1 Primavera P6 102 Training Manual Prepared by Bill Pepoon, Managing Partner Construction Science, LLC 1

2 Day I Introduction Setting up a new Project Activities Activity Types Activity Durations Work Breakdown Structure (WBS) Dates Calendars Activity Codes Activity Logic Constraints Scheduling Custom Layouts & Views (Formatting) 2

3 3

4 Introduction Data Structures in P6 EPS (Enterprise Project Structure) Centralized Management of multiple projects Categorizes work in the Organization: A hierarchy of projects or a grouping of projects within departments Projects represent the lowest level of the EPS Every project in the organization must be included in an EPS 4

5 Introduction (Cont d) Data Structures in P6 OBS (Organization Breakdown Structure) A Separate global hierarchy reflecting the management structure One OBS for the entire organization Used to control access to projects and data An OBS element/person will be responsible for each node/project within the EPS 5

6 Introduction (Cont d) Data Structures in P6 Work Breakdown Structure (Company Name) EPS Acts as a continuation for the individual projects in the EPS Project A Project B Project C The WBS is a Project-Specific Structure. Each project has its own WBS that further breaks down the work in that project. The project is the highest level of the WBS. Activities are the lowest level of the WBS Project B (WBS Level 1) WBS Node 1 WBS Node 2 WBS Node 3 Activity 1 Activity 2 6

7 Introduction (Cont d) Work Breakdown Structure For a more detailed discussion of Work Breakdown Structures, see the WBS handbook published by the Department of Defense (MIL- HDBK-881A, 30 JUL 2005) 7

8 Introduction (Cont d) Data Structures in P6 Activities An operation or process consuming time and possibly resources An element of work that must be performed in order to complete a project The basic component of a schedule Activities must be measurable and controllable An activity may include one or more tasks 8

9 Introduction (Cont d) Data Structures in P6 Activities (Cont d) Any activity has attributes : Schedule-related characteristics and designations that uniquely describe a network activity. Attributes can include : Predecessor and successor activities Early and late start and finish dates Identification codes (e.g. trade, area, phase, etc.) Resource assignments (Labor, equipment ( non-labor ), material) Any other information that places the activity into accurate context 9

10 Introduction (Cont d) Data Structures in P6 Resource Hierarchy Includes the resources across all projects in the organization Could be broken down by Type: labor, equipment, material Subcontractor Function: design, site.. Skill level Project 10

11 Introduction (Cont d) Data Structures in P6 Summary The EPS categorizes work in the Organization Projects belong to EPS nodes Each project has its own WBS that further breaks down the work in that project. Activities are the lowest level of the WBS. The OBS represents the responsible managers in your company and can be assigned at the EPS, project, and/or WBS level 11

12 Introduction (Cont d) Global Data Vs. Project Specific Data Global Data Defined at the EPS level Applies to all projects across the enterprise e.g. EPS and OBS, and resource and role information Project-Level Data Defined at the project level Available only to that project Activities, WBS, and Work Products & Documents 12

13 Introduction (Cont d) Multiple Platforms Windows Client Software resides on host computer Project databases may or may not be located on host computer Web Client Software and project databases are hosted on the web (i.e. cloud computing ) Dashboard organized differently than Windows Client but features are similar 13

14 Introduction (Cont d) New Terminology Name in P3 Activity Columns Activity Form Activity Logs Bar Chart Costs (lump sum) Custom Data Items Estimate at Completion (resource) Estimate to Complete (resource) Expedition Fragnets Name in P6 Activity Table Activity Details Notebook Gantt Chart Expenses User-defined Fields At Completion Units Remaining Units Contract Management Methodologies 14

15 Introduction (Cont d) Name in P3 Hammock (activity type) Independent (activity type) PERT Resource lag Resource Profile Resource Table Target Task (activity type) WBS (activity type) Name in P6 Level of Effort Resource Dependent Activity Network Original lag/remaining lag Resource Usage Profile/ Activity Usage Profile Resource Usage Spreadsheet/ Activity Usage Spreadsheet Baseline Task Dependent WBS Summary 15

16 Navigation (Release 7.0) Command Toolbar Directory Toolbar Bottom Layout 16

17 Navigation (Release 7.0 Cont d) Click on the Directory Icon to show/hide the Directory Toolbar 17

18 Navigation (Release 7.0 Cont d) Right-click anywhere in the Bottom Layout to add/remove tabs 18

19 Navigation (Release 7.0 Cont d) Shows all Projects in the Database Shows the Activities of the Current (Active) Project 19

20 Training Task No. 1 Practice each of the following: 1. Hide the Navigation Bar button text 2. Hide the Navigation Bar 3. Hide the Directory Bar button text 4. Hide the Directory Bar 5. Hide the Command Bar button text 6. Open/close Activity Detail 7. Add all available tabs to Activity Detail 20

21 21

22 Setting up a New Project Creating a New EPS 1. Enterprise Command Menu Enterprise Project Structure 2. Click Add 3. Specify EPS ID & Name 4. Change the EPS position in the hierarchy using arrows 5. Modify Display Options 22

23 Setting up a New Project (Cont d) Creating a New OBS 1. Enterprise Command Menu OBS 2. Right-click OBS Details 3. Click on the OBS node that you want to add a person under, then click Add 4. Change hierarchical position using appropriate arrow 5. Go back to the new EPS to Change the Responsible Manager name 23

24 Creating a New Project To Create a new Project Select the EPS to which you want to add the new project Click Add OR Right- Click the EPS Add Type Project Data Project ID Project Name Planned Start Date Must Finish By : Contract Finish Date Responsible Manager in the OBS Rate Type: Price/Unit 24

25 Creating a New Project (Cont d) Also, you can Cut/Copy & Paste an existing project into the new EPS 25

26 Creating a New Project (Cont d) In the Defaults Tab, Choose the AutoNumbering preferences Use Smart IDs to denote activity s information. E.g. PH1F2C001 : Phase 1, Floor 2, Concrete Works 26

27 Creating a New Project (Cont d) To set Project as Default : Project Menu "Set Default Project. Display Project Details by clicking on the "Show / Hide Bottom Layout" icon, OR Right-Click on the Project Project Details 27

28 Creating a New Project (Cont d) To open the Project: Select the Project in the Home Page Click on the "Activities" tab in the Directory Toolbar OR Right-Click on the Project "Open Project" 28

29 Training Task No. 2 Create an EPS Node called Sample Projects and place it under the highest level of the enterprise Copy Project CHP_NR (provided by the instructor) into the this EPS Node Create an OBS called Training Program and place it under the name of the organization Make CHP_NR the default project 29

30 30

31 Adding Activities Click on the Activities icon in the Directory Toolbar Right-Click where you want to insert the new activity "Add" OR Click the "Add" icon and follow the Wizard steps OR Click "Insert" 31

32 Adding Activities (Cont d) You can also, Cut, Copy, Paste and Delete activities using the Command Bar 32

33 Activity Description The Activity Description should be: Clear: Spell out the task clearly. Avoid generic descriptions Complete: Scope adequately covered by the description Unique: Identify the activity s specific information Example: Electric Fixtures X Light Fixtures X Install Light Fixtures X Install Light Fixtures 5th Floor 33

34 Importing Activities From MS Project [File Menu Import] I. Importing a Schedule in a different format: 1. Select the new Project 2. File Menu Import 3. Choose the format of the file to be imported 4. Select the type of data to import as "Project" 5. Enter the destination of the file to be imported 34

35 Importing Activities From MS Project [File Menu Import] I. Importing a Schedule in a different format (Cont'd): 6. Choose the appropriate import action: either Update / Replace / Add into an existing project or create a new one 7. Select the Project to which the new data will be imported 8. Choose what to update or keep only when updating an existing project 35

36 Exporting Activities To Excel [File Menu Export] II. Exporting/Importing an Activity List in a spreadsheet: 1. Export a spreadsheet that will be used as a template into which you can copy your Activity List, to do this: Open the new Project 2. Create a dummy activity 3. File Menu Export 4. Choose the format of the file to be exported as "Spreadsheet" 5. Select the type of data to export as "Activities" 36

37 Exporting Activities To Excel [File Menu Export] II. Exporting/Importing an Activity List in a spreadsheet: 6. Select the Project to be exported 37

38 Exporting Activities To Excel [File Menu Export] II. Exporting/Importing an Activity List in a spreadsheet: 6. Select / Modify the Template 7. Choose the data that you already have available in your Activity List. The selected fields will appear in the same order in the exported spreadsheet. 8. Choose the destination and name of the spreadsheet to be imported. 38

39 Exporting Activities To Excel [File Menu Export] II. Exporting/Importing an Activity List in a spreadsheet: 9. Copy/Paste your Activity List and enter other activity data into the exported spreadsheet. 10. Make sure Column headings and format is maintained 11. Re-import the exported spreadsheet with the new data into P6 39

40 Version 7 New Feature MS Excel Import Security Problem: Global dictionaries can be easily modified if all users are allowed to import data Previously, users had to be granted all or none permission to import data from other Primavera products, MS Project and MS Excel Now, administrator can allow importing of MS Excel files while still denying permission to import other types of data Available in both Windows and Web clients 40

41 Training Task No. 3 Create a MS Excel export file for schedule CHP_NR Add a new XLS template with the following information in this order: Activity ID Activity Status Activity Name WBS Code Original Duration Stage Predecessors Successors Save the XLS template as Training Template 1 Export both activities and relationships 41

42 42

43 Activity Types In P6, an Activity Type can be either: Task Dependent Resource Dependent Level of Effort Start Milestone / Finish Milestone WBS Summary 43

44 Activity Types (Task) Task Dependent Activity Scheduled only according to the Activity's calendar When you want to control the Activity's duration yourself Activity s Resources are scheduled according to the Activity's Calendar Use this Activity Type for all construction / physical activities 44

45 Activity Types (Resource) Resource Dependent Activity Scheduled according to the calendars of assigned resources Resources are scheduled according to their own calendars Used when several resources are assigned to the same activity, but may work separately, or when availability can affect Activity's duration 45

