation and Revision Training Class Conducted by Evans Technology June 2005 Table of Contents Introduction to Primavera... 3 Project Management (P3eC)...
Assigning Lump Sum Payment Plan to Student Account
File Name Assigning Lump Sum Payment Plan to Student Account.doc Version 8.9 Date Modified 7/14/2008 Last Changed by ASDS Status FINAL Concept Payment plans enable students to pay their education expenses
Integrating Costs With Primavera Contract Manager, P6 Scheduler, and P6 Web
September Webinar Integrating Costs With Primavera Contract Manager, P6 Scheduler, and P6 Web presented by: Jonathan McNatty, PSP DRMcNatty & Associates, Inc. The Primavera Solution! Primavera allows you
PS.12. 4D Scheduling A Case Study
PS.12 4D Scheduling A Case Study Mr. Abhimanyu Basu PE PSP A 4D schedule is a 3 dimensional CAD model How long would it take. attached to the fourth dimension of time via a schedule. The concept of 4D
How To Use P6 For A Project Scheduling System
Managing Assets Through Enterprise - Wide Scheduling Scott Lowe, P.E. Principal, Trauner Consulting Services, Inc. Scott Lowe, Principal, Trauner Consulting Services CPM Scheduler Claims Analyst Expert
ELECTRO-MECHANICAL PROJECT MANAGEMENT
CHAPTER-9 ELECTRO-MECHANICAL PROJECT MANAGEMENT Y K Sharma,SDE(BS-E), 9412739241(M) E-Mail ID: [email protected] Page: 1 Electro-mechanical Project Management using MS Project Introduction: When
Subcontractor Involvement Project Tracking Progress Curves. CSTM 462 Fall 2012
Subcontractor Involvement Project Tracking Progress Curves CSTM 462 Fall 2012 Subcontractor Involvement into the Critical Path Many building contractors get very little input into the schedule from their
How to Develop Work Breakdown Structures
How to Develop Work Breakdown Structures Michael D. Taylor Copyright 2003-2009 by Michael D. Taylor All Rights Reserved. No part of this work covered by the copyright hereon may be reproduced or used in
PROJECT COST MANAGEMENT
7 PROJECT COST MANAGEMENT Project Cost Management includes the processes required to ensure that the project is completed within the approved budget. Figure 7 1 provides an overview of the following major
Advancements in Construction Project Administration Session: 41 October 28, 2014
Advancements in Construction Project Administration Session: 41 October 28, 2014 Room: C220-222 3:00PM 3:45PM Claims ance, Mitigation and Resolution Take Advantage of New Tools Presented by: Andrew Morse,
Appendix A of Project Management. Appendix Table of Contents REFERENCES...761
Appendix A Glossary Terms of Project Management Appendix Table of Contents REFERENCES...761 750 Appendix A. Glossary of Project Management Terms Appendix A Glossary Terms of Project Management A Activity
PROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE
PROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE Table of Contents Introduction...3-1 Overview...3-1 The Process and the Project Plan...3-1 Project Objectives and Scope...3-1 Work Breakdown Structure...3-1
REQUIRED SKILLS AND KNOWLEDGE OF COST ENGINEERING TCM Framework: General Reference (All Sections)
AACE International Recommended Practice No. 11R 88 REQUIRED SKILLS AND KNOWLEDGE OF COST ENGINEERING TCM Framework: General Reference (All Sections) Rev. Note: As AACE International Recommended Practices
Application of Standard Project Management Processes in Fiber Optic Cable Plant Project Management. Introduction. Alfred Sankara, DigiBridge TelCo
Application of Standard Project Management Processes in Fiber Optic Cable Plant Project Management Alfred Sankara, DigiBridge TelCo Introduction The Project Management Institute (PMI) is the world's leading
WORK PROGRAM GUIDELINES
Project Managed Change Program WORK PROGRAM GUIDELINES JABATAN KERJA RAYA MALAYSIA Cawangan Pengurusan Projek Kompleks (PROKOM) Ibu Pejabat JKR Malaysia 2 Document Ownership Section No Section Amendment
Using Primavera Software in Resource Allocation and Project Evaluation of Construction Projects
Using Primavera Software in Resource Allocation and Project Evaluation of Construction Projects Hamed Ziaidoostan 1, Hamidreza Ghaneh 2, Matin Amanin 3, Mohamadmahi Gholipoor 4 1,2,3,4-M A Student of Business
THE PROJECT MANAGEMENT KNOWLEDGE AREAS
THE PROJECT MANAGEMENT KNOWLEDGE AREAS 4. Project Integration Management 5. Project Scope Management 6. Project Time Management 7. Project Cost Management 8. Project Quality Management 9. Project Human
Applied Project Management ( APM )
Applied Project Management Applied Project Management ( APM ) TRAINING PROGRAM Page 1 Of 7 APPLIED PROJECT MANAGEMENT PRO PROGRAM OVERVIEW This course provides in-depth Project Management Training and
SPECIFICATIONS - DETAILED PROVISIONS Section 01310 - Project Control Schedule C O N T E N T S
SPECIFICATIONS - DETAILED PROVISIONS Section 01310 - Project Control Schedule C O N T E N T S PART 1 - SCHEDULE REQUIREMENTS PROGRESS SCHEDULE... 1 PART 2 - SUBMITTAL PROCEDURES... 2 PART 3 - DEFINITIONS...