46 Activity Types (Level of Effort) Level of Effort Activity Commonly known as Hammocks Has a duration which is determined by its dependent activities, from the earliest start of its predecessors to the latest finish of its successors Should be linked to its predecessors with a SS, and to its successors with a FF Overhead-type activities are typically Level of Effort, e.g. Site Cleanup Can be used for monitoring purposes, e.g. "Project Duration" 46

47 Activity Types (Level of Effort, Cont d) Level of Effort Activity (Cont'd) Predecessors: 02 & 03 Predecessors Successors Successors: 04 & 05 47

48 Activity Types (Milestone) Start Milestone/Finish Milestone A zero-duration activity with no resources Used when an activity is intended to signify the commencement/completion of a significant stage, rather than a physical work product Examples : Notice to Proceed, Substantial Completion, etc. 48

49 Activity Types (WBS Summary) WBS Summary Activity Has a duration which is determined by a group of activities that share a common WBS level. The Activity's duration will equal the overall duration of activities assigned to the same WBS level. Resources that drive activity dates cannot be assigned to WBS summary activities. 49

50 Activity Types (Cont d) To change the Activity Type: 1. Select the activity & show activity details 2. Click the "General" tab 3. Choose the appropriate activity type from the drop down menu 50

51 Training Task No. 4 What is the default activity type for Project CHP_NR? Where do we assign the Project Leveling Priority? How do we open two or more projects at the same time? There are at least 4 different ways to add an activity in P6; what are they? 51

52 52

53 Activity Durations To enter/modify Activity's Original Duration Select the activity & show activity details Click the "Status" tab Enter the Activity's duration in the "Original Duration" field OR Enter the Activity's duration in the original duration column 53

54 Training Task No. 5 Create Level of Effort activities in your copy of CHP_NR to represent the length of each of the following stages: Stage 1 (Activity ID LOE_S1 ) Stage 2 (Activity ID LOE_S2 ) Stage 3 (Activity ID LOE_S3 ) Stage 4 (Activity ID LOE_S4 ) Place each Level of Effort activity in the appropriate Stage Assign the same calendar to these Level of Effort activities as the existing Level of Effort Activity ID 40. Relationships will be added during Training Task No. 8 54

55 55

56 Creating the WBS 1. Open the new Project 2. Click on the "WBS" tab in the Directory Toolbar 3. The Project is by default WBS Level 1 4. Click on the "Columns" icon to show the WBS Code, Name & Path 56

57 Creating the WBS (Cont d) 6. Insert a new WBS element by selecting the WBS level under which you want the new WBS node to exist then click "Add" 7. Enter the WBS element s name & code. Code is incremented automatically. 8. Change the WBS element s level in the hierarchy using the arrow keys 57

58 Creating the WBS (Cont d) Modify the WBS display using the "Layout Options" Toolbar You can also Cut/Copy and Paste WBS elements (including activities) 58

59 Assigning WBS Codes 1. Show the new project activities by clicking on the "Activities" tab in the directory toolbar 2. Click on the "Group & Sort" icon on the "Layout Options Toolbar 3. Organize the Activities by the "WBS" 4. Using the Cut & Paste commands, move activities into their appropriate WBS location 5. Also, modify the Activity's WBS location using the "General" tab 59

60 Assigning WBS Codes (Cont d) You can also assign WBS codes by exporting a spreadsheet, filling in WBS codes against activities, then importing it back to P6. 60

61 Assigning WBS Codes When deleting a WBS element, make sure you choose the option Merge Elements to avoid deleting subordinate activities together with the WBS code. 61

62 62

63 Dates P6 expands the types of dates that are possible Date Field Definition Start The current start date of the activity. Set to the remaining start date until the activity starts, then set to the actual start date. A next to the date indicates an actual start date; * indicates that a constraint is being used. 63

64 Dates (Cont d) Date Field Definition Finish The current finish date of the activity. Set to the planned finish date until the activity starts, becomes the remaining finish date while the activity is in progress, and then becomes the actual finish date upon completion. A next to the date indicates an actual finish date; * indicates that a constraint is being used. 64

65 Dates (Cont d) Date Field Definition Early Start The earliest date the remaining portion of the activity can begin. The date is based on activity relationships, schedule constraints and resource availability. Early Finish The earliest date the activity can be completed. The date is based on activity relationships, schedule constraints and resource availability. 65

66 Dates (Cont d) Date Field Definition Late Start The latest date the remaining portion of the activity can begin. The date is based on activity relationships, schedule constraints and resource availability. Late Finish The latest date the activity can be completed. The date is based on activity relationships, schedule constraints and resource availability. 66

67 Dates (Cont d) Date Field Definition Planned Start The date the activity is scheduled to begin. Set to the early start date but can be manually changed by the user. Does not change once an actual start date is applied. Planned Finish The date the activity is scheduled to be completed. Set to the early finish date but can be manually changed by the user. Does not change once an actual finish date is applied. 67

68 Dates (Cont d) Date Field Definition Remaining Early Start The date the remaining portion of the activity is scheduled to resume. Set to the planned start date until the activity begins. Can be manually changed by the user. Remaining Early Finish The date the remaining portion of the activity is scheduled to be completed. Set to the planned finish date until the activity begins. Can be manually 68 changed by the user.

69 Dates (Cont d) Date Field Definition Remaining Early Start The date the remaining portion of the activity is scheduled to resume. Set to the planned start date until the activity begins. Can be manually changed by the user. Remaining Early Finish The date the remaining portion of the activity is scheduled to be completed. Set to the planned finish date until the activity begins. Can be manually changed by the user. 69

70 Dates (Cont d) Date Field Definition Suspend Date The date work stopped on the activity for unexpected, but temporary, reasons. Date is manually entered by the user. Resume Date The date that work resumes after a temporary suspension. Date is manually entered by the user. Tip: before an activity has any progress the Early Start, Planned Start, Current Start and Remaining Early Start dates are all the same. 70

71 71

72 Creating Calendars 1. [Enterprise Calendars] Enterprise Command Menu Calendars 2. Choose Global 3. Click Add to create a new calendar or Modify to edit an existing one 4. Choose the Calendar that you want to use as a template for new Projects 5. Modify the Work Week 6. Double-click to add work/non-work days 7. Check in the Default Box to make this the default Calendar for all future projects 72

73 Creating Calendars (Cont d) 8. In the main Calendars window, choose Project 9. Add the Global Calendar that was created in Step 3 above 10. Holidays will be inherited automatically 11. Go back to the Home Page, RightClick on the new project Project Details 12. In the Defaults Tab, choose the new Calendar from the drop down menu [Enterprise Calendars] 73

74 Creating Calendars (Cont d) To Assign a Calendar 1. Select the Activity. 2. From the General tab, select the appropriate Calendar. 74

75 Training Task No. 6 Add a new Project calendar to your copy of CHP_NR with the following attributes: Calendar Name is Special 6-Day Calendar 6-day workweek for all of 2011 and 2012 No work performed during January 2011 or January 2012 Holidays are March 31st, July 4th and November 15th Workday starts at 7:00 am and ends at 3:30 pm with 30 minutes for lunch 75

76 76

77 Activity Coding Structures In addition to the WBS, you can group, filter, summarize and sort activities using Activity Codes You can use Activity Codes in lieu of, or in combination with the WBS E.g.: Phase, Area, Work type, Specification Division, Subcontractor, etc. 77

78 Activity Coding Structures [Enterprise Activity Codes] Create the Activity Coding structure : Enterprise Command Menu "Activity Codes" P6 provides 3 types of Activity Codes: Global: can be assigned to activities in all projects EPS: can be assigned to projects within the EPS Project: can only be assigned to activities in the opened project 78

79 Activity Coding Structures [Enterprise Activity Codes] Create the Activity Coding structure (Cont'd): Note the difference between the Activity Code and Activity Code Values 79

80 Activity Coding Structures [Enterprise Activity Codes] Create the Activity Coding structure (Cont'd): In the main Activity Codes Window select "EPS" Click "Modify" A new window will appear, add the new code & new code s name Close the window Select the new code from the dropdown menu Add new values to the code 80

81 Version 7 New Feature Activity Field-Level Security Previously, access could only be restricted to Global, EPS and Project levels; any user with Project-level access could change any activity Each user can be assigned edit privileges to only the activity fields they are required to update, while all others are read only Activity-level security gives the flexibility to allow users to update fields such as actual start and finish, percent completes and remaining effort, while limiting those same users to read-only access to other activity-level fields Available in both Windows and Web clients 81

82 Assigning Activity Codes 1. Show the Project details by clicking on the "Show/Hide Bottom Layout" in the "Layout Options" toolbar 2. Click the "Codes" tab 3. Click "Assign" 82

83 Assigning Activity Codes (Cont d) 4. From the top bar, choose the coding level from which you want to assign codes, whether Global, EPS or Project Note: To assign from the Global codes, make sure the display Filter is set to All values 5. Select the code you want to assign 83

84 Assigning Activity Codes (Cont d) 6. From the top bar, choose the coding level from which you want to assign codes, whether Global, EPS or Project Note: To assign from the Global codes, make sure the display Filter is set to All values 7. Select the code you want to assign 84

85 Version 7 New Feature Adding Code Values On the Fly Individuals can now add new code values to the dictionary while assigning codes to activities, without having to navigate to the activity code dictionary User will simply be prompted to specify the activity code value and description Available in both Windows and Web clients Just like P3! 85

86 Training Task No. 7 Add a new Project activity code to your copy of CHP_NR and name it Responsibility Assign the following code values to Responsibility TC (description = Traffic Control ) Dirt (description = Excavate Sub Base Using the Activity Details in the bottom layout, assign code values to select activities Assign TC to all activities with Traffic Control in the Activity Name Assign Dirt to all activities with Excavate Sub Base in the Activity Name What are some other ways to assign Project activity codes? 86