Stefan Glatzmaier, Michael Sokollek. Project Portfolio Management with SAP. RPM and cprojects. Bonn Boston
Stefan Glatzmaier, Michael Sokollek Project Portfolio Management with SAP RPM and cprojects Bonn Boston Contents Acknowledgements... 9 Introduction... 11 1 Overview of Project Portfolio Management with
How To Manage Inventory On Q Global On A Pcode (Q)
Pearson Clinical Assessment Q-global User Guide Managing Inventory PEARSON 2 MANAGING INVENTORY Managing Inventory Overview When inventory is purchased, you will need to set up the allocations for the
Group Mail Lists. Group Mailing Lists. Populating a Global Mail Lists 4. The Problem 6. The Solution 8. Scheduling Regular Updates 17
Group Mail Lists Group Mail Lists 1 Group Mailing Lists 1.1 1.2 1.3 1.4 Populating a Global Mail Lists 4 The Problem 6 The Solution 8 Scheduling Regular Updates 17 Group Mailing Lists Group Mail Lists
108-C-215 CRITICAL PATH METHOD SCHEDULE. (Revised 03-24-10)
CRITICAL PATH METHOD SCHEDULE (Revised 03-24-10) The Standard Specifications are revised as follows: SECTION 108, BEGIN LINE 177, INSERT AS FOLLOWS: 108.04.1 Critical Path Method Schedule (a) General Requirements
The Two Most Useful Earned Value Metrics: the CPI and the TCPI
PM WORLD TODAY SECOND EDITIONS JUNE 2009 Editor s note: Second Editions are papers that have been previously published that have continued relevance and deserve additional visibility. The paper below was
Microsoft Project Dissected
Microsoft Project Dissected by Ron Winter, PSP Schedule Analyzer Software Copyright 2012 Third Annual Construction CPM Conference Introduction Although Oracle/Primavera P6 is dominant Many contracts specify/allow
Scheduling Glossary Activity. A component of work performed during the course of a project.
Scheduling Glossary Activity. A component of work performed during the course of a project. Activity Attributes. Multiple attributes associated with each schedule activity that can be included within the
SECTION 01310 COST LOADED CRITICAL PATH SCHEDULE
SECTION 01310 COST LOADED CRITICAL PATH SCHEDULE 1.0 General 1.1 Description The Work specified in this Section consists of developing and maintaining an accurate cost loaded critical path schedule in
CLARITY PPM TIPS, TRICKS, and TERMINOLOGY
CLARITY PPM TIPS, TRICKS, and TERMINOLOGY Clarity PPM Knowledge Sharing Series Helping the Clarity PPM Community Members Benefit from Best Practice TABLE OF CONTENTS 1 OVERVIEW... 3 2 OVERVIEW PAGE...