87 87

88 Adding Logic Relationships 1. Show the Project details by clicking on the "Show/Hide Bottom Layout" in the "Layout Options" toolbar 2. Click the "Relationships" tab 3. Click "Assign" to add Predecessors / Successors 4. Select the Predecessor / Successor from the list 88

89 Adding Logic Relationships (Cont d) New logic relationships are Finish-to-Start by default. To change the relationship type, double click in the "Relationship Type" field then choose the appropriate type from the drop-down menu. You can only input the Relationship Type & Lag. Other fields are automatically calculated by the software. To customize the displayed columns, Right-Click anywhere in the Predecessor or Successor area. 89

90 Adding Logic Relationships (Cont d) 05/12 05/20 05/22 05/30 FS Lag 1 05/20 FF Lag 2 05/22 05/12 SS Lag 1 05/13 90

91 Adding Logic Relationships (Cont d) To Add a Predecessor / Successor to Multiple Activities 1. Highlight all activities to which you want to add the predecessor / successor 2. Click on the "Predecessors" or "Successors" icon on the "Command Bar", as may be appropriate 3. Select the common predecessor / successor that you want to add to the highlighted activities 91

92 Adding Logic Relationships (Cont d) To link a Series of Activities Ctrl-Click the activities in the order you want them in Right-Click "Link Activities" They are now linked in the order they were selected 92

93 Adding Logic Relationships (Cont d) Dissolve Activity Deletes the activity but joins its predecessors to its successors with a Finish-toStart Relationship Select the Activity, open the Edit Menu "Dissolve Activity" 93

94 Adding Logic Relationships (Cont d) Logic Networks To trace activities predecessors and successors: Click on the "Trace Logic" icon in the Layout options toolbar 94

95 Adding Logic Relationships (Cont d) Logic Networks (Cont'd) To view the overall Project's network, click on the "Activity Network" icon 95

96 Training Task No. 8 We will now add relationships for the Level of Effort Activities added during Training Task No. 5: Stage 1 (Activity ID LOE_S1 ) Stage 2 (Activity ID LOE_S2 ) Stage 3 (Activity ID LOE_S3 ) Stage 4 (Activity ID LOE_S4 ) Open the Activity Details and click on Relationships (hint: this tab may need to be added) Assign one predecessor and one successor for each Level of Effort Activity 96

97 Training Task No. 8 (Cont d) There are at least 4 different ways to add relationships between activities in P6. What are they? 97

98 98

99 Constraints Definition: A Constraint is a restriction imposed on the start or finish date of an activity It may or may not override logic, depending on the Constraint Type Should be used sparingly, only to represent external factors that are not within the control of the organization, e.g. easements, ADOT ROW, etc.. Should not be used as Shortcuts Always Document the basis for using the constraint 99

100 Constraints (Cont d) Constraint Types Start on : imposes a start date. Can delay an early start or accelerate a late start to satisfy the imposed date. Unlike the mandatory start constraint, doesn t violate logic. Start on or after : Also known as "Start no earlier than". Affects only early dates. Limits the earliest time an activity can begin so that early start date cannot be earlier than the constraint date. Logic however, may cause the early start to occur later. Start on or before : Also known as "Start no later than". Affects only late dates. Limits the latest date it can start. When calculating a schedule, it is used in the backward pass only if the calculated late start date will be later than the imposed date. This constraint may decrease total float. Start on Start on or Before Start on or after 100

101 Constraints (Cont d) Constraint Types (Cont'd) Finish on: Similar to the "Start on". Imposes a finish date. The finish on constraint can delay an early finish or accelerate a late finish to satisfy the imposed date. Finish on or after : "Finish no earlier than". Limits the earliest time it can finish so that the finish of an activity is not scheduled before the imposed date. Finish on or before : "Finish no later than". Limits the latest time it can be finished. The finish on or before constraint affects only late dates. Reduces Total Float. Finish on Finish on or Before Finish on or after 101

102 Constraints (Cont d) Constraint Types (Cont'd) As late as possible : Pushes the activity to start as late as possible without delaying its successors, if it has available float. Mandatory start / Mandatory Finish : sets early and late dates equal to the date you specify. Overrides logic..do not Use..!!!! 102

103 Constraints (Cont d) 05/20 05/21 05/20 Constraint to Start on or after 06/05 06/05 103

104 Constraints (Cont d) Constraint (Cont'd) Always re-calculate the schedule after you apply a constraint. Always document the basis of the constraint. 104

105 Training Task No. 9 Assign a Finish On or Before constraint to Activity ID 9999 Finish date should be 01/18/12 Change the previous constraint to Mandatory Finish with a Finish date of 12/05/11 What happens? Is it possible to assign a constraint to an activity so that the activity will appear to be critical at all times? 105

106 106

107 Scheduling Now it s time to calculate the Schedule Click Tools Schedule OR click F9 Select the Data date Schedule the project after each logic change for it to take effect 107

108 Scheduling (Cont d) Float Calculations In Primavera P3, relationship lag was determined by the calendar on the predecessor activity P6 has multiple options for relationship lag: Predecessor activity calendar Successor activity calendar 24-hour calendar Default calendar Progress Override vs. Retained Logic 108

109 109

110 Grouping & Sorting Click on the "Group & Sort" icon in the Layout Options Toolbar Double-click in the "Group by" field to select the grouping data item. Double-Click on the Font & Color field to modify the format of the grouping bands 110

111 Grouping & Sorting (Cont d) Mark "Show Group Totals" to display the totals per data item in the grouping bands (e.g. total budgeted cost per Area) 111

112 Grouping & Sorting (Cont d) Click "Sort" to specify the order of activities within each group When done, click "Apply" for changes to take effect 112

113 Filters 1. Click on the "Filters" icon 2. Click: "New" to create a new filter, "Modify" to edit an existing one, or Copy/paste a global filter under the "User Defined" category to modify it 113

114 Filters (Cont d) 3. Enter the Filter criteria; could be any activity attribute: Code, WBS or Resource assignment, a Date, % complete etc. 4. Choose the Filter Parameter, whether you want to filter to show activities complying with ALL or ANY of the criteria. 114

115 Filters (Cont d) 5. Mark against the filter(s) that you want to apply 6. Select "All Selected Filters" or "Any Selected Filter" to display activities that meet ALL or ANY criteria specified in the selected filters 7. To revert to displaying all activities, mark the "All Activities" checkbox 115

116 Activity Table 1. Click on the "Columns icon" 2. Choose from the available data fields the columns that you want to display, use the arrows keys to add/remove columns to the current layout Click "Edit Column" to modify the Columns format and/or title 116

117 Activity Table (Cont d) Columns can be useful in Adding/modifying activity details, e.g. :Changing Activity Codes 1. Click on the "Columns" icon in the Layout Options Toolbar 2. Choose from the "Activity Codes" categories the columns that you want to display using the arrow keys 117

118 Activity Table (Cont d) 3. In the activity row, doubleclick on the activity code you want to add/modify 4. Select the appropriate code 118

119 Activity Table (Cont d) To view activity group summaries, right-click anywhere in the Activity Table Choose either: "Collapse All" : to summarize all the schedule to the project level "Collapse to": to summarize the schedule up to certain level only "Expand all" to display all activities 119

120 Fill Down Function You can quickly copy a certain activity attribute to many activities For example, to assign the same code to multiple activities: Highlight the activities, Right-Click "Fill Down" 120

121 Training Task No. 10 Create a filter to display all Stage 1 and Stage 2 work Create a filter to display only activities with traffic control in the activity name What is the difference between longest path and critical path? Can a schedule have negative float even though there are no constraints on any activities? 121

122 Customizing the Bar Chart To Customize the Timescale View Menu Timescale OR Click on the "Timescale icon in the Layout Options toolbar Enter the Timescale start Enter the Timescale Interval Use Timescale Type :Calendar 122

123 Customizing the Bar Chart (Cont d) Double-Click anywhere in the Chart area to return to the Project start Click on the Zoom in/zoom out icons to view a smaller/larger time period 123

124 Customizing the Bar Chart (Cont d) To customize the Bars: View Menu Bars OR Click on the "Bars" icon in the Layout Options toolbar Mark the checkbox next to bars you want to show Modify the shape and color of the selected Bar from the Bar Style tab. 124

125 Customizing the Bar Chart (Cont d) Under the Bar Labels Tab, Click "Add" to select a Bar Label, e.g. Activity Name, Start & Finish Dates, etc. 125

126 Customizing the Bar Chart (Cont d) You can add a new bar style for a certain group of activities, e.g.: all activities with a certain Activity code 1. Click "Add" or copy another Bar 2. Enter the new Bar s style and criteria 3. Enter a Filter to associate a group of activities with the Bar s style 126

127 Customizing the Bar Chart (Cont d) Click on the "Spotlight" icon and drag it highlight progress during a certain period 127

128 Customizing the Bar Chart (Cont d) Click on the "logic lines" icon to show logic relationships in the Bar Chart 128

129 Customizing the Bar Chart (Cont d) Careful when clicking in the Bar Chart area, logic relationships can be changed!! 129

130 Customizing the Bar Chart (Cont d) Attachment Tools Add Curtains to highlight certain periods of time 130

131 Customizing the Bar Chart (Cont d) Attachment Tools Add text to Activity Names 131

132 Version 7 New Feature Progress Line A new progress line can be shown on the Gantt chart to graphically communicate variances in project progress The progress line can be displayed with activity current bars and display schedule variance In addition, the progress line can be drawn on top of baseline bars, plotting the progress point of each activity on its baseline bar The progress line shows where the progress should be relative to the data date (available in both Windows and Web Clients) 132

133 Training Task No. 11 Using your copy of CHP_NR, create a new layout with the following attributes: Timescale is dark green and text is white Timescale should display dotted sight lines every quarter and solid sight lines at the end of every year Activity Table should contain the following data in this exact order: Activity ID Activity Name Original Duration Duration Type Remaining Early Start Remaining Early Finish Center align text in each data column 133

134 Training Task No. 11 (Cont d) Group all activities as follows: Activity Code Stage is highest level and should have an orange band with black text (font size = 14) Activity Code Post Mile is the next highest level and should have a dark blue band with white text (font size = 12) Sort activities as follows: Early Start, then Early Finish Filter activities to meet both of the following criteria: Total Float = 0 Activity Type does not include Level of Effort 134

135 Training Task No. 11 (Cont d) Make the following changes to the Gantt Chart Make critical bars purple Add float bars on Row 2 and make them yellow Add a curtain for the month of January in 2011 and 2012 and make the filter light green in color with / fill pattern Save layout as Training Layout 1 135

136 Print Setup [File Menu Page Setup] File Menu Page Setup In the "Page" tab, make sure to "Fit Timescale" to 1 page wide 136

137 Print Setup (Cont d) [File Menu Page Setup] In the "Footer" tab specify Number of sections into which the footer to be divided Which pages to show the footer on Data to be included in each section To enter Data into the footer Sections, select the section, Select Data Item form the drop down menu click Add 137

138 Print Setup (Cont d) [File Menu Page Setup] In the "Options" tab Specify: Timescale Start Timescale Finish Data Items to be printed 138

139 Layouts [View Menu Layout] To open or save layouts: Click the View Menu Layout To Create a new layout 1. Open an existing layout that most closely resembles the format of the new layout you want to create 2. Choose View, Layout, Save As 3. Type a name for the new layout 4. In the Available To field, select a user category, then click Save 139

140 Layouts (Cont d) [View Menu Layout] You can transfer layouts using the import/export options 140

141 Day II Defining Resources Assigning Resources Analyzing Resources & Cost Usage Activity Duration Types Percent Complete Types EV calculations Expenses Updating the Schedule Creating a Baseline Recommended Scheduling Practices 141

142 142

143 Defining Resources To Create a new Resource 1. Click on the Resources tab in the Directory Toolbar 2. Click on the Display Options toolbar to filter the displayed Resources to either all Projects in the Database or the Current Project only 143

144 Defining Resources (Cont d) 3. Click "Add" to add a new resource and follow the Wizard OR Right-click Add OR Click "Insert" You can also Copy/Paste Resources from different Projects. Use the arrows to move the new resource to its appropriate position in the hierarchy Right-click on the new resource "Details" 144

145 Defining Resources (Cont d) 4. Under the General tab, enter the Resource ID & Resource name 145

146 Defining Resources (Cont d) 5. Under the Details tab: Enter the new Resource s type: Labor, Non-labor or Material Select "Auto Compute Actuals" if you want actual units to be automatically updated based on the Activity's % complete Select "Calculate Costs from Units" to generate a "Budgeted Cost" based on the Resource Usage Select the Resource calendar. The default project calendar is recommended 146

147 Defining Resources (Cont d) 6. Under the Units & Prices tab: Click "Add" to enter resource Price/Unit for certain time periods. Example : labor wages increase Enter the Maximum Units/Time: Maximum hours the resource can work per day 147

148 148

149 Assigning Resources 1. In the Resources tab of the Activity Details Bottom Layout, click "Add Resource" OR Click on the Resources icon on the Command Bar 2. Select the Resource you want to add 3. Enter the Resource s Budgeted Units (e.g. Hours) By default: Budgeted Cost = Price/Unit x Budgeted Units Budgeted Units = Units/Time x Duration 149

150 Assigning Resources Budget/Cost To Change a Resource Price/Unit Tools Menu Recalculate Resource Assignments Any changes to Resource information will then take effect 150

151 Assigning Resources Budget/Cost By Default: Budgeted Units = Units/Time x Duration Budgeted Cost = Budgeted Units x Price/Unit 151

152 Importing Resources from XER [File Menu Import] Importing Resources from the Estimating Software To use the resources created in an estimating software: Import the "XER" file generated by the estimating software into P6 You can choose to import the resources only into the existing new project All the new resources will be imported into the shared resource pool 152

153 153

154 Resource Assignment Layout Click on the "Assignment" tab in the Directory Toolbar to display activities per resource To add/remove columns: Right-click on the title bar Columns Customize The Spreadsheet on the right side shows totals per time period (Budgeted Units, Budgeted Cost, etc.) To customize the Spreadsheet contents : Right Click anywhere Spreadsheet Fields Customize Select from either cumulative values or values per time period 154

155 Activity Usage Spreadsheet Click on the "Activities" tab in the Directory Toolbar Click the "Activity Usage Spreadsheet" icon Left pane displays the Activity Table, same as current layout Right pane displays activity data in a timescaled spreadsheet format 155

156 Activity Usage Profile Resource total Units or Costs per time period are represented as a histogram Choose to display usage for either "All activities" or only "Selected Activities" Note that the chart includes only activities listed above in the Activity Table 156

157 Activity Usage Profile (Cont d) Mark the "Time period" checkbox only if you want to filter the activity table based on highlighted periods in the chart 157

158 Activity Usage Profile (Cont d) To customize the chart: Right-click "Activity Usage Profile Options" 158

159 Resource Usage Spreadsheet The left pane lists all the resources or roles stored in the hierarchy, (depending on the current view). The middle pane displays all of the activity assignments for the resource or role currently selected in the left pane. The right pane displays the values for the activities assigned to the resource currently selected in the left pane. 159

160 Resource Usage Profile The left pane lists all the resources stored in the hierarchy view. The right pane displays the total usage of the selected resource, in terms of either units or costs. To customize the chart, right-click in the chart area "Resource Usage Profile Options. 160

161 Training Task No. 12 Copy Project Oracle_R (provided by the instructor) into EPS Node Sample Projects Determine the hours in the schedule for the following resources: Carpenter ( LCARP ) week of 12/13/09 Flatrack ( ETFR ) week of 06/13/10 Link Belt 60T Crane ( EH60T ) week of 04/03/11 Semi Belly Dump ( RT18B ) week of 01/09/11 Equipment Operator ( LO ) week of 07/04/10 161

162 Resource Leveling Definition A process that helps you assure there are sufficient resources available to perform the activities as planned and highlight resource overallocations or conflicts The software reschedules an activity, using its available Total Float, to occur when its resource demands can be met so as the total resource usage does not exceed its limits May result in a late Project Finish date if the affected activities were on the Critical Path 162

163 Resource Leveling (Cont d) 1. Click on the Level Resources icon 2. Click Select Resources to choose the resources you want to level 163

164 Resource Leveling (Cont d) Before Leveling After Leveling 164

165 Resource Leveling Before Leveling After Leveling 165

166 Training Task No. 13 Select only concrete labor ( LCL ) for leveling Change the resource usage profile to show only Remaining Late Dates Increase the maximum units per day for concrete labor to 16 hours Level LCL with all leveling options turned off What happens to the Total Float? Level LCL with the Level resources only within activity Total Float and compare results 166

167 Resource Leveling (Cont d) Guidelines Resource leveling requires a different type of logic; soft logic is necessary to allow enough float for activity dates to be adjusted Level one resource at a time to determine whether any negative float is created; if everything is okay, add more resources for leveling, one at a time All users (including the client) need to understand that resources are driving activity dates in addition to the logic Remember to resource level the schedule after each schedule calculation (or select option to always level when scheduling) 167

168 Resource Leveling (Cont d) Guidelines (Cont d) Leveling one resource will most likely remove the total float available for leveling other resources, so even the order in which you level resources can change the results Over-allocation of resources can be used to identify the need for a different workday calendar, higher limits, or the need for selective overtime Leveling within the activity Total Float (option) will not allow resource leveling to delay the project Resource leveling takes a lot of practice to master; start with a few simple resources and build confidence 168

169 169

170 Activity Duration Types P6 provides 4 types of Activity Durations. Fixed Duration Types Fixed Resource Types 1. Fixed Duration & Units/Time 3. Fixed Units 2. Fixed Duration & Units 4. Fixed Units/time 170

171 Activity Duration Types To change the Activity Duration Type: 1. Show the Activity Details in the Bottom Layout 2. Select the "General" Tab 3. Select from the drop-down menu the appropriate Activity Duration Type 171

172 Activity Duration Types (Cont d) The Duration type only matters when the activity is assigned resources. The following equation must hold true regardless of which variable is updated. Resource Units = Units/Time x Duration The Duration Type enables you to control which variables of this equation are calculated when you change a value. 172

173 Activity Duration Types (Cont d) Fixed Duration Types (Duration drives Resources) Fixed Duration & Units /Time Resource Units = Resource Units/Time x Duration Fixed Duration & Units Resource Units = Resource Units/Time x Duration Task Dependent Activities. Schedule Drives Resources. Duration overrides Resources (Units/Time or Units). Changes Fixed Resource Types (Resources drive Duration) Constant Fixed Units /Time Resource Units = Resource Units/Time x Duration Fixed Units Resource Units = Resource Units/Time x Duration Resource Dependent Activities. Resources Drive the Schedule. Resources (Units/Time or Units) overrides Duration. 173

174 Activity Duration Types (Cont d) Resource Units = Units/Time x Duration Resources Drive Duration Duration Drives Resources (Units & Units/Time) Priority Resource Units Resource Units/Time Duration Fixed Duration & Units/Time Fixed Duration & Units Fixed Units/Time Fixed Units

175 Fixed Duration & Units/Time Duration Overrides Resource Variables (Units & Units/Time) Resource Units = Units/Time x Duration 40 Hrs = 8 Hrs/Day x 5 Days Units Units/Time Duration Input 80 Hrs Input 16 Hrs/Day Input 10 Days Units (Hrs) Units/Time (Hrs/Day) Duration (Day) When Units were Changed, Units/Time were changed to maintain the equation, Duration is never recalculated with this type 175

176 Fixed Duration & Units Duration Overrides Resource Variables (Units & Units/Time) Resource Units = Units/Time x Duration 40 Hrs = 8 Hrs/Day x 5 Days Units Units/Time Duration Input 80 Hrs Input 16 Hrs/Day Input 10 Days Units (Hrs) Units/Time (Hrs/Day) Duration (Day) When Units/Time were Changed, Units were changed to maintain the equation, Duration is never recalculated with this type 176