Almost everyone in the planning and scheduling profession
PS.02 The Great Negative Lag Debate Mr. Edward E. Douglas III CCC PSP, Mr. Timothy T. Calvey PE PSP, Mr. Donald F. McDonald Jr. PE CCE PSP, and Mr. Ronald M. Winter PSP Almost everyone in the planning
Resource Allocation in MS Project
Resource Allocation in MS Project Calendars The project calendar determines the working days and hours available to your project, In addition each resource can have their unique calendars to mark time
763XXX Timing Analysis, Critical Path Method (CPM) Project Schedule
763XXX Timing Analysis, Critical Path Method (CPM) Project Schedule Description: This work shall reflect a Contractor s anticipated work plan for constructing the project using a Critical Path Method Project
Project Control System Manual. Jefferson Science Associates, LLC. 600 Progress Status. Project Control System Manual Revision 7 - 44 -
Jefferson Science Associates, LLC 600 Progress Status Project Control System Manual Revision 7-44 - 600 Progress Status This chapter of the JSA Project Control System Manual explains how the status of
MnDOT Project Management Office Presents: Schedule Updates. Presenter: Eric Costantino Senior Schedule Consultant DRMcNatty & Associates, Inc.
MnDOT Project Management Office Presents: Schedule Updates Presenter: Eric Costantino Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted during the webinar Questions
your project controller
your project controller milemate.it Your project controller MILEMATE! is the application that manages all aspects relating to the project control activities. Born from multiple worldwide experiences in
Collaborative Scheduling using the CPM Method
MnDOT Project Management Office Presents: Collaborative Scheduling using the CPM Method Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines
Release 1. BSBPMG410A Apply project time-management techniques
Release 1 BSBPMG410A Apply project time-management techniques BSBPMG410A Apply project time-management techniques Modification History Release Release 1 Comments This version first released with BSB07
Contract Management The Mavericks Won t Like This!
Contract Management The Mavericks Won t Like This! Keith Wallis How Much Did That Project Cost? Real Life Example Original contract amount $500K Variations scope changes not visible Total variations =
How to Set Up and Manage a Perpetual Inventory System
SAP Business One How-To Guide PUBLIC How to Set Up and Manage a Perpetual Inventory System Applicable Release: SAP Business One 8.8 All Countries English March 2010 Table of Contents Introduction... 4
Using MS Project in Translation Projects Management
Using MS Project in Translation Projects Management When building a translation project plan, there must be taken into account: the tasks involved by the project, duration of each task, task dependencies,
Project success depends on
Project success depends on many factors both within and outside the control of the project team. One of the aspects that is within the control of the project team is the planning. Almost everything we
New Features in Primavera P6 EPPM 16.1
New Features in Primavera P6 EPPM 16.1 COPYRIGHT & TRADEMARKS Copyright 2016, Oracle and/or its affiliates. All rights reserved. Oracle is a registered trademark of Oracle Corporation and/or its affiliates.
Procurement Planning
MatriX Engineering Project Support Pinnacle Business Solutions Ltd www.pinsol.com www.matrix-eps.com Proc_Plan.doc Page 2 of 21 V_09_03 Contents 1.0 INTRODUCTION... 5 1.1 KPIS AND MEASURABLE TARGETS...
Methodology Management. Reference Manual
Methodology Management Reference Manual 1997-2005 Primavera Systems, Inc. All rights reserved. Unless otherwise noted, this software is the property of Primavera Systems, Inc. (Primavera) or its licensors
The Inner Workings of Oracle/Primavera P6. by Ron Winter, PSP Fellow of AACE International
The Inner Workings of Oracle/Primavera P6 by Ron Winter, PSP Fellow of AACE International Copyright April 4, 2016 ABSTRACT Oracle Primavera P6 scheduling software is noted for its diverse and extensive
OVERVIEW. Microsoft Project terms and definitions
PROJECT 2003 DISCLAIMER: This reference guide is meant for experienced Microsoft Project users. It provides a list of quick tips and shortcuts for familiar features. This guide does NOT replace training
MS Project Tutorial. CS 587 Software Project Management Instructor: Dr. Atef Bader. Prepared by Milton Hurtado
CS 587 Software Project Management Instructor: Dr. Atef Bader MS Project Tutorial MS Project in Labs: Available in Siegal Hall Lab in Main Campus Available in Room 210 Rice Campus Prepared by Milton Hurtado
Best Practices Statement Project Management. Best Practices for Managing State Information Technology Projects
State of Arkansas Office of Information Technology 124 W. Capitol Ave. Suite 990 Little Rock, AR 72201 501.682.4300 Voice 501.682.4020 Fax http://www.cio.arkansas.gov/techarch Best Practices Statement
A Project Manager's Book of Forms. A Companion to the PMBOK Guide. 2nd Edition
Brochure More information from http://www.researchandmarkets.com/reports/2326795/ A Project Manager's Book of Forms. A Companion to the PMBOK Guide. 2nd Edition Description: A compendium of ready made
Administering Active Directory. Administering Active Directory. Reading. Review: Organizational Units. Review: Domains. Review: Domain Trees
Reading Read over the Active Directory material in your Network+ Guide I will be providing important materials Administering Active Directory If you don t understand certain concepts, please ask for help!