177 Fixed Units Resource Variables (Units & Units/Time) Override Duration Resource Units = Units/Time x Duration 40 Hrs = 8 Hrs/Day x 5 Days Units Units/Time Duration Input 80 Hrs Input 16 Hrs/Day Input 10 Days Units (Hrs) Units/Time (Hrs/Day) Duration (Day) When Units were Changed, Duration changed to maintain the equation, Units/Time remained Constant. Resource variables take precedence over Duration. 177

178 Fixed Units/Time Resource Variables (Units & Units/Time) Override Duration Resource Units = Units/Time x Duration 40 Hrs = 8 Hrs/Day x 5 Days Units Units/Time Duration Input 80 Hrs Input 16 Hrs/Day Input 10 Days Units (Hrs) Units/Time (Hrs/Day) Duration (Day) When Units/Time were Changed, Duration changed to maintain the equation, Units remained Constant. Resource variables take precedence over Duration. 178

179 Activity Duration Types (Cont d) Resources Drive Duration Duration Drives Resources (Units & Units/Time) Resource Units = Units/Time x Duration Activity Duration Type When you change Units, this value changes... When you change Units/Time, this value changes... When you change Duration, this value changes... Fixed Duration & Units/time Units/Time Units Units Units Units/Time Fixed Duration & Units Duration Overrides Units/Time Fixed Units/Time Duration Fixed Units Duration Units/Time Override Duration Overrides Duration Units Override Duration Units Units/Time 179

180 Activity Duration Types (Cont d) Typically Used: Task Dependent Activity Type & Fixed Duration & Units/Time Activity Duration type 180

181 181

182 Percent Complete Types P6 provides 3 types of Percent Complete 1. Duration 2. Physical 3. Units 182

183 Percent Complete Types (Cont d) To select the Activity's Percent Complete Type: 1. Show the Activity Details in the Bottom Layout 2. Select the "General" Tab 3. Select from the drop-down menu the appropriate Activity Percent Complete Type 183

184 Percent Complete Types (Duration) ACTIVITY % COMPLETE = SELECTED % COMPLETE TYPE 1. Duration Percent Complete : If activity progress can most easily be reported based on original and remaining duration. The Activity % Complete will equal Duration % Complete, calculated as : [(Original Duration Remaining Duration) / Original Duration] x 100 For example, if you have a 10-day activity that has 4 days remaining, it is 60% complete. If Remaining Duration becomes greater than or equal to the Original Duration, Duration Percent complete will equal Zero 184

185 Percent Complete Types (Units) ACTIVITY % COMPLETE = SELECTED % COMPLETE TYPE 2. Units Percent Complete : Progress is reported based on the accomplished work effort (Units) as compared to how much work remains. The Activity % Complete will equal Units % Complete, calculated as : [(Actual Units ) / (Actual Units + Remaining Units)] x 100 For example, if an activity has a resource assigned 40 Hours, and the resource has actually completed 30 Hours, the activity is 75% complete. 185

186 Percent Complete Types (Physical) ACTIVITY % COMPLETE = SELECTED % COMPLETE TYPE 3. Physical Percent Complete : Progress is manually entered by the User. Choose this type when you want to remove the link between the reported remaining duration and the Activity's percent complete i.e. where progress will be reported separately from the remaining duration. Recommended, especially with Cost loaded schedules, where payment is based on schedule s reported progress. Provides a better historical record of the schedule s progress. 186

187 Training Task No. 14 Save the existing Training Layout 1 as Training Layout 2 Add columns to the Activity Table for the following percent complete types: Duration Physical Units Activity Find Activity ID b275.2.a10 using <Control-F> Select current Early Start date as the Actual Start Change the Duration % Complete to 50% What happens to the Remaining Duration? 187

188 Training Task No. 14 (Cont d) Change the Duration % Complete to 50% What happens to the Remaining Duration? Did anything else change? Change the Physical % Complete to 40% Did anything else change? Change the % Complete Type to Physical Did anything else change? Change the % Complete Type to Units Did anything else change? 188

189 189

190 Earned Value Calculations Definition: Budgeted Cost of Work Performed Earned Value = Budgeted Cost x Activity % Complete Activity % Complete = % Complete of Selected Type 190

191 Earned Value Calculations (Duration) Example I : Activity 33 Original Duration Remaining Duration Duration % complete Physical % Complete Percent Complete Type Budgeted Cost Activity Percent Complete Earned Value =3 =1 = [(OD-RD)/OD] x 100 = (3-1)/3 x 100 = 66.67% = 10 % (manually entered) = Duration = $1,000 = Percent Complete Type = Duration % = 66.67% = Activity % x Budgeted Cost = 66.67% x $1,000 = $

192 Earned Value Calculations (Physical) Example II : Activity 103 Original Duration Remaining Duration Duration % complete Physical % Complete Percent Complete Type Budgeted Cost Activity Percent Complete Earned Value =3 =2 = [(OD-RD)/OD] x 100 = (3-2)/3 x 100 = 33.33% = 40 % (manually entered) = Physical = $10,000 = Percent Complete Type = Physical % = 40% = Activity % x Budgeted Cost = 40% x $10,000 = $4,

Project Initiation and Revision Training Manual. Table of Contents

Project Initiation and Revision Training Manual. Table of Contents for Engineering and Construction v.4.1 Project Initiation and Revision Training Class Conducted by Evans Technology June 2005 Table of Contents Introduction to Primavera... 3 Project Management (P3eC)...

More information

Guidelines for Accessing and Using the VDOT Scheduling Application (Primavera P6)

Guidelines for Accessing and Using the VDOT Scheduling Application (Primavera P6) Guidelines for Accessing and Using the VDOT Scheduling Application (Primavera P6) CONSTRUCTION DIVISION (SCHEDULING & CONTRACTS) 1. INTRODUCTION To establish standards and consistent scheduling practices

More information

Oracle Primavera P6 Enterprise Project Portfolio management Overview Programme Reference # 201A

Oracle Primavera P6 Enterprise Project Portfolio management Overview Programme Reference # 201A Oracle Primavera P6 Enterprise Project Portfolio management Overview Programme Reference # 201A Programme Description: Dedicated one full day training module in a structured and professional manner to

More information

PROJECT PLANNING & SCHEDULING USING PRIMAVERA ENTERPRISE. In An. Established Project Environment PAUL EASTWOOD HARRIS

PROJECT PLANNING & SCHEDULING USING PRIMAVERA ENTERPRISE. In An. Established Project Environment PAUL EASTWOOD HARRIS PROJECT PLANNING & SCHEDULING USING PRIMAVERA ENTERPRISE Planning and Progressing a Single Project Schedule With and Without Resources In An Established Project Environment BY PAUL EASTWOOD HARRIS Eastwood

More information

Computer Training Centre University College Cork

Computer Training Centre University College Cork Computer Training Centre University College Cork Project 2013 Table of Contents What's new in Project 2013... 1 Manual scheduling... 1 Graphical Reports... 1 Trace task paths... 1 Easier view customization...

More information

USER CONVERSION P3, SURETRAK AND MICROSOFT PROJECT ASTA POWERPROJECT PAUL E HARRIS EASTWOOD HARRIS

USER CONVERSION P3, SURETRAK AND MICROSOFT PROJECT ASTA POWERPROJECT PAUL E HARRIS EASTWOOD HARRIS P.O. Box 4032 EASTWOOD HARRIS PTY LTD Tel 61 (0)4 1118 7701 Doncaster Heights ACN 085 065 872 Fax 61 (0)3 9846 7700 Victoria 3109 Project Management Systems Email: harrispe@eh.com.au Australia Software

More information

LECTURE -08 INTRODUCTION TO PRIMAVERA PROJECT PLANNER (P6)

LECTURE -08 INTRODUCTION TO PRIMAVERA PROJECT PLANNER (P6) LECTURE -08 INTRODUCTION TO PRIMAVERA PROJECT PLANNER (P6) GOAL In this lecture, we ll learn: Background of Primavera Project Planner (P6) Getting Started P6 Interface Basic Navigation and Operation Setting

More information

Administration. Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT 2010 AND PMBOK GUIDE FOURTH EDITION training course presented by

Administration. Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT 2010 AND PMBOK GUIDE FOURTH EDITION training course presented by Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT 2010 AND PMBOK GUIDE FOURTH EDITION training course presented by Paul E Harris Administration Evacuation Timings, meals and facilities Mobile phones

More information

Primavera Project Manager for the Enterprise Version 6.1 Custom Training Manual

Primavera Project Manager for the Enterprise Version 6.1 Custom Training Manual Primavera Project Manager for the Enterprise Version 6.1 Custom Training Manual Course Contents June 27, 2003 This publication is produced as a custom training document for The University of North Carolina.

More information

MS Project Tutorial for Senior Design Using Microsoft Project to manage projects

MS Project Tutorial for Senior Design Using Microsoft Project to manage projects MS Project Tutorial for Senior Design Using Microsoft Project to manage projects Overview: Project management is an important part of the senior design process. For the most part, teams manage projects

More information

PROJECT PLANNING & SCHEDULING USING PRIMAVERA P6 TM. in an PAUL EASTWOOD HARRIS

PROJECT PLANNING & SCHEDULING USING PRIMAVERA P6 TM. in an PAUL EASTWOOD HARRIS PROJECT PLANNING & SCHEDULING USING PRIMAVERA P6 TM For all industries including Versions 4 to 6 Planning and Progressing Project Schedules With and Without Roles and Resources in an Established Enterprise

More information

OVERVIEW. Microsoft Project terms and definitions

OVERVIEW. Microsoft Project terms and definitions PROJECT 2003 DISCLAIMER: This reference guide is meant for experienced Microsoft Project users. It provides a list of quick tips and shortcuts for familiar features. This guide does NOT replace training

More information

Scheduling Document Creation

Scheduling Document Creation Scheduling Document Creation What is a Schedule in epm? Schedules The epm Schedule application is an integral part of the Portfolio Management suite of applications. Start and end dates for each summary

More information

Project Creation and Gantt Chart Design Using Microsoft Project. R. Baker. The University of Tampa

Project Creation and Gantt Chart Design Using Microsoft Project. R. Baker. The University of Tampa Project Creation and Gantt Chart Design Using Microsoft Project R. Baker The University of Tampa What is Microsoft Project? Microsoft Project is a software package designed help managers manage a variety

More information

Sample book with only two chapters

Sample book with only two chapters PLANNING AND CONTROL USING ORACLE PRIMAVERA P6 Versions 8.2 to 15.1 EPPM WEB Enterprise Portfolio Project Management Planning and Progressing Project Schedules With and Without Roles and Resources in an

More information

Planning and Managing Projects with Microsoft Project Professional 2013

Planning and Managing Projects with Microsoft Project Professional 2013 Slides Steps to Enter Duration: 1. In the Duration column of a task, enter a value, and press Enter on your keyboard Important Points: The default time unit is days, so when you enter 5, this becomes 5

More information

Introduction to Microsoft Project 2010

Introduction to Microsoft Project 2010 Introduction to Microsoft Project 2010 This document provides an introduction in using Microsoft Project 2010. Microsoft Project is a project management application that contains a set of tools to help

More information

P6 Analytics Reference Manual

P6 Analytics Reference Manual P6 Analytics Reference Manual Release 3.2 October 2013 Contents Getting Started... 7 About P6 Analytics... 7 Prerequisites to Use Analytics... 8 About Analyses... 9 About... 9 About Dashboards... 10 Logging

More information

Microsoft Project 2013 Guide to Task and Resource Planning

Microsoft Project 2013 Guide to Task and Resource Planning Starting a Project The Microsoft Project 2013 Start screen Double click Blank Project, select a Recent project, or click Open Other Projects to work on a saved project stored on disk or on SkyDrive. To

More information

PROJECT MANAGEMENT IN PRIMAVERA P6 WEB ACCESS REL 7

PROJECT MANAGEMENT IN PRIMAVERA P6 WEB ACCESS REL 7 PROJECT MANAGEMENT IN PRIMAVERA P6 WEB ACCESS REL 7 Duration: 03 days INTRODUCTION This course provides hands-on training for Primavera s web-based solution. Participants will create a project, add activities

More information

New Features in Primavera P6 EPPM 16.1

New Features in Primavera P6 EPPM 16.1 New Features in Primavera P6 EPPM 16.1 COPYRIGHT & TRADEMARKS Copyright 2016, Oracle and/or its affiliates. All rights reserved. Oracle is a registered trademark of Oracle Corporation and/or its affiliates.

More information

MS Project 2007 Quick Guide

MS Project 2007 Quick Guide MS Project 2007 Quick Guide 1. Setup your project Add project information Determine project start date Check / Edit the standard/base calendar Check / Edit calendar calculation options Fine-tune your configuration

More information

Collaborative Scheduling using the CPM Method

Collaborative Scheduling using the CPM Method MnDOT Project Management Office Presents: Collaborative Scheduling using the CPM Method Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines

More information

ELECTRO-MECHANICAL PROJECT MANAGEMENT

ELECTRO-MECHANICAL PROJECT MANAGEMENT CHAPTER-9 ELECTRO-MECHANICAL PROJECT MANAGEMENT Y K Sharma,SDE(BS-E), 9412739241(M) E-Mail ID: yogeshsharma@bsnl.co.in Page: 1 Electro-mechanical Project Management using MS Project Introduction: When

More information

I N FO RM A T I O N T EC H N O L O G Y S ERV I C ES M I C ROSOFT PROJ EC T 2 0 1 0 T A S K M A N A GEM EN T LEARNING GUIDE

I N FO RM A T I O N T EC H N O L O G Y S ERV I C ES M I C ROSOFT PROJ EC T 2 0 1 0 T A S K M A N A GEM EN T LEARNING GUIDE I N FO RM A T I O N T EC H N O L O G Y S ERV I C ES M I C ROSOFT PROJ EC T 2 0 1 0 T A S K M A N A GEM EN T LEARNING GUIDE Workshop Information Information Technology Services is happy to provide you with

More information

technical tips and tricks

technical tips and tricks technical tips and tricks Document author: Produced by: Displaying a Critical Path Andy Jessop Project Learning International Limited The tips and tricks below are taken from Project Mentor, the smart

More information

Project Management Dashboard Pro v5 Documentation

Project Management Dashboard Pro v5 Documentation Project Management Dashboard Pro v5 Documentation Installation There is NO installation required. It s just a macro enabled excel file that opens if you have Excel 2007, 2010, 2013 and 2016 on your Windows

More information

Microsoft Project 2007 Level 1: Creating Project Tasks

Microsoft Project 2007 Level 1: Creating Project Tasks Microsoft Project 2007 Level 1: Creating Project Tasks By Robin Peers Robin Peers, 2008 ABOUT THIS CLASS Regardless of job title, most of us have needed to act as a project manager, at one time or another.

More information

Microsoft Project From the WBS to a Complete Schedule Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org

Microsoft Project From the WBS to a Complete Schedule Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org Planning and Managing Software Projects 2010-11 Session 6 Microsoft Project From the WBS to a Complete Schedule Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org Credits 2 These

More information

Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time

Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time Computer Scheduling Critical path method (CPM) requires numerous computations to determine activity start and finish dates,

More information

How To Use Ms Powerbook 2.5.2.2 On A Pc Or Mac Or Macbook 2 (Windows)

How To Use Ms Powerbook 2.5.2.2 On A Pc Or Mac Or Macbook 2 (Windows) Overview 1 Content Overview Open a project file Create a new project plan Track progress View and print reports Share a project plan Conclusion 2 Overview With you can: create new/update project plan open

More information

Quick Start Guide. Microsoft Publisher 2013 looks different from previous versions, so we created this guide to help you minimize the learning curve.

Quick Start Guide. Microsoft Publisher 2013 looks different from previous versions, so we created this guide to help you minimize the learning curve. Quick Start Guide Microsoft Publisher 2013 looks different from previous versions, so we created this guide to help you minimize the learning curve. Quick Access Toolbar Add your favorite commands to the

More information

MS Project 2000 Tutorial: Introduction

MS Project 2000 Tutorial: Introduction MS Project 2000 Tutorial: Introduction - Anjana Srikanth Stylus Systems is a Internet Technology company located in Bangalore India. One of our mottos is "a quality process creates a quality product."

More information

Advanced Presentation Features and Animation

Advanced Presentation Features and Animation There are three features that you should remember as you work within PowerPoint 2007: the Microsoft Office Button, the Quick Access Toolbar, and the Ribbon. The function of these features will be more

More information

Primavera P6 Enterprise Project Portfolio Management 8 Essentials (1Z0-567) Exam Study Guide

Primavera P6 Enterprise Project Portfolio Management 8 Essentials (1Z0-567) Exam Study Guide Primavera P6 Enterprise Project Portfolio Management 8 Essentials (1Z0-567) Exam Study Guide Margy Girdzius Director, Partner Enablement WWA&C Objective & Audience Objective Help you prepare to take the

More information

Handout: Word 2010 Tips and Shortcuts

Handout: Word 2010 Tips and Shortcuts Word 2010: Tips and Shortcuts Table of Contents EXPORT A CUSTOMIZED QUICK ACCESS TOOLBAR... 2 IMPORT A CUSTOMIZED QUICK ACCESS TOOLBAR... 2 USE THE FORMAT PAINTER... 3 REPEAT THE LAST ACTION... 3 SHOW

More information

INTRODUCTION TO MICROSOFT PROJECT 2007 CONTENTS

INTRODUCTION TO MICROSOFT PROJECT 2007 CONTENTS INTRODUCTION TO MICROSOFT PROJECT 2007 CONTENTS What is a Project... 2 The Steps involved in Setting up a Project... 3 Views... 4 How To Start a new project... 6 The Gantt Chart... 8 Outlining/Summary

More information

ABOUT THIS COURSE...3 ABOUT THIS MANUAL...4 EXCHANGING PROJECT PLAN DATA WITH OTHER APPLICATIONS...5

ABOUT THIS COURSE...3 ABOUT THIS MANUAL...4 EXCHANGING PROJECT PLAN DATA WITH OTHER APPLICATIONS...5 Table of Contents ABOUT THIS COURSE...3 ABOUT THIS MANUAL...4 EXCHANGING PROJECT PLAN DATA WITH OTHER APPLICATIONS...5 IMPORT A TASK LIST FROM AN EXCEL FILE INTO A NEW PROJECT PLAN... 6 Import a Task List

More information

Scheduling Glossary Activity. A component of work performed during the course of a project.