Baseline Schedule Metrics. Donald R. McNatty, PSP FAACE November 18, 2015
Donald R. McNatty, PSP FAACE November 18, 2015 1 Thank you for joining today s technical webinar Mute all call in phones are automatically muted in order to preserve the quality of the audio for all attendees.
Time Management. Part 2 Work Breakdown Structure (WBS) Review. Richard Boser
Time Management Part 2 Work Breakdown Structure (WBS) Review Richard Boser WBS Planning Process PMBOK WBS is deliverable-oriented grouping of components that organizes and defines the total scope of the
Microsoft Project 2010
Tutorial 1: Planning a Project Microsoft Project 2010 In Tutorial Section 1.1 you will: Learn project management terminology Understand the benefits of project management Explore the Project 2010 window
Module A2 Item Activities, Gantt Chart and Utilization Sheet. A2.1 Project item activities A2.2 Gantt chart A2.3 Utilization sheet
Module A2 Item Activities, Gantt Chart and Utilization Sheet A2.1 Project item activities A2.2 Gantt chart A2.3 Utilization sheet 1 Assistance PSA: Advanced Functionalities Welcome to the Advanced Functionalities
FINAL Cost Estimate Report
Intelligent Transportation System Strategic Deployment Plan Update FINAL Cost Estimate Report Prepared for: Triangle ITS Communications Partners Prepared by: In Association with: March 2010 011494053 Copyright
Kiln Drying Planning Tool. User Guide
Kiln Drying Planning Tool User Guide Prepared by FORAC Research Consortium Université Laval Québec (QC), Canada www.forac.ulaval.ca August 2008 Copyright FORAC, 2008 Table of content TABLE OF CONTENT...
Relationships Field Definitions... 51 Using the WPs & Docs Tab... 52 WPs & Docs Field Definitions... 52
P6 Progress Reporter May 2011 Contents Preface... 7 P6 EPPM Documentation... 7 Where to Get Documentation Updates... 10 Where To Get Training... 10 Where to Get Support... 10 Documentation Accessibility...
Primavera P6 Exercise Worksheet
Primavera P6 Exercise Worksheet P6 Exercise Worksheet Preparing for the Exercises Ten Six Consulting recommends that you download and install your own standalone copy of Primavera P6 Professional for use
Configuration Manager
After you have installed Unified Intelligent Contact Management (Unified ICM) and have it running, use the to view and update the configuration information in the Unified ICM database. The configuration
Microsoft Project Server 2010 Project Manager s Guide for Project Web App
Microsoft Project Server 2010 Project Manager s Guide for Project Web App Copyright This document is provided as-is. Information and views expressed in this document, including URL and other Internet Web
The Project Planning Process Group
3 The Project Planning Process Group............................................... Terms you ll need to understand: Activity Activity attributes Activity list Activity on arrow diagram (AOA) Activity
Primavera P6 Enterprise Project Portfolio Management 8 Essentials (1Z0-567) Exam Study Guide
Primavera P6 Enterprise Project Portfolio Management 8 Essentials (1Z0-567) Exam Study Guide Margy Girdzius Director, Partner Enablement WWA&C Objective & Audience Objective Help you prepare to take the
NOTES ON XER EXPORT AND IMPORT BETWEEN ASTA POWERPROJECT AND IMPORT TO PRIMAVERA VERSION 5.0 PAUL E HARRIS EASTWOOD HARRIS
P.O. Box 4032 EASTWOOD HARRIS PTY LTD Tel 61 (0)4 1118 7701 Doncaster Heights ACN 085 065 872 Fax 61 (0)3 9846 7700 Victoria 3109 Project Management Systems Email: [email protected] Australia Software
Microsoft Project From the WBS to a Complete Schedule Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org
Planning and Managing Software Projects 2010-11 Session 6 Microsoft Project From the WBS to a Complete Schedule Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org Credits 2 These
How to Use the Cash Flow Template
How to Use the Cash Flow Template When you fill in your cash flow you are trying to predict the timing of cash in and out of your bank account to show the affect and timing for each transaction when it