Scheduling Glossary Activity. A component of work performed during the course of a project. Scheduling Glossary Activity. A component of work performed during the course of a project. Activity Attributes. Multiple attributes associated with each schedule activity that can be included within the

More information

Excel 2007: Basics Learning Guide

Excel 2007: Basics Learning Guide Excel 2007: Basics Learning Guide Exploring Excel At first glance, the new Excel 2007 interface may seem a bit unsettling, with fat bands called Ribbons replacing cascading text menus and task bars. This

More information

Applied Project Management ( APM )

Applied Project Management ( APM ) Applied Project Management Applied Project Management ( APM ) TRAINING PROGRAM Page 1 Of 7 APPLIED PROJECT MANAGEMENT PRO PROGRAM OVERVIEW This course provides in-depth Project Management Training and

More information

Asset Track Getting Started Guide. An Introduction to Asset Track

Asset Track Getting Started Guide. An Introduction to Asset Track Asset Track Getting Started Guide An Introduction to Asset Track Contents Introducing Asset Track... 3 Overview... 3 A Quick Start... 6 Quick Start Option 1... 6 Getting to Configuration... 7 Changing

More information

PowerPoint 2013 Basics for Windows Training Objective

PowerPoint 2013 Basics for Windows Training Objective PowerPoint 2013 Basics for Windows PowerPoint 2013 Basics for Windows Training Objective To learn the tools and features to get started using PowerPoint more efficiently and effectively. What you can expect

More information

Microsoft Project 2010 Advanced

Microsoft Project 2010 Advanced Microsoft Project 2010 Advanced Table Of Contents SECTION 1 - REFRESH OF THE BASICS... 3 GUIDE INFORMATION... 4 Introduction... 4 How To Use This Guide... 4 Objectives... 4 Instructions... 4 PROJECT INFORMATION

More information

ECDL. European Computer Driving Licence. Project Planning Project Management Software BCS ITQ Level 2. Syllabus Version 1.0

ECDL. European Computer Driving Licence. Project Planning Project Management Software BCS ITQ Level 2. Syllabus Version 1.0 ECDL European Computer Driving Licence Project Planning Project Management Software BCS ITQ Level 2 Using Microsoft Project 2013 Syllabus Version 1.0 This training, which has been approved by BCS, The

More information

Using Microsoft Project 2000

Using Microsoft Project 2000 Using MS Project Personal Computer Fundamentals 1 of 45 Using Microsoft Project 2000 General Conventions All text highlighted in bold refers to menu selections. Examples would be File and Analysis. ALL

More information

Open Workbench. User Guide. v2.0.00

Open Workbench. User Guide. v2.0.00 Open Workbench User Guide v2.0.00 This documentation, which includes embedded help systems and electronically distributed materials, (hereinafter referred to as the Documentation ) is for your informational

More information

Primavera P6 Exercise Worksheet

Primavera P6 Exercise Worksheet Primavera P6 Exercise Worksheet P6 Exercise Worksheet Preparing for the Exercises Ten Six Consulting recommends that you download and install your own standalone copy of Primavera P6 Professional for use

More information

Education Solutions Development, Inc. APECS Navigation: Business Systems Getting Started Reference Guide

Education Solutions Development, Inc. APECS Navigation: Business Systems Getting Started Reference Guide Education Solutions Development, Inc. APECS Navigation: Business Systems Getting Started Reference Guide March 2013 Education Solutions Development, Inc. What s Inside The information in this reference

More information

Microsoft Access 2010 handout

Microsoft Access 2010 handout Microsoft Access 2010 handout Access 2010 is a relational database program you can use to create and manage large quantities of data. You can use Access to manage anything from a home inventory to a giant

More information

Q&As: Microsoft Excel 2013: Chapter 2

Q&As: Microsoft Excel 2013: Chapter 2 Q&As: Microsoft Excel 2013: Chapter 2 In Step 5, why did the date that was entered change from 4/5/10 to 4/5/2010? When Excel recognizes that you entered a date in mm/dd/yy format, it automatically formats

More information

IDENTIFY ACTIVITIES STEP 2 By: Charlie Jackson (Hill International) & Hannah E. Schumacher (Kitchell Contractors)

IDENTIFY ACTIVITIES STEP 2 By: Charlie Jackson (Hill International) & Hannah E. Schumacher (Kitchell Contractors) IDENTIFY ACTIVITIES STEP 2 By: Charlie Jackson (Hill International) & Hannah E. Schumacher (Kitchell Contractors) Abstract: Many Contract Documents are now requiring the use of the latest version of Primavera

More information

Working together with Word, Excel and PowerPoint

Working together with Word, Excel and PowerPoint Working together with Word, Excel and PowerPoint Have you ever wanted your Word document to include data from an Excel spreadsheet, or diagrams you ve created in PowerPoint? This note shows you how to

More information

Microsoft Project 2010

Microsoft Project 2010 Tutorial 1: Planning a Project Microsoft Project 2010 In Tutorial Section 1.1 you will: Learn project management terminology Understand the benefits of project management Explore the Project 2010 window

More information

Microsoft PowerPoint 2010 Handout

Microsoft PowerPoint 2010 Handout Microsoft PowerPoint 2010 Handout PowerPoint is a presentation software program that is part of the Microsoft Office package. This program helps you to enhance your oral presentation and keep the audience

More information

M-Files Gantt View. User Guide. App Version: 1.1.0 Author: Joel Heinrich

M-Files Gantt View. User Guide. App Version: 1.1.0 Author: Joel Heinrich M-Files Gantt View User Guide App Version: 1.1.0 Author: Joel Heinrich Date: 02-Jan-2013 Contents 1 Introduction... 1 1.1 Requirements... 1 2 Basic Use... 1 2.1 Activation... 1 2.2 Layout... 1 2.3 Navigation...

More information

Microsoft Outlook 2007 Calendar Features

Microsoft Outlook 2007 Calendar Features Microsoft Outlook 2007 Calendar Features Participant Guide HR Training and Development For technical assistance, please call 257-1300 Copyright 2007 Microsoft Outlook 2007 Calendar Objectives After completing

More information

Ohio University Computer Services Center August, 2002 Crystal Reports Introduction Quick Reference Guide

Ohio University Computer Services Center August, 2002 Crystal Reports Introduction Quick Reference Guide Open Crystal Reports From the Windows Start menu choose Programs and then Crystal Reports. Creating a Blank Report Ohio University Computer Services Center August, 2002 Crystal Reports Introduction Quick

More information

Aras Corporation. 2005 Aras Corporation. All rights reserved. Notice of Rights. Notice of Liability

Aras Corporation. 2005 Aras Corporation. All rights reserved. Notice of Rights. Notice of Liability Aras Corporation 2005 Aras Corporation. All rights reserved Notice of Rights All rights reserved. Aras Corporation (Aras) owns this document. No part of this document may be reproduced or transmitted in

More information

Word basics. Before you begin. What you'll learn. Requirements. Estimated time to complete:

Word basics. Before you begin. What you'll learn. Requirements. Estimated time to complete: Word basics Word is a powerful word processing and layout application, but to use it most effectively, you first have to understand the basics. This tutorial introduces some of the tasks and features that

More information

California Department Of Transportation. Class # G0C094

California Department Of Transportation. Class # G0C094 California Department Of Transportation ADVANCED CPM SCHEDULING WITH SURETRAK Class # G0C094 ADVANCED CPM SCHEDULING WITH SURETRAK September 2003 SureTrak is a registered trademark of Primavera Systems,

More information

REUTERS/TIM WIMBORNE SCHOLARONE MANUSCRIPTS COGNOS REPORTS

REUTERS/TIM WIMBORNE SCHOLARONE MANUSCRIPTS COGNOS REPORTS REUTERS/TIM WIMBORNE SCHOLARONE MANUSCRIPTS COGNOS REPORTS 28-APRIL-2015 TABLE OF CONTENTS Select an item in the table of contents to go to that topic in the document. USE GET HELP NOW & FAQS... 1 SYSTEM

More information

Dashboards and Reporting for Program Management

Dashboards and Reporting for Program Management MnDOT Project Management Office Presents: Dashboards and Reporting for Program Management Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will

More information

CRITICAL PATH METHOD (CPM) SCHEDULES

CRITICAL PATH METHOD (CPM) SCHEDULES 96 CRITICAL PATH METHOD (CPM) SCHEDULES How-to for Reading, Understanding, and Using CPM Schedules (without Direct Primavera Access.) 1 Objectives Learn to read, understand, and use CPM schedules (without

More information

Introduction to Microsoft Excel 2007/2010

Introduction to Microsoft Excel 2007/2010 to Microsoft Excel 2007/2010 Abstract: Microsoft Excel is one of the most powerful and widely used spreadsheet applications available today. Excel's functionality and popularity have made it an essential

More information

University of Sunderland. Microsoft Project. Basic Guide

University of Sunderland. Microsoft Project. Basic Guide University of Sunderland Microsoft Project Basic Guide 21/11/2008 A Course in using Microsoft Project Garry Storer Learning Objectives 1. What project management software is, basic concepts, the tasks

More information

PROMASTAR Instructor-led Professional Training Services

PROMASTAR Instructor-led Professional Training Services PROMASTAR Instructor-led Professional Training Services Primavera P6 Professional Fundamentals Rel 8.3 Primavera P6 Professional Fundamentals Rel 8.3 Page 1 Oracle Primavera Learning Experience Learning

More information

BIGPOND ONLINE STORAGE USER GUIDE Issue 1.1.0-18 August 2005

BIGPOND ONLINE STORAGE USER GUIDE Issue 1.1.0-18 August 2005 BIGPOND ONLINE STORAGE USER GUIDE Issue 1.1.0-18 August 2005 PLEASE NOTE: The contents of this publication, and any associated documentation provided to you, must not be disclosed to any third party without

More information

Project planning with MindGenius

Project planning with MindGenius Project planning with MindGenius This workshop looks at using MindGenius for planning and monitoring smaller projects. MindGenius is available free of charge on all University of Brighton staff and student

More information

WBS Schedule Pro. User's Guide

WBS Schedule Pro. User's Guide WBS Schedule Pro User's Guide Critical Tools, Inc. 2014 Table of Contents Overview of WBS Schedule Pro 7 What is WBS Schedule Pro? 7 What is a WBS chart? 9 What is a Network chart? 10 What's New in WBS

More information

MnDOT Project Management Office Presents: Schedule Updates. Presenter: Eric Costantino Senior Schedule Consultant DRMcNatty & Associates, Inc.

MnDOT Project Management Office Presents: Schedule Updates. Presenter: Eric Costantino Senior Schedule Consultant DRMcNatty & Associates, Inc. MnDOT Project Management Office Presents: Schedule Updates Presenter: Eric Costantino Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted during the webinar Questions

More information

PowerPoint 2007 Basics Website: http://etc.usf.edu/te/

PowerPoint 2007 Basics Website: http://etc.usf.edu/te/ Website: http://etc.usf.edu/te/ PowerPoint is the presentation program included in the Microsoft Office suite. With PowerPoint, you can create engaging presentations that can be presented in person, online,

More information

Step One. Step Two. Step Three USING EXPORTED DATA IN MICROSOFT ACCESS (LAST REVISED: 12/10/2013)

Step One. Step Two. Step Three USING EXPORTED DATA IN MICROSOFT ACCESS (LAST REVISED: 12/10/2013) USING EXPORTED DATA IN MICROSOFT ACCESS (LAST REVISED: 12/10/2013) This guide was created to allow agencies to set up the e-data Tech Support project s Microsoft Access template. The steps below have been

More information

Methodology Management. Reference Manual

Methodology Management. Reference Manual Methodology Management Reference Manual 1997-2005 Primavera Systems, Inc. All rights reserved. Unless otherwise noted, this software is the property of Primavera Systems, Inc. (Primavera) or its licensors

More information

FastTrack Schedule 10. Tutorials Manual. Copyright 2010, AEC Software, Inc. All rights reserved.

FastTrack Schedule 10. Tutorials Manual. Copyright 2010, AEC Software, Inc. All rights reserved. FastTrack Schedule 10 Tutorials Manual FastTrack Schedule Documentation Version 10.0.0 by Carol S. Williamson AEC Software, Inc. With FastTrack Schedule 10, the new version of the award-winning project

More information

Microsoft Migrating to Word 2010 from Word 2003

Microsoft Migrating to Word 2010 from Word 2003 In This Guide Microsoft Word 2010 looks very different, so we created this guide to help you minimize the learning curve. Read on to learn key parts of the new interface, discover free Word 2010 training,

More information

Produced by Flinders University Centre for Educational ICT. PivotTables Excel 2010

Produced by Flinders University Centre for Educational ICT. PivotTables Excel 2010 Produced by Flinders University Centre for Educational ICT PivotTables Excel 2010 CONTENTS Layout... 1 The Ribbon Bar... 2 Minimising the Ribbon Bar... 2 The File Tab... 3 What the Commands and Buttons

More information

Project 2013: An introduction

Project 2013: An introduction Project 2013: An introduction TPAF Revision Information Version Date Author Changes made 1.0 February 2013 Jean Glendinning Created 2.0 November 2013 Jean Glendinning Amended elements 3.0 Feb 2014 Jean

More information

Project Management within ManagePro

Project Management within ManagePro Project Management within ManagePro This document describes how to do the following common project management functions with ManagePro: set-up projects, define scope/requirements, assign resources, estimate

More information

Microsoft Word 2010 Training

Microsoft Word 2010 Training Microsoft Word 2010 Training Microsoft Word 102 Instructor: Debbie Minnerly Course goals Learn how to work with paragraphs. Set tabs and work with tables. Learn about styles Use the spelling and grammar

More information

Hands on Microsoft Project (Part I) From a WBS to a Complete Schedule Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.

Hands on Microsoft Project (Part I) From a WBS to a Complete Schedule Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle. Planning and Managing Software Projects 2011-12 Class 10 Hands on Microsoft Project (Part I) From a WBS to a Complete Schedule Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org

More information

Planning and Scheduling Your Project Using Microsoft Project 2003

Planning and Scheduling Your Project Using Microsoft Project 2003 Planning and Scheduling Your Project Using Microsoft Project 2003 Sridhar Pandurangiah Director - Engineering sridhar@sastratechnologies.in Meeting Protocol Agenda Project File Project Calendar Creating

More information

Working together with Word, Excel and PowerPoint 2013

Working together with Word, Excel and PowerPoint 2013 Working together with Word, Excel and PowerPoint 2013 Information Services Working together with Word, Excel and PowerPoint 2013 Have you ever needed to include data from Excel or a slide from PowerPoint

More information

SAP Business Intelligence ( BI ) Financial and Budget Reporting. 7.0 Edition. (Best Seller At Least 43 copies Sold)

SAP Business Intelligence ( BI ) Financial and Budget Reporting. 7.0 Edition. (Best Seller At Least 43 copies Sold) SAP Business Intelligence ( BI ) Financial and Budget Reporting 7.0 Edition (Best Seller At Least 43 copies Sold) November 2011 Table of Contents Log In... 3 Initial Variable Screen... 5 Multiple / Single

More information

Microsoft Project 2007 Level 2: Working with Resources and Managing a Project

Microsoft Project 2007 Level 2: Working with Resources and Managing a Project Microsoft Project 2007 Level 2: Working with Resources and Managing a Project By Robin Peers Robin Peers, 2008 ABOUT THIS CLASS In Microsoft Project 2007 Level 1: Creating Project Tasks, the focus was

More information

Introduction to Microsoft Excel 2010

Introduction to Microsoft Excel 2010 Introduction to Microsoft Excel 2010 Screen Elements Quick Access Toolbar The Ribbon Formula Bar Expand Formula Bar Button File Menu Vertical Scroll Worksheet Navigation Tabs Horizontal Scroll Bar Zoom

More information

Primavera P6 Enterprise Project Portfolio Management Certified Implementation Specialist

Primavera P6 Enterprise Project Portfolio Management Certified Implementation Specialist Oracle 1z0-535 Primavera P6 Enterprise Project Portfolio Management Certified Implementation Specialist Version: 6.0 QUESTION NO: 1 Select the true statement regarding Global Preferences in Primavera P6

More information

Microsoft Excel 2013 Tutorial

Microsoft Excel 2013 Tutorial Microsoft Excel 2013 Tutorial TABLE OF CONTENTS 1. Getting Started Pg. 3 2. Creating A New Document Pg. 3 3. Saving Your Document Pg. 4 4. Toolbars Pg. 4 5. Formatting Pg. 6 Working With Cells Pg. 6 Changing

More information

Lesson 6 - Managing Resources in a Project Plan

Lesson 6 - Managing Resources in a Project Plan Lesson 6 - Managing Resources in a Project Plan Lesson Objectives In this lesson, you will manage resources in a project plan. You will: Create a resource calendar. Assign resources to tasks. Assign additional

More information

Revealing the Secrets of Microsoft Project

Revealing the Secrets of Microsoft Project 2 Revealing the Secrets of Microsoft Project To know that one has a secret is to know half the secret itself. Henry Ward Beecher Topics Covered in This Chapter Recognizing the Underlying Rules of Project

More information

Microsoft Excel 2010 Tutorial

Microsoft Excel 2010 Tutorial 1 Microsoft Excel 2010 Tutorial Excel is a spreadsheet program in the Microsoft Office system. You can use Excel to create and format workbooks (a collection of spreadsheets) in order to analyze data and

More information

Migrating to Excel 2010 from Excel 2003 - Excel - Microsoft Office 1 of 1

Migrating to Excel 2010 from Excel 2003 - Excel - Microsoft Office 1 of 1 Migrating to Excel 2010 - Excel - Microsoft Office 1 of 1 In This Guide Microsoft Excel 2010 looks very different, so we created this guide to help you minimize the learning curve. Read on to learn key

More information

Microsoft Project 2013

Microsoft Project 2013 CALIFORNIA STATE UNIVERSITY, LOS ANGELES INFORMATION TECHNOLOGY SERVICES Microsoft Project 2013 Summer 2014, Version 1.0 Table of Contents Introduction...2 Overview of the User Interface...2 Creating a

More information

USER GUIDE. Unit 2: Synergy. Chapter 2: Using Schoolwires Synergy

USER GUIDE. Unit 2: Synergy. Chapter 2: Using Schoolwires Synergy USER GUIDE Unit 2: Synergy Chapter 2: Using Schoolwires Synergy Schoolwires Synergy & Assist Version 2.0 TABLE OF CONTENTS Introductions... 1 Audience... 1 Objectives... 1 Before You Begin... 1 Getting

More information

Timeless Time and Expense Version 3.0. Copyright 1997-2009 MAG Softwrx, Inc.

Timeless Time and Expense Version 3.0. Copyright 1997-2009 MAG Softwrx, Inc. Timeless Time and Expense Version 3.0 Timeless Time and Expense All rights reserved. No parts of this work may be reproduced in any form or by any means - graphic, electronic, or mechanical, including

More information

SAP Business Intelligence (BI) Reporting Training for MM. General Navigation. Rick Heckman PASSHE 1/31/2012

SAP Business Intelligence (BI) Reporting Training for MM. General Navigation. Rick Heckman PASSHE 1/31/2012 2012 SAP Business Intelligence (BI) Reporting Training for MM General Navigation Rick Heckman PASSHE 1/31/2012 Page 1 Contents Types of MM BI Reports... 4 Portal Access... 5 Variable Entry Screen... 5

More information

Welcome to the topic on creating key performance indicators in SAP Business One, release 9.1 version for SAP HANA.

Welcome to the topic on creating key performance indicators in SAP Business One, release 9.1 version for SAP HANA. Welcome to the topic on creating key performance indicators in SAP Business One, release 9.1 version for SAP HANA. 1 In this topic, you will learn how to: Use Key Performance Indicators (also known as

More information

2) Sharing Projects Made easy by IntelliGantt s Share Wizard, there are three share options to fit the needs of your project.

2) Sharing Projects Made easy by IntelliGantt s Share Wizard, there are three share options to fit the needs of your project. Introduction TeamDirection IntelliGantt solutions allows you and the rest of your project team to collaborate on your projects together. How you would like work together is up to you. The project manager

More information

108-C-215 CRITICAL PATH METHOD SCHEDULE. (Revised 03-24-10)

108-C-215 CRITICAL PATH METHOD SCHEDULE. (Revised 03-24-10) CRITICAL PATH METHOD SCHEDULE (Revised 03-24-10) The Standard Specifications are revised as follows: SECTION 108, BEGIN LINE 177, INSERT AS FOLLOWS: 108.04.1 Critical Path Method Schedule (a) General Requirements

More information

Basic Microsoft Excel 2007

Basic Microsoft Excel 2007 Basic Microsoft Excel 2007 The biggest difference between Excel 2007 and its predecessors is the new layout. All of the old functions are still there (with some new additions), but they are now located

More information